PROCUREMENT PLAN (Textual Part) Project information: Country: Nigeria Project Name: Multi-Sectoral Crisis Recovery Project for North East Nigeria (MCRP) P- Number: P157891 Project Implementation Agency: MCRP PCU (Federal and States) Date of the Procurement Plan: Updated -December 22, 2017. Period covered by this Procurement Plan: From 01/12/2018 – 30/06/2019. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the FGN Public Procurement Act 2007; such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each: Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. 1. Prior Review Threshold for Goods, Works and Non-Consulting Services: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Prior Review Procurement Method Threshold (US$ Comments equivalent) ICB and LIB (Goods and services other than ≥ 5,000,000 ALL consultancy services) NCB (Goods, IT Systems and Non Consulting Services 100,000 < 5,000,000 NONE (NCB) ICB (Works) ≥ 20,000,000 ALL NCB (Works) 150,000 < 20,000,000 NONE Shopping-Goods ≤ 100,000 NONE Shopping-Works ≤ 150,000 NONE Based on Annual Training, Workshops, Study All Values Work Plans & Tours Budgets 2. Prequalification: Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines, although it is not expected that there will be need for prequalification in the procurement arrangements for the MCRP. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 2 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 3. Proposed Procedures for CDD Components (as per paragraph. 6.52 of the Procurement Regulations): Shall apply. 4. Reference to the Project Implementation Manual: Shall apply. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages (Goods and Works) indicating Bank’s Prior and Post Review. MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 3 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT a. Summary of Procurement of Goods: 1 2 3 4 5 6 Review by Estimated Ref. Packag Bank Commen Description Cost (US$ No. es (Prior / ts Million) Post) Total NCB 12.82 43 Post (Goods) Total RfQ (Goods/Non 0.04 1 Post Consulting Services) Procurement of Goods with Selection Methods and Time Schedule (Please see Annex I). b. Summary of Procurement of Civil Works 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 23.59 64 Post (Works) Total RfQ 2.29 20 Post (Works) Procurement of Civil Works with Selection Methods and Time Schedule (Please see Annex II). c. Summary of Procurement of Non- Consulting Services (TBD) 1 2 3 4 5 6 Review by Estimated Ref. Bank Commen Description Cost (US$ Packages No. (Prior / ts Million) Post) Total NCB 0.175 2 Post MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 4 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT 7. Prior Review Threshold for Consultancies: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Selection Method Comments Threshold (USD) Consultant Services-QCBS- International 1. Consulting Services ≥ 300,000 ALL 2. Engineering and Construction ≥ 500,000 Supervision Consultant Services-QCBS < 300,000.00 NONE Consultant Services-CQS < 300,000.00 NONE Consultant Services-lC >300,000.00 ALL Consultant Services-lC <300,000.00 NONE Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 8. Short list comprising entirely of National Consultants: Short list of consultants for services, estimated to cost less than $300,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. a. Summary of Consultancies 1 2 3 4 5 6 Ref. Description Estimate Package Review by Comment No. d Cost s Bank s (US$ (Prior/Post Million) ) Summary of number of 5.72 7 Prior contracts that will be let under International QCBS Summary of number of 6.45 16 Post contracts that will be let under National QCBS Summary of number of 1.74 30 Post contracts that will be let under CQS Summary of number of 0.35 3 Post contracts that will be let under MOU MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 5 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Summary of number of 0.021 3 Post contracts that will be let under Individual Consultancies MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 6 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Estimated Estimated Prior Number of Amount in Investable or Expected Procureme Pre- USD (Over Amount Post Bid- Description (List of Componen nt Procureme qualificati the Project for 18 Revie Opening Contracts) t/Sector Packages nt Method on Life) months w Date WORKS BORNO Construction Of 18-No Double Classroom Blocks in Ngohi, Biji-Biji, Ngulde, C2/Educati Post Tue-19-Jun- Rumirgo, Chul on 3 NCB No 708,196.72 354,098.36 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-19-Jun- Bama (Banki Town) on 2 NCB No 393,442.62 314,754.10 Review 18 Reconstruction Of 39- No. Double Classroom Block in C2/Educati Post Damasak, Mobbar on 4 NCB No 575,409.84 71,926.23 Review Tue-24-Jul-18 Construction Of 15- No. Double Classroom Block - C2/Educati Post Gajibo, Logomane (Dikwa) on 2 NCB No 590,163.93 147,540.98 Review Tue-24-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 7 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 25 No. Double Classroom Block C2/Educati Post GUZAMALA on 2 NCB No 983,606.56 245,901.64 Review Tue-24-Jul-18 Construction Of 20- No. Double Classroom Block - Kukawa Town, Baga, Cross- C2/Educati Post Tue-18-Sep- Kauwa on 2 NCB No 786,885.25 196,721.31 Review 18 Construction Of 10- No. Double Classroom Block - C2/Educati Post Tue-18-Sep- Monguno on 1 NCB No 393,442.62 98,360.66 Review 18 Construction Of 4- No. Double Classroom Block in C2/Educati Post Tue-20-Nov- Ajiri. Mafa on 1 NCB No 157,377.05 39,344.26 Review 18 Renovation Of 20- No. Double Classroom Blockin C2/Educati Post Tue-20-Nov- Damboa Town -Abadam on 2 NCB No 295,081.97 73,770.49 Review 18 Renovation Of 31- No. Double Classroom Block - C2/Educati Post Tue-23-Oct- Bama on 2 NCB No 457,377.05 114,344.26 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 8 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction Of 3-No. C2/Educati Post Tue-18-Sep- Educational Office -Kukawa on 1 NCB No 196,721.31 98,360.66 Review 18 Construction Of 2-No. Educational Office - C2/Educati Post Tue-20-Nov- Konduga on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 2-No. Educational Office -Hawul C2/Educati Post Tue-23-Oct- Sakwa, Kwajafa on 1 NCB No 131,147.54 32,786.89 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Askira-Uba on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 4-No Vip C2/Educati Post Tue-18-Dec- Toilets -Mafa on 1 RfQ No 59,016.39 47,213.11 Review 18 Construction Of 5-No Vip C2/Educati Post Tue-18-Dec- Toilets -Monguno on 1 RfQ No 73,770.49 59,016.39 Review 18 Renovation Of 1-No. Educational Office - C2/Educati Post Tue-18-Dec- Damboa on 1 RfQ No 18,032.79 4,508.20 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 9 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation Of 1-No. Educational Office and 1- No. Principal's Quarters - Benisheik, Kaga- Benisheik, C2/Educati Post Tue-23-Oct- Kaga on 1 RfQ No 42,622.95 16,803.28 Review 18 Rehabilitation of 66KM C2/Transpo 1,223,144. Prior Tue-27-Feb- Maiduguri to Bama road rt 1 NCB No 9,785,152.68 08 Review 18 Rehabilitation of 1 Ngala C2/Transpo Prior Tue-27-Feb- Bridge rt 1 NCB No 2,295,081.97 483,983.71 Review 18 C2/Transpo Post Tue-27-Feb- Rehabilitation of Biu bridge rt 1 NCB No 902,111.48 73,770.49 Review 18 Construction of galameri- dusuman-zabarmari- C2/Transpo Prior Tue-27-Feb- gongulong feeder road rt 1 NCB No 1,104,625.69 59,016.39 Review 18 RehabilitatIon of 3 General Hospital in ABADAM, ASKIRA UBA, KALA-BALGEe and Rehabilitation of Prior Tue-27-Mar- comprehensive Healthcare C2/Health 3 NCB No 1,555,779.01 986,195.83 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 10 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT center (Civil Works, Solar Borehole, Fence & Security Post) Construction of PHC for 15 2,254,098. Prior Tue-27-Mar- LGAs C2/Health 5 NCB No 3,606,557.38 36 Review 18 Rehabilitation of Borno C2/Educati Post Tue-24-Apr- State Library on 2 NCB No 557,377.05 34,426.23 Review 18 Rehabilitation of Umar Ibn C2/Educati Post Tue-24-Apr- Ibrahim college Bama on 2 NCB No 557,377.05 278,688.52 Review 18 Construction of Solar Powered Boreholes (2Nos) in Umar Ibn Ibrahim college Bama Solar Lighting System to Borno C2/Educati Post Tue-24-Apr- Library on 1 NCB No 196,721.31 98,360.66 Review 18 Rehabilitation of Court Buildings in Bama Gwoza C2/Public Post Tue-22-May- Dikwa Mobbar Buildings 4 RfQ No 393,442.62 49,180.33 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 11 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Local Govt Secretariats in Kukawa, Monguno, biu ,Abadam, Kala-Balge, Marte, C2/Public 1,229,508. Post Tue-05-Jun- Magumeri, Guzamala Buildings 8 RfQ No 1,967,213.11 20 Review 18 Rehabilitation of Traditional Rulers' Konduga , Monguno, Kukawa, Nganzai, Baga, Marte, Ngala, Abadam, Guzamala, C2/Public Post Tue-05-Jun- Kwajafa, Kumshe Buildings 6 RfQ No 1,442,622.95 180,327.87 Review 18 Provision of Community Resource Centres in 20 C2/Public Post LGAs Buildings 10 NCB No 2,295,081.97 860,655.74 Review Thu-05-Jul-18 Construction of Handpump Wells in Bama (3) Chibok (5), Biu (5), Mafa(3), Hawul (5), Askira/Uba(5), Konduga(4), Jere(5) Dikwa Post Fri-03-Aug- (3), Gwoza(5), C2/WASH 10 RfQ No 140,983.61 35,245.90 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 12 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Construction of Solar Powered Boreholes in Askira Uba Gwoza(4),Bama(4), Ngala(3), Damboa(3) Jere(4),Kukawa(3), Biu(2),Konduga(3), Gubio(3), Askira/Uba(3), Magumeri(3), Marte(3), Mobbar(3), Monguno(3), Dikwa(2), Mafa(3), Abadam(3), Nganzai(3), Guzamala(3), Kaga(2), Chibok(2), Kala/Balge(3), Hawul(2)(To include 2Nos 5,000lt Plastic water tanks on a 1.5m raised platform , five fetching points/tap gallery, chain link 3,501,639. Post Wed-25-Jul- perimeter fence) C2/WASH 14 NCB No 4,668,852.46 34 Review 18 REHABILITATION OF LOCAL GOVERNMENT LODGES (Marte, Kaga, Chibok, Magumeri, Gwoza, Kala- Balge, Ngala, Guzamala, Abadam, Hawul, C2/Public Post Tue-21-Aug- Askira/Uba, Bama) Buildings 6 NCB No 1,311,475.41 786,885 Review 18 Rehabilitationof Traditional Rulers' Buildings Bama, Konduga, Gwoza ,Kareto, C2/Public Post Damboa , Monguno, Buildings 11 RfQ No 1,442,622.95 180,327.87 Review Thu-26-Jul-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 13 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Kukawa, Askira-Uba , Dikwa, Baga, Marte REHABILITATION OF MINISTRY BUILDING (Ngala, C2/Public Post Tue-21-Aug- Monguno) Buildings 2 NCB No 276,577 Review 18 CONSTRUCTION OF SANITATION FACILITIES IN 21 LOCAL GOVERNMENT AREAS.ABADAM (6) ASKIRA(6) BAMA(6) BIU(6) CHIBOK(6) DAMBOA(6) DIKWA(6) GUBIO(6) GWOZA(6) JERE(6) KAGA(6) KALA-BALGE(6) KONDUGA(6) KUKAWA(6) MAFA(5) MOBBAR(6) MONGUNO(6) MARTE(6) NGALA(6) NGANZAI(6) Post Wed-19-Sep- MAGUMERI(6) C2/WASH 21 NCB No 781,517 Review 18 REHABILITATION OF EXISTING NON- FUNCTIONAL BOREHOLES ABADAM (1) ASKIRA UBA (2) BIU (2) DIKWA (1) Post Tue-18-Sep- GUBIO (1) GUZAMALA (1) C2/WASH 6 NCB No 258,525 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 14 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT JERE (2) KALA BALGE (1) MAFA (2) MAGUMERI (1) MARTE (2) MOBBAR (1) NGALA (1) NGANZAI (1) Rehabilitation of 8 blocks of Laborataries (Umar Ibn C1/Educati Post Tue-18-Sep- Ibrahim college Bama) on 1 NCB No 262,295 Review 18 ADAMAWA Rehabilitation of Gulak Post Mon-14-May- Water Supply System C2/Water 1 NCB No 179,190.16 134,392.62 Review 18 Rehabilitation of Hong Post Mon-14-May- Water Supply System C2/Water 1 NCB No 116,646.90 87,485.18 Review 18 Rehabilitation of Michika Post Mon-14-May- Water supply system C2/Water 1 NCB No 138,193.44 103,645.08 Review 18 Rehabilitation of Uba Water Post Tue-15-May- Supply system C2/Water 1 NCB No 71,967.21 71,967.21 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 15 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of exisitng Water Supply sources in Post Tue-15-May- Gombi C2/Water 1 NCB No 30,475.41 30,475.41 Review 18 Construction of Uba New Post Mon-28-May- Water Supply Project C2/Water 1 NCB No 721,222.95 108,183.44 Review 18 Pella New Water Supply Post Mon-28-May- Project C2/Water 1 NCB No 555,289.34 83,293.40 Review 18 Construction of Hong New Post Mon-28-May- Water supply project C2/Water 1 NCB No 1,256,442.62 188,466.39 Review 18 Construction of Michika Post Tue-29-May- New Water supply project C2/Water 1 NCB No 1,189,261.84 178,389.28 Review 18 Construction GOMBI NEW Post Tue-29-May- WATER SUPPLY PROJECT C2/Water 1 NCB No 915,241.80 137,286.27 Review 18 Installation of 12 nos. Solar Boreholes (in secondary schools)- GSS Gombi, GDSS Garkida, GSS Hong, GDSS Pella, GSSS Uba, Post Thu-10-May- GJSS Uba, GDSS Garaha, C2/Water 1 NCB No 377,609.70 75,521.94 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 16 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT GDSS Kwarhi, GDSS Za'ah, GSS Madagli, GSS Shuwa, GSS Gulak, GCSS Shuwa Installation of 37 Nos Solar Boreholes in 37 Health Centers in 7 Local Post Thu-10-May- Governments Areas C2/Water 4 NCB No 1,164,296.59 291,074.15 Review 18 Construction of 295Nos Hand Powered Bore Holes (in 2 primary schools per 35 wards, 35 Markets, 35 Motor parls and 155 Communities across 7 Post Thu-03-May- LGAs) C2/Water 4 NCB No 1,257,377.05 503,483.61 Review 18 Construction of VIP Latrines of 3-Comp (2 Blks Post Tue-14-Aug- in 24 pri sch) C2/WASH 3 RfQ No 212,459.02 79,672.13 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Markets) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 VIP Latrine of 3-Comp (2 Post Tue-14-Aug- Blks in 26 Motor Parks) C2/WASH 3 RfQ No 230,163.93 92,065.57 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 17 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Lokwa C2/Transpo Post Mon-11-Jun- Bridge Mubi rt 1 NCB No 475,143.96 356,357.97 Review 18 Reconstruction of Main Road - Bangshika Road C2/Transpo Prior Mon-11-Jun- 2.5Km rt 1 NCB No 1,019,295.08 127,411.89 Review 18 Rehabilitation of Mubi Bazza Road with a spur to C2/Transpo 1,255,469. Prior Mon-11-Jun- Mayo Bani 45Km rt 1 NCB No 8,369,796.72 51 Review 18 Rehabilitation of PHC, Construction of Perimeter Fence and Staff Quarters (Civil Works, Solar Borehole, Fence & Security C2/Educati Prior Tue-10-Apr- Post) in 7 Communities on 7 NCB No 1,139,130.43 451,779.49 Review 18 Rehabilitation of Cottage Post Tue-10-Apr- Hospital C2/Health 1 NCB No 451,768.85 192,001.76 Review 18 Establishment of Trauma Post Thu-17-May- Center @ general hospital C2/Health 1 RfQ No 65,194.96 65,194.96 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 18 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of GSS in 10 Towns (Gombi, Hong, Uba, Shuwa, Michika, Bazza, Mubi 1, Maiha, Madagali, C2/Educati Post Mubi North) on 10 NCB No 2,305,292.65 442,327.22 Review Tue-10-Jul-18 Renovation of 25Nos C2/Educati Post Primary School over 7 LGAs on 4 NCB No 865,747.88 324,655.45 Review Tue-10-Jul-18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Song Buildings 1 NCB No 288,590.56 144,295.28 Review 18 Rehabilitation of Local Government Secretariat - C2/Public Post Thu-07-Jun- Madagali Buildings 1 NCB No 315,082.89 157,541.44 Review 18 Rehabilitation of District Head's Palace in 5 Communities (Uba, Gella, Gombi, Maiha/Pakka, C2/Public Post Thu-07-Jun- Gulak) Buildings 5 NCB No 422,463.57 158,423.84 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 19 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE Conversion of Motorised Boreholes (28 Communities in Gulani and Damaturu) into Solar Post Mon-26-Mar- Powered C2/Water 1 NCB No 334,013.66 250,510.24 Review 18 Conversion of existing Motorized powered Borehole without Overhead tank into solar powered (Gujba, Gulani, Yunusari, Damaturu,& Post Mon-26-Mar- Geidam ) C2/Water 1 NCB No 277,532.56 208,149.42 Review 18 Conversion of existing Motorized powered Borehole into solar powered and construction of New Overhead tank (Gujba, Gulani, Yunusari, Post Mon-26-Mar- Damaturu,& Geidam) C2/Water 2 NCB No 542,490.73 406,868.05 Review 18 Drilling of New Solar Powered Boreholes in Gujba, Gulani, Yunusari, Damaturu, Fika, Potiskum, Post Mon-02-Apr- Geidam & Fune C2/Water 2 NCB No 878,917.25 329,593.97 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 20 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Solar Powered Boreholes in Gulani, Gujba and Post Mon-02-Apr- Damaturu C2/Water 1 NCB No 244,228.65 183,171.49 Review 18 Construction & Upgrade of Post Wed-24-Oct- 33 nos. PHC Centres C2/Health 5 NCB No 5,386,554.10 538,655.41 Review 18 Reconstruction of Vandalized 3 Nos Post Wed-09-May- Immunization Offices C2/Health 1 RfQ No 68,618.27 68,618.27 Review 18 Renovation of 1No. General Post Mon-03-Sep- Hospital in Buni Yadi C2/Health 1 RfQ No 88,524.59 44,262.30 Review 18 Construction of 1No. Student Hostel each in College of Nursing and Midwifery Damaturu and College of Health Sciences Post Wed-22-Aug- and Technology, Nguru C2/Health 2 NCB No 983,606.56 245,901.64 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 21 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Renovation of Govt Secondary Schools in Goniri,Bara, Bularafa, ,Kananma, Damagum, Buni Yadi, Kukuwa, Gujba and C2/Educati Post Mon-09-Apr- Best Center in Goniri on 5 NCB No 2,001,760.77 800,704.31 Review 18 Renovation of Dokshi C2/Educati Post Mon-09-Apr- Primary school, Gulani on 1 NCB No 168,034.42 67,213.77 Review 18 Rehabilitation of Local Government Office Secretariat in Gujba and C2/Public Post Wed-09-May- Potiskum Buildings 2 NCB No 472,529.40 75,459.62 Review 18 Rehabilitation of Development Offices in Gujba , Gulani, Yunusari & C2/Public Post Wed-09-May- Geidam Buildings 1 RfQ No 62,203.18 15,550.80 Review 18 Provision of Community Resource Centres in all 17 C2/Public Post Wed-23-May- LGAs Buildings 5 NCB No 1,950,819.67 731,557.38 Review 18 Rehabilitation of Audit C2/Public Post Wed-26-Sep- Office Buildings 1 RfQ No 63,078.12 15,769.53 Review 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 22 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Rehabilitation of Zonal C2/Public Post Wed-26-Sep- Statistical Office Buildings 1 RfQ No 50,491.80 25,245.90 Review 18 Rehabilitation ofCultural Buildings (District Head's Palace) in Buni Yadi and C2/Public Post Mon-27-Aug- Damagum Buildings 2 NCB No 446,682.62 111,670.66 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Agency for Mass Literacy Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 Rehabilitation of Government Buildings; C2/Public Post Mon-11-Jun- Town Engineers Office Buildings 1 RfQ No 121,445.24 60,722.62 Review 18 GOODS BORNO Supply of Returnee C1/Transiti Resettlement Kits Bama, onal 2,216,737. Tue-13-Feb- Dikwa, Gwoza, Ngala, Support 4 NCB No 2,216,737.30 30 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 23 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Monguno, Damboa, Gudumbali, Mobbar, Kala Balge) Supply of Agricultural Support kits with Seeds, Fertilizers and Small Work Farm Tools (Bama, Biu, Gwoza, Ngala, Monguno, C1/Transiti Damboa, Askira, Mobbar, onal Tue-13-Feb- Kukawa) Support 3 NCB No 681,729.10 681,729.10 Post 18 Supply of Small Animals (Bama, Mafa, Gwoza, Ngala, Monguno, Damboa, C1/Transiti Chibok, Nganzai, Kala onal Tue-20-Feb- Balge) Support 3 NCB No 788,935.25 788,935.25 Post 18 Supply of Non-agricultural Livelihood Kits (Bama, Dikwa, Gwoza, Ngala, C1/Transiti Monguno, Damboa, Chibok, onal Tue-13-Feb- Mobbar, Hawul Support 2 NCB No 227,377.05 227,377.05 Post 18 C1/Transiti Supply of Skills Acquisition onal Tue-20-Feb- Start up Kits Support 3 NCB No 737,704.92 387,295.08 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 24 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of solar electrification to 3 GENERAL HOSPITALS in ABADAM, GWOZA and KALA-BALGE and five Comprehensive Health Centre in Abadam, 2 in Gwoza, Kala-Balge, Askira - Tue-01-Jan- Uba C2/Health 3 NCB No 670,553.40 516,770.59 Post 19 Supply of Medical Equipment For 3General Hospitals in ABADAM, ASKIRA UBA, and KALA- Tue-15-Jan- BALGE C2/Health 3 NCB No 590,163.93 73,770.49 Post 19 Supply of Essential Drugs/Medical Consumables For 3 General Hospitals in HAWUL, Tue-05-Mar- MOBBAR AND DAMBOA C2/Health 3 NCB No 472,131.15 59,016.39 Post 19 Supply of Medical Equipment for Comprehensive Health Wed-09-Jan- Centers (Gwoza- Izge) C2/Health 1 NCB No 245,901.64 30,737.70 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 25 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Supply of Essential Drugs/Medical Consumables for Comprehensive Health Tue-05-Feb- Center (Gwoza-izge) C2/Health 1 NCB No 236,065.57 29,508.20 Post 19 Supply of Medical Equipment to 15 PHCs to (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-15-Jan- Mafa, Abadam) C2/Health 2 NCB No 983,606.56 122,950.82 Post 19 Supply of Essential Drugs to 15 PHCs (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Dikwa, Tue-05-Feb- Mafa, Abadam) C2/Health 2 NCB No 786,885.25 98,360.66 Post 19 Supply and Installation of Solar Inverters in 15 PHCs in (Ngala, Nganzai Kukawa, Biu, Konduga, Gubio, Askira/Uba, Guzamala, Bama, Jere, Marte, Mobbar, Tue-06-Mar- Dikwa, Mafa, Abadam) C2/Health 1 NCB No 262,295.08 65,573.77 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 26 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Furniture for Library/ Offices in the Borno State Library and Furniture for 15 blocks of classrooms in Umar Ibn ibrahim college C2/Educati Tue-19-Mar- Bama on 2 NCB No 491,803.28 245,901.64 Post 19 Books and other learning Materials including elibrary C2/Educati Tue-19-Mar- in the Borno State library on 1 NCB No 262,295.08 131,147.54 Post 19 Suppy of Computers and other accessories to the Borno State Library , Maiduguri and Umar Ibn C2/Educati Tue-19-Mar- ibrahim college Bama on 2 RfQ No 81,967.21 40,983.61 Post 19 Supply of Medical Equipment TO 3 Comprehensive Health centers IN HAWUL, MOBBAR AND DAMBOA Tue-06-Mar- (Kwajafa, Kareto, Damboa) C2/Health 1 NCB No 196,721.31 49,180.33 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 27 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Installation of solar inverters for PHC Gwoza( Tue-06-Mar- Izge) C2/Health 1 NCB No 13,114.75 13,114.75 Post 18 ADAMAWA C1/Transiti Supply of Returnee onal Mon-19-Mar- Resettlement Kits Support 2 NCB No 490,780.33 490,780.33 Post 18 Supply of Agricultural Support kits with Seeds, C1/Transiti Fertilizers and Small Work onal 1,496,508. Mon-19-Mar- Farm Tools Support 7 NCB No 1,496,508.20 20 Prior 18 C1/Transiti onal Thu-19-Apr- Supply of Small Animals Support 1 NCB No 182,950.82 182,950.82 Post 18 C1/Transiti Supply of Non-agricultural onal Mon-19-Mar- Livelihood Kits Support 1 NCB No 213,442.62 213,442.62 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 28 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Transiti Start up kits for quick to onal Mon-19-Mar- market trading Support 1 NCB No 114,754.10 114,754.10 Post 18 Housing Refurbishment Returnee Packs for Voluntary Returnees across C1/Transiti the 7 LGAs being onal Thu-14-Jun- rehabilitated. Support 2 NCB No 390,163.93 331,639.34 Post 18 Supply of Medical Equipment to PHCs in 7 communities and Cottage Hospital in Gulak C2/Health 2 NCB No 344,262.30 43,032.79 Post Thu-19-Jul-18 Supply of Essential Drugs/Medical Consumable to PHCs in 7 Communities and Cottage Hospital in Thu-01-Nov- Gulak C2/Health 2 NCB No 452,459.02 108,196.72 Post 18 Installation of Solar Inverters in 7 Rehabilitated PHCs, Cottage Hospital in Mon-06-Aug- Gulak C2/Health 3 NCB No 268,861.16 18,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 29 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Equipping of Trauma Center @ Michika General Mon-06-Aug- hospital C2/Health 1 NCB No 214,142.46 80,303.42 Post 18 Supply of Furniture to C2/Educati Thu-29-Mar- Primary Schools in 7 LGAs on 1 NCB No 245,901.64 30,737.70 Post 18 Supply of Books and Teaching/Learning Materials to Primary C2/Educati Thu-29-Mar- Schools in 7 LGAs on 1 NCB No 327,868.85 122,950.82 Post 18 Establishment of spare part supply chain/buffer Mon-16-Apr- stock for Water Facilities C2/WASH 1 NCB No 114,754.10 86,065.57 Post 18 Train the Trainer/User Workshops (i.e. 2 per LGA) for VLOM (Village Level Operation and Maintenance) WASHCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygiene Promoters) State/LGA Govt Tue-24-Apr- Officials. C2/WASH 1 NCB No 72,131.15 54,098.36 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 30 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT YOBE C1/Transiti Supply of Non Food Items onal Wed-21-Mar- (NFIs) Kits Support 3 NCB No 559,213.11 559,213.11 Post 18 C1/Transiti Supply of Agricultural kits onal 1,048,940. Wed-21-Mar- with seeds, oil, small tools Support 3 NCB No 1,048,940.98 98 Post 18 C1/Transiti onal Mon-23-Apr- Supply of Small Animals Support 3 NCB No 688,524.59 688,524.59 Post 18 C1/Transiti Non-agricultural Livelihood onal Mon-26-Mar- kits Support 2 NCB No 352,295.08 352,295.08 Post 18 C1/Transiti Supply of Skills Acquisition onal Wed-21-Mar- Start up Kits Support 3 NCB No 786,885.25 550,819.67 Post 18 Procure and distribute Plumpy Nuts for Wed-25-Apr- malnourished children in C2/Health 1 NCB No 215,438.65 32,315.80 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 31 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Gujba, Geidam and Yunusari LGAs Equipping of Trauma Mon-12-Feb- Center C2/Health 1 NCB No 214,147.54 53,536.89 Post 18 Supply of Students Textbooks and Teachers' C2/Educati Mon-17-Sep- Guides on 1 NCB No 284,062.30 71,015.57 Post 18 Supply of Laboratory Equipment Physics. C2/Educati Mon-17-Sep- Chemistry & Biology on 1 NCB No 213,114.75 53,278.69 Post 18 C2/Educati Mon-17-Sep- Supply of School Furniture on 3 NCB No 804,885.25 201,221.31 Post 18 CONSULTING SERVICES BORNO Skills Acquisition Training C1/Transiti (3Nos Consultancies across onal Mon-09-Jul- 10 LGAs) Support 3 QCBS No 491,803.28 258,196.72 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 32 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Specialized psycho-social support responding to C1/Commu needs (3Nos Consultancies nity Wed-28-Mar- across 10 LGAs) Resilience 3 QCBS No 826,229.51 619,672.13 Post 18 Consultancy for the Mobilisation and Organisation of Civic Education with Cultural and Recreational activities at Community Level with programs that respond to needs as prioritized by community based diagnosis (3Nos C1/Commu Consultancies across 10 nity Wed-11-Apr- LGAs) Resilience 3 QCBS No 442,622.95 265,573.77 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community needs, grievances; and C1/Commu redress mechanisms. (1No nity Mon-30-Apr- Consultancy) Resilience 1 QCBS No 531,147.54 318,688.52 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 33 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Post- C1/Commu Conflict Transitional Justice nity Mon-21-May- and Accountability Resilience 1 QCBS No 147,540.98 88,524.59 Post 18 Statewide sponsorship for Radio Programming for Peacebuilding Campaign and Content for dissemination (focusing on deradicalisation, grievance C1/Commu redress and peacebuilding nity Mon-04-Jun- outreach themes) Resilience 1 CQS No 475,409.84 178,278.69 Prior 18 Consultancy for Educational campaigns for the prevention of mine and unexploded ordinance accidents /Mobilisation and Sensitization Campaign on Mine Action (Unexploded C1/Commu Ordnances) (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 442,622.95 354,098.36 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 34 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Consultancy for Leadership Accountability and Transparency Training Programme (NELATTP) Targeting 20 LGA Staff and State Ministry Personal per LGA - Development of a transparency and accountability Local Governance Model through community participation C1/Commu (social accountability nity Fri-25-May- mechanisms) Resilience 1 CQS No 88,524.59 55,327.87 Post 18 Consultancy for Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Fri-25-May- Wide e 1 CQS No 49,180.33 30,737.70 Post 18 Consultancy to provide C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Fri-25-May- development e CQS No 88,524.59 55,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 35 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for LG Local officials on programme Governanc Fri-25-May- design and implementation e CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Fri-25-May- monitoring and reporting e 1 CQS No 88,524.59 55,327.87 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Fri-25-May- etc). e CQS No 88,524.59 55,327.87 Post 18 Capacity Building for 10 Local Government C1/Strengt Emergency Management hening Responders in Displaced Local and Transitional Local Governanc Fri-25-May- Government Officials e 1 CQS No 203,278.69 152,459.02 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 36 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state partners on case management of UASC C1/Program (Unaccompanied and Support to Fri-25-May- Separated Children) UASC 1 MOU No 73,770.49 59,016.39 Post 18 Training for officials of relevant State MDAs on C1/Program effective approaches to Support to Thu-28-Jun- UASC UASC 1 IC No 16,393.44 13,114.75 Post 18 Teacher Training and C1/Educati Fri-25-May- Recertification on 1 MOU No 442,622.95 77,459.02 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Targeted Health Facilities (3Nos consultancies across the state. Amount Inclusive of Workshop and per diem Mon-29-Apr- payments) C1/Health 3 QCBS No 796,721.31 298,770.49 Post 19 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 37 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health (Outreach Programs) in 27 LGAs (Over 10 Fri-25-May- engagements) C1/Health 10 CQS No 708,196.72 265,573.77 Post 18 Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Fri-25-May- management. C2/WASH 1 CQS No 98,360.66 73,770.49 Post 18 ADAMAWA Refresher Training of Existing Extension Workers C1/Transiti to support Livelihoods onal Thu-10-May- Projects Support 1 CQS No 65,573.77 65,573.77 Post 18 Training of affected farmers to apply inputs and access targeted C1/Transiti agricultural value chains onal Thu-21-Jun- and agribusiness skills Support 1 CQS No 167,216.39 167,216.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 38 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Establishment of Returnees Resettlement Registry at each LGA for Sensitization, Mobilisation and Logistics support for Safe and C1/Transiti Voluntary returns to 7 onal Thu-24-May- LGAs being rehabilitated Support 1 CQS No 61,565.57 49,252.46 Post 18 Consultancy to provide C1/Transiti Training for Bio Data onal Thu-10-May- Registration Support Support 1 IC No 1,377.05 1,101.64 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 7 Communities(establishmen t of community platforms to discuss community C1/Commu needs, grievances; and nity Mon-04-Jun- redress mechanisms Resilience 1 QCBS No 344,262.30 206,557.38 Prior 18 Diagnosis of community- specific reconciliation, peacebuilding and social C1/Commu cohesion needs and nity Thu-03-May- consequent development Resilience 2 QCBS No 344,262.30 206,557.38 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 39 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT of Civil Education Programs using Cultural and Recreational activities at Community Level (2Nos Consultancies) Provision of specialized psycho-social assessment and support responding to needs through group support, recreational, customary and socializing activities, referrals etc C1/Commu (3Nos Consultancies across nity Mon-11-Jun- the affected areas) Resilience 3 QCBS No 642,622.95 481,967.21 Post 18 Sensitization and Mobilisation Programs for Awareness against Stigmatization of Woman and Children associated C1/Commu with armed groups. (1No nity Mon-04-Jun- Consultancy) Resilience 1 QCBS No 413,114.75 247,868.85 Prior 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity C1/Commu Building within the nity Mon-18-Jun- Community Leadership and Resilience 3 QCBS No 425,960.66 255,576.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 40 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Governance Structures (3Nos Consultancies acrossthe state) C1/Citizen- Consultancy for Leadership Governmen Accountability and t Transparency Training Relationshi Thu-10-May- Programme p Building 1 CQS No 72,131.15 45,081.97 Post 18 Registration, Mapping and C1/Strengt Profiling of all local hening government structures and Local existing capacities State Governanc Mon-28-May- Wide e 1 CQS No 39,344.26 24,590.16 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Mon-28-May- development e 1 CQS No 72,131.15 45,081.97 Post 18 C1/Strengt hening Capacity building for Local programme design and Governanc Mon-28-May- implementation e 1 CQS No 72,131.15 45,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 41 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Mon-28-May- monitoring and reporting e 1 CQS No 72,131.15 45,081.97 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc Thu-21-Jun- etc). e 1 CQS No 72,131.15 45,081.97 Post 18 Hygiene Promotion Mon-17-Sep- Sensitization/Mobilization C2/WASH 1 IC No 9,180.33 6,885.25 Post 18 Hygiene Promotion Mon-12-Nov- Campaign C2/WASH 1 CQS No 85,677.59 64,258.20 Post 18 Training of Community Health Workers (CHeWs) to Staff Targeted Health Thu-13-Dec- Facilities C2/Health 1 CQS No 68,852.46 55,081.97 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 42 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Sensitization and Mobilisation for Health Mon-17-Sep- (Outreach Programs) C2/Health 1 CQS No 183,606.56 146,885.25 Post 18 Mobilization and Sensitization for Children C2/Educati Thu-31-May- Education on 1 CQS No 206,557.38 206,557.38 Post 18 Teacher Training and Recertification ( Primary C2/Educati Thu-13-Dec- and Secondary Schools ) on 1 CQS No 360,655.74 360,656.74 Prior 18 YOBE Skills Acquisition Training C1/Transiti 3 Nos Consultancies across onal Wed-25-Apr- 8 LGAs) Support 3 QCBS No 524,590.16 367,213.11 Post 18 Consultancy for Sensitization, Community Mobilization and formation of peace groups within 15 C1/Peace Wed-23-May- Communities Building 1 QCBS No 491,803.28 319,672.13 Prior 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 43 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Diagnosis of community- specific reconciliation, peacebuilding and social cohesion needs and consequentt development of Civil Education Programs using Cultural and Recreational activities at C1/Peace Mon-04-Jun- Community Level Building 1 CQS No 49,180.33 31,967.21 Post 18 Consultancy for Mediation and Alternate Dispute Resolution Capacity Building within the Community Leadership and C1/Peace Mon-04-Jun- Governance Structures Building 1 CQS No 177,049.18 115,081.97 Post 18 Radio programs on mine awareness, dispute resolution in Hausa, Kanuri C1/Peace Wed-25-Jul- and Fulfulde Building 1 CQS No 280,719.92 105,269.97 Post 18 Provision of specialized psycho-social assessment and support responding to needs (3 Nos Consultancies C1/Peace Wed-20-Jun- across 8 LGAs) Building 3 QCBS No 625,822.95 438,076.07 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 44 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Mapping and profiling of local government C1/Strengt structures and hening communities in places of Local both displacement and Governanc Thu-28-Jun- origin e 1 CQS No 39,344.26 39,344.26 Post 18 Establishment of C1/Strengt community platforms to hening discuss community needs, Local grievances; and building a Governanc Wed-06-Jun- bottom-up planning model e 1 CQS No 74,948.93 59,959.14 Post 18 Development of a transparency and accountability model C1/Strengt through community hening participation (social Local accountability Governanc Wed-06-Jun- mechanisms) e 1 CQS No 47,377.05 37,901.64 Post 18 C1/Strengt Capacity building of LG hening Officers for economic Local planning and policy Governanc Thu-28-Jun- development e 1 CQS No 55,737.70 44,590.16 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 45 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C1/Strengt hening Capacity building for Local programme design and Governanc Thu-28-Jun- implementation e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG C1/Strengt Officers for local hening governments on budget Local planning and execution, Governanc Thu-28-Jun- monitoring and reporting e 1 CQS No 55,737.70 44,590.16 Post 18 Capacity building of LG Officers for strategic communications C1/Strengt (Legislative Advocacy, hening Media relations, Local Stakeholder Management Governanc etc). e 1 CQS No 55,737.70 44,590.16 Post Thu-26-Jul-18 Sensitization, training (especially on Identification, Documentation, Tracing and Reunification and follow up) and coaching for state and non-state C1/Program partners on case Support on Thu-07-Jun- management of UASC UASC 1 CQS No 52,459.02 41,967.21 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 46 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Training for officials of C1/Program relevant MDAs on effective Support on Thu-28-Jun- approaches to UASC UASC 1 CQS No 8,196.72 6,557.38 Post 18 Menstrual Hygiene Management to support Women and Girls of productive ages to effectively maintain their Thu-17-May- menstrual hygiene C2/WASH 1 QCBS No 110,163.93 41,311.48 Post 18 Community Led Total Sanitation (CLTS) Implementation in Thu-31-May- communities C2/WASH 1 QCBS No 220,327.87 82,622.95 Post 18 Community Management training of entire Communities in the 8 proposed LGAs to effectively manage their Water, Sanitation and Mon-18-Jun- Hygiene Facilities C2/WASH 3 QCBS No 293,770.49 110,163.93 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 47 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Identification and training of Village Levels Mechanics and Local Area Mechanics on Operation and Maintenance of existing Hand Pump and Solar powered Borehole for effective utilization and Thu-17-May- management. C2/WASH 1 CQS No 98,360.66 61,475.41 Post 18 Water Safety Plan implementation in the entire Communities of the Mon-16-Jul- four LGAs. C2/WASH 1 CQS No 112,459.02 84,344.26 Post 18 Integrated Outreach Services (Up to 5 activities Thu-17-May- envisaged) C2/Health 5 QCBS No 344,262.30 129,098.36 Post 18 Training of Community Health Workers (CHeWs, VHWs, Midwives) to Staff Thu-15-Nov- Targeted Health Facilities C2/Health 1 QCBS No 501,639.34 376,229.51 Prior 18 Teacher Training and C2/Educati Mon-26-Nov- Recertification in all LGAs on 1 MOU No 278,688.52 209,016.39 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 48 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT PCNI NERSP PMC CELL Project Wide Project C3/Technic Management Consultancy al 2,000,000. Wed-11-Apr- Firm Assistance 1 QCBS No 3,000,000.00 00 Prior 18 Consultancy services for immediate- and medium- term implementation capacity building (4 C3/Technic separate Consultancies al Thu-03-May- Envisaged) Assistance 4 CQS No 536,393.44 268,196.72 Prior 18 Consultancy Services for C3/Technic Monitoring and Evaluation al Baseline Study Assistance 1 QCBS No 177,049.18 177,049.18 Post Fri-27-Apr-18 Consultancy services for setting up citizen engagement and third C3/Technic party monitoring al mechanisms Assistance 1 CQS No 177,049.00 59,016.33 Post Fri-06-Apr-18 Consultancy Services for C3/Technic Environmental Impact al Assessment Assistance 1 QCBS No 39,344.26 39,344.26 Post Fri-13-Apr-18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 49 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT NON- CONSULTING SERVICES ADAMAWA Door to Door Collection of Thu-24-May- Solid waste in 7 LGAs C2/WASH 1 NCB No 236,065.57 88,524.59 Post 18 Disposal of Waste from Door to Door Collection in Tue-13-Feb- 7 LGAs C2/WASH 1 NCB No 229,508.20 86,065.57 Post 18 OPERATIONAL COSTS PCNI NERSP PMC CELL PMC Software, Intranet and C3/Operati Tools onal Costs 3 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Video Conferencing C3/Operati Thu-25-Jan- Equipment onal Costs 1 RfQ No 131,147.54 131,147.54 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 50 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT C3/Operati Tue-27-Mar- Office Vehicles onal Costs 1 RfQ No 344,265.00 344,265.00 Post 18 BORNO STATE Procurement of 12 laptop computers, 12 laserjet printers, 4 photocopiers, 3 desktops, 15 desktops for work stations, 2 deskjet printers, HP Scanjet C3/Operati scanner onal Costs 1 RfQ No 159,240.16 159,240.16 Post Fri-27-Apr-18 Procurement of video conference equipment and C3/Operati internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post Fri-27-Apr-18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 7,000.00 7,000.00 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 51 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Sun-20-May- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Wed-14-Mar- Toyota Corolla onal Costs 1 NCB No 448,525.00 448,525.00 Post 18 ADAMAWA STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 52 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office Vehicles - 2 Toyota Prado Jeep, 3 Toyota Hilux, 1 C3/Operati Tue-27-Mar- Toyota Corolla onal Costs 1 RfQ No 518,033.00 518,033.00 Post 18 YOBE STATE Procurement of computers, printers and other C3/Operati Wed-28-Mar- accessories onal Costs 1 RfQ No 24,131.15 24,131.15 Post 18 Procurement of video conference equipment and C3/Operati Wed-28-Mar- internet connectivity onal Costs 1 RfQ No 65,574.00 65,574.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Furniture onal Costs 1 NCB No 32,786.89 32,786.89 Post 18 Procurement of 1 Video C3/Operati Wed-28-Mar- Camera, 2 DLSR Cameras, onal Costs 1 RfQ No 20,327.87 20,327.87 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 53 THE NORTH EAST MULTI-SECTORAL CRISIS RECOVERY PROJECT Procurement of 100KVA sound proof Generator, C3/Operati Mon-26-Mar- 10KVA Inverter System onal Costs 1 RfQ No 42,623.00 42,623.00 Post 18 Procurement of Office C3/Operati Tue-27-Mar- Vehicles onal Costs 1 RfQ No 468,852.46 468,852.46 Post 18 MCRP 18 MONTHS PROCUREMENT PLAN 2016 - 2018 54 PROCUREMENT Nigeria : Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria PLAN General Information Country: Nigeria 2018-06-06 Bank’s Approval Date of the Original Procurement Plan: 2023-03-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157891 GPN Date: Project Name: Multi-Sectoral Crisis Recovery Project for North Eastern Nigeria Loan / Credit No: IDA / 59880, IDA / 66490 Adamawa MCRP Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-60544- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of G IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 ulak Water Supply System tion & Improvement NG-ADAMAWA MCRP-60190- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of H IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 ong Water Supply System tion & Improvement NG-ADAMAWA MCRP-60574- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of Mi IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 chika Water supply system tion & Improvement NG-ADAMAWA MCRP-60628- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of U IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 ba Water Supply system tion & Improvement NG-ADAMAWA MCRP-60942- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of e IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-04-06 2018-04-11 2018-05-23 2018-06-22 2018-07-27 nvelope 3 xisitng Water Supply sources tion & Improvement in Gombi NG-ADAMAWA MCRP-60952- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-0 CW-RFQ / Construction of VIP IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-07-11 2018-09-05 tions nvelope 4 Latrines of 3-Comp (2 Blks in tion & Improvement 24 pri sch) NG-ADAMAWA MCRP-60083- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-0 CW-RFQ / VIP Latrine of 3-Co IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-07-11 2018-09-05 tions nvelope 4 mp (2 Blks in 26 Markets) tion & Improvement NG-ADAMAWA MCRP-60505- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-0 CW-RFQ / VIP Latrine of 3-Co IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-07-11 2018-09-05 tions nvelope 4 mp (2 Blks in 26 Motor Parks) tion & Improvement NG-ADAMAWA MCRP-60940- Infrastructure Rehabilitation CW-RFB / Rehabilitation of M Single Stage - One E 2019-02-2 IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 0.00 Canceled 2018-05-04 2018-05-09 2018-06-20 2018-07-20 2018-08-24 ubi Bazza Road with a spur t nvelope 0 tion & Improvement o Mayo Bani 45Km NG-ADAMAWA MCRP-60315- Infrastructure Rehabilitation Single Stage - One E 2019-02-1 CW-RFB / Rehabilitation of Lo IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 nvelope 6 cal Government Secretariat - tion & Improvement Madagali NG-ADAMAWA MCRP-69807- Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-03-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-08-05 2019-06-27 2018-09-30 tions nvelope mentation 9 nsion of Uba Water Supply Pr tion & Improvement oject NG-ADAMAWA MCRP-69803- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Limited 476,751.54 Signed 2018-08-01 2019-06-27 2018-09-26 2019-09-05 tions nvelope 5 nsion of Pella Water Supply P tion & Improvement roject NG-ADAMAWA MCRP-69714- Infrastructure Rehabilitation Request for Quota Single Stage - One E 1,063,388.5 2019-02-2 2021-09 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Open - National Signed 2018-07-25 2018-08-29 2019-09-05 tions nvelope 0 5 -24 nsion of Hong Water supply tion & Improvement project NG-ADAMAWA MCRP-69805- Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-03-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-08-01 2019-06-27 2018-09-26 tions nvelope mentation 5 nsion of Gombi Water Supply tion & Improvement Project NG-ADAMAWA MCRP-60578- Infrastructure Rehabilitation Single Stage - One E 2019-02-2 CW-RFB / Rehabilitation of Lo IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 525,084.68 Signed 2018-05-04 2020-02-05 2018-05-09 2020-02-18 2018-06-20 2020-03-17 2018-07-20 2020-08-06 2018-08-24 2020-08-31 nvelope 0 kwa Bridge Mubi tion & Improvement NG-ADAMAWA MCRP-69818- CW-RFQ / Rehabilitation of P Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-1 2021-09 HC, Construction of Perimete IDA / 59880 and Service Delivery Restora Post Limited 806,687.09 Completed 2018-08-21 2019-11-08 2018-10-05 2020-07-10 tions nvelope 4 -16 r Fence and Staff Quarters (C tion & Improvement ivil Works, Fence & Security Post) in 7 Communities NG-ADAMAWA MCRP-69810- CW-RFQ / Rehabilitation of Di Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-2 strict Head's Palace and Offic IDA / 59880 and Service Delivery Restora Post Limited 319,349.34 Signed 2018-08-05 2020-06-30 2018-09-30 2020-09-08 tions nvelope 9 es in 5 Communities (Uba, G tion & Improvement ella, Gombi, Maiha/Pakka, Gu lak) NG-ADAMAWA MCRP-69962- CW-RFQ / Remodeling and up Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple 2018-08-0 IDA / 59880 Post Limited 0.00 2018-07-19 2018-07-26 grade of rented office facility ject Management Support tions nvelope mentation 9 to meet the requirements of the PCU. NG-ADAMAWA MCRP-74570- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-01-2 2020-12 CW-RFQ / Rehabilitation of Lo IDA / 59880 and Service Delivery Restora Post Open - National 268,328.76 Completed 2018-08-20 2018-10-18 2020-01-23 tions nvelope 6 -22 cal Government Secretariat - tion & Improvement Song NG-ADAMAWA MCRP-59963- CW-RFB / Installation of 13 n os. Solar Boreholes (in secon Infrastructure Rehabilitation dary schools)- GSS Gombi, G Request for Quota Single Stage - One E 2019-01-0 IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-08-22 2018-09-30 DSS Garkida, GSS Hong, GDS tions nvelope 8 tion & Improvement S Pella, GSSS Uba, GJSS Uba, GDSS Garaha, GDSS Kwarhi, GDSS Za'ah, GSS Madagli, G SS Shuwa, GSS Gulak, GCSS Shuwa Page 1 NG-ADAMAWA MCRP-60629- Infrastructure Rehabilitation Single Stage - One E 2019-02-2 CW-RFB / Reconstruction of IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 0.00 Canceled 2018-05-04 2018-05-09 2018-06-20 2018-07-20 2018-08-24 nvelope 0 Main Road - Bangshika Road tion & Improvement 2.5Km NG-ADAMAWA MCRP-72562- Infrastructure Rehabilitation Single Stage - One E 2019-01-3 CW-RFB / Rehabilitation of Mi IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 0.00 Canceled 2018-08-02 2018-08-07 2018-08-21 2018-09-11 2018-10-02 nvelope 0 chika Hospital Road tion & Improvement NG-ADAMAWA MCRP-72563- Infrastructure Rehabilitation Single Stage - One E 2019-01-2 CW-RFB / Rehabilitation of ac IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National 0.00 Canceled 2018-08-02 2018-08-07 2018-08-21 2018-09-05 2018-09-23 nvelope 1 cess road to Garkida tion & Improvement NG-ADAMAWA MCRP-74493- Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-02-0 CW-RFQ / Rehabilitation of G IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-08-20 2018-10-11 tions nvelope mentation 8 arkida Water Supply System tion & Improvement NG-ADAMAWA MCRP-74494- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-02-0 CW-RFQ / Rehabilitation of M IDA / 59880 and Service Delivery Restora Post Open - National 392,382.20 Signed 2018-08-20 2018-10-11 2019-09-05 tions nvelope 8 aiha Water Supply System tion & Improvement NG-ADAMAWA MCRP-74626- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-02-0 2022-01 CW-RFQ / Rehabilitation of G IDA / 59880 and Service Delivery Restora Post Open - National 427,332.84 Completed 2018-08-20 2018-10-11 2020-09-04 tions nvelope 8 -18 eneral Hospital Michika tion & Improvement NG-ADAMAWA MCRP-69765- CW-RFQ / Renovation of GSS Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-02-1 in 10 Towns (Gombi, Hong, U IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-12-08 2018-12-14 tions nvelope mentation 2 ba, Shuwa, Michika, Bazza, M tion & Improvement ubi 1, Maiha, Madagali, Mubi North) NG-ADAMAWA MCRP-69808- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-2 CW-RFQ / Upgrade and Expa IDA / 59880 and Service Delivery Restora Post Limited 991,392.87 Signed 2018-11-20 2019-06-27 2018-12-25 2019-09-05 tions nvelope 5 nsion of Michika Water suppl tion & Improvement y project NG-ADAMAWA MCRP-89273- CW-RFQ / Construction of 5 S Infrastructure Rehabilitation olar Boreholes in 5 Sec. Schs. Request for Quota Single Stage - One E Under Imple 2019-02-2 IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-12-12 2018-12-23 , 11 in PHCs and 92 HPBH in tions nvelope mentation 1 tion & Improvement communities in Michika and Madagali LGAs of Adamawa State NG-ADAMAWA MCRP-89262- CW-RFQ / Construction of 10 Infrastructure Rehabilitation Solar Powered Boreholes in P Request for Quota Single Stage - One E Under Imple 2019-02-2 IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-12-12 2018-12-23 HCs, and 80 HPBH in Commu tions nvelope mentation 1 tion & Improvement nities in Mubi North and Mubi South LGAs of Adamawa Stat e NG-ADAMAWA MCRP-89688- CW-RFQ / Construction of 8 S Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2019-02-2 olar boreholes in 8 Sec. Schs, IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-12-12 2018-12-23 tions nvelope mentation 1 16 in PHCs and 123 HPBH in tion & Improvement communities in Gombi, Hong and Maiha LGAs NG-ADAMAWA MCRP-10140 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 9-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 25,604.58 Signed 2018-04-11 2019-06-27 2018-06-06 2019-09-05 tions nvelope 3 exisitng Water Supply source tion & Improvement s in Gombi NG-ADAMAWA MCRP-10138 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2018-12-0 3-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-04-11 2019-06-27 2018-06-06 tions nvelope mentation 3 Uba Water Supply system tion & Improvement NG-ADAMAWA MCRP-10141 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 3-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 114,778.49 Signed 2018-04-11 2019-06-27 2018-06-06 2019-09-05 tions nvelope 3 Michika Water supply system tion & Improvement NG-ADAMAWA MCRP-10141 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 2-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 152,854.94 Signed 2018-04-11 2019-06-27 2018-06-06 2019-09-05 tions nvelope 3 Gulak Water Supply System tion & Improvement NG-ADAMAWA MCRP-10141 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-0 2021-07 0-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 94,375.21 Signed 2018-04-11 2019-06-27 2018-06-06 2019-09-05 tions nvelope 3 -13 Hong Water Supply System tion & Improvement NG-ADAMAWA MCRP-10139 4-CW-RFQ / Construction VIP Infrastructure Rehabilitation Latrine of 3-Compartment (2 Request for Quota Single Stage - One E 2019-03-0 2020-11 IDA / 59880 and Service Delivery Restora Post Limited 199,279.37 Completed 2018-07-11 2019-02-25 2018-09-05 2019-03-25 Blocks in 7 Primary Schools, tions nvelope 4 -30 tion & Improvement 7 Motor Parks and 8 Markets in Mubi-North & Mubi-South L GAs) NG-ADAMAWA MCRP-10144 3-CW-RFQ / Construction VIP Infrastructure Rehabilitation Latrine of 3-Compartment (2 Request for Quota Single Stage - One E 2019-03-0 2020-06 IDA / 59880 and Service Delivery Restora Post Limited 326,673.74 Completed 2018-07-11 2019-02-25 2018-09-05 2019-04-16 Blocks in 10 Primary schools, tions nvelope 4 -23 tion & Improvement 12 motor parks and 9 market s in Gombi, Hong & Maiha LG As ) NG-ADAMAWA MCRP-10138 6-CW-RFQ / Construction of V Infrastructure Rehabilitation IP Latrines of 3-Compartment Request for Quota Single Stage - One E 2019-03-0 2021-03 IDA / 59880 and Service Delivery Restora Post Limited 228,848.59 Completed 2018-07-12 2019-02-25 2018-09-06 2019-03-28 (2 Blocks in 8 Primary School tions nvelope 5 -30 tion & Improvement s, 8 Motor Parks and 8 Marke ts in Michika & Madagali LGA s) NG-ADAMAWA MCRP-14590 7-CW-RFB / Rehabilitation of Infrastructure Rehabilitation Single Stage - One E 12,066,531. 2021-07-3 2021-11 Three (3) Roads in Three (3) IDA / 59880 and Service Delivery Restora Prior Request for Bids Open - National Signed 2019-11-18 2020-02-05 2019-11-23 2020-02-18 2019-12-18 2020-03-17 2020-01-09 2020-08-07 2020-01-30 2020-09-01 nvelope 53 0 -11 Local Government Areas of A tion & Improvement damawa State, Mubi, Michika and Gombi. NG-ADAMAWA MCRP-17761 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-04-0 0-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 416,527.96 Signed 2020-08-23 2021-10-05 2020-10-11 2021-12-20 tions nvelope 9 Male and Female Hostels in tion & Improvement GSS Michika NG-ADAMAWA MCRP-17756 Infrastructure Rehabilitation 4-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E 2021-04-0 IDA / 59880 and Service Delivery Restora Post Limited 183,055.72 Signed 2020-08-24 2021-10-12 2020-10-08 2021-12-10 Classrooms and Teachers Off tions nvelope 6 tion & Improvement ices at GTC Shuwa Page 2 NG-ADAMAWA MCRP-17756 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-03-2 5-CW-RFQ / Construction of 5 IDA / 59880 and Service Delivery Restora Post Limited 175,928.00 Signed 2020-08-09 2021-02-02 2020-09-27 2021-03-31 tions nvelope 6 0 Hand Pump Boreholes in Se tion & Improvement ven LGAs NG-ADAMAWA MCRP-17758 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Imp 2021-04-0 2-CW-RFQ / Construction of 3 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-08-15 2020-10-03 tions nvelope lementation 1 0 nos VIP Latrines in Seven L tion & Improvement GAs NG-ADAMAWA MCRP-15867 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-03-2 5-CW-RFQ / Upgrade and Exp IDA / 59880 and Service Delivery Restora Post Limited 272,410.73 Signed 2020-08-05 2020-07-31 2020-09-23 2020-08-28 tions nvelope 2 ansion of Gulak water supply tion & Improvement scheme NG-ADAMAWA MCRP-16938 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-03-2 2-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 273,739.87 Signed 2020-07-20 2021-10-12 2020-09-21 2021-12-07 tions nvelope 0 Dermatology Centre, Virgwi tion & Improvement NG-ADAMAWA MCRP-17760 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Imp 2021-04-2 8-CW-RFQ / Renovation of 8 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-09-05 2020-10-24 tions nvelope lementation 2 Secondary Schools in 7 LGAS tion & Improvement NG-ADAMAWA MCRP-17756 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2021-03-2 1-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-08-08 2020-09-26 tions nvelope mentation 5 7 nos Primary Schools tion & Improvement NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2021-04-1 7-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-08-31 2020-10-19 tions nvelope mentation 7 7 nos. Primary Health Care C tion & Improvement enter (PHCC) NG-ADAMAWA MCRP-69811- Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 2021-02-1 CW-RFQ / Renovation of 17 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-07-12 2020-08-14 tions nvelope mentation 0 Nos Primary School over 7 LG tion & Improvement As NG-ADAMAWA MCRP-60939- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-02-1 CW-RFQ / Construction of Ne IDA / 59880 and Service Delivery Restora Post Open - National 226,300.17 Signed 2020-07-07 2020-08-18 2020-09-01 tions nvelope 4 w Trauma Center @ General tion & Improvement Hospital mubi NG-ADAMAWA MCRP-15667 Infrastructure Rehabilitation 0-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Under Imple 2021-01-2 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-07-27 2020-09-01 Primary Schools in Michika a tions nvelope mentation 9 tion & Improvement nd Madagali LGAs of Adama wa State NG-ADAMAWA MCRP-15667 Infrastructure Rehabilitation 2-CW-RFQ / Renovation of Go Request for Quota Single Stage - One E Pending Imp 2021-03-0 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-08-02 2020-09-07 vernment Secondary Schools tions nvelope lementation 6 tion & Improvement in Michika and Madagali LGA s of Adamawa State NG-ADAMAWA MCRP-10143 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2018-12-2 2-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-05-05 2018-06-30 tions nvelope 7 Local Government Secretaria tion & Improvement t - Madagali NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation 2021-06-0 6-CW-DIR / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 Canceled 2020-10-29 2020-11-03 2020-12-08 6 Michika General Hospital Roa tion & Improvement d (additional 2KM) NG-ADAMAWA MCRP-69800- Infrastructure Rehabilitation Request for Quota Single Stage - One E 2019-03-1 CW-RFQ / Rehabilitation of C IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2018-07-22 2018-09-16 tions nvelope 5 ottage Hospital in Madagali tion & Improvement NG-ADAMAWA MCRP-27780 Request for Infrastructure Rehabilitation 7-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-01-2 IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-07-05 2022-07-31 General Hospital Garkida, Go tions nvelope Non Bank-SP lementation 7 tion & Improvement mbi LGA in Adamawa State D) NG-ADAMAWA MCRP-27803 Request for Infrastructure Rehabilitation 8-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-01-2 IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-07-05 2022-07-31 Cottage Hospital Maiha, Maih tions nvelope Non Bank-SP lementation 7 tion & Improvement a LGA in Adamawa State D) NG-ADAMAWA MCRP-27804 Request for 2-CW-RFQ / Provision of Hand Infrastructure Rehabilitation Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-12-0 Pump Boreholes (HPBHs) in V IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-04-27 2022-06-10 tions nvelope Non Bank-SP lementation 7 entiilated Improved Pit (VIP) tion & Improvement D) Toilets locations in Adamawa State. NG-ADAMAWA MCRP-27773 Request for Infrastructure Rehabilitation 8-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-12-1 IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-05-17 2022-06-16 Area Social Welfare/ Youth D tions nvelope Non Bank-SP lementation 3 tion & Improvement evelopment Offices in Adama D) wa State. Request for B NG-ADAMAWA MCRP-27778 Infrastructure Rehabilitation ids - Small W 7-CW-RFQ / Rehabilitation an Single Stage - One E 2023-05-0 IDA / 66490 and Service Delivery Restora Post Request for Bids Limited orks SPD (1 e 0.00 Canceled 2022-09-22 2022-09-27 2022-10-18 2022-11-01 2022-11-09 d maintenance of 13 KM Mich nvelope 8 tion & Improvement nvelope proc ika ess) - Vi- Rhuro Road with Culvert s NG-ADAMAWA MCRP-17627 Request for Infrastructure Rehabilitation 7-CW-RFQ / Construction of 2 Request for Quota Single Stage - One E Quotations ( 2021-03-2 2022-05 IDA / 59880 and Service Delivery Restora Post Limited 743,624.21 Completed 2020-08-08 2021-01-04 2020-09-22 2021-03-03 1 Solar Powered Boreholes in tions nvelope Non Bank-SP 1 -19 tion & Improvement Michika and Madagali LGAs o D) f Adamawa State. NG-ADAMAWA MCRP-15626 Request for Infrastructure Rehabilitation 2-CW-RFQ / Construction of S Request for Quota Single Stage - One E Quotations ( 2021-05-0 IDA / 59880 and Service Delivery Restora Post Limited 544,079.48 Signed 2020-09-09 2021-02-02 2020-11-04 2022-03-18 olar Powered Boreholes in th tions nvelope Non Bank-SP 3 tion & Improvement e Insurgency affected LGAs o D) f Adamawa State. NG-ADAMAWA MCRP-26445 Request for Infrastructure Rehabilitation 0-CW-RFQ / Rehabilitation of Request for Quota Single Stage - One E Quotations ( Under Imple 2022-07-1 IDA / 59880 and Service Delivery Restora Post Limited 0.00 2021-11-27 2022-01-11 Government Secondary Scho tions nvelope Non Bank-SP mentation 0 tion & Improvement ol (GSS) Madagali D) Request for NG-ADAMAWA MCRP-28273 Quotations - 6-CW-NULL / Rehabilitate/Up Infrastructure Rehabilitation Request for Quota Single Stage - One E Small Works 2023-03-0 grade 1 no. International Catt IDA / 66490 and Service Delivery Restora Post Limited 0.00 Canceled 2022-08-07 2022-09-04 tions nvelope (Emergency) 3 le Market including veterinar tion & Improvement SPD -Compet y clinics in Adamawa State. itive NG-ADAMAWA MCRP-27780 Request for B 1-CW-RFQ / Rehabilitation an Infrastructure Rehabilitation ids - Small W Single Stage - One E 2023-05-0 d maintenance of Michika - Vi IDA / 66490 and Service Delivery Restora Post Request for Bids Limited orks SPD (1 e 0.00 Canceled 2022-09-22 2022-09-27 2022-10-18 2022-11-01 2022-11-09 nvelope 8 llekwa - Road tion & Improvement nvelope proc Dzurok farming Community ( ess) 15Km) Page 3 NG-ADAMAWA MCRP-27812 Request for B 7-CW-RFQ / Rehabilitation an Infrastructure Rehabilitation ids - Small W Single Stage - One E 2023-05-0 d maintenance of 13km Gella IDA / 66490 and Service Delivery Restora Post Request for Bids Limited orks SPD (1 e 0.00 Canceled 2022-09-22 2022-09-27 2022-10-18 2022-11-01 2022-11-08 nvelope 7 - tion & Improvement nvelope proc Kwaja - Dumo road with drai ess) nage facilities Request for B NG-ADAMAWA MCRP-27781 Infrastructure Rehabilitation ids - Small W Single Stage - One E 2023-05-0 0-CW-RFQ / Rehabilitation an IDA / 66490 and Service Delivery Restora Post Request for Bids Limited orks SPD (1 e 0.00 Canceled 2022-09-22 2022-09-27 2022-10-18 2022-11-01 2022-11-08 nvelope 7 d maintenance of 13 Km Mub tion & Improvement nvelope proc i-Bahuli Road ess) NG-ADAMAWA MCRP-17761 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-05-0 6-CW-RFQ / Rehabilitation of IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-09-07 2020-11-02 tions nvelope 1 road network in Madagali To tion & Improvement wnship Request for NG-ADAMAWA MCRP-29712 Infrastructure Rehabilitation Quotations ( 2023-01-1 4-CW-DIR / Rehabilitation of r IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 Signed 2022-06-22 2022-08-09 2022-06-27 2022-08-10 2022-07-18 Non Bank-SP 4 oad network in Madagali Tow tion & Improvement D) nship NG-ADAMAWA MCRP-29707 Request for Infrastructure Rehabilitation 9-CW-RFQ / Provision of Solar Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-04-1 IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-09-18 2022-10-19 Powered Bore Holes (SPBH) i tions nvelope Non Bank-SP lementation 7 tion & Improvement n Sanitation Centers and sele D) cted communities NG-ADAMAWA MCRP-29710 Request for Infrastructure Rehabilitation 6-CW-RFQ / Provision of Solar Request for Quota Single Stage - One E Quotations ( Under Imple 2023-04-1 IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-09-18 2022-08-24 2022-10-19 Powered Bore holes (SPBHs) i tions nvelope Non Bank-SP mentation 7 tion & Improvement n Primary Health Care Center D) s (PHCCs) NG-ADAMAWA MCRP-17628 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2021-01-0 1-CW-RFQ / Refencing of Peri IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-08-23 2020-09-30 tions nvelope 9 meter Fence at GSS Gombi ( tion & Improvement Entire School) NG-ADAMAWA MCRP-33310 Request for 8-CW-RFQ / Renovation of Go Infrastructure Rehabilitation Request for Quota Single Stage - One E Quotations ( Under Imple 2023-08-1 vernment Day Secondary Sc IDA / 59880 and Service Delivery Restora Post Limited 0.00 2023-01-17 2023-02-15 tions nvelope Non Bank-SP mentation 4 hool UBA in Hong Local Gove tion & Improvement D) rnment Area of Adamawa Sta te. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-59598- Infrastructure Rehabilitation Single Stage - One E GO-RFB / Supply of Furniture IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-02-23 2018-02-28 2018-04-11 2018-05-11 2018-06-15 2018-12-12 nvelope to Primary Schools in 7 LGAs tion & Improvement NG-ADAMAWA MCRP-59960- Infrastructure Rehabilitation GO-RFB / Supply of Books an Single Stage - One E IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-02-23 2018-02-28 2018-04-11 2018-05-11 2018-06-15 2018-12-12 d Teaching/Learning Materia nvelope tion & Improvement ls to Primary Schools in 7 LG As NG-ADAMAWA MCRP-60401- Infrastructure Rehabilitation GO-RFB / Establishment of sp Single Stage - One E IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-03-13 2018-03-18 2018-04-29 2018-05-29 2018-07-03 2018-12-30 are part supply chain/buffer s nvelope tion & Improvement tock for Water Facilities NG-ADAMAWA MCRP-60936- GO-RFB / Train the Trainer/Us er Workshops (i.e. 2 per LGA) Infrastructure Rehabilitation for VLOM (Village Level Oper Single Stage - One E IDA / 59880 and Service Delivery Restora Post Request for Bids Open - National 0.00 Canceled 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2019-01-05 ation and Maintenance) WAS nvelope tion & Improvement HCOMS, (WASH Committees at LGA Level, WASH Units @ LGAs, VHPs (Voluntary Hygie ne Promoters) State/LGA Gov t Officials. NG-ADAMAWA MCRP-60957- Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple GO-RFQ / Procurement of 1 V IDA / 59880 Post Open - National 0.00 2018-02-18 2018-04-15 2018-10-12 ject Management Support tions nvelope mentation ideo Camera, 2 DLSR Camera s, NG-ADAMAWA MCRP-74572- GO-DIR / Procurement of Vid Technical Assistance and Pro IDA / 59880 Post Direct Selection Direct 67,807.55 Completed 2018-08-20 2018-10-22 2018-08-25 2018-09-18 2018-09-18 2018-11-08 2018-12-17 2019-01-09 eo Conference Equipment an ject Management Support d Internet Connectivity (Dedi cated) for 1 year. NG-ADAMAWA MCRP-69762- GO-RFQ / Procurement of 1 S Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple port Utility Vehicle, 1 Eightee IDA / 59880 Post Limited 0.00 2018-07-21 2018-09-15 2019-03-14 ject Management Support tions nvelope mentation n Seater Bus, 3 Double Cabin Pick Up Vans and 1 Four Doo r Sedan. NG-ADAMAWA MCRP-69822- Strengthening Peace Buildin Request for Quota Single Stage - One E GO-RFQ / Provission of Small IDA / 59880 g, Stability and Social Cohesi Post Limited 171,132.92 Completed 2018-08-23 2020-06-30 2018-09-16 2020-08-14 2018-10-31 2020-09-08 tions nvelope Animals For Livelihood Suppo on rt NG-ADAMAWA MCRP-69753- Strengthening Peace Buildin Request for Quota Single Stage - One E GO-RFQ / Non Agricultural Liv IDA / 59880 g, Stability and Social Cohesi Post Limited 500,323.91 Completed 2018-08-22 2018-11-20 2018-10-17 2018-12-17 2018-12-26 2019-02-27 tions nvelope elihood Kits. on NG-ADAMAWA MCRP-69823- Infrastructure Rehabilitation Request for Quota Single Stage - One E GO-RFQ / Equipping of Traum IDA / 59880 and Service Delivery Restora Post Limited 383,168.90 Signed 2018-08-05 2022-03-08 2018-09-30 2022-04-04 2019-03-29 tions nvelope a Center @ Mubi General hos tion & Improvement pital NG-ADAMAWA MCRP-60958- Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple GO-RFQ / Procurement of Offi IDA / 59880 Post Open - National 0.00 2018-08-15 2018-09-19 2018-09-26 ject Management Support tions nvelope mentation ce Furniture NG-ADAMAWA MCRP-74000- GO-RFQ / Supply of Teaching Infrastructure Rehabilitation Request for Quota Single Stage - One E Materials, Labrotary Equipme IDA / 59880 and Service Delivery Restora Post Limited 668,444.08 Completed 2018-08-20 2019-03-07 2018-09-27 2019-04-12 2019-01-05 2019-06-21 tions nvelope nts and First aid Kits to Reha tion & Improvement bilitated Secondary Schools. NG-ADAMAWA MCRP-74210- Strengthening Peace Buildin Request for Quota Single Stage - One E GO-RFQ / Supply of Non-Food IDA / 59880 g, Stability and Social Cohesi Post Limited 379,396.71 Completed 2018-08-21 2018-09-07 2018-09-28 2018-12-10 2018-12-27 2019-01-28 tions nvelope Item Kits For House-hold Sup on port Page 4 NG-ADAMAWA MCRP-74608- GO-RFQ / Installation of Solar Infrastructure Rehabilitation Request for Quota Single Stage - One E Inverters in 7 Rehabilitated P IDA / 59880 and Service Delivery Restora Post Open - National 243,777.83 Signed 2018-08-20 2018-10-11 2021-12-20 2019-01-19 2022-03-18 tions nvelope HCs, Cottage Hospital in Gula tion & Improvement k and General Hospital Michi ka. NG-ADAMAWA MCRP-74618- GO-RFQ / Supply of Medical E Infrastructure Rehabilitation Request for Quota Single Stage - One E quipment to Rehabilitated P IDA / 59880 and Service Delivery Restora Post Open - National 501,499.87 Completed 2018-08-20 2018-10-11 2020-12-10 2019-01-14 2021-03-24 tions nvelope HCs in 7 communities, Cotta tion & Improvement ge Hospital in Gulak and Gen eral Hospital Michika. NG-ADAMAWA MCRP-74624- Infrastructure Rehabilitation GO-RFQ / Supply of Classroo Request for Quota Single Stage - One E Under Imple IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-08-20 2018-10-11 2019-01-19 m Furniture for all Renovated tions nvelope mentation tion & Improvement Secondary Schools. NG-ADAMAWA MCRP-59138- Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple GO-RFQ / Procurement of Co IDA / 59880 Post Open - National 0.00 2018-02-18 2018-04-15 2018-07-14 ject Management Support tions nvelope mentation mputers, Printers and other a ccessories NG-ADAMAWA MCRP-60359- GO-RFQ / Procurement of 60 Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Open - National 28,945.26 Completed 2018-02-18 2018-04-15 2018-09-04 2018-10-12 2018-11-09 KVA sound proof Generator, ject Management Support tions nvelope 10KVA Inverter System NG-ADAMAWA MCRP-69797- Strengthening Peace Buildin GO-RFQ / Provision of Agricul Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Prior Limited 0.00 Canceled 2018-11-03 2018-12-01 2019-01-15 tural Support kits with Seeds, tions nvelope on Fertilizers and Small Work Fa rm Tools NG-ADAMAWA MCRP-69802- GO-RFQ / Supply of Essential Infrastructure Rehabilitation Drugs/Medical Consumable t Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Open - National 597,201.60 Completed 2018-12-17 2019-02-07 2020-12-10 2019-05-18 2020-12-31 o Rehabilitated PHCs in 7 Co tions nvelope tion & Improvement mmunities, Cottage Hospital in Gulak and General Hospita l Michika. NG-ADAMAWA MCRP-10054 Strengthening Peace Buildin Request for Quota Single Stage - One E 3-GO-RFQ / Supply of Cereals IDA / 59880 g, Stability and Social Cohesi Post Limited 654,880.67 Completed 2018-11-03 2019-02-27 2018-12-29 2019-03-21 2019-06-27 2019-05-28 tions nvelope and Legumes Seeds, on NG-ADAMAWA MCRP-10055 Strengthening Peace Buildin Request for Quota Single Stage - One E 1-GO-RFQ / Supply of Fertiliz IDA / 59880 g, Stability and Social Cohesi Post Limited 504,611.67 Completed 2018-11-03 2019-02-27 2018-12-29 2019-03-13 2019-06-27 2019-05-14 tions nvelope er and Small Work Farm Tool on s NG-ADAMAWA MCRP-10142 Infrastructure Rehabilitation 4-GO-RFQ / Establishment of Request for Quota Single Stage - One E Pending Impl IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-03-18 2018-05-13 2018-11-09 spare part supply chain/buffe tions nvelope ementation tion & Improvement r stock for Water Facilities NG-ADAMAWA MCRP-10137 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 9-GO-RFQ / Supply of Furnitu IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-02-28 2018-04-25 2018-10-22 tions nvelope mentation re to Primary Schools in 7 LG tion & Improvement As NG-ADAMAWA MCRP-10141 Infrastructure Rehabilitation 9-GO-RFQ / Supply of Books Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 273,530.41 Completed 2018-02-28 2019-03-07 2018-04-25 2019-04-10 2018-10-22 2019-04-25 and Teaching/Learning Mate tions nvelope tion & Improvement rials to Primary Schools in 7 L GAs NG-ADAMAWA MCRP-10960 0-GO-RFQ / Installation of CC Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 59880 Post Limited 22,640.15 Completed 2019-04-17 2019-09-03 2019-05-06 2019-09-30 2019-05-20 2019-10-03 TV and Intercom System for t ject Management Support tions nvelope he Adamawa MCRP PCU Offic e NG-ADAMAWA MCRP-10969 Infrastructure Rehabilitation 3-GO-RFQ / Networking of Off Request for Quota Single Stage - One E Pending Impl IDA / 59880 and Service Delivery Restora Post Limited 0.00 2019-04-18 2019-05-06 2019-05-20 ice Computer Systems, print tions nvelope ementation tion & Improvement ers and other accessories. NG-ADAMAWA MCRP-13354 Infrastructure Rehabilitation 8-GO-RFQ / Branding and Pac Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 20,744.10 Completed 2019-07-28 2019-07-30 2019-08-25 2019-08-30 2019-09-15 2019-09-09 kaging of Books, Instructional tions nvelope tion & Improvement Material, Laboratory Equipme nt and First Aid Kits. NG-ADAMAWA MCRP-15664 4-GO-RFQ / Supply of Solar in Infrastructure Rehabilitation Request for Quota Single Stage - One E frastructure and computers f IDA / 59880 and Service Delivery Restora Post Limited 73,982.97 Completed 2020-08-23 2020-10-12 2020-10-18 2020-11-30 2021-04-16 2021-06-28 tions nvelope or Rehabilitated Local Gover tion & Improvement nments Secretariat, Song an d Madagali. NG-ADAMAWA MCRP-15663 Infrastructure Rehabilitation 6-GO-RFQ / Supply of Office F Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 63,368.86 Completed 2020-08-23 2020-10-12 2020-10-02 2020-11-25 2021-01-30 2021-04-15 urnitures for Rehabilitated Lo tions nvelope tion & Improvement cal Governments Secretariat, Song NG-ADAMAWA MCRP-17741 Strengthening Peace Buildin Request for Quota Single Stage - One E 7-GO-RFQ / Provision of Non IDA / 59880 g, Stability and Social Cohesi Post Limited 720,510.32 Completed 2020-06-27 2020-11-11 2020-08-04 2020-12-07 2020-09-23 2020-12-16 tions nvelope Agric Livelihood Kits on NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation 8-GO-RFQ / Purchase of Furni Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 536,094.89 Completed 2020-05-10 2021-03-09 2020-06-28 2021-04-14 2020-12-25 2021-05-14 ture for 8 Sec Schs. Includin tions nvelope tion & Improvement g mattresses for GSS Maiha NG-ADAMAWA MCRP-17740 Infrastructure Rehabilitation 6-GO-RFQ / Provision of Solar Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 259,629.93 Signed 2020-05-12 2021-11-18 2020-06-23 2021-12-15 2020-09-21 Inverters and Accessories for tions nvelope tion & Improvement Rehabilitated PHCs NG-ADAMAWA MCRP-15666 Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / Purchase of com IDA / 59880 Post Limited 0.00 2020-07-03 2020-08-08 2020-09-07 ject Management Support tions nvelope ementation puters and other accessories for PCU NG-ADAMAWA MCRP-16945 Technical Assistance and Pro Request for Quota Single Stage - One E 7-GO-RFQ / Purchase of AC U IDA / 59880 Post Limited 10,230.28 Completed 2020-07-04 2021-04-22 2020-08-06 2021-05-25 2020-08-27 2021-06-24 ject Management Support tions nvelope nits and Furniture for Office NG-ADAMAWA MCRP-17628 Infrastructure Rehabilitation Request for Quota Single Stage - One E 0-GO-RFQ / Purchase of Book IDA / 59880 and Service Delivery Restora Post Limited 242,339.55 Completed 2020-08-23 2021-02-09 2020-10-07 2021-03-12 2020-11-16 2021-03-31 tions nvelope s and Instructional Materials f tion & Improvement or 8 Sec. Schools Page 5 NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation Request for Quota Single Stage - One E 2-GO-RFQ / Purchase of Class IDA / 59880 and Service Delivery Restora Post Limited 290,583.94 Completed 2020-09-22 2020-03-09 2020-11-10 2020-04-14 2021-03-10 2021-06-17 tions nvelope room Furniture for 7 Primary tion & Improvement Schools NG-ADAMAWA MCRP-17741 Infrastructure Rehabilitation 9-GO-RFQ / Purchase of Book Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 192,061.45 Completed 2020-09-13 2021-02-09 2020-10-28 2021-03-12 2021-01-26 2021-03-31 s and Instructional Materials f tions nvelope tion & Improvement or 7 Primary. Schools NG-ADAMAWA MCRP-17762 Infrastructure Rehabilitation 0-GO-RFQ / Provision of Drug Request for Quota Single Stage - One E IDA / 59880 and Service Delivery Restora Post Limited 210,000.01 Signed 2020-09-29 2022-03-08 2020-11-17 2022-04-04 2021-02-15 s and Essential Supplies to P tions nvelope tion & Improvement rimary Health Care Centers NG-ADAMAWA MCRP-15663 3-GO-RFQ / Purchase of furni Infrastructure Rehabilitation Request for Quota Single Stage - One E ture for Primary and Second IDA / 59880 and Service Delivery Restora Post Limited 290,632.60 Completed 2020-10-03 2021-03-09 2020-11-28 2021-04-14 2021-03-28 2021-06-18 tions nvelope ary Schools in Michika and M tion & Improvement adagali LGAs of Adamawa St ate NG-ADAMAWA MCRP-15667 3-GO-RFQ / Purchase of Boo Infrastructure Rehabilitation Request for Quota Single Stage - One E ks and Instructional Materials IDA / 59880 and Service Delivery Restora Post Limited 288,756.81 Completed 2020-08-01 2021-02-09 2020-09-19 2021-03-23 2020-12-08 2021-04-23 tions nvelope for Primary and Secondary in tion & Improvement Michika and Madagali LGAs o f Adamawa State NG-ADAMAWA MCRP-15664 Strengthening Peace Buildin 8-GO-RFQ / Supply of basic n Request for Quota Single Stage - One E IDA / 59880 g, Stability and Social Cohesi Post Limited 131,597.00 Completed 2020-07-18 2020-09-29 2020-09-05 2020-10-22 2020-11-04 2020-11-11 ecessity packs for Children (t tions nvelope on o include nutrition packs) NG-ADAMAWA MCRP-15665 Strengthening Peace Buildin Request for Quota Single Stage - One E 0-GO-RFQ / Supply of agricul IDA / 59880 g, Stability and Social Cohesi Post Limited 230,730.26 Completed 2020-07-18 2020-06-29 2020-09-05 2020-07-13 2020-11-04 2020-08-13 tions nvelope tural livelihood support kits t on o include Poultry NG-ADAMAWA MCRP-15627 Infrastructure Rehabilitation Request for Quota Single Stage - One E 9-GO-RFQ / Supply of Basic Li IDA / 59880 and Service Delivery Restora Post Limited 278,829.27 Completed 2020-07-22 2020-11-11 2020-09-09 2020-12-07 2020-11-08 2020-12-07 tions nvelope velihood Kits tion & Improvement NG-ADAMAWA MCRP-10055 Strengthening Peace Buildin Request for Quota Single Stage - One E IDA / 59880 Post Limited 230,129.29 Completed 2018-11-03 2019-02-27 2018-12-29 2019-03-15 2019-06-27 2019-05-14 3-GO-RFQ / Supply of Vegeta g, Stability and Social Cohesi tions nvelope ble Seeds on NG-ADAMAWA MCRP-27780 Infrastructure Rehabilitation 9-GO-RFQ / Procurement of 3 Request for Quota Single Stage - One E IDA / 66490 and Service Delivery Restora Post Limited 564,985.64 Completed 2022-03-30 2022-04-12 2022-04-25 2022-05-10 2022-06-04 2022-06-27 ''inch Solar Powered Water P tions nvelope tion & Improvement umps in Adamawa State. NG-ADAMAWA MCRP-27811 Infrastructure Rehabilitation Request for Quota Single Stage - One E 8-GO-RFQ / Equipping and Fu IDA / 66490 and Service Delivery Restora Post Limited 136,639.09 Completed 2022-03-20 2022-04-27 2022-04-15 2022-06-08 2022-05-25 2022-07-21 tions nvelope rnishing of Gombi Vetinerary tion & Improvement Clinic NG-ADAMAWA MCRP-27778 Strengthening Peace Buildin 3-GO-RFQ / Procurement of l Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-05-03 2022-05-29 2022-07-18 arge ruminant animals (Cattl tions nvelope ementation on e) in Adamawa State. NG-ADAMAWA MCRP-27811 2-GO-RFQ / Procurement of Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl Chaff/Fodder Cutting machin IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-04-17 2022-05-13 2022-06-22 tions nvelope ementation es to support cooperatives in on fodder to boost Animal feed. NG-ADAMAWA MCRP-27772 Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl 8-GO-RFQ / Procurement of f IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-04-17 2022-05-17 2022-06-26 tions nvelope ementation eeds for Large Ruminants. on NG-ADAMAWA MCRP-27780 Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl 3-GO-RFQ / Procurement of M IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-04-17 2022-05-13 2022-06-12 tions nvelope ementation edication for Large Ruminant on s NG-ADAMAWA MCRP-27811 Strengthening Peace Buildin 0-GO-RFQ / Procurement of A Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-04-04 2022-04-30 2022-06-09 ssorted Foundation Seeds to tions nvelope ementation on Community based Seed Prod uction clusters NG-ADAMAWA MCRP-27813 Strengthening Peace Buildin 8-GO-RFQ / Procurement of I Request for Quota Single Stage - One E IDA / 66490 g, Stability and Social Cohesi Post Limited 296,283.62 Completed 2022-06-11 2022-03-08 2022-07-07 2022-04-04 2022-08-16 2022-08-31 nputs tools and Kits to identif tions nvelope on ied Cooperatives. (Dry and R ain Fed Season) NG-ADAMAWA MCRP-27802 8-GO-RFQ / Procurement of M Strengthening Peace Buildin Request for Quota Single Stage - One E Under Imple ini Oil Extraction machines fo IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-05-09 2022-08-24 2022-06-04 2022-07-14 tions nvelope mentation r Groundnut oil/Soybean and on Sesame Oil processing in Ada mawa State. NG-ADAMAWA MCRP-27833 2-GO-RFQ / Procurement of H Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl and held GIS and IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-03-27 2022-05-10 2022-06-09 tions nvelope ementation other equipments for collecti tion & Improvement on of Road Data NG-ADAMAWA MCRP-27779 3-GO-RFQ / Procurement of F Strengthening Peace Buildin odder seeds (Bracharia, Labl Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-04-25 2022-05-21 2022-06-30 ab, Northern Gamba, Stylosa tions nvelope ementation on nthes) to Animal Husbandry Cooperatives for livestock far ming in Adamawa State. NG-ADAMAWA MCRP-31055 Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple 9-GO-RFQ / Acs, Computers, IDA / 66490 Post Limited 0.00 2022-09-02 2022-11-28 2022-09-28 2022-11-07 ject Management Support tions nvelope mentation Laptops, Printers, Photocopie r NG-ADAMAWA MCRP-31055 Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple IDA / 66490 Post Limited 0.00 2022-09-02 2022-09-29 2022-11-08 5-GO-RFQ / Project Staff Furn ject Management Support tions nvelope mentation iture NG-ADAMAWA MCRP-31073 Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl 5-GO-RFQ / Procurement of E IDA / 66490 Post Limited 0.00 2022-09-07 2022-10-03 2022-12-02 ject Management Support tions nvelope ementation lectronic Document Manage ment System Page 6 NG-ADAMAWA MCRP-31073 Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple 6-GO-RFQ / Fire Protective & IDA / 66490 Post Limited 0.00 2022-09-07 2022-08-24 2022-10-02 2022-11-11 ject Management Support tions nvelope mentation Prevention Equipments NG-ADAMAWA MCRP-31056 Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple IDA / 66490 Post Limited 0.00 2022-09-13 2022-11-28 2022-10-09 2022-12-08 2-GO-RFQ / Purchase of Powe ject Management Support tions nvelope mentation r Generator NG-ADAMAWA MCRP-31056 Infrastructure Rehabilitation Request for Quota Single Stage - One E 5-GO-RFQ / Furniture Supplie IDA / 66490 and Service Delivery Restora Post Limited 0.00 Signed 2022-09-13 2022-08-24 2022-10-10 2023-01-28 tions nvelope s to 6 Schools (Secondary) Sc tion & Improvement hools NG-ADAMAWA MCRP-31073 Infrastructure Rehabilitation Request for Quota Single Stage - One E 3-GO-RFQ / Furniture Supplie IDA / 66490 and Service Delivery Restora Post Limited 0.00 Signed 2022-09-13 2022-08-24 2022-10-09 2023-02-06 tions nvelope s to 6 Schools (Primary) tion & Improvement NG-ADAMAWA MCRP-32025 Strengthening Peace Buildin Request for Quota Single Stage - One E Under Imple 8-GO-RFQ / Procurement of S IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-10-31 2022-10-12 2022-11-26 2023-01-25 tions nvelope mentation afety kits/work tools for LIPW on beneficiaries NG-ADAMAWA MCRP-32025 Strengthening Peace Buildin 7-GO-RFQ / Provision of equi Request for Quota Single Stage - One E Under Imple IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-10-25 2022-10-12 2022-11-20 2023-01-19 pment and supplies to fish fa tions nvelope mentation on rmer cooperatives NG-ADAMAWA MCRP-32024 Strengthening Peace Buildin 3-GO-RFQ / Procurement of T Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-11-09 2022-12-06 2023-02-04 ube well drilling rigs to youth tions nvelope ementation on farmer cooperative groups. NG-ADAMAWA MCRP-32026 4-GO-RFQ / Procurement of h Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl igh volume solar irrigation pu IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-11-10 2022-12-06 2023-02-04 tions nvelope ementation mps for the rehabilitated Irrig on ation Project sites under 1.02 in 3 LGAs NG-ADAMAWA MCRP-32024 0-GO-RFQ / Procurement and Strengthening Peace Buildin distribution of fodder seeds ( Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-11-11 2022-12-07 2023-02-05 Bracharia, Lablab, Northern tions nvelope ementation on Gamba, Stylosanthes) to Ani mal Husbandry Cooperatives for livestock farming. NG-ADAMAWA MCRP-32024 Strengthening Peace Buildin 4-GO-RFQ / Refurbishing and Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-11-12 2022-12-11 2023-06-09 Upgrade of Fufore Fish Hatch tions nvelope ementation on ery including brood stock an d consumables NG-ADAMAWA MCRP-32026 Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl 1-GO-RFQ / Purchase of 2 No IDA / 66490 Post Limited 0.00 2022-11-22 2022-12-21 2023-02-19 ject Management Support tions nvelope ementation s Hilux Pickup Vans NG-ADAMAWA MCRP-32026 5-GO-RFQ / Strategic Commu Technical Assistance and Pro Request for Quota Single Stage - One E Under Imple IDA / 66490 Post Limited 0.00 2022-11-22 2022-11-28 2022-12-18 2023-02-16 nications (Equipment Camer ject Management Support tions nvelope mentation as, lights, Recorders) NG-ADAMAWA MCRP-27774 Infrastructure Rehabilitation Request for Quota Single Stage - One E Under Imple 4-GO-RFQ / Supply of Books f IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-07-27 2022-11-28 2022-08-24 2022-09-23 tions nvelope mentation or Secondary Schools in Ada tion & Improvement mawa State. NG-ADAMAWA MCRP-34038 Strengthening Peace Buildin 4-GO-RFQ / Provision of Briqu Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2023-02-21 2023-03-22 2023-05-21 ette Making machines for val tions nvelope ementation on ue addition in agricultural wa ste NG-ADAMAWA MCRP-34307 Strengthening Peace Buildin 1-GO-RFQ / Supply of small r Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2023-03-21 2023-04-18 2023-06-17 uminants as additional livest tions nvelope ementation on ock support to identified ben eficiary clusters NG-ADAMAWA MCRP-34307 Strengthening Peace Buildin Request for Quota Single Stage - One E Pending Impl 2-GO-RFQ / Procurement of f IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2023-03-27 2023-04-24 2023-06-23 tions nvelope ementation eeds and medications for sm on all ruminants NG-ADAMAWA MCRP-34307 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl 7-GO-RFQ / Purchase of Class IDA / 59880 and Service Delivery Restora Post Limited 0.00 2023-03-05 2023-04-02 2023-07-01 tions nvelope ementation room Furniture tion & Improvement NG-ADAMAWA MCRP-34308 Infrastructure Rehabilitation 0-GO-RFQ / Supply of Instruct Request for Quota Single Stage - One E Pending Impl IDA / 66490 and Service Delivery Restora Post Limited 0.00 2023-03-20 2023-04-16 2023-06-15 ional Materials to Primary an tions nvelope ementation tion & Improvement d Secondary Schools NG-ADAMAWA MCRP-34308 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl 2-GO-RFQ / Supply of Laborat IDA / 66490 and Service Delivery Restora Post Limited 0.00 2023-03-25 2023-04-21 2023-05-21 tions nvelope ementation ory Euipment to Senior Seco tion & Improvement ndary Schools NG-ADAMAWA MCRP-34326 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl 9-GO-RFQ / Supply of Medical IDA / 66490 and Service Delivery Restora Post Limited 0.00 2023-03-07 2023-04-03 2023-06-02 tions nvelope ementation Equipment to Rehabilitated P tion & Improvement HCs in 7 LGAs NG-ADAMAWA MCRP-34327 Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl 7-GO-RFQ / Supply of Furnitu IDA / 66490 and Service Delivery Restora Post Limited 0.00 2023-03-13 2023-04-09 2023-07-08 tions nvelope ementation re to rehabilitated Hospitals tion & Improvement and PHCCS NG-ADAMAWA MCRP-34342 Strengthening Peace Buildin 4-GO-RFQ / Rehabilitation of I Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2023-03-11 2023-04-07 2023-08-05 nfrastructure and Fencing of tions nvelope ementation on Gombi Veterinary Clinic NG-ADAMAWA MCRP-34038 3-GO-RFQ / Provision of Mini Strengthening Peace Buildin Single Stage - One E Pending Impl Mechanized tools to farmer c IDA / 66490 g, Stability and Social Cohesi Post Request for Bids Limited 0.00 2023-03-14 2023-03-19 2023-04-30 2023-05-30 2023-06-05 2023-09-03 nvelope ementation ooperatives/groups (Hand Till on ers, Harrows, Planters, Multi- Crop Threshers etc) NG-ADAMAWA MCRP-34328 Strengthening Peace Buildin 7-GO-RFQ / Procurement of S Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2023-03-15 2023-04-11 2023-06-10 porting Equipment for the re tions nvelope ementation on habilitated sports centers an d schools Page 7 NG-ADAMAWA MCRP-34306 Strengthening Peace Buildin 9-GO-RFQ / Provision of Com Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Request for Bids Limited 0.00 2023-03-15 2023-03-20 2023-04-10 2023-04-24 2023-05-01 2023-10-28 plete Set of Mini Rice process nvelope ementation on ing equipment to Cooperativ e Clusters/User groups. NG-ADAMAWA MCRP-34327 5-GO-RFQ / Supply of Essenti Infrastructure Rehabilitation al Drugs/Medical consumable Request for Quota Single Stage - One E Pending Impl IDA / 66490 and Service Delivery Restora Post Limited 0.00 2023-03-07 2023-04-03 2023-06-02 s to Rehabilitated General Ho tions nvelope ementation tion & Improvement spitals and PHCCs (based on the list of Essential Drugs by the FMoH & NPHCDA) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-69795- Infrastructure Rehabilitation Request for Quota Single Stage - One E Pending Impl NC-RFQ / Door to Door Collec IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-08-05 2018-09-30 2019-03-29 tions nvelope ementation tion of Solid waste in 7 LGAs tion & Improvement NG-ADAMAWA MCRP-16947 5-NC-RFQ / Production of Me Technical Assistance and Pro Request for Quota Single Stage - One E Pending Impl IDA / 59880 Post Limited 0.00 2020-07-26 2020-09-09 2020-10-19 dia Materials,Documentaries ject Management Support tions nvelope ementation Jingles,Billboards,Slots,Websi te NG-ADAMAWA MCRP-32025 Strengthening Peace Buildin 9-NC-RFQ / Procurement of P Request for Quota Single Stage - One E Pending Impl IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-10-29 2022-12-03 2023-12-08 ayment Service Provider (PSP tions nvelope ementation on ) for LIPW Implementation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-59463- Infrastructure Rehabilitation Consultant Qualifi Pending Impleme CS-CQS / Hygiene Promotion IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-08-10 2018-08-10 2018-08-10 2018-08-10 2018-08-10 2018-08-10 cation Selection ntation Campaign tion & Improvement NG-ADAMAWA MCRP-69092- CS-CQS / Consultation for Sur Infrastructure Rehabilitation Consultant Qualifi Pending Impleme vey, Design and Supervision IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-07-10 2018-07-13 2018-07-19 2018-07-23 2018-07-27 2018-08-11 cation Selection ntation of Health, Education and Publ tion & Improvement ic Buildings Projects under C omponent 2 NG-ADAMAWA MCRP-69097- Infrastructure Rehabilitation CS-CQS / Consultancy for Sur Consultant Qualifi Pending Impleme IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-07-11 2018-07-13 2018-07-20 2018-07-23 2018-07-26 2018-08-16 vey, Design and Supervision cation Selection ntation tion & Improvement of Roads Projects under Com ponent 2 NG-ADAMAWA MCRP-62277- Infrastructure Rehabilitation CS-CQS / consultancy for Proj Consultant Qualifi IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-07-02 2018-07-23 2018-09-05 2018-10-05 2018-11-09 2019-05-08 ect design and Supervision fo cation Selection tion & Improvement r Road Projects Under Compo nent 2. NG-ADAMAWA MCRP-62278- Infrastructure Rehabilitation CS-CQS / Consultancy For Pro Consultant Qualifi IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-07-30 2018-08-20 2018-10-03 2018-11-02 2018-12-07 2019-06-05 ject Design and Supervision F cation Selection tion & Improvement or Water Projects Under Com ponent 2. NG-ADAMAWA MCRP-62006- CS-CQS / Consultancy for pro Infrastructure Rehabilitation Consultant Qualifi jects design and supervision IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-04-17 cation Selection for Education, Health, and Pu tion & Improvement blic buildings Projects under Component 2. NG-ADAMAWA MCRP-60470- CS-CQS / Training of affecte Strengthening Peace Buildin Consultant Qualifi d farmers to apply inputs and IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Under Review 2018-08-16 2019-08-02 2018-08-23 2018-09-20 2018-10-04 2018-10-21 2018-12-20 cation Selection access targeted agricultural on value chains and agribusine ss skills NG-ADAMAWA MCRP-73882- Strengthening Peace Buildin Consultant Qualifi CS-CQS / Provision of Speciali IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Under Review 2018-08-14 2018-10-30 2018-08-28 2018-09-28 2018-10-16 2018-11-13 2019-04-22 cation Selection sed Psycho-social needs ass on essment NG-ADAMAWA MCRP-59454- Strengthening Peace Buildin CS-CQS / Consultancy for Lea Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-02-05 2021-06-01 2018-02-05 2018-02-05 2018-02-05 2018-02-05 2018-02-05 dership Accountability and cation Selection ation on Transparency Training Progr amme NG-ADAMAWA MCRP-60475- Strengthening Peace Buildin CS-CQS / Capacity building of Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-02-23 2021-05-05 2018-03-02 2018-03-23 2018-04-13 2018-05-11 2018-09-08 LG Officers for economic plan cation Selection ation on ning and policy development NG-ADAMAWA MCRP-60855- CS-CQS / Capacity building o Strengthening Peace Buildin Consultant Qualifi Under Implement f LG Officers for local govern IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-02-23 2021-05-05 2018-03-09 2018-04-13 2018-05-04 2018-06-08 2018-10-06 cation Selection ation ments on budget planning an on d execution, monitoring and reporting NG-ADAMAWA MCRP-60956- CS-CQS / Capacity building o Strengthening Peace Buildin Consultant Qualifi Under Implement f LG Officers for strategic co IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-03-19 2021-05-07 2018-04-02 2018-05-07 2018-05-28 2018-07-02 2018-10-30 cation Selection ation mmunications (Legislative Ad on vocacy, Media relations, Stak eholder Management etc). NG-ADAMAWA MCRP-60852- Strengthening Peace Buildin Consultant Qualifi Under Implement CS-CQS / Capacity building fo IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-02-23 2021-05-05 2018-03-09 2018-04-13 2018-05-04 2018-06-08 2018-10-06 cation Selection ation r programme design and imp on lementation NG-ADAMAWA MCRP-60513- CS-CQS / Registration, Mappi Strengthening Peace Buildin Consultant Qualifi ng and Profiling of all local go IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Under Review 2018-02-23 2019-01-07 2018-03-16 2018-04-29 2018-05-29 2018-07-03 2018-12-30 cation Selection vernment structures and exis on ting capacities State Wide Page 8 NG-ADAMAWA MCRP-73941- CS-CQS / Soft Skill Training/ r Strengthening Peace Buildin Consultant Qualifi Pending Impleme e-orientation on quick to Mar IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 2018-08-19 2018-09-02 2018-09-23 2018-10-03 2018-10-20 2019-01-28 cation Selection ntation ket Trading, Training for Non on agricultural Kits (Refresher Tr aining Skill Upgrade) NG-ADAMAWA MCRP-60997- CS-CQS / Consultancy Servic Strengthening Peace Buildin Consultant Qualifi es For Refresher Training of IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Under Review 2018-08-22 2018-11-16 2018-08-29 2018-09-19 2018-10-03 2018-10-20 2019-01-28 cation Selection Existing Extension Workers t on o support Livelihoods Project s NG-ADAMAWA MCRP-69796- CS-CQS / Consultancy for Sen sitization, Community Mobiliz Strengthening Peace Buildin ation and formation of peace Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Prior Open - National 0.00 Canceled 2018-10-30 2019-06-27 2018-11-13 2018-12-11 2018-12-25 2019-01-11 2019-04-11 groups within 7 Communities cation Selection on (establishment of community platforms to discuss commun ity needs, grievances; and re dress mechanisms NG-ADAMAWA MCRP-69809- Strengthening Peace Buildin CS-CQS / Design and Implem Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Prior Open - National 0.00 Canceled 2018-10-29 2019-06-27 2018-11-05 2018-11-19 2018-11-26 2018-12-10 2019-04-09 entation of Adamawa State C cation Selection on ivic Education Programe NG-ADAMAWA MCRP-69806- CS-CQS / Sensitization and M Strengthening Peace Buildin obilisation Programs for Awar Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Prior Open - National 0.00 Canceled 2018-11-12 2018-11-26 2018-12-17 2018-12-31 2019-01-14 2019-05-14 eness against Stigmatization cation Selection on of Woman and Children asso ciated with armed groups. (1 No Consultancy) NG-ADAMAWA MCRP-69804- CS-CQS / Consultancy for Me diation and Alternate Dispute Strengthening Peace Buildin Consultant Qualifi Resolution Capacity Building IDA / 59880 g, Stability and Social Cohesi Prior Open - National 0.00 Canceled 2018-11-26 2018-12-03 2018-12-17 2018-12-24 2019-01-14 2019-04-14 cation Selection within the Community Leader on ship and Governance Structu res (3Nos Consultancies acro ssthe state) NG-ADAMAWA MCRP-73883- CS-CQS / Provision of Speciali sed Psycho-social support t Strengthening Peace Buildin Consultant Qualifi hrough group support, recre IDA / 59880 g, Stability and Social Cohesi Prior Open - National 0.00 Canceled 2018-12-10 2018-12-17 2019-01-03 2019-01-10 2019-01-24 2019-05-04 cation Selection ational , customary and socia on lization activities referrals etc responding to needs identifi ed during the assessment. NG-ADAMAWA MCRP-81646- CS-CQS / Consultancy for Sur Infrastructure Rehabilitation Consultant Qualifi Under Implement vey, Design and Supervision IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-10-23 2018-07-03 2018-10-30 2018-11-13 2018-11-20 2018-11-30 2019-01-14 cation Selection ation of boreholes, VIP Latrines an tion & Improvement d Hygiene promotion Campai gn NG-ADAMAWA MCRP-81653- CS-CQS / Consultancy for Sur Infrastructure Rehabilitation Consultant Qualifi Under Implement vey, Design and Supervision IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-10-23 2018-11-06 2018-10-30 2018-11-13 2018-11-20 2018-12-02 2019-03-02 cation Selection ation of small towns water project tion & Improvement s Rehabilitation and upgrade . NG-ADAMAWA MCRP-10143 4-CS-CQS / Train the Trainer/ User Workshops (i.e. 2 per L Infrastructure Rehabilitation GA) for VLOM (Village Level Consultant Qualifi Pending Impleme IDA / 59880 and Service Delivery Restora Post Open - National 0.00 2018-03-19 2018-04-09 2018-05-23 2018-06-22 2018-07-27 2019-01-23 Operation and Maintenance) cation Selection ntation tion & Improvement WASHCOMS, (WASH Committ ees at LGA Level, WASH Unit s @ LGAs, VHPs (Voluntary H ygiene Promoters) State/LGA Govt Officials. NG-ADAMAWA MCRP-12489 9-CS-CQS / Consultancy for S ensitization, Community Mob Strengthening Peace Buildin Consultant Qualifi ilization and formation of pea IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 Under Review 2019-08-05 2019-08-02 2019-08-19 2019-09-02 2019-09-17 2020-03-15 cation Selection ce groups and community pl on atforms to discuss communit y needs, grievances; and red ress mechanisms NG-ADAMAWA MCRP-12491 Strengthening Peace Buildin 8-CS-CQS / Design and Imple Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2019-08-05 2019-08-02 2019-08-19 2019-08-29 2019-09-15 2020-03-13 mentation of Adamawa State cation Selection ation on Civic Education Programe NG-ADAMAWA MCRP-12493 1-CS-CQS / Sensitization and Strengthening Peace Buildin mobilisation programs for aw Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 Canceled 2019-08-15 2018-11-08 2019-08-29 2019-09-12 2019-10-03 2020-03-31 areness against stigmatizatio cation Selection on n of women and children ass ociated with armed groups. NG-ADAMAWA MCRP-12493 8-CS-CQS / Provision of Speci alised Psycho-social support Strengthening Peace Buildin Consultant Qualifi through group support, recr IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 Under Review 2019-09-11 2021-06-01 2019-09-25 2019-10-16 2019-11-06 2020-11-05 cation Selection eational , customary and soci on alization activities referrals e tc responding to needs ident ified during the assessment. NG-ADAMAWA MCRP-12494 0-CS-CQS / Consultancy for M Strengthening Peace Buildin ediation and Alternate Disput Consultant Qualifi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 2019-08-15 2020-09-01 2019-08-29 2019-09-19 2019-10-10 2020-04-07 e Resolution Capacity Buildin cation Selection ation on g within the Community Lead ership and Governance Struc tures NG-ADAMAWA MCRP-17754 Infrastructure Rehabilitation 6-CS-CQS / Capacity Building Consultant Qualifi Under Implement IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-06-25 2021-05-18 2020-07-09 2020-07-30 2020-08-16 2020-11-14 of Public Sector Personnel on cation Selection ation tion & Improvement Disaster Recovery Planning & Coordination NG-ADAMAWA MCRP-17756 Infrastructure Rehabilitation Consultant Qualifi Pending Impleme 8-CS-CQS / Training of Health IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-09-10 2020-09-24 2020-10-24 2020-11-28 2021-05-27 cation Selection ntation Workers (50) tion & Improvement Page 9 NG-ADAMAWA MCRP-15627 1-CS-CQS / Consultancy Servi Infrastructure Rehabilitation Consultant Qualifi Under Implement ce for Survey, design and Su IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-07-20 2020-08-19 2020-08-03 2020-08-24 2020-09-08 2021-06-05 cation Selection ation pervision of Solar Powered tion & Improvement Boreholes in Adamawa State. (Water Sector) NG-ADAMAWA MCRP-27775 0-CS-CQS / Design and Deplo Strengthening Peace Buildin yment of Platform/Software f Consultant Qualifi Pending Impleme IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-04-04 2022-04-18 2022-05-18 2022-06-22 2022-12-19 or Monitoring performance of cation Selection ntation on Beneficiaries of Agric. Livelih ood Kits/Small Animals by Ex tension Workers NG-ADAMAWA MCRP-27833 4-CS-CQS / Training of extens Strengthening Peace Buildin Consultant Qualifi Pending Impleme ion workers to support fame IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-05-14 2022-05-28 2022-06-18 2022-07-23 2023-01-19 cation Selection ntation rs and Agribusiness Coopera on tives in Adamawa State. NG-ADAMAWA MCRP-27833 3-CS-CQS / Monitoring of Part Strengthening Peace Buildin Consultant Qualifi icipants and assessing the im IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 Under Review 2022-02-28 2022-06-25 2022-03-14 2022-04-04 2022-04-09 2022-06-08 cation Selection pact of Alternative Dispute R on esolution Capacity Building undertaken in 2020/21 NG-ADAMAWA MCRP-27778 9-CS-CQS / Training of Social Strengthening Peace Buildin Welfare & Youth Workers/Co Consultant Qualifi Pending Impleme IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-05-10 2022-05-24 2022-06-14 2022-06-19 2022-07-29 mmunity/Religious leaders a cation Selection ntation on nd Women groups on Sexual and Gender Based Violence ( SGBV) in Adamawa State. NG-ADAMAWA MCRP-17757 2-CS-CQS / Consultancy Servi Infrastructure Rehabilitation ces for Design of An Impleme Consultant Qualifi Under Implement IDA / 59880 and Service Delivery Restora Post Limited 0.00 2020-07-31 2020-09-10 2020-08-14 2020-09-01 2020-09-22 2021-03-21 ntation Strategy for The Sust cation Selection ation tion & Improvement ainability and Functionality 0f Community Wash Facilities in Adamawa State. NG-ADAMAWA MCRP-27780 Strengthening Peace Buildin 4-CS-CQS / Targeting, Profilin Consultant Qualifi Under Implement IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-02-28 2022-10-10 2022-03-14 2022-04-04 2022-04-09 2022-06-08 g and Identification of Farme cation Selection ation on r and Agribusiness Cooperati ves in Adamawa State. NG-ADAMAWA MCRP-27802 Strengthening Peace Buildin 2-CS-CQS / Assessment and Consultant Qualifi IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 Canceled 2022-03-03 2022-03-17 2022-04-07 2022-04-12 2022-05-22 upgrade of Adamawa State C cation Selection on ooperatives Administration S ystem NG-ADAMAWA MCRP-60954- Infrastructure Rehabilitation Consultant Qualifi CS-CQS / Sensitization and M IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 2018-06-15 cation Selection obilisation for Health (Outrea tion & Improvement ch Programs) NG-ADAMAWA MCRP-60983- Infrastructure Rehabilitation Consultant Qualifi CS-CQS / Teacher Training on IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-10-29 2020-11-12 2020-12-03 2020-12-20 2021-04-19 cation Selection Pedagogy ( Primary and Seco tion & Improvement ndary Schools ) NG-ADAMAWA MCRP-60850- Infrastructure Rehabilitation CS-CQS / Training of Commu Consultant Qualifi IDA / 59880 and Service Delivery Restora Post Open - National 0.00 Canceled 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 nity Health Workers (CHeWs) cation Selection tion & Improvement to Staff Targeted Health Facil ities NG-ADAMAWA MCRP-60949- Infrastructure Rehabilitation Consultant Qualifi CS-CQS / Mobilization and Se IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-10-05 2020-10-19 2020-11-06 2020-11-23 2021-03-15 cation Selection nsitization for Children Educa tion & Improvement tion NG-ADAMAWA MCRP-15664 1-CS-CQS / design and Super Infrastructure Rehabilitation Consultant Qualifi vision for Rehabilitation of P IDA / 59880 and Service Delivery Restora Post Limited 0.00 Canceled 2020-07-03 2020-07-17 2020-08-07 2020-08-24 2021-05-31 cation Selection rimary and Secondary School tion & Improvement s In Adamawa State.(Educati on Sector) NG-ADAMAWA MCRP-73939- CS-CQS / Capacity Building fo Strengthening Peace Buildin r Local Government Emergen Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Open - National 0.00 Canceled 2018-08-15 2018-08-29 2018-09-26 2018-10-10 2018-10-31 2019-02-28 cy Responders among Displa cation Selection on ced and Transitional Local Go vernment Officials per LGA NG-ADAMAWA MCRP-29716 0-CS-CQS / CONSULTANCY S ERVICES FOR DESIGN AND S Infrastructure Rehabilitation UPERVISION OF REHABILITAT Consultant Qualifi Pending Impleme IDA / 59880 and Service Delivery Restora Prior Limited 0.00 2020-09-02 2020-09-16 2020-10-07 2020-10-17 2021-11-21 ION/RENOVATION OF PUBLIC cation Selection ntation tion & Improvement BUILDINGS(SCHOOLS AND H EALTH FACILITIES) IN THE SE VEN (7) INSURGENCY AFFECT ED LGAs IN ADAMAWA STATE . NG-ADAMAWA MCRP-31262 9-CS-CQS / Consultancy For F Technical Assistance and Pro Consultant Qualifi Under Implement IDA / 66490 Post Limited 0.00 2022-08-31 2022-10-18 2022-09-07 2022-09-28 2022-10-06 2022-11-15 unctional Review of Capacitie ject Management Support cation Selection ation s and Systems of PCU NG-ADAMAWA MCRP-32022 Strengthening Peace Buildin 5-CS-CQS / Procurement of LI Consultant Qualifi Under Implement IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-10-25 2022-11-10 2022-11-08 2022-11-29 2022-12-07 2024-01-31 PW Implementing Partner (IP) cation Selection ation on for Beneficiary Targeting and process Management NG-ADAMAWA MCRP-32022 Infrastructure Rehabilitation Consultant Qualifi Under Implement 3-CS-CQS / Consultancy for D IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-10-27 2022-12-23 2022-11-10 2022-12-01 2022-12-10 2023-09-06 cation Selection ation esign and Supervision of Hea tion & Improvement lth Facilities NG-ADAMAWA MCRP-32025 Infrastructure Rehabilitation 5-CS-CQS / Consultancy for t Consultant Qualifi Under Implement IDA / 66490 and Service Delivery Restora Post Limited 0.00 2022-10-28 2022-12-23 2022-11-11 2022-12-02 2022-12-11 2023-11-06 he Survey, Design and Super cation Selection ation tion & Improvement vision of Schools Projects. NG-ADAMAWA MCRP-32025 2-CS-CQS / Consultancy on st Strengthening Peace Buildin udy to assess and redesign ir Consultant Qualifi Pending Impleme IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-11-10 2022-11-24 2022-12-15 2022-12-24 2023-11-19 rigations and the design and cation Selection ntation on supervision of infrastructure f acilities under the livelhood i nfrastructure Components. Page 10 NG-ADAMAWA MCRP-32141 6-CS-CQS / Consultancy Servi Strengthening Peace Buildin Consultant Qualifi Under Implement ce to assess and upgrade Ad IDA / 66490 g, Stability and Social Cohesi Post Limited 0.00 2022-10-24 2022-10-25 2022-11-07 2022-11-28 2022-12-05 2023-03-05 cation Selection ation amawa State Cooperatives A on dministration System. NG-ADAMAWA MCRP-29715 Infrastructure Rehabilitation 6-CS-CQS / Consultancy for s Consultant Qualifi IDA / 66490 and Service Delivery Restora Post Limited 0.00 Canceled 2022-06-24 2022-07-08 2022-07-29 2022-08-08 2024-01-30 urvey, design and supervisio cation Selection tion & Improvement n of WASH Projects. NG-ADAMAWA MCRP-16939 2-CS-CQS / Design and Deplo Strengthening Peace Buildin yment of Platform/Software f Consultant Qualifi IDA / 59880 g, Stability and Social Cohesi Post Limited 0.00 Canceled 2020-08-12 2020-08-26 2020-09-25 2020-10-30 2021-04-28 or Monitoring performance of cation Selection on Beneficiaries of Agric. Livelih ood Kits/Small Animals by Ex tension Workers NG-ADAMAWA MCRP-34253 Infrastructure Rehabilitation 9-CS-CQS / Consultancy for s Consultant Qualifi Pending Impleme IDA / 66490 and Service Delivery Restora Post Limited 0.00 2023-02-24 2023-03-10 2023-03-31 2023-04-08 2024-04-07 urvey, design and supervisio cation Selection ntation tion & Improvement n of small towns/urban water supply system NG-ADAMAWA MCRP-34253 Infrastructure Rehabilitation 3-CS-CQS / Consultancy for s Consultant Qualifi Pending Impleme IDA / 66490 and Service Delivery Restora Post Limited 0.00 2023-02-27 2023-03-13 2023-04-03 2023-04-10 2023-10-07 upervision of boreholes (sola cation Selection ntation tion & Improvement r and Handpumps) in Adama wa State INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-ADAMAWA MCRP-74496- Infrastructure Rehabilitation Individual Consult Pending Impleme CS-INDV / Hygiene Promotion IDA / 59880 and Service Delivery Restora Post Limited 0.00 2018-08-20 2018-08-25 2018-09-08 2018-10-02 2019-01-30 ant Selection ntation Sensitization/Mobilization. tion & Improvement NG-ADAMAWA MCRP-60989- CS-CQS / Verification/Validati Strengthening Peace Buildin on of Unified Registry and Be Under Implement IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 2018-12-10 2019-01-15 2018-12-13 2018-12-18 2019-01-17 neficiary Targeting for distrib ation on ution of interventions in Seve n Local Government Areas of Adamawa State. NG-ADAMAWA MCRP-10949 8-CS-CDS / Procurement of S Infrastructure Rehabilitation afeguards Consultants to pro IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2019-04-08 2019-07-29 2019-04-16 2019-04-25 2019-05-16 duce ESMPs for Adamawa PC tion & Improvement U Infrastructure projects. NG-ADAMAWA MCRP-10950 6-CS-CDS / Procurement of E Infrastructure Rehabilitation nvironmental Safeguards Co IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2019-04-08 2019-07-29 2019-04-16 2019-04-25 2019-05-16 nsultants to produce ESIAs fo tion & Improvement r Adamawa PCU Infrastructur e projects. NG-ADAMAWA MCRP-10950 Infrastructure Rehabilitation 7-CS-CDS / Procurement of S IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2019-04-08 2019-07-22 2019-04-16 2019-04-25 2019-05-16 afeguards Consultants to pro tion & Improvement duce RAP for Adamawa PCU I nfrastructure projects. NG-ADAMAWA MCRP-13045 5-CS-CDS / consultancy servi Strengthening Peace Buildin ces for beneficiary targeting IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 Under Review 2019-09-04 2018-10-09 2019-09-14 2019-10-02 2019-11-01 for livelihood support interve on ntions in the seven affected L ocal government Areas of Ad amawa State. NG-ADAMAWA MCRP-16944 0-CS-CDS / Training of Farme Strengthening Peace Buildin rs to apply inputs and access IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 Under Review 2020-07-22 2021-07-05 2020-08-01 2020-09-08 2021-01-06 targeted argricultural value c on hain and agribusiness skills NG-ADAMAWA MCRP-17755 Infrastructure Rehabilitation 4-CS-CDS / Consultancy for d Under Implement IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 2020-07-14 2020-09-11 2020-07-24 2020-08-24 2021-07-26 esign and supervision of Roa ation tion & Improvement d and bridge projects NG-ADAMAWA MCRP-15662 Infrastructure Rehabilitation 4-CS-CDS / Consultancy for P IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 Under Review 2020-07-02 2020-10-05 2020-07-12 2020-08-07 2020-10-06 reparation of Environmental tion & Improvement and Social Safeguard Instrum ents NG-ADAMAWA MCRP-17755 Strengthening Peace Buildin 0-CS-CDS / Beneficiary List V IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 Canceled 2020-06-25 2020-07-05 2020-08-21 2020-10-20 erification and Targeting on NG-ADAMAWA MCRP-17740 9-CS-CDS / Consultancy for P Infrastructure Rehabilitation roduction of Engineering dra IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 Canceled 2020-07-09 2020-07-19 2020-08-24 2021-05-21 wings design and supervision tion & Improvement of Contracts for Primary & Se condary schools. NG-ADAMAWA MCRP-16943 Strengthening Peace Buildin 7-CS-CDS / Soft skills training IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 Canceled 2020-09-30 2020-10-10 2020-11-12 2021-03-12 /orientation on Quick to mark on et trading NG-ADAMAWA MCRP-17741 Strengthening Peace Buildin 6-CS-CDS / Softskills Training IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 Canceled 2020-06-22 2020-07-02 2020-08-09 2020-12-07 on Quick to Market Trades on NG-ADAMAWA MCRP-27780 2-CS-CDS / Design and imple mentation of Mediation and A Strengthening Peace Buildin Pending Impleme lternate Dispute Resolution f IDA / 66490 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 2022-04-21 2022-05-01 2022-05-27 2022-07-26 ntation or Community Leaders, Justic on e Officials, Religious Leaders, Community Peace Groups (2 nd Phase) Page 11 NG-ADAMAWA MCRP-27775 2-CS-CDS / Procurement of C Infrastructure Rehabilitation Under Implement onsultant for Development IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-03-22 2022-06-27 2022-04-01 2022-07-04 2022-04-16 2022-06-15 ation of Environmental and social tion & Improvement safeguards instruments NG-ADAMAWA MCRP-22356 Strengthening Peace Buildin 7-CS-CDS / Consultancy servi Under Implement IDA / 59880 g, Stability and Social Cohesi Post Direct Selection Direct 0.00 2020-12-02 2020-12-02 2020-12-12 2021-02-06 2021-04-27 ce for soft skill training and r ation on e-orientation on quick to mar ket trading (2020) NG-ADAMAWA MCRP-27814 Infrastructure Rehabilitation 1-CS-CDS / Assessment of th Pending Impleme IDA / 66490 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-03-08 2022-03-18 2022-04-15 2022-06-14 e Adamawa State Hides/Skin/ ntation tion & Improvement Leather Value Chain NG-ADAMAWA MCRP-29715 9-CS-CDS / Procurement of C Infrastructure Rehabilitation Under Implement onsultant for survey, IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 2022-05-31 2022-10-06 2022-06-10 2022-08-09 2022-07-03 2023-08-07 ation Design and supervision of Ro tion & Improvement ads and Bridges. NG-ADAMAWA MCRP-17754 Infrastructure Rehabilitation 8-CS-CDS / Consultancy for IDA / 59880 and Service Delivery Restora Post Direct Selection Direct 0.00 Canceled 2020-07-20 2020-07-30 2020-09-07 2021-03-06 water projects Design and su tion & Improvement pervision (Solar and Hand Pu mp Boreholes) Page 12