Private Sector-Led Mini-Grid Energy Access Project PROCUREMENT PLAN (Textual Part) Project information: Country: Nepal Project Name: Private Sector-Led Mini-Grid Energy Access Project, Project ID: P149239 Project Implementation agency: Alternative Energy Promotion Centre Khumaltaar Heights, Lalipur, Nepal Date of the Procurement Plan: October 24, 2018 Period covered by this Procurement Plan: October 2018 – March 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Open Procurement Arrangements: These procedures are applicable for the procurement of goods, works and non-consulting services only. In accordance with paragraph 5.3 of the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nepal’s Public Procurement Act, 2007, as amended by Amendment 2073 (2016) - (1st Amendment) and the Public Procurement Regulation, 2007, as amended by Amendment 2073 (2017) - (5th Amendment) made thereunder, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: (a) Eligibility to participate in a procurement process for and to be awarded the Bank financed contracts shall be as defined under the paragraph “Eligibility” of Section III Governance of the Procurement Regulations. Foreign bidders shall not be precluded from bidding and no preference of any kind shall be given to national bidders. (b)If a contract is terminated because of fundamental breach of contract by the contractor, the amount to be recovered from the contractor representing the employer’s additional costs for completing the contract shall be provisioned as agreed with the Bank in model bidding documents. (c) Performance security should be an amount of five (5) to ten (10) percent of the contract price and shall not be increased merely based on comparison of the bid price of awarded bidders with the pre-bid cost estimate. (d)Qualification criteria (in case pre-qualifications were not carried out) shall be stated in the bidding documents for all contracts, irrespective of the value, and if a registration process is required, a foreign firm declared as the lowest evaluated bidder shall be given a reasonable opportunity to register, without let or hindrance. (e) Model bidding documents, including contract conditions agreed with the Bank (as amended from time to time), shall be used. Bidding documents shall be made available, by mail or in person, or through e-GP portal to all who are willing to pay the required fee. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not applicable for those contracts identified in the Procurement Plan tables; Works: Not applicable, as no works procurement under this project. PROCUREMENT Nepal : Nepal: Private Sector-Led Mini-Grid Energy Access Project PLAN General Information Country: Nepal 2018-10-26 Bank’s Approval Date of the Original Procurement Plan: 2023-03-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149239 GPN Date: Project Name: Nepal: Private Sector-Led Mini-Grid Energy Access Project Loan / Credit No: / , TF / A8336, TF / A8382 Alternative Energy Promotion Centre Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-AEPC-77114-GO-RFQ / Pr Component 2: Technical Assi ocurement of Kitchen Consu stance to the Mini-grid Secto Request for Quota Single Stage - One E / Post Limited 8,000.00 548.50 Completed 2018-11-15 2019-12-26 2018-12-13 2020-01-16 2021-10-28 2020-01-16 mables (Water, Tea, Sugar, C r, ESCOs and Partner Banks tions nvelope offee etc.) and Project Management Su pport Component 2: Technical Assi NP-AEPC-77115-GO-RFQ / Pr stance to the Mini-grid Secto Request for Quota Single Stage - One E ocurement of Logistics (Stati / Post Limited 8,000.00 2,198.71 Completed 2018-11-15 2020-01-23 2018-12-13 2020-02-13 2021-10-28 2020-02-24 r, ESCOs and Partner Banks tions nvelope onery, Toner etc.) and Project Management Su pport Component 2: Technical Assi NP-AEPC-77117-GO-RFQ / Pr stance to the Mini-grid Secto Request for Quota Single Stage - One E ocurement of Printer, Scanne / Post Limited 10,000.00 3,130.25 Completed 2018-11-18 2019-12-06 2018-12-16 2020-01-06 2019-01-15 2020-02-05 r, ESCOs and Partner Banks tions nvelope r, Projector, Camera etc. and Project Management Su pport Component 2: Technical Assi NP-AEPC-77118-GO-RFQ / Pr stance to the Mini-grid Secto Request for Quota Single Stage - One E ocurement of Laptops for PIU / Post Open - National 20,000.00 15,349.51 Completed 2018-11-26 2020-08-12 2019-01-15 2020-06-14 2019-02-14 2020-06-21 r, ESCOs and Partner Banks tions nvelope (15 Laptops) and Project Management Su pport NP-AEPC-77119-GO-DIR / Pro Component 2: Technical Assi curement of Office Vehicle (T stance to the Mini-grid Secto / Post Direct Selection Direct 15,000.00 12,478.09 Completed 2018-11-16 2019-12-01 2018-11-23 2019-12-03 2018-12-07 2020-02-02 2019-01-21 2020-07-13 wo Wheeler) from authorized r, ESCOs and Partner Banks Dealer and Project Management Su pport NP-AEPC-77122-GO-RFQ / D Component 2: Technical Assi esign and Printing of Templat stance to the Mini-grid Secto Request for Quota Single Stage - One E es, Awareness Campaign Mat / r, ESCOs and Partner Banks Post Limited 9,000.00 0.00 Canceled 2019-03-27 2019-04-24 2019-05-14 tions nvelope erials, Guidelines, Standards, and Project Management Su Training Manuals and Report pport s Component 2: Technical Assi NP-AEPC-77116-GO-RFQ / Pr stance to the Mini-grid Secto Request for Quota Single Stage - One E TF / A8382 Post Limited 5,000.00 4,004.92 Completed 2021-11-20 2022-03-25 2021-12-18 2022-04-17 2022-01-17 2022-05-08 ocurement of Office Furniture r, ESCOs and Partner Banks tions nvelope and Project Management Su pport Component 2: Technical Assi NP-AEPC-258794-GO-RFQ / P stance to the Mini-grid Secto Request for Quota Single Stage - One E rocurement of Laptops and P TF / A8382 Post Limited 5,000.00 3,879.15 Completed 2021-11-20 2021-12-07 2021-12-18 2021-12-28 2022-01-08 2022-01-04 r, ESCOs and Partner Banks tions nvelope rinter and Project Management Su pport Component 2: Technical Assi NP-AEPC-333001-GO-RFQ / P stance to the Mini-grid Secto Request for Quota Single Stage - One E Under Imple TF / A8382 Post Limited 5,000.00 0.00 2023-01-01 2023-01-29 2023-02-13 rocurement of Printers r, ESCOs and Partner Banks tions nvelope mentation and Project Management Su pport NP-AEPC-333002-GO-RFB / P Component 2: Technical Assi rocurement of Goods: stance to the Mini-grid Secto Single Stage - One E Under Imple Slice 1: Monitoring Equipmen TF / A8382 r, ESCOs and Partner Banks Post Request for Bids Open - National 35,000.00 0.00 2023-01-13 2023-02-27 2023-01-15 2023-02-14 2023-02-24 2023-03-14 2023-04-28 nvelope mentation t and Project Management Su Slice 2: Flow Meters and Gas pport Analyser NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-AEPC-77123-NC-RFB / Hir ing Consultant for Awareness Campaign, Promotional Activi Component 2: Technical Assi ties, Training and Capacity B stance to the Mini-grid Secto Single Stage - One E uilding Activities of ESCOs an / r, ESCOs and Partner Banks Post Request for Bids Open - National 100,000.00 0.00 Canceled 2019-05-03 2019-05-08 2019-06-07 2019-06-27 2019-07-25 2019-09-23 nvelope d PBs (Technical, E&S, GESI, and Project Management Su Project Financing, Business D pport evelopment, Tariff Managem ent, Formation of Cooperativ e & Company, PEU....... NP-AEPC-272283-NC-RFQ / Li Component 2: Technical Assi cense Renewal of Sophos Fir stance to the Mini-grid Secto Request for Quota Single Stage - One E TF / A8382 Post Open - National 16,000.00 14,687.49 Completed 2022-01-30 2022-02-14 2022-03-13 2022-03-20 2022-03-17 2022-04-03 ewall, Antivirus and Barracud r, ESCOs and Partner Banks tions nvelope a Email Security Gateway and Project Management Su pport NP-AEPC-258649-NC-RFQ / S Component 2: Technical Assi election of Service Provider f stance to the Mini-grid Secto Request for Quota Single Stage - One E TF / A8382 Post Open - National 12,550.00 0.00 Canceled 2022-01-09 2022-03-17 2022-05-16 or conducting Socio-Economi r, ESCOs and Partner Banks tions nvelope c Survey of Two Subprojects and Project Management Su pport NP-AEPC-304401-NC-DIR / S Component 2: Technical Assi election of Service Provider f stance to the Mini-grid Secto or Technical and Financial Ve TF / A8382 r, ESCOs and Partner Banks Post Direct Selection Direct - National 4,067.00 3,882.97 Signed 2022-07-15 2022-09-07 2022-07-18 2022-09-07 2022-07-31 2022-09-08 2023-04-30 rification: Multi Tech Enginee and Project Management Su ring Consultancy Pvt. Ltd. pport CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-AEPC-77121-CS-QCBS / H iring Consultant for Preparati Component 2: Technical Assi on & Revision of Templates, stance to the Mini-grid Secto Quality And Cost- Guidelines, Technical Standa / r, ESCOs and Partner Banks Post Open - National 70,000.00 0.00 Canceled 2018-11-20 2018-12-05 2019-01-03 2019-01-31 2019-02-15 2019-03-16 2019-04-09 2019-05-09 Based Selection rds and Training Manuals for and Project Management Su Grid Interconnection & Mini G pport rid Intra Connection, Micro/Mi ni Hydro and Solar/Wind Mini Grid Component 2: Technical Assi NP-AEPC-77120-CS-QCBS / H stance to the Mini-grid Secto Quality And Cost- iring Quality Assurance Cons / Post Open - National 71,400.00 0.00 Canceled 2018-11-18 2018-12-03 2019-01-01 2019-01-29 2019-02-13 2019-02-27 2019-03-13 2023-10-31 r, ESCOs and Partner Banks Based Selection ultant (Firm) for sub-projects and Project Management Su pport NP-AEPC-264180-CS-CQS / S election of Consultant for rev Component 2: Technical Assi iew of Detailed Feasibility Stu stance to the Mini-grid Secto Consultant Qualifi dy (DFS) Reports including D TF / A8382 r, ESCOs and Partner Banks Post Open - National 13,000.00 11,585.45 Completed 2021-12-01 2021-11-25 2021-12-22 2022-02-06 2022-02-04 2022-02-22 2022-03-11 2022-04-08 2022-04-05 2022-04-12 2022-05-20 2022-05-26 cation Selection etailed Engineering Designs ( and Project Management Su DED) of Amadablam Mini Hyd pport ro Subproject and Monjo Khol a Mini Hydro Subproject NP-AEPC-333003-CS-CQS / S Component 2: Technical Assi election of Consultant for Co stance to the Mini-grid Secto Consultant Qualifi Under Implement TF / A8382 Post Open - National 17,000.00 0.00 2022-12-30 2023-02-27 2023-01-14 2023-02-08 2023-03-25 2023-04-08 2023-04-29 nduction of O&M Training of t r, ESCOs and Partner Banks cation Selection ation he large biogas system and Project Management Su pport NP-AEPC-333004-CS-CQS / S Component 2: Technical Assi election of Consultant for Qu stance to the Mini-grid Secto Consultant Qualifi Under Implement ality Assurance (Site Enginee TF / A8382 r, ESCOs and Partner Banks Post Open - National 17,000.00 0.00 2022-12-30 2023-02-14 2023-01-14 2023-02-08 2023-03-25 2023-04-08 2023-04-30 cation Selection ation rs) for Supervision, Monitorin and Project Management Su g and Reporting of subprojec pport ts NP-AEPC-333005-CS-CQS / S Component 2: Technical Assi election of Consultant for Co stance to the Mini-grid Secto Consultant Qualifi Under Implement TF / A8382 Post Open - National 17,000.00 0.00 2022-12-30 2023-02-27 2023-01-14 2023-02-08 2023-03-25 2023-04-08 2023-04-29 nduction of Training on Grid I r, ESCOs and Partner Banks cation Selection ation nterconnection of Micro/Mini and Project Management Su Hydro and Solar Projects pport INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Technical Assi NP-AEPC-77101-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult ring of Renewable Energy (So / Post Open 97,500.00 122,803.04 Signed 2018-09-16 2018-12-12 2018-10-17 2019-05-30 2018-10-20 2019-05-30 2018-11-01 2019-06-02 2023-10-31 r, ESCOs and Partner Banks ant Selection lar Wind) Expert and Project Management Su pport Component 2: Technical Assi NP-AEPC-77102-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult ring of Renewable Energy (Mi / Post Open 97,500.00 108,358.59 Signed 2018-09-16 2018-12-12 2018-10-17 2019-05-30 2018-10-20 2019-05-31 2018-11-01 2019-06-03 2023-10-31 r, ESCOs and Partner Banks ant Selection cro/Mini Hydro) Expert and Project Management Su pport Component 2: Technical Assi NP-AEPC-77104-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult TF / A8336 Prior Open 97,500.00 79,038.00 Signed 2018-09-16 2018-12-23 2018-10-13 2019-03-11 2018-10-17 2019-05-29 2018-10-27 2019-06-02 2023-10-26 ring of Procurement Expert r, ESCOs and Partner Banks ant Selection and Project Management Su pport NP-AEPC-77105-CS-INDV / Hi Component 2: Technical Assi ring of Senior Environment S stance to the Mini-grid Secto Individual Consult / Post Open 78,000.00 89,188.74 Signed 2018-09-16 2018-12-12 2018-10-17 2019-05-30 2018-10-20 2019-05-30 2018-11-01 2019-06-03 2023-10-31 afeguard Expert (Intermittent r, ESCOs and Partner Banks ant Selection for Project Implementation) and Project Management Su pport Component 2: Technical Assi NP-AEPC-77109-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult ring of Financial Managemen / Post Open 97,500.00 66,853.05 Signed 2018-09-16 2018-12-12 2018-10-17 2019-05-31 2018-10-20 2019-06-03 2018-11-01 2019-06-10 2023-10-31 r, ESCOs and Partner Banks ant Selection t Expert and Project Management Su pport Component 2: Technical Assi NP-AEPC-77110-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult ring of Social Safeguard Expe / Post Open 97,500.00 74,233.92 Signed 2018-09-16 2018-12-12 2018-10-17 2019-05-16 2018-10-20 2019-05-23 2018-11-01 2019-06-02 2023-10-31 r, ESCOs and Partner Banks ant Selection rt and Project Management Su pport Component 2: Technical Assi NP-AEPC-77111-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult ring of Environmental Safegu / Post Open 97,500.00 73,820.41 Signed 2018-09-16 2018-12-12 2018-10-17 2019-06-02 2018-10-20 2019-06-02 2018-11-01 2019-06-03 2023-10-31 r, ESCOs and Partner Banks ant Selection ard Expert and Project Management Su pport NP-AEPC-77106-CS-INDV / Hi Component 2: Technical Assi ring of Senior Social Safeguar stance to the Mini-grid Secto Individual Consult / Post Open 78,000.00 0.00 Canceled 2018-09-16 2018-12-12 2018-10-17 2018-10-20 2018-11-01 2023-10-31 d Expert (Intermittent for Pro r, ESCOs and Partner Banks ant Selection ject Implementation) and Project Management Su pport NP-AEPC-77107-CS-INDV / Hi Component 2: Technical Assi ring of Senior M&E Expert (In stance to the Mini-grid Secto Individual Consult / Post Open 78,000.00 0.00 Canceled 2018-09-16 2018-12-12 2018-10-17 2018-10-20 2018-11-01 2023-10-31 termittent for Project Implem r, ESCOs and Partner Banks ant Selection entation) and Project Management Su pport Component 2: Technical Assi NP-AEPC-77112-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult / Post Open 65,000.00 0.00 Canceled 2018-09-16 2020-01-08 2018-10-17 2018-10-20 2018-11-01 2023-10-31 ring of Credit Officer r, ESCOs and Partner Banks ant Selection and Project Management Su pport NP-AEPC-77108-CS-INDV / Hi Component 2: Technical Assi ring of Senior Financial Asses stance to the Mini-grid Secto Individual Consult / Post Open 78,000.00 0.00 Canceled 2018-09-16 2020-01-08 2018-10-17 2018-10-20 2018-11-01 2023-10-31 sment Expert (Intermittent fo r, ESCOs and Partner Banks ant Selection r Project Implementation) and Project Management Su pport Component 2: Technical Assi NP-AEPC-77113-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult ring of Business Developmen / Post Open 39,000.00 0.00 Canceled 2018-09-16 2018-12-12 2018-10-17 2018-10-20 2018-11-01 2021-10-31 r, ESCOs and Partner Banks ant Selection t Officer and Project Management Su pport Component 2: Technical Assi NP-AEPC-77103-CS-INDV / Hi stance to the Mini-grid Secto Individual Consult ring of Grid Interconnection E / Post Open 97,500.00 0.00 Canceled 2018-09-16 2018-12-12 2018-10-17 2018-10-20 2018-11-01 2023-10-31 r, ESCOs and Partner Banks ant Selection xpert and Project Management Su pport Page 2 NP-AEPC-258646-CS-INDV / Component 2: Technical Assi Selection of Biodiversity Spec stance to the Mini-grid Secto Individual Consult TF / A8382 Post Direct 4,180.00 4,163.34 Completed 2021-11-01 2021-11-01 2021-11-11 2021-11-24 2021-11-21 2022-01-09 2021-12-08 2022-01-09 2022-01-22 2022-04-29 ialist for the study of Two Su r, ESCOs and Partner Banks ant Selection bprojects: Dr. Prayag Raj Ta and Project Management Su mrakar pport NP-AEPC-258647-CS-INDV / Component 2: Technical Assi Selection of Geological Speci stance to the Mini-grid Secto Individual Consult TF / A8382 Post Direct 4,180.00 4,137.07 Completed 2021-11-01 2021-11-01 2021-11-11 2021-11-24 2021-11-21 2022-01-25 2021-12-08 2022-01-26 2022-01-22 2022-04-29 alist for the study of Two Sub r, ESCOs and Partner Banks ant Selection projects: Mr. Biraj Gautam and Project Management Su pport NP-AEPC-304201-CS-INDV / Component 2: Technical Assi Selection of Senior Bioenergy stance to the Mini-grid Secto Individual Consult TF / A8382 Post Direct - National 25,317.41 22,042.26 Signed 2022-07-14 2022-08-06 2022-07-20 2022-08-10 2022-07-23 2022-08-10 2022-08-02 2022-08-10 2023-04-30 Specialist: Mr. Sushim Man A r, ESCOs and Partner Banks ant Selection matya and Project Management Su pport NP-AEPC-304204-CS-INDV / Component 2: Technical Assi Selection of Climate and Car stance to the Mini-grid Secto Individual Consult TF / A8382 Post Direct - National 11,936.77 10,511.95 Signed 2022-07-14 2022-08-06 2022-07-20 2022-08-10 2022-07-23 2022-08-10 2022-08-02 2022-08-11 2023-04-30 bon Specialist: Mr. Shreejan r, ESCOs and Partner Banks ant Selection Ram Shrestha and Project Management Su pport NP-AEPC-304203-CS-INDV / Component 2: Technical Assi Selection of Senior Monitorin stance to the Mini-grid Secto Individual Consult TF / A8382 Post Direct - National 18,583.83 17,450.97 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2023-04-30 g & Evaluation Specialist: Mr. r, ESCOs and Partner Banks ant Selection Lok Raj Pathak and Project Management Su pport Component 2: Technical Assi NP-AEPC-304206-CS-INDV / stance to the Mini-grid Secto Individual Consult Selection of Programme Offic TF / A8382 Post Direct - National 12,049.90 11,315.34 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2023-04-30 r, ESCOs and Partner Banks ant Selection er: Anupam Bhusal and Project Management Su pport Component 2: Technical Assi NP-AEPC-304209-CS-INDV / stance to the Mini-grid Secto Individual Consult Selection of Site Engineer: Su TF / A8382 Post Direct - National 6,788.42 6,374.60 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2023-04-30 r, ESCOs and Partner Banks ant Selection jan Poudel and Project Management Su pport Component 2: Technical Assi NP-AEPC-304205-CS-INDV / stance to the Mini-grid Secto Individual Consult Selection of Technical Officer TF / A8382 Post Direct - National 6,176.46 5,799.95 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2023-04-30 r, ESCOs and Partner Banks ant Selection : Nabin Kumar Shrestha and Project Management Su pport Component 2: Technical Assi NP-AEPC-304211-CS-INDV / stance to the Mini-grid Secto Individual Consult Selection of Site Engineer: Pit TF / A8382 Post Direct - National 1,769.67 1,661.79 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2022-10-31 r, ESCOs and Partner Banks ant Selection amber Pandey and Project Management Su pport NP-AEPC-304207-CS-INDV / Component 2: Technical Assi Selection of Municipal Waste stance to the Mini-grid Secto Individual Consult TF / A8382 Post Direct - National 5,129.99 4,817.27 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2022-12-31 to Energy Project Coordinator r, ESCOs and Partner Banks ant Selection : Rabindra Dhital and Project Management Su pport Component 2: Technical Assi NP-AEPC-304210-CS-INDV / stance to the Mini-grid Secto Individual Consult Selection of Site Engineer: Pr TF / A8382 Post Direct - National 2,606.13 18,569.29 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2022-11-30 r, ESCOs and Partner Banks ant Selection abhat Kumar Jha and Project Management Su pport Component 2: Technical Assi NP-AEPC-304214-CS-INDV / stance to the Mini-grid Secto Individual Consult Selection of Site Engineer: As TF / A8382 Post Direct - National 1,769.67 1,661.79 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2022-10-31 r, ESCOs and Partner Banks ant Selection hish Dutta Bhatta and Project Management Su pport Component 2: Technical Assi NP-AEPC-304213-CS-INDV / stance to the Mini-grid Secto Individual Consult Selection of Site Engineer: Bi TF / A8382 Post Direct - National 5,115.50 4,803.67 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2023-02-28 r, ESCOs and Partner Banks ant Selection shnu Dawadi and Project Management Su pport NP-AEPC-304208-CS-INDV / Component 2: Technical Assi Selection of Provincial Project stance to the Mini-grid Secto Individual Consult Coordinator (including projec TF / A8382 r, ESCOs and Partner Banks Post Direct - National 4,212.26 3,955.48 Signed 2022-08-24 2022-08-24 2022-08-28 2022-08-25 2022-08-30 2022-08-25 2022-09-09 2022-08-26 2022-11-30 ant Selection t focal person of Bagmati Pro and Project Management Su vince): Ramesh Ranabhat pport Component 2: Technical Assi NP-AEPC-346353-CS-INDV / stance to the Mini-grid Secto Individual Consult Pending Impleme Selection of Site Engineer Mr. TF / A8382 Post Direct - National 1,300.00 0.00 2023-03-02 2023-03-08 2023-03-11 2023-03-16 2023-04-30 r, ESCOs and Partner Banks ant Selection ntation Pitamber Pandey and Project Management Su pport Page 3