(P159843) Metropolitan Buenos Aires Urban Transformation Project PROCUREMENT PLAN Country: Argentina Region: LATIN AMERICA AND CARIBBEAN Approval Date: 27-Feb-2017 General Procurement Notice published on: 24-Feb-2017 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT Argentina : Metropolitan Buenos Aires Urban Transformation Project PLAN General Information Country: Argentina Bank’s Approval Date of the Original Procurement Plan: 2017-10-04 2022-02-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159843 GPN Date: 2017-02-24 Project Name: Metropolitan Buenos Aires Urban Transformation Project Loan / Credit No: IBRD / 87070, IBRD / 89910 S Executing Agency(ies): ocial and Urban Integration Provincial Entity WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AR-UCEPO-58819-CW-RFB / "Completamiento y Habitat improvement of Mejoramiento de 48 Viviendas disadvantaged Solicitud de Single Stage - One 2018-12- IBRD / 87070 Posterior Open - National 270,000.00 167,529.57 Firmado 2018-04-13 2018-04-19 2018-04-18 2018-05-03 2018-05-18 2018-05-28 2018-06-07 2018-07-19 2018-07-01 2018-10-08 Barrio Carlos Gardel" Partido neighborhoods in Greater ofertas Envelope 28 de Morón, Provincia de Buenos Aires Buenos Aires AR-UCEPO-59136-CW-RFB / Habitat improvement of Mejoramiento de Barrios disadvantaged Solicitud de Single Stage - One 1,077,121.1 2018-12- IBRD / 87070 Posterior Open - National 2,105,774.00 Firmado 2018-04-13 2018-04-19 2018-04-18 2018-05-03 2018-05-18 2018-05-30 2018-06-07 2018-07-12 2018-07-01 2018-09-19 Carlos Gardel - Presidente neighborhoods in Greater ofertas Envelope 6 28 Sarmiento Buenos Aires AR-UCEPO-81641-CW-RFB / Habitat improvement of "Mejoramiento edilicio en disadvantaged Solicitud de Single Stage - One 4,281,716.8 2020-03- IBRD / 87070 Posterior Open - National 4,233,144.12 Firmado 2018-10-16 2018-11-01 2018-10-26 2018-11-25 2019-02-18 2018-12-25 2019-03-11 2019-01-29 2019-04-16 Conjunto Habitacional neighborhoods in Greater ofertas Envelope 7 24 Presidente Sarmiento" Buenos Aires AR-UCEPO-81650-CW-RFB / Habitat improvement of "Infraestructura de servicios disadvantaged Solicitud de Single Stage - One 3,899,692.8 2020-07- básicos en Conjunto IBRD / 87070 Posterior Open - National 3,711,939.00 Firmado 2018-10-16 2018-11-01 2018-10-26 2018-11-25 2019-02-19 2018-12-25 2019-03-13 2019-01-29 2019-04-12 neighborhoods in Greater ofertas Envelope 8 22 Habitacional Presidente Buenos Aires Sarmiento" AR-OPISU-95750-CW-RFB / Habitat improvement of LPN Puesta en Valor Plaza disadvantaged Solicitud de Single Stage - One 1,907,784.2 2020-03- Central y Cancha Villegas en IBRD / 87070 Posterior Open - National 1,910,021.56 Firmado 2019-06-03 2019-01-31 2019-06-08 2019-07-20 2019-02-28 2019-08-19 2019-04-10 2019-09-23 2019-05-02 neighborhoods in Greater ofertas Envelope 2 21 Conjunto Habitacional Buenos Aires Presidente Sarmiento Habitat improvement of AR-OPISU-95752-CW-RFB / disadvantaged Solicitud de Single Stage - One 2,242,230.0 2020-04- LPN Instalación de Gas IBRD / 87070 Posterior Open - National 3,240,452.69 Firmado 2019-07-01 2019-04-27 2019-07-06 2019-08-17 2019-06-14 2019-09-16 2019-06-27 2019-10-21 2019-07-19 neighborhoods in Greater ofertas Envelope 2 18 Domiciliaria Buenos Aires National AR-OPISU-253667-CW-RFB / Procurement Proyecto de Integración Project Management and Solicitud de Single Stage - One Ejecución 2022-07- IBRD / 89910 Posterior Open - National Document - 1 7,422,100.00 0.00 2021-09-16 2021-09-21 2021-11-02 2021-12-02 2022-01-06 Urbana Peribebuy. Municipio Monitoring – PBA ofertas Envelope pendiente 05 Envelope process La Matanza. (Non Bank-SPD) AR-OPISU-253861-CW-RFB / PUESTA EN VALOR DE National VEREDAS Y MEJORA DEL Procurement Project Management and Solicitud de Single Stage - One Ejecución 2022-07- CONDUCTO PLUVIAL EN IBRD / 89910 Posterior Open - National Document - 1 332,529.13 0.00 2021-09-16 2021-09-21 2021-11-02 2021-12-02 2022-01-06 Monitoring – PBA ofertas Envelope pendiente 05 CALLES FORMOSA, FALUCHO, Envelope process MISIONES Y GRAL. LAVALLE. (Non Bank-SPD) MUNICIPIO QUILMES National AR-OPISU-253867-CW-RFB / Procurement RED SECUNDARIA PUERTA DE Project Management and Solicitud de Single Stage - One Ejecución 2022-07- IBRD / 89910 Posterior Open - National Document - 1 356,332.64 0.00 2021-09-16 2021-09-21 2021-11-02 2021-12-02 2022-01-06 HIERRO: ETAPA 2 - LA Monitoring – PBA ofertas Envelope pendiente 05 Envelope process MATANZA (Non Bank-SPD) National AR-OPISU-259259-CW-RFB / Procurement Consolidación del espacio Project Management and Solicitud de Single Stage - One Ejecución 2022-08- IBRD / 87070 Posterior Open - National Document - 1 775,911.00 0.00 2021-10-25 2021-10-30 2021-12-11 2022-01-10 2022-02-14 Público: Pulmón Deportivo y Monitoring – PBA ofertas Envelope pendiente 13 Envelope process recreativo - MORON (Non Bank-SPD) AR-OPISU-236596-CW-RFQ / Construcción de Islas de Habitat improvement of Disposición Transitoria y Request for disadvantaged Solicitud de Single Stage - One 2022-01- Cestos para la Gestión IBRD / 89910 Posterior Open - National Quotations (Non 185,932.00 0.00 Cancelado 2021-06-02 2021-07-28 neighborhoods in Greater cotizaciones Envelope 24 Integral de Residuos Sólidos Bank-SPD) Buenos Aires Urbanos - Puerta de Hierro y San Petersburgo - La Matanza AR-OPISU-236597-CW-RFQ / Construcción de Islas de Habitat improvement of Request for Disposición Transitoria y disadvantaged Solicitud de Single Stage - One 2022-01- IBRD / 89910 Posterior Open - National Quotations (Non 188,763.00 0.00 Cancelado 2021-06-03 2021-07-29 Cestos para la Gestión neighborhoods in Greater cotizaciones Envelope 25 Bank-SPD) Integral de Residuos Sólidos Buenos Aires Urbanos - Villa Itatí - Quilmes AR-OPISU-225843-CW-CDD / Construcción De Islas De Disposición Transitoria Para Habitat improvement of La Gestión Integral De Participación de la disadvantaged 2022-01- Residuos Sólidos Urbanos En IBRD / 87070 Posterior comunidad en las Open - National 107,901.28 0.00 Cancelado 2021-03-29 2021-04-03 2021-05-15 2021-06-14 2021-07-19 neighborhoods in Greater 15 Los Barrios Presidente adquisiciones Buenos Aires Sarmiento Y Carlos Gardel, Dentro Del Municipio De Morón AR-OPISU-266981-CW-RFB / National Islas de Disposición Procurement Project Management and Solicitud de Single Stage - One Ejecución 2022-09- Transitorias y Cestos - Partido IBRD / 89910 Posterior Open - National Document - 1 780,129.20 0.00 2021-12-10 2021-12-15 2022-01-26 2022-02-25 2022-04-01 Monitoring – PBA ofertas Envelope pendiente 28 de La Matanza; Partido de Envelope process Morón y Partido de Quilmes (Non Bank-SPD) AR-OPISU-279866-CW-RFB / National CONSTRUCCION DE Procurement Project Management and Solicitud de Single Stage - One Ejecución 2023-06- POLIDEPORTIVO Y IBRD / 87070 Posterior Open - National Document - 1 1,980,000.00 0.00 2022-09-05 2022-09-10 2022-10-22 2022-11-21 2022-12-26 Monitoring – PBA ofertas Envelope pendiente 24 MEJORAMIENTO DEL Envelope process ENTORNO - MORON (Non Bank-SPD) Page 1 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCEPO-28864-GO-RFB / Project Management and Solicitud de Single Stage - One Equipamiento para el Equipo IBRD / 87070 Posterior Limited 10,829.00 0.00 Cancelado 2017-12-04 2018-02-27 2018-04-28 Monitoring – PBA cotizaciones Envelope central de la SSTUyV AR-OPISU-199999-GO-RFQ Project Management and Solicitud de Single Stage - One / Adquisición de Equipos IBRD / 87070 Posterior Open - National 91,809.00 0.00 En ejecución 2020-11-03 2021-03-15 2020-12-26 2021-02-24 Monitoring – PBA cotizaciones Envelope Informáticos AR-OPISU-200000-GO-RFQ Project Management and Solicitud de Single Stage - One / Adquisición de GPS IBRD / 87070 Posterior Open - National 19,453.00 0.00 En ejecución 2020-11-03 2020-12-26 2021-02-24 Monitoring – PBA cotizaciones Envelope diferencial con Sistema GNSS RTK NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-OPISU-200782-NC-CDD / “Servicio de limpieza y Habitat improvement of mantenimiento de espacio Participación de la disadvantaged público para los Barrios Carlos IBRD / 87070 Posterior comunidad en las Open - National 179,023.00 0.00 En ejecución 2020-10-30 2021-03-02 2020-11-04 2020-11-14 2020-12-14 2021-01-18 2022-01-18 neighborhoods in Greater Gardel y Presidente adquisiciones Buenos Aires Sarmiento”, de la Municipalidad de Morón. AR-OPISU-201350-NC-CDD / Servicio de Promoción Socio- Habitat improvement of Ambiental y Recolección Participación de la disadvantaged diferenciada de Residuos IBRD / 87070 Posterior comunidad en las Open - National 116,386.00 0.00 En ejecución 2020-10-30 2021-05-11 2020-11-04 2020-12-16 2021-01-15 2021-02-19 2022-02-19 neighborhoods in Greater Sólidos Urbanos secos en el adquisiciones Buenos Aires Barrio Carlos Gardel y Presidente Sarmiento AR-OPISU-203060-NC-RFQ / Habitat improvement of Estudio de Suelo y Agua para disadvantaged Solicitud de Single Stage - One IBRD / 87070 Posterior Open - National 4,385.39 0.00 En ejecución 2020-11-21 2021-01-20 2021-01-16 2021-03-17 el Barrio Puerta de Hierro del neighborhoods in Greater cotizaciones Envelope Municipio de la Matanza Buenos Aires AR-OPISU-213722-NC-CDD / “Servicio de limpieza y Habitat improvement of mantenimiento de espacio Participación de la disadvantaged Ejecución público para los Barrios Puerta IBRD / 87070 Posterior comunidad en las Open - National 187,425.79 0.00 2021-01-19 2021-01-24 2021-03-07 2021-04-06 2021-05-11 2021-11-07 neighborhoods in Greater pendiente de Hierro, San Petersburgo,17 adquisiciones Buenos Aires de Marzo , 17 de Marzo Bis" del Municipio de La Matanza AR-OPISU-213721-NC-CDD / “Servicio de limpieza y Habitat improvement of Participación de la mantenimiento de espacio disadvantaged IBRD / 87070 Posterior comunidad en las Open - National 178,792.85 0.00 En ejecución 2021-01-19 2021-03-05 2021-01-24 2021-03-07 2021-04-06 2021-05-11 2021-11-07 público para el Barrio de Villa neighborhoods in Greater adquisiciones Itatí”, del Municipio de Buenos Aires Quilmes AR-OPISU-217691-NC-CDD / "Servicio de Promoción Socio- Ambiental y Recolección Habitat improvement of Diferenciada de Residuos Participación de la disadvantaged Sólidos Urbanos Secos en los IBRD / 87070 Posterior comunidad en las Open - National 124,371.11 0.00 En ejecución 2021-02-28 2021-05-11 2021-03-05 2021-04-16 2021-05-16 2021-06-20 2021-12-17 neighborhoods in Greater Barrios Puerta de Hierro, San adquisiciones Buenos Aires Petersburgo, 17 de Marzo y 17 de Marzo Bis", del Municipio de La Matanza AR-OPISU-223171-NC-CDD / "Servicio de Promoción Socio- Habitat improvement of Ambiental y Recolección Participación de la disadvantaged Diferenciada de Residuos IBRD / 87070 Posterior comunidad en las Open - National 195,310.00 0.00 En ejecución 2021-03-31 2021-05-11 2021-04-05 2021-05-17 2021-06-16 2021-07-21 2022-07-21 neighborhoods in Greater Sólidos Urbanos Secos en el adquisiciones Buenos Aires Barrio de Villa Itatí", del Municipio de Quilmes AR-OPISU-226119-NC-RFB / Habitat improvement of Saneamiento De Barrios disadvantaged Solicitud de Single Stage - One Ejecución Populares Desobstrucción De IBRD / 87070 Posterior Open - National 326,086.95 0.00 2021-04-19 2021-04-24 2021-06-05 2021-07-05 2021-08-09 2022-08-09 neighborhoods in Greater ofertas Envelope pendiente Pozos Ciegos Y Pluviales en Buenos Aires Varios Municipios AR-OPISU-239569-NC-RFB / “Saneamiento de Barrios Habitat improvement of Populares - Desobstrucción disadvantaged Solicitud de Single Stage - One IBRD / 87070 Posterior Open - National 1,392,197.00 0.00 En ejecución 2021-06-30 2021-06-17 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2023-04-13 de Pozos Ciegos y Pluviales en neighborhoods in Greater ofertas Envelope los Municipios de La Matanza, Buenos Aires Morón y Quilmes” AR-OPISU-258767-NC-RFB / “Generación de base de datos geoespaciales en el marco del Sistema de Información Territorial OPISU, para Project Management and Solicitud de Single Stage - One Ejecución IBRD / 87070 Posterior Open - National 196,350.00 0.00 2021-10-25 2021-10-30 2021-12-11 2022-01-10 2022-02-14 2022-08-13 planificación de Monitoring – PBA ofertas Envelope pendiente intervenciones en barrios del Registro Público de Villas y Asentamiento de la provincia de Buenos Aires." CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Habitat improvement of AR-UCEPO-29446-CS-INDV / disadvantaged Organizaciones sin Programa Fortalecimiento de IBRD / 87070 Posterior Limited 105,882.00 0.00 Cancelado 2018-01-24 2018-02-07 2018-03-09 2018-04-13 2019-04-08 neighborhoods in Greater fines de lucro Consorcios. Buenos Aires Page 2 AR-UCEPO-27888-CS-QCBS / Estudio para la realización de un Diagnóstico Integral Habitat improvement of Urbano Ambiental y Plan disadvantaged Selección basada Maestro para el Barrio IBRD / 87070 Posterior Open - National 400,000.00 0.00 Cancelado 2017-09-29 2017-11-03 2017-12-12 2018-01-27 2018-02-26 2018-03-18 2018-04-13 2018-11-09 neighborhoods in Greater en calidad y costo Presidente Sarmiento en Buenos Aires Morón. Subprograma de renovación urbana en conjuntos habitacionales. AR-UCEPO-27317-CS-QCBS / Estudio para Diagnóstico Habitat improvement of Integral y Diseño de Proyectos disadvantaged Selección basada Ejecutivos de las condiciones IBRD / 87070 Posterior Open - National 620,000.00 0.00 Cancelado 2017-09-29 2017-10-05 2017-11-03 2017-12-12 2018-01-27 2018-02-26 2018-03-18 2018-04-13 2018-09-10 neighborhoods in Greater en calidad y costo edilicias e infraestructura Buenos Aires urbana para el barrio Presidente Sarmiento ( Morón) AR-OPISU-146994-CS-QCBS / Servicios de Inspección Técnica de Obras de la Habitat improvement of Intervención Integral del disadvantaged Selección basada IBRD / 87070 Posterior Open - National 668,000.00 0.00 Bajo Revision 2020-01-06 2019-12-09 2020-03-31 2020-05-21 2020-06-25 2020-12-22 Barrio Carlos Gardel y Puesta neighborhoods in Greater en calidad y costo en Valor del Conjunto Buenos Aires Habitacional Presidente Sarmiento INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Habitat improvement of AR-UCEPO-27884-CS-CDS / disadvantaged Selección directa Relevamiento Socio- IBRD / 87070 Posterior Direct 130,000.00 112,058.03 Finalizado 2017-09-29 2017-10-04 2017-10-20 2017-11-22 2017-11-03 2018-03-28 2018-01-02 2018-08-15 neighborhoods in Greater de consultores Habitacional. Buenos Aires AR-UCEPO-75184-CS-INDV / Project Management and Especialista en Regularización IBRD / 87070 Posterior Individual Limited 11,650.00 6,614.38 Firmado 2018-08-24 2018-09-12 2018-08-27 2018-09-10 2018-09-03 2018-09-13 2018-09-04 2018-11-02 2018-12-31 Monitoring – PBA Dominial AR-UCEPO-75189-CS-INDV / Project Management and Especialista Coordinador de la IBRD / 87070 Posterior Individual Limited 10,000.00 5,617.98 Firmado 2018-08-24 2018-09-12 2018-08-27 2018-09-10 2018-09-03 2018-09-13 2018-09-04 2018-10-10 2018-12-31 Monitoring – PBA Gestión AR-UCEPO-75246-CS-INDV / Project Management and Especialista de Proyectos de IBRD / 87070 Posterior Individual Limited 13,350.00 7,559.29 Finalizado 2018-08-24 2018-09-12 2018-08-27 2018-09-10 2018-09-03 2018-09-13 2018-09-04 2018-10-31 2018-12-31 2018-12-31 Monitoring – PBA Obra de Equipamientos AR-UCEPO-75247-CS-INDV / Project Management and Coordinador General IBRD / 87070 Posterior Individual Limited 9,170.00 5,127.86 Firmado 2018-08-24 2018-09-12 2018-08-27 2018-09-10 2018-09-03 2018-09-12 2018-09-04 2018-10-10 2018-12-31 Monitoring – PBA SocioProductivo AR-UCEPO-75248-CS-INDV / Project Management and Especialista en Desarrollo IBRD / 87070 Posterior Individual Limited 9,170.00 5,149.81 Firmado 2018-08-24 2018-09-12 2018-08-27 2018-09-10 2018-09-03 2018-09-12 2018-09-04 2018-10-10 2018-12-31 Monitoring – PBA Comercial e Institucional AR-UCEPO-75249-CS-INDV / Especialista en Formulación Project Management and IBRD / 87070 Posterior Individual Limited 9,170.00 5,149.81 Firmado 2018-08-24 2018-09-12 2018-08-27 2018-09-10 2018-09-03 2018-09-12 2018-09-04 2018-10-10 2018-12-31 de Programas Monitoring – PBA SocioProductivos AR-UCEPO-75250-CS-INDV / Consultoría Individual para la elaboración de la Evaluación Project Management and de Impacto Ambiental y Social IBRD / 87070 Posterior Individual Limited 6,670.00 5,327.65 Finalizado 2018-08-24 2018-10-10 2018-08-27 2018-09-13 2018-09-03 2018-09-14 2018-09-04 2018-12-17 2018-12-31 2018-12-31 Monitoring – PBA de Villa Itatí y Villa Azul, y actualización del Marco de Gestión Ambiental y Social AR-UCEPO-75252-CS-INDV / Consultoría para la Project Management and Elaboración del Marco y Plan IBRD / 87070 Posterior Individual Limited 6,670.00 7,325.52 Finalizado 2018-08-24 2018-10-10 2018-08-27 2018-09-13 2018-09-03 2018-09-14 2018-09-04 2018-12-17 2018-12-31 2018-12-31 Monitoring – PBA de Reasentamiento Involuntario del Programa AR-UCEPO-75253-CS-INDV / Consultoría para la Project Management and Elaboración de la Evaluación IBRD / 87070 Posterior Individual Limited 9,170.00 7,325.52 Finalizado 2018-08-24 2018-10-10 2018-08-27 2018-09-13 2018-09-03 2018-09-14 2018-09-04 2018-12-17 2018-12-31 2018-12-31 Monitoring – PBA Ambiental y Social del Programa Habitat improvement of AR-UCEPO-29449-CS-INDV / disadvantaged IBRD / 87070 Posterior Individual Limited 205,000.00 0.00 Cancelado 2017-11-30 2017-12-05 2017-12-26 2018-01-30 2019-01-25 Fortalecimiento SSTUYV neighborhoods in Greater Buenos Aires AR-UCEPO-69018-CS-INDV / Project Management and Coordinador de Planificación IBRD / 87070 Posterior Individual Limited 19,240.00 0.00 Cancelado 2018-07-11 2018-07-04 2018-07-12 2018-07-16 2018-07-17 2018-12-31 Monitoring – PBA Urbana AR-UCEPO-69029-CS-INDV / Project Management and Especialista Urbanista IBRD / 87070 Posterior Individual Limited 14,790.00 0.00 Cancelado 2018-07-11 2018-07-04 2018-07-13 2018-07-16 2018-07-17 2018-12-31 Monitoring – PBA Ambiental AR-UCEPO-69033-CS-INDV / Project Management and Especialista en Seguimiento, IBRD / 87070 Posterior Individual Limited 13,000.00 0.00 Cancelado 2018-07-11 2018-07-04 2018-07-13 2018-07-15 2018-07-17 2018-12-31 Monitoring – PBA Monitoreo y Evaluación Habitat improvement of AR-UCEPO-29447-CS-INDV / disadvantaged Programa de inclusión IBRD / 87070 Posterior Individual Limited 240,000.00 0.00 Cancelado 2018-01-10 2018-01-15 2018-02-05 2018-03-12 2018-09-08 neighborhoods in Greater deportiva Buenos Aires AR-OPISU-97188-CS-INDV / Habitat improvement of Consultor para la Edición del disadvantaged IBRD / 87070 Posterior Individual Limited 7,800.00 0.00 Cancelado 2019-03-01 2019-03-06 2019-03-27 2019-05-01 2019-10-28 Plan Maestro del Barrio Carlos neighborhoods in Greater Gardel Buenos Aires Page 3 AR-OPISU-103129-CS-INDV / Fortalecimiento de la UCIBa- Project Management and IBRD / 87070 Posterior Individual Limited 87,000.00 12,673.43 Firmado 2019-02-28 2019-03-14 2019-03-05 2019-03-14 2019-03-26 2019-03-14 2019-04-30 2019-04-08 2023-12-31 MISP: Especialista en Gestión Monitoring – PBA Ambiental y Social de Obras. AR-OPISU-103139-CS-INDV / Fortalecimiento de UCIBa- Project Management and IBRD / 87070 Posterior Individual Limited 87,000.00 0.00 Cancelado 2019-02-28 2019-03-15 2019-03-05 2019-03-26 2019-04-30 2023-12-31 MISP: Especialista en Monitoring – PBA Adquisiciones AR-OPISU-115018-CS-INDV Habitat improvement of / Dos Consultores Senior disadvantaged IBRD / 87070 Posterior Individual Limited 24,418.00 7,008.76 Firmado 2019-05-17 2019-05-17 2019-05-22 2019-07-01 2019-06-12 2019-07-01 2019-07-17 2019-06-24 2019-12-31 Supervisores de Obra para el neighborhoods in Greater Fortalecimiento de UCIBa Buenos Aires AR-OPISU-115020-CS-INDV Habitat improvement of / Consultor Semi Senior disadvantaged IBRD / 87070 Posterior Individual Limited 7,849.00 0.00 Cancelado 2019-05-17 2019-05-17 2019-05-22 2019-06-12 2019-07-17 2019-12-31 Supervisor de Obra para el neighborhoods in Greater fortalecimiento de UCIBa Buenos Aires AR-OPISU-115446-CS-INDV / Consultor Administrativo Project Management and para fortalecer al área de IBRD / 87070 Posterior Individual Limited 35,406.00 0.00 Cancelado 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2022-05-02 Monitoring – PBA Adquisiciones del Municipio de Morón. AR-OPISU-115442-CS-INDV / Consultor para la Gestión Social y Articulación Project Management and IBRD / 87070 Posterior Individual Limited 40,465.00 0.00 Cancelado 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2022-05-02 Interinstitucional del Monitoring – PBA Programa para Fortalecer al Municipio de Morón AR-OPISU-115444-CS-INDV / Consultor para la Gestión de Obra y Articulación Project Management and IBRD / 87070 Posterior Individual Limited 40,465.00 0.00 Cancelado 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2022-05-02 Interinstitucional para Monitoring – PBA fortalecer al Municipio de Moron AR-OPISU-115440-CS-INDV Habitat improvement of / 3 (tres) Consultores disadvantaged Inspectores de Obra para IBRD / 87070 Posterior Individual Limited 20,930.00 0.00 Cancelado 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2022-05-02 neighborhoods in Greater Fortalecer al Municipio de Buenos Aires Morón AR-OPISU-115441-CS-INDV Habitat improvement of / Consultor Inspector de Obra disadvantaged IBRD / 87070 Posterior Individual Limited 12,210.00 0.00 Cancelado 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2022-05-02 Senior para fortalecer al neighborhoods in Greater Municipio de Morón Buenos Aires AR-OPISU-96262-CS-INDV / Project Management and IBRD / 87070 Previa Individual Limited 87,000.00 0.00 Cancelado 2020-03-01 2020-02-25 2020-03-07 2020-02-26 2020-03-16 2020-04-02 2024-12-30 Coordinador de Adquisiciones Monitoring – PBA AR-OPISU-97187-CS-INDV / Implementación del Plan de Habitat improvement of Reasentamiento de Carlos disadvantaged IBRD / 87070 Posterior Individual Limited 24,000.00 0.00 Cancelado 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2020-10-28 Gardel: Equipo de neighborhoods in Greater Acompañamiento Social (2 Buenos Aires consultores) AR-OPISU-157563-CS-INDV / Asistente Legal para la Project Management and IBRD / 87070 Posterior Individual Direct 8,318.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-18 2020-02-14 2020-02-14 2020-12-31 Dirección Provincial Técnica Monitoring – PBA Legal del MIySP AR-OPISU-157572-CS-INDV / Analista Legal para la Project Management and IBRD / 87070 Posterior Individual Direct 10,396.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Dirección Provincial Técnica Monitoring – PBA Legal del MIySP AR-OPISU-157574-CS-INDV / Asistente en Redeterminaciones de Precios Project Management and IBRD / 87070 Posterior Individual Direct 6,519.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 para la Dirección Provincial de Monitoring – PBA Redeterminación de precios del MIySP AR-OPISU-157578-CS-INDV / Especialista en Análisis de Project Management and IBRD / 87070 Posterior Individual Direct 10,396.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Viabilidad para la UCEPO del Monitoring – PBA MIySP AR-OPISU-157579-CS-INDV / Asistente en Seguimiento y Project Management and IBRD / 87070 Posterior Individual Direct 6,519.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Monitoreo de Obras para la Monitoring – PBA UCEPO del MIySP AR-OPISU-157584-CS-INDV / Especialista en Proyectos de Project Management and IBRD / 87070 Posterior Individual Direct 10,396.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Infraestructura Barrial para Monitoring – PBA UCIBA del MIySP AR-OPISU-157586-CS-INDV / Analista de Proyectos de Project Management and IBRD / 87070 Posterior Individual Direct 8,840.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Infraestructura Barrial para Monitoring – PBA UCIBA del MIySP AR-OPISU-157587-CS-INDV / Experto en Proyectos de Project Management and IBRD / 87070 Posterior Individual Direct 16,628.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Infraestructura Barrial para Monitoring – PBA UCIBA del MIySP AR-OPISU-157589-CS-INDV / Experto en Proyectos de Project Management and IBRD / 87070 Posterior Individual Direct 16,628.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Infraestructura Barrial para Monitoring – PBA UCIBA del MIySP AR-OPISU-157591-CS-INDV / Experto en Proyectos de Project Management and IBRD / 87070 Posterior Individual Direct 16,628.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Infraestructura Barrial para Monitoring – PBA UCIBA del MIySP Page 4 AR-OPISU-157592-CS-INDV / Especialista en Coordinación Project Management and IBRD / 87070 Posterior Individual Direct 10,396.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Administrativa para la UCIBA Monitoring – PBA del MIySP AR-OPISU-157594-CS-INDV / Especialista en Gestión Project Management and IBRD / 87070 Posterior Individual Direct 10,396.00 0.00 Cancelado 2020-02-05 2020-02-06 2020-02-06 2020-02-14 2020-02-14 2020-12-31 Presupuestaria para la UCIBA Monitoring – PBA del MIySP AR-OPISU-157602-CS-INDV Project Management and / Especialista en IBRD / 87070 Posterior Individual Limited 10,396.00 0.00 En ejecución 2020-02-05 2020-02-06 2020-02-10 2020-03-02 2020-04-06 2020-12-31 Monitoring – PBA Adquisiciones para OPISU AR-OPISU-157603-CS-INDV / Experto en Gestión y Project Management and Seguimiento de Proyectos IBRD / 87070 Posterior Individual Limited 16,628.00 0.00 En ejecución 2020-02-05 2020-02-06 2020-02-10 2020-03-02 2020-04-06 2020-12-31 Monitoring – PBA Integrales de Urbanización para OPISU AR-OPISU-157604-CS-INDV / Coordinador Experto en Project Management and Monitoreo de Proyectos con IBRD / 87070 Posterior Individual Limited 11,917.00 0.00 En ejecución 2020-02-05 2020-02-06 2020-02-10 2020-03-02 2020-04-06 2020-12-31 Monitoring – PBA Financiamiento Externo para OPISU AR-OPISU-169955-CS-INDV / Coordinador General de Project Management and Proyecto Urbano y IBRD / 87070 Posterior Individual Direct 7,060.00 4,949.99 Firmado 2020-04-23 2020-05-06 2020-05-03 2020-06-03 2020-05-24 2020-06-04 2020-06-28 2020-06-12 2020-12-25 Monitoring – PBA Arquitectónico Barrio Carlos Gardel AR-OPISU-169956-CS-INDV / Coordinador General de Project Management and IBRD / 87070 Posterior Individual Direct 7,060.00 4,917.05 Firmado 2020-04-23 2020-05-06 2020-05-03 2020-06-10 2020-05-24 2020-06-11 2020-06-28 2020-06-12 2020-12-25 Proyecto Urbano y Monitoring – PBA Arquitectónico Barrio Villa Itatí AR-OPISU-169959-CS-INDV Project Management and / Experto en Desarrollo de IBRD / 87070 Posterior Individual Direct 5,300.00 3,697.62 Firmado 2020-04-23 2020-05-06 2020-05-03 2020-06-04 2020-05-24 2020-06-04 2020-06-28 2020-06-12 2020-12-25 Monitoring – PBA Plan de Viviendas AR-OPISU-169963-CS-INDV Project Management and / Experto en Desarrollo de IBRD / 87070 Posterior Individual Direct 5,300.00 3,696.29 Firmado 2020-04-23 2020-05-06 2020-05-03 2020-06-03 2020-05-24 2020-06-05 2020-06-28 2020-06-12 2020-12-25 Monitoring – PBA Plan Urbano AR-OPISU-169964-CS-INDV / Experto en Diseño y Re- Project Management and IBRD / 87070 Posterior Individual Direct 5,300.00 3,696.29 Firmado 2020-04-23 2020-05-06 2020-05-03 2020-05-06 2020-05-24 2020-06-01 2020-06-28 2020-06-12 2020-12-25 acondicionamiento Socio Monitoring – PBA Productivo AR-OPISU-169969-CS-INDV Project Management and / 7 (siete) IBRD / 87070 Posterior Individual Direct 30,880.00 21,693.91 Firmado 2020-04-23 2020-05-06 2020-05-03 2020-06-04 2020-05-24 2020-05-26 2020-06-28 2020-06-12 2020-12-25 Monitoring – PBA Proyectistas/Dibujantes AR-OPISU-169971-CS-INDV Project Management and / Experto Legal en IBRD / 87070 Posterior Individual Direct 8,820.00 0.00 En ejecución 2020-04-23 2020-05-06 2020-05-03 2020-05-24 2020-06-28 2020-12-25 Monitoring – PBA Contrataciones AR-OPISU-178213-CS-INDV Project Management and / Consultor en Evaluación IBRD / 87070 Posterior Individual Direct 5,200.00 4,229.07 Firmado 2020-06-05 2020-07-16 2020-06-15 2020-07-15 2020-07-06 2020-07-17 2020-08-10 2020-08-04 2021-02-06 Monitoring – PBA Ambiental y Social AR-OPISU-182119-CS-CDS / Project Management and IBRD / 87070 Posterior Individual Direct 5,200.00 4,229.07 Firmado 2020-06-29 2020-07-15 2020-06-29 2020-07-16 2020-06-29 2020-07-17 2020-07-18 2020-08-04 2020-12-28 Especialista en Adquisiciones Monitoring – PBA AR-OPISU-182120-CS-INDV Project Management and IBRD / 87070 Posterior Individual Direct 5,200.00 4,229.07 Firmado 2020-06-29 2020-07-15 2020-06-29 2020-07-16 2020-06-29 2020-07-16 2020-07-15 2020-08-04 2020-12-27 / Experto en Contrataciones Monitoring – PBA AR-OPISU-182121-CS-INDV Project Management and / Especialista en Gestión IBRD / 87070 Posterior Individual Direct 6,400.00 4,362.24 Firmado 2020-06-29 2020-07-22 2020-06-29 2020-07-22 2020-07-07 2020-07-23 2020-07-15 2020-08-10 2020-12-28 Monitoring – PBA Presupuestaria AR-OPISU-182161-CS-INDV Project Management and / Consultoría de Procesos IBRD / 87070 Posterior Individual Direct 9,150.00 7,518.36 Firmado 2020-06-26 2020-07-02 2020-07-01 2020-07-01 2020-07-01 2020-07-23 2020-07-15 2020-08-06 2020-12-28 Monitoring – PBA Administrativos y Legales AR-OPISU-187700-CS-INDV / Especialista en Derecho Project Management and IBRD / 87070 Posterior Individual Direct 3,909.00 3,489.79 Firmado 2020-08-10 2020-08-13 2020-08-20 2020-08-12 2020-09-10 2020-08-14 2020-10-15 2020-08-31 2021-04-13 Urbano e Instrumentos de Monitoring – PBA Gestión Urbana para el OPISU AR-OPISU-187696-CS-INDV / Especialista en Hábitat, Project Management and Planificación Urbana y/o IBRD / 87070 Posterior Individual Direct 3,909.00 3,489.79 Firmado 2020-08-12 2020-08-12 2020-08-22 2020-08-12 2020-09-12 2020-08-14 2020-10-17 2020-08-31 2021-04-15 Monitoring – PBA Gestión del Suelo Urbano para el OPISU. AR-OPISU-188354-CS-INDV Project Management and / Comunicador Institucional IBRD / 87070 Posterior Individual Direct 3,896.00 3,489.79 Firmado 2020-08-15 2020-08-17 2020-08-25 2020-08-14 2020-09-15 2020-08-19 2020-10-20 2020-08-31 2021-04-18 Monitoring – PBA para el OPISU AR-OPISU-188358-CS-INDV / Experto en Integración e Project Management and IBRD / 87070 Posterior Individual Direct 2,857.00 2,525.40 Firmado 2020-08-15 2020-08-14 2020-08-25 2020-08-14 2020-09-15 2020-08-19 2020-10-20 2020-09-01 2021-04-18 Inserción Laboral para el Monitoring – PBA Opisu AR-OPISU-189378-CS-INDV Project Management and / Asistente Técnico de IBRD / 87070 Posterior Individual Direct 2,718.00 2,145.70 Firmado 2020-08-21 2020-08-20 2020-08-31 2020-09-23 2020-09-21 2020-10-26 2020-09-24 2021-04-24 Monitoring – PBA Proyectos Urbanos AR-OPISU-189379-CS-INDV Project Management and / Tres (3) Analistas en IBRD / 87070 Posterior Individual Direct 11,650.00 9,194.99 Firmado 2020-08-21 2020-08-20 2020-08-31 2020-09-07 2020-09-21 2020-09-07 2020-10-26 2020-09-14 2021-04-24 Monitoring – PBA Indicadores AR-OPISU-190236-CS-INDV Project Management and / Experto en Evaluación IBRD / 87070 Posterior Individual Direct 3,151.00 2,503.32 Firmado 2020-08-31 2020-08-27 2020-09-10 2020-09-14 2020-10-01 2020-11-05 2020-09-15 2021-05-04 Monitoring – PBA Ambiental y Social Page 5 AR-OPISU-190916-CS-INDV Project Management and / Dos (2) Expertos en IBRD / 87070 Posterior Individual Direct 4,630.00 3,692.80 Firmado 2020-09-03 2020-09-02 2020-09-13 2020-09-29 2020-10-04 2020-09-30 2020-11-08 2020-10-01 2021-05-07 Monitoring – PBA Sistemas Informáticos AR-OPISU-191604-CS-INDV / Consultor individual para la Actualización del Marco de Project Management and Gestión Ambiental y Social IBRD / 87070 Posterior Individual Direct 7,731.00 0.00 Bajo Revision 2020-09-08 2020-09-18 2020-10-09 2020-11-13 2021-05-12 Monitoring – PBA (MGAS) y Elaboración de Evaluaciones de Impacto Ambiental y Social (EIAS) AR-OPISU-191612-CS-INDV Project Management and Ejecución / Asistente Técnico de IBRD / 87070 Posterior Individual Direct 2,875.00 0.00 2020-09-08 2020-09-18 2020-10-09 2020-11-13 2021-05-12 Monitoring – PBA pendiente Servicios Auxiliares y Bienes AR-OPISU-198878-CS-INDV Project Management and / Experto en Ingeniería IBRD / 87070 Posterior Individual Direct 1,708.00 1,436.82 Firmado 2020-10-10 2020-10-15 2020-10-20 2020-10-15 2020-11-10 2020-10-16 2020-12-15 2020-10-20 2021-06-13 Monitoring – PBA Hidráulica AR-OPISU-198879-CS-INDV / Asistente Técnico del Equipo Project Management and IBRD / 87070 Posterior Individual Direct 1,708.00 1,430.47 Firmado 2020-10-14 2020-10-13 2020-10-24 2020-10-29 2020-11-14 2020-12-19 2020-10-30 2021-06-17 de Gestión Ambiental y Social Monitoring – PBA (EGAS) AR-OPISU-198881-CS-INDV / Coordinador de Integración Project Management and IBRD / 87070 Posterior Individual Direct 1,829.00 1,532.65 Firmado 2020-10-10 2020-10-15 2020-10-20 2020-10-28 2020-11-10 2020-12-15 2020-10-30 2021-06-13 de Proyectos y Gestión Monitoring – PBA Participativa AR-OPISU-200270-CS-CDS / Project Management and Selección directa Ejecución Especialista en Adquisiciones IBRD / 87070 Posterior Direct 1,808.31 0.00 2020-10-22 2020-11-01 2021-01-05 2021-07-04 Monitoring – PBA de consultores pendiente Senior AR-OPISU-201347-CS-CDS / Project Management and Selección directa Referente en Desarrollo IBRD / 87070 Posterior Direct 1,351.00 0.00 Bajo Revision 2020-10-29 2020-11-08 2021-01-12 2021-07-11 Monitoring – PBA de consultores Económico Territorial AR-OPISU-201371-CS-CDS / Project Management and Selección directa Coordinador del Equipo IBRD / 87070 Posterior Direct 1,681.00 1,075.60 Firmado 2020-10-29 2020-10-29 2020-11-08 2020-11-12 2021-01-12 2020-11-13 2021-07-11 Monitoring – PBA de consultores Territorial Social y Urbano AR-OPISU-204762-CS-INDV Habitat improvement of / Referente en organizaciones disadvantaged Ejecución productivas territoriales con IBRD / 87070 Posterior Individual Direct 647.00 0.00 2020-11-20 2020-11-30 2020-12-04 2020-12-07 2020-12-31 neighborhoods in Greater pendiente perfil en valorización de Buenos Aires residuos AR-OPISU-204765-CS-INDV Habitat improvement of / Consultor en disadvantaged IBRD / 87070 Posterior Individual Direct 788.00 0.00 Bajo Revision 2020-11-20 2020-11-30 2020-12-04 2020-12-07 2020-12-31 Acompañamiento de Unidades neighborhoods in Greater Productivas Autogestionadas Buenos Aires Habitat improvement of AR-OPISU-208140-CS-INDV disadvantaged IBRD / 87070 Posterior Individual Direct 17,291.00 15,401.21 Firmado 2020-12-09 2020-12-21 2020-12-19 2020-12-22 2021-01-01 2021-02-15 2021-01-04 2021-02-22 2021-11-21 / Consultor Agrimensor neighborhoods in Greater Buenos Aires AR-OPISU-208150-CS-INDV / Dos (2) Arquitectos Project Management and IBRD / 87070 Posterior Individual Limited 10,144.10 9,090.44 Firmado 2020-12-09 2020-12-10 2020-12-14 2020-12-29 2021-01-04 2021-01-22 2021-02-08 2021-02-22 2021-08-07 Especialistas en Planeamiento Monitoring – PBA Paisajista y Medio Ambiente AR-OPISU-210383-CS-INDV Project Management and / Experto Legal en IBRD / 87070 Posterior Individual Limited 8,205.00 639.22 Firmado 2020-12-21 2020-12-22 2020-12-26 2020-12-23 2021-01-16 2021-01-07 2021-02-20 2021-01-04 2021-12-31 Monitoring – PBA Contrataciones AR-OPISU-210389-CS-INDV Project Management and / Especialista en IBRD / 87070 Posterior Individual Limited 8,205.00 639.22 Firmado 2020-12-21 2020-12-22 2020-12-26 2020-12-23 2021-01-16 2021-01-07 2021-02-20 2021-01-04 2021-12-31 Monitoring – PBA Adquisiciones AR-OPISU-210390-CS-INDV Project Management and / Especialista en Gestión IBRD / 87070 Posterior Individual Limited 10,256.00 9,588.24 Firmado 2020-12-21 2020-12-22 2020-12-26 2020-12-23 2021-01-16 2021-01-10 2021-02-20 2021-01-04 2021-12-31 Monitoring – PBA Presupuestaria AR-OPISU-210393-CS-INDV / Especialista en Derecho Project Management and IBRD / 87070 Posterior Individual Limited 8,205.00 7,505.11 Firmado 2020-12-21 2020-12-22 2020-12-26 2020-12-29 2021-01-16 2021-01-13 2021-02-20 2021-01-05 2021-12-31 Urbano e Instrumentos de Monitoring – PBA Gestión Urbana AR-OPISU-210394-CS-INDV / Especialista en Hábitat, Project Management and IBRD / 87070 Posterior Individual Limited 8,205.00 7,375.58 Firmado 2020-12-21 2020-12-22 2020-12-26 2021-01-05 2021-01-16 2021-01-06 2021-02-20 2021-01-11 2021-12-31 Planificación Urbana y/o Monitoring – PBA Gestión del Suelo Urbano AR-OPISU-210400-CS-INDV Project Management and IBRD / 87070 Posterior Individual Limited 8,205.00 7,375.58 Firmado 2020-12-21 2020-12-22 2020-12-26 2020-12-28 2021-01-16 2020-12-28 2021-02-20 2021-01-04 2021-12-31 / Comunicador Institucional Monitoring – PBA AR-OPISU-210404-CS-INDV Project Management and / Tres (3) Analistas en IBRD / 87070 Posterior Individual Limited 24,615.00 21,544.92 Firmado 2020-12-21 2020-12-22 2020-12-26 2021-01-06 2021-01-16 2021-02-20 2021-01-28 2021-12-31 Monitoring – PBA Indicadores AR-OPISU-210409-CS-INDV Project Management and / Asistente Técnico de IBRD / 87070 Posterior Individual Limited 6,837.00 3,204.73 Firmado 2020-12-21 2021-01-13 2020-12-26 2021-01-26 2021-01-16 2021-01-28 2021-02-20 2021-02-19 2021-12-31 Monitoring – PBA Proyectos Urbanos AR-OPISU-210412-CS-INDV Project Management and / Experto en Evaluación IBRD / 87070 Posterior Individual Limited 6,700.00 0.00 En ejecución 2020-12-21 2021-11-30 2020-12-26 2021-01-16 2021-02-20 2021-12-31 Monitoring – PBA Ambiental y Social AR-OPISU-210417-CS-INDV Project Management and / Dos (2) Expertos en IBRD / 87070 Posterior Individual Limited 16,410.00 7,385.60 Firmado 2020-12-21 2020-12-28 2020-12-26 2021-01-11 2021-01-16 2021-01-12 2021-02-20 2021-01-18 2021-12-31 Monitoring – PBA Sistemas Informáticos AR-OPISU-210419-CS-INDV / Asistente Técnico del Equipo Project Management and IBRD / 87070 Posterior Individual Limited 4,786.00 0.00 Cancelado 2020-12-21 2020-12-26 2021-01-16 2021-02-20 2021-12-31 de Gestión Ambiental y Social Monitoring – PBA (EGAS) Page 6 AR-OPISU-210423-CS-INDV Project Management and / Experto en Ingeniería IBRD / 87070 Posterior Individual Limited 8,752.00 8,444.49 Firmado 2020-12-21 2021-01-13 2020-12-26 2021-02-11 2021-01-16 2021-02-12 2021-02-20 2021-02-19 2021-12-31 Monitoring – PBA Hidráulica AR-OPISU-210425-CS-INDV Project Management and / Coordinador del Equipo IBRD / 87070 Posterior Individual Limited 4,786.00 3,728.64 Firmado 2020-12-21 2021-01-13 2020-12-26 2021-02-19 2021-01-16 2021-03-09 2021-02-20 2021-03-10 2021-12-31 Monitoring – PBA Territorial Social y Urbano AR-OPISU-205409-CS-INDV Habitat improvement of / Ingeniero Civil para el disadvantaged IBRD / 87070 Posterior Individual Direct 880.00 0.00 Bajo Revision 2020-11-21 2020-11-26 2020-12-01 2020-12-07 2021-01-06 Fortalecimiento de neighborhoods in Greater Organizaciones Productivas Buenos Aires AR-OPISU-196390-CS-INDV / Siete (7) Habitat improvement of Proyectistas/Dibujantes para disadvantaged los Barrios 17 de Marzo, 17 IBRD / 87070 Posterior Individual Direct 31,598.00 0.00 Bajo Revision 2020-09-30 2020-09-30 2020-10-10 2020-10-31 2020-12-05 2021-06-03 neighborhoods in Greater de Marzo Bis, Puerta de Hierro Buenos Aires y San Petersburgo - Municipio de La Matanza AR-OPISU-196387-CS-INDV / Experto en Desarrollo de Habitat improvement of Plan de Vivienda (barrios 17 disadvantaged de Marzo, 17 de Marzo bis, IBRD / 87070 Posterior Individual Direct 5,416.92 0.00 Bajo Revision 2020-10-01 2020-10-11 2020-11-01 2020-12-06 2021-06-04 neighborhoods in Greater Puerta de Hierro y San Buenos Aires Petersburgo del Municipio de La Matanza) AR-OPISU-196388-CS-INDV / Coordinador General de Habitat improvement of Proyecto Urbano y disadvantaged IBRD / 87070 Posterior Individual Direct 7,222.00 0.00 Bajo Revision 2020-09-30 2020-09-29 2020-10-10 2020-10-31 2020-12-05 2021-06-03 Arquitectónico (barrios Puerta neighborhoods in Greater de Hierro y San Petersburgo Buenos Aires del Municipio de La Matanza) AR-OPISU-196386-CS-INDV / Coordinador General de Habitat improvement of Proyecto Urbano y disadvantaged IBRD / 87070 Posterior Individual Direct 7,222.00 0.00 Bajo Revision 2020-09-30 2020-10-10 2020-10-31 2020-12-05 2021-06-03 Arquitectónico (Barrios 17 de neighborhoods in Greater Marzo y 17 de Marzo bis del Buenos Aires Municipio de La Matanza) AR-OPISU-196389-CS-INDV / Experto en Diseño y Habitat improvement of Reacondicionamiento Socio disadvantaged Productivo (Barrios 17 de IBRD / 87070 Posterior Individual Direct 5,416.92 0.00 Bajo Revision 2020-09-30 2020-10-10 2020-10-31 2020-12-05 2021-06-03 neighborhoods in Greater Marzo, 17 de Marzo bis, Buenos Aires Puerta de Hierro y San Petersburgo del Municipio de La Matanza) AR-OPISU-196384-CS-INDV / Experto en Desarrollo de Habitat improvement of Plan Urbano (barrios 17 de disadvantaged IBRD / 87070 Posterior Individual Direct 5,416.92 0.00 Bajo Revision 2020-09-30 2020-10-10 2020-10-31 2020-12-05 2021-06-03 Marzo, 17 de Marzo bis, neighborhoods in Greater Puerta de Hierro y San Buenos Aires Petersburgo del Municipio de La Matanza) AR-OPISU-211392-CS-INDV Project Management and / Coordinador de IBRD / 87070 Previa Individual Open 40,793.00 0.00 Cancelado 2020-12-28 2021-01-12 2021-01-17 2021-02-07 2021-03-14 2024-12-31 Monitoring – PBA Adquisiciones Habitat improvement of AR-OPISU-210438-CS-INDV disadvantaged / Referente en Desarrollo IBRD / 87070 Posterior Individual Limited 9,801.00 9,057.13 Firmado 2020-12-21 2020-12-28 2020-12-26 2021-01-11 2021-01-16 2021-01-12 2021-02-20 2021-01-13 2021-12-31 neighborhoods in Greater Económico Territorial Buenos Aires AR-OPISU-212259-CS-INDV Project Management and / Especialista Coordinador de IBRD / 87070 Posterior Individual Limited 8,605.00 7,860.68 Firmado 2021-01-09 2021-01-12 2021-01-14 2021-01-20 2021-02-04 2021-01-21 2021-03-11 2021-01-21 2021-12-31 Monitoring – PBA la Gestión AR-OPISU-210597-CS-INDV Habitat improvement of / Ingeniero Civil para el disadvantaged IBRD / 87070 Posterior Individual Limited 4,178.00 3,850.30 Firmado 2020-12-21 2021-01-12 2020-12-26 2021-01-13 2021-01-16 2021-01-13 2021-02-20 2021-01-14 2021-06-30 Fortalecimiento de neighborhoods in Greater Organizaciones Productivas Buenos Aires AR-OPISU-213655-CS-INDV Habitat improvement of / Tres (3) Abogados disadvantaged IBRD / 87070 Posterior Individual Limited 20,552.48 17,105.08 Firmado 2021-01-19 2021-02-03 2021-01-24 2021-02-26 2021-02-14 2021-03-02 2021-03-21 2021-03-02 2021-12-31 asistentes en Regularización neighborhoods in Greater Dominial Buenos Aires AR-OPISU-215429-CS-INDV / Consultor Legal para la Project Management and IBRD / 87070 Posterior Individual Limited 6,027.00 3,409.04 Firmado 2021-01-28 2021-02-03 2021-02-05 2021-03-02 2021-02-26 2021-03-03 2021-04-02 2021-03-09 2021-12-31 Dirección Provincial de Monitoring – PBA Integración Productiva AR-OPISU-215435-CS-INDV Habitat improvement of / Profesional de ciencias disadvantaged económicas con formación en IBRD / 87070 Posterior Individual Limited 7,232.00 4,081.42 Firmado 2021-01-28 2021-02-03 2021-02-05 2021-02-25 2021-02-26 2021-02-25 2021-04-02 2021-03-01 2021-12-31 neighborhoods in Greater economía popular, social y Buenos Aires solidaria. Habitat improvement of AR-OPISU-216196-CS-INDV disadvantaged / Referente en Desarrollo IBRD / 87070 Posterior Individual Limited 7,771.00 3,995.10 Firmado 2021-01-30 2021-02-03 2021-02-04 2021-02-18 2021-02-25 2021-04-01 2021-02-19 2021-12-31 neighborhoods in Greater Laboral y Comercial Buenos Aires AR-OPISU-217853-CS-INDV Project Management and / Asesor Económico- IBRD / 87070 Posterior Individual Limited 8,042.00 4,609.73 Firmado 2021-02-10 2021-02-22 2021-02-15 2021-03-03 2021-03-08 2021-03-04 2021-04-12 2021-03-15 2021-10-09 Monitoring – PBA Financiero en Contrataciones AR-OPISU-218073-CS-INDV / Experto en Arquitectura y Project Management and IBRD / 87070 Posterior Individual Limited 8,042.00 0.00 Cancelado 2021-02-12 2021-02-22 2021-02-17 2021-03-10 2021-04-14 2021-10-11 Ordenamiento Territorial del Monitoring – PBA Hábitat Popular Habitat improvement of AR-OPISU-221609-CS-INDV disadvantaged / Dos (2) Consultores IBRD / 87070 Posterior Individual Limited 14,854.00 0.00 En ejecución 2021-03-01 2021-03-02 2021-03-06 2021-03-27 2021-05-01 2022-01-31 neighborhoods in Greater Territoriales Buenos Aires Page 7 AR-OPISU-221611-CS-INDV Project Management and / Asesor en calidad IBRD / 87070 Posterior Individual Limited 5,300.00 0.00 En ejecución 2021-03-01 2021-03-02 2021-03-06 2021-04-06 2021-03-27 2021-05-01 2021-12-31 Monitoring – PBA constructiva AR-OPISU-223152-CS-INDV Project Management and IBRD / 87070 Posterior Individual Limited 6,629.83 7,482.61 Firmado 2021-03-11 2021-03-18 2021-03-16 2021-04-08 2021-04-06 2021-05-11 2021-05-14 2021-11-07 / Experto en Ingeniería Civil Monitoring – PBA AR-OPISU-225244-CS-INDV Project Management and / Especialista en Gestión, IBRD / 87070 Posterior Individual Limited 6,961.32 4,319.65 Firmado 2021-03-26 2021-04-13 2021-03-31 2021-04-14 2021-04-21 2021-04-14 2021-05-26 2021-04-19 2021-11-22 Monitoring – PBA Seguimiento y Monitoreo AR-OPISU-225851-CS-INDV / Proyectista de Obras Project Management and IBRD / 87070 Posterior Individual Limited 9,944.75 11,123.82 Firmado 2021-03-29 2021-04-07 2021-04-03 2021-05-04 2021-04-24 2021-05-05 2021-05-29 2021-08-04 2021-11-25 Eléctricas y Alumbrado Monitoring – PBA Público AR-OPISU-225866-CS-INDV Project Management and / Proyectista de Obras IBRD / 87070 Posterior Individual Limited 9,944.75 11,155.55 Firmado 2021-03-29 2021-04-20 2021-04-03 2021-05-03 2021-04-24 2021-07-30 2021-05-29 2021-08-03 2021-11-25 Monitoring – PBA Hidráulicas Habitat improvement of AR-OPISU-225902-CS-INDV disadvantaged / Seis (6) Supervisores de IBRD / 87070 Posterior Individual Limited 6,528.00 0.00 Cancelado 2021-03-29 2021-04-05 2021-04-03 2021-04-24 2021-05-29 2021-12-31 neighborhoods in Greater Obras Buenos Aires Habitat improvement of AR-OPISU-225903-CS-INDV disadvantaged IBRD / 87070 Posterior Individual Limited 6,528.00 0.00 Cancelado 2021-03-29 2021-04-05 2021-04-03 2021-04-24 2021-05-29 2021-12-31 / Seis (6) Inspectores de Obra neighborhoods in Greater Buenos Aires AR-OPISU-228621-CS-INDV Project Management and / Asistente Técnico - IBRD / 87070 Posterior Individual 6,358.70 0.00 En ejecución 2021-04-12 2021-04-12 2021-04-17 2021-04-19 2021-05-08 2021-06-12 2021-12-31 Monitoring – PBA Arquitecto Habitat improvement of AR-OPISU-229687-CS-INDV disadvantaged IBRD / 87070 Posterior Individual Direct 1,650.00 1,659.50 Firmado 2021-04-19 2021-04-16 2021-04-29 2021-05-24 2021-05-20 2021-05-24 2021-06-24 2021-05-26 2021-12-21 / Consultor Territorial neighborhoods in Greater Buenos Aires AR-OPISU-236624-CS-INDV Project Management and / Arquitecto Proyectista IBRD / 87070 Posterior Individual Limited 6,030.00 5,742.73 Firmado 2021-06-21 2021-06-22 2021-06-26 2021-07-15 2021-07-17 2021-07-16 2021-08-21 2021-07-30 2022-01-23 Monitoring – PBA Urbano Senior AR-OPISU-236867-CS-INDV Project Management and / Administrativo de Planes IBRD / 87070 Posterior Individual Direct 3,015.00 3,065.29 Firmado 2021-06-21 2021-07-08 2021-07-01 2021-07-30 2021-07-22 2021-07-30 2021-08-26 2021-07-30 2022-01-24 Monitoring – PBA Integrales AR-OPISU-235657-CS-INDV / Tres (3) Coordinadores Project Management and IBRD / 87070 Posterior Individual Limited 13,600.00 0.00 En ejecución 2021-07-15 2021-07-15 2021-07-20 2021-07-26 2021-08-10 2021-09-14 2022-03-13 Territoriales - Quilmes y La Monitoring – PBA Matanza. AR-OPISU-244212-CS-INDV Project Management and Ejecución / Experto en Desarrollo de IBRD / 87070 Posterior Individual Limited 4,904.00 0.00 2021-08-30 2021-09-04 2021-09-25 2021-10-30 2021-12-21 Monitoring – PBA pendiente Viviendas Arquitecto AR-OPISU-244220-CS-INDV Project Management and Ejecución / Dos (2) Arquitectos IBRD / 87070 Posterior Individual Limited 3,464.00 0.00 2021-08-30 2021-09-04 2021-09-25 2021-10-30 2021-12-21 Monitoring – PBA pendiente Proyectistas AR-OPISU-244333-CS-INDV / Dos (2) Ingenieros Senior en Project Management and IBRD / 87070 Posterior Individual Limited 7,750.44 0.00 En ejecución 2021-08-30 2021-09-07 2021-09-04 2021-09-25 2021-10-30 2021-12-21 Proyectos e Instalaciones Monitoring – PBA Civiles AR-OPISU-244335-CS-INDV / Dos (2) Ingenieros Senior en Project Management and IBRD / 87070 Posterior Individual Limited 7,750.44 0.00 En ejecución 2021-08-30 2021-09-07 2021-09-04 2021-09-25 2021-10-30 2021-12-21 Proyectos e Instalaciones Monitoring – PBA Eléctricas y Electromecánicas AR-OPISU-251125-CS-INDV Project Management and / Experto en Planeamiento IBRD / 87070 Posterior Individual Limited 3,293.94 0.00 En ejecución 2021-08-30 2021-09-01 2021-09-22 2021-10-27 2021-12-21 Monitoring – PBA Paisajista y Medio Ambiente AR-OPISU-251128-CS-INDV Project Management and / Dos (2) Supervisores de IBRD / 87070 Posterior Individual Limited 7,362.92 0.00 En ejecución 2021-08-30 2021-09-04 2021-09-25 2021-10-30 2021-12-21 Monitoring – PBA Obras AR-OPISU-251129-CS-INDV Project Management and / Asesor Técnico IBRD / 87070 Posterior Individual Limited 3,681.46 0.00 En ejecución 2021-08-30 2021-09-04 2021-09-25 2021-10-30 2021-12-21 Monitoring – PBA Administrativo AR-OPISU-251914-CS-INDV Project Management and / Especialista Estadístico IBRD / 87070 Posterior Individual Limited 2,330.00 0.00 En ejecución 2021-09-03 2021-09-08 2021-09-29 2021-11-03 2021-12-21 Monitoring – PBA Social y Productivo AR-OPISU-251127-CS-INDV Project Management and / Consultor Asistente en IBRD / 87070 Posterior Individual Limited 3,100.17 0.00 En ejecución 2021-08-30 2021-09-04 2021-09-25 2021-10-30 2021-12-21 Monitoring – PBA Adquisiciones AR-OPISU-253807-NC-DIR / Contratación del Instituto de Espacialidad Humana (IEH), para la creación de Proyectos arquitectónicos licitatorios, Project Management and Selección directa Ejecución IBRD / 87070 Posterior Direct 861,680.00 0.00 2021-10-20 2021-10-30 2022-01-03 2022-07-02 enmarcados en propuestas Monitoring – PBA de consultores pendiente urbanas integrales para Barrios insertos en la Región Metropolitana de Buenos Aires. AR-OPISU-266025-CS-INDV Project Management and / Ingeniero Senior con IBRD / 87070 Posterior Individual Limited 13,628.00 0.00 En ejecución 2021-12-03 2021-12-08 2021-12-29 2022-02-02 2022-05-30 Monitoring – PBA experiencia en proyectos AR-OPISU-266027-CS-INDV Project Management and / Consultor de Procedimientos IBRD / 87070 Posterior Individual Limited 755.00 0.00 En ejecución 2021-12-03 2021-12-08 2021-12-29 2022-02-02 2022-03-30 Monitoring – PBA Administrativos y Legales Page 8 AR-OPISU-274401-CS-INDV Project Management and / Consultor en Seguridad e IBRD / 87070 Posterior Individual Limited 8,462.00 0.00 En ejecución 2022-01-24 2022-01-25 2022-01-29 2022-02-19 2022-03-26 2022-12-21 Monitoring – PBA Higiene AR-OPISU-274405-CS-INDV / Proyectista de obras a Project Management and IBRD / 87070 Posterior Individual Limited 9,520.00 0.00 En ejecución 2022-01-24 2022-01-25 2022-01-29 2022-02-19 2022-03-26 2022-12-21 realizar con Organizaciones Monitoring – PBA Productivas de la Comunidad AR-OPISU-274411-CS-INDV Project Management and / Referente/a Inclusión IBRD / 87070 Posterior Individual Limited 8,462.00 0.00 En ejecución 2022-01-24 2022-01-25 2022-01-29 2022-02-19 2022-03-26 2022-09-22 Monitoring – PBA Financiera AR-OPISU-274417-CS-INDV Project Management and IBRD / 87070 Posterior Individual Limited 8,462.00 0.00 En ejecución 2022-01-24 2022-01-29 2022-02-19 2022-03-26 2022-12-21 / Comunicador Institucional Monitoring – PBA AR-OPISU-274435-CS-INDV Project Management and / Experto en análisis IBRD / 87070 Posterior Individual Limited 10,577.00 0.00 En ejecución 2022-01-24 2022-01-29 2022-02-19 2022-03-26 2022-12-21 Monitoring – PBA demográficos AR-OPISU-274436-CS-INDV / Especialista en econometría, Project Management and análisis económico espacial, IBRD / 87070 Posterior Individual Limited 10,577.00 0.00 En ejecución 2022-01-24 2022-01-29 2022-02-19 2022-03-26 2022-12-21 Monitoring – PBA web scraping y desarrollo de algoritmos AR-OPISU-274402-CS-INDV Project Management and / Tres (3) Asistentes IBRD / 89910 Posterior Individual Limited 20,625.00 0.00 En ejecución 2022-01-24 2022-01-26 2022-01-29 2022-02-19 2022-03-26 2022-12-21 Monitoring – PBA Territoriales – La Matanza Page 9