The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Guinea Natural Resources, Mining and Environmental Management Project (P168613) AFRICA WEST | Guinea | Environment, Natural Resources & the Blue Economy Global Practice | IBRD/IDA | Investment Project Financing | FY 2021 | Seq No: 1 | ARCHIVED on 22-Dec-2021 | ISR49570 | Implementing Agencies: Ministry of Environment and Sustainable Development, Republic of Guinea, Ministry of Mining and Geology Key Dates Key Project Dates Bank Approval Date: 26-May-2021 Effectiveness Date: 16-Jul-2021 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 30-Sep-2027 Revised Closing Date: 30-Sep-2027 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Development Objective is to strengthen institutional capacities for integrated management of mineral and natural resources in Guinea and enhanced benefits from the mining and environment sectors. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Improve the institutional framework for mining and environment:(Cost $5.00 M) Mining policies, institutions, governance, and economic integration:(Cost $29.00 M) Environmental and natural resources management:(Cost $28.00 M) Project management:(Cost $3.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Satisfactory Overall Implementation Progress (IP) -- Moderately Satisfactory Overall Risk Rating -- Substantial Implementation Status and Key Decisions Following the events of early September 2021, OP7.30 was triggered and as a result project implementation slowed down, including procurement for several key activities. An annual budgeted work plan for the year 2022 is in preparation as well as the procurement plan and the terms of reference for the main contracts and activities. A project kick-off workshop and steering committee meeting are planned for early 2022. 12/22/2021 Page 1 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial -- Substantial Macroeconomic Moderate -- Moderate Sector Strategies and Policies Substantial -- Substantial Technical Design of Project or Program Substantial -- Substantial Institutional Capacity for Implementation and Substantial -- Substantial Sustainability Fiduciary Substantial -- Substantial Environment and Social Substantial -- Substantial Stakeholders Moderate -- Moderate Other -- -- -- Overall Substantial -- Substantial Results PDO Indicators by Objectives / Outcomes Strengthen institutional capacities in the integrated management of mineral and natural resources IN01079636 ►Forest area brought under management plans (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 87,000.00 1,191,800.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079638 Kounounkan management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5,700.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079639 Niger source management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target 12/22/2021 Page 2 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Value 0.00 -- 0.00 260,000.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079640 Haut-Niger NP management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 705,000.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079641 Pic de Fon management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 32,200.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079642 Mont Béro management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 27,600.00 27,600.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079643 Mont Nimba management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 14,600.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079644 Diécké management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 59,400.00 59,400.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079645 Konkouré management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 29,900.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079646 Rio Pongo management plan (Hectare(Ha), Custom Breakdown) 12/22/2021 Page 3 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 26,100.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079647 Rio Kapatchez management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 29,900.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079648 Loos management plan (Hectare(Ha), Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,400.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079649 ►Annual environmental monitoring inspections of large infrastructure projects undertaken (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 Environmental and social inspection of infrastructures project that are undertaken by MEEF including Comments: proportion of inspection carried out with the implication of citizens through the establishment of Prefectoral Committees for E&S management plans monitoring IN01079650 Annual environmental monitoring inspections of large infrastructure projects undertaken with citizen consultation (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 12.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079651 ►Annual technical monitoring and control completed on industrial mines (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 -- 100.00 100.00 Date 26-Feb-2020 -- 07-Dec-2021 31-Dec-2026 Comments: Annual inspections completed on all operating industrial mines in Guinea. Enhance benefits from mining and environment sectors to communities IN01079637 12/22/2021 Page 4 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) ►Value of goods and services procured by mining companies through the online purchasing platform (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 9,000,000.00 -- 9,000,000.00 60,000,000.00 Date 15-Feb-2021 -- 13-Dec-2021 31-Dec-2026 Amount of goods and services procured by miners from SME/SMI through the Online Purchasing Platform Comments: from miners accumulated through the life of project Intermediate Results Indicators by Components A. Mining and Environment Political, regulatory and institutional framework IN01079652 ►Score for reform of the legal and regulatory framework and dissemination (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 8.00 -- 8.00 20.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 This indicator should capture the progress of regulatory reforms underway in the natural resources and environmental management sector. It refers to five specific laws and related regulations. Advancement in Comments: the reform of each Code will be assessed by the following score: 0= No law existing / 1= Drafted law or law to be revised / 2= Law adopted / 3= Law adopted and related regulation drafted / 4= Law and related regulation adopted and disseminated The indicator global score will be the addition of each Code score IN01079659 a. Protected Area Code sub-indicator (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 1.00 -- 1.00 4.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079663 b. Wildlife Code sub-indicator (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 1.00 -- 1.00 4.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079665 c. Water Code sub-indicator (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 1.00 -- 1.00 4.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079670 d. Forest Code sub-indicator (Number, Custom Breakdown) 12/22/2021 Page 5 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Baseline Actual (Previous) Actual (Current) End Target Value 2.00 -- 2.00 4.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079674 e. Environment Code sub-indicator (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 3.00 -- 3.00 4.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 IN01079676 ►Updated mining related regulatory framework (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 16.00 -- 16.00 29.00 Date 10-Feb-2021 -- 13-Dec-2021 31-Dec-2026 Comments: Drafted mining related regulations and guidelines IN01079678 ►SESA updated and recommendations regularly monitored (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 10-Feb-2020 -- 07-Dec-2021 31-Dec-2026 The existing Mining reform SESA is going to be updated and an annual report on the implementation of the "Guiding Framework for Improved Environmental and Social Governance in the Mining Sector" will be Comments: provided B1 - Mining policies, institutions, and governance IN01079655 ►Mining sector gender strategy drafted (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Mar-2021 -- 13-Dec-2021 31-Dec-2026 IN01079661 ►Advisory services for projects development or expansion (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes 12/22/2021 Page 6 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Date 10-Feb-2020 -- 13-Dec-2021 31-Dec-2026 Comments: Legal, technical, and or financial advisory services delivered to support new or existing project expansion. IN01079664 ►Mining permits excluded from classified forests (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 10-Feb-2020 -- 13-Dec-2021 31-Dec-2026 Comments: Classified forests outlined and excluded from licensing possibilities in the mining cadastre IN01079667 ►Civil servants and accountability organizations representatives trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 350.00 Date 10-Feb-2020 -- 13-Dec-2021 31-Dec-2026 IN01079672 Training for CSOs, parliamentarians and other accountability organisations (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 80.00 IN01079673 ►Seismic surveillance system installed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 10-Feb-2020 -- 13-Dec-2021 31-Dec-2026 Comments: A network of seismic sensors installed in the country IN01079675 ►Geochemical survey of southern Guinea completed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 01-Mar-2021 -- 13-Dec-2021 31-Dec-2026 IN01079677 ►Transparent access procedure to Government geological and mining assets developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes 12/22/2021 Page 7 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Date 01-Mar-2021 -- 13-Dec-2021 31-Dec-2026 IN01079679 ►Publication of earmarked revenues distributed to mining communities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4.00 -- 4.00 10.00 Date 10-Feb-2020 -- 13-Dec-2021 31-Dec-2026 Comments: Publication of revenues earmarked for communities IN01079680 ►Overall beneficiaries of mining interventions (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20,000.00 Date 10-Feb-2020 -- 13-Dec-2021 31-Dec-2026 Comments: Number of people trained, sensitized, or supported through the mining component. IN01079681 Including women (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 30.00 IN01079682 ►People trained and sensitized on the environmental, social and gender legislation, good practices in mining. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 5,150.00 -- 5,150.00 15,000.00 Date 26-Feb-2020 -- 13-Dec-2021 31-Dec-2026 Mining inspectors, community based organisations, Civil society organisation and artisanal miners trained Comments: or sensitized on the environmental, social and gender legislation/regulations and good practices pertaining to mining. B2 - Economic integration of the mining sector IN01079656 ►SME/SMI registered with the Online Mining Local Content Platform (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1,794.00 -- 1,794.00 2,300.00 Date 10-Feb-2020 -- 13-Dec-2021 31-Dec-2026 Number of small medium size enterprises and industries registered to potentially participate to the bidding Comments: for bidding for mining contracts through the Online Mining Local Content Platform. IN01079660 12/22/2021 Page 8 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) ►SME/SMI representatives trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 -- 100.00 400.00 Date 10-Feb-2020 -- 13-Dec-2021 31-Dec-2026 Comments: Number of SME/SMI trained to access to potential mining contracts for good and services i IN01079666 ►EITI Reports produced (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 14.00 -- 14.00 20.00 Date 15-Feb-2021 -- 13-Dec-2021 31-Dec-2026 Comments: EITI Reports produced IN01079669 ►Registered companies with the BSTP belonging to women beneficiaries of contracts with mining companies (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 -- 5.00 20.00 Date 01-Mar-2021 -- 13-Dec-2021 31-Dec-2026 C1. Institutional, logistical support and Environmental & Social standards management IN01079654 ►a. Channels institutionalized for citizens to provide input on planning and execution of infrastructure projects (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 This indicator will assess the formal involvement of local population committees in infrastructure projects' Comments: environmental and social monitoring process IN01079658 ►b. Modernization and generalization of the database of the environmental and social assessment database to all relevant projects (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 Capacity of BGACE in identifying and mapping all ongoing or planned infrastructure projects (dams, Comments: roads, railways, mines, etc.) to be environmentally and socially monitored 12/22/2021 Page 9 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) C2. Protected area management in selected areas IN01079653 ►a. Annual person-days of rangers surveillance and control missions in targeted sites (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1,000.00 -- 0.00 60,000.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 Comments: This indicator measures the efficiency of targeted zones surveillance IN01079657 ►b. Proportion of local committees in targeted sites' surrounding communes actively engaged in protected areas management (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 75.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 Proportion of communes' committee linked with targeted protected areas, involved into validation of PA Comments: annual workplans IN01079662 sub-indicator b. Share of women represented in local decision-making committees (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 20.00 IN01079668 ►c. Targeted beneficiaries with increased income due to access to alternative income-generating activities intervention (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 500.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 This indicator will measure the number beneficiaries of the income-generating activities program self Comments: reporting an increase in their incomes IN01079671 Sub-indicator c. Women reporting increased income due to access to alternative livelihood (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 350.00 Date 31-Dec-2020 -- 07-Dec-2021 31-Dec-2026 Performance-Based Conditions Data on Financial Performance 12/22/2021 Page 10 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P168613 IDA-68850 Effective USD 32.50 32.50 0.00 0.00 32.72 0% P168613 IDA-D8190 Effective USD 32.50 32.50 0.00 0.83 31.84 2.5% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P168613 IDA-68850 Effective 26-May-2021 09-Jun-2021 16-Jul-2021 30-Sep-2027 30-Sep-2027 P168613 IDA-D8190 Effective 26-May-2021 09-Jun-2021 16-Jul-2021 30-Sep-2027 30-Sep-2027 Cumulative Disbursements PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC 12/22/2021 Page 11 of 12 The World Bank Implementation Status & Results Report Guinea Natural Resources, Mining and Environmental Management Project (P168613) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/22/2021 Page 12 of 12