Procurement Plan – Project Preparation Advance P4760
             3rd South West Indian Ocean Project

I. General

2.        Bank’s approval Date of the procurement Plan: 26th January 2017
3.        Date of General Procurement Notice: Pending
4.        Period covered by this procurement plan: 28th April 2016 to
          31st December 2017


II. Goods and Works and non-consulting services.

1.        Prior Review Threshold: Procurement Decisions subject to Prior
          Review by the Bank as stated in Appendix 1 to the Guidelines for
          Procurement:
                        Procurement Method               Prior Review          Comments
                                                          Threshold
                                                             US$
            1.     ICB and LIB (Goods)              Above US$ 500,000               All
            2.     NCB (Goods)                      Above US$ 100,000         First contract
            3.     ICB (Works)                     Above US$ 15 million             All
            4.     NCB (Works)                     Above US$ 5 million              All
            5.      (Non-Consultant Services)       Below US$ 100,000         First contract
                   [Add other methods if
                   necessary]

2.        Prequalification. Bidders for _Not applicable_ shall be prequalified in
          accordance with the provisions of paragraphs 2.9 and 2.10 of the
          Guidelines.

3.        Proposed Procedures for CDD Components (as per paragraph.
          3.17 of the Guidelines: N/A

4.        Reference to (if any) Project Operational/Procurement Manual:
          Under preparation

5.        Any Other Special Procurement Arrangements: N/A

6.        Summary of the Procurement Packages planned during the first 18
          months after project effectiveness

      1             2           3           4        5          6         7

     Ref.        Descripti   Estimat    Packages   Dome      Review     Comme
     No.            on         ed                   stic     by Bank      nts
                              Cost
July 9, 2010
                            US$                 Prefe     (Prior /
                           million              rence      Post)
                                                (yes/
                                                 no)
           Summary
           of the ICB
           (Works)
           Summary
           of the ICB
           (Goods)
           Summary
           of the NCB
           (Works)
           Summary
           of the NCB
           (Goods)
           Summary
           of the ICB
           (Non-
           Consultant
           Services)

III. Selection of Consultants

1.     Prior Review Threshold: Selection decisions subject to Prior Review
       by Bank as stated in Appendix 1 to the Guidelines Selection and
       Employment of Consultants:

                       Selection Method             Prior Review            Comments
                                                     Threshold
         1.       Competitive Methods (Firms)     Above US$ 100,000
         2.       Single Source (Firms)                   All
         3.       Individual                      Above US$ 50,000

     2. Short list comprising entirely of national consultants: Short list of
        consultants for services, estimated to cost less than
        $_100,000_equivalent per contract, may comprise entirely of national
        consultants in accordance with the provisions of paragraph 2.7 of the
        Consultant Guidelines.

3.     Any Other Special Selection Arrangements: N.A

4.     Consultancy Assignments with Selection Methods and Time
       Schedule

              1             2              3       4         5          6

       Ref. No.       Description    Estimate   Package   Review     Comment
                      of             d          s         by         s
                      Assignmen      Cost                 Bank
                      t              US$
July 9, 2010
                                           (Prior /
                                           Post)
               Summary     245,000    2    Post
               of number
               of
               contracts
               that will
               be let
               under
               QCBS
               Summary     1,015,00   17   Prior &    CQS, IC,
               of number   0               Post       SSS
               of
               contracts
               that will
               be let
               under
               other
               methods




July 9, 2010
PROCUREMENT
                Eastern and Southern Africa : Third South West Indian Ocean Fisheries Governance and Shared Growth Project (SWIOFish3)
PLAN
General Information
Country:           Eastern and Southern Africa                                                              2017-04-04
                                                       Bank’s Approval Date of the Original Procurement Plan:
                                                                                                            2023-12-04
                                                       Revised Plan Date(s): (comma delineated, leave blank if none)
Project ID:        P155642                             GPN Date:
Project Name:      Third South West Indian Ocean Fisheries Governance and Shared Growth Project (SWIOFish3)
Loan / Credit No:  IBRD / P4760, IBRD / 87790
                   Ministry of Finance, Trade and the Blue Economy
Executing Agency(ies):

WORKS
Activity Reference No. /                                                                                                                                                                          Estimated Actual Am                                                                                                                                                                                      Bid Evaluation Report
                                 Loan / Credit N                                                                      Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D                     Process St Draft Pre-qualification Prequalification Evalu                                   Draft Bidding Docum Specific Procurement       Bidding Documents a Proposal Submission /                                                               Contract Complet
       Description                                        Component                Review Type       Method                                                                                       Amount (U ount (US$                                                                                                                                                                                      and Recommendation                    Signed Contract
                                        o.                                                                                   h             cess           (Y/N)             isk     ocument Type                         atus         Documents               ation Report                                         ent / Justification Notice / Invitation             s Issued        Opening / Minutes                                                                        ion
                                                                                                                                                                                                      S$)       )                                                                                                                                                                                                for Award
                                                                                                                                                                                                                                  Planned     Actual      Planned      Actual                                     Planned       Actual      Planned     Actual    Planned     Actual  Planned     Actual    Planned     Actual                 Planned       Actual      Planned




GOODS
Activity Reference No. /                                                                                                                                                                                                                                                                                                                                                              Bid Evaluation Report
                                 Loan / Credit N                                                                      Market Approac Procurement Pro Prequalification Estimated Am Actual Amount                      Process St Draft Pre-qualification Prequalification Evalu         Draft Bidding Docum Specific Procurement            Bidding Documents a Proposal Submission /
       Description                                        Component                Review Type       Method                                                                                                                                                                                                                                                                           and Recommendation               Signed Contract         Contract Completion
                                        o.                                                                                   h             cess           (Y/N)        ount (US$)      (US$)                             atus         Documents              ation Report                ent / Justification Notice / Invitation                  s Issued        Opening / Minutes
                                                                                                                                                                                                                                                                                                                                                                                            for Award
                                                                                                                                                                                                                                     Planned      Actual      Planned       Actual      Planned       Actual      Planned       Actual       Planned     Actual  Planned     Actual    Planned     Actual            Planned       Actual      Planned       Actual

 GEF23-SWIOFISH3 / FEIU pur                        Component 2: Improved gov                     Request for Quota                           Single Stage - One E
                            IBRD / 87790                                         Post                              Open - National                                                      12,000.00         25,561.00   Completed                                                                                   2020-07-05   2021-06-06                                                                            2020-08-30   2021-10-14   2021-02-26   2022-02-19
chase of data servers                              ernance of priority fisheries                 tions                                       nvelope


 GEF16/G/2020-SWF3 / THEM                          Component 1: Expansion of
                                                                                                                                             Single Stage - One E                                                     Under Imple
IS AIS, Radar installation and   IBRD / 87790      sustainable-use marine prot   Post            Request for Bids     Limited                                                          160,000.00              0.00                                                                     2020-03-31   2020-04-24   2020-04-05                                     2020-05-17                2020-06-16                2020-07-21                2021-01-17
                                                                                                                                             nvelope                                                                  mentation
maintenance                                        ected areas


 IBRD28/G/2020-SWF3 / Equi                         Component 3: Sustainable d                    Request for Quota Open - Internationa Single Stage - One E
                                 IBRD / 87790                                  Post                                                                                                     25,000.00         37,249.65   Signed                                                                                      2020-08-19   2021-11-18                                                                            2020-10-14   2022-06-23   2021-04-12
pment for SFA post harvest l                       evelopment of the blue econ                   tions             l                   nvelope
ab                                                 omy

 GEF43/G/2020-SWF3 / Purch                         Component 2: Improved gov                     Request for Quota                           Single Stage - One E                                                     Pending Impl
                              IBRD / 87790                                       Post                              Open - National                                                      55,000.00              0.00                                                                                               2020-11-21                                                                                         2021-01-16                2021-07-15
asing Surveillance tender ves                      ernance of priority fisheries                 tions                                       nvelope                                                                  ementation
sel.

 IBRD42/G/2021/EQUIPMENT
FOR SBS/FIQCU / Equipment f
or Seychelles Bureau of Stan                       Component 3: Sustainable d
                                                                                                                      Open - Internationa Single Stage - One E
dards (HIGH PERFORMANCE       IBRD / 87790         evelopment of the blue econ Post              Request for Bids                                                                      336,000.00        282,146.93   Signed                                                            2021-11-26   2022-03-03   2021-12-01   2022-03-06                        2022-01-12   2022-04-19   2022-02-11   2022-05-12   2022-03-18   2022-06-27   2022-09-14
                                                                                                                      l                   nvelope
LIQUID CHROMATOGRAPH (H                            omy
PLC) and SINGLE QUADRUPO
LE INDUCTIVELY COUPLED PL
ASMA MASS SPECTROMETER
(ICP MS) )
 GEF52/NCS/2021-SWF3 / Pur                         Component 2: Improved gov                                          Open - Internationa Single Stage - One E
                              IBRD / 87790                                       Post            Request for Bids                                                                      350,000.00              0.00   Signed                                                            2022-07-31   2023-03-24   2022-08-05   2023-03-24                        2022-09-16   2023-04-27   2022-10-16   2023-05-25   2022-11-20   2023-07-06   2023-05-19
chase of one vessel for surve                      ernance of priority fisheries                                      l                   nvelope
illance

 IBRD48/RFB/2022-SWF3 / De
                                                   Component 3: Sustainable d
sign and build of containerise                                                                                        Open - Internationa Single Stage - One E
                               IBRD / 87790        evelopment of the blue econ Post              Request for Bids                                                                      200,000.00              0.00   Signed                                                            2022-09-30   2022-11-21   2022-10-05   2023-01-27                        2022-11-16   2023-02-28   2022-12-16   2023-03-14   2023-01-20   2023-04-04   2023-07-19
d hatchery in support of local                                                                                        l                   nvelope
                                                   omy
small-scale invertebrate aqu
aculture development

 GEF66/G/2023-SWF3 / Purch
                                                   Component 1: Expansion of
ase of diving and survey equi                                                                                         Open - Internationa Single Stage - One E                                                        Under Imple
                              IBRD / 87790         sustainable-use marine prot   Post            Request for Bids                                                                      100,000.00              0.00                                                                     2023-02-08   2023-05-19   2023-02-13   2023-05-19                        2023-03-27                2023-04-26                2023-05-31                2023-11-27
pment for National Marine Pr                                                                                          l                   nvelope                                                                     mentation
                                                   ected areas
otected Area Authority


 IBRD42/G/2023-SWF3/ EQUI                          Component 3: Sustainable d
                                                                                                 Request for Quota Open - Internationa Single Stage - One E
PMENT FOR POST H / Equipm IBRD / 87790             evelopment of the blue econ Post                                                                                                     15,000.00              0.00   Signed                                                                                      2023-02-12   2023-03-16                                                                            2023-04-09   2023-05-02   2023-10-06
                                                                                                 tions             l                   nvelope
ent for post harvest lab: blast                    omy
freezer

 GEF68/G/2023-SWF3 / Upgra                         Component 1: Expansion of
                                                                                                 Request for Quota Open - Internationa Single Stage - One E                                                           Under Imple
de to the national GIS system IBRD / P4760         sustainable-use marine prot   Post                                                                                                   40,000.00              0.00                                                                                               2023-04-23   2023-09-04                                                                            2023-06-18                2023-12-15
                                                                                                 tions             l                   nvelope                                                                        mentation
to support boundary limitatio                      ected areas
n and the MSP

 GEF65/G/2022-SWF3 / Purch                         Component 1: Expansion of                                          Open - Internationa Single Stage - One E                                                        Pending Impl
                             IBRD / 87790                                        Post            Request for Bids                                                                      500,000.00              0.00                                                                     2023-12-20                2023-12-25                                     2024-02-05                2024-03-06                2024-04-10                2024-10-07
ase of surveillance equipmen                       sustainable-use marine prot                                        l                   nvelope                                                                     ementation
t for MSP                                          ected areas

 GEF73/G/2023-SWF3 / FAD
                                                   Component 1: Expansion of
Module for Themis and syste                                                                                           Direct - Internation                                                                            Under Imple
                                 IBRD / 87790      sustainable-use marine prot   Post            Direct Selection                                                                       40,000.00              0.00                                                                     2023-12-07   2023-12-05   2023-12-12   2023-12-05                                                                            2024-01-16                2024-07-14
m for NICSS data sharing to                                                                                           al                                                                                              mentation
                                                   ected areas
use data for FAD recovery




NON CONSULTING SERVICES
Activity Reference No. /                                                                                                                                                                                                                                                                                                                                                              Bid Evaluation Report
                                 Loan / Credit N                                                                      Market Approac Procurement Pro Prequalification Estimated Am Actual Amount                      Process St Draft Pre-qualification Prequalification Evalu         Draft Bidding Docum Specific Procurement            Bidding Documents a Proposal Submission /
       Description                                        Component                Review Type       Method                                                                                                                                                                                                                                                                           and Recommendation               Signed Contract         Contract Completion
                                        o.                                                                                   h             cess           (Y/N)        ount (US$)      (US$)                             atus         Documents              ation Report                ent / Justification Notice / Invitation                  s Issued        Opening / Minutes
                                                                                                                                                                                                                                                                                                                                                                                            for Award
                                                                                                                                                                                                                                     Planned      Actual      Planned       Actual      Planned       Actual      Planned       Actual       Planned     Actual  Planned     Actual    Planned     Actual            Planned       Actual      Planned       Actual
 GEF35/NCS/2020-SWF3 / Pro
                                                   Component 2: Improved gov                                          Open - Internationa Single Stage - One E                                                        Pending Impl
vision of satellite data (AIS, r IBRD / 87790                                    Post            Request for Bids                                                                      231,000.00              0.00                                                                     2020-09-01                2020-09-06                                     2020-10-18                2020-11-17                2020-12-22                2023-12-22
                                                   ernance of priority fisheries                                      l                   nvelope                                                                     ementation
adar, imagery) to Seychelles
Fishing Authority

IBRD20/RFB/2020-SWF3 / GE                          Component 3: Sustainable d
                                                                                                                                             Single Stage - Two E                                                     Pending Impl
OTECH SURVEY FOR GRAND IBRD / 87790                evelopment of the blue econ Post              Request for Bids     Open - National                                                  200,000.00              0.00                                                                     2020-06-01                2020-06-06                                     2020-07-18                2020-09-30                2020-11-04                2021-05-03
                                                                                                                                             nvelope                                                                  ementation
ANSE AQUACULTURE HUB                               omy




CONSULTING FIRMS
Activity Reference No. /                                                                                                                                                                                                                                                                                                                                                     Combined Evaluation
                                 Loan / Credit N                                                                      Market Approac          Contract Type         Estimated Amo Actual Amount                                                  Expression of Interest Short List and Draft R Request for Proposals Opening of Technical              Evaluation of Technic
       Description                                        Component                Review Type        Method                                                                                    Process Status         Terms of Reference                                                                                                                                    Report and Draft Neg         Signed Contract         Contract Completion
                                        o.                                                                                   h                                         unt (US$)      (US$)                                                             Notice          equest for Proposals        as Issued         Proposals / Minutes                   al Proposal
                                                                                                                                                                                                                                                                                                                                                                                otiated Contract
                                                                                                                                                                                                                       Planned       Actual       Planned      Actual      Planned       Actual      Planned       Actual      Planned       Actual    Planned      Actual    Planned     Actual        Planned       Actual      Planned       Actual
 PA2-SWIOFISH3 / Evaluation                        Component 1: Expansion of
                                                                                                 Consultant Qualifi   Open - Internationa
of the contribution of the ext IBRD / P4760        sustainable-use marine prot   Post                                                                                    75,000.00           0.00   Canceled          2018-08-20                 2018-09-10   2018-08-21   2018-10-24                                                                                         2018-11-23                2018-12-28                2019-06-26
                                                                                                 cation Selection     l
ended MPA network to the ec                        ected areas
onomy

 PA3-SWIOFISH3 / Education
                                                   Component 2: Improved gov                     Consultant Qualifi   Open - Internationa
and awareness program on fi IBRD / P4760                                         Post                                                                                    50,000.00           0.00   Canceled          2017-05-15                 2017-05-15   2018-01-23   2017-05-15                                                                                         2017-05-15                2017-06-05                2017-12-02
                                                   ernance of priority fisheries                 cation Selection     l
sheries management plan im
plementation




                                                                                                                                                                                                                                        Page 1
 IBRD4-SWIOFISH3 / Fisheries
                                                Component 3: Sustainable d
sector employment survey &                                                           Consultant Qualifi   Open - Internationa
                              IBRD / 87790      evelopment of the blue econ Post                                                 75,000.00         0.00   Canceled          2019-04-15                 2019-05-06   2019-06-04   2019-06-19                                                                    2019-07-19                2019-08-23                2020-02-19
identify method for routine e                                                        cation Selection     l
                                                omy
mployment monitoring


 GEF5-SWIOFISH3 / Drafting                      Component 1: Expansion of
                                                                                     Consultant Qualifi
of a coral reef conservation p IBRD / 87790     sustainable-use marine prot   Post                        Open - National        50,000.00    48,278.00   Completed         2019-05-15   2019-08-27    2019-06-05                2019-07-19   2019-11-11                                                       2019-08-18   2020-03-17   2019-09-22   2020-04-08   2020-03-20   2021-04-20
                                                                                     cation Selection
olicy and plan                                  ected areas


 GEF7-SWIOFISH3 / Perceptio
n survey of management per                      Component 1: Expansion of
                                                                                     Consultant Qualifi
formance for sustainable use     IBRD / 87790   sustainable-use marine prot   Post                        Open - National        25,000.00         0.00   Canceled          2019-04-30   2019-11-29    2019-05-21                2019-07-04                                                                    2019-08-03                2019-09-07                2020-03-05
                                                                                     cation Selection
area and fisheries plans (info                  ected areas
rmation for M&E indicator)


 IBRD17-SWIOFISH3 / Develo                      Component 3: Sustainable d           Consultant Qualifi   Open - Internationa
                                 IBRD / 87790                               Post                                                 80,000.00   104,030.00   Signed            2019-06-30   2020-01-21    2019-07-21                2019-09-03   2020-05-13                                                       2019-10-03   2020-08-17   2019-11-07   2020-08-21   2020-05-05
pment of Seychelles seafood                     evelopment of the blue econ          cation Selection     l
brand                                           omy

 IBRD1-SWIOFISH3 / Capacity
                                                Component 3: Sustainable d
building in project planning a                                                       Consultant Qualifi
                               IBRD / 87790     evelopment of the blue econ Post                          Open - National       100,000.00   182,987.00   Signed            2019-03-29   2019-03-25    2019-04-19                2019-06-02   2019-05-10                                                       2019-07-02   2019-10-15   2019-08-06   2019-10-24   2020-02-02
nd business development for                                                          cation Selection
                                                omy
small-scale fishers


 IBRD23-SWIOFISH3 / Fisheri
                                                Component 3: Sustainable d
es sector employment surve                                                           Quality And Cost-    Open - Internationa                             Pending Impleme
                                 IBRD / 87790   evelopment of the blue econ Post                                                 75,000.00         0.00                     2019-08-22                 2019-08-22                2019-08-22                2019-09-13                2019-10-13                2019-11-17                2019-12-22                2020-12-21
y and identification of metho                                                        Based Selection      l                                               ntation
                                                omy
d for routine monitoring


 GEF26-SWIOFISH3A / Comm
unication strategy and plan f                   Component 2: Improved gov            Consultant Qualifi   Open - Internationa
                                 IBRD / 87790                                 Post                                               35,000.00    51,291.00   Signed            2019-09-25   2019-11-29    2019-10-16                2019-11-29   2020-10-12                                                       2019-12-29   2020-12-23   2020-02-02   2021-01-24   2020-07-31
or Mahe Plateau fisheries ma                    ernance of priority fisheries        cation Selection     l
nagement measures


 IBRD24-SWIOFISH3 / Develo
                                                Component 3: Sustainable d
pment of a communication st                                                          Consultant Qualifi
                              IBRD / 87790      evelopment of the blue econ Post                          Open - National        20,000.00    44,188.00   Completed         2019-10-11   2020-03-13    2019-11-01                2019-12-15   2020-06-09                                                       2020-01-14   2020-09-10   2020-02-18   2020-10-07   2020-08-16   2021-11-07
rategy and online platform fo                                                        cation Selection
                                                omy
r the Grievance Redress Mec
hanism

 IBRD26/CQS/2020-SWF3 / Co                      Component 3: Sustainable d           Consultant Qualifi
                            IBRD / 87790                                    Post                          Open - National       200,000.00   220,000.00   Signed            2020-01-15   2020-01-21    2020-02-05                2020-03-20   2020-05-18                                                       2020-04-19   2020-06-19   2020-05-24   2020-07-07   2020-11-20
mmunication support for Blu                     evelopment of the blue econ          cation Selection
e Finance                                       omy

 GEF21-SWIOFISH3 / Feasibili
                                                Component 2: Improved gov            Quality And Cost-    Open - Internationa
ty study on mechanisms for f IBRD / 87790                                     Post                                               80,000.00         0.00   Canceled          2019-07-15                 2019-08-05                2019-09-18                2019-10-16                2019-11-15                2019-12-20                2020-01-24                2021-01-23
                                                ernance of priority fisheries        Based Selection      l
leet capacity reduction


 GEF32/CQS/2020-SWF3 / Bio
logical, ecological and socioe                  Component 1: Expansion of
                                                                                     Consultant Qualifi   Open - Internationa                             Pending Impleme
conomic monitoring of sustai IBRD / 87790       sustainable-use marine prot   Post                                              150,000.00         0.00                     2020-10-15                 2020-11-05                2020-12-19                                                                    2021-01-18                2021-02-22                2021-08-21
                                                                                     cation Selection     l                                               ntation
nable-use areas: baseline sur                   ected areas
veys, indicators and protocol
s

 GEF36/CQS/2020-SWF3 / Re
                                                Component 1: Expansion of
search on ways to mitigate i                                                         Consultant Qualifi   Open - Internationa                             Pending Impleme
                                 IBRD / 87790   sustainable-use marine prot   Post                                               50,000.00         0.00                     2020-07-15                 2020-08-05                2020-09-18                                                                    2020-10-18                2020-11-22                2021-05-21
mpacts of industrial fisheries                                                       cation Selection     l                                               ntation
                                                ected areas
on coastal marine habitats a
nd fisheries

 GEF40/QCBS/2020-SWF3 / C
                                                Component 2: Improved gov            Quality And Cost-                                                    Pending Impleme
ommunication and education IBRD / 87790                                       Post                        Open - National       150,000.00         0.00                     2020-07-01                 2020-07-22                2020-09-04                2020-10-02                2020-11-01                2020-12-06                2021-01-10                2022-01-10
                                                ernance of priority fisheries        Based Selection                                                      ntation
/awareness activity support f
or SFA

 GEF45/QCBS/2020-SWF3 / Pr
                                                Component 2: Improved gov            Quality And Cost-    Open - Internationa
eparation of national tuna fis IBRD / 87790                                   Post                                              100,000.00   216,920.50   Signed            2020-05-01   2022-02-09    2020-05-22   2022-02-16   2020-07-05   2022-04-04   2020-08-02   2022-05-10   2020-09-01   2022-07-20   2020-10-06   2022-07-29   2020-11-10   2022-09-26   2021-11-10
                                                ernance of priority fisheries        Based Selection      l
heries development and man
agement plan

 GEF48/QCBS/2020-SWF3 / D
evelopment of a sport and re                    Component 2: Improved gov            Quality And Cost-    Open - Internationa                             Pending Impleme
                                 IBRD / 87790                                 Post                                              170,000.00         0.00                     2020-07-15                 2020-08-05                2020-09-18                2020-10-16                2020-11-15                2020-12-20                2021-01-24                2022-01-24
creational fishery data collec                  ernance of priority fisheries        Based Selection      l                                               ntation
tion and monitoring system


 IBRD29/QCBS/2020-SWF3 / F                      Component 3: Sustainable d
                                                                                     Quality And Cost-    Open - Internationa                             Pending Impleme
easibility study on invertebra IBRD / 87790     evelopment of the blue econ Post                                                 60,000.00         0.00                     2020-05-31                 2020-06-21                2020-08-04                2020-09-01                2020-10-01                2020-11-05                2020-12-10                2021-12-10
                                                                                     Based Selection      l                                               ntation
te hatcheries at Grand Anse                     omy
Aquaculture Hub

 GEF1-SWIOFISH3 / Blue carb                     Component 1: Expansion of
                                                                                     Consultant Qualifi   Open - Internationa
on assessment for Mahe Plat      IBRD / 87790   sustainable-use marine prot   Post                                              100,000.00   299,099.55   Signed            2020-04-15   2020-07-12    2020-05-06   2020-08-04   2020-06-19   2020-09-24                                                       2020-07-19   2021-01-20   2020-08-23   2021-08-16   2021-02-19
                                                                                     cation Selection     l
eau: Mangrove ecosystems                        ected areas


 GEF3-SWIOFISH3 / Develop
                                                Component 1: Expansion of
ment of a Harvest Strategy P                                                         Consultant Qualifi   Open - Internationa
                              IBRD / 87790      sustainable-use marine prot   Post                                               75,000.00   139,974.31   Completed         2019-04-15   2021-01-27    2019-05-06   2021-02-22   2019-06-19   2021-03-31                                                       2019-07-19   2021-06-17   2019-08-23   2021-07-18   2020-02-19   2022-07-13
olicy and Management Stand                                                           cation Selection     l
                                                ected areas
ards for Seychelles Fisheries


 GEF6-SWIOFISH3 / Studies o
                                                Component 1: Expansion of
n importance (social, econom                                                         Consultant Qualifi   Open - Internationa
                                IBRD / 87790    sustainable-use marine prot   Post                                               50,000.00   149,547.30   Signed            2020-06-30   2021-05-20    2020-07-21   2021-06-10   2020-09-03   2021-07-23                                                       2020-10-03   2021-11-11   2020-11-07   2021-12-13   2021-05-06
ic, value chains) of charter a                                                       cation Selection     l
                                                ected areas
nd sport fishing sector to defi
ne MSP impacts

 IBRD3-SWIOFISH3 / Educatio
                                                Component 3: Sustainable d
n & awareness to promote ta                                                          Consultant Qualifi                                                   Pending Impleme
                              IBRD / 87790      evelopment of the blue econ Post                          Open - National       105,000.00         0.00                     2020-07-15                 2020-08-05                2020-09-18                                                                    2020-10-18                2020-11-22                2021-05-21
g and release in sport and re                                                        cation Selection                                                     ntation
                                                omy
creational fisheries


 IBRD10/CQS/2020-SWF3 / H                       Component 3: Sustainable d
                                                                                     Consultant Qualifi   Open - Internationa
uman capacity development        IBRD / 87790   evelopment of the blue econ Post                                                 90,000.00   103,243.50   Completed         2020-04-15   2020-05-28    2020-05-06   2020-06-07   2020-06-19   2020-10-21                                                       2020-07-19   2020-12-15   2020-08-23   2021-02-11   2021-02-19   2022-08-30
                                                                                     cation Selection     l
plan in support of aquacultur                   omy
e sector

 IBRD22-SWIOFISH3 / Pre-ass                     Component 3: Sustainable d
                                                                                     Consultant Qualifi   Open - Internationa
essment of Seychelles longlin IBRD / 87790      evelopment of the blue econ Post                                                 35,000.00   105,745.00   Signed            2020-05-15   2021-05-18    2020-06-05   2021-06-10   2020-07-19   2021-08-10                                                       2020-08-18   2022-03-02   2020-09-22   2022-04-25   2021-03-21
                                                                                     cation Selection     l
e fishery against MSC standa                    omy
rd

 GEF22-SWIOFISH3 / Develop
                                                Component 2: Improved gov            Quality And Cost-    Open - Internationa
ment of the Fisheries Informa IBRD / 87790                                    Post                                              160,000.00   202,457.25   Signed            2020-06-15   2022-02-08    2020-07-06   2022-02-14   2020-08-19   2022-06-27   2020-09-16   2022-07-26   2020-10-16   2022-08-05   2020-11-20   2022-09-05   2020-12-25   2022-09-16   2021-12-25
                                                ernance of priority fisheries        Based Selection      l
tion Management System (in
cl. dashboards)

 IBRD16-SWIOFISH3 / Develo                      Component 3: Sustainable d
                                                                                     Quality And Cost-    Open - Internationa
pment and piloting of app to     IBRD / 87790   evelopment of the blue econ Post                                                 50,000.00   120,000.00   Signed            2020-04-15   2021-03-23    2020-05-06   2021-03-30   2020-06-19   2021-05-31   2020-07-17   2021-07-07   2020-08-16   2021-07-26   2020-09-20   2021-08-09   2020-10-25   2021-10-18   2022-10-25
                                                                                     Based Selection      l
promote post harvest inform                     omy
ation sharing

 GEF18/QCBS/2020-SWF3 / SI                      Component 2: Improved gov            Quality And Cost-    Open - Internationa
                            IBRD / 87790                                      Post                                               80,000.00         0.00   Canceled          2020-06-15   2020-06-10    2020-07-06   2020-06-22   2020-08-19                2020-09-16                2020-10-16                2020-11-20                2020-12-25                2021-12-25
H Data Processing and Repor                     ernance of priority fisheries        Based Selection      l
ting Tools




                                                                                                                                                                                              Page 2
GEF18/CQS/2020-SWF3 / SIH
                                                   Component 2: Improved gov                      Consultant Qualifi   Open - Internationa
DATA PROCESSING AND REP IBRD / 87790                                             Post                                                                             80,000.00     172,414.92   Signed            2020-09-25   2020-09-30    2020-10-16                2020-11-29   2020-10-01                                                   2020-12-29   2021-02-11   2021-02-02   2021-05-27   2021-08-01
                                                   ernance of priority fisheries                  cation Selection     l
ORTING TOOLS


 IBRD41/CQS/2021-SWF3 / G                          Component 3: Sustainable d
                                                                                                  Consultant Qualifi   Open - Internationa
ender Assessment in the Blu      IBRD / 87790      evelopment of the blue econ Post                                                                              100,000.00     123,078.90   Signed            2021-10-22   2021-11-30    2021-11-12   2022-01-13   2021-12-26   2022-03-03                                                   2022-01-25   2022-07-12   2022-03-01   2022-07-27   2022-08-28
                                                                                                  cation Selection     l
e Economy Sector                                   omy


 GEF4-SWIOFISH3 / Preparati                        Component 1: Expansion of
                                                                                                  Consultant Qualifi   Open - Internationa
on of management plans for IBRD / 87790            sustainable-use marine prot   Post                                                                            290,000.00     337,631.75   Signed            2021-12-16   2022-02-04    2021-12-28   2022-02-09   2022-02-10   2022-03-28                                                   2022-03-12   2022-08-08   2022-04-16   2022-08-15   2022-10-13
                                                                                                  cation Selection     l
sustainable use marine prote                       ected areas
cted areas

 IBRD40/CQS/2021-SWF3 / Pr
                                                   Component 3: Sustainable d
eparation of policies and stan                                                                    Consultant Qualifi   Open - Internationa
                               IBRD / 87790        evelopment of the blue econ Post                                                                               50,000.00           0.00   Signed            2022-07-07   2022-06-24    2022-07-28   2022-08-04   2022-09-10   2022-09-16                                                   2022-10-10   2022-11-15   2022-10-31   2022-12-17   2023-04-29
dards to improve recruitment                                                                      cation Selection     l
                                                   omy
and retention of local crew a
nd skippers

 IBRD27/CQS/2022-SWF3 / St                         Component 3: Sustainable d
                                                                                                  Consultant Qualifi   Open - Internationa
udy of post-harvest losses an IBRD / 87790         evelopment of the blue econ Post                                                                               80,000.00           0.00   Signed            2022-07-05   2022-06-24    2022-07-26   2022-08-24   2022-09-08   2022-10-31                                                   2022-10-08   2023-01-05   2022-11-12   2023-02-01   2023-05-11
                                                                                                  cation Selection     l
d introduction of routine surv                     omy
ey methodology

 IBRD39/NCS/2021-SWF3 / Int                        Component 4: Project mana                      Consultant Qualifi
                            IBRD / 87790                                         Post                                  Open - National                            10,000.00           0.00   Canceled          2022-07-31   2022-08-24    2022-08-21                2022-10-04                                                                2022-11-03                2022-12-08                2023-06-06
ernal audit of SeyCCAT                             gement and coordination                        cation Selection


 GEF58/CQS/2022-SWF3 / Ind
ependent assessment of EU                          Component 2: Improved gov                      Consultant Qualifi   Open - Internationa
                              IBRD / 87790                                       Post                                                                             60,000.00           0.00   Signed            2022-10-11   2022-10-19    2022-11-01   2022-10-27   2022-12-15   2022-12-22                                                   2023-01-14   2023-02-16   2023-02-18   2023-04-04   2023-08-17
and Mauritian Fisheries Partn                      ernance of priority fisheries                  cation Selection     l
ership Agreements


 GEF64/CQS/2022-SWF3 / Pre
paration of policy and legal fr                    Component 2: Improved gov                      Consultant Qualifi   Open - Internationa
                                IBRD / 87790                                     Prior                                                                            70,000.00           0.00   Under Review      2022-10-11   2022-10-28    2022-11-01   2022-11-23   2022-12-15   2023-01-23                                                   2023-01-14                2023-02-18                2023-08-17
amework for beneficial owne                        ernance of priority fisheries                  cation Selection     l
rship and joint ventures


 IBRD44/CQS/2023-SWF3 / D
                                                   Component 3: Sustainable d
evelopment of a new interact                                                                      Consultant Qualifi
                             IBRD / 87790          evelopment of the blue econ Post                                    Open - National                            30,000.00           0.00   Signed            2023-02-08   2023-02-03    2023-03-01                2023-04-14   2023-03-17                                                   2023-05-14   2023-04-26   2023-06-18   2023-05-18   2023-12-15
ive website for the Developm                                                                      cation Selection
                                                   omy
ent Bank of Seychelles


 GEF69/CQS/2023-SWF3 / Co
mmunication consultancy for                        Component 2: Improved gov                      Consultant Qualifi   Open - Internationa                                                   Under Implement
                              IBRD / 87790                                       Post                                                                            100,000.00           0.00                     2023-05-29   2023-07-14    2023-06-19   2023-07-21   2023-08-02                                                                2023-09-01                2023-10-06                2024-04-03
final SWIOFish3 project repor                      ernance of priority fisheries                  cation Selection     l                                                                     ation
ting and dissemination




INDIVIDUAL CONSULTANTS
Activity Reference No. /
                                 Loan / Credit N                                                                       Market Approac        Contract Type   Estimated Amo Actual Amount                                                  Invitation to Identifie Draft Negotiated Cont
       Description                                        Component                 Review Type        Method                                                                            Process Status        Terms of Reference                                                               Signed Contract         Contract Completion
                                        o.                                                                                    h                                 unt (US$)      (US$)                                                      d/Selected Consultant            ract
                                                                                                                                                                                                               Planned       Actual        Planned      Actual      Planned       Actual      Planned       Actual      Planned      Actual
 PA5-SWOIFISH3 / Data admi
                                                   Component 2: Improved gov                      Individual Consult                                                                         Under Implement
nistrator to assist with adopti IBRD / P4760                                     Post                                  Open                                       25,000.00           0.00                     2017-04-30                 2017-06-18                2017-07-09                2017-08-13                2018-02-09
                                                   ernance of priority fisheries                  ant Selection                                                                              ation
on of SIH including economic
data

 PA12-SWIOFISH3 / Technical
                                                   Component 3: Sustainable d
Assistance to Fishing Port De                                                                     Individual Consult                                                                         Under Implement
                                 IBRD / P4760      evelopment of the blue econ Post                                    Open                                       15,000.00           0.00                     2017-04-28                 2017-06-16                2017-07-07                2017-08-11                2018-02-07
velopment Committee: proje                                                                        ant Selection                                                                              ation
                                                   omy
ct management system


 PA18 SWIOFISH3 / Preparati                        Component 4: Project mana                      Individual Consult                                                                         Under Implement
                                 IBRD / P4760                                    Post                                  Open                                       30,000.00           0.00                     2017-04-18                 2017-06-06                2017-06-27                2017-08-01                2018-01-28
on of Project Implementation                       gement and coordination                        ant Selection                                                                              ation
Manual

 PA25-SWIOFISH3 / Elaborati
                                                   Component 3: Sustainable d
on of a standardized proposa                                                                      Individual Consult                                                                         Under Implement
                             IBRD / P4760          evelopment of the blue econ Post                                    Open                                       50,000.00           0.00                     2017-08-01                 2017-09-19                2017-10-10                2017-11-14                2018-05-13
l assessment methology (blu                                                                       ant Selection                                                                              ation
                                                   omy
e bonds onlending) & Trainin
g

 PA14-SWIOFISH3 / Value cha
in and feasibility study to gui                    Component 3: Sustainable d
                                                                                                  Individual Consult                                                                         Under Implement
de investment in fish process IBRD / P4760         evelopment of the blue econ Post                                    Open                                       50,000.00           0.00                     2017-08-07                 2017-09-25                2017-10-16                2017-11-20                2018-05-19
                                                                                                  ant Selection                                                                              ation
ing & services sector and ass                      omy
essment of maximum carryin
g capacity

 PA34-SWIOFISH3 / Preparato
ry activities for Seychelles to                    Component 2: Improved gov                      Individual Consult                                                                         Under Implement
                                IBRD / P4760                                     Post                                  Open                                       20,000.00           0.00                     2017-08-21                 2017-10-09                2017-10-30                2017-12-04                2018-06-02
conduct first report for the Fi                    ernance of priority fisheries                  ant Selection                                                                              ation
sheries Transparency Initiativ
e

 PA35-SWIOFISH3 / Develop
                                                   Component 2: Improved gov                      Individual Consult                                                                         Pending Impleme
ment of an Institutional Strat IBRD / P4760                                      Post                                  Open                                       25,000.00           0.00                     2017-09-25                 2017-11-13                2017-12-04                2018-01-08                2018-07-07
                                                   ernance of priority fisheries                  ant Selection                                                                              ntation
egic Plan for the Seychelles F
ishing Authority

 PA36-SWIOFISH3 / Draft poli
                                                   Component 3: Sustainable d
cy on the management of by                                                                        Individual Consult                                                                         Under Implement
                                IBRD / P4760       evelopment of the blue econ Post                                    Open                                       20,000.00           0.00                     2017-10-17                 2017-12-05   2017-11-30   2017-12-26                2018-01-30                2018-07-29
catch landings by industrial fi                                                                   ant Selection                                                                              ation
                                                   omy
shing vessels in Seychelles


 PA16-SWIOFISH3 / Extension
of Jan Robinson's contract (Pr
oject Manager) for coordinati
on and manage project prep                         Component 4: Project mana
                               IBRD / P4760                                      Prior            Direct Selection     Direct                                     65,820.00     166,320.00   Signed            2017-11-24   2017-11-28    2017-11-24   2017-10-20                             2017-11-24   2017-12-13   2018-12-31
aration and implementation                         gement and coordination
activities in accordance to th
e implementation arrangeme
nts set forth in the loan and
grant agreements .

 SWIOFISH3-PA32 / Environm
                                                   Component 4: Project mana                      Individual Consult
ent and Social Specialist to t   IBRD / 87790                                    Post                                  Open                                       90,000.00      90,000.00   Signed            2018-07-11   2018-04-05    2018-08-29                2018-09-19   2018-08-22   2018-10-24   2018-09-16   2019-04-22
                                                   gement and coordination                        ant Selection
he Project Implementation U
nit

 GEF14-SWIOFISH3 / Support
                                                   Component 2: Improved gov                      Individual Consult
to legal framework update (r     IBRD / 87790                                    Post                                  Limited                                    25,000.00      64,707.00   Signed            2019-04-17   2019-07-12    2019-04-22   2019-12-05   2019-05-13   2020-01-13   2019-06-17   2020-01-21   2019-12-14
                                                   ernance of priority fisheries                  ant Selection
evision of Fisheries Act and r
egulations)

 GEF15-SWIOFISH3 / Evaluati                        Component 1: Expansion of
                                                                                                                                                                                             Pending Impleme
on of the contribution of the IBRD / 87790         sustainable-use marine prot   Post             Direct Selection     Direct                                     75,000.00           0.00                     2019-05-15                 2019-05-25                                          2019-07-29                2020-01-25
                                                                                                                                                                                             ntation
extended MPA network to the                        ected areas
economy




                                                                                                                                                                                                                                 Page 3
 GEF17-SWIOFISH3 / Manage
ment strategy evaluation an                     Component 2: Improved gov                                                                    Pending Impleme
                                 IBRD / 87790                                 Post   Direct Selection     Direct     30,000.00        0.00                     2019-07-01                 2019-07-11                                          2019-09-14                2020-03-12
d capacity building (through                    ernance of priority fisheries                                                                ntation
CSIRO cooperation)


 GEF19-SWIOFISH3 / Data ca                      Component 2: Improved gov
                                 IBRD / 87790                                 Post   Direct Selection     Direct     96,000.00        0.00   Canceled          2019-05-08                 2019-05-08                                          2019-05-08                2021-06-15
pture software for SIH (EIS fe                  ernance of priority fisheries
es)

 GEF26-SWIOFISH3 / Commu
nication strategy and plan for                  Component 2: Improved gov            Individual Consult
                               IBRD / 87790                                   Post                        Open       35,000.00        0.00   Canceled          2019-06-15                 2019-08-03                2019-08-24                2019-09-28                2020-03-26
Mahe Plateau fisheries mana                     ernance of priority fisheries        ant Selection
gement measures


 GEF29-SWIOFISH3 / Stock di                     Component 1: Expansion of
                                                                                                                                             Under Implement
scrimination analysis to infor   IBRD / 87790   sustainable-use marine prot   Post   Direct Selection     Direct    135,000.00        0.00                     2019-05-30   2019-11-29    2019-06-09                                          2019-08-13                2020-08-12
                                                                                                                                             ation
m marine spatial planning                       ected areas


 IBRD19-SWIOFISH3 / Annual
                                                Component 4: Project mana                                                                    Pending Impleme
financial audits of the project IBRD / 87790                                  Post   Direct Selection     Direct     50,000.00        0.00                     2019-06-30                 2019-07-10                                          2019-09-13                2024-09-11
                                                gement and coordination                                                                      ntation
by the Office of the Auditor G
eneral

 IBRD13-SWIOFISH3 / Monitor
                                                Component 4: Project mana            Individual Consult
ing and evaluation and com     IBRD / 87790                                   Post                        Open       50,000.00   55,885.00   Completed         2019-04-15   2019-08-13    2019-06-03   2020-07-22   2019-06-24   2020-08-07   2019-07-29   2020-08-17   2020-01-25   2021-03-22
                                                gement and coordination              ant Selection
munication specialist - expert
support

 IBRD25-SWIOFISH3 / Procure
                                                Component 4: Project mana            Individual Consult
ment Assistant to the Project IBRD / 87790                                    Post                        Limited    85,000.00   79,200.00   Signed            2019-10-15   2019-10-24    2019-10-20   2019-12-20   2019-11-10   2020-01-08   2019-12-15   2020-02-26   2022-12-14
                                                gement and coordination              ant Selection
Implementation Unit


 GEF31/IC/2020-SWF3 / Devel
                                                Component 1: Expansion of
opment of Strategic Manage                                                           Individual Consult
                            IBRD / 87790        sustainable-use marine prot   Post                        Open       22,000.00   40,612.00   Completed         2020-02-23   2020-02-25    2020-04-12   2020-06-24   2020-05-03   2020-08-03   2020-06-07   2020-08-20   2020-12-04   2021-06-13
ment Framework for Seychell                                                          ant Selection
                                                ected areas
es Marine Spatial Plan


 GEF24-SWIOFISH3 / Technic                      Component 1: Expansion of            Individual Consult
                                 IBRD / 87790                                 Post                        Open        5,000.00        0.00   Canceled          2019-05-15                 2019-07-03                2019-07-24                2019-08-28                2020-02-24
al assistant to MEECC for pre                   sustainable-use marine prot          ant Selection
paring TORs                                     ected areas

 GEF11-SWIOFISH3 / Educatio
n on fisheries management:                      Component 2: Improved gov            Individual Consult
                            IBRD / 87790                                      Post                        Open       45,000.00        0.00   Canceled          2019-06-30                 2019-08-18                2019-09-08                2019-10-13                2020-04-10
course development, deliver                     ernance of priority fisheries        ant Selection
y, local trainer training


 GEF20-SWIOFISH3 / Data tra
                                                Component 2: Improved gov
nsfer and trouble shootimg f IBRD / 87790                                     Post   Direct Selection     Direct     30,000.00        0.00   Canceled          2019-04-15                 2019-04-25                                          2019-06-29                2019-12-26
                                                ernance of priority fisheries
or longline logbook module f
or Observe (IRD)

 GEF27-SWIOFISH3 / Develop
                                                Component 2: Improved gov
ment of centralised vessel re    IBRD / 87790                                 Post   Direct Selection     Direct     30,000.00        0.00   Canceled          2019-09-30                 2019-10-10                                          2019-12-14                2020-04-07
                                                ernance of priority fisheries
gistry for SFA and SMSA


 IBRD18-SWIOFISH3 / Mud cr                      Component 3: Sustainable d
                                 IBRD / 87790                               Post     Direct Selection     Direct     28,500.00        0.00   Canceled          2019-06-03                 2019-06-13                                          2019-08-17                2020-08-11
ab recuitment study                             evelopment of the blue econ
                                                omy

 GEF39/IC/2020-SWF3 / Seyc
                                                Component 2: Improved gov            Individual Consult
helles' report to the Fisheries IBRD / 87790                                  Post                        Open       35,000.00   23,170.00   Completed         2020-04-30   2020-05-15    2020-06-18   2020-09-02   2020-07-09   2020-09-11   2020-08-13   2020-10-06   2021-02-09   2021-04-12
                                                ernance of priority fisheries        ant Selection
Transparency Initiative


 GEF41/IC/2020-SWF3 / Traini
ng on data analysis, risk asse                  Component 2: Improved gov            Individual Consult                                      Pending Impleme
                               IBRD / 87790                                   Post                        Open       30,000.00        0.00                     2020-07-15                 2020-09-02                2020-09-23                2020-10-28                2021-04-26
ssment and asset deploymen                      ernance of priority fisheries        ant Selection                                           ntation
t planning for MCS


 GEF44/IC/2020-SWF3 / Scien
tific design and analytical su                  Component 2: Improved gov            Individual Consult
                               IBRD / 87790                                   Post                        Open       45,000.00   77,233.00   Signed            2020-06-30   2021-03-17    2020-08-18   2021-06-11   2020-09-08   2021-08-03   2020-10-13   2021-08-09   2021-04-11
pport for a fisheries-indepen                   ernance of priority fisheries        ant Selection
dent assessment of sea cucu
mber status

 GEF47/IC/2020-SWF3 / Study
                                                Component 2: Improved gov            Individual Consult                                      Pending Impleme
on the implications of local b IBRD / 87790                                   Post                        Limited    25,000.00        0.00                     2020-10-01                 2020-10-06                2020-10-27                2020-12-01                2021-05-30
                                                ernance of priority fisheries        ant Selection                                           ntation
amboo utilisation for FADs


 GEF42/SSS/2020-SWF3 / Sec
retary to Implementation Co-
                                                Component 2: Improved gov            Individual Consult
management Committee for IBRD / 87790                                         Post                        Direct     48,000.00   53,200.00   Signed            2020-04-15   2020-10-29    2020-04-25   2020-10-30   2020-05-16   2020-11-04   2020-06-20   2020-11-27   2020-12-17
                                                ernance of priority fisheries        ant Selection
Mahe Plateau Demersal Fishe
ries Management Plan


 IBRD31/SSS/2020-SWF3 / Fis                     Component 3: Sustainable d
                                                                                                                                             Pending Impleme
h quality assessment training IBRD / 87790      evelopment of the blue econ Post     Direct Selection     Direct     48,000.00        0.00                     2020-03-31                 2020-04-10                                          2020-06-14                2020-12-11
                                                                                                                                             ntation
- Phase 2 (contract with firm                   omy
SeaFish UK)

 IBRD10-SWIOFISH3 / Human                       Component 3: Sustainable d
                                                                                     Individual Consult
capacity development plan in IBRD / 87790       evelopment of the blue econ Post                          Open       28,500.00        0.00   Canceled          2019-04-30                 2019-06-18                2019-07-09                2019-08-13                2020-02-09
                                                                                     ant Selection
support of aquaculture sector                   omy


 GEF9-SWIOFISH3 / Implicatio
                                                Component 1: Expansion of
ns of sustainable-use zone all                                                       Individual Consult                                      Pending Impleme
                               IBRD / 87790     sustainable-use marine prot   Post                        Open       60,000.00        0.00                     2020-05-15                 2020-07-03                2020-07-24                2020-08-28                2021-02-24
owable activities on purse sei                                                       ant Selection                                           ntation
                                                ected areas
ne and long-line fisheries


 GEF10-SWIOFISH3 / Stock as
sessment update: CPUE stan                      Component 2: Improved gov            Individual Consult
                             IBRD / 87790                                     Post                        Limited    40,000.00        0.00   Canceled          2020-04-15   2020-06-24    2020-04-20                2020-05-11                2020-06-15                2020-12-12
dardisation and production m                    ernance of priority fisheries        ant Selection
odels for indicator species


 GEF25-SWIOFISH3 / Capacity
                                                Component 2: Improved gov            Individual Consult                                      Pending Impleme
building for Seychelles' Feder IBRD / 87790                                   Post                        Limited    50,000.00        0.00                     2020-07-01                 2020-07-06                2020-07-27                2020-08-31                2023-08-31
                                                ernance of priority fisheries        ant Selection                                           ntation
ation of Fisher Associations


 GEF28-SWIOFISH3 / Develop
ment of a social accounting                     Component 2: Improved gov            Individual Consult
                               IBRD / 87790                                   Post                        Open       40,000.00   67,280.00   Signed            2020-05-15   2020-09-10    2020-07-03   2020-11-09   2020-07-24   2020-12-10   2020-08-28   2021-02-07   2021-01-25
matrix and artisanal fisheries                  ernance of priority fisheries        ant Selection
component for the fisheries s
atellite account

 GEF13-SWIOFISH3 / Study to
                                                Component 2: Improved gov            Individual Consult
quantify public sector suppor IBRD / 87790                                    Post                        Open       35,000.00   41,202.70   Terminated        2020-09-15   2021-05-11    2020-11-03   2021-07-16   2020-11-24   2021-08-19   2020-12-29   2021-09-02   2021-06-27
                                                ernance of priority fisheries        ant Selection
t to the fisheries sector




                                                                                                                                                                                 Page 4
 IBRD11-SWIOFISH3 / FBOA l                     Component 3: Sustainable d
                                                                                    Individual Consult                                      Pending Impleme
abel program coordination a     IBRD / 87790   evelopment of the blue econ Post                          Open      100,000.00        0.00                     2020-04-30                 2020-06-18                2020-07-09                2020-08-13                2022-08-13
                                                                                    ant Selection                                           ntation
nd management                                  omy


 IBRD12-SWIOFISH3 / Needs                      Component 3: Sustainable d
                                                                                    Individual Consult                                      Pending Impleme
assessment study for sanitar    IBRD / 87790   evelopment of the blue econ Post                          Open       25,000.00        0.00                     2020-09-30                 2020-11-18                2020-12-09                2021-01-13                2021-07-12
                                                                                    ant Selection                                           ntation
y and phytosanitary monitori                   omy
ng

 IBRD21-SWIOFISH3 / Nationa
                                               Component 3: Sustainable d
l standard for sanitary and p                                                       Individual Consult
                              IBRD / 87790     evelopment of the blue econ Post                          Open       40,000.00        0.00   Canceled          2019-10-01                 2019-11-19                2019-12-10                2020-01-14                2020-07-12
htyosanitary including imple                                                        ant Selection
                                               omy
mentation plan and roadmap


 GEF18-SWIOFISH3 / SFA co-fi
                                               Component 2: Improved gov
nancing of SIH (fees and cost IBRD / 87790                                   Post   Direct Selection     Direct     60,000.00        0.00   Canceled          2019-04-15                 2019-04-25                                          2019-06-29                2019-12-26
                                               ernance of priority fisheries
s for IFREMER)


 GEF16-SWIOFISH3 / THEMIS                      Component 1: Expansion of
AIS, Radar installation maint IBRD / 87790     sustainable-use marine prot   Post   Direct Selection     Direct    441,500.00        0.00   Canceled          2019-04-15   2019-08-29    2019-04-25                                          2019-06-29                2019-12-26
enance and subscription cost                   ected areas
s

 GEF8-SWIOFISH3 / Drafting
                                               Component 1: Expansion of
of governance authority esta                                                        Individual Consult
                                IBRD / 87790   sustainable-use marine prot   Post                        Limited    30,000.00        0.00   Canceled          2019-04-30   2020-02-23    2019-05-05                2019-05-26                2019-06-30                2019-12-27
blishment act and other MSP                                                         ant Selection
                                               ected areas
regulatory frameworks


 GEF30/IC/2020-SWF3 / Study                    Component 1: Expansion of
                                                                                    Individual Consult
on the status of ETP sharks a IBRD / 87790     sustainable-use marine prot   Post                        Open       60,000.00   74,570.00   Signed            2020-05-29   2021-02-09    2020-07-17   2021-05-10   2020-08-07   2021-05-27   2020-09-11   2021-06-16   2021-03-10
                                                                                    ant Selection
nd rays in MSP zones                           ected areas


 GEF38/IC/2020-SWF3 / Socio
                                               Component 2: Improved gov            Individual Consult                                      Under Implement
-economic impact assessmen IBRD / 87790                                      Post                        Open       40,000.00        0.00                     2020-06-01   2021-10-07    2020-07-20                2020-08-10                2020-09-14                2021-03-13
                                               ernance of priority fisheries        ant Selection                                           ation
ts for fisheries management
measures

 IBRD14-SWIOFISH3 / Environ
                                               Component 4: Project mana            Individual Consult
mental and social specialist - IBRD / 87790                                  Post                        Limited    40,000.00        0.00   Canceled          2019-04-15   2020-05-05    2019-04-20                2019-05-11                2019-06-15                2020-06-14
                                               gement and coordination              ant Selection
local expert on retainer


IBRD14-SWIOFISHA / ENVIRO                      Component 4: Project mana            Individual Consult
                          IBRD / 87790                                       Post                        Open       40,000.00   55,878.00   Completed         2020-05-06   2020-05-05    2020-06-24   2020-06-25   2020-07-15   2020-08-05   2020-08-19   2020-08-19   2021-02-15   2021-09-13
NMENTAL AND SOCIAL SPECI                       gement and coordination              ant Selection
ALIST

 IBRD33/SSS/2020-SWF3 / Mo
                                               Component 4: Project mana
nitoring and Evaluation Speci IBRD / 87790                                   Post   Direct Selection     Direct     90,000.00   90,000.00   Signed            2020-05-06   2020-05-05    2020-05-16   2020-05-22                             2020-07-20   2020-06-13   2023-07-20
                                               gement and coordination
alist for the PIU


 IBRD5-SWIOFISH3 / Support
to the Development Bank of
                                               Component 3: Sustainable d
Seychelles for Implementatio                                                        Individual Consult                                      Pending Impleme
                               IBRD / 87790    evelopment of the blue econ Post                          Open       25,000.00        0.00                     2020-09-14                 2020-11-02                2020-11-23                2020-12-28                2021-12-23
n of the Blue Investment Fun                                                        ant Selection                                           ntation
                                               omy
d: Financial analyst on retain
er for DBS capacity building
and technical backstopping

 IBRD34/SSS/2020-SWF3 / Up
dating the manuals for the Bl                  Component 3: Sustainable d
ue Investment Fund of the D IBRD / 87790       evelopment of the blue econ Post     Direct Selection     Direct     15,000.00   12,000.00   Completed         2020-09-03   2020-09-03    2020-09-13   2020-09-04                             2020-11-17   2020-09-14   2021-01-16   2021-06-15
evelopment Bank of Seychell                    omy
es to incorporate proposed c
hanges to the fund

 GEF10-SWIOFISH3A / Stock
assessment update; CPUE st                     Component 2: Improved gov            Individual Consult
                              IBRD / 87790                                   Post                        Open       40,000.00   23,267.00   Completed         2020-12-09   2020-12-11    2021-01-27   2021-02-12   2021-02-17   2021-02-17   2021-03-24   2021-03-06   2021-09-20   2021-12-15
andardization and production                   ernance of priority fisheries        ant Selection
models for indicator species.


 IBRD37/IC/2021-SWF3 / Mid                     Component 4: Project mana            Individual Consult
                             IBRD / 87790                                    Post                        Open       40,000.00   36,270.00   Terminated        2021-02-02   2021-02-24    2021-03-23   2021-04-19   2021-04-13   2021-05-12   2021-05-18   2021-05-31   2021-11-14
term Evaluation for SWIOFish                   gement and coordination              ant Selection
3 Project

 GEF55/IC/2021-SWF3 / Tech
nical Assistant to Seychelles                  Component 3: Sustainable d
                                                                                    Individual Consult
Conservation and Climate Ad     IBRD / 87790   evelopment of the blue econ Post                          Limited    90,000.00   60,000.00   Signed            2021-02-10   2021-02-23    2021-02-15   2021-03-01   2021-03-08   2021-03-03   2021-04-12   2021-03-22   2021-10-09
                                                                                    ant Selection
aptation Trust (SeyCCAT) for                   omy
the Blue Grants Fund (Blue B
ond proceeds)

 GEF53/CQS/2021-SWF3 / Tec
hnical assistant to the Ministr                Component 2: Improved gov
                                IBRD / P4760                                 Post   Direct Selection     Direct     72,000.00        0.00   Canceled          2021-03-22                 2021-04-01                                          2021-06-05                2021-12-02
y of Fisheries and the Blue Ec                 ernance of priority fisheries
onomy: marketing specialist


 GEF57/SSS/2021-SWF3 / Pro
                                               Component 2: Improved gov
duction of Seychelles 2nd an    IBRD / 87790                                 Post   Direct Selection     Direct     35,000.00   15,720.00   Completed         2021-07-13   2021-07-07    2021-07-23   2021-07-13                             2021-09-26   2021-08-07   2022-03-25   2021-12-21
                                               ernance of priority fisheries
nual report to FiTI


 IBRD8-SWIOFISH3 / Environ
mental and Social Impact Ass
                                               Component 3: Sustainable d
essments for Blue Investmen                                                         Individual Consult
                              IBRD / 87790     evelopment of the blue econ Post                          Limited    15,000.00   26,660.00   Signed            2021-08-19   2021-08-23    2021-08-24   2021-08-09   2021-09-14   2021-10-06   2021-10-19   2021-10-25   2022-04-17
t Fund Application, Providenc                                                       ant Selection
                                               omy
e Industrial Zone & Fish Proc
essing Land, Zone 14, Ile Du
Port

 GEF12-SWIOFISH3 DS / Liais
                                               Component 2: Improved gov
on Officer for the Mahe Plate   IBRD / 87790                                 Post   Direct Selection     Direct     24,000.00   26,353.59   Signed            2021-09-24   2021-10-09    2021-10-04   2021-10-11                             2021-12-08   2021-11-14   2022-06-06
                                               ernance of priority fisheries
au Trap and Line Fishery Co-
management Plan

 GEF53/IC/2021-SWF3 / Devel                    Component 2: Improved gov            Individual Consult
                              IBRD / 87790                                   Post                        Open       72,000.00   43,834.85   Signed            2021-10-29   2021-10-15    2021-12-17   2022-07-26   2022-01-07   2022-08-09   2022-02-11   2022-08-25   2022-08-10
opment of a Market Intelligen                  ernance of priority fisheries        ant Selection
ce Plan

 GEF7/DS/2021-SWF3 / Surve
                                               Component 1: Expansion of
y of Perceptions on Ocean Go
                             IBRD / 87790      sustainable-use marine prot   Post   Direct Selection     Direct     25,000.00   71,041.54   Signed            2021-11-23   2022-02-04    2021-12-03   2021-11-08                             2022-02-06   2022-03-26   2022-08-05
vernance, Fisheries Manage
                                               ected areas
ment and the Blue Economy


 GEF12-SWIOFISH3 / Liaison
                                               Component 2: Improved gov            Individual Consult
officer for Mahe Plateau Dem IBRD / 87790                                    Post                        Open       24,000.00        0.00   Canceled          2019-04-30   2019-09-13    2019-06-18                2019-07-09                2019-08-13                2020-02-09
                                               ernance of priority fisheries        ant Selection
ersal Fisheries Management
Plan

 GEF60/IC/2022-SWF3-C2 / P
REPARATION OF SEYCHELLES                       Component 2: Improved gov            Individual Consult
                           IBRD / 87790                                      Post                        Open       25,000.00   10,585.00   Signed            2022-04-29   2022-04-21    2022-06-17   2022-08-01   2022-07-08   2022-08-17   2022-08-12   2022-09-03   2023-02-08
’ 3rd NATIONAL REPORT TO T                     ernance of priority fisheries        ant Selection
HE FISHERIES TRANSPARENC
Y INITIATIVE




                                                                                                                                                                                Page 5
 IBRD27/IC/2020-SWF3 / Stud                    Component 3: Sustainable d
                                                                                    Individual Consult
y of post-harvest losses and i IBRD / 87790    evelopment of the blue econ Post                          Open                    30,000.00   0.00   Canceled          2020-09-01                 2020-10-20                2020-11-10                2020-12-15                2021-06-13
                                                                                    ant Selection
ntroduction of routine survey                  omy
methodology

 GEF66/SSS/2022-SWF3 / Log
                                               Component 2: Improved gov            Individual Consult   Direct - Internation
istical and technical backstop IBRD / 87790                                  Post                                                 5,000.00   0.00   Signed            2022-09-25   2022-09-27    2022-10-05   2022-09-14   2022-10-26   2022-09-27   2022-11-30   2022-10-06   2023-05-29
                                               ernance of priority fisheries        ant Selection        al
ping for P2P: Shetland, UK


 GEF67/SSS/2022-SWF3 / Log
                                               Component 2: Improved gov            Individual Consult   Direct - Internation
istical and technical backstop IBRD / 87790                                  Post                                                 5,000.00   0.00   Signed            2022-09-26   2022-09-27    2022-10-06   2022-09-13   2022-10-27   2022-09-28   2022-12-01   2022-10-06   2023-05-30
                                               ernance of priority fisheries        ant Selection        al
ping for P2P: Sete, France


 GEF59/IC/2022-SWF3 / Tech
nical Assistant to MACCE on                    Component 1: Expansion of
                                                                                    Individual Consult
MSP surveillance options, pil IBRD / 87790     sustainable-use marine prot   Post                        Limited                 70,000.00   0.00   Signed            2022-10-10   2022-10-12    2022-10-15   2022-10-31   2022-11-05   2022-12-20   2022-12-10   2023-01-01   2023-06-08
                                                                                    ant Selection
oting, tender preparation and                  ected areas
asset purchasing oversight


 GEF63/IC/2022-SWF3 / Revie
                                               Component 2: Improved gov            Individual Consult   Open - Internationa
w fisheries sector strategy an IBRD / 87790                                  Post                                                30,000.00   0.00   Signed            2022-10-10   2022-10-19    2022-11-28   2022-12-12   2022-12-19   2022-12-16   2023-01-23   2023-01-01   2023-07-22
                                               ernance of priority fisheries        ant Selection        l
d comprehensive plan imple
mentation

 IBRD8/IC/2022-SWF3 / Envir
                                               Component 3: Sustainable d
onmental and Social Impact                                                          Individual Consult
                             IBRD / 87790      evelopment of the blue econ Post                          Limited                 30,000.00   0.00   Signed            2022-11-20   2023-02-14    2022-11-25   2023-01-05   2022-12-16   2023-02-22   2023-01-20   2023-03-10   2023-07-19
Assessments for Island Devel                                                        ant Selection
                                               omy
opment Company Prawn Proj
ect, Coetivy Island

 GEF13-SWIOFISH3-2 / Public
                                               Component 2: Improved gov            Individual Consult
Sector Support to the Seyche IBRD / 87790                                    Post                        Limited                 17,000.00   0.00   Signed            2023-01-11   2023-01-25    2023-01-16   2023-02-07   2023-02-06   2023-02-21   2023-03-13   2023-03-23   2023-09-09
                                               ernance of priority fisheries        ant Selection
lles Fisheries Sector


 IBRD39/IC/2023-SWF3 / Inter                   Component 4: Project mana            Individual Consult
                             IBRD / 87790                                    Post                        Limited                 10,000.00   0.00   Signed            2023-02-21   2023-02-22    2023-02-26   2023-02-15   2023-03-19   2023-04-06   2023-04-23   2023-05-17   2023-10-20
nal Audit of SeyCCAT                           gement and coordination              ant Selection


 IBRD45/SSS/2023-SWF3 / As                     Component 3: Sustainable d
                                                                                    Individual Consult
sessing the Potential of the Li IBRD / 87790   evelopment of the blue econ Post                          Direct - National       30,000.00   0.00   Signed            2023-03-14   2023-03-13    2023-03-24   2023-03-15   2023-04-14   2023-03-24   2023-05-19   2023-04-05   2023-11-15
                                                                                    ant Selection
ve Aboard and Yachting Indu                    omy
stry

 IBRD46/IC/2023-SWF3 / Crea                    Component 3: Sustainable d
                                                                                    Individual Consult
ting awareness on the econo IBRD / 87790       evelopment of the blue econ Post                          Limited                 60,000.00   0.00   Canceled          2023-03-14   2023-03-13    2023-03-19                2023-04-09                2023-05-14                2023-11-10
                                                                                    ant Selection
mic potential of Seychelles’ B                 omy
lue Economy

 IBRD46/IC/2023/SWF3 / Crea                    Component 3: Sustainable d
                                                                                    Individual Consult
ting awareness on the econo IBRD / 87790       evelopment of the blue econ Post                          Limited                 30,000.00   0.00   Signed            2023-03-26   2023-04-04    2023-03-31   2023-03-21   2023-04-21   2023-04-21   2023-05-26   2023-05-02   2023-11-22
                                                                                    ant Selection
mic potential of Seychelles' B                 omy
lue Economy

 IBRD47/SSS/2023-SWF3 / Fu                     Component 3: Sustainable d
                                                                                    Individual Consult   Direct - Internation
nctional Review of the Fish In IBRD / 87790    evelopment of the blue econ Post                                                  30,000.00   0.00   Signed            2023-03-26   2023-04-04    2023-04-05   2023-04-14   2023-04-26   2023-04-27   2023-05-31   2023-05-18   2023-11-27
                                                                                    ant Selection        al
spection and Quality Control                   omy
Unit (FIQCU)

 IBRD48/IC/2023-SWF3 / Asse
                                               Component 3: Sustainable d
ssing the economic potential                                                        Individual Consult                                              Under Implement
                              IBRD / 87790     evelopment of the blue econ Post                          Limited                 40,000.00   0.00                     2023-03-26   2023-04-12    2023-03-31   2023-04-12   2023-04-21                2023-05-26                2023-11-22
of the Seychelles’ Blue Econo                                                       ant Selection                                                   ation
                                               omy
my and business case planni
ng for key sectors.

 GEF67/SSS/2023-SWF3 / Dev                     Component 1: Expansion of
elopment of boiler plate texts IBRD / P4760    sustainable-use marine prot   Post   Direct Selection     Direct - National        3,000.00   0.00   Signed            2023-04-16   2023-05-02    2023-04-26   2023-05-03                             2023-06-30   2023-05-17   2023-12-27
for MPA Management Plans                       ected areas


IBRD49/IC/2023-SWF3 / Com                      Component 3: Sustainable d
                                                                                    Individual Consult                                              Under Implement
munication specialist for the IBRD / 87790     evelopment of the blue econ Post                          Limited                 20,000.00   0.00                     2023-05-29   2023-07-14    2023-06-03   2023-07-18   2023-06-24                2023-07-29                2024-01-25
                                                                                    ant Selection                                                   ation
Department of Blue Economy                     omy


 GEF70/SSS/2023-SWF3 / Str
                                               Component 1: Expansion of
ategic Threat and Risk Asses                                                                             Direct - Internation
                             IBRD / P4760      sustainable-use marine prot   Post   Direct Selection                             30,000.00   0.00   Signed            2023-08-15   2023-08-12    2023-08-25   2023-08-16                             2023-10-29   2023-09-29   2024-04-26
sment for MPAs Designated u                                                                              al
                                               ected areas
nder the Seychelles Marine S
patial Plan

 IBRD50/IC/2023-SWF3 / Prep
aration of Options Paper on                    Component 3: Sustainable d
                                                                                    Individual Consult   Open - Internationa                        Under Implement
Marketing Opportunities for F IBRD / 87790     evelopment of the blue econ Post                                                  20,000.00   0.00                     2023-08-31   2023-08-29    2023-10-19                2023-11-09                2023-12-14                2024-06-11
                                                                                    ant Selection        l                                          ation
infish Products of the Mahé Pl                 omy
ateau Trap and Line Fishery
of Seychelles

 IBRD51/IC/203-SWF3 / Monit
oring and evaluation support                   Component 4: Project mana            Individual Consult   Open - Internationa                        Under Implement
                                IBRD / 87790                                 Post                                                30,000.00   0.00                     2023-10-15   2023-10-10    2023-12-03                2023-12-24                2024-01-28                2024-07-26
for data quality review, result                gement and coordination              ant Selection        l                                          ation
s framework, final evaluation
preparation

 IBRD52/SSS/2023-SWF3 / Un                     Component 3: Sustainable d
                                                                                                         Direct - Internation                       Under Implement
derstanding the Risks of Clim IBRD / 87790     evelopment of the blue econ Post     Direct Selection                            100,000.00   0.00                     2023-10-13   2023-10-10    2023-10-23                                          2023-12-27                2024-06-24
                                                                                                         al                                         ation
ate Change to Seychelles’ Fis                  omy
heries Sector

 GEF71/SSS/2023-SWF3 / Tec
hnical support for developing                  Component 2: Improved gov            Individual Consult   Direct - Internation
                              IBRD / 87790                                   Post                                                30,000.00   0.00   Canceled          2023-09-05   2023-10-04    2023-09-15                2023-10-06                2023-11-10                2024-05-08
a Harvest Strategy for Seych                   ernance of priority fisheries        ant Selection        al
elles’ sea cucumber fishery


 GEF72/IC/2023-SWF3 / Devel
                                               Component 2: Improved gov            Individual Consult   Open - Internationa                        Under Implement
opment of Legal Framework f IBRD / P4760                                     Post                                                20,000.00   0.00                     2023-11-06   2023-11-06    2023-12-25                2024-01-15                2024-02-19                2024-08-17
                                               ernance of priority fisheries        ant Selection        l                                          ation
or the regulations of FADS


 IBRD53/IC/2023-SWF3 / Soci
                                               Component 3: Sustainable d
al Impact Assessment of the                                                         Individual Consult                                              Under Implement
                             IBRD / P4760      evelopment of the blue econ Post                          Limited                 30,000.00   0.00                     2023-11-06   2023-11-29    2023-11-11                2023-12-02                2024-01-06                2024-07-04
Sustainable Use Seychelles M                                                        ant Selection                                                   ation
                                               omy
arine Spatial Plan (MPAs


 GEF38/IC/2023-SWF3-2 / Soc
io-economic impact assessm                     Component 2: Improved gov            Individual Consult
                             IBRD / 87790                                    Post                        Limited                 30,000.00   0.00   Under Review      2023-12-10   2023-12-06    2023-12-15                2024-01-05                2024-02-09                2024-08-07
ent of the Mahé Plateau trap                   ernance of priority fisheries        ant Selection
and line fishery co-managem
ent plan

 IBRD54/IC/2023-SWF3 / Envi
                                               Component 3: Sustainable d
ronment and Social Manage                                                           Individual Consult   Open - Internationa
                              IBRD / 87790     evelopment of the blue econ Post                                                  30,000.00   0.00   Under Review      2023-12-21   2023-12-06    2024-02-08                2024-02-29                2024-04-04                2024-10-01
ment System (ESMS) for Dev                                                          ant Selection        l
                                               omy
elopment Bank of Seychelles
(DBS)

IBRD55/IC/2023-SWF3 / SWI                      Component 4: Project mana            Individual Consult   Open - Internationa                        Pending Impleme
                              IBRD / 87790                                   Post                                                30,000.00   0.00                     2024-02-04                 2024-03-24                2024-04-14                2024-05-19                2024-11-15
OFish3 Final project report                    gement and coordination              ant Selection        l                                          ntation




                                                                                                                                                                                        Page 6
 IBRD56/IC/2023-SWF3 / Envi               Component 3: Sustainable d
                                                                             Individual Consult                               Pending Impleme
ronmental and Social Manag IBRD / 87790   evelopment of the blue econ Post                        Limited   5,000.00   0.00                     2024-01-18            2024-01-23   2024-02-13   2024-03-19   2024-09-15
                                                                             ant Selection                                    ntation
ement for Blue Investments F              omy
und Applicant




                                                                                                                                                             Page 7