PROCUREMENT PLAN (Textual Part) Project information: Mali, Strengthening Climate Resilience in Mali, P161406 Project Implementation agency: Ministry of security and Civil Protection Date of the Procurement Plan: February 1st, 2020 Period covered by this Procurement Plan: January 1 to December 31, 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. - When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree N °2015-0604 / P- RM of September 25, 2015 relating to the Code of Public Procurement and Public Service Delegations and the decree N ° 2015-3731 / MEF- SG of October 22, 2015 setting the terms of application of the Decree N °2015-0604 / P-RM, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - When other national procurement arrangements other than national open competitive procurement arrangements are applied by the 1 Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. - To avoid any risk of non-compliance of national procedures with the principles and standards of the World Bank, when they are used in the context of procurement for this project, the standard World Bank procurement documents will be given priority used in the national circuit for the acquisition of goods, works and services. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as specified below :  Goods: not applicable for the contracts in the Procurement Plan;  Works: applicable for the contracts in the Procurement Plan. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. The project is in the start-up phase and benefits from the support of the Bank for certain consulting services activities directly implemented by the Bank in CREWS. (Paragraph 3.10-b of the Procurement Regulations). Other Relevant Procurement Information. This manual includes eligible activities, services and work approved by the World Bank. This is emergency support to save people and their property in the event of a natural disaster. The activities to be carried out on this component are endowed with financial resources drawn from the other components of the project on the basis of an official declaration of crisis by the Government. Contracts for these activities follow standard procurement principles and are carried out as an emergency project. Contingency Emergency Response Component (CERC) Operational Manuel has been established to guide the implementation of these activities. 2 PROCUREMENT Mali : Strengthening Climate Resilience in Mali Project PLAN General Information Country: Mali 2020-03-21 Bank’s Approval Date of the Original Procurement Plan: 2023-02-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161406 GPN Date: Project Name: Strengthening Climate Resilience in Mali Project Loan / Credit No: IDA / D4730 Strengthening Climate Resilience Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ML-HYDROMET-160015-CW- Improvement of Hydromet a Single Stage - One E En attente d 2021-07-0 RFB / Travaux de réhabilitati IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 314,135.00 0.00 2020-09-17 2020-09-22 2020-11-03 2020-12-03 2021-01-07 nvelope 'exécution 6 on du bâtiment de la DSGRE ure de l'Hydraulique ML-HYDROMET-160458-CW- Improvement of Hydromet a Single Stage - One E En attente d 2023-01-1 RFB / Travaux de modernisati IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 680,000.00 0.00 2020-09-30 2020-10-09 2020-11-20 2020-12-10 2021-01-14 nvelope 'exécution 4 on du Centre de Prévisions et ure de calcul ML-HYDROMET-160235-CW- Improvement of Hydromet a Single Stage - One E En attente d 2021-08-1 RFB / Travaux d'aménageme IDA / D4730 nd Early Warning Infrastruct A posteriori Demande de prix Open 127,500.00 0.00 2020-10-27 2020-12-22 nvelope 'exécution 9 nt de la salle des archives de ure la météo ML-HYDROMET-160196-CW- Improvement of Hydromet a RFB / Travaux de constructio Single Stage - One E En attente d 2022-06-1 IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 1,458,000.00 0.00 2020-08-27 2020-09-01 2020-10-13 2020-11-12 2020-12-17 n du bâtiment du Centre Nati nvelope 'exécution 0 ure onal des Opérations d'Urgenc es ML-HYDROMET-160474-CW- Improvement of Hydromet a RFB / Travaux d'électrificatio Single Stage - One E En attente d 2021-08-1 IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 255,000.00 0.00 2020-09-08 2020-09-15 2020-10-27 2020-11-16 2020-12-14 n du bâtiment de la météo p nvelope 'exécution 1 ure ar de l’énergie solaire ML-HYDROMET-160463-CW- Single Stage - One E En attente d 2021-04-1 RFQ / Travaux de réhabilitati IDA / D4730 Project Management A posteriori Demande de prix Limited 41,400.00 0.00 2020-08-25 2020-10-13 nvelope 'exécution 1 on des bureaux de l'UCP ML-HYDROMET-171247-CW- Enhancement of Service Deli Single Stage - One E 2021-01-1 IDA / D4730 A posteriori Demande de prix Limited 68,611.00 70,630.66 Signé 2020-05-20 2020-05-12 2020-07-15 2020-06-19 RFQ / Travaux de curage des very and Warnings to Comm nvelope 1 caniveaux unities ML-HYDROMET-189220-CW- Enhancement of Service Deli Passation de marc 2020-12-1 DIR / Travaux d'extension du IDA / D4730 very and Warnings to Comm A posteriori Direct 68,610.00 70,398.54 Signé 2020-08-20 2020-09-09 2020-08-25 2020-08-24 2020-09-11 2020-10-02 hé de gré à gré 0 curage des collecteurs à Bam unities ako ML-HYDROMET-189221-CW- Enhancement of Service Deli Passation de marc 2020-12-0 DIR / Travaux d'extension de IDA / D4730 very and Warnings to Comm A posteriori Direct 34,305.00 36,335.21 Signé 2020-08-20 2020-09-09 2020-08-25 2020-08-24 2020-09-02 2020-10-05 hé de gré à gré 1 curage des caniveaux à Bam unities ako ML-HYDROMET-171241-CW- Enhancement of Service Deli Single Stage - One E 2021-01-0 IDA / D4730 A posteriori Demande de prix Limited 34,305.00 35,871.98 Signé 2020-05-17 2020-05-12 2020-07-12 2020-06-19 RFQ / Travaux de curage des very and Warnings to Comm nvelope 8 collecteurs unities Demande d'offres ML-HYDROMET-287513-CW- Improvement of Hydromet a Single Stage - One E - DTPM Travaux - En attente d 2023-01-1 RFB / Travaux de constructio IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 1,003,430.00 0.00 2022-03-30 2022-04-04 2022-05-16 2022-06-15 2022-07-20 nvelope Droit civil français 'exécution 6 n du siège du SAP ure (français) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-HYDROMET-160028-GO- Improvement of Hydromet a Single Stage - One E En cours d'ex IDA / D4730 A posteriori Appel d'offres Open - National 475,000.00 0.00 2020-03-03 2021-06-11 2020-03-08 2021-10-19 2020-04-19 2020-05-19 2020-06-23 2020-08-22 RFB / Véhicules de secours s nd Early Warning Infrastruct nvelope écution pécialisés ure ML-HYDROMET-160467-GO- Improvement of Hydromet a Single Stage - One E En attente d' RFB / Installation de données IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 200,000.00 0.00 2020-09-09 2020-09-18 2020-10-30 2020-11-19 2020-12-17 2021-04-16 nvelope exécution de detétection de foudre ure ML-HYDROMET-160445-GO- Improvement of Hydromet a Single Stage - One E RFQ / Engin à deux roues pou IDA / D4730 nd Early Warning Infrastruct A posteriori Demande de prix Limited 29,800.00 29,754.13 Signé 2020-03-25 2020-05-26 2020-05-08 2020-07-02 2020-05-22 nvelope r la météo et l'UCP ure ML-HYDROMET-160426-GO- Improvement of Hydromet a RFB / Équipements en moyen Single Stage - One E IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 250,000.00 261,638.83 Signé 2020-03-03 2021-06-24 2020-03-08 2021-08-26 2020-04-19 2021-07-08 2020-05-19 2021-07-08 2020-06-10 2021-08-27 2020-09-08 s de transmissions pour véhi nvelope ure cules et postes fixes ML-HYDROMET-160476-GO- Improvement of Hydromet a Single Stage - One E RFQ / Equipements en mobili IDA / D4730 nd Early Warning Infrastruct A posteriori Demande de prix Limited 40,300.00 41,837.46 Signé 2020-04-06 2020-05-05 2020-05-15 2020-06-01 2020-06-14 nvelope ers pour la gestion de projet ure ML-HYDROMET-160223-GO- Improvement of Hydromet a Single Stage - One E En cours d'ex IDA / D4730 A posteriori Appel d'offres Open - National 950,000.00 0.00 2020-03-12 2021-11-02 2020-03-24 2020-05-05 2020-06-04 2020-07-09 2020-09-07 RFB / Equipements informati nd Early Warning Infrastruct nvelope écution ques - SAP ure ML-HYDROMET-160393-GO- Improvement of Hydromet a Single Stage - One E En attente d' RFB / Equipements divers po IDA / D4730 nd Early Warning Infrastruct A posteriori Demande de prix Limited 39,400.00 0.00 2020-04-28 2020-06-23 2020-12-20 nvelope exécution ur la gestion de projet. ure ML-HYDROMET-160421-GO- RFB / Installation des stations Capacity Building and Institu Single Stage - One E En cours d'ex automatiques synoptiques et IDA / D4730 A posteriori Appel d'offres Open - National 1,900,000.00 0.00 2020-07-08 2021-08-26 2020-07-16 2020-08-27 2020-09-26 2020-10-31 2021-02-28 tional Development nvelope écution agro-météorologiques et d’ali mentation solaire (2 lots) ML-HYDROMET-160185-GO- Improvement of Hydromet a Single Stage - One E RFB / Véhicules pour les servi IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 435,000.00 327,257.88 Signé 2020-02-21 2020-10-19 2020-03-02 2021-08-02 2020-04-01 2020-11-19 2020-05-01 2020-12-10 2020-06-05 2020-12-18 2020-12-02 nvelope ces techniques et l'UCP ure Page 1 ML-HYDROMET-160454-GO- Improvement of Hydromet a Single Stage - One E RFB / Matériels informatiques IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 72,550.00 62,630.64 Signé 2020-04-16 2020-05-27 2020-04-21 2020-06-18 2020-06-02 2020-06-30 2020-07-02 2020-07-08 2020-08-06 2020-08-12 2021-02-02 nvelope pour la gestion du projet ure ML-HYDROMET-171164-GO- Enhancement of Service Deli RFQ / Acquisition et installati Single Stage - One E En cours d'ex IDA / D4730 very and Warnings to Comm A priori Demande de prix Limited 38,593.00 0.00 2020-05-09 2020-07-04 2020-12-31 on de dispositifs de lavage d nvelope écution unities e fabrication locale ML-HYDROMET-171159-GO- Enhancement of Service Deli Single Stage - One E RFQ / Acquisition et distributi IDA / D4730 very and Warnings to Comm A posteriori Demande de prix Limited 85,763.00 90,788.05 Signé 2020-05-05 2020-04-29 2020-06-30 2020-05-08 2020-12-27 nvelope on gratuite de masques de c unities onfection locale ML-HYDROMET-261731-GO- Enhancement of Service Deli Single Stage - One E En attente d' DIR / Acquisition d'un véhicul IDA / D4730 very and Warnings to Comm A posteriori Demande de prix Limited 61,406.00 0.00 2022-04-01 2022-05-27 2022-06-30 nvelope exécution e pour le compte du projet unities ML-HYDROMET-287630-GO- Improvement of Hydromet a Single Stage - One E En attente d' RFB / Acquisition d'équipeme IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 401,373.00 0.00 2022-04-28 2022-05-03 2022-06-03 2022-07-03 2022-08-07 2022-12-02 nvelope exécution nts du laboratoire d'étalonna ure ge ML-HYDROMET-287638-GO- Improvement of Hydromet a RFB / Acquisition et installati Single Stage - One E En attente d' IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 351,200.00 0.00 2022-09-15 2022-09-20 2022-10-12 2022-11-11 2022-12-16 2023-03-16 on d’équipements météorolo nvelope exécution ure giques classiques et consom mables ML-HYDROMET-287641-GO- Improvement of Hydromet a Single Stage - One E En attente d' RFB / Acquisition et installati IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 301,030.00 0.00 2022-09-13 2022-09-19 2022-10-19 2022-11-04 2022-12-09 2023-03-09 nvelope exécution on de capteurs de mesure de ure la pollution ML-HYDROMET-287498-GO- RFQ / Acquisition de smart p Single Stage - One E En cours d'ex hone pour la collecte de don IDA / D4730 Project Management A posteriori Demande de prix Limited 36,364.00 0.00 2022-05-25 2022-04-12 2022-07-20 2023-01-16 nvelope écution nées au profit des structures communautaires d’alerte ML-HYDROMET-249677-GO- Enhancement of Service Deli Single Stage - One E En attente d' RFQ / Acquisition de drones d IDA / D4730 very and Warnings to Comm A priori Demande de prix Limited 30,017.00 0.00 2021-08-28 2021-10-23 2022-04-21 nvelope exécution e surveillance unities ML-HYDROMET-334026-GO- Improvement of Hydromet a RFQ / Equipements en matéri Single Stage - One E En attente d' IDA / D4730 nd Early Warning Infrastruct A posteriori Demande de prix Open - National 51,460.00 0.00 2023-01-27 2023-04-25 els informatiques et logiciels nvelope exécution ure pour la gestion de projet ML-HYDROMET-334051-GO- Improvement of Hydromet a Single Stage - One E En attente d' RFB / Equipements spécialisé IDA / D4730 nd Early Warning Infrastruct A posteriori Appel d'offres Open - National 340,165.00 0.00 2023-01-03 2023-01-09 2023-02-20 2023-03-22 2023-04-26 2023-10-23 nvelope exécution s pour la surveillance de la q ure ualité de l'eau. ML-HYDROMET-334287-GO- Improvement of Hydromet a Single Stage - One E En attente d' RFQ / Equipements (Kits d'an IDA / D4730 nd Early Warning Infrastruct A posteriori Demande de prix Limited 8,030.00 0.00 2023-01-07 2023-03-04 2023-08-31 nvelope exécution alyse) système d’observation ure pour les DRH ML-HYDROMET-334288-GO- Capacity Building and Institu Single Stage - One E En attente d' RFQ / Equipement en mobilie IDA / D4730 A posteriori Demande de prix Limited 42,865.00 0.00 2023-01-10 2023-03-07 2023-09-03 tional Development nvelope exécution r de bureau pour le siège de l 'UCP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-HYDROMET-160464-NC-R Improvement of Hydromet a FQ / Etablissement d'un contr Single Stage - One E En attente d' IDA / D4730 nd Early Warning Infrastruct A posteriori Demande de prix Limited 10,000.00 0.00 2020-04-09 2020-05-14 2021-05-09 at formel avec les fournisseu nvelope exécution ure rs d'images satellitaires ML-HYDROMET-160441-NC-R Enhancement of Service Deli FP / Développement d’inform Passation de marc En cours d'ex IDA / D4730 very and Warnings to Comm A priori Direct 95,000.00 0.00 2020-11-27 2020-12-02 2021-01-06 2021-06-05 ations agro-météorologiques hé de gré à gré écution unities (mise à jour de l'AGROMET T OOLBOX) ML-HYDROMET-160444-NC-R FQ / Installation d'un logiciel Single Stage - One E En attente d' IDA / D4730 Project Management A posteriori Demande de prix Limited 24,014.00 0.00 2020-07-20 2020-09-14 2021-03-13 de gestion informatique du s nvelope exécution ystème de Suivi-Evaluation ML-HYDROMET-160243-NC- Passation de marc En cours d'ex DIR / Installation de logiciels IDA / D4730 Project Management A priori Direct 41,165.00 0.00 2020-03-24 2021-04-20 2020-03-29 2020-04-15 2021-04-10 hé de gré à gré amen pour la gestion de projet ML-HYDROMET-160241-NC- Enhancement of Service Deli DIR / Développement d'appli Demande de prop Single Stage - Two E IDA / D4730 very and Warnings to Comm A posteriori Limited 355,000.00 359,669.31 Signé 2020-07-30 2020-05-10 2020-10-15 2020-07-29 2020-10-15 2020-07-29 2020-12-24 2020-08-30 2021-03-08 2020-11-26 2021-04-12 2020-11-19 2021-08-10 cation d'alerte et de collecte/ ositions nvelope unities partage d'informations ML-HYDROMET-160012-NC-R FQ / Mise en place d'un SIG e t d'une base de données par Enhancement of Service Deli Single Stage - One E En attente d' les stations de mesures. Aprè IDA / D4730 very and Warnings to Comm A posteriori Demande de prix Limited 50,000.00 0.00 2020-11-17 2021-01-12 2021-07-11 nvelope exécution s discussion avec le SGF, il es unities t indiqué de répartir le financ ement de ce marché sur IDA à 40% et sur GCF à 60%. ML-HYDROMET-169012-NC- DIR / Montage de sketchs de Single Stage - One E sensibilisation en langues loc IDA / D4730 Project Management A posteriori Demande de prix Limited 13,700.00 13,651.23 Signé 2020-05-02 2020-06-02 2020-06-01 2020-07-17 2020-07-15 nvelope ales des communautés sur le s risques, mécanismes et sys tèmes d'alerte précoce ML-HYDROMET-169002-NC- DIR / Montage de bandes des Single Stage - One E En attente d' sinées pour la sensibilisation IDA / D4730 Project Management A posteriori Demande de prix Limited 13,700.00 0.00 2020-05-05 2020-06-10 2020-07-31 nvelope exécution des enfants et des adultes s ur les systèmes d'alerte préc oce ML-HYDROMET-171250-NC-R Enhancement of Service Deli Single Stage - One E FQ / Service de diffusion de IDA / D4730 very and Warnings to Comm A posteriori Demande de prix Limited 30,875.00 32,028.35 Signé 2020-05-12 2020-04-29 2020-07-07 2020-06-09 2020-12-31 nvelope message sur radio, télé et au unities tres médias Page 2 ML-HYDROMET-160448-NC-R Improvement of Hydromet a Single Stage - One E FQ / Fournir la connexion int IDA / D4730 nd Early Warning Infrastruct A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2020-03-15 2020-04-22 2021-04-17 nvelope ernet à la DNH ure ML-HYDROMET-189222-NC-R Capacity Building and Institu Single Stage - One E En attente d' FQ / Développement d’un sit IDA / D4730 A posteriori Demande de prix Limited 24,500.00 0.00 2020-10-05 2020-11-30 2021-02-28 tional Development nvelope exécution e web pour le SAP ML-HYDROMET-189533-NC- Passation de marc En attente d' DIR / Acquisition de logiciel d IDA / D4730 Project Management A posteriori Direct 24,014.00 0.00 2020-08-31 2020-09-05 2020-10-10 2021-04-08 hé de gré à gré exécution e suivi-évaluation ML-HYDROMET-287062-NC-R Single Stage - One E En attente d' FQ / Production de supports a IDA / D4730 Project Management A posteriori Demande de prix Limited 25,385.00 0.00 2022-04-05 2022-05-31 2022-06-30 nvelope exécution udio visuel ML-HYDROMET-287063-NC-R Single Stage - One E En attente d' FQ / Service de diffusion / Co IDA / D4730 Project Management A posteriori Demande de prix Limited 17,670.00 0.00 2022-04-05 2022-05-31 2022-09-30 nvelope exécution mmunication sur les médias ML-HYDROMET-287579-NC-R FQ / Dynamisation du site W Capacity Building and Institu Single Stage - One E En attente d' IDA / D4730 A posteriori Demande de prix Limited 85,000.00 0.00 2022-05-03 2022-06-28 2022-09-28 EB de la DGPC et mise en lig tional Development nvelope exécution ne d'un système d'informatio n sur les risques ML-HYDROMET-287593-NC-R Capacity Building and Institu Single Stage - One E En attente d' FQ / Actualisation de la plate IDA / D4730 A posteriori Demande de prix Limited 20,070.00 0.00 2022-05-09 2022-07-04 2022-09-30 tional Development nvelope exécution forme informatique de la DN H ML-HYDROMET-291751-NC-R Single Stage - One E En attente d' FQ / Impression de supports IDA / D4730 Project Management A posteriori Demande de prix Limited 25,560.00 0.00 2022-05-25 2022-07-20 2022-09-02 nvelope exécution de communication ML-HYDROMET-287619-NC- DIR / Acquisition d'une soluti Capacity Building and Institu Passation de marc Direct - Internation En attente d' IDA / D4730 A posteriori 157,805.00 0.00 2022-12-26 2022-12-31 2023-02-04 2023-08-03 on opérationnelle pour la DG tional Development hé de gré à gré al exécution PC (Solution CRIMSON) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-HYDROMET-160630-CS-Q Enhancement of Service Deli Sélection fondée s CBS / Etude diagnostic de l’o En cours d'exécut IDA / D4730 very and Warnings to Comm A posteriori ur la qualité et le Open - National 80,000.00 0.00 2020-05-13 2020-05-30 2020-05-20 2020-08-16 2020-06-26 2020-07-24 2020-08-14 2020-09-11 2020-10-09 2020-10-21 util d’enquête de vulnérabilit ion unities coût é urbaine du SAP ML-HYDROMET-160652-CS-C Improvement of Hydromet a Sélection fondée s QS / Etude et suivi des trava En cours d'exame IDA / D4730 nd Early Warning Infrastruct A posteriori ur les qualification Limited 45,000.00 0.00 2020-06-30 2021-08-04 2020-07-14 2020-08-13 2020-09-17 2021-09-12 ux d'électrification du bâtime n ure s des consultants nt de la Météo en Energie sol aire ML-HYDROMET-160563-CS-Q Sélection fondée s CBS / Audit des comptes du P IDA / D4730 Project Management A posteriori ur la qualité et le Open - National 41,166.00 22,274.25 Signé 2020-11-19 2020-02-24 2020-12-03 2020-06-18 2021-01-07 2020-08-13 2021-02-04 2020-09-16 2021-03-05 2020-11-30 2021-04-01 2020-12-15 2021-04-29 2021-02-16 2022-04-29 rojet pour 2020 - 2022 coût ML-HYDROMET-160647-CS-Q Improvement of Hydromet a Sélection fondée s CBS / Etude technique et suiv En cours d'exécut IDA / D4730 nd Early Warning Infrastruct A posteriori ur la qualité et le Open - National 100,000.00 0.00 2020-04-30 2020-05-12 2020-05-07 2020-06-11 2020-07-10 2020-07-31 2020-09-04 2020-10-02 2021-10-02 i des travaux de construction ion ure coût du siège de SAP ML-HYDROMET-160566-CS-Q Improvement of Hydromet a Sélection fondée s En cours d'exécut CBS / Etude et suivi des trava IDA / D4730 nd Early Warning Infrastruct A posteriori ur la qualité et le Open - National 120,000.00 0.00 2020-07-23 2020-05-10 2020-08-13 2020-09-11 2020-10-12 2020-11-11 2020-12-09 2021-01-06 2021-03-07 ion ux du Centre de Previsions et ure coût de calcul ML-HYDROMET-160649-CS-Q Sélection fondée s CBS / Etude qualitative globa Capacity Building and Institu En cours d'exécut IDA / D4730 A posteriori ur la qualité et le Open - National 100,000.00 0.00 2020-12-26 2020-05-30 2021-01-16 2021-11-05 2021-02-12 2021-03-15 2021-04-14 2021-05-19 2021-06-16 2021-09-14 le pou un suivi potentiel de la tional Development ion coût qualité des cours d'eau (Nige r, Sénégal et Volta) ML-HYDROMET-160675-CS-Q Improvement of Hydromet a Sélection fondée s En cours d'exécut CBS / Etude architecturale et IDA / D4730 nd Early Warning Infrastruct A posteriori ur la qualité et le Open - National 162,000.00 0.00 2020-06-18 2020-06-01 2020-07-02 2020-08-07 2020-08-27 2020-09-26 2020-10-31 2020-11-27 2022-11-27 ion suivi des travaux du bâtimen ure coût t du CNOU ML-HYDROMET-189525-CS-C Sélection fondée s Capacity Building and Institu En attente d'exéc QS / Formation de 15 cadres IDA / D4730 A posteriori ur les qualification Limited 25,500.00 0.00 2020-09-09 2020-09-23 2020-10-23 2020-11-27 2021-05-26 tional Development ution du SAP en analyse de donné s des consultants es qualitatives ML-HYDROMET-160660-CS-Q CBS / Etude combinée des co urs d’eau pérenne et non pér Sélection fondée s enne et diagnostiques des st Capacity Building and Institu Open - Internationa En cours d'exécut IDA / D4730 A posteriori ur la qualité et le 950,000.00 0.00 2021-06-10 2021-05-27 2021-07-01 2022-12-19 2021-08-14 2022-10-06 2021-09-11 2022-12-15 2021-10-11 2022-12-15 2021-11-15 2021-12-20 2022-12-20 ations hydrologiques dans le tional Development l ion coût s bassins du fleuve Sénégal, du Niger supérieur et du Bani en vue du renforcement suivi hydrométrique ML-HYDROMET-160635-CS-Q Sélection fondée s CBS / Etude sur l'hydrologie Capacity Building and Institu IDA / D4730 A posteriori ur la qualité et le Open - National 150,000.00 0.00 Annulé 2020-12-16 2020-05-30 2020-12-31 2020-08-16 2021-02-05 2021-03-08 2021-03-31 2021-05-05 2021-06-03 2021-10-08 des petits cours d'eau et cou tional Development coût rs d'eau non pérennes sur 3 sites pilotes ML-HYDROMET-249661-CS-C Improvement of Hydromet a Sélection fondée s QS / Etude et suivi de la réha En attente d'exéc IDA / D4730 nd Early Warning Infrastruct A posteriori ur les qualification Limited 23,000.00 0.00 2021-08-22 2021-09-05 2021-10-05 2021-11-09 2022-05-08 bilitation du bâtiment de la D ution ure s des consultants SGRE de l’Hydraulique ML-HYDROMET-287537-CS-C Sélection fondée s En attente d'exéc QS / Etude d'impact environn IDA / D4730 Project Management A posteriori ur les qualification Limited 23,760.00 0.00 2022-03-31 2022-04-14 2022-05-13 2022-06-17 2022-08-15 ution emental et social du projet s des consultants ML-HYDROMET-287554-CS-C Sélection fondée s Capacity Building and Institu En attente d'exéc QS / Elaboration du Manuel d IDA / D4730 A posteriori ur les qualification Limited 24,014.00 0.00 2022-04-06 2022-04-20 2022-05-20 2022-06-24 2022-08-23 tional Development ution e gestion de la qualité pour l s des consultants a Météo ML-HYDROMET-333824-CS-Q Sélection fondée s En attente d'exéc CBS / Audit externe des com IDA / D4730 Project Management A posteriori ur la qualité et le Open - National 25,720.00 0.00 2022-12-27 2023-01-17 2023-03-02 2023-03-30 2023-04-29 2023-06-03 2023-07-08 2024-07-07 ution ptes 2023 et 2024 du projet coût Page 3 ML-HYDROMET-334289-CS-Q CBS / Etude de modernisatio Improvement of Hydromet a Sélection fondée s n du Centre de Prévisions et En attente d'exéc IDA / D4730 nd Early Warning Infrastruct A posteriori ur la qualité et le Open - National 154,375.00 0.00 2023-01-24 2023-02-14 2023-03-30 2023-04-27 2023-05-27 2023-07-01 2023-08-05 2024-08-04 de calcul, de la Salle des arc ution ure coût hives, du studio et de la Salle d'étalonnage du bâtiment de la Météo ML-HYDROMET-334290-CS-Q Enhancement of Service Deli Sélection fondée s CBS / Développement d'un s Open - Internationa En attente d'exéc IDA / D4730 very and Warnings to Comm A posteriori ur la qualité et le 451,545.00 0.00 2023-04-18 2023-05-09 2023-06-22 2023-07-20 2023-08-19 2023-09-23 2023-10-28 2024-10-27 ystème d'alerte météorologiq l ution unities coût ue et climatologique ML-HYDROMET-287602-CS-C Enhancement of Service Deli Sélection fondée s QS / Etude portant sur la per En attente d'exéc IDA / D4730 very and Warnings to Comm A posteriori ur les qualification Limited 150,515.00 0.00 2023-01-04 2023-01-18 2023-02-17 2023-03-24 2023-09-20 ception des communautés su ution unities s des consultants r les risques naturels et des s tratégies de réponses ML-HYDROMET-334291-CS-C QS / Etude d'impact environn Improvement of Hydromet a Sélection fondée s En attente d'exéc emental et social relative au IDA / D4730 nd Early Warning Infrastruct A posteriori ur les qualification Limited 44,597.00 0.00 2023-02-08 2023-02-22 2023-03-24 2023-04-28 2023-10-25 ution x travaux de réhabilitation de ure s des consultants la DSGRE, CNOU, SAP, METE O et UCP INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-HYDROMET-160688-CS-I Capacity Building and Institu En cours d'exame NDV / Elaboration du plan d'A IDA / D4730 A posteriori Individuel Limited 20,000.00 0.00 2020-05-21 2020-05-29 2020-05-28 2020-06-11 2020-07-02 2020-07-08 tional Development n ffaire pour Mali-Meteo ML-HYDROMET-160685-CS-I Improvement of Hydromet a NDV / Etudes et suivi des tra En attente d'exéc IDA / D4730 nd Early Warning Infrastruct A posteriori Individuel Limited 22,500.00 0.00 2020-08-25 2020-09-01 2020-09-22 2020-10-13 2021-10-08 vaux aménagement de la sall ution ure e des archives de la Météo ML-HYDROMET-160567-CS-I NDV / Élaboration du manuel En cours d'exame IDA / D4730 Project Management A posteriori Individuel Limited 42,880.00 0.00 2020-05-29 2022-03-04 2020-06-03 2020-06-24 2020-07-15 2020-09-14 de procédures suivi évaluatio n n et formation des acteurs ML-HYDROMET-160670-CS-I Enhancement of Service Deli En attente d'exéc NDV / Elaboration du mécani IDA / D4730 very and Warnings to Comm A posteriori Individuel Limited 10,300.00 0.00 2020-12-02 2020-12-09 2020-12-30 2021-01-20 2021-05-20 ution sme alerte spécifique à la pr unities otection civile ML-HYDROMET-158771-CS-I En attente d'exéc NDV / Un spécialiste Passatio IDA / D4730 Project Management A posteriori Individuel Open 33,242.00 0.00 2019-10-10 2019-12-06 2019-12-27 2020-01-06 2020-12-31 ution n des marchés ML-HYDROMET-160230-CS-I En cours d'exécut NDV / Un spécialiste en Sauv IDA / D4730 Project Management A posteriori Individuel Open 39,120.00 0.00 2019-11-14 2019-12-18 2020-03-27 2020-05-05 2020-05-22 2021-05-17 ion egarde Environnementale ML-HYDROMET-160203-CS-I En cours d'exécut NDV / Un spécialiste en Déve IDA / D4730 Project Management A posteriori Individuel Open 39,120.00 0.00 2019-11-14 2020-02-14 2020-03-13 2020-04-03 2020-04-21 2021-04-16 ion loppement/Sauvegarde socia le ML-HYDROMET-160189-CS-I En cours d'exécut IDA / D4730 Project Management A posteriori Individuel Open 28,820.00 0.00 2019-12-16 2020-12-16 2020-02-03 2020-02-13 2020-02-23 2021-02-17 NDV / Un spécialiste de Suivi ion Évaluation ML-HYDROMET-160234-CS-I En cours d'exécut IDA / D4730 Project Management A posteriori Individuel Open 28,820.00 0.00 2019-12-16 2020-12-14 2020-02-03 2020-02-18 2020-03-02 2021-02-25 NDV / Un auditeur Interne ion ML-HYDROMET-158769-CS-I En attente d'exéc IDA / D4730 Project Management A posteriori Individuel Open 33,242.00 0.00 2020-02-17 2020-02-17 2020-02-17 2020-02-17 2020-02-17 NDV / Specialiste en gestion f ution inanciere ML-HYDROMET-160568-CS-I NDV / Développement des S Capacity Building and Institu En cours d'exécut IDA / D4730 A posteriori Individuel Limited 50,000.00 0.00 2020-11-04 2020-05-20 2020-11-09 2022-05-03 2020-11-30 2020-12-15 2021-02-13 OP (Manuel des procédures a tional Development ion dministratives, financières et comptables) ML-HYDROMET-160693-CS-I En cours d'exécut NDV / Etudes et suivi des tra IDA / D4730 Project Management A posteriori Individuel Limited 7,720.00 0.00 2020-06-02 2021-11-05 2020-06-09 2020-06-30 2020-07-14 2021-07-14 ion vaux de réhabilitation des bu reaux UCP ML-HYDROMET-172810-CS-I Contingent Emergency Resp En cours d'exécut NDV / Recrutement d'un Com IDA / D4730 A posteriori Individuel Limited 17,150.00 0.00 2020-05-08 2020-04-24 2020-05-13 2020-05-27 2020-06-10 2021-02-05 onse Component ion municateur Traditionnel ML-HYDROMET-160031-CS-I Capacity Building and Institu NDV / Assistance à maîtrise d IDA / D4730 A priori Individuel Direct 115,270.00 0.00 Annulé 2020-04-01 2020-04-10 2020-04-20 2020-04-30 2020-10-27 tional Development 'ouvrage pour la l'hydrauliqu e ML-HYDROMET-160232-CS-I NDV / Un Chargé de commun IDA / D4730 Project Management A posteriori Individuel Open 39,120.00 2,317.73 Signé 2020-03-12 2021-08-14 2021-06-30 2021-04-09 2021-07-05 2021-06-23 2021-07-16 2021-06-23 2022-07-11 ication du Projet ML-HYDROMET-160640-CS-I NDV / Elaboration des manue En attente d'exéc IDA / D4730 Project Management A posteriori Individuel Limited 23,520.00 0.00 2020-11-30 2020-12-07 2020-12-28 2021-01-11 2021-03-12 ls de gestion Environnement ution ale et Sauvegarde sociale ML-HYDROMET-160690-CS-I Improvement of Hydromet a NDV / Etude et suivi de la réh IDA / D4730 nd Early Warning Infrastruct A posteriori Individuel Limited 23,000.00 0.00 Annulé 2020-07-30 2020-05-10 2020-08-06 2020-08-27 2020-09-10 2021-09-10 abilitation du bâtiment de la ure DSGRE de l'Hydraulique ML-HYDROMET-261598-CS-I NDV / Recrutement d'un cons En attente d'exéc IDA / D4730 Project Management A posteriori Individuel Open - National 76,843.00 0.00 2021-11-24 2022-01-01 2022-01-12 2022-02-07 2024-07-26 ultant individuel assistant en ution passation des marchés Page 4