Poverty Alleviation and Agriculture Development Demonstration in Poor Areas Project Guizhou Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: May 13, 2015: 1stRevision: May 11, 2018; 2nd Revision: December 28, 2020] 2. Date of General Procurement Notice: November 23, 2015 3. Period covered by this procurement plan: 2021 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 10million All 2. NCB (Goods) Above US$ 2million All 3. ICB (Works) Above US$ 40 million All 4. NCB (Works) Above US$ 10 million All 5. (Non-Consultant Services) Above US$ 2million All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Yes, in procurement manual] 4. Reference to (if any) Project Operational/Procurement Manual: Yes 5. Any Other Special Procurement Arrangements: no 6. Summary of the Procurement Packages planned: [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimated Packag Domesti Review Comments No. on Cost es c by Bank US$ Prefere (Prior / million nce Post) (yes/no) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary 1.73 7 No Post of the Shopping (Works) Summary 0.76 5 No Post of the Shopping (Goods) Summary of the ICB (Non- Consultant Services) Summary of the NCB (Non- Consultant Services) Summary of the Shopping (Non- Consultant Services) Summary of the Direct Contractin g (Works) Summary 0.036 2 No Post Agricultur of the al Direct Selection insuran (Non- ce for Consultant Xishui Services) County III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 1 million 2. Single Source (Firms) Above US$ 1 million 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: No 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimated Packages Review Comments of Assignment Cost by Bank US$ million (Prior / Post) Summary of number of contracts that will be let under QCBS Summary 0.38 6 Post of number of contracts that will be let under CQS Summary of number of contracts that will be let under IS Summary 0.16 2 Post of number of contracts that will be let under IC PROCUREMENT China : Poverty Alleviation and Agriculture-based Industry Pilot and Demonstration in Poor Areas Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2018-05-13 2022-04-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133326 GPN Date: Project Name: Poverty Alleviation and Agriculture-based Industry Pilot and Demonstration in Poor Areas Project Loan / Credit No: IBRD / 85090 Sichuan poverty Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SCZJGD07 / Zhaojue County Liuhe Township four kg five Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- villages and other potato IBRD / 85090 Post Limited 118,052.00 0.00 Implementa Services Quotations Envelope 02 26 26 projects rectification Village tion Road (hardening) 1.5 km SCZJGD08 / Zhaojue County Pending four Kam Township, Yi Li Mu Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 18,016.00 0.00 Implementa village potato production Services Quotations Envelope 02 26 26 tion road 2 kilometers SCZJGD14 / Zhaojue County, Liangshan County, the village Pending of slash fire village, a semi Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 39,344.00 0.00 Implementa fine wool sheep project, 1.2 Services Quotations Envelope 02 26 26 tion kilometers of new village road. SCZJGD12 / Zhaojue County four open Township good Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- Valley Village potato project IBRD / 85090 Post Limited 53,115.00 0.00 Implementa Services Quotations Envelope 02 26 26 rectification Village Road tion 1.08 kilometers SCJYG001 / Jinyang Yongsheng konjac farmers' Pending professional cooperatives Public Infrastructure and Single Stage - One 2018-05- 2018-05- 2018-06- 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Request for Bids Open - National 236,098.00 0.00 Implementa remediation village road Services Envelope 20 25 25 26 06 06 tion hardening 3 km project contract SCBTG01 / Construction of Integrated Value Chain Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-11- office building in Luocun co- IBRD / 85090 Post Limited 24,590.00 36,411.06 Completed Development Quotations Envelope 27 07 25 13 25 operatives in Bu Tuo County SCBTG10 / Building of co- operative room of co- Integrated Value Chain Request for Single Stage - One 2018-06- 2018-09- 2018-07- 2018-10- 2018-11- IBRD / 85090 Post Limited 24,590.00 30,637.54 Completed operatives in Japanese village Development Quotations Envelope 27 14 25 08 25 in Bu Tuo County SCXYG140 / Xuyong County regulation Village Road Public Infrastructure and Request for Single Stage - One 2018-05- 2018-12- 2018-06- 2019-01- 2018-08- IBRD / 85090 Post Limited 166,256.00 154,291.34 Completed (hardening) 2 km, New Services Quotations Envelope 26 21 20 16 20 Village Road 0.27 km SCXYG143 / Xuyong County Pending regulation Village Road Public Infrastructure and Request for Single Stage - One 2018-05- 2018-06- 2018-08- IBRD / 85090 Post Limited 81,387.00 0.00 Implementa (hardening) 0.73 km, New Services Quotations Envelope 26 20 20 tion Village Road 0.73 km SCXYG145 / A new 1000 mu sweet orange garden drip Public Infrastructure and Single Stage - One 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-08- 2018-10- 2018-08- 2018-11- 2018-12- IBRD / 85090 Post Request for Bids Open - National 242,689.00 223,045.58 Completed irrigation system in Xuyong Services Envelope 02 30 04 04 30 04 30 12 28 30 County SCXYG49 / Xuyong county has built 60 cubic meters of Pending water pool 3, 200 cubic Public Infrastructure and Request for Single Stage - One 2018-05- 2018-06- 2018-08- IBRD / 85090 Post Limited 80,817.00 0.00 Implementa meters of pool 2, PE 1.8 40 Services Quotations Envelope 27 20 20 tion km 1.8 km, PE 90 90 km 4.2 km SCZJGD09 / Zhaojue County four open Township good Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- Valley Village potato project IBRD / 85090 Post Limited 196,754.00 0.00 Implementa Services Quotations Envelope 02 26 26 rectification Village Road tion (hardening) 2.5 kilometers SCZJGD10 / haojue County Liuhe Township, the village Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- of potato in the village of Bo IBRD / 85090 Post Limited 39,351.00 0.00 Implementa Services Quotations Envelope 02 26 26 Luo regulation Village Road tion (hardening) 0.5 km SCZJGD11 / ZhaojueCounty, Pending Damo Township, Dagu Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 21,820.00 0.00 Implementa Village, Potato Project Services Quotations Envelope 02 26 26 tion Production Road, 2.42 km SCZJGD13 / Zhaojue County, Bowling Township, United Pending Township, Liangshan Semi- Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 78,702.00 0.00 Implementa finishing Sheep Project, Services Quotations Envelope 02 26 26 tion Renovation, Village Road (hardened), 1 km SCZJGD16 / Zhaojue County, Pending Bowling Township, United Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 36,064.00 0.00 Implementa Township, Liangshan Semi- Services Quotations Envelope 02 26 26 tion fine Sheep Project 4km SCZJGD17 / Zhaojue County Pending Shaolapo Township Bolige Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 27,049.00 0.00 Implementa Village Liangshan Semi-fine Services Quotations Envelope 02 26 26 tion Sheep Project 3km SCBTG02 / Butuo County Integrated Value Chain Request for Single Stage - One 2018-06- 2018-06- 2018-07- 2018-07- 2018-11- IBRD / 85090 Post Limited 24,590.00 27,710.20 Completed Villages Cooperatives Offices Development Quotations Envelope 27 22 25 16 25 SCZJGD039 / Zhaojue County Liberation Township Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- Liangshan Semi-finishing IBRD / 85090 Post Limited 78,702.00 0.00 Implementa Services Quotations Envelope 04 28 28 Sheep Project Renovation tion Village Road (hardened) 1km SCBTG05 / Butuo County Integrated Value Chain Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-11- IBRD / 85090 Post Limited 24,590.00 34,247.99 Completed Rijie Village Cooperative Development Quotations Envelope 27 07 25 03 25 Office SCBTG06 / Suzuo Village Integrated Value Chain Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-11- Cooperative Office House in IBRD / 85090 Post Limited 24,590.00 33,547.20 Signed Development Quotations Envelope 27 06 25 03 25 Butuo County SCZJGD040 / Zhaojue County Sangang Township Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- Liangshan semi-fine wool IBRD / 85090 Post Limited 39,344.00 0.00 Implementa Services Quotations Envelope 04 28 28 sheep rectification village tion inner road (hardened) 0.8 kilometers SCBTG11 / Yahe Village Integrated Value Chain Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-11- 2018-11- Cooperative Office in Butuo IBRD / 85090 Post Limited 24,590.00 33,923.44 Completed Development Quotations Envelope 27 06 25 16 25 County SCZJGD041 / Zhaojue County Shaolapo Township Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- Liangshan Semi-fine Haired IBRD / 85090 Post Limited 49,180.00 0.00 Implementa Services Quotations Envelope 04 28 28 Sheep Project Renovation tion Village Road Highway (hardened) 1km SCBTG14 / Buer Village Integrated Value Chain Request for Single Stage - One 2018-06- 2018-06- 2018-07- 2018-07- 2018-11- Cooperative Office in Butuo IBRD / 85090 Post Limited 24,590.00 166,501.32 Completed Development Quotations Envelope 27 24 25 19 25 County SCZJGD042 / Zhaojue Pending County Liuhe Township Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 49,180.00 0.00 Implementa potato project remedies Services Quotations Envelope 04 28 28 tion village road (hardened) 1km SCBTG17 / Zhuerku Village Integrated Value Chain Request for Single Stage - One 2018-06- 2019-11- 2018-07- 2018-12- 2018-11- Cooperative Office in Butuo IBRD / 85090 Post Limited 24,590.00 34,019.44 Completed Development Quotations Envelope 27 07 25 23 25 County SCZJGD043 / Zhaojue Pending County Sangang Town Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 39,344.00 0.00 Implementa Liangshan Semi-finishing Services Quotations Envelope 04 28 28 tion Sheep Project 1.2km of Newly Built Village Road SCBTG18 / Labozuo Village Integrated Value Chain Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-11- Cooperative Office in Buto IBRD / 85090 Post Limited 24,590.00 34,156.57 Completed Development Quotations Envelope 27 19 25 13 25 County SCZJGD044 / Zhaoju County Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- Dimo Potato Project Newly IBRD / 85090 Post Limited 32,787.00 0.00 Implementa Services Quotations Envelope 04 28 28 built village road 1km tion SCZJGD045 / Zhaojue Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- County Sangang Township IBRD / 85090 Post Limited 27,049.00 0.00 Implementa Services Quotations Envelope 04 28 28 Liangshan Semi-fine Sheep tion Project 3km SCZJGD046 / Zhaojue Pending County Bowling Township Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 18,033.00 0.00 Implementa Liangshan Semi-fine Sheep Services Quotations Envelope 04 28 28 tion Production Project 2 km SCZJGD047 / Zhaojue Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- County Sikai Town Potato IBRD / 85090 Post Limited 18,033.00 0.00 Implementa Services Quotations Envelope 04 28 28 Project Production Road 2 km tion SCBTG22 / Poli Village Integrated Value Chain Request for Single Stage - One 2018-06- 2019-09- 2018-07- 2019-10- 2018-11- Cooperative Office in Buto IBRD / 85090 Post Limited 24,590.00 40,818.51 Signed Development Quotations Envelope 27 30 25 25 25 County SCBTG23 / Moci Village Integrated Value Chain Request for Single Stage - One 2018-06- 2019-09- 2018-07- 2019-10- 2018-11- Cooperative Office in Butuo IBRD / 85090 Post Limited 24,590.00 34,889.37 Signed Development Quotations Envelope 27 30 25 25 25 County Page 1 SCBTG26 / Ashengrida Integrated Value Chain Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-11- Village Cooperative Office in IBRD / 85090 Post Limited 24,590.00 34,570.47 Signed Development Quotations Envelope 27 06 25 02 25 Butuo County SCBTG27 / Laojiugui Village Integrated Value Chain Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-11- Cooperative Office in Butuo IBRD / 85090 Post Limited 24,590.00 34,354.50 Completed Development Quotations Envelope 27 06 25 03 25 County SCZJGD048 / Zhaoju County Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- Dimo Potato Production IBRD / 85090 Post Limited 18,033.00 0.00 Implementa Services Quotations Envelope 04 28 28 Project 2 km tion SCZJGD049 / Zhaojue Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- County Sarawipo Township IBRD / 85090 Post Limited 9,016.00 0.00 Implementa Services Quotations Envelope 04 28 28 Liangshan Semi-fine Sheep tion Project 1km SCBTG28 / Shouzi Village Integrated Value Chain Request for Single Stage - One 2018-06- 2019-09- 2018-07- 2018-10- 2018-11- Cooperative Office in Butuo IBRD / 85090 Post Limited 24,590.00 33,505.98 Completed Development Quotations Envelope 27 15 25 10 25 County SCBTG29 / Dianzi Village Integrated Value Chain Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-11- Cooperative Office in Butuo IBRD / 85090 Post Limited 24,590.00 36,788.83 Signed Development Quotations Envelope 27 06 25 02 25 County SCBTG31 / The village of Butuo County rectifies the Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-07- 2018-07- 2018-10- IBRD / 85090 Post Limited 73,771.00 3,192.00 Completed village road (hardened) 1.5 Services Quotations Envelope 16 22 12 16 12 kilometers SCBTG34 / Zuluo Village, Butuo County, remedies the Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-10- IBRD / 85090 Post Limited 73,771.00 0.00 Canceled village road (hardened) 1.5 Services Quotations Envelope 16 12 12 kilometers SCBTG35 / Old Tuofeng Village, Butuo County, Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-10- IBRD / 85090 Post Limited 73,771.00 0.00 Canceled remedies village roads Services Quotations Envelope 16 12 12 (hardened) 1.5 kilometers SCBTG37 / Road Renovation Public Infrastructure and Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-10- (hardening) 1.5km in Niche IBRD / 85090 Post Limited 73,771.00 43,342.57 Signed Services Quotations Envelope 16 06 12 03 12 Village, Butuo County SCBTG38 / Road in the village of Rida Village, Abu Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-10- IBRD / 85090 Post Limited 7,377.00 0.00 Canceled Province, Butuo County Services Quotations Envelope 16 12 12 (hardening) 0.15 km SCBTG39 / Butuo County Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-10- Shou zi Village Reclamation IBRD / 85090 Post Limited 39,344.00 0.00 Canceled Services Quotations Envelope 16 12 12 (hardening) 0.8 km SCBTG40 / Zhuercun Village Public Infrastructure and Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-10- Road Regulation (hardening) IBRD / 85090 Post Limited 39,344.00 125,831.25 Completed Services Quotations Envelope 16 06 12 03 12 0.8 km in Butuo County SCBTG41 / Dianzi Village Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-10- Road Regulation (hardening) IBRD / 85090 Post Limited 39,344.00 0.00 Canceled Services Quotations Envelope 16 12 12 0.8 km in Butuo County SCBTG42 / Yahe Village Public Infrastructure and Request for Single Stage - One 2018-06- 2018-11- 2018-07- 2018-12- 2018-10- Road Regulation (hardening) IBRD / 85090 Post Limited 98,360.00 9,204.55 Signed Services Quotations Envelope 16 06 12 03 12 0.8 km in Butuo County SCJYG002 / Jinyang Yongsheng konjac farmers Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- cooperatives set up 60 cubic IBRD / 85090 Post Limited 20,262.00 0.00 Implementa Services Quotations Envelope 08 02 20 meters of irrigation tion reservoirs 5 contracts SCJYG003 / Jinyang County Shida village white konjac Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- Planting Farmers' IBRD / 85090 Post Limited 98,360.00 0.00 Implementa Services Quotations Envelope 10 04 23 professional cooperatives tion new village road 3 km project contract SCJYG004 / Jinyang County, Shida village, white konjac Planting Farmers' Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- professional cooperatives to IBRD / 85090 Post Limited 20,262.00 0.00 Implementa Services Quotations Envelope 08 02 20 build irrigation reservoirs 60 tion cubic meters and 5 engineering contracts SCJYG005 / Jinyang County, the village of jiguru white Pending konjac farmers cooperatives Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- IBRD / 85090 Post Limited 20,262.00 0.00 Implementa professional irrigation pool Services Quotations Envelope 08 02 20 tion 60 cubic meters 5 engineering contracts SCJYG006 / Jinyang County Desheng white konjac green Pending pepper pepper farmers' Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- IBRD / 85090 Post Limited 49,180.00 0.00 Implementa professional cooperative new Services Quotations Envelope 10 04 23 tion 1.5 km village road project contract SCJYG007 / Jinyang County Desheng white konjac green Pending pepper pepper farmers Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- IBRD / 85090 Post Limited 40,524.00 0.00 Implementa cooperatives irrigation pool Services Quotations Envelope 08 02 20 tion 60 cubic meters 10 engineering contracts SCJYG008 / Jinyang County Desheng white konjac green Pending pepper pepper farmers Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- IBRD / 85090 Post Limited 11,426.00 0.00 Implementa professional cooperatives Services Quotations Envelope 10 04 23 tion irrigation pipe irrigation 4 km project contract SCJYG009 / Jinyang County Hongli white konjac Planting Pending Farmers Cooperatives Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- IBRD / 85090 Post Limited 12,164.00 0.00 Implementa irrigation pool 60 cubic Services Quotations Envelope 08 02 20 tion meters 3 engineering contracts SCJYG010 / Jinyang County Hongli white konjac Planting Pending Farmers' professional Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- IBRD / 85090 Post Limited 93,803.00 0.00 Implementa cooperatives to install Services Quotations Envelope 10 04 23 tion irrigation pipe 16 km project contract SCJYG011 / 3 km project Public Infrastructure and Request for Single Stage - One 2018-06- 2019-01- 2018-06- 2019-02- 2018-09- contract of New Village Road IBRD / 85090 Post Limited 98,361.00 137,517.87 Completed Services Quotations Envelope 01 12 27 03 27 in Mu Ni Guer village, Jinyang SCJYG012 / Jinyang County Fu Tai semi wool sheep Public Infrastructure and Request for Single Stage - One 2018-06- 2019-04- 2018-06- 2019-05- 2018-09- IBRD / 85090 Post Limited 49,180.00 122,721.88 Completed professional cooperative new Services Quotations Envelope 01 24 27 04 27 village road 1.5 km project SCJYG013 / Jinyang County, Fujian Province, semi fine Pending wool sheep professional Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-09- IBRD / 85090 Post Limited 18,032.00 0.00 Implementa cooperative production of 2 Services Quotations Envelope 01 27 27 tion km bypass engineering contract SCJYG014 / Jinyang County, Fujian Province, semi fine Public Infrastructure and Request for Single Stage - One 2018-07- 2019-05- 2018-08- 2019-06- 2018-09- wool breeding professional IBRD / 85090 Post Limited 14,279.00 27,832.06 Completed Services Quotations Envelope 09 06 04 01 30 cooperatives irrigation pipe 5 KM project contract SCJYG017 / Jinyang County Pending Desheng white konjac, green Integrated Value Chain Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 24,590.00 0.00 Implementa pepper, farmers' professional Development Quotations Envelope 10 06 06 tion cooperative office space 100. SCJYG018 / Jinyang County Ben Kang konjac planting Integrated Value Chain Request for Single Stage - One 2018-06- 2019-07- 2018-07- 2019-07- 2018-09- professional cooperative IBRD / 85090 Post Limited 24,590.00 204,697.35 Completed Development Quotations Envelope 10 16 06 25 06 office space construction contract SCJYG019 / Construction Pending Integrated Value Chain Request for Single Stage - One 2018-06- 2018-07- 2018-09- contract for building office IBRD / 85090 Post Limited 24,590.00 0.00 Implementa Development Quotations Envelope 08 02 02 building of Jinyang County tion SCJYG020 / Jinyang County TengXiang white konjac Pending Integrated Value Chain Request for Single Stage - One 2018-06- 2018-07- 2018-09- Planting Farmers Professional IBRD / 85090 Post Limited 24,590.00 0.00 Implementa Development Quotations Envelope 08 02 02 Cooperatives office space tion 100 contract project SCJYG021 / Jinyang County Jia Fu white konjac Planting Pending Integrated Value Chain Request for Single Stage - One 2018-06- 2018-07- 2018-09- Farmers' professional IBRD / 85090 Post Limited 24,590.00 0.00 Implementa Development Quotations Envelope 08 02 02 cooperatives office space 100 tion contract project SCJYG022 / Jinyang County Lan Po semi fine wool sheep Integrated Value Chain Request for Single Stage - One 2018-06- 2019-07- 2018-07- 2019-08- 2018-09- breeding farmers IBRD / 85090 Post Limited 24,590.00 47,124.22 Completed Development Quotations Envelope 08 19 02 10 02 cooperatives professional office 100 square project contract SCJYG023 / Jinyang County NYDA IDA semi fine wool Integrated Value Chain Request for Single Stage - One 2018-06- 2019-09- 2018-07- 2019-10- 2018-09- sheep farmers professional IBRD / 85090 Post Limited 24,590.00 41,438.28 Completed Development Quotations Envelope 08 12 02 07 02 cooperative office space 100 contract project SCJYG024 / Jinyang County Jifu metropolitan semi fine Integrated Value Chain Request for Single Stage - One 2018-06- 2019-09- 2018-07- 2019-10- 2018-09- wool sheep farmers IBRD / 85090 Post Limited 24,590.00 42,840.79 Completed Development Quotations Envelope 08 12 02 08 02 professional cooperatives new office space project contract SCJYG025 / Jinyang County Joint farmers' professional Integrated Value Chain Request for Single Stage - One 2018-06- 2019-08- 2018-07- 2019-09- 2018-09- IBRD / 85090 Post Limited 24,590.00 30,790.66 Completed cooperatives union office 100 Development Quotations Envelope 08 13 02 30 02 square project contract Page 2 SCJYG034 / Jinyang County, Fujian Province, semi fine wool sheep farmers Pending Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-08- specialized cooperatives IBRD / 85090 Post Limited 20,262.00 0.00 Implementa Services Quotations Envelope 08 02 20 irrigation reservoir 60 cubic tion meters 5 engineering contracts SCJYG032 / Contract for construction of animal Public Infrastructure and Single Stage - One 2018-06- 2020-05- 2018-06- 2018-07- 2020-05- 2018-07- 2020-05- 2018-07- 2020-05- 2018-10- IBRD / 85090 Post Request for Bids Open - National 230,180.00 129,970.60 Signed husbandry trading market in Services Envelope 08 04 10 10 04 11 18 23 26 31 Jinyang County SCMGG05 / Jiwei village Pending professional cooperative Integrated Value Chain Request for Single Stage - One 2018-08- 2018-08- 2018-10- IBRD / 85090 Post Limited 24,590.00 0.00 Implementa building in Ba Pu town, Mei Development Quotations Envelope 01 25 25 tion Gu County SCMGG11 / Mei Gu County, Xixiang, La Luo village, the Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 18,032.00 0.00 Canceled construction of 2 kilometers Services Quotations Envelope 01 02 02 of convenient road SCMGG18 / Mei Gu County, nine villages in the village of Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 157,410.00 0.00 Canceled Wu village regulation Services Quotations Envelope 01 02 02 (hardening) 2 km SCMGG19 / Nine villages in Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- Mei Gu County, New Village IBRD / 85090 Post Limited 30,164.00 0.00 Canceled Services Quotations Envelope 01 02 02 Road 0.92 km SCMGG20 / 2 kilometers of Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- New Village Road in Longmen IBRD / 85090 Post Limited 65,574.00 0.00 Canceled Services Quotations Envelope 01 05 05 Township, Mei Gu County SCMGG21 / Mei Gu County, Rama Ai Village, new village Public Infrastructure and Request for Single Stage - One 2018-07- 2018-07- 2018-09- IBRD / 85090 Post Limited 73,771.00 0.00 Canceled regulation Village Road Services Quotations Envelope 01 25 25 (hardening) 1.5 km SCMGG22 / Mei Gu County, La Ma Jiao Township rad Public Infrastructure and Request for Single Stage - One 2018-07- 2018-07- 2018-09- IBRD / 85090 Post Limited 49,180.00 0.00 Canceled village regulation Village Services Quotations Envelope 01 25 25 Road (hardening) 1 km SCMGG23 / Mei Gu County, nine villages, nine villages, Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 22,541.00 0.00 Canceled new production of 2.5 Services Quotations Envelope 01 02 02 kilometers SCMGG24 / The new rural area of Luo Yi Yi village in Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 22,541.00 0.00 Canceled Mei Gu county has 2.5 Services Quotations Envelope 01 05 05 kilometers of new production. SCMGG25 / Mei Gu County, Luo Wo Yi village EBOHR Wo Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- Village 60 cubic meters of IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 05 02 new reservoir 1 Install PE 40 pipe 3 km SCMGG27 / Mei Gu County agricultural township Yi Cun Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- new 60 cubic meters IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 05 02 reservoir 1 Install PE 40 pipe 3 km SCMGG28 / Mei Gu County, farming village, WA Yi village, Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- a new 60 cubic meter IBRD / 85090 Post Limited 12,606.00 0.00 Canceled Services Quotations Envelope 01 05 02 reservoir 1. Install PE 40 pipe 3 km SCMGG29 / Mei Gu County rural farming village of new Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 12,607.00 0.00 Canceled 60 cubic meters reservoir 1 Services Quotations Envelope 01 05 02 Install PE 40 pipe 3 km SCMGG34 / A new 60 cubic meter reservoir in Longmen Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- village, Mei Gu County, has 1 IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 05 02 cubic meters installed PE 3 40 kilometers. SCMGG35 / Mei Gu County, Longmen Township, new Public Infrastructure and Request for Single Stage - One 2018-07- 2018-07- 2018-09- village 60 cubic meters of IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 28 20 cistern reservoir 1, install PE 3 40 km pipeline SCMGG36 / Mei Gu County, Longmen Township tree Buyi Public Infrastructure and Request for Single Stage - One 2018-07- 2018-07- 2018-09- Luo village, a new 60 cubic IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 28 20 meters reservoir 1, install PE 3 40 km pipeline SCMGG40 / Ha Gu village, Longmen Township, Mei Gu Public Infrastructure and Request for Single Stage - One 2018-07- 2018-07- 2018-09- IBRD / 85090 Post Limited 19,443.00 0.00 Canceled County, has built 200 cubic Services Quotations Envelope 01 28 20 meters of reservoir 1. SCMGG41 / 1.92 kilometers of New Village Road in Public Infrastructure and Request for Single Stage - One 2018-07- 2018-07- 2018-09- IBRD / 85090 Post Limited 62,951.00 0.00 Canceled Longmen village, Ma Ma Services Quotations Envelope 01 28 20 Village, Mei Gu County SCMGG42 / Mei Gu County, Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-08- Xixiang, 1 wells in the New IBRD / 85090 Post Limited 32,787.00 0.00 Canceled Services Quotations Envelope 02 30 30 Village Road SCMGG43 / Village Road in Public Infrastructure and Request for Single Stage - One 2018-07- 2018-07- 2018-09- Longmen village of Mei Gu IBRD / 85090 Post Limited 73,771.00 0.00 Canceled Services Quotations Envelope 01 28 20 County, 1.5 km SCMGG44 / Mei Gu County, Pending WA Xixiang, West Village Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 49,180.00 0.00 Implementa regulation Village Road Services Quotations Envelope 01 02 02 tion (hardening) 1 km SCMGG45 / A new production road 5 kilometers Public Infrastructure and Request for Single Stage - One 2018-08- 2018-08- 2018-11- in the village of Er Ma Village, IBRD / 85090 Post Limited 45,082.00 0.00 Canceled Services Quotations Envelope 01 29 15 Longmen Township, Mei Gu County SCMGG46 / Mei Gu County, farming village, new village Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 8,335.00 0.00 Canceled 60 cubic meters, 1 reservoirs Services Quotations Envelope 01 05 02 Install PE 40 pipe 1.5 km SCMGG47 / Mei Gu County agricultural township Yi Cun Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- new 60 cubic meters IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Services Quotations Envelope 01 05 02 reservoir 1 Install PE 40 pipe 1.5 km SCMGG49 / Mei Gu County, WA Xixiang, West Village Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- installed PE 40 1.5 km IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Services Quotations Envelope 01 02 02 pipeline, 60 cubic meters of new reservoir 1. SCMGG50 / Mei Gu County, Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- Xixiang, La Luo village, PE IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Services Quotations Envelope 01 02 02 1.5 40 km pipeline SCMGG51 / Mei Gu County, Xixiang, Dalla am village, PE Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- 40 1.5 km pipeline, 1 cubic IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Services Quotations Envelope 01 02 02 meters of new 60 cubic meters. SCMGG52 / Mei Gu County, Xixiang, Nei Mu village Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- installed PE 1.5 40 km IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Services Quotations Envelope 01 02 02 pipeline, 60 cubic meters of new reservoir 1. SCMGG54 / Mei Gu County, BAP town ridge village new Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 12,607.00 0.00 Canceled 60 cubic meters reservoir 1 Services Quotations Envelope 04 02 05 Install PE 40 pipe 3 km SCMGG55 / 60 new cubic meters of 1 new reservoirs in Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- Sanhe Village, BAP Town, Mei IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Services Quotations Envelope 04 02 05 Gu County Install PE 40 pipe 1.5 km SCMGG56 / Mei Gu County, Longmen village, new village Public Infrastructure and Request for Single Stage - One 2018-08- 2018-08- 2018-10- 60 cubic meters of water IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 29 15 storage tank 1, install PE 3 40 km pipeline SCMGG57 / Mei Gu County, Longmen Township, hung Bi Public Infrastructure and Request for Single Stage - One 2018-08- 2018-08- 2018-10- Village, a new 60 cubic meter IBRD / 85090 Post Limited 9,754.00 0.00 Canceled Services Quotations Envelope 01 29 15 reservoir 1, PE 2 40 km pipeline SCMGG58 / Mei Gu County, according to Guo Gu township, ancient village 60 cubic meters of new reservoir Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- IBRD / 85090 Post Limited 126,380.00 0.00 Canceled 1 Services Quotations Envelope 04 02 05 Installation of PE 1.5 40 km pipeline, regulation of Village Road (hardening) 1.5 km SCMGG60 / Mei Gu County, according to Guo Er Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-09- Township, Erma village, a IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Services Quotations Envelope 04 02 05 new 60 cubic meter reservoir 1. Install PE 40 pipe 1.5 km Page 3 SCMGG61 / Mei Gu County, Longmen Township, the Public Infrastructure and Request for Single Stage - One 2018-08- 2018-08- 2018-10- village has 200 cubic meters IBRD / 85090 Post Limited 57,016.00 0.00 Canceled Services Quotations Envelope 01 29 15 of new reservoir 1, PE 7 40, 7 kilometers, PE 3, 3 kilometers. SCMGG67 / Mei Gu County Jue Luo Russian village Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-08- IBRD / 85090 Post Limited 102,312.00 0.00 Canceled regulation Village Road Services Quotations Envelope 05 30 30 (hardening) 1.3 km SCMGG72 / Mei Gu County jilo Township jilo village new Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-08- IBRD / 85090 Post Limited 12,607.00 0.00 Canceled 60 cubic meters reservoir 1 Services Quotations Envelope 05 30 30 Install PE 40 pipe 3 km SCMGG73 / Mei Gu County, Jue Luo Township, Pago Public Infrastructure and Request for Single Stage - One 2018-07- 2018-07- 2018-09- village, a new 60 cubic meter IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 25 25 reservoir 1. Install PE 40 pipe 3 km SCMGG80 / Mei Gu County, Xixiang, west of the village of Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-08- PE PE 40 2 km / 60 cubic IBRD / 85090 Post Limited 50,148.00 0.00 Canceled Services Quotations Envelope 02 30 30 meters reservoir 1, 90 km 4 km SCMGG82 / Mei Gu County well ye te Xixiang thousand Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-08- village PE 40 2 km, 60 cubic IBRD / 85090 Post Limited 15,656.00 0.00 Canceled Services Quotations Envelope 02 30 30 meters, 1 reservoirs / PE 1 63 km 1 km SCMGG83 / Mei Gu County, Xixiang fine leaf bamboo Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-08- IBRD / 85090 Post Limited 8,335.00 0.00 Canceled picking village PE 40 1.5 km Services Quotations Envelope 02 30 30 / 60 cubic meters reservoir 1. SCMGG84 / Mei Gu County, Xixiang, Tate Ye Village, PE Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-08- village, installed with a IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Services Quotations Envelope 02 30 30 diameter of 40 km, 1.5 km / 60 cubic meters, 1 reservoirs. SCMGG85 / Mei Gu County well ye te Xixiang West Public Infrastructure and Request for Single Stage - One 2018-06- 2018-06- 2018-08- IBRD / 85090 Post Limited 8,335.00 0.00 Canceled Village installed PE, 40, 1.5 Services Quotations Envelope 02 30 30 km, 60 cubic meters, 1 reservoirs. SCMGG88 / Mei Gu County, Jilao Township, the village of Public Infrastructure and Request for Single Stage - One 2018-08- 2018-08- 2018-10- e 60 cubic meters of new IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 25 25 reservoir 1. Install PE 40 pipe 3 km SCMGG89 / Mei Gu County jilo Township Code Arni Public Infrastructure and Request for Single Stage - One 2018-08- 2018-08- 2018-10- village 60 cubic meters of IBRD / 85090 Post Limited 12,607.00 0.00 Canceled Services Quotations Envelope 01 25 25 new reservoir 1 Install PE 40 pipe 3 km SCGLG40 / Gullin county shi Under bao white horse village Public Infrastructure and Request for Single Stage - One 2019-01- 2018-12- 2019-01- 2019-08- IBRD / 85090 Post Limited 157,403.00 0.00 Implementa regulation village road Services Quotations Envelope 01 10 25 15 tion hardening 2 km SCGLG32 / There are 13 reservoirs of 60 cubic meters Under Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-02- 2019-08- in shibao baima village, IBRD / 85090 Post Limited 83,013.00 0.00 Implementa Services Quotations Envelope 26 10 02 15 gullin county, and 10.625 tion kilometers of PE40 irrigation pipes SCGLG63 / Gullin county Under shishibaokou village Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- IBRD / 85090 Post Limited 172,131.00 0.00 Implementa renovation village road Services Quotations Envelope 26 10 25 15 tion (hardening) 3 km SCGLG35 / There are 13 reservoirs of 60 cubic meters Under Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-02- 2019-08- and PE40 irrigation pipes of IBRD / 85090 Post Limited 74,448.00 0.00 Implementa Services Quotations Envelope 26 10 02 15 7.625 kilometers in tion shibaokou village, gullin county SCGLG37 / Gullin county Under stone gem mouth village Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- IBRD / 85090 Post Limited 157,403.00 0.00 Implementa regulation village road Services Quotations Envelope 26 10 25 15 tion hardening 2 km SCGLG66 / Gullin county Under maxi tongxin village 60 cubic Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-02- 2019-08- IBRD / 85090 Post Limited 49,087.00 0.00 Implementa meters reservoir 10, PE40 Services Quotations Envelope 26 10 02 15 tion irrigation pipe 3 km SCGLG64 / Gulin county Under Integrated Value Chain Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- maxi tongxin village office IBRD / 85090 Post Limited 37,361.00 0.00 Implementa Development Quotations Envelope 26 17 27 15 room 100 square meters tion SCGLG73 / Gulin county ma Under xinhe village 60 cubic meters Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-02- 2019-08- IBRD / 85090 Post Limited 89,608.00 0.00 Implementa reservoir 20, PE40 pipeline 3 Services Quotations Envelope 26 10 02 15 tion km SCGLG69 / Gullin county ma Under Integrated Value Chain Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- xinhe village office 100 IBRD / 85090 Post Limited 37,361.00 0.00 Implementa Development Quotations Envelope 26 17 27 15 square meters tion SCGLG45 / Gullin county Under jiaoyuan longfeng village Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- IBRD / 85090 Post Limited 157,403.00 0.00 Implementa regulation village road Services Quotations Envelope 26 10 25 15 tion hardening 2 km SCGLG107 / Gullin county Under jiaoyuan yulin village Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- IBRD / 85090 Post Limited 157,403.00 0.00 Implementa regulation village road Services Quotations Envelope 26 10 25 15 tion hardening 2 km SCGLG108 / Gullin county jiaoyuan yulin village Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-01- 2019-08- IBRD / 85090 Post Limited 172,131.00 164,571.52 Completed renovation of the village road Services Quotations Envelope 26 10 27 28 15 (hardening) 3 km SCGLG03 / Gullin county jiaoyuan yulin village 60 Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-02- 2019-01- 2019-08- IBRD / 85090 Post Limited 82,827.00 77,437.23 Completed cubic meters 20 reservoir, Services Quotations Envelope 26 10 02 28 15 PE40 pipe 0.63 km SCGLG94 / Gullin county Integrated Value Chain Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-01- 2019-08- maoxi qinglong village office IBRD / 85090 Post Limited 37,361.00 32,735.87 Completed Development Quotations Envelope 26 10 27 22 15 100 square meters SCGLG95 / Gullin county maoxi qinglong village Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-01- 2019-08- IBRD / 85090 Post Limited 114,754.00 106,105.06 Completed renovation village road Services Quotations Envelope 26 10 27 24 15 (hardening) 2 km SCGLG97 / Gullin county Under maoxi qinglong village 200 Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-02- 2019-08- IBRD / 85090 Post Limited 28,014.00 0.00 Implementa cubic meters reservoir 1, Services Quotations Envelope 26 10 02 15 tion PE40 pipeline 3 km SCGLG57 / Gullin county Under horse shoe town ring road Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- IBRD / 85090 Post Limited 157,403.00 0.00 Implementa village regulation village road Services Quotations Envelope 26 12 25 15 tion hardening 2 km SCGLG87 / Gulin county ma Under shoe town ring road village Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-02- 2019-08- IBRD / 85090 Post Limited 49,087.00 0.00 Implementa 60 cubic meters reservoir 10, Services Quotations Envelope 26 12 02 15 tion PE40 pipeline 3 km SCGLG56 / Gullin county Under horseshoe town orchid Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- IBRD / 85090 Post Limited 57,377.00 0.00 Implementa village renovation village Services Quotations Envelope 26 12 27 15 tion road (hardening) 1 km SCGLG84 / Gullin county Under mahoozhen lanhua village 60 Public Infrastructure and Request for Single Stage - One 2018-12- 2018-12- 2019-02- 2019-08- IBRD / 85090 Post Limited 54,797.00 0.00 Implementa cubic meters reservoir 10, Services Quotations Envelope 26 12 02 15 tion PE40 pipeline 5 km SCGLG16 / The office Under building of shunhe village, Integrated Value Chain Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2019-08- IBRD / 85090 Post Limited 37,361.00 0.00 Implementa baini township, gullin county Development Quotations Envelope 26 10 27 15 tion is 100 square meters SCBTG09 / Butuo county Integrated Value Chain Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2018-12- 2019-02- rijiu village cooperative office IBRD / 85090 Post Limited 37,361.00 37,113.93 Completed Development Quotations Envelope 08 03 03 26 03 building construction SCBTG43 / butuo countyLaobo village road Public Infrastructure and Request for Single Stage - One 2018-12- 2018-11- 2019-01- 2018-12- 2019-04- IBRD / 85090 Post Limited 198,866.00 183,805.72 Completed renovation (hardening) 1.913 Services Quotations Envelope 08 06 03 26 03 km SCBTG36 / Moci Village Public Infrastructure and Request for Single Stage - One 2019-03- 2019-09- 2019-04- 2019-10- 2019-07- Road Regulation (hardening) IBRD / 85090 Post Limited 129,237.00 34,889.37 Signed Services Quotations Envelope 21 30 16 23 17 1.393km in Butuo County SCMGG26 / There are 6 newly built 60 cubic meters reservoir and 50 kilometers Public Infrastructure and Request for Single Stage - One 2019-04- 2019-11- 2019-05- 2019-12- 2019-07- IBRD / 85090 Post Limited 155,472.00 91,499.74 Completed of PE40 pipeline in azuowawu Services Quotations Envelope 02 17 26 19 21 village, luoyigan township, meigu county. SCMGG30 / Wawu village, jiukou township, meigu Under Public Infrastructure and Request for Single Stage - One 2019-04- 2019-11- 2019-05- 2019-07- county, is 30km away from IBRD / 85090 Post Limited 76,442.00 0.00 Implementa Services Quotations Envelope 02 17 26 21 the installation of PE40 tion pipeline. Page 4 SCMGG31 / Three new reservoirs of 60 cubic meters Pending were built in waluo village, Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-07- IBRD / 85090 Post Limited 64,995.00 0.00 Implementa jiukou township, meigu Services Quotations Envelope 02 26 21 tion county. Install PE40 pipe for 20km. SCMGG32 / Mei Gu County, nine villages, Bo Wo bitter Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-07- New 60 cubic meters IBRD / 85090 Post Limited 60,317.00 0.00 Implementa Services Quotations Envelope 02 26 21 reservoir 2 tion Install PE 40 pipe 20 km SCMGG33 / Meigu longmen township WaGu village 60 Public Infrastructure and Request for Single Stage - One 2019-04- 2019-11- 2019-05- 2019-12- 2019-07- cubic meters of new reservoir IBRD / 85090 Post Limited 90,476.00 46,052.12 Signed Services Quotations Envelope 02 17 26 19 21 3 mouth, PE Φ 40 pipe installation, 30 km SCMGG37 / In jiwei village, bapu town, meigu county, 6 new reservoirs of 60 cubic Public Infrastructure and Request for Single Stage - One 2019-04- 2019-11- 2019-05- 2019-12- 2019-07- IBRD / 85090 Post Limited 66,290.00 146,446.68 Signed meters were built, and 15 Services Quotations Envelope 02 07 26 19 21 kilometers of PE40 pipeline was installed. SCMGG38 / In dagge village, bapu town, meigu county, 5 Pending new reservoirs of 60 cubic Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-07- IBRD / 85090 Post Limited 87,093.00 0.00 Implementa meters were built, and 25 Services Quotations Envelope 02 26 21 tion kilometers of PE40 pipeline was installed. SCMGG39 / There are 4 newly built 60 cubic meters Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-07- reservoir and 20 kilometers IBRD / 85090 Post Limited 69,674.00 0.00 Implementa Services Quotations Envelope 02 26 21 of PE40 pipeline in sahler tion village, bapu town, migu county. SCMGG48 / Nongzuo village, nongzuo township, meigu Pending county, built 4 reservoirs of Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-07- IBRD / 85090 Post Limited 82,415.00 0.00 Implementa 60 cubic meters, and Services Quotations Envelope 02 26 21 tion installed 25 kilometers of PE40 pipeline. SCMGG59 / According to the fruit sleep township in accordance with the DE amor Public Infrastructure and Request for Single Stage - One 2019-04- 2019-11- 2019-05- 2019-12- 2019-07- IBRD / 85090 Post Limited 141,437.00 74,113.48 Signed village 60 cubic meters of Services Quotations Envelope 02 07 26 19 21 new reservoir 3 mouth, install PE Φ 40, 50 km pipeline SCMGG81 / Guokhe village, jingyate west township, meigu county, built 6 new Public Infrastructure and Request for Single Stage - One 2019-04- 2019-11- 2019-05- 2019-12- 2019-07- IBRD / 85090 Post Limited 91,769.00 51,151.38 Signed reservoirs of 60 cubic Services Quotations Envelope 02 18 26 15 21 meters, and installed 25 kilometers of PE40 pipeline. SCBTG19 / Butuo county hey Integrated Value Chain Request for Single Stage - One 2019-04- 2019-06- 2019-04- 2019-07- 2019-06- door village cooperative IBRD / 85090 Post Limited 33,343.09 34,020.10 Completed Development Quotations Envelope 06 19 30 19 30 office building 100 square meters SCBTG08 / Butuo county, gaguang village cooperative Integrated Value Chain Request for Single Stage - One 2019-04- 2019-09- 2019-04- 2019-11- 2019-06- IBRD / 85090 Post Limited 33,343.09 38,100.96 Signed office building of 100 square Development Quotations Envelope 06 25 30 20 30 meters SCBTG20 / Butuo county ah Integrated Value Chain Request for Single Stage - One 2019-04- 2019-09- 2019-04- 2019-10- 2019-06- bao village cooperative office IBRD / 85090 Post Limited 33,343.09 39,106.52 Signed Development Quotations Envelope 06 19 30 25 30 building of 100 square meters SCBTG24 / Butuo county Integrated Value Chain Request for Single Stage - One 2019-04- 2019-10- 2019-05- 2019-11- 2019-07- feige village cooperative IBRD / 85090 Post Limited 33,343.09 38,202.95 Signed Development Quotations Envelope 08 28 03 23 03 office building 100 square meters SCBTG12 / Butuo county shizui village cooperative Integrated Value Chain Request for Single Stage - One 2019-04- 2019-09- 2019-05- 2019-10- 2019-07- IBRD / 85090 Post Limited 33,343.09 33,978.78 Completed office building of 100 square Development Quotations Envelope 08 11 03 25 03 meters SCBTG15 / Butuo county mo cooperative village Integrated Value Chain Request for Single Stage - One 2019-04- 2019-09- 2019-05- 2019-10- 2019-07- IBRD / 85090 Post Limited 33,343.09 34,125.61 Signed cooperative office building Development Quotations Envelope 11 16 05 25 05 100 square meters SCBTG16 / Butuo county weizipo village cooperative Integrated Value Chain Request for Single Stage - One 2019-04- 2019-10- 2019-05- 2019-11- 2019-07- IBRD / 85090 Post Limited 33,343.09 38,202.95 Signed office building of 100 square Development Quotations Envelope 11 28 05 23 05 meters SCBTG13 / Butuo county filian wu village cooperative Integrated Value Chain Request for Single Stage - One 2019-04- 2019-10- 2019-05- 2019-10- 2019-07- IBRD / 85090 Post Limited 33,343.09 34,048.70 Signed office building of 100 square Development Quotations Envelope 11 15 05 15 05 meters SCBTG32 / Road Public Infrastructure and Request for Single Stage - One 2019-04- 2019-09- 2019-05- 2019-10- 2019-09- improvement (hardening) IBRD / 85090 Post Limited 193,531.05 206,450.83 Signed Services Quotations Envelope 11 09 05 25 05 2.086 km in filian wucun village, butuo county SCBTG44 / Road remediation Under (hardening) in mohezuo Public Infrastructure and Request for Single Stage - One 2019-04- 2019-09- 2019-04- 2019-08- IBRD / 85090 Post Limited 138,422.02 0.00 Implementa village, butuo county, 1.492 Services Quotations Envelope 06 16 30 30 tion km SCBTG45 / Road Public Infrastructure and Request for Single Stage - One 2019-04- 2019-09- 2019-05- 2019-10- 2019-09- improvement (hardening) IBRD / 85090 Post Limited 36,275.48 38,406.12 Signed Services Quotations Envelope 08 11 03 25 03 0.391 km in shizui village, butuo county SCBTG46 / Road Pending improvement (hardening) Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-08- IBRD / 85090 Post Limited 11,040.36 0.00 Implementa 0.119 km in yakaocun Services Quotations Envelope 06 30 30 tion village, butuo county SCMGG10 / Construction of Integrated Value Chain Request for Single Stage - One 2019-04- 2019-08- 2019-04- 2019-09- 2019-07- office buildings for yijiayuan IBRD / 85090 Post Limited 33,343.00 34,531.29 Completed Development Quotations Envelope 05 07 29 03 21 cooperative in meigu county SCMGG106 / Meigu Pending thousand ha village four 60 Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-07- IBRD / 85090 Post Limited 69,674.00 0.00 Implementa cubic meters of the Services Quotations Envelope 08 04 27 tion construction of reservoir, PE Φ 40 pipe 20 km SCMGG64 / Two reservoirs o Pending f 60 cubic meters will be built Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-07- IBRD / 85090 Post Limited 22,096.00 0.00 Implementa in guohe village of meigu cou Services Quotations Envelope 08 04 27 tion nty PE40 pipeline 5 km SCMGG103 / Jiwei village, Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-05- 2019-07- meigu county, construction IBRD / 85090 Post Limited 109,290.00 0.00 Implementa Services Quotations Envelope 02 26 20 of a drip irrigation project tion SCMGG105 / Meigu county ji Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-05- 2019-10- wei village slope ladder IBRD / 85090 Post Limited 52,670.08 0.00 Implementa Services Quotations Envelope 02 26 15 construction 80 mu tion SCXYG1901 / Water conservancy facilities project in haiya village, xuyong Public Infrastructure and Request for Single Stage - One 2019-04- 2019-10- 2019-05- 2019-12- 2019-08- IBRD / 85090 Post Limited 24,727.41 29,536.64 Completed county (200m 1 reservoir, Services Quotations Envelope 11 29 15 21 15 PE40 water pipe, 1.2km, PE63 water pipe, 0.8km) SCXYG1902 / Water Pending conservancy facilities project Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 21,037.64 0.00 Implementa of shuiliao village, xuyong Services Quotations Envelope 11 15 15 tion county (PE63 water pipe, 4km) SCXYG1903 / Tianba village water conservancy facilities project in xuyong county Public Infrastructure and Request for Single Stage - One 2019-04- 2019-10- 2019-05- 2019-11- 2019-08- IBRD / 85090 Post Limited 26,547.64 27,594.31 Completed (200m 1 reservoir, 1.5km Services Quotations Envelope 11 29 15 21 15 PE40 water pipe, 1km PE63 water pipe) SCXYG1904 / Water conservancy facilities project in shuilaopu village, xuyong Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-04- 2019-08- IBRD / 85090 Post Limited 32,193.23 33,511.08 Completed county (200m 1 reservoir, Services Quotations Envelope 11 01 15 22 15 60m 3 reservoir, PE40 water pipe 1.5km) SCXYG1905 / Water conservancy facilities project Pending of yantang village, xuyong Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 13,466.17 0.00 Implementa county (3 outlets of 60m Services Quotations Envelope 11 15 15 tion reservoir, 1km of PE40 water pipe) SCXYG1906 / Water conservancy facilities project Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-05- 2019-06- 2019-08- of xiekou village, xuyong IBRD / 85090 Post Limited 14,746.76 15,339.71 Completed Services Quotations Envelope 11 31 15 26 15 county (3 60m reservoirs, PE40 water pipes, 1.5km) SCXYG1907 / Water conservancy facilities project of sunjia village, xuyong Public Infrastructure and Request for Single Stage - One 2019-04- 2019-08- 2019-05- 2019-09- 2019-08- IBRD / 85090 Post Limited 50,920.29 53,036.38 Completed county (200m 2 reservoir, Services Quotations Envelope 11 23 15 21 15 60m 3 reservoir, PE40 water pipe 2km) SCXYG1908 / Shuangshan village water conservancy facilities project in xuyong Public Infrastructure and Request for Single Stage - One 2019-04- 2019-08- 2019-05- 2019-09- 2019-08- IBRD / 85090 Post Limited 25,267.05 30,004.29 Completed county (200m 1 reservoir, Services Quotations Envelope 11 23 15 30 15 1km PE40 water pipe, 1km PE63 water pipe) SCXYG1909 / Water conservancy facilities project of dawen village, xuyong Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 78,543.24 45,455.24 Completed county (4 200m reservoir, 1 Services Quotations Envelope 11 24 15 18 15 60m reservoir, 2km PE40 water pipe) Page 5 SCXYG1910 / Water conservancy facilities project Public Infrastructure and Request for Single Stage - One 2019-04- 2019-08- 2019-05- 2019-09- 2019-08- in nanshan village, xuyong IBRD / 85090 Post Limited 21,288.23 25,742.39 Completed Services Quotations Envelope 11 23 15 20 15 county (200m 1 reservoir, PE40 water pipe, 1.5km) SCXYG1912 / In chahe Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- village of xuyong county, the IBRD / 85090 Post Limited 2,793.29 0.00 Implementa Services Quotations Envelope 11 15 15 low-voltage line is 0.4km tion SCXYG1913 / Xiongguang Pending village, xuyong county, Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 1,396.64 0.00 Implementa implemented a low-voltage Services Quotations Envelope 11 15 15 tion line of 0.2km SCXYG1915 / The Pending implementation of the low Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 2,793.29 0.00 Implementa voltage line in dama village Services Quotations Envelope 11 15 15 tion of xuyong county is 0.4km SCXYG1916 / The Pending implementation of the low- Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 2,094.97 0.00 Implementa voltage line in tianba village Services Quotations Envelope 11 15 15 tion of xuyong county is 0.3km SCXYG1917 / The low- Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- voltage line in anle village of IBRD / 85090 Post Limited 3,491.61 0.00 Implementa Services Quotations Envelope 11 15 15 xuyong county is 0.5km tion SCXYG1918 / The implementation of the low- Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- voltage line in shuilaopu IBRD / 85090 Post Limited 22,683.20 0.00 Implementa Services Quotations Envelope 11 15 15 village of xuyong county is tion 0.3km SCXYG1921 / The Pending implementation of the low- Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 2,094.97 0.00 Implementa voltage line in sunjia village Services Quotations Envelope 11 15 15 tion of xuyong county is 0.3km SCXYG1928 / The Pending implementation of the low- Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 1,396.64 0.00 Implementa voltage line in daben village Services Quotations Envelope 11 15 15 tion of xuyong county is 0.2km SCXYG1930 / Xuyong county chahe village regulation Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 128,676.47 138,289.49 Completed village road (hardening) 2.5 Services Quotations Envelope 11 29 15 30 15 km SCXYG1931 / Baila village, Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-06- 2019-08- xuyong county, built 1.92 km IBRD / 85090 Post Limited 56,470.58 65,215.65 Completed Services Quotations Envelope 11 29 15 03 15 of road within the village SCXYG1933 / Shuiliao village, xuyong county, Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- improved village road IBRD / 85090 Post Limited 20,002.35 0.00 Implementa Services Quotations Envelope 11 15 15 (hardening) 0.2km, new tion village road 0.2km SCXYG1935 / Yan tang village yan yong county Public Infrastructure and Request for Single Stage - One 2019-04- 2019-03- 2019-05- 2019-04- 2019-08- IBRD / 85090 Post Limited 154,411.76 160,854.65 Completed consolidation (hardening) Services Quotations Envelope 11 29 15 20 15 village road 3 km SCXYG1937 / Sunjia village, xuyong county, remediation Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 154,411.76 160,790.28 Completed of the village road Services Quotations Envelope 11 12 15 14 15 (hardening) 3 km SCXYG1938 / Dawen Village, Xuyong County, renovates 3 Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 154,411.76 160,859.09 Completed kilometers of roads in the Services Quotations Envelope 11 26 15 23 15 village SCGLG109 / Water conservancy facilities project of shaba village, baini Pending township, gullin county (3 Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 56,234.97 0.00 Implementa reservoirs of 60 cubic Services Quotations Envelope 11 15 15 tion meters, 11 kilometers of PE40 pipeline, 1 reservoir of 200 cubic meters) SCGLG110 / Improvement of Pending road (hardening) 3 km in Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 153,621.07 0.00 Implementa shaba village, bainai Services Quotations Envelope 11 15 15 tion township, gullin county SCGLG111 / Gullin county Pending white mud township sand Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 140,476.95 0.00 Implementa dam village regulation village Services Quotations Envelope 11 15 15 tion road road (hardening) 2 km SCGLG113 / Low voltage line project of shaba village, baini Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- township, gullin county (1 IBRD / 85090 Post Limited 27,430.28 0.00 Implementa Services Quotations Envelope 11 15 15 km of low voltage line, 1 tion transformer) SCGLG114 / Water conservancy construction Pending project of yulin village, Erlang Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 56,136.94 0.00 Implementa town, gulin county (12 Services Quotations Envelope 11 15 15 tion reservoirs of 60 cubic meters, PE40 pipeline of 5 km) SCGLG115 / Water conservancy construction Pending project of yulin village, Erlang Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 43,519.53 0.00 Implementa town, gulin county (1 mouth Services Quotations Envelope 11 15 15 tion of 200 cubic meters reservoir, 5 km of PE63 pipeline) SCGLG116 / Gulin county Pending Erlang town yulin village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 51,485.00 0.00 Implementa production road construction Services Quotations Envelope 11 15 15 tion 3 km SCGLG117 / Gulin county Pending Erlang town yulin village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 153,621.06 0.00 Implementa regulation village road Services Quotations Envelope 11 15 15 tion (hardening) 3 km SCGLG118 / Gullin county Pending Erlang town yulin village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 140,476.95 0.00 Implementa regulation road (hardening) 2 Services Quotations Envelope 11 15 15 tion km SCGLG120 / Construction of low-voltage line in yulin Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- village, Erlang town, gulin IBRD / 85090 Post Limited 27,430.28 0.00 Implementa Services Quotations Envelope 11 15 15 county (1km of low-voltage tion power line, 1 transformer) SCGLG121 / Gullin county Pending jiaoyuan town yulin village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 154,455.00 0.00 Implementa production road construction Services Quotations Envelope 11 15 15 tion 9 km SCGLG122 / Water conservancy construction Pending project of yulin village, Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 65,291.00 0.00 Implementa jiaoyuan town, gullin county Services Quotations Envelope 11 15 15 tion (2 200 cubic meters reservoir, 12 km PE40 pipeline) SCGLG123 / Gullin county Pending jiaoyuan town yulin village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 140,476.95 0.00 Implementa regulation village road km Services Quotations Envelope 11 15 15 tion (hardening) 2 km SCGLG124 / Gullin county Pending jiaoyuan town yulin village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 153,621.07 0.00 Implementa regulation village road Services Quotations Envelope 11 15 15 tion (hardening) 3 km SCGLG125 / Construction of water conservancy facilities in biaozi village, jiaoyuan Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- town, gullin county (1 200 IBRD / 85090 Post Limited 115,165.47 0.00 Implementa Services Quotations Envelope 11 15 15 cubic meter reservoir, 10 km tion PE40 pipe, 20 60 cubic meters reservoir) SCGLG126 / Water conservancy facilities Pending construction in qinglong Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 34,714.26 0.00 Implementa village, maoxi town, gulin Services Quotations Envelope 11 15 15 tion county (2 reservoirs of 200 cubic meters) SCGLG128 / Gulin county maoxi town qinglong village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-06- 2019-05- 2019-07- 2019-08- IBRD / 85090 Post Limited 154,455.00 169,868.64 Completed production road construction Services Quotations Envelope 11 05 15 02 15 9 km SCGLG127 / Construction of water conservancy facilities in qinglong village, maoxi Public Infrastructure and Request for Single Stage - One 2019-04- 2019-06- 2019-05- 2019-07- 2019-08- IBRD / 85090 Post Limited 52,686.47 96,296.57 Completed town, gulin county (4 Services Quotations Envelope 11 05 15 09 15 reservoirs of 60 cubic meters, PE40 pipeline of 15 kilometers) SCGLG129 / Water conservancy project of chayuan village, mahisi Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- township, gullin county (20 IBRD / 85090 Post Limited 123,288.95 131,671.15 Completed Services Quotations Envelope 11 26 15 25 15 reservoirs of 60 cubic meters, 20 kilometers of PE40 pipeline) SCGLG130 / Construction of water conservancy project in Under chayuan village, mahisi Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 69,681.92 0.00 Implementa township, gullin county (1 Services Quotations Envelope 11 15 15 tion 200 cubic meter reservoir, 10 km PE63 pipeline) Page 6 SCGLG131 / Gullin county masi township tea garden Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 137,293.34 145,178.09 Completed village production road Services Quotations Envelope 11 26 15 25 15 construction 8 km SCGLG132 / Gullin county mahisi township tea garden Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 140,476.95 149,709.28 Completed village regulation village road Services Quotations Envelope 11 26 15 25 15 km (hardening) 2 km SCGLG133 / Gullin county mahisi township tea garden Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 153,621.07 164,946.54 Completed village regulation village road Services Quotations Envelope 11 26 15 25 15 (hardening) 3 km SCGLG135 / Construction of low-voltage line in chayuan village, mahisi township, Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 27,430.28 18,222.26 Completed gullin county (1km of low- Services Quotations Envelope 11 26 15 25 15 voltage power line, 1 transformer) SCGLG136 / Construction of water conservancy facilities in tuguan village, horseshoe town, gullin county (20 Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 158,003.21 166,679.56 Completed reservoirs of 60 cubic Services Quotations Envelope 11 22 15 28 15 meters,20 kilometers of PE40 pipeline,2 reservoirs of 200 cubic meters) SCGLG137 / Gullin county horseshoe town tuguan Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 171,616.67 181,472.14 Completed village production road Services Quotations Envelope 11 22 15 29 15 construction 10 km SCGLG138 / Improvement of road (hardening) 3 km in Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 153,621.07 165,348.85 Completed tuguan village, horseshoe Services Quotations Envelope 11 22 15 29 15 town, gullin county SCGLG139 / Six groups of tuguan village, horseshoe Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- town, gullin county, will IBRD / 85090 Post Limited 153,621.07 162,516.43 Completed Services Quotations Envelope 11 22 15 29 15 renovate the village road (hardening) for 3 kilometers SCGLG140 / Four groups of tuguan village, horseshoe Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- town, gullin county, regulate IBRD / 85090 Post Limited 140,476.95 151,902.46 Completed Services Quotations Envelope 11 22 15 29 15 village roads and highways (hardening) for 2 kilometers SCGLG143 / Construction of low-voltage line in tuguan Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- village, horseshoe town, IBRD / 85090 Post Limited 27,430.29 0.00 Implementa Services Quotations Envelope 11 15 15 gullin county (1km of low- tion voltage power line, 1 transformer) SCGLG144 / Gullin county, horseshoe town, tuguan Public Infrastructure and Request for Single Stage - One 2019-04- 2019-08- 2019-05- 2019-09- 2019-08- IBRD / 85090 Post Limited 103,547.48 63,173.60 Completed village small 2 - type Services Quotations Envelope 11 23 15 18 15 irrigation station construction SCGLG145 / Construction of water conservancy facilities in jiulong village, taiping Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- town, gulin county (6 60m3 IBRD / 85090 Post Limited 84,850.41 0.00 Implementa Services Quotations Envelope 11 15 15 reservoir, 2 200m3 reservoir, tion 3 km PE63 pipeline, 5 km PE40 pipeline) SCGLG146 / Gulin county Pending taiping town jiulong village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- IBRD / 85090 Post Limited 102,414.04 0.00 Implementa production road construction Services Quotations Envelope 11 15 15 tion 5.97 km SCGLG147 / Groups 5 and 6, jiulong village, taiping town, Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- gulin county, will regulate the IBRD / 85090 Post Limited 153,621.07 0.00 Implementa Services Quotations Envelope 11 15 15 village road (hardening) for 3 tion kilometers SCGLG148 / Groups 2 and 3 of jiulong village, taiping Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- town, gulin county, regulate IBRD / 85090 Post Limited 153,621.07 0.00 Implementa Services Quotations Envelope 11 15 15 the roads within the village tion (hardening) for 3 kilometers SCGLG149 / Gulin county taiping town jiulong village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 140,476.96 133,103.62 Completed regulation village road road Services Quotations Envelope 11 29 15 30 15 (hardening) 2 km SCGLG151 / Construction of low-voltage line in jiulong Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- village, taiping town, gulin IBRD / 85090 Post Limited 27,430.28 0.00 Implementa Services Quotations Envelope 11 15 15 county (1km of low-voltage tion power line, 1 transformer) SCGLG152 / Construction of water conservancy facilities in shuiluo village, yongle Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- town, gulin county (6 IBRD / 85090 Post Limited 72,110.02 47,780.43 Completed Services Quotations Envelope 11 30 15 27 15 reservoirs of 60 cubic meters, 1 reservoir of 200 cubic meters, 3 kilometers of PE40 pipeline) SCGLG153 / Gulin county yongle town shuiluo village Public Infrastructure and Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 85,808.34 91,122.91 Completed production road construction Services Quotations Envelope 11 30 15 27 15 5 km SCGLG154 / Office building construction in shuiluo Integrated Value Chain Request for Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-08- IBRD / 85090 Post Limited 33,343.08 37,155.66 Completed village, yongle town, gulin Development Quotations Envelope 11 30 15 27 15 county (100 square meters) SCGLG155 / Construction of low-voltage line in shuiluo Pending Public Infrastructure and Request for Single Stage - One 2019-04- 2019-05- 2019-08- village, yongle town, gulin IBRD / 85090 Post Limited 27,430.29 0.00 Implementa Services Quotations Envelope 11 15 15 county (1km of low-voltage tion power line, 1 transformer) SCXYG1939 / Construction Pending of an agricultural products Public Infrastructure and Single Stage - One 2019-04- 2019-04- 2019-05- 2019-05- 2019-05- 2019-07- IBRD / 85090 Post Request for Bids Open - National 200,967.21 0.00 Implementa trading market in xuyong Services Envelope 10 15 16 17 30 30 tion county SCXYG1940 / Xuyong county Public Infrastructure and Single Stage - One 2019-04- 2019-06- 2019-04- 2019-05- 2019-07- 2019-05- 2019-07- 2019-05- 2019-08- 2019-07- 5 small two - type irrigation IBRD / 85090 Post Request for Bids Open - National 520,402.20 525,144.88 Completed Services Envelope 10 10 15 16 12 17 12 30 13 30 station construction projects SCGLG141 / Tuguan Village, Ma Ti Town, Gulin County, Public Infrastructure and Request for Single Stage - One 2019-05- 2019-08- 2019-06- 2019-09- 2019-09- IBRD / 85090 Post Limited 140,476.95 151,711.82 Completed renovates 2 km of Village Services Quotations Envelope 11 23 14 18 14 Road highway (hardening) SCXYG1936 / 1.9 km road renovation (hardening) in Public Infrastructure and Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-09- IBRD / 85090 Post Limited 97,794.11 101,866.18 Completed Xiekou Village, Xuyong Services Quotations Envelope 11 31 14 26 14 County SCXYG1941 / Improvement Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- of market roads in xuyong IBRD / 85090 Post Limited 115,784.00 0.00 Implementa Services Quotations Envelope 11 14 14 county (hardening) tion SCXYG1934 / Village road improvement (hardening) Public Infrastructure and Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-09- IBRD / 85090 Post Limited 56,480.00 58,844.59 Completed 0.8km in shuilaopu village, Services Quotations Envelope 11 15 14 06 14 xuyong county SCXYG1914 / Baila village Pending of Xuyong County plans to Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 6,983.23 0.00 Implementa implement 1 km low-voltage Services Quotations Envelope 11 14 14 tion line SCXYG1919 / Yantang Pending village of Xuyong County Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 2,793.29 0.00 Implementa plans to implement 0.4 km Services Quotations Envelope 11 14 14 tion low-voltage line SCXYG1920 / Xiekou Village Pending of Xuyong County plans to Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 3,491.61 0.00 Implementa implement 0.5 km low- Services Quotations Envelope 11 14 14 tion voltage line SCXYG1922 / The Chishui Pending Community Plan of Xuyong Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 2,793.29 0.00 Implementa County implements 0.3 km Services Quotations Envelope 11 14 14 tion low-voltage line SCXYG1923 / Shuangshan Pending Village of Xuyong County Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 8,379.88 0.00 Implementa plans to implement 1.2 km Services Quotations Envelope 11 14 14 tion low-voltage line SCXYG1924 / Zhongsha Pending Village of Xuyong County Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 4,189.94 0.00 Implementa plans to implement 0.6 km Services Quotations Envelope 11 14 14 tion low-voltage line SCXYG1925 / Songlin village Pending of Xuyong County plans to Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 2,094.97 0.00 Implementa implement 0.3 km low- Services Quotations Envelope 11 14 14 tion voltage line SCXYG1926 / liangping Pending village of Xuyong County Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 5,586.58 0.00 Implementa plans to implement 0.8 km Services Quotations Envelope 11 14 14 tion low-voltage line SCXYG1927 / Huangping Pending village of Xuyong County Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 6,983.23 0.00 Implementa plans to implement 1 km low- Services Quotations Envelope 11 14 14 tion voltage linee line Page 7 SCXYG1929 / Nanshan Pending village in xuyong county Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 1,396.64 0.00 Implementa plans to implement 0.2km Services Quotations Envelope 11 14 14 tion line of low-voltage lines SCXYG1932 / Road improvement (hardening) of Public Infrastructure and Request for Single Stage - One 2019-05- 2019-08- 2019-06- 2019-09- 2019-09- IBRD / 85090 Post Limited 82,352.94 86,844.35 Completed tianba village, xuyong Services Quotations Envelope 11 13 14 05 14 county, 1.6km SCXYG1911 / Shuiliao Pending Village of Xuyong County Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-09- IBRD / 85090 Post Limited 6,983.23 0.00 Implementa plans to implement 1 km low- Services Quotations Envelope 11 14 14 tion voltage line SCJYG015 / Jinyang County Under Public Infrastructure and Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-09- plans to build 2 kilometers of IBRD / 85090 Post Limited 91,673.53 0.00 Implementa Services Quotations Envelope 12 06 06 06 village roads tion SCJYG026 / Jinyang County Pending Public Infrastructure and Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-09- renovated village roads IBRD / 85090 Post Request for Bids Open - National 279,761.03 0.00 Implementa Services Envelope 10 15 17 17 29 29 (hardened) 2.4KM. tion SCJYG027 / 41 new 60 cubic Pending meters reservoirs and 25 kilo Public Infrastructure and Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-08- IBRD / 85090 Post Request for Bids Open - National 256,820.00 0.00 Implementa meters of PE40 pipelines in Ji Services Envelope 10 15 17 17 29 29 tion nyang County SCZJGD088 / Jiefang Pending Township of Zhaojue County Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 175,794.12 0.00 Implementa plans to build 8.6 kilometers Services Quotations Envelope 11 14 28 tion of production sidewalk. SCZJGD89 / Zhaojue County Pending Jiefang Township plans to Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 55,004.12 0.00 Implementa build 1.2 kilometers of Services Quotations Envelope 11 14 28 tion village roads. SCZJG44 / Zhaojue County Pending Dimo Township renovation Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 152,469.76 0.00 Implementa Village Road (hardening) Services Quotations Envelope 11 14 28 tion 1.635 kilometers. SCZJG93 / Liuqie Township, Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- Zhaojue County, plans to IBRD / 85090 Post Limited 45,836.76 0.00 Implementa Services Quotations Envelope 11 14 28 build a 1 km village road. tion SCZJG95 / Liuqie Township, Pending Zhaojue County, plans to Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 81,764.70 0.00 Implementa build a production sidewalk Services Quotations Envelope 11 14 28 tion of 4 kilometers. SCZJG96 / Shujue Village, Pending Yipo, Zhaojue County, Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 195,832.72 0.00 Implementa renovates 2.1 kilometers of Services Quotations Envelope 11 14 28 tion village roads. SCZJG58 / Shujue Village, Pending Yipo, Zhaojue County, plans Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 99,548.53 0.00 Implementa to build 4.87 kilometers of Services Quotations Envelope 11 14 28 tion production sidewalk. SCZJG52 / Zhaojue county Pending agency juwa village five Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 30,252.26 0.00 Implementa village road construction Services Quotations Envelope 11 14 28 tion plans 0.66 km SCZJG71 / Zhaojue county Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- SiKai township road IBRD / 85090 Post Limited 83,928.40 0.00 Implementa Services Quotations Envelope 11 14 28 (hardening) 0.9 km. tion SCZJG72 / The Sikai Pending Township of Zhaojue County Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 40,882.40 0.00 Implementa plans to build a production Services Quotations Envelope 11 14 28 tion sidewalk of 2 kilometers. SCZJG83 / Shaladipo Village Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- Road Renovation in Zhaojue IBRD / 85090 Post Limited 78,333.08 0.00 Implementa Services Quotations Envelope 11 14 28 county is 0.84 kilometers. tion SCZJG53 / Zhaojue County Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- plans to build 1.59 IBRD / 85090 Post Limited 72,880.45 0.00 Implementa Services Quotations Envelope 11 14 28 kilometers of village roads. tion SCZJG81 / Wanchang Pending Township, Zhaojue County, Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- IBRD / 85090 Post Limited 186,507.35 0.00 Implementa renovates village roads by 2 Services Quotations Envelope 11 14 28 tion kilometers. SVMGG60 / Wagujue village Pending in meigu county plans to Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-10- IBRD / 85090 Post Limited 178,760.00 0.00 Implementa build 3.29 kilometers of Services Quotations Envelope 15 06 09 tion village road. SCMGG62 / Meigu Azowau Public Infrastructure and Request for Single Stage - One 2019-07- 2019-11- 2019-08- 2019-12- 2019-10- Village plans to build 2 km of IBRD / 85090 Post Limited 91,204.00 61,516.28 Completed Services Quotations Envelope 15 19 09 19 10 village roads. SCMGG63 / Waxi Village in Pending Meigu County plans to build Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-10- IBRD / 85090 Post Limited 54,722.00 0.00 Implementa 1.2 kilometers of village Services Quotations Envelope 15 09 10 tion roads. SCMGG65 / Meigu County farming village plans to Public Infrastructure and Request for Single Stage - One 2019-07- 2019-12- 2019-08- 2019-12- 2019-10- IBRD / 85090 Post Limited 74,221.00 80,995.82 Signed renovate (harden) village Services Quotations Envelope 15 05 09 19 10 roads 0.8 kilometers. SCMGG66 / Wagujue Village in Meigu County plans to Public Infrastructure and Request for Single Stage - One 2019-07- 2019-11- 2019-08- 2019-12- 2019-10- IBRD / 85090 Post Limited 111,331.00 111,208.70 Completed renovate (harden) 1.2 km of Services Quotations Envelope 15 17 09 19 10 village roads. SCMGG68 / Meigu Azowau Village plans to renovate Public Infrastructure and Request for Single Stage - One 2019-07- 2019-12- 2019-08- 2019-12- 2019-10- IBRD / 85090 Post Limited 111,331.00 123,248.52 Signed (harden) village roads for 1.2 Services Quotations Envelope 15 05 09 15 10 km. SCMGG69 / Guohe village in meigu county is planned to Public Infrastructure and Request for Single Stage - One 2019-07- 2019-12- 2019-08- 2019-12- 2019-10- IBRD / 85090 Post Limited 92,776.00 99,284.89 Signed renovate (harden) the village Services Quotations Envelope 15 04 09 15 10 road by 1 km. SCMGG70 / Jiwei Village in Meigu County plans to Public Infrastructure and Request for Single Stage - One 2019-07- 2019-11- 2019-08- 2019-12- 2019-10- IBRD / 85090 Post Limited 129,887.00 142,047.86 Signed renovate (harden) 1.4 km of Services Quotations Envelope 15 17 09 12 10 village roads. SCMGG71 / Yide Amo Village in Meigu County plans Public Infrastructure and Request for Single Stage - One 2019-07- 2019-11- 2019-08- 2019-12- 2019-10- IBRD / 85090 Post Limited 64,943.00 67,464.59 Signed to renovate (harden) village Services Quotations Envelope 15 17 09 19 10 roads by 0.7 kilometers. SCMGG90 / Wau Village in Under Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-10- Meigu County plans to build IBRD / 85090 Post Limited 45,602.00 0.00 Implementa Services Quotations Envelope 15 09 10 1 km of village roads. tion SCMGG91 / Wau Village in Meigu County plans to Public Infrastructure and Request for Single Stage - One 2019-07- 2019-11- 2019-08- 2019-12- 2019-10- IBRD / 85090 Post Limited 92,776.00 100,804.72 Signed renovate (harden) 1 km of Services Quotations Envelope 15 17 09 19 10 village roads. SCMGG74 / Waxi Village in Pending Meigu County plans to Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-10- IBRD / 85090 Post Limited 83,499.00 0.00 Implementa renovate (harden) village Services Quotations Envelope 15 09 10 tion roads by 0.9 km. SCMGG92 / Jiukou Township, Meigu County, Public Infrastructure and Request for Single Stage - One 2019-07- 2019-12- 2019-08- 2019-12- 2019-10- IBRD / 85090 Post Limited 81,346.00 86,980.58 Signed plans to build a production Services Quotations Envelope 15 06 09 19 10 ramp of 4 kilometers. SCMGG93 / Meigu county Pending luo‘e'yi gan township Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-10- IBRD / 85090 Post Limited 40,673.00 0.00 Implementa planned to build production Services Quotations Envelope 15 09 10 tion road 2 km. SCMGG94 / Guoke village of Under Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-08- 2019-10- meigu county plans to build IBRD / 85090 Post Limited 20,337.00 26,196.10 Implementa Services Quotations Envelope 15 17 09 10 1 kilometer production road. tion SCMGG95 / Dage Village in Under Meigu County plans to build Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-10- IBRD / 85090 Post Limited 61,010.00 0.00 Implementa a production sidewalk of 3 Services Quotations Envelope 15 09 10 tion kilometers. SCMGG96 / Meigu county Pending Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-10- jiwei village plans to build 4 IBRD / 85090 Post Limited 81,346.00 0.00 Implementa Services Quotations Envelope 15 09 10 km production road tion SCMGG97 / Meigu county Public Infrastructure and Request for Single Stage - One 2019-07- 2019-11- 2019-08- 2019-12- 2019-10- ide amor village plans to IBRD / 85090 Post Limited 24,404.00 25,345.04 Signed Services Quotations Envelope 15 05 09 15 10 build 1.2 km production road. SCMGG98 / Waxi village of Under Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-10- meigu county plans to build IBRD / 85090 Post Limited 81,346.00 0.00 Implementa Services Quotations Envelope 15 09 10 4 kilometers of production tion road SCGLG162 / Caiban village, gulin county, plans to build 10 mouths of 60 cubic Public Infrastructure and Request for Single Stage - One 2019-07- 2019-09- 2019-08- 2019-10- 2019-11- IBRD / 85090 Post Limited 95,293.05 105,824.17 Completed meters of reservoir, 3 Services Quotations Envelope 16 16 21 28 21 kilometers of PE40 water pipeline and 3 kilometers of production road. SCGLG163 / Shuiluo village in gulin county plans to Public Infrastructure and Request for Single Stage - One 2019-07- 2019-07- 2019-08- 2019-08- 2019-11- IBRD / 85090 Post Limited 105,357.72 113,484.19 Completed renovate (harden) 1.5 km of Services Quotations Envelope 16 18 21 15 21 roads in the village. Page 8 SCGLG164 / Baima village, gulin county, plans to build 8 Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-08- 2019-09- 2019-11- IBRD / 85090 Post Limited 137,293.34 144,652.80 Completed kilometers of production Services Quotations Envelope 16 10 22 06 22 roads. SCGLG165 / Yulin Village in Gulin County plans to build a Public Infrastructure and Request for Single Stage - One 2019-07- 2019-09- 2019-08- 2019-10- 2019-11- IBRD / 85090 Post Limited 85,808.34 89,429.39 Completed production sidewalk of 5 Services Quotations Envelope 16 10 21 23 21 kilometers. SCGLG166 / Gulin county rhinoceros village plans to renovate (hardening) 2 km of Public Infrastructure and Request for Single Stage - One 2019-07- 2019-09- 2019-08- 2019-10- 2019-11- roads, build 8 mouths of 60 IBRD / 85090 Post Limited 177,052.23 185,430.88 Completed Services Quotations Envelope 16 10 21 22 21 cubic meters of reservoirs, and install PE40 water pipeline 5 km. SCGLG167 / Tuguancun in Gulin County plans to install Public Infrastructure and Request for Single Stage - One 2019-07- 2019-08- 2019-08- 2019-09- 2019-11- IBRD / 85090 Post Limited 18,109.14 18,577.74 Completed 2 km of PE63 pipeline and 3 Services Quotations Envelope 16 23 21 18 21 km of PE40 pipeline. SCBTG65 / Butuo County Under Integrated Value Chain Request for Single Stage - One 2020-07- 2020-12- 2020-09- 2020-12- plans to build 23 disinfection IBRD / 85090 Post Limited 64,834.39 0.00 Implementa Development Quotations Envelope 07 25 01 31 rooms for cattle farms. tion SCBTG66 / Butuo County Under plans to install low-voltage Public Infrastructure and 2020-05- 2020-06- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Direct Selection Direct 54,009.87 0.00 Implementa Electric power lines for Services 22 01 27 01 01 28 tion Mohezuo Village. SCXYGDL2002 / Xuyong County plans to purchase a Pending Public Infrastructure and 2020-06- 2020-06- 2020-07- 2020-12- transformer and install 10 IBRD / 85090 Post Direct Selection Direct 86,600.00 0.00 Implementa Services 02 07 14 20 kilometers of low-voltage tion power lines. SCXYGLHS2001 / Chishui and Puhui Planting and Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- Breeding Cooperatives in IBRD / 85090 Post Limited 75,000.00 0.00 Implementa Development Quotations Envelope 15 10 31 Xuyong County plan to build tion office houses. SCXYGLHS2004 / Chishui and Puhui Planting and Breeding Cooperatives in Xuyong County plan to build Pending an agricultural product Public Infrastructure and Single Stage - One 2020-06- 2020-06- 2020-07- 2020-08- 2020-09- 2020-12- IBRD / 85090 Post Request for Bids Open - National 578,369.16 0.00 Implementa trading market, trading Services Envelope 10 15 27 26 30 30 tion market connecting highways, 20 beef cattle trading epidemic prevention observation fields, and a fruit storage warehouse. SCXYGLHS2003 / Chishui and Puhui Planting and Breeding Cooperatives in Public Infrastructure and Request for Single Stage - One 2020-06- 2020-05- 2020-08- 2020-06- 2020-12- Xuyong County plan to build IBRD / 85090 Post Limited 165,945.04 9,131.79 Completed Services Quotations Envelope 15 28 10 18 31 supporting water conservancy facilities, Including irrigation cisterns and irrigation pipes. SCJYG030 / Jinyang County Integrated Value Chain Request for Single Stage - One 2020-06- 2018-01- 2020-07- 2018-01- 2020-12- plans to build office houses IBRD / 85090 Post Limited 133,372.35 38,700.42 Completed Development Quotations Envelope 07 05 28 17 31 for cooperative. SCJYG031 / Tengda Livestock Farming Integrated Value Chain Request for Single Stage - One 2020-06- 2020-03- 2020-07- 2020-03- 2020-12- Professional Cooperative in IBRD / 85090 Post Limited 323,335.80 615,813.10 Signed Development Quotations Envelope 07 08 28 30 31 Jinyang County plans to build a livestock circle. SCJYG033 / The Shenglong Livestock Farming Integrated Value Chain Request for Single Stage - One 2020-06- 2020-05- 2020-07- 2020-06- 2020-12- Professional Cooperative of IBRD / 85090 Post Limited 385,501.00 116,943.06 Signed Development Quotations Envelope 07 04 28 29 31 Jinyang County plans to build livestock habitats. SCJYG035 / Jinyang County Pending plans to build 5 Integrated Value Chain Request for Single Stage - One 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Limited 146,305.78 0.00 Implementa environmental treatment Development Quotations Envelope 07 26 31 tion sites for the cooperative. SCJYG036 / Jinyang County Pending plans to build 5 trading Integrated Value Chain Request for Single Stage - One 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Limited 109,729.33 0.00 Implementa epidemic prevention Development Quotations Envelope 07 26 31 tion observation fields. SCJYG037 / Jinyang County Pending plans to rehabilitate the Public Infrastructure and Request for Single Stage - One 2020-06- 2020-07- 2020-10- IBRD / 85090 Post Limited 299,139.06 0.00 Implementa village roads (hardening) for Services Quotations Envelope 07 25 30 tion the cooperative. SCJYG038 / Jinyang County Pending Public Infrastructure and 2020-06- 2020-06- 2020-07- 2020-12- plans to install 2 kilometers IBRD / 85090 Post Direct Selection Direct 13,899.05 0.00 Implementa Services 02 07 14 20 of low-voltage power lines. tion SCJYG039 / Xuyong County Pending Public Infrastructure and 2020-06- 2020-06- 2020-07- 2020-12- plans to purchase and install IBRD / 85090 Post Direct Selection Direct 20,482.81 0.00 Implementa Services 02 07 10 16 an electric power tion transformer. SCMGG016 / Meigu County Pending plans to build 6 trading Integrated Value Chain Request for Single Stage - One 2020-06- 2020-07- 2021-01- IBRD / 85090 Post Limited 4,285.71 0.00 Implementa epidemic prevention Development Quotations Envelope 08 27 01 tion observation fields. SCMGG009 / Jinyang County Pending plans to build 6 Integrated Value Chain Request for Single Stage - One 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Limited 54,857.10 0.00 Implementa environmental treatment Development Quotations Envelope 08 27 31 tion sites for the cooperative. SCJYG040 / Futai Sheep Farming Farmers Professional Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- Cooperative in Jinyang IBRD / 85090 Post Limited 219,707.40 0.00 Implementa Development Quotations Envelope 13 03 31 County plans to build a tion livestock circle. SCJYG041 / Fengnong Professional Livestock Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- Cooperative in Jinyang IBRD / 85090 Post Limited 385,501.00 0.00 Implementa Development Quotations Envelope 13 03 31 County plans to build a tion livestock circle. SCMGG001 / Meigu County Under Integrated Value Chain Request for Single Stage - One 2020-06- 2017-02- 2020-08- 2020-12- plans to build a livestock IBRD / 85090 Post Limited 57,143.00 0.00 Implementa Development Quotations Envelope 13 10 03 31 circle for Cooperative. tion SCMGG002 / Meigu County Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- plans to build a livestock IBRD / 85090 Post Limited 57,143.00 0.00 Implementa Development Quotations Envelope 13 03 31 circle for Cooperative. tion SCMGG003 / Meigu County Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- plans to build a livestock IBRD / 85090 Post Limited 57,143.00 0.00 Implementa Development Quotations Envelope 13 03 31 circle for Cooperative. tion SCMGG004 / Meigu County Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- plans to build a livestock IBRD / 85090 Post Limited 57,143.00 0.00 Implementa Development Quotations Envelope 13 03 31 circle for Cooperative. tion SCMGG005 / Meigu County Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- plans to build a livestock IBRD / 85090 Post Limited 57,143.00 0.00 Implementa Development Quotations Envelope 13 03 31 circle for Cooperative. tion SCMGG008 / Meigu County Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- plans to build a livestock IBRD / 85090 Post Limited 57,143.00 0.00 Implementa Development Quotations Envelope 13 03 31 circle for Cooperative. tion SCMGGYGJ005 / Meigu Pending County plans to build a Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- IBRD / 85090 Post Limited 18,497.10 0.00 Implementa livestock circle for Development Quotations Envelope 13 03 31 tion Cooperative. GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCMGH01 / 10 cooperative Integrated Value Chain Request for Single Stage - One 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- office equipment purchase in IBRD / 85090 Post Limited 38,525.00 35,830.60 Completed Development Quotations Envelope 28 13 22 09 20 18 Mei Gu County SCJYH046 / Jinyang county poverty alleviation project Public Infrastructure and Request for Single Stage - One 2018-06- 2018-05- 2018-07- 2018-06- 2018-08- management center, product IBRD / 85090 Post Limited 16,967.00 88,188.01 Signed Services Quotations Envelope 13 07 07 06 06 market information release platform. SCBTH03 / The product Pending market information platform Public Infrastructure and Request for Single Stage - One 2018-06- 2018-07- 2018-07- IBRD / 85090 Post Limited 16,967.00 0.00 Implementat of the project office of Bu Services Quotations Envelope 22 15 30 ion Tuo County SCBTH02 / 11 cooperative Integrated Value Chain Request for Single Stage - One 2018-07- 2020-09- 2018-08- 2020-09- 2018-08- 2020-11- office equipment purchase in IBRD / 85090 Post Limited 42,377.00 39,651.60 Completed Development Quotations Envelope 11 02 06 25 21 16 Bu Tuo County SCJYH044 / Jinyang County 7.5 fine wool sheep project Pending Integrated Value Chain Request for Single Stage - One 2018-06- 2018-07- 2018-08- area cooperative 7 sets of IBRD / 85090 Post Limited 26,967.00 0.00 Implementat Development Quotations Envelope 13 09 05 office equipment ion procurement contract SCJYH045 / Jinyang County 7.5 fine wool sheep project Pending Integrated Value Chain Request for Single Stage - One 2018-06- 2018-07- 2018-08- area cooperative 7 sets of IBRD / 85090 Post Limited 48,311.00 0.00 Implementat Development Quotations Envelope 13 09 05 office furniture procurement ion contract SCBTH05 / Butuo county 9 Integrated Value Chain Request for Single Stage - One 2018-12- 2018-12- 2019-01- 2018-12- 2019-02- 2018-12- cooperative office furniture IBRD / 85090 Post Limited 62,115.00 56,847.07 Completed Development Quotations Envelope 09 03 03 24 03 26 procurement Page 9 SCBTH07 / Butuo county le Pending Integrated Value Chain Request for Single Stage - One 2019-04- 2019-05- 2019-05- 'an township office IBRD / 85090 Post Limited 1,463.05 0.00 Implementat Development Quotations Envelope 16 12 27 equipment procurement ion SCXYH201902 / Xuyong Integrated Value Chain Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- County purchased 19 sets of IBRD / 85090 Post Limited 10,618.00 15,225.15 Completed Development Quotations Envelope 11 31 14 25 14 23 forage processing equipment. SCXYH201903 / Xuyong county procurement zha hay Integrated Value Chain Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-08- kneading baling baling IBRD / 85090 Post Limited 28,824.00 22,155.15 Completed Development Quotations Envelope 11 31 14 25 14 01 integrated silage processing equipment 4 sets/set SCXYH201904 / Xuyong Integrated Value Chain Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-08- County plans to purchase 20 IBRD / 85090 Post Limited 29,412.00 30,183.71 Completed Development Quotations Envelope 11 31 14 25 14 05 tricycles SCXYH201905 / Xuyong Integrated Value Chain Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-07- county procurement of a IBRD / 85090 Post Limited 24,156.00 24,943.69 Completed Development Quotations Envelope 11 31 14 25 14 23 transport vehicle SCXYH201901 / Xuyong Under County plans to purchase 20 Integrated Value Chain Request for Single Stage - One 2019-05- 2019-05- 2019-06- 2019-07- IBRD / 85090 Post Limited 88,235.00 81,132.21 Implementat sets of wet and dry Development Quotations Envelope 11 31 14 14 ion separation equipment SCJYH097 / Jinyang County Pending Integrated Value Chain Request for Single Stage - One 2019-05- 2019-06- 2019-07- plans to purchase 92 forage IBRD / 85090 Post Limited 51,412.00 0.00 Implementat Development Quotations Envelope 11 14 14 processing equipment. ion SCJYH098 / Jinyang County Pending Integrated Value Chain Request for Single Stage - One 2019-05- 2019-06- 2019-07- plans to purchase 15 rotary IBRD / 85090 Post Limited 12,574.00 0.00 Implementat Development Quotations Envelope 11 14 14 tillers. ion Pending SCJYH099 / Jinyang county Integrated Value Chain Request for Single Stage - One 2019-05- 2019-06- 2019-07- IBRD / 85090 Post Limited 3,971.00 0.00 Implementat purchases 54 sprayers. Development Quotations Envelope 11 14 14 ion SCBTH23 / Butuo County plans to purchase office Integrated Value Chain Request for Single Stage - One 2019-08- 2020-03- 2019-09- 2020-04- 2019-10- 2020-04- IBRD / 85090 Post Limited 24,067.00 25,331.61 Completed equipment for seven Development Quotations Envelope 21 16 15 09 15 28 cooperatives. SCGLH134 / Gulin county Pending plans to purchase office Integrated Value Chain Request for Single Stage - One 2019-07- 2019-08- 2019-11- IBRD / 85090 Post Limited 38,771.03 0.00 Implementat equipment for 10 Development Quotations Envelope 16 21 21 ion cooperatives. SCBTH06 / Butuo County Integrated Value Chain Request for Single Stage - One 2019-08- 2020-09- 2019-09- 2020-09- 2019-10- 2020-11- plans to purchase office IBRD / 85090 Post Limited 67,754.00 62,149.20 Completed Development Quotations Envelope 21 02 15 25 15 16 furniture for 11 cooperatives. SCGLH135 / Gulin County Integrated Value Chain Request for Single Stage - One 2019-07- 2019-10- 2019-08- 2019-11- 2019-11- 2019-11- plans to purchase office IBRD / 85090 Post Limited 67,754.21 25,271.17 Completed Development Quotations Envelope 16 13 21 07 21 28 furniture for 11 cooperatives. SCJYH114 / Jinyang County Integrated Value Chain Request for Single Stage - One 2019-07- 2019-06- 2019-08- 2019-08- 2019-09- plans to purchase konjac IBRD / 85090 Post Limited 454,413.00 477,796.70 Signed Development Quotations Envelope 16 30 14 06 14 processing equipment. SCZJH-129 / Zhaojue County Pending Integrated Value Chain Request for 2020-05- 2020-07- 2020-07- purchased 8 sets of IBRD / 85090 Post 4,503.70 0.00 Implementat Development Quotations 18 13 30 cooperative financial ion software. SCGLH200 / Gulin County Pending Integrated Value Chain Request for Single Stage - One 2020-05- 2020-07- 2020-12- plans to purchase office IBRD / 85090 Post Limited 12,933.43 0.00 Implementat Development Quotations Envelope 27 22 25 furniture for 4 cooperatives. ion SCGLH201 / Gulin County Pending Integrated Value Chain Request for Single Stage - One 2020-05- 2020-07- 2020-12- plans to purchase 20 sets of IBRD / 85090 Post Limited 11,704.46 0.00 Implementat Development Quotations Envelope 27 22 31 financial software. ion SCGLH202 / Gulin County plans to purchase office Pending Integrated Value Chain Request for Single Stage - One 2020-05- 2020-07- 2020-12- equipment, including IBRD / 85090 Post Limited 4,389.17 0.00 Implementat Development Quotations Envelope 27 22 31 computers, projectors, and ion microphones. SCXYH2001 / Xuyong Pending Integrated Value Chain Request for Single Stage - One 2020-06- 2020-07- 2020-11- County plans to purchase two IBRD / 85090 Post Limited 1,126.76 0.00 Implementat Development Quotations Envelope 07 14 24 sets of financial software. ion SCMGH017 / Meigu County Under Integrated Value Chain Request for Single Stage - One 2020-06- 2017-05- 2020-07- 2020-11- plans to purchase 10 sets of IBRD / 85090 Post Limited 5,714.28 0.00 Implementat Development Quotations Envelope 08 11 15 25 cooperative financial ion software. SCXYHLHS202001 / Chishui and Puhui Planting and Pending Breeding Cooperatives in Integrated Value Chain Request for Single Stage - One 2020-06- 2020-08- 2020-12- IBRD / 85090 Post Limited 20,583.50 0.00 Implementat Xuyong County plan to Development Quotations Envelope 15 10 31 ion purchase equipment for keeping fresh fruit. SCXYH202201 / Training equipment procurement (2 laptops, 1 portable projector, 1 fixed projector, 1 set of Pending training impact equipment, 1 Project Management, Request for Single Stage - One 2022-05- 2022-05- 2022-06- IBRD / 85090 Post Limited 24,300.00 0.00 Implementat camera, 1 typing and Monitoring and Evaluation Quotations Envelope 08 29 06 ion photocopying equipment, 1 camera, 2 sets of display screens, 1 set of training desks and chairs) NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCMGFZ02 / Walnut Pending Public Infrastructure and Request for Single Stage - One 2018-08- 2018-09- 2018-12- trademark registration in Mei IBRD / 85090 Post Limited 8,196.00 0.00 Implementat Services Quotations Envelope 28 22 20 Gu County ion SCMGFZ03 / Certification of Pending Public Infrastructure and Request for Single Stage - One 2018-08- 2018-09- 2019-10- walnut green agricultural IBRD / 85090 Post Limited 22,459.00 0.00 Implementat Services Quotations Envelope 28 22 01 products in Mei Gu County ion SCZJFZ25 / Trademark Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2019-08- Design and Registration IBRD / 85090 Post Limited 14,705.88 0.00 Implementat Services Quotations Envelope 22 16 30 Service of Zhaojue County ion Products SCZJFZ11 / Green Pending Public Infrastructure and Request for Single Stage - One 2019-05- 2019-06- 2020-06- Agricultural Product IBRD / 85090 Post Limited 40,294.11 0.00 Implementat Services Quotations Envelope 22 16 15 Certification in Zhaojue ion County SCZJZ-31 / Zhaojue County selected a company to carry Pending Public Infrastructure and Request for Single Stage - One 2020-05- 2020-07- 2020-12- out green agricultural IBRD / 85090 Post Limited 19,281.47 0.00 Implementat Services Quotations Envelope 20 15 31 product trademark ion certification for the cooperative. SCGLFZ101 / Gulin County Pending plans to select a company to Public Infrastructure and Request for Single Stage - One 2020-06- 2020-08- 2021-08- IBRD / 85090 Post Limited 16,898.32 0.00 Implementat build and maintain the Services Quotations Envelope 06 01 01 ion website. SCGLFZ104 / Gulin County plans to select a company to Pending carry out green agricultural Public Infrastructure and Request for Single Stage - One 2020-06- 2020-08- 2020-12- IBRD / 85090 Post Limited 60,131.68 0.00 Implementat product trademark Services Quotations Envelope 06 01 31 ion certification for the cooperative. SCXYFZ2002 / Xuyong County plans to select a Pending company to carry out green Public Infrastructure and Request for Single Stage - One 2020-06- 2020-08- 2020-12- IBRD / 85090 Post Limited 19,295.77 0.00 Implementat agricultural product Services Quotations Envelope 07 01 30 ion trademark certification for the cooperative. SCJYF2020-30 / Jinyang County plans to select a Pending company to carry out green Public Infrastructure and Request for Single Stage - One 2020-06- 2020-08- 2020-12- IBRD / 85090 Post Limited 20,043.89 0.00 Implementat agricultural product Services Quotations Envelope 13 07 31 ion trademark certification for the cooperative. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCMGZ12 / The design of Consultant Public Infrastructure and Pending 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- the walnut trademark in IBRD / 85090 Post Qualification Open - National 8,197.00 0.00 2018-08-20 Services Implementation 28 13 20 23 20 meigu county. Selection SCMGZ13 / Packaging Consultant Public Infrastructure and Pending 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- design of Walnut in Mei Gu IBRD / 85090 Post Qualification Open - National 14,754.00 0.00 2018-08-20 Services Implementation 28 13 15 24 24 County Selection SCXYZ19 / Investigation and design of drip irrigation Consultant Public Infrastructure and Under 2018-05- 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- system for 1000 mu sweet IBRD / 85090 Post Qualification Open - National 13,118.00 0.00 2018-05-22 Services Implementation 27 27 27 30 09 29 orange garden in Xuyong Selection County SCXYZ18 / Sichuan World Bank six phase poverty Consultant Research, Training and Pending 2018-08- 2018-09- 2018-10- 2018-11- 2019-05- alleviation project "industrial IBRD / 85090 Post Qualification Open - National 24,590.00 0.00 2018-07-16 Extension Implementation 06 19 19 23 22 poverty alleviation risk Selection prevention" project research SCGLZ011 / Research on the "poverty alleviation model of Consultant Research, Training and Pending 2018-08- 2018-09- 2018-10- 2018-11- 2019-05- industry" in the six phase of IBRD / 85090 Post Qualification Open - National 24,590.00 0.00 2018-07-16 Extension Implementation 06 19 19 23 22 poverty alleviation project of Selection Sichuan World Bank Page 10 SCXYZ17 / Research on cooperative operation Consultant Research, Training and Pending 2018-08- 2018-09- 2018-10- 2018-11- 2019-05- mechanism of Sichuan World IBRD / 85090 Post Qualification Open - National 24,590.00 0.00 2018-07-16 Extension Implementation 06 19 19 23 22 Bank's six phase poverty Selection alleviation project SCZJZ28 / Consulting Service Consultant Public Infrastructure and Pending 2019-05- 2019-05- 2019-06- 2019-06- 2019-08- of Product Packaging Design IBRD / 85090 Post Qualification Open - National 13,235.29 0.00 2019-05-10 Services Implementation 12 28 15 26 26 in Zhaojue County Selection SCZ2020-1 / Sichuan Province plans to hire a consulting firm to conduct special research on the Consultant Research, Training and Under 2020-09- 2020-06- 2020-07- 2020-08- 2020-09- 2021-12- project's industrial poverty IBRD / 85090 Post Qualification Open - National 132,352.94 0.00 2020-05-21 Extension Implementation 01 11 25 24 28 31 alleviation model and Selection cooperative management mechanism, and develop training courseware. SCZJZ-29 / Zhaojue County plans to select a company to Consultant carry out product trademark Public Infrastructure and Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-03- IBRD / 85090 Post Qualification Open - National 14,074.07 0.00 2020-05-22 design and trademark Services Implementation 12 26 25 29 28 Selection registration for the cooperative. SCZ2020-2 / Sichuan Province plans to hire a consulting firm to carry out Consultant experience summary and Research, Training and Under 2020-11- 2020-05- 2020-07- 2020-08- 2020-09- 2021-12- IBRD / 85090 Post Qualification Open - National 132,352.94 0.00 2020-05-22 acceptance evaluation of the Extension Implementation 01 27 10 09 13 01 Selection project, and to refine effective experience to guide future poverty alleviation. SCZJZ-32 / Zhaojue County plans to select a veterinary service company to provide Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2020-12- medical services such as IBRD / 85090 Post Qualification Open - National 58,041.45 0.00 2020-05-22 Development Implementation 12 26 25 29 15 disease prevention and Selection diagnosis and treatment for animals. SCZJZ-35 / Zhaojue County plans to select an audit Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2022-09- company to conduct a IBRD / 85090 Post Qualification Open - National 1,688.89 0.00 2020-05-22 Development Implementation 12 26 25 29 30 financial audit of the Selection cooperative. SCZJZ-34 / Zhaojue County plans to hire a consulting service team to provide daily consulting services for Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-09- cooperatives in terms of IBRD / 85090 Post Qualification Open - National 27,022.21 0.00 2020-05-22 Development Implementation 12 26 25 29 29 standardized management, Selection production, operation, product branding, and marketing. SCZJZ-30 / Zhaojue County Consultant plans to select a company to Public Infrastructure and Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-03- IBRD / 85090 Post Qualification Open - National 12,666.66 0.00 2020-05-22 design the packaging of the Services Implementation 12 26 25 29 28 Selection cooperative product. SCGLZ033 / Gulin County plans to hire a consulting service team to provide daily consulting services for Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-10- 2021-10- cooperatives in terms of IBRD / 85090 Post Qualification Open - National 10,534.02 0.00 2020-05-26 Development Implementation 16 30 29 03 02 standardized management, Selection production, operation, product branding, and marketing. SCGLZ034 / Gulin County plans to select a cooperative Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-10- operation firm to guide the IBRD / 85090 Post Qualification Open - National 42,136.06 0.00 2020-05-22 Development Implementation 12 26 25 29 28 operation and management Selection of the cooperative. SCGLZ035 / Gulin County plans to select an audit Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2022-09- company to conduct a IBRD / 85090 Post Qualification Open - National 21,068.03 0.00 2020-05-22 Development Implementation 12 26 25 29 29 financial audit of the Selection cooperative. SCGLZ036 / Gulin County plans to select a veterinary service company to provide Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-09- medical services such as IBRD / 85090 Post Qualification Open - National 6,583.76 0.00 2020-05-22 Development Implementation 12 26 25 29 29 disease prevention and Selection diagnosis and treatment for animals. SCGLFZ102 / Gulin County plans to select a company to Consultant carry out product trademark Public Infrastructure and Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-03- IBRD / 85090 Post Qualification Open - National 43,891.74 0.00 2020-05-22 design and trademark Services Implementation 12 26 25 29 28 Selection registration for the cooperative. SCGLFZ103 / Gulin County Consultant plans to select a company to Public Infrastructure and Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-03- IBRD / 85090 Post Qualification Open - National 39,502.56 0.00 2020-05-22 design the packaging of the Services Implementation 12 26 25 29 28 Selection cooperative product. SCBTZ053 / Butuo County plans to select a veterinary service company to provide Consultant Integrated Value Chain Under 2017-08- 2020-06- 2020-07- 2020-08- 2020-09- 2020-12- medical services such as IBRD / 85090 Post Qualification Open - National 16,668.00 0.00 2020-05-22 Development Implementation 06 12 26 25 29 31 disease prevention and Selection diagnosis and treatment for animals. SCBTZ078 / Butuo County plans to select a cooperative Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-09- operation firm to guide the IBRD / 85090 Post Qualification Open - National 40,592.00 0.00 2020-05-22 Development Implementation 12 26 25 29 30 operation and management Selection of the cooperative. SCBTZ079 / Butuo County plans to hire a consulting service team to provide daily consulting services for Consultant Integrated Value Chain Under 2019-01- 2020-06- 2020-07- 2020-08- 2020-09- 2021-03- cooperatives in terms of IBRD / 85090 Post Qualification Open - National 91,332.00 0.00 2020-05-22 Development Implementation 06 12 26 25 29 28 standardized management, Selection production, operation, product branding, and marketing. SCBTZ080 / Butuo County plans to select an audit Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-03- company to conduct a IBRD / 85090 Post Qualification Open - National 27,061.00 0.00 2020-05-22 Development Implementation 12 26 25 29 28 financial audit of the Selection cooperative. SCXYZ2012 / Xuyong County plans to select an Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-09- audit company to conduct a IBRD / 85090 Post Qualification Open - National 21,126.76 0.00 2020-06-02 Development Implementation 18 21 12 02 01 financial audit of the Selection cooperative. SCXYFZ2001 / Xuyong County plans to select a Consultant Public Infrastructure and Pending 2020-06- 2020-07- 2020-08- 2020-09- 2020-12- company to design the IBRD / 85090 Post Qualification Open - National 12,676.06 0.00 2020-06-02 Services Implementation 23 25 20 16 31 packaging of the cooperative Selection product. SCXYFZ2003 / Xuyong Consultant County plans to select a Public Infrastructure and Pending 2020-06- 2020-08- 2020-08- 2020-09- 2020-12- IBRD / 85090 Post Qualification Open - National 19,647.89 0.00 2020-06-02 company to build and Services Implementation 23 01 26 16 31 Selection maintain the website. SCMGZ0021 / Meigu County plans to hire a consulting service team to provide daily consulting services for Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-08- 2021-05- cooperatives in terms of IBRD / 85090 Post Qualification Open - National 5,714.00 0.00 2020-06-03 Development Implementation 16 14 05 16 05 standardized management, Selection production, operation, product branding, and marketing. SCMGZ0023 / Meigu County plans to select an audit Consultant Integrated Value Chain Pending 2020-06- 2020-08- 2020-08- 2020-08- 2022-08- company to conduct a IBRD / 85090 Post Qualification Open - National 10,285.71 0.00 2020-06-03 Development Implementation 24 07 15 26 26 financial audit of the Selection cooperative. SCMGZ0024 / Meigu County plans to select a cooperative Consultant Integrated Value Chain Pending 2020-06- 2020-08- 2020-08- 2020-08- 2021-08- operation firm to guide the IBRD / 85090 Post Qualification Open - National 34,285.70 0.00 2020-06-03 Development Implementation 24 07 15 31 30 operation and management Selection of the cooperative. SCMGZ0022 / Meigu County plans to select a company to provide cooperative technical Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-07- 2020-08- 2021-08- support services, including IBRD / 85090 Post Qualification Open - National 44,571.43 0.00 2020-06-08 Development Implementation 15 16 24 09 08 agricultural planting, Selection production and cultivation techniques. SCJYZ2020-25 / Gingyang County plans to hire a consulting service team to provide daily consulting Consultant Integrated Value Chain Pending 2020-06- 2020-07- 2020-08- 2020-08- 2021-05- services for cooperatives in IBRD / 85090 Post Qualification Open - National 58,639.36 0.00 2020-06-08 Development Implementation 21 19 10 21 10 terms of standardized Selection management, production, operation, product branding, and marketing. SCJYZ2020-26 / Jinyang County plans to select an Consultant Integrated Value Chain Pending 2020-06- 2020-08- 2020-08- 2020-08- 2022-08- audit company to conduct a IBRD / 85090 Post Qualification Open - National 17,556.69 0.00 2020-06-08 Development Implementation 29 12 20 31 31 financial audit of the Selection cooperative. SCJYF2020-29 / Ginyang Consultant County plans to select a Public Infrastructure and Pending 2020-06- 2020-08- 2020-09- 2020-10- 2021-04- IBRD / 85090 Post Qualification Open - National 20,409.66 0.00 2020-06-08 company to build and Services Implementation 29 12 11 16 14 Selection maintain the website. Page 11 SCJYF2020-28 / Jinyang County plans to select a Consultant Public Infrastructure and Pending 2020-06- 2020-07- 2020-08- 2020-09- 2021-01- company to design the IBRD / 85090 Post Qualification Open - National 13,167.52 0.00 2020-06-08 Services Implementation 29 31 26 22 06 packaging of the cooperative Selection product. SCJYF2020-27 / Jinyang County plans to select a Consultant company to carry out product Public Infrastructure and Pending 2020-06- 2020-08- 2020-08- 2020-09- 2020-12- IBRD / 85090 Post Qualification Open - National 14,630.57 0.00 2020-06-08 trademark design and Services Implementation 29 05 20 02 31 Selection trademark registration for the cooperative. SCMGZ84 / Meigu County plans to select a technical support service team to help Consultant Integrated Value Chain Pending 2021-05- 2021-05- 2021-05- 2021-06- 2021-12- with daily crop management IBRD / 85090 Post Qualification Open - National 70,942.34 0.00 2021-04-30 Development Implementation 06 25 31 17 25 and carry out management Selection and protection technical training. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCMGZ61 / Veterinary Individual services for 1,178 sheep at Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 3,446.96 0.00 2019-05-01 fukang cooperative in meigu Development Implementation 06 27 20 30 Selection county SCMGZ72 / Meigu county employs financial experts to Individual guide the financial work of Public Infrastructure and Pending 2019-04- 2019-04- 2019-04- 2019-12- IBRD / 85090 Post Consultant Limited 3,511.34 0.00 2019-04-05 hongsen cooperative, Services Implementation 15 20 30 31 Selection yijiayuan cooperative and nimumogu cooperative. SCMGZ71 / Meigu county employs financial experts to Individual guide the financial work of Public Infrastructure and Pending 2019-04- 2019-04- 2019-04- 2019-12- IBRD / 85090 Post Consultant Limited 3,511.34 0.00 2019-04-05 shuse cooperative, Russian Services Implementation 15 20 30 31 Selection farming cooperative and Russian farming cooperative SCBTZ060 / Butuo county employs financial personnel Individual to guide the professional Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 cooperatives in shuizi village, Services Implementation 06 15 06 27 31 Selection dianzi village and jinai village to complete financial work SCBTZ061 / Butuo county to hire financial staff to guide Individual the village, suga village, Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 zheluo village professional Services Implementation 06 15 06 27 31 Selection cooperatives to complete the financial work SCBTZ062 / Butuo county employs financial personnel to guide the professional Individual Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- cooperatives of riqi village, IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 Services Implementation 06 15 06 27 31 sihe village and guangming Selection village to complete financial work SCBTZ063 / Butuo county employs financial staff to Individual guide labo village, zhuerku Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 village, buer village Services Implementation 06 15 06 27 31 Selection professional cooperatives to complete financial work SCBTZ064 / Butuo county to hire financial personnel to Individual guide the ya river village, hey Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 door village, long village Services Implementation 06 15 06 27 31 Selection professional cooperatives to complete the financial work SCBTZ065 / Butuo county employs financial staff to Individual guide professional Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 cooperatives in shizui village, Services Implementation 06 15 06 27 31 Selection poli village and abao village to complete financial work SCBTZ066 / Butuo county hired financial personnel Individual guiding fe villages, alberta, Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 old dove gage village, village Services Implementation 06 15 06 27 31 Selection professional cooperatives to complete financial work SCBTZ067 / Butuo county to hire financial staff to guide Individual mo this village, village, pan Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 village professional Services Implementation 06 15 06 27 31 Selection cooperatives to complete financial work SCBTZ068 / Butuo county employs financial personnel to guide the professional Individual Public Infrastructure and Under 2019-01- 2019-04- 2019-05- 2019-05- 2020-05- cooperatives in filian wu IBRD / 85090 Post Consultant Limited 5,267.01 0.00 2019-04-10 Services Implementation 06 15 06 27 31 village, mo cooperative Selection village and weizipo village to complete financial work SCMGZ62 / Veterinary Individual services for 930 sheep from Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 2,721.28 0.00 2019-05-01 huangmaogeng zhuanhe Development Implementation 06 27 20 30 Selection community, meigu county SCMGZ64 / Veterinary Individual services for 1,150 sheep at Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 3,365.03 0.00 2019-05-01 the larry cooperative in Development Implementation 06 27 20 30 Selection meigu county SCMGZ65 / Veterinary Individual services for 774 sheep at Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 2,264.81 0.00 2019-05-01 nimumogu cooperative in Development Implementation 06 27 20 30 Selection meigu county SCMGZ67 / Veterinary Individual services for 800 sheep in Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 2,340.89 0.00 2019-05-01 yijiayuan cooperative, meigu Development Implementation 06 27 20 30 Selection county SCMGZ60 / Veterinary Individual services for 1430 sheep of Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 4,184.34 0.00 2019-05-01 the Russian farming Development Implementation 06 27 20 30 Selection cooperative in meigu county SCMGZ63 / Veterinary Individual services for 3,258 sheep at Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 9,533.28 0.00 2019-05-01 huadu cooperative in meigu Development Implementation 06 27 20 30 Selection county SCMGZ66 / Veterinary Individual services for 1200 sheep in Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 3,511.33 0.00 2019-05-01 shuse cooperative in meigu Development Implementation 06 27 20 30 Selection county SCMGZ68 / Veterinary Individual services for 1,100 sheep at Integrated Value Chain Pending 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 85090 Post Consultant Limited 3,218.72 0.00 2019-05-01 yulong cooperative in meigu Development Implementation 06 27 20 30 Selection county SCMGZ69 / Meigu county employs financial experts to Individual guide the financial work of Public Infrastructure and Pending 2019-04- 2019-04- 2019-04- 2019-12- IBRD / 85090 Post Consultant Limited 3,511.34 0.00 2019-04-05 huadu cooperative, fukang Services Implementation 15 20 30 31 Selection cooperative and larry cooperative. SCMGZ70 / Meigu county employs financial experts to Individual guide the financial work of Public Infrastructure and Pending 2019-04- 2019-04- 2019-04- 2019-12- IBRD / 85090 Post Consultant Limited 3,511.34 0.00 2019-04-05 yulong cooperative, jingye Services Implementation 15 20 30 31 Selection texi cooperative and huangmaogeng cooperative SCBTZ052 / Butuo county employs professional Individual Integrated Value Chain Under 2017-08- 2019-04- 2019-05- 2019-05- 2020-05- veterinarians to provide IBRD / 85090 Post Consultant Limited 12,921.73 0.00 2019-04-10 Development Implementation 06 15 06 27 31 veterinary services for 11 Selection beef cattle breeding cooperatives SCXYZ1906 / Xuyong County employs financial personnel to guide the Individual specialized cooperatives in Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 12,352.94 0.00 2019-05-10 Dam, Tianba, Chahe, Services Implementation 12 22 30 31 Selection Shuibao, Haiya, Xiongguang and Baila Village to complete their financial work. SCXYZ1907 / Xuyong County employs financial personnel to guide Individual professional cooperatives in Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 12,352.94 0.00 2019-05-10 Xiekou, Sun Jia, Chishui, Services Implementation 12 22 30 31 Selection Shuangshan, Zhongsha, Huangping and Nanshan villages to complete financial management work. SCXYZ1908 / Xuyong County employs financial personnel to guide Individual professional cooperatives Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 12,352.94 0.00 2019-05-10 such as Liangping, Dawen, Services Implementation 12 22 30 31 Selection Songlin, Anle, Weitang, Shuibaopu Village to complete financial management work. Page 12 SCXYZ1909 / Xuyong County employs professional veterinarians to provide veterinary services for 1540 Individual beef cattle farming in 9 Integrated Value Chain Pending 2019-05- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 6,794.12 0.00 2019-05-10 professional cooperatives, Development Implementation 12 22 30 31 Selection such as Daba, Tianba, Chahe, Shuibao, Xiongguang, Baila Anle, Yantang and Shuibaopu Village. SCXYZ1910 / Xuyong County employs professional veterinarians to provide veterinary services for 1560 beef cattle farming in 10 Individual Integrated Value Chain Pending 2019-05- 2019-05- 2019-05- 2020-05- professional cooperatives, IBRD / 85090 Post Consultant Limited 6,882.35 0.00 2019-05-10 Development Implementation 12 22 30 31 including Xiekou, Sun Jia, Selection Chishui, Shuangshan, Zhongsha, Huangping, Nanshan, Liangping, Dawen and Songlin Villag SCGLZ06 / Gullin county employs a financial expert to Individual Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2020-05- guide 20 specialized IBRD / 85090 Post Consultant Limited 35,113.39 0.00 2019-05-10 Services Implementation 12 22 30 31 cooperatives to complete Selection financial work. SCGLZ07 / Gulin County employs professional veterinarians to provide Individual veterinary services to 600 Integrated Value Chain Pending 2019-05- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 2,633.50 0.00 2019-05-10 cattle from six cooperatives Development Implementation 12 22 30 31 Selection of Baijiatengyue, Shaba, Tuguan, Muxi, Longjiashan and Huamu. SCZJZ12 / Zhaojue County employs animal husbandry and veterinary doctors to provide animal husbandry and veterinary services to Individual Integrated Value Chain Pending 2019-05- 2019-05- 2019-05- 2020-05- 4125 cattle and sheep of five IBRD / 85090 Post Consultant Limited 12,132.35 0.00 2019-05-10 Development Implementation 12 22 30 31 Liangshan semi-fine wool Selection sheep cooperatives in Wanchang, Sangang, Nidi, Jiefang and Saladipo Townships. SCZJZ26 / Zhaojue County employs financial experts to Individual guide four cooperatives, Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 7,058.82 0.00 2019-05-10 Dimo, Liuqie, Sikai and Services Implementation 12 22 30 31 Selection Saladipo, to complete financial management work. SCZJZ27 / Zhaojue County employs financial experts to Individual guide the four cooperatives Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2020-05- IBRD / 85090 Post Consultant Limited 7,058.82 0.00 2019-05-10 of Nidi, Jiefang, Wanchang Services Implementation 12 22 30 31 Selection and Sangang to complete financial management work. SCJYZ-17 / Jinyang County employs financial experts to Individual guide Zhongzi and Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2019-12- IBRD / 85090 Post Consultant Limited 2,059.00 0.00 2019-05-10 Nanwashubo Cooperatives to Services Implementation 12 22 30 31 Selection complete financial management. SCJYZ-18 / Jinyang County employs financial experts to Individual Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2019-12- guide Tengxiang and IBRD / 85090 Post Consultant Limited 2,059.00 0.00 2019-05-10 Services Implementation 12 22 30 31 Benkang Cooperatives to Selection complete financial management. SCJYZ-19 / Jinyang County employs financial experts to Individual Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2019-12- guide Futai and MuNiGuEr IBRD / 85090 Post Consultant Limited 2,059.00 0.00 2019-05-10 Services Implementation 12 22 30 31 Cooperatives to complete Selection financial management. SCJYZ-20 / Jinyang County employs financial experts to Individual guide Lianqiang, Yongsheng Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2019-12- IBRD / 85090 Post Consultant Limited 3,088.00 0.00 2019-05-10 and Manulife Cooperatives to Services Implementation 12 22 30 31 Selection complete financial management. SCJYZ-21 / Jinyang County employs financial experts to Individual guide the financial Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2019-12- IBRD / 85090 Post Consultant Limited 3,088.00 0.00 2019-05-10 management work of Shida, Services Implementation 12 22 30 31 Selection Desheng and Ribugule Cooperatives. SCJYZ-22 / Jinyang County employs financial experts to Individual guide Fengnong, Shenglong Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2019-12- IBRD / 85090 Post Consultant Limited 3,088.00 0.00 2019-05-10 and Tengda Cooperatives to Services Implementation 12 22 30 31 Selection complete financial management. SCJYZ-23 / Jinyang County employs financial experts to Individual Public Infrastructure and Pending 2019-05- 2019-05- 2019-05- 2019-12- guide Jiafu and Shama IBRD / 85090 Post Consultant Limited 2,059.00 0.00 2019-05-10 Services Implementation 12 22 30 31 Cooperatives to complete Selection financial management. SCZJZ-28 / Zhaojue County plans to hire a cooperative Individual Integrated Value Chain Pending 2020-07- 2020-07- 2020-09- 2020-12- operation expert to guide the IBRD / 85090 Post Consultant Open 13,511.00 0.00 2020-05-22 Development Implementation 10 31 04 20 operation and management Selection of the cooperative. SCZJZ-36 / Zhaojue County Individual Public Infrastructure and Pending 2020-05- 2020-06- 2020-07- 2020-12- plans to hire an accountant IBRD / 85090 Post Consultant Limited 6,774.68 0.00 2020-05-22 Services Implementation 27 17 22 31 to guide financial accounting. Selection SCZJZ-33 / Zhaojue County plans to hire a cooperative Individual Integrated Value Chain Pending 2020-07- 2020-07- 2020-09- 2021-09- operation expert to guide the IBRD / 85090 Post Consultant Open 13,511.00 0.00 2020-05-22 Development Implementation 10 31 04 01 operation and management Selection of the cooperative. SCZJZ-37 / Zhaojue County Individual plans to hire a financial Public Infrastructure and Pending 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 6,774.68 0.00 2020-05-22 accountant to guide the Services Implementation 27 17 22 31 Selection cooperative's financial work. SCBTZ069 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 22 31 Selection cooperative's financial work. SCBTZ071 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 22 31 Selection cooperative's financial work. SCBTZ072 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 22 31 Selection cooperative's financial work. SCBTZ073 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 22 31 Selection cooperative's financial work. SCBTZ074 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 22 31 Selection cooperative's financial work. SCBTZ075 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 22 31 Selection cooperative's financial work. SCBTZ076 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 22 31 Selection cooperative's financial work. SCBTZ077 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 10 31 Selection cooperative's financial work. SCBTZ070 / Butuo County Individual plans to hire a financial Public Infrastructure and Under 2019-01- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,074.00 0.00 2020-05-22 accountant to guide the Services Implementation 06 27 17 22 31 Selection cooperative's financial work. SCXYZ2006 / Xuyong Individual County plans to hire a Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 11,830.99 0.00 2020-06-02 financial accountant to guide Services Implementation 07 18 23 31 Selection the cooperative's financial work. SCXYZ2007 / Xuyong Individual County plans to hire a Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 11,830.99 0.00 2020-06-02 financial accountant to guide Services Implementation 07 18 23 31 Selection the cooperative's financial work. SCXYZ2008 / Xuyong Individual County plans to hire a Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 11,830.99 0.00 2020-06-02 financial accountant to guide Services Implementation 07 18 23 31 Selection the cooperative's financial work. SCXYZ2009 / Xuyong County plans to hire a Individual Integrated Value Chain Pending 2020-07- 2020-08- 2020-08- 2022-05- cooperative operation expert IBRD / 85090 Post Consultant Open 27,042.25 0.00 2020-06-02 Development Implementation 11 01 20 20 to guide the operation and Selection management of the cooperative. SCXYZ2010 / Xuyong County plans to hire a Individual Integrated Value Chain Pending 2020-07- 2020-07- 2020-08- 2022-05- cooperative operation expert IBRD / 85090 Post Consultant Open 27,042.25 0.00 2020-06-02 Development Implementation 11 26 10 10 to guide the operation and Selection management of the cooperative. Page 13 SCXYZ2011 / Xuyong County plans to hire a Individual Integrated Value Chain Pending 2020-07- 2020-07- 2020-08- 2022-05- cooperative operation expert IBRD / 85090 Post Consultant Open 27,042.25 0.00 2020-06-02 Development Implementation 08 23 07 07 to guide the operation and Selection management of the cooperative. SCMGZ0018 / Meigu County Individual plans to hire a financial Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 8,571.00 0.00 2020-06-03 accountant to guide the Services Implementation 08 19 24 31 Selection cooperative's financial work. SCMGZ0019 / Meigu County Individual plans to hire a financial Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 5,142.00 0.00 2020-06-03 accountant to guide the Services Implementation 08 19 24 31 Selection cooperative's financial work. SCMGZ0020 / Meigu County Individual plans to hire a financial Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 3,428.00 0.00 2020-06-03 accountant to guide the Services Implementation 08 19 24 31 Selection cooperative's financial work. SCJYZ21 / Ginyang County Individual plans to hire a financial Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 588.23 0.00 2020-06-08 accountant to guide the Services Implementation 13 24 29 31 Selection cooperative's financial work. SCJYZ18 / Jinyang County Individual plans to hire a financial Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 735.29 0.00 2020-06-08 accountant to guide the Services Implementation 13 24 29 31 Selection cooperative's financial work. SCJYZ19 / Jinyang County Individual plans to hire a financial Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 588.23 0.00 2020-06-08 accountant to guide the Services Implementation 13 24 29 31 Selection cooperative's financial work. SCJYZ20 / Jinyang County Individual plans to hire a financial Public Infrastructure and Pending 2020-06- 2020-06- 2020-07- 2020-12- IBRD / 85090 Post Consultant Limited 588.23 0.00 2020-06-08 accountant to guide the Services Implementation 13 24 29 31 Selection cooperative's financial work. SCJYZ22 / Jinyang County plans to hire a cooperative Individual Integrated Value Chain Pending 2020-07- 2020-08- 2020-08- 2022-05- operation expert to guide the IBRD / 85090 Post Consultant Open 14,117.64 0.00 2020-06-08 Development Implementation 17 07 26 26 operation and management Selection of the cooperative. SCJYZ23 / Jingyang County plans to hire a cooperative Individual Integrated Value Chain Pending 2020-07- 2020-08- 2020-08- 2022-05- operation expert to guide the IBRD / 85090 Post Consultant Open 14,117.64 0.00 2020-06-08 Development Implementation 17 07 26 26 operation and management Selection of the cooperative. SCJYZ24 / Jingyang County plans to hire a cooperative Individual Integrated Value Chain Pending 2020-07- 2020-08- 2020-08- 2022-05- operation expert to guide the IBRD / 85090 Post Consultant Open 14,117.64 0.00 2020-06-08 Development Implementation 17 07 26 26 operation and management Selection of the cooperative. Page 14