PROCUREMENT PLAN (Textual Part) Project information: [West Bank and Gaza] [Digital West Bank and Gaza Project] [P-174355] Project Implementation agency: [Ministry of Telecommunication and Information Technology] [High Council for Public Procurement Policies] Date of the Procurement Plan: [April-2021] Period covered by this Procurement Plan: [April-2021 – December- 2026] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods). Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; PROCUREMENT West Bank and Gaza : Digital West Bank & Gaza Project PLAN General Information Country: West Bank and Gaza 2021-07-08 Bank’s Approval Date of the Original Procurement Plan: 2023-12-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174355 GPN Date: 2021-07-26 Project Name: Digital West Bank & Gaza Project Loan / Credit No: TF / B5236 Ministry of Telecommunication and Information Technology Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MTIT-249273-GO-RFQ / I Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 0.00 Canceled 2021-08-31 2021-09-21 2021-10-26 2021-12-07 T and Office equipment for th gement and Implementation tions nvelope e PMU Staff Support GZ-MTIT-249275-GO-RFQ / O Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 7,495.00 Completed 2021-08-24 2021-06-16 2021-10-19 2021-10-05 2021-11-30 2022-03-04 ffice Furniture for the PMU St gement and Implementation tions nvelope aff Support GZ-MTIT-259158-GO-RFQ / I Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 28,535.12 Signed 2021-10-26 2021-10-21 2021-12-21 2022-01-08 2022-02-01 T and Office equipment for th gement and Implementation tions nvelope e PMU Staff Support GZ-MTIT-238970-GO-RFB / P Component 2 – Implementin urchase of bandwidth capacit g Digital infrastructure soluti Open - Internationa Single Stage - One E TF / B5236 Post Request for Bids 0.00 Canceled 2022-02-15 2022-02-20 2022-04-03 2022-05-03 2022-06-07 2023-06-07 y for targeted and selected P ons for Emergency response l nvelope ost offices , recovery and resilience GZ-MTIT-313003-GO-RFQ / V Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 0.00 Canceled 2022-09-10 2022-09-25 2022-11-05 2023-05-04 ehicle for PMU use gement and Implementation tions nvelope Support GZ-MTIT-270833-GO-RFQ / C Component 4 – Project Mana Request for Quota Single Stage - One E onference Room Multimedia TF / B5236 gement and Implementation Post Limited 0.00 Canceled 2023-01-21 2023-03-18 2023-04-29 tions nvelope and Sound system renovatio Support n GZ-MTIT-269714-GO-RFQ / C Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 0.00 Canceled 2023-01-21 2023-03-18 2023-04-29 onference Room Furniture re gement and Implementation tions nvelope novation Support GZ-MTIT-324517-GO-RFQ / O Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 0.00 Signed 2022-11-11 2022-12-07 2023-01-06 2023-05-23 2023-02-17 ffice Furniture for the PMU St gement and Implementation tions nvelope aff - 2 Support GZ-MTIT-325510-GO-RFQ / V Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 0.00 Canceled 2022-11-18 2022-11-30 2023-01-13 2023-07-12 ehicles for PMU use gement and Implementation tions nvelope Support GZ-MTIT-325743-GO-RFB / S Component 2 – Implementin upply, Installation and Traini g Digital infrastructure soluti Open - Internationa Single Stage - One E Under Imple TF / B5236 Prior Request for Bids 0.00 2022-12-15 2023-01-17 2023-01-14 2023-02-26 2023-02-25 2023-05-15 2023-04-08 2023-09-24 2023-05-13 2024-01-08 ng of an Emergency Respons ons for Emergency response l nvelope mentation e Center Solution , recovery and resilience GZ-MTIT-339073-GO-RFQ / I Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 0.00 Signed 2023-02-10 2023-03-02 2023-04-07 2023-07-12 2023-06-06 T and Office equipment for th gement and Implementation tions nvelope e PMU Staff Support GZ-MTIT-325510-GO-RFQ- / Component 4 – Project Mana Request for Quota Single Stage - One E TF / B5236 Post Limited 0.00 Signed 2022-11-11 2022-11-30 2023-02-01 2023-03-10 2023-04-02 Supply of Vehicles for PMU us gement and Implementation tions nvelope e- Support GZ-MTIT-237282-GO-RFQ / P Component 1 – Enabling leg Request for Quota Single Stage - One E urchase of IT and Office equi TF / B5236 al and regulatory environme Post Limited 0.00 Canceled 2023-09-06 2023-11-01 2023-12-31 tions nvelope pment for TRA & CA nt for Digital Economy GZ-MTIT-393112-GO-RFQ / 2 Component 4 – Project Mana Request for Quota Single Stage - One E Under Imple TF / B5236 Post Open - National 0.00 2023-11-24 2024-01-19 2024-03-04 Laptops for TRA gement and Implementation tions nvelope mentation Support GZ-MTIT-398487-GO-RFQ / M Component 3 – Fostering Us Request for Quota Single Stage - One E Pending Impl TF / B5236 Post Limited 0.00 2023-12-20 2024-01-31 2024-05-30 inistry of Heath Datacenter er centered e-Service deliver tions nvelope ementation y NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MTIT-284843-NC-RFB / P Component 2 – Implementin urchase of bandwidth capacit g Digital infrastructure soluti Single Stage - One E TF / B5236 Post Request for Bids Open - National 0.00 Signed 2022-03-24 2022-04-03 2022-03-29 2022-05-10 2022-05-23 2022-06-09 2022-08-04 2022-07-14 2022-10-26 2025-07-13 y for targeted and selected P ons for Emergency response nvelope ost offices , recovery and resilience CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MTIT-236773-CS-QCBS / I Component 1 – Enabling leg nstitutional & Regulatory Fra Quality And Cost- Open - Internationa TF / B5236 al and regulatory environme Post 0.00 Signed 2021-10-01 2021-10-10 2021-10-22 2021-11-18 2021-12-05 2022-01-30 2022-01-02 2022-03-14 2022-02-01 2022-04-20 2022-03-08 2022-06-26 2022-04-12 2022-08-26 2023-04-12 mework for the Root Certifica Based Selection l nt for Digital Economy tion Authority (CA) GZ-MTIT-238972-CS-QCBS / Component 3 – Fostering Us Development of a whole of g Quality And Cost- Open - Internationa TF / B5236 er centered e-Service deliver Post 0.00 Signed 2021-10-01 2021-11-21 2021-10-22 2021-12-08 2021-12-05 2022-03-13 2022-01-02 2022-04-25 2022-02-01 2022-05-15 2022-03-08 2022-07-19 2022-04-12 2022-11-07 2022-10-09 overnment strategy and acti Based Selection l y on plan for digitalization of g overnment. GZ-MTIT-258635-CS-QCBS / Component 4 – Project Mana Quality And Cost- Financial audit for the project TF / B5236 gement and Implementation Post Open - National 11,000.00 Signed 2021-11-10 2021-11-22 2021-12-01 2022-01-14 2021-12-05 2022-02-11 2022-01-04 2022-03-13 2022-02-01 2022-04-17 2022-02-19 2022-05-22 2022-03-14 2023-11-13 Based Selection for the fiscal years of (2021- Support 2022) Page 1 GZ-MTIT-235500-CS-QCBS / Component 1 – Enabling leg Develop Institutional Framew Quality And Cost- Open - Internationa TF / B5236 al and regulatory environme Post 0.00 Canceled 2022-03-01 2022-03-09 2022-03-22 2022-05-05 2022-06-02 2022-07-02 2022-08-06 2022-09-10 2023-03-09 ork for Telecom. & Info. Tech Based Selection l nt for Digital Economy Regulatory Authority (TITRA) GZ-MTIT-238971-CS-QCBS / Recruitment of a consulting fi rm and transaction adviser fo Component 2 – Implementin r the recruitment of an opera g Digital infrastructure soluti Quality And Cost- Open - Internationa TF / B5236 Prior 0.00 Canceled 2022-02-01 2022-02-22 2022-04-07 2022-05-05 2022-06-04 2022-07-09 2022-08-13 2023-08-13 tor in charge of the manage ons for Emergency response Based Selection l ment, marketing, commercial , recovery and resilience ization of the optical fiber tel ecommunication network of t he JEDCO GZ-MTIT-238973-CS-QCBS / Component 3 – Fostering Us Quality And Cost- Open - Internationa e-Government Service Invent TF / B5236 er centered e-Service deliver Post 0.00 Signed 2022-01-10 2021-12-23 2022-01-31 2022-01-09 2022-03-16 2022-03-20 2022-04-13 2022-05-16 2022-05-13 2022-07-07 2022-06-17 2022-09-07 2022-07-22 2022-11-19 2022-12-19 Based Selection l ory and Prioritization y GZ-MTIT-284819-CS-QCBS / Component 1 – Enabling leg Develop Institutional Framew Quality And Cost- Open - Internationa TF / B5236 al and regulatory environme Post 0.00 Canceled 2022-03-16 2022-03-22 2022-04-06 2022-04-12 2022-05-07 2022-08-30 2022-06-18 2022-10-17 2022-07-18 2023-01-17 2022-08-15 2022-09-19 2023-05-17 ork for Telecommunications Based Selection l nt for Digital Economy Regulatory Authority (TRA) GZ-MTIT-309964-CS-CQS / F Component 3 – Fostering Us Consultant Qualifi easibility Study for Assisted P TF / B5236 er centered e-Service deliver Post Open - National 0.00 Signed 2022-08-20 2022-08-23 2022-09-10 2022-10-24 2022-12-18 2022-11-23 2023-03-20 2022-12-28 2023-03-28 2023-06-26 cation Selection ost Offices to be Digital Acce y ss Points GZ-MTIT-238963-CS-QCBS / Component 2 – Implementin Development of Emergency g Digital infrastructure soluti Quality And Cost- Open - Internationa TF / B5236 Post 0.00 Canceled 2022-11-01 2022-11-22 2023-01-05 2023-02-02 2023-03-04 2023-04-08 2023-05-13 2023-11-09 Management Framework & A ons for Emergency response Based Selection l ction Plan , recovery and resilience GZ-MTIT-325509-CS-QCBS / Component 1 – Enabling leg Quality And Cost- Open - Internationa Cybersecurity National Legal TF / B5236 al and regulatory environme Post 0.00 Canceled 2022-11-13 2022-11-16 2022-12-04 2023-01-17 2023-02-14 2023-03-16 2023-04-20 2023-05-25 2023-11-21 Based Selection l Reform nt for Digital Economy GZ-MTIT-330337-CS-QCBS / Component 1 – Enabling leg Updating the Enabling Legal Quality And Cost- Open - Internationa TF / B5236 al and regulatory environme Post 0.00 Canceled 2022-12-06 2022-12-06 2022-12-13 2022-12-25 2023-01-26 2023-03-20 2023-02-23 2023-07-10 2023-03-25 2023-04-29 2023-06-03 2023-11-30 Environment for the Digital E Based Selection l nt for Digital Economy conomy in Palestine GZ-MTIT-366626-CS-QCBS / Component 4 – Project Mana Quality And Cost- Under Implement Financial audit for the project TF / B5236 gement and Implementation Post Open - National 0.00 2023-08-01 2023-09-19 2023-08-22 2023-10-05 2023-11-02 2023-12-02 2024-01-06 2024-02-10 2026-02-09 Based Selection ation for the fiscal years of (2023- Support 2024) GZ-MTIT-237280-CS-QCBS / Component 1 – Enabling leg Quality And Cost- Open - Internationa Cybersecurity National Risk A TF / B5236 al and regulatory environme Post 0.00 Canceled 2023-07-10 2023-07-31 2023-09-13 2023-10-11 2023-11-10 2023-12-15 2024-01-19 2024-09-15 Based Selection l ssessment & Maturity Model nt for Digital Economy Analysis GZ-MTIT-237279-CS-QCBS / Review and update of existin Component 1 – Enabling leg Quality And Cost- Open - Internationa Pending Impleme g Telecommunication policy, TF / B5236 al and regulatory environme Post 0.00 2024-02-15 2024-03-07 2024-04-20 2024-05-18 2024-06-17 2024-07-22 2024-08-26 2025-08-26 Based Selection l ntation regulatory frameworks and t nt for Digital Economy he development of new byla ws GZ-MTIT-237281-CS-CQS / C Component 1 – Enabling leg Consultant Qualifi Under Implement apacity Building for Cybersec TF / B5236 al and regulatory environme Post Open - National 0.00 2023-11-20 2023-11-28 2023-12-11 2024-01-24 2024-02-23 2024-03-29 2024-09-25 cation Selection ation urity nt for Digital Economy INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-MTIT-238968-CS-INDV / Recruitment of a consultant f Component 2 – Implementin or the preparation of the bid g Digital infrastructure soluti Individual Consult TF / B5236 Post Open 23,200.00 Completed 2021-08-01 2021-08-12 2021-09-19 2021-09-27 2021-10-10 2021-10-17 2021-11-14 2021-11-04 2022-05-13 2022-09-08 ding documentation for the p ons for Emergency response ant Selection urchase of bandwidth capacit , recovery and resilience y for targeted and selected P ost offices GZ-MTIT-239013-CS-INDV / P Component 4 – Project Mana MU Director/Full time (for on Individual Consult TF / B5236 gement and Implementation Post Limited 45,008.44 Signed 2021-06-10 2021-01-08 2021-06-15 2021-02-16 2021-07-06 2021-02-18 2021-08-10 2021-04-20 2022-08-10 e year extendable for the wh ant Selection Support ole project period) GZ-MTIT-239014-CS-INDV / P Component 4 – Project Mana rocurement Specialist/Full ti Individual Consult TF / B5236 gement and Implementation Post Limited 37,063.92 Signed 2021-06-10 2021-01-08 2021-06-15 2021-02-25 2021-07-06 2021-03-21 2021-08-10 2021-07-05 2022-08-10 me (for one year extendable ant Selection Support for the whole project period) GZ-MTIT-239015-CS-INDV / F Component 4 – Project Mana inancial Management Special Individual Consult TF / B5236 gement and Implementation Post Limited 18,753.52 Signed 2021-06-10 2021-01-08 2021-06-15 2021-03-10 2021-07-06 2021-03-14 2021-08-10 2021-09-06 2022-08-10 ist/full time (for one year ext ant Selection Support endable for the whole project period) GZ-MTIT-239016-CS-INDV / Component 4 – Project Mana Individual Consult TF / B5236 Post Open 18,000.00 Signed 2021-06-20 2021-04-28 2021-08-08 2021-07-26 2021-08-29 2021-08-30 2021-10-03 2021-11-21 2022-10-03 Admin Officer / Full Time gement and Implementation ant Selection Support GZ-MTIT-239017-CS-INDV / E Component 4 – Project Mana Individual Consult nvironmental and Social Spe TF / B5236 gement and Implementation Post Open 31,200.00 Signed 2021-06-20 2021-04-28 2021-08-08 2021-07-26 2021-08-29 2021-09-08 2021-10-03 2021-12-06 2022-10-03 ant Selection cialist/Full time Support GZ-MTIT-239376-CS-INDV / Component 4 – Project Mana Individual Consult Monitoring and evaluation sp TF / B5236 gement and Implementation Post Open 31,200.00 Signed 2021-06-20 2021-04-28 2021-08-08 2021-08-08 2021-08-29 2021-09-07 2021-10-03 2021-11-05 2022-10-03 ant Selection ecialist / Full time Support GZ-MTIT-240476-CS-INDV / Component 4 – Project Mana Individual Consult Digital transformation expert TF / B5236 gement and Implementation Post Limited 50,000.00 Completed 2021-06-20 2021-07-05 2021-06-25 2021-07-27 2021-07-16 2021-08-02 2021-08-20 2021-09-17 2022-02-16 2022-01-05 ant Selection / Short term contract Support GZ-MTIT-249633-CS-INDV / Recruitment of Digital Transf Component 4 – Project Mana Individual Consult ormation Specialist - full time TF / B5236 gement and Implementation Post Open 36,000.00 Signed 2021-08-25 2021-01-08 2021-10-13 2021-07-27 2021-11-03 2021-09-02 2021-12-08 2022-01-18 2022-12-08 ant Selection (for one year extendable for t Support he whole project period) GZ-MTIT-260884-CS-INDV / Component 4 – Project Mana Individual Consult TF / B5236 Post Open 0.00 Signed 2022-02-01 2022-02-08 2022-03-22 2022-09-04 2022-04-12 2022-10-23 2022-05-17 2022-11-22 2023-05-17 Communication Officer gement and Implementation ant Selection Support Page 2 GZ-MTIT-260159-CS-INDV / L Component 1 – Enabling leg Individual Consult egal Advisor to prepare for TI TF / B5236 al and regulatory environme Post Limited 0.00 Canceled 2022-01-01 2022-01-06 2022-01-27 2022-03-03 2022-08-30 ant Selection TRA establishment nt for Digital Economy GZ-MTIT-273471-CS-INDV / Component 2 – Implementin National Emergency Respons g Digital infrastructure soluti Individual Consult TF / B5236 Post Open 100,000.00 Signed 2022-02-01 2022-01-29 2022-03-22 2022-05-15 2022-04-12 2022-06-07 2022-05-17 2022-08-03 2022-11-13 e Center - ERC Protocol Cons ons for Emergency response ant Selection ultant , recovery and resilience GZ-MTIT-237283-CS-CQS / D Component 2 – Implementin esign of the component for N g Digital infrastructure soluti Individual Consult TF / B5236 Post Open 0.00 Canceled 2021-12-01 2021-09-14 2022-01-19 2022-02-09 2022-03-16 2022-06-14 ational Emergency Managem ons for Emergency response ant Selection ent Systems , recovery and resilience GZ-MTIT-273764-CS-INDV / Component 4 – Project Mana Individual Consult TF / B5236 Post Direct 42,910.78 Signed 2022-03-15 2022-03-28 2022-03-25 2022-03-30 2022-03-30 2022-04-05 2022-04-15 2022-04-29 2023-04-15 Renewal of PMU Director Con gement and Implementation ant Selection tract Support GZ-MTIT-274054-CS-INDV / Component 4 – Project Mana Individual Consult Renewal of Financial Manage TF / B5236 gement and Implementation Post Direct 36,761.33 Signed 2022-02-28 2022-03-28 2022-03-10 2022-03-30 2022-03-15 2022-03-30 2022-04-01 2022-04-05 2023-04-01 ant Selection ment Specialist Contract Support GZ-MTIT-277721-CS-INDV / L Component 1 – Enabling leg Individual Consult egal Advisor to prepare for T TF / B5236 al and regulatory environme Post Open 50,000.00 Signed 2022-02-08 2022-02-10 2022-03-29 2022-05-26 2022-04-19 2022-06-07 2022-05-24 2022-07-10 2022-10-21 ant Selection RA establishment nt for Digital Economy GZ-MTIT-279547-CS-INDV / Component 1 – Enabling leg Individual Consult National Table of Frequency TF / B5236 al and regulatory environme Post Open 100,000.00 Signed 2022-03-08 2022-04-24 2022-04-26 2022-06-02 2022-05-17 2022-06-19 2022-06-21 2022-07-15 2023-04-17 ant Selection Allocations (NTFA) Consultan nt for Digital Economy t GZ-MTIT-299420-CS-INDV / Component 4 – Project Mana Individual Consult Renewal of Procurement Spe TF / B5236 gement and Implementation Post Direct 35,576.64 Signed 2022-06-15 2022-06-19 2022-06-19 2022-06-23 2022-06-21 2022-07-25 2022-07-01 2022-07-15 2023-07-01 ant Selection cialist Contract Support GZ-MTIT-320268-CS-INDV / Component 4 – Project Mana Individual Consult TF / B5236 Post Open - National 0.00 Signed 2022-10-12 2022-10-31 2022-11-30 2022-12-14 2022-12-21 2023-01-03 2023-01-25 2023-01-26 2024-01-25 Monitoring and evaluation sp gement and Implementation ant Selection ecialist Support GZ-MTIT-324577-CS-INDV / Component 4 – Project Mana Individual Consult Renewal of Environmental an TF / B5236 gement and Implementation Post Direct - National 0.00 Signed 2022-11-10 2022-11-17 2022-11-17 2022-11-24 2022-11-19 2022-11-24 2022-12-01 2023-02-13 2023-12-01 ant Selection d Social Specialist Contract Support GZ-MTIT-325508-CS-INDV / Component 4 – Project Mana Individual Consult Renewal of Digital Transform TF / B5236 gement and Implementation Post Direct - National 0.00 Signed 2022-11-15 2022-11-20 2022-11-25 2022-11-27 2022-12-02 2022-12-04 2023-01-01 2023-01-11 2023-12-31 ant Selection ation Specialist Contract Support GZ-MTIT-326266-CS-INDV / Component 4 – Project Mana Individual Consult TF / B5236 Post Direct - National 0.00 Signed 2022-11-13 2022-11-13 2022-11-13 2022-11-13 2022-11-13 2022-11-13 2022-11-13 2022-11-09 2023-11-13 Renewal of Admin Officer Co gement and Implementation ant Selection ntract Support GZ-MTIT-331837-CS-INDV / Component 1 – Enabling leg Individual Consult Open - Internationa Quality of Telecom Services ( TF / B5236 al and regulatory environme Post 0.00 Canceled 2022-12-18 2022-12-19 2023-02-05 2023-03-26 2023-02-26 2023-05-22 2023-04-02 2023-05-22 ant Selection l QoS)Technical Assistance nt for Digital Economy GZ-MTIT-347256-CS-INDV / Component 4 – Project Mana Individual Consult Renewal of Financial Manage TF / B5236 gement and Implementation Post Direct - National 0.00 Signed 2023-03-07 2023-03-07 2023-03-17 2023-03-17 2023-03-22 2023-03-22 2023-04-01 2023-04-09 2024-03-31 ant Selection ment Specialist Contract - 20 Support 23 GZ-MTIT-347257-CS-INDV / Component 4 – Project Mana Individual Consult Renewal of PMU Director Con TF / B5236 gement and Implementation Post Direct - National 0.00 Signed 2023-03-12 2023-03-12 2023-03-22 2023-03-20 2023-03-27 2023-03-25 2023-04-15 2023-04-22 2024-04-14 ant Selection tract - 2023 Support Component 1 – Enabling leg GZ-MTIT-269713-CS-INDV / 4 Individual Consult TF / B5236 al and regulatory environme Post Open 0.00 Canceled 2022-01-15 2021-12-23 2022-03-05 2022-03-11 2022-03-26 2022-04-30 2023-04-30 G Technical Advisor ant Selection nt for Digital Economy GZ-MTIT-372145-CS-INDV / E Component 4 – Project Mana Individual Consult Under Implement TF / B5236 Post Open - National 0.00 2023-07-16 2023-08-20 2023-08-17 2023-08-31 2023-09-24 2024-09-23 nvironmental and Social Spe gement and Implementation ant Selection ation cialist Support GZ-MTIT-376183-CS-INDV / Component 4 – Project Mana Individual Consult Renewal of Procurement Spe TF / B5236 gement and Implementation Post Direct - National 0.00 Signed 2023-06-01 2023-06-01 2023-06-11 2023-06-11 2023-06-16 2023-06-15 2023-07-01 2023-07-02 2024-06-30 ant Selection cialist Contract 2023 Support GZ-MTIT-378020-CS-INDV / P Component 4 – Project Mana Individual Consult Under Implement TF / B5236 Post Open - National 0.00 2023-08-21 2023-09-06 2023-09-22 2023-09-26 2023-10-10 2024-10-09 MU Director gement and Implementation ant Selection ation Support GZ-MTIT-391623-CS-INDV / Component 4 – Project Mana Individual Consult Under Implement Renewal of Admin Officer Co TF / B5236 gement and Implementation Post Direct - National 0.00 2023-10-15 2023-10-15 2023-10-25 2023-10-30 2023-11-15 2024-11-14 ant Selection ation ntract -2023 Support GZ-MTIT-391523-CS-INDV / Component 4 – Project Mana Individual Consult Under Implement Renewal of Communication O TF / B5236 gement and Implementation Post Direct - National 0.00 2023-10-01 2023-10-01 2023-10-11 2023-10-16 2023-11-01 2024-10-31 ant Selection ation fficer Contract -2023 Support GZ-MTIT-399518-CS-INDV / Component 4 – Project Mana Individual Consult Pending Impleme Renewal of Monitoring and E TF / B5236 gement and Implementation Post Direct - National 0.00 2023-12-22 2023-12-28 2024-01-04 2024-01-17 2025-01-16 ant Selection ntation valuation Specialist Contract Support 2024 GZ-MTIT-399500-CS-INDV / Component 4 – Project Mana Individual Consult Pending Impleme Renewal of Digital Transform TF / B5236 gement and Implementation Post Direct - National 0.00 2023-12-01 2023-12-11 2023-12-16 2024-01-01 2024-12-31 ant Selection ntation ation Specialist Contract 202 Support 4 Page 3