Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under July 9, 2010 other methods July 9, 2010 PROCUREMENT Bangladesh : Bangladesh NATP-2: National Agricultural Technology Program - Phase II Project PLAN General Information Country: Bangladesh 2017-03-09 Bank’s Approval Date of the Original Procurement Plan: 2022-09-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149553 GPN Date: Project Name: Bangladesh NATP-2: National Agricultural Technology Program - Phase II Project Loan / Credit No: IDA / 56650 Project Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned WD/PMU-01 / Refurbishment Request for Quota Single Stage - One E 2019-01-1 of Kitchen, Office Space and IDA / 56650 Project Management Post Limited 12,903.00 11,396.45 Signed 2018-05-19 2018-05-20 2018-07-14 2018-06-06 tions nvelope 0 building of baths WD/PMU-02 / Refurbishment Request for Quota Single Stage - One E 2019-11-1 of PMU Office Space-Account IDA / 56650 Project Management Post Open - National 6,450.00 0.00 Canceled 2019-03-25 2019-05-20 tions nvelope 6 Building BARC Request for Quota WD/PMU-03 / Renovation of Request for Quota Single Stage - One E 2021-10-2 IDA / 56650 Project Management Post Limited tions (Non Bank-S 12,900.00 10,901.08 Signed 2021-08-05 2021-11-25 2021-08-30 2021-12-02 PMU Office and Bathrooms tions nvelope 0 PD) Request for Quota WD/PMU-04 / Repair & Reno Request for Quota Single Stage - One E Pending Imp 2022-10-2 IDA / 56650 Project Management Post Limited tions (Non Bank-S 6,480.00 0.00 2022-09-05 2022-09-20 vation of PMU Office. tions nvelope lementation 0 PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD/PMU/09A / Office supplie Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,450.00 0.00 Canceled 2017-03-17 2017-04-06 2017-04-20 s and Consumables, PMU tions nvelope Request for Quota Single Stage - One E GD/PMU-6 / Furniture, PMU IDA / 56650 Project Management Post Open - National 2,970.00 2,306.33 Signed 2017-03-22 2017-04-27 2017-06-21 2017-05-27 tions nvelope GD/PMU-07 / Electrical Good s: Television- 01 No, Refriger Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 2,580.00 2,329.98 Signed 2017-05-15 2018-04-24 2017-07-24 2017-06-15 2017-08-21 ator- No, Micro Oven- 01 No, tions nvelope Electric Kettle- 01 No. NATP-2/PP/GD-2 / Laptop Co Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 363,871.00 330,377.87 Signed 2017-10-02 2017-12-19 2017-10-09 2017-11-06 2018-01-25 2017-12-04 2018-04-30 2018-01-15 2018-05-28 2018-02-26 mputer nvelope NATP-2/PP/GD-3 / Mobile Tab Single Stage - One E Under Imple IDA / 56650 Project Management Post Request for Bids Open - National 1,508,387.00 0.00 2017-10-09 2017-12-19 2017-10-16 2017-11-13 2018-02-13 2017-11-27 2018-04-30 2018-01-08 2018-02-05 lets nvelope mentation NATP-2/PP/GD-7 / Furniture f Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 1,640,000.00 863,135.98 Signed 2017-11-06 2018-05-06 2017-11-13 2017-12-11 2018-02-15 2018-01-08 2018-04-30 2018-02-19 2018-05-09 2018-03-19 or FIAC centers nvelope GD/PMU-10 / Stationery and Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,452.00 4,673.51 Completed 2018-05-19 2018-05-21 2018-07-14 2018-06-05 2019-01-10 2018-06-24 Consumables tions nvelope GD/PMU-11 / Computer and Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 3,871.00 3,537.18 Completed 2018-05-19 2018-05-28 2018-07-14 2018-06-05 2019-01-10 2018-06-12 Consumables tions nvelope NATP-2/PP/GD-8 / Furniture f Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 1,141,936.00 0.00 Canceled 2017-11-06 2018-05-06 2017-11-13 2017-12-11 2018-02-19 2018-01-08 2018-04-30 2018-02-19 2018-03-19 or Training Centers nvelope Single Stage - One E NATP-2/PP/GD-6 / Air Cooler IDA / 56650 Project Management Post Request for Bids Open - National 456,774.00 0.00 Canceled 2017-11-15 2017-12-19 2017-11-22 2017-12-13 2018-02-12 2017-12-27 2018-04-30 2018-02-07 2018-03-07 nvelope NATP-2/PP/GD-1 / Computer Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 936,774.00 0.00 Canceled 2017-10-02 2017-12-19 2017-10-09 2017-11-06 2018-01-30 2017-12-04 2018-04-30 2018-01-15 2018-02-26 and Accessories nvelope NATP-2/PP/GD-5 / Video and Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 1,003,871.00 0.00 Canceled 2017-10-23 2017-12-19 2017-10-30 2017-11-20 2018-02-06 2017-12-18 2018-04-30 2018-01-29 2018-02-26 Digital Camera nvelope NATP-2/PP/GD-4 / Pico Projec Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 123,871.00 0.00 Canceled 2017-10-02 2017-12-19 2017-10-09 2017-11-06 2018-02-06 2017-11-20 2018-04-30 2018-01-01 2018-01-29 tor nvelope NATP-2/PP/E-GP/GD-04 / Pico Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 123,871.00 114,387.84 Signed 2018-07-11 2018-07-10 2018-07-16 2018-08-27 2018-08-01 2018-09-26 2018-10-23 2018-10-31 2018-11-22 2019-04-29 Projector nvelope NATP-2/PP/E-GP/GD-08 / Pool ed Procurement of Furniture f Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 994,998.00 909,558.49 Signed 2018-08-27 2019-02-07 2018-09-01 2018-09-30 2018-12-11 2018-10-30 2018-12-22 2018-12-11 2019-03-07 2019-03-26 or Training Centers for PIU-B nvelope ARC, PIU-DAE, PIU-DoF and PI U-DLS NATP-2/PP/E-GP/GD-01 LOT- 01 / Pooled Procurement of D Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 851,335.00 786,166.18 Signed 2018-08-27 2018-09-12 2018-09-01 2018-10-13 2018-10-25 2018-11-12 2018-11-28 2018-12-17 2019-01-08 2019-03-17 esktop Computers, Offline UP nvelope S, Printers, Scanners and Ser ver NATP-2/PP/E-GP/GD-05 LOT- Single Stage - One E 02 / Pooled Procurement of M IDA / 56650 Project Management Post Request for Bids Open - National 761,548.00 703,959.87 Signed 2018-08-19 2018-09-06 2018-08-24 2018-10-05 2018-10-08 2018-11-04 2018-12-03 2018-12-09 2019-01-20 2019-03-10 nvelope ultimedia Projector with Scre en NATP-2/PP/E-GP/GD-05 LOT- Single Stage - One E 03 / Photocopier Normal & H IDA / 56650 Project Management Post Request for Bids Open - National 49,212.00 44,728.05 Signed 2018-08-20 2018-09-25 2018-08-25 2018-10-06 2018-10-29 2018-11-05 2018-11-13 2018-12-10 2019-01-20 2019-03-11 nvelope eavy Duty and Fax Machine NATP-2/PP/E-GP/GD-06 / Pool Single Stage - One E IDA / 56650 Project Management Post Request for Bids Open - National 456,774.00 421,805.16 Signed 2018-08-09 2018-08-27 2018-08-14 2018-09-13 2018-09-24 2018-10-13 2018-12-18 2018-11-17 2019-01-17 2021-09-30 ed Procurement Air Coolers nvelope NATP-2/PP/E-GP/GD-05 LOT- Single Stage - One E 01 / Digital Camera and Vide IDA / 56650 Project Management Post Request for Bids Open - National 170,839.00 0.00 Canceled 2018-08-15 2018-08-20 2018-10-01 2018-10-31 2018-12-05 2019-03-07 nvelope o Camera Handycam Page 1 NATP-2/PP/E-GP/SD-05A LOT Request for Quota Single Stage - One E 1 / Digital Camera and Video IDA / 56650 Project Management Post Open - National 170,839.00 0.00 Canceled 2019-04-01 2019-05-27 2019-11-23 tions nvelope Camera Handycam NATP-2/PP/GD-5A / Pooled Pr Enhancing Agricultural Tech Single Stage - One E ocurement of Digital Camera IDA / 56650 Post Request for Bids Open - National 173,000.00 0.00 Canceled 2019-09-09 2019-09-14 2019-10-09 2019-11-20 2020-01-01 2020-06-29 nology Generation nvelope and Video Camera GD/PMU-20 / Procurement of Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,415.00 5,832.89 Signed 2019-10-24 2020-06-24 2019-11-10 2020-07-05 2019-11-28 Photocopy Machine tions nvelope GD/PMU-15 / Supply and Inst Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,452.00 0.00 Canceled 2018-09-11 2018-10-14 2018-11-04 allation of IP Phone tions nvelope GD/PMU-14 / Printing of Ann Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,452.00 0.00 Canceled 2018-08-27 2018-09-23 2018-11-22 ual Report of NATP-2 Project tions nvelope GD/PMU-16 / Office Stationer Request for Quota Single Stage - One E IDA / 56650 Project Management Post Open - National 4,968.00 0.00 Canceled 2019-03-25 2019-05-20 2019-11-16 y and Consumables tions nvelope GD/PMU-13 / Office Equipme Request for Quota Single Stage - One E nt and Computer Consumabl IDA / 56650 Project Management Post Limited 6,452.00 0.00 Canceled 2018-12-21 2019-01-24 2019-02-21 tions nvelope es for PMU Office GD/PMU-24 / Zoom Apps for Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,450.00 1,768.97 Signed 2021-01-21 2021-02-04 2021-02-01 2021-02-17 2021-12-31 video conference tions nvelope GD/PMU-25 / Printing of Ann Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,450.00 5,686.50 Signed 2021-01-21 2021-03-29 2021-02-01 2021-04-13 2021-12-31 ual Progress Report (2019-20 tions nvelope ) GD/PMU-22 / Office Stationer Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,450.00 5,768.35 Signed 2021-03-14 2021-03-29 2021-04-04 2021-05-09 2021-04-15 y & Consumables Goods tions nvelope GD/PMU-23 / Computer Cons Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,450.00 5,726.93 Signed 2021-03-17 2021-05-24 2021-04-04 2021-06-03 2021-04-15 umables for PMU tions nvelope GD/PMU-26 / Procurement of Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,450.00 5,757.03 Signed 2021-08-15 2022-02-01 2021-08-25 2022-03-07 2021-09-20 Office Furniture for PMU tions nvelope GD/PMU-27 / Printing of Ann Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,450.00 0.00 Canceled 2022-03-15 2022-03-30 2022-05-17 ual Progress Report ( 2020-2 tions nvelope 021 ) GD/PMU-28 / Office Stationer Request for Quota Single Stage - One E Pending Impl IDA / 56650 Project Management Post Limited 6,450.00 0.00 2022-01-16 2022-01-30 2022-02-28 y & Consumables for PMU tions nvelope ementation GD/PMU-29 / Computer Con Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 6,450.00 5,344.86 Signed 2022-04-20 2021-12-26 2022-05-05 2022-01-09 2022-05-31 sumables/Accessories for PM tions nvelope U GD/PMU-31 / Internet conne Request for Quota Single Stage - One E Pending Impl IDA / 56650 Project Management Post Limited 6,450.00 0.00 2022-01-24 2022-02-28 2023-03-31 ctivity for PMU tions nvelope ementation GD/PMU-32 / Printing of NAT Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 5,900.00 2,200.64 Signed 2021-11-30 2022-01-06 2021-12-13 2022-02-13 2022-01-09 P-2 Diary for the year 2022 tions nvelope GD/E-GP/ PMU- 09 / Procure Single Stage - One E Under Imple ment of Office Equipment, D IDA / 56650 Project Management Post Request for Bids Open - National 25,710.00 0.00 2021-12-02 2022-05-22 2021-12-07 2022-09-04 2021-12-28 2022-01-16 2022-02-20 2022-03-23 nvelope mentation esktop, Laptop etc. and Serv er accessories GD/E-GP/PMU-10 / Printing it ems: (i)Annual Progress Repo rt 2020-21 (ii) Communicatio n Strategy action Plan. Single Stage - One E Under Imple (iii)Gender and Value Chain S IDA / 56650 Project Management Post Request for Bids Open - National 17,700.00 0.00 2022-01-13 2022-03-29 2022-01-18 2022-03-30 2022-02-10 2022-03-10 2022-04-21 2022-05-31 nvelope mentation tudy. (iv) Strategy and Actio n Plan: Gender Equality, Soci al Inclusion and Women' Em powerment. (v) Booklet GD/PMU-33 / Procurement of Request for Quota Single Stage - One E Pending Impl IDA / 56650 Project Management Post Limited 2,120.00 0.00 2022-08-29 2022-09-07 2022-09-21 1(One) Laptop for PMU tions nvelope ementation GD/PMU-34 / Computer Con Request for Quota Single Stage - One E Pending Impl IDA / 56650 Project Management Post Limited 5,888.00 0.00 2022-09-01 2022-09-11 2022-09-27 sumables/ Accessories for P tions nvelope ementation MU GD/PMU-35 / Office Stationer Request for Quota Single Stage - One E Pending Impl IDA / 56650 Project Management Post Limited 5,888.00 0.00 2022-10-02 2022-10-13 2022-10-31 y & Consumables for PMU tions nvelope ementation GD/PMU-36 / Printing of Ann Request for Quota Single Stage - One E Pending Impl IDA / 56650 Project Management Post Limited 5,653.00 0.00 2023-01-02 2023-01-12 2023-02-08 ual Progress Report (2021-20 tions nvelope ementation 22) GD/E-GP/PMU-11 / Printing of Documents- 1.Success StoriesNATP-2 (Ba ngla & English), 2. Research- Single Stage - One E Pending Impl Extension Linkage Strategy a IDA / 56650 Project Management Post Request for Bids Open - National 24,145.00 0.00 2022-11-01 2022-11-06 2022-11-22 2022-12-22 2023-02-02 2023-03-14 nvelope ementation nd Action Plan, 3. Informatio n of Agriculture Innovation F und (AIF-2 & AIF-3), 4. Inform ation of FIAC, 5. Data base of Producer Organization NATP- 2 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD/PMU-12 / Non-consulting Request for Quota Single Stage - One E IDA / 56650 Project Management Post Limited 3,871.00 2,217.16 Completed 2018-05-19 2018-05-14 2018-07-14 2018-05-21 2019-01-10 2018-06-20 Service for Computer repair tions nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 SD/PMU/F1 / Firm Hire for Ba Quality And Cost- se Line Survey, Monitoring & IDA / 56650 Project Management Prior Open - National 1,637,419.00 0.00 Canceled 2017-10-11 2018-01-15 2017-10-18 2017-12-06 2018-07-30 2018-01-17 2018-11-28 2018-02-15 2018-03-15 2018-04-26 2021-09-30 Based Selection Evaluation and Impact Asses sments. SD/PMU/F2 / Consulting Firm Quality And Cost- Under Implement IDA / 56650 Project Management Post Open - National 677,419.00 0.00 2017-10-18 2017-12-19 2017-11-01 2017-12-13 2018-12-18 2018-01-10 2018-12-18 2018-02-07 2018-11-28 2018-03-07 2019-03-04 2018-04-18 2021-09-30 for Internal Audit. Based Selection ation SD/PMU/F-3 / Consulting Fir m Hire for Developing of Co Consultant Qualifi IDA / 56650 Project Management Post Open - National 82,580.00 82,644.66 Signed 2018-08-20 2018-09-10 2018-09-10 2018-10-24 2019-05-05 2018-11-23 2019-10-21 2018-12-28 2019-11-04 2021-09-30 mputerized/Web Based Acco cation Selection unting and Reporting Softwar e SD/PMU/F-4 / Consulting Fir Quality And Cost- IDA / 56650 Project Management Post Open - National 200,000.00 0.00 Canceled 2019-09-22 2019-10-13 2019-12-12 2020-01-09 2020-02-27 2020-03-24 2020-05-05 2021-11-02 m Hire for AudioVideo/Film Pr Based Selection oduction SD/PMU/F-5 / Consulting Fir Quality And Cost- m Hire for Information and C IDA / 56650 Project Management Post Open - National 464,516.00 232,692.38 Signed 2019-09-19 2020-04-19 2019-10-10 2020-06-29 2019-12-19 2020-12-22 2020-01-16 2021-01-24 2020-03-12 2021-05-06 2020-04-16 2021-05-16 2020-05-21 2021-05-23 2021-09-30 Based Selection ommunication Technologies f or PMU SD/PMU/F-6 / Pooled Procure ment of Consulting Firm for d Supporting Agricultural Tech Quality And Cost- esign and development of ag IDA / 56650 nology for Crops Developme Post Open - National 335,484.00 225,983.88 Signed 2019-09-15 2019-11-20 2019-10-06 2019-12-10 2019-12-08 2020-03-03 2020-01-05 2020-06-10 2020-02-27 2020-08-27 2020-04-02 2020-09-17 2020-05-07 2020-12-27 2021-05-07 Based Selection ricultural extension MIS for P nt IU-DAE, PIU-DOF and PIU-DLS SD/PMU/F-7 / Pooled Procure ment of Consulting Firm for D Supporting Agricultural Tech Quality And Cost- esign and Development of Ag IDA / 56650 nology for Crops Developme Post Open - National 174,193.00 84,534.93 Signed 2019-09-24 2019-04-21 2019-10-15 2020-06-17 2019-12-12 2021-01-17 2020-01-09 2021-02-17 2020-02-27 2021-06-03 2020-04-02 2021-06-28 2020-05-07 2021-08-09 2021-05-07 Based Selection ricultural Knowledge and Lea nt rning Platform for PIU-DAE, P IU-DLS and PIU-DOF SD/PMU/F-8 / Procurement of Quality And Cost- Open - Internationa Consulting Firm for Impact A IDA / 56650 Project Management Prior 580,645.00 350,816.37 Signed 2019-12-15 2021-03-14 2020-01-05 2021-05-17 2020-03-08 2021-12-18 2020-04-05 2022-01-18 2020-05-05 2022-04-04 2020-06-09 2022-05-09 2020-07-14 2022-05-16 2021-09-30 Based Selection l ssessment of NATP-2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD/PMU/IC-10 / Training and Individual Consult IDA / 56650 Project Management Post Open 267,100.00 300,829.66 Signed 2017-03-02 2017-10-17 2017-05-15 2017-10-22 2017-05-29 2017-10-26 2017-06-26 2017-10-31 2021-09-30 Communication Specialist, P ant Selection MU SD/PMU/IC-09 / Monitoring a Individual Consult IDA / 56650 Project Management Post Open 267,100.00 297,234.66 Signed 2017-03-02 2017-10-17 2017-05-15 2017-10-22 2017-05-29 2017-10-26 2017-06-26 2017-11-02 2021-09-30 nd Evaluation Specialist, PMU ant Selection SD/PMU/IC-13 / Assistant Ma Individual Consult IDA / 56650 Project Management Prior Open 222,580.00 108,466.38 Signed 2017-03-02 2017-05-15 2017-10-05 2017-05-29 2017-10-30 2017-06-26 2017-11-06 2021-09-30 nager (Procurement), PMU ant Selection SD/PMU/IC-07 / ICT Specialis Individual Consult IDA / 56650 Project Management Post Open 267,100.00 407,246.00 Signed 2017-03-02 2017-05-15 2017-12-18 2017-05-29 2017-12-21 2017-06-26 2020-11-17 2021-09-30 t, PMU ant Selection SD/PMU/IC-12 / Assistant Ma Individual Consult IDA / 56650 Project Management Prior Open 445,160.00 216,411.12 Signed 2017-03-02 2017-05-15 2017-10-05 2017-05-29 2017-10-30 2017-06-26 2017-11-01 2021-09-30 nager (Accounts), PMU, 2 Pos ant Selection ition SD/PMU/IC-3 / Procurement Enhancing Agricultural Tech Individual Consult Specialist (PMU, BARC, DAE, IDA / 56650 Prior Open 1,112,910.00 730,181.93 Signed 2017-02-23 2017-08-20 2017-10-22 2017-08-24 2017-11-05 2017-08-31 2017-11-26 2021-12-28 nology Generation ant Selection DoF and DLS)- 5 Positions SD/PIU-BARC-5 / Procuremen Individual Consult IDA / 56650 Project Management Prior Open 222,580.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 t Specialist (PIU-BARC) ant Selection SD DOF/IC-02 / Procurement Individual Consult IDA / 56650 Project Management Prior Open 244,840.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 Specialist (PIU-DOF) ant Selection PS/LS-4 / Procurement Speci Individual Consult IDA / 56650 Project Management Prior Open 133,550.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 alist (PIU-DLS) ant Selection SD/PMU/IC-14 / Procurement Individual Consult IDA / 56650 Project Management Post Open 89,030.00 90,198.45 Signed 2017-03-02 2017-05-15 2017-10-05 2017-05-29 2017-10-10 2017-06-26 2017-10-24 2019-07-31 Support Specialist, PMU ant Selection PP/SD/PIU-DAE/IC-02 / Procur Individual Consult IDA / 56650 Project Management Prior Open 244,840.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 ement Specialist, PIU-DAE ant Selection PP/SD/PIU-DAE/IC-01 / Mana Individual Consult IDA / 56650 Project Management Post Open 244,840.00 0.00 Canceled 2017-03-01 2017-05-14 2017-05-28 2017-06-25 2021-09-30 ger (Financial Management), ant Selection PIU-DAE SD/PIU-BARC-4 / Manager (Fi Individual Consult IDA / 56650 Project Management Post Open 267,100.00 0.00 Canceled 2017-02-28 2017-05-13 2017-05-27 2017-06-24 2021-09-30 nancial Management), PIU-B ant Selection ARC SD DOF/IC-01 / Manager (Fin Individual Consult IDA / 56650 Project Management Post Open 244,840.00 0.00 Canceled 2017-03-01 2017-05-14 2017-05-28 2017-06-25 2021-09-30 ancial Management), PIU-DO ant Selection F PS/LS-3 / Manager (Financial Individual Consult IDA / 56650 Project Management Post Open 267,100.00 0.00 Canceled 2017-03-01 2017-05-14 2017-05-28 2017-06-25 2021-09-30 Management), PIU-DLS ant Selection SD/PMU/IC-16 / Consultant ( Individual Consult Office Management and Coor IDA / 56650 Project Management Prior Direct 13,355.00 0.00 Canceled 2017-03-12 2017-03-18 2017-03-23 2017-04-01 2017-06-30 ant Selection dination), PMU SD/PMU/IC-15 / Consultant ( Individual Consult IDA / 56650 Project Management Prior Direct 13,355.00 0.00 Canceled 2017-03-12 2017-03-18 2017-03-23 2017-04-01 2017-06-30 Human Resource Developme ant Selection nt), PMU SD/PMU/IC-2 / Manager (Fina Individual Consult IDA / 56650 Project Management Post Open 267,100.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 ncial Management), PMU ant Selection SD/PMU/IC-02 / Manager (Fin Enhancing Agricultural Tech Individual Consult ancial Management) for PMU IDA / 56650 Prior Open 1,290,980.00 723,362.10 Signed 2017-09-19 2017-11-07 2017-10-09 2017-11-28 2017-10-30 2018-01-02 2017-11-30 2018-07-01 nology Generation ant Selection and four PIUs SD/PMU/IC-01 / Sector Coord Individual Consult IDA / 56650 Project Management Post Open 267,097.00 268,831.95 Signed 2017-12-04 2017-12-03 2018-01-22 2018-06-11 2018-02-12 2018-06-20 2018-03-19 2018-06-28 2018-09-15 inator, Extension Specialist ant Selection Page 3 SD/PMU/IC-04 / Project Mana Individual Consult IDA / 56650 Project Management Post Open 267,097.00 146,743.01 Signed 2017-12-04 2017-12-03 2018-01-22 2018-06-11 2018-02-12 2018-06-20 2018-03-19 2018-06-28 2018-09-15 gement Specialist ant Selection SD/PMU/IC-05 / Research-Ext Individual Consult IDA / 56650 Project Management Post Open 267,097.00 268,846.34 Signed 2017-12-04 2017-12-03 2018-01-22 2018-06-11 2018-02-12 2018-06-20 2018-03-19 2018-06-28 2018-09-15 ension Linkage Specialist ant Selection SD/PMU/IC-06 / Producer Org Individual Consult IDA / 56650 Project Management Post Open 267,097.00 268,831.95 Signed 2017-12-04 2017-12-03 2018-01-22 2018-06-11 2018-02-12 2018-06-20 2018-03-19 2018-06-28 2018-09-15 anization Mobilization Special ant Selection ist SD/PIUS/PP/IC-1 / Environme Individual Consult Under Implement ntal and Social Safeguard Sp IDA / 56650 Project Management Prior Open 390,968.00 0.00 2017-12-04 2018-01-22 2018-08-08 2018-02-12 2018-11-01 2018-03-19 2018-09-15 ant Selection ation ecialist, PIU-BARC, PIU-DAE, P IU-DoF, PIU-DLS SD/PMU/IC-02A / Manager ( F Individual Consult IDA / 56650 Project Management Prior Open 267,100.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-02-25 2018-05-17 2018-11-13 inancial Management), PIU-D ant Selection LS SD/PMU/IC-3A / Procurement Individual Consult IDA / 56650 Project Management Prior Open 244,840.00 147,405.63 Signed 2018-02-01 2018-03-22 2018-04-12 2018-05-15 2018-05-17 2018-05-24 2018-11-13 Specialist, PIU-DAE ant Selection SD/PMU/IC-08 / Gender Spec Individual Consult IDA / 56650 Project Management Post Open 267,097.00 0.00 Canceled 2017-12-04 2017-12-03 2018-01-22 2018-02-12 2018-03-19 2018-09-15 ialist ant Selection SD/PMU/IC-11 / Assistant Ma Individual Consult IDA / 56650 Project Management Post Open 222,580.00 0.00 Canceled 2017-03-02 2017-11-30 2017-05-15 2017-05-29 2017-06-26 2021-09-30 nager (Administration), PMU ant Selection SD/PMU/IC-11A / Assistant M Individual Consult Under Implement IDA / 56650 Project Management Post Open 63,870.00 0.00 2018-11-12 2019-02-20 2018-12-31 2019-01-21 2019-02-25 2019-08-24 anager (Administration), PMU ant Selection ation SD/PMU/IC-3B / Procurement Individual Consult IDA / 56650 Project Management Prior Open 278,581.00 169,416.56 Signed 2019-03-21 2019-07-21 2019-05-09 2019-10-07 2019-05-30 2019-10-29 2019-07-04 2019-11-20 2019-12-31 Specialist, PIU-BARC, PIU-DoF ant Selection SD/PMU/IC-13A / Assistant M Individual Consult Under Implement IDA / 56650 Project Management Prior Open 83,575.00 0.00 2019-03-21 2019-07-22 2019-05-09 2019-09-25 2019-05-30 2019-09-30 2019-07-04 2019-12-31 anager (Procurement), PMU ant Selection ation SD/PMU/IC-2B / Pooled Procu rement of Manager (Financia Individual Consult Under Implement IDA / 56650 Project Management Prior Limited 435,484.00 0.00 2018-08-16 2018-09-10 2018-10-01 2018-11-05 2021-09-30 l Management) for PIU-DAE , ant Selection ation PIU-DLS, PIU-DOF SD/PMU/IC-13B / Assistant M Individual Consult IDA / 56650 Project Management Post Open 49,000.00 122,943.41 Signed 2019-11-11 2019-07-22 2019-11-11 2019-10-29 2019-11-11 2019-10-31 2019-11-24 2019-11-17 2021-09-30 anager ( Procurement ) for P ant Selection MU SD/PMU/IC-STC2 / DPP Revisi Individual Consult on and Procurement Support IDA / 56650 Project Management Post Direct 24,194.00 0.00 Canceled 2019-12-15 2020-03-02 2019-12-25 2019-12-30 2020-01-13 2021-01-12 ant Selection Consultant SD/PMU/IC-12A / Assistant M Individual Consult IDA / 56650 Project Management Post Open 41,000.00 94,205.47 Completed 2020-01-27 2020-01-29 2020-03-16 2020-11-19 2020-03-23 2020-12-06 2020-04-06 2020-12-09 2021-08-26 2022-05-16 anager ( Accounts) of PMU ant Selection SD/PMU/IC-07A / Procureme Individual Consult IDA / 56650 Project Management Post Open 67,000.00 160,697.51 Signed 2020-01-28 2020-03-09 2020-03-17 2020-09-17 2020-03-23 2020-11-08 2020-04-07 2020-11-17 2021-09-30 nt of ICT Specialist for PMU ant Selection SD/PMU-IC -STC 01 / Commu Individual Consult Under Implement nication Consultant for PMU IDA / 56650 Project Management Post Limited 29,032.00 0.00 2018-09-16 2019-03-07 2018-09-21 2018-10-12 2018-11-16 2019-05-15 ant Selection ation Duration = 6 months SD/PMU/IC-08A / Gender Spe Individual Consult Under Implement IDA / 56650 Project Management Post Open 106,451.00 0.00 2018-11-12 2019-02-26 2018-12-31 2019-01-21 2019-02-25 2021-09-30 cialist, PMU ant Selection ation SD/PMU/IC-STC2A / Individua Individual Consult l Short Term Consultant for IDA / 56650 Project Management Post Open 29,500.00 0.00 Canceled 2020-03-15 2020-03-11 2020-05-03 2020-05-24 2020-06-28 2020-12-25 ant Selection DPP Revision and Procureme nt Support SD/PMU/IC-04A / Project Man Individual Consult IDA / 56650 Project Management Post Open 38,709.67 116,720.20 Signed 2020-11-09 2020-11-22 2020-12-28 2021-09-02 2021-01-18 2021-09-16 2021-02-22 2021-09-21 2021-09-30 agement Specialist ( PMS) of ant Selection PMU SD/PMU/IC- STC-03 / Short T Individual Consult erm Consultant for Gender a IDA / 56650 Project Management Post Limited 12,903.22 13,208.10 Signed 2020-11-08 2020-12-22 2020-11-17 2020-12-28 2020-11-25 2021-04-15 2020-12-08 2021-04-27 2021-03-08 ant Selection nd Value Chain Study for PM U SD/PMU/IC-03C / Procureme Supporting Agricultural Tech Individual Consult IDA / 56650 Post Open 38,709.67 0.00 Canceled 2020-11-22 2020-11-24 2021-01-10 2021-01-31 2021-03-07 2021-09-30 nt Specialist of PIU- DOF nology for Fisheries Develop ant Selection ment SD/PMU/IC/STC-04 / Short-Te Individual Consult Pending Impleme rm Individual - Technical Co IDA / 56650 Project Management Post Open - National 25,405.00 0.00 2022-09-20 2022-11-10 2022-11-17 2022-12-22 2023-06-30 ant Selection ntation nsultant for Project Completi on Report (PCR) SD/PMU/IC/STC-05 / Short-Te Individual Consult Pending Impleme rm Individual Consultant -Ec IDA / 56650 Project Management Post Open - National 20,320.00 0.00 2022-09-20 2022-11-10 2022-11-17 2022-12-22 2023-06-30 ant Selection ntation onomist for Project Completi on Report (PCR) SD/PMU/IC/STC-06 / Short-Te rm Individual Consultant Fin Individual Consult Pending Impleme IDA / 56650 Project Management Post Open - National 20,320.00 0.00 2022-09-20 2022-11-10 2022-11-17 2022-12-22 2023-06-30 ancial Expert for Project Co ant Selection ntation mpletion Report (PCR) SD/PMU/IC/STC-07 / Short-Te rm Individual Consultant –Pr Individual Consult Pending Impleme oject Results Assessment Ex IDA / 56650 Project Management Post Open - National 25,405.00 0.00 2022-09-20 2022-11-10 2022-11-17 2022-12-22 2023-06-30 ant Selection ntation pert for Implementation Co mpletion and Results Report (ICRR) SD/PMU/IC/STC-08 / Short-Te rm Individual Consultant -Ec Individual Consult Pending Impleme IDA / 56650 Project Management Post Open - National 20,320.00 0.00 2022-09-20 2022-11-10 2022-11-17 2022-12-22 2023-06-30 onomist for Implementation ant Selection ntation Completion and Results Rep ort (ICRR SD/PMU/IC/STC-09 / Short-Te rm Individual- Technical Co Individual Consult Pending Impleme IDA / 56650 Project Management Post Open - National 20,320.00 0.00 2022-09-20 2022-11-10 2022-11-17 2022-12-22 2023-06-30 nsultant for Implementation ant Selection ntation Completion and Results Rep ort (ICRR) SD/PMU/IC- 03D / Pooled Pro Supporting Agricultural Tech Individual Consult curement of Procurement Sp IDA / 56650 nology for Livestock Develop Post Open 55,868.00 0.00 Canceled 2021-12-05 2022-01-27 2022-02-01 2022-02-07 2022-03-10 2023-02-09 ant Selection ecialist for PIU- DLS ment Page 4 SD/PMU/ IC- 2 / Pooled Procu Supporting Agricultural Tech Individual Consult rement of Environmental and IDA / 56650 nology for Crops Developme Post Open 81,300.00 0.00 Canceled 2021-12-05 2022-01-05 2022-02-01 2022-02-07 2022-03-10 2023-06-30 ant Selection Social Safeguard Specialist fo nt r PIU-DAE SD/PMU/IC-2A / Pooled Procu Individual Consult Pending Impleme rement of Environmental and IDA / 56650 Project Management Post Limited 27,429.00 0.00 2022-09-20 2022-09-27 2022-10-04 2022-10-08 2023-06-30 ant Selection ntation Social Safe guard Specialist f or PIU-DAE SD/PMU/IC-03E / Pooled Proc Individual Consult Pending Impleme urement of Procurement Spe IDA / 56650 Project Management Post Limited 45,720.00 0.00 2022-09-20 2022-09-27 2022-10-04 2022-10-08 2023-07-09 ant Selection ntation cialist for PIU-DLS Page 5