PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, One WASH- Consolidated WASH Account (CWA) Project “Phase II”, P167794 Project Implementation agency: Water Development Commission (WDC) of the Ministry of Water, Irrigation and Energy (MoWIE) Date of the Procurement Plan: August 28, 2019 Period covered by this Procurement Plan: September 2019 to August 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2020-03-11 2021-11-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167794 GPN Date: 2019-12-06 Project Name: One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) Loan / Credit No: IDA / 64450 W Executing Agency(ies): ater Development Commission WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-WDC-165778-CW-RFB / Procurement Civil Work Construction with supply and installation of pipes and Climate Resilient Water fittings and supply and Supply, Sanitation, and Single Stage - One 2021-08- IDA / 64450 Post Request for Bids Open - International 0.00 Canceled 2020-05-15 2020-05-28 2020-05-20 2020-05-29 2020-06-19 2020-08-18 2020-07-19 2020-10-20 2020-08-23 installation of Hygiene (Climate Resilient Envelope 23 Electromechanical Equipment WASH) for Asaita Afambo Multi village Water Supply Project in Afar Region by WDC. ET-WDC-179853-CW-RFB / Procurement Civil Work Construction with supply and installation of pipes and Climate Resilient Water fittings and supply and Supply, Sanitation, and Single Stage - One 2,701,713.1 2021-10- IDA / 64450 Post Request for Bids Open - National Signed 2020-06-30 2020-10-01 2020-07-05 2020-08-04 2020-11-03 2020-09-03 2021-01-15 2020-10-08 2021-03-10 installation of Hygiene (Climate Resilient Envelope 9 08 Electromechanical Equipment WASH) for Sankura Multi village Water Supply Project in SNNPR by WDC ET-WDC-192686-CW-RFB / Drilling and Construction of Climate Resilient Water Pending Three Deep Water Wells for Supply, Sanitation, and Single Stage - One 2021-02- IDA / 64450 Post Request for Bids Open - National 0.00 Implementat 2020-09-20 2020-09-25 2020-10-25 2020-11-24 2020-12-29 Daro-labu CRWASH Multi Hygiene (Climate Resilient Envelope 27 ion Village Water Supply Project WASH) by WDC ET-WDC-192681-CW-RFB / 14 Deep Water Well Drilling and Well Completion Works of Climate Resilient Water Bena-Hamer Woreda CR- Pending Supply, Sanitation, and Single Stage - One 2021-03- WaSH Rural Multi-Kebeles and IDA / 64450 Post Request for Bids Open - National 0.00 Implementat 2020-09-23 2020-10-24 2020-11-23 2020-12-23 2021-01-27 Hygiene (Climate Resilient Envelope 28 Urban Water Supply & ion WASH) Sanitation Projects, Shaba Cluster and Hammer Woreda Pressure Zone-2 implements by WDC ET-WDC-204085-CW-RFB / Procurement of four water well drilling & construction (lot-1 one well drilling for Rural Water Supply, Pending Billa Kebelle, Lot-2 tow well Single Stage - One 2021-09- IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementat 2020-12-10 2020-12-15 2021-01-26 2021-02-25 2021-04-01 drilling for Fathuli Kebelle & Envelope 28 (Rural WASH) ion Lot-3 one well drilling for Uridata Kebelle) in Errer Woreda of Somali Region implemented by WDC ET-WDC-205227-CW-RFB / Procurement of Civil Works Construction, Supply & Climate Resilient Water Installation of Pipes & Fittings Under Supply, Sanitation, and Single Stage - One 2021-10- and Supply & Installation of IDA / 64450 Post Request for Bids Open - National 0.00 Implementat 2021-01-12 2021-02-05 2021-01-17 2021-02-28 2021-03-09 2021-03-30 2021-06-24 2021-05-04 Hygiene (Climate Resilient Envelope 31 Electro-Mechanical Equipment ion WASH) for Ongogi & Ulaw Multi village WSP in Gambella Region by WDC ET-WDC-205219-CW-RFB / procurement of Civil Works Construction, Supply & Climate Resilient Water Under Installation of Pipes & Fittings Supply, Sanitation, and Single Stage - One 2022-09- IDA / 64450 Post Request for Bids Open - International 0.00 Implementat 2020-12-10 2021-05-25 2020-12-15 2021-07-08 2021-01-26 2021-07-27 2021-02-25 2021-11-03 2021-04-01 and Supply & Installation of Hygiene (Climate Resilient Envelope 23 ion Electro-Mechanical Equipment WASH) for Ayun Multivillage WSP in Somali Region by WDC ET-WDC-213650-CW-RFB- REBID / Civil Work Construction with Supply and Installation of Pipes and Climate Resilient Water Under Fittings and Supply and Supply, Sanitation, and Single Stage - One 2022-11- IDA / 64450 Post Request for Bids Open - International 0.00 Implementat 2021-02-10 2021-04-03 2021-02-15 2021-04-06 2021-03-29 2021-05-18 2021-04-28 2021-06-23 2021-06-02 Installation of Electro- Hygiene (Climate Resilient Envelope 24 ion Mechanical Equipment for WASH) Ayysayta-Afambo Multi- Village Water Supply Project in Afar Region by WDC (Re-bid) ET-WDC-192670-CW-RFB / Civil Work Construction with Supply and Installation of Climate Resilient Water Pipes and Fitting and Supply, Sanitation, and Single Stage - One 2022-08- IDA / 64450 Post Request for Bids Open - International 0.00 Canceled 2020-11-03 2020-11-20 2020-11-08 2020-11-26 2020-12-20 2021-01-12 2021-01-19 2021-02-04 2021-02-23 Electromechanical Equipment Hygiene (Climate Resilient Envelope 17 for the Zuhamusit Multi WASH) Village Water Supply Project by WDC ET-WDC-192697-CW-RFB / Civil Work Construction with Supply and Installation of Climate Resilient Water Pipes and Fitting and Supply, Sanitation, and Single Stage - One 2021-12- IDA / 64450 Post Request for Bids Open - International 0.00 Canceled 2020-09-21 2020-11-11 2020-09-26 2020-10-26 2020-12-21 2020-11-25 2020-12-30 Electromechanical Equipment Hygiene (Climate Resilient Envelope 30 for Guredhamole Multi Village WASH) Water Supply Project in Somali Region by WDC Page 1 ET-WDC-257689-CW-RFB- RE-BID / Civil work Construction with Supply and Request for Climate Resilient Water Laying Pipes and Fittings and Bids - Small Pending Supply, Sanitation, and Single Stage - One 2023-09- supply and Installation of EME IDA / 64450 Prior Request for Bids Open - International Works SPD (1 0.00 Implementat 2021-11-25 2021-11-30 2022-01-14 2022-02-13 2022-03-20 Hygiene (Climate Resilient Envelope 11 for Guradamole Multi-Village envelope ion WASH) Water Supply Project in Somali process) Region by Water Development Commission (Re-Bid) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-WDC-165210-GO-RFB / procurement of IT infrastructure (# work station computers, #RAID, # power Pending Institutional Strengthening Single Stage - One supply controller, # Storage IDA / 64450 Post Request for Bids Open - National 0.00 Implementati 2020-04-15 2020-04-20 2020-05-20 2020-06-19 2020-07-24 2020-11-21 and Project Management Envelope rack) for the data base server, on application server and other IT System for Basin Development Authority by WDC ET-WDC-165214-GO-RFQ / procurement of hydro-logical data mart (movable shelf, fire Pending distinguishes and accessories) Institutional Strengthening Request for Single Stage - One IDA / 64450 Post Limited 0.00 Implementati 2020-04-20 2020-06-15 2020-09-13 for archiving different types of and Project Management Quotations Envelope on historical hard copy data sets for Basin Development Authority by WDC ET-WDC-169864-GO-RFB / Procurement of Borehole Camera, Resistivity meter syscal junior, Deep meter, Hand Held GPS, Geological Under Institutional Strengthening Single Stage - One Hammer, Mobile Water quality IDA / 64450 Post Request for Bids Open - National 0.00 Implementati 2020-05-07 2021-02-11 2020-05-12 2021-02-26 2020-06-11 2020-07-11 2020-08-08 2020-09-22 and Project Management Envelope kits, Hand Lens, Pocket on Pentameter and Field Van Shear test for WDC PMU Staff by Water Development Commission. ET-WDC-169873-GO-RFB / Procurement of Plotter, Scanner & Digitizer, Total Under Institutional Strengthening Single Stage - One Station Instrument and IDA / 64450 Post Request for Bids Open 0.00 Implementati 2020-05-07 2020-06-26 2020-05-12 2020-06-11 2020-08-26 2020-07-11 2020-09-21 2020-08-08 2020-09-22 and Project Management Envelope A3/A4 Photocopy/ Printer for on WDC PMU Staff by Water Development Commission. ET-WDC-165209-GO-RFB / Procurement of supply and installation of Water Resource Management Software packages ( data base Pending Institutional Strengthening Single Stage - One management system, data IDA / 64450 Post Request for Bids Open - National 0.00 Implementati 2020-05-05 2020-05-10 2020-06-09 2020-07-09 2020-08-13 2020-12-11 and Project Management Envelope migration and Training) and on addition background software for the data base for Basin Development Authority by WDC ET-WDC-170088-GO-RFQ / Procurement of Multi Mater,Megger Tester, Clamp Meter, Pressure gauge, Under electrical toolbox, digital Institutional Strengthening Request for Single Stage - One IDA / 64450 Post Limited 0.00 Implementati 2020-05-13 2020-05-20 2020-06-17 2020-07-01 tachometer, Dial gauge and Project Management Quotations Envelope on alignment and Voltage detector for WDC PMU Staff by Water Development Commission ET-WDC-170089-GO-RFQ / Procurement of Desk top Computer for Database, Power Bank, Tablet,External Hard Pending Institutional Strengthening Request for Single Stage - One Disk,LCD Projector,UPS IDA / 64450 Post Limited 0.00 Implementati 2020-05-12 2020-06-16 2020-06-30 and Project Management Quotations Envelope Battery, Portable SSD type-1 & on scanner for WDC PMU Staff by Water Development Commission ET-WDC-172500-GO-RFB / Procurement of vehicles ( lot I, #64 units of Double Cabin Diesel 4 WD 6 cylinders Pick up with spare parts and field Institutional Strengthening UN Agencies IDA / 64450 Prior Direct 2,753,868.36 Signed 2020-08-31 2020-10-28 2020-09-07 2021-05-24 2020-10-19 2021-09-09 2021-02-16 kits and lot II, #2 units of and Project Management (Direct) station wagons 4 WD (having 6 cylinders with field kits and spare parts) for Regional Bureaus and WDC by WDC ET-WDC-172502-GO-RFB / Procurement of 508 units of Motor Bikes with Field kits Institutional Strengthening UN Agencies IDA / 64450 Prior Direct 1,960,982.60 Signed 2020-08-31 2020-10-28 2020-09-07 2021-05-19 2020-10-19 2021-09-09 2021-02-16 and spare parts for Regional and Project Management (Direct) Water Bureaus and Woredas by WDC ET-WDC-215572-GO-RFQ / Procurement of office Pending equipment's ( #41 Laptop Institutional Strengthening Request for Single Stage - One IDA / 64450 Post Limited 0.00 Implementati 2021-02-23 2021-04-20 2021-05-11 Computer and # 20 Desk Top and Project Management Quotations Envelope on computer) for WDC PMU staff implemented by WDC Page 2 ET-WDC-219554-GO-RFB / Procurement of IT Pending Equipment's (computers, Institutional Strengthening Single Stage - One IDA / 64450 Post Request for Bids Open - National 0.00 Implementati 2021-03-15 2021-03-20 2021-04-19 2021-05-19 2021-06-23 2021-09-21 network, power backup) for and Project Management Envelope on HQ and Regional Offices of National Metrological Agency by WDC ET-WDC-231713-GO-DIR / Procurement of Climate Data base with #2 potential servers Climate Resilient Water Pending including Oracle license from Supply, Sanitation, and IDA / 64450 Post Direct Selection Direct 0.00 Implementati 2021-05-05 2021-05-10 2021-06-14 2021-12-11 from Czech Republic Hygiene (Climate Resilient on Meteorological and Hydro- WASH) logical Institute for National Metrological Agency by WDC ET-WDC-242608-GO-RFB / Procurement of Drafting and Surveying Equipment (#1Plotter, #2 Total Station Pending Instrument with full Institutional Strengthening Single Stage - One IDA / 64450 Post Request for Bids Open - National 0.00 Implementati 2021-07-22 2021-07-27 2021-08-26 2021-09-25 2021-10-30 2022-03-29 accessories, #2 RTK GPS, and and Project Management Envelope on #6 Way Radio with GPS Navigator) for WDC PMU Staff by Water Development Commission. ET-WDC-241358-GO-RFQ / procurement of Electro- mechnical measuring instrument & maintenance tools such as Multi meter Rural Water Supply, Pending (professional & standard) Request for Single Stage - One IDA / 64450 Sanitation, and Hygiene Post Limited 0.00 Implementati 2021-09-20 2021-10-13 2021-11-12 Megger tester, clamper meter, Quotations Envelope (Rural WASH) on Heavy Duty mechanical tool box, Digital Tachometer,Electrical Tool box and others , for PMU staff by WDC ET-WDC-231712-GO-DIR / Procurement of model climate data for NMA (Ethiopia Climate Resilient Water Pending weather and climate forecast Supply, Sanitation, and IDA / 64450 Post Direct Selection Direct 0.00 Implementati 2021-09-20 2021-09-25 2021-10-30 2022-10-30 and research) from European Hygiene (Climate Resilient on Centre for Medium-Range WASH) Weather Forecasts (including license) by WDC ET-WDC-261188-GO-DIR / Procurement of 6 hard top Pending Institutional Strengthening vehicles for Water IDA / 64450 Post Direct Selection Direct 0.00 Implementati 2021-10-20 2021-10-25 2021-11-29 2022-05-28 and Project Management Development Commission on PMU implemented by WDC. ET-WDC-261680-GO-RFB / Procurement of Geophysical, Geotechnical, Hydrogeology Equipments such as (Lot- Rural Water Supply, Pending 1)Auger /Geotechnical Single Stage - One IDA / 64450 Sanitation, and Hygiene Post Request for Bids Open - National 0.00 Implementati 2021-11-30 2021-12-05 2022-01-04 2022-01-19 2022-02-23 2022-06-23 Investigation equipment (Lot- Envelope (Rural WASH) on 2) Hand Held GPS (with better accuracy), (Lot-3) Hand Held Walkie-Talkie- Waterproof, by Ministry of Water & Energy NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-WDC-231238-NC-RFQ / For Printing Service of Pending Operation and Maintenance Institutional Strengthening Request for Single Stage - One IDA / 64450 Post Limited 0.00 Implementati 2021-05-02 2021-06-27 2021-09-25 Manuals for all Regions ,Zones and Project Management Quotations Envelope on and Woreda on Rural Water Supply. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-WDC-154074-CS-QCBS / consultancy service forFeasibility Study and Detail Design of Climate Resilient Climate Resilient Water Water Supply ,Sanitation and Supply, Sanitation, and Quality And Cost- Under Hygiene in SNNP region of IDA / 64450 Post Open - National 0.00 2020-02-27 2020-08-31 2020-03-19 2020-04-30 2021-06-25 2020-05-30 2020-06-20 2020-07-25 2020-08-29 2021-02-25 Hygiene (Climate Resilient Based Selection Implementation Tembaro Woreda (Tembaro WASH) Multi Village WSP) and in Zala Woreda (Zala Multi Village WSP) by Water Development Commission. ET-WDC-154134-CS-QCBS / Consultancy service for Strategy Development in Institutional Strengthening Quality And Cost- Under Gender Equity and Disability IDA / 64450 Post Open - National 0.00 2020-02-25 2020-04-06 2020-03-17 2020-04-30 2020-05-28 2020-06-27 2020-08-01 2020-09-05 2021-03-04 and Project Management Based Selection Implementation inclusive for WASH Sector in Ethiopia by Water Development Commission Page 3 ET-WDC-154063-CS-QCBS / Selection and Employment of Independent procurement Audit service for three years procurement Audit (2020- Rural Water Supply, 2022 years ) for Ethiopia - Quality And Cost- Under IDA / 64450 Sanitation, and Hygiene Prior Open - National 0.00 2020-04-15 2020-09-30 2020-05-06 2021-01-11 2020-06-25 2020-07-25 2020-08-24 2020-09-28 2020-11-02 2023-11-02 P167794 - One Based Selection Implementation (Rural WASH) WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project by Water Development Commission ET-WDC-165217-CS-QCBS / Selection and employment of consultant for development of Institutional Strengthening Quality And Cost- Under concept of operation/service IDA / 64450 Post Open - National 0.00 2020-04-15 2020-05-15 2020-05-06 2020-06-19 2020-07-17 2020-08-16 2020-09-20 2020-10-25 2021-02-22 and Project Management Based Selection Implementation strategy for Basin Development Authority by WDC ET-WDC-154085-CS-QCBS / Consultancy service for Feasibility Study and Detail Design of climate Resilient Climate Resilient Water Water Supply ,Sanitation and Supply, Sanitation, and Quality And Cost- Under Hygiene in SNNP Region of IDA / 64450 Post Open - National 0.00 2020-05-15 2020-08-31 2020-06-05 2021-07-21 2020-07-10 2021-06-25 2020-08-09 2020-08-30 2020-10-04 2020-11-08 2021-05-07 Hygiene (Climate Resilient Based Selection Implementation Siraro Woreda (Siraro Multi WASH) Village WSP and Hawassa Zuria Woreda Multi Village WSP ) by Water Development Commission ET-WDC-154091-CS-QCBS / Consultancy service for Feasibility Study and Detail Design of Climate Resilient Climate Resilient Water Water Supply ,Sanitation and Supply, Sanitation, and Quality And Cost- Under Hygiene in Somali Region of IDA / 64450 Post Open - National 0.00 2020-05-15 2020-08-31 2020-06-05 2021-04-09 2020-07-17 2021-06-18 2020-08-16 2020-09-06 2020-10-11 2020-11-15 2021-05-14 Hygiene (Climate Resilient Based Selection Implementation Adale Woreda (Adadle Town WASH) WSP) & Danana Woreda (Danana Multi- Village WSP ) by Water Development Commission. ET-WDC-154100-CS-QCBS / Consultancy service for Feasibility Study and Detail Design of CR Water Supply Climate Resilient Water ,Sanitation and Hygiene in Supply, Sanitation, and Quality And Cost- Under Somali Region of Danot IDA / 64450 Post Open - National 0.00 2020-05-15 2020-08-31 2020-06-05 2021-03-30 2020-07-10 2021-06-18 2020-08-09 2020-08-30 2020-10-04 2020-11-08 2021-05-07 Hygiene (Climate Resilient Based Selection Implementation Woreda ( Danot Multi- Village WASH) WSP ) and Dararo Woreda ( Dararo Multi Village WSP ) by Water Development Commission ET-WDC-202184-CS-QCBS / Consultancy Service for Study Climate Resilient Water and Design of Multi Village Supply, Sanitation, and Quality And Cost- Under IDA / 64450 Post Open - National 0.00 2020-11-10 2020-11-02 2020-12-01 2021-01-14 2021-02-11 2021-03-13 2021-04-17 2021-05-22 2022-05-22 Water Supply System in Salhad Hygiene (Climate Resilient Based Selection Implementation and Duhun Woredas in Somali WASH) Region by WDC ET-WDC-202186-CS-QCBS / Consultancy Service for Study Climate Resilient Water and Design of Multi Village Supply, Sanitation, and Quality And Cost- Under IDA / 64450 Post Open - National 0.00 2020-11-10 2020-11-21 2020-12-01 2021-01-14 2021-02-11 2021-03-13 2021-04-17 2021-05-22 2022-05-22 Water Supply System in Burji Hygiene (Climate Resilient Based Selection Implementation and Conso Woredas in SNNPR WASH) Region by WDC ET-WDC-202187-CS-QCBS / Consultancy Service for Study Climate Resilient Water and Design of Multi Village Supply, Sanitation, and Quality And Cost- Under IDA / 64450 Post Open - National 0.00 2020-11-10 2020-11-21 2020-12-01 2021-01-14 2021-02-11 2021-03-13 2021-04-17 2021-05-22 2022-05-22 Water Supply System in Mirab Hygiene (Climate Resilient Based Selection Implementation Abeya Woreda in SNNPR WASH) Region by WDC ET-WDC-202188-CS-QCBS / Consultancy Service for Study Climate Resilient Water and Design of Multi Village Supply, Sanitation, and Quality And Cost- Under Water Supply System in Melka IDA / 64450 Post Open - National 0.00 2020-11-10 2020-12-03 2020-12-01 2021-01-14 2021-02-11 2021-03-13 2021-04-17 2021-05-22 2022-05-22 Hygiene (Climate Resilient Based Selection Implementation Soda, Bule-Hora and Aga WASH) Wayu Woredas in Oromia Region by WDC ET-WDC-202189-CS-QCBS / Consultancy Service for Study Climate Resilient Water and Design of Multi Village Supply, Sanitation, and Quality And Cost- Under Water Supply System in Meda IDA / 64450 Post Open - National 0.00 2020-11-10 2020-12-03 2020-12-01 2021-01-14 2021-02-11 2021-03-13 2021-04-17 2021-05-22 2022-05-22 Hygiene (Climate Resilient Based Selection Implementation Wolabu and Honkolo Wabe WASH) Woredas in Oromia Region by WDC ET-WDC-202192-CS-QCBS / Consultancy Service for Study Climate Resilient Water and Design of Multi Village Supply, Sanitation, and Quality And Cost- Under IDA / 64450 Post Open - National 0.00 2020-11-10 2020-12-03 2020-12-01 2021-01-14 2021-02-11 2021-03-13 2021-04-17 2021-05-22 2022-05-22 Water Supply System in Kumbi Hygiene (Climate Resilient Based Selection Implementation Woreda in Oromia Region by WASH) WDC ET-WDC-202194-CS-QCBS / Consultancy Service for Study Climate Resilient Water and Design of Multi Village Supply, Sanitation, and Quality And Cost- Under IDA / 64450 Post Open - National 0.00 2020-11-10 2020-12-03 2020-12-01 2021-01-14 2021-02-11 2021-03-13 2021-04-17 2021-05-22 2022-05-22 Water Supply System in Sisiga Hygiene (Climate Resilient Based Selection Implementation Woreda in Oromia Region by WASH) WDC ET-WDC-231722-CS-QCBS / support for operationalization Climate Resilient Water of existing NMA numerical Supply, Sanitation, and Quality And Cost- Pending IDA / 64450 Post Open - National 0.00 2021-05-12 2021-06-02 2021-07-16 2021-08-13 2021-09-12 2021-10-17 2021-11-21 2023-11-11 weather prediction system Hygiene (Climate Resilient Based Selection Implementation with ECMWF data stream by WASH) WDC Page 4 ET-WDC-252531-CS-CQS / Selection & Employment of Climate Resilient Water Consulting Firm for Consultant Supply, Sanitation, and Pending Consultancy Service for IDA / 64450 Post Qualification Open - National 0.00 2021-09-23 2021-10-07 2021-11-01 2021-11-06 2021-11-18 2022-04-17 Hygiene (Climate Resilient Implementation preparation of Floride Selection WASH) Mitigation 10 years strategy by WDC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-WDC-165216-CS-INDV / Selection and Employment IC for data rescue for historical Individual observational data (inventory, Institutional Strengthening Pending IDA / 64450 Post Consultant Direct 0.00 2020-05-15 2020-05-25 2020-06-15 2020-07-20 2020-11-17 scanning, arranging and etc of and Project Management Implementation Selection surface and ground water data set) for Basin Development Authority by WDC ET-WDC-179854-CS-INDV / Individual Selection and Employment of Institutional Strengthening Under IDA / 64450 Prior Consultant Open 0.00 2020-06-22 2020-10-28 2020-07-26 2020-08-16 2020-09-20 2021-09-20 one (1) Individual and Project Management Implementation Selection Procurement Consultant for WDC by WDC ET-WDC-155145-CS-INDV / Selection and Employment of Individual Senior Procurement Institutional Strengthening IDA / 64450 Prior Consultant Open 0.00 Canceled 2020-04-22 2020-05-27 2020-06-06 2020-07-07 2023-07-07 Management Specialist for and Project Management Selection WDC by Water Development Commission ET-WDC-155144-CS-INDV / Selection and Employment of Individual Senior Procurement Institutional Strengthening IDA / 64450 Prior Consultant Open 0.00 Canceled 2020-04-23 2020-05-28 2020-06-07 2020-07-08 2023-07-08 Management Specialist for and Project Management Selection WDC by Water Development Commission ET-WDC-155142-CS-INDV / Selection and Employment of Individual Senior Procurement Institutional Strengthening IDA / 64450 Prior Consultant Open 0.00 Canceled 2020-04-23 2020-05-26 2020-06-10 2020-06-30 2023-06-30 Management Specialist for and Project Management Selection WDC by Water Development Commission ET-WDC-155133-CS-INDV / Selection and Employment of Individual Senior Procurement Institutional Strengthening IDA / 64450 Prior Consultant Open 0.00 Canceled 2020-04-23 2020-05-28 2020-06-07 2020-07-08 2023-07-08 Management Specialist for and Project Management Selection WDC by Water Development Commission ET-WDC-199282-CS-INDV / Individual Selection and employment of Institutional Strengthening Under IDA / 64450 Prior Consultant Open 0.00 2020-11-10 2020-11-17 2020-12-29 2021-01-19 2021-02-23 2024-02-23 3 procurement specialist for and Project Management Implementation Selection WDC PIU ET-WDC-219558-CS-INDV / Constancy service to identify user needs for hydro-met Individual Institutional Strengthening Pending services and product focused IDA / 64450 Post Consultant Open 0.00 2021-03-15 2021-05-03 2021-05-24 2021-06-28 2022-06-28 and Project Management Implementation on the WaSH and Water Selection Resource Sector for NMA by WDC ET-WDC-219572-CS-INDV / Technical advisory service on climate science research, Individual Institutional Strengthening Pending focusing on down scaling IDA / 64450 Post Consultant Open 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2023-06-23 and Project Management Implementation climate models for providing Selection local impact assessments for NMA by WDC ET-WDC-231724-CS-CQS / Selection and employment of 2 (two) experts (#1 Climate Resilient Water Individual Meteorologist and climate Supply, Sanitation, and Pending IDA / 64450 Post Consultant Open 0.00 2021-09-20 2021-11-08 2021-11-29 2022-01-03 2022-07-02 modeling expert # climate Hygiene (Climate Resilient Implementation Selection change and atmospheric WASH) science expert) for NBA by WDC Page 5