The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Bangladesh Modern Food Storage Facilities Project (P120583) SOUTH ASIA | Bangladesh | Agriculture and Food Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 22 | ARCHIVED on 22-Dec-2023 | ISR59482 | Implementing Agencies: Directorate General of Food, Ministry of Food, Government of Bangladesh Key Dates Key Project Dates Bank Approval Date: 30-Dec-2013 Effectiveness Date: 27-May-2014 Planned Mid Term Review Date: 05-Mar-2018 Actual Mid-Term Review Date: 07-May-2018 Original Closing Date: 30-Jun-2020 Revised Closing Date: 31-Dec-2024 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The overall Project development objective is to increase the grain reserve available to households to meet their post-disaster needs and improve the efficiency of grain storage management. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component A – Construction of Modern Grain Storage Silo Facilities:(Cost $323.08 M) Component B – Support for Food and Market Planning and Monitoring Program:(Cost $52.00 M) Component C - Project management, Construction Supervision, Technical Assistance, Training and Strategic Studies:(Cost $45.07 M) Component D - Contingent Emergency Response (CERC) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The following key issues and actions were identified during this Implementation Support Mission (November 16-28, 2023):  Expedite completion of remaining silo constructions: Constructions of all remaining silos (Narayanganj, Barishal, Chattogram, Ashuganj and Kulna) are experiencing delays. The mission requested PMU to conduct very close monitoring including monthly field visits and follow up meetings with contractors, expedite any pending approvals and payments to ensure completion of these sites before the Project closing date (December 31, 2024)  Finalize the Food Stocks and Market Monitoring System (FSMMMS). The FSMMS pilots are under implementation in Rajsahi division and Chattogram district before the system goes live. 12/22/2023 Page 1 of 7 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583)  Operational continuity of the project without any managemental gap during the rest of project life as well as retaining key personnel/consultants towards the proper closing: DG Food is requested to fill the vacant position at the PMU and to keep the key consultants including financial management, procurement/contract management, safeguards specialists until the project closing date.  Start planning for the project closure with adequate focus on evaluating project’s impacts: Given the project is approaching to the final year of its life, PMU was advised to start preparing project closure including adequate analysis of project’s outcomes. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial Substantial Macroeconomic -- Substantial Substantial Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and -- Substantial Substantial Sustainability Fiduciary -- Substantial Substantial Environment and Social -- Substantial Substantial Stakeholders -- Moderate Moderate Other -- Substantial Substantial Overall -- Substantial Substantial Results PDO Indicators by Objectives / Outcomes 1. To increase the grain reserve available to households IN01387210 ►P1. Increased grain storage capacity in public and household storage facilities (Metric ton, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 28,000.00 28,000.00 400,000.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 Distribution of 500,000 household silo (HHS) with 56 kg capacity completed as of 30 Nov, 2019. Hence, Comments: total HHS capacity is 500,000*56=28,000 Tones IN01387466 12/22/2023 Page 2 of 7 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) ►P2. Direct Project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,560,000.00 2,560,000.00 10,000,000.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 IN01387468 Of which female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 48.00 48.00 50.00 2. To improve the efficiency of grain storage management IN01387467 ►P3. Reduction in grain storage and handling losses in public storage facilities (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 Intermediate Results Indicators by Components Component A – Construction of Modern Grain Storage Silo Facilities IN01387469 ►A1. Site development works completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 8.00 8.00 7.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 IN01387472 ►A2. Public food grain silo constructed and operational (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 Mymensingh and Madhupur silos are completed but not yet handed over to DG Food for operation. Comments: IN01387475 ►A3. Households provided with safe grain storage containers (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 12/22/2023 Page 3 of 7 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Value 0.00 500,000.00 500,000.00 500,000.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 30-Jun-2020 IN01387478 ►A4. Percentage women employed in construction of steel silos (relative to total labor force employed) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 10.00 7.00 12.00 Date 30-Nov-2018 31-Oct-2021 19-Dec-2023 31-Dec-2024 IN01387480 ►A5. Targeted beneficiaries satisfied with the household silos (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 98.00 90.00 90.00 Date 30-Nov-2018 31-Oct-2021 19-Dec-2023 31-Dec-2024 IN01387481 Of which female (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 98.00 90.00 90.00 Date 30-Nov-2018 31-Oct-2021 19-Dec-2023 31-Dec-2024 IN01387482 ►A6. Contractor workforce received training on Gender-Based Violence/ SEA (percentage of total contractor workforce) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 100.00 Date 30-Nov-2018 31-Oct-2021 19-Dec-2023 31-Dec-2024 Component B – Support for Food and Market Planning and Monitoring Program IN01387470 ►B1. CSDs and LSDs connected to a centralized public food storage and distribution management system (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 40.00 80.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 Current value for B1 indictor is corrected to 0. Comments: IN01387473 ►B2. Research papers completed and approved by FPMU (Number, Custom) 12/22/2023 Page 4 of 7 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12.00 16.00 15.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 IN01387476 ►B3. Policy notes prepared under the Food Policy Reasearch Program published (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 8.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 Component C - Project management, Construction Supervision, Technical Assistance, Training and Strategic Studies IN01387471 ►C1. Client days of training provided by gender (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 128,051.00 138,820.00 200,000.00 Date 01-Feb-2014 31-Oct-2021 19-Dec-2023 31-Dec-2024 IN01387474 % of female (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 45.34 45.00 25.00 IN01387477 ►C2. People living in the adjacent areas of steel silos are aware and satisfied with the presence and benefits of steel silos (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 30-Nov-2018 31-Oct-2021 19-Dec-2023 31-Dec-2024 Information for this indicator will be provided by the Citizen Report Card surveys to be undertaken Comments: by a third-party monitoring firm when silos will be erected and operational. IN01387479 Of which female (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 05-Apr-2020 31-Oct-2021 19-Dec-2023 31-Dec-2024 Performance-Based Conditions 12/22/2023 Page 5 of 7 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P120583 IDA-52650 Effective USD 210.00 210.00 0.00 158.84 29.83 84% P120583 IDA-67260 Effective USD 202.00 202.00 0.00 83.71 115.35 42% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P120583 IDA-52650 Effective 30-Dec-2013 07-Apr-2014 27-May-2014 30-Jun-2020 31-Dec-2024 P120583 IDA-67260 Effective 31-Jul-2020 19-Oct-2020 27-Oct-2020 31-Oct-2023 31-Dec-2024 Cumulative Disbursements 12/22/2023 Page 6 of 7 The World Bank Implementation Status & Results Report Bangladesh Modern Food Storage Facilities Project (P120583) Restructuring History Level 2 Approved on 19-Aug-2015 ,Level 2 Approved on 12-Feb-2020 ,Level 2 Approved on 18-Sep-2023 Related Project(s) P168484-Additional Financing For Modern Food Storage Facilities Project 12/22/2023 Page 7 of 7