Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: March 17, 2017 2. Date of General Procurement Notice: July 19, 2013 3. Period covered by this procurement plan: March 2017 to Feb 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 5 High installation of plant and equipment and PPP) 2. (Goods; Information Technology & 1.5 High Non-Consulting Services) 3. Consultant Services (Firms) 0.5 High 4. Consultant Services (Individual 0.2 High Consultants) 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. March 17, 2017 9. Renewal or extension of individual consultants contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 17, 2017 PROCUREMENT Kenya : Kenya Infrastructure Finance/PPP project PLAN General Information Country: Kenya 2017-03-22 Bank’s Approval Date of the Original Procurement Plan: 2023-03-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P121019 GPN Date: 2018-01-22 Project Name: Kenya Infrastructure Finance/PPP project Loan / Credit No: IDA / 51570, IDA / 61210 National Treasury - Public Private Partnership (PPP) Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-NT PPP-8920-CW-RFB / P Technical Support to PPP Ins ROPOSED OFFICE FIT-OUT FO titutions for PPP Legal, Regul Single Stage - One E 2017-11-2 IDA / 51570 Post Request for Bids Open - National 1,050,000.00 0.00 Signed 2017-03-10 2017-04-28 2017-03-15 2017-04-14 2017-06-06 2017-05-05 2017-08-28 2017-05-26 R PPP UNIT OFFICES AT REIN atory and PPP Financing Envi nvelope 2 SURANCE PLAZA, NAIROBI ronment GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NT PPP-8929-GO-RFQ / S Technical Support to PPP Ins Request for Quota Single Stage - One E UPPLY AND DELIVERY OF LAP IDA / 51570 titutions for PPP Legal, Regul Post Limited 15,000.00 0.00 Signed 2017-03-15 2017-03-23 2017-04-26 2017-07-25 tions nvelope TOPS FOR THE PPP UNIT atory and PPP Financing Envi ronment KE-NT PPP-16677-GO-RFQ / Support for Program Manage Request for Quota Single Stage - One E IDA / 51570 Post Limited 14,000.00 0.00 Canceled 2017-06-13 2017-07-25 2017-08-15 Branded Stationery and Bann ment tions nvelope ers KE-NT PPP-79640-GO-RFB / S Technical Support to PPP Ins Single Stage - One E UPPLY AND FITTING OF OFFIC IDA / 51570 titutions for PPP Legal, Regul Post Request for Bids Open - National 300,000.00 64,333.34 Signed 2018-10-03 2019-01-24 2018-10-08 2018-11-07 2019-03-08 2018-12-07 2019-04-02 2018-12-28 2019-07-05 2019-03-28 nvelope E FURNITURE FOR PPP UNIT atory and PPP Financing Envi ronment IFPPP/PIU/PPPU/NC/05/2019- 2020 / Supply, Installation an AF Component 1: Support to Single Stage - One E d Commissioning of Informati IDA / 61210 Post Request for Bids Open - National 300,150.00 247,475.86 Signed 2019-08-05 2019-09-25 2019-08-10 2019-09-09 2019-11-28 2019-10-09 2020-01-31 2019-11-13 2020-05-18 2020-03-12 2020-07-03 Institutional Strengthening nvelope on Technology Equipment for the Public Private Partnership s Unit IFPPP/PIU/PFF/NC/06/2019-2 AF Component 3: Support to Single Stage - One E 0 / Supply and Delivery of Mo IDA / 61210 Post Request for Bids Open - National 220,000.00 0.00 Canceled 2020-03-08 2020-03-25 2020-03-13 2020-04-24 2020-05-28 2020-05-24 2020-07-28 2020-06-28 2020-09-26 Project Management nvelope tor Vehicles for the Project Fa cilitation Fund IFPPP/PIU/27/2019-20 / Supp AF Component 1: Support to Request for Quota Single Stage - One E ly and delivery of Branded O IDA / 61210 Post Limited 5,600.00 0.00 Canceled 2020-02-29 2020-04-25 2020-05-25 Institutional Strengthening tions nvelope utfits for PPP Unit Staff IFPPP/PIU/27/2020-21 / Supp AF Component 1: Support to Request for Quota Single Stage - One E Under Imple ly and Delivery of Library Boo IDA / 61210 Post Limited 10,000.00 0.00 2020-08-11 2022-05-23 2020-09-29 2020-12-28 Institutional Strengthening tions nvelope mentation ks for the Public Private Partn erships Unit IFPPP/PFF/28/2020-21 / Supp AF Component 3: Support to Request for Quota Single Stage - One E Under Imple ly and Delivery of a Heavy D IDA / 61210 Post Limited 100,000.00 0.00 2021-02-27 2021-06-04 2021-04-07 2021-07-06 Project Management tions nvelope mentation uty Passenger Utility Motor V ehicle IFPPP/PPPD/30/2021-22 / Su AF Component 1: Support to Request for Quota Single Stage - One E Under Imple IDA / 61210 Post Limited 20,000.00 0.00 2022-01-31 2022-02-04 2022-02-28 2022-03-30 pply & Delivery of High End T Institutional Strengthening tions nvelope mentation ablets KE-NT PPP-8924-GO-RFB / S Technical Support to PPP Ins Single Stage - One E UPPLY AND FITTING OF FURN IDA / 51570 titutions for PPP Legal, Regul Post Request for Bids Open - National 300,000.00 0.00 Canceled 2017-03-17 2017-07-20 2017-03-22 2017-04-21 2017-08-31 2017-05-05 2017-05-26 2017-09-25 nvelope ITURE FOR THE PPP UNIT atory and PPP Financing Envi ronment IFPPP/PPPD/29/2020-21 / Su AF Component 1: Support to Request for Quota Single Stage - One E pply and Installation of Vide IDA / 61210 Post Limited 5,000.00 0.00 Canceled 2021-05-31 2021-06-22 2021-07-05 2021-07-19 Institutional Strengthening tions nvelope o Conferencing Accessories IFPPP/PPPD/31/2021-22 / Su AF Component 1: Support to Request for Quota Single Stage - One E pply and Delivery of Bulk File IDA / 61210 Post Limited 19,600.00 0.00 Canceled 2022-11-19 2023-01-07 2023-02-06 Institutional Strengthening tions nvelope rs and Shelving Racks for the PPP Directorate IFPPP/PFF/32/2021-22 / Supp ly and Installation of a Huma AF Component 3: Support to Request for Quota Single Stage - One E IDA / 61210 Post Limited 2,500.00 0.00 Canceled 2022-11-15 2023-01-03 2023-02-02 n Resource System for the Pr Project Management tions nvelope oject Facilitation Fund Secret ariat NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NT PPP-14338-NC-RFQ / P Support for Preparation of In Request for Quota Single Stage - One E IDA / 51570 Post Limited 50,000.00 0.00 Completed 2017-05-17 2017-05-30 2017-06-21 2018-06-20 rovision of Data Room Servic dividual PPPs tions nvelope es IFPPP/PPPU/25/2019-20 / Pro AF Component 1: Support to Request for Quota Single Stage - One E IDA / 61210 Post Limited 35,000.00 24,301.80 Signed 2020-02-17 2020-03-12 2020-03-23 2020-08-26 2020-04-13 duction of TV informercials fo Institutional Strengthening tions nvelope r the PPP Unit IFPPP/PPPU/24/2019-20 / Pri AF Component 1: Support to Request for Quota Single Stage - One E nting Services of IEC Material IDA / 61210 Post Limited 30,000.00 8,203.42 Signed 2020-02-29 2020-03-12 2020-04-25 2020-08-17 2020-05-16 2022-03-30 Institutional Strengthening tions nvelope s for the PPP Unit CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 KE-NT PPP-10800-CS-QCBS / Support for Preparation of In Quality And Cost- Open - Internationa Transaction Advisor for 2nd IDA / 51570 Prior 2,660,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-28 2017-07-28 2017-09-01 2017-10-06 2017-12-31 dividual PPPs Based Selection l Nyali Bridge as a PPP Project KE-NT PPP-10806-CS-QCBS / Transaction Advisor for Devel Support for Preparation of In Quality And Cost- Open - Internationa opment, Operation and Maint IDA / 51570 Prior 3,650,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-28 2017-07-28 2017-09-01 2017-10-06 2017-12-31 dividual PPPs Based Selection l enance of Nairobi- Nakuru Ro ad (A104) as a PPP Project KE-NT PPP-10808-CS-QCBS / Transaction Advisor for Devel Support for Preparation of In Quality And Cost- Open - Internationa opment, Operation and Maint IDA / 51570 Prior 2,500,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-28 2017-07-28 2017-09-01 2017-10-06 2019-04-05 dividual PPPs Based Selection l enance of Nairobi- Mombasa Highway (A109) as a PPP Proj ect KE-NT PPP-10810-CS-QCBS / Transaction Advisor for Oper Support for Preparation of In Quality And Cost- Open - Internationa IDA / 51570 Prior 2,900,000.00 0.00 Canceled 2017-03-27 2017-04-17 2017-05-31 2017-06-28 2017-07-28 2017-09-01 2017-10-06 2017-12-31 ation and Maintenance of Nai dividual PPPs Based Selection l robi- Thika Road (A2) as a PP P Project KE-NT PPP-10816-CS-QCBS / Transaction Advisor for Devel Support for Preparation of In Quality And Cost- Open - Internationa IDA / 51570 Prior 1,100,000.00 1,097,716.00 Signed 2017-03-27 2017-04-10 2017-05-24 2017-06-21 2017-07-21 2017-05-12 2017-08-25 2018-02-09 2017-09-22 2018-03-22 2017-12-31 opment, Operation and Maint dividual PPPs Based Selection l enance of a 300-Bed Private Hospital KE-NT PPP-10819-CS-QCBS / Transaction Advisory Service Support for Preparation of In Quality And Cost- Open - Internationa s for the Development, Oper IDA / 51570 Prior 1,800,000.00 0.00 Canceled 2017-04-03 2017-04-17 2017-05-08 2017-06-05 2017-06-15 2017-07-08 2017-07-29 2017-12-31 dividual PPPs Based Selection l ation & Maintenance of Unive rsities' PPP Projects (Phase II) KE-NT PPP-17994-CS-QCBS / CONSULTANCY TO PROVIDE TRANSACTION ADVISORY SE Support for Preparation of In Quality And Cost- Open - Internationa IDA / 51570 Prior 1,100,000.00 1,341,382.00 Signed 2017-06-23 2019-11-01 2017-07-14 2017-07-31 2017-08-27 2018-04-25 2017-09-24 2018-06-08 2017-10-24 2019-11-17 2017-11-28 2019-11-24 2018-01-02 2021-06-30 2019-01-02 RVICES FOR THE dividual PPPs Based Selection l PROCUREMENT OF A TOLLIN G OPERATOR FOR KENYA'S FI RST MOVER TOLL ROADS PPP PROGRAMME KE-NT PPP-79799-CS-QCBS / Transaction Advisory Service AF Component 2: Support to Quality And Cost- Open - Internationa s for the Proposed Pwani Uni IDA / 61210 Project Preparation and Proc Prior 1,869,000.00 949,792.99 Signed 2018-10-03 2018-12-18 2018-10-24 2019-02-12 2018-12-07 2021-11-30 2019-01-04 2020-03-24 2019-02-03 2021-12-06 2019-03-10 2021-12-16 2019-04-14 2022-09-26 2020-10-12 Based Selection l versity Teaching & Referral H urement ospital PPP Project - Pwani Un iversity KE-NT PPP-79803-CS-QCBS / AF Component 2: Support to Transaction Advisor for Naku Quality And Cost- Open - Internationa Under Implement IDA / 61210 Project Preparation and Proc Prior 1,115,000.00 0.00 2018-11-27 2019-05-17 2018-12-18 2019-01-31 2020-06-18 2019-02-28 2020-08-21 2019-03-30 2019-05-04 2019-06-08 2020-06-07 ru Solid Waste Management Based Selection l ation urement PPP Project - Nakuru County KE-NT PPP-79801-CS-QCBS / AF Component 2: Support to Transaction Advisor for Nany Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 920,000.00 0.00 Canceled 2018-10-04 2018-10-25 2018-12-08 2019-01-05 2019-02-04 2019-03-11 2019-04-15 2020-02-14 uki Bulk Water Supply PPP Pr Based Selection l urement oject - Laikipia County IFPPP/PIU/KNH/03/2019-20 / Transaction Advisory Service s to Support the Request for Support for Preparation of In Quality And Cost- Open - Internationa Under Implement Proposals Bidding Stage thro IDA / 61210 Prior 1,050,000.00 0.00 2019-11-07 2019-11-24 2019-11-28 2020-02-14 2020-01-11 2020-02-08 2020-03-09 2020-04-13 2020-05-18 2022-05-18 dividual PPPs Based Selection l ation ugh to Financial Close for the Proposed KNH Private Hospit al PPP Project at the Kenyatt a National Hospital IFPPP/PIU/KURA/04/2019-20 / AF Component 2: Support to Transaction Advisory Service Quality And Cost- Open - Internationa Under Implement IDA / 61210 Project Preparation and Proc Prior 1,410,000.00 0.00 2019-12-06 2019-12-11 2019-12-27 2020-02-14 2020-02-09 2022-01-21 2020-03-08 2020-04-07 2020-05-12 2020-06-16 2022-06-16 s for the Proposed 2nd Nyali Based Selection l ation urement Bridge as a PPP Project KE-NT PPP-157882-CS-QCBS AF Component 2: Support to / Framework Agreement for T Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 2,500,000.00 0.00 Canceled 2020-02-11 2020-03-03 2020-03-18 2020-04-15 2020-05-15 2020-06-19 2020-07-24 2021-07-24 ransaction Advisory Services Based Selection l urement for Railway Sector KE-NT PPP-157884-CS-QCBS AF Component 2: Support to / Framework Agreement for T Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 2,500,000.00 0.00 Canceled 2020-02-11 2020-03-03 2020-09-13 2020-10-11 2020-11-10 2020-12-15 2021-01-19 2022-01-19 ransaction Advisory Services Based Selection l urement for the Water and Sanitation KE-NT PPP-157893-CS-QCBS AF Component 2: Support to / Framework Agreement for T Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 2,400,000.00 0.00 Canceled 2020-02-11 2020-03-03 2020-04-04 2020-05-02 2020-06-01 2020-07-06 2020-08-10 2021-08-10 ransaction Advisory Services Based Selection l urement for Accommodation Sector KE-NT PPP-157905-CS-QCBS AF Component 2: Support to / Framework Agreement for T Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 1,000,000.00 0.00 Canceled 2020-02-11 2020-03-03 2020-09-13 2020-10-11 2020-11-10 2020-12-15 2021-01-19 2022-01-19 ransaction Advisory Services Based Selection l urement for the Agriculture & Livestoc k Sector KE-NT PPP-157895-CS-QCBS AF Component 2: Support to / Framework Agreement for T Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 4,600,000.00 0.00 Canceled 2020-02-11 2020-03-03 2020-09-13 2020-10-11 2020-11-10 2020-12-15 2021-01-19 2022-01-19 ransaction Advisory Services Based Selection l urement for Energy Sector KE-NT PPP-157880-CS-QCBS AF Component 2: Support to / Framework Agreement for T Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 5,500,000.00 0.00 Canceled 2020-02-11 2020-03-24 2020-03-03 2020-09-13 2020-10-11 2020-11-10 2020-12-15 2021-01-19 2022-01-19 ransaction Advisory Services Based Selection l urement for the Roads and Bridges Se ctor KE-NT PPP-157886-CS-QCBS AF Component 2: Support to / Framework Agreement for T Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 4,000,000.00 0.00 Canceled 2020-02-11 2020-03-03 2020-09-13 2020-10-11 2020-11-10 2020-12-15 2021-01-19 2022-01-19 ransaction Advisory Services Based Selection l urement for Ports Sector KE-NT PPP-157888-CS-QCBS AF Component 2: Support to Quality And Cost- Open - Internationa / Framework Agreement for T IDA / 61210 Project Preparation and Proc Prior 3,600,000.00 0.00 Canceled 2020-02-11 2020-03-03 2020-09-13 2020-10-11 2020-11-10 2020-12-15 2021-01-19 2022-01-19 Based Selection l ransaction Advisory for Healt urement h Sector IFPPP/PIU/ML5H/05/2019-20 AF Component 2: Support to / Transaction Advisory Servic Quality And Cost- Open - Internationa IDA / 61210 Project Preparation and Proc Prior 1,000,000.00 0.00 Canceled 2020-02-28 2020-03-20 2020-05-03 2020-05-31 2020-06-30 2020-08-04 2020-09-08 2022-03-10 es for the Proposed Cancer C Based Selection l urement are Center PPP Project at the Meru Level 5 Hospital Page 2 IFPPP/PIU/PPPU/07/2019-20 / Assess Requirements of an In tegrated Monitoring, Evaluati AF Component 1: Support to Consultant Qualifi on, Learning and Knowledge IDA / 61210 Post Open - National 298,000.00 0.00 Canceled 2020-03-25 2020-03-25 2020-04-15 2020-05-29 2020-06-28 2020-08-02 2021-11-02 Institutional Strengthening cation Selection Management System for Ken ya’s PPP Program and Develo p the Program Knowledge Ma nagement Strategy and Fram ework IFPPP/PIU/SDOT/9/2019-20 / Development of an Aviation AF Component 1: Support to Quality And Cost- Open - Internationa Policy for Kenya and Review IDA / 61210 Prior 2,500,000.00 456,759.65 Signed 2020-04-30 2020-05-07 2020-05-21 2020-08-03 2020-07-04 2021-01-18 2020-08-01 2021-02-25 2020-08-31 2021-05-17 2020-10-05 2021-09-27 2020-11-09 2021-11-30 2021-04-26 Institutional Strengthening Based Selection l of the Proposed Restructurin g for the Aviation Sub-sector IFPPP/PIU/ML5H/05/2019-202 AF Component 2: Support to 0 / Transaction Advisory for t Quality And Cost- Open - Internationa Under Implement IDA / 61210 Project Preparation and Proc Prior 1,500,000.00 0.00 2020-04-30 2020-08-11 2020-05-21 2020-08-26 2020-07-04 2021-09-27 2020-08-01 2021-11-24 2020-08-31 2022-12-12 2020-10-05 2020-11-09 2022-05-11 he Proposed Cancer Care Ce Based Selection l ation urement ntre PPP Project at the Meru Level 5 Hospital IFPPP/PIU/MWSI/10/2021/22 / AF Component 2: Support to Consultancy to Prioritize and Quality And Cost- Open - Internationa Under Implement IDA / 61210 Project Preparation and Proc Prior 5,000,000.00 0.00 2021-10-01 2022-01-25 2021-10-22 2022-03-22 2021-12-05 2022-11-03 2022-01-02 2023-01-12 2022-02-01 2023-03-23 2022-03-08 2022-04-12 2023-08-29 Prepare Bankable PPP Project Based Selection l ation urement s for Implementation IFPPP/PFF/MTRH/11/2021-22 AF Component 2: Support to / Transaction Advisory for the Quality And Cost- Open - Internationa Under Implement IDA / 61210 Project Preparation and Proc Post 800,000.00 0.00 2021-11-15 2021-12-01 2021-12-06 2022-03-01 2022-01-19 2022-09-30 2022-02-16 2022-03-18 2022-04-22 2022-05-27 2023-11-25 Proposed Ultra-Modern Traini Based Selection l ation urement ng Complex PPP Project IFPPP/PIU/KETRACO/10/2019 -20 / Transaction Advisory for AF Component 2: Support to Quality And Cost- Open - Internationa the Proposed Malindi-Galana IDA / 61210 Project Preparation and Proc Prior 3,000,000.00 0.00 Canceled 2020-05-17 2020-05-14 2020-06-07 2020-06-09 2020-07-21 2020-08-18 2020-09-17 2020-10-22 2020-11-26 2022-11-26 Based Selection l and Rongai-Keringet-Chemos urement it Power Transmission Lines P PP Project IFPPP/PIU/PPPU/08/2019-20 / Development of a Curriculum AF Component 1: Support to Least Cost Selecti and Related Documents for C IDA / 61210 Post Open - National 350,000.00 0.00 Canceled 2020-03-30 2020-03-25 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-09-04 2020-10-09 2021-04-07 Institutional Strengthening on apacity Building on Public Pri vate Partnerships in Kenya INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-NT PPP-10801-CS-INDV / Technical Support to PPP Ins Individual Consult Recruitment of PPP Procurem IDA / 51570 titutions for PPP Legal, Regul Prior Open 240,000.00 0.00 Canceled 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2017-12-31 ant Selection ent Expert atory and PPP Financing Envi ronment KE-NT PPP-10812-CS-INDV / Support for Preparation of In Individual Consult Technical Advisor to Support IDA / 51570 Prior Open 250,000.00 0.00 Canceled 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2017-12-31 dividual PPPs ant Selection the Water Sub sector KE-NT PPP-10815-CS-INDV / Support for Preparation of In Individual Consult IDA / 51570 Prior Open 280,000.00 0.00 Canceled 2017-03-27 2017-05-15 2017-06-05 2017-07-10 2017-12-31 PPP Advisor to the PPP Unit dividual PPPs ant Selection KE-NT PPP-38244-CS-INDV / Support for Preparation of In Individual Consult Recruitment of a Biodiversity IDA / 51570 Post Limited 48,000.00 0.00 Canceled 2017-11-29 2017-12-06 2017-12-20 2018-01-17 2018-03-19 dividual PPPs ant Selection Specialist for the PPP Unit KE-NT PPP-38247-CS-INDV / Support for Preparation of In Individual Consult Recruitment of an Environme IDA / 51570 Post Limited 37,000.00 0.00 Canceled 2017-11-29 2017-12-06 2017-12-20 2018-01-17 2018-03-19 dividual PPPs ant Selection ntal Specialist for the PPP Uni t KE-NT PPP-38249-CS-INDV / Support for Preparation of In Individual Consult Recruitment of a Social Speci IDA / 51570 Post Limited 37,000.00 0.00 Canceled 2017-11-29 2017-12-06 2017-12-20 2018-01-17 2018-03-19 dividual PPPs ant Selection alist for the PPP Unit IFPPP-PPPU-FM-02-2018-19 / Consultancy to engage a PPP AF Component 1: Support to IDA / 61210 Post Direct Selection Direct 162,000.00 0.00 Canceled 2019-02-15 2019-02-25 2019-04-15 2020-04-14 Financial Modeller to Provide Institutional Strengthening Technical Support to the PPP Unit in Kenya IFPPP/PPPU/DC/01/2018-19 / Capacity Building towards PP AF Component 1: Support to IDA / 61210 Post Direct Selection Direct 390,000.00 294,565.00 Signed 2019-09-30 2019-10-09 2019-10-15 2020-01-31 2019-12-19 2020-07-31 2020-06-16 P Certification for National a Institutional Strengthening nd County Governments IFPPP/PPPU/M&E/2017-18 / R AF Component 1: Support to Individual Consult ecruitment of one (1) Monitor IDA / 61210 Post Open 135,000.00 62,077.57 Signed 2019-11-25 2018-05-15 2020-01-13 2019-05-16 2020-02-03 2019-10-03 2020-03-09 2019-10-31 2021-09-04 Institutional Strengthening ant Selection ing and Evaluation Expert IFPPP/PPPU/CB/2017-18 / Re AF Component 1: Support to Individual Consult cruitment of one (1) PPP Cap IDA / 61210 Post Open 90,000.00 50,020.86 Signed 2019-11-25 2018-05-15 2020-01-13 2019-09-04 2020-02-03 2019-09-11 2020-03-09 2019-10-31 2021-09-04 Institutional Strengthening ant Selection acity Building Expert for the PPP Unit IFPPP/PPPU/IO/2017-18 / Rec AF Component 1: Support to Individual Consult ruitment of one (1) Informati IDA / 61210 Post Open 36,000.00 20,008.34 Signed 2019-11-25 2018-05-15 2020-01-13 2019-05-16 2020-02-03 2019-06-28 2020-03-09 2019-08-29 2021-09-04 Institutional Strengthening ant Selection on Officer for the PPP Unit IFPPP/PPPU/CO/2017-18 / Re AF Component 1: Support to Individual Consult cruitment of three (3) PPP Co IDA / 61210 Post Open 378,000.00 110,091.70 Signed 2019-11-25 2018-05-15 2020-01-13 2019-05-16 2020-02-03 2019-06-27 2020-03-09 2019-08-30 2021-09-04 Institutional Strengthening ant Selection unty Officers for the PPP Unit IFPPP/PPPU/LO/2017-18 / Re AF Component 1: Support to Individual Consult cruitment of three (3) PPP Le IDA / 61210 Post Open 378,000.00 160,133.37 Signed 2019-11-25 2018-05-15 2020-01-13 2019-05-16 2020-02-03 2019-07-18 2020-03-09 2019-08-30 2021-09-04 Institutional Strengthening ant Selection gal Officers for the PPP Unit IFPPP/PPPU/PRO/2017-18 / R AF Component 1: Support to Individual Consult ecruitment of three (3) PPP P IDA / 61210 Post Open 378,000.00 103,085.87 Signed 2019-11-25 2018-05-15 2020-01-13 2019-10-29 2020-02-03 2019-11-12 2020-03-09 2020-01-31 2021-09-04 Institutional Strengthening ant Selection roject Officers for the PPP Uni t IFPPP/PPPU/PO/2017-18 / Re AF Component 1: Support to Individual Consult cruitment of one (1) PPP Proc IDA / 61210 Post Open 126,000.00 41,517.31 Signed 2019-11-25 2018-05-15 2020-01-13 2019-05-16 2020-02-03 2019-06-28 2020-03-09 2019-08-29 2021-09-04 Institutional Strengthening ant Selection urement Officer for the PPP U nit Page 3 IFPPP/PPPU/ES/2019-20 / Rec AF Component 1: Support to Individual Consult Under Implement ruitment of one (1) Environm IDA / 61210 Post Open 288,000.00 0.00 2019-11-28 2020-02-13 2020-01-16 2022-05-27 2020-02-06 2022-09-12 2020-03-12 2023-03-12 Institutional Strengthening ant Selection ation ental Safeguards Expert for t he PPP Unit IFPPP/PPPU/FIN/2017-18 / Re AF Component 1: Support to Individual Consult cruitment of one (1) Finance IDA / 61210 Post Open 271,000.00 0.00 Canceled 2019-11-25 2019-12-23 2020-01-13 2020-02-07 2020-02-03 2020-03-09 2021-09-04 Institutional Strengthening ant Selection Expert for the PPP Unit IFPPP/PPPU/TECH/2017-18 / AF Component 1: Support to Individual Consult Recruitment of one (1) PPP T IDA / 61210 Post Open 271,000.00 0.00 Canceled 2019-11-25 2019-12-23 2020-01-13 2020-02-03 2020-03-09 2021-09-04 Institutional Strengthening ant Selection echnical Expert for the PPP U nit IFPPP/PPPU/TRN/2017-18 / R AF Component 1: Support to Individual Consult ecruitment of Transaction Ex IDA / 61210 Post Open 287,000.00 0.00 Canceled 2020-02-25 2020-02-26 2020-04-14 2019-03-15 2020-05-05 2020-06-09 2021-12-05 Institutional Strengthening ant Selection pert for the PPP Unit IFPPP/PPPU/TRN2/2017-18 / AF Component 1: Support to Individual Consult Recruitment of Transaction E IDA / 61210 Post Open 287,000.00 0.00 Canceled 2020-02-25 2020-02-26 2020-04-14 2019-05-16 2020-05-05 2020-06-09 2021-12-05 Institutional Strengthening ant Selection xpert 2 for the PPP Unit IFPPP/PPPU/TRN3/2017-18 / AF Component 1: Support to Individual Consult Recruitment of Transaction E IDA / 61210 Post Open 287,000.00 0.00 Canceled 2020-02-25 2020-02-26 2020-04-14 2019-05-16 2020-05-05 2020-06-09 2021-12-05 Institutional Strengthening ant Selection xpert 3 for the PPP Unit IFPPP/PPPU/TECH/2019-20 / AF Component 1: Support to Individual Consult Recruitment of a Technical E IDA / 61210 Post Open 271,040.00 0.00 Canceled 2020-02-26 2020-02-26 2020-04-15 2020-05-06 2020-06-10 2022-06-10 Institutional Strengthening ant Selection xpert for the PPP Unit IFPPP/PPPU/FIN/2019-20 / Re AF Component 1: Support to Individual Consult cruitment of a Financial Expe IDA / 61210 Post Open 205,000.00 0.00 Canceled 2020-02-27 2020-02-26 2020-04-16 2020-05-07 2020-06-11 2022-06-11 Institutional Strengthening ant Selection rt for the PPP Unit IFPPP/PIU/TRN/06/2019-20 / AF Component 1: Support to Individual Consult Recruitment of 3No Transacti IDA / 61210 Prior Open 1,050,000.00 0.00 Canceled 2020-03-26 2020-05-14 2020-06-04 2020-07-09 2022-07-09 Institutional Strengthening ant Selection on Experts for the PPP Unit IFPPP/PIU/CS/2019-20 / Advis AF Component 1: Support to or to the Cabinet Secretary, IDA / 61210 Prior Direct Selection Direct 408,000.00 402,895.37 Signed 2020-05-25 2020-06-05 2020-06-04 2020-06-30 2020-08-08 2020-07-30 2022-08-08 Institutional Strengthening National Treasury & Planning IFPPP/PPU/EA/2019-2020 / R AF Component 1: Support to Individual Consult ecruitment of an Executive A IDA / 61210 Post Open 96,000.00 0.00 Canceled 2020-05-28 2020-06-03 2020-07-16 2020-08-06 2020-09-10 2021-03-09 Institutional Strengthening ant Selection ssistant to the Director, PPPU IFPPP/PPPU/PPPA/2020-21 / P AF Component 1: Support to IDA / 61210 Prior Direct Selection Direct 300,000.00 0.00 Canceled 2020-11-05 2020-10-30 2020-11-15 2020-12-15 2021-12-15 PP Advisor to the Director, PP Institutional Strengthening P Unit IFPPP/PPP/PA/2020-21 / Recr uitment of Personal Assistant AF Component 1: Support to Individual Consult IDA / 61210 Post Open 120,000.00 46,953.28 Signed 2021-02-10 2021-02-08 2021-03-16 2021-07-09 2021-03-23 2021-07-14 2021-04-13 2021-10-07 2022-10-05 to the Director General Public Institutional Strengthening ant Selection Private Partnerships IFPPP/PPPD/CE/2021-22 / Re cruitment of a Communicatio AF Component 1: Support to Individual Consult Under Implement IDA / 61210 Post Open 45,000.00 0.00 2021-12-14 2022-02-17 2022-01-12 2022-08-29 2022-01-19 2022-09-07 2022-02-02 2022-10-30 n Expert for the Public Privat Institutional Strengthening ant Selection ation e Partnership Directorate IFPPP/PIU/M&ES/2019-20 / R Support for Program Manage Individual Consult ecruitment of Monitoring and IDA / 61210 Post Open 30,240.00 0.00 Canceled 2020-02-26 2020-03-13 2020-04-15 2019-05-16 2020-05-06 2020-06-10 2022-06-10 ment ant Selection Evaluation Specialist for the PIU KE-NT PPP-8933-CS-INDV / R Support for Program Manage Individual Consult ECRUITMENT OF ASSISTANT IDA / 51570 Post Open 30,000.00 0.00 Canceled 2017-03-10 2017-04-12 2017-04-26 2017-05-17 2017-12-31 ment ant Selection PROJECT ACCOUNTANT FOR THE PIU IFPPP/PPPU/CE/2018-19 / Re AF Component 1: Support to Individual Consult cruitment of a Communicatio IDA / 61210 Post Open 180,000.00 0.00 Canceled 2019-04-30 2019-05-31 2019-06-18 2019-10-29 2019-07-09 2019-08-13 2022-08-12 Institutional Strengthening ant Selection n Expert for the PPP Unit IFPPP/PIU/PS/2018-19 / Recr AF Component 1: Support to Individual Consult uitment of two (2) Procureme IDA / 61210 Post Open 252,000.00 0.00 Canceled 2019-11-25 2019-12-23 2020-01-13 2019-10-29 2020-02-03 2020-03-09 2023-03-09 Institutional Strengthening ant Selection nt Specialists for the Project I mplementation Unit IFPPP/PPPD/PPPA/2020-21 / Recruitment of a PPP Advisor AF Component 1: Support to Individual Consult IDA / 61210 Prior Open 300,000.00 0.00 Canceled 2021-05-26 2021-05-25 2021-07-14 2021-08-04 2021-09-08 2022-09-03 to Provide Technical Support Institutional Strengthening ant Selection to the PPP Directorate in Ken ya IFPPP/PPPU/SGE/2018-19 / R AF Component 1: Support to Individual Consult ecruitment of a Safeguards E IDA / 61210 Post Open 288,000.00 0.00 Canceled 2019-04-30 2019-11-13 2019-06-18 2022-05-27 2019-07-09 2019-08-13 2022-08-12 Institutional Strengthening ant Selection xpert for the PPP Unit Page 4