PROCUREMENT PLAN (Textual Part) Project information: São Tomé and Principe; STP Girls Empowerment and Quality Education for All Project; P169222 Project Implementation agency: Ministry of Education, with fiduciary functions to be carried by AFAP Date of the Procurement Plan: 15 June 2020 Period covered by this Procurement Plan: 15 June to 30 September 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used – Not applicable. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is Not applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information All Direct Contract will be prior reviewed during the first year of project’s implementation. At the end of that period, an assessment will be made to revise the requirement, if needed. PROCUREMENT Sao Tome and Principe : Girls Empowerment and Quality Education for All Project PLAN General Information Country: Sao Tome and Principe 2020-06-16 Bank’s Approval Date of the Original Procurement Plan: 2023-12-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169222 GPN Date: Project Name: Girls Empowerment and Quality Education for All Project Loan / Credit No: IDA / V3070, IDA / D7340, TF / B3318 Project Fiduciary and Administrative Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Project Coordination, Monito 04/W/GEE/2020 / Rehabilitati Solicitação de Cot Single Stage - One E 2021-04-0 IDA / V3070 ring and Evaluation, and Cap Posterior Open - National 30,000.00 27,416.49 Concluído 2020-08-16 2020-10-11 2020-10-13 on of PCU office in the MEES ações nvelope 9 acity Building 20/G/GEE/2020 / Rehabilitati Empowering Girls through th on and construction of bathr e Acquisition of Life Skills an Solicitação de Ofe Single Stage - One E 2021-10-0 IDA / V3070 Posterior Open - National 1,600,000.00 0.00 Cancelado 2020-12-21 2020-12-26 2021-02-06 2021-03-08 2021-04-12 ooms and water suplply in sc d the Promotion of a Safe Sc rtas nvelope 9 hools hool Environment Documento Nacio 48/W/GEE/2022 / Hiring a co nal de Licitação - Empowering Girls through th nstruction company to build processo de 1 env e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E 2023-01-2 a room (medium-sized physic IDA / D7340 Posterior Open - National elope (Document 47,539.74 52,420.20 Assinado 2022-05-29 2022-07-24 2022-09-12 d the Promotion of a Safe Sc ações nvelope 0 al space for backstage int th o Não Padrão do hool Environment e MEES) Banco Mundial - D ocumento Padrão de Aquisição Documento (DPA Nacio 68/W/GEE/2022 / MECC War ) de Licitação - nal Empowering Girls through th ehouse refurbishment works, processo de 1 env e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E 2023-11-0 to archive the AALEEB AND A IDA / D7340 Posterior Limited elope (Document 15,498.73 0.00 Concluído 2023-03-13 2022-12-09 2023-05-08 2023-02-12 d the Promotion of a Safe Sc ações nvelope 4 ALEES assessment instrumen o Não Padrão do hool Environment ts Banco Mundial - D ocumento Padrão de Aquisição (DPA 75/W/GEE/2023 / Hiring of a ) Solicitação de Ofe Civil Construction Company t Empowering Girls through th rtas - Pequenas O o carry out the Construction e Acquisition of Life Skills an Solicitação de Ofe Single Stage - One E bras Documento 2024-01-2 IDA / D7340 Posterior Open - National 1,831,758.37 0.00 Assinado 2023-04-04 2023-04-12 2023-04-09 2023-05-21 2023-06-16 2023-06-20 2023-09-05 2023-07-25 2023-10-04 and Rehabilitation of Bathroo d the Promotion of a Safe Sc rtas nvelope Padrão de Aquisiç 1 ms and Improvements to the hool Environment ão (DPA) - proces Infrastructures of Schools in so de 1 envelope São Tomé and Príncipe (1.1.2 ) 81/W/GEE/2023 / Hiring of a Civil Construction Company t Solicitação de Ofe o carry out the Construction Empowering Girls through th rtas - Pequenas O Em fase de I and Rehabilitation of Bathroo e Acquisition of Life Skills an Solicitação de Ofe Single Stage - One E bras Documento 2024-06-0 IDA / D7340 Posterior Open - National 1,790,849.80 0.00 mplementa 2023-08-22 2023-07-05 2023-08-27 2023-10-08 2023-11-07 2023-12-12 ms and Improvements to the d the Promotion of a Safe Sc rtas nvelope Padrão de Aquisiç 9 ção Infrastructures of Schools (Es hool Environment ão (DPA) - proces c. Basica Leal Bouças, Esc. B so de 1 envelope as.Venêncio Pires, Esc. Bas. Secun. Guadalup)in São Tom é and Príncipe GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 03/G/GEE/2020 / Acquisition Project Coordination, Monito Solicitação de Cot Single Stage - One E of officve furniture for PIU (Mi IDA / V3070 ring and Evaluation, and Cap Posterior Limited 3,000.00 4,322.05 Concluído 2020-05-05 2020-11-16 2020-06-30 2020-12-31 2020-12-27 2021-07-01 ações nvelope nistry of Education) acity Building Project Coordination, Monito 14/G/GEE/2020 / Purchase of Solicitação de Cot Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Posterior Limited 10,000.00 5,035.30 Concluído 2020-05-13 2020-04-21 2020-07-08 2020-07-22 2021-01-04 2020-08-25 ITC Equipments for DPIE ações nvelope acity Building Project Coordination, Monito 01/G/GEE/2020 / Axquisition Solicitação de Cot Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Posterior Open - National 50,000.00 60,391.62 Concluído 2020-08-01 2020-09-26 2020-12-11 2021-03-25 2021-02-27 of two (2) vehicles ações nvelope acity Building 02/G/GEE/2020 / Purchase of Project Coordination, Monito ITC equipment (5 Desktops, Solicitação de Cot Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Posterior Limited 15,500.00 17,018.05 Concluído 2020-08-29 2020-10-12 2020-10-24 2020-11-28 2021-04-22 2021-06-29 1 multifunction printer, 4 po ações nvelope acity Building wer stations, 2 laptops) for P CU 18/C/GEE/2020 / Editing and Empowering Girls through th Printing of communication m e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E IDA / V3070 Posterior Limited 50,000.00 0.00 Cancelado 2021-02-15 2021-04-12 2021-10-09 aterials (tamps, logos, etc.) f d the Promotion of a Safe Sc ações nvelope or PEREQT hool Environment Project Coordination, Monito 01/G/GEE/2021 / Aquisição d Solicitação de Cot Single Stage - One E IDA / V3070 ring and Evaluation, and Cap Posterior Limited 28,000.00 29,713.52 Concluído 2021-01-24 2021-01-20 2021-03-21 2021-01-27 2021-09-17 2021-06-21 e 19 Computadores Portáteis ações nvelope acity Building 37/G/GEE/2021 / Acquisition of 40 Tablets and Technology Equipment (2 video-conferen Solicitação de Cot Single Stage - One E IDA / D7340 Tackling Learning Poverty Posterior Limited 30,000.00 22,203.12 Concluído 2022-01-03 2021-06-30 2022-02-28 2021-08-30 2022-08-27 2021-10-29 cing systems and 4 Laptops) ações nvelope to support the implementatio n of Basic Education classroo m observation (TEACH) 46/G/GEE/2022 / Acquisition Project Coordination, Monito and installation of Generator Solicitação de Cot Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Posterior Limited 31,252.85 22,593.03 Concluído 2022-04-02 2022-03-16 2022-05-28 2022-07-09 2022-11-24 2022-08-27 and Electric Pump (including ações nvelope acity Building Construction of Generator Ho use). 44/G/GEE/2022 / Acquisition Project Coordination, Monito Solicitação de Cot Single Stage - One E of Equipment and Furniture f IDA / D7340 ring and Evaluation, and Cap Posterior Limited 12,770.22 0.00 Cancelado 2022-03-05 2022-03-01 2022-04-30 2022-10-27 ações nvelope or MEES acity Building Project Coordination, Monito 59/G/GEE/2022 / Purchasing Solicitação de Cot Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Posterior Limited 9,000.00 6,169.41 Concluído 2022-07-05 2022-07-22 2022-08-30 2022-09-27 2023-02-26 2023-01-05 a UPS for AFAP ações nvelope acity Building Empowering Girls through th 63/G/GEE/2022 / Acquisition e Acquisition of Life Skills an Solicitação de Ofe Single Stage - One E of 5 off-road vehicles to supe IDA / D7340 Posterior Open - National 211,168.60 0.00 Concluído 2022-09-21 2022-09-21 2022-09-26 2022-11-07 2022-11-03 2022-12-07 2022-11-15 2023-01-11 2022-11-30 2023-07-10 d the Promotion of a Safe Sc rtas nvelope rvise the Project's activities. hool Environment Page 1 49/G/GEE/2022 / Acquisition Empowering Girls through th of 4 vehicles to supervise the e Acquisition of Life Skills an Solicitação de Ofe Single Stage - One E IDA / D7340 Posterior Open - National 175,000.00 0.00 Cancelado 2022-05-20 2022-05-25 2022-07-06 2022-08-05 2022-09-09 2023-03-08 works of Bathrooms in School d the Promotion of a Safe Sc rtas nvelope s hool Environment Project Coordination, Monito 65/G/GEE/2022 / Supply of F Solicitação de Cot Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Posterior Limited 7,431.94 0.00 Concluído 2022-11-27 2022-11-07 2023-01-22 2022-12-14 2023-07-21 2023-04-07 urniture for MEES ações nvelope acity Building 66/G/GEE/2022 / Acquisition Project Coordination, Monito of equipment (CHARGER FOR Solicitação de Cot Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Posterior Limited 2,799.49 0.00 Concluído 2022-11-30 2022-11-04 2023-01-25 2022-12-14 2023-07-24 DIGITALCAMERA, AIR CONDIT ações nvelope acity Building IONING and PROJECTOR) for MEES 19/G/GEE/2020 / Design, edi Solicitação de Ofe Open - Internationa Single Stage - One E ting and printing of Teaching IDA / V3070 Tackling Learning Poverty Posterior 500,000.00 0.00 Cancelado 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2021-06-20 rtas l nvelope learning materials (TLMS) for Basic education 09/G/GEE/2020 / Editing and Contingency Emergency Res Solicitação de Cot Single Stage - One E IDA / V3070 Posterior Open - National 70,000.00 0.00 Cancelado 2023-01-04 2023-03-01 2023-08-28 printing of materials on COVI ponse Component (CERC) ações nvelope D19 17/G/GEE/2020 / Purchase of ITC equipments for schools (c Solicitação de Ofe Open - Internationa Single Stage - One E TF / B3318 Tackling Learning Poverty Posterior 700,000.00 0.00 Cancelado 2022-06-29 2022-07-04 2022-08-15 2022-09-14 2022-10-19 2023-04-17 omputers,printers, tablets, la rtas l nvelope ptops, power stations) (2.2.1) Empowering Girls through th 79/G/GEE/2023 / Providing e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E menstrual management prod IDA / D7340 Posterior Limited 30,000.00 0.00 Cancelado 2023-06-17 2023-08-12 2024-02-08 d the Promotion of a Safe Sc ações nvelope ucts/reusable pads (1.1.2) hool Environment Empowering Girls through th 83/G/GEE/2023 / Providing Em fase de I e Acquisition of Life Skills an Solicitação de Cot Open - Internationa Single Stage - One E menstrual management prod IDA / D7340 Posterior 30,000.00 0.00 mplementaç 2023-08-20 2023-08-28 2023-10-15 2024-04-12 d the Promotion of a Safe Sc ações l nvelope ucts/reusable pads ão hool Environment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 06/S/GEE/2020 / Updadte of Project Coordination, Monito Tompro for Eduication Projec IDA / V3070 ring and Evaluation, and Cap Posterior Aquisição Direta Direct 15,000.00 16,500.00 Concluído 2020-05-29 2021-05-28 2020-06-03 2021-05-31 2020-07-08 2021-06-22 2021-01-04 2021-07-15 t acity Building 37/NC/GEE/2020 / Editing an Empowering Girls through th d printing of communication e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E IDA / V3070 Posterior Limited 40,000.00 4,088.74 Concluído 2021-06-22 2021-09-10 2021-08-17 2021-11-18 2022-02-13 2021-12-18 materials (tamps, logos, etc.) d the Promotion of a Safe Sc ações nvelope for PEREQT hool Environment 18/S/GEE/2020 / Editing and Empowering Girls through th Printing of communication m e Acquisition of Life Skills an Solicitação de Cot Single Stage - One E IDA / V3070 Posterior Open - National 50,000.00 0.00 Cancelado 2021-03-15 2021-05-10 2021-11-06 aterials (tamps, logos, etc.) f d the Promotion of a Safe Sc ações nvelope or PEREQT hool Environment 05/G/GEE/220 / Internet Serv IDA / V3070 Tackling Learning Poverty Posterior Aquisição Direta Direct 20,000.00 0.00 Cancelado 2020-07-31 2020-08-05 2020-09-09 2021-03-08 ice for MEES Empowering Girls through th 60/S/GEE/2022 / Provision of e Acquisition of Life Skills an services to MEES/PEREQT in t IDA / D7340 Posterior Aquisição Direta Direct - National 72,750.00 72,750.00 Assinado 2022-08-30 2022-07-27 2022-09-04 2022-07-28 2022-10-09 2022-09-02 2023-04-07 d the Promotion of a Safe Sc he area of ​communication hool Environment Project Coordination, Monito 64/NC/GEE/2022 / TomPro S Direct - Internation IDA / V3070 ring and Evaluation, and Cap Posterior Aquisição Direta 10,000.00 0.00 Concluído 2022-10-06 2022-09-27 2022-10-11 2022-10-06 2022-11-15 2022-10-13 2023-05-14 2023-01-05 ystem Technical Support al acity Building Project Coordination, Monito 62/S/GEE/2022 / Provision of Solicitação de Cot Single Stage - One E IDA / D7340 ring and Evaluation, and Cap Posterior Limited 2,538.79 0.00 Concluído 2022-11-27 2022-11-04 2023-01-22 2022-12-27 2023-07-21 2023-02-01 Security Service for MEES ações nvelope acity Building CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 10/C/GEE/2020 / Capacity bu Project Coordination, Monito Seleção Baseada Open - Internationa ilding activity on large scale IDA / V3070 ring and Evaluation, and Cap Posterior nas Qualificações 80,000.00 0.00 Cancelado 2020-09-14 2020-10-05 2020-11-18 2020-12-18 2021-01-22 2021-07-21 l student learning assessment acity Building dos Consultores 27/C/GEE/2020 / TA to imple Seleção Baseada Open - Internationa ment the Professional develo IDA / V3070 Tackling Learning Poverty Posterior na Qualidade e Cu 350,000.00 0.00 Cancelado 2021-01-28 2021-02-18 2021-04-03 2021-05-01 2021-05-31 2021-07-05 2021-08-09 2022-08-09 l pment program for pre-schoo sto l teachers 26/C/GEE/2020 / TA to condu Seleção Baseada ct large-scale students learni Open - Internationa IDA / V3070 Tackling Learning Poverty Posterior na Qualidade e Cu 300,000.00 0.00 Cancelado 2021-04-22 2021-02-11 2021-05-13 2021-02-18 2021-06-26 2021-07-24 2021-08-23 2021-09-27 2021-11-01 2022-11-01 ng assessment in primary an l sto d secondarybschools (ALLEB and ALLES) 42/C/GEE/2022 / Selection a nd contracting of a Consultan Empowering Girls through th Seleção Baseada cy Office/Company to develo e Acquisition of Life Skills an IDA / V3070 Posterior nas Qualificações Open - National 79,296.00 30,764.97 Assinado 2022-01-26 2022-01-17 2022-02-16 2022-01-24 2022-04-01 2022-04-05 2022-05-01 2022-05-09 2022-06-05 2022-06-07 2022-12-02 2023-03-02 p architectural and structural d the Promotion of a Safe Sc dos Consultores projects for the construction hool Environment and rehabilitation of bathroo ms in schools 45/C/GEE/2022 / Hiring a co Project Coordination, Monito Seleção Baseada mpany to teach the English c IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações Open - National 24,000.00 24,773.57 Assinado 2022-03-30 2022-03-14 2022-04-20 2022-06-03 2022-06-06 2022-07-03 2022-08-08 2022-08-07 2022-09-02 2023-02-03 ourse for MEES´s Technicians acity Building dos Consultores . Empowering Girls through th 29/C/GEE/2020 / TA to imple Seleção Baseada e Acquisition of Life Skills an Open - Internationa ment the Girls' Empweremen IDA / V3070 Posterior na Qualidade e Cu 220,000.00 0.00 Cancelado 2021-01-04 2021-01-25 2021-03-10 2021-04-07 2021-05-07 2021-06-11 2021-07-16 2022-07-16 d the Promotion of a Safe Sc l t Program sto hool Environment Page 2 28/C/GEE/2020 / TA to imple ment the Professional Develo Seleção Baseada Open - Internationa Em fase de Imple pment Program for Elementa IDA / D7340 Tackling Learning Poverty Prévia na Qualidade e Cu 1,840,000.00 0.00 2022-06-30 2022-11-21 2022-07-21 2023-04-25 2022-09-03 2022-10-01 2022-10-31 2022-12-05 2023-01-09 2024-01-09 l mentação ry School Teachers (Elaborati sto on of Structured Materials) 55/C/GEE/2022 / Project com Project Coordination, Monito Seleção Baseada munication strategy (Educati IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações Open - National 52,500.00 0.00 Cancelado 2022-06-24 2022-07-15 2022-08-28 2022-09-27 2022-11-01 2023-04-30 on Strengthening, Inclusive E acity Building dos Consultores ducation) 61/C/GEE/2022 / PREPARATI Project Coordination, Monito Seleção Baseada Open - Internationa ON OF ENVIRONMENTAL AND IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações 35,843.00 0.00 Concluído 2022-08-30 2022-07-20 2022-09-20 2022-08-02 2022-11-03 2022-11-11 2022-12-03 2023-03-09 2023-01-07 2023-04-24 2023-07-06 2023-11-16 l SOCIAL MANAGEMENT PLANS acity Building dos Consultores (ESMP) 69/C/GEE/2022 / Technical A ssistance to develop process Empowering Girls through th es and actions that promote Seleção Baseada e Acquisition of Life Skills an Open - Internationa a more sustainable, safe and IDA / D7340 Posterior nas Qualificações 65,127.00 0.00 Assinado 2023-01-10 2022-12-19 2023-01-31 2022-12-22 2023-03-16 2023-03-30 2023-04-15 2023-06-15 2023-05-20 2023-07-18 2023-11-16 d the Promotion of a Safe Sc l inclusive school environment dos Consultores hool Environment , as well as strategies for adv ocacy and behavior change i n schools in STP (Wash) 71/C/GEE/2023 / Hiring an in stitution to revise the Teache Seleção Baseada rs' Management Policy in São Open - Internationa Em fase de Imple IDA / D7340 Tackling Learning Poverty Posterior na Qualidade e Cu 460,000.00 0.00 2023-08-22 2023-03-17 2023-09-12 2023-03-20 2023-10-26 2023-07-27 2023-11-23 2023-12-23 2024-01-27 2024-03-02 2025-03-02 Tomé and Príncipe and carry l mentação sto out training, certification in s chool leadership for manager s and supervisors. 72/C/GEE/2023 / Hiring a Offi Empowering Girls through th Seleção Baseada ce/Company to supervise the e Acquisition of Life Skills an TF / B3318 Posterior nas Qualificações Open - National 213,578.27 0.00 Assinado 2023-10-24 2023-04-12 2023-11-14 2023-12-28 2023-07-25 2024-01-27 2023-09-22 2024-03-02 2023-10-20 2024-08-29 Works of Construction and R d the Promotion of a Safe Sc dos Consultores ehabilitation of Bathrooms in hool Environment Schools (1.1.2) 74/C/GEE/2023 / Hiring a TA to develop an integrated tec Seleção Baseada hnological system that make Reaching the Most Vulnerabl Implementação P IDA / D7340 Posterior nas Qualificações Open - National 80,000.00 0.00 2023-11-29 2023-12-20 2024-02-02 2024-03-03 2024-04-07 2024-10-04 s it possible to cross-referenc e endente dos Consultores e the database of both sector s (MECC and Social Protectio n) (3.3.3) 22/C/GEE/2020 / Adaptation Project Coordination, Monito Seleção Baseada Open - Internationa and supervision of data colle IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações 140,000.00 0.00 Cancelado 2022-11-29 2022-11-14 2022-12-20 2022-11-15 2023-02-02 2023-02-20 2023-03-04 2023-04-08 2023-10-05 l ction to baseline using MELQ acity Building dos Consultores O 84/C/GEE/2023 / Hiring a Offi ce/Company to supervise the Empowering Girls through th Works of Construction and R Seleção Baseada e Acquisition of Life Skills an Em fase de Imple ehabilitation of Bathrooms ( IDA / D7340 Posterior nas Qualificações Open - National 106,789.14 0.00 2023-08-22 2023-08-23 2023-09-12 2023-10-26 2023-11-25 2023-12-30 2024-06-27 d the Promotion of a Safe Sc mentação Esc. Basica Leal Bouças, Esc. dos Consultores hool Environment Bas.Venêncio Pires, Esc. Bas. Secun. Guadalup) in São Tom é and Príncipe 78/C/GEE/2023 / STRENGTH EN THE CAPACITY OF PUBLIC Empowering Girls through th Seleção Baseada SCHOOLS AND GIRLS, ESPECI e Acquisition of Life Skills an Open - Internationa IDA / D7340 Posterior na Qualidade e Cu 252,303.00 0.00 Cancelado 2023-05-23 2023-05-23 2023-06-13 2023-05-23 2023-07-27 2023-08-24 2023-09-23 2023-10-28 2023-12-02 2024-12-01 ALLY THE MOST VULNERABLE d the Promotion of a Safe Sc l sto , TO MANAGE MENSTRUATIO hool Environment N WITH DIGNITY AND IN A SA FE ENVIRONMENT (1.1.2) 53/C/GEE/2022 / T.A to prom Project Coordination, Monito Seleção Baseada ote Inclusive Education that r Open - Internationa IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações 145,000.00 0.00 Cancelado 2022-06-30 2022-07-21 2022-09-03 2022-10-03 2022-11-07 2023-05-06 esponds to the challenges of l acity Building dos Consultores the Framework Law 23/C/GEE/2020 / Technical A Seleção Baseada Open - Internationa ssistance for implementation TF / B3318 Tackling Learning Poverty Posterior na Qualidade e Cu 210,000.00 0.00 Cancelado 2023-06-21 2023-07-12 2023-08-25 2023-09-22 2023-10-22 2023-11-26 2023-12-31 2024-12-30 l of the accelerated Education sto Program (3.3.1) 54/C/GEE/2022 / Hiring a co Project Coordination, Monito Seleção Baseada Open - Internationa nsultancy to update the Scho IDA / D7340 ring and Evaluation, and Cap Posterior nas Qualificações 50,000.00 0.00 Cancelado 2023-09-27 2023-10-18 2023-12-01 2023-12-31 2024-02-04 2024-08-02 l ol Charter (4.4.2) acity Building dos Consultores 70/C/GEE/2022 / T.A TO STR ENGTHEN THE IMPLEMENTAT Project Coordination, Monito Seleção Baseada Open - Internationa ION OF THE DEVELOPMENT S TF / B3318 ring and Evaluation, and Cap Posterior na Qualidade e Cu 291,852.00 0.00 Cancelado 2023-07-25 2023-08-15 2023-09-28 2023-10-26 2023-11-25 2023-12-30 2024-02-03 2025-02-02 l TRATEGY FOR SPECIAL EDUC acity Building sto ATION IN SÃO TOMÉ AND PRÍ NCIPE. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 11/C/GEE/2020 / Technical a Project Coordination, Monito ssistance to elaborate the En IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 40,000.00 0.00 Cancelado 2020-07-19 2020-09-06 2020-09-27 2020-11-01 2021-04-30 vironmental and Social Fram acity Building ework instruments 13/C/GEE/2020 / Technical a Project Coordination, Monito ssistance for training and for IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 40,000.00 0.00 Cancelado 2020-06-26 2020-08-14 2020-09-04 2020-10-09 2021-04-07 providing specialized support acity Building to the statics staff 08/CGEE/2020 / Hiring Envir Project Coordination, Monito onmental and Social Develop IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 32,000.00 39,150.00 Assinado 2020-05-14 2020-12-04 2020-07-02 2021-03-05 2020-07-23 2021-03-24 2020-08-27 2021-04-15 2021-02-23 ment specialist for PIU (MEES acity Building ) 07/C/GEE/2020 / Hiring Moni Project Coordination, Monito toring and Evaluation speciali IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 32,000.00 0.00 Cancelado 2020-07-13 2020-07-10 2020-08-31 2020-08-06 2020-09-21 2020-10-26 2021-04-24 st acity Building Project Coordination, Monito 15/C/GEE/2020 / Hiring a Pro IDA / V3070 ring and Evaluation, and Cap Posterior Individual Open 100,000.00 0.00 Cancelado 2020-06-30 2020-07-06 2020-08-18 2020-09-10 2020-09-08 2020-10-13 2021-04-11 ject Management Expert acity Building Empowering Girls through th 16/C/GEE/2020 / Hiring a Co e Acquisition of Life Skills an IDA / V3070 Posterior Individual Open 35,000.00 0.00 Cancelado 2020-07-03 2020-07-10 2020-08-21 2020-09-11 2020-10-16 2021-04-14 ordinator for PCU d the Promotion of a Safe Sc hool Environment Page 3 30/C/GEE/2020 / Technical a Project Coordination, Monito Seleção Direta de ssistance to elaborate the en IDA / V3070 ring and Evaluation, and Cap Posterior Direct 40,000.00 15,000.00 Concluído 2020-08-14 2020-08-14 2020-08-24 2020-08-10 2020-10-28 2020-09-06 2021-04-26 2021-12-25 Consultores vironmental &Social framewo acity Building rk instruments Empowering Girls through th 31/C/GEE/2020 / Hiring Moni e Acquisition of Life Skills an toring and Evaluation speciali IDA / V3070 Posterior Individual Open 32,000.00 68,232.60 Assinado 2020-10-08 2020-09-30 2020-11-26 2020-11-04 2020-12-17 2020-11-17 2021-01-21 2020-12-18 2021-07-20 d the Promotion of a Safe Sc st hool Environment Empowering Girls through th 32/C/GEE/2020 / Hiring a Co e Acquisition of Life Skills an IDA / V3070 Posterior Individual Open 35,000.00 16,200.00 Assinado 2020-10-08 2020-09-29 2020-11-26 2020-11-27 2020-12-17 2020-11-30 2021-01-21 2020-12-18 2021-07-20 ordinator for PCU d the Promotion of a Safe Sc hool Environment Empowering Girls through th 33/C/GEE/2020 / Hiring a Pro e Acquisition of Life Skills an IDA / V3070 Posterior Individual Open 100,000.00 93,176.52 Concluído 2020-10-13 2020-09-30 2020-12-01 2020-11-17 2020-12-22 2020-11-24 2021-01-26 2020-12-07 2021-07-25 2021-12-02 ject Management Expert d the Promotion of a Safe Sc hool Environment Empowering Girls through th 36/C/GEE/2020 / Design of c e Acquisition of Life Skills an ommunication materials (ta IDA / V3070 Posterior Individual Limited 10,000.00 13,750.00 Concluído 2021-04-05 2021-03-18 2021-04-10 2021-03-22 2021-05-01 2021-05-17 2021-06-05 2021-06-04 2021-12-02 2021-11-25 d the Promotion of a Safe Sc mps, logos, etc.) for PEREQT hool Environment 35/C/GEE/2020 / TA to condu ct Large-Scale Students Lear Seleção Direta de IDA / D7340 Tackling Learning Poverty Prévia Direct 300,000.00 327,424.09 Assinado 2021-03-31 2021-03-29 2021-04-10 2021-03-30 2021-06-14 2022-02-04 2021-12-11 ning Assessment in Primary a Consultores nd Secondarybschools (AALE B AND AALES) 34/C/GEE/2020 / Techical As Seleção Direta de sistance to conduct the Lear IDA / D7340 Tackling Learning Poverty Prévia Direct 290,000.00 141,459.43 Assinado 2021-03-31 2021-03-30 2021-04-10 2021-04-15 2021-06-14 2021-12-19 2021-12-11 Consultores ning Assessment PASEC Empowering Girls through th 08/C/GEE/2021 / Hiring a Co e Acquisition of Life Skills an IDA / V3070 Posterior Individual Open 32,000.00 45,000.00 Assinado 2021-06-10 2021-06-07 2021-07-29 2021-08-06 2021-08-19 2021-08-19 2021-09-23 2021-09-03 2022-03-22 ordinator for PCU d the Promotion of a Safe Sc hool Environment Empowering Girls through th 09/C/GEE/2021 / Hiring Civil e Acquisition of Life Skills an IDA / D7340 Posterior Individual Open 26,400.00 0.00 Cancelado 2021-09-28 2021-06-09 2021-11-16 2021-12-07 2022-01-11 2022-07-10 Construction Engineer d the Promotion of a Safe Sc hool Environment Empowering Girls through th 38/C/GEE/2021 / Hiring a Civ e Acquisition of Life Skills an IDA / D7340 Posterior Individual Open 33,840.00 48,600.00 Assinado 2021-07-28 2021-06-23 2021-09-15 2021-09-29 2021-10-06 2021-10-06 2021-11-10 2021-10-13 2022-05-09 il Construction Engineer d the Promotion of a Safe Sc hool Environment 39/C/GEE/2021 / TECHNICAL ASSISTANCE FOR TRAINING A ND SUPPORT IN DATA ANALY IDA / D7340 Tackling Learning Poverty Posterior Individual Open 42,500.00 0.00 Cancelado 2021-09-22 2021-06-23 2021-11-10 2021-12-01 2022-01-05 2022-07-04 SIS FOR THE STATISTICS AND EDUCATIONAL EVALUATION T EAM 40/C/GEE/2021 / Hiring an in Project Coordination, Monito dividual consultant to survey IDA / D7340 ring and Evaluation, and Cap Posterior Individual Limited 2,500.00 2,500.00 Concluído 2021-09-22 2021-09-08 2021-09-27 2021-09-10 2021-10-18 2021-10-18 2021-11-22 2021-10-23 2022-05-21 2021-12-11 the conditions of the MEES el acity Building ectrical system 41/C/GEE/2021 / TA FOR TRA INING PRESCHOOL EDUCATIO N TEACHERS, CONCEPTION, Seleção Direta de IDA / V3070 Tackling Learning Poverty Posterior Direct 1,151,003.00 1,151,003.00 Assinado 2021-12-20 2021-12-17 2021-12-30 2021-12-20 2022-03-05 2022-02-02 2022-09-01 CONSTRUCTION AND ACQUIS Consultores ITION OF SUPPORT MATERIAL S FOR THE TEACHING AND LE ARNING OF CHILDREN 43/C/GEE/2022 / TECHNICAL ASSISTANCE FOR TRAINING A ND SUPPORT IN DATA ANALY IDA / D7340 Tackling Learning Poverty Posterior Individual Open 78,200.00 75,167.84 Assinado 2022-01-26 2022-01-17 2022-03-16 2022-04-27 2022-04-06 2022-06-13 2022-05-11 2022-07-13 2022-11-07 SIS FOR THE EDUCATIONAL S TATISTICS AND EVALUATION TEAM IN SAO TOME AND PRI NCIPE Empowering Girls through th 56/C/GEE/2022 / Financial M e Acquisition of Life Skills an IDA / D7340 Posterior Individual Direct 45,627.24 45,627.24 Assinado 2022-04-18 2022-05-19 2022-04-28 2022-06-13 2022-05-19 2022-06-14 2022-06-23 2022-06-28 2022-12-20 anager for AFAP d the Promotion of a Safe Sc hool Environment Empowering Girls through th 58/C/GEE/2022 / Senior Acco e Acquisition of Life Skills an IDA / D7340 Posterior Individual Direct 32,340.00 32,340.00 Assinado 2022-04-18 2022-05-19 2022-04-28 2022-06-13 2022-05-19 2022-06-14 2022-06-23 2022-06-28 2022-12-20 untant for AFAP d the Promotion of a Safe Sc hool Environment Empowering Girls through th 57/C/GEE/2022 / Specialist i e Acquisition of Life Skills an n Environmental and Social S IDA / D7340 Posterior Individual Direct 44,465.76 0.00 Em Análise 2022-04-18 2022-05-20 2022-04-28 2022-05-19 2022-06-23 2022-12-20 d the Promotion of a Safe Sc afeguards for AFAP hool Environment Empowering Girls through th 47/C/GEE/2022 / TA to imple e Acquisition of Life Skills an Seleção Direta de ment the Girls' Empweremen IDA / D7340 Posterior Direct 761,584.00 726,207.00 Assinado 2022-06-28 2022-05-10 2022-07-08 2022-05-19 2022-09-11 2022-06-06 2023-03-10 d the Promotion of a Safe Sc Consultores t Program hool Environment Project Coordination, Monito 76/C/GEE/2023 / Hiring a GB IDA / D7340 ring and Evaluation, and Cap Posterior Individual Limited 32,000.00 0.00 Cancelado 2023-04-05 2023-04-10 2023-05-01 2023-06-05 2023-12-02 V specialist (4.4.1) acity Building Project Coordination, Monito 77/C/GEE/2023 / Hiring a GB Seleção Direta de IDA / D7340 ring and Evaluation, and Cap Posterior Direct - National 32,000.00 0.00 Assinado 2023-05-10 2023-05-02 2023-05-20 2023-05-03 2023-07-24 2023-05-12 2024-01-20 V specialist (4.4.1) Consultores acity Building 80/C/GEE/2023 / Data Cente Project Coordination, Monito r Design and Specifications f TF / B3318 ring and Evaluation, and Cap Posterior Individual Limited 5,000.00 0.00 Concluído 2023-06-13 2023-06-01 2023-06-18 2023-06-06 2023-07-09 2023-08-28 2023-08-13 2023-08-29 2024-02-09 2023-10-13 or Ministry of Education of Sa acity Building o Tome and Principe 82/C/GEE/2023 / Project Audi Project Coordination, Monito Seleção Direta de Direct - Internation t for the years 2022, 2023 an IDA / D7340 ring and Evaluation, and Cap Posterior 9,634.00 0.00 Assinado 2023-07-03 2022-12-28 2023-07-13 2023-06-26 2023-09-16 2023-08-29 2024-03-14 Consultores al d 2024. acity Building Project Coordination, Monito 67/C/GEE/2022 / Project Audi Seleção Direta de Direct - Internation TF / B3318 ring and Evaluation, and Cap Posterior 19,000.00 0.00 Cancelado 2022-11-11 2022-11-21 2023-01-25 2023-07-24 t Consultores al acity Building Page 4 Empowering Girls through th 85/C/GEE/2023 / Hiring Moni e Acquisition of Life Skills an toring and Evaluation speciali IDA / D7340 Posterior Individual Open - National 32,000.00 0.00 Assinado 2023-08-22 2023-08-23 2023-10-10 2023-10-02 2023-10-31 2023-10-03 2023-12-05 2023-10-24 2024-06-02 d the Promotion of a Safe Sc st hool Environment 24/C/GEE/2020 / TA to imple Reaching the Most Vulnerabl ment an Early warning syste IDA / V3070 Posterior Individual Open 199,000.00 0.00 Cancelado 2020-12-16 2021-02-03 2021-02-24 2021-03-31 2021-09-27 e m to signal students in learn dificulties 86/C/GEE/2023 / Datacenter Project Coordination, Monito Seleção Direta de Direct - Internation Update and design of the dat TF / B3318 ring and Evaluation, and Cap Posterior 3,750.00 0.00 Em Análise 2024-01-12 2023-12-20 2024-01-22 2024-03-27 2024-09-23 Consultores al a network of the 5 MECC buil acity Building dings in STP 88/C/GEE/2023 / Contrataçã Project Coordination, Monito Implementação P o de um(a) (1) Engº/ª Civil Sé IDA / D7340 ring and Evaluation, and Cap Posterior Individual Open - National 32,400.00 0.00 2024-01-16 2024-03-05 2024-03-26 2024-04-30 2024-10-27 endente nior acity Building 87/C/GEE/2023 / Contrataçã Project Coordination, Monito Implementação P o de um(a) (1) Engº/ª Civil Jú IDA / D7340 ring and Evaluation, and Cap Posterior Individual Open - National 21,600.00 0.00 2024-01-15 2024-03-04 2024-03-25 2024-04-29 2024-10-26 endente nior acity Building Page 5