PROCUREMENT PLAN (Textual Part) Project information: Sri Lanka – Water Resources Management Project-P-166865 Project Implementation agency: Ministry of Mahaweli Development and Environment Date of the Procurement Plan: 24 June, 2019 Period covered by this Procurement Plan: 15 March 2020-30 Sep. 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 4. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT Sri Lanka : Sri Lanka Integrated Watershed and Water Resources Management Project PLAN General Information Country: Sri Lanka 2019-06-28 Bank’s Approval Date of the Original Procurement Plan: 2022-10-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166865 GPN Date: 2020-07-28 Project Name: Sri Lanka Integrated Watershed and Water Resources Management Project Loan / Credit No: / , IDA / 66190, IDA / 66210 Ministry of Mahaweli Development and Environment Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LK-MOMDE-117185-CW-RFQ Component 4: Project Manag Request for Quota Single Stage - One E 2019-11-1 / Refurbishment of PMU offic / Post Limited 45,311.47 38,887.42 Completed 2019-06-26 2019-06-18 2019-08-14 2019-09-04 ement tions nvelope 2 e (IWWRMP/PP/WORKS/01) LK-MOMDE-123620-CW-RFB / Improvements to Unnichcha Component 2: Infrastructure Single Stage - One E 2021-03-1 i LB main channel from stn 0 / Post Request for Bids Open - National 923,033.71 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 Improvements nvelope 8 +000 to stn 13+725 (IWWRM P-2/WORKS/ID/OCBN/04-1) LK-MOMDE-124032-CW-RFB / Improvements to Unnichcha Component 2: Infrastructure Single Stage - One E 2021-03-0 i RB main channel from stn 0 / Post Request for Bids Open - National 906,741.57 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 Improvements nvelope 1 +000 to stn 4+950 ( IWWRM P-2/WORKS/ID/OCBN/04-2 ) LK-MOMDE-124217-CW-RFB / Improvements to Unnichcha Component 2: Infrastructure Single Stage - One E 2021-03-0 i RB main channel from stn 4 / Post Request for Bids Open - National 887,640.45 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 Improvements nvelope 1 +950 to stn 10+000 ( IWWR MP-2/WORKS/ID/OCBN/04-3 ) LK-MOMDE-124409-CW-RFB Component 2: Infrastructure Single Stage - One E 2021-03-0 / Rehabilititation of Panama T / Post Request for Bids Open - National 342,696.63 0.00 Canceled 2019-11-26 2019-12-10 2019-12-31 2020-01-30 2020-03-05 Improvements nvelope 5 ank ( IWWRMP-2/WORKS/ID/ OCBN/07 ) LK-MOMDE-124659-CW-RFB Component 2: Infrastructure Single Stage - One E 2021-03-2 / Rehabilititation of Peramad / Post Request for Bids Open - National 898,876.40 0.00 Canceled 2019-12-20 2020-01-03 2020-01-24 2020-02-23 2020-03-29 Improvements nvelope 9 uwa Scheme ( IWWRMP-2/W ORKS/ID/OCBN/17 ) LK-MOMDE-124666-CW-RFB Component 2: Infrastructure Single Stage - One E 2021-03-2 / Improvements Viyadikulam / Post Request for Bids Open - National 950,185.39 0.00 Canceled 2019-12-20 2020-01-03 2020-01-24 2020-02-23 2020-03-29 Improvements nvelope 9 Spill ( IWWRMP-2/WORKS/ID/ OCBN/18-2 ) LK-MOMDE-124667-CW-RFB Component 2: Infrastructure Single Stage - One E 2021-05-0 / Rehabilititation of Abakolaw / Post Request for Bids Open - National 325,505.62 0.00 Canceled 2020-01-24 2020-02-07 2020-02-28 2020-03-29 2020-05-03 Improvements nvelope 3 ewa Tank ( IWWRMP-2/WORK S/ID/OCBN/19 ) LK-MOMDE-124683-CW-RFB Component 2: Infrastructure Single Stage - One E 2021-03-0 / Rehabilititation of Karawita / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2019-11-25 2019-12-09 2019-12-30 2020-01-29 2020-03-04 Improvements nvelope 4 tank ( IWWRMP-2/WORKS/ID/ OCBN/20 ) LK-MOMDE-125489-CW-RFB Component 2: Infrastructure Single Stage - One E 2021-04-0 / Rehabilititation of Madiyaw / Post Request for Bids Open - National 464,775.28 0.00 Canceled 2019-12-23 2020-01-06 2020-01-27 2020-02-26 2020-04-01 Improvements nvelope 1 a Tank ( IWWRMP-2/WORKS/I D/OCBN/23 ) LK-MOMDE-125508-CW-RFB Component 2: Infrastructure Single Stage - One E 2021-04-0 / Rehabilititation of Mannank / Post Request for Bids Open - National 280,898.88 0.00 Canceled 2019-12-27 2020-01-10 2020-01-31 2020-03-01 2020-04-05 Improvements nvelope 5 atiya Tank ( IWWRMP-2/WOR KS/ID/OCBN/27 ) LK-MOMDE-125511-CW-RFB / Rehabilititation of Main Can Component 2: Infrastructure Single Stage - One E 2021-03-1 / Post Request for Bids Open - National 347,780.90 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 al of Kimbulawana Oya Sche Improvements nvelope 8 me (LBMC) ( IWWRMP-2/WOR KS/ID/OCBN/28-1 ) LK-MOMDE-125513-CW-RFB / Rehabilititation of Main Can Component 2: Infrastructure Single Stage - One E 2021-03-0 / Post Request for Bids Open - National 262,859.69 0.00 Canceled 2019-12-09 2019-12-10 2019-12-31 2020-01-30 2020-03-05 al of Kimbulawana Oya Sche Improvements nvelope 5 me (RBMC) ( IWWRMP-2/WO RKS/ID/OCBN/28-2) LK-MOMDE-125515-CW-RFB Component 2: Infrastructure Single Stage - One E 2021-03-1 / Rehabilititation of Maha And / Post Request for Bids Open - National 896,067.42 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 Improvements nvelope 8 ara Wewa ( IWWRMP-2/WOR KS/ID/OCBN/29 ) LK-MOMDE-125834-CW-RFB / Improvement of Spillway Ta Component 2: Infrastructure Single Stage - One E 2021-03-0 / Post Request for Bids Open - National 369,101.12 0.00 Canceled 2019-11-26 2019-12-10 2019-12-31 2020-01-30 2020-03-05 il Canal of Kotmale Dam ( IW Improvements nvelope 5 WRMP-2/WORKS/MASL/OCBN /101 ) LK-MOMDE-125839-CW-RFB / Repairs to gates of irrigatio Component 2: Infrastructure Single Stage - One E 2021-09-1 n structures in Kalawewa Left / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2019-12-06 2019-12-20 2020-01-10 2020-02-09 2020-03-15 Improvements nvelope 6 Bank main canal (IWWRMP-2 /WORKS/MASL//OCBN/105) LK-MOMDE-125846-CW-RFB / Reconstruction of Muthuiya Component 2: Infrastructure Single Stage - One E 2020-11-1 nkaddu RB Canal - Muthuiyan / Post Request for Bids Open - National 365,168.54 0.00 Canceled 2019-11-15 2019-11-29 2019-12-20 2020-01-19 2020-02-23 Improvements nvelope 9 kaddu Division - Package 01 (RB/Track 03) ( IWWRMP-2/W ORKS/NPC/OCBN/200-1 ) LK-MOMDE-125994-CW-RFB / Reconstruction of Muthuiya Component 2: Infrastructure Single Stage - One E 2020-11-2 nkaddu LB Canal - Muthuiyan / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 Improvements nvelope 0 kaddu Division - (LB/Track 02 ) ( IWWRMP-2/WORKS/NPC/O CBN/200-6 ) LK-MOMDE-125995-CW-RFB / Reconstruction of Muthuiya Component 2: Infrastructure Single Stage - One E 2021-02-1 nkaddu LB Canal - Muthuiyan / Post Request for Bids Open - National 196,629.21 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 Improvements nvelope 8 kaddu Division - (LB/Track 04 ) ( IWWRMP-2/WORKS/NPC/O CBN/200-7 ) Page 1 LK-MOMDE-126158-CW-RFB / Reconstruction of Muthuiya Component 2: Infrastructure Single Stage - One E 2021-10-2 nkaddu LB Canal - Muthuiyan / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 Improvements nvelope 5 kaddu Division - (LB/Track 01 ) (IWWRMP-2/WORKS/NPC/OC BN/200-9) LK-MOMDE-126330-CW-RFB / Reconstruction of Muthuiya Component 2: Infrastructure Single Stage - One E 2021-04-2 nkaddu RB Canal - Muthuiyan / Post Request for Bids Open - National 674,157.30 0.00 Canceled 2020-04-17 2020-05-01 2020-05-22 2020-06-21 2020-07-26 Improvements nvelope 2 kaddu Division - (RB/Track 04 ) ( IWWRMP-2/WORKS/NPC/O CBN/200-10 ) LK-MOMDE-126332-CW-RFB / Reconstruction of Muthuiya Component 2: Infrastructure Single Stage - One E 2021-05-2 nkaddu LB Canal - Muthuiyan / Post Request for Bids Open - National 561,797.75 0.00 Canceled 2020-05-17 2020-05-31 2020-06-21 2020-07-21 2020-08-25 Improvements nvelope 2 kaddu Division - (LB/Track 03 ) ( IWWRMP-2/WORKS/NPC/O CBN/200-11) LK-MOMDE-126333-CW-RFB / Reconstruction of Muthuiya Component 2: Infrastructure Single Stage - One E 2021-05-2 nkaddu RB Canal - Muthuiyan / Post Request for Bids Open - National 146,067.42 0.00 Canceled 2020-05-15 2020-05-29 2020-06-19 2020-07-19 2020-08-23 Improvements nvelope 0 kaddu Division - (RB/Track 08 ) (IWWRMP-2/WORKS/NPC/OC BN/200-12) LK-MOMDE-126337-CW-RFB / Improvements of Muthuiyan Component 2: Infrastructure Single Stage - One E 2021-05-2 kaddu RB Main Canal - Muthu / Post Request for Bids Open - National 84,269.66 0.00 Canceled 2020-05-20 2020-06-03 2020-06-24 2020-07-24 2020-08-28 Improvements nvelope 5 iyankaddu Division ( IWWRM P-2/WORKS/NPC/OCBN/200-1 3) LK-MOMDE-126338-CW-RFB / Improvements of Muthuiyan Component 2: Infrastructure Single Stage - One E 2021-07-2 kaddu LB Main Canal - Muthu / Post Request for Bids Open - National 84,269.66 0.00 Canceled 2020-07-20 2020-08-03 2020-08-24 2020-09-23 2020-10-28 Improvements nvelope 5 iyankaddu Division ( IWWRM P-2/WORKS/NPC/OCBN/200-1 4) LK-MOMDE-126345-CW-RFB / Rehabilitation of Kalmadu S Component 2: Infrastructure Single Stage - One E 2020-11-2 / Post Request for Bids Open - National 1,404,494.38 0.00 Canceled 2019-11-18 2019-12-02 2019-12-23 2020-01-22 2020-02-26 cheme Headworks ( IWWRMP Improvements nvelope 2 -2/WORKS/NPC/OCBN/201-1 ) LK-MOMDE-126347-CW-RFB / Rehabilitation of channel to Component 2: Infrastructure Single Stage - One E 2022-08-2 kandawalai under RB cannel / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2021-08-23 2021-09-06 2021-09-27 2021-10-27 2021-12-01 Improvements nvelope 8 under Kalmadu Scheme ( IW WRMP-2/WORKS/NPC/OCBN/2 01-2 ) LK-MOMDE-126353-CW-RFB / Rehabilitation of channel to Component 2: Infrastructure Single Stage - One E 2021-10-2 Puliyampokkanai under RB c / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 Improvements nvelope 5 annel under Kalmadu Schem e ( IWWRMP-2/WORKS/NPC/O CBN/201-3 ) LK-MOMDE-126367-CW-RFB / Improvements of Spill & spil Component 2: Infrastructure Single Stage - One E 2021-10-2 / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 ltail under Kalmadu Scheme ( Improvements nvelope 1 IWWRMP-2/WORKS/NPC/OCB N/201-5 ) LK-MOMDE-126371-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One E 2021-02-1 kulam channel to kannagipur / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 Improvements nvelope 8 am under LB cannel ( IWWR MP-2/WORKS/NPC/OCBN/202- 1) LK-MOMDE-126376-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One E 2021-10-2 kulam channel to Akkarayan / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 Improvements nvelope 1 under LB cannel & lift irrigati on ( IWWRMP-2/WORKS/NPC/ OCBN/202-2 ) LK-MOMDE-126378-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One E 2021-10-0 / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 kulam RB cannel ( IWWRMP-2 Improvements nvelope 3 /WORKS/NPC/OCBN/202-3 ) LK-MOMDE-126387-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One E 2021-10-2 / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 kulam spill & spilltail channel Improvements nvelope 1 ( IWWRMP-2/WORKS/NPC/OC BN/202-5 ) LK-MOMDE-126390-CW-RFB / Rehabilitation of Headworks Component 2: Infrastructure Single Stage - One E 2021-10-0 / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 under Piramanthalaru Sche Improvements nvelope 3 me ( IWWRMP-2/WORKS/NPC/ OCBN/203-1 ) LK-MOMDE-126391-CW-RFB / Rehabilitation of Downstrea Component 2: Infrastructure Single Stage - One E 2020-11-2 m under Piramanthalaru Irrig / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2019-11-18 2019-12-02 2019-12-23 2020-01-22 2020-02-26 Improvements nvelope 2 ation Scheme (phase 01) (IW WRMP-2/WORKS/NPC/OCBN/2 03-2) LK-MOMDE-126392-CW-RFB / Rehabilitation of Downstrea Component 2: Infrastructure Single Stage - One E 2021-09-2 m under Piramanthalaru Irrig / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2020-09-21 2020-10-05 2020-10-26 2020-11-25 2020-12-30 Improvements nvelope 6 ation Scheme (phase 02) ( I WWRMP-2/WORKS/NPC/OCB N/203-3 ) LK-MOMDE-126396-CW-RFB / Rehabilitation of Headworks Component 2: Infrastructure Single Stage - One E 2021-10-2 / Post Request for Bids Open - National 196,629.21 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 under Kanagambikai Irrigatio Improvements nvelope 1 n Scheme (IWWRMP-2/WOR KS/NPC/OCBN/204-1) LK-MOMDE-126400-CW-RFB / Rehabilitation of Downstrea Component 2: Infrastructure Single Stage - One E 2020-11-2 / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 m under Kanagambikai Sche Improvements nvelope 6 me ( IWWRMP-2/WORKS/NPC /OCBN/204-2 ) LK-MOMDE-126410-CW-RFB / Rehabilitation of Head work Component 2: Infrastructure Single Stage - One E 2020-12-2 / Post Request for Bids Open - National 421,348.31 0.00 Canceled 2019-12-19 2020-01-02 2020-01-23 2020-02-22 2020-03-28 s of Kudamuruddy Tank ( IW Improvements nvelope 3 WRMP-2/WORKS/NPC/OCBN/2 06-1) Page 2 LK-MOMDE-126412-CW-RFB / Rehabilitation of Downstrea Component 2: Infrastructure Single Stage - One E 2021-10-0 m under Kudamuruddy Tank / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 Improvements nvelope 3 Irrigation Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/206-2) LK-MOMDE-126413-CW-RFB / Rehabilitation of Head work Component 2: Infrastructure Single Stage - One E 2020-12-2 / Post Request for Bids Open - National 1,123,595.51 0.00 Canceled 2019-12-16 2019-12-30 2020-01-20 2020-02-19 2020-03-25 s of Kariyalai Nagapaduwan Improvements nvelope 0 Tank ( IWWRMP-2/WORKS/NP C/OCBN/207-1 ) LK-MOMDE-126416-CW-RFB / Rehabilitation of LB cannel Component 2: Infrastructure Single Stage - One E 2021-10-2 / Post Request for Bids Open - National 365,168.54 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 under Kariyalai Nagapaduwa Improvements nvelope 5 n Tank (IWWRMP-2/WORKS/N PC/OCBN/207-2) LK-MOMDE-126417-CW-RFB / Rehabilitation of RB cannel Component 2: Infrastructure Single Stage - One E 2021-10-2 / Post Request for Bids Open - National 308,988.76 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 under Kariyalai Nagapaduwa Improvements nvelope 5 n Tank ( IWWRMP-2/WORKS/ NPC/OCBN/207-3 ) LK-MOMDE-126418-CW-RFB / Rehabilitation of Downstrea Component 2: Infrastructure Single Stage - One E 2021-10-0 m under Vaneri kulam Irrigati / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 Improvements nvelope 3 on Scheme ( IWWRMP-2/WOR KS/NPC/OCBN/208-1 ) LK-MOMDE-126420-CW-RFB / Rehabilitation of Head work Component 2: Infrastructure Single Stage - One E 2021-10-2 / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 s of Vaneri kulam ( IWWRMP- Improvements nvelope 1 2/WORKS/NPC/OCBN/208-2 ) LK-MOMDE-126422-CW-RFB / Rehabilitation of Dowstrea Component 2: Infrastructure Single Stage - One E 2020-11-2 m infrastructure in Periyapan / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 Improvements nvelope 6 divirichan Kulam ( IWWRMP- 2/WORKS/NPC/OCBN/209 ) LK-MOMDE-126382-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One E 2022-07-2 / Post Request for Bids Open - National 842,696.63 0.00 Canceled 2021-07-16 2021-07-30 2021-08-20 2021-09-19 2021-10-24 kulam Headworks ( IWWRMP- Improvements nvelope 1 2/WORKS/NPC/OCBN/202-4 ) LK-MOMDE-163016-CW-RFB / Reconstruction of Muthuiya Component 2: Infrastructure Single Stage - One E 2022-02-2 nkaddu LB Canal - Muthuiyan / Post Request for Bids Open - National 589,887.64 0.00 Canceled 2021-02-16 2021-03-02 2021-03-23 2021-04-22 2021-05-27 Improvements nvelope 1 kaddu Division - (LB/Track 01 ) (IWWRMP-2/WORKS/NPC/OC BN/200-9) LK-MOMDE-126361-CW-RFB / Rehabilitation of channel to Component 2: Infrastructure Single Stage - One E 2022-01-1 kalmadu nagar under LB can / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2021-01-10 2021-01-24 2021-02-14 2021-03-16 2021-04-20 Improvements nvelope 5 nel under Kalmadu Scheme ( IWWRMP-2/WORKS/NPC/OCB N/201-4 ) LK-MOMDE-163054-CW-RFB / Improvements to canal Syst Component 2: Infrastructure Single Stage - One E Pending Imp 2024-03-1 em (18km) inculuding structu IDA / 66210 Post Request for Bids Open - National 561,797.75 0.00 2021-05-20 2021-12-16 2022-01-13 2022-02-12 2022-03-19 Improvements nvelope lementation 8 res of Puluganawai-Kankaniy ar scheme (IWWRMP-2/WORK S/EPC/OCBN/303) LK-MOMDE-224661-CW-RFB / Rehabilitation of Muththuiya Component 2: Infrastructure Single Stage - One E 2022-07-1 nkaddu RB Canal - Muththuiy IDA / 66210 Post Request for Bids Open - National 365,168.54 495,097.40 Signed 2021-03-15 2021-03-15 2021-07-13 2021-09-29 2021-08-10 2021-10-29 2021-09-09 2021-11-17 2021-10-14 2021-12-18 Improvements nvelope 1 ankaddu Division - (RB/Track 03) (IWWRMP-2/WORKS/NPC/ OCBN/200-1) LK-MOMDE-125854-CW-RFB / Rehabilitation of Muthuiyan Component 2: Infrastructure Single Stage - One E 2022-11-1 kaddu RB Canal - Muthuiyank IDA / 66210 Post Request for Bids Open - National 617,977.53 630,858.08 Signed 2019-11-15 2019-11-15 2021-08-12 2021-09-29 2021-09-09 2021-10-29 2021-10-09 2021-11-17 2021-11-13 2021-12-15 Improvements nvelope 3 addu Division - (RB/Track 05) ( IWWRMP-2/WORKS/NPC/OC BN/200-3 ) LK-MOMDE-125855-CW-RFB / Rehabilitation of Muthuiyan Component 2: Infrastructure Single Stage - One E 2023-05-0 kaddu RB Canal - Muthuiyank IDA / 66210 Post Request for Bids Open - National 634,831.46 718,142.02 Signed 2020-01-20 2020-01-20 2021-08-11 2021-10-07 2021-09-08 2021-11-05 2021-10-08 2021-11-12 2021-11-12 2021-12-28 Improvements nvelope 6 addu Division - (RB/Track 01) ( IWWRMP-2/WORKS/NPC/OC BN/200-4) LK-MOMDE-125856-CW-RFB / Rehabilitation of Muthuiyan Component 2: Infrastructure Single Stage - One E 2022-08-1 kaddu RB Canal - Muthuiyank IDA / 66210 Post Request for Bids Open - National 831,460.67 842,331.64 Signed 2020-01-20 2020-01-20 2021-08-19 2021-10-07 2021-09-16 2021-11-05 2021-10-16 2021-11-12 2021-11-20 2022-02-01 Improvements nvelope 7 addu Division - (RB/Track 02) ( IWWRMP-2/WORKS/NPC/OC BN/200-5) LK-MOMDE-163045-CW-RFB / Rehabilitation of Kalmadu S Component 2: Infrastructure Single Stage - One E 2,577,071.6 2023-11-1 IDA / 66210 Post Request for Bids Open - National 1,619,101.12 Signed 2020-11-18 2020-11-18 2021-08-16 2021-10-07 2021-09-13 2021-11-11 2021-10-13 2021-11-17 2021-11-17 2021-12-23 cheme Headworks (IWWRMP- Improvements nvelope 2 7 2/WORKS/NPC/OCBN/201-1) LK-MOMDE-163038-CW-RFB / Rehabilitation of Downstrea Component 2: Infrastructure Single Stage - One E 2022-08-1 m under Piramanthalaru Irrig IDA / 66210 Post Request for Bids Open - National 139,213.48 150,556.82 Signed 2020-11-18 2020-11-18 2021-08-16 2021-10-07 2021-09-13 2021-12-05 2021-10-13 2021-11-17 2021-11-17 2021-12-27 Improvements nvelope 4 ation Scheme (phase 01) (IW WRMP-2/WORKS/NPC/OCBN/2 03-2) LK-MOMDE-124412-CW-RFB / Rehabilitation of tank bund Component 2: Infrastructure Single Stage - One E 2024-01-0 (1.5 km) including Rip Rap an IDA / 66210 Post Request for Bids Open - National 337,640.45 237,807.17 Signed 2019-12-02 2019-12-03 2021-10-04 2021-07-15 2021-11-01 2021-07-29 2021-12-01 2021-08-11 2022-01-05 2021-12-23 Improvements nvelope 5 d sluice of Mahalindawewa T ank ( IWWRMP-2/WORKS/ID/ OCBN/06) LK-MOMDE-125529-CW-RFB Request for Bids - / Improvements to Walawa R Component 2: Infrastructure Single Stage - One E Works (without pr 2,482,005.7 2024-01-3 B 41 km Main Canal from 0+ IDA / 66210 Post Request for Bids Open - National 2,302,251.70 Signed 2019-11-22 2020-01-21 2021-05-03 2021-06-27 2021-05-31 2021-08-17 2021-06-30 2021-10-27 2021-08-04 2021-12-24 Improvements nvelope equalification) SP 8 1 000 km to 17+400 km ( IWW D RMP-2/WORKS/MASL/OCBN/1 00-1) LK-MOMDE-125831-CW-RFB / Improvements to Walawa R Request for Bids - B 41 km Main Canal from 23 Component 2: Infrastructure Single Stage - One E Works (without pr 2,825,799.7 2024-03-0 IDA / 66210 Post Request for Bids Open - National 2,444,167.62 Signed 2019-11-22 2019-12-20 2021-06-02 2021-06-27 2021-06-30 2021-08-17 2021-07-30 2021-10-27 2021-09-03 2021-12-24 +400 km to 33+420 km and Improvements nvelope equalification) SP 4 1 34+640km to 40+910 km ( I D WWRMP-2/WORKS/MASL/OCB N/100-2 ) Page 3 LK-MOMDE-125832-CW-RFB Request for Bids - / Hydro Mechanical works of Component 2: Infrastructure Single Stage - One E Works (without pr 2023-03-2 IDA / 66210 Post Request for Bids Open - National 332,261.49 325,986.56 Signed 2019-11-29 2019-12-20 2021-06-09 2021-06-27 2021-07-07 2021-08-10 2021-08-06 2021-09-23 2021-09-10 2021-12-30 Walawa RB Main Canal ( IWW Improvements nvelope equalification) SP 4 RMP-2/WORKS/MASL/OCBN/1 D 00-3 ) LK-MOMDE-125833-CW-RFB Request for Bids - / Ecological Improvements an Component 2: Infrastructure Single Stage - One E Works (without pr 2023-03-2 d Marking Reservation along IDA / 66210 Post Request for Bids Open - National 422,232.84 376,090.19 Signed 2019-11-29 2019-12-17 2021-06-09 2021-06-27 2021-07-07 2021-08-10 2021-08-06 2021-09-08 2021-09-10 2021-12-06 Improvements nvelope equalification) SP 4 Walawa RB Main Canal ( IWW D RMP-2/WORKS/MASL/OCBN/1 00-4 ) LK-MOMDE-125835-CW-RFB National Procure / Installation of Automated G ment Document - eodetic Survey Systems in K Component 2: Infrastructure Single Stage - Two E 2022-11-2 IDA / 66210 Prior Request for Bids Open - National 2 Envelope proce 1,623,595.51 0.00 Canceled 2019-11-19 2021-07-09 2021-08-06 2021-11-23 otmale & Randenigala Dams Improvements nvelope 3 ss (Non Bank-SPD for Dam Movement Monitorin ) g ( IWWRMP-2/WORKS/MASL/ /OCBN/102 ) National Procure LK-MOMDE-125836-CW-RFB ment Document - / Supply and Installation of G Component 2: Infrastructure Single Stage - Two E 2022-12-0 IDA / 66210 Prior Request for Bids Open - National 2 Envelope proce 2,000,000.00 0.00 Canceled 2019-12-03 2021-07-23 2021-08-20 2021-12-07 antry Crane for Polgolla Barr Improvements nvelope 7 ss (Non Bank-SPD age ( IWWRMP-2/WORKS/MA ) SL//OCBN/103 ) National Procure LK-MOMDE-125838-CW-RFB ment Document - / Supply and Installation of G Component 2: Infrastructure Single Stage - Two E 2022-11-2 IDA / 66210 Prior Request for Bids Open - National 2 Envelope proce 1,185,393.26 0.00 Canceled 2019-12-03 2021-07-12 2021-08-09 2021-11-26 antry Crane for Udawalawe D Improvements nvelope 6 ss (Non Bank-SPD am ( IWWRMP-2/WORKS/MAS ) L//OCBN/104 ) LK-MOMDE-163036-CW-RFB National Procure / Repairs to gates of irrigatio ment Document - Component 2: Infrastructure Single Stage - One E 2023-04-2 n structures in Kalawewa Left IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 449,438.20 427,739.47 Signed 2020-07-06 2020-07-16 2021-07-16 2021-09-13 2021-08-13 2021-10-12 2021-09-12 2021-12-13 2021-10-17 2022-02-11 Improvements nvelope 0 Bank main canal (IWWRMP-2/ ss (Non Bank-SPD WORKS/MASL//OCBN/105) ) National Procure LK-MOMDE-163046-CW-RFB ment Document - / Rehabilitation of Downstrea Component 2: Infrastructure Single Stage - One E 2022-10-2 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 224,719.10 225,969.75 Signed 2020-09-21 2020-09-21 2021-07-19 2021-10-07 2021-08-16 2021-11-05 2021-09-15 2021-11-17 2021-10-20 2021-12-27 m under Kanagambikai Sche Improvements nvelope 0 ss (Non Bank-SPD me (IWWRMP-2/WORKS/NPC/ ) OCBN/204) LK-MOMDE-125488-CW-RFB Request for Bids - / Rehabilitation of Haththota Component 2: Infrastructure Single Stage - One E Works (without pr 2023-03-0 IDA / 66210 Post Request for Bids Open - National 341,337.08 257,360.61 Terminated 2019-12-23 2019-12-26 2021-12-03 2021-07-15 2021-12-31 2021-07-29 2022-01-30 2021-09-13 2022-03-06 2021-11-10 Anicut Scheme (1st to 5th K Improvements nvelope equalification) SP 6 m canal) ( IWWRMP-2/WORK D S/ID/OCBN/16-1) LK-MOMDE-234772-CW-RFB Request for Bids - / Rehabilititation of Haththot Component 2: Infrastructure Single Stage - One E Works (without pr 2023-01-2 IDA / 66210 Post Request for Bids Open - National 314,971.91 122,969.66 Terminated 2021-07-01 2021-07-01 2021-10-28 2021-07-15 2021-11-25 2021-07-29 2021-12-25 2021-09-07 2022-01-29 2021-11-10 a Anicut Scheme (6th to 10th Improvements nvelope equalification) SP 9 Km canal) (IWWRMP-2/WORK D S/ID/OCBN/16-2) National Procure LK-MOMDE-241092-CW-RFB ment Document - / Supply installation of Gantr Component 2: Infrastructure Single Stage - Two E Under Imple 2022-11-2 IDA / 66210 Post Request for Bids Open - National 2 Envelope proce 2,000,000.00 0.00 2021-06-27 2021-06-28 2021-07-16 2021-07-11 2021-08-27 2021-08-24 2021-10-24 2022-01-25 2021-11-28 y Crane mechanism for Polgo Improvements nvelope mentation 8 ss (Non Bank-SPD lla Barrage (IWWRMP-2/WOR ) KS/MASL/OCBN/103) LK-MOMDE-241083-CW-RFB National Procure / Installation of Automated G ment Document - eodetic Survey Systems in K Component 2: Infrastructure Single Stage - Two E Under Imple 2022-11-2 IDA / 66210 Post Request for Bids Open - National 2 Envelope proce 1,623,595.51 0.00 2021-06-25 2021-06-28 2021-07-15 2021-07-11 2021-08-26 2021-09-03 2021-10-23 2022-03-29 2021-11-27 otmale & Randenigala Dams Improvements nvelope mentation 7 ss (Non Bank-SPD for Dam Movement Monitorin ) g (IWWRMP-2/WORKS/MASL/ OCBN/102) National Procure LK-MOMDE-241095-CW-RFB ment Document - / Supply and Installation of G Component 2: Infrastructure Single Stage - Two E Under Imple 2022-11-2 IDA / 66210 Post Request for Bids Open - National 2 Envelope proce 1,185,393.26 0.00 2021-06-25 2021-06-27 2021-07-15 2021-07-11 2021-08-26 2021-08-24 2021-10-23 2022-01-25 2021-11-27 antry Crane for Udawalawe D Improvements nvelope mentation 7 ss (Non Bank-SPD am (IWWRMP-2/WORKS/MAS ) L/OCBN/104) National Procure LK-MOMDE-123597-CW-RFB ment Document - / Improvement to Bathalagod Component 2: Infrastructure Single Stage - One E 2022-07-2 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 179,606.74 0.00 Canceled 2021-06-27 2021-07-20 2021-08-17 2021-09-16 2021-10-21 a main CHL road from 0+000 Improvements nvelope 8 ss (Non Bank-SPD to 2+100 km ( IWWRMP-2/W ) ORKS/ID/OCBN/01-4 ) LK-MOMDE-123572-CW-RFB National Procure / Improvements to Bathalago ment Document - Component 2: Infrastructure Single Stage - One E 2022-10-1 da Anicut & Anicut inlet CHL IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 411,123.60 353,143.92 Terminated 2019-11-15 2019-11-15 2021-07-08 2021-07-15 2021-08-07 2021-07-29 2021-09-06 2021-10-09 2021-10-11 2021-11-10 Improvements nvelope 1 road from CH0 to 3+775 (IW ss (Non Bank-SPD WRMP-2/WORKS/ID/OCBN/01- ) 1) National Procure LK-MOMDE-123606-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E Under Imple 2023-12-2 / Rehabilitation of Dewahuwa IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 568,854.87 0.00 2019-11-19 2022-03-28 2021-09-22 2022-04-21 2021-10-20 2022-06-03 2021-11-19 2021-12-24 Improvements nvelope mentation 4 Scheme ( IWWRMP-2/WORKS ss (Non Bank-SPD /ID/OCBN/03 ) ) National Procure LK-MOMDE-125496-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E 2022-11-1 / Rehabilitation of Arawatta t IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 230,492.13 213,054.90 Signed 2019-12-27 2021-08-20 2021-08-09 2021-08-31 2021-09-06 2021-10-12 2021-10-06 2021-10-21 2021-11-10 2022-01-18 Improvements nvelope 0 ank bund ( IWWRMP-2/WORK ss (Non Bank-SPD S/ID/OCBN/18) ) National Procure LK-MOMDE-123594-CW-RFB ment Document - / Improvement to Bathalagod Component 2: Infrastructure Single Stage - One E 2022-10-2 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 190,769.66 157,638.22 Terminated 2019-11-15 2019-11-18 2021-10-21 2021-08-10 2021-11-18 2021-07-29 2021-12-18 2021-08-31 2022-01-22 2021-11-10 a main bund road ch from 0 t Improvements nvelope 9 ss (Non Bank-SPD o 1+525 ( IWWRMP-2/WORKS ) /ID/OCBN/01-2 ) LK-MOMDE-123600-CW-RFB Request for Bids - / Rehabilitation of D1, D2, D4 Component 2: Infrastructure Single Stage - One E Works (without pr 2022-10-2 IDA / 66210 Post Request for Bids Open - National 321,657.30 0.00 Canceled 2019-11-19 2021-08-20 2021-07-26 2021-08-31 2021-08-23 2021-09-22 2021-10-27 canals in Bathalagoda Schem Improvements nvelope equalification) SP 7 e ( IWWRMP-2/WORKS/ID/OC D BN/02-1) National Procure LK-MOMDE-123602-CW-RFB ment Document - / Rehabilitation of D5, D7, D7 Component 2: Infrastructure Single Stage - One E 2022-11-0 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 231,629.21 0.00 Canceled 2019-11-19 2021-08-20 2021-07-29 2021-08-31 2021-08-28 2021-09-27 2021-11-01 RB canals in Bathalagoda Sc Improvements nvelope 1 ss (Non Bank-SPD heme ( IWWRMP-2/WORKS/ID ) /OCBN/02-2 ) LK-MOMDE-225755-CW-RFB National Procure / Improvement to Bund (1 km ment Document - ), rip rap Protection, Instrume Component 2: Infrastructure Single Stage - One E 2024-07-2 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 3,132,932.58 0.00 Canceled 2021-06-30 2022-04-26 2022-05-26 2022-06-25 2022-07-30 ntation and Toe filter & drain Improvements nvelope 9 ss (Non Bank-SPD of Senanayaka Samudraya R ) eservoir (IWWRMP-2/WORKS/ ID/OCBN/20) LK-MOMDE-302734-CW-RFB National Procure / Providing rip-rap protection ment Document - Component 2: Infrastructure Single Stage - One E Under Imple 2024-12-0 to Senanayaka Samudraya B IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 1,660,000.00 0.00 2022-07-18 2022-07-22 2022-08-31 2022-08-14 2022-09-30 2022-09-06 2022-10-30 2022-12-04 Improvements nvelope mentation 3 und & Improvement to Bund ss (Non Bank-SPD Road (IWWRMP-2/WORKS/ID/ ) OCBN/20-1) Page 4 National Procure LK-MOMDE-124591-CW-RFB ment Document - / Rehabilitation of Tank Bund, Component 2: Infrastructure Single Stage - One E Pending Imp 2022-12-2 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 205,500.00 0.00 2019-11-14 2021-09-20 2021-10-18 2021-11-17 2021-12-22 Sluice and Spillway in Nagad Improvements nvelope lementation 2 ss (Non Bank-SPD eepa tank( IWWRMP-2/WORK ) S/ID/OCBN/07) LK-MOMDE-124595-CW-RFB National Procure / Improvements to Akathimur ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2022-11-2 ippu tank bund from 0+000 t IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 865,000.00 0.00 2019-12-02 2021-08-23 2021-09-20 2021-10-20 2021-11-24 Improvements nvelope lementation 4 o 6+450 of Akathimurippu Sc ss (Non Bank-SPD heme ( IWWRMP-2/WORKS/ID ) /OCBN/11) National Procure LK-MOMDE-124402-CW-RFB ment Document - / Improvements to Huruluwe Component 2: Infrastructure Single Stage - One E Pending Imp 2024-07-0 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 565,000.00 0.00 2022-08-18 2022-10-01 2022-10-31 2022-12-10 2023-01-14 wa Right Bank Main Canal (R Improvements nvelope lementation 7 ss (Non Bank-SPD B) (IWWRMP-2/WORKS/ID/OC ) BN/04-2) LK-MOMDE-125494-CW-RFB National Procure / Improvements to Muhathan ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-01-0 kulam Main Canal from 0+00 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 367,000.00 0.00 2022-09-15 2022-10-06 2022-11-05 2022-12-05 2023-01-09 Improvements nvelope lementation 9 0 to 4+400 of Muhathankula ss (Non Bank-SPD m Scheme( IWWRMP-2/WOR ) KS/ID/OCBN/17) LK-MOMDE-305818-CW-RFB National Procure / Improvements to Bathalago ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2025-06-2 da Anicut & Anicut inlet CHL IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 204,000.00 0.00 2024-01-31 2024-03-15 2024-04-14 2024-05-24 2024-06-28 Improvements nvelope lementation 8 road from CH0 to 3+775 (Ret ss (Non Bank-SPD ender) (IWWRMP-2/WORKS/I ) D/OCBN/01-1) LK-MOMDE-305823-CW-RFB National Procure / Improvement to Bathalagod ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2025-06-2 a main bund road ch from 0 t IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 95,000.00 0.00 2024-01-31 2024-03-15 2024-04-14 2024-05-24 2024-06-28 Improvements nvelope lementation 8 o 1+525 (Retender)(IWWRMP ss (Non Bank-SPD -2/WORKS/ID/OCBN/01-2) ) National Procure LK-MOMDE-302519-CW-RFB ment Document - / Rehabilitation of D1, D2, D4 Component 2: Infrastructure Single Stage - One E Pending Imp 2024-02-2 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 188,000.00 0.00 2022-09-26 2022-11-09 2022-12-09 2023-01-18 2023-02-22 canals in Bathalagoda Schem Improvements nvelope lementation 2 ss (Non Bank-SPD e (Retender) (IWWRMP-2/WO ) RKS/ID/OCBN/02-1) LK-MOMDE-302531-CW-RFB National Procure / Rehabilitation of D5, D7 and ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-02-2 D7 RB canals in Bathalagoda IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 134,000.00 0.00 2022-09-26 2022-11-09 2022-12-09 2023-01-18 2023-02-22 Improvements nvelope lementation 2 Scheme (Retender) (IWWRMP ss (Non Bank-SPD -2/WORKS/ID/OCBN/02-2) ) National Procure LK-MOMDE-124090-CW-RFB ment Document - / Improvements to LB Main C Component 2: Infrastructure Single Stage - One E Pending Imp 2024-08-1 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 360,000.00 0.00 2022-09-30 2022-11-13 2022-12-13 2023-01-22 2023-02-26 anal of Huruluwewa Major Sc Improvements nvelope lementation 9 ss (Non Bank-SPD heme ( IWWRMP-2/WORKS/ID ) /OCBN/04-1) National Procure LK-MOMDE-124408-CW-RFB ment Document - / Improvements to (22 km) B Component 2: Infrastructure Single Stage - One E Pending Imp 2025-05-2 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 815,235.96 0.00 2023-07-07 2023-08-20 2023-09-19 2023-10-29 2023-12-03 ranch canal and structures of Improvements nvelope lementation 6 ss (Non Bank-SPD Illukuchenal Unit ( IWWRMP-2 ) /WORKS/ID/OCBN/05 ) National Procure LK-MOMDE-124592-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-12-1 / Rehabilititation of Wadamu IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 369,932.58 0.00 2023-07-17 2023-08-30 2023-09-29 2023-11-08 2023-12-13 Improvements nvelope lementation 2 nai Tank ( IWWRMP-2/WORKS ss (Non Bank-SPD /ID/OCBN/08 ) ) National Procure LK-MOMDE-124593-CW-RFB ment Document - / Rehabilitation of Vahanery Component 2: Infrastructure Single Stage - One E Pending Imp 2025-01-3 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 551,604.19 0.00 2023-09-04 2023-10-18 2023-11-17 2023-12-27 2024-01-31 Tank bund from Stn 0+000 t Improvements nvelope lementation 0 ss (Non Bank-SPD o Stn 2+100 ( IWWRMP-2/WO ) RKS/ID/OCBN/09-1 ) National Procure LK-MOMDE-124594-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2025-03-2 / Rehabilitation of HaliEla Tan IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 422,191.01 0.00 2023-10-25 2023-12-08 2024-01-07 2024-02-16 2024-03-22 Improvements nvelope lementation 2 k ( IWWRMP-2/WORKS/ID/OC ss (Non Bank-SPD BN/10) ) National Procure LK-MOMDE-124596-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2025-03-2 / Rehabilitation of Pavatkula IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 874,719.10 0.00 2023-10-31 2023-12-14 2024-01-13 2024-02-22 2024-03-28 Improvements nvelope lementation 8 m Tank ( IWWRMP-2/WORKS/ ss (Non Bank-SPD ID/OCBN/12 ) ) National Procure LK-MOMDE-124655-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2025-04-1 / Rehabilitation of Peramadu IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 595,505.62 0.00 2023-11-13 2023-12-27 2024-01-26 2024-03-06 2024-04-10 Improvements nvelope lementation 0 Tank ( IWWRMP-2/WORKS/ID/ ss (Non Bank-SPD OCBN/14) ) National Procure LK-MOMDE-124642-CW-RFB ment Document - / Rehabilitation of Mavilaru L Component 2: Infrastructure Single Stage - One E Pending Imp 2025-01-1 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 614,000.00 0.00 2023-08-22 2023-10-05 2023-11-04 2023-12-14 2024-01-18 B Bund from 0+130 to 2+73 Improvements nvelope lementation 7 ss (Non Bank-SPD 0 ( IWWRMP-2/WORKS/ID/OC ) BN/13-1) LK-MOMDE-124649-CW-RFB / Improvements to Mavilaru Component 2: Infrastructure Single Stage - One E 2023-03-0 IDA / 66210 Post Request for Bids Open - National 412,247.19 0.00 Canceled 2020-02-06 2021-12-01 2021-12-29 2022-01-28 2022-03-04 Headworks (RB) ( IWWRMP-2/ Improvements nvelope 4 WORKS/ID/OCBN/13-2 ) LK-MOMDE-124671-CW-RFB / Improvements of Access ro Component 2: Infrastructure Single Stage - One E 2023-04-1 ad of Vahanery tank form Stn IDA / 66210 Post Request for Bids Open - National 775,000.00 0.00 Canceled 2019-12-27 2022-01-11 2022-02-08 2022-03-10 2022-04-14 Improvements nvelope 4 0+000 to 7+683 (Santhiyar r oad) ( IWWRMP-2/WORKS/ID/ OCBN/09-2 ) National Procure LK-MOMDE-123596-CW-RFB ment Document - / Improvement to Bathalagod Component 2: Infrastructure Single Stage - One E 2022-10-1 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 103,988.76 0.00 Canceled 2019-11-15 2021-07-08 2021-08-07 2021-09-06 2021-10-11 a Anicut (Mechanical works) ( Improvements nvelope 1 ss (Non Bank-SPD IWWRMP-2/WORKS/ID/OCBN/ ) 01-3 ) LK-MOMDE-124660-CW-RFB National Procure / Improvements to RB Main c ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-12-2 anal from 0+000Km to 1+46 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 676,471.91 0.00 2023-07-31 2023-09-13 2023-10-13 2023-11-22 2023-12-27 Improvements nvelope lementation 6 5Km of Viyadikulam Scheme ss (Non Bank-SPD ( IWWRMP-2/WORKS/ID/OCB ) N/15) LK-MOMDE-305824-CW-RFB National Procure / Improvements to Canal (1st ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-04-0 - 5th km) system including st IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 341,000.00 0.00 2022-11-11 2022-12-25 2023-01-24 2023-03-05 2023-04-09 Improvements nvelope lementation 8 ructures of Haththota Anicut ss (Non Bank-SPD Scheme (Retender) (IWWRMP ) -2/WORKS/ID/OCBN/16-1) Page 5 LK-MOMDE-305825-CW-RFB National Procure / Improvements to Canal (6th ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-06-0 - 10th km) system including IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 279,000.00 0.00 2023-01-11 2023-02-24 2023-03-26 2023-05-05 2023-06-09 Improvements nvelope lementation 8 structures of Haththota Anicu ss (Non Bank-SPD t Scheme (Retender) (IWWR ) MP-2/WORKS/ID/OCBN/16-2) National Procure LK-MOMDE-125506-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-12-2 / Rehabilitation of Waduwaw IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 352,808.99 0.00 2023-07-25 2023-09-07 2023-10-07 2023-11-16 2023-12-21 Improvements nvelope lementation 0 ala Scheme ( IWWRMP-2/WO ss (Non Bank-SPD RKS/ID/OCBN/19 ) ) National Procure LK-MOMDE-302735-CW-RFB ment Document - / Instrumentation facility to S Component 2: Infrastructure Single Stage - One E Pending Imp 2026-02-0 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 355,000.00 0.00 2023-09-14 2023-10-28 2023-11-27 2024-01-06 2024-02-10 enanayake Samudra bund (I Improvements nvelope lementation 9 ss (Non Bank-SPD WWRMP-2/WORKS/ID/OCBN/2 ) 0-2) LK-MOMDE-163031-CW-RFB National Procure / Improvement of Spillway Ta ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2025-01-2 il Canal and removing rock b IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 842,696.63 0.00 2023-08-31 2023-10-14 2023-11-13 2023-12-23 2024-01-27 Improvements nvelope lementation 6 oulders in Kotmale Dam ( IW ss (Non Bank-SPD WRMP-2/WORKS/MASL/OCBN ) /101 ) LK-MOMDE-163066-CW-RFB National Procure / Immediate improvement of ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2025-04-0 upper phephary of Polgolla D IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 786,516.85 0.00 2023-11-06 2023-12-20 2024-01-19 2024-02-28 2024-04-03 Improvements nvelope lementation 3 am - Phase I (IWWRMP-2/WO ss (Non Bank-SPD RKS/MASL/OCBN/106-1) ) LK-MOMDE-125851-CW-RFB National Procure / Rehabilitation of Muthuiyan ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-11-2 kaddu RB Canal - Muthuiyank IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 325,842.70 0.00 2023-06-26 2023-08-09 2023-09-08 2023-10-18 2023-11-22 Improvements nvelope lementation 1 addu Division - (RB/Track 07) ss (Non Bank-SPD ( IWWRMP-2/WORKS/NPC/OC ) BN/200-2 ) LK-MOMDE-126155-CW-RFB National Procure / Rehabilitation of Muththuiya ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-10-2 nkaddu RB Canal - Muththuiy IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 464,831.46 0.00 2023-06-01 2023-07-15 2023-08-14 2023-09-23 2023-10-28 Improvements nvelope lementation 7 ankaddu Division - (RB/Track ss (Non Bank-SPD 06) (IWWRMP-2/WORKS/NPC/ ) OCBN/200-6) LK-MOMDE-163023-CW-RFB National Procure / Rehabilitation of Muthuiyan ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2025-02-2 kaddu LB Canal - Muthuiyank IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 589,887.64 0.00 2023-10-02 2023-11-15 2023-12-15 2024-01-24 2024-02-28 Improvements nvelope lementation 7 addu Division - (LB/Track 03) ss (Non Bank-SPD ( IWWRMP-2/WORKS/NPC/OC ) BN/200-7) National Procure LK-MOMDE-163041-CW-RFB ment Document - / Improvements of Spill & spil Component 2: Infrastructure Single Stage - One E Pending Imp 2025-01-0 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 291,011.24 0.00 2023-08-08 2023-09-21 2023-10-21 2023-11-30 2024-01-04 l tail under Kalmadu Scheme Improvements nvelope lementation 3 ss (Non Bank-SPD ( IWWRMP-2/WORKS/NPC/OC ) BN/201-2 ) National Procure LK-MOMDE-228195-CW-RFB ment Document - / Rehabilitation on Akkarayan Component 2: Infrastructure Single Stage - One E Pending Imp 2025-05-3 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 842,696.63 0.00 2023-07-11 2023-08-24 2023-09-23 2023-11-02 2023-12-07 kulam Headworks (IWWRMP- Improvements nvelope lementation 0 ss (Non Bank-SPD 2/WORKS/NPC/OCBN/202 ) National Procure LK-MOMDE-163026-CW-RFB ment Document - / Rehabilitation of Headworks Component 2: Infrastructure Single Stage - One E Pending Imp 2025-01-0 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 327,865.17 0.00 2023-08-08 2023-09-21 2023-10-21 2023-11-30 2024-01-04 under Piramanthalaru Schem Improvements nvelope lementation 3 ss (Non Bank-SPD e (IWWRMP-2/WORKS/NPC/O ) CBN/203-1) National Procure LK-MOMDE-126401-CW-RFB ment Document - / Rehabilitation of Head work Component 2: Infrastructure Single Stage - One E Pending Imp 2025-04-1 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 2023-11-20 2024-01-03 2024-02-02 2024-03-13 2024-04-17 s in Periyamdu Tank ( IWWR Improvements nvelope lementation 7 ss (Non Bank-SPD MP-2/WORKS/NPC/OCBN/205 ) ) National Procure LK-MOMDE-163044-CW-RFB ment Document - / Rehabilitation of Head work Component 2: Infrastructure Single Stage - One E Pending Imp 2025-01-1 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 510,000.00 0.00 2023-08-24 2023-10-07 2023-11-06 2023-12-16 2024-01-20 s of Kudamuruddy Tank ( IW Improvements nvelope lementation 9 ss (Non Bank-SPD WRMP-2/WORKS/NPC/OCBN/2 ) 06) LK-MOMDE-163059-CW-RFB National Procure / Rehabilitation of Head work ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-08-2 s and Downstream infrastruc IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 253,000.00 0.00 2023-03-29 2023-05-12 2023-06-11 2023-07-21 2023-08-25 Improvements nvelope lementation 5 ture of Kariyalai Nagapaduwa ss (Non Bank-SPD n Tank (IWWRMP-2/WORKS/N ) PC/OCBN/207) National Procure LK-MOMDE-225762-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-07-1 / Rehabilitation of Maruthank IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 417,000.00 0.00 2023-02-20 2023-04-05 2023-05-05 2023-06-14 2023-07-19 Improvements nvelope lementation 9 ulam (IWWRMP-2/WORKS/NP ss (Non Bank-SPD C/OCBN/209) ) National Procure LK-MOMDE-317179-CW-RFB ment Document - / Rehabilitation of Welimarut Component 2: Infrastructure Single Stage - One E Pending Imp 2024-09-1 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 167,000.00 0.00 2023-04-19 2023-06-02 2023-07-02 2023-08-11 2023-09-15 hamadu Tank Headworks (IW Improvements nvelope lementation 4 ss (Non Bank-SPD WRMP-2/WORKS/NPC/OCBN/2 ) 10) LK-MOMDE-163051-CW-RFB National Procure / Rehablitation of tank Bund ( ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-12-1 0.8km) including Rip Rap, Spi IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 250,000.00 0.00 2023-01-25 2023-03-10 2023-04-09 2023-05-19 2023-06-23 Improvements nvelope lementation 4 ll and both sluice to Meiyank ss (Non Bank-SPD al Tank (IWWRMP-2/WORKS/E ) PC/OCBN/300) National Procure LK-MOMDE-163052-CW-RFB ment Document - / Rehabilitation of Chadayant Component 2: Infrastructure Single Stage - One E Pending Imp 2024-12-0 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 112,000.00 0.00 2023-01-20 2023-03-05 2023-04-04 2023-05-14 2023-06-18 halawa Tank (IWWRMP-2/WO Improvements nvelope lementation 9 ss (Non Bank-SPD RKS/EPC/OCBN/301) ) National Procure LK-MOMDE-163053-CW-RFB ment Document - / Rehabilitation of Saliyapura Component 2: Infrastructure Single Stage - One E Pending Imp 2024-08-0 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 65,000.00 0.00 2023-03-13 2023-04-26 2023-05-26 2023-07-05 2023-08-09 anicut of Paravipanchan Sche Improvements nvelope lementation 8 ss (Non Bank-SPD me (IWWRMP-2/WORKS/EPC/ ) OCBN/302) LK-MOMDE-163055-CW-RFB National Procure / Improvements of tank bund ment Document - (1.5km), including Rip Rap an Component 2: Infrastructure Single Stage - One E Pending Imp 2024-11-3 IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 168,539.33 0.00 2023-07-05 2023-08-18 2023-09-17 2023-10-27 2023-12-01 d Sluice Structure to Pulugan Improvements nvelope lementation 0 ss (Non Bank-SPD awai-Kankaniyar scheme (IW ) WRMP-2/WORKS/EPC/OCBN/3 05) National Procure LK-MOMDE-163064-CW-RFB ment Document - Component 2: Infrastructure Single Stage - One E Pending Imp 2024-07-0 / Rehabilitation of Nithakaikul IDA / 66210 Post Request for Bids Open - National 1 Envelope proce 416,000.00 0.00 2023-02-06 2023-03-22 2023-04-21 2023-05-31 2023-07-05 Improvements nvelope lementation 4 am (IWWRMP-2/WORKS/NPC/ ss (Non Bank-SPD OCBN/208) ) Page 6 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-117380-GO-DIR / Procurement of Relevant Dat a and Maps for preparation o Component 1: Watershed an / Post Direct Selection Direct 15,151.52 0.00 Canceled 2019-08-05 2019-08-13 2019-09-17 2020-01-15 f GIS maps including specific d Water Resources Planning geographic locations/sub-wat ersheds (IWWRMP/PP/GOODS /01) LK-MOMDE-123586-GO-RFB Component 2: Infrastructure Single Stage - One E / Procurement of Crew Cabs ( / Post Request for Bids Open - National 475,000.00 0.00 Canceled 2020-06-09 2020-06-23 2020-08-04 2020-09-03 2020-10-08 2021-04-06 Improvements nvelope IWWRMP-2/GOODS/PMU/OCB N/3 ) LK-MOMDE-124216-GO-DIR / Purchasing of GIS Maps and Component 1: Watershed an / Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-01-27 2020-02-10 2020-03-21 2020-09-17 Satellite Images ( IWWRMP-1/ d Water Resources Planning GOODS/PMU/OCBN/6 ) LK-MOMDE-123574-GO-RFB / Procurement of clay groutin Component 2: Infrastructure Single Stage - One E IDA / 66210 Post Request for Bids Open - National 675,000.00 543,120.43 Signed 2022-01-24 2022-02-24 2022-02-07 2022-03-07 2022-03-07 2022-04-06 2022-04-06 2022-05-17 2022-05-11 2022-07-04 2023-03-07 g machines ( IWWRMP-2/GO Improvements nvelope ODS/PMU/OCBN/1 ) LK-MOMDE-273765-GO-RFQ Component 2: Infrastructure Request for Quota Single Stage - One E / Procurement and Supply of IDA / 66210 Post Limited 13,250.00 10,217.89 Signed 2022-02-16 2022-03-16 2022-04-16 2022-04-11 2022-05-16 Improvements tions nvelope Laptops for PMU LK-MOMDE-273774-GO-RFQ / Procurement of Multifunctio Component 2: Infrastructure Request for Quota Single Stage - One E IDA / 66210 Post Limited 13,250.00 10,300.28 Signed 2022-03-01 2022-03-16 2022-05-13 2022-04-29 2022-06-12 nal Color Printer with binding Improvements tions nvelope Facility and Scanner for PMU LK-MOMDE-273776-GO-RFQ Component 2: Infrastructure Request for Quota Single Stage - One E / Procurement and Supply of IDA / 66210 Post Limited 5,300.00 2,000.00 Signed 2022-03-01 2022-05-05 2022-05-13 2022-05-30 2022-06-12 Improvements tions nvelope Server UPS for PMU LK-MOMDE-123581-GO-RFB Component 2: Infrastructure Single Stage - One E Pending Impl / Procurement of water weed IDA / 66210 Post Request for Bids Open - National 845,000.00 0.00 2022-10-21 2022-11-18 2022-12-16 2023-01-15 2023-02-19 2023-12-16 Improvements nvelope ementation s removers ( IWWRMP-2/GOO DS/PMU/OCBN/2 ) LK-MOMDE-124212-GO-RFB / Procurement of computer a Component 1: Watershed an Single Stage - One E Pending Impl IDA / 66210 Post Request for Bids Open - National 106,000.00 0.00 2023-01-23 2023-02-06 2023-03-06 2023-04-05 2023-05-10 2023-09-07 nd accessories-1 ( IWWRMP-2 d Water Resources Planning nvelope ementation /GOODS/PMU/OCBN/4 ) LK-MOMDE-124214-GO-RFB Component 2: Infrastructure Single Stage - One E Pending Impl / Procurement of Photocopy IDA / 66210 Post Request for Bids Open - National 30,000.00 0.00 2023-08-25 2023-09-08 2023-10-06 2023-11-05 2023-12-10 2024-04-08 Improvements nvelope ementation Machines-1 ( IWWRMP-2/GOO DS/PMU/OCBN/5 ) LK-MOMDE-303520-GO-RFB Component 2: Infrastructure Single Stage - One E Pending Impl / Procurement of Reservoir S IDA / 66210 Post Request for Bids Open - National 417,000.00 0.00 2022-10-14 2022-10-28 2022-11-27 2022-12-27 2023-01-31 2024-01-31 Improvements nvelope ementation pillways Bridge under side In spection Machine LK-MOMDE-284455-GO-RFB / Procurement and Supply of Component 2: Infrastructure Single Stage - One E Pending Impl IDA / 66210 Post Request for Bids Open - National 285,400.00 0.00 2023-08-01 2023-08-06 2023-09-05 2023-10-05 2023-11-09 2024-05-07 High Pressure water pumps (I Improvements nvelope ementation WWRMP-2/GOODS/PMU/OCB N/13) LK-MOMDE-282437-GO-DIR / Procurement and Supply of s pare parts for repairing and Component 1: Watershed an Direct - Internation Pending Impl IDA / 66190 Post Direct Selection 385,740.00 0.00 2022-10-07 2022-10-21 2022-11-25 2023-05-24 maintenance of automated in d Water Resources Planning al ementation struments of HMIS stations (I WWRMP-1/GOODS/PMU/OCBI /19) LK-MOMDE-317333-GO-RFQ Component 2: Infrastructure Request for Quota Single Stage - One E Pending Impl / Procurement and Supply of IDA / 66210 Post Limited 42,000.00 0.00 2022-11-01 2023-01-03 2023-02-02 Improvements tions nvelope ementation Computer and Accessories fo r ID LK-MOMDE-302803-GO-RFQ / Procurement and Supply of spare parts for repairing and Component 1: Watershed an Request for Quota Single Stage - One E Pending Impl IDA / 66190 Post Open - National 2,000.00 0.00 2022-12-01 2023-02-22 2023-08-21 maintenance of automated in d Water Resources Planning tions nvelope ementation struments of HMIS stations of MASL (National) (IWWRMP-1/ GOODS/PMU/NS/22) LK-MOMDE-124219-GO-RFB Component 1: Watershed an Single Stage - One E Pending Impl / Procurement of Office Equip IDA / 66210 Post Request for Bids Open - National 30,000.00 0.00 2023-08-25 2023-09-14 2023-10-12 2023-11-11 2023-12-16 2024-04-14 d Water Resources Planning nvelope ementation ments-1 ( IWWRMP-2/GOODS /PMU/OCBN/7 ) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-282432-NC-RFQ / Hiring Service provider for M Component 1: Watershed an Request for Quota Single Stage - One E aintenance and Service for H IDA / 66190 Post Limited 14,000.00 0.00 Canceled 2022-03-14 2022-05-16 2025-05-15 d Water Resources Planning tions nvelope MIS Server & Related Equipm ent at Data Center of ID (IW WRMP-1/NC/PMU/S/1) LK-MOMDE-302793-NC-RFQ / Hiring Service provider for M Component 1: Watershed an Request for Quota Single Stage - One E Pending Impl aintenance and Service for H IDA / 66190 Post Open - National 7,400.00 0.00 2022-10-24 2023-01-27 2026-01-26 d Water Resources Planning tions nvelope ementation MIS Server & Related Equipm ent at Data Center of ID (IW WRMP-1/NC/PMU/S/1) LK-MOMDE-302794-NC-RFQ / Geotechnical Investigations f Component 1: Watershed an Request for Quota Single Stage - One E Pending Impl or proposed locations of eart IDA / 66190 Post Limited 2,600.00 0.00 2022-11-07 2023-02-08 2023-08-07 d Water Resources Planning tions nvelope ementation h retaining structures around Polgolla reservoir periphery (I WWRMP-1/NC/PMU/S/2) Page 7 LK-MOMDE-302797-NC-RFQ / Re-establishment of boundari Component 1: Watershed an Request for Quota Single Stage - One E Pending Impl es in acquired lands by MASL IDA / 66190 Post Limited 6,350.00 0.00 2022-10-25 2023-01-26 2023-07-25 d Water Resources Planning tions nvelope ementation for the purposes of Polgolla R eservoir (IWWRMP-1/NC/PMU/ S/3) LK-MOMDE-157171-NC-RFQ / Component 4: Project Manag Request for Quota Single Stage - One E Pending Impl Conducting Asset verification IDA / 66210 Post Limited 2,808.99 0.00 2023-07-18 2023-09-05 2023-10-05 ement tions nvelope ementation and Valuation for the PMU-IW WRMP Assets CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-116917-CS-INDV / Consultancy services for Pre Component 3: Multi-sector Consultant Qualifi / Post Limited 9,090.91 0.00 Canceled 2019-07-25 2019-08-08 2019-09-07 2019-10-12 2020-04-09 paration of TOR for River Bas Water Resources Planning cation Selection in Management Plan (IWWRM P/PP/CONS/30) LK-MOMDE-120102-CS-QCBS / Consultancy service to finali Component 1: Watershed an Quality And Cost- ze the Bid documents for irri / Post Open - National 12,121.21 0.00 Canceled 2019-09-16 2019-10-07 2019-11-20 2019-12-18 2020-01-17 2020-02-21 2020-03-27 2021-03-27 d Water Resources Planning Based Selection gation dam rehabilitation of Component 1 (IWWRMP/PP/C ONS/35) LK-MOMDE-121715-CS-CQS / Consultancy Service for prep Component 1: Watershed an Consultant Qualifi aration of Watershed Manage / Post Open - National 15,151.52 0.00 Canceled 2019-07-17 2019-08-07 2019-09-20 2019-10-20 2019-11-24 2020-05-22 d Water Resources Planning cation Selection ment plans for selected area (IWWRMP/PP/CONS/36) LK-MOMDE-121716-CS-CQS / Consultancy services for pre Component 2: Infrastructure Consultant Qualifi / Post Open - National 30,303.03 0.00 Canceled 2019-09-15 2019-10-06 2019-11-19 2019-12-19 2020-01-23 2020-07-21 paration of Risk Assesment (I Improvements cation Selection WWRMP/PP/CONS/37) LK-MOMDE-125891-CS-QCBS / Consultancy service for pre paration of Watershed mana gement plan for seven select Component 1: Watershed an Quality And Cost- Open - Internationa / Post 1,348,314.61 0.00 Canceled 2019-12-05 2019-12-26 2020-02-08 2020-03-07 2020-04-06 2020-05-11 2020-06-15 2021-06-15 ed divisions -Nuwara Eliya, B d Water Resources Planning Based Selection l adulla, Walapnae & Kandy (D elthota, Haguranketha and P ahatha Hewaheta) (IWWRMP- 1/CS/QCBS/1) LK-MOMDE-125993-CS-QCBS / Consultancy Service for stu dy and recommendation for back erosion of Rantambe da Component 2: Infrastructure Quality And Cost- Open - Internationa m spillway tail canal ,LB erosi / Post 786,516.85 0.00 Canceled 2019-11-25 2019-12-16 2020-01-29 2020-02-26 2020-03-27 2020-05-01 2020-06-05 2021-06-05 Improvements Based Selection l on of Victoria dam spillway ta il canal, Back Analysis for Vic toria dam and Kotmale Dam grouting gallery inspection (I WWRMP-2/CS/QCBS/7) LK-MOMDE-126757-CS-QCBS / Development of Basin Mana Component 1: Watershed an Quality And Cost- gement plan for Walawa & M / Post Open - National 421,348.31 0.00 Canceled 2020-05-25 2020-06-15 2020-07-29 2020-08-26 2020-09-25 2020-10-30 2020-12-04 2021-12-04 d Water Resources Planning Based Selection a Oya including the stakehol der workshops (IWWRMP-1/C S/QCBS/5) LK-MOMDE-126759-CS-QCBS / Consultancy service for Exp Component 1: Watershed an Quality And Cost- ansion and enhancement of / Post Open - National 561,797.75 0.00 Canceled 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-04-05 2021-05-10 2023-05-10 d Water Resources Planning Based Selection WMS/MASL bulk water allocat ion model (IWWRMP-1/CS/QC BS/6) LK-MOMDE-138818-CS-CQS / Consultancy on improving re servoir capacity by dredging Component 1: Watershed an Consultant Qualifi / Post Open - National 112,359.55 0.00 Canceled 2020-04-01 2020-04-22 2020-06-05 2020-07-05 2020-08-09 2021-08-09 sand deposits - medium and d Water Resources Planning cation Selection minor irrigation tanks within the watershed (IWWRMP-1/C S/CQS/2) LK-MOMDE-138828-CS-CQS / Establishment of policy and i Component 2: Infrastructure Consultant Qualifi nstitutional arrangements for / Post Open - National 112,359.55 0.00 Canceled 2020-04-14 2020-05-05 2020-06-18 2020-07-18 2020-08-22 2021-08-22 Improvements cation Selection dam safety, and water resour ces management (IWWRMP-2 /CS/CQS/15) LK-MOMDE-138831-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi al Management Framework a / Post Open - National 25,280.90 0.00 Canceled 2020-12-16 2021-01-06 2021-02-19 2021-03-21 2021-04-25 2022-04-25 Improvements cation Selection nd Environmental social scre ening report for rehabiliate d ams & canals cluster VII (IW WRMP-2/CS/CQS/18) LK-MOMDE-138832-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi al Management Framework a / Post Open - National 25,280.90 0.00 Canceled 2019-12-13 2020-01-03 2020-02-16 2020-03-17 2020-04-21 2021-04-21 Improvements cation Selection nd Environmental social scre ening report for rehabilitate dams & canals cluster VIII (I WWRMP-2/CS/CQS/19) LK-MOMDE-138824-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi al Management Framework a / Post Open - National 56,179.78 0.00 Canceled 2020-09-09 2020-09-30 2020-11-13 2020-12-13 2021-01-17 2021-07-16 Improvements cation Selection nd Environmental social scre ening report for rehabilitate dams & canals cluster IV ( IW WRMP-2/CS/CQS/11) LK-MOMDE-138829-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi al Management Framework a / Post Open - National 11,235.96 0.00 Canceled 2020-02-17 2020-03-09 2020-04-22 2020-05-22 2020-06-26 2021-06-26 Improvements cation Selection nd Environmental social scre ening report for rehabiliate d ams & canals cluster V (IWW RMP-2/CS/CQS/16) Page 8 LK-MOMDE-138830-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi al Management Framework a / Post Open - National 22,471.91 0.00 Canceled 2019-12-09 2019-12-30 2020-02-12 2020-03-13 2020-04-17 2021-04-17 Improvements cation Selection nd Environmental social scre ening report for rehabilitate dams & canals cluster VI (IW WRMP-2/CS/CQS/17) LK-MOMDE-138822-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi al Management Framework a / Post Open - National 56,179.78 0.00 Canceled 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2021-01-03 Improvements cation Selection nd Environmental social scre ening report for rehabilitate dams & canals cluster II (IW WRMP-2/CS/CQS/9) LK-MOMDE-138835-CS-CQS / Feasibility study tocheck the Component 2: Infrastructure Consultant Qualifi possibility of diverson of Kalu / Post Open - National 280,898.88 0.00 Canceled 2020-09-28 2020-10-19 2020-12-02 2021-01-01 2021-02-05 2022-02-05 Improvements cation Selection ganga Water to the CKD area (IWWRMP-2/CS/CQS/22) LK-MOMDE-138823-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi al Management Framework a / Post Open - National 56,179.78 0.00 Canceled 2020-08-31 2020-09-21 2020-11-04 2020-12-04 2021-01-08 2021-07-07 Improvements cation Selection nd Environmental social scre ening report for rehabilitate dams & canals cluster III ( IW WRMP-2/CS/CQS/10) LK-MOMDE-138836-CS-CQS / Preparation of guidline for s Component 2: Infrastructure Consultant Qualifi / Post Open - National 11,235.96 0.00 Canceled 2020-07-30 2020-08-20 2020-10-03 2020-11-02 2020-12-07 2021-12-07 ustainable Dam safety and H Improvements cation Selection ydraulic Assets ( IWWRMP-2/ CS/CQS/23 ) LK-MOMDE-138838-CS-CQS / Component 2: Infrastructure Consultant Qualifi / Post Open - National 280,898.88 0.00 Canceled 2020-11-01 2020-11-22 2021-01-05 2021-02-04 2021-03-11 2022-03-11 Risk assessment for all identi Improvements cation Selection fied dams LK-MOMDE-162965-CS-QCBS / Consultancy service for pre Component 1: Watershed an Quality And Cost- paration of Mahaweli Upper / Post Open - National 280,898.88 0.00 Canceled 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-04-05 2021-05-10 2022-05-10 d Water Resources Planning Based Selection Watershed management inte rvention plan for cluster II (I WWRMP-1/CS/QCBS/2) LK-MOMDE-138837-CS-CQS / preparation of O & M Manual Component 2: Infrastructure Consultant Qualifi / Post Open - National 280,898.88 0.00 Canceled 2021-12-01 2021-12-22 2022-02-04 2022-03-06 2022-04-10 2023-04-10 s and Emergency Action plan Improvements cation Selection s for selected dams ( IWWRM P-2/CS/CQS/24 ) LK-MOMDE-162967-CS-QCBS / Consultancy service for pre Component 1: Watershed an Quality And Cost- paration of Mahaweli Upper / Post Open - National 224,719.10 0.00 Canceled 2021-02-01 2021-02-22 2021-04-07 2021-05-05 2021-06-04 2021-07-09 2021-08-13 2022-08-13 d Water Resources Planning Based Selection Watershed management inte rvention plan for cluster III (I WWRMP-1/CS/QCBS/3) LK-MOMDE-162968-CS-QCBS / Consultancy Service develo pment of best practices for w Component 1: Watershed an Quality And Cost- / Post Open - National 56,179.78 0.00 Canceled 2020-09-29 2020-10-20 2020-12-03 2020-12-31 2021-01-30 2021-03-06 2021-04-10 2021-10-07 ater management using nati d Water Resources Planning Based Selection ve , herbal, economical impo rtant species (IWWRMP-1/CS/ QCBS/4) LK-MOMDE-138839-CS-CQS / Consultancy Service for Deve Component 4: Project Manag Consultant Qualifi / Post Open - National 14,044.94 0.00 Canceled 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-05-23 lopment for Project Website ( ement cation Selection IWWRMP-4/CS/CQS/26) LK-MOMDE-162972-CS-QCBS / Consultancy service for dev Component 1: Watershed an Quality And Cost- elopment for integrated desi / Post Open - National 56,179.78 0.00 Canceled 2020-09-29 2020-10-20 2020-12-03 2020-12-31 2021-01-30 2021-03-06 2021-04-10 2022-04-10 d Water Resources Planning Based Selection gn proposal for upper periph ary of Polgolla reservoir (IW WRMP-1/CS/QCBS/5) LK-MOMDE-162975-CS-CQS / Consultancy service for Expa Component 1: Watershed an Consultant Qualifi Open - Internationa / Post 561,795.75 0.00 Canceled 2020-11-02 2020-11-23 2021-02-06 2021-03-08 2021-04-19 2022-04-19 nsion and enhancement of W d Water Resources Planning cation Selection l MS/MASL bulk water allocatio n model LK-MOMDE-138819-CS-CQS / Development Groundwater M anagement plans for Malwat hoya, Deduru Oya, Kumbukk Component 1: Watershed an Consultant Qualifi Under Implement an Oya, MathuruOya, Mee Oy IDA / 66190 Post Open - National 140,449.44 0.00 2021-08-19 2022-02-07 2021-09-09 2022-07-29 2021-11-06 2022-01-05 2022-02-09 2023-02-09 d Water Resources Planning cation Selection ation a, Maa Oya, Kelani basin and Jaffna Peninsula (WRB) by co nsidering the real-time data on water quality, quantity, et c.(IWWRMP-1/CS/CQS/3) LK-MOMDE-162977-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi Under Implement al Management Plan and Env IDA / 66210 Post Open - National 84,269.00 0.00 2021-06-30 2021-08-23 2021-07-26 2021-09-07 2021-09-08 2022-03-02 2021-10-08 2022-05-19 2021-11-12 2022-05-11 Improvements cation Selection ation ironmental and Social Screen ing report for rehabilitate da ms & canals in NPC (IWWRMP -2/CS/CQS/7) LK-MOMDE-138821-CS-CQS / Consultancy service for Prep aration of Environmental Soci Component 2: Infrastructure Consultant Qualifi Under Implement al Management Plan and Env IDA / 66210 Post Open - National 56,179.78 0.00 2021-06-30 2021-08-23 2021-07-20 2021-09-07 2021-09-02 2022-03-02 2021-10-02 2022-05-19 2021-11-06 2022-05-05 Improvements cation Selection ation ironmental and Social Screen ing report for rehabilitate da ms & canals in EPC (IWWRMP -2/CS/CQS/8) LK-MOMDE-138825-CS-CQS / Consultancy Service for prep aration of Livelihood Support Component 2: Infrastructure Consultant Qualifi Under Implement IDA / 66210 Post Open - National 56,179.78 0.00 2021-09-23 2022-04-04 2021-10-14 2022-05-23 2021-11-27 2021-12-27 2022-01-31 2022-07-30 Assistance Plan (LSA) for the Improvements cation Selection ation period of Cultivation forgo of selected dams (IWWRMP-2/C S/CQS/9) LK-MOMDE-138826-CS-CQS / Consultancy Service for inspe ction, identification of defect Component 2: Infrastructure Consultant Qualifi Under Implement IDA / 66210 Post Open - National 84,269.66 0.00 2021-07-28 2022-03-04 2021-08-18 2022-03-24 2021-10-01 2021-10-31 2021-12-05 2022-06-03 s and repair works of syphon Improvements cation Selection ation e from 3+950 km to 4+330 k m of walawa RB main canal (I WWRMP-2/CS/CQS/10) Page 9 LK-MOMDE-138827-CS-CQS / Consultancy service for desig Component 2: Infrastructure Consultant Qualifi Under Implement IDA / 66210 Post Open - National 28,089.89 0.00 2021-08-13 2022-03-04 2021-09-03 2022-03-24 2021-10-17 2021-11-16 2021-12-21 2022-06-19 n of Bridge at 4+000 km of w Improvements cation Selection ation alawa RB main canal (IWWR MP-2/CS/CQS/11) LK-MOMDE-138834-CS-CQS / Feasibility Study for Construc tion of Poonery Tank and Bar Component 2: Infrastructure Consultant Qualifi IDA / 66210 Post Open - National 252,808.99 0.00 Under Review 2022-02-01 2022-08-09 2022-02-22 2022-04-07 2022-05-07 2022-06-11 2023-06-11 rages including Investigation, Improvements cation Selection Detailed Design, BD preparat ion, EIA and Social assessme nt (IWWRMP-2/CS/CQS/13) LK-MOMDE-121717-CS-CQS / Component 4: Project Manag Consultant Qualifi Under Implement Preparation of Management I IDA / 66210 Post Open - National 12,121.21 0.00 2022-02-01 2022-02-11 2022-02-15 2022-03-13 2022-04-07 2022-05-07 2022-06-11 2022-12-08 ement cation Selection ation nformation System (IWWRMP /PP/CONS/15) LK-MOMDE-162963-CS-QCBS / Consultancy service for pre Component 1: Watershed an Quality And Cost- paration of Implementation s IDA / 66190 Post Open - National 955,056.18 0.00 Canceled 2021-08-18 2021-10-28 2021-12-11 2022-01-10 2022-02-09 2022-03-02 2022-04-06 2023-04-06 d Water Resources Planning Based Selection upport Upper Mahaweli Wate rshed management plan (IW WRMP-1/CS/QCBS/1) LK-MOMDE-240803-CS-QCBS / Consultancy for Dams Portf olio Risk Assessment and Pre Component 2: Infrastructure Quality And Cost- Under Implement paration of Operation and Ma IDA / 66210 Post Open - National 505,617.98 0.00 2022-08-22 2022-08-23 2022-09-16 2022-09-16 2022-10-30 2022-11-29 2022-12-29 2023-01-19 2023-02-23 2024-02-23 Improvements Based Selection ation intenance (O&M) Plan and E mergency Preparedness Plan (EPP) for all identified dams ( IWWRMP-2/CS/QCBS/16) LK-MOMDE-315784-CS-CQS / Component 4: Project Manag Consultant Qualifi Consultancy Service for Deve IDA / 66210 Post Open - National 13,250.00 0.00 Under Review 2022-09-26 2022-10-03 2022-10-17 2022-11-21 2022-12-21 2023-01-25 2023-04-25 ement cation Selection lopment for Project Website LK-MOMDE-240780-CS-CQS / Consultancy service for devel Component 1: Watershed an Consultant Qualifi Pending Impleme opment for integrated design IDA / 66190 Post Open - National 44,943.82 0.00 2023-09-01 2023-11-22 2024-01-19 2024-03-19 2024-04-23 2024-10-20 d Water Resources Planning cation Selection ntation proposal for upper periphary of Polgolla reservoir (IWWRM P-1/CS/CQS/2) LK-MOMDE-138820-CS-CQS / Development of Groundwate Component 1: Watershed an Consultant Qualifi r Data & Information System IDA / 66190 Post Open - National 56,179.78 0.00 Canceled 2022-04-14 2022-06-22 2022-08-19 2022-10-18 2022-11-22 2023-11-22 d Water Resources Planning cation Selection for WRB covering entire coun try (IWWRMP-1/CS/CQS/4) LK-MOMDE-118633-CS-QCBS / Consultancy Services for De veloping a suitable Back anal ysis for Victoria dam to study Component 2: Infrastructure Quality And Cost- Open - Internationa Pending Impleme IDA / 66210 Post 417,000.00 0.00 2023-08-02 2023-10-03 2023-11-16 2023-12-14 2024-01-13 2024-02-17 2024-03-23 2025-03-23 the AAR and its impacts on t Improvements Based Selection l ntation he safety of Victoria dam for FSL and HFL including necess ary testing and surveys and portfolio risk assessment for all the dams LK-MOMDE-118622-CS-QCBS / Consultancy Services for St udy on cracks in intake sluice Component 2: Infrastructure Quality And Cost- Open - Internationa Pending Impleme IDA / 66210 Post 842,696.63 0.00 2023-02-27 2023-03-30 2023-05-13 2023-06-10 2023-07-10 2023-08-14 2023-09-18 2024-09-17 tower and dam stability in Se Improvements Based Selection l ntation nanayaka Samudraya Headw orks ( IWWRMP-2/CS/QCBS/6 ) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-113221-CS-INDV / Consultancy services for En vironmental Social Impact As Component 2: Infrastructure Individual Consult sessment for Rehabilitation o / Post Limited 9,090.91 9,340.87 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-28 2019-06-07 2019-06-03 2019-06-17 2019-06-03 2019-08-16 Improvements ant Selection f Elahara scheme, Haththota scheme and Arawatta Tank (IWWRMP/PP/CONS/01) LK-MOMDE-113250-CS-INDV / Consultancy services for En vironmental Social Impact As Component 2: Infrastructure Individual Consult sessment for Rehabilitation o / Post Limited 12,121.21 3,593.15 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-28 2019-06-07 2019-06-02 2019-06-15 2019-06-03 2019-08-14 Improvements ant Selection f Hali Ela Tank, Akathimuripu Tank, Madiyawa Tank and W aduwala Scheme (IWWRMP/P P/CONS/02) LK-MOMDE-113252-CS-INDV / Consultancy services for Aq Component 2: Infrastructure Individual Consult / Post Limited 6,060.61 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-08-16 uatic Survey Improvements ant Selection (IWWRMP/PP/CONS/03) LK-MOMDE-116871-CS-INDV / Consultancy service for Pre paration of Operation manual for river basin planning and Component 2: Infrastructure Individual Consult management, customized to / Post Limited 24,242.42 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-08-16 Improvements ant Selection the selected river basins (Wa lawa including the Walawa R B preparation of ESMP, Kalaw ewa and Mahalindawewa) (IWWRMP/PP/CONS/06) LK-MOMDE-116883-CS-INDV / Consultancy for Preparation Component 1: Watershed an Individual Consult / Post Limited 12,121.21 8,274.72 Signed 2019-08-01 2019-07-01 2019-08-06 2019-05-03 2019-08-27 2019-07-09 2019-10-01 2019-07-15 2020-03-29 of guideline for Sustainable d Water Resources Planning ant Selection Watershed Management (IW WRMP/PP/CONS/08) LK-MOMDE-116900-CS-INDV Component 4: Project Manag Individual Consult / Short-term assignment for P / Post Limited 3,030.30 0.00 Canceled 2019-05-30 2019-05-08 2019-06-04 2019-06-18 2019-07-09 2020-01-05 ement ant Selection ersonal Assistant (IWWRMP/P P/CONS/17) LK-MOMDE-116901-CS-INDV / Consultancy services for En vironmental Social Impact As Component 2: Infrastructure Individual Consult / Post Limited 12,121.21 2,756.51 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-09 2019-06-07 2019-05-27 2019-06-17 2019-05-30 2019-08-16 sesment for Rehabilitation of Improvements ant Selection Muththuiyankaddu irrigation scheme (IWWRMP/PP/CONS/1 8) Page 10 LK-MOMDE-116906-CS-INDV / Consultancy services for En vironmental Social Impact As Component 2: Infrastructure Individual Consult / Post Limited 12,121.21 1,875.18 Signed 2019-05-30 2019-05-08 2019-06-04 2019-04-09 2019-06-09 2019-05-27 2019-06-19 2019-06-03 2019-08-18 sesment for Rehabilitation of Improvements ant Selection Dewahuwa tank & scheme a nd Baththalagoda Anicut & s cheme (IWWRMP/PP/CONS/2 2) LK-MOMDE-116907-CS-INDV / Consultancy services for En vironmental Social Impact As Component 2: Infrastructure Individual Consult sessment for Rehabilitation o / Post Limited 21,212.12 9,340.87 Signed 2019-05-30 2019-05-08 2019-06-02 2019-04-09 2019-06-07 2019-04-10 2019-06-17 2019-06-03 2019-08-16 Improvements ant Selection f Huruluwewa irrigation sche me, Karawita Tank & Ambak olawewa Tank (IWWRMP/PP/C ONS/23) LK-MOMDE-116909-CS-INDV / Consultancy services for En vironmental Social Impact As sesment for Rehabilitation of Component 2: Infrastructure Individual Consult / Post Limited 24,242.42 14,236.74 Signed 2019-05-30 2019-05-08 2019-06-04 2019-05-28 2019-06-11 2019-05-28 2019-06-25 2019-06-03 2019-09-23 Vahanery Dam, Panama Tan Improvements ant Selection k, Unnichchai scheme, Naga deepa Tank, Illukuchenal & S enanayake Samudraya Reser voir (IWWRMP/PP/CONS/24) LK-MOMDE-116910-CS-INDV / Consultancy services for En vironmental Social Impact As sesment for Rehabilitation of Component 2: Infrastructure Individual Consult / Post Limited 24,242.42 13,898.79 Signed 2019-05-30 2019-05-08 2019-06-04 2019-04-09 2019-06-11 2019-05-28 2019-06-25 2019-05-30 2019-09-23 Pavatkulam Tank, Muhathank Improvements ant Selection ulam Scheme, Viyadhikulam irrigation scheme, Peramadu Tank & Scheme and Mavilaru Headworks (IWWRMP/PP/CON S/25) LK-MOMDE-116911-CS-INDV / Consultancy service for pre Component 2: Infrastructure Individual Consult paration of Livelihood Suppor / Post Limited 18,181.82 0.00 Canceled 2019-07-09 2019-07-14 2019-08-04 2019-09-08 2020-03-06 Improvements ant Selection t Assistance Plan (LSA) - Wal awa (IWWRMP/PP/CONS/26) LK-MOMDE-116912-CS-INDV / Consultancy services for En vironmental Social Impact As Component 2: Infrastructure Individual Consult / Post Limited 9,090.91 3,736.75 Signed 2019-05-30 2019-05-08 2019-06-04 2019-05-15 2019-06-11 2019-05-24 2019-06-25 2019-06-20 2019-08-24 sesment for Rehabilitation of Improvements ant Selection Kothmale Dam & irrigation sc heme (IWWRMP/PP/CONS/27) LK-MOMDE-116914-CS-INDV / Individual Consultancy servi ces to prepare mechanical sp Component 2: Infrastructure Individual Consult ecification, Estimation & Bid / Post Limited 9,090.91 11,032.96 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-23 2019-06-07 2019-05-28 2019-06-17 2019-06-03 2020-06-16 Improvements ant Selection documents for Gantry crane Polgolla, Udawalawe and Gat e Automation for Bowatenna (IWWRMP/PP/CONS/28) LK-MOMDE-116896-CS-INDV / Short-term assignment for P Component 4: Project Manag Individual Consult / Post Limited 3,030.30 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-12-14 rocurement Assistant (IWWR ement ant Selection MP/PP/CONS/16) LK-MOMDE-116904-CS-INDV / Consultancy services for En vironmental Social Impact As sesment for Rehabilitation of Component 2: Infrastructure Individual Consult / Post Limited 27,272.27 8,299.72 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-23 2019-06-07 2019-05-24 2019-06-17 2019-05-30 2019-08-16 Piramanthalaru Kulam irrigati Improvements ant Selection on scheme, Kanagambikaikul am irrigation scheme and Kal madu tank irrigation scheme (IWWRMP/PP/CONS/21) LK-MOMDE-121767-CS-INDV / Individual consultancy servi ces for preparation and revie Component 2: Infrastructure Individual Consult wing the RFP of study & reco / Post Open 60,000.00 0.00 Canceled 2019-07-28 2019-09-15 2019-10-06 2019-11-10 2020-05-08 Improvements ant Selection mmendation for selected MA SL Dams (Rantambe, Victoria , Kothmale) (IWWRMP/PP/CO NS/32) LK-MOMDE-121782-CS-INDV / Consultancy for Preparation Component 2: Infrastructure Individual Consult of guideline for sustainable / Post Limited 12,121.21 0.00 Canceled 2019-09-18 2019-09-23 2019-10-14 2019-11-18 2020-05-16 Improvements ant Selection Dam safety and Hydraulic As sert (IWWRMP/PP/CONS/07) LK-MOMDE-138929-CS-INDV / Consultancy services for Pre Component 2: Infrastructure Individual Consult / Post Limited 8,426.97 0.00 Canceled 2020-05-29 2020-06-03 2020-06-24 2020-07-29 2021-07-29 paration of TOR for River Bas Improvements ant Selection in Management Plan (IWWRM P-2/CS/IC/20) LK-MOMDE-118665-CS-INDV / Training program on Procur Component 4: Project Manag Individual Consult / Post Limited 6,060.61 0.00 Canceled 2020-11-15 2020-11-20 2020-12-11 2021-01-15 2021-01-22 ement (Evaluation of Consult ement ant Selection ancy, Goods and Works) (IW WRMP/PP/CONS/41) LK-MOMDE-184063-CS-INDV Component 4: Project Manag Individual Consult / Short-term assignment for P IDA / 66190 Post Limited 2,500.00 0.00 Under Review 2020-07-15 2020-07-15 2020-07-18 2020-07-15 2020-08-01 2020-09-05 2021-03-04 ement ant Selection ersonal Assistant (IWWRMP/P P/CONS/17) LK-MOMDE-162970-CS-INDV / Consultancy service for Pre paration of Environmental So cial Management Framework Component 2: Infrastructure Individual Consult IDA / 66210 Post Limited 11,235.96 3,069.72 Signed 2021-08-13 2021-09-15 2021-08-18 2021-10-04 2021-09-09 2022-04-05 2021-10-14 2022-04-05 2022-01-12 and Environmental social scr Improvements ant Selection eening report for Rehabilitati on of Wadamunai tank & Lun ugamwehera Reservoir (IWW RMP-2/CS/IND/12) LK-MOMDE-282411-CS-INDV / Consultancy service for Pre Component 2: Infrastructure Individual Consult Under Implement paration of TOR for Senenaya IDA / 66210 Post Limited 5,500.00 0.00 2022-04-24 2022-04-25 2022-04-29 2022-07-11 2022-05-20 2022-06-10 2022-08-09 Improvements ant Selection ation ka Samudraya feasibility stu dy (IWWRMP-2/CS/IND/19) LK-MOMDE-282414-CS-INDV / Consultancy service for pre paration of Initial Environme Component 2: Infrastructure Individual Consult IDA / 66210 Post Limited 7,950.00 4,904.12 Signed 2022-04-25 2022-04-25 2022-04-30 2022-05-23 2022-05-21 2022-07-25 2022-06-11 2022-09-12 2022-09-09 nt Examination (IEE) Report Improvements ant Selection for Improvements to Mavilar u Headworks (LB & RB) (IWW RMP-2/CS/IND/20) Page 11 LK-MOMDE-302749-CS-CDS / Consultancy service for Prep Component 1: Watershed an Pending Impleme aration of Implementation Su IDA / 66190 Post Direct Selection Direct - National 564,000.00 0.00 2022-09-21 2022-10-19 2022-12-23 2024-12-22 d Water Resources Planning ntation pport Upper Mahaweli Water shed Management Plan (IWW RMP-1/CS/DIR/1) LK-MOMDE-282420-CS-INDV / Consultancy service for Pre pare TOR for the Consultancy Component 2: Infrastructure Individual Consult Open - Internationa Pending Impleme IDA / 66210 Post 11,000.00 0.00 2022-12-27 2023-03-27 2023-04-10 2023-05-01 2023-07-30 Service for the Evaluation an Improvements ant Selection l ntation d Recommendation of Kothm ale, Victoria & Rantambe Res ervoirs (IWWRMP-2/CS/IND/1 8) LK-MOMDE-116903-CS-INDV / Consultancy services for En vironmental Social Impact As sesment for Rehabilitation of Component 2: Infrastructure Individual Consult / Post Limited 27,272.73 0.00 Canceled 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 Akkarayankulam irrigation sc Improvements ant Selection heme, Kudamuruthy Tank an d Vannerikulam headworks & irrigation scheme (IWWRMP/P P/CONS/20) LK-MOMDE-116902-CS-INDV / Consultancy services for En vironmental Social Impact As sesment for Rehabilitation of Component 2: Infrastructure Individual Consult / Post Limited 24,242.42 0.00 Canceled 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2019-12-29 Periyamadu Tank and Kariyal Improvements ant Selection ai Nagarpaduwan Tank & irri gation scheme and Periyapa ndivirichchan scheme (IWWR MP/PP/CONS/19) LK-MOMDE-318527-CS-INDV / Hiring Individual Consultant Component 2: Infrastructure Individual Consult Pending Impleme ( Eng. E.M.S.Bandara - Electr IDA / 66210 Post Direct - National 5,840.00 0.00 2022-10-31 2022-11-10 2022-11-24 2022-12-29 2023-06-27 Improvements ant Selection ntation ical and Mechanical) to estab lish Dam Safety Review Pane l (DSRP) LK-MOMDE-318538-CS-INDV / Hiring Individual Consultant ( Prof. Nimal Seneviratne - Component 2: Infrastructure Individual Consult Pending Impleme IDA / 66210 Post Direct - National 5,840.00 0.00 2022-10-20 2022-10-30 2022-11-13 2022-12-18 2023-06-16 Engineering Geology / Geote Improvements ant Selection ntation chnical Engineering) to estab lish Dam Safety Review Pane l (DSRP) LK-MOMDE-318539-CS-INDV / Hiring Individual Consultant ( Dr.H.A.Dharmagunawardha Component 2: Infrastructure Individual Consult Pending Impleme IDA / 66210 Post Direct - National 5,840.00 0.00 2022-10-20 2022-10-30 2022-11-13 2022-12-18 2023-06-16 ne - Engineering Geology / G Improvements ant Selection ntation eotechnical Engineering ) to Establish Dam Safety Review Panel (DSRP) LK-MOMDE-318535-CS-INDV / Hiring Individual Consultant Component 2: Infrastructure Individual Consult Pending Impleme ( Eng.T.D Wickramarathna - IDA / 66210 Post Direct - National 5,840.00 0.00 2022-10-25 2022-11-04 2022-11-18 2022-12-23 2023-06-21 Improvements ant Selection ntation Hydrology ) to establish Da m Safety Review Panel (DSR P) LK-MOMDE-318532-CS-INDV / Hiring Individual Consultant Component 2: Infrastructure Individual Consult Pending Impleme ( Eng.Chandani Hema Deven IDA / 66210 Post Direct - National 5,840.00 0.00 2022-10-27 2022-11-06 2022-11-20 2022-12-25 2023-06-23 Improvements ant Selection ntation dra - Dam Design) to Establi sh Dam Safety Review Panel (DSRP) LK-MOMDE-318531-CS-INDV / Hiring Individual Consultant ( Eng.S.W.Ediriweera - Dam Component 2: Infrastructure Individual Consult Pending Impleme IDA / 66210 Post Direct - National 5,840.00 0.00 2022-10-27 2022-11-06 2022-11-20 2022-12-25 2023-06-23 Instrumentation and Monitori Improvements ant Selection ntation ng Equipment ) to establish Dam Safety Review Panel (D SRP) LK-MOMDE-318533-CS-INDV / Hiring Individual Consultant (Eng.Badra Kamaladasa - D Component 2: Infrastructure Individual Consult Pending Impleme IDA / 66210 Post Direct - National 5,840.00 0.00 2022-10-25 2022-11-04 2022-11-18 2022-12-23 2023-06-21 am Construction, Quality Ass Improvements ant Selection ntation urance and Management) to Establish Dam Safety Review Panel (DSRP) LK-MOMDE-318537-CS-INDV / Hiring Individual Consultant Component 2: Infrastructure Individual Consult Pending Impleme ( Prof. K.P.P. Pathirana - D IDA / 66210 Post Direct - National 5,840.00 0.00 2022-10-24 2022-11-03 2022-11-17 2022-12-22 2023-06-20 Improvements ant Selection ntation am Design ) to Establish Da m Safety Review Panel (DSR P) Page 12