PROCUREMENT PLAN - Textual Part Project information: Uzbekistan Medium-Size Cities Integrated Urban Development Project (P162929) Project Implementation agency: “State Investment Committee” or “SIC” means the Borrower’s governmental body established pursuant to the Borrower’s Presidential Decree No. УП-4996 “On the Formation of the State Committee of the Republic of Uzbekistan for Investments” dated March 31, 2017 Date of the Procurement Plan: November 7, 2018 Period covered by this Procurement Plan: From November 2018 to November 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Law of Republic of Uzbekistan “On Public Procurement” dated January 25, 2018 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The Bank’s Anti-Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. 2. Contracts with an appropriate allocation of responsibilities, risks, and liabilities between the Borrower and the contractors/suppliers/consultants. 3. Rights for the Bank to review procurement documentation and activities. In accordance with the Procurement Regulations, each bidding document and contract shall include provisions stating the Bank's policy to sanction firms or individuals, found to have engaged in fraud and/or corruption as defined in the Procurement Regulations. In accordance with the Procurement Regulations, each bidding document and contract financed out of the proceeds of the Financing Agreement shall provide that bidders, suppliers, contractors and their subcontractors, agents, personnel, consultants, service providers, or suppliers shall permit the Bank to inspect all accounts, records and other documents relating to the bid submission and performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. Acts intended to materially impede the exercise of the Bank's inspection and audit rights provided for in the Procurement Regulations constitute an obstructive practice as defined in the Regulations. 4. No bids shall be rejected solely because they fall below or exceed the estimated cost. All bids (including in the case when less than two bids are received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank's prior written concurrence. The Bidding Documents template to be used under “national open competitive procurement arrangements” are subject to prior written concurrence by the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Uzbekistan : Medium-Size Cities Integrated Urban Development Project PLAN General Information Country: Uzbekistan 2019-01-15 Bank’s Approval Date of the Original Procurement Plan: 2022-06-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162929 GPN Date: Project Name: Medium-Size Cities Integrated Urban Development Project Loan / Credit No: TF / A7556, IBRD / 89140 State Investment Committee of the Republic of Uzbekistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MSC/UZB-C/W/1.6 / Restorati on/strengthening and adapti Component 1: Improvement ve reuse in accordance to m of Urban Services and Enhan Single Stage - One E 2020-11-3 IBRD / 89140 Post Request for Bids Open - National 500,553.00 0.00 Canceled 2020-02-12 2020-02-12 2020-02-17 2020-02-15 2020-03-30 2020-05-14 2020-04-29 2020-09-09 2020-06-03 odern energy efficiency norm cement of Public Urban Spac nvelope 0 s of the former Kindergarten es #17 and Administrative build ing at the Chartak city MSC/UZB-C/W/1.6.1 / Restor ation/strengthening and ada Component 1: Improvement ptive reuse in accordance to of Urban Services and Enhan Single Stage - One E 2021-06-2 IBRD / 89140 Post Request for Bids Open - National 500,553.00 0.00 Canceled 2020-09-09 2020-09-11 2020-09-14 2020-09-11 2020-10-26 2020-08-05 2020-11-18 2020-09-11 2020-12-23 modern energy efficiency nor cement of Public Urban Spac nvelope 1 ms of the former Kindergarte es n #17 and Administrative bui lding at the Chartak city MSC/UZB-C/W/1.6.2 / Restor ation/strengthening and ada Component 1: Improvement ptive reuse in accordance to of Urban Services and Enhan Single Stage - One E 2021-06-3 IBRD / 89140 Post Request for Bids Open - National 500,553.00 459,525.50 Signed 2020-09-11 2020-07-04 2020-09-16 2020-10-28 2020-08-05 2020-11-27 2020-08-28 2021-01-01 2020-10-05 modern energy efficiency nor cement of Public Urban Spac nvelope 0 ms of the former Kindergarte es n #17 and Administrative bui lding at the Chartak city. MSC-CKY/W/2.1 / Constructio Component 2: Institutional S Single Stage - One E 2021-08-1 n / Repair of Garage Premise IBRD / 89140 trengthening and Capacity B Post Request for Bids Open - National 340,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-11-02 2020-11-24 2020-12-14 2020-12-24 2021-01-13 2021-01-21 2021-02-17 nvelope 6 s for Municipal Equipment in uilding the Chartak city MSC-CKY/W/2.2 / Constructio Component 2: Institutional S Single Stage - One E 2021-08-1 n / Repair of Garage Premise IBRD / 89140 trengthening and Capacity B Post Request for Bids Open - National 300,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-10-28 2020-11-24 2020-12-09 2020-12-24 2021-01-08 2021-01-21 2021-02-12 nvelope 1 s for Municipal Equipment in uilding the Kagan city MSC-CKY/W/2.3 / Constructio Component 2: Institutional S Single Stage - One E 2021-08-1 n / Repair of Garage Premise IBRD / 89140 trengthening and Capacity B Post Request for Bids Open - National 330,000.00 0.00 Canceled 2020-10-23 2020-11-24 2020-10-28 2020-11-24 2020-12-09 2020-12-24 2021-01-08 2021-01-21 2021-02-12 nvelope 1 s for Municipal Equipment in uilding the Yangiyul city MSC-СKY/W/2.1.1 / Construct Component 2: Institutional S ion of garages for parking an Single Stage - One E 2021-12-0 IBRD / 89140 trengthening and Capacity B Post Request for Bids Open - National 340,000.00 332,777.08 Signed 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 2021-06-09 d maintenance of special equ nvelope 5 uilding ipment in Chartak, Namanga n region. MSC-СKY/W/2.2.1 / Construct Component 2: Institutional S ion of garages for parking an Single Stage - One E 2021-12-0 IBRD / 89140 trengthening and Capacity B Post Request for Bids Open - National 300,000.00 300,299.26 Signed 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 2021-06-14 d maintenance of special equ nvelope 5 uilding ipment in Kagan, Bukhara re gion. MSC-СKY/W/2.3.1 / Construct Component 2: Institutional S ion of garages for parking an Single Stage - One E 2021-12-0 IBRD / 89140 trengthening and Capacity B Post Request for Bids Open - National 330,000.00 0.00 Canceled 2021-02-11 2021-02-15 2021-02-21 2021-02-16 2021-04-04 2021-03-19 2021-05-04 2021-05-07 2021-06-08 d maintenance of special equ nvelope 5 uilding ipment in Yangiyul, Tashkent region. MSC-C/W/1.4 / Reconstructio Component 1: Improvement Request for Bids - n of the existing building of t of Urban Services and Enhan Single Stage - One E Small Works SPD 2022-09-3 IBRD / 89140 Post Request for Bids Open - National 746,158.55 646,384.20 Signed 2021-05-24 2021-05-27 2021-06-01 2021-05-31 2021-07-15 2021-06-30 2021-08-16 2021-07-22 2021-09-27 2021-08-17 he "Old Bazaar" located in Ch cement of Public Urban Spac nvelope (1 envelope proce 0 artak city, Namangan region es ss) MSC-СKY/W/2.3.1.1 / Constru Request for Bids - Component 2: Institutional S ction of garages for parking a Single Stage - One E Small Works SPD 2022-03-1 IBRD / 89140 trengthening and Capacity B Post Request for Bids Open - National 330,000.00 0.00 Canceled 2021-05-31 2021-05-31 2021-06-05 2021-05-31 2021-07-17 2021-06-30 2021-08-16 2021-09-20 nd maintenance of special eq nvelope (1 envelope proce 9 uilding uipment in Yangiyul, Tashken ss) t region. National Procure MSC-СKY/W/2.3.1.1.1 / Const Component 2: Institutional S ment Document - ruction of garages for parkin Single Stage - One E 2022-05-0 IBRD / 89140 trengthening and Capacity B Post Request for Bids Open - National 1 Envelope proce 330,000.00 293,069.96 Signed 2021-07-28 2021-07-29 2021-07-28 2021-07-29 2021-08-31 2021-08-31 2021-09-30 2021-09-22 2021-11-04 2021-10-26 g and maintenance of special nvelope 3 uilding ss (Non Bank-SPD equipment in Yangiyul, Tashk ) ent region. Request for Bids - MSC-Y/W/1.1 / Reconstructio Component 1: Improvement Open - Internationa Single Stage - One E Small Works SPD Under Imple 2022-09-1 n of Nyozbash WI and Water IBRD / 89140 of Urban Services and Enhan Prior Request for Bids 6,215,354.36 0.00 2021-12-01 2021-12-05 2021-12-06 2021-12-13 2022-01-17 2022-01-27 2022-02-16 2022-06-14 2022-03-23 l nvelope (1 envelope proce mentation 9 Main of the Yangiyul city cement of Public Urban Spac ss) es Request for Bids - MSC-K/W/1.1 / Reconstructio Component 1: Improvement Open - Internationa Single Stage - One E Small Works SPD Under Imple 2022-09-1 n of sewerage system of the IBRD / 89140 of Urban Services and Enhan Prior Request for Bids 7,612,634.43 0.00 2021-12-01 2021-12-20 2021-12-06 2021-12-21 2022-01-17 2022-02-08 2022-02-16 2022-06-22 2022-03-23 l nvelope (1 envelope proce mentation 9 Kagan city cement of Public Urban Spac ss) es MSC-C/W/1.2.1 / Constructio Component 1: Improvement Request for Bids - n of bridges for the construct of Urban Services and Enhan Single Stage - One E Small Works SPD Under Imple 2022-12-1 IBRD / 89140 Post Request for Bids Open - National 441,338.53 0.00 2022-02-01 2022-02-03 2022-02-16 2022-02-04 2022-04-02 2022-03-10 2022-05-02 2022-06-10 2022-06-16 ion of the Eco-trail in the city cement of Public Urban Spac nvelope (1 envelope proce mentation 3 of Chartak, Namangan region es ss) Request for Bids - MSC-Y/W/1.2 / Reconstructio Component 1: Improvement Open - Internationa Single Stage - One E Small Works SPD Under Imple 2023-04-2 n of Water Supply systems in IBRD / 89140 of Urban Services and Enhan Prior Request for Bids 6,230,467.98 0.00 2022-06-15 2022-06-20 2022-06-16 2022-06-22 2022-07-31 2022-09-09 2022-10-23 l nvelope (1 envelope proce mentation 1 Yangiyul city cement of Public Urban Spac ss) es Request for Bids - MSC-C/W/1.2 / Construction i Component 1: Improvement Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2023-05-2 n the Chartak Eco-Trail for no IBRD / 89140 of Urban Services and Enhan Post Request for Bids 4,600,000.00 0.00 2022-08-01 2022-08-06 2022-09-20 2022-10-25 2022-11-29 l nvelope (1 envelope proce lementation 8 n-motorized mobility cement of Public Urban Spac ss) es Request for Bids - MSC-C/W/1.1 / Reconstructio Component 1: Improvement Open - Internationa Single Stage - One E Works (without pr 18,840,834.0 Pending Imp 2023-05-0 n and extension of water sup IBRD / 89140 of Urban Services and Enhan Prior Request for Bids 0.00 2022-06-29 2022-07-04 2022-08-18 2022-10-02 2022-11-06 l nvelope equalification) SP 0 lementation 5 ply system of Chartak city cement of Public Urban Spac D es GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSC/UZB-G-RFQ/2.1 / Streng Component 2: Institutional S thening the material and tec Request for Quota Single Stage - One E IBRD / 89140 trengthening and Capacity B Post Open - National 115,000.00 98,087.01 Completed 2020-02-12 2020-02-26 2020-02-27 2020-02-24 2020-04-30 2020-05-14 hnical base of the State Com tions nvelope uilding mittee Tourism Development MSC/UZB-G/2.1 / Procureme Component 2: Institutional S nt of Special equipment for k Open - Internationa Single Stage - One E IBRD / 89140 trengthening and Capacity B Prior Request for Bids 2,600,000.00 0.00 Canceled 2020-02-28 2020-02-27 2020-02-29 2020-03-05 2020-03-31 2020-05-14 2020-04-30 2020-09-15 2020-06-04 2020-12-01 hokimiyats of Chartak, Kagan l nvelope uilding and Yangiyul cities MSC/UZB-G/2.1.1 / Procurem Component 2: Institutional S ent of Special equipment for Open - Internationa Single Stage - One E IBRD / 89140 trengthening and Capacity B Prior Request for Bids 3,330,000.00 3,087,093.00 Signed 2020-09-14 2020-09-16 2020-09-19 2020-09-17 2020-10-31 2020-01-03 2020-11-30 2021-03-04 2021-01-04 2021-03-31 2021-07-03 khokimiyats of Chartak, Kaga l nvelope uilding n and Yangiyul cities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UZ-MSCIUDP-300386-NC-RF Component 2: Institutional S Q / Educational trip of a grou Request for Quota Single Stage - One E Pending Impl IBRD / 89140 trengthening and Capacity B Post Open - National 40,000.00 0.00 2022-06-18 2022-06-22 2022-06-27 p of specialists to the Netherl tions nvelope ementation uilding ands from 2 to 9 July 2022 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSCIUDP-CS/QCBS-03-02 / D evelopment of feasibility stu dy,detailed designs and cons Component 1: Improvement truction supervision, for the u of Urban Services and Enhan Quality And Cost- Open - Internationa pgrading and improvements TF / A7556 Prior 1,235,000.00 1,028,000.00 Signed 2018-10-04 2018-10-08 2018-11-21 2019-03-28 2018-12-19 2019-01-18 2019-05-02 2019-02-22 2019-09-11 2019-03-29 2019-11-08 2020-03-28 cement of Public Urban Spac Based Selection l of three cities of Uzbekistan. es The first Lump-Sum contract to be financed by ECAPDEV G rant and Second and Third c ontracts by IBRD Loans. UDP-CS/CQS-5 / Consultant F Component 1: Improvement Consultant Qualifi Open - Internationa irm for Environmental and So TF / A7556 of Urban Services and Enhan Post 25,000.00 0.00 Canceled 2019-01-23 2018-08-06 2019-02-13 2019-03-29 2019-04-28 2019-06-02 2019-11-29 cation Selection l cial Safeguards, including tra cement of Public Urban Spac ining and RPF es UDP-CS/CQS-6 / M&E survey Component 1: Improvement Consultant Qualifi Open - Internationa s (beneficiary satisfaction sur TF / A7556 of Urban Services and Enhan Post 19,000.00 0.00 Canceled 2019-01-23 2018-11-15 2019-02-13 2019-03-29 2019-04-28 2019-01-17 2019-06-02 2019-11-29 cation Selection l vey) cement of Public Urban Spac es Component 1: Improvement UDP-CS/CQS-04 / Grant Audi Consultant Qualifi Open - Internationa TF / A7556 of Urban Services and Enhan Post 6,000.00 0.00 Canceled 2019-01-30 2019-02-20 2019-04-05 2019-05-05 2019-06-09 2019-12-06 t cation Selection l cement of Public Urban Spac es UDP-CS/CQS-01 / Preparatio n of detailed designs DDs an Component 1: Improvement d Bidding Documents, and co of Urban Services and Enhan Consultant Qualifi Open - Internationa IBRD / 89140 Post 80,000.00 80,000.00 Signed 2019-03-06 2019-03-05 2019-03-08 2019-03-25 2019-03-20 2019-03-28 2019-04-05 2019-04-01 2019-04-09 2019-09-30 nstruction supervision. For th cement of Public Urban Spac cation Selection l e Phase 1 - US $ 30 000 Lum es p Sum, Phase 2 - US $ 50 00 0 Time Based. MSCIUDP-CS/QCBS-05-02 / D evelopment of a National Mo Component 2: Institutional S Quality And Cost- Open - Internationa nitoring and Evaluation (M&E IBRD / 89140 trengthening and Capacity B Post 270,000.00 0.00 Canceled 2019-09-27 2019-10-18 2019-12-01 2019-12-29 2020-01-28 2020-03-03 2020-04-07 2021-04-07 Based Selection l ) system for the sustainable uilding Tourism & Travel sector in Uz bekistan MSCIUDP-CS/QCBS-06-01 / A nalysis and Assessment of th Component 2: Institutional S Quality And Cost- Open - Internationa e Financing of Urban Develop IBRD / 89140 trengthening and Capacity B Prior 1,000,000.00 0.00 Canceled 2019-09-27 2019-10-18 2019-12-01 2019-12-29 2020-01-28 2020-03-03 2020-04-07 2021-04-07 Based Selection l ment and Intergovernmental uilding Fiscal Relations in Uzbekistan MSCIUDP-CS/QCBS-05-01 / D evelopment of new susainabl e tourism destinations, includ Component 2: Institutional S Quality And Cost- Open - Internationa ing promotion, marketing & b IBRD / 89140 trengthening and Capacity B Post 480,000.00 0.00 Canceled 2019-11-05 2019-11-26 2020-01-09 2020-02-06 2020-03-07 2020-04-11 2020-05-16 2021-05-16 Based Selection l randing strategy and action uilding plan, for (i) the Fergana Valle y and (ii) Bukhara Region in Uzbekistan MSC-PA/3.1 / Consultant for Component 3: Implementati Least Cost Selecti Open - Internationa IBRD / 89140 Post 70,000.00 29,500.00 Signed 2020-06-19 2020-06-24 2020-07-10 2020-07-29 2020-08-23 2020-12-21 2020-09-20 2021-01-22 2020-10-20 2021-04-14 2020-11-24 2021-05-05 2020-12-29 2021-05-10 2021-06-27 Audit on Support on l MSC-CKY/CS/1.1 / Preparatio Component 1: Improvement n of Detailed Design and Bid of Urban Services and Enhan Quality And Cost- Open - Internationa ding Documents, and Constr IBRD / 89140 Prior 2,200,000.00 2,068,573.00 Signed 2020-06-26 2020-06-30 2020-07-17 2020-08-27 2020-08-30 2021-01-08 2020-09-27 2021-02-11 2020-10-27 2021-06-17 2020-12-01 2021-08-06 2021-01-05 2021-08-09 2022-01-05 cement of Public Urban Spac Based Selection l uction Supervision for integra es ted urban upgrading in the th ree pilot cities. MSC-MA/3.2 / Project Monito Component 3: Implementati Fixed Budget Sele Open - Internationa ring and Evaluation Baseline IBRD / 89140 Post 80,000.00 79,700.00 Signed 2020-06-29 2020-09-11 2020-07-20 2020-09-11 2020-09-02 2021-02-01 2020-09-30 2021-03-09 2020-10-30 2021-04-14 2020-12-04 2021-05-05 2021-01-08 2021-05-10 2022-01-08 on Support ction l Survey and Beneficiary Satisf action MSC-CS/2.3 / Advisory Servic Component 2: Institutional S es to State Committee on To Quality And Cost- Open - Internationa IBRD / 89140 trengthening and Capacity B Prior 800,000.00 727,887.71 Signed 2020-06-29 2020-06-30 2020-07-20 2020-08-31 2020-09-02 2021-02-11 2020-09-30 2021-03-17 2020-10-30 2021-08-20 2020-12-04 2021-12-17 2021-01-08 2021-12-17 2022-01-08 urism Development on devel Based Selection l uilding oping comprehensive strateg y MSCIUDP-CS/QCBS-04-01 / D etailed Design, Bidding Docu Component 1: Improvement ments, and Supervision for R of Urban Services and Enhan Quality And Cost- Open - Internationa estoration and adaptive reus IBRD / 89140 Prior 1,300,000.00 1,128,000.00 Signed 2019-09-30 2020-08-17 2019-10-21 2020-08-31 2019-12-04 2021-05-27 2020-01-01 2021-08-08 2020-01-31 2021-08-30 2020-03-06 2021-12-17 2020-04-10 2021-12-17 2021-04-10 cement of Public Urban Spac Based Selection l e of (i) Emir's Palace; (ii) Itali es an Hotel; and (iii) Russian Co nsulate (Makhalla Committee Building) in Kagan (Bukhara r egion) Page 2 MSC-CS/2.2 / Analysis and A Component 2: Institutional S ssessment of the Financing o Quality And Cost- Open - Internationa IBRD / 89140 trengthening and Capacity B Prior 1,000,000.00 997,864.00 Signed 2020-12-01 2020-12-02 2020-12-01 2020-12-07 2021-01-19 2021-06-02 2021-02-16 2021-07-13 2021-03-18 2021-10-13 2021-04-22 2021-12-17 2021-05-27 2021-12-17 2022-05-27 f Urban Development and Int Based Selection l uilding ergovernmental Fiscal Relati ons in Uzbekistan MSC-CS/3.3.2 / Development of presentation materials (vid Component 3: Implementati Least Cost Selecti Under Implement IBRD / 89140 Post Open - National 25,000.00 0.00 2021-10-08 2021-10-13 2021-11-15 2021-10-19 2021-12-29 2022-01-26 2022-02-25 2022-04-01 2022-05-06 2022-11-02 eo 360 and augmented realit on Support on ation y) for Eco-trail and old bazaa r in Chartak city MSC-CS/AF/1 / Consulting Se Component 1: Improvement rvices for the Development o of Urban Services and Enhan Quality And Cost- Open - Internationa IBRD / 89140 Post 485,150.00 0.00 Canceled 2022-03-07 2022-03-28 2022-05-20 2022-06-17 2022-07-22 2022-09-04 2022-10-10 2023-10-10 f a Feasibility Study for an Ad cement of Public Urban Spac Based Selection l ditional Financing Project es MSC-CS/AF/1.1 / Consulting Services for the Developmen Component 3: Implementati Consultant Qualifi Under Implement IBRD / 89140 Prior Open - National 500,000.00 0.00 2022-04-01 2022-04-01 2022-04-22 2022-04-01 2022-06-05 2022-07-05 2022-08-09 2023-02-05 t of a Feasibility Study for an on Support cation Selection ation Additional Financing Project MSIUDP-CS/QCBS-03-02/3 / Consulting services for Const Component 1: Improvement ruction Supervision of Urban Services and Enhan Quality And Cost- Open - Internationa Under Implement IBRD / 89140 Post 465,000.00 0.00 2022-04-28 2022-04-29 2022-05-23 2022-07-06 2022-08-03 2022-09-02 2022-10-07 2022-11-11 2024-11-10 for the water supply and sew cement of Public Urban Spac Based Selection l ation erage facilities of Chartak, Ka es gan and Yangiyul cities INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UDP-CS/SSS-01 / Feasibility Component 1: Improvement Studies and detailed designs TF / A7556 of Urban Services and Enhan Prior Direct Selection Direct 30,000.00 0.00 Under Review 2019-01-23 2019-02-02 2019-04-08 2019-10-05 for Year-1 Chartak Eco-trail cement of Public Urban Spac es MSCIUDP-CS/IND-02/1 / Proje Component 3: Implementati Individual Consult TF / A7556 Prior Open 9,600.00 0.00 Canceled 2019-01-23 2019-03-13 2019-04-03 2019-05-08 2019-11-04 ct Implementation Unit Mana on Support ant Selection ger MSCIUDP-CS/IND-02/4 / Soci Component 3: Implementati Individual Consult TF / A7556 Post Open 5,600.00 0.00 Canceled 2019-01-23 2018-08-31 2019-03-13 2019-04-03 2019-05-08 2019-11-04 ologist on Support ant Selection MSCIUDP-CS/IND-02/5 / Ecol Component 3: Implementati Individual Consult TF / A7556 Post Open 5,200.00 0.00 Canceled 2019-01-23 2018-09-28 2019-03-13 2019-04-03 2019-05-08 2019-11-04 ogist on Support ant Selection MSCIUDP-CS/IND-02/6 / Engi Component 3: Implementati Individual Consult TF / A7556 Post Open 5,200.00 0.00 Canceled 2019-01-23 2018-09-10 2019-03-13 2019-04-03 2019-05-08 2019-11-04 neer on Support ant Selection MSCIUDP-CS/IND-02/3 / Fina Component 3: Implementati Individual Consult TF / A7556 Post Open 4,000.00 0.00 Canceled 2019-01-23 2019-03-13 2019-04-03 2019-05-08 2019-11-04 ncial management specialist on Support ant Selection MSCIUDP-CS/IND-02/2 / Proc Component 3: Implementati Individual Consult TF / A7556 Post Open 8,800.00 0.00 Canceled 2019-03-06 2019-04-24 2019-05-15 2019-06-19 2019-12-16 urement specialist on Support ant Selection MSC-C/CS/1.1 / Consulting s ervices for the development Component 1: Improvement of detailed design, bidding d of Urban Services and Enhan IBRD / 89140 Post Direct Selection Direct 425,000.00 0.00 Canceled 2020-03-26 2020-02-03 2020-04-05 2020-02-28 2020-06-09 2021-04-01 ocuments and construction s cement of Public Urban Spac upervision of the Chartak Eco es -Trail for non-motorized mobi lity in the city of Chartak MSC-CKY/CS/2.3.1.1 / Adviso ry Services to Ministry of Con Component 2: Institutional S Individual Consult struction on modernization of IBRD / 89140 trengthening and Capacity B Post Open 132,000.00 0.00 Canceled 2020-06-29 2020-06-29 2020-08-17 2021-01-08 2020-09-07 2020-10-12 2021-04-10 ant Selection Urban and Regional Planning uilding Practices in Uzbekistan (phas e 1 - international) MSC-CKY/CS/2.3.1.2 / Adviso ry Services to Ministry of Con Component 2: Institutional S Individual Consult struction on modernization of IBRD / 89140 trengthening and Capacity B Post Open 21,000.00 16,000.00 Signed 2020-06-29 2020-06-29 2020-08-17 2020-11-25 2020-09-07 2020-12-07 2020-10-12 2021-02-25 2021-04-10 ant Selection Urban and Regional Planning uilding Practices in Uzbekistan (phas e 1 - local) MSC-C/CS/1.1.1 / Consulting services for the development Component 1: Improvement of detailed design, bidding d of Urban Services and Enhan IBRD / 89140 Post Direct Selection Direct 424,900.00 424,900.00 Signed 2020-08-05 2020-08-05 2020-08-05 2020-08-05 2020-08-05 2020-04-22 2021-10-05 ocuments and construction s cement of Public Urban Spac upervision of the Chartak Eco es -Trail for non-motorized mobi lity in the city of Chartak MSC-CKY/CS/2.1 / Consultant for Development of Detailed Designs and Bid documents, Component 2: Institutional S and Construction Supervision IBRD / 89140 trengthening and Capacity B Post Direct Selection Direct 91,600.00 91,600.00 Signed 2020-03-26 2020-04-07 2020-04-05 2020-05-13 2020-06-09 2020-05-15 2020-12-06 for the Construction / Repair uilding of Garage Premises in the citi es of Chartak, Kagan and Yan giyul. MSC-CKY/CS/2.3.1.1.1 / Advi sory Services to Ministry of C Component 2: Institutional S Individual Consult onstruction on modernization IBRD / 89140 trengthening and Capacity B Post Open 132,000.00 0.00 Canceled 2021-04-12 2021-04-14 2021-05-31 2021-06-21 2021-07-26 2022-01-22 ant Selection of Urban and Regional Planni uilding ng Practices in Uzbekistan (p hase 1 - international) MSC-C/CS/1.2 / SERVICES O N COMPLETION OF DETAILED Component 1: Improvement DESIGN, ESTIMATE, BID DOC of Urban Services and Enhan Pending Impleme IBRD / 89140 Post Direct Selection Direct 222,049.03 0.00 2021-09-25 2021-10-05 2021-12-09 2024-04-07 UMENTS AND CONSTRUCTIO cement of Public Urban Spac ntation N SUPERVISON FOR ECO-TRA es IL CONSTRUCTION IN CHART AK, NAMANGAN REGION MSC-CKY/CS/2.3.1.1.1.1 / Ad visory Services to Ministry of Component 2: Institutional S Individual Consult Construction on modernizatio IBRD / 89140 trengthening and Capacity B Post Open 132,000.00 0.00 Canceled 2021-09-24 2021-12-14 2021-11-12 2021-12-03 2022-01-07 2022-07-06 ant Selection n of Urban and Regional Plan uilding ning Practices in Uzbekistan ( phase 1 - international) MSC-CKY/CS/2.3.1.1.1.1.1 / A Component 2: Institutional S dvisory Services to Ministry o Individual Consult IBRD / 89140 trengthening and Capacity B Post Open 132,000.00 120,000.00 Signed 2021-12-21 2021-12-22 2021-12-22 2021-12-22 2021-12-22 2021-12-22 2021-12-22 2021-10-08 2022-08-19 f Construction, International ant Selection uilding consultant (Phase 1) Page 3 Page 4