The World Bank                                                                                      Implementation Status & Results Report
         Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)



Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)


 AFRICA EAST | Tanzania | Education Global Practice |
 IBRD/IDA | Investment Project Financing | FY 2020 | Seq No: 4 | ARCHIVED on 13-Dec-2021 | ISR48464 |


 Implementing Agencies: President's Office, Regional; Administration and Local Government, Ministry of Finance and Planning, Ministry of Education,
 Science and Technology



 Key Dates


  Key Project Dates

   Bank Approval Date: 31-Mar-2020                                            Effectiveness Date: 23-Nov-2020
   Planned Mid Term Review Date: 21-Jun-2023                                  Actual Mid-Term Review Date:
   Original Closing Date: 31-Jan-2026                                         Revised Closing Date: 31-Jan-2026
 pdoTable

 Project Development Objectives

  Project Development Objective (from Project Appraisal Document)
  To increase access to secondary education, provide responsive learning environments for girls, and improve completion of quality secondary
  education for girls and boys.

  Has the Project Development Objective been changed since Board Approval of the Project Objective?
  No


 Components Table

 Name
 Component 1: Empowering Girls Through Secondary Education and Life Skills:(Cost $180.00 M)
 Component 2: Digitally-Enabled Effective Teaching and Learning:(Cost $115.00 M)
 Component 3: Reducing Barriers to Girls' Education through Facilitating Access to Secondary Schools:(Cost
 $185.00 M)
 Component 4: Project Coordination, Monitoring and Evaluation:(Cost $20.00 M)

 Overall Ratings

 Name                                                                       Previous Rating                          Current Rating

 Progress towards achievement of PDO                                        Satisfactory                            Satisfactory
 Overall Implementation Progress (IP)                                       Moderately Satisfactory                 Moderately Satisfactory
 Overall Risk Rating                                                        Substantial                             Substantial


 Implementation Status and Key Decisions

  Significant progress has been made since April 2021. Government has revised the Alternative Education Pathways (AEP) syllabus, developed
  teacher training materials, committed to providing fee-free places for all girls, and set out a costed implementation plan to more than double AEP
  centers in the neediest areas over the lifetime of the project. On November 29, 2021, Government issued a statement and circular allowing all
  dropouts, including young mothers, to return to formal schools to complete their education; and the developed ‘dropout early warning system
  (DEWS)’ will enable accurate tracking of school dropouts and their return to school. A taskforce comprising key players in the promotion of girls’
  education has been set up to guide the development of the Safe Schools Program (SSP) package for Tanzania. The science and mathematics
  modules to be used in the Continuous Professional Development (CPDs) program for secondary teachers have been developed and the in-service


12/13/2021                                                                                                                  Page 1 of 12
            The World Bank                                                                                     Implementation Status & Results Report
            Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)



  teacher orientation to the modules is scheduled for December 2021. The development process for the ICT in education strategy that will enable
  development and application of digital technologies in teacher training and classroom instruction is ongoing. In addition, the assessment of school
  infrastructure needs, along with the infrastructure designs have been prepared for use by the Implementation Support Team (IST) that will oversee
  the quality of school construction activities supported by SEQUIP.

  The World Bank Task Team continues to provide the necessary supervision support for timely implementation of SEQUIP.




  Risks


 Systematic Operations Risk-rating Tool


  Risk Category                                              Rating at Approval              Previous Rating               Current Rating

  Political and Governance                                   Substantial                    Moderate                     Moderate
  Macroeconomic                                              Moderate                       Moderate                     Moderate
  Sector Strategies and Policies                             Moderate                       Moderate                     Moderate
  Technical Design of Project or Program                     Substantial                    Moderate                     Moderate
  Institutional Capacity for Implementation and
                                                             Substantial                    Substantial                  Substantial
  Sustainability
  Fiduciary                                                  Substantial                    Substantial                  Substantial
  Environment and Social                                     Substantial                    Substantial                  Substantial
  Stakeholders                                               Moderate                       Moderate                     Moderate
  Other                                                      --                              Moderate                     Moderate
  Overall                                                    Substantial                    Substantial                  Substantial



  Results


 PDO Indicators by Objectives / Outcomes



   Access and responsive learning environments for girls

   IN01045583
   ►Percentage of female secondary school drop-outs completing Alternative Education Pathways Form 4 (Stage 2) (Percentage, Custom,
   PBC)

                                       Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                             1.00                         1.00                         1.00                       15.00

    Date                              31-Mar-2019                  03-Dec-2020                  03-Dec-2020               31-Mar-2025
                                       The Government is currently preparing for implementation, and MoEST and the Institute of Adult
                                       Education (IAE) are preparing a Implementation Manual which identifies improvements required in data.
   Comments:
                                       Currently this data is not available but will be reported in 2022.




12/13/2021                                                                                                                   Page 2 of 12
           The World Bank                                                                                   Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)



    IN01045585
    ►Alternative Education Pathway females enrolling in Form 5 and other post-secondary education (Percentage, Custom, PBC)

                                     Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            13.00                       13.00                        13.00                      26.00

    Date                             31-Mar-2019                 03-Dec-2020                  03-Dec-2020               31-Mar-2025
                                     The Government is currently preparing for implementation, and MoEST and the Institute of Adult
                                     Education (IAE) are preparing a Implementation Manual which identifies improvements required in data.
   Comments:                         This data is being compiled by IAE, therefore the baseline information is used and updated data will be
                                     reported in 2022.

    IN01045598
    ►Government schools implementing Safe School Program to support girls (Number, Custom, PBC)

                                     Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                        0.00                         0.00                       2,000.00

    Date                             31-Mar-2019                 03-Dec-2020                  03-Dec-2020               31-Mar-2025
                                     Implementation of the safe schools program is yet to start and any progress will be reported in Year 2,
   Comments:                         2022.



   Improved completion of secondary education

    IN01045582
    ►Government school enrolment in Form 4 (last grade of lower secondary) (Number, Custom)

                                     Baseline                    Actual (Previous)            Actual (Current)           End Target

    Value                            278,239.00                  334,284.00                   422,403.00                 515,438.00

    Date                             31-Mar-2018                 03-Dec-2020                  31-Mar-2021               31-Mar-2025
                                     The data recorded is from the BEMIS 2021. Results indicate a 21 percent increase in government school
                                     enrolment in Form 4. Decomposed results by gender indicate that girls' enrolment grew much more than
   Comments:                         boys- 22 percent for girls against 19 percent for the boys. This is trend matches what was recorded in the
                                     last ISR whereby in 2020 girls enrollment grew more compared to boys.

     IN01045597
     Government school enrolment in Form 4 (last grade of lower secondary) (Female, Number) (Number, Custom Breakdown)

                                   Baseline                     Actual (Previous)            Actual (Current)           End Target

     Value                         139,596.00                  171,532.00                    220,385.00                 259,555.00

     Date                          31-May-2019                 03-Nov-2020                   31-Mar-2021                31-May-2025

     IN01045599
     Government school enrolment in Form 4 (last grade of lower secondary) (Male, Number) (Number, Custom Breakdown)

                                   Baseline                     Actual (Previous)            Actual (Current)           End Target

     Value                         138,643.00                  162,752.00                    202,018.00                 255,883.00




12/13/2021                                                                                                                 Page 3 of 12
           The World Bank                                                                                       Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)




     Date                            31-May-2019                  03-Dec-2020                    31-Mar-2021                 31-May-2025

    IN01045600
    ►Females enrolled in Form 5 in government schools (Number, Custom, PBC)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              24,637.00                    22,727.00                     29,165.00                  39,637.00

    Date                               31-Mar-2019                  03-Dec-2020                   31-Mar-2021                31-Mar-2025
                                       The number of girls enrolled in Form 5 has increased by 16 percent since the baseline, and 22 percent
                                       since the last ISR (December 2020). This is a positive trend, and the indicator will be continue to be
   Comments:
                                       closely monitored to ensure the upward trend once SEQUIP activities begin.



   Improved quality of secondary education

   IN01045584
   ►Improvement in classroom teaching practice in Government Secondary Schools through regular in-service teacher training (Number,
   Custom, PBC)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         0.00                          0.00                       20,000.00

    Date                               31-Mar-2019                  03-Dec-2020                   03-Dec-2020                31-Mar-2025
                                       Implementation of the teachers in-service training is yet to start and any progress will be reported in Year
   Comments:                           2, 2022.

    IN01045596
    ►Secondary schools with adequate learning environments (Text, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target
                                                                                                                             50% of schools in all
                                                                                                                             184 LGAs meet
    Value                              0.00                         0.0. as at baseline           0.0. as at baseline
                                                                                                                             standards


    Date                               31-Mar-2019                  03-Dec-2020                   03-Dec-2020                31-Mar-2025

                                       Implementation of this activity is yet to start and any progress will be reported in Year 2, 2022.
   Comments:


 Overall Comments PDO

  Overall for the two out of seven PDO indicators reported in this ISR, there is a positive trend. The indicators of improved completion of
  secondary education show enrollment of girls and boys in lower secondary increasing by 21 percent and enrollment in advanced secondary
  increasing by 22 percent. This positive trend will continue to be monitored as the project moves into the second year of implementation and
  begins the implementation of project activities. Five out of the seven PDO indicators do not have data available and will be reported on in the
  second year of the program (2022).




 Intermediate Results Indicators by Components




12/13/2021                                                                                                                      Page 4 of 12
           The World Bank                                                                                      Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)




   Empowering Girls through Secondary Education and Life Skills

    IN01045604
    ►Strengthening information systems and incentives to prevent drop-out and support transfer to/from AEP (Yes/No, Custom, PBC)

                                     Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                            No                           No                             No                         Yes

    Date                             31-Mar-2019                  03-Dec-2020                    03-Dec-2020                31-May-2025
                                     The information system is being prepared during the first year and is yet to be approved and functional.
   Comments:                         Therefore progress for this indicator will be reported on in year two, 2022.

    IN01045608
    ►AEP centers with adequate learning materials (Percentage, Custom)

                                     Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                            0.00                         0.00                           0.00                       75.00

    Date                             31-Mar-2019                  03-Dec-2020                    03-Dec-2020                31-May-2025
                                     The IAE is following up on up-to-date information on this indicator, however, the activity has not yet
   Comments:                         started and will therefore be reported on in year two, 2022.

    IN01045610
    ►AEP centers with trained facilitators and provided with adequate teacher guides (Percentage, Custom)

                                     Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                            0.00                         0.00                           0.00                       75.00

    Date                             31-Mar-2019                  03-Dec-2020                    03-Dec-2020                31-May-2025
                                     The IAE is following up on up to date information on this indicator, however the activity has not started
   Comments:                         yet and will therefore be reported on in year two, 2022.

    IN01045613
    ►Female AEP learners (Number, Custom)

                                     Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                            2,839.00                     3,096.00                       3,096.00                   6,000.00

    Date                             31-Mar-2018                  03-Dec-2020                    03-Dec-2020                31-Mar-2025

                                     The IAE is following up on up to date information on this indicator, and this will be reflected.
   Comments:

    IN01045615
    ►AEP centers receiving government subsidy to support enrollment of vulnerable girls (Number, Custom)

                                     Baseline                     Actual (Previous)              Actual (Current)           End Target

    Value                            0.00                         0.00                           0.00                       50.00

    Date                             31-Mar-2019                  03-Dec-2020                    03-Dec-2020                31-May-2025



12/13/2021                                                                                                                    Page 5 of 12
           The World Bank                                                                                    Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)



                                     Provision of AEP centers with a government subsidy to support enrollment of vulnerable girls has not yet
   Comments:                         started. This will be reported in year two, 2022.



   Digitally-Enabled and Effective Teaching and Learning

    IN01045606
    ►Average gender gap in Form 4 and Form 6 examination pass rates in mathematics and science (Percentage, Custom)

                                     Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            13.00                       13.00                         11.50                     8.00

    Date                             31-Mar-2017                 03-Dec-2020                   03-Dec-2020               31-May-2025
                                     Average gender gap in Form 4 and Form 6 examination pass rates in mathematics and science has
                                     improved in 2019. The average gender gap in Form 4 examination pass rates (math and science)
                                     declined slightly compared to baseline to 12.85 percent; and in Form 6 we see, on average, girls
                                     performed better then boys. The gender gap in Form 6 is now in favor of girls with on average girls scoring
   Comments:
                                     84.3 percent compared to boys who scored 83 percent in 2019.
                                     This is the latest data reported in the Annual Education Sector Performance Report, further updates will
                                     be provided for 2020 and 2021 in the forthcoming ISR.

   IN01045609
   ►Government secondary schools with mathematics and science teachers deployed in line with national standards (Percentage, Custom,
   PBC)

                                     Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                        0.00                          0.00                      50.00

    Date                             31-Mar-2019                 03-Dec-2020                   03-Dec-2020               31-May-2025
                                     Currently the government is preparing the Teachers Deployment Strategy for approval, and therefore
                                     activities to deploy teachers as per the national standards have not yet begun. Progress on this indicator
   Comments:
                                     will be reported on in year two, 2022.

    IN01045611
    ►LGAs where 50 percent of secondary schools have minimum teaching and learning material standards (Text, Custom, PBC)

                                     Baseline                    Actual (Previous)             Actual (Current)          End Target
                                                                                                                         50% of all schools in
    Value                            0.00                        0.0 as at baseline            0.0 as at baseline        184 LGAs meet
                                                                                                                         standards
    Date                             31-Mar-2019                 03-Dec-2020                   03-Dec-2020               31-May-2025
                                     This indicator has required some data improvements in the BEMIS and will be reported on in the next ISR
   Comments:                         cycle.

    IN01045614
    ►Government schools successfully implementing ICT program (Number, Custom, PBC)

                                     Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                        0.00                          0.00                      1,500.00

    Date                             31-Mar-2019                 03-Dec-2020                   03-Dec-2020               31-Mar-2025




12/13/2021                                                                                                                 Page 6 of 12
           The World Bank                                                                                    Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)



                                      Currently the Government is developing the draft ICT in Education Strategy which will define the ICT
                                      program to be approved and rolled-out. Therefore reporting on this indicator is expected to begin in year
   Comments:
                                      two, 2022.

    IN01045616
    ►Form 3 national learning evaluation conducted (Number, Custom, PBC)

                                     Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                         0.00                         0.00                       2.00

    Date                             31-Mar-2019                  03-Dec-2020                  03-Dec-2020               31-Mar-2025
                                      This initiative has not yet started and the Government has restructured the deadline for this DLI. The
                                      Government is expecting to prepare the design of the learning evaluation for Form 3 by June 2022, and
   Comments:
                                      the evaluation will be conducted from there on. Further updates will be provided in year two, 2022.



   Reducing Barriers to Girls' Education through Facilitating Access to Secondary Schools

    IN01045601
    ►LGAs where 50 percent of secondary schools have basic infrastructure package (Text, Custom, PBC)

                                     Baseline                     Actual (Previous)            Actual (Current)          End Target
                                                                                                                         50% of all schools in
    Value                            0.00                         as at baseline               4.00                      184 LGAs meet
                                                                                                                         standards
    Date                             31-Mar-2019                  03-Dec-2020                  31-Mar-2021               31-May-2025
                                      As per the 2021 BEMIS data only four LGAs have 50 percent or more of their government schools
                                      achieving the basic infrastructure package. A total of fourteen LGAs had 25 percent or more of their
   Comments:                          government schools achieving the basic infrastructure package. This will continue to monitored closely
                                      once project activities begin.

    IN01045603
    ►Level of biannually released funds in line with agreed program budget framework (Percentage, Custom, PBC)

                                     Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                            0.00                         0.00                         60.00                      100.00

    Date                             31-Mar-2019                  03-Dec-2020                  24-Jun-2021               31-May-2025
                                      The bi-annual achievement of funds released as per the agreed program budget framework was 60
                                      percent for the period of July to December 2020, and the Government submitted a Notification of Results
   Comments:                          Achievement in June 2021 following verification. This bi-annual release will for January to June 2021 has
                                      recently been submitted but not yet verified.

    IN01045605
    ►Average distance to government secondary schools in rural areas (Text, Custom)

                                     Baseline                     Actual (Previous)            Actual (Current)           End Target

    Value                            tbd (June 2020)              tbd Dec 2020                 tbd Dec 2020               tbd (June 2020)

    Date                             31-Mar-2019                  03-Dec-2020                  03-Dec-2020               31-Mar-2025
   Comments:                          Agreement on the measurement norms for this indicator is yet to be reached.


12/13/2021                                                                                                                  Page 7 of 12
           The World Bank                                                                                      Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)




    IN01045607
    ►Students benefiting from direct interventions to enhance learning (Number, Corporate)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             1,814,686.00                1,814,686.00                  1,814,686.00               6,451,006.00

    Date                              31-Mar-2019                 03-Dec-2020                   03-Dec-2020                31-Mar-2025
                                      Interventions are yet to be implemented hence the baseline figure has been retained. However, it should
                                      be noted as per the latest BEMIS data enrollment in secondary schools (Form 1 to 6) has been
                                      increasing. The baseline data (2018) shows 1,814,686 students enrolled, in 2019 this increased to
                                      2,023,205 students, by 2020 this increased further to 2,172,257, and finally in 2021 this reached
   Comments:
                                      2,379,945 students enrolled in Form 1-6 government schools. The data shows that since 2018 there has
                                      been a 6 to 10 percent increase in the number of potential project beneficiaries, and this will continue to
                                      be closely monitored once program activities begin.

     IN01045612
     Students benefiting from direct interventions to enhance learning - Female (Number, Corporate Supplement)

                                    Baseline                     Actual (Previous)             Actual (Current)            End Target

     Value                          920,039.00                   920,039.00                    920,039.00                  3,191,718.00


   Project Coordination, Monitoring and Evaluation

    IN01045602
    ►Percentage of grievances received and addressed through the Project Grievance Redress Mechanisms (Percentage, Custom)

                                      Baseline                    Actual (Previous)             Actual (Current)           End Target

    Value                             0.00                        0.00                          0.00                       80.00

    Date                              31-Mar-2019                 03-Dec-2020                   03-Dec-2020                31-Mar-2025
                                      The Government recently completed a assessment on the GRMs for education and findings of the
                                      assessment will be used to strengthen the GRMs to ensure we can track (i) grievances received and (ii)
   Comments:
                                      grievances addressed.



 Overall Comments IR

  Activities are yet to be implemented and therefore few updates are provided in this ISR. The Government is also in the process of improving
  data systems to ensure the core indicators for SEQUIP are tracked over time. However, there is evidence of positive trend in closing the
  gender gap for Form 4 and Form 6 examination results in math and science, with girls demonstrating improved performance.




 Performance-Based Conditions




   IN01045617
   ►PBC 1 Percentage of female secondary school drop-outs completing Alternative Education Pathways Form 4 (Stage 2) (Percentage,
   Intermediate Outcome, 50,000,000.00, 10%)


12/13/2021                                                                                                                   Page 8 of 12
           The World Bank                                                                               Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)




                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       1.00                        1.00                         1.00                        --

    Date                        --                          03-Dec-2020                  03-Dec-2020                 --




   IN01045618
   ►PBC 2 Alternative Education Pathway females enrolling in Form 5 and other post-secondary education (Percentage, Intermediate
   Outcome, 30,000,000.00, 6%)


                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       13.00                       13.00                        13.00                       --

    Date                        --                          03-Dec-2020                  03-Dec-2020                 --




   IN01045619
    ►PBC 3 Government schools implementing Safe School Program to support girls (Number, Process, 30,000,000.00, 6%)


                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       0.00                        0.00                         0.00                        --

    Date                        --                          03-Dec-2020                  03-Dec-2020                 --




   IN01045620
    ►PBC 4 Females enrolled in Form 5 in government schools (Number, Output, 60,000,000.00, 12%)


                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       24,637.00                   22,727.00                    29,165.00                   --

    Date                        --                          03-Dec-2020                  31-Mar-2021                 --




   IN01045621
   ►PBC 5 Strengthening information systems and incentives to prevent drop-out and support transfer to/from AEP (Yes/No, Process,
   10,000,000.00, 2.00%)


                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       No                          No                           No                          --

    Date                        --                          03-Dec-2020                  03-Dec-2020                 --


12/13/2021                                                                                                            Page 9 of 12
           The World Bank                                                                               Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)




   IN01045622
   ►PBC 6 Improvement in classroom teaching practice in Government Secondary Schools through regular in-service teacher training
   (Number, Output, 30,000,000.00, 6.00%)


                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       0.00                        0.00                         0.00                        --

    Date                        --                          03-Dec-2020                  03-Dec-2020                 --




   IN01045623
   ►PBC 7 Government secondary schools with mathematics and science teachers deployed in line with national standards (Percentage,
   Intermediate Outcome, 30,000,000.00, 6.00%)


                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       0.00                        0.00                         0.00                        --

    Date                        --                          03-Dec-2020                  03-Dec-2020                 --




   IN01045624
   ►PBC 8 LGAs where 50 percent of secondary schools have minimum teaching and learning material standards (Text, Output,
   30,000,000.00, 6%)


                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       0.00                        0.0 as at baseline           0.0 as at baseline          --

    Date                        --                          03-Dec-2020                  03-Dec-2020                 --




   IN01045625
    ►PBC 9 Government schools successfully implementing ICT program (Number, Output, 10,000,000.00, 2.00%)


                                 Baseline                    Actual (Previous)           Actual (Current)            FY25

    Value                       0.00                        0.00                         0.00                        --

    Date                        --                          03-Dec-2020                  03-Dec-2020                 --




   IN01045626
    ►PBC 10 Form 3 national learning evaluation conducted (Number, Process, 15,000,000.00, 3.00%)


12/13/2021                                                                                                           Page 10 of 12
           The World Bank                                                                                      Implementation Status & Results Report
           Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)




                                 Baseline                        Actual (Previous)             Actual (Current)              FY25

    Value                        0.00                            0.00                          0.00                          --

    Date                         --                              03-Dec-2020                   03-Dec-2020                   --




   IN01045627
    ►PBC 11 LGAs where 50 percent of secondary schools have basic infrastructure package (Text, Output, 110,000,000.00, 22%)


                                 Baseline                        Actual (Previous)             Actual (Current)              FY25

    Value                        0.00                            as at baseline                4.00                          --

    Date                         --                              03-Dec-2020                   31-Mar-2021                   --




   IN01045628
    ►PBC 12 Level of biannually released funds in line with agreed program budget framework (Percentage, Process, 75,000,000.00, 15%)


                                 Baseline                        Actual (Previous)             Actual (Current)              FY25

    Value                        0.00                            0.00                          60.00                         --

    Date                         --                              03-Dec-2020                   24-Jun-2021                   --



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF    Status       Currency        Original   Revised       Cancelled       Disbursed     Undisbursed             % Disbursed


 P170480       IDA-65340         Effective    USD             500.00      500.00             0.00         74.00            446.04                   14%


 Key Dates (by loan)

 Project        Loan/Credit/TF    Status      Approval Date       Signing Date       Effectiveness Date      Orig. Closing Date     Rev. Closing Date

 P170480        IDA-65340         Effective   31-Mar-2020         21-May-2020        23-Nov-2020             31-Jan-2026            31-Jan-2026


Cumulative Disbursements




12/13/2021                                                                                                                   Page 11 of 12
          The World Bank                                                                          Implementation Status & Results Report
          Tanzania Secondary Education Quality Improvement Project (SEQUIP) (P170480)




 PBC Disbursement

                                                                                 Achievement   Disbursed amount in     Disbursement %
 PBC ID                   PBC Type     Description        Coc      PBC Amount
                                                                                 Status        Coc                     for PBC




  Restructuring History


  There has been no restructuring to date.


  Related Project(s)


 There are no related projects.




12/13/2021                                                                                                     Page 12 of 12