PROCUREMENT PLAN (Textual Part) Project information: Mauritania Social Safety Net Project II (P171125) Project Implementation agency: Delegation Générale Taazour Date of the Procurement Plan: March 17th, 2020 Period covered by this Procurement Plan: 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable” Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Mauritania : Social Safety Net System Project II PLAN General Information Country: Mauritania 2020-03-18 Bank’s Approval Date of the Original Procurement Plan: 2023-02-20 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171125 GPN Date: Project Name: Social Safety Net System Project II Loan / Credit No: IDA / D5680, COFN / C1950 Social Safety Net System Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Document na tional de pas sation des m MR-SSNS-304769-CW-RFQ / Component 1: Updating and Single Stage - One E archés - Proc En attente d 2023-07-0 Aménagements des Bureaux IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2022-11-08 2023-01-03 nvelope essus à une 'exécution 2 RS, Coord et TK y enveloppe (D TPM ne prov enant pas de la Banque) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-178803-GO-RFB / Acquisition 9 véhiculeS (4x4) Component 1: Updating and : Lot 1 (4 pour le RS, 1 pour l Single Stage - One E En attente d' IDA / D5680 enhancing the Social Registr A posteriori Appel d'offres Open - National 0.00 2020-06-10 2020-06-15 2020-07-27 2020-08-26 2020-09-30 2021-03-29 e PFSRC et 2 pour Tekavoul) nvelope exécution y Lot 2 (1 véhicule pour le RS) Lot 3 (1 véhicule pour Tekav oul) TEK/RS/PFSRC MR-SSNS-211604-GO-RFB / Component 1: Updating and Single Stage - One E Matériel Informatique (TEK,R IDA / D5680 enhancing the Social Registr A posteriori Appel d'offres Open - National 23,939.74 Signé 2020-12-31 2021-07-08 2021-01-05 2021-02-16 2021-08-09 2021-03-18 2021-08-12 2021-04-22 2021-11-08 2021-10-19 nvelope S,PFSRC,Coord.) y MR-SSNS-211605-GO-RFQ / Component 1: Updating and Mobilier et équipements de b Single Stage - One E IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 74,363.65 Résilié 2021-01-09 2021-09-13 2021-03-06 2021-10-12 2021-09-02 ureaux (bureaux, mobiliers, t nvelope y éléphones, climatiseurs…) T EK,RS,PFSRC,Coord. MR-SSNS-211968-GO-RFQ / Component 1: Updating and Single Stage - One E En cours d'ex Consommable informatique IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2021-01-25 2021-09-13 2021-03-22 2021-09-18 nvelope écution & fournitures de bureau TEK, y RS,PFSRC,Coord MR-SSNS-211973-GO-RFQ / Component 2: Enhancing th Single Stage - One E Equipement Promotion Social IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 32,831.89 Achevé 2021-01-25 2021-03-09 2021-03-22 2021-06-23 2021-09-18 2021-08-26 nvelope e + Dialogue Familiale (form f poor households ation) TEK MR-SSNS-212002-GO-RFQ / Component 1: Updating and Single Stage - One E Kits équipes mobiles (nattes, IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 12,548.12 Signé 2021-01-25 2021-08-03 2021-03-22 2021-08-30 2021-09-18 nvelope torches, lits picots…) TEK,RS y MR-SSNS-212017-GO-RFB / Production outils de commun ication (images, brochures, s Component 1: Updating and Single Stage - One E En cours d'ex pots radio, vidéo sur les réali IDA / D5680 enhancing the Social Registr A posteriori Appel d'offres Open - National 0.00 2021-02-10 2021-09-06 2021-02-15 2021-09-30 2021-03-29 2021-04-28 2021-06-02 2021-11-29 nvelope écution sations du prog, postres, pan y neau, depliant rollup, bander ol gadgets, casquette, gilet, f oulard) TEK/RS MR-SSNS-212049-GO-RFQ / Component 4: Project Coordi Single Stage - One E IDA / D5680 A posteriori Demande de prix Limited 3,650.64 Achevé 2021-01-25 2021-08-03 2021-03-22 2021-08-19 2021-09-18 2021-08-31 Matériels de protection Covid nation and Management nvelope 19 Coord MR-SSNS-212283-GO-RFB / Component 1: Updating and Single Stage - Two E En attente d' IDA / D5680 A posteriori Appel d'offres Open - National 0.00 2021-02-22 2021-02-27 2021-04-10 2021-06-23 2021-07-28 2022-01-24 Acquisition de 2 Véhicules 4X enhancing the Social Registr nvelope exécution 4 RS/ TK y MR-SSNS-219273-GO-RFB / Acquisition 6 véhicules 4x4: Component 1: Updating and Lot 1 ( (04) véhicules 4X4 Pic Open - Internationa Single Stage - One E En attente d' IDA / D5680 enhancing the Social Registr A posteriori Appel d'offres 0.00 2021-03-17 2021-03-22 2021-05-03 2021-06-02 2021-07-07 2022-01-03 k up : 3 pour Tekavoul et 1 p l nvelope exécution y our MAOUNA) Lot 2 ( (02) vé hicules 4X4 1 pour la Coordi nation et 1 pour RS) MR-SSNS-257197-GO-RFQ / Component 4: Project Coordi Single Stage - One E En cours d'ex Acquisition et installation sys IDA / D5680 A posteriori Demande de prix Limited 0.00 2021-10-23 2021-09-16 2021-12-18 2022-06-16 nation and Management nvelope écution tème de surveillance MR-SSNS-257213-GO-RFB / Component 1: Updating and Single Stage - One E En attente d' Acquisition 03 véhicules lég IDA / D5680 enhancing the Social Registr A posteriori Appel d'offres Open - National 0.00 2021-11-28 2021-12-03 2022-01-14 2022-02-13 2022-03-20 2022-09-16 nvelope exécution ers pour service y MR-SSNS-257229-GO-RFQ / I Component 2: Enhancing th Single Stage - One E mpression des cartes de mén IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 4,688.99 Signé 2021-10-18 2021-04-21 2021-12-13 2021-06-16 2022-06-11 nvelope ages TK et ELMAOUNA f poor households MR-SSNS-257223-GO-RFQ / Component 1: Updating and Single Stage - One E IDA / D5680 A posteriori Demande de prix Limited 41,135.78 Signé 2021-10-17 2021-04-13 2021-12-12 2021-06-11 2022-06-10 Acquisition des tablettes enhancing the Social Registr nvelope y MR-SSNS-212037-GO-RFQ / Component 1: Updating and Acquisition, installation et mi Single Stage - One E IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 9,743.25 Signé 2021-01-26 2022-01-28 2021-03-23 2022-02-18 2021-09-19 se en service des équipemen nvelope y ts d’une sale de de vidéoconf érence MR-SSNS-276742-GO-RFQ / Component 1: Updating and Single Stage - One E En attente d' IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-05-03 2022-06-28 2022-12-25 Matériels de protection COVI enhancing the Social Registr nvelope exécution D 2022 y MR-SSNS-276743-GO-RFQ / Component 1: Updating and Single Stage - One E En cours d'ex Téléphone de service pour le IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2022-06-28 2022-03-14 2022-08-23 2023-02-19 nvelope écution s Directeurs y MR-SSNS-276747-GO-RFB / Component 1: Updating and Single Stage - One E En attente d' IDA / D5680 A posteriori Appel d'offres Open - National 0.00 2022-07-07 2022-07-12 2022-08-23 2022-09-22 2022-10-27 2023-04-25 Acquisition des véhicules lég enhancing the Social Registr nvelope exécution ers y Page 1 MR-SSNS-276758-GO-RFQ / Component 1: Updating and Acquisition d’un système d’a Single Stage - One E IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 Annulé 2022-06-27 2022-08-22 2023-02-18 rchivage numérique et gestio nvelope y n électronique des document s MR-SSNS-276767-GO-RFQ / Component 1: Updating and Single Stage - One E En attente d' IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-03-14 2022-05-09 2022-11-05 Système d'un contrôle d'accè enhancing the Social Registr nvelope exécution s y MR-SSNS-276896-GO-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Licences logiciels et certificat IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-03-05 2022-04-30 2022-10-27 nvelope exécution s (Toad for SQL Server, SSL) f poor households Component 2: Enhancing th MR-SSNS-276901-GO-RFQ / Single Stage - One E En attente d' IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-04-26 2022-06-21 2022-12-18 Téléphones Thuraya nvelope exécution f poor households MR-SSNS-276944-GO-DIR / I Component 4: Project Coordi Passation de marc nstallation Liaison fibre optiq IDA / D5680 A posteriori Direct 20,031.62 Signé 2022-02-15 2022-01-20 2022-02-20 2021-09-22 2022-03-27 2022-02-02 2022-09-23 nation and Management hé de gré à gré ue pour la sale de vidéo conf érence MR-SSNS-279333-GO-DIR / A Component 2: Enhancing th Passation de marc En attente d' chat des cartes de crédit (TK- IDA / D5680 e socio-economic inclusion o A posteriori Direct 0.00 2022-03-09 2022-03-14 2022-04-18 2022-10-15 hé de gré à gré exécution DF motivation couples) f poor households MR-SSNS-279334-GO-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Achat des bouteilles d'eau (r IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-03-13 2022-05-08 2022-11-04 nvelope exécution afraichissement couples) TK- f poor households DF MR-SSNS-291581-GO-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Achat des cartes de crédit (T IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-05-02 2022-06-27 2022-12-24 nvelope exécution K-DF motivation couples) f poor households MR-SSNS-304699-GO-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Acquisition KITS et Matériel d IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-10-02 2022-11-27 2023-05-26 nvelope exécution e formation et Projection DF f poor households + PS MR-SSNS-276916-GO-RFQ / Component 2: Enhancing th Single Stage - One E Kits et matériel de formation IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 Annulé 2022-04-04 2021-04-12 2022-05-30 2022-11-26 nvelope et de Projection DT + PS f poor households MR-SSNS-276583-GO-RFQ / Component 1: Updating and Kit équipes mobiles du RS et Single Stage - One E En attente d' IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2022-04-10 2022-06-05 2022-12-02 TK (moustiquaires, nattes, lit nvelope exécution y picot, torches, couvertures, e tc.) MR-SSNS-276585-GO-RFQ / Component 1: Updating and Single Stage - One E En attente d' IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-04-23 2022-06-18 2022-12-15 Fourniture de bureau et cons enhancing the Social Registr nvelope exécution ommables y MR-SSNS-276591-GO-RFQ / Component 1: Updating and Single Stage - One E IDA / D5680 A posteriori Demande de prix Limited 0.00 Annulé 2022-04-17 2022-06-12 2022-12-09 Mobilier de bureau enhancing the Social Registr nvelope y MR-SSNS-276936-GO-RFQ / Component 1: Updating and Single Stage - One E En cours d'ex Acquisition Groupe Electrogè IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2022-03-20 2022-10-14 2022-05-15 2022-11-11 nvelope écution ne Coord-TK-RS y MR-SSNS-304772-GO-RFQ / Component 1: Updating and Single Stage - One E En attente d' Acquisition du Matériels infor IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2022-11-09 2023-01-04 2023-07-03 nvelope exécution matiques RS 2022 y MR-SSNS-304773-GO-RFQ / Component 1: Updating and Single Stage - One E En attente d' Acquisition d'un Système de IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2022-08-09 2022-10-04 2023-04-02 nvelope exécution vidéo surveillance RS y MR-SSNS-304918-GO-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Acquisition des tablettes et d IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-11-06 2023-01-01 2023-06-30 nvelope exécution es portables Extension PS Juil f poor households let 2022 MR-SSNS-304971-GO-RFQ / Component 2: Enhancing th Acquisition d'un Système de Single Stage - One E En attente d' IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-11-08 2023-01-03 2023-07-02 suivi des véhicules (GPS et tr nvelope exécution f poor households aking) TK, Ext PS et Coord MR-SSNS-304978-GO-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Acquisition du Mobilier et éq IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-11-08 2023-01-03 2023-07-02 nvelope exécution uipements pour Extension TK f poor households Juillet 2022 MR-SSNS-315456-GO-RFB / Component 1: Updating and Acquisition de 12 véhicule 4X Single Stage - One E IDA / D5680 enhancing the Social Registr A posteriori Appel d'offres Open - National 0.00 Annulé 2022-09-15 2022-10-03 2022-09-20 2022-10-04 2022-11-01 2022-11-01 2022-12-01 2023-01-05 2023-07-04 4 et 5 véhicules légers de liai nvelope y son pour le PASYFIS II 2022 e n deux lots MR-SSNS-325413-GO-RFQ / Acquisition de véhicules en d Component 1: Updating and Single Stage - One E En cours d'ex eux lots : 12 véhicules 4x4 pi IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2022-11-26 2022-11-21 2023-01-21 2023-07-20 nvelope écution ckup et 5 véhicules légers de y liaison pour le PASYFIS II 202 2 MR-SSNS-339424-GO-RFQ / Component 1: Updating and Acquisition de Mobilier de bu Single Stage - One E En attente d' COFN / C1950 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2023-09-09 2023-11-04 2024-11-03 reau pour toutes les compos nvelope exécution y antes (RS, Tek, Elmaou et la Coordination) MR-SSNS-339425-GO-RFQ / Acquisition de fournitures de Component 1: Updating and Single Stage - One E En attente d' bureau et consommables inf IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2023-09-09 2023-11-04 2024-11-03 nvelope exécution ormatique pour toutes les co y mposantes (RS, Tek, El maou na et la coordination) MR-SSNS-304974-GO-RFQ / Acquisition de matériels d'ar Component 1: Updating and Single Stage - One E En attente d' chivage numérique Soft et H IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2022-09-06 2022-11-01 2023-04-30 nvelope exécution ard et de Gestion electroniqu y e de document en deux lots ( RS et Coor) 2023 MR-SSNS-339426-GO-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Acqui sition de Kits et matéri IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2023-09-09 2023-11-04 2024-11-03 nvelope exécution el de formation et de Projecti f poor households on EX, DF et PS NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-165047-NC-RFB / S ELECTION D’UN OU PLUSIEU RS OPERATEURS DE PAIEMEN Component 2: Enhancing th Open - Internationa Single Stage - One E T POUR LA REALISATION DE IDA / D5680 e socio-economic inclusion o A priori Appel d'offres 0.00 Signé 2020-03-20 2020-09-15 2020-03-25 2020-09-16 2020-05-06 2021-02-17 2020-06-05 2022-10-18 2020-07-10 2021-01-06 l nvelope TRANSFERTS MONETAIRES E f poor households LECTRONIQUES AU PROFIT D ES MENAGES PAUVRES (5 lot s) - Accord Cadre 2 ans et de mi -PNTS MR-SSNS-196334-NC-RFB / S élection d'un ou plusieurs op érateurs dans le cadre d'un d Component 3: Strengthening euxième passage de distribut the shock response system f Single Stage - One E En cours d'ex IDA / D5680 A posteriori Demande de prix Limited 0.00 2020-10-10 2020-12-05 2021-06-03 ion de cash transfer au profit or households vulnerable to nvelope écution de 210 000 ménages bénéfic climate-shocks iaires en réponse au COVID 1 9 (Financement: BAD, BM et Etat Mauritanien) MR-SSNS-211963-NC-RFB / I Component 1: Updating and Single Stage - One E En attente d' MPRESSION cartes de ménag IDA / D5680 enhancing the Social Registr A posteriori Appel d'offres Open - National 0.00 2021-02-08 2021-02-13 2021-03-27 2021-04-26 2021-05-31 2021-11-27 nvelope exécution es TEK/RS/PFSRC y MR-SSNS-211978-NC-RFQ / Component 2: Enhancing th Single Stage - One E Maintenance matériels infor IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 21,894.74 Signé 2021-01-25 2021-11-01 2021-03-22 2021-12-14 2021-09-18 nvelope matiques et de froid Coord/T f poor households EK MR-SSNS-211982-NC-RFQ / Component 1: Updating and Single Stage - One E Entretien et réparation des v IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 46,779.07 Signé 2021-01-25 2021-10-28 2021-03-22 2021-11-16 2021-09-18 nvelope éhicules TEK,RS,PFSRC,Coord y MR-SSNS-211958-NC-RFB / L Component 1: Updating and Single Stage - One E IDA / D5680 A posteriori Appel d'offres Open - National 0.00 Annulé 2021-01-05 2021-02-15 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-10-24 ocation Véhicules TEK/RS/PFS enhancing the Social Registr nvelope RC y MR-SSNS-212229-NC-RFQ / P Component 2: Enhancing th Single Stage - One E En cours d'ex roduction des émissions Radi IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2021-01-25 2021-04-22 2021-03-22 2021-09-18 nvelope écution o TEK f poor households MR-SSNS-212285-GO-RFQ / Component 1: Updating and Single Stage - One E Location de Véhicules (Contr IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 Annulé 2021-01-31 2021-03-28 2021-09-24 nvelope at de 3mois) TEK Coord RS y MR-SSNS-218651-NC-DIR / L Component 1: Updating and ocation de véhicules pour le Passation de marc En cours d'ex IDA / D5680 enhancing the Social Registr A priori Direct 0.00 2021-02-10 2021-03-10 2021-02-15 2022-09-08 2021-03-22 2021-09-18 PASyFIS (contrat de 3 mois r hé de gré à gré écution y enouvelable 1 fois) MR-SSNS-275308-NC-DIR / U Component 1: Updating and n Accord cadre de 24 mois p Passation de marc IDA / D5680 enhancing the Social Registr A posteriori Direct 558,806.00 Signé 2022-01-27 2022-01-25 2022-02-01 2022-02-03 2022-03-08 2022-02-22 2022-09-04 our la location de véhicules 2 hé de gré à gré y 022 par Entente Directe MR-SSNS-276588-NC-RFQ / Component 1: Updating and Single Stage - One E En cours d'ex IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-04-20 2021-10-28 2022-06-15 2022-12-12 Entretien véhicules enhancing the Social Registr nvelope écution y MR-SSNS-276898-NC-RFQ / P Component 2: Enhancing th Single Stage - One E En attente d' roduction épisodes radio Tek IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-03-28 2022-05-23 2022-11-19 nvelope exécution avoul f poor households MR-SSNS-276904-NC-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Maintenance Matériel inform IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2022-03-14 2022-05-09 2022-11-05 nvelope exécution atique TK f poor households MR-SSNS-276918-NC-RFQ / F Component 3: Strengthening ilm vidéo sur le circuit de mis the shock response system f Single Stage - One E En attente d' IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-04-24 2022-06-19 2022-12-16 e en œuvre et fonctionneme or households vulnerable to nvelope exécution nt des organes du DCAN /EL climate-shocks MAOUNA MR-SSNS-276926-NC-RFQ / Component 4: Project Coordi Single Stage - One E En cours d'ex Maintenance Matériel inform IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-02-28 2021-10-27 2022-04-25 2022-10-22 nation and Management nvelope écution atique et froids nouveaux bur eau / Coord MR-SSNS-276929-NC-RFQ / Component 4: Project Coordi Single Stage - One E En attente d' Contrat de nettoyage nouvea IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-03-05 2022-04-30 2022-10-27 nation and Management nvelope exécution u local pour la coordination MR-SSNS-276932-NC-RFQ / Component 4: Project Coordi Single Stage - One E En attente d' Contrat de maintenance de l IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-03-01 2022-04-26 2022-10-23 nation and Management nvelope exécution a salle vidéo conférence MR-SSNS-276939-NC-RFQ / Component 4: Project Coordi Single Stage - One E Maintenance Groupes Electro IDA / D5680 A posteriori Demande de prix Limited 0.00 Annulé 2022-09-20 2022-11-15 2023-05-14 nation and Management nvelope gènes/ Coord MR-SSNS-276941-NC-RFQ / Component 4: Project Coordi Single Stage - One E En attente d' IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-04-24 2022-06-19 2022-12-16 Maintenance Système de sur nation and Management nvelope exécution veillance MR-SSNS-276950-NC-DIR / C Component 2: Enhancing th ontrat clientèle ED pour l’imp Passation de marc IDA / D5680 e socio-economic inclusion o A posteriori Direct 77,681.00 Signé 2022-02-07 2022-02-07 2022-02-12 2022-02-04 2022-03-19 2022-02-09 2022-09-15 ression des cartes de ménag hé de gré à gré f poor households e du TK-PASyFiS II. MR-SSNS-276933-GO-DIR / A Component 4: Project Coordi Passation de marc En attente d' ssistance Technique Logiciel IDA / D5680 A posteriori Direct 0.00 2022-04-20 2022-04-25 2022-05-30 2022-11-26 nation and Management hé de gré à gré exécution TOMPRO (Multi sites, Multi pr ojets) MR-SSNS-276586-NC-RFQ / Component 1: Updating and Single Stage - One E En attente d' IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-04-27 2022-06-22 2022-12-19 Réparation des véhicules enhancing the Social Registr nvelope exécution y MR-SSNS-304768-NC-RFQ / Component 1: Updating and Single Stage - One E En attente d' IDA / D5680 A posteriori Demande de prix Limited 0.00 2022-09-06 2022-11-01 2023-04-30 Nettoyage local RS enhancing the Social Registr nvelope exécution y MR-SSNS-304838-NC-RFQ / Component 2: Enhancing th Single Stage - One E Nettoyage nouveau local de IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 Annulé 2022-09-07 2022-11-02 2023-05-01 nvelope TEKAVOUL1 Juillet 2022 f poor households Page 3 MR-SSNS-304979-NC-RFB / R ecrutement des operateurs d Component 2: Enhancing th e payement 2023-2025 POU Open - Internationa Single Stage - One E En cours d'ex IDA / D5680 e socio-economic inclusion o A priori Appel d'offres 0.00 2022-08-05 2022-10-26 2022-08-10 2023-02-06 2022-09-21 2022-10-21 2022-11-25 2023-05-24 R LA REALISATION DE TRANS l nvelope écution f poor households FERTS MONETAIRES ELECTR ONIQUES AU PROFIT DES ME NAGES PAUVRES (5 Lots) MR-SSNS-322727-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Single Stage - One E IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 Annulé 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Ouest (2 744 ménages bénéficiaires) MR-SSNS-322728-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Single Stage - One E IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 Annulé 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Nord (4 199 ménages b énéficiaires). MR-SSNS-322729-NC-RFQ / Recrutement d’un opérateur de paiement pour la réalisati Component 2: Enhancing th on de transferts monétaires Single Stage - One E IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 Annulé 2022-11-19 2023-01-21 2025-07-29 électroniques par le PASyFiS nvelope f poor households II au profit des ménages pau vres dans la wilaya de Nouak chott Sud (7 220 ménages bé néficiaires). MR-SSNS-339433-NC-RFQ / Component 1: Updating and Selection d'un prestataire de Single Stage - One E En attente d' IDA / D5680 enhancing the Social Registr A posteriori Demande de prix Limited 0.00 2023-06-10 2023-08-05 2024-08-04 services pour le nettoyage d nvelope exécution y e locaux : RS, TEK et Coordin ation MR-SSNS-339440-NC-RFQ / Component 4: Project Coordi Single Stage - One E En attente d' Contrat de maintenance de l COFN / C1950 A posteriori Demande de prix Limited 0.00 2023-11-06 2024-01-01 2024-12-31 nation and Management nvelope exécution a salle vidéo conférence Coor dination MR-SSNS-339441-NC-RFQ / Component 4: Project Coordi Single Stage - One E En attente d' Maintenance Système de sur IDA / D5680 A posteriori Demande de prix Limited 0.00 2023-09-09 2023-11-04 2024-11-03 nation and Management nvelope exécution veillance, RS, Tek et la Coord ination MR-SSNS-339443-NC-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Maintenance materiel inform IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2023-04-01 2023-05-27 2023-07-02 nvelope exécution atique et froids (Tek et Coord f poor households ination) MR-SSNS-339683-NC-RFQ / Component 2: Enhancing th Single Stage - One E En attente d' Medias (Production et diffusi IDA / D5680 e socio-economic inclusion o A posteriori Demande de prix Limited 0.00 2023-02-25 2023-04-22 2024-04-21 nvelope exécution on audiovisuelle) f poor households MR-SSNS-342207-NC-RFB / S élection d’un ou Plusieurs Op erateur des Paiements Mobil Component 2: Enhancing th es dans le cadre de réalisatio Single Stage - One E En attente d' IDA / D5680 e socio-economic inclusion o A posteriori Appel d'offres Open - National 0.00 2023-02-20 2023-02-25 2023-03-18 2023-04-01 2023-04-18 2025-09-30 n des transferts monétaires a nvelope exécution f poor households u profit du ménages inscrit (1 4 193 ménages) dans les Wil ayas de Nouakchott Nord, Su d et Ouest, en trois (03) lots MR-SSNS-342246-NC-DIR / C Component 4: Project Coordi Passation de marc En attente d' ontrat de maintenace du Sys IDA / D5680 A posteriori Direct - National 0.00 2023-03-27 2023-04-01 2023-05-06 2024-05-05 nation and Management hé de gré à gré exécution teme TOMPRO CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-196264-CS-LCS / A uditeur Externe pour les exer Component 4: Project Coordi Sélection au moin Open - Internationa En cours d'exécut IDA / D5680 A priori 0.00 2020-09-28 2020-09-25 2020-10-19 2020-10-13 2020-12-02 2021-01-19 2020-12-30 2021-03-09 2021-01-29 2021-06-15 2021-03-05 2021-04-09 2021-10-06 cices 2020, 2021 et 2022 - U nation and Management dre coût l ion nité de Coordination MR-SSNS-212039-CS-CQS / Développement d’une API d’ Component 1: Updating and Sélection fondée s accès externe et d’un systèm Open - Internationa IDA / D5680 enhancing the Social Registr A posteriori ur les qualification 0.00 Annulé 2021-02-15 2021-03-08 2021-04-21 2021-05-21 2021-06-25 2021-12-22 e de collecte des retours et d l y s des consultants es activités des utilisateurs d es données du Registre socia l RS MR-SSNS-212041-CS-CQS / Création d'une plateforme w eb pour l'accès et la gestion Component 1: Updating and Sélection fondée s sécurisées de données ména IDA / D5680 enhancing the Social Registr A posteriori ur les qualification Open - National 0.00 Annulé 2021-02-17 2021-03-10 2021-04-23 2021-05-23 2021-06-27 2021-12-24 ges inscrits (Développement y s des consultants d’une interface et tableau de bord dynamique des donnée s du registre social) RS MR-SSNS-212042-CS-CQS / Component 1: Updating and Sélection fondée s Analyse des profils ménages IDA / D5680 enhancing the Social Registr A posteriori ur les qualification Open - National 0.00 Annulé 2021-02-23 2021-03-16 2021-04-29 2021-05-29 2021-07-03 2021-12-30 enregistrés dans la base de d y s des consultants onnées RS MR-SSNS-212044-CS-CQS / Component 1: Updating and Sélection fondée s Création d'un système de gé En attente d'exéc IDA / D5680 enhancing the Social Registr A posteriori ur les qualification Open - National 0.00 2021-03-01 2021-03-22 2021-05-05 2021-06-04 2021-07-09 2022-01-05 nération et de lecture autom ution y s des consultants atique des cartes de ménage s RS MR-SSNS-211981-CS-CQS / T Sélection fondée s Component 4: Project Coordi raduction de documents du P IDA / D5680 A posteriori ur les qualification Open - National 0.00 Annulé 2021-01-20 2021-02-10 2021-03-26 2021-04-25 2021-05-30 2021-11-26 nation and Management aSyFiS II Coord. s des consultants MR-SSNS-219081-CS-CQS / Component 2: Enhancing th Sélection fondée s En cours d'exécut Bureau pour l'élaboration de IDA / D5680 e socio-economic inclusion o A posteriori ur les qualification Open - National 0.00 2021-02-22 2021-03-15 2021-03-15 2021-04-28 2021-03-09 2021-05-28 2022-04-22 2021-07-02 2021-12-29 ion l'enquête de suivi Spotcheck f poor households s des consultants du PASYFIS II MR-SSNS-276762-CS-CQS / Component 1: Updating and Sélection fondée s En attente d'exéc Analyse des profils ménages IDA / D5680 enhancing the Social Registr A posteriori ur les qualification Open - National 0.00 2022-07-07 2022-07-28 2022-09-10 2022-10-10 2022-11-14 2023-05-13 ution enregistrés dans la base de d y s des consultants onnées RS Page 4 MR-SSNS-276764-CS-CQS / Création d'une plateforme w eb pour l'accès et la gestion Component 1: Updating and Sélection fondée s En cours d'exécut sécurisées de données ména IDA / D5680 enhancing the Social Registr A posteriori ur les qualification Open - National 0.00 2022-04-29 2022-06-30 2022-05-20 2022-08-29 2022-07-03 2022-08-21 2022-08-02 2022-09-05 2022-09-06 2023-03-05 ion ges inscrits (Développement y s des consultants d’une interface et tableau de bord dynamique des donnée s du registre social) MR-SSNS-266009-CS-QCBS / Recrutement des structures d’accompagnement AGR pou Component 2: Enhancing th Sélection fondée s r la mise en œuvre du progra En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori ur la qualité et le Open - National 0.00 2022-01-03 2021-12-13 2022-01-24 2022-03-09 2022-07-28 2022-04-06 2022-09-06 2022-05-06 2022-10-17 2022-06-10 2022-10-31 2022-07-15 2023-07-15 mme d’accompagnement de ion f poor households coût s ménages bénéficiaires du p aquet de services d’inclusion économique dans le cadre de la sous composante 2.2. du P ASyFiSII Sélection fondée s MR-SSNS-292496-CS-CQS / Component 4: Project Coordi En cours d'exécut IDA / D5680 A posteriori ur les qualification Open - National 0.00 2022-03-10 2022-04-04 2022-03-31 2022-05-14 2022-08-15 2022-06-13 2022-08-29 2022-07-18 2023-01-14 Audit RH /Coord nation and Management ion s des consultants MR-SSNS-276923-CS-QCBS / Sélection fondée s Component 4: Project Coordi En cours d'exécut Audit Protection des données IDA / D5680 A posteriori ur la qualité et le Open - National 0.00 2022-02-14 2022-07-14 2022-03-07 2022-08-23 2022-04-20 2022-05-18 2022-06-17 2022-07-22 2022-08-26 2023-08-26 nation and Management ion et sécurité des systèmes coût MR-SSNS-276765-CS-CQS / Développement d’une API d’ Component 1: Updating and Sélection fondée s accès externe et d’un systèm En attente d'exéc IDA / D5680 enhancing the Social Registr A posteriori ur les qualification Open - National 0.00 2023-04-28 2023-05-19 2023-07-02 2023-08-01 2023-09-05 2024-03-03 e de collecte des retours et d ution y s des consultants es activités des utilisateurs d es données du Registre socia l MR-SSNS-339431-CS-CQS / S ÉLECTION D’UN CONSULTAN Component 3: Strengthening Sélection fondée s T (FIRME) INFORMATIQUE / D the shock response system f En attente d'exéc IDA / D5680 A posteriori ur les qualification Open - National 0.00 2023-02-20 2023-03-13 2023-04-26 2023-05-26 2023-06-30 2023-12-27 ÉVELOPPEUR or households vulnerable to ution s des consultants INTERNATIONAL POUR LE DÉ climate-shocks VELOPPEMENT DE LA PLATEF ORME D’INFORMATION DE L’ OSA MR-SSNS-212022-CS-CQS / Component 1: Updating and Sélection fondée s Acquisition d’un système d’a IDA / D5680 enhancing the Social Registr A posteriori ur les qualification Open - National 0.00 Annulé 2021-02-08 2021-03-01 2021-04-14 2021-05-14 2021-06-18 2021-12-15 rchivage numérique et gestio y s des consultants n elecronique des documents RS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-SSNS-199379-CS-CDS / E Component 2: Enhancing th Sélection de cons nquête d'Evaluation d'Impact IDA / D5680 e socio-economic inclusion o A priori ultants par entent Direct 449,184.00 Signé 2020-10-13 2020-10-13 2020-10-23 2019-11-12 2020-12-27 2020-11-09 2021-06-25 (midline) f poor households e directe MR-SSNS-212051-CS-INDV / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-16 2021-04-06 2021-04-27 2021-06-01 2021-11-28 Secretaire Coord nation and Management ution MR-SSNS-212052-CS-INDV / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-10 2021-03-31 2021-04-21 2021-05-26 2021-11-22 Assistant SE (02) Coord nation and Management ution MR-SSNS-212057-CS-INDV / Component 2: Enhancing th En attente d'exéc 2 Facilitateurs/trices Dialogu IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-02-18 2021-04-08 2021-04-29 2021-06-03 2021-11-30 ution e Familiale TEK f poor households MR-SSNS-212061-CS-INDV / 7 superviseurs pour les Moug Component 2: Enhancing th En attente d'exéc hataas du Hodh Chargui ( Ti IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-02-02 2021-03-23 2021-04-13 2021-05-18 2021-11-14 ution mbedra, Nema, Bassiknou, N' f poor households Beiket Lehwach, Oualata, Am ourj, Djiguenni) TEK MR-SSNS-212064-CS-INDV / 13 animateurs (2 à Timbedra Component 2: Enhancing th En attente d'exéc , 2 à Nema, 1 à Bassiknou, 1 IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-03-09 2021-04-27 2021-05-18 2021-06-22 2021-12-19 ution à N'Beiket Lehwach, 1 à Oula f poor households ta, 3 à Amourj et 3 à Djiguen ni) TEK MR-SSNS-212221-CS-INDV / Component 2: Enhancing th En cours d'exécut 12 Enquêteurs de suivi spot c IDA / D5680 e socio-economic inclusion o A posteriori Individuel Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 ion heck T4 2020, et T1/T2/T3 20 f poor households 21 TEK MR-SSNS-212231-CS-INDV / Component 2: Enhancing th En attente d'exéc Traducteur pour l'unité Dialo IDA / D5680 e socio-economic inclusion o A posteriori Individuel Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 ution gue et Ressources Familiales f poor households TEK MR-SSNS-212233-CS-INDV / Component 2: Enhancing th En attente d'exéc Prestation graphiste pour ad IDA / D5680 e socio-economic inclusion o A posteriori Individuel Limited 0.00 2021-03-30 2021-04-04 2021-04-25 2021-05-30 2021-11-26 ution aptation du manuel (dessin; f poor households graphiques) TEK MR-SSNS-212241-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-01-20 2020-04-10 2021-03-10 2021-02-24 2021-03-31 2021-03-11 2021-05-05 2021-11-01 Aide comptable Coord nation and Management ion MR-SSNS-212244-CS-INDV / Component 1: Updating and En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-01-20 2021-05-18 2021-03-10 2021-09-06 2021-03-31 2021-09-06 2021-05-05 2021-11-01 Assistant Communication RS enhancing the Social Registr ion y MR-SSNS-212245-CS-INDV / Component 1: Updating and En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-01-20 2021-05-18 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Assistant archivage RS enhancing the Social Registr ion y Component 2: Enhancing th MR-SSNS-212284-CS-INDV / En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 Animateur Teintan TK ution f poor households MR-SSNS-212004-CS-INDV / Component 4: Project Coordi En attente d'exéc Consultant chargé de la gesti IDA / D5680 A posteriori Individuel Limited 0.00 2021-02-16 2021-02-21 2021-03-14 2021-04-18 2021-10-15 nation and Management ution on de l'infrastructure informa tique Coord MR-SSNS-212046-CS-INDV / Component 1: Updating and En cours d'exécut Responsable Administratif et IDA / D5680 enhancing the Social Registr A priori Individuel Open 0.00 2021-02-08 2021-02-17 2021-03-29 2021-03-30 2021-04-19 2021-04-15 2021-05-24 2021-11-20 ion Moyens Généraux Coordinati y on Page 5 MR-SSNS-212236-CS-INDV / Component 2: Enhancing th En attente d'exéc Responsable Promotion Socia IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-01-04 2021-02-22 2021-03-15 2021-04-19 2021-10-16 ution le TEK. f poor households MR-SSNS-212237-CS-INDV / Component 2: Enhancing th En cours d'exécut Responsable Développement IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-01-20 2021-06-02 2021-03-10 2021-03-31 2021-05-05 2021-11-01 ion Plateforme TEK f poor households MR-SSNS-212238-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A priori Individuel Open 0.00 2021-01-20 2021-03-25 2021-03-10 2021-03-31 2021-05-05 2021-11-01 Expert Point Focal Bassiknou nation and Management ion Coord MR-SSNS-212287-CS-CDS / E Component 1: Updating and Sélection de cons En attente d'exéc xpert informatique et base d IDA / D5680 enhancing the Social Registr A posteriori ultants par entent Direct 0.00 2021-01-13 2021-01-23 2021-03-29 2021-09-25 ution e données RS y e directe Component 1: Updating and Sélection de cons MR-SSNS-212288-CS-CDS / E En attente d'exéc IDA / D5680 enhancing the Social Registr A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 xpert mobilisation sociale RS ution y e directe MR-SSNS-212228-CS-INDV / Component 2: Enhancing th En attente d'exéc Production films primoadopta IDA / D5680 e socio-economic inclusion o A posteriori Individuel Direct 0.00 2021-01-20 2021-01-30 2021-02-20 2021-03-27 2021-09-23 ution nts TEK f poor households MR-SSNS-212289-CS-CDS / E Component 1: Updating and Sélection de cons En attente d'exéc xpert Collecte de Données R IDA / D5680 enhancing the Social Registr A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution S y e directe MR-SSNS-212290-CS-CDS / Component 1: Updating and Sélection de cons En attente d'exéc Gestionnaire / médiateur récl IDA / D5680 enhancing the Social Registr A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution amations RS y e directe Component 1: Updating and Sélection de cons MR-SSNS-212291-CS-CDS / En attente d'exéc IDA / D5680 enhancing the Social Registr A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistant administratif RS ution y e directe MR-SSNS-212292-CS-CDS / Component 1: Updating and Sélection de cons En attente d'exéc Assistant informatique et ba IDA / D5680 enhancing the Social Registr A posteriori ultants par entent 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution se de données RS y e directe Component 1: Updating and Sélection de cons MR-SSNS-212296-CS-CDS / S En attente d'exéc IDA / D5680 enhancing the Social Registr A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ecrétaire (1) RS ution y e directe MR-SSNS-212298-CS-CDS / Component 2: Enhancing th Sélection de cons En attente d'exéc Coordinateur du programme IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution transferts sociaux TK f poor households e directe MR-SSNS-212299-CS-CDS / Component 2: Enhancing th Sélection de cons En attente d'exéc Responsable supervision pai IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution ements TK f poor households e directe MR-SSNS-212300-CS-CDS / Component 2: Enhancing th Sélection de cons En attente d'exéc Responsable du système d'in IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution formation TK f poor households e directe MR-SSNS-212302-CS-CDS / Component 2: Enhancing th Sélection de cons En attente d'exéc Responsable promotion dial IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution ogue et Ressource Familiale f poor households e directe TK MR-SSNS-212306-CS-CDS / Component 2: Enhancing th Sélection de cons En attente d'exéc Gestionnaire des réclamation IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution s TEK f poor households e directe Component 2: Enhancing th Sélection de cons MR-SSNS-212307-CS-CDS / S En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ecrétaire TK ution f poor households e directe MR-SSNS-212309-CS-CDS / S Sélection de cons Component 4: Project Coordi En attente d'exéc pécialiste en passation des m IDA / D5680 A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 nation and Management ution archés Coord e directe MR-SSNS-212235-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A priori Individuel Limited 0.00 2021-01-20 2021-03-05 2021-01-25 2021-03-11 2021-02-15 2021-03-25 2021-03-22 2021-09-18 Responsable Communication nation and Management ion Coord. MR-SSNS-212303-CS-CDS / Component 2: Enhancing th Sélection de cons En attente d'exéc Adjoint au RSI Developpeme IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 ution nt SI TK f poor households e directe Component 2: Enhancing th Sélection de cons MR-SSNS-212304-CS-CDS / En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Adjoint au Resp PS TK ution f poor households e directe Component 2: Enhancing th Sélection de cons MR-SSNS-212305-CS-CDS / En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Assistante de DirectionTK ution f poor households e directe Sélection de cons MR-SSNS-212310-CS-CDS / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Auditeur interne Coord nation and Management ution e directe MR-SSNS-212311-CS-CDS / Sélection de cons Component 4: Project Coordi En cours d'exécut Responsable Suivi Evaluation IDA / D5680 A posteriori ultants par entent Direct 0.00 2021-01-12 2021-11-09 2021-01-22 2021-03-28 2021-09-24 nation and Management ion Coor e directe MR-SSNS-212312-CS-CDS / Sélection de cons Component 4: Project Coordi En attente d'exéc Responsable de communicati IDA / D5680 A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 nation and Management ution on Coor e directe MR-SSNS-212313-CS-CDS / Sélection de cons Component 4: Project Coordi En attente d'exéc Assistant Comptable et Finan IDA / D5680 A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 nation and Management ution cier Coord e directe MR-SSNS-212314-CS-CDS / Sélection de cons Component 4: Project Coordi En attente d'exéc Assistant Moyens Généraux e IDA / D5680 A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 nation and Management ution t logistique Coord e directe Sélection de cons MR-SSNS-212315-CS-CDS / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori ultants par entent Direct 0.00 2021-01-05 2021-01-15 2021-03-21 2021-09-17 Assistant RH Coord nation and Management ution e directe Page 6 Sélection de cons MR-SSNS-212316-CS-CDS / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori ultants par entent Direct 0.00 2021-01-12 2021-01-22 2021-03-28 2021-09-24 Consultant informatique Coor nation and Management ution e directe MR-SSNS-219094-CS-INDV / Component 3: Strengthening Consultant international pour the shock response system f En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-26 2021-04-16 2021-05-07 2021-06-11 2021-12-08 la mise en place de la stratég or households vulnerable to ution ie de financement de la répo climate-shocks nse MR-SSNS-219102-CS-INDV / Component 3: Strengthening Consultant National pour la the shock response system f En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 mise en place de la stratégie or households vulnerable to ution de financement de la répons climate-shocks e MR-SSNS-219204-CS-INDV / Component 2: Enhancing th En cours d'exécut Illustrateur pour l'unité Dialo IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-02-25 2021-05-22 2021-04-15 2021-05-06 2021-06-10 2021-12-07 ion gue et Ressources Familiales f poor households MR-SSNS-219206-CS-INDV / Component 1: Updating and En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Assistant SIG RS enhancing the Social Registr ution y MR-SSNS-219207-CS-INDV / Component 1: Updating and En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-04-14 2021-05-05 2021-06-09 2021-12-06 2 Superviseurs mobilisation s enhancing the Social Registr ution ociale y Component 3: Strengthening MR-SSNS-219213-CS-INDV / the shock response system f En cours d'exécut Expert en sécurité alimentair IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-07-26 2021-04-14 2021-11-05 2021-05-05 2021-11-05 2021-06-09 2021-12-06 or households vulnerable to ion e climate-shocks Component 3: Strengthening MR-SSNS-219215-CS-INDV / the shock response system f En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Coordinateur de la Réponse or households vulnerable to ution climate-shocks Component 3: Strengthening MR-SSNS-219216-CS-INDV / the shock response system f En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Amélioration du site Web or households vulnerable to ution climate-shocks MR-SSNS-219256-CS-INDV / Component 2: Enhancing th En attente d'exéc Responsable appui à l’enrôle IDA / D5680 e socio-economic inclusion o A posteriori Individuel Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 ution ment à l'Etat civil f poor households MR-SSNS-219258-CS-INDV / Component 2: Enhancing th En attente d'exéc Responsable mesure inclusio IDA / D5680 e socio-economic inclusion o A posteriori Individuel Direct 0.00 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 ution n économique f poor households MR-SSNS-219261-CS-INDV / Component 2: Enhancing th En cours d'exécut 1 adjoint au RSI Base de don IDA / D5680 e socio-economic inclusion o A posteriori Individuel Direct 0.00 2021-12-16 2020-04-10 2021-12-26 2022-01-16 2022-02-20 2022-08-19 ion nées f poor households Component 2: Enhancing th MR-SSNS-219264-CS-INDV / En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori Individuel Direct 0.00 2021-12-13 2021-12-23 2022-01-13 2022-02-17 2022-08-16 Adjoint au Resp PS ution f poor households MR-SSNS-219266-CS-INDV / Component 2: Enhancing th En attente d'exéc Adjoint au Resp paiement (0 IDA / D5680 e socio-economic inclusion o A posteriori Individuel Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 ution 2) f poor households MR-SSNS-219268-CS-INDV / Component 2: Enhancing th 6 Facilitateurs "promotion di IDA / D5680 e socio-economic inclusion o A posteriori Individuel Direct 0.00 Annulé 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 alogue familial" f poor households MR-SSNS-219269-CS-INDV / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori Individuel Direct 0.00 2021-12-15 2021-12-25 2022-01-15 2022-02-19 2022-08-18 Responsable Financier et Co nation and Management ution mptable MR-SSNS-219270-CS-INDV / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori Individuel Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 Responsable Social et genre nation and Management ution MR-SSNS-219271-CS-INDV / Component 4: Project Coordi IDA / D5680 A posteriori Individuel Direct 0.00 Annulé 2021-12-08 2021-12-18 2022-01-08 2022-02-12 2022-08-11 Assistant Passation des Marc nation and Management hés MR-SSNS-219272-CS-INDV / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori Individuel Direct 0.00 2021-12-16 2021-12-26 2022-01-16 2022-02-20 2022-08-19 Assistant communication nation and Management ution MR-SSNS-254473-CS-CDS / Conception et la production d Component 1: Updating and Sélection de cons es cartes graphiques pour les IDA / D5680 enhancing the Social Registr A posteriori ultants par entent Direct 22,211.81 Signé 2021-09-22 2021-09-24 2021-10-02 2021-09-30 2021-12-06 2021-10-13 2022-06-04 districts de recensement des y e directe neuves communes de Nouak chott Component 2: Enhancing th MR-SSNS-254598-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-09-22 2021-09-12 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Animateur Tintane ion f poor households MR-SSNS-254603-CS-INDV / Component 1: Updating and En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-09-22 2021-09-21 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Deux 2 animateurs pour le R enhancing the Social Registr ion S y MR-SSNS-254606-CS-INDV / Component 1: Updating and En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-09-22 2021-11-10 2021-12-01 2022-01-05 2022-07-04 Assistant RSI enhancing the Social Registr ution y Component 2: Enhancing th MR-SSNS-254613-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-09-27 2021-09-29 2021-11-15 2021-12-06 2022-01-10 2022-07-09 Superviseur Koubeni ion f poor households Component 3: Strengthening MR-SSNS-219214-CS-INDV / the shock response system f En cours d'exécut Assistant technique du progr IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-06-24 2021-04-15 2021-10-14 2021-05-06 2021-10-14 2021-06-10 2021-12-07 or households vulnerable to ion amme ELMAOUNA climate-shocks MR-SSNS-219217-CS-INDV / Component 1: Updating and En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-05-18 2021-04-14 2021-05-05 2021-06-09 2021-12-06 Assistant mise à jour du RS enhancing the Social Registr ion y MR-SSNS-219103-CS-INDV / Component 3: Strengthening Consultant International App the shock response system f En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 ui à la mise en place d'un ca or households vulnerable to ution dre permanent de réponse a climate-shocks ux chocs Page 7 Component 3: Strengthening MR-SSNS-219193-CS-INDV / the shock response system f En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-02-24 2021-01-28 2021-04-14 2021-04-20 2021-05-05 2021-04-20 2021-06-09 2021-12-06 Statisticien junior OSA or households vulnerable to ion climate-shocks MR-SSNS-254621-CS-CDS / Component 2: Enhancing th Sélection de cons Contractualisation avec la Fir IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 Annulé 2021-09-22 2021-10-28 2021-10-02 2021-12-06 2022-06-04 me internationale AGR Inclus f poor households e directe ion Economique Tekavoul Component 3: Strengthening MR-SSNS-257123-CS-INDV / the shock response system f En cours d'exécut Assistant chargé de la mise e IDA / D5680 A posteriori Individuel Open 0.00 2021-10-11 2021-07-13 2021-11-29 2021-12-20 2022-01-24 2022-07-23 or households vulnerable to ion n œuvre du dispositif climate-shocks Component 3: Strengthening MR-SSNS-257215-CS-INDV / the shock response system f En cours d'exécut Informaticien développeur (O IDA / D5680 A posteriori Individuel Open 0.00 2021-12-16 2022-02-08 2022-02-03 2022-02-24 2022-03-31 2022-09-27 or households vulnerable to ion SA) climate-shocks Component 2: Enhancing th MR-SSNS-257227-CS-INDV / En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-10-13 2021-12-01 2021-12-22 2022-01-26 2022-07-25 3 Animateur Kaédi ution f poor households MR-SSNS-257218-CS-INDV / Component 1: Updating and En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-10-12 2021-04-22 2021-11-30 2021-10-14 2021-12-21 2021-10-14 2022-01-25 2022-07-24 Responsable de qualité RS enhancing the Social Registr ion y MR-SSNS-257210-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-11-17 2021-11-04 2022-01-05 2022-01-26 2022-03-02 2022-08-29 Responsable SE nation and Management ion MR-SSNS-257195-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-10-09 2021-07-30 2021-11-27 2021-11-16 2021-12-18 2021-11-30 2022-01-22 2022-07-21 Consultant Formateur NES nation and Management ion Component 2: Enhancing th MR-SSNS-260197-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-10-28 2021-10-27 2021-12-16 2022-02-08 2022-01-06 2022-02-24 2022-02-10 2022-08-09 1 Facilitateur H ion f poor households Component 2: Enhancing th MR-SSNS-260198-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-10-28 2021-10-27 2021-12-16 2022-02-11 2022-01-06 2022-02-24 2022-02-10 2022-08-09 3 Facilitateurs P ion f poor households MR-SSNS-263939-CS-INDV / Component 2: Enhancing th En cours d'exécut 1 Gestionnaire de Réclamatio IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-02-14 2022-01-28 2022-02-14 2022-03-04 2022-08-31 ion n TEKAVOUL f poor households MR-SSNS-263941-CS-INDV / Component 2: Enhancing th En cours d'exécut Assistant Responsable Systè IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-02-11 2022-01-28 2022-02-25 2022-03-04 2022-08-31 ion me d'Information TEKAVOUL f poor households MR-SSNS-263945-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-11-19 2021-11-04 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Spécialiste Passation de Marc nation and Management ion hés Component 2: Enhancing th MR-SSNS-263947-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Superviseur Ghabou ion f poor households Component 2: Enhancing th MR-SSNS-263949-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Superviseur Sélibaby ion f poor households MR-SSNS-264045-CS-CDS / Component 2: Enhancing th Sélection de cons Contractualisation avec la Fir En cours d'exame IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 2021-12-02 2022-12-21 2021-12-12 2023-01-26 2022-02-15 2022-08-14 me internationale AGR Inclus n f poor households e directe ion Economique Tekavoul Component 2: Enhancing th MR-SSNS-264051-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2021-11-26 2021-11-15 2022-01-14 2022-02-04 2022-03-11 2022-09-07 2 Animateurs Selibaby ion f poor households MR-SSNS-264052-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Responsable Financier et Co nation and Management ion mptable MR-SSNS-264055-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Responsable Genre et Social nation and Management ion Component 3: Strengthening MR-SSNS-264056-CS-INDV / the shock response system f En cours d'exécut IDA / D5680 A posteriori Individuel Open 0.00 2021-11-19 2021-11-15 2022-01-07 2022-01-28 2022-03-04 2022-08-31 Assistant SI El Maouna or households vulnerable to ion climate-shocks MR-SSNS-267846-CS-CDS / P Component 2: Enhancing th Sélection de cons roduction films primoadoptan IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 42,282.63 Signé 2021-12-14 2021-01-11 2021-12-24 2021-01-29 2022-02-27 2022-01-11 2022-08-26 ts TEK f poor households e directe MR-SSNS-276749-CS-INDV / Component 1: Updating and En attente d'exéc Expert Gestionnaire / médiat IDA / D5680 enhancing the Social Registr A posteriori Individuel Open 0.00 2022-03-17 2022-05-05 2022-05-26 2022-06-30 2022-12-27 ution eur réclamations RS y MR-SSNS-276752-CS-INDV / Component 1: Updating and IDA / D5680 A posteriori Individuel Open 0.00 Annulé 2022-03-16 2022-05-04 2022-05-25 2022-06-29 2022-12-26 Refonte du site web du Regis enhancing the Social Registr tre CI y MR-SSNS-276768-CS-INDV / Component 2: Enhancing th En cours d'exécut Animateurs 'Tekavoul" (53) p IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2022-02-16 2022-02-15 2022-04-06 2022-04-27 2022-06-01 2022-11-28 ion our 48 000 ménages f poor households MR-SSNS-276772-CS-INDV / Component 2: Enhancing th En cours d'exécut Superviseur de Terrain 'Teka IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2022-02-17 2022-02-07 2022-04-07 2022-04-28 2022-06-02 2022-11-29 ion voul" (5) f poor households MR-SSNS-276914-CS-INDV / Component 2: Enhancing th En attente d'exéc Prestation traducteurs (10 jo IDA / D5680 e socio-economic inclusion o A posteriori Individuel Limited 0.00 2022-03-23 2022-03-28 2022-04-18 2022-05-23 2022-11-19 ution urs) TK / DF f poor households MR-SSNS-276920-CS-INDV / Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori Individuel Limited 0.00 2022-04-05 2022-04-10 2022-05-01 2022-06-05 2022-12-02 Consultant junior (3) Coord nation and Management ution MR-SSNS-276925-CS-INDV / Component 4: Project Coordi En attente d'exéc Consultant pour le calcul des IDA / D5680 A posteriori Individuel Open 0.00 2022-03-28 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ution quotas RS et TEK Page 8 MR-SSNS-276948-CS-INDV / Component 3: Strengthening Assistant en rédaction et co the shock response system f En attente d'exéc IDA / D5680 A posteriori Individuel Open 0.00 2022-04-19 2022-06-07 2022-06-28 2022-08-02 2023-01-29 mmunication Elmaaouna (OS or households vulnerable to ution A Observatoire de la Sécurité climate-shocks Alimentaire) MR-SSNS-282215-CS-INDV / Component 2: Enhancing th Recrutement de six (6) Gardi En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori Individuel Limited 0.00 2022-03-08 2022-03-13 2022-04-03 2022-05-08 2022-11-04 ens pour maisons (M'Bout, K ution f poor households ank, Selib, Aioun, Néma et M aghama) Component 2: Enhancing th MR-SSNS-283268-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2022-03-22 2022-03-03 2022-05-10 2022-05-31 2022-07-05 2023-01-01 Animateur GHABOU ion f poor households Component 2: Enhancing th MR-SSNS-283269-CS-INDV / En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori Individuel Limited 0.00 2022-03-22 2022-03-27 2022-04-17 2022-05-22 2022-11-18 Planton/coursier TK ution f poor households MR-SSNS-289042-CS-CDS / Component 2: Enhancing th Sélection de cons Recrutement d'un consultant IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 25,674.31 Signé 2022-04-08 2022-02-22 2022-04-18 2022-06-30 2022-06-22 2022-06-30 2022-12-19 pour initier les animateurs su f poor households e directe r les modules d'inclusion éco nomique Tekavoul MR-SSNS-291583-CS-INDV / Component 4: Project Coordi En cours d'exécut IDA / D5680 A posteriori Individuel Limited 0.00 2022-04-21 2022-04-25 2022-04-26 2022-05-17 2022-06-21 2022-12-18 Assistant Comptable nation and Management ion MR-SSNS-291584-CS-INDV / Component 4: Project Coordi IDA / D5680 A posteriori Individuel Open 15,000.00 Signé 2022-04-25 2022-04-20 2022-06-13 2022-07-04 2022-07-04 2022-07-27 2022-08-08 2022-08-10 2023-02-04 Assistant Passation des Marc nation and Management hés Component 2: Enhancing th MR-SSNS-291586-CS-INDV / En cours d'exécut IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 2022-04-25 2022-06-24 2022-06-13 2022-07-04 2022-08-08 2023-02-04 Assistant Promotion Sociale ion f poor households MR-SSNS-292480-CS-INDV / Component 4: Project Coordi En cours d'exécut Deux Assistants pour l'unité IDA / D5680 A posteriori Individuel Limited 0.00 2022-04-29 2022-04-26 2022-05-04 2022-05-25 2022-06-29 2022-12-26 nation and Management ion d'audit interne MR-SSNS-292501-CS-INDV / Component 4: Project Coordi En cours d'exécut Responsable Financier et Co IDA / D5680 A posteriori Individuel Limited 0.00 2022-05-11 2022-06-01 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ion mptable (CI/Comp-CV) MR-SSNS-292503-CS-INDV / Component 4: Project Coordi En attente d'exéc Responsable Social et genre IDA / D5680 A posteriori Individuel Limited 0.00 2022-05-11 2022-05-16 2022-06-06 2022-07-11 2023-01-07 nation and Management ution (CI/Comp-CV) MR-SSNS-276771-CS-INDV / Component 2: Enhancing th Chauffeur (15) ( 13 pour TK e IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 Annulé 2022-05-26 2022-07-14 2022-08-04 2022-09-08 2023-03-07 t 2 pour CSA) f poor households Component 2: Enhancing th Sélection de cons MR-SSNS-212308-CS-CDS / IDA / D5680 e socio-economic inclusion o A posteriori ultants par entent Direct 0.00 Annulé 2021-02-15 2021-02-25 2021-05-01 2021-10-28 Chauffeurs (03) TK f poor households e directe MR-SSNS-257047-CS-INDV / Component 2: Enhancing th Recrutement d'un consultant IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open 0.00 Annulé 2022-03-01 2022-04-19 2022-05-10 2022-06-14 2022-12-11 pour initier les animateurs su f poor households r les modules d'inclusion éco nomique Tekavoul MR-SSNS-304770-CS-INDV / Recrutement de Neuf (9) Gar Component 1: Updating and En attente d'exéc diens (2 pour RS, 3 pour TK, IDA / D5680 enhancing the Social Registr A posteriori Individuel Limited 0.00 2022-08-05 2022-08-10 2022-08-31 2022-10-05 2023-04-03 ution 1 pour Coord, 1 pour Baskno y u, 1 pour Néma, 1 pour Magh ama) Juillet 2022 MR-SSNS-304831-CS-INDV / Recrutement de Onze (11) a Component 1: Updating and En attente d'exéc nimateurs (remplacement: d IDA / D5680 enhancing the Social Registr A posteriori Individuel Open - National 0.00 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 ution e1 pour RS et 3 TK ((Koubeni, y Mbout et Amourje)) et 7 pour Mberra) juillet 2022 MR-SSNS-304834-CS-INDV / Component 2: Enhancing th Recrutement d'un Supervise En attente d'exéc IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open - National 0.00 2022-10-12 2022-11-30 2022-12-21 2023-01-25 2023-07-24 ur de Terrain 'Tekavoul" Mbe ution f poor households rra (01) Juillet 2022 MR-SSNS-304972-CS-INDV / Component 4: Project Coordi En attente d'exéc Recrutement d'un Assistant IDA / D5680 A posteriori Individuel Open - National 0.00 2022-09-01 2022-10-20 2022-11-10 2022-12-15 2023-06-13 nation and Management ution Archive Coord Juillet 2022 MR-SSNS-212005-CS-INDV / Component 1: Updating and Recrutement de 28 Chauffeu En attente d'exéc IDA / D5680 enhancing the Social Registr A posteriori Individuel Limited 0.00 2021-01-20 2021-01-25 2021-02-15 2021-03-22 2021-09-18 rs (pour TK (8 TK; 1 Mbera, 9 ution y Extention), 2 ELMAOUNA, 6 R S, Coord 2) Juillet 2022 MR-SSNS-304976-CS-CDS / Sélection de cons Component 4: Project Coordi En cours d'exame Recrutement d'un Avocat ou IDA / D5680 A posteriori ultants par entent Direct - National 0.00 2022-07-26 2022-07-28 2022-08-05 2022-10-09 2023-04-07 nation and Management n Conseiller juridique e directe MR-SSNS-319327-CS-INDV / Component 3: Strengthening Recrutement d'un consultant the shock response system f Open - Internationa En attente d'exéc IDA / D5680 A posteriori Individuel 0.00 2022-10-05 2022-10-29 2022-11-19 2022-12-24 2023-12-19 international chargé d'appuiy or households vulnerable to l ution er la mise en oeuvre du disp climate-shocks ositif du DCAN MR-SSNS-325447-CS-INDV / Recrutement d'un responsabl Component 4: Project Coordi En attente d'exéc IDA / D5680 A posteriori Individuel Open - National 0.00 2022-11-07 2022-12-10 2022-12-15 2023-01-03 2023-12-29 e passation des marchés (RP nation and Management ution M) au profit de l'UCP PASyFiS II MR-SSNS-315465-CS-INDV / Component 4: Project Coordi En cours d'exécut Consultant chargé de la revu IDA / D5680 A posteriori Individuel Direct - National 0.00 2022-10-17 2022-12-15 2022-10-27 2022-12-15 2022-11-17 2022-12-19 2022-12-22 2023-02-20 nation and Management ion e à mi-parcours pour le PSYFI S II MR-SSNS-334753-CS-CDS / Component 3: Strengthening Sélection de cons Consultant chargé de l'organi the shock response system f Direct - Internation IDA / D5680 A posteriori ultants par entent 0.00 Annulé 2023-01-09 2022-12-08 2023-01-16 2022-12-08 2023-01-19 2023-02-03 sation d'une formation sur le or households vulnerable to al e directe PNR/DCAN climate-shocks MR-SSNS-339690-CS-INDV / Component 2: Enhancing th En attente d'exéc Recutement de Cinq (05) Fac IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ution ilitateurs Promotion DF f poor households Page 9 MR-SSNS-339693-CS-INDV / Component 2: Enhancing th En attente d'exéc Recrutement d'un Supervise IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ution ur de terrain DF f poor households MR-SSNS-339694-CS-INDV / Component 1: Updating and En attente d'exéc IDA / D5680 A posteriori Individuel Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 Recrutement d'un Animateur enhancing the Social Registr ution RS y MR-SSNS-339695-CS-INDV / Component 1: Updating and En attente d'exéc Eecrutement d'un Assistant A COFN / C1950 enhancing the Social Registr A posteriori Individuel Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ution rchivage RS y MR-SSNS-339696-CS-INDV / Component 2: Enhancing th En attente d'exéc Recrutement de cinq (05) Ani IDA / D5680 e socio-economic inclusion o A posteriori Individuel Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 ution mateurs Tekavoul f poor households Component 3: Strengthening MR-SSNS-339699-CS-INDV / the shock response system f En attente d'exéc Recrutement d'un Expert Sta IDA / D5680 A posteriori Individuel Open - National 0.00 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-07-13 or households vulnerable to ution tisticien OSA climate-shocks MR-SSNS-339705-CS-INDV / Component 4: Project Coordi En attente d'exéc Recrutement d'un Assistant IDA / D5680 A posteriori Individuel Open - National 0.00 2023-04-28 2023-06-16 2023-07-07 2023-08-11 2024-08-10 nation and Management ution Administratif et Comptable ( Coordination) MR-SSNS-339707-CS-INDV / Component 2: Enhancing th Recrutement de cinq (05) gar En attente d'exéc COFN / C1950 e socio-economic inclusion o A posteriori Individuel Limited 0.00 2023-03-31 2023-04-05 2023-04-26 2023-05-31 2024-05-30 diens (M'Bout, Kank, Selib, Ai ution f poor households oun et Bassiknou) MR-SSNS-339710-CS-INDV / Component 1: Updating and En attente d'exéc Recrutement de vingt-un (21 COFN / C1950 enhancing the Social Registr A posteriori Individuel Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-08-29 ution ) Chauffeurs pour toutes les c y omposantes MR-SSNS-342206-CS-INDV / Component 4: Project Coordi En attente d'exéc Recrutement d'un Assistant P IDA / D5680 A posteriori Individuel Open - National 0.00 2023-03-13 2023-05-01 2023-05-22 2023-06-26 2024-06-25 nation and Management ution assation de Marchés au profit du PASyFiS II MR-SSNS-339449-CS-CDS / Contractualisation avec un b ureau pour la realisation d'un Sélection de cons Component 4: Project Coordi En attente d'exéc e formation sur la passation IDA / D5680 A posteriori ultants par entent Direct - National 0.00 2023-02-20 2023-03-02 2023-05-06 2023-11-02 nation and Management ution de marchés (Procedures de l e directe a Banque Mondiale) au profit des membres de la CPMP-Ta azour et le SPM du PASyFiS II MR-SSNS-339706-CS-INDV / Component 4: Project Coordi En attente d'exéc Recrutement d'un Assistant IDA / D5680 A posteriori Individuel Open - National 0.00 2023-04-28 2023-06-16 2023-07-07 2023-08-11 2024-08-10 nation and Management ution Auditeur interne (Coordinatio n) Page 10