Procurement Plan – Project Preparation Advance P4760 3rd South West Indian Ocean Project I. General 2. Bank’s approval Date of the procurement Plan: 26th January 2017 3. Date of General Procurement Notice: Pending 4. Period covered by this procurement plan: 28th April 2016 to 31st December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 4. Reference to (if any) Project Operational/Procurement Manual: Under preparation 5. Any Other Special Procurement Arrangements: N/A 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost July 9, 2010 US$ Prefe (Prior / million rence Post) (yes/ no) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_100,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N.A 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Package Review Comment of d s by s Assignmen Cost Bank t US$ July 9, 2010 (Prior / Post) Summary 245,000 2 Post of number of contracts that will be let under QCBS Summary 1,015,00 17 Prior & CQS, IC, of number 0 Post SSS of contracts that will be let under other methods July 9, 2010 PROCUREMENT Eastern and Southern Africa : Third South West Indian Ocean Fisheries Governance and Shared Growth Project (SWIOFish3) PLAN General Information Country: Eastern and Southern Africa 2017-04-04 Bank’s Approval Date of the Original Procurement Plan: 2023-12-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155642 GPN Date: Project Name: Third South West Indian Ocean Fisheries Governance and Shared Growth Project (SWIOFish3) Loan / Credit No: IBRD / P4760, IBRD / 87790 Ministry of Finance, Trade and the Blue Economy Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GEF23-SWIOFISH3 / FEIU pur Component 2: Improved gov Request for Quota Single Stage - One E IBRD / 87790 Post Open - National 12,000.00 25,561.00 Completed 2020-07-05 2021-06-06 2020-08-30 2021-10-14 2021-02-26 2022-02-19 chase of data servers ernance of priority fisheries tions nvelope GEF16/G/2020-SWF3 / THEM Component 1: Expansion of Single Stage - One E Under Imple IS AIS, Radar installation and IBRD / 87790 sustainable-use marine prot Post Request for Bids Limited 160,000.00 0.00 2020-03-31 2020-04-24 2020-04-05 2020-05-17 2020-06-16 2020-07-21 2021-01-17 nvelope mentation maintenance ected areas IBRD28/G/2020-SWF3 / Equi Component 3: Sustainable d Request for Quota Open - Internationa Single Stage - One E IBRD / 87790 Post 25,000.00 37,249.65 Signed 2020-08-19 2021-11-18 2020-10-14 2022-06-23 2021-04-12 pment for SFA post harvest l evelopment of the blue econ tions l nvelope ab omy GEF43/G/2020-SWF3 / Purch Component 2: Improved gov Request for Quota Single Stage - One E Pending Impl IBRD / 87790 Post Open - National 55,000.00 0.00 2020-11-21 2021-01-16 2021-07-15 asing Surveillance tender ves ernance of priority fisheries tions nvelope ementation sel. IBRD42/G/2021/EQUIPMENT FOR SBS/FIQCU / Equipment f or Seychelles Bureau of Stan Component 3: Sustainable d Open - Internationa Single Stage - One E dards (HIGH PERFORMANCE IBRD / 87790 evelopment of the blue econ Post Request for Bids 336,000.00 282,146.93 Signed 2021-11-26 2022-03-03 2021-12-01 2022-03-06 2022-01-12 2022-04-19 2022-02-11 2022-05-12 2022-03-18 2022-06-27 2022-09-14 l nvelope LIQUID CHROMATOGRAPH (H omy PLC) and SINGLE QUADRUPO LE INDUCTIVELY COUPLED PL ASMA MASS SPECTROMETER (ICP MS) ) GEF52/NCS/2021-SWF3 / Pur Component 2: Improved gov Open - Internationa Single Stage - One E IBRD / 87790 Post Request for Bids 350,000.00 0.00 Signed 2022-07-31 2023-03-24 2022-08-05 2023-03-24 2022-09-16 2023-04-27 2022-10-16 2023-05-25 2022-11-20 2023-07-06 2023-05-19 chase of one vessel for surve ernance of priority fisheries l nvelope illance IBRD48/RFB/2022-SWF3 / De Component 3: Sustainable d sign and build of containerise Open - Internationa Single Stage - One E IBRD / 87790 evelopment of the blue econ Post Request for Bids 200,000.00 0.00 Signed 2022-09-30 2022-11-21 2022-10-05 2023-01-27 2022-11-16 2023-02-28 2022-12-16 2023-03-14 2023-01-20 2023-04-04 2023-07-19 d hatchery in support of local l nvelope omy small-scale invertebrate aqu aculture development GEF66/G/2023-SWF3 / Purch Component 1: Expansion of ase of diving and survey equi Open - Internationa Single Stage - One E Under Imple IBRD / 87790 sustainable-use marine prot Post Request for Bids 100,000.00 0.00 2023-02-08 2023-05-19 2023-02-13 2023-05-19 2023-03-27 2023-04-26 2023-05-31 2023-11-27 pment for National Marine Pr l nvelope mentation ected areas otected Area Authority IBRD42/G/2023-SWF3/ EQUI Component 3: Sustainable d Request for Quota Open - Internationa Single Stage - One E PMENT FOR POST H / Equipm IBRD / 87790 evelopment of the blue econ Post 15,000.00 0.00 Signed 2023-02-12 2023-03-16 2023-04-09 2023-05-02 2023-10-06 tions l nvelope ent for post harvest lab: blast omy freezer GEF68/G/2023-SWF3 / Upgra Component 1: Expansion of Request for Quota Open - Internationa Single Stage - One E Under Imple de to the national GIS system IBRD / P4760 sustainable-use marine prot Post 40,000.00 0.00 2023-04-23 2023-09-04 2023-06-18 2023-12-15 tions l nvelope mentation to support boundary limitatio ected areas n and the MSP GEF65/G/2022-SWF3 / Purch Component 1: Expansion of Open - Internationa Single Stage - One E Pending Impl IBRD / 87790 Post Request for Bids 500,000.00 0.00 2023-12-20 2023-12-25 2024-02-05 2024-03-06 2024-04-10 2024-10-07 ase of surveillance equipmen sustainable-use marine prot l nvelope ementation t for MSP ected areas GEF73/G/2023-SWF3 / FAD Component 1: Expansion of Module for Themis and syste Direct - Internation Under Imple IBRD / 87790 sustainable-use marine prot Post Direct Selection 40,000.00 0.00 2023-12-07 2023-12-05 2023-12-12 2023-12-05 2024-01-16 2024-07-14 m for NICSS data sharing to al mentation ected areas use data for FAD recovery NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GEF35/NCS/2020-SWF3 / Pro Component 2: Improved gov Open - Internationa Single Stage - One E Pending Impl vision of satellite data (AIS, r IBRD / 87790 Post Request for Bids 231,000.00 0.00 2020-09-01 2020-09-06 2020-10-18 2020-11-17 2020-12-22 2023-12-22 ernance of priority fisheries l nvelope ementation adar, imagery) to Seychelles Fishing Authority IBRD20/RFB/2020-SWF3 / GE Component 3: Sustainable d Single Stage - Two E Pending Impl OTECH SURVEY FOR GRAND IBRD / 87790 evelopment of the blue econ Post Request for Bids Open - National 200,000.00 0.00 2020-06-01 2020-06-06 2020-07-18 2020-09-30 2020-11-04 2021-05-03 nvelope ementation ANSE AQUACULTURE HUB omy CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PA2-SWIOFISH3 / Evaluation Component 1: Expansion of Consultant Qualifi Open - Internationa of the contribution of the ext IBRD / P4760 sustainable-use marine prot Post 75,000.00 0.00 Canceled 2018-08-20 2018-09-10 2018-08-21 2018-10-24 2018-11-23 2018-12-28 2019-06-26 cation Selection l ended MPA network to the ec ected areas onomy PA3-SWIOFISH3 / Education Component 2: Improved gov Consultant Qualifi Open - Internationa and awareness program on fi IBRD / P4760 Post 50,000.00 0.00 Canceled 2017-05-15 2017-05-15 2018-01-23 2017-05-15 2017-05-15 2017-06-05 2017-12-02 ernance of priority fisheries cation Selection l sheries management plan im plementation Page 1 IBRD4-SWIOFISH3 / Fisheries Component 3: Sustainable d sector employment survey & Consultant Qualifi Open - Internationa IBRD / 87790 evelopment of the blue econ Post 75,000.00 0.00 Canceled 2019-04-15 2019-05-06 2019-06-04 2019-06-19 2019-07-19 2019-08-23 2020-02-19 identify method for routine e cation Selection l omy mployment monitoring GEF5-SWIOFISH3 / Drafting Component 1: Expansion of Consultant Qualifi of a coral reef conservation p IBRD / 87790 sustainable-use marine prot Post Open - National 50,000.00 48,278.00 Completed 2019-05-15 2019-08-27 2019-06-05 2019-07-19 2019-11-11 2019-08-18 2020-03-17 2019-09-22 2020-04-08 2020-03-20 2021-04-20 cation Selection olicy and plan ected areas GEF7-SWIOFISH3 / Perceptio n survey of management per Component 1: Expansion of Consultant Qualifi formance for sustainable use IBRD / 87790 sustainable-use marine prot Post Open - National 25,000.00 0.00 Canceled 2019-04-30 2019-11-29 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2020-03-05 cation Selection area and fisheries plans (info ected areas rmation for M&E indicator) IBRD17-SWIOFISH3 / Develo Component 3: Sustainable d Consultant Qualifi Open - Internationa IBRD / 87790 Post 80,000.00 104,030.00 Signed 2019-06-30 2020-01-21 2019-07-21 2019-09-03 2020-05-13 2019-10-03 2020-08-17 2019-11-07 2020-08-21 2020-05-05 pment of Seychelles seafood evelopment of the blue econ cation Selection l brand omy IBRD1-SWIOFISH3 / Capacity Component 3: Sustainable d building in project planning a Consultant Qualifi IBRD / 87790 evelopment of the blue econ Post Open - National 100,000.00 182,987.00 Signed 2019-03-29 2019-03-25 2019-04-19 2019-06-02 2019-05-10 2019-07-02 2019-10-15 2019-08-06 2019-10-24 2020-02-02 nd business development for cation Selection omy small-scale fishers IBRD23-SWIOFISH3 / Fisheri Component 3: Sustainable d es sector employment surve Quality And Cost- Open - Internationa Pending Impleme IBRD / 87790 evelopment of the blue econ Post 75,000.00 0.00 2019-08-22 2019-08-22 2019-08-22 2019-09-13 2019-10-13 2019-11-17 2019-12-22 2020-12-21 y and identification of metho Based Selection l ntation omy d for routine monitoring GEF26-SWIOFISH3A / Comm unication strategy and plan f Component 2: Improved gov Consultant Qualifi Open - Internationa IBRD / 87790 Post 35,000.00 51,291.00 Signed 2019-09-25 2019-11-29 2019-10-16 2019-11-29 2020-10-12 2019-12-29 2020-12-23 2020-02-02 2021-01-24 2020-07-31 or Mahe Plateau fisheries ma ernance of priority fisheries cation Selection l nagement measures IBRD24-SWIOFISH3 / Develo Component 3: Sustainable d pment of a communication st Consultant Qualifi IBRD / 87790 evelopment of the blue econ Post Open - National 20,000.00 44,188.00 Completed 2019-10-11 2020-03-13 2019-11-01 2019-12-15 2020-06-09 2020-01-14 2020-09-10 2020-02-18 2020-10-07 2020-08-16 2021-11-07 rategy and online platform fo cation Selection omy r the Grievance Redress Mec hanism IBRD26/CQS/2020-SWF3 / Co Component 3: Sustainable d Consultant Qualifi IBRD / 87790 Post Open - National 200,000.00 220,000.00 Signed 2020-01-15 2020-01-21 2020-02-05 2020-03-20 2020-05-18 2020-04-19 2020-06-19 2020-05-24 2020-07-07 2020-11-20 mmunication support for Blu evelopment of the blue econ cation Selection e Finance omy GEF21-SWIOFISH3 / Feasibili Component 2: Improved gov Quality And Cost- Open - Internationa ty study on mechanisms for f IBRD / 87790 Post 80,000.00 0.00 Canceled 2019-07-15 2019-08-05 2019-09-18 2019-10-16 2019-11-15 2019-12-20 2020-01-24 2021-01-23 ernance of priority fisheries Based Selection l leet capacity reduction GEF32/CQS/2020-SWF3 / Bio logical, ecological and socioe Component 1: Expansion of Consultant Qualifi Open - Internationa Pending Impleme conomic monitoring of sustai IBRD / 87790 sustainable-use marine prot Post 150,000.00 0.00 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-08-21 cation Selection l ntation nable-use areas: baseline sur ected areas veys, indicators and protocol s GEF36/CQS/2020-SWF3 / Re Component 1: Expansion of search on ways to mitigate i Consultant Qualifi Open - Internationa Pending Impleme IBRD / 87790 sustainable-use marine prot Post 50,000.00 0.00 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-05-21 mpacts of industrial fisheries cation Selection l ntation ected areas on coastal marine habitats a nd fisheries GEF40/QCBS/2020-SWF3 / C Component 2: Improved gov Quality And Cost- Pending Impleme ommunication and education IBRD / 87790 Post Open - National 150,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-02 2020-11-01 2020-12-06 2021-01-10 2022-01-10 ernance of priority fisheries Based Selection ntation /awareness activity support f or SFA GEF45/QCBS/2020-SWF3 / Pr Component 2: Improved gov Quality And Cost- Open - Internationa eparation of national tuna fis IBRD / 87790 Post 100,000.00 216,920.50 Signed 2020-05-01 2022-02-09 2020-05-22 2022-02-16 2020-07-05 2022-04-04 2020-08-02 2022-05-10 2020-09-01 2022-07-20 2020-10-06 2022-07-29 2020-11-10 2022-09-26 2021-11-10 ernance of priority fisheries Based Selection l heries development and man agement plan GEF48/QCBS/2020-SWF3 / D evelopment of a sport and re Component 2: Improved gov Quality And Cost- Open - Internationa Pending Impleme IBRD / 87790 Post 170,000.00 0.00 2020-07-15 2020-08-05 2020-09-18 2020-10-16 2020-11-15 2020-12-20 2021-01-24 2022-01-24 creational fishery data collec ernance of priority fisheries Based Selection l ntation tion and monitoring system IBRD29/QCBS/2020-SWF3 / F Component 3: Sustainable d Quality And Cost- Open - Internationa Pending Impleme easibility study on invertebra IBRD / 87790 evelopment of the blue econ Post 60,000.00 0.00 2020-05-31 2020-06-21 2020-08-04 2020-09-01 2020-10-01 2020-11-05 2020-12-10 2021-12-10 Based Selection l ntation te hatcheries at Grand Anse omy Aquaculture Hub GEF1-SWIOFISH3 / Blue carb Component 1: Expansion of Consultant Qualifi Open - Internationa on assessment for Mahe Plat IBRD / 87790 sustainable-use marine prot Post 100,000.00 299,099.55 Signed 2020-04-15 2020-07-12 2020-05-06 2020-08-04 2020-06-19 2020-09-24 2020-07-19 2021-01-20 2020-08-23 2021-08-16 2021-02-19 cation Selection l eau: Mangrove ecosystems ected areas GEF3-SWIOFISH3 / Develop Component 1: Expansion of ment of a Harvest Strategy P Consultant Qualifi Open - Internationa IBRD / 87790 sustainable-use marine prot Post 75,000.00 139,974.31 Completed 2019-04-15 2021-01-27 2019-05-06 2021-02-22 2019-06-19 2021-03-31 2019-07-19 2021-06-17 2019-08-23 2021-07-18 2020-02-19 2022-07-13 olicy and Management Stand cation Selection l ected areas ards for Seychelles Fisheries GEF6-SWIOFISH3 / Studies o Component 1: Expansion of n importance (social, econom Consultant Qualifi Open - Internationa IBRD / 87790 sustainable-use marine prot Post 50,000.00 149,547.30 Signed 2020-06-30 2021-05-20 2020-07-21 2021-06-10 2020-09-03 2021-07-23 2020-10-03 2021-11-11 2020-11-07 2021-12-13 2021-05-06 ic, value chains) of charter a cation Selection l ected areas nd sport fishing sector to defi ne MSP impacts IBRD3-SWIOFISH3 / Educatio Component 3: Sustainable d n & awareness to promote ta Consultant Qualifi Pending Impleme IBRD / 87790 evelopment of the blue econ Post Open - National 105,000.00 0.00 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-05-21 g and release in sport and re cation Selection ntation omy creational fisheries IBRD10/CQS/2020-SWF3 / H Component 3: Sustainable d Consultant Qualifi Open - Internationa uman capacity development IBRD / 87790 evelopment of the blue econ Post 90,000.00 103,243.50 Completed 2020-04-15 2020-05-28 2020-05-06 2020-06-07 2020-06-19 2020-10-21 2020-07-19 2020-12-15 2020-08-23 2021-02-11 2021-02-19 2022-08-30 cation Selection l plan in support of aquacultur omy e sector IBRD22-SWIOFISH3 / Pre-ass Component 3: Sustainable d Consultant Qualifi Open - Internationa essment of Seychelles longlin IBRD / 87790 evelopment of the blue econ Post 35,000.00 105,745.00 Signed 2020-05-15 2021-05-18 2020-06-05 2021-06-10 2020-07-19 2021-08-10 2020-08-18 2022-03-02 2020-09-22 2022-04-25 2021-03-21 cation Selection l e fishery against MSC standa omy rd GEF22-SWIOFISH3 / Develop Component 2: Improved gov Quality And Cost- Open - Internationa ment of the Fisheries Informa IBRD / 87790 Post 160,000.00 202,457.25 Signed 2020-06-15 2022-02-08 2020-07-06 2022-02-14 2020-08-19 2022-06-27 2020-09-16 2022-07-26 2020-10-16 2022-08-05 2020-11-20 2022-09-05 2020-12-25 2022-09-16 2021-12-25 ernance of priority fisheries Based Selection l tion Management System (in cl. dashboards) IBRD16-SWIOFISH3 / Develo Component 3: Sustainable d Quality And Cost- Open - Internationa pment and piloting of app to IBRD / 87790 evelopment of the blue econ Post 50,000.00 120,000.00 Signed 2020-04-15 2021-03-23 2020-05-06 2021-03-30 2020-06-19 2021-05-31 2020-07-17 2021-07-07 2020-08-16 2021-07-26 2020-09-20 2021-08-09 2020-10-25 2021-10-18 2022-10-25 Based Selection l promote post harvest inform omy ation sharing GEF18/QCBS/2020-SWF3 / SI Component 2: Improved gov Quality And Cost- Open - Internationa IBRD / 87790 Post 80,000.00 0.00 Canceled 2020-06-15 2020-06-10 2020-07-06 2020-06-22 2020-08-19 2020-09-16 2020-10-16 2020-11-20 2020-12-25 2021-12-25 H Data Processing and Repor ernance of priority fisheries Based Selection l ting Tools Page 2 GEF18/CQS/2020-SWF3 / SIH Component 2: Improved gov Consultant Qualifi Open - Internationa DATA PROCESSING AND REP IBRD / 87790 Post 80,000.00 172,414.92 Signed 2020-09-25 2020-09-30 2020-10-16 2020-11-29 2020-10-01 2020-12-29 2021-02-11 2021-02-02 2021-05-27 2021-08-01 ernance of priority fisheries cation Selection l ORTING TOOLS IBRD41/CQS/2021-SWF3 / G Component 3: Sustainable d Consultant Qualifi Open - Internationa ender Assessment in the Blu IBRD / 87790 evelopment of the blue econ Post 100,000.00 123,078.90 Signed 2021-10-22 2021-11-30 2021-11-12 2022-01-13 2021-12-26 2022-03-03 2022-01-25 2022-07-12 2022-03-01 2022-07-27 2022-08-28 cation Selection l e Economy Sector omy GEF4-SWIOFISH3 / Preparati Component 1: Expansion of Consultant Qualifi Open - Internationa on of management plans for IBRD / 87790 sustainable-use marine prot Post 290,000.00 337,631.75 Signed 2021-12-16 2022-02-04 2021-12-28 2022-02-09 2022-02-10 2022-03-28 2022-03-12 2022-08-08 2022-04-16 2022-08-15 2022-10-13 cation Selection l sustainable use marine prote ected areas cted areas IBRD40/CQS/2021-SWF3 / Pr Component 3: Sustainable d eparation of policies and stan Consultant Qualifi Open - Internationa IBRD / 87790 evelopment of the blue econ Post 50,000.00 0.00 Signed 2022-07-07 2022-06-24 2022-07-28 2022-08-04 2022-09-10 2022-09-16 2022-10-10 2022-11-15 2022-10-31 2022-12-17 2023-04-29 dards to improve recruitment cation Selection l omy and retention of local crew a nd skippers IBRD27/CQS/2022-SWF3 / St Component 3: Sustainable d Consultant Qualifi Open - Internationa udy of post-harvest losses an IBRD / 87790 evelopment of the blue econ Post 80,000.00 0.00 Signed 2022-07-05 2022-06-24 2022-07-26 2022-08-24 2022-09-08 2022-10-31 2022-10-08 2023-01-05 2022-11-12 2023-02-01 2023-05-11 cation Selection l d introduction of routine surv omy ey methodology IBRD39/NCS/2021-SWF3 / Int Component 4: Project mana Consultant Qualifi IBRD / 87790 Post Open - National 10,000.00 0.00 Canceled 2022-07-31 2022-08-24 2022-08-21 2022-10-04 2022-11-03 2022-12-08 2023-06-06 ernal audit of SeyCCAT gement and coordination cation Selection GEF58/CQS/2022-SWF3 / Ind ependent assessment of EU Component 2: Improved gov Consultant Qualifi Open - Internationa IBRD / 87790 Post 60,000.00 0.00 Signed 2022-10-11 2022-10-19 2022-11-01 2022-10-27 2022-12-15 2022-12-22 2023-01-14 2023-02-16 2023-02-18 2023-04-04 2023-08-17 and Mauritian Fisheries Partn ernance of priority fisheries cation Selection l ership Agreements GEF64/CQS/2022-SWF3 / Pre paration of policy and legal fr Component 2: Improved gov Consultant Qualifi Open - Internationa IBRD / 87790 Prior 70,000.00 0.00 Under Review 2022-10-11 2022-10-28 2022-11-01 2022-11-23 2022-12-15 2023-01-23 2023-01-14 2023-02-18 2023-08-17 amework for beneficial owne ernance of priority fisheries cation Selection l rship and joint ventures IBRD44/CQS/2023-SWF3 / D Component 3: Sustainable d evelopment of a new interact Consultant Qualifi IBRD / 87790 evelopment of the blue econ Post Open - National 30,000.00 0.00 Signed 2023-02-08 2023-02-03 2023-03-01 2023-04-14 2023-03-17 2023-05-14 2023-04-26 2023-06-18 2023-05-18 2023-12-15 ive website for the Developm cation Selection omy ent Bank of Seychelles GEF69/CQS/2023-SWF3 / Co mmunication consultancy for Component 2: Improved gov Consultant Qualifi Open - Internationa Under Implement IBRD / 87790 Post 100,000.00 0.00 2023-05-29 2023-07-14 2023-06-19 2023-07-21 2023-08-02 2023-09-01 2023-10-06 2024-04-03 final SWIOFish3 project repor ernance of priority fisheries cation Selection l ation ting and dissemination INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PA5-SWOIFISH3 / Data admi Component 2: Improved gov Individual Consult Under Implement nistrator to assist with adopti IBRD / P4760 Post Open 25,000.00 0.00 2017-04-30 2017-06-18 2017-07-09 2017-08-13 2018-02-09 ernance of priority fisheries ant Selection ation on of SIH including economic data PA12-SWIOFISH3 / Technical Component 3: Sustainable d Assistance to Fishing Port De Individual Consult Under Implement IBRD / P4760 evelopment of the blue econ Post Open 15,000.00 0.00 2017-04-28 2017-06-16 2017-07-07 2017-08-11 2018-02-07 velopment Committee: proje ant Selection ation omy ct management system PA18 SWIOFISH3 / Preparati Component 4: Project mana Individual Consult Under Implement IBRD / P4760 Post Open 30,000.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 on of Project Implementation gement and coordination ant Selection ation Manual PA25-SWIOFISH3 / Elaborati Component 3: Sustainable d on of a standardized proposa Individual Consult Under Implement IBRD / P4760 evelopment of the blue econ Post Open 50,000.00 0.00 2017-08-01 2017-09-19 2017-10-10 2017-11-14 2018-05-13 l assessment methology (blu ant Selection ation omy e bonds onlending) & Trainin g PA14-SWIOFISH3 / Value cha in and feasibility study to gui Component 3: Sustainable d Individual Consult Under Implement de investment in fish process IBRD / P4760 evelopment of the blue econ Post Open 50,000.00 0.00 2017-08-07 2017-09-25 2017-10-16 2017-11-20 2018-05-19 ant Selection ation ing & services sector and ass omy essment of maximum carryin g capacity PA34-SWIOFISH3 / Preparato ry activities for Seychelles to Component 2: Improved gov Individual Consult Under Implement IBRD / P4760 Post Open 20,000.00 0.00 2017-08-21 2017-10-09 2017-10-30 2017-12-04 2018-06-02 conduct first report for the Fi ernance of priority fisheries ant Selection ation sheries Transparency Initiativ e PA35-SWIOFISH3 / Develop Component 2: Improved gov Individual Consult Pending Impleme ment of an Institutional Strat IBRD / P4760 Post Open 25,000.00 0.00 2017-09-25 2017-11-13 2017-12-04 2018-01-08 2018-07-07 ernance of priority fisheries ant Selection ntation egic Plan for the Seychelles F ishing Authority PA36-SWIOFISH3 / Draft poli Component 3: Sustainable d cy on the management of by Individual Consult Under Implement IBRD / P4760 evelopment of the blue econ Post Open 20,000.00 0.00 2017-10-17 2017-12-05 2017-11-30 2017-12-26 2018-01-30 2018-07-29 catch landings by industrial fi ant Selection ation omy shing vessels in Seychelles PA16-SWIOFISH3 / Extension of Jan Robinson's contract (Pr oject Manager) for coordinati on and manage project prep Component 4: Project mana IBRD / P4760 Prior Direct Selection Direct 65,820.00 166,320.00 Signed 2017-11-24 2017-11-28 2017-11-24 2017-10-20 2017-11-24 2017-12-13 2018-12-31 aration and implementation gement and coordination activities in accordance to th e implementation arrangeme nts set forth in the loan and grant agreements . SWIOFISH3-PA32 / Environm Component 4: Project mana Individual Consult ent and Social Specialist to t IBRD / 87790 Post Open 90,000.00 90,000.00 Signed 2018-07-11 2018-04-05 2018-08-29 2018-09-19 2018-08-22 2018-10-24 2018-09-16 2019-04-22 gement and coordination ant Selection he Project Implementation U nit GEF14-SWIOFISH3 / Support Component 2: Improved gov Individual Consult to legal framework update (r IBRD / 87790 Post Limited 25,000.00 64,707.00 Signed 2019-04-17 2019-07-12 2019-04-22 2019-12-05 2019-05-13 2020-01-13 2019-06-17 2020-01-21 2019-12-14 ernance of priority fisheries ant Selection evision of Fisheries Act and r egulations) GEF15-SWIOFISH3 / Evaluati Component 1: Expansion of Pending Impleme on of the contribution of the IBRD / 87790 sustainable-use marine prot Post Direct Selection Direct 75,000.00 0.00 2019-05-15 2019-05-25 2019-07-29 2020-01-25 ntation extended MPA network to the ected areas economy Page 3 GEF17-SWIOFISH3 / Manage ment strategy evaluation an Component 2: Improved gov Pending Impleme IBRD / 87790 Post Direct Selection Direct 30,000.00 0.00 2019-07-01 2019-07-11 2019-09-14 2020-03-12 d capacity building (through ernance of priority fisheries ntation CSIRO cooperation) GEF19-SWIOFISH3 / Data ca Component 2: Improved gov IBRD / 87790 Post Direct Selection Direct 96,000.00 0.00 Canceled 2019-05-08 2019-05-08 2019-05-08 2021-06-15 pture software for SIH (EIS fe ernance of priority fisheries es) GEF26-SWIOFISH3 / Commu nication strategy and plan for Component 2: Improved gov Individual Consult IBRD / 87790 Post Open 35,000.00 0.00 Canceled 2019-06-15 2019-08-03 2019-08-24 2019-09-28 2020-03-26 Mahe Plateau fisheries mana ernance of priority fisheries ant Selection gement measures GEF29-SWIOFISH3 / Stock di Component 1: Expansion of Under Implement scrimination analysis to infor IBRD / 87790 sustainable-use marine prot Post Direct Selection Direct 135,000.00 0.00 2019-05-30 2019-11-29 2019-06-09 2019-08-13 2020-08-12 ation m marine spatial planning ected areas IBRD19-SWIOFISH3 / Annual Component 4: Project mana Pending Impleme financial audits of the project IBRD / 87790 Post Direct Selection Direct 50,000.00 0.00 2019-06-30 2019-07-10 2019-09-13 2024-09-11 gement and coordination ntation by the Office of the Auditor G eneral IBRD13-SWIOFISH3 / Monitor Component 4: Project mana Individual Consult ing and evaluation and com IBRD / 87790 Post Open 50,000.00 55,885.00 Completed 2019-04-15 2019-08-13 2019-06-03 2020-07-22 2019-06-24 2020-08-07 2019-07-29 2020-08-17 2020-01-25 2021-03-22 gement and coordination ant Selection munication specialist - expert support IBRD25-SWIOFISH3 / Procure Component 4: Project mana Individual Consult ment Assistant to the Project IBRD / 87790 Post Limited 85,000.00 79,200.00 Signed 2019-10-15 2019-10-24 2019-10-20 2019-12-20 2019-11-10 2020-01-08 2019-12-15 2020-02-26 2022-12-14 gement and coordination ant Selection Implementation Unit GEF31/IC/2020-SWF3 / Devel Component 1: Expansion of opment of Strategic Manage Individual Consult IBRD / 87790 sustainable-use marine prot Post Open 22,000.00 40,612.00 Completed 2020-02-23 2020-02-25 2020-04-12 2020-06-24 2020-05-03 2020-08-03 2020-06-07 2020-08-20 2020-12-04 2021-06-13 ment Framework for Seychell ant Selection ected areas es Marine Spatial Plan GEF24-SWIOFISH3 / Technic Component 1: Expansion of Individual Consult IBRD / 87790 Post Open 5,000.00 0.00 Canceled 2019-05-15 2019-07-03 2019-07-24 2019-08-28 2020-02-24 al assistant to MEECC for pre sustainable-use marine prot ant Selection paring TORs ected areas GEF11-SWIOFISH3 / Educatio n on fisheries management: Component 2: Improved gov Individual Consult IBRD / 87790 Post Open 45,000.00 0.00 Canceled 2019-06-30 2019-08-18 2019-09-08 2019-10-13 2020-04-10 course development, deliver ernance of priority fisheries ant Selection y, local trainer training GEF20-SWIOFISH3 / Data tra Component 2: Improved gov nsfer and trouble shootimg f IBRD / 87790 Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-04-15 2019-04-25 2019-06-29 2019-12-26 ernance of priority fisheries or longline logbook module f or Observe (IRD) GEF27-SWIOFISH3 / Develop Component 2: Improved gov ment of centralised vessel re IBRD / 87790 Post Direct Selection Direct 30,000.00 0.00 Canceled 2019-09-30 2019-10-10 2019-12-14 2020-04-07 ernance of priority fisheries gistry for SFA and SMSA IBRD18-SWIOFISH3 / Mud cr Component 3: Sustainable d IBRD / 87790 Post Direct Selection Direct 28,500.00 0.00 Canceled 2019-06-03 2019-06-13 2019-08-17 2020-08-11 ab recuitment study evelopment of the blue econ omy GEF39/IC/2020-SWF3 / Seyc Component 2: Improved gov Individual Consult helles' report to the Fisheries IBRD / 87790 Post Open 35,000.00 23,170.00 Completed 2020-04-30 2020-05-15 2020-06-18 2020-09-02 2020-07-09 2020-09-11 2020-08-13 2020-10-06 2021-02-09 2021-04-12 ernance of priority fisheries ant Selection Transparency Initiative GEF41/IC/2020-SWF3 / Traini ng on data analysis, risk asse Component 2: Improved gov Individual Consult Pending Impleme IBRD / 87790 Post Open 30,000.00 0.00 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2021-04-26 ssment and asset deploymen ernance of priority fisheries ant Selection ntation t planning for MCS GEF44/IC/2020-SWF3 / Scien tific design and analytical su Component 2: Improved gov Individual Consult IBRD / 87790 Post Open 45,000.00 77,233.00 Signed 2020-06-30 2021-03-17 2020-08-18 2021-06-11 2020-09-08 2021-08-03 2020-10-13 2021-08-09 2021-04-11 pport for a fisheries-indepen ernance of priority fisheries ant Selection dent assessment of sea cucu mber status GEF47/IC/2020-SWF3 / Study Component 2: Improved gov Individual Consult Pending Impleme on the implications of local b IBRD / 87790 Post Limited 25,000.00 0.00 2020-10-01 2020-10-06 2020-10-27 2020-12-01 2021-05-30 ernance of priority fisheries ant Selection ntation amboo utilisation for FADs GEF42/SSS/2020-SWF3 / Sec retary to Implementation Co- Component 2: Improved gov Individual Consult management Committee for IBRD / 87790 Post Direct 48,000.00 53,200.00 Signed 2020-04-15 2020-10-29 2020-04-25 2020-10-30 2020-05-16 2020-11-04 2020-06-20 2020-11-27 2020-12-17 ernance of priority fisheries ant Selection Mahe Plateau Demersal Fishe ries Management Plan IBRD31/SSS/2020-SWF3 / Fis Component 3: Sustainable d Pending Impleme h quality assessment training IBRD / 87790 evelopment of the blue econ Post Direct Selection Direct 48,000.00 0.00 2020-03-31 2020-04-10 2020-06-14 2020-12-11 ntation - Phase 2 (contract with firm omy SeaFish UK) IBRD10-SWIOFISH3 / Human Component 3: Sustainable d Individual Consult capacity development plan in IBRD / 87790 evelopment of the blue econ Post Open 28,500.00 0.00 Canceled 2019-04-30 2019-06-18 2019-07-09 2019-08-13 2020-02-09 ant Selection support of aquaculture sector omy GEF9-SWIOFISH3 / Implicatio Component 1: Expansion of ns of sustainable-use zone all Individual Consult Pending Impleme IBRD / 87790 sustainable-use marine prot Post Open 60,000.00 0.00 2020-05-15 2020-07-03 2020-07-24 2020-08-28 2021-02-24 owable activities on purse sei ant Selection ntation ected areas ne and long-line fisheries GEF10-SWIOFISH3 / Stock as sessment update: CPUE stan Component 2: Improved gov Individual Consult IBRD / 87790 Post Limited 40,000.00 0.00 Canceled 2020-04-15 2020-06-24 2020-04-20 2020-05-11 2020-06-15 2020-12-12 dardisation and production m ernance of priority fisheries ant Selection odels for indicator species GEF25-SWIOFISH3 / Capacity Component 2: Improved gov Individual Consult Pending Impleme building for Seychelles' Feder IBRD / 87790 Post Limited 50,000.00 0.00 2020-07-01 2020-07-06 2020-07-27 2020-08-31 2023-08-31 ernance of priority fisheries ant Selection ntation ation of Fisher Associations GEF28-SWIOFISH3 / Develop ment of a social accounting Component 2: Improved gov Individual Consult IBRD / 87790 Post Open 40,000.00 67,280.00 Signed 2020-05-15 2020-09-10 2020-07-03 2020-11-09 2020-07-24 2020-12-10 2020-08-28 2021-02-07 2021-01-25 matrix and artisanal fisheries ernance of priority fisheries ant Selection component for the fisheries s atellite account GEF13-SWIOFISH3 / Study to Component 2: Improved gov Individual Consult quantify public sector suppor IBRD / 87790 Post Open 35,000.00 41,202.70 Terminated 2020-09-15 2021-05-11 2020-11-03 2021-07-16 2020-11-24 2021-08-19 2020-12-29 2021-09-02 2021-06-27 ernance of priority fisheries ant Selection t to the fisheries sector Page 4 IBRD11-SWIOFISH3 / FBOA l Component 3: Sustainable d Individual Consult Pending Impleme abel program coordination a IBRD / 87790 evelopment of the blue econ Post Open 100,000.00 0.00 2020-04-30 2020-06-18 2020-07-09 2020-08-13 2022-08-13 ant Selection ntation nd management omy IBRD12-SWIOFISH3 / Needs Component 3: Sustainable d Individual Consult Pending Impleme assessment study for sanitar IBRD / 87790 evelopment of the blue econ Post Open 25,000.00 0.00 2020-09-30 2020-11-18 2020-12-09 2021-01-13 2021-07-12 ant Selection ntation y and phytosanitary monitori omy ng IBRD21-SWIOFISH3 / Nationa Component 3: Sustainable d l standard for sanitary and p Individual Consult IBRD / 87790 evelopment of the blue econ Post Open 40,000.00 0.00 Canceled 2019-10-01 2019-11-19 2019-12-10 2020-01-14 2020-07-12 htyosanitary including imple ant Selection omy mentation plan and roadmap GEF18-SWIOFISH3 / SFA co-fi Component 2: Improved gov nancing of SIH (fees and cost IBRD / 87790 Post Direct Selection Direct 60,000.00 0.00 Canceled 2019-04-15 2019-04-25 2019-06-29 2019-12-26 ernance of priority fisheries s for IFREMER) GEF16-SWIOFISH3 / THEMIS Component 1: Expansion of AIS, Radar installation maint IBRD / 87790 sustainable-use marine prot Post Direct Selection Direct 441,500.00 0.00 Canceled 2019-04-15 2019-08-29 2019-04-25 2019-06-29 2019-12-26 enance and subscription cost ected areas s GEF8-SWIOFISH3 / Drafting Component 1: Expansion of of governance authority esta Individual Consult IBRD / 87790 sustainable-use marine prot Post Limited 30,000.00 0.00 Canceled 2019-04-30 2020-02-23 2019-05-05 2019-05-26 2019-06-30 2019-12-27 blishment act and other MSP ant Selection ected areas regulatory frameworks GEF30/IC/2020-SWF3 / Study Component 1: Expansion of Individual Consult on the status of ETP sharks a IBRD / 87790 sustainable-use marine prot Post Open 60,000.00 74,570.00 Signed 2020-05-29 2021-02-09 2020-07-17 2021-05-10 2020-08-07 2021-05-27 2020-09-11 2021-06-16 2021-03-10 ant Selection nd rays in MSP zones ected areas GEF38/IC/2020-SWF3 / Socio Component 2: Improved gov Individual Consult Under Implement -economic impact assessmen IBRD / 87790 Post Open 40,000.00 0.00 2020-06-01 2021-10-07 2020-07-20 2020-08-10 2020-09-14 2021-03-13 ernance of priority fisheries ant Selection ation ts for fisheries management measures IBRD14-SWIOFISH3 / Environ Component 4: Project mana Individual Consult mental and social specialist - IBRD / 87790 Post Limited 40,000.00 0.00 Canceled 2019-04-15 2020-05-05 2019-04-20 2019-05-11 2019-06-15 2020-06-14 gement and coordination ant Selection local expert on retainer IBRD14-SWIOFISHA / ENVIRO Component 4: Project mana Individual Consult IBRD / 87790 Post Open 40,000.00 55,878.00 Completed 2020-05-06 2020-05-05 2020-06-24 2020-06-25 2020-07-15 2020-08-05 2020-08-19 2020-08-19 2021-02-15 2021-09-13 NMENTAL AND SOCIAL SPECI gement and coordination ant Selection ALIST IBRD33/SSS/2020-SWF3 / Mo Component 4: Project mana nitoring and Evaluation Speci IBRD / 87790 Post Direct Selection Direct 90,000.00 90,000.00 Signed 2020-05-06 2020-05-05 2020-05-16 2020-05-22 2020-07-20 2020-06-13 2023-07-20 gement and coordination alist for the PIU IBRD5-SWIOFISH3 / Support to the Development Bank of Component 3: Sustainable d Seychelles for Implementatio Individual Consult Pending Impleme IBRD / 87790 evelopment of the blue econ Post Open 25,000.00 0.00 2020-09-14 2020-11-02 2020-11-23 2020-12-28 2021-12-23 n of the Blue Investment Fun ant Selection ntation omy d: Financial analyst on retain er for DBS capacity building and technical backstopping IBRD34/SSS/2020-SWF3 / Up dating the manuals for the Bl Component 3: Sustainable d ue Investment Fund of the D IBRD / 87790 evelopment of the blue econ Post Direct Selection Direct 15,000.00 12,000.00 Completed 2020-09-03 2020-09-03 2020-09-13 2020-09-04 2020-11-17 2020-09-14 2021-01-16 2021-06-15 evelopment Bank of Seychell omy es to incorporate proposed c hanges to the fund GEF10-SWIOFISH3A / Stock assessment update; CPUE st Component 2: Improved gov Individual Consult IBRD / 87790 Post Open 40,000.00 23,267.00 Completed 2020-12-09 2020-12-11 2021-01-27 2021-02-12 2021-02-17 2021-02-17 2021-03-24 2021-03-06 2021-09-20 2021-12-15 andardization and production ernance of priority fisheries ant Selection models for indicator species. IBRD37/IC/2021-SWF3 / Mid Component 4: Project mana Individual Consult IBRD / 87790 Post Open 40,000.00 36,270.00 Terminated 2021-02-02 2021-02-24 2021-03-23 2021-04-19 2021-04-13 2021-05-12 2021-05-18 2021-05-31 2021-11-14 term Evaluation for SWIOFish gement and coordination ant Selection 3 Project GEF55/IC/2021-SWF3 / Tech nical Assistant to Seychelles Component 3: Sustainable d Individual Consult Conservation and Climate Ad IBRD / 87790 evelopment of the blue econ Post Limited 90,000.00 60,000.00 Signed 2021-02-10 2021-02-23 2021-02-15 2021-03-01 2021-03-08 2021-03-03 2021-04-12 2021-03-22 2021-10-09 ant Selection aptation Trust (SeyCCAT) for omy the Blue Grants Fund (Blue B ond proceeds) GEF53/CQS/2021-SWF3 / Tec hnical assistant to the Ministr Component 2: Improved gov IBRD / P4760 Post Direct Selection Direct 72,000.00 0.00 Canceled 2021-03-22 2021-04-01 2021-06-05 2021-12-02 y of Fisheries and the Blue Ec ernance of priority fisheries onomy: marketing specialist GEF57/SSS/2021-SWF3 / Pro Component 2: Improved gov duction of Seychelles 2nd an IBRD / 87790 Post Direct Selection Direct 35,000.00 15,720.00 Completed 2021-07-13 2021-07-07 2021-07-23 2021-07-13 2021-09-26 2021-08-07 2022-03-25 2021-12-21 ernance of priority fisheries nual report to FiTI IBRD8-SWIOFISH3 / Environ mental and Social Impact Ass Component 3: Sustainable d essments for Blue Investmen Individual Consult IBRD / 87790 evelopment of the blue econ Post Limited 15,000.00 26,660.00 Signed 2021-08-19 2021-08-23 2021-08-24 2021-08-09 2021-09-14 2021-10-06 2021-10-19 2021-10-25 2022-04-17 t Fund Application, Providenc ant Selection omy e Industrial Zone & Fish Proc essing Land, Zone 14, Ile Du Port GEF12-SWIOFISH3 DS / Liais Component 2: Improved gov on Officer for the Mahe Plate IBRD / 87790 Post Direct Selection Direct 24,000.00 26,353.59 Signed 2021-09-24 2021-10-09 2021-10-04 2021-10-11 2021-12-08 2021-11-14 2022-06-06 ernance of priority fisheries au Trap and Line Fishery Co- management Plan GEF53/IC/2021-SWF3 / Devel Component 2: Improved gov Individual Consult IBRD / 87790 Post Open 72,000.00 43,834.85 Signed 2021-10-29 2021-10-15 2021-12-17 2022-07-26 2022-01-07 2022-08-09 2022-02-11 2022-08-25 2022-08-10 opment of a Market Intelligen ernance of priority fisheries ant Selection ce Plan GEF7/DS/2021-SWF3 / Surve Component 1: Expansion of y of Perceptions on Ocean Go IBRD / 87790 sustainable-use marine prot Post Direct Selection Direct 25,000.00 71,041.54 Signed 2021-11-23 2022-02-04 2021-12-03 2021-11-08 2022-02-06 2022-03-26 2022-08-05 vernance, Fisheries Manage ected areas ment and the Blue Economy GEF12-SWIOFISH3 / Liaison Component 2: Improved gov Individual Consult officer for Mahe Plateau Dem IBRD / 87790 Post Open 24,000.00 0.00 Canceled 2019-04-30 2019-09-13 2019-06-18 2019-07-09 2019-08-13 2020-02-09 ernance of priority fisheries ant Selection ersal Fisheries Management Plan GEF60/IC/2022-SWF3-C2 / P REPARATION OF SEYCHELLES Component 2: Improved gov Individual Consult IBRD / 87790 Post Open 25,000.00 10,585.00 Signed 2022-04-29 2022-04-21 2022-06-17 2022-08-01 2022-07-08 2022-08-17 2022-08-12 2022-09-03 2023-02-08 ’ 3rd NATIONAL REPORT TO T ernance of priority fisheries ant Selection HE FISHERIES TRANSPARENC Y INITIATIVE Page 5 IBRD27/IC/2020-SWF3 / Stud Component 3: Sustainable d Individual Consult y of post-harvest losses and i IBRD / 87790 evelopment of the blue econ Post Open 30,000.00 0.00 Canceled 2020-09-01 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection ntroduction of routine survey omy methodology GEF66/SSS/2022-SWF3 / Log Component 2: Improved gov Individual Consult Direct - Internation istical and technical backstop IBRD / 87790 Post 5,000.00 0.00 Signed 2022-09-25 2022-09-27 2022-10-05 2022-09-14 2022-10-26 2022-09-27 2022-11-30 2022-10-06 2023-05-29 ernance of priority fisheries ant Selection al ping for P2P: Shetland, UK GEF67/SSS/2022-SWF3 / Log Component 2: Improved gov Individual Consult Direct - Internation istical and technical backstop IBRD / 87790 Post 5,000.00 0.00 Signed 2022-09-26 2022-09-27 2022-10-06 2022-09-13 2022-10-27 2022-09-28 2022-12-01 2022-10-06 2023-05-30 ernance of priority fisheries ant Selection al ping for P2P: Sete, France GEF59/IC/2022-SWF3 / Tech nical Assistant to MACCE on Component 1: Expansion of Individual Consult MSP surveillance options, pil IBRD / 87790 sustainable-use marine prot Post Limited 70,000.00 0.00 Signed 2022-10-10 2022-10-12 2022-10-15 2022-10-31 2022-11-05 2022-12-20 2022-12-10 2023-01-01 2023-06-08 ant Selection oting, tender preparation and ected areas asset purchasing oversight GEF63/IC/2022-SWF3 / Revie Component 2: Improved gov Individual Consult Open - Internationa w fisheries sector strategy an IBRD / 87790 Post 30,000.00 0.00 Signed 2022-10-10 2022-10-19 2022-11-28 2022-12-12 2022-12-19 2022-12-16 2023-01-23 2023-01-01 2023-07-22 ernance of priority fisheries ant Selection l d comprehensive plan imple mentation IBRD8/IC/2022-SWF3 / Envir Component 3: Sustainable d onmental and Social Impact Individual Consult IBRD / 87790 evelopment of the blue econ Post Limited 30,000.00 0.00 Signed 2022-11-20 2023-02-14 2022-11-25 2023-01-05 2022-12-16 2023-02-22 2023-01-20 2023-03-10 2023-07-19 Assessments for Island Devel ant Selection omy opment Company Prawn Proj ect, Coetivy Island GEF13-SWIOFISH3-2 / Public Component 2: Improved gov Individual Consult Sector Support to the Seyche IBRD / 87790 Post Limited 17,000.00 0.00 Signed 2023-01-11 2023-01-25 2023-01-16 2023-02-07 2023-02-06 2023-02-21 2023-03-13 2023-03-23 2023-09-09 ernance of priority fisheries ant Selection lles Fisheries Sector IBRD39/IC/2023-SWF3 / Inter Component 4: Project mana Individual Consult IBRD / 87790 Post Limited 10,000.00 0.00 Signed 2023-02-21 2023-02-22 2023-02-26 2023-02-15 2023-03-19 2023-04-06 2023-04-23 2023-05-17 2023-10-20 nal Audit of SeyCCAT gement and coordination ant Selection IBRD45/SSS/2023-SWF3 / As Component 3: Sustainable d Individual Consult sessing the Potential of the Li IBRD / 87790 evelopment of the blue econ Post Direct - National 30,000.00 0.00 Signed 2023-03-14 2023-03-13 2023-03-24 2023-03-15 2023-04-14 2023-03-24 2023-05-19 2023-04-05 2023-11-15 ant Selection ve Aboard and Yachting Indu omy stry IBRD46/IC/2023-SWF3 / Crea Component 3: Sustainable d Individual Consult ting awareness on the econo IBRD / 87790 evelopment of the blue econ Post Limited 60,000.00 0.00 Canceled 2023-03-14 2023-03-13 2023-03-19 2023-04-09 2023-05-14 2023-11-10 ant Selection mic potential of Seychelles’ B omy lue Economy IBRD46/IC/2023/SWF3 / Crea Component 3: Sustainable d Individual Consult ting awareness on the econo IBRD / 87790 evelopment of the blue econ Post Limited 30,000.00 0.00 Signed 2023-03-26 2023-04-04 2023-03-31 2023-03-21 2023-04-21 2023-04-21 2023-05-26 2023-05-02 2023-11-22 ant Selection mic potential of Seychelles' B omy lue Economy IBRD47/SSS/2023-SWF3 / Fu Component 3: Sustainable d Individual Consult Direct - Internation nctional Review of the Fish In IBRD / 87790 evelopment of the blue econ Post 30,000.00 0.00 Signed 2023-03-26 2023-04-04 2023-04-05 2023-04-14 2023-04-26 2023-04-27 2023-05-31 2023-05-18 2023-11-27 ant Selection al spection and Quality Control omy Unit (FIQCU) IBRD48/IC/2023-SWF3 / Asse Component 3: Sustainable d ssing the economic potential Individual Consult Under Implement IBRD / 87790 evelopment of the blue econ Post Limited 40,000.00 0.00 2023-03-26 2023-04-12 2023-03-31 2023-04-12 2023-04-21 2023-05-26 2023-11-22 of the Seychelles’ Blue Econo ant Selection ation omy my and business case planni ng for key sectors. GEF67/SSS/2023-SWF3 / Dev Component 1: Expansion of elopment of boiler plate texts IBRD / P4760 sustainable-use marine prot Post Direct Selection Direct - National 3,000.00 0.00 Signed 2023-04-16 2023-05-02 2023-04-26 2023-05-03 2023-06-30 2023-05-17 2023-12-27 for MPA Management Plans ected areas IBRD49/IC/2023-SWF3 / Com Component 3: Sustainable d Individual Consult Under Implement munication specialist for the IBRD / 87790 evelopment of the blue econ Post Limited 20,000.00 0.00 2023-05-29 2023-07-14 2023-06-03 2023-07-18 2023-06-24 2023-07-29 2024-01-25 ant Selection ation Department of Blue Economy omy GEF70/SSS/2023-SWF3 / Str Component 1: Expansion of ategic Threat and Risk Asses Direct - Internation IBRD / P4760 sustainable-use marine prot Post Direct Selection 30,000.00 0.00 Signed 2023-08-15 2023-08-12 2023-08-25 2023-08-16 2023-10-29 2023-09-29 2024-04-26 sment for MPAs Designated u al ected areas nder the Seychelles Marine S patial Plan IBRD50/IC/2023-SWF3 / Prep aration of Options Paper on Component 3: Sustainable d Individual Consult Open - Internationa Under Implement Marketing Opportunities for F IBRD / 87790 evelopment of the blue econ Post 20,000.00 0.00 2023-08-31 2023-08-29 2023-10-19 2023-11-09 2023-12-14 2024-06-11 ant Selection l ation infish Products of the Mahé Pl omy ateau Trap and Line Fishery of Seychelles IBRD51/IC/203-SWF3 / Monit oring and evaluation support Component 4: Project mana Individual Consult Open - Internationa Under Implement IBRD / 87790 Post 30,000.00 0.00 2023-10-15 2023-10-10 2023-12-03 2023-12-24 2024-01-28 2024-07-26 for data quality review, result gement and coordination ant Selection l ation s framework, final evaluation preparation IBRD52/SSS/2023-SWF3 / Un Component 3: Sustainable d Direct - Internation Under Implement derstanding the Risks of Clim IBRD / 87790 evelopment of the blue econ Post Direct Selection 100,000.00 0.00 2023-10-13 2023-10-10 2023-10-23 2023-12-27 2024-06-24 al ation ate Change to Seychelles’ Fis omy heries Sector GEF71/SSS/2023-SWF3 / Tec hnical support for developing Component 2: Improved gov Individual Consult Direct - Internation IBRD / 87790 Post 30,000.00 0.00 Canceled 2023-09-05 2023-10-04 2023-09-15 2023-10-06 2023-11-10 2024-05-08 a Harvest Strategy for Seych ernance of priority fisheries ant Selection al elles’ sea cucumber fishery GEF72/IC/2023-SWF3 / Devel Component 2: Improved gov Individual Consult Open - Internationa Under Implement opment of Legal Framework f IBRD / P4760 Post 20,000.00 0.00 2023-11-06 2023-11-06 2023-12-25 2024-01-15 2024-02-19 2024-08-17 ernance of priority fisheries ant Selection l ation or the regulations of FADS IBRD53/IC/2023-SWF3 / Soci Component 3: Sustainable d al Impact Assessment of the Individual Consult Under Implement IBRD / P4760 evelopment of the blue econ Post Limited 30,000.00 0.00 2023-11-06 2023-11-29 2023-11-11 2023-12-02 2024-01-06 2024-07-04 Sustainable Use Seychelles M ant Selection ation omy arine Spatial Plan (MPAs GEF38/IC/2023-SWF3-2 / Soc io-economic impact assessm Component 2: Improved gov Individual Consult IBRD / 87790 Post Limited 30,000.00 0.00 Under Review 2023-12-10 2023-12-06 2023-12-15 2024-01-05 2024-02-09 2024-08-07 ent of the Mahé Plateau trap ernance of priority fisheries ant Selection and line fishery co-managem ent plan IBRD54/IC/2023-SWF3 / Envi Component 3: Sustainable d ronment and Social Manage Individual Consult Open - Internationa IBRD / 87790 evelopment of the blue econ Post 30,000.00 0.00 Under Review 2023-12-21 2023-12-06 2024-02-08 2024-02-29 2024-04-04 2024-10-01 ment System (ESMS) for Dev ant Selection l omy elopment Bank of Seychelles (DBS) IBRD55/IC/2023-SWF3 / SWI Component 4: Project mana Individual Consult Open - Internationa Pending Impleme IBRD / 87790 Post 30,000.00 0.00 2024-02-04 2024-03-24 2024-04-14 2024-05-19 2024-11-15 OFish3 Final project report gement and coordination ant Selection l ntation Page 6 IBRD56/IC/2023-SWF3 / Envi Component 3: Sustainable d Individual Consult Pending Impleme ronmental and Social Manag IBRD / 87790 evelopment of the blue econ Post Limited 5,000.00 0.00 2024-01-18 2024-01-23 2024-02-13 2024-03-19 2024-09-15 ant Selection ntation ement for Blue Investments F omy und Applicant Page 7