PROCUREMENT PLAN (Textual Part) Project information: Project Preparation Grant for the Ghana Landscape Restoration and Small-Scale Mining Project (P171933) Project Implementation agency: Ministry of Environment, Science, Technology and Innovation (MESTI) Date of the Procurement Plan: 18 December, 2020 Period covered by this Procurement Plan: 30 November, 2020 – 31 July, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Ghana Public Procurement Act 663 of 2003 as amended by the Public Procurement (Amendment) Act 2016 (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations – not applicable. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – not applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations is not applicable. Consultancy Assignments with Selection Methods and Time Schedule Expected Activity proposals Estimated Reference Review Selection submission Amount No. / Type Method date (US$) Description: (YYYY/MM/DD) GH-LRP- Post 205773-CS- INDV / Consultancy for Preparation Individual and Disclosure Consultant 2020/11/30 20,000.00 of Environmental Selection and Social Management Framework (ESMF) GH-LRP- Post 205768-CS- INDV / Consultancy Individual for Preparation Consultant 2020/11/30 15,000.00 and Disclosure of Selection Resettlement Framework (RF) GH-LRP- Post Individual 205763-CS- Consultant 2020/11/30 15,000.00 INDV / Selection Consultancy for Gender Assessment and Action Plan GH-LRP- Post 205757-CS- INDV / Individual Consultancy Consultant 2020/11/30 15,000.00 for Water Selection Quality Analysis GH-LRP- Post 205766-CS- INDV / Consultant to Provide Technical Individual Assistance to Consultant 2020/11/30 20,000.00 the Team for Selection the Development of Project Documents i.e PIM, PAD, etc GH-LRP- Post 205775-CS- INDV / Individual Consultancy Consultant 2020/11/30 5,000.00 for External Selection Auditing of Accounts PROCUREMENT Ghana : Ghana Landscape Restoration and Small-Scale Mining Project PLAN General Information Country: Ghana 2022-02-09 Bank’s Approval Date of the Original Procurement Plan: 2023-02-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171933 GPN Date: 2022-07-11 Project Name: Ghana Landscape Restoration and Small-Scale Mining Project Loan / Credit No: IDA / 69690 Environmental Protection Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-EPA-293786-CW-RFB / C Request for Bids - arry out the installation of 2, Component 3: Sustainable cr Single Stage - One E Small Works SPD 2023-10-1 200 Pegs for the Pegging of 2 IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 366,666.67 0.00 Canceled 2022-06-15 2022-06-25 2022-07-25 2022-08-29 2022-10-10 nvelope (1 envelope proce 0 ,000ha of moribund/ disease nagement ss) d Cocoa farms (COCOBOD) GH-EPA-300883-CW-RFQ / In stallation of PREFAB OFFICES Component 4: Project monit Request for Quota Request for Quota Single Stage - One E Under Imple 2022-12-0 and washing rooms (120squa IDA / 69690 oring and knowledge manag Post Limited tions (Non Bank-S 40,000.00 0.00 2022-07-30 2022-10-24 tions nvelope mentation 3 re meters: three-bedroom, h ement PD) all, toilet and bath and kitche n) at EPA Compound National Procure GH-EPA-307336-CW-DIR / Co Component 3: Sustainable cr ment Document - nstruction of 17No. Various Direct - Internation Under Imple 2024-03-1 IDA / 69690 op and forest landscape ma Post Direct Selection 1 Envelope proce 920,000.00 0.00 2022-08-31 2022-08-23 2022-09-30 2022-11-21 Water Systems (Dug Outs)/W al mentation 5 nagement ss (Non Bank-SPD aterholes in selected sites an ) d communities GH-EPA-340873-CW-RFB / R eplacement of 9,085No. miss Request for Bids - Component 3: Sustainable cr ing/broken/defaced Forest Re Single Stage - One E Small Works SPD Pending Imp 2026-03-2 IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 468,000.00 0.00 2023-03-07 2023-03-12 2023-04-23 2023-05-23 2023-06-24 serve Boundary Pillars (FRBP nvelope (1 envelope proce lementation 9 nagement s) and 1118 Admitted Farm ss) Pillars in Selected Forest Res erves and Admitted Farms GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-EPA-279448-GO-RFQ / S Component 1: Institutional s upply and Installation of Offic Request for Quota Single Stage - One E IDA / 69690 trengthening for participator Post Limited 36,702.00 34,990.28 Signed 2022-04-03 2022-04-08 2022-06-22 2022-07-27 2022-07-22 e Furniture and Accessories a tions nvelope y landscape management t the GLRSSMP EPA PCU GH-EPA-279449-GO-RFB / Su Component 1: Institutional s pply of 21No. Pick-Ups Vehicl Single Stage - One E IDA / 69690 trengthening for participator Prior Request for Bids Open - National 2,765,345.31 3,095,320.68 Completed 2022-03-31 2022-04-06 2022-04-05 2022-04-07 2022-05-05 2022-05-09 2022-06-04 2022-06-11 2022-07-06 2022-07-28 2022-08-20 2022-08-23 es and 11No. SUV Cross Cou nvelope y landscape management ntry Vehicles for project impl ementation GH-EPA-279450-GO-RFB / Su Component 1: Institutional s Single Stage - One E pply of 141No. Motorcycles f IDA / 69690 trengthening for participator Post Request for Bids Open - National 831,900.00 0.00 Signed 2022-03-30 2022-04-08 2022-04-04 2022-04-08 2022-05-06 2022-05-09 2022-06-05 2022-05-26 2022-07-10 2022-09-08 nvelope or Project Implementation y landscape management GH-EPA-279458-GO-RFQ / S upply of 62No. Various Digita Component 1: Institutional s Request for Quota Single Stage - One E l Cameras, 66No. Mobile Inte IDA / 69690 trengthening for participator Post Limited 92,880.00 57,334.31 Signed 2022-04-05 2022-04-08 2022-06-24 2022-07-27 2022-07-24 tions nvelope rnet Routers and 82No. Vario y landscape management us External Storage Drives GH-EPA-282256-GO-RFB / Su pply of 226No. Various Globa Component 3: Sustainable cr Single Stage - One E l Positioning System Devices, IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 136,960.00 172,737.64 Completed 2022-03-31 2022-04-29 2022-04-09 2022-05-04 2022-05-09 2022-05-31 2022-06-08 2022-06-24 2022-07-17 2022-07-29 2022-08-16 nvelope 30No. Ruggered Smart Andro nagement id Phones and monitor GH-EPA-279452-GO-RFB / Su pply and Installation of Desk Component 1: Institutional s Single Stage - One E Under Imple top Computers & UPS Device IDA / 69690 trengthening for participator Post Request for Bids Open - National 430,461.00 0.00 2022-03-30 2022-04-30 2022-04-04 2022-05-04 2022-05-04 2022-05-31 2022-06-03 2022-07-21 2022-07-12 2022-08-11 nvelope mentation s, Laptop Computers and Prin y landscape management ters, Copiers and Scanners GH-EPA-288436-GO-RFQ / S Component 4: Project monit Request for Quota Single Stage - One E upply and Installation of Acco IDA / 69690 oring and knowledge manag Post Limited 30,000.00 28,984.38 Completed 2022-04-17 2022-04-11 2022-06-15 2022-07-26 2022-07-15 2022-08-02 tions nvelope unting Software for EPA PCU ement GH-EPA-291611-GO-RFQ / S Component 3: Sustainable cr upply of 4000No. Forceps for Request for Quota Single Stage - One E IDA / 69690 op and forest landscape ma Post Limited 60,000.00 69,961.11 Completed 2022-05-29 2022-05-20 2022-08-20 2022-07-27 2022-10-19 2022-08-02 COCOBOD for the Implement tions nvelope nagement ation of Hand Pollination Exer cise GH-EPA-291834-GO-RFQ / S Component 3: Sustainable cr Request for Quota Single Stage - One E upply of 30No. Tricycles for P IDA / 69690 op and forest landscape ma Post Limited 93,000.00 93,807.64 Completed 2022-06-12 2022-05-31 2022-09-06 2022-07-27 2022-10-11 2022-08-08 tions nvelope roject Implementation nagement GH-EPA-291616-GO-RFB / Su pply of 5,000 Bags of Ammon ium Sulphate, 2,444 Galons o Component 3: Sustainable cr Single Stage - One E Under Imple f Aboricides and 2000Litres o IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 165,744.33 0.00 2022-05-31 2022-07-08 2022-06-05 2022-07-13 2022-07-05 2022-08-10 2022-08-04 2022-09-12 2022-09-08 2022-11-07 nvelope mentation f Vitazyme organic Fertilizer f nagement or the Rehabilitation of Merib und infected Cocoa farms by COCOBOD GH-EPA-291619-GO-RFB / Su pply of 10,000No. Earth Chis els, 4,000No. Plastic Buckets, 4,000No. Painting Brushes, 4, Component 3: Sustainable cr Single Stage - One E Under Imple 000No. Measuring Tape, 2,00 IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 131,529.99 0.00 2022-05-31 2022-07-08 2022-06-05 2022-07-13 2022-07-05 2022-08-09 2022-09-13 2022-11-12 nvelope mentation 0Bundlles of Rope, 508No. W nagement ater Bottles, 508No. Canvas Bags for the Rehabilitation of Moribund /Diseased Cocoa fa rms by COCOBOD Page 1 GH-EPA-291771-GO-RFB / Su pply of 40,000No. Economic Component 3: Sustainable cr Tree Seedlings and 2,400,00 Single Stage - One E IDA / 69690 op and forest landscape ma Post Request for Bids Limited 488,000.00 0.00 Canceled 2022-05-31 2022-06-07 2022-07-07 2022-08-11 2022-09-15 2023-09-15 0No. Plantain Suckers for the nvelope nagement Rehabilitation of Meribund inf ected Cocoa farms by COCO BOD GH-EPA-291622-GO-RFQ / S upply of PPE (508No. Welling ton Boots, 1,016No. Nose Ma Component 3: Sustainable cr Request for Quota Single Stage - One E Under Imple sk, 1,016No. Hand Gloves, 50 IDA / 69690 op and forest landscape ma Post Limited 14,139.34 0.00 2022-06-05 2022-09-06 2022-10-21 tions nvelope mentation 8No. Overalls, 508No. Rain C nagement oats and 508No. Reflectors) f or the Rehabilitation of morib und/diseased Cocoa Farms b y COCOBOD GH-EPA-298273-GO-RFB / Su Component 3: Sustainable cr Single Stage - One E pply of 3No. Tractors with Ac IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 260,000.00 0.00 Canceled 2022-07-19 2022-07-08 2022-07-24 2022-07-13 2022-09-04 2022-08-10 2022-10-14 2022-08-31 2022-11-18 2023-02-16 nvelope cessories and 1No. Truck nagement GH-EPA-298274-GO-RFB / Su pply of Legume, Stylosanthes and Pasture Seeds, and other Component 3: Sustainable cr Assorted Seeds for II Fodder Single Stage - One E Under Imple IDA / 69690 op and forest landscape ma Post Request for Bids Limited 728,138.34 0.00 2022-07-18 2022-09-07 2022-07-23 2022-09-13 2022-09-03 2022-10-18 2022-10-03 2022-10-31 2022-11-07 2023-12-12 Bank establishment, Cocoa L nvelope mentation nagement andscape support Project, ou tside Pra Basin and Cashew a groforestry farms in the Sava nnah landscape GH-EPA-298275-GO-RFB / Su Component 3: Sustainable cr pply of 2,998,000No. Various Single Stage - One E Under Imple IDA / 69690 op and forest landscape ma Post Request for Bids Limited 556,301.40 0.00 2022-07-14 2022-08-01 2022-07-24 2022-09-04 2022-10-04 2022-11-12 2024-02-05 Timber Tree Seedlings to vari nvelope mentation nagement ous selected project sites GH-EPA-298276-GO-RFB / Pr ocure and Transport Assorte Component 3: Sustainable cr d Tree Seedlings for Sub-proj Single Stage - One E Under Imple IDA / 69690 op and forest landscape ma Post Request for Bids Limited 350,000.00 0.00 2022-07-11 2022-07-31 2022-07-22 2022-08-01 2022-09-02 2022-09-01 2022-10-02 2022-11-06 2024-02-29 ect Implementation in the Ag nvelope mentation nagement ricultural Savannah & Transit ion Landscape (200hr), and C ocoa Landscape (150hr) GH-EPA-298277-GO-RFB / Su pply of Seedlings (including T Component 3: Sustainable cr Single Stage - One E Under Imple ransportation) as Support to IDA / 69690 op and forest landscape ma Post Request for Bids Limited 122,500.00 0.00 2022-07-07 2022-08-01 2022-07-19 2022-08-30 2022-09-29 2022-11-10 2024-01-14 nvelope mentation 700 Smallholders for the Esta nagement blishment of Cashew Agrofor estry Farms GH-EPA-298279-GO-RFQ / S upply of 5No. Various Unman Component 3: Sustainable cr Request for Quota Single Stage - One E Under Imple ned Aircrafts (Drones) and Ac IDA / 69690 op and forest landscape ma Post Limited 89,200.00 0.00 2022-07-19 2022-10-22 2022-12-06 tions nvelope mentation cessories, 10No. LCD Project nagement ors & 1No. Mobile Projector S creen GH-EPA-298280-GO-RFB / Su pply of Fertilizers to Savanna Component 3: Sustainable cr Single Stage - One E Under Imple and Transitional Landscape s IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 599,240.74 0.00 2022-07-12 2022-07-18 2022-07-21 2022-07-22 2022-09-01 2022-10-01 2022-11-12 2023-11-12 nvelope mentation ub-project and Cocoa landsc nagement ape and outside Pra Basin GH-EPA-300870-GO-RFQ / S upply and installation of 60N o. Rugged Smart Phones, 30 No. GPS Devices with subscri Component 1: Institutional s Request for Quota Single Stage - One E Pending Impl ption, 2No. Desktop Compute IDA / 69690 trengthening for participator Post Limited 51,800.00 0.00 2022-07-18 2022-09-26 2022-10-26 tions nvelope ementation rs, 1No. Laptop Computer, 2 y landscape management No. Flat Screen TV set, Intern et Router & rack for Mole and Digya National Park under Ea rth Ranger /SMART GH-EPA-300877-GO-RFB / Su pply of Seedlings, Fencing M aterials, Watering Pumps etc. Component 3: Sustainable cr for the establishment of Ripa Single Stage - One E Pending Impl IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 300,900.00 0.00 2022-07-19 2022-07-24 2022-09-04 2022-10-14 2022-11-18 2023-05-17 rian Vegetation and River Ba nvelope ementation nagement nk Soil Erosion Control Measu res in the Cocoa Landscape, Northern Savannah and Tran sitional Zones and PROGREE N districts GH-EPA-300880-GO-RFQ / S Component 3: Sustainable cr Request for Quota Single Stage - One E Under Imple upply of 150No. Durable Tabl IDA / 69690 op and forest landscape ma Post Limited 48,000.00 0.00 2022-07-26 2022-08-15 2022-10-27 2022-11-26 tions nvelope mentation ets for Data Collection nagement GH-EPA-307283-GO-RFB / Su pply of Wire Products, Mesh, Component 3: Sustainable cr Binding Wires and Metal Pole Single Stage - One E IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 934,746.94 0.00 Signed 2022-08-29 2022-08-04 2022-09-03 2022-08-05 2022-10-08 2022-09-01 2022-11-07 2022-09-14 2022-12-12 2023-12-12 s for Rangelands, Savannah nvelope nagement and Transitional Sub-projects , Cashew agroforestry and Fo dder banks GH-EPA-324493-GO-RFQ / S Component 3: Sustainable cr Request for Quota Single Stage - One E Under Imple upply of 450No. Bicycles for IDA / 69690 op and forest landscape ma Post Limited 47,000.00 0.00 2022-11-22 2022-11-08 2023-02-11 2023-03-13 tions nvelope mentation Project Implementation nagement GH-EPA-324494-GO-RFQ / S upply of 256No. Donkey Cart s, 1,325No. Watering Cans, 1 58No. Barrels, Various Hand Component 3: Sustainable cr Request for Quota Single Stage - One E Under Imple Tools and 372 Galons of Bitu IDA / 69690 op and forest landscape ma Post Limited 79,068.79 0.00 2022-11-22 2022-11-08 2023-02-07 2023-03-09 tions nvelope mentation men for Compost Production nagement and the establishment of Rip arian Vegetation and Riverba nk Soil Erosion Control Measu res for MOFA, FSD and EPA GH-EPA-324495-GO-RFQ / S upply of 1,380No. Cutlasses, 1,380 Pairs of Wellington Boo Component 3: Sustainable cr Request for Quota Single Stage - One E Under Imple ts, 1,380No. Torch lights & W IDA / 69690 op and forest landscape ma Post Limited 70,000.00 0.00 2022-11-22 2022-11-08 2023-02-14 2023-03-16 tions nvelope mentation histles, and 3,080No. Custom nagement ized T-Shirts for Fire as Fire Management, Prevention and Control Tools for EPA and FS D GH-EPA-340870-GO-RFQ / S Component 4: Project monit Request for Quota Single Stage - One E Pending Impl IDA / 69690 Post Limited 10,000.00 0.00 2023-02-26 2023-05-03 2023-06-02 upply of food relief items oring and knowledge manag tions nvelope ementation ement Page 2 GH-EPA-343157-GO-RFB / Pr ovision of 308No. Sign Posts f Component 3: Sustainable cr Single Stage - One E Pending Impl or Improved Project Visibility IDA / 69690 op and forest landscape ma Post Request for Bids Open - National 146,000.00 0.00 2023-03-01 2023-03-13 2023-04-12 2023-05-12 2023-06-23 2024-05-24 nvelope ementation and Identification Signages a nagement t all EPA PCU Project Sites (Pr oject Sign Post) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-EPA-324392-NC-RFB / Pr ovision of livelihood support f or 429 farmers/beneficiaries Component 3: Sustainable cr Single Stage - One E Pending Impl to implement natural resourc IDA / 69690 op and forest landscape ma Post Request for Bids Limited 257,400.00 0.00 2022-11-17 2022-11-22 2022-12-24 2023-01-23 2023-02-27 2024-02-27 nvelope ementation e based livelihood activities i nagement n bee keeping under the Fore st Services Division and Wildl ife Division GH-EPA-324397-NC-RFB / SE RVICE PROVISION FOR REHA Component 3: Sustainable cr Single Stage - One E Pending Impl BILITATION (TREE CUTTING, IDA / 69690 op and forest landscape ma Prior Request for Bids Limited 2,370,000.67 0.00 2022-12-06 2022-12-11 2023-01-22 2023-02-21 2023-04-04 2024-11-24 nvelope ementation REPLANTING AND MAINTENA nagement NCE) OF 2000HA OF MORIBU ND COCOA FARMS GH-EPA-343149-NC-RFQ / Pr Component 3: Sustainable cr ovision of livelihood support Request for Quota Single Stage - One E Pending Impl IDA / 69690 op and forest landscape ma Post Limited 75,000.00 0.00 2023-03-05 2023-05-23 2025-01-12 activities in aquaculture (cag tions nvelope ementation nagement e culture and pond) to select ed beneficiaries CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-EPA-307364-CS-QCBS / P roject works and infrastructur Component 3: Sustainable cr Quality And Cost- Under Implement al consultants for the Ghana IDA / 69690 op and forest landscape ma Post Open - National 801,600.00 0.00 2022-08-29 2022-08-09 2022-09-19 2022-09-22 2022-11-09 2022-12-10 2023-01-09 2023-02-13 2023-03-13 2026-02-01 Based Selection ation Landscape and Small Scale M nagement ining Project - EPA PCU GH-EPA-277941-CS-CQS / Co nsultancy Services for the As Component 3: Sustainable cr sessment and development o Consultant Qualifi IDA / 69690 op and forest landscape ma Post Limited 70,000.00 0.00 Canceled 2022-02-15 2022-02-09 2022-03-01 2022-04-08 2022-03-22 2022-04-19 2022-09-16 f Tourism Potential in Digya cation Selection nagement National Park and Odweano ma Southern Scarp Forest Re serve GH-EPA-327914-CS-CQS / Co nsultancy Services for the As Component 3: Sustainable cr sessment and development o Consultant Qualifi Under Implement IDA / 69690 op and forest landscape ma Post Limited 110,000.00 0.00 2022-12-06 2022-12-07 2022-12-20 2023-01-19 2023-02-23 2023-08-22 f Tourism Potential in Digya cation Selection ation nagement National Park and Odweano ma Southern Scarp Forest Re serve GH-EPA-288441-CS-CQS / Re Component 3: Sustainable cr cruitment of an NGO for Trai Consultant Qualifi IDA / 69690 op and forest landscape ma Post Limited 89,000.00 0.00 Canceled 2022-04-19 2022-05-19 2022-05-10 2022-05-31 2022-07-05 2025-09-03 ning Of Village Savings and L cation Selection nagement oans Associations/Groups In Project Communities GH-EPA-327921-CS-CQS / Re cruitment of an NGO for Trai Component 3: Sustainable cr Consultant Qualifi Under Implement ning of Village Savings and L IDA / 69690 op and forest landscape ma Post Limited 175,000.00 0.00 2022-12-05 2022-12-07 2022-12-19 2023-01-18 2023-02-22 2025-11-18 cation Selection ation oans Associations/Groups in nagement Selected Project Beneficiary Communities GH-EPA-343115-CS-CQS / Co nsultancy Service for the Ind Component 4: Project monit ependent Audit of the Landsc Consultant Qualifi IDA / 69690 oring and knowledge manag Post Limited 35,000.00 0.00 Canceled 2023-03-06 2023-03-20 2023-05-04 2023-05-25 2023-06-24 ape Restoration Option of the cation Selection ement Ghana Landscape Restoratio n and Small-Scale Mining Proj ect (GLRSSMP) at the EPA PC U GH-EPA-344234-CS-LCS / Co nsultancy Service for the Ind Component 4: Project monit ependent Audit of the Landsc Least Cost Selecti Pending Impleme IDA / 69690 oring and knowledge manag Post Open - National 80,000.00 0.00 2023-03-09 2023-03-30 2023-06-03 2023-06-17 2023-07-17 2023-08-21 2023-09-25 2025-08-15 ape Restoration Option of the on ntation ement Ghana Landscape Restoratio n and Small-Scale Mining Proj ect (GLRSSMP) at the EPA PC U INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-EPA-258329-CS-INDV / R ecruitment of a Technical Sp Component 1: Institutional s ecialist to update technical m Individual Consult IDA / 69690 trengthening for participator Post Limited 60,000.00 59,600.00 Signed 2022-02-15 2022-02-09 2022-02-20 2022-02-18 2022-03-13 2022-05-05 2022-04-10 2022-05-18 2022-07-09 ethodologies and procedures ant Selection y landscape management for the implementation of lan d and watershed manageme nt activities under the project GH-EPA-288439-CS-INDV / C Component 3: Sustainable cr onsultancy Service to Evaluat Individual Consult Under Implement IDA / 69690 op and forest landscape ma Post Limited 30,000.00 0.00 2022-04-15 2022-05-20 2022-05-06 2022-05-20 2022-06-10 2022-07-30 e the Validity of the Draft Co ant Selection ation nagement nservation Status of Forest Tr ee Species In Ghana GH-EPA-295829-CS-CDS / Pr Component 1: Institutional s ovision of Technical Support/ Under Implement IDA / 69690 trengthening for participator Post Direct Selection Direct 810,000.00 0.00 2022-06-09 2022-05-26 2022-07-30 2022-08-10 2022-09-06 2025-12-19 Assistance to the GLRSSMP ( ation y landscape management Landscape Option) On Impro ved Spatial Monitoring Page 3