PROCUREMENT PLAN PERU INTEGRATED WATER RESOURCES MANAGEMENT IN TEN BASINS PROJECT P151851 I. General 1. Bank’s approval Date of the procurement Plan: Original, February 23, 2017 2. Date of General Procurement Notice: February 23, 2017 3. Period covered by this procurement plan: all the procurement process planned II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Below US$ 2 million None 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Below US$ 10 million None 2. Project Operational/Procurement Manual: Procurement implementation details activities will be outlined in the Project Operational Manual (POM) 3. Any Other Special Procurement Arrangements: None 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 Description Estimat Packa Domest Review Commen ed ges ic by Bank ts Cost Prefere (Prior / US$ nce Post) million (yes/no ) Summary of the ICB 25.2 5 No Prior (Goods) Summary of the NCB 9.28 5 No Post (Works) Summary of the NCB 3.16 4 No Post (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 350,000 All 2. Single Source (Firms) All 3. Individual Key personnel All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 350,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Description of Estimated Package Review Comments Assignment Cost s by Bank US$ million (Prior / Post) Summary of number of 15.95 10 Prior contracts that will be let under QCBS > US$ 350 mil Summary of number of 1.20 5 Post contracts that will be let under QCBS < US$ 350 mil PROCUREMENT Peru : Integrated Water Resources Management in Ten Basins PLAN General Information Country: Peru Bank’s Approval Date of the Original Procurement Plan: 2018-03-16 Revised Plan Date(s): (comma delineated, leave blank if none)2022-02-22 Project ID: P151851 GPN Date: Project Name: Integrated Water Resources Management in Ten Basins Loan / Credit No: IBRD / 87400 Executing Agency(ies):National Water Authority of the Ministry of Agriculture - Autoridad Nacional del Agua (ANA) WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Signed Contract No. Approach Process n (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned LPN 003 2018 ANA PGIRH BM / PERFORACIÓN E INSTALACIÓN DE 58 Component 1: Solicitud de Single Stage - One 2,205,593. En 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2019-01- PIEZÓMETROS EN LOS IBRD / 87400 Consolidating IWRM at the Posterior Open - National 0.00 ofertas Envelope 00 ejecución 26 08 29 28 25 07 27 26 23 ACUÍFEROS DE ICA Y National Level TACNA: LOTE 01 ICA Y LOTE 02 TACNA LPN 007-2018-ANA- PGIRH-BM / PERFORACION E INSTALACION DE 58 PIEZOMETROS EN LOS ACUIFEROS DE ICA Y Component 1: Solicitud de Single Stage - One 1,664,437. 2,141,562 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-11- 2018-11- 2018-11- 2018-12- 2018-12- 2019-04- TACNA lote 1 ICA 28 IBRD / 87400 Consolidating IWRM at the Posterior Open - National Firmado ofertas Envelope 00 .01 04 12 07 12 06 21 16 28 05 05 03 perfotaciones metodo National Level diamantina, lote 2 TACNA 8 perforaciones metodo diamantina, lote 3 TACNA 22 perforaciones metodo RC CP 001 2018 ANA PGIRH BM / OBRAS PRELIMINARES Y DE CIERRE PARA LA Component 1: Solicitud de Single Stage - One 2018-10- 2018-11- 2018-12- EJECUCIÒN DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 21,870.00 0.00 Cancelado cotizaciones Envelope 21 15 30 PERFORACIÒN E National Level INSTALACION DE 28 PIEZOMETROS EN LOS ACUIFEROS DE ICA CP 002 2018 ANA PGIRH BM / OBRAS PRELIMINARES Y DE CIERRE PARA LA Component 1: Solicitud de Single Stage - One Ejecución 2018-10- 2018-11- 2018-12- EJECUCION DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 13,587.00 0.00 cotizaciones Envelope pendiente 21 15 30 PERFORACION E National Level INSTALACION DE 30 PIEZOMETROS EN LOS ACUIFEROS DE TACNA CP 003 2018 ANA PGIRH BM / CONSTRUCCION DE Component 1: Solicitud de Single Stage - One 2019-04- 2019-05- 2019-06- CASETAS DE PROTECCION IBRD / 87400 Consolidating IWRM at the Posterior Limited 55,239.00 0.00 Cancelado cotizaciones Envelope 07 02 16 DE 30 PIEZOMETROS EN National Level LOS ACUIFEROS DE TACNA LPN 008 2018 ANA PGIRH / Contratación para la Construcción - Obras Civiles para la Component 1: Implementación de la Solicitud de Single Stage - One 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2020-02- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 238,806.00 0.00 Cancelado Infraestructura del Centro ofertas Envelope 24 26 26 31 17 13 National Level de Datos, Laboratorio de Instrumentación, Centro de Monitoreo Y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-126672-CW-RFQ / Perforación y habilitación Component 1: Solicitud de Single Stage - One 225,104.3 2019-09- 2019-10- 2019-09- 2019-12- de 18 piezómetros en los IBRD / 87400 Consolidating IWRM at the Posterior Open - National 180,000.00 Firmado cotizaciones Envelope 8 21 31 27 15 acuiferos de Ica, Villacurí y National Level Lanchas PE-ANA-121004-CW-RFQ / Obras Civiles para la Implementación del Centro Component 1: de Datos, Laboratorio de Solicitud de Single Stage - One 2019-09- 2019-10- 2020-04- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 238,806.00 0.00 Cancelado Instrumentación, Centro de cotizaciones Envelope 18 26 23 National Level Monitoreo y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-139769-CW-RFB / Obras Civiles para la Implementación del Centro Component 1: de Datos, Laboratorio de Solicitud de Single Stage - One 392,098.5 2019-10- 2019-10- 2019-10- 2020-02- 2019-12- 2019-11- 2019-12- 2019-12- 2019-12- 2020-02- 2020-03- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 410,326.94 Firmado Instrumentación, Centro de ofertas Envelope 0 21 25 26 18 07 29 17 20 27 14 26 National Level Monitoreo y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-145138-CW-RFQ / Construcción de Component 1: subestación y red de media Solicitud de Single Stage - One 2019-11- 2020-04- 2019-12- 2020-07- 2020-02- IBRD / 87400 Consolidating IWRM at the Posterior Limited 58,541.00 62,575.10 Firmado tensión para la cotizaciones Envelope 22 17 06 31 04 National Level electrificación del Centro de Procesamiento de Datos Secundarios ICA PE-ANA-165869-NC-RFB / CONSTRUCCIÓN DE 22 Component 1: Solicitud de Single Stage - One 155,808.8 2020-05- 2021-01- 2020-07- 2021-01- 2020-09- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 117,848.00 Firmado cotizaciones Envelope 4 06 05 01 08 29 MEDICIÓN DE AGUA EN LA National Level REGIÓN TUMBES PE-ANA-165872-NC-RFB / CONSTRUCCIÓN DE 11 Component 1: Solicitud de Single Stage - One 2020-05- 2021-01- 2020-07- 2020-11- 2020-08- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 58,924.00 69,812.60 Firmado cotizaciones Envelope 06 04 01 12 30 MEDICIÓN DE AGUA EN LA National Level REGIÓN MOQUEGUA PE-ANA-165873-NC-RFB / CONSTRUCCIÓN DE 15 Component 1: Solicitud de Single Stage - One 2020-05- 2021-01- 2020-07- 2020-11- 2020-08- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 80,351.00 76,073.91 Firmado cotizaciones Envelope 06 05 01 16 30 MEDICIÓN DE AGUA EN LA National Level REGIÓN TACNA PE-ANA-166008-CW-RFB / CONSTRUCCIÓN DE 73 Component 1: Solicitud de Single Stage - One En 2020-05- 2020-12- 2020-05- 2020-12- 2020-06- 2021-01- 2020-07- 2021-01- 2020-08- 2021-01- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 391,041.00 0.00 ofertas Envelope ejecución 01 04 06 21 17 22 17 27 21 18 MEDICIÓN DE AGUA EN LA National Level REGIÓN ANCASH PE-ANA-166009-CW-RFB Component 1: / CONSTRUCCIÓN DE 87 Solicitud de Single Stage - One 389,871.3 2020-05- 2021-02- 2020-05- 2021-02- 2020-06- 2021-03- 2020-07- 2021-06- 2020-08- 2021-09- 2021-01- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 466,035.00 Firmado ESTRUCTURAS DE ofertas Envelope 9 01 06 06 11 17 31 17 04 21 02 18 National Level MEDICIÓN DE AGUA EN LA REGIÓN LIMA PE-ANA-145139-CW-RFQ Component 1: Solicitud de Single Stage - One 2019-11- 2019-12- 2020-01- / CONSTRUCCIÓN DE RED IBRD / 87400 Consolidating IWRM at the Posterior Limited 30,434.00 0.00 Cancelado cotizaciones Envelope 22 06 20 MATRIZ DE AGUA Y National Level DESAGUE PE-ANA-216706-CW-RFB / CONSTRUCCIÓN DE 73 Component 1: Solicitud de Single Stage - One 305,112.3 2021-02- 2021-02- 2021-02- 2021-02- 2021-03- 2021-03- 2021-03- 2021-05- 2021-04- 2021-07- 2021-10- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 391,041.00 Firmado ofertas Envelope 8 02 05 07 09 21 30 31 17 05 13 02 MEDICIÓN DE AGUA EN LA National Level REGIÓN ANCASH (2da Convocatoria) PE-ANA-165981-CW-RFB Component 1: / CONSTRUCCIÓN DE 131 Solicitud de Single Stage - One Other (with field 2021-08- 2022-01- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 701,729.85 0.00 Cancelado ESTRUCTURAS DE ofertas Envelope for explanation) 26 23 National Level MEDICIÓN DE AGUA EN LA REGIÓN PIURA PE-ANA-166005-CW-RFB / CONSTRUCCIÓN DE 95 Component 1: Solicitud de Single Stage - One Other (with field 457,627.4 2021-07- 2021-06- 2021-07- 2021-06- 2021-08- 2021-08- 2021-09- 2021-09- 2021-10- 2021-11- 2022-04- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 508,889.00 Firmado ofertas Envelope for explanation) 2 01 25 06 30 17 13 16 17 21 15 19 MEDICIÓN DE AGUA EN LA National Level REGIÓN LAMBAYEQUE PE-ANA-166006-CW-RFB / CONSTRUCCIÓN DE 80 Component 1: Solicitud de Single Stage - One Other (with field En 2021-08- 2022-01- 2021-08- 2022-01- 2021-09- 2021-10- 2021-11- 2022-05- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 428,537.31 0.00 ofertas Envelope for explanation) ejecución 02 14 07 23 18 18 22 21 MEDICIÓN DE AGUA EN LA National Level REGIÓN LA LIBERTAD PE-ANA-166011-CW-RFB Component 1: / CONSTRUCCIÓN DE 107 Solicitud de Single Stage - One Other (with field 934,950.8 En 2021-08- 2021-09- 2021-08- 2021-09- 2021-09- 2021-10- 2021-10- 2021-12- 2021-11- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 573,168.66 ESTRUCTURAS DE ofertas Envelope for explanation) 5 ejecución 02 13 07 14 18 21 18 21 22 20 National Level MEDICIÓN DE AGUA EN LA REGIÓN ICA PE-ANA-166012-CW-RFB / CONSTRUCCIÓN DE 190 Component 1: Solicitud de Single Stage - One Other (with field 1,017,777. En 2021-07- 2021-08- 2021-07- 2021-08- 2021-08- 2021-09- 2021-09- 2021-10- 2022-06- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 0.00 ofertas Envelope for explanation) 00 ejecución 01 25 06 25 17 24 16 21 18 MEDICIÓN DE AGUA EN LA National Level REGIÓN AREQUIPA PE-ANA-251359-CW-RFB Request for Bids Component 1: / CONSTRUCCIÓN DE 111 Solicitud de Single Stage - One - Small Works 575,368.2 En 2021-09- 2021-09- 2021-09- 2021-09- 2021-09- 2021-10- 2021-10- 2021-11- 2021-11- 2022-05- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 558,000.00 ESTRUCTURAS DE ofertas Envelope SPD (1 envelope 8 ejecución 03 07 05 07 08 13 08 19 12 11 National Level MEDICIÓN DE AGUA EN LA process) REGIÓN PIURA PE-ANA-256754-CW-RFB / CONSTRUCCIÓN DE 190 Component 1: Solicitud de Single Stage - One Other (with field En 2021-10- 2022-01- 2021-10- 2022-01- 2021-11- 2021-12- 2021-12- 2022-08- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 878,750.00 0.00 ofertas Envelope for explanation) ejecución 11 14 16 23 27 12 27 24 MEDICIÓN DE AGUA EN LA National Level REGIÓN AREQUIPA (2da convocatoria) PE-ANA-272357-CW-RFQ / CONSTRUCCIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One Other (with field Ejecución 2022-02- 2022-04- 2022-09- IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,000.00 0.00 PROTECCIÓN Y CASETAS EN cotizaciones Envelope for explanation) pendiente 06 03 30 National Level PIEZÓMETROS UBICADOS EN EL ACUÍFERO CAPLINA PE-ANA-126678-CW-RFQ / CONSTRUCCIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One Other (with field Ejecución 2022-03- 2022-04- 2022-07- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 80,000.00 0.00 PROTECCIÓN Y CASETAS EN cotizaciones Envelope for explanation) pendiente 06 15 14 National Level PIEZÓMETROS UBICADOS EN EL ACUÍFERO ICA PE-ANA-235842-CW-RFB / CONSTRUCCIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One Other (with field 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-01- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 90,000.00 0.00 Cancelado PROTECCIÓN Y CASETAS EN ofertas Envelope for explanation) 22 27 08 07 12 10 National Level PIEZÓMETROS UBICADOS EN EL ACUÍFERO CAPLINA PE-ANA-279825-CW-RFB Component 1: / CONSTRUCCIÓN DE 107 Solicitud de Single Stage - One Other (with field Ejecución 2022-03- 2022-03- 2022-04- 2022-04- 2022-05- 2022-12- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 573,168.66 0.00 ESTRUCTURAS DE ofertas Envelope for explanation) pendiente 04 09 08 23 28 24 National Level MEDICIÓN DE AGUA EN LA REGIÓN ICA GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual LPI 003 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN, PUESTA EN Component 1: FUNCIONAMIENTO Y Solicitud de Open - Single Stage - One 2018-07- 2019-05- 2018-07- 2019-06- 2018-09- 2019-09- 2018-09- 2019-10- 2018-10- 2019-11- 2019-01- IBRD / 87400 Consolidating IWRM at the Previa 5,786,425.49 7,376,638.41 Firmado CAPACITACIÓN DEL ofertas International Envelope 06 30 11 03 13 30 23 28 25 13 03 National Level EQUIPAMIENTO PARA EL SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPI 004 2018 ANA PGIRH / SUMINISTRO , INSTALACIÓN, PUESTA EN Component 1: FUNCIONAMIENTO Y Solicitud de Open - Single Stage - One 2018-07- 2018-07- 2018-09- 2018-09- 2018-10- 2019-01- IBRD / 87400 Consolidating IWRM at the Posterior 1,418,283.54 0.00 Cancelado CAPACITACIÓN DE LOS ofertas International Envelope 09 14 16 26 28 11 National Level SUBSISTEMAS PARA EL SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPN 001 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE EQUIPAMIENTO PARA LA Component 1: Solicitud de Single Stage - One 2018-07- 2018-08- 2018-07- 2018-10- 2018-09- 2018-10- 2018-09- 2018-10- 2022-08- 2018-12- 2022-10- PLATAFORMA IBRD / 87400 Consolidating IWRM at the Posterior Open - National 100,250.00 151,040.00 Firmado ofertas Envelope 09 05 14 11 16 05 26 31 25 10 24 TECNOLÓGICA PARA LA National Level ADQUISICIÓN, DECODIFICACIÓN, INTEGRACIÓN Y DISTRIBUCIÓN DE DATOS DE LAS ESTACIONES AUTOMATICAS CON TELEMETRIA Page 1 LPN 002 2018 ANA PGIRH BM / ADQUISICIÓN DE Component 1: CATORCE (14) VEHÍCULOS Solicitud de Single Stage - One 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-09- 2018-10- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 592,732.00 500,888.09 Firmado PARA LA SUPERVISIÓN, ofertas Envelope 26 22 31 31 17 05 25 20 27 20 National Level SEDE CENTRAL Y ADMINISTRACIÓN DE LAS CUENCAS DEL PGIRH LPN 004 2018 ANA PGIRH BM / SUMINISTRO, INSTALACIÓN, PUESTA EN Component 1: FUNCIONAMIENTO Y Solicitud de Single Stage - One 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2019-01- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 564,000.00 0.00 Cancelado CAPACITACIÓN DE 141 ofertas Envelope 31 06 05 17 04 02 National Level SENSORES CON SISTEMA DE TELEMETRÍA PARA PIEZÓMETROS EN ICA Y TACNA LPI 005 2018 ANA PGIRH BM / SUMINISTRO, Component 1: INSTALACIÓN, PUESTA EN Solicitud de Open - Single Stage - One En 2018-07- 2018-09- 2018-07- 2018-09- 2018-09- 2018-11- 2018-09- 2018-12- 2018-10- 2018-12- IBRD / 87400 Consolidating IWRM at the Previa 3,200,000.00 0.00 FUNCIONAMIENTO Y ofertas International Envelope ejecución 26 07 31 07 14 22 19 14 04 28 National Level CAPACITACIÓN DE INSTRUMENTACIÓN DE PRESAS LPN 006 2018 ANA PGIRH BM / SUMINISTRO, Component 1: INSTALACIÓN, PUESTA EN Solicitud de Single Stage - One 2018-09- 2018-10- 2018-09- 2018-10- 2018-10- 2018-12- 2018-10- 2019-01- 2018-11- 2019-03- 2019-02- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 645,577.00 0.30 Firmado FUNCIONAMIENTO Y ofertas Envelope 13 12 18 12 18 03 21 03 13 25 11 National Level CAPACITACIÓN DE INSTRUMENTACIÓN DE PIEZOMETROS CP 010 2018 ANA PGIRH BM / ADQUISICION DE EQUIPOS INFORMATICOS Y Component 3: General Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2018-11- 2018-12- 2018-12- IBRD / 87400 Posterior Limited 45,151.52 6,737.05 Finalizado ACCESORIOS PERIFERICOS Project Adminstration cotizaciones Envelope 21 16 06 19 21 13 PARA LAS COORDINACIONES TECNICAS DE CUENCA CP 011 2018 ANA PGIRH Component 3: General Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- BM / ADQUISICION DE LAP IBRD / 87400 Posterior Limited 14,470.00 16,425.03 Finalizado Project Adminstration cotizaciones Envelope 21 23 06 06 21 28 TOP PARA LA SEDE CENTRAL LPN 002 2019 ANA PGIRH Component 1: Solicitud de Single Stage - One 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-04- 2019-06- BM2 / ADQUISICIÓN DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 55,000.00 46,967.58 Firmado ofertas Envelope 08 25 13 26 15 28 25 03 29 24 13 CORRENTOMETROS National Level LPI 001 2019 ANA PGIRH BM / SUMINISTRO, Component 1: INSTALACIÓN, PUESTA EN Solicitud de Open - Single Stage - One 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-04- 2019-06- 2019-06- 2019-07- 2020-06- IBRD / 87400 Consolidating IWRM at the Previa 3,200,000.00 2,709,756.00 Firmado FUNCIONAMIENTO Y ofertas International Envelope 24 01 01 01 17 29 24 06 06 12 05 National Level CAPACITACIÓN DE LA INSTRUMENTACIÓN PARA LA SEGURIDAD DE OCHO PRESAS CP 010 B 2018 ANA PGRIH BM / Equipos Informaticos Component 2: Improving Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- 2019-01- y Accesorios Perifericos IBRD / 87400 WRM in Selected Pilot River Posterior Limited 20,121.00 19,216.27 Finalizado cotizaciones Envelope 16 16 04 04 24 15 para las Coordinaciones Basins Tecnicas de Cuenca. LPN 009 2018 ANA PGIRH / ADQUISICION E INSTALACION DE EQUIPOS DE TELEMETRIA PARA Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One 2019-02- 2019-03- 2019-02- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 147,962.00 0.00 Cancelado MEDICION DE AGUA CON ofertas Envelope 22 08 26 12 28 02 20 20 National Level SENSORES PARA LAS ADMINISTRACIONES DE LOCAL DE AGUA DE TUMBES, PIURA, LAMBAYEQUE, AREQUIPA PE-ANA-116125-GO-RFB / SUMINISTRO , INSTALACIÓN, PUESTA EN Component 1: FUNCIONAMIENTO Y Solicitud de Open - Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at the Previa 2,000,000.00 2,573,999.07 Firmado CAPACITACIÓN DE LOS ofertas International Envelope 27 30 01 03 13 26 12 20 16 27 14 National Level SUBSISTEMAS PARA EL SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPI 006 2018 ANA PGIRH BM / ADQUISICIÓN, INSTALACIÓN, CAPACITACIÓN Y PUESTA Component 1: Solicitud de Open - Single Stage - One 2018-09- 2018-09- 2018-10- 2018-09- 2018-10- 2018-11- 2020-08- EN MARCHA DE EQUIPOS DE IBRD / 87400 Consolidating IWRM at the Previa 3,480,149.89 0.00 Cancelado ofertas International Envelope 10 15 15 17 25 19 10 MEDICIÓN DE AGUA Y National Level TRANSMISIÓN DE DATOS EN LAS CAPTACIONES Y BLOQUES DE RIEGO SELECCIONADOS EN LA COSTA DEL PERU PE-ANA-116523-GO-RFB / SUMINISTRO, Component 1: INSTALACIÓN, PUESTA EN Solicitud de Open - Single Stage - One En 2019-10- 2020-06- 2019-10- 2020-06- 2019-11- 2020-10- 2019-12- 2021-01- 2020-01- 2022-01- IBRD / 87400 Consolidating IWRM at the Previa 7,874,768.00 0.00 FUNCIONAMIENTO Y ofertas International Envelope ejecución 10 26 19 26 23 05 08 21 04 03 National Level CAPACITACIÓN DE 153 ESTACIONES HIDROLÓGICAS CON 33 EHCA LPI 001 ANA PGIRH / SUMINISTRO, INSTALACIÓN, Component 1: PUESTA EN Solicitud de Open - Single Stage - One 2019-04- 2019-04- 2019-06- 2019-07- 2019-08- 2020-08- IBRD / 87400 Consolidating IWRM at the Previa 7,874,768.00 0.00 Cancelado FUNCIONAMIENTO Y ofertas International Envelope 05 14 16 07 31 30 National Level CAPACITACIÓN DE 153 ESTACIONES HIDROLÓGICAS CON 33 EHCA PE-ANA-121041-GO-RFP Component 1: Solicitud de Single Stage - One 2019-10- 2019-11- 2019-12- / ADQUISICIÓN DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 36,882.35 0.00 Cancelado cotizaciones Envelope 06 18 18 PLOTTERS E IMPRESORAS National Level LPN 005 2018 ANA PGIRH BM / SUMINISTRO , INSTALACIÓN, PUESTA EN Component 1: FUNCIONAMIENTO Y Solicitud de Single Stage - One 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-07- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 1,418,283.54 0.00 Cancelado CAPACITACIÓN DE LOS ofertas Envelope 01 02 02 13 03 02 National Level SUBSISTEMAS PARA EL SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPN 001 2019 ANA PGIRH BM / EQUIPAMIENTO PARA LA IMPLEMENTACIÓN DE LAS SALAS DE MONITOREO Component 2: Improving Solicitud de Single Stage - One 2019-10- 2020-07- 2019-10- 2019-11- 2020-09- 2019-12- 2020-10- 2020-01- 2020-10- 2020-03- HÍDRICO EN LOS IBRD / 87400 WRM in Selected Pilot River Posterior Open - National 850,000.00 870,755.10 Firmado ofertas Envelope 01 24 09 25 04 05 05 06 30 06 COORDINACIÓN DE Basins RECURSOS HÍDRICOS DE LAS CUENCAS DE LA VERTIENTE DEL ATLÁNTICO PE-ANA-134184-GO-RFQ Component 1: / ADQUISICION DE Solicitud de Single Stage - One 2019-09- 2019-11- 2019-10- 2019-12- 2019-10- IBRD / 87400 Consolidating IWRM at the Posterior Limited 32,613.00 37,219.02 Firmado SOFTWARE (INC. LICENCIA) cotizaciones Envelope 18 25 07 20 22 National Level DISEÑO DE PROCESOS PE-ANA-155600-GO-RFQ / ADQUISICIÓN DE EQUIPOS Component 1: DEMOSTRATIVOS: CUATRO Solicitud de Single Stage - One 2020-01- 2020-02- 2020-11- 2020-03- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 13,134.00 8,703.10 Firmado DE MEDICIÓN DE AGUA Y cotizaciones Envelope 28 04 05 05 National Level CUATRO DE TRANSMISIÓN DE DATOS. PE-ANA-158249-GO-RFB / SUMINISTRO, INSTALACIÓN, PUESTA EN Component 1: FUNCIONAMIENTO Y Solicitud de Open - Single Stage - One En 2020-03- 2020-10- 2020-03- 2020-11- 2020-05- 2021-03- 2020-05- 2021-06- 2020-06- 2021-10- IBRD / 87400 Consolidating IWRM at the Previa 3,822,975.00 0.00 CAPACITACIÓN DE ofertas International Envelope ejecución 17 20 22 03 06 05 26 03 30 23 National Level INSTRUMENTACIÓN PARA LA MEDICIÓN DEL AGUA EN LAS CAPTACIONES Y BLOQUES DE RIEGO EN LA COSTA DEL PERÚ PE-ANA-155601-GO-RFQ / ADQUISICIÓN DE Component 1: Solicitud de Single Stage - One 2020-01- 2020-03- 2020-02- 2020-02- 2020-04- ACCESORIOS PARA IBRD / 87400 Consolidating IWRM at the Posterior Open - National 5,970.00 5,448.45 Firmado cotizaciones Envelope 28 12 04 27 06 CORRENTOMETROS National Level ELECTROMAGNÉTICOS (BARRA CONCENTRICA HERES) LPI 002 ANA PGIRH / SUMINISTRO INSTALACION Component 1: PUESTA EN Solicitud de Open - Single Stage - One 2019-04- 2019-04- 2019-06- 2019-07- 2019-07- 2020-07- IBRD / 87400 Consolidating IWRM at the Previa 3,190,000.00 0.00 Cancelado FUNCIONAMIENTO Y ofertas International Envelope 05 19 20 06 21 20 National Level CAPACITACION DE 110 SISTEMA MECANIZADOS DE AFOROS PE-ANA-161081-GO-RFQ / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE 121 Component 1: SISTEMAS MECANIZADOS Solicitud de Open - Single Stage - One 2020-03- 2020-07- 2020-03- 2020-07- 2020-05- 2020-10- 2020-06- 2020-11- 2020-07- 2020-12- 2021-12- IBRD / 87400 Consolidating IWRM at the Previa 3,500,000.00 5,377,304.00 Firmado DE AFOROS, 05 PASARELAS ofertas International Envelope 16 15 21 16 02 23 01 13 06 23 28 National Level METÁLICAS PARA AFOROS Y WINCHES PARA AFOROS EN SECCIONES DE CONTROL DE ESTACIONES HIDROLÓGICAS PARA FINES DE GESTIÓN DE RECURSOS HÍDRICOS PE-ANA-164500-GO-RFQ Component 1: Solicitud de Single Stage - One 2020-03- 2021-01- 2020-04- 2020-11- 2020-06- / compra de flujometros IBRD / 87400 Consolidating IWRM at the Posterior Open - National 26,000.00 32,139.47 Firmado cotizaciones Envelope 27 13 03 19 04 ultrasonicos portátiles National Level PE-ANA-165163-GO-RFQ / ADQUISICIÓN DE Component 3: General Solicitud de Single Stage - One Ejecución 2020-04- 2020-05- 2020-05- IBRD / 87400 Posterior Open - National 30,000.00 0.00 MOBILIARIO PARA LAS Project Adminstration cotizaciones Envelope pendiente 19 14 29 OFICINAS DEL PGIRH PE-ANA-165181-GO-RFQ / ADQUISICION DE Component 1: Solicitud de Single Stage - One 2020-06- 2020-11- 2020-08- 2020-11- 2021-02- EQUIPAMIENTO PARA IBRD / 87400 Consolidating IWRM at the Posterior Limited 23,000.00 7,198.79 Firmado cotizaciones Envelope 19 10 14 25 10 ANALISIS HIDROBIOLOGICO National Level EN LAS CUATRO CUENCAS PE-ANA-165894-GO-RFQ Component 1: / ADQUISICIÓN DE 03 Solicitud de Single Stage - One En 2020-04- 2020-05- 2020-07- IBRD / 87400 Consolidating IWRM at the Posterior Limited 2,687.00 0.00 NIVELES DE INGENIERO, cotizaciones Envelope ejecución 22 08 07 National Level INCLUIDO ACCESORIOS PE-ANA-186823-GO-RFQ / ADQUISICIÓN E Component 1: Solicitud de Single Stage - One 2020-09- 2020-10- 2020-10- 2020-11- 2020-12- INSTALACIÓN DE BASES IBRD / 87400 Consolidating IWRM at the Posterior Limited 18,000.00 23,490.72 Firmado cotizaciones Envelope 18 29 06 18 05 ANTI SÍSMICAS PARA EL National Level SISTEMA ELÉCTRICO DEL CENTRO DE DATOS PE-ANA-116126-GO-RFB / ADQUISICIÓN DE EQUIPOS Component 1: DE MEDICIÓN Y Solicitud de Open - Single Stage - One 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2020-06- IBRD / 87400 Consolidating IWRM at the Previa 3,822,971.00 0.00 Cancelado TRANSMISIÓN DE DATOS ofertas International Envelope 27 01 13 12 16 12 National Level PARA EL CONTROL DEL AGUA EN LAS CAPTACIONES Y BLOQUES DE RIEGO PE-ANA-164478-GO-RFB Component 1: / ADQUISICIÓN DE EQUIPOS Solicitud de Single Stage - One 2020-04- 2020-04- 2020-06- 2020-07- 2020-08- 2021-02- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 247,100.00 0.00 Cancelado DE MEDICIÓN DE CAUDAL - ofertas Envelope 20 25 06 06 10 06 National Level TIPO ADCP PE-ANA-167427-GO-RFQ / Adquisición de equipos Component 1: Solicitud de Single Stage - One 2020-04- 2020-05- 2020-05- 2020-07- 2020-06- de medición de caudal y IBRD / 87400 Consolidating IWRM at the Posterior Limited 37,500.00 61,518.14 Firmado cotizaciones Envelope 15 29 05 10 19 medición de calidad de National Level agua en campo PE-ANA-163933-GO-RFB / ADQUISICIÓN DE EQUIPOS Component 1: MULTIPARÁMETROS Solicitud de Single Stage - One En 2020-04- 2020-10- 2020-04- 2020-11- 2020-05- 2020-11- 2020-06- 2020-11- 2020-07- 2020-09- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 755,000.00 0.00 PORTÁTILES PARA ofertas Envelope ejecución 01 19 06 25 18 23 17 23 22 20 National Level MEDICIÓN DE CALIDAD DE AGUA SUPERFICIAL PE-ANA-190562-GO-RFQ / ADQUISICION DE EQUIPOS Component 1: Solicitud de Single Stage - One Ejecución 2020-10- 2020-10- 2020-12- DE MUESTREO Y EQUIPOS IBRD / 87400 Consolidating IWRM at the Posterior Limited 38,000.00 0.00 cotizaciones Envelope pendiente 02 26 25 MULTIPARAMETROS PARA National Level AGUAS SUBTERRANEAS PE-ANA-190602-GO-RFQ Component 1: Solicitud de Single Stage - One 2020-09- 2020-10- 2020-12- / ADQUISICION DE EQUIPOS IBRD / 87400 Consolidating IWRM at the Posterior Limited 43,000.00 0.00 Cancelado cotizaciones Envelope 29 29 28 DE PROSPECCION National Level GEOFISICA PE-ANA-190604-GO-RFQ Component 1: / ADQUISICION DE SONDA Solicitud de Single Stage - One 2020-09- 2020-10- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 43,000.00 0.00 Cancelado DE RESONANCIA cotizaciones Envelope 30 26 25 National Level MAGNETICA NUCLEAR PE-ANA-190605-GO-RFQ Component 1: / ADQUISICION DE EQUIPOS Solicitud de Single Stage - One 2020-09- 2020-11- 2021-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 30,000.00 0.00 Cancelado DE PERFILAJE GEOFISICO Y cotizaciones Envelope 30 04 03 National Level DE CAUDAL DE POZOS PE-ANA-190610-GO-RFQ Component 1: / ADQUISICION DE EQUIPOS Solicitud de Single Stage - One 2020-09- 2020-11- 2021-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,000.00 0.00 Cancelado SISTEMA CMT PARA SEIS cotizaciones Envelope 29 03 02 National Level PIEZOMETROS Page 2 PE-ANA-194534-GO-RFB / ADQUISICIÓN DE Component 1: CAMIONETAS PARA LA Solicitud de Single Stage - One En 2020-10- 2021-01- 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 183,000.00 0.00 SUPERVISION - EQUIPO ofertas Envelope ejecución 12 11 17 28 08 05 04 National Level TECNICO COORDINADO DE EHA- SMA PE-ANA-199721-GO-RFQ / Impresoras Multifuncional Monocromática para la Component 2: Improving Implementación de las Solicitud de Single Stage - One 2020-10- 2020-11- 2020-10- 2020-11- 2021-02- IBRD / 87400 WRM in Selected Pilot River Posterior Limited 50,000.00 38,366.78 Firmado Salas de Monitoreo Hídrico cotizaciones Envelope 18 02 28 16 25 Basins en las Coordinaciones de Recursos Hídricos de las Cuencas de la Vertiente PE-ANA-202827-GO-RFQ / Suministro, instalación y puesta en funcionamiento Component 1: Solicitud de Single Stage - One 2020-12- 2020-11- 2021-01- 2020-12- 2021-05- de transmisión de datos via IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 49,857.20 Firmado cotizaciones Envelope 06 19 31 01 01 el satélite GOES de la National Level instrumentación de presas poechos y san Lorenzo PE-ANA-202829-GO-RFB / Suministro, instalación y puesta en funcionamiento de sensor de nivel de agua Component 1: Solicitud de Single Stage - One 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-02- 2020-12- 2021-03- 2021-03- 2021-06- del embalse y pluviómetro IBRD / 87400 Consolidating IWRM at the Posterior Open - National 190,000.00 318,318.01 Firmado ofertas Envelope 01 12 06 25 17 17 16 28 23 29 21 y del sistema de National Level transmisión de datos via satélite GOES de la instrumentación en las siete presas priorizadas del PGIRH PE-ANA-206763-GO-RFQ / Adquisición de 01 Component 1: Solicitud de Single Stage - One 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- correntómetro para aforos IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,000.00 13,228.32 Firmado cotizaciones Envelope 16 15 20 12 21 de bajos caudales en National Level campo Cuenca piloto Mayo PE-ANA-208164-GO-RFB / Adquisición de Equipos Component 1: Solicitud de Single Stage - One 2020-12- 2020-12- 2021-01- 2021-01- 2021-02- 2021-02- 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- Multiparámetros Portátiles IBRD / 87400 Consolidating IWRM at the Posterior Open - National 755,000.00 426,427.39 Firmado ofertas Envelope 30 18 04 05 15 12 17 09 21 03 20 para Medición de Calidad National Level de Agua Superficial PE-ANA-212984-GO-RFQ / Adquisición de 2 equipos Component 1: Solicitud de Single Stage - One 2021-01- 2021-02- 2021-03- 2021-06- para Capacitación, Pruebas IBRD / 87400 Consolidating IWRM at the Posterior Open - National 36,320.00 25,390.02 Firmado cotizaciones Envelope 30 28 16 28 y Operación de Sistemas National Level Mecanizados de Aforos PE-ANA-161084-GO-RFQ / SUMINISTRO DE EQUIPOS Component 1: Solicitud de Single Stage - One En 2020-04- 2021-02- 2020-04- 2021-02- 2020-05- 2021-04- 2020-06- 2020-07- 2020-10- E INSTRUMENTACIÓN PARA IBRD / 87400 Consolidating IWRM at the Posterior Open - National 1,200,000.00 0.00 ofertas Envelope ejecución 12 16 17 24 29 21 18 23 31 LA OPERACIÓN DE National Level SISTEMAS MECANIZADOS DE AFORO PE-ANA-190607-GO-RFQ Component 1: / ADQUISICIÓN Solicitud de Single Stage - One Ejecución 2021-07- 2021-08- 2021-11- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 20,000.00 0.00 SOFTWARES PARA AGUAS cotizaciones Envelope pendiente 05 13 11 National Level SUBTERRÁNEAS Y CAPACITACIÓN. PE-ANA-236203-GO-RFB Component 1: / ADQUISICION DE EQUIPO Solicitud de Single Stage - One 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 60,000.00 0.00 Cancelado DE MEDICION DE CAUDAL ofertas Envelope 26 01 12 11 16 14 National Level EN POZOS (SPINNER) + WINCHE PE-ANA-236204-GO-RFB / ADQUISICION DE EQUIPO Component 1: Solicitud de Single Stage - One 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- DE MEDICION DE CAUDAL IBRD / 87400 Consolidating IWRM at the Posterior Open - National 60,000.00 0.00 Cancelado ofertas Envelope 03 08 19 18 23 21 EN POZOS (PULSO DE National Level CALOR) + WINCHE PE-ANA-161126-GO-RFQ / SUMINISTRO, Component 1: Solicitud de Single Stage - One 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- INSTALACIÓN DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 456,716.00 0.00 Cancelado ofertas Envelope 06 11 23 22 26 25 FLUJÓMETROS Y SISTEMAS National Level DE TELEMETRÍA EN LOS ÁMBITOS DE ICA Y TACNA. PE-ANA-268542-GO-RFB / SUMINISTRO DE EQUIPOS Component 1: E INSTRUMENTACIÓN PARA Solicitud de Single Stage - One En 2021-12- 2022-02- 2022-01- 2022-02- 2022-02- 2022-02- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 523,275.00 0.00 LA OPERACIÓN DE ofertas Envelope ejecución 28 17 02 17 13 28 25 23 National Level SISTEMAS MECANIZADOS DE AFORO (2da. Convocatoria) PE-ANA-272266-GO-RFQ Component 1: / ADQUISICIÓN DE PIEZAS Solicitud de Single Stage - One Ejecución 2022-02- 2022-03- 2022-04- IBRD / 87400 Consolidating IWRM at the Posterior Limited 15,000.00 0.00 SENSIBLES cotizaciones Envelope pendiente 05 02 01 National Level INSTRUMENTACIÓN PIEZOMETROS PE-ANA-241746-GO-RFQ / ADQUISICION DE EQUIPO Component 1: Solicitud de Single Stage - One 2021-07- 2021-09- 2022-03- DE MEDICION DE CAUDAL IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 0.00 Cancelado cotizaciones Envelope 17 11 10 EN POZOS (PULSO DE National Level CALOR) + WINCHE PE-ANA-241743-GO-RFQ Component 1: / ADQUISICION DE EQUIPO Solicitud de Single Stage - One 2021-07- 2021-09- 2022-03- IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 0.00 Cancelado DE MEDICION DE CAUDAL cotizaciones Envelope 17 11 10 National Level EN POZOS (SPINNER) + WINCHE PE-ANA-164501-GO-RFB / ADQUISICIÓN DE UNA Component 1: Solicitud de Single Stage - One 2020-04- 2020-04- 2020-05- COMPRESORA PARA IBRD / 87400 Consolidating IWRM at the Posterior Open - National 35,000.00 0.00 Cancelado cotizaciones Envelope 06 20 30 MONITOREO DE AGUAS National Level SUBTERRANEAS PE-ANA-244363-GO-RFB / ADQUISICION DE Component 1: Solicitud de Single Stage - One 2021-08- 2021-08- 2021-09- 2021-09- 2021-10- 2022-03- DISPOSITIVOS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 200,000.00 0.00 Cancelado ofertas Envelope 01 06 20 30 20 19 TELEMETRIA PARA National Level FLUJOMETROS PREEXISTENTES EN ICA PE-ANA-272373-GO-RFB / SUMINISTRO, Component 1: Solicitud de Open - Single Stage - One Ejecución 2022-02- 2022-03- 2022-04- 2022-05- 2022-05- 2022-09- INSTALACION DE IBRD / 87400 Consolidating IWRM at the Posterior 1,100,000.00 0.00 ofertas International Envelope pendiente 28 05 16 06 31 08 FLUJOMETROS Y SISTEMAS National Level DE TELEMETRIA EN LOS AMBITOS DE ICA Y TACNA. PE-ANA-240307-GO-RFB / SUMINISTRO, Component 1: Solicitud de Open - Single Stage - One 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- INSTALACION DE IBRD / 87400 Consolidating IWRM at the Previa 2,000,000.00 0.00 Cancelado ofertas International Envelope 11 16 27 16 11 19 FLUJOMETROS Y SISTEMAS National Level DE TELEMETRIA EN LOS AMBITOS DE ICA Y TACNA. NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual CP 004 2018 ANA PGIRH Component 1: Solicitud de Single Stage - One 2018-12- 2018-10- 2019-01- 2019-02- 2019-03- BM / SERVICIO DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 38,044.00 39,072.17 Rescindido cotizaciones Envelope 23 31 17 11 03 NIVELACION Y National Level MONUMENTACION ICA CP 005 2018 ANA PGIRH Component 1: Solicitud de Single Stage - One 2018-12- 2018-10- 2019-01- 2019-02- 2019-03- BM / SERVICIO DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,760.00 44,281.79 Rescindido cotizaciones Envelope 22 31 16 11 02 NIVELACION Y National Level MONUMENTACION TACNA CP 008 2018 ANA PGIRH Component 1: BM / ADQUISICION DE DOS Solicitud de Single Stage - One Ejecución 2018-10- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 29,892.00 0.00 CAUDALIMETROS cotizaciones Envelope pendiente 21 06 21 National Level ULTRASONICOS CP 009 2018 ANA PGIRH Component 1: BM / ADQUISICION DE UNA Solicitud de Single Stage - One En 2018-10- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 29,629.00 0.00 CAMARA DE INSPECCION cotizaciones Envelope ejecución 21 06 21 National Level DE POZOS CP 014 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION DE NIVEL DE AGUA EN BLOQUES DE RIEGO DE LOS Component 1: Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- VALLES DE ALGARROBO - IBRD / 87400 Consolidating IWRM at the Posterior Limited 28,528.00 129,635.34 Firmado cotizaciones Envelope 28 19 20 16 14 VALLE HERMOSO - National Level HUALTACO I - II - IV - SOMATE ALTO - SOMATE BAJO - VALLE LOS INCAS - CHIPILLICO BAJO -M - MALINGAS CP 015 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: DE NIVEL DE AGUA EN Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 25,934.00 207,452.42 Firmado BLOQUES DE RIEGO DE LOS cotizaciones Envelope 28 19 20 16 13 National Level VALLES DE QUIROZ PAMPAS- SAN ISIDRO I-II-TEJEDORES- TG-MALINGAS-YUSCAY- TABLAZO ALTO CP 016 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-11- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,550.00 57,574.33 Firmado DE NIVEL DE AGUA EN cotizaciones Envelope 02 21 25 16 07 National Level BLOQUES DE RIEGO DE LOS VALLES DE PRAXADES- SANTA MARCELA CP 017 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-11- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 28,485.00 26,918.23 Firmado DE NIVEL DE AGUA EN cotizaciones Envelope 02 12 25 16 18 National Level BLOQUES DE RIEGO DEL VALLE DE CASCAJAL- ANITAS-ILLIMO CP 018 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 25,990.00 131,662.63 Firmado DE NIVEL DE AGUA EN cotizaciones Envelope 28 12 20 16 10 National Level BLOQUES DE RIEGO DEL VALLE DE MARGEN DERECHA CP 019 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-10- 2019-08- 2018-11- 2019-09- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 23,103.00 20,790.00 Firmado cotizaciones Envelope 28 11 20 25 08 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE MIGUEL CHECA CP 020 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 25,636.00 20,942.09 Firmado cotizaciones Envelope 28 12 20 16 10 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE CASARANA CP 021 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-10- 2018-12- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 19,167.00 14,735.72 Firmado cotizaciones Envelope 28 13 20 17 03 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE SAN ANDRES CP 022 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-01- 2018-12- DE NIVEL DE AGUA EN IBRD / 87400 Consolidating IWRM at the Posterior Limited 42,727.00 31,139.78 Firmado cotizaciones Envelope 02 09 25 30 28 BLOQUES DE RIEGO DE LOS National Level VALLES DE CAPOTE-LA RAMADA-CHONGOYAOPE- PITIPO CP 023 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 28,485.00 85,114.40 Firmado DE NIVEL DE AGUA EN cotizaciones Envelope 02 09 25 12 18 National Level BLOQUES DE RIEGO DE LOS VALLES DE PUCALA TUMAN- POMALCA CP 024 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 19,939.00 66,347.73 Firmado cotizaciones Envelope 02 15 25 01 10 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE LAMBAYEQUE CP 025 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2019-02- 2018-11- 2019-03- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 37,030.00 19,450.38 Firmado cotizaciones Envelope 02 08 25 22 19 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE TALAMBO CP 013 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 39,879.00 20,893.44 Firmado cotizaciones Envelope 28 23 20 16 20 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE Page 3 CP 026 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 42,342.00 37,500.33 Firmado cotizaciones Envelope 02 07 25 14 28 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE SAN PEDRO CP 027 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 36,697.00 33,668.21 Firmado cotizaciones Envelope 02 07 25 13 19 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE SAN JOSÉ CP 028 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 14,243.00 0.00 Cancelado DE NIVEL DE AGUA EN cotizaciones Envelope 02 25 07 National Level BLOQUES DE RIEGO DEL VALLE DE SAN MIGUEL CP 029 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-11- 2018-12- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 19,940.00 20,805.11 Firmado DE NIVEL DE AGUA EN cotizaciones Envelope 02 14 25 30 10 National Level BLOQUES DE RIEGO DEL VALLE DE SAYAN CP 030 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2018-12- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 28,485.00 83,611.18 Firmado cotizaciones Envelope 02 05 25 16 18 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE LLAMACHUPAN CP 031 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 25,636.00 0.00 Cancelado cotizaciones Envelope 02 25 15 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE HUARICANGA CP 032 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 22,788.00 0.00 Cancelado cotizaciones Envelope 02 25 13 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE NARANJAL CP 033 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-11- 2019-08- 2018-12- 2019-09- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 28,485.00 29,951.43 Firmado DE NIVEL DE AGUA EN cotizaciones Envelope 02 11 05 25 28 National Level BLOQUES DE RIEGO DE LOS VALLES DE MACASH-POCOS CP 034 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 8,546.00 0.00 Cancelado cotizaciones Envelope 02 25 04 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE RINCONADA CP 035 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 17,091.00 0.00 Cancelado DE NIVEL DE AGUA EN cotizaciones Envelope 02 25 08 National Level BLOQUES DE RIEGO DE LOS VALLES DE LATERAL 4, 5 Y 6 CP 036 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - One 2018-11- 2019-02- 2018-11- 2019-03- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Consolidating IWRM at the Posterior Limited 37,030.00 33,424.63 Firmado cotizaciones Envelope 02 24 25 22 19 DE NIVEL DE AGUA EN National Level BLOQUES DE RIEGO DEL VALLE DE EL CHOLOQUE CP 038 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 22,788.00 38,281.31 Firmado DE NIVEL DE AGUA EN cotizaciones Envelope 28 23 20 16 08 National Level BLOQUES DE RIEGO DE LOS VALLES DE MALA MUERTE- CHICAMITA CP 006 2018 ANA PGIRH BM / SERVICIO DE Component 1: Solicitud de Single Stage - One 2019-04- 2019-05- 2019-06- NIVELACION Y IBRD / 87400 Consolidating IWRM at the Posterior Limited 43,479.00 0.00 Cancelado cotizaciones Envelope 07 02 16 MONUMENTACION ICA National Level (POZOS RED CONTROL GLOBAL ALA, AAA, DCERH) CP 007 2018 ANA PGIRH BM / SERVICIO DE Component 1: Solicitud de Single Stage - One 2019-04- 2019-05- 2019-06- NIVELACION Y IBRD / 87400 Consolidating IWRM at the Posterior Limited 24,457.00 0.00 Cancelado cotizaciones Envelope 07 02 16 MONUMENTACION TACNA National Level (POZOS RED CONTROL GLOBAL ALA, AAA, DCERH) CP 012 2018 ANA PGIRH BM / CONTRATACION DE Component 3: General Solicitud de Single Stage - One 2019-04- 2019-04- 2019-06- IBRD / 87400 Posterior Limited 25,000.00 0.00 Cancelado AGENCIA PARA Project Adminstration cotizaciones Envelope 07 21 14 PUBLICACION DE AVISOS EN DIARIOS CP 037 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE MEDICION Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 17,091.00 0.00 Cancelado DE NIVEL DE AGUA EN cotizaciones Envelope 02 25 08 National Level BLOQUES DE RIEGO DE LOS VALLES DE MORO- VICHANZAO PE-ANA-130327-NC-RFQ / SERVICIO DE ELABORACIÓN DEL PLAN DE Component 1: MONITOREO Solicitud de Single Stage - One 2019-09- 2019-09- 2019-10- 2019-10- 2020-02- IBRD / 87400 Consolidating IWRM at the Posterior Limited 32,915.00 31,674.21 Firmado ARQUEOLÓGICO PARA cotizaciones Envelope 20 26 07 21 04 National Level ADECUACIÓN DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LA ZONA SUR DE LA COSTA PE-ANA-133579-NC-RFB / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES TÉCNICOS DE Solicitud de Single Stage - One 2019-10- 2019-11- 2019-10- 2019-11- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 8,000.00 114.45 Firmado ESTRUCTURAS DE cotizaciones Envelope 03 06 14 22 13 National Level MEDICIÓN GRUPO 10 SECTORES HIDRÁULICOS CASMA, HUARMEY PE-ANA-133581-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: Solicitud de Single Stage - One 2019-10- 2019-11- 2019-10- 2019-11- 2020-01- EXPEDIENTES TÉCNICOS DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,000.00 98.48 Firmado cotizaciones Envelope 03 06 14 22 12 ESTRUCTURAS DE National Level MEDICIÓN GRUPO 3 SECTORES HIDRÁULICOS MyBP, SECHURA PE-ANA-133582-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES TÉCNICOS DE Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,000.00 92.63 Firmado ESTRUCTURAS DE cotizaciones Envelope 03 30 14 22 12 National Level MEDICIÓN GRUPO 5 SECTORES HIDRÁULICOS OLMOS, MOTUPE, LA LECHE PE-ANA-133583-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES TÉCNICOS DE Solicitud de Single Stage - One 2019-10- 2019-11- 2019-10- 2020-01- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,000.00 78.52 Firmado ESTRUCTURAS DE cotizaciones Envelope 03 05 14 14 10 National Level MEDICIÓN GRUPO 8 SECTORES HIDRÁULICOS MOCHE, VIRU, CHAO, GUADALUPITO PE-ANA-133584-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES TÉCNICOS DE Solicitud de Single Stage - One En 2019-10- 2019-10- 2020-02- IBRD / 87400 Consolidating IWRM at the Posterior Limited 16,000.00 0.00 ESTRUCTURAS DE cotizaciones Envelope ejecución 03 14 09 National Level MEDICIÓN GRUPO 12 SECTORES HIDRÁULICOS CHILLÓN, RIMAC, LURIN, CAÑETE PE-ANA-133585-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES TÉCNICOS DE Solicitud de Single Stage - One 2019-10- 2019-11- 2019-10- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,000.00 95.39 Firmado ESTRUCTURAS DE cotizaciones Envelope 03 06 14 22 12 National Level MEDICIÓN GRUPO 13 SECTORES HIDRÁULICOS SAN JUAN, PISCO PE-ANA-133586-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES TÉCNICOS DE Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2019-11- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 8,000.00 3,297.84 Firmado ESTRUCTURAS DE cotizaciones Envelope 03 30 14 25 13 National Level MEDICIÓN GRUPO 14 SECTORES HIDRÁULICOS ICA, LA ACHIRANA PE-ANA-133587-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2019-11- 2020-01- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,000.00 111.79 Firmado cotizaciones Envelope 03 01 14 22 12 MEDICIÓN GRUPO 18 National Level SECTORES HIDRÁULICOS IRRIG. MAJES, STA RITA DE SIGUAS, LA JOYA, VITOR YURA PE-ANA-133588-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2019-11- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 8,000.00 6,790.53 Firmado MEDICIÓN GRUPO 20 cotizaciones Envelope 03 30 14 22 13 National Level SECTORES HIDRÁULICOS IRRIG. EMM, PTA DE BOMBOM, MOQUEGUA, TORATA, LOCUMBA, SAMA, UCHUSUMA, BAJO CAPLINA PE-ANA-136558-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: Solicitud de Single Stage - One 2019-10- 2020-02- 2019-11- 2020-03- 2020-01- MEDICIÓN DE NIVEL DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 32,740.00 29,723.68 Firmado cotizaciones Envelope 19 18 17 05 16 AGUA EN BLOQUES DE National Level RIEGO EN EL SECTOR HIDRÁULICO MENOR CAÑETE PE-ANA-136561-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: Solicitud de Single Stage - One 2019-10- 2020-03- 2019-11- 2020-08- 2020-01- MEDICIÓN DE NIVEL DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 35,680.00 28,030.30 Firmado cotizaciones Envelope 19 13 17 24 03 AGUA EN BLOQUES DE National Level RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO I PE-ANA-137039-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: Solicitud de Single Stage - One 2019-10- 2020-03- 2019-11- 2020-08- 2019-12- MEDICIÓN DE NIVEL DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 28,312.00 23,487.57 Firmado cotizaciones Envelope 19 13 17 24 27 AGUA EN BLOQUES DE National Level RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO II PE-ANA-137046-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE NIVEL DE Solicitud de Single Stage - One 2019-10- 2020-06- 2019-11- 2020-08- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 23,452.00 36,147.55 Firmado AGUA EN BLOQUES DE cotizaciones Envelope 19 23 17 24 16 National Level RIEGO EN LOS SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN PE-ANA-137047-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE NIVEL DE Solicitud de Single Stage - One 2019-10- 2020-07- 2019-11- 2020-09- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 43,598.00 27,065.09 Firmado AGUA EN BLOQUES DE cotizaciones Envelope 19 10 17 02 27 National Level RIEGO EN EL SECTOR HIDRÁULICO MENOR IRRIGACIÓN MAJES , VALLE DE MAJES, CAMANÁ PE-ANA-137048-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE NIVEL DE Solicitud de Single Stage - One 2019-10- 2020-07- 2019-11- 2020-09- 2020-02- IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,110.00 29,982.46 Firmado AGUA EN BLOQUES DE cotizaciones Envelope 19 29 17 02 03 National Level RIEGO EN EL SECTOR HIDRÁULICO MENOR LA JOYA, CHILI REGULADO Y CHILI NO REGULADO PE-ANA-137049-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE Component 1: Solicitud de Single Stage - One 2019-10- 2020-09- 2019-11- 2020-11- 2020-02- AGUA EN BLOQUES DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 22,399.00 13,241.97 Firmado cotizaciones Envelope 19 18 17 03 03 RIEGO EN EL SECTOR National Level HIDRÁULICO MENOR IRRIGACIÓN ENSENADA- MEJIA-MOLLENDO Y PUNTA DE BOMBOM Page 4 PE-ANA-137051-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE Component 1: Solicitud de Single Stage - One 2019-10- 2020-09- 2019-11- 2020-11- 2020-02- AGUA EN BLOQUES DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 44,793.00 33,679.65 Firmado cotizaciones Envelope 19 29 17 03 03 RIEGO EN LOS SECTORES National Level HIDRÁULICOS MENOR MOQUEGUA, LOCUMBA, SAMA Y BAJO UCHUSUMA PE-ANA-137052-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: Solicitud de Single Stage - One 2019-10- 2019-11- 2019-11- 2020-01- 2020-02- MEDICIÓN DE AGUA EN IBRD / 87400 Consolidating IWRM at the Posterior Limited 36,795.00 24,051.35 Firmado cotizaciones Envelope 19 20 17 09 03 BLOQUES DE RIEGO EN EL National Level SECTOR HIDRÁULICO MENOR MOTUPE-OLMOS- LA LECHE PE-ANA-139771-NC-RFQ Component 1: Solicitud de Single Stage - One 2019-10- 2019-11- 2020-05- / SERVICIO PARA EJECUTAR IBRD / 87400 Consolidating IWRM at the Posterior Open - National 26,268.66 0.00 Cancelado cotizaciones Envelope 26 24 02 11 PERFILAJES GEOFISICOS National Level PE-ANA-139772-NC-RFQ / SERVICIO PARA LA Component 1: Solicitud de Single Stage - One 2019-10- 2019-11- 2020-01- INSTALACIÓN Y IBRD / 87400 Consolidating IWRM at the Posterior Open - National 35,820.90 0.00 Cancelado cotizaciones Envelope 26 24 23 CONSTRUCCIÓN DE National Level CASETAS PRE FABRICADAS TACNA PE-ANA-139773-NC-RFQ / SERVICIO PARA LA Component 1: Solicitud de Single Stage - One 2019-10- 2019-11- 2020-01- INSTALACIÓN Y IBRD / 87400 Consolidating IWRM at the Posterior Open - National 33,433.00 0.00 Cancelado cotizaciones Envelope 26 24 23 CONSTRUCCIÓN DE National Level CASETAS PRE FABRICADAS ICA PE-ANA-139774-NC-RFQ / SERVICIO DE ADAPTACIÓN, SEGURIDAD PARA LA Component 1: Solicitud de Single Stage - One 2019-10- 2019-11- 2020-01- INSTRUMENTACIÓN DE 27 IBRD / 87400 Consolidating IWRM at the Posterior Open - National 29,553.00 0.00 Cancelado cotizaciones Envelope 26 24 23 POZOS Y PIEZOMETROS EN National Level ESTADO UTILIZABLE Y 15 EN ESTADO UTILIZADO EN EL ACUIFERO DE ICA, VILLACURI Y LANCHAS PE-ANA-152835-NC-RFQ / SERVICIO DE Component 1: Solicitud de Single Stage - One 2020-01- 2020-01- 2020-02- 2020-01- 2020-07- ALOJAMIENTO DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 30,000.00 60,749.10 Firmado cotizaciones Envelope 25 13 21 20 20 INFRAESTRUCTURA National Level TECNOLÓGICA DE DATA CENTER PE-ANA-154274-NC-RFQ / SERVICIO DE ALOJAMIENTO Y Component 1: Solicitud de Single Stage - One 2020-01- 2020-01- 2020-01- 2020-01- 2020-02- ALIMENTACIÓN PARA LOS IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 53,878.72 Firmado cotizaciones Envelope 18 21 26 23 02 PARTICIPANTES DEL TALLER National Level DE CAPACITACIÓN PARA ESPECIALISTAS DE CALIDAD DE RECURSOS HIDRICOS PE-ANA-155598-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE Component 1: Solicitud de Single Stage - One 2020-02- 2020-02- 2020-03- 2020-04- EXPEDIENTES TÉCNICOS IBRD / 87400 Consolidating IWRM at the Posterior Open - National 8,597.00 9,632.19 Firmado cotizaciones Envelope 09 19 02 04 PARA LA CONSTRUCCIÓN National Level DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS VALLE DE MAJES Y VALLE SIGUAS QUILCA. PE-ANA-155595-NC-RFQ / SERVICIO DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE Component 1: Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-04- EXPEDIENTES TÉCNICOS IBRD / 87400 Consolidating IWRM at the Posterior Open - National 6,179.00 10,075.32 Firmado cotizaciones Envelope 09 19 28 04 PARA LA CONSTRUCCIÓN National Level DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR ALTO PIURA. PE-ANA-155594-NC-RFQ / SERVICIO DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA Component 1: ELABORACIÓN DE Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 9,134.00 6,815.66 Firmado EXPEDIENTES TÉCNICOS cotizaciones Envelope 09 19 28 20 National Level PARA LA CONSTRUCCIÓN DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR CHIRA. PE-ANA-155596-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE Component 1: Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- EXPEDIENTES TÉCNICOS IBRD / 87400 Consolidating IWRM at the Posterior Open - National 8,597.00 9,329.13 Firmado cotizaciones Envelope 09 19 28 30 PARA LA CONSTRUCCIÓN National Level DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS MENOR ZAÑA Y JEQUETEPEQUE PE-ANA-155599-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE Component 1: EXPEDIENTES TÉCNICOS Solicitud de Single Stage - One 2020-02- 2020-02- 2020-03- 2020-03- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 5,373.00 4,212.49 Firmado PARA LA CONSTRUCCIÓN cotizaciones Envelope 09 19 02 20 National Level DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO. PE-ANA-155597-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE Component 1: EXPEDIENTES TÉCNICOS Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 9,134.00 7,134.04 Firmado PARA LA CONSTRUCCIÓN cotizaciones Envelope 09 19 28 25 National Level DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS PALPA, NASCA, ACARI, BELLA UNIÓN, CHAPARRA, Y YAUCA. PE-ANA-158210-NC-RFQ / Alquiler de camionetas 4x4 para las actividades de Supervisión del Suministro, Instalación, Puesta en Component 1: Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- 2020-06- funcionamiento y IBRD / 87400 Consolidating IWRM at the Posterior Limited 38,500.00 38,925.20 Firmado cotizaciones Envelope 20 20 29 02 13 Capacitación de la National Level Instrumentación para la Seguridad de las presas Poechos, San Lorenzo, Tinajones y Gallito Ciego. PE-ANA-158215-NC-RFQ / Alquiler de camionetas 4x4 para las actividades de Supervisión del Suministro, Instalación, Puesta en Component 1: Solicitud de Single Stage - One 2020-02- 2020-09- 2020-03- 2020-09- 2020-06- funcionamiento y IBRD / 87400 Consolidating IWRM at the Posterior Limited 23,500.00 14,775.32 Firmado cotizaciones Envelope 21 23 01 29 19 Capacitación de la National Level Instrumentación para la Seguridad de las presas del Sur Condoroma, El Frayle, Sutunta y Pasto Grande. PE-ANA-159315-NC-RFQ / SERVICIO DE LIMPIEZA, Component 1: Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- TALA Y DESBROCE, Y IBRD / 87400 Consolidating IWRM at the Posterior Limited 23,000.00 20,343.08 Firmado cotizaciones Envelope 21 18 28 21 30 TRASLADO DE MATERIAL National Level ELIMINADO EN LA PRESA POECHOS PE-ANA-161087-NC-RFQ / SERVICIO DE ALOJAMIENTO, ALIMENTACIÓN Y SALAS Component 1: Solicitud de Single Stage - One 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- EQUIPADAS PARA EL IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 40,733.54 Firmado cotizaciones Envelope 02 02 05 03 07 TALLER NACIONAL: National Level FORTALECIMIENTO DE LAS JUNTAS USUARIAS Y SU ROL EN EL DESARROLLO PRODUCTIVO AGRARIO PE-ANA-161131-NC-RFQ / SERVICIOS DE LIMPIEZA Y Component 1: ADAPTACIÓN DE 15 POZOS Solicitud de Single Stage - One 2020-03- 2020-04- 2020-07- IBRD / 87400 Consolidating IWRM at the Posterior Limited 14,925.00 0.00 Cancelado UBICADO EN LOS cotizaciones Envelope 18 04 03 National Level ACUÍFEROS DE ICA, VILLACURI Y LANCHAS. PE-ANA-164268-NC-DIR / SERVICIO DE ARRENDAMIENTO DE Component 3: General Adquisición 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-06- 2022-12- INMUEBLE 2 PARA EL IBRD / 87400 Posterior Direct 84,500.00 55,200.00 Firmado Project Adminstration directa 23 09 30 16 01 30 31 PROYECTO GESTIÓN INTEGRADA DE RECURSOS HIDRICOS EN DIEZ CUENCAS PE-ANA-164313-NC-RFQ Component 1: / SERVICIO DE Solicitud de Single Stage - One 2020-03- 2020-05- 2020-11- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 10,448.00 0.00 Cancelado ELABORACIÓN DE cotizaciones Envelope 31 26 22 National Level CARTELES DE IDENTIFICACIÓN POZOS PE-ANA-164550-NC-RFQ / SERVICIO DE Component 1: Solicitud de Single Stage - One Ejecución 2020-04- 2020-05- 2021-01- AGENCIAMIENTO DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 29,851.00 0.00 cotizaciones Envelope pendiente 13 04 12 PASAJES AÉREOS National Level NACIONALES Y INTERNACIONALES PE-ANA-164552-NC-RFQ / SERVICIO DE PUBLICIDAD Component 1: Solicitud de Single Stage - One 2020-04- 2020-05- 2021-08- 2021-01- DE AVISOS RELACIONADOS IBRD / 87400 Consolidating IWRM at the Posterior Open - National 17,910.00 26,731.37 Firmado cotizaciones Envelope 13 04 09 12 A LAS CONVOCATORIAS National Level DEL PROYECTO PE-ANA-164985-NC-DIR / SERVICIO DE ARRENDAMIENTO DE INMUEBLE PARA LA SEDE Component 3: General Adquisición 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2022-12- PRINCIPAL DEL PGIRH DE LA IBRD / 87400 Posterior Direct 239,415.00 174,120.00 Firmado Project Adminstration directa 18 16 25 16 05 31 31 UNIDAD EJECUTORA N°002 MODERNIZACION DE LA GESTION DE LOS RECURSOS HIDRICOS PE-ANA-165161-NC-RFQ / SERVICIO DE CABLEADO Component 3: General Solicitud de Single Stage - One 2020-04- 2020-04- 2020-08- 2020-05- IBRD / 87400 Posterior Open - National 30,000.00 29,483.43 Firmado DE VOZ Y DATA PARA Project Adminstration cotizaciones Envelope 16 26 13 11 LOCAL DEL PGIRH PE-ANA-165867-NC-RFB / CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One 2020-04- 2020-06- 2020-09- IBRD / 87400 Consolidating IWRM at the Posterior Limited 42,728.00 0.00 Cancelado MEDICIÓN DE AGUA EN LOS cotizaciones Envelope 25 20 18 National Level SECTORES HIDRÁULICOS MENORES COMPRENDIDOS DESDE CHICAMA HASTA SANTA PE-ANA-165868-NC-RFB / CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One 2020-04- 2020-06- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Limited 26,192.00 0.00 Cancelado MEDICIÓN DE AGUA EN LOS cotizaciones Envelope 25 20 19 National Level SECTORES HIDRÁULICOS MENORES COMPRENDIDOS DESDE FORTALEZA HASTA LURÍN PE-ANA-165877-NC-RFQ Component 1: / ALQUILER DE CAMIONETA Solicitud de Single Stage - One Ejecución 2020-04- 2020-04- 2020-06- IBRD / 87400 Consolidating IWRM at the Posterior Limited 9,242.00 0.00 PARA VERIFICACIÓN DE cotizaciones Envelope pendiente 21 30 29 National Level COBERTURA DE TRANSMISIÓN PE-ANA-165652-GO-RFB / CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One 2020-06- 2020-06- 2020-08- 2020-08- 2020-09- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 130,401.14 0.00 Cancelado MEDICIÓN DE AGUA EN LOS ofertas Envelope 15 20 01 21 25 24 National Level SECTORES HIDRÁULICOS MENORES COMPRENDIDOS DESDE TUMBES HASTA JEQUETEPEQUE PE-ANA-187094-NC-RFQ / SERVICIO DE TELEFONIA MOVIL PARA EL PERSONAL Component 3: General Solicitud de Single Stage - One 2020-09- 2020-10- 2020-10- 2020-11- 2021-10- IBRD / 87400 Posterior Limited 20,000.00 14,423.97 Firmado DEL PROYECTO DE GESTION Project Adminstration cotizaciones Envelope 17 16 01 20 01 INTEGRADA DE RECURSOS HIDRICOS EN DIEZ CUENCAS Page 5 PE-ANA-187470-NC-RFQ / ELABORACION E Component 1: Solicitud de Single Stage - One 2020-09- 2020-09- 2020-10- 2020-11- 2021-03- IMPLEMENTACION DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 49,055.79 Firmado cotizaciones Envelope 17 21 08 04 07 PLANES DE MONITOREO National Level ARQUEOLÓGICO - PMA. PE-ANA-164575-NC-RFB Component 1: / SERVICIO DE ANÁLISIS DE Solicitud de Single Stage - One 2020-04- 2020-11- 2020-04- 2020-12- 2020-05- 2021-01- 2020-06- 2021-02- 2020-07- 2021-03- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Open - National 477,650.00 248,246.81 Firmado LABORATORIO PARA ofertas Envelope 06 22 11 21 23 13 22 12 27 04 24 National Level MUESTRAS DE AGUA NATURAL PE-ANA-165874-NC-RFB / ELABORAR E Component 1: Solicitud de Single Stage - One 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- IMPLEMENTAR ONCE (11) IBRD / 87400 Consolidating IWRM at the Posterior Open - National 59,702.00 0.00 Cancelado ofertas Envelope 30 05 16 16 20 17 PLANES DE MONITOREO National Level ARQUEOLÓGICO-PMA PE-ANA-191481-NC-RFQ / SERVICIO DE INTERNET PARA EL CENTRO DE Component 1: Solicitud de Single Stage - One 2020-09- 2020-09- 2020-10- 2020-10- 2021-01- PROCESAMIENTO DE DATOS IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,000.00 17,122.15 Firmado cotizaciones Envelope 17 23 01 23 29 SECUNDARIO DE LA National Level AUTORIDAD NACIONAL DEL AGUA PE-ANA-187303-NC-RFQ / SERVICIO DE Component 3: General Solicitud de Single Stage - One Ejecución 2020-09- 2020-10- 2021-10- INFRAESTRUCTURA Y IBRD / 87400 Posterior Limited 32,500.00 0.00 Project Adminstration cotizaciones Envelope pendiente 27 22 22 PLATAFORMA EN LA NUBE PARA EL PROYECTO PGIRH PE-ANA-202872-NC-RFQ / CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One Ejecución 2020-11- 2020-12- 2021-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,900.00 0.00 MEDICIÓN DE AGUA EN LOS cotizaciones Envelope pendiente 22 01 30 National Level SECTORES HIDRÁULICOS MENORES COMPRENDIDOS DESDE CHICAMA HASTA SANTA PE-ANA-202873-NC-RFQ / CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One 2020-11- 2021-02- 2020-12- 2021-03- 2021-01- IBRD / 87400 Consolidating IWRM at the Posterior Limited 25,100.00 31,352.14 Firmado MEDICIÓN DE AGUA EN LOS cotizaciones Envelope 22 16 01 15 30 National Level SECTORES HIDRÁULICOS MENORES COMPRENDIDOS DESDE FORTALEZA HASTA LURÍN PE-ANA-206762-NC-RFQ / SERVICIOS Component 1: COMPLEMENTARIOS PARA Solicitud de Single Stage - One 2020-12- 2020-12- 2020-12- 2020-12- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 28,000.00 21,878.55 Firmado EL CENTRO DE cotizaciones Envelope 16 18 20 23 21 National Level PROCESAMIENTO SECUNDARIO DEL MONITOREO DEL RECURSO HÍDRICO - ICA PE-ANA-208167-NC-RFQ / SEGURO VEHICULAR Component 3: General Solicitud de Single Stage - One 2020-12- 2020-12- 2020-12- 2020-12- 2020-12- IBRD / 87400 Posterior Limited 37,350.00 21,521.29 Firmado ANUAL PARA LOS Project Adminstration cotizaciones Envelope 13 11 17 18 18 VEHICULOS DEL PGIRH PE-ANA-208190-NC-RFQ / SERVICIO DE ADUANA Component 1: PARA LA IMPORTACION DE Solicitud de Single Stage - One 2020-12- 2021-01- 2020-12- 2021-02- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,000.00 35,148.56 Firmado ESTACIONES AUTOMATICAS cotizaciones Envelope 16 18 26 06 27 National Level (HIDROLOGICAS E HIDROMETEOROLOGICAS) PE-ANA-208191-NC-RFQ / SERVICIO DE ADUANA PARA LA IMPORTACION DE Component 1: Solicitud de Single Stage - One 2020-12- 2021-01- 2020-12- 2021-02- 2020-12- SISTEMAS MECANIZADOS IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,000.00 26,899.18 Firmado cotizaciones Envelope 16 15 20 06 21 DE AFORO, PASARELAS National Level METALICAS DE AFOROS Y WINCHES PARA AFOROS PE-ANA-203041-NC-RFQ / ALQUILER DE CAMIONETA 4 X 4 PARA ACTIVIDADES Component 1: DE INSPECCION AL Solicitud de Single Stage - One 2021-02- 2021-01- 2021-02- 2021-02- 2021-06- IBRD / 87400 Consolidating IWRM at the Posterior Limited 21,000.00 20,459.53 Firmado SERVICIO DE SUMINISTRO cotizaciones Envelope 02 22 12 24 27 National Level INSTALACION PUESTA EN FUNCIONAMIENTO Y CAPACITACION DE PRESAS EN PIURA PE-ANA-213295-NC-RFQ / SERVICIO DE ALQUILER DE CAMIONETA 4X4 PARA ACTIVIDADES DE Component 1: Solicitud de Single Stage - One 2021-01- 2021-01- 2021-02- 2021-02- 2021-04- INSPECCION AL SERVICIO IBRD / 87400 Consolidating IWRM at the Posterior Limited 9,334.00 9,093.12 Firmado cotizaciones Envelope 21 22 01 24 02 DE SUMINISTRO, National Level INSTALACION, PUESTA EN FUNCIONAMIENTO Y CAPACITACION DE PRESAS GALLITO CIEGO - CAJAMARCA PE-ANA-213296-NC-RFQ / SERVICIO DE ALQUILER DE CAMIONETA 4X4 PARA ACTIVIDADES DE Component 1: INSPECCION AL SERVICIO Solicitud de Single Stage - One 2021-01- 2021-01- 2021-02- 2021-02- 2021-04- IBRD / 87400 Consolidating IWRM at the Posterior Limited 9,167.00 8,930.75 Firmado DE SUMINISTRO, cotizaciones Envelope 21 22 01 24 02 National Level INSTALACION, PUESTA EN FUNCIONAMIENTO Y CAPACITACION DE PRESAS - PRESA TINAJONES EN CHILCAYO - GRUPO II PE-ANA-213297-NC-RFQ / SERVICIO DE ALQUILER DE 02 CAMIONETAS 4X4 PARA ACTIVIDADES DE Component 1: Solicitud de Single Stage - One 2021-01- 2021-01- 2021-01- 2021-02- 2021-04- INSPECCION AL SERVICIO IBRD / 87400 Consolidating IWRM at the Posterior Limited 18,667.00 18,186.25 Firmado cotizaciones Envelope 21 22 31 24 01 DE SUMINISTRO, National Level INSTALACION, PUESTA EN FUNCIONAMIENTO Y CAPACITACION DE PRESAS DEL SUR PE-ANA-213485-NC-RFQ / SERVICIO DE DISEÑO, DIAGRAMACIÓN Y Component 3: General Solicitud de Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2022-12- IBRD / 87400 Posterior Limited 26,000.00 26,134.23 Firmado CORRECCIÓN DE ESTILO DE Project Adminstration cotizaciones Envelope 25 29 15 03 30 11 BOLETINES DIGITALES DEL PGIRH (2021-2022) PE-ANA-221551-NC-RFQ / CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One 2021-03- 2021-05- 2021-04- 2021-07- 2021-06- IBRD / 87400 Consolidating IWRM at the Posterior Limited 49,000.00 46,889.86 Firmado MEDICIÓN DE AGUA EN LOS cotizaciones Envelope 13 07 06 02 22 National Level SECTORES HIDRÁULICOS MENORES COMPRENDIDOS DESDE TUMBES HASTA ALTO PIURA PE-ANA-221560-NC-RFQ / CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Solicitud de Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- IBRD / 87400 Consolidating IWRM at the Posterior Limited 41,500.00 51,703.66 Firmado MEDICIÓN DE AGUA EN LOS cotizaciones Envelope 13 08 06 07 30 National Level SECTORES HIDRÁULICOS MENORES COMPRENDIDOS DESDE OLMOS HASTA JEQUETEPEQUE PE-ANA-229523-NC-RFQ Component 1: / Elaboración de Planes de Solicitud de Single Stage - One 2021-04- 2021-04- 2021-05- 2021-05- 2021-10- IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 10,051.39 Firmado Monitoreo Arqueológico cotizaciones Envelope 21 26 07 03 04 National Level para Estaciones Hidrometricas PE-ANA-235377-NC-RFQ / Servicio de movilidad para la supervisión de la Component 1: culminación de la Solicitud de Single Stage - One Ejecución 2021-06- 2021-06- 2021-09- IBRD / 87400 Consolidating IWRM at the Posterior Limited 7,200.00 0.00 adecuación de las cotizaciones Envelope pendiente 06 28 28 National Level estructuras de medición de agua en sectores hidráulicos desde Tumbes hasta Alto Piura PE-ANA-235381-NC-RFQ / Servicio de movilidad para la supervisión de la Component 1: Solicitud de Single Stage - One Ejecución 2021-07- 2021-08- 2021-10- culminación de la IBRD / 87400 Consolidating IWRM at the Posterior Limited 6,000.00 0.00 cotizaciones Envelope pendiente 20 11 26 adecuación de las National Level estructuras de medición de agua en sectores hidráulicos desde Chicama hasta Santa PE-ANA-202887-NC-RFB / SERVICIO DE COMUNICACIÓN DE DATOS Component 1: Solicitud de Single Stage - One Ejecución 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- DE ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 142,900.00 0.00 ofertas Envelope pendiente 01 06 17 02 22 27 MEDICIÓN DE AGUA EN National Level BLOQUES DE RIEGO A PLATAFORMA DEL SNIRH, CON TECNOLOGÍA GPRS/GSM-SMS PE-ANA-236180-NC-RFB / SERVICIO PARA EJECUTAR Component 1: Solicitud de Single Stage - One 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2021-09- PERFILES GAMMA RAY, CE Y IBRD / 87400 Consolidating IWRM at the Posterior Open - National 80,000.00 0.00 Cancelado ofertas Envelope 11 16 28 17 11 17 T EN PIEZOMETROS National Level CULMINADOS EN ICA PE-ANA-241748-NC-RFQ / SERVICIO PARA EJECUTAR Component 1: Solicitud de Single Stage - One En 2021-07- 2021-07- 2021-09- 2022-03- PERFILES GAMMA RAY, CE Y IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,000.00 0.00 cotizaciones Envelope ejecución 20 22 14 13 T EN PIEZOMETROS National Level CULMINADOS EN ICA PE-ANA-241755-NC-RFQ / SERVICIO PARA EJECUTAR Component 1: Solicitud de Single Stage - One Ejecución 2021-07- 2021-09- 2022-03- PERFILES GAMMA RAY, CE Y IBRD / 87400 Consolidating IWRM at the Posterior Limited 30,000.00 0.00 cotizaciones Envelope pendiente 20 14 13 T EN PIEZOMETROS National Level CULMINADOS EN TACNA PE-ANA-243230-NC-RFQ / SERVICIO DE CULMINACIÓN DE LA Component 1: Solicitud de Single Stage - One 2021-07- 2021-07- 2021-07- 2021-09- 2021-08- ADECUACIÓN DE TRECE IBRD / 87400 Consolidating IWRM at the Posterior Limited 10,300.00 29,595.31 Firmado cotizaciones Envelope 15 16 27 22 26 (13) ESTRUCTURAS DE National Level MEDICIÓN DE AGUA EN EL SECTOR HIDRÁULICO MENOR PISCO PE-ANA-244365-NC-RFQ Component 1: Solicitud de Single Stage - One Ejecución 2021-07- 2021-08- 2021-09- / ADQUISICION DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 5,000.00 0.00 cotizaciones Envelope pendiente 26 06 05 TUBERIAS DE PVC National Level PE-ANA-248255-NC-RFQ / SERVICIO DE IMPRESION Y Component 1: EMPASTADO DE ESTUDIOS Solicitud de Single Stage - One Ejecución 2021-08- 2021-09- 2021-10- IBRD / 87400 Consolidating IWRM at the Posterior Limited 2,000.00 0.00 EJECUTADOS EN EL cotizaciones Envelope pendiente 30 17 17 National Level COMPONENTE MONITOREO DE ACUIFEROS SELECCIONADOS PE-ANA-261827-NC-DIR / SERVICIO DE ARRENDAMIENTO DEL Component 3: General Adquisición 2021-11- 2021-11- 2021-11- 2021-11- 2021-11- 2021-11- 2022-12- INMUEBLE N°2 PARA EL IBRD / 87400 Posterior Direct 54,000.00 46,800.00 Firmado Project Adminstration directa 09 08 10 09 15 09 31 PROYECTO GESTION INTEGRADA DE RECURSOS HIDRICOS (2) PE-ANA-265813-NC-RFQ / Elaboración y aprobación Component 1: de Planes de Monitoreo Solicitud de Single Stage - One Ejecución 2021-12- 2021-12- 2022-03- IBRD / 87400 Consolidating IWRM at the Posterior Limited 30,000.00 0.00 Arqueológico de Estaciones cotizaciones Envelope pendiente 10 25 25 National Level Hidrológicas Automáticas en la región Cusco PE-ANA-202823-NC-RFQ Component 1: / Conductor 02 de Solicitud de Single Stage - One Ejecución 2022-02- 2022-03- 2022-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 10,625.00 0.00 camioneta para la cotizaciones Envelope pendiente 05 01 26 National Level supervisión de EHA - SMA PE-ANA-202818-NC-RFQ Component 1: / Conductor 01 de Solicitud de Single Stage - One Ejecución 2022-02- 2022-03- 2022-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 10,625.00 0.00 camioneta para la cotizaciones Envelope pendiente 05 01 26 National Level supervisión de EHA - SMA PE-ANA-202826-NC-RFQ Component 1: / Conductor 04 de Solicitud de Single Stage - One Ejecución 2022-02- 2022-03- 2022-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 10,625.00 0.00 camioneta para la cotizaciones Envelope pendiente 05 01 26 National Level supervisión de EHA - SMA PE-ANA-202824-NC-RFQ Component 1: / Conductor 03 de Solicitud de Single Stage - One Ejecución 2022-02- 2022-04- 2022-12- IBRD / 87400 Consolidating IWRM at the Posterior Limited 10,625.00 0.00 camioneta para la cotizaciones Envelope pendiente 05 02 08 National Level supervisión de EHA - SMA PE-ANA-236194-NC-RFB / SERVICIO DE PERFILAJE E INTERPRETACION A TRAVES Component 1: Solicitud de Single Stage - One 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- DE SONDAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 200,000.00 0.00 Cancelado ofertas Envelope 05 10 21 20 25 23 RESONANCIA MAGNETIA National Level NUCLEAR (NMR) EN PIEZOMETROS EN EL AMBITO TACNA Page 6 PE-ANA-248203-NC-RFQ / SERVICIO DE SOCIABILIZACION DE LA ACTIVIDAD CAMBIO DE Component 1: ARBOLES DE DESCARGA, Solicitud de Single Stage - One 2021-09- 2021-09- 2021-11- IBRD / 87400 Consolidating IWRM at the Posterior Limited 40,000.00 0.00 Cancelado INSTALACION DE cotizaciones Envelope 06 19 18 National Level FLUJOMETROS Y SISTEMAS DE TELEMETRIA EN POZOS UBICADOS EN EL AMBITO DE TACNA PE-ANA-244364-NC-RFQ / ADQUISICION DE EQUIPOS Component 1: Solicitud de Single Stage - One 2021-07- 2021-08- 2021-11- DE MEDICION DE GAMA IBRD / 87400 Consolidating IWRM at the Posterior Limited 25,000.00 0.00 Cancelado cotizaciones Envelope 27 06 04 RAY, CE, T°, ACCESORIOS Y National Level CAPACITACION PE-ANA-236191-NC-RFQ / SERVICIO DE Component 1: Solicitud de Single Stage - One 2021-06- 2021-08- 2021-09- INSTALACION DE CARTELES IBRD / 87400 Consolidating IWRM at the Posterior Limited 3,000.00 0.00 Cancelado cotizaciones Envelope 12 07 06 DE IDENTIFICACION EN National Level POZOS Y PIEZOMETROS AMBITO TACNA PE-ANA-236190-NC-RFQ / SERVICIO DE Component 1: Solicitud de Single Stage - One 2021-06- 2021-08- 2021-10- INSTALACION DE CARTELES IBRD / 87400 Consolidating IWRM at the Posterior Limited 3,000.00 0.00 Cancelado cotizaciones Envelope 12 07 06 DE IDENTIFICACION EN National Level POZOS Y PIEZOMETROS AMBITO ICA (I-V-L) PE-ANA-126675-NC-RFQ / SERVICIO DE EJECUCIÓN Component 1: Solicitud de Single Stage - One 2019-09- 2019-10- 2019-11- DE SIETE PRUEBAS DE IBRD / 87400 Consolidating IWRM at the Posterior Open - National 45,000.00 0.00 Cancelado cotizaciones Envelope 21 31 30 BOMBEO EN PIEZÓMETROS National Level UBICADOS EN EL ACUÍFERO CAPLINA PE-ANA-161129-NC-RFQ / SERVICIO DE Component 1: Solicitud de Single Stage - One Ejecución 2022-02- 2022-03- 2022-04- 2022-05- 2022-06- 2022-08- ADAPTACIÓN DE ÁRBOLES IBRD / 87400 Consolidating IWRM at the Posterior Open - National 75,000.00 0.00 ofertas Envelope pendiente 28 05 16 06 10 09 DE DESCARGA EN POZOS National Level UBICADOS EN EL ÁMBITO DE TACNA PE-ANA-236175-NC-RFQ / SERVICIO DE IMPLEMENTACIÓN DE EJEMPLOS PILOTO DE MEDICIÓN DE CONSUMO DE Component 1: Solicitud de Single Stage - One Ejecución 2022-04- 2022-04- 2022-07- AGUA EN POZOS DE IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 0.00 cotizaciones Envelope pendiente 02 20 19 PRODUCCIÓN UBICADOS EN National Level EL ÁMBITO DE TACNA A TRAVÉS FLUJÓMETROSELECTROMÁG NETICOS Y DE TURBINA PE-ANA-236174-NC-RFQ / SERVICIO DE IMPLEMENTACIÓN DE EJEMPLOS PILOTO DE Component 1: MEDICIÓN DE CONSUMO DE Solicitud de Single Stage - One Ejecución 2022-03- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Limited 50,000.00 0.00 AGUA EN POZOS DE cotizaciones Envelope pendiente 03 21 19 National Level PRODUCCIÓN UBICADOS EN EL ÁMBITO DE ICA A TRAVÉS FLUJÓMETROSELECTROMÁG NETICOS Y DE TURBINA. PE-ANA-248252-NC-RFQ Component 1: / CONDUCTOR DE Solicitud de Single Stage - One Ejecución 2022-03- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,000.00 0.00 VEHICULO 02 MONITOREO cotizaciones Envelope pendiente 03 21 19 National Level DE ACUIFEROS SELECCIONADOS PE-ANA-248250-NC-RFQ Component 1: / CONDUCTOR 01 Solicitud de Single Stage - One Ejecución 2022-03- 2022-03- 2022-07- IBRD / 87400 Consolidating IWRM at the Posterior Limited 12,000.00 0.00 MONITOREO DE ACUIFEROS cotizaciones Envelope pendiente 03 16 14 National Level SELECCIONADOS PE-ANA-248201-NC-RFQ / SERVICIO DE SOCIABILIZACION DE LA Component 1: ACTIVIDAD SUMINISTRO, Solicitud de Single Stage - One Ejecución 2022-03- 2022-03- 2022-04- IBRD / 87400 Consolidating IWRM at the Posterior Limited 10,000.00 0.00 INSTALACION DE cotizaciones Envelope pendiente 08 21 20 National Level FLUJOMETROS Y SISTEMAS DE TELEMTERIA EN LOS AMBITOS DE ICA PE-ANA-236182-NC-RFQ Component 1: / NIVELACIÓN DE Solicitud de Single Stage - One Ejecución 2022-03- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Limited 15,000.00 0.00 PRECISIÓN DE 99 POZOS EN cotizaciones Envelope pendiente 03 21 19 National Level LOS ÁMBITOS DE ICA VILLACURÍ Y LANCHAS PE-ANA-236181-NC-RFQ Component 1: / NIVELACIÓN PRECISIÓN Solicitud de Single Stage - One Ejecución 2022-03- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Limited 15,000.00 0.00 DE 47 PIEZÓMETROS cotizaciones Envelope pendiente 03 21 19 National Level UBICADOS EN EL ÁMBITO DE TACNA CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Process Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SBCC 002 ANA MGRH / CONSULTORIA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TECNICOS PARA CONSTRUCCION DE 200 Component 1: Selección basada 2018-06- 2018-06- 2018-06- 2018-06- 2018-06- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2018-07- 2018-07- 2018-10- ESTRUCTURAS DE CONTROL IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 125,000.00 0.00 Cancelado 01 13 08 18 23 10 08 12 11 26 13 31 14 Y MEDICION DE AGUA EN National Level costo BLOQUES DE RIEGO EN DIECIOCHO SECTORES HIDRAULICO DE LA ZONA CENTRO DE LA COSTA DEL PERU SBCC 003 2018 ANA PGIRH / CONSULTORÍA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS PARA Component 1: Selección basada CONSTRUCCIÓN DE 274 2018-06- 2018-06- 2018-06- 2018-07- 2018-08- 2018-08- 2018-10- 2018-11- 2019-02- IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 148,931.00 0.00 Cancelado ESTRUCTURAS DE 15 25 20 23 07 16 29 16 14 National Level costo MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN DOCE (12) SECTORES HIDRÁULICOS DE LA ZONA NORTE DE LA COSTA DEL PERÚ SBCC 001 ANA PGIRH / FORMULACIÓN DE LOS Component 2: Improving Selección basada Open - 2018-06- 2018-08- 2018-06- 2018-07- 2018-10- 2018-10- 2018-10- 2018-11- 2020-11- PLANES DE GESTIÓN DE IBRD / 87400 WRM in Selected Pilot River Previa en calidad y 5,955,217.00 0.00 Cancelado International 01 08 06 11 08 19 26 27 26 RECURSOS HDRICOS EN Basins costo CUATRO CUENCAS SBCC 004 2018 ANA PGIRH / CONSULTORIA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS PARA Component 1: Selección basada CONSTRUCCIÓN DE 337 2018-07- 2018-07- 2018-07- 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- 2019-01- IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 155,680.00 0.00 Cancelado ESTRUCTURAS DE 05 17 11 08 15 12 19 27 05 03 National Level costo MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN TREINTA (30) SECTORES HIDRÁULICOS DE LA ZONA SUR DE LA COSTA DEL PERÚ SBC 001 2018 ANA PGIRH BM / ESTUDIO DE LÍNEA Component 3: General Selección basada 2018-07- 2018-08- 2018-07- 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- 2018-09- 2018-10- 2018-09- 2018-10- 2018-12- BASE DEL PIP 302961 IBRD / 87400 Posterior Open - National 88,459.00 99,407.20 Firmado Project Adminstration en calidad 23 08 25 12 22 11 24 14 05 17 18 28 19 27 GESTIÓN INTEGRADA DE LOS RECURSOS HÍDRICOS EN DIEZ CUENCAS SBCC 005 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN DE Component 2: Improving Selección basada Open - 2018-08- 2018-10- 2018-09- 2018-10- 2018-09- 2019-03- 2018-10- 2019-04- 2018-10- 2019-05- 2018-10- 2019-07- 2018-11- 2019-07- 2020-11- RECURSOS HÍ DRICOS EN IBRD / 87400 WRM in Selected Pilot River Previa en calidad y 1,809,400.00 2,537,766.50 Firmado International 22 03 06 11 16 06 16 08 21 09 24 24 13 26 02 DOS CUENCAS PILOTO DE Basins costo LA VERTIENTE DEL ATLÁNTICO: MAYO Y MANTARO SBCC 006 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN DE Component 2: Improving Selección basada RECURSOS HIDRICOS EN Open - 2018-08- 2018-10- 2018-09- 2018-10- 2018-09- 2019-03- 2018-10- 2019-04- 2018-10- 2019-05- 2018-10- 2019-07- 2018-11- 2020-05- IBRD / 87400 WRM in Selected Pilot River Previa en calidad y 2,151,920.00 0.00 En ejecución DOS CUENCAS PILOTO DE International 22 03 06 11 16 06 16 08 21 09 24 24 13 06 Basins costo LA VERTIENTE DEL ATLÁNTICO: PAMPAS- APURIMAC Y URUBAMBA- VILCANOTA SBCC 007 2018 ANA PGIRH BM / SUPERVISIÓN DE LA PERFORACIÓN E Component 1: Selección basada 2018-09- 2018-09- 2018-10- 2018-09- 2018-10- 2018-10- 2018-10- 2018-11- 2019-03- INSTALACIÓN DE 58 IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 236,142.00 0.00 Cancelado 07 08 12 25 23 26 30 15 14 PIEZOMETROS EN LOS National Level costo ACUIFEROS DE ICA Y TACNA: LOTE 01 ICA Y LOTE 02 TACNA SCC 001 2018 ANA PGIRH BM / SERVICIO DE ASESORÍA Component 1: Selección basada 2019-01- 2019-01- 2019-02- 2019-03- 2019-05- EN LA EJECUCIÓN DE LAS IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Limited 190,000.00 0.00 Cancelado 04 18 17 24 08 PERFORACIONES EN LA National Level de consultores REGIÓN DE ICA Y TACNA SBCC 001 2019 ANA PGIRH BM / SUPERVISION PARA EL SUMINISTRO, INSTALACIÓN, Component 1: Selección basada 2019-02- 2019-04- 2019-02- 2019-04- 2019-03- 2019-07- 2019-04- 2019-08- 2019-05- 2019-08- 2019-05- 2019-08- 2019-06- 2020-01- PUESTA EN IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 326,071.00 0.00 En ejecución 11 05 16 05 31 03 28 02 08 09 18 19 13 09 FUNCIONAMIENTO Y National Level costo CAPACITACIÓN DE LA INSTRUMENTACIÓN PARA LA SEGURIDAD DE OCHO PRESAS SCC 001 2019 ANA PGIRH BM / SERVICIO DE Component 2: Improving Selección basada 2019-04- 2019-04- 2019-06- 2019-07- 2019-08- 2020-08- CONSULTORIA PARA LA IBRD / 87400 WRM in Selected Pilot River Posterior en calificaciones Open - National 164,180.00 0.00 Cancelado 05 26 09 09 13 12 IMPLEMENTACIÓN DEL Basins de consultores PLAN DE DESARROLLO DE CAPACIDADES SBCC 003 2019 ANA PGIRH BM / SERVICIO DE Component 1: Selección basada 2019-04- 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-11- CONSULTORIA PARA LA IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 126,453.73 0.00 En ejecución 01 17 15 06 27 11 25 17 14 IMPLEMENTACION DE LA National Level costo FASE 0 - GOBIERNO DE DATOS PE-ANA-121030-CS-QCBS / SERVICIO DE CONSULTORÍA PARA LA PROMOCIÓN E Component 2: Improving Selección basada IMPLEMENTACIÓN DE 2019-09- 2021-07- 2019-09- 2021-08- 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2022-03- IBRD / 87400 WRM in Selected Pilot River Posterior en calidad y Open - National 1,399,406.25 0.00 En ejecución MECANISMOS DE 19 27 24 11 21 20 29 13 23 12 Basins costo FINANCIAMIENTO DE PROGRAMAS Y PROYECTOS DE LOS PLANES DE GESTIÓN INTEGRADA DE RECURSOS HÍDRICOS DE CUENCA PE-ANA-161088-CS-QCBS / SUPERVISION DEL SUMINISTRO, INSTALACIÓN PUESTA EN Component 1: Selección basada Open - 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2020-09- 2020-10- 2021-10- FUNCIONAMIENTO Y IBRD / 87400 Consolidating IWRM at the Posterior en calidad y 500,000.00 0.00 Cancelado International 12 03 16 14 13 17 22 22 CAPACITACIÓN DE National Level costo SISTEMAS MECANIZADOS DE AFOROS, PASARELAS DE AFOROS Y WINCHAS DE AFOROS PE-ANA-165654-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada 2020-11- 2020-11- 2021-01- 2021-02- 2021-03- 2021-08- CONSTRUCCIÓN DE 131 IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 80,600.00 0.00 Cancelado 02 23 06 05 12 09 ESTRUCTURAS DE National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN PIURA PE-ANA-165655-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada CONSTRUCCIÓN DE 95 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2021-03- IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 58,449.43 0.00 Cancelado ESTRUCTURAS DE 01 22 05 04 09 08 National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN LAMBAYEQUE PE-ANA-165656-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada CONSTRUCCIÓN DE 80 2020-06- 2020-06- 2020-08- 2020-09- 2020-10- 2021-03- IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 49,220.57 0.00 Cancelado ESTRUCTURAS DE 01 22 05 04 09 08 National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN LA LIBERTAD PE-ANA-165657-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada CONSTRUCCIÓN DE 73 2020-05- 2021-03- 2020-05- 2021-03- 2020-07- 2021-05- 2020-08- 2021-07- 2020-09- 2021-08- 2021-02- IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 44,913.77 109,794.54 Firmado ESTRUCTURAS DE 01 23 22 25 05 12 04 02 08 02 05 National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN ANCASH Page 7 PE-ANA-165658-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada CONSTRUCCIÓN DE 73 2020-05- 2020-05- 2020-07- 2020-08- 2020-09- 2021-02- IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 44,913.77 0.00 Cancelado ESTRUCTURAS DE 01 22 05 04 08 05 National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN ANCASH PE-ANA-165659-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada 2020-05- 2021-04- 2020-05- 2021-04- 2020-07- 2021-08- 2020-08- 2021-09- 2020-09- 2021-09- 2021-02- CONSTRUCCIÓN DE 87 IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 53,527.37 116,890.84 Firmado 01 15 22 26 05 19 04 07 08 29 05 ESTRUCTURAS DE National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN LIMA PE-ANA-165660-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada 2020-11- 2020-11- 2021-01- 2021-02- 2021-03- 2021-08- CONSTRUCCIÓN DE 107 IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 65,832.51 0.00 Cancelado 02 23 06 05 12 09 ESTRUCTURAS DE National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN ICA PE-ANA-165661-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada CONSTRUCCIÓN DE 190 2020-11- 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 116,898.86 0.00 Cancelado ESTRUCTURAS DE 02 23 06 05 12 08 National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN AREQUIPA SBCC 002 2019 ANA PGIRH BM / SUPERVISIÓN PARA EL SUMINISTRO, INSTALACIÓN, Component 1: Selección basada 2019-02- 2019-02- 2019-04- 2019-05- 2019-05- 2019-06- 2019-07- 2021-01- PUESTA EN IBRD / 87400 Consolidating IWRM at the Previa en calidad y Open - National 629,981.44 0.00 Cancelado 22 27 08 08 13 05 06 03 FUNCIONAMIENTO Y National Level costo CAPACITACIÓN DE 153 ESTACIONES HIDROLÓGICAS CON 33 EHCA PE-ANA-242466-CS-QCBS / SERVICIO DE CONSULTORIA PARA FORTALECER LAS Component 2: Improving Selección basada 2021-07- 2021-07- 2021-08- 2021-07- 2021-08- 2021-08- 2021-09- 2021-09- 2021-10- 2021-11- 2022-11- CAPACIDADES DE LOS IBRD / 87400 WRM in Selected Pilot River Posterior en calidad y Open - National 322,000.00 0.00 En ejecución 15 23 05 26 20 17 17 27 12 07 07 MIEMBROS DE LOS Basins costo CONSEJOS DE RECURSOS HÍDRICOS DE LAS CUENCAS SELECCIONADAS DE LA VERTIENTE DEL PACÍFICO PE-ANA-251936-CS-QCBS / SUPERVISIÓN DE LA CONSTRUCCIÓN DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN 5 Component 1: Selección basada REGIONES DE LA COSTA 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-01- 2022-02- 2022-03- 2022-10- IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 550,000.00 0.00 Cancelado DEL PERU 10 10 01 14 12 11 15 22 18 National Level costo ITEM 1: REGION LAMBAYEQUE (95), ITEM 2: REGION AREQUIPA (190), ITEM 3: REGION PIURA (111), ITEM 4: REGION ICA (107), ITEM 5: REGION LA LIBERTAD (80) PE-ANA-254267-CS-CQS / SUPERVISIÓN DE LA Component 1: Selección basada CONSTRUCCIÓN DE 95 2021-09- 2021-09- 2021-10- 2021-09- 2021-10- 2021-10- 2021-10- 2021-11- 2021-11- 2021-12- 2022-05- IBRD / 87400 Consolidating IWRM at the Posterior en calificaciones Open - National 109,500.00 119,615.97 Firmado ESTRUCTURAS DE 22 22 06 27 11 29 18 29 04 10 03 National Level de consultores MEDICIÓN DE AGUA EN LA REGIÓN LAMBAYEQUE PE-ANA-254268-CS-QCBS / SUPERVISIÓN DE LA Component 1: Selección basada CONSTRUCCIÓN DE 190 2021-09- 2021-09- 2021-10- 2021-10- 2021-10- 2021-11- 2021-11- 2021-11- 2021-12- 2022-08- IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 183,115.00 0.00 En ejecución ESTRUCTURAS DE 22 29 06 11 16 13 20 27 14 11 National Level costo MEDICIÓN DE AGUA EN LA REGIÓN AREQUIPA PE-ANA-254270-CS-QCBS / SUPERVISIÓN DE LA Component 1: Selección basada 2021-09- 2021-09- 2021-10- 2021-10- 2021-10- 2021-12- 2021-11- 2022-01- 2021-11- 2022-01- 2021-11- 2021-12- 2022-07- CONSTRUCCIÓN DE 111 IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 127,815.00 0.00 En ejecución 22 29 06 11 16 01 13 12 20 26 27 14 12 ESTRUCTURAS DE National Level costo MEDICIÓN DE AGUA EN LA REGIÓN PIURA PE-ANA-254272-CS-QCBS / SUPERVISIÓN DE LA Component 1: Selección basada 2021-09- 2021-09- 2021-10- 2021-10- 2021-10- 2021-12- 2021-11- 2022-02- 2021-11- 2021-11- 2021-12- 2022-07- CONSTRUCCIÓN DE 107 IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 127,015.00 0.00 En ejecución 22 29 06 11 16 30 13 07 20 27 14 12 ESTRUCTURAS DE National Level costo MEDICIÓN DE AGUA EN LA REGIÓN ICA PE-ANA-254274-CS-QCBS / SUPERVISIÓN DE LA Component 1: Selección basada CONSTRUCCIÓN DE 80 2021-09- 2021-09- 2021-10- 2021-10- 2021-10- 2022-01- 2021-11- 2021-11- 2021-11- 2021-12- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 106,650.00 0.00 En ejecución ESTRUCTURAS DE 22 29 06 11 16 17 13 20 27 14 12 National Level costo MEDICIÓN DE AGUA EN LA REGIÓN LA LIBERTAD PE-ANA-272272-CS-QCBS / SUPERVISIÓN DE CAMPO Component 1: Selección basada DEL SUMINISTRO, Ejecución 2022-01- 2022-02- 2022-03- 2022-04- 2022-05- 2022-07- 2022-08- 2023-01- IBRD / 87400 Consolidating IWRM at the Posterior en calidad y Open - National 100,000.00 0.00 INSTALACIÓN DE pendiente 24 14 30 27 27 01 05 02 National Level costo FLUJÓMETROS Y SISTEMAS DE TELEMETRÍA EN LOS ÁMBITOS DE ICA Y TACNA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Process Draft Negotiated Description Component Review Type Method Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Status Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCI-001 / III Component 3: General 2017-12- 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- 2018-04- 2018-10- Administración General del IBRD / 87400 Previa Individual Open 360,000.00 324,000.00 Firmado Project Adminstration 28 31 12 12 15 24 18 06 15 Proyecto III.a Director Ejecutivo SCI 003 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-05- 2018-05- 2018-05- 2022-11- IBRD / 87400 Previa Individual Limited 202,500.00 0.00 Cancelado Especialista en Project Adminstration 22 30 23 29 31 06 Adquisiciones SCI 004 ANA PGIRH / ESPECIALISTA EN ADMINISTRACIÓN DE Component 3: General 2018-05- 2018-06- 2018-06- 2018-06- 2022-05- IBRD / 87400 Previa Individual Limited 192,000.00 0.00 Cancelado RECURSOS HÍDRICOS - Project Adminstration 25 01 08 12 22 COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 005 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2022-05- ESPECIALISTA EN AGUA IBRD / 87400 Posterior Individual Limited 192,000.00 13,730.67 Firmado Project Adminstration 28 28 04 27 11 29 13 29 23 SUBTERRÁNEAS SCI 009 ANA PGIRH / Component 3: General 2018-05- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2021-05- IBRD / 87400 Posterior Individual Limited 72,000.00 7,292.52 Firmado GEOGRAFO - SIG Project Adminstration 28 09 04 11 11 14 13 29 28 SCI 010 ANA PGIRH / Component 3: General 2018-05- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2021-05- IBRD / 87400 Posterior Individual Limited 71,460.00 5,955.00 Firmado ASISTENTE TECNICO Project Adminstration 25 25 01 26 08 01 12 01 27 TALLERES SCI 011 ANA PGIRH / Component 2: Improving 2018-05- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2022-05- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 184,140.00 19,664.33 Firmado 28 15 04 18 11 06 13 06 23 CUENCA PILOTO Basins URUBAMBA SCI 012 ANA PGIRH / Component 2: Improving 2018-05- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2022-05- 2018-10- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 184,140.00 19,664.33 Finalizado 28 15 04 18 11 06 13 06 23 04 CUENCA PILOTO MAYO Basins SCI 013 ANA PGIRH / Component 2: Improving 2018-05- 2018-07- 2018-06- 2018-07- 2018-06- 2018-07- 2018-06- 2018-07- 2022-11- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 184,140.00 15,489.35 Firmado 28 16 04 20 11 25 13 30 19 CUENCA PILOTO PAMPAS Basins SCI 014 ANA PGIRH / Component 2: Improving 2018-05- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2022-05- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 184,140.00 17,105.99 Firmado 28 15 04 18 11 05 13 06 23 CUENCA PILOTO MANTARO Basins SCI 017 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2022-06- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,772.45 Firmado RECURSOS HIDRICOS 04 27 11 27 19 01 22 11 01 Basins CUENCA PILOTO MAYO SCI 016 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-06- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,630.53 Firmado RECURSOS HIDRICOS 04 14 11 14 19 20 22 11 01 Basins CUENCA PILOTO PAMPAS SCI 018 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-06- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,763.15 Firmado RECURSOS HIDRICOS 04 14 11 14 19 24 22 11 01 Basins CUENCA PILOTO MANTARO SCI 024 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2022-11- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,681.43 Firmado AMBIENTAL CUENCA 04 27 11 27 19 02 22 11 28 Basins PILOTO MAYO SCI 025 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-11- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,681.43 Firmado AMBIENTAL CUENCA 04 22 11 22 19 25 22 11 28 Basins PILOTO PAMPAS SCI 026 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-11- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,434.04 Firmado AMBIENTAL CUENCA 04 22 11 22 19 25 22 11 28 Basins PILOTO MANTARO SCI 027 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-06- 2018-06- 2022-11- ASESOR EN GESTIÓN DE IBRD / 87400 Posterior Individual Limited 286,200.00 0.00 Cancelado Project Adminstration 25 01 08 12 18 RECURSOS HÍDRICOS SCI 029 ANA PGIRH / Component 3: General 2018-05- 2018-07- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2022-11- IBRD / 87400 Posterior Individual Limited 64,800.00 4,119.20 Firmado SECRETARIA DE LA Project Adminstration 29 29 06 02 13 08 15 29 21 JEFATURA SCI 031 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2022-11- IBRD / 87400 Posterior Individual Limited 54,000.00 3,432.67 Firmado CHOFER DE JEFATURA Project Adminstration 29 29 06 15 13 24 15 29 21 SCI 035 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2021-05- IBRD / 87400 Posterior Individual Limited 36,000.00 2,747.18 Firmado ASISTENTE SOPORTE Project Adminstration 29 29 06 13 13 14 15 28 30 TECNICO SCI 036 ANA PGIRH / Component 3: General 2018-05- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-11- SECRETARIA DE IBRD / 87400 Posterior Individual Limited 54,000.00 2,574.50 Firmado Project Adminstration 29 20 06 26 13 28 15 01 21 ADMINISTRACION Y FINANZAS SCI 037 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2018-08- 2022-11- CHOFER DE IBRD / 87400 Posterior Individual Limited 48,600.00 3,139.64 Firmado Project Adminstration 29 29 06 30 13 08 15 29 21 ADMINISTRACIÓN Y FINANZAS SCI 038 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2021-05- ASISTENTE DE IBRD / 87400 Posterior Individual Limited 103,500.00 8,625.00 Firmado Project Adminstration 29 29 06 26 13 01 15 01 30 ADQUISICIONES 1 SCI 040 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2018-09- 2022-11- IBRD / 87400 Posterior Individual Limited 48,600.00 2,354.73 Firmado CHOFER DE ADQUISICIONES Project Adminstration 29 29 06 23 13 07 15 24 21 SCI 042 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2018-09- 2021-05- IBRD / 87400 Posterior Individual Limited 67,500.00 6,059.71 Firmado ASISTENTE DE Project Adminstration 28 28 04 24 11 04 13 17 28 CONTABILIDAD SCI 043 ANA PGIRH / Component 3: General 2018-05- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2022-11- IBRD / 87400 Posterior Individual Limited 155,250.00 7,607.80 Firmado ESPECIALISTA FINANCIERO Project Adminstration 28 17 04 18 11 26 13 28 19 SCI 044 ANA PGIRH / Component 3: General 2018-05- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2022-11- IBRD / 87400 Posterior Individual Limited 194,076.00 12,680.56 Firmado ESPECIALISTA EN Project Adminstration 28 24 04 24 11 29 13 29 19 TESORERIA SCI 045 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2018-08- 2021-05- IBRD / 87400 Posterior Individual Limited 67,500.00 6,802.54 Firmado ASISTENTE DE TESORERIA Project Adminstration 29 29 06 30 13 08 15 29 30 SCI 033 ANA PGIRH / Component 3: General 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2022-11- ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 155,250.00 7,378.62 Firmado Project Adminstration 04 11 11 13 18 24 22 24 28 PRESUPUESTO SCI 002 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-05- 2018-05- 2018-05- 2018-11- Especialista en IBRD / 87400 Previa Individual Limited 243,000.00 0.00 Cancelado Project Adminstration 22 29 23 29 31 09 Administración y Finanzas SCI 053 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- ESPECIALISTA EN IBRD / 87400 Previa Individual Open 243,000.00 13,500.00 Firmado Project Adminstration 14 21 02 22 02 09 03 10 30 ADMINISTRACIÓN Y FINANZAS SCI 054 2018 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- ESPECIALISTA EN IBRD / 87400 Previa Individual Open 202,500.00 9,125.00 Firmado Project Adminstration 14 21 02 03 02 22 03 22 30 ADQUISICIONES SCI 007-ANA-PGIRH / Component 3: General 2018-05- 2018-06- 2018-06- 2018-06- 2022-05- IBRD / 87400 Posterior Individual Direct 192,000.00 0.00 Cancelado ESPECIALISTA AMBIENTAL Project Adminstration 25 04 06 08 18 SCI 028 2018 ANA PGIRH Component 3: General 2018-07- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2022-12- IBRD / 87400 Posterior Individual Limited 192,000.00 13,687.88 Firmado BM / ESPECIALISTA Project Adminstration 19 08 20 10 30 19 31 29 30 AMBIENTAL Page 8 SCI 030 2018 ANA PGIRH BM / ESPECIALISTA EN ADMINISTRACIÓN DE Component 3: General 2018-07- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 Posterior Individual Limited 192,000.00 12,000.00 Firmado RECURSOS HÍDRICOS - Project Adminstration 19 20 25 30 01 31 01 30 COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 006 2018 ANA PGIRH Component 3: General 2018-07- 2018-08- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2018-11- 2022-12- BM / ASESOR EN GESTIÓN IBRD / 87400 Previa Individual Limited 286,200.00 15,900.00 Firmado Project Adminstration 19 02 20 07 30 03 31 05 30 DE RECURSOS HÍDRICOS SCI 008 2018 ANA PGIRH Component 3: General 2018-07- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2022-12- BM / ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 192,000.00 14,155.09 Firmado Project Adminstration 19 25 20 25 30 29 31 29 30 GESTIÓN DE RECURSOS HÍDRICOS SCI 060 2018 ANA PGIRH / Component 2: Improving ESPECIALISTA EN SISTEMAS 2018-07- 2018-09- 2018-07- 2018-09- 2018-07- 2018-09- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,434.04 Firmado DE INFORMACIÓN CUENCA 19 14 20 14 30 25 31 11 30 Basins PILOTO MANTARO SCI 061 2018 ANA PGIRH Component 2: Improving BM / ESPECIALISTA EN 2018-07- 2018-09- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,339.10 Firmado SISTEMAS DE INFORMACIÓN 19 25 20 25 30 01 31 12 30 Basins CUENCA PILOTO PAMPAS SCI 062 2018 ANA PGIRH Component 2: Improving BM / ESPECIALISTA EN 2018-07- 2018-09- 2018-07- 2020-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,101.27 Firmado SISTEMAS DE INFORMACIÓN 19 28 20 28 30 05 31 12 30 Basins CUENCA PILOTO MAYO SCI 063 2018 ANA PGIRH Component 2: Improving BM / ASISTENTE TÉCNICO 2018-07- 2018-10- 2018-07- 2018-10- 2018-07- 2018-10- 2018-07- 2018-11- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 2,887.04 Firmado EN SISTEMAS DE 19 23 20 23 30 25 31 09 30 Basins INFORMACIÓN CUENCA PILOTO URUBAMBA SCI 064 2018 ANA PGIRH Component 2: Improving BM / ASISTENTE TÉCNICO 2018-07- 2018-07- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,348.05 Firmado EN SISTEMAS DE 19 19 20 28 30 05 31 16 30 Basins INFORMACIÓN CUENCA PILOTO MANTARO SCI 065 2018 ANA PGIRH Component 2: Improving BM / ASISTENTE TÉCNICO 2018-07- 2018-07- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,576.89 Firmado EN SISTEMAS DE 19 19 20 28 30 02 31 11 30 Basins INFORMACIÓN CUENCA PILOTO MAYO SCI 034 2018 ANA PGIRH Component 2: Improving BM / ASISTENTE TÉCNICO 2018-07- 2018-09- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,198.58 Firmado EN SISTEMAS DE 19 18 20 25 30 02 31 12 30 Basins INFORMACIÓN CUENCA PILOTO PAMPAS SBCC 066 2018 ANA PGIRH Component 1: 2018-08- 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-09- 2022-12- 2018 / ESPECIALISTA EN IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 192,000.00 12,000.00 Firmado 28 28 30 07 01 28 05 28 30 HIDROMETRIA National Level SCI 015 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2019-02- 2020-02- 2019-02- 2020-02- 2019-02- 2020-03- 2019-02- 2020-03- 2020-02- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 16,119.48 7,099.38 Firmado RECURSOS HIDRICOS 08 20 15 24 20 02 28 02 28 Basins CUENCA PILOTO URUBAMBA SCI 056 2018 ANA PGIRH Component 2: Improving 2019-02- 2019-04- 2019-02- 2019-04- 2019-02- 2019-04- 2019-02- 2019-06- 2020-02- BM / COORDINADOR IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 40,920.00 5,904.71 Firmado 08 17 15 24 20 29 28 28 28 TECNICO CUENCA Basins URUBAMBA SCI 057 2018 ANA PGIRH Component 2: Improving 2019-02- 2019-07- 2019-02- 2019-07- 2019-02- 2019-07- 2019-02- 2019-07- 2020-02- BM / COORDINADOR IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 40,920.00 5,511.15 Firmado 08 12 15 18 20 24 28 31 28 TÉCNICO CUENCA MAYO Basins SCI 023 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2019-04- 2020-02- 2019-04- 2020-02- 2019-04- 2020-03- 2019-04- 2020-03- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 33,600.00 9,939.13 Firmado AMBIENTAL CUENCA 05 18 15 24 20 02 30 02 29 Basins PILOTO URUBAMBA SCI 046 ANA PGIRH / Component 3: General 2019-04- 2021-11- 2019-04- 2021-11- 2019-04- 2021-12- 2019-04- 2021-12- 2020-04- ESPECIALISTA EN CONTROL IBRD / 87400 Posterior Individual Limited 34,500.00 3,289.04 Firmado Project Adminstration 05 10 15 19 20 02 30 07 29 PATRIMONIAL Y ALMACEN SCI 055 2018 ANA PGIRH Component 3: General 2019-04- 2019-09- 2019-05- 2020-01- 2019-05- 2019-05- 2020-05- BM / ESPECIALISTA EN IBRD / 87400 Posterior Individual Open 54,000.00 0.00 En ejecución Project Adminstration 05 20 15 15 20 31 24 ADMINISTRACIÓN Y FINANZAS SCI 071 2018 ANA PGIRH Component 3: General 2019-04- 2019-09- 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 87400 Previa Individual Open 55,880.63 0.00 Bajo Revision BM / JEFE DE PROYECTO Project Adminstration 05 20 20 25 09 08 SCI 059 2018 ANA PGIRH / Component 2: Improving ESPECIALISTA EN SISTEMAS 2019-04- 2020-02- 2019-04- 2020-02- 2019-04- 2020-03- 2019-05- 2020-03- 2020-05- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 33,600.00 9,939.13 Firmado DE INFORMACIÓN CUENCA 05 17 20 21 25 02 05 02 04 Basins PILOTO URUBAMBA SCI 058 2018 ANA PGIRH Component 1: BM / CONSULTOR EN 2019-04- 2019-04- 2019-04- 2019-04- 2019-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 6,000.00 0.00 Cancelado SEGURIDAD DE PRESAS - 05 15 20 30 30 National Level SALVAGUARDAS BANCO MUNDIAL PE-ANA-116127-CS-INDV / ESTUDIO DE INGENIERÍA DE DETALLE DE Component 1: TELECOMUNICACIONES 2019-05- 2019-07- 2019-08- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 13,433.00 0.00 Cancelado PARA LA TRANSMISIÓN DE 31 19 09 13 12 National Level DATOS DE 396 PUNTOS DE MEDICIÓN DE NIVEL EN BLOQUES DE RIEGO PE-ANA-121010-CS-INDV / SUPERVISIÓN DE LA CONTRATACIÓN - OBRAS CIVILES PARA LA IMPLEMENTACIÓN DEL CENTRO DE DATOS, Component 1: 2019-10- 2020-02- 2019-11- 2020-02- 2019-11- 2020-02- 2019-12- 2020-02- 2020-06- LABORATORIO DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 23,880.00 24,349.99 Firmado 01 04 20 03 25 26 05 26 02 INSTRUMENTACIÓN, National Level CENTRO DE MONITOREO Y MODELAMIENTO DE RECURSOS HÍDRICOS DE LA AUTORIDAD NACIONAL DEL AGUA PE-ANA-122155-CS-INDV Component 2: Improving / ASISTENTE DE 2019-10- 2020-02- 2019-10- 2020-02- 2019-10- 2020-02- 2019-10- 2020-03- 2020-10- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 7,099.38 Firmado COMUNICACIONES CUENCA 01 17 06 20 21 27 31 02 30 Basins URUBAMBA PE-ANA-122156-CS-INDV Component 2: Improving / ASISTENTE DE 2019-10- 2020-02- 2019-10- 2020-01- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 7,099.38 Firmado COMUNICACIONES CUENCA 01 18 06 29 21 02 31 02 30 Basins MAYO PE-ANA-122157-CS-INDV Component 2: Improving 2019-10- 2020-02- 2019-10- 2020-01- 2019-10- 2020-02- 2019-10- 2020-03- 2020-10- / ESPECIALISTA SOCIAL IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 33,600.00 9,231.08 Firmado 01 18 06 30 21 28 31 02 30 AMBIENTAL CUENCA MAYO Basins PE-ANA-122158-CS-INDV Component 2: Improving 2019-10- 2020-02- 2019-10- 2020-01- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- / ESPECIALISTA SISTEMA DE IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 33,600.00 9,939.13 Firmado 01 18 06 29 21 02 31 02 30 INFORMACIÓN CUENCA Basins MAYO PE-ANA-122159-CS-INDV Component 2: Improving / ASISTENTE DE 2019-10- 2020-02- 2019-10- 2020-02- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 7,101.30 Firmado COMUNICACIÓN CUENCA 01 18 06 21 21 02 31 03 30 Basins PAMPAS PE-ANA-122160-CS-INDV Component 2: Improving 2019-10- 2020-02- 2019-10- 2020-02- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- / COORDINADOR TÉCNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 134,220.00 61,721.04 Firmado 01 18 06 21 21 02 31 02 30 CUENCA MANTARO Basins PE-ANA-122161-CS-INDV Component 2: Improving / ASISTENTE DE 2019-10- 2020-02- 2019-10- 2020-02- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 7,101.30 Firmado COMUNICACIÓN CUENCA 01 18 06 21 21 02 31 02 30 Basins MANTARO SCI 047 ANA PGIRH / Component 3: General 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 13,500.00 0.00 Cancelado TECNICO DE ARCHIVO Project Adminstration 05 15 20 30 29 SCI 048 ANA PGIRH / Component 3: General 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE EN SERVICIOS IBRD / 87400 Posterior Individual Limited 13,500.00 0.00 Cancelado Project Adminstration 05 15 20 30 29 GENERALES Y ARCHIVO SCI 069 2018 ANA PGIRH Component 3: General 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- BM / TECNICO IBRD / 87400 Posterior Individual Limited 8,400.00 0.00 Cancelado Project Adminstration 05 15 20 30 29 ADMINISTRATIVO DE JEFATURA SCI 049 ANA PGIRH / Component 2: Improving 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 16,119.48 0.00 Cancelado 05 15 20 30 29 ADMINISTRATIVO CUENCA Basins PILOTO URUBAMBA SCI 050 ANA PGIRH / Component 2: Improving 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 16,119.48 0.00 Cancelado 05 15 20 30 29 ADMINISTRATIVO CUENCA Basins PILOTO MAYO SCI 051 ANA PGIRH / Component 2: Improving 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 16,119.48 0.00 Cancelado 05 15 20 30 29 ADMINISTRATIVO CUENCA Basins PILOTO PAMPAS SCI 052 ANA PGIRH / Component 3: General 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE IBRD / 87400 Posterior Individual Limited 16,119.48 0.00 Cancelado Project Adminstration 05 15 20 30 29 ADMINISTRATIVO CUENCA PILOTO MANTARO SCI 020 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 0.00 Cancelado CULTURA DEL AGUA 05 15 20 30 29 Basins CUENCA PILOTO MAYO SCI 021 ANA PGIRH / Component 2: Improving ASISTENTE TÉCNICO 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 0.00 Cancelado CULTURA DEL AGUA 05 15 20 30 29 Basins CUENCA PILOTO PAMPAS SCI 019 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 0.00 Cancelado CULTURA DEL AGUA 05 15 20 30 29 Basins CUENCA PILOTO URUBAMBA SCI 022 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 0.00 Cancelado CULTURA DEL AGUA 05 15 20 30 29 Basins CUENCA PILOTO MANTARO SCI 070 2018 ANA PGIRH Component 3: General 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- BM / ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 Cancelado Project Adminstration 05 15 20 30 29 INFORMATICA PE-ANA-122164-CS-INDV Component 3: General Ejecución 2019-10- 2019-10- 2019-10- 2019-10- 2020-10- / ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 Project Adminstration pendiente 01 16 21 31 30 SISTEMAS DE INFORMACIÓN SCI 067 2018 ANA PGIRH BM / Supervision de la Contratación - Obras Civiles para la Component 1: Implementación de la 2019-04- 2019-04- 2019-04- 2019-04- 2019-10- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 19,387.61 0.00 Cancelado Infraestructura del Centro 05 15 20 30 27 National Level de Datos, Laboratorio de Instrumentación, Centro de Monitoreo Y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-130323-CS-INDV / SUPERVISOR 01 DE LA ELABORACIÓN DE Component 1: EXPEDIENTES TÉCNICOS DE 2019-09- 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-10- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 14,330.00 8,180.28 Firmado ESTRUCTURAS DE 18 23 23 26 26 07 30 14 28 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130324-CS-INDV / SUPERVISOR 02 DE LA ELABORACIÓN DE Component 1: EXPEDIENTES TÉCNICOS DE 2019-09- 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-10- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 14,330.00 8,137.40 Firmado ESTRUCTURAS DE 18 23 23 03 26 07 30 14 28 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130325-CS-INDV / SUPERVISOR 03 DE LA ELABORACIÓN DE Component 1: EXPEDIENTES TÉCNICOS DE 2019-09- 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 14,330.00 6,259.54 Firmado ESTRUCTURAS DE 18 23 23 23 26 07 30 04 28 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ Page 9 PE-ANA-130326-CS-INDV / SUPERVISOR 04 DE LA ELABORACIÓN DE Component 1: EXPEDIENTES TÉCNICOS DE 2019-09- 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-10- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 14,330.00 8,235.45 Firmado ESTRUCTURAS DE 18 23 23 04 26 01 30 14 28 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130328-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 01 Component 1: PARA LA ELABORACIÓN DE 2019-09- 2019-07- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 38,059.71 0.00 En ejecución LOS EXPEDIENTES 05 22 10 11 13 12 National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS TUMBES, SAN LORENZO PE-ANA-130329-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 03 Component 1: PARA LA ELABORACIÓN DE 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-09- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 46,567.17 10,314.88 Firmado LOS EXPEDIENTES 05 22 10 11 11 10 13 10 14 National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTOR HIDRÁULICOS MyBP, SECHURA PE-ANA-130330-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 05 Component 1: PARA LA ELABORACIÓN DE 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 46,567.17 10,314.88 Firmado LOS EXPEDIENTES 05 22 10 11 11 10 13 10 11 National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS OLMOS, MOTUPE, LA LECHE PE-ANA-130331-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 06 PARA LA ELABORACIÓN DE Component 1: 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- LOS EXPEDIENTES IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 50,746.27 10,296.71 Firmado 05 22 10 11 11 30 13 30 11 TÉCNICOS DE National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS CHANCAY- LAMBAYEQUE, CHICAMA PE-ANA-130334-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 10 Component 1: PARA LA ELABORACIÓN DE 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 34,925.38 7,758.27 Firmado LOS EXPEDIENTES 05 22 10 11 11 10 13 10 12 National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS CASMA HUARMEY PE-ANA-130335-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 11 PARA LA ELABORACIÓN DE Component 1: 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- LOS EXPEDIENTES IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 38,059.71 7,736.16 Firmado 05 22 10 11 11 10 13 10 12 TÉCNICOS DE National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS FORTALEZA, PATIVILCA, SUPE, HUAURA, CH-HUARAL PE-ANA-130336-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 12 PARA LA ELABORACIÓN DE Component 1: 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-02- LOS EXPEDIENTES IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 11,641.80 10,344.36 Firmado 05 22 10 11 11 27 13 27 10 TÉCNICOS DE National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS CHILLÓN, RIMAC, LURIN, CAÑETE PE-ANA-130337-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 13 Component 1: PARA LA ELABORACIÓN DE 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 46,567.17 10,344.36 Firmado LOS EXPEDIENTES 05 22 10 11 11 10 13 10 11 National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS SAN JUAN, PISCO PE-ANA-130338-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 14 Component 1: PARA LA ELABORACIÓN DE 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-08- 2019-10- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 34,925.38 7,736.16 Firmado LOS EXPEDIENTES 05 22 10 11 15 11 01 10 30 National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS ICA, LA ACHIRANA PE-ANA-130339-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 16 Component 1: PARA LA ELABORACIÓN DE 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 38,059.71 7,692.31 Firmado LOS EXPEDIENTES 05 22 10 11 11 10 13 10 12 National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS OCOÑA, CAMANÁ PE-ANA-132925-CS-INDV / CONSULTORES INDIVIDUALES GRUPO 20 PARA LA ELABORACIÓN DE Component 1: LOS EXPEDIENTES 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 34,925.38 5,157.44 Firmado TÉCNICOS DE 09 22 14 11 15 10 17 10 16 National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS Irrig. EMM, Pta de Bombón, Moquegua, Torata, Locumba, Sama, Uchusuma, Bajo Caplina PE-ANA-132943-CS-INDV Component 1: / ESPECIALISTA EN 2019-09- 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-10- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 44,118.00 5,345.12 Firmado SENSIBILIZACIÓN Y 18 23 23 01 26 01 30 11 28 National Level CAPACITACIÓN 01 PE-ANA-132945-CS-INDV Component 1: / ESPECIALISTA EN 2019-09- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 44,118.00 0.00 En ejecución SENSIBILIZACIÓN Y 18 23 23 26 30 28 National Level CAPACITACIÓN 02 PE-ANA-120995-CS-INDV Component 1: / ESPECIALISTA EN 2019-10- 2019-11- 2019-11- 2019-12- 2020-03- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 44,118.00 0.00 Cancelado SENSIBILIZACIÓN Y 01 20 25 05 04 National Level CAPACITACIÓN 01 PE-ANA-120996-CS-INDV Component 1: / ESPECIALISTA EN 2019-10- 2019-11- 2019-11- 2019-12- 2020-03- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 44,118.00 0.00 Cancelado SENSIBILIZACION Y 01 20 25 05 04 National Level CAPACITACIÓN 02 PE-ANA-130340-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 18 PARA LA ELABORACIÓN DE Component 1: 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- LOS EXPEDIENTES IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 46,567.17 10,314.88 Firmado 05 22 10 11 11 10 13 10 11 TÉCNICOS DE National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS IRRIG. MAJES, STA RITA DE SIGUAS, LA JOYA, VITOR, YURA PE-ANA-130332-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 08 PARA LA ELABORACIÓN DE Component 1: 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- LOS EXPEDIENTES IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 46,567.17 10,314.88 Firmado 05 22 10 11 11 02 13 10 11 TÉCNICOS DE National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS MOCHE, VIRU, CHAO, GUADALUPITO PE-ANA-130333-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 09 Component 1: PARA LA ELABORACIÓN DE 2019-09- 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Open 38,059.71 7,736.16 Firmado LOS EXPEDIENTES 05 22 10 11 11 10 13 10 12 National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS SANTA, NEPEÑA, IRCHIM PE-ANA-135207-CS-INDV Component 3: General 2019-09- 2021-05- 2019-10- 2019-10- 2019-10- 2020-10- / ESPECIALISTA EN IBRD / 87400 Previa Individual Open 45,000.00 0.00 Bajo Revision Project Adminstration 20 19 06 11 14 13 ADQUISICIONES PE-ANA-139763-CS-INDV / Contratación de Consultor Component 1: Internacional para apoyo 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-11- 2019-10- 2019-11- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 11,842.00 11,842.00 Firmado técnico al Taller Análisis de 21 21 28 23 02 23 09 29 27 National Level Modos de fallo potenciales de la presa Poechos PE-ANA-152038-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 17 PARA LA ELABORACIÓN DE Component 1: LOS EXPEDIENTES 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 50,000.00 0.00 En ejecución TÉCNICOS DE 02 10 12 17 27 26 National Level ESTRUCTURAS DE MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS MENOR VALLE DE MAJES Y VALLE SIGUAS QUILCA PE-ANA-157004-CS-INDV / Contratación de un Especialista Internacional Component 1: 2020-01- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- para el diagnóstico de IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 66,823.00 66,382.18 Firmado 31 03 02 03 02 04 02 03 17 situación y análisis de la National Level seguridad de la presa Poechos recrecida, durante el llenado del embalse PE-ANA-155010-CS-INDV / SUPERVISOR 01 DE LA ELABORACIÓN DE Component 1: EXPEDIENTES TÉCNICOS DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-04- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 7,165.00 6,259.54 Firmado ESTRUCTURAS DE 06 04 08 04 09 06 13 07 13 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERU PE-ANA-155004-CS-INDV / GRUPO 19 PARA LA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 34,925.00 0.00 En ejecución 06 04 08 09 13 13 MEDICIÓN DE AGUA EN LOS National Level SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO. PE-ANA-154991-CS-INDV / GRUPO 07 PARA LA ELABORACIÓN DE LOS Component 1: EXPEDIENTES TÉCNICOS DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 33,134.00 0.00 En ejecución ESTRUCTURAS DE 06 04 08 09 14 15 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS ZAÑA Y JEQUETEPEQUE PE-ANA-155862-CS-INDV / GRUPO 02 - PARA Component 1: ELABORACIÓN DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 38,059.00 0.00 En ejecución EXPEDIENTES TÉCNICOS DE 06 04 08 09 13 13 National Level ESTRUCTURAS DE MEDICIÓN DE AGUA. PE-ANA-155863-CS-INDV / GRUPO 15 PARA Component 1: ELABORACIÓN DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-06- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 46,566.00 0.00 En ejecución EXPEDIENTES TÉCNICOS DE 06 04 08 09 13 12 National Level ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-154996-CS-INDV / GRUPO 04 PARA LA ELABORACIÓN DE LOS Component 1: EXPEDIENTES TÉCNICOS DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 38,060.00 0.00 En ejecución ESTRUCTURAS DE 06 04 08 09 13 13 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO PE-ANA-160683-CS-INDV / CONSULTORES ADICIONALES AL GRUPO 07 PARA LA ELABORACIÓN DE Component 1: 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-06- LOS EXPEDIENTES IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 18,400.00 0.00 En ejecución 16 03 18 19 24 08 TÉCNICOS DE National Level ESTRUCTURAS DE MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS ZAÑA Y JEQUETEPEQUE PE-ANA-161048-CS-INDV Component 2: Improving 2020-03- 2020-02- 2020-03- 2020-02- 2020-03- 2020-03- 2020-03- 2023-01- / ESPECIALISTA SOCIAL IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 93,170.00 8,353.32 En ejecución 02 17 09 21 16 13 27 01 AMBIENTAL CUENCA Basins PAMPAS Page 10 PE-ANA-161050-CS-INDV Component 2: Improving 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2022-12- / ASISTENTE DE RECURSOS IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 93,170.00 6,151.37 Firmado 02 02 09 10 16 10 27 13 30 HIDRICOS CUENCA PAMPAS Basins PE-ANA-161052-CS-INDV Component 2: Improving 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2022-12- / COORDINADOR TÉCNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 113,469.00 8,970.73 Firmado 02 02 09 10 16 31 24 31 30 CUENCA URUBAMBA Basins PE-ANA-163778-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: Ejecución 2020-03- 2020-03- 2020-03- 2020-03- 2020-05- MEDICIÓN DE NIVEL DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 4,776.00 0.00 pendiente 16 17 24 25 25 AGUA EN BLOQUES DE National Level RIEGO EN LOS SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN. PE-ANA-163779-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: 2020-03- 2020-08- 2020-03- 2020-08- 2020-03- 2020-09- 2020-03- 2020-09- 2020-06- MEDICIÓN DE NIVEL DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 5,970.00 7,694.18 Firmado 16 10 17 26 24 15 25 15 08 AGUA EN BLOQUES DE National Level RIEGO EN EL SECTOR HIDRÁULICO MENOR IRRIGACION MAJES, VALLE DE MAJES, CAMANA PE-ANA-164551-CS-INDV / APOYO AL ANÁLISIS DE LA Component 1: SEGURIDAD DE LA PRESA 2020-04- 2020-01- 2020-04- 2020-04- 2020-04- 2020-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 6,500.00 0.00 En ejecución POECHOS RECRECIDA, 01 29 08 13 20 08 National Level DURANTE EL LLENADO DEL EMBALSE PE-ANA-164570-CS-INDV Component 1: / SERVICIO DE 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 30,600.00 26,133.61 Firmado COORDINADOR DE 19 21 24 21 15 12 19 06 31 National Level CALIDAD DE RECURSOS HIDRICOS PGIRH PE-ANA-164571-CS-INDV / SERVICIO DE Component 1: 2020-03- 2020-04- 2020-04- 2020-05- 2020-04- 2020-05- 2020-05- 2020-12- ESPECIALISTA DE CALIDAD IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 19,600.00 13,367.93 En ejecución 29 30 03 11 18 29 03 31 DE AGUA SUPERFICIAL National Level CUENCA URUBAMBA PE-ANA-164572-CS-INDV Component 1: / SERVICIO DE 2020-03- 2020-03- 2020-04- 2020-05- 2020-04- 2020-05- 2020-05- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 19,600.00 13,367.93 En ejecución ESPECIALISTA DE CALIDAD 29 30 03 11 18 29 03 31 National Level DE AGUA SUPERFICIAL CUENCA PAMPAS PE-ANA-164573-CS-INDV Component 1: / SERVICIO DE 2020-03- 2020-04- 2020-04- 2021-05- 2020-04- 2020-05- 2020-05- 2020-06- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 19,600.00 13,367.93 Firmado ESPECIALISTA DE CALIDAD 29 30 03 11 18 29 03 05 31 National Level DE AGUA SUPERFICIAL CUENCA MAYO PE-ANA-164574-CS-INDV / SERVICIO DE Component 1: 2020-03- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-12- ESPECIALISTA EN GESTION IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 19,600.00 19,084.99 En ejecución 29 13 03 24 18 08 03 31 DE CALIDAD DE RECURSOS National Level HIDRICOS CUENCA MANTARO PE-ANA-164991-CS-INDV / SERVICIO DE APOYO EN PROCESAMIENTO DE Component 1: INFORMACION DE 2020-04- 2020-04- 2020-04- 2020-06- 2020-04- 2020-07- 2020-05- 2020-07- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 16,000.00 9,694.36 Firmado ACTIVIDADES DEL 01 01 06 24 21 02 06 02 31 National Level COMPONENTE DE CALIDAD DE RECURSOS HIDRICOS EN LA CUENCA MANTARO PE-ANA-164992-CS-INDV / SERVICIO DE APOYO EN GESTIONES Y MONITOREO Component 1: DE EJECUCION DE 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 11,000.00 10,394.88 Firmado ACTIVIDADES DEL 01 06 06 24 11 08 21 06 31 National Level COMPONENTE DE MONITOREO DE LA CALIDAD DE LOS RECURSOS HIDRICOS PGIRH PE-ANA-165879-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: 2020-05- 2020-08- 2020-05- 2020-08- 2020-05- 2020-09- 2020-05- 2020-09- 2020-07- MEDICIÓN DE NIVEL DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 5,672.00 5,134.37 Firmado 20 10 21 26 28 15 29 15 27 AGUA EN BLOQUES DE National Level RIEGO EN LOS SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN PE-ANA-165880-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: Ejecución 2020-05- 2020-05- 2020-05- 2020-05- 2020-08- MEDICIÓN DE NIVEL DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 7,090.00 0.00 pendiente 20 21 28 29 12 AGUA EN BLOQUES DE National Level RIEGO EN EL SECTOR HIDRÁULICO MENOR IRRIGACIÓN MAJES , VALLE DE MAJES, CAMANÁ PE-ANA-165881-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: 2020-06- 2020-08- 2020-06- 2020-08- 2020-06- 2020-09- 2020-06- 2020-09- 2020-09- MEDICIÓN DE NIVEL DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 7,090.00 7,701.56 Firmado 19 10 22 26 29 15 30 15 14 AGUA EN BLOQUES DE National Level RIEGO EN EL SECTOR HIDRÁULICO MENOR LA JOYA, CHILI REGULADO Y CHILI NO REGULADO PE-ANA-165883-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE Component 1: AGUA EN BLOQUES DE 2020-06- 2020-09- 2020-06- 2020-09- 2020-06- 2020-10- 2020-06- 2020-10- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 5,672.00 6,417.96 Firmado RIEGO EN EL SECTOR 19 22 22 25 29 30 30 30 28 National Level HIDRÁULICO MENOR IRRIGACIÓN ENSENADA- MEJIA-MOLLENDO, PUNTA DE BOMBOM, MOQUEGUA, LOCUMBA, SAMA Y BAJO UCHUSUMA PE-ANA-165889-CS-INDV / BACHILLER 01 PARA Component 1: TRABAJOS DE HIDROMETRÍA 2020-04- 2020-04- 2020-05- 2020-06- 2022-11- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 38,955.00 0.00 Cancelado EN ESTRUCTURAS DE 20 27 18 22 09 National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165890-CS-INDV / BACHILLER 02 PARA Component 1: TRABAJOS DE HIDROMETRÍA 2020-04- 2020-04- 2020-05- 2020-06- 2022-11- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 38,955.00 0.00 Cancelado EN ESTRUCTURAS DE 20 27 18 22 09 National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165891-CS-INDV / PROFESIONAL Component 1: 2020-04- 2020-03- 2020-04- 2020-04- 2020-05- 2020-04- 2020-06- 2020-07- 2021-02- ESPECIALISTA PARA IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 26,269.00 8,562.53 Firmado 20 30 27 01 18 13 22 06 17 ADECUACIÓN DE National Level ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165964-CS-INDV / TÉCNICO 01: Component 1: 2020-04- 2020-04- 2020-04- 2020-05- 2021-03- SENSIBILIZACIÓN Y IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 14,300.00 0.00 Cancelado 19 24 29 14 10 CAPACITACIÓN EN National Level SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-165971-CS-INDV / TÉCNICO 02: Component 1: 2020-04- 2020-04- 2020-04- 2020-05- 2021-03- SENSIBILIZACIÓN Y IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 14,300.00 0.00 Cancelado 19 24 29 14 10 CAPACITACIÓN EN National Level SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-165979-CS-INDV / TÉCNICO EN METRADOS, Component 1: COSTOS Y PRESUPUESTOS 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 4,030.00 3,633.92 Firmado 01 PARA 20 20 25 22 30 08 15 08 13 National Level ESTANDARIZACIÓN E INTEGRACIÓN DE EXPEDIENTTES TÉCNICOS PE-ANA-165984-CS-INDV / TÉCNICO EN METRADOS, Component 1: COSTOS Y PRESUPUESTOS 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 4,030.00 3,633.92 Firmado 02 PARA 20 20 25 22 30 08 06 08 04 National Level ESTANDARIZACIÓN E INTEGRACIÓN DE EXPEDIENTTES TÉCNICOS PE-ANA-165985-CS-INDV / PROFESIONAL Component 1: 2020-04- 2020-03- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2022-01- ESPECIALISTA EN IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 81,493.00 28,070.18 Firmado 20 30 25 02 30 01 06 22 26 EJECUCIÓN DE OBRAS DE National Level ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165987-CS-INDV / PROFESIONAL ASISTENTE Component 1: 2020-04- 2020-03- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2022-01- EN EJECUCIÓN DE OBRAS DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 59,553.00 20,512.82 Firmado 20 30 25 02 30 01 06 22 26 ESTRUCTURAS DE National Level MEDICIÓN DE AGUA PE-ANA-165989-CS-INDV / SUPERVISIÓN DE LA Component 1: CONSTRUCCIÓN DE 22 2020-04- 2020-09- 2020-04- 2020-09- 2020-04- 2020-10- 2020-05- 2021-02- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 14,142.00 14,011.42 Firmado ESTRUCTURAS DE 20 16 25 17 30 02 15 10 13 National Level MEDICIÓN DE AGUA EN LA REGIÓN TUMBES PE-ANA-165990-CS-INDV / SUPERVISIÓN DE LA Component 1: CONSTRUCCIÓN DE 11 2020-04- 2020-09- 2020-04- 2020-11- 2020-04- 2020-11- 2020-05- 2020-11- 2020-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 7,071.00 8,118.86 Firmado ESTRUCTURAS DE 20 16 25 04 30 09 15 18 21 National Level MEDICIÓN DE AGUA EN LA REGIÓN MOQUEGUA PE-ANA-165991-CS-INDV / SUPERVISIÓN DE LA Component 1: CONSTRUCCIÓN DE 15 2020-04- 2020-09- 2020-04- 2020-09- 2020-04- 2020-10- 2020-05- 2020-11- 2020-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 9,643.00 9,705.99 Firmado ESTRUCTURAS DE 20 16 25 11 30 02 15 02 14 National Level MEDICIÓN DE AGUA EN LA REGIÓN TACNA PE-ANA-165993-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE 2020-04- 2020-07- 2020-04- 2020-07- 2020-04- 2020-07- 2020-05- 2020-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 5,672.00 4,917.82 En ejecución MEDICIÓN DE NIVEL DE 20 10 25 09 30 29 15 14 National Level AGUA EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO PE-ANA-165994-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA Component 1: ADECUACIÓN DE 2020-04- 2020-04- 2020-04- 2020-05- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 8,508.00 0.00 Cancelado ESTRUCTURAS DE 20 25 30 15 13 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE TUMBES HASTA JEQUETEPEQUE PE-ANA-165998-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA Component 1: ADECUACIÓN DE 2020-04- 2020-04- 2020-04- 2020-05- 2020-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 5,672.00 0.00 Cancelado ESTRUCTURAS DE 20 25 30 15 14 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE CHICAMA HASTA SANTA PE-ANA-165999-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA Component 1: ADECUACIÓN DE 2020-04- 2020-04- 2020-04- 2020-05- 2020-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 5,672.00 0.00 Cancelado ESTRUCTURAS DE 20 25 30 15 14 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE FORTALEZA HASTA LURÍN PE-ANA-166000-CS-INDV / TÉCNICO 01 PARA SUPERVISIÓN DEL Component 1: SUMINISTRO, INSTALACIÓN, 2020-04- 2020-04- 2020-04- 2020-05- 2021-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 25,075.00 0.00 Cancelado PUESTA EN MARCHA Y 20 25 30 15 10 National Level CAPACITACIÓN DE INSTRUMENTACIÓN PARA LA MEDICIÓN Page 11 PE-ANA-166002-CS-INDV / TÉCNICO 02 PARA SUPERVISIÓN DEL Component 1: SUMINISTRO, INSTALACIÓN, 2020-04- 2020-04- 2020-04- 2020-05- 2021-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 25,075.00 0.00 Cancelado PUESTA EN MARCHA Y 20 25 30 15 10 National Level CAPACITACIÓN DE INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-171096-CS-INDV Component 1: / TECNICO EN AUTOCAD 01 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 4,030.00 3,648.11 Firmado PARA ESTANDARIZACION E 27 20 29 22 04 08 05 08 03 National Level INTEGRACION DE PLANOS PE-ANA-171097-CS-INDV Component 1: / TECNICO EN AUTOCAD 02 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 4,030.00 3,648.11 Firmado PARA ESTANDARIZACION E 27 20 29 22 04 08 05 08 03 National Level INTEGRACION DE PLANOS PE-ANA-171099-CS-INDV Component 1: / TECNICO EN AUTOCAD 03 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 4,030.00 3,648.11 Firmado PARA ESTANDARIZACION E 27 20 29 22 04 08 05 08 03 National Level INTEGRACION DE PLANOS PE-ANA-165886-CS-INDV / PROFESIONAL 01 PARA Component 1: TRABAJOS DE HIDROMETRÍA 2020-05- 2020-05- 2020-06- 2020-07- 2022-11- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 51,940.00 0.00 Cancelado EN ESTRUCTURAS DE 08 15 05 10 27 National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165888-CS-INDV / PROFESIONAL 02 PARA Component 1: TRABAJOS DE HIDROMETRÍA 2020-05- 2020-05- 2020-06- 2020-07- 2022-11- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 51,940.00 0.00 Cancelado EN ESTRUCTURAS DE 08 15 05 10 27 National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-171926-CS-INDV / PROFESIONAL 01 PARA Component 1: 2020-05- 2020-04- 2020-05- 2020-04- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- ESTANDARIZACIÓN E IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 8,400.00 7,671.60 Firmado 03 14 13 22 16 02 20 02 18 INTEGRACIÓN DE National Level EXPEDIENTES TÉCNICOS PE-ANA-171929-CS-INDV / PROFESIONAL 02 PARA Component 1: 2020-05- 2020-04- 2020-05- 2020-04- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- ESTANDARIZACIÓN E IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 8,400.00 7,671.60 Firmado 03 14 08 22 11 02 14 02 12 INTEGRACIÓN DE National Level EXPEDIENTES TÉCNICOS PE-ANA-182711-CS-INDV / PROFESIONAL SENIOR Component 1: 2020-06- 2020-06- 2020-07- 2020-06- 2020-07- 2020-07- 2020-07- 2020-07- 2020-11- PARA ACTUALIZAR LA IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 21,000.00 19,411.82 Firmado 30 30 02 30 07 02 13 02 10 POLITICA Y ESTRATEGIA National Level NACIONAL DE RECURSOS HÍDRICOS. PE-ANA-187092-CS-INDV Component 2: Improving / ESPECIALISTA SOCIAL 2020-09- 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-10- 2020-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 73,500.00 7,416.42 Firmado AMBIENTAL CUENCA MAYO 21 23 26 24 28 02 01 02 31 Basins - PGIRH PE-ANA-190830-NC-RFQ Component 1: 2020-09- 2020-10- 2020-10- 2020-11- 2020-12- / Estudio Geológico del IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 35,000.00 0.00 Cancelado 28 03 13 08 08 acuífero Caplina National Level PE-ANA-190616-NC-RFQ Component 1: / Estudio Geológico de los 2020-09- 2020-10- 2020-10- 2020-11- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 35,000.00 0.00 Cancelado acuíferos de Ica, Villacurí y 28 03 13 08 08 National Level Lanchas PE-ANA-199722-CS-INDV / Profesional especialista Component 1: 2020-10- 2020-11- 2020-10- 2020-11- 2020-10- 2020-11- 2020-10- 2020-11- 2022-12- para la instrumentación de IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 72,500.00 65,708.42 Firmado 20 02 22 05 27 13 31 25 31 las estructuras de Medición National Level de agua en bloques de riego PE-ANA-199657-CS-INDV Component 3: General 2020-10- 2020-08- 2020-10- 2020-10- 2020-10- 2020-11- 2020-10- 2020-11- 2022-12- / Especialista en IBRD / 87400 Posterior Individual Direct 103,000.00 53,604.25 Firmado Project Adminstration 14 28 18 05 23 11 31 11 30 Administración y Finanzas del Proyecto PGIRH PE-ANA-202833-CS-INDV / TÉCNICO 01: Component 1: 2020-11- 2021-01- 2020-11- 2021-01- 2020-11- 2021-01- 2020-12- 2021-02- 2021-03- SENSIBILIZACIÓN Y IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 20,600.00 15,062.30 Firmado 20 15 23 15 25 20 01 01 31 CAPACITACIÓN EN National Level SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-202851-CS-INDV / TÉCNICO 02: Component 1: 2020-11- 2021-01- 2020-11- 2021-01- 2020-11- 2021-01- 2020-12- 2021-02- 2021-03- SENSIBILIZACIÓN Y IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 20,600.00 15,058.18 Firmado 20 12 23 15 25 20 01 02 31 CAPACITACIÓN EN National Level SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-202855-CS-INDV / PROFESIONAL PARA Component 1: ESTANDARIZACIÓN E 2020-11- 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-03- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 8,200.00 7,828.59 Firmado INTEGRACIÓN DE 09 28 14 11 19 24 01 26 01 National Level EXPEDIENTES TÉCNICOS, REGIÓN ICA PE-ANA-202860-CS-INDV / TÉCNICO EN AUTOCAD 01 Component 1: 2020-11- 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-03- PARA ESTANDARIZACIÓN E IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 3,900.00 3,704.16 Firmado 09 28 14 11 19 23 01 26 01 INTEGRACIÓN DE PLANOS, National Level REGIÓN ICA PE-ANA-202861-CS-INDV / TÉCNICO EN METRADOS, COSTOS Y PRESUPUESTOS Component 1: 2020-11- 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-03- 01 PARA IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 3,900.00 3,704.16 Firmado 09 28 14 11 19 23 01 26 01 ESTANDARIZACIÓN E National Level INTEGRACIÓN DE EXPEDIENTES TÉCNICOS, REGIÓN ICA PE-ANA-202862-CS-INDV / PROFESIONAL PARA ESTANDARIZACIÓN E Component 1: 2020-11- 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-04- INTEGRACIÓN DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 13,600.00 13,054.83 Firmado 09 28 14 11 19 23 01 26 30 EXPEDIENTES TÉCNICOS, National Level REGIONES PIURA, LAMBAYEQUE Y LA LIBERTAD PE-ANA-202863-CS-INDV / TÉCNICO EN AUTOCAD 01 Component 1: PARA ESTANDARIZACIÓN E 2020-11- 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-04- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 6,500.00 6,180.47 Firmado INTEGRACIÓN DE PLANOS, 09 28 14 11 19 23 01 26 30 National Level REGIONES PIURA, LAMBAYEQUE Y LA LIBERTAD PE-ANA-202864-CS-INDV / TÉCNICO EN METRADOS, COSTOS Y PRESUPUESTOS Component 1: 01 PARA 2020-11- 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-04- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 6,500.00 6,173.60 Firmado ESTANDARIZACIÓN E 09 28 14 11 19 23 01 26 30 National Level INTEGRACIÓN DE EXPEDIENTES TÉCNICOS, REGIONES PIURA, LAMBAYEQUE Y LA LIBERTAD PE-ANA-202869-CS-INDV / TÉCNICO 01 PARA SUPERVISIÓN DEL Component 1: SUMINISTRO, INSTALACIÓN, 2020-11- 2021-03- 2020-11- 2020-11- 2020-12- 2022-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 40,000.00 0.00 En ejecución PUESTA EN MARCHA Y 20 03 22 25 01 24 National Level CAPACITACIÓN EN INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-202870-CS-INDV / TÉCNICO 02 PARA SUPERVISIÓN DEL Component 1: SUMINISTRO, INSTALACIÓN, 2020-11- 2021-03- 2020-11- 2020-11- 2020-12- 2022-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 40,000.00 0.00 En ejecución PUESTA EN MARCHA Y 20 03 23 26 01 24 National Level CAPACITACIÓN EN INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-202874-CS-INDV / SUPERVISIÓN PARA CULMINACIÓN DE Component 1: ADECUACIÓN DE 2020-11- 2021-11- 2020-11- 2020-11- 2020-12- 2021-02- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 9,300.00 0.00 En ejecución ESTRUCTURAS DE 20 08 22 25 01 14 National Level MEDICIÓN DE AGUA EN SECTORES HIDRAULICOS DESDE CHICAMA HASTA SANTA PE-ANA-202875-CS-INDV / SERVICIO DE SUPERVISIÓN PARA CULMINACIÓN DE Component 1: ADECUACIÓN DE 2020-11- 2020-11- 2020-11- 2020-12- 2021-02- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 9,300.00 0.00 Cancelado ESTRUCTURAS DE 20 22 25 01 14 National Level MEDICIÓN DE AGUA EN SECTORES HIDRAULICOS DESDE FORTALEZA HASTA LURÍN PE-ANA-202876-CS-INDV / PROFESIONAL 01 PARA Component 1: TRABAJOS DE HIDROMETRÍA 2020-11- 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-01- 2022-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 30,900.00 19,706.59 Firmado EN ESTRUCTURAS DE 20 17 22 18 25 02 01 13 25 National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-202877-CS-INDV / PROFESIONAL 02 PARA Component 1: TRABAJOS DE HIDROMETRÍA 2020-11- 2020-12- 2020-11- 2021-01- 2020-11- 2021-01- 2020-12- 2021-01- 2022-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 30,900.00 19,706.59 Firmado EN ESTRUCTURAS DE 20 17 23 18 26 02 01 13 25 National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-202878-CS-INDV / BACHILLER 01 PARA Component 1: TRABAJOS DE HIDROMETRÍA 2020-11- 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-01- 2022-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 20,600.00 13,137.73 Firmado EN ESTRUCTURAS DE 20 17 22 18 25 05 01 13 25 National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-202879-CS-INDV / BACHILLER 02 PARA Component 1: TRABAJOS DE HIDROMETRÍA 2020-11- 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-01- 2022-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 20,600.00 12,553.94 Firmado EN ESTRUCTURAS DE 20 17 22 18 25 05 01 13 25 National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-204399-CS-CDS Component 3: General Selección directa 2020-11- 2020-07- 2020-11- 2020-11- 2020-11- 2020-11- 2022-12- IBRD / 87400 Posterior Direct 156,000.00 78,870.15 Firmado / DIRECTOR EJECUTIVO Project Adminstration de consultores 16 10 22 10 25 11 30 PE-ANA-202802-CS-INDV Component 1: Ejecución 2020-12- 2020-12- 2021-01- 2021-02- 2022-08- / Responsable Jefe IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 81,274.00 0.00 pendiente 22 27 17 21 15 Supervisión EHA-SMA National Level PE-ANA-202807-CS-INDV Component 1: Ejecución 2020-12- 2020-12- 2021-01- 2021-02- 2022-08- / Asistente Supervisión EHA- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 71,302.00 0.00 pendiente 22 27 17 21 15 SMA National Level PE-ANA-202808-CS-INDV Component 1: 2020-12- 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- 2021-02- 2021-05- 2022-08- / Supervisor 1 - Obras IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 66,316.00 64,002.99 Firmado 22 11 27 17 17 28 21 07 15 Civiles EHA - SMA National Level PE-ANA-202814-CS-INDV Component 1: 2020-12- 2021-05- 2020-12- 2021-01- 2021-02- 2022-08- IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 En ejecución / Supervisor 2 - Montaje Consolidating IWRM at the 22 07 27 17 21 15 EHA National Level PE-ANA-202810-CS-INDV Component 1: 2020-12- 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- 2021-02- 2020-12- 2022-08- / Supervisor 2 - Obras IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 66,316.00 43,029.89 Firmado 22 11 27 17 17 30 21 30 15 Civiles EHA -SMA National Level PE-ANA-202811-CS-INDV Component 1: 2020-12- 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- 2021-02- 2020-12- 2022-08- / Supervisor 3 - Obras IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 66,316.00 43,029.89 Firmado 22 11 27 17 17 30 21 30 15 Civiles EHA - SMA National Level PE-ANA-202813-CS-INDV Component 1: 2020-12- 2021-05- 2020-12- 2021-01- 2021-02- 2022-08- IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 En ejecución / Supervisor 1 - Montaje Consolidating IWRM at the 22 07 27 17 21 15 EHA National Level PE-ANA-202815-CS-INDV Component 1: Ejecución 2020-12- 2020-12- 2021-01- 2021-02- 2022-08- IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 / Supervisor 3 - Montaje Consolidating IWRM at the pendiente 22 27 17 21 15 SMA National Level PE-ANA-202816-CS-INDV Component 1: Ejecución 2020-12- 2020-12- 2021-01- 2021-02- 2022-08- IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 / Supervisor 4 - Montaje Consolidating IWRM at the pendiente 22 27 17 21 15 SMA National Level PE-ANA-211979-CS-INDV / ESPECIALISTA DE CALIDAD DE AGUA PARA EL Component 1: 2021-01- 2021-10- 2021-01- 2021-11- 2021-01- 2021-11- 2021-02- 2021-11- 2022-02- MONITOREO DE LA IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 27,000.00 25,259.83 Firmado 18 05 20 08 25 11 01 12 01 INSTALACION DE SENSORES National Level DE CALIDAD DE AGUA SUPERFICIAL EN EL AMBITO DEL PGIRH Page 12 PE-ANA-212242-CS-INDV / ESPECIALISTA EN CALIDAD DE AGUA PARA LA Component 1: SUPERVISIÓN DE LA 2021-01- 2021-12- 2021-01- 2021-01- 2021-01- 2022-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 30,000.00 0.00 En ejecución ELABORACIÓN DE LOS 15 17 17 22 29 29 National Level DIAGNÓSTICOS DE LA CALIDAD DE LOS RECURSOS HÍDRICOS SUPERFICIALES DEL ÁMBITO DEL PGIRH PE-ANA-212246-CS-INDV / ESPECIALISTA EN CALIDAD DE AGUAPARA LA SUPERVISIÓN DEL REGISTRO DE DATOS DE LAS Component 1: Ejecución 2021-01- 2021-01- 2021-01- 2021-01- 2022-01- ACTIVIDADES DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 30,000.00 0.00 pendiente 15 17 22 29 29 VIGILANCIA DE LA CALIDAD National Level DE LOS RECURSOS HÍDRICOS SUPERFICIALES DEL PERIODO 2010 A 2020 EN LA PLATAFORMA DEL SNIRH/DCERH EN 25 U.H. PE-ANA-212247-CS-INDV / ESPECIALISTA EN CALIDAD DE AGUA PARA LA SUPEVISION DEL REGISTRO DE DATOS DE LAS Component 1: Ejecución 2021-01- 2021-01- 2021-01- 2021-01- 2022-01- ACTIVIDADES DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 30,000.00 0.00 pendiente 15 17 22 29 29 VIGILANCIA DE LA CALIDAD National Level DE LOS RECURSOS HIDRICOS SUPERFICIALES DEL PERIODO 2010 A 2020 EM LA PLATAFORMA DEL SNIRH/DCERH EN 17 U.H PE-ANA-212248-CS-INDV / ESPECIALISTA PARA EL GEOPROCESAMIENTO DE INFORMACION PARA LA SUPERVISION Y Component 1: ELABORACION DE 2021-01- 2021-12- 2021-01- 2021-01- 2021-01- 2022-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 27,000.00 0.00 En ejecución DIAGNOSTICOS DE LA 15 17 17 22 29 29 National Level CALIDAD DE LOS RECURSOS HIDRICOS SUPERFICIALES Y REGISTRO DE INFORMACION DE LA PLATAFORMA DEL SNIRH/DCERH DE LA ANA DEL AMBITO NACIONAL PE-ANA-212257-CS-INDV Component 3: General 2021-01- 2021-02- 2021-01- 2021-03- 2021-01- 2021-03- 2021-02- 2021-03- 2022-12- / ASISTENTE EN IBRD / 87400 Posterior Individual Limited 68,000.00 26,623.28 Firmado Project Adminstration 18 05 25 16 28 30 02 31 31 ADQUISICIONES 2 PE-ANA-212262-CS-INDV Component 3: General 2021-02- 2021-11- 2021-02- 2021-11- 2021-02- 2021-12- 2021-02- 2021-12- 2022-12- IBRD / 87400 Posterior Individual Limited 76,000.00 3,289.04 Firmado / ASESOR LEGAL - PGIRH Project Adminstration 13 10 20 19 23 09 28 10 31 PE-ANA-212264-CS-INDV Component 3: General 2021-02- 2021-11- 2021-02- 2021-11- 2021-02- 2021-12- 2021-03- 2021-12- 2021-05- / ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 76,500.00 3,289.04 Firmado Project Adminstration 15 10 22 19 27 02 03 07 08 CONTABILIDAD SCI 039 ANA PGIRH / Component 3: General 2019-02- 2019-02- 2019-02- 2019-02- 2020-02- ASISTENTE DE IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 Cancelado Project Adminstration 08 15 20 28 28 ADQUISICIONES 2 SCI 068 2018 ANA PGIRH Component 3: General 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 Cancelado BM / ASESOR LEGAL Project Adminstration 05 15 20 30 29 PE-ANA-214176-CS-INDV / ESPECIALISTA EN Component 3: General 2021-02- 2021-02- 2021-02- 2021-02- 2021-02- 2021-02- 2021-03- 2021-03- 2022-12- IBRD / 87400 Posterior Individual Limited 92,000.00 40,594.30 Firmado PLANIFICACION, Project Adminstration 15 18 22 22 27 26 03 05 30 PRESUPUESTO Y EVALUACION SCI 032 ANA PGIRH / ESPECIALISTA EN Component 3: General 2019-04- 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 48,000.00 0.00 Cancelado PLANIFICACION, Project Adminstration 05 15 20 30 29 PRESUPUESTO Y EVALUACIÓN PE-ANA-122163-CS-INDV Component 3: General Ejecución 2021-02- 2021-02- 2021-02- 2021-03- 2022-12- IBRD / 87400 Posterior Individual Limited 58,000.00 0.00 / ASISTENTE DE Project Adminstration pendiente 15 22 27 03 30 CONTABILIDAD SCI 041 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-06- 2018-06- 2022-11- ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 194,076.00 0.00 Cancelado Project Adminstration 28 04 11 13 19 CONTABILIDAD PE-ANA-122162-CS-INDV Component 3: General 2021-02- 2021-02- 2021-02- 2021-03- 2021-02- 2021-03- 2021-03- 2021-03- 2022-12- / ASISTENTE DE IBRD / 87400 Posterior Individual Limited 58,000.00 22,992.83 Firmado Project Adminstration 15 26 22 11 27 26 03 31 30 MONITOREO Y EVALUACIÓN PE-ANA-216395-CS-INDV Component 3: General 2021-02- 2021-11- 2021-02- 2021-02- 2021-02- 2022-01- / Especialista Financiero del IBRD / 87400 Posterior Individual Limited 33,600.00 0.00 Bajo Revision Project Adminstration 08 19 13 18 23 24 Proyecto PE-ANA-221587-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA Component 1: ADECUACIÓN DE 2021-03- 2021-05- 2021-03- 2021-06- 2021-03- 2021-06- 2021-04- 2021-07- 2021-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 8,000.00 8,876.20 Firmado ESTRUCTURAS DE 15 18 20 03 25 14 09 02 10 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE TUMBES HASTA ALTO PIURA PE-ANA-221592-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA Component 1: ADECUACIÓN DE 2021-03- 2021-03- 2021-03- 2021-04- 2021-03- 2021-04- 2021-04- 2021-05- 2021-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 8,750.00 10,020.77 Firmado ESTRUCTURAS DE 15 11 20 12 25 27 09 11 18 National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE OLMOS HASTA JEQUETEPEQUE PE-ANA-234084-CS-INDV / PROFESIONAL 01 PARA EL Component 1: SEGUIMIENTO Y CONTROL 2021-05- 2021-06- 2021-06- 2021-06- 2021-06- 2021-06- 2021-06- 2021-07- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 36,000.00 34,732.27 Firmado DE LA EJECUCION DE OBRAS 28 11 02 09 03 24 10 02 05 National Level DE ESTRUCTURAS DE MEDICION DE AGUA PE-ANA-234087-CS-INDV / PROFESIONAL 02 PARA EL Component 1: SEGUIMIENTO Y CONTROL 2021-05- 2021-06- 2021-06- 2021-06- 2021-06- 2021-06- 2021-06- 2021-07- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 36,000.00 34,732.27 Firmado DE LA EJECUCION DE OBRAS 28 04 02 09 03 24 09 02 04 National Level DE ESTRUCTURAS DE MEDICION DE AGUA PE-ANA-234089-CS-INDV / TECNICO EN AUTOCAD, METRADOS, COSTOS Y Component 1: PRESUPUESTO PARA EL 2021-05- 2021-06- 2021-06- 2021-06- 2021-06- 2021-06- 2021-06- 2021-07- 2022-01- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 15,000.00 14,208.66 Firmado SEGUIMIENTO Y CONTROL 28 04 02 09 03 24 10 02 06 National Level DE LA EJECUCION DE OBRAS DE ESTRUCTURAS DE MEDICION DE AGUA PE-ANA-165885-CS-INDV / DESARROLLO E Component 1: IMPLEMENTACIÓN DE Ejecución 2021-10- 2021-10- 2021-10- 2021-12- 2022-03- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 9,851.00 0.00 CURSO VIRTUAL: MEDICIÓN pendiente 01 08 29 03 05 National Level DEL AGUA EN SISTEMAS HIDRÁULICOS COMUNES PE-ANA-235103-CS-INDV / PROFESIONAL PARA LA Component 1: ELABORACION DE 20 Ejecución 2021-07- 2021-07- 2021-07- 2021-07- 2021-09- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 22,000.00 0.00 EXPEDIENTES TECNICOS EN pendiente 01 06 16 28 26 National Level LOS SECTORES DE MEDIO Y BAJO PIURA Y SECHURA PE-ANA-235582-CS-INDV / TECNICO 01 PAAR SUPERVISION DEL Component 1: SUMINISTRO, INSTALACION 2021-07- 2021-07- 2021-07- 2021-07- 2022-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 17,000.00 0.00 Cancelado , PUESTA EN MARCHA Y 01 06 13 26 22 National Level CAPACITACION DE INSTRUMENTACION PARA LA MEDICION PE-ANA-235586-CS-INDV / TECNICO 02 PARA SUPERVISION DEL Component 1: SUMINISTRO, INSTALACION, 2021-07- 2021-07- 2021-07- 2021-07- 2022-05- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 17,000.00 0.00 Cancelado PUESTA EN MARCHA Y 01 06 13 26 22 National Level CAPACITACION DE INSTRUMENTACION PARA LA MEDICION PE-ANA-248241-CS-INDV / SUPERVISION DE CAMPO DE LA IMPLEMENTACION DE EJEMPLOS PILOTO DE MEDICION DE CONSUMO DE Component 1: Ejecución 2021-08- 2021-09- 2021-09- 2021-09- 2021-11- AGUA EN POZOS DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 10,000.00 0.00 pendiente 30 04 14 18 17 PRODUCCION A TRAVES DE National Level FLUJOMETROS ELECTROMAGNETICOS Y DE TRUBINA EN LOS AMBITOS DE ICA Y TACNA PE-ANA-248244-CS-INDV / SUPERVISION DE CAMPO Component 1: DE LA EJECUCION DE Ejecución 2021-08- 2021-09- 2021-09- 2021-09- 2021-10- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 3,500.00 0.00 PERFILES GAMMA RAY, CE Y pendiente 30 01 08 12 12 National Level T° EN PIEZOMETROS CULMINADOS ICA PE-ANA-248245-CS-INDV / SUPERVISION DE CAMPO DE LA CONSTRUCCION DE Component 1: Ejecución 2021-08- 2021-09- 2021-09- 2021-09- 2021-11- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 9,000.00 0.00 pendiente 30 01 08 12 11 PROTECCION Y CASTEAS EN National Level PIEZOMETROS UBICADOS EB EL ACUIFERO CAPLINA E ICA PE-ANA-248246-CS-INDV / SUPERVISION DE CAMPO Component 1: Ejecución 2021-08- 2021-09- 2021-09- 2021-09- 2021-11- DE LA NIVELACION DE 99 IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 5,000.00 0.00 pendiente 30 01 08 12 11 PIEZOMETROS UBICADOS National Level EN EL AMBITO DE ICA PE-ANA-268538-CS-INDV Component 2: Improving 2021-12- 2021-12- 2021-12- 2021-12- 2021-12- 2022-12- / Coordinador Técnico de IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 34,000.00 0.00 En ejecución 20 16 27 28 30 30 Cuenca Mantaro Basins PE-ANA-270069-CS-INDV / Asesoramiento Técnico – Panel de Expertos: Component 1: 2022-01- 2022-02- 2022-02- 2022-04- 2022-10- Seguridad de la presa IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 11,200.00 0.00 En ejecución 28 07 28 04 01 Poechos: Propuestas para el National Level diseño de la cortina de inyecciones en la presa de Poechos PE-ANA-270321-CS-INDV Component 1: / Consultor internacional 2022-01- 2022-02- 2022-02- 2022-02- 2022-02- 2022-02- IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 8,500.00 0.00 En ejecución para entrenamiento en 28 08 07 09 12 26 National Level recarga de acuíferos PE-ANA-272250-CS-INDV / SUPERVISOR 4 - ESPECIALISTA EN Component 1: 2022-01- 2022-02- 2022-01- 2022-01- 2022-01- 2022-12- SUPERVISIÓN OBRAS CIVILES IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 22,000.00 0.00 En ejecución 14 16 19 26 31 27 DE ESTACIONES National Level HIDROLÓGICAS AUTOMÁTICAS Y DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-272253-CS-INDV / SUPERVISOR 5 - ESPECIALISTA EN Component 1: 2022-01- 2022-02- 2022-01- 2022-02- 2022-02- 2023-01- SUPERVISIÓN OBRAS CIVILES IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 22,000.00 0.00 En ejecución 20 16 25 01 06 02 DE ESTACIONES National Level HIDROLÓGICAS AUTOMÁTICAS Y DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-272257-CS-INDV / SUPERVISOR 6 - ESPECIALISTA EN Component 1: 2022-01- 2022-01- 2022-01- 2022-01- 2022-12- SUPERVISIÓN OBRAS CIVILES IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 22,000.00 0.00 En ejecución 14 19 26 31 27 DE ESTACIONES National Level HIDROLÓGICAS AUTOMÁTICAS Y DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-272258-CS-INDV / SUPERVISOR 7 - ESPECIALISTA EN Component 1: 2022-01- 2022-01- 2022-01- 2022-01- 2022-12- SUPERVISIÓN OBRAS CIVILES IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 22,000.00 0.00 En ejecución 14 19 26 31 27 DE ESTACIONES National Level HIDROLÓGICAS AUTOMÁTICAS Y DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-272260-CS-INDV Component 1: / SUPERVISOR 1 - Ejecución 2022-01- 2022-01- 2022-01- 2022-01- 2022-04- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 6,500.00 0.00 INSTRUMENTACIÓN DE pendiente 14 19 26 31 01 National Level PRESAS Page 13 PE-ANA-272261-CS-INDV Component 1: / SUPERVISOR 2 - Ejecución 2022-01- 2022-01- 2022-01- 2022-01- 2022-04- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 4,500.00 0.00 INSTRUMENTACIÓN DE pendiente 14 19 26 31 01 National Level PRESAS PE-ANA-272262-CS-INDV Component 1: / SUPERVISOR 3 - Ejecución 2022-01- 2022-01- 2022-01- 2022-01- 2022-04- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 3,500.00 0.00 INSTRUMENTACIÓN DE pendiente 14 19 26 31 01 National Level PRESAS PE-ANA-272267-CS-INDV Component 1: / PERSONAL DE APOYO Ejecución 2022-01- 2022-01- 2022-02- 2022-03- 2022-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 12,000.00 0.00 TECNICO MONITOREO DE pendiente 24 29 19 26 30 National Level AGUAS SUBTERRANEAS PE-ANA-272268-CS-INDV / ESPECIALISTA EN ESTUDIOS SOCIALES PARA Component 1: EL FORTALECIMIENTO DE 2022-01- 2022-02- 2022-02- 2022-02- 2022-04- 2022-07- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 7,500.00 0.00 En ejecución COMITÉS DE GESTIÓN Y LA 31 17 05 26 02 01 National Level IMPLEMENTACIÓN DE UN PLAN DE ACCIÓN EN EL ACUÍFERO CAPLINA-TACNA PE-ANA-272269-CS-INDV / PROFESIONAL PARA EL Component 1: FORTALECIMIENTO DE 2022-01- 2022-02- 2022-02- 2022-02- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 6,000.00 0.00 En ejecución COMITES DE GESTION E 28 17 02 23 30 13 National Level IMPLEMENTACION DE PLAN DE ACCION TACNA N° 2 PE-ANA-272271-CS-INDV / PROFESIONAL PARA Component 1: FORTALECIMIENTO DE 2022-01- 2022-02- 2022-01- 2022-02- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 6,000.00 0.00 En ejecución COMITES DE GESTION E 24 17 29 19 26 09 National Level IMPLEMENTACION DE PLAN DE ACCION ICA N° 2 PE-ANA-202817-CS-INDV Component 1: 2022-01- 2022-02- 2022-02- 2022-02- 2022-04- 2022-12- / Coordinador IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 22,500.00 0.00 En ejecución 31 16 05 26 02 31 Administrativo EHA - SMA National Level PE-ANA-190831-NC-RFQ Component 1: / Estudio de prospección 2020-09- 2020-10- 2020-10- 2020-11- 2020-12- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 13,000.00 0.00 Cancelado geofísica reubicación 28 03 13 08 08 National Level piezómetros PE-ANA-248243-CS-INDV / SUPERVISION DE CAMPO Component 1: DE LA EJECUCION DE SIETE 2021-08- 2021-09- 2021-09- 2021-09- 2021-10- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 4,000.00 0.00 Cancelado PRUEBAS DE BOMBEO EN 30 01 03 12 12 National Level PIEZOMETROS UBICADOS EN EL ACUIFERO CAPLINA PE-ANA-248242-CS-INDV / SUPERVISION DE CAMPO PARA LA EJECUCION DE Component 1: Ejecución 2022-03- 2022-03- 2022-03- 2022-03- 2022-06- ADPATACIONES DE IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 9,000.00 0.00 pendiente 01 10 12 21 19 ARBOLES DE DESCARGA EN National Level POZOS UBICADOS EN EL AMBITO DE TACNA PE-ANA-278962-CS-INDV / PROFESIONAL LEGAL Component 1: PARA EL FORTALECIMIENTO 2022-02- 2022-02- 2022-02- 2022-03- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 6,000.00 0.00 En ejecución DE COMITÉS DE GESTIÓN E 21 17 26 08 20 03 National Level IMPLEMENTACIÓN DE PLAN DE ACCIÓN TACNA N°1 PE-ANA-272270-CS-INDV / PROFESIONAL PARA Component 1: FORTALECIMIENTO DE 2022-01- 2022-02- 2022-01- 2022-02- 2022-03- 2022-06- IBRD / 87400 Consolidating IWRM at the Posterior Individual Limited 6,000.00 0.00 Cancelado COMITES DE GESTION E 24 11 29 19 26 09 National Level IMPLEMENTACION DE PLAN DE ACCION ICA N° 1 PE-ANA-270062-CS-INDV / Capacitación en gestión Component 1: Ejecución 2022-03- 2022-03- 2022-03- 2022-03- 2022-04- de seguridad de presas a IBRD / 87400 Consolidating IWRM at the Posterior Individual Direct 11,650.00 0.00 pendiente 04 14 19 29 20 operadores de presas- National Level Módulo I Page 14