PROCUREMENT PLAN (Textual Part) Project information: Burundi - Great Lakes Trade Facilitation and Integration Project] (P174814) Project Implementation agency: Burundi-Ministry of Finance, Budget and Privatization Date of the Procurement Plan: November 8, 2021 Period covered by this Procurement Plan: December 2017 – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the country procurement handbook, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. - Rights for the Bank to review procurement documentation and activities. - An effective complaints mechanism. - Maintenance of records of the Procurement Process When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables : Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is Not Applicable Works: is not Applicable PROCUREMENT Eastern and Southern Africa : Great Lakes Trade Facilitation and Integration Project PLAN General Information Country: Eastern and Southern Africa 2021-12-16 Bank’s Approval Date of the Original Procurement Plan: 2022-07-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174814 GPN Date: Project Name: Great Lakes Trade Facilitation and Integration Project Loan / Credit No: IDA / V3940 Cellule Infrastructures Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - ZR-CI-301825-CW-RFB / Trav Component 2: Improving Cor Open - Internationa Single Stage - One E Works (without pr En attente d 2024-11-1 aux de construction du poste IDA / V3940 A posteriori Appel d'offres 7,000,000.00 0.00 2022-07-15 2022-07-20 2022-09-18 2022-10-18 2022-11-22 e Trade Infrastructure l nvelope equalification) SP 'exécution 1 frontalier de Kamvivira D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-265743-CS-QCBS / Pre stations d'un consultant-Firm Sélection fondée s Component 2: Improving Cor En cours d'exécut e chargé des études de faisa IDA / V3940 A posteriori ur la qualité et le Open - National 480,000.00 0.00 2021-12-15 2022-01-03 2022-01-05 2022-02-18 2022-03-18 2022-04-17 2022-05-22 2022-06-26 2022-10-24 e Trade Infrastructure ion bilité pour la construction du coût port et du marché à Idjwi ain si que leurs dépendances ZR-CI-265749-CS-QCBS / Pre Component 4: Supporting Im Sélection fondée s En attente d'exéc stations d'un consultant-Firm IDA / V3940 plementation and Monitoring A posteriori ur la qualité et le Open - National 15,000.00 0.00 2022-02-02 2022-02-23 2022-04-08 2022-05-06 2022-06-05 2022-07-10 2022-08-14 2022-09-28 ution e chargé de l'audit du PPA and Evaluation coût ZR-CI-266442-CS-QCBS / Pre station d'un consultant firme chargé du développement et Component 3: Supporting Co Sélection fondée s cartographie des chaines de Open - Internationa En cours d'exécut IDA / V3940 mmercialization of Selected A posteriori ur la qualité et le 400,000.00 0.00 2022-01-12 2022-01-03 2022-02-02 2022-03-15 2022-03-18 2022-03-15 2022-04-15 2022-04-07 2022-05-15 2022-06-19 2022-07-24 2023-01-20 valeur agricoles et halieutiqu l ion Cross-border Value Chains coût es (Étude sur la chaine de val eur à forte de croissance et c apacité d’exportation (diagn ostic général)) ZR-CI-273328-CS-QCBS / Pre stations d'un consultant-Firm Sélection fondée s Component 2: Improving Cor En cours d'exécut e chargé des études techniq IDA / V3940 A posteriori ur la qualité et le Open - National 450,000.00 0.00 2022-01-31 2022-05-07 2022-02-21 2022-06-05 2022-04-06 2022-05-04 2022-06-03 2022-07-08 2022-08-12 2023-08-12 e Trade Infrastructure ion ues détaillées pour la réhabili coût tation du port de Kalundu da ns le Sud-Kivu ZR-CI-267671-CS-QCBS / Pre stations d'un consultant (firm e) chargé des études techniq Sélection fondée s ues détaillées pour la constru Component 2: Improving Cor IDA / V3940 A posteriori ur la qualité et le Open - National 250,000.00 0.00 Annulé 2022-01-12 2022-02-02 2022-03-18 2022-04-15 2022-05-15 2022-06-19 2022-07-24 2023-01-20 ction des marchés : Marché d e Trade Infrastructure coût e Kavimvira, Marché de Kasin di, Marché de Bunagana, Mar ché de Kamanyola dans le N ord et le sud-Kivu ZR-CI-265745-CS-QCBS / Pre stations d'un consultant-Firm Sélection fondée s e chargé des études techniq Component 2: Improving Cor IDA / V3940 A posteriori ur la qualité et le Open - National 350,000.00 0.00 Annulé 2021-12-10 2021-12-31 2022-02-13 2022-03-13 2022-04-12 2022-05-17 2022-06-21 2022-11-18 ues détaillées pour la constru e Trade Infrastructure coût ction de la Route d'accès et d u Poste Frontalier de Nyamo ma ZR-CI-265746-CS-QCBS / Pre stations d'un consultant (firm e) chargé des études techniq Sélection fondée s ues détaillées pour la constru Component 2: Improving Cor IDA / V3940 A posteriori ur la qualité et le Open - National 215,000.00 0.00 Annulé 2021-12-20 2022-01-10 2022-02-23 2022-03-23 2022-04-22 2022-05-27 2022-07-01 2022-10-29 ction des marchés : Marché d e Trade Infrastructure coût e Kavimvira, Marché de Kasin di, Marché de Bunagana, Mar ché de Nyamoma/Sange dan s le Nord et le sud-Kivu ZR-CI-300034-CS-QCBS / Re crutement d’un consultant (fi rme) chargé des études tech Sélection fondée s niques détaillées, surveillanc Component 2: Improving Cor Open - Internationa En attente d'exéc IDA / V3940 A priori ur la qualité et le 1,275,000.00 0.00 2022-08-01 2022-08-22 2022-10-05 2022-11-02 2022-12-02 2023-01-06 2023-02-10 2026-02-09 e et suivi des travaux pour la e Trade Infrastructure l ution coût construction de : (i) Lot 1 : M arché de Bunagana (ii) Lot 2 : Marché de Kasindi (iii) Lot 3 : Marché de Kamvivira ZR-CI-300044-CS-QCBS / Co nsultant (firme) chargé des é tudes, surveillance et suivi d Sélection fondée s es travaux de : (i) Lot1:Amén Component 2: Improving Cor Open - Internationa En attente d'exéc IDA / V3940 A priori ur la qualité et le 1,380,000.00 0.00 2022-08-08 2022-08-29 2022-10-12 2022-11-09 2022-12-09 2023-01-13 2023-02-17 2026-02-16 agement bitumage route acc e Trade Infrastructure l ution coût ès poste frontalier Rubenga (ii) Lot2:Construction poste fr ontalier Kamanyola (iii) Lot3: Construction poste frontalier Rubenga Page 1 ZR-CI-300060-CS-QCBS / Re crutement d’un consultant (fi rme) chargé des études détai Sélection fondée s llées, surveillance et suivi de Component 2: Improving Cor Open - Internationa En attente d'exéc IDA / V3940 A posteriori ur la qualité et le 900,000.00 0.00 2022-08-10 2022-08-31 2022-10-14 2022-11-11 2022-12-11 2023-01-15 2023-02-19 2026-02-18 s travaux de : (i) Lot1:Aména e Trade Infrastructure l ution coût gement, bitumage route d'ac cès au poste frontalier de Ny amoma (ii) Lot2:Construction du poste frontalier de Nyamo ma ZR-CI-304641-CS-CQS / Recr utement d'un consultant (fir Sélection fondée s me) chargé de la revue techn Component 2: Improving Cor En attente d'exéc IDA / V3940 A posteriori ur les qualification Open - National 175,000.00 0.00 2022-07-29 2022-08-19 2022-10-02 2022-11-01 2022-12-06 2023-03-06 ique des études techniques d e Trade Infrastructure ution s des consultants étaillées pour la construction du poste frontalier de Kavimv ira ZR-CI-304837-CS-CQS / Recr utement d'un Consultant (fir me) chargé de conduire une Component 1. Improving Poli Sélection fondée s En attente d'exéc Étude sur le système d'appro IDA / V3940 cy and Regulatory Environm A posteriori ur les qualification Open - National 200,000.00 0.00 2022-08-24 2022-09-14 2022-10-28 2022-11-27 2023-01-01 2023-06-30 ution visionnement et de distributi ent for cross border trade s des consultants on des produits grâce à la str atégie d'achats groupés par l es commerçants transfrontali ers ZR-CI-304842-CS-CQS / Pres tations de services d'un Cons Component 1. Improving Poli Sélection fondée s ultant (firme) chargé de l'Ide En attente d'exéc IDA / V3940 cy and Regulatory Environm A posteriori ur les qualification Limited 200,000.00 0.00 2022-08-11 2022-08-25 2022-09-24 2022-10-29 2023-04-27 ntification et la Cartographie ution ent for cross border trade s des consultants des associations de commerç ants transfrontaliers à Uvira, Kamanyola, Idjwi, Kiliba. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-265059-CS-CDS / Élab oration des Études d’Impact Environnemental et Social, EI ES, des travaux d’aménagem Sélection de cons Component 2: Improving Cor En attente d'exéc ent des installations frontaliè IDA / V3940 A posteriori ultants par entent Direct 317,100.00 0.00 2021-12-03 2021-12-13 2022-02-16 2022-05-17 e Trade Infrastructure ution res (Poste frontalier de Kamv e directe ivira), installations portuaires (Port de Kalundu) et des infra structures routières (Route K amvivira-Uvira) ZR-CI-265214-CS-CDS / Élab oration du Cadre de Planifica Sélection de cons tion en faveur des Peuples A Component 2: Improving Cor En attente d'exéc IDA / V3940 A posteriori ultants par entent Direct 149,263.00 0.00 2021-12-03 2021-12-13 2022-02-16 2022-05-17 utochtones (CPPA) du Projet e Trade Infrastructure ution e directe de Facilitation du Commerce et d'Intégration dans la Régio n des Grands Lacs, PFCIGL ZR-CI-265221-CS-CDS / Élab oration du Cadre de Politique Sélection de cons de Réinstallation de Populati Component 2: Improving Cor En attente d'exéc IDA / V3940 A posteriori ultants par entent Direct 173,887.00 0.00 2021-12-03 2021-12-13 2022-02-16 2022-05-17 ons (CPR) du Projet de Facilit e Trade Infrastructure ution e directe ation du Commerce et d'Inté gration dans la Région des G rands Lacs, PFCIGL ZR-CI-265222-CS-CDS / Élab oration du Cadre de Gestion Sélection de cons Environnementale et Sociale Component 2: Improving Cor En attente d'exéc IDA / V3940 A posteriori ultants par entent Direct 282,129.00 0.00 2021-12-03 2021-12-13 2022-02-16 2022-05-17 (CGES) du Projet de Facilitati e Trade Infrastructure ution e directe on du Commerce et d'Intégra tion dans la Région des Gran ds Lacs, PFCIGL ZR-CI-265722-CS-INDV / Pre stations d’un consultant indiv iduel chargé de l’évaluation des risques sur les violences Component 2: Improving Cor En cours d'exécut IDA / V3940 A posteriori Individuel Limited 90,073.00 0.00 2021-12-10 2022-02-02 2021-12-15 2022-01-05 2022-02-09 2022-03-26 basées sur le genre et de la c e Trade Infrastructure ion apacité de réaction en faveur des populations autochtones des installations ciblées dans le cadre de la préparation du PFCIGL ZR-CI-265752-CS-INDV / Pre Component 4: Supporting Im stations d'un consultant indiv En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 40,000.00 0.00 2021-12-10 2021-12-15 2022-01-05 2022-02-09 2022-04-10 iduel chargé de l'élaboration ution and Evaluation du manuel de procédures du Projet PFCIGL ZR-CI-266000-CS-INDV / Rec rutement d'un consultant ind Component 4: Supporting Im En cours d'exécut ividuel en qualité d'Expert en IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 48,000.00 0.00 2021-12-10 2021-12-19 2021-12-20 2022-01-10 2022-02-14 2023-02-14 ion Développement Social du pro and Evaluation jet PFCIGL pour les douze (12 ) mois à venir ZR-CI-266280-CS-INDV / Rec rutement d'un consultant ind Component 4: Supporting Im En cours d'exécut ividuel en qualité d'Expert en IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 48,000.00 0.00 2021-12-10 2021-12-19 2021-12-20 2022-01-10 2022-02-14 2023-02-14 ion Environnement du projet PFC and Evaluation IGL pour les douze (12) mois à venir ZR-CI-266290-CS-INDV / Rec rutement d'un consultant ind Component 4: Supporting Im En cours d'exécut ividuel en qualité de Compta IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 42,000.00 0.00 2021-12-16 2021-12-19 2021-12-26 2022-01-16 2022-02-20 2023-02-20 ion ble du projet PFCIGL pour les and Evaluation douze (12) mois à venir ZR-CI-266424-CS-INDV / Réa lisation des études technique s pour l'aménagement et le b Component 2: Improving Cor En attente d'exéc IDA / V3940 A posteriori Individuel Limited 82,400.00 0.00 2021-12-10 2021-12-15 2022-01-05 2022-02-09 2022-05-10 itumage de la RN30 Kavimvir e Trade Infrastructure ution a (Uvira) – Frontière Burundi (7 km) dans la province du S ud-Kivu ZR-CI-266429-CS-INDV / Etu des topographiques, géotech Component 2: Improving Cor En attente d'exéc niques, géophysiques, hydro IDA / V3940 A posteriori Individuel Limited 78,395.00 0.00 2021-12-10 2021-12-15 2022-01-05 2022-02-09 2022-05-10 e Trade Infrastructure ution géologiques, études d'implan tation du poste frontalier de Kavimvira Page 2 ZR-CI-266445-CS-CDS / Recr utement du Consultant (Firm Component 3: Supporting Co Sélection de cons En attente d'exéc e) chargé de la préparation e IDA / V3940 mmercialization of Selected A priori ultants par entent Direct 550,000.00 0.00 2022-01-20 2022-01-30 2022-04-05 2022-10-02 ution t mise en œuvre du concours Cross-border Value Chains e directe de meilleurs plans d'affaires ( Phase 1) ZR-CI-267602-CS-INDV / Pre Component 4: Supporting Im station de service d'un consu En cours d'exécut IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 24,000.00 0.00 2021-12-15 2021-12-19 2021-12-25 2022-01-15 2022-02-19 2023-02-19 ltant individuel assistant adm ion and Evaluation inistratif du projet basé à Kin shasa(CI) ZR-CI-267680-CS-INDV / Pre stations de service d'un cons ultant individuel chargé des études topographiques, géot Component 2: Improving Cor En attente d'exéc IDA / V3940 A posteriori Individuel Limited 160,000.00 0.00 2022-01-13 2022-01-18 2022-02-08 2022-03-15 2022-09-11 echniques, géophysiques, hy e Trade Infrastructure ution drogéologiques, études d’im plantation du poste frontalier de Kamanyola et de la plate f orme logistique de Kasindi ZR-CI-267697-CS-INDV / Pre Component 4: Supporting Im station de service d'un consu En cours d'exécut IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 12,000.00 0.00 2021-12-14 2021-12-19 2021-12-24 2022-01-14 2022-02-18 2023-02-18 ltant individuel Chauffeur bas ion and Evaluation é à Kinshasa (CI) ZR-CI-267740-CS-INDV / Pre Component 4: Supporting Im En cours d'exécut station de service d'un consu IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 12,000.00 0.00 2021-12-14 2021-12-19 2021-12-24 2022-01-14 2022-02-18 2023-02-18 ion ltant individuel Chauffeur bas and Evaluation é à Goma (CI) ZR-CI-267743-CS-INDV / Pre Component 4: Supporting Im En attente d'exéc station de service d'un consu IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 12,000.00 0.00 2021-12-16 2021-12-21 2022-01-11 2022-02-15 2023-02-15 ution ltant individuel Chauffeur bas and Evaluation é à Bukavu ZR-CI-273333-CS-INDV / Pre stations d'un consultant indiv Component 1. Improving Poli En attente d'exéc iduel chargé de l’élaboration IDA / V3940 cy and Regulatory Environm A posteriori Individuel Open 80,000.00 0.00 2022-02-02 2022-03-23 2022-04-13 2022-05-18 2022-11-14 ution du manuel des opérations po ent for cross border trade ur la distribution de subventi ons ZR-CI-283992-CS-INDV / Pre Component 4: Supporting Im stations de service d'un cons En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Open 93,000.00 0.00 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-07-14 ultant individuel en qualité d ution and Evaluation e Coordonnateur National du PFCIGL ZR-CI-284008-CS-INDV / Pre Component 4: Supporting Im stations de service d'un cons En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Open 60,000.00 0.00 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-07-14 ultant individuel en qualité d ution and Evaluation e Responsable Administratif et Financier du PFCIGL ZR-CI-284014-CS-INDV / Pre Component 4: Supporting Im stations de service d'un cons En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Open 36,000.00 0.00 2022-04-01 2022-05-20 2022-06-10 2022-07-15 2023-07-15 ultant individuel en qualité d ution and Evaluation e Comptable du PFCIGL ZR-CI-284017-CS-INDV / Pre Component 4: Supporting Im En attente d'exéc stations de service en qualité IDA / V3940 plementation and Monitoring A posteriori Individuel Open 60,000.00 0.00 2022-04-01 2022-05-20 2022-06-10 2022-07-15 2023-07-15 ution de Spécialiste en Suivi-Evalu and Evaluation ation du PFCIGL ZR-CI-284080-CS-INDV / Rec rutement par entente directe Component 4: Supporting Im En cours d'exécut de Monsieur Célestin BUCEK IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 75,000.00 0.00 2022-04-01 2022-07-19 2022-04-11 2022-05-02 2022-06-06 2023-06-06 ion UDERHWA BASHIGE en qualit and Evaluation é de Chef de Projet Commerc e ZR-CI-284093-CS-INDV / Pre Component 4: Supporting Im stations de service d'un cons En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Open 60,000.00 0.00 2022-04-01 2022-05-20 2022-06-10 2022-07-15 2023-07-15 ultant individuel en qualité d' ution and Evaluation Auditeur Interne du PFCIGL ZR-CI-284119-CS-INDV / Rec Component 4: Supporting Im En attente d'exéc rutement du Chargé de Com IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 45,000.00 0.00 2022-04-04 2022-04-09 2022-04-30 2022-06-04 2023-06-04 ution munication du PFCIGL and Evaluation ZR-CI-284162-CS-INDV / Rec rutement d'un consultant ind Component 4: Supporting Im En attente d'exéc ividuel Spécialiste en Chaîne IDA / V3940 plementation and Monitoring A posteriori Individuel Open 60,000.00 0.00 2022-04-04 2022-05-23 2022-06-13 2022-07-18 2023-07-18 ution s de Valeur au sein de l'Unité and Evaluation de Gestion du PFCIGL ZR-CI-284229-CS-INDV / Rec rutement d'un consultant ind Component 4: Supporting Im En attente d'exéc ividuel en qualité d'Assistant IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 24,000.00 0.00 2022-04-04 2022-04-09 2022-04-30 2022-06-04 2023-06-04 ution Prorgamme au sein de l'Unité and Evaluation de Gestion du PFCIGL ZR-CI-284611-CS-INDV / Rec Component 4: Supporting Im rutement d'un consultant ind En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 16,800.00 0.00 2022-04-05 2022-04-10 2022-05-01 2022-06-05 2023-06-05 ividuel en qualité de Cassier ution and Evaluation au sein du PFCIGL/CI basé à Goma ZR-CI-284616-CS-INDV / Rec Component 4: Supporting Im rutement d'un consultant ind En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 16,800.00 0.00 2022-04-04 2022-04-09 2022-04-30 2022-06-04 2023-06-04 ividuel en qualité de Caissier ution and Evaluation au sein du PFCIGL/UGP basé à Bukavu ZR-CI-284994-CS-INDV / Rec Component 4: Supporting Im rutement du consultant en c En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 48,000.00 0.00 2022-04-06 2022-04-11 2022-05-02 2022-06-06 2023-06-06 harge des VBG au sein du PF ution and Evaluation CIGL basé à Bukavu ZR-CI-285021-CS-INDV / Rec rutement par entente directe Component 4: Supporting Im En cours d'exécut Madame Clarisse MBWIHANG IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 42,000.00 0.00 2022-03-31 2022-07-05 2022-04-10 2022-05-01 2022-06-05 2023-06-05 ion ANE NDERO au poste de Spé and Evaluation cialiste Junior en Passation d e Marchés. ZR-CI-285255-CS-INDV / Rec Component 4: Supporting Im rutement d'un consultant ind En cours d'exécut IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 48,000.00 0.00 2022-04-05 2022-07-05 2022-04-10 2022-05-01 2022-06-05 2023-06-05 ividuel chargé des Aspects d ion and Evaluation e Sécurité au sein du PFCIGL Page 3 ZR-CI-285261-CS-INDV / Rec Component 4: Supporting Im rutement d'un consultant ind En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 48,000.00 0.00 2022-04-06 2022-04-11 2022-05-02 2022-06-06 2023-06-06 ividuel au poste d'Expert en ution and Evaluation Génie Civil au sein du PFCIGL ZR-CI-285278-CS-INDV / Rec Component 4: Supporting Im rutement d'un consultant ind En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 50,000.00 0.00 2022-04-06 2022-04-11 2022-05-02 2022-06-06 2022-10-04 ividuel chargé de l'élaboratio ution and Evaluation n du manuel des procédures du PFCIGL ZR-CI-285295-CS-INDV / Rec Component 4: Supporting Im rutement d'un consultant ind En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 50,000.00 0.00 2022-04-05 2022-04-10 2022-05-01 2022-06-05 2022-10-03 ividuel chargé de l'élaboratio ution and Evaluation n du manuel d'exécution du PFCIGL ZR-CI-285713-CS-INDV / Rec rutement d'un Consultant ind ividuel chargé de conduire u Component 1. Improving Poli En cours d'exécut ne Étude sur le système d'ap IDA / V3940 cy and Regulatory Environm A posteriori Individuel Limited 80,000.00 0.00 2022-04-07 2022-06-09 2022-04-12 2022-05-03 2022-06-07 2022-10-05 ion provisionnement et de distrib ent for cross border trade ution des produits grâce à la stratégie d'achats groupés p ar les commerçants transfron taliers ZR-CI-285717-CS-INDV / Pre stations de services d'un Con Component 1. Improving Poli sultant Individuel chargé de l' En cours d'exécut IDA / V3940 cy and Regulatory Environm A posteriori Individuel Limited 80,000.00 0.00 2022-04-07 2022-06-10 2022-04-12 2022-05-03 2022-06-07 2022-10-05 Identification et la Cartograp ion ent for cross border trade hie des associations de com merçants transfrontaliers à U vira, Kamanyola, Idjwi, Kiliba. ZR-CI-286706-CS-INDV / Rec Component 4: Supporting Im rutement d'un consultant ind En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 40,000.00 0.00 2022-04-26 2022-05-01 2022-05-22 2022-06-26 2022-10-24 ividuel chargé de l'élaboratio ution and Evaluation n d'un manuel d'exécution d u projet PFCIGL ZR-CI-265971-CS-INDV / Pre Component 4: Supporting Im stations d'un consultant-Firm IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 40,000.00 0.00 Annulé 2021-12-10 2021-12-15 2022-01-05 2022-02-09 2022-04-10 e chargée de l'élaboration d' and Evaluation un manuel d'exécution du pr ojet PFCIGL ZR-CI-273312-CS-INDV / Pre stations d'un consultant indiv iduel chargé de l'audit de la Component 2: Improving Cor IDA / V3940 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2022-01-31 2022-02-05 2022-02-26 2022-04-02 2022-09-29 mise en oeuvre du PAR pour l e Trade Infrastructure a Construction du poste front alier de la Petite Barrière de Goma ZR-CI-265982-CS-INDV / Rec rutement d'un consultant ind Component 4: Supporting Im ividuel en qualité de Chef de IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 72,000.00 0.00 Annulé 2021-12-06 2021-12-19 2021-12-16 2022-01-06 2022-02-10 2023-02-10 Projet Infrastructures du proj and Evaluation et PFCIGL pour les douze (12 ) mois à venir ZR-CI-286794-CS-INDV / Rec Component 4: Supporting Im rutement par entente directe En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 30,000.00 0.00 2022-04-01 2022-04-11 2022-05-02 2022-06-06 2022-12-03 de Monsieur Franklin MUSHA ution and Evaluation GALUSA en qualité de Chef d e Projet ZR-CI-265992-CS-INDV / Rec rutement d'un consultant ind Component 4: Supporting Im ividuel en qualité de Spéciali IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 66,000.00 0.00 Annulé 2021-12-10 2021-12-19 2021-12-20 2022-01-10 2022-02-14 2023-02-14 ste en Passation de Marchés and Evaluation du projet PFCIGL pour les do uze (12) mois à venir ZR-CI-286797-CS-INDV / Rec rutement par entente directe Component 4: Supporting Im En attente d'exéc de Monsieur Rémy MALEMBE IDA / V3940 plementation and Monitoring A posteriori Individuel Direct 27,960.00 0.00 2022-04-02 2022-04-12 2022-05-03 2022-06-07 2022-12-04 ution A en qualité de Spécialiste en and Evaluation Passation de Marchés ZR-CI-273290-CS-INDV / Pre stations d'un consultant indiv iduel chargé de l’élaboration Component 2: Improving Cor du plan de restauration des IDA / V3940 A posteriori Individuel Direct 115,000.00 0.00 Annulé 2022-01-26 2022-02-05 2022-02-26 2022-04-02 2022-09-29 e Trade Infrastructure moyens de subsistance en fa veur de la population affecté e par le Projet à la petite barr ière de Goma ZR-CI-286800-CS-INDV / Rec rutement d'un consultant ind ividuel chargé des études tec Component 2: Improving Cor En attente d'exéc IDA / V3940 A posteriori Individuel Limited 150,000.00 0.00 2022-04-20 2022-04-25 2022-05-16 2022-06-20 2022-12-17 hniques détaillées pour const e Trade Infrastructure ution ruction du poste frontalier de Rubenga dans la province du Sud-Kivu ZR-CI-300114-CS-INDV / Rec rutement d'un consultant int Component 2: Improving Cor En attente d'exéc IDA / V3940 A posteriori Individuel Open 180,000.00 0.00 2022-07-07 2022-08-25 2022-09-15 2022-10-20 2024-04-17 ernational chargé de la sauv e Trade Infrastructure ution egarde environnementale et sociale ZR-CI-304648-CS-INDV / Rec rutement du Chef de Mission Component 4: Supporting Im En attente d'exéc du Projet de Facilitation du C IDA / V3940 plementation and Monitoring A posteriori Individuel Direct - National 48,000.00 0.00 2022-07-30 2022-08-09 2022-08-30 2022-10-04 2023-04-02 ution ommerce et Intégration dans and Evaluation la Région des Grands Lacs ZR-CI-304658-CS-INDV / Rec rutement d'un consultant int Component 2: Improving Cor En attente d'exéc ernational chargé de la gesti IDA / V3940 A posteriori Individuel Limited 180,000.00 0.00 2022-08-01 2022-08-06 2022-08-27 2022-10-01 2024-03-24 e Trade Infrastructure ution on environnementale et soci ale au sein de la Cellule Infra structures ZR-CI-304680-CS-INDV / Pre stations de service d'un Cons ultant Individuel chargé des Component 4: Supporting Im Accords Commerciaux bilatér En attente d'exéc IDA / V3940 plementation and Monitoring A posteriori Individuel Direct - National 48,000.00 0.00 2022-08-19 2022-08-29 2022-09-19 2022-10-24 2023-10-24 aux et Intégration au sein de ution and Evaluation l'Unité de Gestion du Projet d e Facilitation du Commerce e t Intégration dans la Région des Grands Lacs, PFCIGL ZR-CI-305109-CS-INDV / Rec Component 4: Supporting Im En attente d'exéc rutement d'un Assistant Proje IDA / V3940 plementation and Monitoring A posteriori Individuel Limited 30,000.00 0.00 2022-08-10 2022-08-15 2022-09-05 2022-10-10 2023-10-10 ution t au sein de la Cellule Infrastr and Evaluation uctures Page 4