Summarized Procurement Plan I. GENERAL Project information: Borrower: Government of Lesotho Project Name: Lowlands Water Development Project Project ID No: P 160672 Grant No.: Project Implementing Agency: Commission of Water Bank’s approval Date of the Procurement Plan: December 17, 2019 Date of General Procurement Notice: Period covered by this procurement plan: 18 months II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 <7 ≤ 0.2 Goods, IT, and non- ≥4 ≥1 <1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on April 2019. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB 45.3 2 NIL Prior NIL (Works) Summary of the NCB 9.5 4 NIL Post NIL (Works) Summary of the ICB NIL NIL NIL NIL NIL (Goods) Summary of the NCB .47 4 n/a Post NIL (Goods) Summary of the RfQ .1 1 n/a Post NIL (Goods & Non- Consulting Services) Summary of the DC NIL NIL NIL NIL (Non-consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) 2 Review Consulting Engineering and (US$ Services Construction Supervision millions) Consultants (Firms) ≥2 ≤ 0.1 ≤ 0.3 Individual Consultants ≥ 0.4 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Procurement Regulations for IPF Borrowers. 3. Terms of Reference (TOR) for all consultancy contracts as well as all direction selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of 4.9 5 Post 1 Prior review contracts through QCBS Summary of 1.4 9 Post NIL contracts through CQS 3 Summary of 0.15 million 2 Post NIL contracts through IC 4 PROCUREMENT Lesotho : Lesotho Lowlands Water Development Project - Phase II PLAN General Information Country: Lesotho Bank’s Approval Date of the Original Procurement Plan: 2020-01-08 2022-02-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160672 GPN Date: Project Name: Lesotho Lowlands Water Development Project - Phase II Loan / Credit No: IDA / 64030, IDA / 64020 Lesotho Lowlands Water Development project Phase II Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LLWDP/W/04 / Construction Component 1. Water Supply Single Stage - One 18,720,000.0 2021-05- (with design), Transmission IDA / 64030 Prior Request for Bids Open - International 0.00 Canceled 2020-07-30 2020-08-04 2020-09-15 2020-10-15 2020-11-19 Investments in Zones 2 and 3 Envelope 0 18 Mains , zone 2 and 3 LLWDP/W/01 / Contractor Component 1. Water Supply Single Stage - One 2020-11- Refurbishment of Boreholes IDA / 64030 Post Request for Bids Open - National 300,000.00 342,080.56 Signed 2020-01-14 2020-03-27 2020-01-19 2020-01-23 2020-03-01 2020-12-03 2020-03-31 2020-12-10 2020-05-05 2021-02-17 Investments in Zones 2 and 3 Envelope 01 at Zones 2 and 3 LLWDP/W/07 / Contractor installation meters and valves Pending to Leakage Control Zones and Component 1. Water Supply Single Stage - One 2023-08- IDA / 64030 Post Request for Bids Open - National 2,700,000.00 0.00 Implementat 2022-10-31 2022-11-05 2022-12-17 2023-01-16 2023-02-20 refurbishment to existing Investments in Zones 2 and 3 Envelope 19 ion mains in Maputsoe, Hlotse and Tsikoane LLWDP/W/05 / Construction Pending of Distribution Systems - Component 1. Water Supply Single Stage - One 2023-08- IDA / 64030 Post Request for Bids Open - National 5,500,000.00 0.00 Implementat 2022-11-10 2022-11-15 2022-12-27 2023-01-26 2023-03-02 Khanyane, Hlotse, Tsikoane, Investments in Zones 2 and 3 Envelope 29 ion Ha Lesiamo, Mpharane LLWDP/W/03 / Design and Construction River Intake - Pending Raw Water Pumps & Water Component 1. Water Supply Single Stage - One 26,580,000.0 2024-07- IDA / 64030 Prior Request for Bids Open - International 0.00 Implementat 2022-06-23 2022-09-18 2022-09-18 2022-07-08 2022-11-27 2022-12-27 2023-01-31 Treatment Works, Reservoirs Investments in Zones 2 and 3 Envelope 0 24 ion and Pumping station - Leribe District LLWDP/W/06 / Construction Pending Component 1. Water Supply Single Stage - One 2023-07- of Distribution Systems - IDA / 64030 Post Request for Bids Open - National 6,000,000.00 0.00 Implementat 2022-09-22 2022-09-27 2022-11-08 2022-12-08 2023-01-12 Investments in Zones 2 and 3 Envelope 11 Maputsoe ion LLWDP/W/08 / Procurement Request for Bids - Component 4. Contingent of a contract to refurbish Single Stage - One Works (without 2023-01- IDA / 64020 Emergency Response Post Request for Bids Open - National 910,000.00 0.00 Canceled 2022-03-24 2022-03-29 2022-05-10 2022-06-09 2022-07-14 Gravity Systems Department Envelope prequalification) 10 Component of Rural Water Supply (DRWS). SPD LLWDP/W/11 / Procurement Component 4. Contingent Request for of a contractor for Request for Single Stage - One 2022-11- IDA / 64030 Emergency Response Post Open - National Quotations (Non 100,000.00 0.00 Canceled 2022-03-21 2022-05-16 Rehabilitation of Hydrometric Quotations Envelope 12 Component Bank-SPD) Stations LLWDP/W/12 / Procurement Request for Bids - of a contract for the Component 4. Contingent Single Stage - One Small Works SPD 2023-01- Rehabilitation of Water and IDA / 64030 Emergency Response Post Request for Bids Open - National 700,000.00 0.00 Canceled 2022-03-17 2022-03-22 2022-05-03 2022-06-02 2022-07-07 Envelope (1 envelope 03 Sewerage Company (WASCO) Component process) affected Systems Request for Bids - LLWDP/W/02 / Contractor Works (after Installation of meters and Pending Component 1. Water Supply Single Stage - One prequalification) 2024-01- valves Required for National IDA / 64030 Post Request for Bids Open - National 1,000,000.00 0.00 Implementat 2023-03-27 2023-04-01 2023-05-13 2023-06-12 2023-07-17 Investments in Zones 2 and 3 Envelope SPD - Applying 13 Baseline Assessment and ion contractor Study of Non Revenue Water disqualificiation LLWDP/W/10 / Procurement Component 4. Contingent Request for of Diesel Pumping Systems for Request for Single Stage - One 2022-10- IDA / 64030 Emergency Response Post Open - National Quotations (Non 20,000.00 0.00 Canceled 2022-02-26 2022-04-23 the Department of Rural Water Quotations Envelope 20 Component Bank-SPD) supply (DRWS) LLWDP/W/09 / procurement Request for Bids - Component 4. Contingent of Solar and Electric Pumping Single Stage - One Works (without 2023-01- IDA / 64030 Emergency Response Post Request for Bids Open - National 210,000.00 0.00 Canceled 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 Systems for the Department Envelope prequalification) 17 Component of Rural Water Supply (DRWS) SPD LLWDP/W/13 / Construction Pending Component 1. Water Supply Other (with field 2022-10- and Rehabilitation of IDA / 64020 Post Direct Selection Direct 40,000.00 0.00 Implementat 2022-02-28 2022-03-05 2022-04-09 Investments in Zones 2 and 3 for explanation) 06 Hydrometric Stations ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2. Capacity LLWDP/G/03 / Office Building, Institutional Single Stage - One IDA / 64030 Post Request for Bids Open - National 120,000.00 35,817.78 Signed 2020-01-14 2020-01-20 2020-01-19 2020-01-23 2020-03-01 2019-12-12 2020-03-31 2019-12-05 2020-05-05 2020-06-30 2020-11-01 supplies and furniture. Strengthening and Project Envelope Management Component 2. Capacity LLWDP/G/01 / Procurement Building, Institutional Request for Single Stage - One IDA / 64030 Post Open - National 100,000.00 -942,484.18 Signed 2020-01-19 2020-01-29 2020-03-15 2019-12-20 2020-09-11 of Project Vehicles Strengthening and Project Quotations Envelope Management Component 2. Capacity LLWDP/G/02 / Procurement Building, Institutional Single Stage - One IDA / 64030 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2020-01-14 2020-01-20 2020-01-19 2020-01-20 2020-03-01 2020-03-31 2020-05-05 2020-11-01 of ICT equipment, Strengthening and Project Envelope Management Page 1 Component 2. Capacity LLWDP/G/02 (A) / Building, Institutional Single Stage - One Procurement of ICT IDA / 64030 Post Request for Bids Open - National 150,000.00 134,966.28 Signed 2020-04-30 2020-06-17 2020-05-05 2020-06-24 2020-06-16 2020-07-31 2020-07-16 2020-08-28 2020-08-20 2020-11-18 2021-02-16 Strengthening and Project Envelope equipment for the Project Management LLWDP/G/04 / Procurement Component 2. Capacity of ICT equipment for the Building, Institutional Single Stage - One Office of Commissioner of IDA / 64030 Post Request for Bids Open - National 300,000.00 177,128.20 Signed 2021-04-08 2021-03-24 2021-04-13 2021-03-30 2021-05-25 2021-05-19 2021-06-24 2021-06-25 2021-07-29 2021-08-30 2022-01-25 Strengthening and Project Envelope water and the Ministry of Management Development Planning LLWDP/G/06 / Procurement of meters and valves Required Pending Component 1. Water Supply Single Stage - One for National Baseline IDA / 64020 Post Request for Bids Open - International 1,000,000.00 0.00 Implementati 2022-06-13 2022-06-18 2022-07-30 2022-08-29 2022-10-03 2023-04-01 Investments in Zones 2 and 3 Envelope Assessment and Study of Non- on Revenue Water LLWDP/G/05 / procurement Component 4. Contingent of Water Resources and Flood Single Stage - One IDA / 64020 Emergency Response Post Request for Bids Open - International 1,050,000.00 0.00 Canceled 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 Monitoring and Response Envelope Component Equipment LLWDP/G/07 / Procurement of valves to Leakage Control Pending Component 1. Water Supply Single Stage - One Zones and refurbishment to IDA / 64020 Prior Request for Bids Open - International 2,890,000.00 0.00 Implementati 2023-01-31 2023-02-05 2023-03-19 2023-04-18 2023-05-23 2023-11-19 Investments in Zones 2 and 3 Envelope existing mains in Maputsoe, on Hlotse and Tsikoane NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2. Capacity LLWDP/NC/01 / Procurement Building, Institutional Single Stage - One of Project management IDA / 64030 Post Request for Bids Open - International 150,000.00 0.00 Canceled 2020-01-09 2020-01-21 2020-01-14 2020-04-16 2020-02-25 2020-05-28 2020-03-26 2020-09-09 2020-04-30 2020-10-27 Strengthening and Project Envelope software Management LLWDP/NC/02 / Non- Consultancy services for the Component 2. Capacity Supply, Installation and Building, Institutional IDA / 64030 Post Direct Selection Direct 50,400.00 50,400.00 Signed 2020-04-30 2020-03-02 2020-05-05 2020-05-22 2020-06-09 2020-06-02 2020-12-06 Commissioning of Tomate Strengthening and Project Software for Support of Management Financial Management LLWDP/NC/04 / WASCO Computerized Maintenance Component 3. WASCO Single Stage - One IDA / 64030 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2021-05-13 2021-06-02 2021-05-18 2021-06-04 2021-06-29 2021-07-29 2021-09-02 2022-03-01 Management System Performance Improvements Envelope (Provision of a CMMS solution) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LLWDP/C/06 / Design and Construction Supervision of Component 1. Water Supply Quality And Cost- Leakage Control Zones and IDA / 64030 Post Open - National 300,000.00 0.00 Canceled 2021-03-11 2021-04-01 2021-05-15 2021-06-12 2021-07-12 2021-08-16 2021-09-20 2022-09-20 Investments in Zones 2 and 3 Based Selection Refurbishment in Maputsoe, Hlotse and Tsikoane Component 2. Capacity Consultant LLWDP/C/08 / Preparation of Building, Institutional IDA / 64020 Post Qualification Open - National 200,000.00 567,448.33 Signed 2019-12-12 2020-06-17 2020-01-02 2020-06-24 2020-02-15 2020-11-11 2020-03-16 2021-10-21 2020-04-20 2021-10-21 2020-10-17 asset valuation Strengthening and Project Selection Management Component 2. Capacity LLWDP/C/10 / Coaching of Consultant Building, Institutional the Board of Directors on IDA / 64020 Post Qualification Open - National 200,000.00 0.00 Canceled 2020-02-13 2020-06-08 2020-03-05 2020-06-18 2020-04-18 2020-05-18 2020-06-22 2020-12-19 Strengthening and Project Governance issues. Selection Management Component 2. Capacity LLWDP/C/12 / Financial Data Consultant Building, Institutional & Reporting – Develop plan IDA / 64030 Post Qualification Open - National 200,000.00 823,524.00 Signed 2020-02-13 2020-09-16 2020-03-05 2020-09-23 2020-04-18 2020-09-24 2020-05-18 2021-05-18 2020-06-22 2021-07-20 2020-12-19 Strengthening and Project and complete 4years Selection Management Component 2. Capacity LLWDP/C/14 / Service Consultant Building, Institutional Provider Maturity Assessment IDA / 64020 Post Qualification Open - National 150,000.00 0.00 Canceled 2020-02-13 2020-03-05 2020-04-18 2020-05-18 2020-06-22 2020-12-19 Strengthening and Project Prior to Mid-Tem Review Selection Management Component 2. Capacity LLWDP/C/16 / Establishment Consultant Building, Institutional of institutional framework for IDA / 64020 Post Qualification Open - National 150,000.00 213,256.00 Signed 2020-01-23 2021-02-03 2020-02-13 2021-02-10 2020-03-28 2021-03-23 2020-04-27 2021-04-21 2020-06-01 2021-06-07 2020-11-28 Strengthening and Project Bulk water operation (BWA). Selection Management LLWDP/C/17 / WASCO Turn Component 3. WASCO Quality And Cost- Around Support (Change IDA / 64020 Post Open - National 900,000.00 791,515.00 Signed 2020-02-06 2020-03-31 2020-02-27 2020-04-10 2020-04-11 2021-06-29 2020-05-09 2020-12-24 2020-06-08 2021-02-12 2020-07-13 2021-03-30 2020-08-17 2021-06-07 2021-08-17 Performance Improvements Based Selection Management) LLWDP/C/02 / Asset verification mapping and Consultant Component 1. Water Supply development of geo- IDA / 64030 Post Qualification Open - National 150,000.00 377,050.20 Signed 2020-01-30 2019-08-29 2020-02-20 2020-04-04 2020-03-19 2020-05-04 2020-10-12 2020-06-08 2020-10-27 2020-12-05 Investments in Zones 2 and 3 referenced asset register Selection within the LLWDP II. LLWDP/C/01 / Environmental Flow assessment (EFA) and Component 1. Water Supply Quality And Cost- IDA / 64030 Post Open - International 300,000.00 645,200.74 Signed 2020-01-16 2020-01-20 2020-02-06 2020-01-20 2020-03-21 2020-01-23 2020-04-18 2020-04-28 2020-05-18 2020-09-18 2020-06-22 2020-09-18 2020-07-27 2020-12-14 2021-07-27 water quality modeling within Investments in Zones 2 and 3 Based Selection the LLWDP II (Hlotse River) LLWDP/C/04 / Design Review Component 1. Water Supply Quality And Cost- and Construction Supervision IDA / 64030 Prior Open - International 4,500,000.00 0.00 Under Review 2020-03-09 2020-04-21 2020-03-30 2020-04-24 2020-05-13 2020-12-15 2020-06-10 2021-04-16 2020-07-10 2021-07-27 2020-08-14 2020-09-18 2021-09-18 Investments in Zones 2 and 3 Based Selection Consultant Page 2 LLWDP/C/03 / Heritage (Archeological and Consultant Component 1. Water Supply paleontology) impact IDA / 64030 Post Qualification Open - National 150,000.00 72,068.39 Signed 2020-04-20 2020-08-24 2020-05-11 2020-06-24 2020-03-19 2020-07-24 2020-09-16 2020-08-28 2020-09-21 2021-02-24 Investments in Zones 2 and 3 assessment (HIA) within the Selection LLWDP II. Component 2. Capacity LLWDP/C/13 / WASCo Building, Institutional Quality And Cost- IDA / 64030 Post Open - National 200,000.00 0.00 Canceled 2020-08-20 2020-09-16 2020-09-10 2020-10-24 2020-11-21 2020-12-21 2021-01-25 2021-03-01 2022-03-01 Customer Identification suvery Strengthening and Project Based Selection Management Component 2. Capacity LLWDP/C/07 / LEWA Building, Institutional Quality And Cost- Technical Support in Technical IDA / 64030 Post Open - International 245,000.00 139,000.00 Signed 2020-08-13 2020-08-24 2020-09-03 2020-08-27 2020-10-17 2020-11-16 2020-11-14 2021-01-21 2020-12-14 2021-02-19 2021-01-18 2021-03-15 2021-02-22 2021-06-26 2022-02-22 Strengthening and Project Based Selection Audit Management Component 2. Capacity LLWDP/C/11 / Monitoring of Building, Institutional Quality And Cost- Pending ESMP and RAP for zones two IDA / 64030 Post Open - International 700,000.00 0.00 2022-05-26 2022-06-16 2022-07-30 2022-08-27 2022-09-26 2022-10-31 2022-12-05 2023-12-05 Strengthening and Project Based Selection Implementation and three Management LLWDP/C/19 / Procurement Consultant of a consultant to assist Component 3. WASCO IDA / 64030 Post Qualification Open - International 240,000.00 0.00 Canceled 2021-01-28 2021-01-25 2021-02-18 2021-04-03 2021-05-03 2021-06-07 2021-12-04 WASCO in the Reduction of Performance Improvements Selection Non-Revenue Water LLWDP/C/05 / Design and specification for water Component 1. Water Supply Quality And Cost- Pending IDA / 64030 Prior Open - International 1,900,000.00 0.00 2022-08-25 2022-09-15 2022-10-29 2022-11-26 2022-12-26 2023-01-30 2023-03-06 2024-03-05 treatment works, pump Investments in Zones 2 and 3 Based Selection Implementation station and reservoirs LLWDP/C/09 / Preparation Component 2. Capacity of Operations and Consultant Building, Institutional Maintenance plan including IDA / 64020 Post Qualification Open - National 200,000.00 0.00 Canceled 2021-03-31 2021-04-21 2021-06-04 2021-07-04 2021-08-08 2022-02-04 Strengthening and Project possible operations and Selection Management maintenance contracts INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LLWDP/C/18(A) / Individual Engagement of panel of Component 3. WASCO IDA / 64020 Post Consultant Open 66,700.00 0.00 Canceled 2021-03-11 2021-01-21 2021-04-29 2021-05-20 2021-06-24 2021-12-21 experts for monitoring of Performance Improvements Selection Metolong Dam - Environment LLWDP/C/18(B) / Individual Engagement of panel of Component 3. WASCO IDA / 64020 Post Consultant Open 66,700.00 0.00 Canceled 2021-03-11 2021-01-21 2021-04-29 2021-05-20 2021-06-24 2021-12-21 experts for monitoring of Performance Improvements Selection Metolong Dam – Dam Safety LLWDP/C/18(C) / Individual Engagement of panel of Component 3. WASCO IDA / 64020 Post Consultant Open 66,700.00 0.00 Canceled 2021-03-11 2021-01-21 2021-04-29 2021-05-20 2021-06-24 2021-12-21 experts for monitoring of Performance Improvements Selection Metolong Dam - Hydrology Component 2. Capacity LLWDP /PIU/01 (F) / Individual Building, Institutional Procurement of Mechanical IDA / 64030 Prior Consultant Open 504,000.00 398,355.24 Signed 2020-03-12 2020-03-30 2020-04-30 2020-10-02 2020-05-21 2020-10-22 2020-06-25 2020-10-21 2020-12-22 Strengthening and Project Engineer for the Project Selection Management Component 2. Capacity LLWDP /PIU/01 (G) / Individual Building, Institutional Procurement of a Civil IDA / 64030 Prior Consultant Open 504,000.00 328,392.00 Signed 2020-03-12 2020-03-18 2020-04-30 2020-09-29 2020-05-21 2020-11-19 2020-06-25 2020-11-24 2020-12-22 Strengthening and Project Engineer for the Project Selection Management LLWDP /PIU/01 (A) / Component 2. Capacity Individual Procurement of Project Building, Institutional IDA / 64030 Post Consultant Open 268,800.00 248,428.82 Signed 2020-08-07 2018-11-09 2020-09-25 2020-02-23 2020-10-16 2019-02-24 2020-11-20 2019-03-15 2021-05-19 Manager for Lesotho Lowlands Strengthening and Project Selection Water Development II Management Component 2. Capacity LLWDP /PIU/01 (H) / Individual Building, Institutional Procurement of Social IDA / 64030 Post Consultant Open 80,800.00 74,676.52 Signed 2020-08-07 2019-07-11 2020-09-25 2020-10-16 2019-07-25 2020-11-20 2019-08-01 2021-05-19 Strengthening and Project safeguards Specialist Selection Management Component 2. Capacity LLWDP /PIU/01 (D) / Individual Building, Institutional Procurement of Monitoring IDA / 64030 Post Consultant Open 80,800.00 74,676.52 Signed 2020-08-07 2018-07-06 2020-09-25 2019-07-26 2020-10-16 2019-07-28 2020-11-20 2019-08-01 2021-05-19 Strengthening and Project and Evaluation Specialist Selection Management Component 2. Capacity LLWDP /PIU/01 (I) / Individual Building, Institutional Procurement of Environmental IDA / 64030 Post Consultant Open 80,800.00 78,060.76 Signed 2020-08-07 2019-10-11 2020-09-25 2019-10-11 2020-10-16 2019-10-25 2020-11-20 2019-11-01 2021-05-19 Strengthening and Project safeguard specialist Selection Management Component 2. Capacity Individual LLWDP /PIU/01 (E) / Building, Institutional IDA / 64030 Post Consultant Open 80,800.00 73,642.22 Signed 2020-08-07 2018-06-21 2020-09-25 2019-07-18 2020-10-16 2019-07-01 2020-11-20 2019-08-01 2021-05-19 Procurement of GIS Specialist Strengthening and Project Selection Management Component 2. Capacity LLWDP /PIU/01 (C) / Individual Building, Institutional Procurement of Financial IDA / 64030 Post Consultant Open 128,000.00 121,256.92 Signed 2020-08-07 2019-07-22 2020-09-25 2019-07-26 2020-10-16 2020-07-28 2020-11-20 2019-10-01 2021-05-19 Strengthening and Project Management Specialist Selection Management LLWDP /PIU/01 (B) / Component 2. Capacity Procurement of Procurement Individual Building, Institutional Specialist for Lesotho IDA / 64030 Post Consultant Open 136,000.00 125,191.78 Signed 2020-08-07 2018-04-24 2020-09-25 2019-06-27 2020-10-16 2019-07-01 2020-11-20 2019-08-01 2021-05-19 Strengthening and Project Lowlands Water Development Selection Management Project II LLWDP/C/19 (A) / Wasco Individual Technical Assistance for Component 3. WASCO Under IDA / 64030 Post Consultant Open 240,000.00 0.00 2021-02-22 2021-10-22 2021-04-12 2021-05-03 2021-06-07 2021-12-04 Reduction of Non-Revenue Performance Improvements Implementation Selection Water Page 3 Component 2. Capacity LLWDP/C/20 / Individual Individual Building, Institutional consultant to draft Sanitation IDA / 64030 Post Consultant Open 10,000.00 0.00 Canceled 2021-10-10 2021-10-07 2021-11-28 2021-12-19 2022-01-23 2022-07-22 Strengthening and Project Strategy Selection Management LLWDP/PIU/01/(M) / The Component 2. Capacity purpose is to procure the Individual Building, Institutional Pending services of a Procurement IDA / 64030 Post Consultant Open 87,000.00 0.00 2022-02-24 2022-04-14 2022-05-05 2022-06-09 2022-12-06 Strengthening and Project Implementation Officer to provide support to Selection Management the Procurement Specialist LLWDP/PIU/01(L) / Component 2. Capacity Individual Procurement of Deputy Project Building, Institutional Pending IDA / 64030 Post Consultant Direct 100,000.00 0.00 2022-02-21 2022-03-03 2022-03-24 2022-04-28 2022-10-25 Manager to support the Strengthening and Project Implementation Selection Project Implementation Unit Management Page 4