The World Bank                                                                                     Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)



Bhutan Human Capital Recovery and Resilience Project (P174399)


 SOUTH ASIA | Bhutan | Social Protection & Jobs Global Practice | Requesting Unit: SACBB | Responsible Unit: HSASP
 IBRD/IDA | Program-for-Results Financing | FY 2022 | Team Leader(s): Jumana Jamal Subhi Alaref, T. M. Asaduzzaman


 Seq No: 4 | ARCHIVED on 14-Dec-2023 | ISR59147 | Created by: Jumana Jamal Subhi Alaref on 04-Dec-2023 | Modified by: Jumana Jamal Subhi
 Alaref on 14-Dec-2023


 Program Development Objectives

  PDO Table
  Program Development Objective (from Program Appraisal Document)
  Support building, protecting, and utilizing human capital in Bhutan

 Overall Ratings

 Name                                                                          Previous Rating                        Current Rating

 Progress towards achievement of PDO                                           Moderately Satisfactory               Moderately Satisfactory
 Overall Implementation Progress (IP)                                          Moderately Satisfactory               Moderately Satisfactory


 Implementation Status and Key Decisions

  The HCRRP Mid-Term Review (MTR), conducted on September 6, 2023, found that the HCRRP has achieved important results since it became
  effective. One PDO indicator out of five has been achieved (digitization of education for improved student outcomes). Work is ongoing for the rest of
  intermediary and outcome indicators, with progress expected during the second and third year of implementation.



 Data on Financial Performance


 Disbursements (by loan)

 Project       Loan/Credit/TF     Status       Currency         Original    Revised     Cancelled     Disbursed     Undisbursed             % Disbursed


 P174399       IDA-70290          Effective    USD                20.00       20.00           0.00         8.13            10.92                    43%


 Key Dates (by loan)

 Project        Loan/Credit/TF     Status      Approval Date        Signing Date      Effectiveness Date    Orig. Closing Date     Rev. Closing Date

 P174399        IDA-70290          Effective   03-Feb-2022          07-Mar-2022       30-Mar-2022           31-Jan-2025            31-Jan-2025


 DLI Disbursement

                                                                                           Achievement     Disbursed amount in      Disbursement % for
 DLI ID      DLI Type       Description                   Coc              DLI Amount
                                                                                           Status          Coc                      DLI

 Loan: IDA70290-001




12/14/2023                                                                                                                   Page 1 of 18
        The World Bank                                                                                     Implementation Status & Results Report
        Bhutan Human Capital Recovery and Resilience Project (P174399)




                         DLI#1:Strengthening
  1           Regular                                 XDR           2,150,000.00       Not Achieved                    0.00
                         quality of ECCD serv
                         DLI#2:Expansion of ECCD
  2           Regular                            XDR                  700,000.00       Not Achieved                    0.00
                         in targ populati
                         DLI#3:ICT in edu fr                                           Partially
  3           Regular                                 XDR           3,600,000.00                              2,489,782.03                   69 %
                         learning reco& imp a                                          Achieved
                         DLI#4:Bldng climate
  4           Regular                                 XDR             700,000.00       Not Achieved                    0.00
                         change res thru edu
                         DLI#5:Enhanced incl                                           Partially
  5           Regular                                 XDR           1,800,000.00                              1,060,306.71                   59 %
                         under SDP                                                     Achieved
                         DLI#6:Increased                                               Partially
  6           Regular                                 XDR           2,150,000.00                              1,065,491.44                   50 %
                         employmnt post SDP                                            Achieved
                         DLI#7:Improved quality of                                     Partially
  7           Regular                                 XDR             700,000.00                                211,493.14                   30 %
                         entrepren supp                                                Achieved
                         DLI#8:Strgth sys to enh                                       Partially
  8           Regular                                 XDR           1,800,000.00                              1,258,081.98                   70 %
                         emp sup MOLHR                                                 Achieved
                         DLI#9:Training in climate
  9           Regular                                 XDR             700,000.00       Not Achieved                    0.00
                         resp initiativ

 Program Action Plan

  Action Description          ECCD - Evaluation and targeting methodologies developed and approved

  Source                      DLI#                   Responsibility           Timing                  Timing Value             Status

  Technical                   DLI 2                  MoESD                    Other                   End of year 1            Delayed

                              Impact eval. designed to assess child development and women’s economic empowerment (WEE). Process eval.
                              designed to assess implementation fidelity, quality, uptake, and WEE. Targeting methods developed for
  Completion Measurement      rural/poor/deprived communities.



  Comments                    Impact evaluation will likely be replaced by a process evaluation.



  Action Description          ECCD - Evaluation and targeting methodologies implemented

  Source                      DLI#                   Responsibility           Timing                  Timing Value             Status

  Technical                   DLI 2                  MoESD                    Other                   End of year 3            Not Yet Due

                              1. Baseline data collected, analyzed, and disseminated
                              2. Process evaluation of ECCD services completed
  Completion Measurement
                              3. National enrollment data disaggregated to identify rural populations and poor/deprived communities using targeting
                              methodology

  Comments                    Impact evaluation will likely be replaced by a process evaluation.



  Action Description          ECCD - Community communications and capacity building plans implemented




12/14/2023                                                                                                               Page 2 of 18
        The World Bank                                                                                      Implementation Status & Results Report
        Bhutan Human Capital Recovery and Resilience Project (P174399)




  Source                     DLI#                   Responsibility            Timing                  Timing Value                Status

  Technical                  DLI 2                  MoESD                     Other                   End of year 2               Not Yet Due

                             1. Communications outreach strategy (developed as part of the National ECCD Action Plan) is being rolled out
  Completion Measurement
                             2. Capacity building plan for parents to effectively support ECCD services has been developed and is being rolled out

  Comments



                             MoESD clarifies how ECCD facilitators for private ECCD provision can access training for the Basic Certificate in
  Action Description
                             ECCD

  Source                     DLI#                   Responsibility            Timing                  Timing Value                Status

  Technical                  DLI 1                  MoE                       Other                   End of year 2               Not Yet Due

                             This should include (i) clarifications on the training requirements for those working in private ECCD provision; (ii)
  Completion Measurement
                             ways to access the training for the Basic Certificate in ECCD.

  Comments



  Action Description         Instructional guides for all subjects for competency-based curriculum prepared and disseminated

  Source                     DLI#                   Responsibility            Timing                  Timing Value                Status

  Technical                  DLI 3                  MoESD                     Other                   End of year 1               Completed

  Completion Measurement     Instructional guidelines will have to be based on the newly approved curriculum covering all subjects

                             Completed. The curriculum frameworks and Instructional Guides for all the subjects are uploaded on the
                             Department's website- www.rec.gov.bt
  Comments




                             Tracer study of outcomes from the first 7 months of SDP implementation is conducted to establish baselines for DLIS
  Action Description
                             on inclusion and employment outcomes

  Source                     DLI#                   Responsibility            Timing                  Timing Value                Status

  Technical                  DLI 6                  MoESD                     Other                   February 15, 2023           Completed

                             Data collection instrument is prepared with no objection from the World Bank; Data is collected; key findings
  Completion Measurement
                             approved by MoESD and shared with the World Bank

                             This is complete and baseline values established. The WB team received access to baseline data and completed
  Comments
                             report from the TVET MIS MoESD team.



                             Approval of revisions on SDP budget, operational design and implementation plan based on process evaluation,
  Action Description
                             tracking system (tracer surveys), study under DLI5 and GRM assessments by MoESD

  Source                     DLI#                   Responsibility            Timing                  Timing Value                Status



12/14/2023                                                                                                                 Page 3 of 18
        The World Bank                                                                                 Implementation Status & Results Report
        Bhutan Human Capital Recovery and Resilience Project (P174399)




  Technical                  DLI 8                 MoESD and MoF           Other                  yearly                     In Progress

                             Approved Minutes of the MoESD and MoF meeting, Revised SDP Operational Manual and Implementation plan , and
  Completion Measurement
                             documents shared with the Bank.

                             SDP POM was revised to reflect the changes to the TVET MIS that includes the single intake window (the Bhutan
  Comments                   Labor Market Information System), the tracer survey, and the approval of the TVET strategy to improve women's
                             enrolment in this sector.



                             Enhance SDP linkages with entrepreneurship support provided under MoICE led portion of Start-Up and Cottage and
  Action Description
                             Small Industries (CSI) flagship.

  Source                     DLI#                  Responsibility          Timing                 Timing Value               Status

                             DLI 7                                                                One year after
  Technical                                        MoICE                   Other                                             In Progress
                                                                                                  effectiveness

  Completion Measurement     Approved report with linkage strategy developed by MolCE and shared with the Bank

                             By January, MoICE Department of Employment and Entrepreneurship to update the outreach section for each
  Comments
                             center’s business plans to focus on attracting SDP graduates



  Action Description         Approved MoESD plan for green jobs and mainstream climate resilience in employment support programs.

  Source                     DLI#                  Responsibility          Timing                 Timing Value               Status

                             DLI 9                                                                3rd year after
  Technical                                        MoESD                   Other                                             Not Yet Due
                                                                                                  effectiveness

                             Approved operational plan for green jobs and mainstreaming of climate resilience developed by MoESD based on the
  Completion Measurement
                             operational strategy and shared with the Bank for no objection prior to distribution

  Comments



  Action Description         Designate Environmental and Social Focal Points/Consultants (with ES experience and background) for the Program

  Source                     DLI#                  Responsibility          Timing                 Timing Value               Status

  Environmental and Social
                                                   MoESD and MoICE         Recurrent              Yearly                     Completed
  Systems

                             There is at least one staff/consultant per ministry whose performance agreement includes duties of an environmental
  Completion Measurement
                             focal point and one/consultant per ministry whose performance agreement includes duties of a social focal point

  Comments



                             Use and strengthen existing Grievance Redress Mechanism (GRM) including addressing GBV issues if or
  Action Description
                             development of a new GRM in absence of existing GRM, if necessary

  Source                     DLI#                  Responsibility          Timing                 Timing Value               Status




12/14/2023                                                                                                            Page 4 of 18
        The World Bank                                                                                    Implementation Status & Results Report
        Bhutan Human Capital Recovery and Resilience Project (P174399)




  Environmental and Social
                                                    MoESD and MoICE         Recurrent               Semi-Annually               In Progress
  Systems

  Completion Measurement     Each ministry produces annual GRM reports that include coverage of GBV issues

  Comments



  Action Description         Citizen Engagement and Stakeholder Engagement (One Communication Consultant/Focal Point for each ministry)

  Source                     DLI#                   Responsibility          Timing                  Timing Value                Status

  Environmental and Social
                                                    MoESD and MoICE         Recurrent               Yearly                      In Progress
  Systems

                             There is at least one staff/consultant per ministries whose annual performance agreement includes duties around
  Completion Measurement
                             citizen and stakeholder engagement

  Comments



                             Strengthening of institutional capacity for safeguards management of both Ministries through training for ES
  Action Description
                             personnel provided by the Bank

  Source                     DLI#                   Responsibility          Timing                  Timing Value                Status

  Environmental and Social
                                                    MoESD and MoICE         Due Date                27-May-2022                 In Progress
  Systems

                             World Bank has provided training to relevant personnel in both ministries (with mandatory inclusion of social,
  Completion Measurement
                             environmental and stakeholder engagement focal points)

                             The WB provided training on ESF issues twice, one in February, 2023, and the recent training took place on June 13,
  Comments
                             2023 in Thimphu



  Action Description         Actions taken at the TTIs to offset the adverse effects of COVID-19

  Source                     DLI#                   Responsibility          Timing                  Timing Value                Status

  Environmental and Social
                                                    MoESD                   Due Date                27-May-2022                 Completed
  Systems

                             World Bank receives a detailed list of actions taken to offset the adverse effects of COVID-19 in TTIs along with the
  Completion Measurement
                             action plan in case of new outbreaks from MoESD

  Comments



  Action Description         Actions taken at ECCD centers to offset the adverse effects of COVID-19

  Source                     DLI#                   Responsibility          Timing                  Timing Value                Status

  Environmental and Social
                                                    MoESD                   Due Date                27-May-2022                 Completed
  Systems


12/14/2023                                                                                                               Page 5 of 18
        The World Bank                                                                                  Implementation Status & Results Report
        Bhutan Human Capital Recovery and Resilience Project (P174399)




                             World Bank receives a list of actions taken at ECCD centers to offset the impacts of COVID-19 along with the action
  Completion Measurement
                             plan for safe operation in case of new outbreaks prepared by MOE

  Comments



  Action Description         Nominate focal points for implementation

  Source                     DLI#                  Responsibility           Timing                 Timing Value                Status

                                                                                                   Within three months
                                                   MOF, MoESD,
  Fiduciary Systems                                                         Other                  from the date of            Completed
                                                   MoICE
                                                                                                   effectiveness

  Completion Measurement     Each ministry is represented by a focal point responsible for coordination on implementation and reporting

  Comments



                             Implementing agencies agree not to award contracts under the Program to any of the Bank debarred or suspended
  Action Description
                             persons or entities

  Source                     DLI#                  Responsibility           Timing                 Timing Value                Status

  Fiduciary Systems                                MoESD, MoICE             Recurrent              Semi-Annually               In Progress

                             MoICE and MoESD prepare and submit for the World Bank review semi-annual reports on procurement under the
  Completion Measurement
                             Program to ensure that contracts are not awarded to any of the Bank debarred or suspended persons or entities.

                             WB team received confirmation from MoICE on June 20, 2023 that none of the contracts for activities supported by
  Comments
                             the HCRRP so far have been awarded to any of the Bank debarred or suspended persons or entities.



  Action Description         MOF receives reports of complaints from the Anti-Corruption Commission and shares them with the World Bank

  Source                     DLI#                  Responsibility           Timing                 Timing Value                Status

  Fiduciary Systems                                MOF                      Recurrent              Semi-Annually               In Progress

                             MOF prepares semi-annual reports on complains from Anti-Corruption Commission and submits them to the World
  Completion Measurement
                             Bank for review

  Comments



  Action Description         Awareness and communication materials on ICT in education are distributed to parents

  Source                     DLI#                  Responsibility           Timing                 Timing Value                Status

  Technical                  DLI 3                 MoESD                    Other                  End of Year 1               In Progress

                             MOE prepares awareness and communication materials on ICT in education to reduce the digital divide and improve
  Completion Measurement
                             education equity and build system resilience.




12/14/2023                                                                                                               Page 6 of 18
        The World Bank                                                                                    Implementation Status & Results Report
        Bhutan Human Capital Recovery and Resilience Project (P174399)




                             In progress. This will ne addressed along with the training program for 1000 teachers in year 2
  Comments




                             The MoICE and MoESD to identify focal point officials responsible for ensuring that Program activities are
  Action Description         implemented in accordance with the provisions of WB ACGs and agreed protocols.



  Source                     DLI#                   Responsibility          Timing                   Timing Value               Status

  Environmental and Social                                                                           Six months after
                                                    MoESD, MoICE            Other                                               Completed
  Systems                                                                                            effectiveness

                             Focal points nominations are communicated to the WB team. Roles, responsibilities, and ACG protocols are outlined
  Completion Measurement
                             in the Implementation Guidance Note.

  Comments



                             Budget for improve ECCD access under DLI 2 will be released by MoF in the first quarter of every year as per plan
  Action Description
                             submitted by MoESD to achieve DLR and program targets

  Source                     DLI#                   Responsibility          Timing                   Timing Value               Status

  Fiduciary Systems          DLI 2                  Ministry of Finance     Recurrent                Yearly                     Not Yet Due

  Completion Measurement     Relevant budget released based on the request by MoESD on time

  Comments



                             Budget for improved local connectivity under DLI 3 will be released by MoF in the first quarter of every year as per
  Action Description
                             plan submitted by MoESD to achieve DLR and program targets

  Source                     DLI#                   Responsibility          Timing                   Timing Value               Status

  Fiduciary Systems          DLI 3                  Ministry of Finance     Recurrent                Yearly                     Not Yet Due

  Completion Measurement     Relevant budget released based on the request by MoESD on time

  Comments



                             Budget for WASH activities under DLI 10 will be released by MoF in the first quarter of every year as per plan
  Action Description
                             submitted by MoESD to achieve DLR and program targets

  Source                     DLI#                   Responsibility          Timing                   Timing Value               Status

  Fiduciary Systems          DLI 10                 Ministry of Finance     Recurrent                Yearly                     Not Yet Due

  Completion Measurement     Relevant budget released based on the request by MoESD on time

  Comments




12/14/2023                                                                                                               Page 7 of 18
          The World Bank                                                                                         Implementation Status & Results Report
          Bhutan Human Capital Recovery and Resilience Project (P174399)




                               List of ECCD centers which will undergo renovation, upgradation and new establishment will be shared with World
  Action Description           Bank for review and finalization



  Source                       DLI#                    Responsibility            Timing                      Timing Value            Status

  Technical                    DLI 2                   DoSE (MoE)                Due Date                    15-Aug-2023             Not Yet Due

  Completion Measurement       By a report including selection criteria and a list of final target schools

  Comments



                               List of schools receiving ICT equipment and connectivity support will be shared with World Bank for review and
  Action Description
                               finalization

  Source                       DLI#                    Responsibility            Timing                      Timing Value            Status

  Technical                    DLI 3                   DoSE (MoE)                Due Date                    15-Aug-2023             Completed

  Completion Measurement       By a report including selection criteria and a list of final target schools

  Comments                     MoESD submitted the list of schools based on remoteness and internet connectivity to distribute ICT equipment



  Action Description           Selection criteria and list of schools for the WASH program will be shared with World Bank for review and finalization

  Source                       DLI#                    Responsibility            Timing                      Timing Value            Status

  Technical                    DLI 10                  DEP (MoE)                 Due Date                    15-Aug-2023             Completed

  Completion Measurement       By a report including selection criteria and a list of final target schools

  Comments                     This has been shared with the WB.



                               Tender bid document for procurement pertaining to ECCD centers will be shared with World Bank for review and
  Action Description           comments



  Source                       DLI#                    Responsibility            Timing                      Timing Value            Status

  Fiduciary Systems            DLI 2                   DoSE (MoE)                Due Date                    15-Aug-2023             Delayed

  Completion Measurement       A report including a proof of tendering bid document for procurement pertaining to ECCD centers

  Comments                     This is yet to be shared with the WB team, who are following up.




  Risks


 Systematic Operations Risk-rating Tool




12/14/2023                                                                                                                     Page 8 of 18
            The World Bank                                                                                     Implementation Status & Results Report
            Bhutan Human Capital Recovery and Resilience Project (P174399)




  Risk Category                                             Rating at Approval              Previous Rating                Current Rating

  Political and Governance                                  Moderate                       Moderate                      Moderate
  Macroeconomic                                             Substantial                    Substantial                   Substantial
  Sector Strategies and Policies                            Moderate                       Moderate                      Moderate
  Technical Design of Project or Program                    Substantial                    Substantial                   Substantial
  Institutional Capacity for Implementation and
                                                            Substantial                    Substantial                   Substantial
  Sustainability
  Fiduciary                                                 Moderate                       Moderate                      Moderate
  Environment and Social                                    Low                            Low                           Low
  Stakeholders                                              Moderate                       Moderate                      Moderate
  Other                                                     --                              --                             --
  Overall                                                   Moderate                       Moderate                      Moderate




  Results


 PDO Indicators by Objectives / Outcomes


  Expanded access and professionalization of ECCD
   IN01377475
   ►Percentage of children (3-5 years old) enrolled in ECCD services led by a ECCD facilitator which complete the basic certificate
   (Percentage, Custom)

                                      Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                             26.00                        26.00                         26.00                     30.00

    Date                              16-Nov-2021                  30-May-2022                   30-May-2022              25-Jan-2025
                                      The indicator tracks improvement in children (3-5 years old) enrolled in ECCD services after 90% of all
    Comments                          ECCD facilitators have been trained in the basic certificate and 30 new integrated ECCD centers and 90
                                      smaller ECCD centers targeting rural areas have been operationalized.

  Digitization of education for improved student outcomes
    IN01377476
    ►Percentage of schools accessing and teachers utilizing digital content in LMS (Percentage, Custom)

                                      Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                             0.00                         86.00                         86.00                     80.00

    Date                              16-Nov-2021                  26-Jun-2023                   26-Jun-2023              25-Jan-2025

                                      The indicator tracks the progress towards improved access of schools to digital contents which are hosted
    Comments
                                      on at least two digital platforms.
     IN01377479
     in Urban areas (Percentage, Custom Breakdown)

                                     Baseline                    Actual (Previous)           Actual (Current)             End Target

     Value                           0.00                        86.00                       86.00                        80.00



12/14/2023                                                                                                                      Page 9 of 18
           The World Bank                                                                                      Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)




     Date                             16-Nov-2021                 26-Jun-2023                  26-Jun-2023                 25-Jan-2025

     IN01377480
     in Rural areas (Percentage, Custom Breakdown)

                                      Baseline                    Actual (Previous)            Actual (Current)            End Target

     Value                            0.00                        58.00                        58.00                       40.00

     Date                             16-Nov-2021                 26-Jun-2023                  26-Jun-2023                 25-Jan-2025

  Improve employment and inclusion outcomes
    IN01377481
    ►Percentage increase from baseline (TBE) in percent of trainees employed (including full and part-time, wage and self-employment) within 6
    months of completing SDP (Percentage, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target

    Value                              42.10                       0.00                          0.00                      20.00

    Date                               01-Dec-2022                 30-May-2022                   30-May-2022               25-Jan-2025
                                       The definition of the indicator is the percentage increase compared to the baseline value (to be established)
                                       in the ratio of trainees who are employed (either full or part-time in the wage of self-employment) within 6
    Comments                           months of SDP completion over all those trained by SDP. The indicator is cumulative. The baseline will be
                                       established 7 months after the start of SDP implementation.

     IN01377482
     for women (Percentage, Custom Breakdown)

                                      Baseline                    Actual (Previous)            Actual (Current)            End Target

     Value                            38.70                       0.00                         0.00                        35.00

     Date                             01-Dec-2022                 30-May-2022                  30-May-2022                 25-Jan-2025

  Enhanced resilience of jobseekers
   IN01377477
    ►MoICE established operational linkages with key relevant agencies (Text, Custom)

                                       Baseline                    Actual (Previous)             Actual (Current)          End Target
                                                                                                                           Linkages established
                                                                                                                           either through MOUs
                                                                                                                           or data sharing
                                                                                                                           protocols with Ministry
    Value                              No linkages                 No linkages                   No linkages
                                                                                                                           of Education, Ministry
                                                                                                                           of Agriculture and
                                                                                                                           Forests (MoAF), and
                                                                                                                           Tourism Council
    Date                               16-Nov-2021                 30-May-2022                   30-May-2022               25-Jan-2025
                                       The indicator measures operational linkages that can be established either through data sharing protocols
                                       captured in MoICE MIS, official documentation or signing of a Memorandum of Understanding (MOU). The
    Comments
                                       relevant agencies are MOAF, MoESD, and Tourism Council.


  Improve access to safe water and sanitation facilities at primary and secondary schools
    IN01377478
    ►Number of public schools and Special Education Needs schools with proper WASH facilities (Number, Custom)



12/14/2023                                                                                                                  Page 10 of 18
           The World Bank                                                                                       Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)




                                      Baseline                      Actual (Previous)             Actual (Current)            End Target

    Value                             0.00                         0.00                           0.00                        60.00

    Date                              01-Mar-2023                  01-Mar-2023                    01-Mar-2023                 31-Jan-2025

    Comments


 Intermediate Results Indicators by Results Areas



  Expanded access and professionalization of ECCD
   IN01377485
   ►Number of ECCD facilitators for government-supported provision trained or receiving training in the ECCD Diploma program (Number,
   Custom)

                                      Baseline                      Actual (Previous)             Actual (Current)            End Target

    Value                             248.00                       248.00                         248.00                      450.00

    Date                              16-Nov-2021                  30-May-2022                    30-May-2022                 25-Jan-2025

                                      The indicator tracks the number of ECCD facilitators enrolled or having completed training in ECCD Diploma
    Comments
                                      Program (in-service training program delivered over 3 years).
    IN01377488
    ►Number of ECCD facilitators for government-supported provision trained in the two-week basic ECCD certificate (Number, Custom)

                                      Baseline                      Actual (Previous)             Actual (Current)            End Target

    Value                             600.00                       600.00                         600.00                      810.00

    Date                              16-Nov-2021                  30-May-2022                    30-May-2022                 25-Jan-2025

    Comments                          The indicator tracks the successful completion of training the basic certificate (an initial 2-week training)
    IN01377492
    ►Number of focal monitors trained (Number, Custom)

                                      Baseline                      Actual (Previous)             Actual (Current)            End Target

    Value                             200.00                       200.00                         200.00                      650.00

    Date                              16-Nov-2021                  30-May-2022                    30-May-2022                 25-Jan-2025

                                    The indicator tracks the successful completion of training of the focal monitors in terms of effective planning,
   Comments
                                    coordination, and monitoring of ECCD services
   IN01377496
   ►Percentage of ECCD facilitators receive a supervision and coaching visit by a trained focal monitor aimed at improving their teaching
   practice (Percentage, Custom)

                                      Baseline                      Actual (Previous)             Actual (Current)            End Target

    Value                             24.00                        24.00                          24.00                       40.00

    Date                              16-Nov-2021                  30-May-2022                    30-May-2022                 25-Jan-2025

    Comments                          The indicator tracks the successful deployment of focal monitors after they received their training
    IN01377498
    ►Number of new government supported integrated ECCD centers and smaller ECCD centers in the targeted areas (Number, Custom)


12/14/2023                                                                                                                     Page 11 of 18
           The World Bank                                                                                   Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)




                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                            0.00                        0.00                         0.00                      180.00

    Date                             16-Nov-2021                 30-May-2022                  30-May-2022               25-Jan-2025

                                     The indicator tracks the provision of integrated ECCD centers and smaller ECCD centers in the targeted
    Comments
                                     areas.
    IN01377501
    ►Percentage of government supported ECCD services that meet the basic quality standards (Number, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                            0.00                        0.00                         0.00                      30.00

    Date                             16-Nov-2021                 30-May-2022                  30-May-2022               25-Jan-2025

                                   The indicator tracks the number of services which meet the basic quality standards. The existing quality
   Comments
                                   standards for ECCD centers and mobile ECCD services will be reviewed and refined as needed.
   IN01377502
   ►Percentage point increase from baseline in percent of mothers with improved economic empowerment outcomes in areas of ECCD
   expansion (Percentage, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                            0.00                        0.00                         0.00                      4.00

    Date                             17-Nov-2021                 30-May-2022                  30-May-2022               25-Jan-2025
                                     The indicator accounts for targeted outreach to mothers in areas of ECCD expansion and impacts of ECCD
                                     expansion on women's economic empowerment. Economic empowerment is measured by increase labor
                                     force participation, increased earnings, or enrollment in skill and employment support provided by
    Comments
                                     MoESD/MoICE, or ECCD facilitator training provided by MOE. Baseline value will be established by end of
                                     Year 1 under baseline data collection for impact evaluation.



  Digitization of education for improved student outcomes
    IN01377484
    ►Number of teachers trained on Digital Pedagogy (Number, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target

    Value                            0.00                        4,000.00                     4,000.00                  5,000.00

    Date                             16-Nov-2021                 26-Jun-2023                  26-Jun-2023               25-Jan-2025

                                     The indicator tracks training of teachers in accordance with the ICT competencies outlined in the ICT
    Comments
                                     competency standards for teachers.
     IN01377487
     Number of female teachers trained on Digital Pedagogy for improved competency, mentorship and professional development (Number,
     Custom Supplement)

                                    Baseline                    Actual (Previous)            Actual (Current)           End Target

      Value                         0.00                        0.00                         1,760.00                   2,000.00
    IN01377493
    ►Percentage of schools having remote learning facilities in rural areas (Percentage, Custom)

                                      Baseline                    Actual (Previous)           Actual (Current)          End Target



12/14/2023                                                                                                               Page 12 of 18
           The World Bank                                                                                    Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)




    Value                            0.00                         0.00                          0.00                      20.00

    Date                             16-Nov-2021                  30-May-2022                   30-May-2022               25-Jan-2025

                                     The indicator tracks the progress towards reducing digital divide in rural areas by providing them remote
    Comments
                                     learning facilities (Digital device, trained teachers)


  Improve employment and inclusion outcomes
    IN01377486
    ►Percentage increase from baseline in percentage of female SDP graduates (Percentage, Custom)

                                     Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                            47.50                        0.00                          0.00                      40.00

    Date                             01-Dec-2022                  30-May-2022                   30-May-2022               25-Jan-2025
                                     The definition of female SDP graduate is “women aged between 15-64 who have completed SDP training
    Comments                         program”. The indicator tracks the percentage increase in the proportion of female graduates from baseline
                                     that will be established within the first 12 months of SDP functioning.
    IN01377489
    ►Percentage increase from baseline (TBE) in trainings delivered outside of Thimphu, Paro and Phuentsholling (Percentage, Custom)

                                     Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                            78.60                        0.00                          0.00                      40.00

    Date                             01-Dec-2022                  30-May-2022                   30-May-2022               25-Jan-2025
                                     The definition of the indicator is the percentage increase from the baselines of the ratio of SDP training
    Comments                         delivered outside Thimphu, Paro and Phuentsholling over the total number of SDP training provided. The
                                     baseline will be established in year 1 after 7 months of SDP implementation.
    IN01377491
    ►Percentage of users requesting services through the single intake and profiling window under MoESD and MoICE (Percentage, Custom)

                                     Baseline                     Actual (Previous)             Actual (Current)          End Target

    Value                            0.00                         0.00                          0.00                      75.00

    Date                             16-Nov-2021                  30-May-2022                   30-May-2022               25-Jan-2025

                                     The share of direct applicants to training, entrepreneurship, apprenticeship, and internship opportunities that
    Comments
                                     are using the updated system either in person or online.
     IN01377497
     Of those who are women (Percentage, Custom Breakdown)

                                    Baseline                    Actual (Previous)             Actual (Current)            End Target

     Value                          0.00                        0.00                          0.00                        50.00

     Date                           16-Nov-2021                 30-May-2022                   30-May-2022                 25-Jan-2025

     IN01377499
     of those who are not from of Thimphu, Paro and Phuentsholling (Percentage, Custom Breakdown)

                                    Baseline                    Actual (Previous)             Actual (Current)            End Target

     Value                          0.00                        0.00                          0.00                        30.00



12/14/2023                                                                                                                 Page 13 of 18
           The World Bank                                                                                       Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)




     Date                         16-Nov-2021                  30-May-2022               30-May-2022              25-Jan-2025
   IN01377500
   ►Percentage of job seekers registered with single intake window who perceive improvements in access to employment promotion services
   (Percentage, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         91.54                         91.54                      75.00

    Date                               16-Nov-2021                  26-Jun-2023                   26-Jun-2023                25-Jan-2025
                                       The share of direct project beneficiaries who report being very satisfied or extremely satisfied with the
    Comments                           MoESD/ MoICE training programs

     IN01377503
     of those who are women (Percentage, Custom Breakdown)

                                      Baseline                     Actual (Previous)             Actual (Current)            End Target

     Value                            0.00                        93.14                          93.14                       50.00

     Date                           16-Nov-2021              26-Jun-2023                 26-Jun-2023                 25-Jan-2025
   IN01377504
   ►SDP program design on outreach, enrollment, delivery and placement support is revised following the completion of the study under DLR 1
   as evidenced by revisions to the POM (Yes/No, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              No                           No                            Yes                        Yes

    Date                               17-Nov-2021                  30-May-2022                   04-Dec-2023                25-Jan-2025
                                       The indicator measures the outcome of Year 1 DLR under DLI 5 in terms of revisions to the SDP Project
    Comments                           Operations Manual that follow recommendations around outreach, delivery, and placement support (if
                                       needed).


  Enhanced resilience of jobseekers
   IN01377483
    ►Monitoring system for regular tracking of employment up to 6 months post SDP completion is established (Yes/No, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              No                           No                            Yes                        Yes

    Date                               16-Nov-2021                  30-May-2022                   04-Dec-2023                25-Jan-2025

                                       SDP management information system has a fully functional system to track employment outcomes of
    Comments
                                       graduates up to six months after completion of SDP training
    IN01377490
    ►Percentage of graduates from acceleration and incubation programs are linked to financing opportunities (Percentage, Custom)

                                       Baseline                     Actual (Previous)             Actual (Current)           End Target

    Value                              0.00                         0.00                          0.00                       30.00

    Date                               16-Nov-2021                  30-May-2022                   30-May-2022                25-Jan-2025
                                       The share of direct MoICE acceleration and incubation program beneficiaries who report participating in
    Comments                           pitching competitions or receiving guidance submission of requests for loan/equity financing.
    IN01377494


12/14/2023                                                                                                                    Page 14 of 18
           The World Bank                                                                                  Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)




    ►Development of a Strategy for increasing climate responsiveness of MoESD financed trainings (Yes/No, Custom)

                                       Baseline                   Actual (Previous)           Actual (Current)         End Target

    Value                              No                         No                          No                       Yes

    Date                               16-Nov-2021                30-May-2022                 30-May-2022              25-Jan-2025
                                       Publication of strategy with actionable adjustments to the design of MoESD supported programs and
    Comments                           timelines
   IN01377495
   ►Development of data sharing and referral system between MoESD and MoICE to enable referrals for mothers benefiting from ECCD to
   programs provided by MoICE (Yes/No, Custom)

                                       Baseline                   Actual (Previous)           Actual (Current)         End Target

    Value                              No                         No                          No                       Yes

    Date                               17-Nov-2021                30-May-2022                 30-May-2022              25-Jan-2025
                                       The indicator measures steps taken to increase linkages between the expansion of ECCD and economic
    Comments                           empowerment. Data sharing protocol and MIS linkages should be captured under relevant guidelines and
                                       MIS architecture revisions.

 Disbursement Linked Indicators
 DLI_IND_TABLE
    ►DLI 1 Strengthening the quality of ECCD services for improved child outcomes (Outcome, 3,000,000.00, 0%)

                                                                                                                        3 Years after
                                 Baseline                       Actual (Previous)           Actual (Current)            effectiveness

    Value                        N/A                           0.00                         0.00                        N/A

    Date                         --                            30-May-2022                  30-May-2022                 --

    Comments



    ►DLI 2 Expansion of ECCD in targeted population (Outcome, 1,500,000.00, 0%)

                                                                                                                        3 Years after
                                 Baseline                       Actual (Previous)           Actual (Current)            effectiveness
                                                                                                                        ECCD program
                                                                                                                        expanded in rural
                                                                                                                        areas, deprived and
    Value                        N/A                           0.00                         0.00                        poor communities as
                                                                                                                        measured by a 9%
                                                                                                                        increase over the
                                                                                                                        baseline.
    Date                         --                            30-May-2022                  30-May-2022                 --

    Comments



    ►DLI 3 ICT in education for learning recovery and improved access (Outcome, 5,500,000.00, 0%)




12/14/2023                                                                                                              Page 15 of 18
           The World Bank                                                                              Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)



                                                                                                                    3 Years after
                                 Baseline                    Actual (Previous)          Actual (Current)            effectiveness
                                                                                                                    Reduction in the
                                                                                                                    digital divide in rural
                                                                                                                    areas (i) by ensuring
                                                                                                                    an increase by 20%
                                                                                                                    over baseline in
                                                                                                                    schools having
                                                                                                                    access to remote
                                                                                                                    learning facilities
                                                                                                                    through improved
                                                                                                                    access for schools
    Value                        N/A                         0.00                       0.00
                                                                                                                    to digital learning (to
                                                                                                                    be financed by
                                                                                                                    HCRRP), (ii) by
                                                                                                                    ensuring an
                                                                                                                    increase by 40 rural
                                                                                                                    schools which will
                                                                                                                    be equipped with
                                                                                                                    local connectivity (to
                                                                                                                    be financed by
                                                                                                                    HCRRP AF)
    Date                         --                          30-May-2022                30-May-2022                 --

    Comments



    ►DLI 4 Building Climate Change resilience through education system (Outcome, 1,000,000.00, 0%)

                                                                                                                    3 Years after
                                 Baseline                    Actual (Previous)          Actual (Current)            effectiveness

    Value                        N/A                         0.00                       0.00                        N/A

    Date                         --                          30-May-2022                30-May-2022                 --

    Comments



    ►DLI 5 Enhanced inclusion under SDP (Outcome, 2,500,000.00, 0%)

                                                                                                                    3 Years after
                                 Baseline                    Actual (Previous)          Actual (Current)            effectiveness
                                                                                                                    (a) at least 40%
                                                                                                                    increase in the
                                                                                                                    percentage of
                                                                                                                    female trainees
                                                                                                                    completing SDP
                                 Current % of women and                                                             from the baseline
                                 beneficiaries from areas                                                           established in Y1(b)
    Value                                                    Prior Result Achieved      Prior Result Achieved
                                 outside of Thimphu, Paro                                                           at least 40%
                                 and Phuentsholling                                                                 increase from
                                                                                                                    baseline established
                                                                                                                    in Y1 in trainings
                                                                                                                    delivered outside of
                                                                                                                    Thimphu, Paro, and
                                                                                                                    Phuentsholling
    Date                         --                          28-Feb-2022                28-Feb-2022                 --



12/14/2023                                                                                                          Page 16 of 18
           The World Bank                                                                                  Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)



                                 The Prior Result "Foundational Operational Manual for SDP" has been achieved on February 28th, 2022, and
                                 verified by the Central Coordination Commission Independent Verification Agency (IVA) by April 25th,
    Comments                     2022. MoESD has developed a work plan to establish the baseline for the Year 2 and Year 3 DLIs.




    ►DLI 6 Increased employment post SDP (Outcome, 3,000,000.00, 0%)

                                                                                                                        3 Years after
                                 Baseline                      Actual (Previous)           Actual (Current)             effectiveness
                                                                                                                        20% increase from
                                                                                                                        baseline in
                                                                                                                        percentage of
                                                                                                                        trainees employed
                                 Established through tracer
    Value                                                      0.00                        0.00                         (including full and
                                 study conducted in Year 1
                                                                                                                        part-time, wage and
                                                                                                                        self-employment)
                                                                                                                        within 6 months of
                                                                                                                        completing SDP
    Date                         --                            30-May-2022                 30-May-2022                  --

    Comments



    ►DLI 7 Improved quality of entrepreneurship support (Outcome, 1,000,000.00, 0%)

                                                                                                                        3 Years after
                                 Baseline                      Actual (Previous)           Actual (Current)             effectiveness

    Value                        N/A                           0.00                        0.00                         N/A

    Date                         --                            30-May-2022                 30-May-2022                  --

                                 MoICE has achieved year-one DLR and is working on year-two DLR.
    Comments



    ►DLI 8 Strengthen systems and coordination to enhance employment support delivery under MOLHR (Outcome, 2,500,000.00, 0%)

                                                                                                                        3 Years after
                                 Baseline                      Actual (Previous)           Actual (Current)             effectiveness
                                                                                                                        30% increase from
                                                                                                                        baseline in the
                                                                                                                        number of SDP
                                                                                                                        beneficiaries
                                                               Prior Result achieved on    Prior Result achieved on
    Value                        N/A                                                                                    supported through
                                                               February 28th, 2022.        February 28th, 2022.
                                                                                                                        YELP; certificate-
                                                                                                                        based skilling or
                                                                                                                        entrepreneurship
                                                                                                                        support
    Date                         --                            30-May-2022                 30-May-2022                  --
                                 Prior Result "Core Modules of SDP MIS are operational" was achieved on February 28th, 2022. The modules
                                 included: profile creation, enrollment, attendance tracking, and grievance redress. The achievement of the
                                 Prior Result was verified by the Central Coordination Agency (CCA) that acts as an independent verification
    Comments
                                 agency (IVA) for the Program.




12/14/2023                                                                                                              Page 17 of 18
           The World Bank                                                                                  Implementation Status & Results Report
           Bhutan Human Capital Recovery and Resilience Project (P174399)




    ►DLI 9 Training in climate-responsive initiatives offered to jobseekers (Outcome, 1,000,000.00, 0%)

                                                                                                                        3 Years after
                                 Baseline                      Actual (Previous)            Actual (Current)            effectiveness
                                                                                                                        The operational
                                                                                                                        strategy for
                                                                                                                        increasing climate
                                                                                                                        responsiveness of
    Value                        N/A                           0.00                         0.00
                                                                                                                        MOLHR provided
                                                                                                                        skill training is
                                                                                                                        approved by
                                                                                                                        MOLHR
    Date                         --                            30-May-2022                  30-May-2022                 --

    Comments


   ►DLI 10 Improving safe water and sanitation facilities for Special Education Needs school as well as public primary and secondary school
   children (Output, 1,500,000.00, 0%)

                                                                                                                        3 Years after
                                 Baseline                      Actual (Previous)            Actual (Current)            effectiveness
                                                                                                                        Equip (i) 20 public
                                                                                                                        Special Education
                                                                                                                        Needs schools with
                                                                                                                        inclusive WASH
                                 No proper WASH facilities     No proper WASH               No proper WASH facilities   facilities
    Value                        are constructed under the     facilities are constructed   are constructed under the   (US$750,000) and
                                 project                       under the project            project                     (ii) 40 public primary
                                                                                                                        and secondary
                                                                                                                        schools with proper
                                                                                                                        WASH facilities
                                                                                                                        (US$750,000)
    Date                         --                            01-Mar-2023                  01-Mar-2023                 --

    Comments




12/14/2023                                                                                                              Page 18 of 18