PROCUREMENT PLAN (Textual Part) Project information: Sindh Flood Emergency Rehabilitation Project (P179981) Project Implementation agency(ies): (i) Sindh Planning & Development Department (ii) Sindh Irrigation Department Date of the Procurement Plan: December 2022 Period covered by this Procurement Plan: June 30 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in public procurement rules such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is not allowed Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Sindh Flood Emergency Rehabilitation Project PLAN General Information Country: Pakistan 2023-01-17 Bank’s Approval Date of the Original Procurement Plan: 2023-02-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P179981 GPN Date: 2023-01-19 Project Name: Sindh Flood Emergency Rehabilitation Project Loan / Credit No: IDA / 72500 Province of Sindh Irrigation Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-POSID-336211-CW-RFB / Rehabilitation/ Construction Single Stage - One E Other (with field f Under Imple 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 5,681,818.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 of Additional Outfall Regulato nvelope or explanation) mentation 1 r Along Ochitto Outfall Drain and Leading Channel. PK-POSID-336212-CW-RFB / Single Stage - One E Other (with field f Pending Imp 2024-03-1 Rehabilitation of Main East Br IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 1,006,738.00 0.00 2023-01-13 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) lementation 1 anch Nawabshah. PK-POSID-336213-CW-RFB / Single Stage - One E Other (with field f Under Imple 2024-03-1 Rehabilitation of Shikarpur Br IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 258,748.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 . Drain system. PK-POSID-336214-CW-RFB / Rehabilitation of Pharho Esca Single Stage - One E Other (with field f Under Imple 2024-03-1 pe from RD 0+000 to 30+00 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 139,273.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 0 Both Sides in KhairpurGam bo Sub Division of Nasir Divis ion. PK-POSID-336215-CW-RFB / Raising and Rehabilitation (E arthwork) along Oderolal Esc Single Stage - One E Other (with field f Under Imple 2024-03-1 ape from RD 0+000 to 71+0 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 2,250,000.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 00 NIP Side i/c installation of new gates to increase capaci ty of water to enable escape discharge in Indus River. PK-POSID-336216-CW-RFB / Single Stage - One E Other (with field f Pending Imp 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 652,658.00 0.00 2023-01-13 2023-01-13 2023-01-24 2023-02-23 2023-03-13 Rehabilitation of Karampur Ri nvelope or explanation) lementation 1 ng Bund. PK-POSID-336217-CW-RFB / Single Stage - One E Other (with field f Under Imple 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 1,590,120.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 Rehabilitation of Suprio Bund nvelope or explanation) mentation 1 . PK-POSID-336218-CW-RFB / Package No. 1 Lot No. 1 Floo d Detention Dam Lat-01 (DD/ Single Stage - One E Other (with field f Under Imple 2024-03-1 W-L01 along LatNai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,586,543.00 0.00 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-03-02 2023-03-20 nvelope or explanation) mentation 8 Lot No.2 Floo d Detention Dam Lat-02 (DD/ W-L02 along LatNai). PK-POSID-336219-CW-RFB / Package No. 2 Lot No. 1 Floo d Detention Dam Lat-03 (DD/ Single Stage - One E Other (with field f Under Imple 2024-03-1 W-L03 along LatNai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,919,065.00 0.00 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-03-02 2023-03-20 nvelope or explanation) mentation 8 Lot No. 2 Flo od Detention Dam Lat-04 (D D/W-L04 along LatNai). PK-POSID-336220-CW-RFB / Single Stage - One E Other (with field f Under Imple 2024-03-1 Package No.3 Flood Detentio IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 4,597,684.00 0.00 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-03-02 2023-03-20 nvelope or explanation) mentation 8 n Dam Mole-02 (DD/W-M2 al ong Mole Nai). PK-POSID-336221-CW-RFB / Package No. 4 Lot No. 1 Floo d Detention Dam Mole-03 (D Single Stage - One E Other (with field f Under Imple 2024-03-1 D/W-M3 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,993,696.00 0.00 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-03-02 2023-03-20 nvelope or explanation) mentation 8 Lot No. 2 Floo d Detention Dam Mole-04 (D D/W-M4 along Mole Nai). PK-POSID-336223-CW-RFB / Package No. 5 Lot No. 1 Floo d Detention Dam Mole-05 (D Single Stage - One E Other (with field f Under Imple 2024-03-1 D/W-M5 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 8,779,468.00 0.00 2023-01-14 2022-12-26 2023-01-14 2023-01-25 2023-01-31 2023-03-02 2023-03-20 nvelope or explanation) mentation 8 Lot No. 2 Floo d Detention Dam Mole-06 (D D/W-M6 along Mole Nai). PK-POSID-336225-CW-RFB / Package No. 6 Lot No.1 Floo d Detention Dam Mole-07 (D Single Stage - One E Other (with field f Under Imple 2024-03-1 D/W-M7 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,608,233.00 0.00 2023-01-14 2022-12-26 2023-01-14 2023-01-25 2023-01-31 2023-03-02 2023-03-20 nvelope or explanation) mentation 8 Lot No. 2 Flo od Detention Dam Mole -08 ( DD/W-M8 along Mole Nai). PK-POSID-336067-CW-DIR / Other (with field f Pending Imp 2023-04-2 Rehabilitation OF Manchar C IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,251,592.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 ONTAINING BUND (RD 0+000 TO 27+000 ). PK-POSID-336093-CW-DIR / Other (with field f Pending Imp 2023-04-2 REHABILITATION OF DANISTA IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,682,097.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 R CANAL (RD 0+000 TO 27+ 440). PK-POSID-336083-CW-DIR / Other (with field f Pending Imp 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,427,760.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 PURAN RD 176+400 to 210+ 000. PK-POSID-336069-CW-DIR / REHABILITATION OF MANCHA Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,483,243.00 0.00 2023-01-13 2023-01-13 2023-01-21 R CONTAINING BUND (RD 54 or explanation) lementation 1 +000 TO 77+000 ). Page 1 PK-POSID-336074-CW-DIR / Other (with field f Pending Imp 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,543,288.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 380+000 to RD 445+000). PK-POSID-336077-CW-DIR / Rehabilitation of FP Bund (RD Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,748,317.00 0.00 2023-01-13 2023-01-13 2023-01-21 490+000 to RD 502+000 & R or explanation) lementation 1 D 263+000 to RD 220+000). PK-POSID-336079-CW-DIR / Other (with field f Pending Imp 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,492,892.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 220+000 to RD 169+000). PK-POSID-336085-CW-DIR / REHABILITATION OF DHORO Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,318,122.00 0.00 2023-01-13 2023-01-13 2023-01-21 PURAN RD 210+000 TO 222 or explanation) lementation 1 +130 AND MAIN DRAIN RD 2 12+300 TO 217+600. PK-POSID-336075-CW-DIR / Other (with field f Pending Imp 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,604,680.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 445+000 to RD 490+000). PK-POSID-335890-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 635,481.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 of Breach along Saifullah Ma gsi Branch. PK-POSID-335912-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging, Strengthening Rest IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 930,558.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 oration and Rehabilitation of Dhamrah Wah. PK-POSID-335914-CW-DIR / Replacement / Supply and In stallation of Motor Pump (10 Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,074,545.00 0.00 2023-01-12 2023-01-12 2023-01-20 0 H.P) Including All Accessori or explanation) lementation 0 es Along Ghaar, Shahmeer, Mehar, Mashori, K.N.Shah, Mi ro Khan and Agani Pumping Stations. PK-POSID-335916-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 977,477.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Breach along Main Nara V or explanation) lementation 9 alley (MNV) Drain at RD 280. PK-POSID-335928-CW-DIR / Other (with field f Pending Imp 2023-02-1 Closing of cuts alog Rohri Mai IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 469,559.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 n Canal, Moro Division. PK-POSID-335933-CW-DIR / Plugging And Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,022,523.00 0.00 2023-01-12 2023-01-12 2023-01-20 Of Relief Cut Along Johi Branc or explanation) lementation 9 h Along Rd 80 To Rd 86 And Rd 95 To Rd 98. PK-POSID-335862-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 226,695.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 of Breach along FP Bund alon g 169+000. PK-POSID-335917-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 309,602.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Breach along Main Nara V or explanation) lementation 9 alley (MNV) Drain at RD 330. PK-POSID-335893-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 407,933.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Breaches / Cuts Along Gha or explanation) lementation 9 r Main Drain & Leading Chan nel. PK-POSID-335905-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 782,058.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 of Breaches / Cuts Along Miro Khan Main Drain. PK-POSID-335919-CW-DIR / Plugging, Strengthening and Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 346,364.00 0.00 2023-01-12 2023-01-12 2023-01-20 Stone Pitching of Breach alon or explanation) lementation 9 g Superio Bund RD 12. PK-POSID-335920-CW-DIR / Plugging, Strengthening and Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 249,294.00 0.00 2023-01-12 2023-01-12 2023-01-20 Stone Pitching of Breach alon or explanation) lementation 9 g Superio Bund RD 28. PK-POSID-336089-CW-DIR / REMODELING AND REHABILIT Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 6,486,130.00 0.00 2023-01-13 2023-01-13 2023-01-21 ATION OF ARAL HEAD REGUL or explanation) lementation 1 ATOR (MC RD 0+000). PK-POSID-336087-CW-DIR / REHABILITATION OF OUTFALL Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,482,485.00 0.00 2023-01-13 2023-01-13 2023-01-21 STRUCTURE AT RD 210+000 or explanation) lementation 1 OF DHORO PURAN. PK-POSID-336070-CW-DIR / REHABILITATION OF MANCHA Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,542,517.00 0.00 2023-01-13 2023-01-13 2023-01-21 R CONTAINING BUND (RD 77 or explanation) lementation 1 +000 TO 100+000). PK-POSID-336071-CW-DIR / Other (with field f Pending Imp 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,475,187.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 160+000 to RD 210+000). PK-POSID-335923-CW-DIR / Plugging, Strengthening and Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 60,393.00 0.00 2023-01-12 2023-01-12 2023-01-20 Stone Pitching of Breach alon or explanation) lementation 9 g Superio Bund RD 42. PK-POSID-336091-CW-DIR / Other (with field f Pending Imp 2023-04-2 REHABILITATION OF LEFT AR IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,156,718.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 AL BUND RD 0+000 TO RD 1 9+000. PK-POSID-335931-CW-DIR / Other (with field f Pending Imp 2023-02-1 Repair of Rain Damages of S IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,397,355.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 mall Dams Under Small Dam s Organization. Page 2 PK-POSID-335855-CW-DIR / Plugging, Strengthening & St Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 219,056.00 0.00 2023-01-12 2023-01-12 2023-01-20 one Pitching of Relief Cut Lar or explanation) lementation 9 kana Sehwan Bund along Mil e 95/6. PK-POSID-336080-CW-DIR / Other (with field f Pending Imp 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,250,317.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 PURAN RD 110+000 TO 143 +330. PK-POSID-335851-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,249,943.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Relief Cut along Manchar or explanation) lementation 9 Containing Bund at RD 52+0 00. PK-POSID-335854-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,133,842.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Breach along Main Nara V or explanation) lementation 9 aley (MNV) Drain at RD 8+06 8. PK-POSID-335887-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 180,708.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 of Breach along FP Bund alon g RD 476+000. PK-POSID-336081-CW-DIR / Other (with field f Pending Imp 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,491,000.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 PURAN RD 143+330 TO 176 +400. PK-POSID-335925-CW-DIR / Plugging, Strengthening and Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 189,836.00 0.00 2023-01-12 2023-01-12 2023-01-20 Stone Pitching of Breach alon or explanation) lementation 9 g Superio Bund RD 52. PK-POSID-335929-CW-DIR / Other (with field f Pending Imp 2023-02-1 Repair of Rain Damages Sma IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,912,465.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 ll Dams Under Sindh Resilien ce Project (SRP). PK-POSID-335898-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 493,189.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Breaches Along K.N Shah or explanation) lementation 9 Main Drain & Leading Chann el. PK-POSID-335927-CW-DIR / Plugging, Strengthening and Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 44,676.00 0.00 2023-01-12 2023-01-12 2023-01-20 Stone Pitching of Breach alon or explanation) lementation 9 g Superio Bund RD 82. PK-POSID-335858-CW-DIR / Plugging, Strengthening & St Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 906,846.00 0.00 2023-01-12 2023-01-12 2023-01-20 one Pitching of Relief Cut Lar or explanation) lementation 9 kana Sehwan Bund along Mil e 97/2. PK-POSID-335873-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,452,498.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 of Breach along FP Bund alon g RD 340+000. PK-POSID-335915-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 802,253.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Breach along Main Nara V or explanation) lementation 9 alley (MNV) Drain at RD 210. PK-POSID-335821-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,135,696.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Relief Cut along Manchar or explanation) lementation 9 Containing Bund at RD 14+0 00. PK-POSID-335903-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 385,539.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Breaches / Cuts Along Sha or explanation) lementation 9 hdad Kot Branch Drain. PK-POSID-336068-CW-DIR / REHABILITATION OF MANCHA Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,538,878.00 0.00 2023-01-13 2023-01-13 2023-01-21 R CONTAINING BUND (RD 27 or explanation) lementation 1 +000 TO 54+000 ). PK-POSID-336072-CW-DIR / Other (with field f Pending Imp 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,524,135.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 325+000 to RD 380+000). PK-POSID-336094-CW-DIR / Other (with field f Pending Imp 2023-04-2 REHABILITATION OF DANISTA IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,633,010.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 R CANAL (RD 27+440 TO 56 +434). PK-POSID-335860-CW-DIR / Plugging, Strengthening & St Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,231,284.00 0.00 2023-01-12 2023-01-12 2023-01-20 one Pitching of Relief Cut Lar or explanation) lementation 9 kana Sehwan Bund along Mil e 99/3. PK-POSID-335909-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,075,286.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 of Breach Along F.P Bund Rd 432. PK-POSID-335932-CW-DIR / Repair of Gaj Diversion Bund Other (with field f Pending Imp 2023-02-1 ledge and stone apron from IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,342,347.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 RD 3-11, Repair of Gaj Divers ion Bund stone apron from R D 15-32.5. PK-POSID-335867-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 552,124.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 of Breach along FP Bund alon g RD 215+000. PK-POSID-335853-CW-DIR / Plugging and Strengthening Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,361,326.00 0.00 2023-01-12 2023-01-12 2023-01-20 of Breach along Main Nara V or explanation) lementation 9 aley (MNV) Drain at RD 2+31 8. PK-POSID-335901-CW-DIR / Other (with field f Pending Imp 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 337,811.00 0.00 2023-01-12 2023-01-12 2023-01-20 Rehabilitation Of Mehar Main or explanation) lementation 9 Drain. Page 3 PK-POSID-335908-CW-DIR / Other (with field f Pending Imp 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,747,581.00 0.00 2023-01-12 2023-01-12 2023-01-20 or explanation) lementation 9 of Breaches Along Indus Link Drain. PK-POSID-336092-CW-DIR / REMODELING AND REHABILIT Other (with field f Pending Imp 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,469,384.00 0.00 2023-01-13 2023-01-13 2023-01-21 ATION OF ARAL WAH (RD 1+ or explanation) lementation 1 250 TO RD 0+000 & RD 0+0 00 TO 14+000). PK-POSID-336095-CW-DIR / Remodeling and Rehabilitatio Other (with field f Pending Imp 2023-04-2 n of Danister Tail Regulator a IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,745,403.00 0.00 2023-01-13 2023-01-13 2023-01-21 or explanation) lementation 1 nd Regulator for 10 Phats (Mi nors) Danister Canal (Civil W orks). PK-POSID-343948-CW-DIR / Other (with field f Pending Imp 2023-05-2 Rehabilitation Of Old Water IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 173,193.00 0.00 2023-02-20 2023-02-20 2023-02-28 or explanation) lementation 9 Way In Desert Area Of Khairp ur. Request for Quota PK-POSID-341482-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-1 Rehabilitation of Talpur Wad IDA / 72500 Infrastructure Rehabilitation Post Limited 530,161.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP lementation 2 a Pumping Station And Water D -Competitive Carrier Drain. PK-POSID-341480-CW-RFQ / Request for Quota Rehabilitation of Syphon at A Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Limited 294,021.00 0.00 2023-02-24 2023-03-17 li Bahar Branch And Rehabilit tions nvelope s (Emergency) SP lementation 2 ation of Syphon at Kubri Mino D -Competitive r. Request for Quota PK-POSID-341483-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-1 Rehabilitation of G & F Pumpi IDA / 72500 Infrastructure Rehabilitation Post Limited 752,713.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP lementation 2 ng Station. D -Competitive Request for Quota PK-POSID-341485-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-1 Rehabilitation of Karampur Ri IDA / 72500 Infrastructure Rehabilitation Post Limited 527,885.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP lementation 2 ng Bund. D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-POSID-342908-CS-QCBS / Institutional Strengthening f Forensic Analysis of 2022 Flo Quality And Cost- Open - Internationa Pending Impleme IDA / 72500 or Resilience and Technical Prior 1,500,000.00 0.00 2023-02-16 2023-02-20 2023-04-06 2023-05-11 2023-06-10 2023-06-27 2023-07-07 2024-07-06 ods and Mitigation Options o Based Selection l ntation Assistance n the Right Bank of Indus. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-POSID-344014-CS-CDS / Institutional Strengthening f Development & Integration o Direct - Internation Pending Impleme IDA / 72500 or Resilience and Technical Post Direct Selection 949,373.00 0.00 2023-02-20 2023-03-01 2023-04-04 2024-04-02 f Kirthar Model and Operatio al ntation Assistance ns & Maintenance of Data Ce nter. Page 4