PROCUREMENT PLAN (Textual Part) Project information: Senegal Gas Project Negotiations & Inst Capacity (P160652) Project Implementation agency: GES Petrogez Date of the Procurement Plan: October 15, 2017 Period covered by this Procurement Plan: May 26, 2017 – December 23, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Decree No2014 – 1212 of September 22nd, 2016 , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is not Applicable. PROCUREMENT Senegal : Supporting Gas Project Negotiations and Enhancing Institutional Capacities PLAN General Information Country: Senegal 2017-10-17 Bank’s Approval Date of the Original Procurement Plan: 2023-03-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160652 GPN Date: Project Name: Supporting Gas Project Negotiations and Enhancing Institutional Capacities Loan / Credit No: IDA / 60530 GES PETROGAZ Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-GES PETROGAZ-49072-G Project management and co Single Stage - One E O-RFQ / Fourniture de mobili IDA / 60530 A posteriori Demande de prix Limited 100,000.00 37,201.27 Achevé 2018-03-05 2018-05-18 2018-04-30 2018-07-13 2018-10-27 2018-10-10 ordination nvelope er de bureau SN-GES PETROGAZ-49074-G Project management and co Single Stage - One E O-RFQ / Fourniture de matéri IDA / 60530 A posteriori Demande de prix Limited 100,000.00 58,153.16 Achevé 2018-03-05 2018-05-09 2018-04-30 2018-06-22 2018-10-27 2018-10-22 ordination nvelope els informatiques SN-GES PETROGAZ-49078-G Project management and co Single Stage - One E O-RFQ / Fournitures de burea IDA / 60530 A posteriori Demande de prix Limited 10,000.00 13,457.51 Achevé 2018-03-20 2019-05-29 2018-05-15 2019-06-25 2018-11-11 2019-07-24 ordination nvelope u et consommables informati ques SN-GES PETROGAZ-64967-G O-DIR / Acquisition du logiciel Project management and co Passation de marc TOM2PRO avec avec les mod IDA / 60530 A posteriori Direct 45,000.00 26,344.41 Achevé 2018-06-15 2018-08-23 2018-06-20 2018-09-14 2018-07-25 2018-10-17 2019-01-21 2018-11-29 ordination hé de gré à gré ules Comptabilité, Passation des marchés,monitoring et p aie y compris la formation. FOUR BUREAU 2020 / Fourni Project management and co Single Stage - One E tures de bureau, consommab IDA / 60530 A posteriori Demande de prix Limited 50,000.00 33,229.89 Signé 2020-05-02 2020-07-27 2020-06-27 2020-09-10 2020-07-27 ordination nvelope les informatiques et matériel d'entretien ASSUR-2019 / Renouvelleme Project management and co Passation de marc IDA / 60530 A posteriori Direct 80,000.00 20,476.89 Signé 2020-10-26 2019-07-15 2020-10-31 2020-12-05 2019-07-29 2023-12-05 nt contrat assurance (2019-2 ordination hé de gré à gré 022) FOUR21 / Fournitures de bur Project management and co Single Stage - One E IDA / 60530 A posteriori Demande de prix Limited 30,000.00 25,516.57 Achevé 2021-02-20 2021-07-08 2021-04-17 2021-08-16 2021-05-08 2021-11-09 eau et consommables inform ordination nvelope atiques MOBILIER / Acquisition de m Institutional diagnostic and c Single Stage - One E IDA / 60530 A posteriori Appel d'offres Open - National 290,000.00 25,413.66 Achevé 2021-06-21 2021-07-29 2021-06-26 2021-07-26 2021-09-02 2021-07-31 2021-10-05 2021-09-13 2021-11-23 2021-10-04 2021-12-20 obiliers et matériels de burea apacity building nvelope u MAT INFO / Acquisition de lo Institutional diagnostic and c Single Stage - One E IDA / 60530 A posteriori Appel d'offres Open - National 513,000.00 416,635.99 Signé 2021-05-31 2021-09-28 2021-06-05 2021-07-05 2021-11-17 2021-07-06 2021-12-22 2021-08-10 2022-04-14 2021-08-31 giciels et matériels informati apacity building nvelope ques MOB 22 / Acquisition de mob Project management and co Single Stage - One E IDA / 60530 A posteriori Demande de prix Limited 60,000.00 36,277.00 Achevé 2022-02-12 2022-02-23 2022-04-09 2022-05-31 2022-05-24 2022-06-08 iliers de bureau ordination nvelope FOUR 22 / Fournitures de bu Project management and co Single Stage - One E En cours d'ex IDA / 60530 A posteriori Demande de prix Limited 40,000.00 0.00 2022-04-11 2022-10-13 2022-06-05 2022-06-26 reau et consommables infor ordination nvelope écution matiques INFO PETRO / Acquisition de Institutional diagnostic and c Single Stage - One E En cours d'ex IDA / 60530 A posteriori Appel d'offres Open - National 140,000.00 0.00 2023-01-02 2023-01-11 2023-01-12 2023-02-11 2023-03-03 2023-04-07 2023-04-28 matériels informatiques apacity building nvelope écution NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-GES PETROGAZ-63442-N C-RFQ / Sélection d'un Assur Project management and co Single Stage - One E IDA / 60530 A posteriori Demande de prix Limited 40,000.00 17,156.27 Achevé 2018-06-09 2018-06-08 2018-08-04 2018-08-17 2019-01-31 2018-10-01 eur pour la prise en charge d ordination nvelope u volet médicale du personn el du Projet INPG / Services de formation Institutional diagnostic and c Passation de marc IDA / 60530 A posteriori Direct 600,000.00 603,697.22 Signé 2021-07-19 2021-07-28 2021-07-24 2021-07-28 2021-10-06 2021-10-19 2022-10-06 s apacity building hé de gré à gré ERP PETRO / Système compt able ERP de type SAP intégra Institutional diagnostic and c Single Stage - One E En attente d' nt une comptabilité analytiqu IDA / 60530 A posteriori Demande de prix Open - National 100,000.00 0.00 2023-02-23 2023-05-19 2023-09-16 apacity building nvelope exécution e avec un système d’allocati on des coûts communs INFRAS PETRO / Service de Institutional diagnostic and c Single Stage - One E En attente d' mise à niveau d’une infrastru IDA / 60530 A posteriori Demande de prix Limited 100,000.00 0.00 2023-03-02 2023-05-11 2023-09-08 apacity building nvelope exécution cture Hyperconvergée STAMP / Solution technique Support for hydrocarbon proj Passation de marc Direct - Internation En attente d' STAMP: Technology Access a IDA / 60530 A priori 2,220,000.00 0.00 2023-03-08 2023-03-13 2023-05-01 2023-12-31 ect negotiations hé de gré à gré al exécution nd Mastery Program CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GES-STRACOM-14 / Recrute Sélection fondée s Stakeholders engagement c Open - Internationa ment d'une société chargée IDA / 60530 A priori ur la qualité et le 1,000,000.00 645,435.52 Achevé 2018-03-06 2018-04-11 2018-03-27 2018-05-18 2018-05-10 2018-10-17 2018-06-07 2018-11-21 2018-07-07 2019-06-03 2018-08-11 2019-06-13 2018-09-15 2019-06-24 2019-09-15 2023-01-20 ampaign l d'élaborer une stratégie de c coût ommunication Page 1 GES-COMGAZ-6 / Recruteme nt d'un cabinet de conseil sp Sélection fondée s Enhancement of the strategi Open - Internationa écialisé dans l'analyse de co IDA / 60530 A priori ur la qualité et le 1,000,000.00 956,875.29 Signé 2017-07-17 2017-11-16 2017-08-07 2017-09-20 2018-04-20 2017-10-18 2018-01-17 2017-11-17 2018-06-07 2017-12-22 2018-09-17 2018-01-26 2019-05-03 2019-01-26 c and policy framework l mmercialisation du gaz natur coût el et du GNL dans le monde e ntier GES PRO GAZ 3 / Recruteme Sélection fondée s nt d'une compagnie spécialis Enhancement of the strategi Open - Internationa IDA / 60530 A priori ur la qualité et le 3,500,000.00 8,712,833.38 Signé 2017-06-13 2017-11-16 2017-07-04 2017-08-17 2018-02-20 2017-09-14 2017-12-06 2017-10-14 2018-06-07 2017-11-18 2018-09-07 2017-12-23 2018-10-04 2018-12-23 ée dans les projets gaziers e c and policy framework l coût n haute mer et dans les proje ts GNL GES RES CER UNI 2 / Recrut Sélection fondée s ement d'un cabinet spécialis Enhancement of the strategi Open - Internationa IDA / 60530 A priori ur la qualité et le 3,500,000.00 1,142,786.29 Signé 2017-06-20 2017-11-16 2017-07-11 2017-08-24 2017-09-21 2017-12-13 2017-10-21 2018-04-30 2017-11-25 2018-07-08 2017-12-30 2018-10-22 2018-12-30 é dans l'ingénierie de réservo c and policy framework l coût ir, la certification des réserve s et unitisation GES-AUDIT-18 / Sélection d' Sélection fondée s Project management and co En attente d'exéc un Cabinet externe pour l'Au IDA / 60530 A posteriori ur la qualité et le Open - National 50,000.00 0.00 2018-09-20 2018-10-11 2018-11-24 2018-12-22 2019-01-21 2019-02-25 2019-04-01 2020-03-31 ordination ution dit Financier et comptable du coût projet SN-GES PETROGAZ-61542-C S-QCBS / Recrutement d'un c Sélection fondée s Institutional diagnostic and c Open - Internationa abinet de ressources humain IDA / 60530 A priori ur la qualité et le 500,000.00 0.00 Annulé 2018-06-08 2019-05-30 2018-06-29 2019-06-18 2018-08-12 2018-09-09 2018-10-09 2018-11-13 2018-12-18 2019-12-18 apacity building l es spécialisé dans le recrute coût ment, l'audit et le renforcem ent de capacités GES PI SIG 2019 2 / Sélectio Sélection fondée s n d'un cabinet de consultants Institutional diagnostic and c Open - Internationa IDA / 60530 A posteriori ur les qualification 200,000.00 618,813.94 Signé 2019-04-01 2019-09-23 2019-04-22 2019-11-08 2019-06-05 2020-03-17 2019-07-05 2020-07-07 2019-08-09 2020-08-21 2020-02-05 pour la mise en place d'un SI apacity building l s des consultants G pour l'amont pétrolier et le cadastre pétrolier GES FIN GAZ 4 / Recrutemen t d'un cabinet de conseil spé Sélection fondée s Enhancement of the strategi Open - Internationa cialisé dans le financement a IDA / 60530 A priori ur la qualité et le 1,000,000.00 0.00 Annulé 2017-06-13 2017-11-16 2017-07-04 2017-08-17 2018-05-01 2017-09-14 2018-02-08 2017-10-14 2018-06-08 2017-11-18 2017-12-23 2018-12-23 c and policy framework l mont du gaz et le financeme coût nt de projets de liquéfaction du gaz GES-SCHEMADIR-13 / Recrut Sélection fondée s ement d'une société chargée Institutional diagnostic and c Open - Internationa IDA / 60530 A priori ur la qualité et le 500,000.00 0.00 Annulé 2018-04-16 2018-09-24 2018-05-07 2018-10-23 2018-06-20 2018-07-18 2018-08-17 2018-09-21 2018-10-26 2019-10-26 d'élaborer un schéma directe apacity building l coût ur du pétrole et du gaz GES PI AUCDITCOUPE / Audit Support for hydrocarbon proj Sélection fondée s Open - Internationa En cours d'exécut IDA / 60530 A priori 2,000,000.00 0.00 2019-05-13 2019-06-25 2019-06-03 2019-07-12 2019-07-17 2020-12-10 2019-08-14 2021-02-02 2019-09-13 2021-05-27 2019-10-18 2021-08-09 2019-11-22 2022-11-21 des coûts pétroliers ect negotiations ur la qualité et le l ion coût SN-GES PETROGAZ-61540-C S-QCBS / Recrutement d'un c abinet chargé de la revue du Sélection fondée s Support for hydrocarbon proj Open - Internationa cadre légal et fiscal des inves IDA / 60530 A priori ur la qualité et le 500,000.00 0.00 Annulé 2018-06-07 2018-06-28 2018-08-11 2018-09-08 2018-10-08 2018-11-12 2018-12-17 2019-12-17 ect negotiations l tissements faits dans le dom coût aine des hydrocarbures amo nt au Sénégal pour le MEFP e t le MPE. GES PI SCHEMDIR / Élaborati Sélection fondée s Institutional diagnostic and c Open - Internationa on plan directeur pour le dév IDA / 60530 A posteriori ur la qualité et le 500,000.00 501,480.00 Signé 2019-05-06 2019-05-07 2019-05-27 2019-07-10 2019-09-06 2019-08-07 2019-10-23 2019-09-06 2020-02-03 2019-10-11 2020-07-17 2019-11-15 2020-09-01 2020-11-14 apacity building l eloppement du secteur pétro coût lier et gazier GES PI ENVI 2019 1 / Recrut Sélection fondée s Institutional diagnostic and c Open - Internationa ement d'un cabinet de consul IDA / 60530 A posteriori ur la qualité et le 380,000.00 491,781.06 Signé 2019-05-06 2019-08-14 2019-05-27 2019-07-10 2020-03-09 2019-08-07 2020-04-29 2019-09-06 2020-07-03 2019-10-11 2020-10-23 2019-11-15 2020-11-20 2020-11-14 apacity building l tants spécialisé en gestion e coût nvironnementale 2019 RENFOR / Diagnostic d’ Sélection fondée s institutions impliquées dans l Institutional diagnostic and c Open - Internationa IDA / 60530 A posteriori ur la qualité et le 500,000.00 450,793.76 Achevé 2019-11-18 2020-02-19 2019-12-09 2020-01-22 2020-07-21 2020-02-19 2020-09-09 2020-03-20 2020-11-20 2020-04-24 2020-12-11 2020-05-29 2021-02-17 2021-02-23 2021-10-29 a gestion du secteur amont d apacity building l coût es hydrocarbures et le renfor cement de capacités GES-CONS 15-MEDER / Recr utement d'un cabinet de con Sélection fondée s Project management and co Open - Internationa seillers ad hoc pour le MPE s IDA / 60530 A priori ur la qualité et le 1,000,000.00 0.00 Annulé 2018-04-16 2018-05-07 2018-06-20 2018-07-18 2018-08-17 2018-09-21 2018-10-26 2019-10-26 ordination l pecialisé dans le Developpe coût ment des hydrocarbures SN-GES PETROGAZ-61717-C Sélection fondée s S-QCBS / Recrutement d'un c Support for hydrocarbon proj Open - Internationa IDA / 60530 A priori ur la qualité et le 500,000.00 0.00 Annulé 2018-06-07 2018-06-28 2018-08-11 2018-09-08 2018-10-08 2018-11-12 2018-12-17 2019-12-17 abinet pour la réalisation de l ect negotiations l coût 'étude post-mortem "Requin- Tigre" SN-GES PETROGAZ-49070-C S-QCBS / Recrutement d'un C Sélection fondée s Enhancement of the strategi Open - Internationa abinet de spécialistes des qu IDA / 60530 A priori ur la qualité et le 1,000,000.00 0.00 Annulé 2018-02-28 2018-03-21 2018-05-04 2018-06-01 2018-07-01 2018-08-05 2018-09-09 2019-09-09 c and policy framework l estions juridiques et fiscales coût dans l'industrie pétrolière et gazière Enhancement of the strategi Sélection fondée s Open - Internationa GES PI LOI GAZ / Loi gazière IDA / 60530 A posteriori 500,000.00 0.00 Annulé 2019-06-03 2019-05-10 2019-06-24 2019-08-07 2019-09-04 2019-10-04 2019-11-08 2019-12-13 2020-12-12 c and policy framework ur la qualité et le l coût SEFA 2020 / Mise en place d Sélection fondée s Support for hydrocarbon proj Open - Internationa u SEFA - (Evaluation Environ IDA / 60530 A posteriori ur les qualification 380,000.00 0.00 Annulé 2020-05-25 2020-07-09 2020-08-22 2020-09-21 2020-11-04 2021-05-03 ect negotiations l nementale Stratégique du se s des consultants cteur offshore) CART MARINE 2020 / Service Sélection fondée s Support for hydrocarbon proj Open - Internationa s d'élaboration carte des sen IDA / 60530 A posteriori ur les qualification 40,000.00 0.00 Annulé 2020-06-01 2020-07-16 2020-08-29 2020-09-28 2020-11-02 2021-01-31 ect negotiations l sibilités marines s des consultants 2020 CAB ING / Recrutemen Sélection fondée s Support for hydrocarbon proj Open - Internationa t d’un cabinet d’ingénierie po IDA / 60530 A posteriori ur la qualité et le 600,000.00 0.00 Annulé 2020-03-08 2020-03-29 2020-05-12 2020-06-09 2020-07-09 2020-08-13 2020-09-17 2021-09-17 ect negotiations l ur un contrat cadre coût GES AFF JUR 1 / Recrutemen Sélection fondée s t d'un cabinet de conseil spé Enhancement of the strategi Open - Internationa IDA / 60530 A priori ur la qualité et le 1,000,000.00 0.00 Annulé 2017-06-12 2017-11-16 2017-07-03 2017-08-16 2017-09-13 2017-10-13 2017-11-17 2017-12-22 2018-12-22 cialisé dans les affaires juridi c and policy framework l coût ques et fiscales dans l'industr ie du pétrole et du gaz JUR MPE / Services juridique Support for hydrocarbon proj Sélection fondée s Open - Internationa IDA / 60530 A priori 1,000,000.00 1,698,466.25 Signé 2021-02-01 2021-04-20 2021-02-22 2021-04-28 2021-04-07 2021-07-29 2021-05-22 2021-09-02 2021-06-21 2021-11-15 2021-07-26 2022-04-08 2021-09-08 2022-05-23 2023-09-08 s MPE ect negotiations ur la qualité et le l coût SEFA / Mise en place SEFA (E Sélection fondée s Enhancement of the strategi Open - Internationa valuation Environnementale IDA / 60530 A posteriori ur la qualité et le 400,000.00 294,975.00 Signé 2021-02-08 2021-06-08 2021-03-01 2021-07-09 2021-04-14 2021-08-12 2021-05-29 2021-12-10 2021-06-28 2022-01-12 2021-08-02 2022-04-08 2021-09-15 2022-07-18 2022-09-15 c and policy framework l Stratégique du secteur offsh coût ore) Page 2 SE INDIC / Formation suivi-é Institutional diagnostic and c Sélection au moin valuation des projets pétrolie IDA / 60530 A posteriori Open - National 24,000.00 0.00 Annulé 2021-03-15 2021-03-03 2021-04-05 2021-05-19 2021-06-23 2021-07-23 2021-08-27 2021-10-10 2021-12-09 apacity building dre coût rs pour la mise à jour des indi cateurs ACCOSTAGE / Etude faisabili Sélection fondée s Enhancement of the strategi té infrastructures d’accostag IDA / 60530 A posteriori ur les qualification Open - National 180,000.00 177,243.79 Signé 2021-09-27 2021-07-22 2021-10-18 2021-12-17 2021-10-20 2022-01-16 2022-02-09 2022-03-01 2022-03-08 2022-06-29 c and policy framework e s des consultants SE CNSCL / Définition et mis Sélection fondée s e en place d'outils de suivi et Institutional diagnostic and c Open - Internationa IDA / 60530 A posteriori ur les qualification 200,000.00 0.00 Signé 2022-02-21 2022-04-18 2022-03-14 2022-05-12 2022-04-18 2022-08-18 2022-05-18 2022-10-04 2022-06-22 2022-10-20 d'évaluation du contenu local apacity building l s des consultants dans les projets pétroliers et gaziers STRAT CNSCL / Services d'él Sélection fondée s Institutional diagnostic and c En cours d'exécut aboration de la stratégie nati IDA / 60530 A posteriori ur les qualification Open - National 100,000.00 0.00 2022-02-23 2022-09-12 2022-03-16 2022-09-20 2022-04-29 2022-05-29 2022-07-03 2022-10-31 apacity building ion onale du contenu local s des consultants SIG POLLUTION / Elaboration et Mise en place d'un systèm Sélection fondée s e d'information pour la gestio Institutional diagnostic and c Open - Internationa En cours d'exécut IDA / 60530 A posteriori ur la qualité et le 600,000.00 0.00 2022-03-30 2022-03-23 2022-04-20 2022-04-13 2022-05-20 2022-08-19 2022-07-04 2022-09-21 2022-07-25 2022-12-16 2022-09-23 2023-01-11 2022-10-28 2023-12-31 n de la sécurité, sureté préve apacity building l ion coût ntion de la pollution des navi res et plateformes offshore ATLAS / Atlas de l'Environne Institutional diagnostic and c Sélection fondée s Open - Internationa En cours d'exécut IDA / 60530 A posteriori 500,000.00 0.00 2021-07-26 2022-05-17 2021-08-16 2022-06-14 2021-09-29 2022-10-10 2021-11-13 2022-11-16 2021-12-13 2022-01-17 2022-03-02 2022-08-31 ment du milieu Offshore apacity building ur la qualité et le l ion coût LABO / Etude de faisabilité Sélection fondée s Institutional diagnostic and c Open - Internationa En cours d'exécut mise en place laboratoire po IDA / 60530 A posteriori ur la qualité et le 386,000.00 0.00 2022-05-10 2022-11-11 2022-05-31 2022-12-21 2022-07-14 2022-08-28 2022-09-27 2022-11-01 2022-12-15 2023-08-12 apacity building l ion ur le contrôle qualité des hyd coût rocarbures COMPTAGE / Recrutement d' Sélection fondée s un cabinet spécialisé en com Institutional diagnostic and c Open - Internationa En cours d'exécut IDA / 60530 A posteriori ur la qualité et le 340,000.00 0.00 2022-06-13 2022-11-08 2022-07-04 2022-12-02 2022-08-17 2022-08-31 2022-09-30 2022-11-04 2022-12-09 2023-12-31 ptage mesurage et certificati apacity building l ion coût on des compteurs CAB CODE MAR / Recruteme Sélection fondée s nt d’un cabinet pour la réfor Enhancement of the strategi En cours d'exécut IDA / 60530 A posteriori ur les qualification Open - National 160,000.00 0.00 2023-01-16 2022-12-12 2023-02-10 2022-12-14 2023-03-11 2023-04-01 2023-05-06 2023-11-07 me du Code de la Marine ma c and policy framework ion s des consultants rchande du Sénégal et de se s textes d’application CAB SIT REF / Recrutement d’un Cabinet d’étude pour fai Sélection fondée s re la situation de référence d Enhancement of the strategi Open - Internationa En cours d'exécut IDA / 60530 A posteriori ur les qualification 160,000.00 0.00 2023-01-23 2022-12-13 2023-02-22 2023-03-29 2023-04-19 2023-05-24 2023-11-20 es projets pétroliers et gazier c and policy framework l ion s des consultants s dans une perspective d’éva luation ultérieure des impact s économiques ECO MPEC / Sélection d'un c abinet pour l'étude de l'adapt Sélection fondée s Enhancement of the strategi Open - Internationa En cours d'exécut ation de l’économie sénégala IDA / 60530 A posteriori ur les qualification 140,000.00 0.00 2023-01-09 2022-12-13 2023-02-08 2023-03-15 2023-04-05 2023-05-10 2023-11-06 c and policy framework l ion ise à l’exploitation des resso s des consultants urces pétrolières et gazières RESERVES / Services d'ingén Sélection fondée s Support for hydrocarbon proj Open - Internationa ierie de réservoir et de certifi IDA / 60530 A posteriori ur la qualité et le 420,000.00 0.00 Annulé 2022-04-18 2022-04-28 2022-05-09 2022-05-16 2022-06-22 2022-07-06 2022-08-05 2022-09-09 2022-10-14 2023-12-31 ect negotiations l cation de réserves coût FIN GAZ / Recrutement d'un Sélection fondée s Support for hydrocarbon proj Open - Internationa cabinet de conseils en financ IDA / 60530 A posteriori ur la qualité et le 540,000.00 0.00 Annulé 2021-07-05 2021-12-02 2021-07-26 2021-09-08 2021-10-23 2021-11-22 2021-12-27 2022-01-31 2024-01-31 ect negotiations l es pour PETROSEN coût PLAN STRA PETRO / Sélectio Sélection fondée s n de cabinet de consultants p Institutional diagnostic and c Open - Internationa En cours d'exécut IDA / 60530 A priori ur la qualité et le 1,000,000.00 0.00 2023-01-03 2023-01-11 2023-01-18 2023-01-19 2023-03-03 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2023-12-31 our l’élaboration du Plan Stra apacity building l ion coût tégique PETROSEN INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GES-COMPT-16 / Recutemen Support for hydrocarbon proj IDA / 60530 A posteriori Individuel Limited 150,000.00 21,422.16 Signé 2017-08-29 2018-02-21 2017-09-03 2018-03-18 2017-09-24 2018-03-18 2017-10-29 2018-03-26 2018-04-27 t d'un comptable ect negotiations SN-GES PETROGAZ-48216-C Project management and co S-INDV / Recrutement d'un S IDA / 60530 A posteriori Individuel Limited 100,000.00 32,266.26 Signé 2018-02-19 2018-02-23 2018-02-24 2017-02-27 2018-03-17 2018-03-08 2018-04-21 2018-04-01 2018-10-18 ordination pécialiste en Suivi-Evaluation SN-GES PETROGAZ-48222-C Project management and co S-INDV / Recrutement d'un R IDA / 60530 A posteriori Individuel Limited 100,000.00 3,213.32 Signé 2018-02-19 2018-02-23 2018-02-24 2018-03-20 2018-03-17 2018-04-24 2018-04-21 2018-08-01 2018-10-18 ordination esponsable Administratif et F inancier GES-INGPETR-07 / Recrutem Enhancement of the strategi IDA / 60530 A priori Individuel Limited 300,000.00 0.00 Annulé 2017-08-22 2017-08-27 2017-09-17 2017-10-22 2018-04-20 ent d'un ingénieur pétrolier c and policy framework GES-ECOPETR-08 / Recrutem Enhancement of the strategi IDA / 60530 A priori Individuel Open 300,000.00 0.00 Annulé 2017-08-22 2017-10-10 2017-10-31 2017-12-05 2018-06-03 ent d'un économiste pétrole c and policy framework et gaz GES-INGRES-09 / Recruteme Enhancement of the strategi IDA / 60530 A priori Individuel Open 300,000.00 0.00 Annulé 2017-08-22 2017-10-10 2017-10-31 2017-12-05 2018-06-03 nt d'un ingénieur réservoir c and policy framework GES-INGGESPRO-10 / Recrut Enhancement of the strategi IDA / 60530 A priori Individuel Open 300,000.00 0.00 Annulé 2017-08-29 2017-10-17 2017-11-07 2017-12-12 2018-06-10 ement d'un ingénieur gestion c and policy framework de projet GES-JURPETR-11 / Recrutem Enhancement of the strategi IDA / 60530 A priori Individuel Open 300,000.00 0.00 Annulé 2017-08-29 2017-10-17 2017-11-07 2017-12-12 2018-06-10 ent d'un juriste pétrole et gaz c and policy framework GES-FISC-12 / Recrutement Enhancement of the strategi IDA / 60530 A priori Individuel Open 300,000.00 0.00 Annulé 2017-08-29 2017-10-17 2017-11-07 2017-12-12 2018-06-10 d'un fiscaliste c and policy framework GES PS 5 / Recrutement d'un Project management and co spécialiste de la passation de IDA / 60530 A posteriori Individuel Open 100,000.00 32,133.24 Signé 2018-04-02 2018-06-01 2018-05-21 2018-06-13 2018-06-11 2018-06-13 2018-07-16 2018-08-01 2019-01-12 ordination marchés Senior Page 3 SN-GES PETROGAZ-48791-C S-INDV / Recrutement d'un R Project management and co IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-14 2018-05-19 2018-06-19 2018-07-10 2018-08-14 2019-02-10 esponsable de la composant ordination e Campagne de mobilisation des parties prenantes SN-GES PETROGAZ-48787-C S-INDV / Recrutement d'un R Project management and co esponsable de la Composant IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-14 2018-05-19 2018-06-19 2018-07-10 2018-08-14 2019-02-10 ordination e Soutien aux négociations s ur le projet d'hydrocarbures SN-GES PETROGAZ-48789-C S-INDV / Recrutement d'un R Project management and co IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-14 2018-05-19 2018-06-19 2018-07-10 2018-08-14 2019-02-10 esponsable de la composant ordination e Renforcement du cadre str atégique et politique SN-GES PETROGAZ-48790-C S-INDV / Recrutement d'un R Project management and co esponsable de la composant IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-14 2018-05-19 2018-06-19 2018-07-10 2018-08-14 2019-02-10 ordination e Diagnostic institutionnel et renforcement des capacités SN-GES PETROGAZ-61538-C S-INDV / Recrutement d'un c Support for hydrocarbon proj onseiller spécialisé dans l'ind IDA / 60530 A priori Individuel Open 300,000.00 0.00 Annulé 2018-06-01 2018-05-25 2018-07-20 2018-08-10 2018-09-14 2019-03-13 ect negotiations ustrie pétrolière et gazière p our le Ministère du Pétrole et des Energies SN-GES PETROGAZ-65002-C S-INDV / Recrutement d'un c Project management and co hargé du suivi des bénéficiair IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-08 2018-06-13 2018-07-04 2018-08-08 2019-02-04 ordination es du Projet pour le compte d e l' unité d'exécution du Proj et. SN-GES PETROGAZ-60803-C S-INDV / Recrutement d'un E Support for hydrocarbon proj xpert juriste et fiscaliste spéc IDA / 60530 A priori Individuel Open 500,000.00 0.00 Annulé 2018-05-31 2018-05-31 2018-07-19 2018-08-09 2018-09-13 2019-03-12 ect negotiations ialisé dans l'industrie du Pétr ole et du Gaz pour le MEFP et le MPE SN-GES PETROGAZ-65698-C S-INDV / Recrutement d'un E Support for hydrocarbon proj xpert juriste et fiscaliste spéc IDA / 60530 A priori Individuel Open 500,000.00 1,304,861.00 Signé 2018-06-14 2018-06-20 2018-08-02 2018-09-14 2018-08-23 2020-01-07 2018-09-27 2020-01-01 2019-03-26 ect negotiations ialisé dans l'industrie du Pétr ole et du Gaz pour le MEFP et le MPE SN-GES PETROGAZ-66665-C S-INDV / Recrutement d'un c Project management and co onseiller spécialisé dans l'ind IDA / 60530 A posteriori Individuel Open 300,000.00 230,400.00 Signé 2018-06-20 2018-06-20 2018-08-08 2018-09-07 2018-08-29 2019-12-02 2018-10-03 2019-01-22 2019-04-01 ordination ustrie pétrolière et gazière p our le Ministère du Pétrole et des Energies SN-GES PETROGAZ-70424-C S-INDV / Recrutement d'un R Project management and co IDA / 60530 A posteriori Individuel Open 100,000.00 31,953.42 Signé 2018-07-30 2018-09-03 2018-09-17 2019-03-11 2018-10-08 2019-03-11 2018-11-12 2019-06-01 2019-05-11 esponsable de la composant ordination e Campagne de mobilisation des parties prenantes SN-GES PETROGAZ-70425-C S-INDV / Recrutement d'un R Project management and co esponsable de la composant IDA / 60530 A posteriori Individuel Open 100,000.00 31,950.72 Signé 2018-07-30 2018-09-03 2018-09-17 2019-02-11 2018-10-08 2019-02-11 2018-11-12 2019-04-01 2019-05-11 ordination e Diagnostic institutionnel et renforcement des capacités SN-GES PETROGAZ-70426-C S-INDV / Recrutement d'un c Project management and co hargé du suivi des bénéficiair IDA / 60530 A posteriori Individuel Open 100,000.00 32,129.10 Signé 2018-08-03 2018-11-09 2018-09-21 2019-04-10 2018-10-12 2020-04-10 2018-11-16 2020-05-13 2019-05-15 ordination es du Projet pour le compte d e l' unité d'exécution du Proj et GES CI DON 2019 1 / Recrut ement d'un consultant indivi duel pour l'étude sur la mise Institutional diagnostic and c ne place d'une plateforme de IDA / 60530 A posteriori Individuel Limited 12,000.00 18,639.50 Signé 2018-12-17 2019-11-20 2018-12-22 2020-01-13 2019-01-12 2020-05-13 2019-02-16 2020-07-17 2019-03-18 apacity building collectes de données pour le compte du Ministère de l'Envi ronnement et du Développe ment durable (MEDD) SN-GES PETROGAZ-70422-C S-INDV / Recrutement d'un R Project management and co esponsable de la Composant IDA / 60530 A posteriori Individuel Open 100,000.00 0.00 Annulé 2018-07-30 2018-09-18 2018-09-17 2018-10-08 2018-11-12 2019-05-11 ordination e Soutien aux négociations s ur le projet d'hydrocarbures SN-GES PETROGAZ-70423-C S-INDV / Recrutement d'un R Project management and co IDA / 60530 A posteriori Individuel Open 100,000.00 0.00 Annulé 2018-07-30 2018-09-18 2018-09-17 2018-10-08 2018-11-12 2019-05-11 esponsable de la composant ordination e Renforcement du cadre str atégique et politique SN-GES PETROGAZ-64998-C S-INDV / Recrutement d'un c Project management and co onseiller technique en charg IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-20 2018-06-25 2018-07-16 2018-08-20 2019-02-16 ordination e des projets pétroliers et ga ziers pour le Ministre du Pétr ole et des Énergies SN-GES PETROGAZ-64994-C S-INDV / Recrutement d'un c Project management and co onseiller technique en midstr IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-13 2018-06-18 2018-07-09 2018-08-13 2019-02-09 ordination eam et aval pétrolier et gazie r pour le Ministre du Pétrole et des Energies SN-GES PETROGAZ-54565-C S-INDV / Sélection d'un Cons Project management and co IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-03 2018-06-08 2018-06-29 2018-08-03 2019-01-30 ultant Individuel pour la trad ordination uction de documents en angl ais ou en français. GES CI MAN EXE 2019 / Recr Support for hydrocarbon proj utement d'un consultant pou IDA / 60530 A posteriori Individuel Limited 20,000.00 18,327.70 Achevé 2019-04-01 2019-03-26 2019-04-06 2019-04-01 2019-04-27 2019-04-10 2019-06-01 2019-04-30 2019-07-01 2020-07-06 ect negotiations r l'élaboration d'un manuel d' exécution SN-GES PETROGAZ-48898-C S-INDV / Recrutement d'un E Project management and co IDA / 60530 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2018-03-05 2018-03-10 2018-03-31 2018-05-05 2018-11-01 xpert en Business et Stratégi ordination e Organisationnelle du Pétrol e et du Gaz Page 4 SN-GES PETROGAZ-48223-C Project management and co S-INDV / Recrutement d'un A IDA / 60530 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2018-03-29 2018-04-03 2018-04-24 2018-05-29 2018-11-25 ordination uditeur Interne SN-GES PETROGAZ-54540-C S-INDV / Recrutement d'un S Project management and co pécialiste en Passation des M IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-05-21 2018-05-24 2018-05-26 2018-06-16 2018-07-21 2019-01-17 ordination archés pour le Ministère du P étrole et des Energies SN-GES PETROGAZ-64996-C S-INDV / Recrutement d'un c Project management and co IDA / 60530 A posteriori Individuel Limited 100,000.00 0.00 Annulé 2018-06-13 2018-06-20 2018-06-18 2018-07-09 2018-08-13 2019-02-09 onseiller économique et strat ordination égique pour le Ministre du Pé trole et des Énergies STAT COTIERE 2020 / Etude sur la contribution des statio Support for hydrocarbon proj IDA / 60530 A posteriori Individuel Limited 30,000.00 0.00 Annulé 2020-05-03 2020-09-29 2020-05-08 2020-12-14 2020-05-29 2020-07-03 2020-10-01 ns côtières de surveillance a ect negotiations u développement du secteur pétro gazier PLAN MARIN 2020 / Etude su Support for hydrocarbon proj IDA / 60530 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2020-04-27 2020-05-02 2020-05-23 2020-06-27 2020-09-25 r la planification spatiale mar ect negotiations ine 2020 RSE / Recrutement d’u Project management and co IDA / 60530 A posteriori Individuel Direct 36,000.00 0.00 Annulé 2020-04-06 2020-04-16 2020-05-07 2020-06-11 2021-06-11 n responsable du suivi évalu ordination ation RECRU-JUR-2019 / Recrutem Support for hydrocarbon proj IDA / 60530 A priori Individuel Open 1,000,000.00 0.00 Annulé 2019-09-02 2019-08-23 2019-10-21 2019-11-11 2019-12-16 2020-12-15 ent d'une expert conseiller ju ect negotiations ridique RECRU-ANAFIN-2019 / Recru Support for hydrocarbon proj tement d'un analyste écono IDA / 60530 A priori Individuel Open 1,000,000.00 0.00 Annulé 2019-09-02 2019-08-23 2019-10-21 2019-11-11 2019-12-16 2020-12-15 ect negotiations miste et financier GES-MANUELEXC-17 / Recrut ement d'un consultant charg Support for hydrocarbon proj IDA / 60530 A posteriori Individuel Open 50,000.00 0.00 Annulé 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2018-12-10 é de développer le manuel d' ect negotiations exécution du projet CONS-RMP / Consultant revu Project management and co IDA / 60530 A posteriori Individuel Limited 40,000.00 42,389.69 Signé 2020-10-22 2020-10-23 2020-10-27 2020-10-27 2020-11-17 2020-11-13 2020-12-22 2020-12-04 2021-02-20 e à mi-parcours ordination TEX FPSO / Elaboration texte Enhancement of the strategi s applicables aux FPSO, FLNG IDA / 60530 A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-01-25 2021-01-29 2021-04-09 2021-04-30 2021-06-13 2021-12-10 c and policy framework , méthaniers et tankers PECHE ARTI / Elaboration ca Enhancement of the strategi dre réglementaire sur la sécu IDA / 60530 A posteriori Individuel Limited 30,000.00 26,460.90 Achevé 2021-01-18 2021-07-02 2021-01-23 2021-06-09 2021-03-09 2021-06-30 2021-04-22 2021-08-10 2021-09-19 2022-02-11 c and policy framework rité de la pêche artisanale POLMAR / Elaboration d’un p Institutional diagnostic and c lan sectoriel POLMAR pour le IDA / 60530 A posteriori Individuel Limited 30,000.00 26,441.55 Achevé 2021-02-22 2021-05-21 2021-02-27 2021-06-08 2021-04-13 2021-06-30 2021-05-27 2021-09-14 2021-08-25 2022-03-14 apacity building s aires marines protégées EX AMON / Recrutement d'u Support for hydrocarbon proj IDA / 60530 A posteriori Individuel Open 288,000.00 105,807.00 Achevé 2021-02-15 2021-03-09 2021-04-05 2021-06-07 2021-04-26 2021-07-23 2021-06-09 2021-10-25 2023-06-09 2021-12-15 n expert dans l'Amont pétroli ect negotiations er EX OPER / Recrutement d'un Support for hydrocarbon proj expert en Contrôle des Opéra IDA / 60530 A posteriori Individuel Open 288,000.00 148,129.80 Signé 2021-02-15 2021-03-05 2021-04-05 2021-06-07 2021-04-26 2021-07-23 2021-05-31 2021-10-25 2023-05-31 ect negotiations tions pétrolières JUR PETRO / Recrutement d' Sélection de cons un cabinet de conseils juridiq Support for hydrocarbon proj IDA / 60530 A posteriori ultants par entent Direct 800,000.00 734,515.41 Signé 2021-08-02 2021-10-13 2021-08-12 2021-11-02 2021-10-25 2022-07-20 2023-10-25 ues pour le financement des ect negotiations e directe parts de PETROSEN FPSO / Recrutement d'un co nsultant individuel pour l'éla Enhancement of the strategi boration de manuels de proc IDA / 60530 A posteriori Individuel Open 90,000.00 69,086.80 Achevé 2021-11-08 2021-07-28 2022-01-22 2021-10-08 2022-02-12 2021-11-09 2022-03-28 2021-12-08 2022-09-24 2022-08-10 c and policy framework édures pour les inspections des FPSO,FLNG , méthaniers et tankers ING COUT / Recrutement d'u Institutional diagnostic and c n ingénieur en charge du co IDA / 60530 A posteriori Individuel Open 216,000.00 84,323.16 Signé 2021-07-20 2021-12-17 2021-09-07 2022-04-22 2021-10-07 2022-05-13 2021-11-20 2022-06-13 2023-11-20 apacity building ntrôle des coûts ING PLAN / Recrutement d'u Institutional diagnostic and c En cours d'exécut IDA / 60530 A posteriori Individuel Open 216,000.00 0.00 2021-08-17 2021-12-17 2021-10-05 2021-11-04 2021-12-18 2024-03-17 n ingénieur méthode et plani apacity building ion fication CONC SE / Conception et im Project management and co plémentation d'un système d IDA / 60530 A posteriori Individuel Limited 24,000.00 23,827.63 Signé 2021-08-30 2021-08-25 2021-09-04 2021-10-21 2021-10-04 2021-11-26 2021-11-08 2021-12-17 2022-02-06 ordination e suivi-évaluation du projet REGUL DSR / Services acco Support for hydrocarbon proj En cours d'exécut mpagnement MPE dans la ré IDA / 60530 A posteriori Individuel Open 66,000.00 0.00 2022-03-21 2022-04-12 2022-05-09 2022-12-15 2022-05-30 2022-07-04 2023-06-29 ect negotiations ion glementation du secteur des hydrocarbures COM CNSCL / Services d’éla Stakeholders engagement c En cours d'exécut boration de la stratégie de co IDA / 60530 A posteriori Individuel Open 50,000.00 0.00 2022-03-09 2022-11-09 2022-04-18 2022-05-09 2022-06-13 2022-09-11 ampaign ion mmunication du comité de c ontenu local SE MEPC / Recrutement d'un expert suivi-évaluation des p Institutional diagnostic and c En cours d'exécut IDA / 60530 A posteriori Individuel Open 72,000.00 0.00 2022-04-27 2022-04-08 2022-05-31 2022-09-05 2022-06-21 2022-07-26 2023-07-26 rojets pétroliers et gaziers po apacity building ion ur le compte du MEPC ING GEOPHY / Recrutement Support for hydrocarbon proj En cours d'exécut d'un expert sénior en Géoph IDA / 60530 A posteriori Individuel Open 200,000.00 0.00 2022-03-14 2022-05-23 2022-05-02 2022-05-23 2022-06-27 2023-12-31 ect negotiations ion ysique Pétrolière ING GEOLO / Recrutement d' Support for hydrocarbon proj En cours d'exécut un expert sénior en Géologie IDA / 60530 A posteriori Individuel Open 200,000.00 0.00 2022-03-14 2022-05-23 2022-05-02 2022-05-23 2022-06-27 2023-12-31 ect negotiations ion -Pétrophysique Pétrolière ING RESERVE / Recrutement Support for hydrocarbon proj En cours d'exécut d'un expert sénior en ingénie IDA / 60530 A posteriori Individuel Open 200,000.00 0.00 2022-03-14 2022-05-23 2022-05-02 2022-05-23 2022-06-27 2023-12-31 ect negotiations ion rie de réservoir ING AVAL / Recrutement d'u Institutional diagnostic and c En attente d'exéc IDA / 60530 A posteriori Individuel Open 208,000.00 0.00 2022-04-11 2022-05-30 2022-06-29 2022-08-12 2023-12-31 n ingénieur Aval apacity building ution Page 5 ING AMON / Recrutement d' Institutional diagnostic and c IDA / 60530 A posteriori Individuel Open 208,000.00 0.00 Signé 2022-04-11 2022-03-23 2022-05-30 2022-07-25 2022-06-29 2022-08-16 2022-08-12 2023-12-31 un ingénieur Amont apacity building ING MID / Recrutement d'un Institutional diagnostic and c En attente d'exéc IDA / 60530 A posteriori Individuel Open 208,000.00 0.00 2022-04-11 2022-05-30 2022-06-29 2022-08-12 2023-12-31 ingénieur midstream apacity building ution EX ARCHI / Recrutement d' u Institutional diagnostic and c En cours d'exécut IDA / 60530 A priori Individuel Open 321,000.00 0.00 2022-04-11 2022-04-08 2022-05-30 2023-02-02 2022-06-29 2022-08-12 2023-12-31 n conseiller en architecture p apacity building ion étrolière CODE MAR / Réforme code d Enhancement of the strategi IDA / 60530 A posteriori Individuel Limited 130,000.00 0.00 Annulé 2021-07-26 2022-03-03 2021-07-31 2022-03-23 2021-09-14 2021-10-28 2022-06-27 e la marine marchande c and policy framework SIT REF / Etude de la situatio n de référence des projets pé Institutional diagnostic and c IDA / 60530 A posteriori Individuel Open 160,000.00 0.00 Annulé 2022-03-28 2022-05-16 2022-06-06 2022-07-11 2022-11-08 troliers et gaziers pour une é apacity building valuation ultérieure des impa cts économiques CADRE BUDGET / Services d e mise en place d'un cadre b Enhancement of the strategi IDA / 60530 A posteriori Individuel Limited 50,000.00 0.00 Annulé 2022-04-25 2022-04-30 2022-05-21 2022-07-04 2022-10-02 udgétaire de gestion des rec c and policy framework ettes du pétrole et du gaz EX ECO / Recrutement d'un expert économiste pour l'inté Institutional diagnostic and c gration de la dimension pétro IDA / 60530 A posteriori Individuel Open 108,000.00 0.00 Annulé 2022-03-28 2022-05-25 2022-05-16 2022-06-06 2022-07-11 2022-10-09 apacity building lière et gazière dans les mod èles de cadrage macro-écono mique STRA COM 2 / Poursuite de l Sélection de cons Stakeholders engagement c En cours d'exécut a mise en œuvre de la straté IDA / 60530 A priori ultants par entent Direct - National 500,000.00 0.00 2023-02-13 2023-02-07 2023-03-10 2023-02-23 2023-04-19 2023-12-31 ampaign ion gie de communication e directe INPG 2 / Services de mise en Sélection de cons œuvre du plan de renforcem Institutional diagnostic and c En cours d'exécut IDA / 60530 A priori ultants par entent Direct - National 1,000,000.00 0.00 2023-02-07 2023-02-07 2023-02-17 2023-04-07 2023-12-31 ent des capacités de la missi apacity building ion e directe on de diagnostic institutionn el Page 6