PROCUREMENT PLAN (Textual Part) Project information: Eastern Recovery Project (P145196) Project Implementation agency: FSRDC Date of the Procurement Plan: February 2018 Period covered by this Procurement Plan: January 2018 – December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Eastern Recovery Project PLAN General Information Country: Congo, Democratic Republic of 2018-02-12 Bank’s Approval Date of the Original Procurement Plan: 2022-10-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145196 GPN Date: Project Name: DRC Eastern Recovery Project Loan / Credit No: IDA / 57510, IDA / 66650, IDA / D8440 Fonds Social de la République Démocratique du Congo Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-FSRDC-49337-CW-RFB / Single Stage - One E 2018-12-1 Construction du bâtiment an IDA / 57510 3. Capacity Building A posteriori Appel d'offres Open - National 350,000.00 0.00 Annulé 2018-03-01 2018-03-06 2018-04-17 2018-05-17 2018-06-21 nvelope 8 nexe du bureau de la CG GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-49334-GO-RFQ / Acquisition de 4 tracteurs et remorques matériel - Brigade Single Stage - One E IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 185,000.00 258,572.05 Signé 2018-03-05 2018-06-22 2018-04-30 2018-07-26 2018-10-27 d'entretien - OVD nvelope 1) Lot 1Nord Kivu (2), 2) L ot 2 Ituri (1), 3) Lot 3: Tanga nyika (1) ZR-FSRDC-51041-GO-RFQ / Single Stage - One E Acquisition LABOSEM phytos IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2018-12-01 2019-01-26 2019-07-25 nvelope anitaire du Sud Kivu ZR-FSRDC-51046-GO-RFB / A Single Stage - One E csuisition des équipements p IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 45,000.00 0.00 Annulé 2018-11-28 2019-01-23 2019-07-22 nvelope our LABO INERA ZR-FSRDC-49370-GO-RFQ / Single Stage - One E Acquisition des équipements IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 40,000.00 0.00 Annulé 2018-06-06 2018-08-01 2019-01-28 nvelope du nouveau bureau de la CG à construire. ZR-FSRDC-232746-GO-RFQ / Fourniture des matériels info Single Stage - One E rmatiques pour les antennes IDA / 66650 4. Project Management A posteriori Demande de prix Limited 300,000.00 174,620.00 Signé 2021-06-20 2021-05-14 2021-08-15 2021-07-09 2022-02-11 nvelope provinciales (Kinshasa, Nord Kivu, Sud Kivu, Kasaï Central, Nord Ubangi) du STEP 2 ZR-FSRDC-232763-GO-RFQ / Acquisition et Installation de Single Stage - One E IDA / 66650 4. Project Management A posteriori Demande de prix Limited 15,000.00 17,050.00 Signé 2021-06-13 2021-05-21 2021-08-08 2021-08-06 2022-02-04 3 VSAT pour la connexion Int nvelope ernet/Nord Ubangi/Kasaï Cen tral et Ituri ZR-FSRDC-232782-GO-RFQ / Single Stage - One E En attente d' IDA / 66650 5. CERC A posteriori Demande de prix Limited 50,000.00 0.00 2021-07-13 2021-09-07 2022-03-06 Acquisition d’un mini bus pou nvelope exécution r le CERC ZR-FSRDC-232804-GO-DIR / Passation de marc En attente d' Acquisition, mise à jour et for IDA / 66650 4. Project Management A posteriori Direct 55,000.00 0.00 2021-06-15 2021-06-20 2021-07-25 2022-01-21 hé de gré à gré exécution mation sur le logiciel TOM2P RO ZR-FSRDC-232809-GO-RFQ / Single Stage - One E IDA / 66650 4. Project Management A posteriori Demande de prix Limited 30,000.00 37,207.94 Signé 2021-06-13 2021-07-20 2021-08-08 2021-10-25 2022-02-04 Aménagement des container nvelope s ZR-FSRDC-232820-GO-RFQ / Acquisition des motos de terr 2. Livelihoods and Employm Single Stage - One E IDA / 66650 A posteriori Demande de prix Limited 42,800.00 47,650.00 Signé 2021-09-05 2021-07-14 2021-10-31 2021-08-31 2022-04-29 ain, lot 1: 4 pour le NU et lot ent Generation nvelope 2: 6 pour Kananga ZR-FSRDC-220575-GO-RFQ / Single Stage - One E En attente d' Acquisition de trois véhicules IDA / 66650 4. Project Management A posteriori Demande de prix Limited 150,000.00 0.00 2021-02-24 2021-04-21 2021-10-18 nvelope exécution automobile 4x4 pour le proje t STEP II ZR-FSRDC-236847-GO-RFQ / Single Stage - One E Fourniture de bureau et cons IDA / 66650 4. Project Management A posteriori Demande de prix Limited 40,000.00 3,660.00 Signé 2021-07-26 2021-07-16 2021-07-31 2021-11-27 2021-09-11 2021-08-09 2021-10-11 2021-09-21 2021-11-15 2021-10-11 2022-11-15 nvelope ommable informatique ZR-FSRDC-220580-GO-RFQ / Single Stage - One E En cours d'ex Acquisition de matériels infor IDA / 66650 4. Project Management A posteriori Demande de prix Limited 30,000.00 0.00 2021-02-24 2021-04-21 2021-10-18 nvelope écution matiques pour le staff du proj et STEP II ZR-FSRDC-49338-GO-RFQ / 1. Support to Community Re Single Stage - One E Acquisition de 50 tablettes p IDA / 57510 A posteriori Demande de prix Limited 25,000.00 0.00 Annulé 2018-02-10 2018-04-07 2018-10-04 silience nvelope our MIS de Kalemie et filières agricoles ZR-FSRDC-49609-GO-RFQ / Acquisition de 7 groupes mot opompes pour Brigade d'entr Single Stage - One E etien -THIMO IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2018-03-12 2018-05-07 2018-11-03 nvelope 1) Lot 1: Nord Kivu (2), 2) Lot 2: Sud Kivu (2), 3) Lot 3: Ituri (1), 4)Lot 4: Haut Uele (1), 5) Lot 5: Tanganyika (1) ZR-FSRDC-120255-GO-RFQ / Acquisition de 8 motos pour I Single Stage - One E IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 36,000.00 0.00 Annulé 2019-06-26 2019-08-21 2020-02-17 PAPEL et SENASEM pour la pr nvelope ovince de Tanganyika ZR-FSRDC-228078-GO-RFQ / Acquisition de deux générate Single Stage - One E urs de 20 KVA pour les bâtim IDA / 66650 4. Project Management A posteriori Demande de prix Limited 50,000.00 30,628.00 Signé 2021-04-17 2021-05-13 2021-06-12 2021-07-16 2021-12-09 nvelope ents du FSRDC/Antennes du Nord Ubangi et Kasaï Central Page 1 ZR-FSRDC-120248-GO-RFQ / Acquisition de 2 Véhicules 4 Single Stage - One E IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2019-06-27 2019-08-22 2020-02-18 X 4 cinq portes pour IPAPEL e nvelope t SENASEM pour la province de Tanganyika ZR-FSRDC-121711-GO-RFQ / Acquisition de trois (3) appar Single Stage - One E eils Topographique Station T IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 50,000.00 0.00 Annulé 2019-07-18 2019-09-12 2020-03-10 nvelope otale pour OVD dans les prov inces de Tshopo, Ituri et Tan ganyika ZR-FSRDC-49229-GO-RFQ / Acquisition de 5 vehicules ad ditionnelles pour les partenai Single Stage - One E IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 225,000.00 0.00 Annulé 2018-03-05 2018-04-30 2018-10-27 res institutionnelles (OVD Bu nvelope nia 1,OVD Kisangani 1, OVD Bukavu 1 OVD Kalemie 1 et OVD Nord Kivu) ZR-FSRDC-49623-GO-RFQ / Acquisition de 36 motos - po ur OVD (10) et Carg (26) Single Stage - One E 1) Lot 1: Nord Kivu (9), 2) IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 90,000.00 0.00 Annulé 2018-03-10 2018-05-05 2018-11-01 nvelope Lot 2: Sud Kivu (9), 3) Lot 3: Ituri (9), 4)Lot 4: Haut Uele (5), 5) Lot 5: Tanganyika (2) et 6) Lot 6: Tshopo (2) ZR-FSRDC-51040-GO-RFB / A Single Stage - One E cquisition de 6 Kits pour Mini- IDA / 57510 3. Capacity Building A posteriori Appel d'offres Open - National 120,000.00 0.00 Annulé 2018-03-07 2018-03-12 2018-04-23 2018-05-23 2018-06-27 2018-12-24 nvelope LABOSEM physique dans un corridor ZR-FSRDC-49377-GO-RFQ / Acquisition de 14 tronçonneu ses pour Brigade d'entretien Single Stage - One E IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 38,000.00 0.00 Annulé 2018-03-06 2018-05-01 2018-10-28 -THIMO: 1) Lot 1: Nord Kivu ( nvelope 4); 2) Lot 2: Sud Kivu (4); 3 ) Lot 3; Ituri (2); 4)Lot 4: Hau t Uele (2)); 5) Lot 5: Tanganyi ka (2) ZR-FSRDC-49335-GO-RFQ / Acquisition de 10 compacteu rs manuels pour Brigade d'en tretien -THIMO - OVD Single Stage - One E IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 140,000.00 0.00 Annulé 2018-03-05 2018-05-03 2018-04-30 2018-10-27 1) Lot 1: Nord Kivu (2), 2) nvelope Lot 2: Sud Kivu (2), 3) Lot 3: Ituri (2), 4)Lot 4: Tshopo (2 ), 5) Lot 5: Tanganyika (2) ZR-FSRDC-244139-GO-RFQ / Single Stage - One E Acquisition de onze (11) Tabl IDA / 66650 4. Project Management A posteriori Demande de prix Limited 3,300.00 0.00 Annulé 2021-08-21 2021-10-16 2022-04-14 nvelope ettes enquêteurs pour YAKO MA ZR-FSRDC-244164-GO-RFQ / Single Stage - One E Acquisition de vingt (20) tabl IDA / 66650 4. Project Management A posteriori Demande de prix Limited 6,000.00 0.00 Annulé 2021-08-21 2021-10-16 2022-04-14 nvelope ettes pour les enquêteurs de GOMA ZR-FSRDC-244198-GO-RFQ / Acquisition de quarante un (4 Single Stage - One E IDA / 66650 4. Project Management A posteriori Demande de prix Limited 12,300.00 0.00 Annulé 2021-08-21 2021-10-16 2022-04-14 1) tablettes pour les enquête nvelope urs pour BUKAVU et UVIRA ZR-FSRDC-244224-GO-RFQ / Single Stage - One E Acquisition vingt neuf (29) ta IDA / 66650 4. Project Management A posteriori Demande de prix Limited 8,700.00 0.00 Annulé 2021-08-21 2021-10-16 2022-04-14 nvelope blettes enquêteurs pour BUNI A ZR-FSRDC-251678-GO-RFQ / Acquisition de 97 kits smartp hones pour le Suivi-Evaluatio 2. Livelihoods and Employm Single Stage - One E IDA / 66650 A posteriori Demande de prix Limited 34,000.00 38,315.00 Signé 2021-09-11 2021-09-08 2021-11-06 2021-10-19 2022-05-05 n et le Transfert Monétaire In ent Generation nvelope conditionnel pour le Nord Ub angi, Kasaï Central et Sud Kiv u. ZR-FSRDC-251682-GO-RFQ / Acquisition de matériels infor mations pour le TMI, en deux lots. 2. Livelihoods and Employm Single Stage - One E Lot 1: 4 imprimantes, 67 rub IDA / 66650 A posteriori Demande de prix Limited 30,000.00 20,115.00 Signé 2021-09-11 2021-09-08 2021-11-06 2021-10-19 2022-05-05 ent Generation nvelope ans d'impression, 22 cartes v ierges PVC, 20 kits de nettoy age et 4 logiciels d'impressio n de badges Lot 2: 10 kits tablettes et 4 o rdinateurs portables ZR-FSRDC-232729-GO-RFQ / Acquisition de 6 véhicules 4x Single Stage - One E 4 munis d'équipement de co IDA / 66650 4. Project Management A posteriori Demande de prix Limited 390,000.00 381,854.30 Signé 2021-07-20 2021-06-01 2021-09-14 2021-08-03 2022-03-13 nvelope mmunication pour les antenn es du Nord-Ubangi et Kasaï C entral ZR-FSRDC-244093-GO-RFQ / Acquisition des mobiliers de bureau pour le STEP II Lot 1 : Coordination générale Single Stage - One E Lot 2 : Kasaï Central IDA / 66650 4. Project Management A posteriori Demande de prix Limited 300,000.00 0.00 Annulé 2021-08-21 2021-10-16 2022-04-14 nvelope Lot 3 : Nord Ubangi Lot 4 : Nord Kivu Lot 5 : Sud Kivu Lot 6 : Ituri ZR-FSRDC-253625-GO-RFQ / Acquisition de 5 véhicules 4x Single Stage - One E 4 munis d'équipement de co IDA / 66650 4. Project Management A posteriori Demande de prix Limited 320,000.00 0.00 Annulé 2021-12-04 2022-01-29 2022-07-28 nvelope mmunication pour l'antenne du Sud-Kivu et Yakoma ZR-FSRDC-264842-GO-RFQ / (20): Acquisition de 19 véhic ules 4x4 munis d’équipemen ts de communication : Single Stage - One E En attente d' - Lot 1 : 5 véhicules pour le S IDA / 66650 4. Project Management A posteriori Demande de prix Limited 950,000.00 0.00 2022-03-21 2022-05-16 2022-11-12 nvelope exécution K - Lot 2 : 5 véhicules pour le N K - Lot 3 : 5 véhicules pour It - Lot 4 : 2 véhicules pour le N U Lot 5: 2 véhicules pour le K/ -ZR-FSRDC-264845-GO-RFQ Single Stage - One E En attente d' (21): C Acquisition de mobiliers IDA / 66650 4. Project Management A posteriori Demande de prix Limited 75,000.00 0.00 2022-03-15 2022-05-10 2022-11-06 nvelope exécution de bureau pour la Coordinati on Générale Page 2 ZR-FSRDC-285251-GO-DIR / Acquisition de quatre (4) vé hicules Land Cruiser Pick Up Passation de marc En cours d'ex cabine simple et de six (6) vé IDA / 66650 4. Project Management A posteriori Direct 588,520.00 0.00 2022-03-28 2022-03-25 2022-03-29 2022-03-25 2022-04-01 2022-04-15 hé de gré à gré écution hicules Land Cruiser Pick Up double cabines par ED avec Grands Lacs Motors CONGO ( GMLC) ZR-FSRDC-292851-GO-RFQ / Fourniture et installation d’u Single Stage - One E En attente d' IDA / 66650 4. Project Management A posteriori Demande de prix Limited 40,000.00 0.00 2022-07-31 2022-09-25 2023-03-24 n serveur pour une salle serv nvelope exécution eur de FSDRC et des activité s de CERC Kinshasa ZR-FSRDC-297925-GO-RFQ / Acquisition de matériels infor matiques pour le personnel d édié STEP II de l'Antenne de Single Stage - One E En attente d' Sud Ubangi IDA / 66650 4. Project Management A posteriori Demande de prix Limited 40,000.00 0.00 2022-08-27 2022-09-21 2022-10-21 nvelope exécution (3 Desk Top : CC, Cais. et Se crét.,- 13 lap top : CDECO, CT M, CTIC, CTHIMO, CSAES, CS E; CMEDAC, CPM, ASNV,CBD, AAF, Log. et réserve, Imprim ante couleur,...) ZR-FSRDC-317787-GO-RFQ / Acquisition de 16 motos de t errain, dont 10 pour les équi pes de zone (Sud-Kivu, Nord- Single Stage - One E En attente d' IDA / 66650 4. Project Management A posteriori Demande de prix Limited 80,000.00 0.00 2022-11-02 2022-12-28 2023-06-26 Kivu, Ituri, Nord-Ubangi et Ka nvelope exécution saï Central) et 6 pour les coo rdinations provinciales du Pro jet STEP II/Fonds Sociales (Su d-Kivu, Nord-Kivu et Ituri) ZR-FSRDC-314462-GO-RFQ / Acquisition des fournitures d Single Stage - One E En attente d' IDA / 66650 4. Project Management A posteriori Demande de prix Limited 12,000.00 0.00 2022-11-02 2022-12-28 2023-06-26 e bureau pour le STEP II - Co nvelope exécution ordination Générale (Besoin de 6 mois) ZR-FSRDC-317793-GO-RFQ / Acquisition des Fournitures e Single Stage - One E En attente d' IDA / D8440 5. CERC A posteriori Demande de prix Limited 12,000.00 0.00 2022-10-31 2022-12-26 2023-06-24 t consommables de bureau e nvelope exécution t Informatiques pour le CERC KIN ZR-FSRDC-317792-GO-RFQ / Single Stage - One E En attente d' Acquisition des Equipements IDA / D8440 5. CERC A posteriori Demande de prix Limited 50,000.00 0.00 2022-10-29 2022-12-24 2023-06-22 nvelope exécution informatiques et télécom pou r le CERC KIN NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-139684-NC-RFQ / Recrutement d'un Consultant firme/individuel pour la tradu 1. Support to Community Re Single Stage - One E IDA / 57510 A posteriori Demande de prix Limited 3,500.00 0.00 Annulé 2019-10-11 2019-10-22 2020-04-19 ction de documents de travai silience nvelope l du Fonds Social de la RDC d u Français en Anglais et de l' Anglais en Français. ZR-FSRDC-236411-NC-RFQ / Impression et fourniture des Single Stage - One E En attente d' IDA / 66650 5. CERC A posteriori Demande de prix Limited 4,975.00 0.00 2021-03-01 2021-04-26 2021-10-23 supports de visibilité pour la nvelope exécution distribution du cash à Kinsha sa ZR-FSRDC-236346-NC-RFQ / Impression et fourniture de 1 Single Stage - One E En attente d' IDA / 66650 5. CERC A posteriori Demande de prix Limited 4,534.40 0.00 2021-02-23 2021-04-20 2021-10-17 00 000 flyers et 1 000 affiche nvelope exécution s pour la distribution du Cash à Kinshasa ZR-FSRDC-236549-NC-RFQ / Mise en place et suivi d’une c Single Stage - One E En attente d' IDA / 66650 5. CERC A posteriori Demande de prix Open - National 419,220.00 0.00 2021-01-10 2021-03-07 2021-09-03 ollecte de données par télép nvelope exécution hone mobile dans la ville de Kinshasa ZR-FSRDC-190923-NC-RFB / Recrutement des prestataire Single Stage - One E IDA / 66650 5. CERC A priori Appel d'offres Limited 2,000,000.00 0.00 Annulé 2020-08-28 2020-09-02 2020-09-01 2020-09-06 2020-10-01 2020-10-16 2020-11-09 2020-11-18 de Services de Paiements Di nvelope gitaux des Bénéficiaires STEP -Kinshasa ZR-FSRDC-236334-NC-RFQ / Selection d'une entreprise po Single Stage - One E En attente d' IDA / 66650 5. CERC A posteriori Demande de prix Limited 205,737.84 0.00 2021-02-02 2021-03-30 2021-09-26 ur assurer les Services de Pai nvelope exécution ements Digitaux des Bénéfici aires STEP-Kinshasa ZR-FSRDC-245007-NC-DIR / Recrutement par entente dir Passation de marc ecte de l'entreprise AFRIMON IDA / 66650 5. CERC A posteriori Direct 765,000.00 261,000.00 Signé 2021-08-22 2021-07-07 2021-08-27 2021-07-30 2021-10-01 2021-08-03 2022-03-30 hé de gré à gré EY pour assurer le service de paiements digitaux des béné ficiaires STEP Kinshasa. ZR-FSRDC-319455-NC-RFQ / Single Stage - One E En attente d' Impression de Supports de c IDA / D8440 5. CERC A posteriori Demande de prix Limited 44,000.00 0.00 2022-10-29 2022-12-24 2023-06-22 nvelope exécution ommunications pour le CERC KIN ZR-FSRDC-319457-NC-RFQ / Single Stage - One E En attente d' Sélection d’une Agence de co IDA / D8440 5. CERC A posteriori Demande de prix Limited 37,500.00 0.00 2022-10-29 2022-12-24 2023-06-22 nvelope exécution mmunication pour le CERC KI N ZR-FSRDC-322623-NC-DIR / Recrutement d'AFRIMONEY p Passation de marc En attente d' our l'accompagnement dans IDA / D8440 5. CERC A posteriori Direct - National 204,600.00 0.00 2022-10-24 2022-10-29 2022-12-03 2023-06-01 hé de gré à gré exécution l'implémentation du paiemen t digital du projet STEP KIN 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 ZR-FSRDC-46218-CS-UN / Re crutement de FAO pour la mi Passation de marc se en œuvre des filières agric 2. Livelihoods and Employm IDA / 57510 A priori hés auprès des ag Direct 1,294,186.00 1,508,910.79 Signé 2018-02-10 2018-06-21 2018-08-09 oles dans le corridor Kalemie ent Generation ences de l'ONU -Nyunzu - bassins de Kyoko, Kasanga-Nyemba et Kisunkul u, Province de Tanganyika ZR-FSRDC-46235-CS-FBS / R ecrutement d'une ONG parte Sélection dans le naire de la mise en œuvre de 2. Livelihoods and Employm IDA / 57510 A posteriori cadre d'un budget Open - National 365,880.00 0.00 Annulé 2018-01-26 2018-01-26 2018-01-29 2018-01-29 2018-02-09 2018-03-10 2018-03-18 2020-07-05 s filières agricoles dans le ba ent Generation déterminé ssin de Panda, corridor de Ka lemie- Nyunzu, Province de T anganyika ZR-FSRDC-121707-CS-QCBS / Recruitment d'un consultan t pour la réalisation d' Audit t Sélection fondée s 1. Support to Community Re Open - Internationa echnique externe du Projet p IDA / 57510 A posteriori ur la qualité et le 450,000.00 0.00 Annulé 2019-07-08 2019-07-10 2019-07-13 2019-07-14 2019-07-16 2019-07-18 2019-07-21 2020-07-20 silience l our la Stabilisation de l'Est d coût e la RDC pour la Paix "STEP" pour les exercices 2017, 201 8 et 2019, ZR-FSRDC-46241-CS-QCBS / Recruitement d'un consultan Sélection fondée s 1. Support to Community Re Open - Internationa t pour la réalisation de audit IDA / 57510 A posteriori ur la qualité et le 100,000.00 0.00 Annulé 2018-02-01 2018-02-02 2018-02-04 2018-02-05 2018-02-15 2018-02-25 2018-03-09 2019-03-09 silience l financier et comptable des e coût xercices 2017, 2018 et 2019 ZR-FSRDC-87769-CS-CQS / R ecrutement d'un Consultant-f Sélection fondée s 2. Livelihoods and Employm irme pour mener l'enquête fi IDA / 57510 A posteriori ur les qualification Open - National 300,000.00 0.00 Annulé 2018-11-23 2018-11-07 2018-11-26 2018-12-10 2018-12-14 2018-12-31 2019-03-29 ent Generation nale d'évaluation d'impact de s des consultants la composante THIMO urbain du Projet STEP. ZR-FSRDC-252569-CS-QCBS / Recrutement d'un Consulta nt (firme) chargé de l'audit fi Sélection fondée s Open - Internationa En cours d'exécut nancier et comptable du Proj IDA / 66650 4. Project Management A posteriori ur la qualité et le 100,000.00 0.00 2021-11-01 2021-10-18 2021-11-22 2022-01-05 2022-02-02 2022-03-04 2022-04-08 2022-05-13 2023-05-13 l ion et pour la Stabilisation de l'E coût st de la RDC pour la Paix "ST EP 2" (Exercices 2020, 2021 et 2022) ZR-FSRDC-244043-CS-CQS / Recrutement d’une Structure Sélection fondée s chargée du Renforcement de 2. Livelihoods and Employm IDA / 66650 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2021-08-16 2021-09-29 2021-09-06 2021-10-20 2021-11-19 2021-12-24 2022-06-22 Capacités en MEDAC des Bén ent Generation s des consultants éficiaires THIMO de 1 500 bé néficiaires de la ville de Diba ya ZR-FSRDC-244041-CS-CQS / Recrutement d’une Structure Sélection fondée s chargée du Renforcement de 2. Livelihoods and Employm IDA / 66650 A posteriori ur les qualification Open - National 100,000.00 0.00 Annulé 2021-08-16 2021-09-29 2021-09-06 2021-10-20 2021-11-19 2021-12-24 2022-06-22 Capacités en MEDAC des Bén ent Generation s des consultants éficiaires THIMO de 1 250 bé néficiaires de la ville de Tshi mbulu ZR-FSRDC-315552-CS-QCBS / Recrutement d'un Consulta nt (firme) chargé de l'audit fi nancier externe du Fonds soc Sélection fondée s Open - Internationa En cours d'exécut ial de la République «FSRDC IDA / 66650 4. Project Management A posteriori ur la qualité et le 75,000.00 0.00 2022-10-04 2022-10-11 2022-10-25 2022-12-08 2023-01-05 2023-02-04 2023-03-11 2023-04-15 2024-04-14 l ion », du Projet pour la Stabilisati coût on de l’Est de la RDC pour la Paix–Financements Additionn els 2 et 3 «STEP» (Exercices 2022, 2023 et la clôture) ZR-FSRDC-319458-CS-CQS / Sélection fondée s Recrutement d’un cabinet po En attente d'exéc IDA / D8440 5. CERC A posteriori ur les qualification Open - National 200,000.00 0.00 2022-10-24 2022-11-14 2022-12-28 2023-01-27 2023-03-03 2023-08-30 ur l’étude d’évaluation pour l ution s des consultants e projet (CERC KIN) ZR-FSRDC-319459-CS-CQS / Sélection fondée s Recrutement d’un prestatair En attente d'exéc IDA / D8440 5. CERC A posteriori ur les qualification Open - National 100,000.00 0.00 2022-10-26 2022-11-16 2022-12-30 2023-01-29 2023-03-05 2023-09-01 e pour les mesures d'accomp ution s des consultants agnement des bénéficiaires p our le CERC KIN INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-110894-CS-CDS / Recrutement de l'Institut Na Sélection de cons tional de Préparation Professi 1. Support to Community Re IDA / 57510 A priori ultants par entent Direct 400,000.00 0.00 Annulé 2019-04-19 2020-02-16 2019-04-29 2019-07-03 2019-12-30 onnel « INPP » pour la forma silience e directe tion des bénéficiaires « THIM O sociaux », deuxième phase ZR-FSRDC-232840-CS-INDV / En cours d'exécut Recrutement d'un Spécialiste IDA / 66650 4. Project Management A posteriori Individuel Open 42,000.00 0.00 2021-06-15 2021-07-23 2021-08-03 2021-08-24 2021-09-28 2022-03-27 ion , Expert en MEDAC du Projet STEP 2 ZR-FSRDC-232849-CS-INDV / En cours d'exécut Recrutement d'un Assistant IDA / 66650 4. Project Management A posteriori Individuel Open 24,000.00 0.00 2021-06-15 2021-11-11 2021-08-03 2021-08-24 2021-09-28 2022-03-27 ion Comptable pour le Projet STE P ZR-FSRDC-232851-CS-INDV / Contractualisation par entent En cours d'exécut e directe de Monsieur Guy B IDA / 66650 4. Project Management A posteriori Individuel Direct 24,000.00 0.00 2021-06-15 2021-06-29 2021-06-25 2021-07-16 2021-08-20 2022-02-16 ion UKALANGI comme Assistant du Chargé des Opérations du Projet STEP 2 ZR-FSRDC-232854-CS-INDV / En cours d'exécut Recrutement d'un Consultant IDA / 66650 4. Project Management A posteriori Individuel Limited 12,000.00 0.00 2021-06-15 2021-07-23 2021-06-20 2021-07-11 2021-08-15 2022-02-11 ion Secrétaire Réceptionniste du Projet STEP 2 ZR-FSRDC-232859-CS-INDV / IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 Annulé 2021-07-30 2021-07-23 2021-09-17 2021-10-08 2021-11-12 2022-05-11 Chargé du Transfert Monétair e/KC ZR-FSRDC-232860-CS-INDV / IDA / 66650 4. Project Management A posteriori Individuel Open 18,000.00 0.00 Annulé 2021-08-31 2021-06-01 2021-10-19 2021-11-09 2021-12-14 2022-06-12 Assistant Administratif et Fin ancier/KC Page 4 ZR-FSRDC-232867-CS-INDV / IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 Annulé 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 Chargé de MGP/KC ZR-FSRDC-232866-CS-INDV / Recrutement d'un Assistant e En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 24,000.00 0.00 2021-06-15 2021-09-20 2021-08-03 2021-08-24 2021-09-28 2022-03-27 n Base de Données (gestion ion du système intégré/MIS) du P rojet STEP 2 ZR-FSRDC-232868-CS-INDV / Recrutement d'un Consultant IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 Annulé 2021-06-15 2021-07-23 2021-08-03 2021-08-24 2021-09-28 2022-03-27 Chargé de Transfert Monétair e à l'antenne du Nord Ubangi ZR-FSRDC-232870-CS-INDV / Consultant chargé de la com En attente d'exéc ptabilité pour le Contingent E IDA / 66650 5. CERC A posteriori Individuel Open 39,600.00 0.00 2021-07-12 2021-08-30 2021-09-20 2021-10-25 2022-04-23 ution mergency Response Compon ent ‘CERC-COVID19’ KINSHA SA ZR-FSRDC-232871-CS-INDV / Recrutement d'un Assistant IDA / 66650 4. Project Management A posteriori Individuel Limited 18,000.00 0.00 Annulé 2021-06-15 2021-07-23 2021-06-20 2021-07-11 2021-08-15 2022-02-11 Administratif et Financier du Projet STEP 2 ZR-FSRDC-232873-CS-INDV / En attente d'exéc Recrutement d'un Chauffeur IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 2021-06-15 2021-06-20 2021-07-11 2021-08-15 2022-02-11 ution n° 1 de Course du Projet STE P2 ZR-FSRDC-232874-CS-INDV / En attente d'exéc Recrutement d'un Chauffeur IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 2021-06-15 2021-06-20 2021-07-11 2021-08-15 2022-02-11 ution n° 2 du Projet STEP 2 ZR-FSRDC-232876-CS-INDV / En attente d'exéc Recrutement d'un Chauffeur IDA / 66650 4. Project Management A posteriori Individuel Limited 12,020.00 0.00 2021-06-15 2021-06-20 2021-07-11 2021-08-15 2022-02-11 ution N) 3 du Projet STEP 2 ZR-FSRDC-191751-CS-INDV / En attente d'exéc Recrutement du Chargé des IDA / 66650 4. Project Management A posteriori Individuel Direct 62,400.00 0.00 2020-09-07 2020-09-11 2020-09-13 2020-09-17 2020-10-23 ution Opérations du STEP 2 (Franç ois Kabemba) ZR-FSRDC-236044-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236371-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236103-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236422-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236096-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236351-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236110-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236045-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236403-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236369-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236087-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236376-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236515-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236370-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236352-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236278-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236146-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236112-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236528-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236409-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236402-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236135-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation Page 5 ZR-FSRDC-236382-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236530-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236046-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236154-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236532-CS-INDV / 2. Livelihoods and Employm IDA / 66650 A posteriori Individuel Open 1,800.00 0.00 Annulé 2020-11-24 2021-01-12 2021-02-02 2021-03-09 2021-09-05 Consultants Enquêteurs/KC ent Generation ZR-FSRDC-236137-CS-INDV / En attente d'exéc Spécialiste en Sauvegardes E IDA / 66650 4. Project Management A posteriori Individuel Open 57,810.00 0.00 2021-04-05 2021-05-24 2021-06-14 2021-07-19 2022-01-15 ution nvironnementales ZR-FSRDC-236357-CS-INDV / En attente d'exéc Spécialiste en Suivi et Evalua IDA / 66650 4. Project Management A posteriori Individuel Open 52,800.00 0.00 2021-01-10 2021-02-28 2021-03-21 2021-04-25 2021-10-22 ution tion STEP 2 ZR-FSRDC-236506-CS-INDV / Contractualisation avec le Co En cours d'exécut nsultant Yves MISSIATU com IDA / 66650 4. Project Management A posteriori Individuel Direct 24,600.00 0.00 2021-04-01 2021-03-04 2021-04-11 2021-05-02 2021-06-06 2021-12-03 ion me Assistant en Passation de s Marches du Projet STEP 2 ZR-FSRDC-235770-CS-INDV / Contractualisation avec le Co En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Direct 62,400.00 0.00 2020-08-24 2020-09-03 2020-09-24 2020-10-29 2021-04-27 nsultant Francois KABEMBA c ution omme Chargé des Opération s du Projet STEP 2 ZR-FSRDC-235768-CS-INDV / Contractualisation avec le Co En cours d'exécut nsultant Claude OGOU comm IDA / 66650 4. Project Management A posteriori Individuel Direct 117,730.00 0.00 2021-03-22 2021-03-05 2021-04-01 2021-04-22 2021-05-27 2021-11-23 ion e Assistant Technique en Pas sation des Marchés du Projet STEP 2 ZR-FSRDC-236005-CS-INDV / Contractualisation avec le Co En cours d'exécut nsultant Magnant MUBONGE IDA / 66650 4. Project Management A posteriori Individuel Direct 54,000.00 0.00 2020-10-14 2020-09-29 2020-10-24 2020-11-14 2020-12-19 2021-06-17 ion MUKULUMANYA comme Spéc ialiste en Sauvegardes Social es du Projet STEP 2 ZR-FSRDC-236006-CS-INDV / Contractualisation avec la Co En attente d'exéc nsultante Sylvie LUZALA com IDA / 66650 4. Project Management A posteriori Individuel Direct 22,560.00 0.00 2020-10-19 2020-10-29 2020-11-19 2020-12-24 2021-06-22 ution me Assistant du Chargé des Opérations du Projet STEP 2 ( Administration-RH) ZR-FSRDC-236534-CS-INDV / Contractualisation avec le Co En cours d'exécut nsultant Ademar NAMUISI KI IDA / 66650 4. Project Management A posteriori Individuel Direct 12,240.00 0.00 2021-01-06 2021-01-05 2021-01-16 2021-02-06 2021-03-13 2021-09-09 ion NABUNA comme Chauffeur d u Chargé des Opérations du Projet STEP 2 ZR-FSRDC-236164-CS-INDV / Contractualisation avec le Co En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Direct 12,240.00 0.00 2021-01-06 2021-01-05 2021-01-16 2021-02-06 2021-03-13 2021-09-09 nsultant D'Acquin NZAU DIM ion AVINGA comme Chauffeur du Projet STEP 2 ZR-FSRDC-235773-CS-INDV / Contractualisation avec le Co En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Direct 18,480.00 0.00 2020-10-16 2020-09-29 2020-10-26 2020-11-16 2020-12-21 2021-06-19 nsultant Adeline M'BUY MAN ion DEAK comme Caissière du Pr ojet STEP 2 ZR-FSRDC-236525-CS-INDV / Contractualisation avec le Co En cours d'exécut nsultant Bernard TSHISHIKU IDA / 66650 4. Project Management A posteriori Individuel Direct 47,860.00 0.00 2020-11-23 2020-11-11 2020-12-03 2020-12-24 2021-01-28 2021-07-27 ion BULULU comme Chargé de la Comptabilité à l'antenne du Kasai Central ZR-FSRDC-236053-CS-INDV / Contractualisation avec le Co nsultant Raymond BWANAHE En cours d'exécut RI MAPISANO comme Chargé IDA / 66650 4. Project Management A posteriori Individuel Direct 47,860.00 0.00 2021-02-15 2021-01-25 2021-02-25 2021-03-18 2021-04-22 2021-10-19 ion de Développement Commun autaire et Gestion des Conflit s à l'antenne du Kasai Centra l dans la le cadre du Projet S TEP 2 ZR-FSRDC-236057-CS-INDV / Contractualisation avec le Co nsultant Joslin KAMADILU TS En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Direct 44,400.00 0.00 2021-03-02 2021-03-12 2021-04-02 2021-05-07 2021-11-03 HIPAMBULA comme Chargé d ution e Suivi et Evaluation à l'angt enne du Kasai Central dans l e cadre du Projet STEP 2 ZR-FSRDC-235697-CS-INDV / Contractualisation avec le Co nsultant Zacharie MASIALA L En cours d'exécut ELI-VAKANDA comme Spécial IDA / 66650 4. Project Management A posteriori Individuel Direct 41,250.00 0.00 2021-02-15 2021-01-25 2021-02-25 2021-03-18 2021-04-22 2021-10-19 ion iste en Travaux d'Infrastructu res Communautaires à l'ante nne du Kasai Central dans le cadre du Projet STEP 2 ZR-FSRDC-236148-CS-INDV / Contractualisation avec le Co En cours d'exécut nsultant Titien LIKONDJI BAA IDA / 66650 4. Project Management A posteriori Individuel Direct 48,110.00 0.00 2020-10-14 2020-09-29 2020-10-24 2020-11-14 2020-12-19 2021-06-17 ion TA comme Spécialiste en Infr astructure au sein du Projet S TEP 2 ZR-FSRDC-236330-CS-INDV / Contractualisation avec le Co nsultant Serge MUFENGI NZO En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Direct 49,200.00 0.00 2020-10-20 2020-09-29 2020-10-30 2020-11-20 2020-12-25 2021-06-23 FU comme Spécialiste en Tra ion vaux à Haute Intensité de Ma in d’œuvre au sein du Projet STEP 2 ZR-FSRDC-236076-CS-INDV / En attente d'exéc Chargé en Travaux à Haute I IDA / 66650 4. Project Management A posteriori Individuel Open 56,000.00 0.00 2021-04-06 2021-05-25 2021-06-15 2021-07-20 2022-01-16 ution ntensité de Main d’œuvre Page 6 ZR-FSRDC-236166-CS-INDV / En attente d'exéc Chargé des Sauvegardes Env IDA / 66650 4. Project Management A posteriori Individuel Open 49,200.00 0.00 2021-04-06 2021-05-25 2021-06-15 2021-07-20 2022-01-16 ution ironnementales et Sociales ZR-FSRDC-235776-CS-INDV / Contractualisation avec le Co En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Direct 12,240.00 0.00 2021-04-19 2021-01-05 2021-04-29 2021-05-20 2021-06-24 2021-12-21 nsultant Serge ZOLA KIAMA c ion omme Chauffeur du Projet ST EP 2 ZR-FSRDC-236078-CS-INDV / En attente d'exéc Spécialiste en Base de Donn IDA / 66650 5. CERC A posteriori Individuel Open 108,965.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ution ées du CERC-STEP2 ZR-FSRDC-236009-CS-INDV / En attente d'exéc Assistant en Mécanisme de G IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 2021-03-29 2021-04-03 2021-04-24 2021-05-29 2021-11-25 ution estion des Plaintes CERC Kin ZR-FSRDC-236332-CS-INDV / Chargé du suivi des activités En attente d'exéc IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 2021-04-02 2021-04-07 2021-04-28 2021-06-02 2021-11-29 de transfert monétaire dans l ution e cadre du STEP-Kin ZR-FSRDC-236083-CS-INDV / Chargé du suivi des activités En attente d'exéc IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 2021-04-02 2021-04-07 2021-04-28 2021-06-02 2021-11-29 de transfert monétaire dans l ution e cadre du STEP-Kin ZR-FSRDC-236027-CS-INDV / Chargé du suivi des activités En attente d'exéc IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 2021-04-02 2021-04-07 2021-04-28 2021-06-02 2021-11-29 de transfert monétaire dans l ution e cadre du STEP-Kin ZR-FSRDC-236036-CS-INDV / Chargé du suivi des activités En attente d'exéc IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 2021-04-05 2021-04-10 2021-05-01 2021-06-05 2021-12-02 de transfert monétaire dans l ution e cadre du STEP-Kin ZR-FSRDC-236404-CS-INDV / Chargé du suivi des activités En attente d'exéc IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 2021-04-07 2021-04-12 2021-05-03 2021-06-07 2021-12-04 de transfert monétaire dans l ution e cadre du STEP-Kin ZR-FSRDC-236388-CS-INDV / En attente d'exéc IDA / 66650 5. CERC A posteriori Individuel Open 44,700.00 0.00 2020-10-05 2020-11-23 2020-12-14 2021-01-18 2021-07-17 Expert en Transfert Monétair ution e du CERC ZR-FSRDC-236040-CS-INDV / Chargé du suivi des mécanis IDA / 66650 5. CERC A posteriori Individuel Limited 12,300.00 0.00 Annulé 2021-04-01 2021-04-06 2021-04-27 2021-06-01 2021-11-28 mes de gestion des plaintes du STEP2 ZR-FSRDC-237048-CS-INDV / En cours d'exécut Contractualisation au poste d IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 2021-06-30 2021-06-15 2021-07-10 2021-07-31 2021-09-04 2022-03-03 ion e MEDAC avec Adolphe NAKA KULA ZR-FSRDC-237050-CS-INDV / IDA / 66650 4. Project Management A posteriori Individuel Limited 9,000.00 0.00 Annulé 2021-07-30 2021-08-04 2021-08-25 2021-09-29 2022-03-28 Recrutement d'un MGP Kasaï Central ZR-FSRDC-191792-CS-INDV / En attente d'exéc Recrutement du Responsable IDA / 66650 4. Project Management A posteriori Individuel Open 50,400.00 0.00 2020-09-07 2020-09-21 2020-10-12 2020-11-16 2021-05-15 ution Administratif et Financier du STEP 2 ZR-FSRDC-191764-CS-INDV / En attente d'exéc Recrutement du Spécialiste e IDA / 57510 4. Project Management A posteriori Individuel Open 50,400.00 0.00 2020-09-07 2020-09-24 2020-10-01 2020-10-22 2021-10-17 ution n Passation des Marchés du P rojet STEP 2 ZR-FSRDC-141795-CS-INDV / Recrutement d'un Consultant Individuel pour réaliser la mis 1. Support to Community Re sion d’élaborer le Cadre de P IDA / 57510 A posteriori Individuel Limited 35,000.00 0.00 Annulé 2019-10-22 2019-10-24 2019-10-25 2019-10-28 2019-11-12 silience olitique de Réinstallation (CP R) du Projet de STEP - FA dan s les provinces de Kasai, Kas ai Oriental et Kasai Central ZR-FSRDC-141821-CS-INDV / Recrutement d'un Consultant Individuel pour réaliser la mis sion d’élaborer le Cadre de G 1. Support to Community Re IDA / 57510 A posteriori Individuel Limited 35,000.00 0.00 Annulé 2019-10-22 2019-10-25 2019-10-26 2019-10-29 2019-11-13 estion Environnementale et S silience ociale (CGES) du Projet de ST EP - FA dans les provinces de Kasai, Kasai Oriental et Kasai Central ZR-FSRDC-120259-CS-INDV / Recrutement de consultants i 1. Support to Community Re En attente d'exéc IDA / 57510 A posteriori Individuel Limited 50,000.00 0.00 2019-06-30 2019-07-02 2019-07-07 2019-07-17 2019-07-23 ndividuels/panels pour appuy silience ution er le FSRDC dans les évaluati ons des offres. ZR-FSRDC-236830-CS-CDS / recrutement du consultant Gi Sélection de cons 1. Support to Community Re En cours d'exécut veDirectly, pour la mise en œ IDA / 66650 A posteriori ultants par entent Direct 735,000.00 0.00 2021-06-30 2021-06-17 2021-07-10 2021-09-13 2022-03-12 silience ion uvre du Pilote MobileAid dans e directe le cadre du programme STEP KIN ZR-FSRDC-240661-CS-INDV / Recrutement d'un Assistant T En cours d'exécut IDA / 66650 5. CERC A posteriori Individuel Open 54,000.00 0.00 2021-06-30 2021-06-25 2021-08-18 2021-09-08 2021-10-13 2022-04-11 echnique International en tra ion nsferts monétaires ZR-FSRDC-244084-CS-INDV / Consultant pour appuyer la C En attente d'exéc IDA / 66650 3. Capacity Building A posteriori Individuel Open 45,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 NR dans la transmission et g ution estion de la base de données ZR-FSRDC-244089-CS-INDV / Recrutement d’un Spécialiste En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 100,000.00 0.00 2021-08-16 2021-07-29 2021-10-04 2021-10-25 2021-11-29 2022-05-28 en Développement Commun ion autaire du STEP 2 ZR-FSRDC-244090-CS-INDV / En cours d'exécut Recrutement d’un Chef Com IDA / 66650 4. Project Management A posteriori Individuel Open 80,000.00 0.00 2021-08-16 2021-06-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 ion ptable du STEP 2 Page 7 ZR-FSRDC-244095-CS-CDS / Mise en œuvre de l’enquête Sélection de cons par téléphone auprès des mé IDA / 66650 3. Capacity Building A posteriori ultants par entent Direct 55,000.00 44,330.00 Signé 2021-08-16 2021-08-13 2021-08-26 2021-08-27 2021-10-30 2021-09-06 2022-04-28 nages issus de l’ECVM Kinsha e directe sa pour mesurer l’impact du Covid-19 (avec l’Institut Nati onal Statistique) ZR-FSRDC-244097-CS-INDV / Recrutement d'un(e) Assista IDA / 66650 4. Project Management A posteriori Individuel Limited 25,000.00 0.00 Annulé 2021-08-16 2021-08-21 2021-09-11 2021-10-16 2022-04-14 nt(e) en Communication pour le Projet STEP 2 ZR-FSRDC-244128-CS-INDV / Recrutement de dix (10) enq IDA / 66650 4. Project Management A posteriori Individuel Open 18,720.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 uêteurs pour le Kasaï Central (Tshimbulu_Rural) ZR-FSRDC-244129-CS-INDV / Recrutement d’un Chargé de Suivi des Mécanismes de Ges IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 tion des Plaintes du STEP 2 p our l’antenne du Nord Ubangi ZR-FSRDC-244132-CS-INDV / Recrutement d’un Assistant IDA / 66650 4. Project Management A posteriori Individuel Limited 25,000.00 0.00 Annulé 2021-08-16 2021-08-21 2021-09-11 2021-10-16 2022-04-14 Administratif et Financier du STEP 2 pour le Nord Ubangi ZR-FSRDC-244140-CS-INDV / En attente d'exéc Recrutement du Chargé de la IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 ution Comptabilité du STEP 2 pour le Nord Kivu ZR-FSRDC-244143-CS-INDV / Recrutement d’un Chargé de En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 s Travaux d'Infrastructure Co ution mmunautaire du STEP 2 pour le Nord Kivu ZR-FSRDC-244144-CS-INDV / Recrutement d’un Chargé de En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Suivi et Evaluation du STEP 2 ution pour le Nord Kivu ZR-FSRDC-244147-CS-INDV / En cours d'exécut Recrutement d’un Chargé ME IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-11 2021-10-04 2021-10-25 2021-11-29 2022-05-28 ion DAC du STEP 2 pour le Nord Kivu ZR-FSRDC-244148-CS-INDV / Recrutement d’un Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 MGP du STEP 2 pour le Nord Kivu ZR-FSRDC-244151-CS-INDV / Recrutement d’un Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Transfert Monétaire du STEP 2 pour le Nord Kivu ZR-FSRDC-244156-CS-INDV / Recrutement d’un Assistant IDA / 66650 4. Project Management A posteriori Individuel Open 25,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Administratif et Financier du STEP 2 pour le Nord Kivu ZR-FSRDC-244162-CS-INDV / Recrutement de dix sept (17) IDA / 66650 4. Project Management A posteriori Individuel Open 31,824.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 enquêteurs pour Goma dans le Nord Kivu ZR-FSRDC-244165-CS-INDV / En attente d'exéc Recrutement du Chargé de la IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 ution Comptabilité du STEP 2 pour le Sud Kivu ZR-FSRDC-244172-CS-INDV / Recrutement d’un Chargé de En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-22 2021-10-10 2021-10-31 2021-12-05 2022-06-03 Suivi et Evaluation du STEP 2 ution pour le Sud Kivu ZR-FSRDC-244173-CS-INDV / Recrutement d’un Chargé de En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 s Sauvegardes Environneme ution ntales et Sociales du STEP 2 pour le Sud Kivu ZR-FSRDC-244177-CS-INDV / En cours d'exécut Recrutement d’un Chargé ME IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-11 2021-10-04 2021-10-25 2021-11-29 2022-05-28 ion DAC du STEP 2 pour le Sud Ki vu ZR-FSRDC-244179-CS-INDV / Recrutement d’un Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 MGP du STEP 2 pour le Sud Ki vu ZR-FSRDC-244181-CS-INDV / Recrutement d’un Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Transfert Monétaire du STEP 2 pour le Sud Kivu ZR-FSRDC-244182-CS-INDV / Recrutement d’un Chargé de En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Passation des Marchés du ST ution EP 2 pour le Nord Kivu ZR-FSRDC-244188-CS-INDV / Recrutement d’un Assistant IDA / 66650 4. Project Management A posteriori Individuel Limited 25,000.00 0.00 Annulé 2021-08-16 2021-08-21 2021-09-11 2021-10-16 2022-04-14 Administratif et Financier du STEP 2 pour le Nord Kivu ZR-FSRDC-244191-CS-INDV / En attente d'exéc Recrutement de trois (3) cha IDA / 66650 4. Project Management A posteriori Individuel Limited 45,000.00 0.00 2021-08-16 2021-08-21 2021-09-11 2021-10-16 2022-04-14 ution uffeurs du STEP 2 pour le Su d Kivu ZR-FSRDC-244205-CS-INDV / Recrutement d’un Chargé de En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Direct 50,000.00 0.00 2021-08-16 2021-08-26 2021-09-16 2021-10-21 2022-04-19 s Travaux d'Infrastructure Co ution mmunautaire du STEP 2 pour l’Ituri Page 8 ZR-FSRDC-244207-CS-INDV / Recrutement d’un Chargé de En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 s Sauvegardes Environneme ution ntales et Sociales du STEP 2 pour l’Ituri ZR-FSRDC-244208-CS-INDV / Recrutement d’un Chargé en En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Travaux à Haute Intensité de ution Main d'Œuvre du STEP 2 pou r l’Ituri ZR-FSRDC-244211-CS-INDV / En cours d'exécut Recrutement d’un Chargé ME IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2021-08-16 2021-10-11 2021-10-04 2021-10-25 2021-11-29 2022-05-28 ion DAC du STEP 2 pour l’Ituri ZR-FSRDC-244213-CS-INDV / Recrutement d’un Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 MGP du STEP 2 pour l’Ituri ZR-FSRDC-244214-CS-INDV / Recrutement d’un Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Transfert Monétaire du STEP 2 pour l’Ituri ZR-FSRDC-244219-CS-INDV / Recrutement d’un Assistant IDA / 66650 4. Project Management A posteriori Individuel Limited 25,000.00 0.00 Annulé 2021-08-16 2021-08-21 2021-09-11 2021-10-16 2022-04-14 Administratif et Financier du STEP 2 pour l’Ituri ZR-FSRDC-244221-CS-INDV / En attente d'exéc Recrutement de 3 chauffeurs IDA / 66650 4. Project Management A posteriori Individuel Limited 45,000.00 0.00 2021-08-16 2021-08-21 2021-09-11 2021-10-16 2022-04-14 ution du STEP 2 pour l’antenne du Sud Kivu ZR-FSRDC-244223-CS-INDV / Recrutement de vingt quatre IDA / 66650 4. Project Management A posteriori Individuel Open 51,840.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 (24) enquêteurs pour l’Ituri ( Bunia) ZR-FSRDC-232836-CS-INDV / En cours d'exécut Recrutement d'un Assistant e IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 2021-08-23 2021-07-29 2021-08-28 2021-09-18 2021-10-23 2022-04-21 ion n Communication et TIC du P rojet STEP 2 ZR-FSRDC-245144-CS-CDS / Recrutement par entente dir ecte de l'Institut National de l Sélection de cons 'INS pour la poursuite de la En attente d'exéc IDA / 66650 5. CERC A posteriori ultants par entent Direct 52,448.00 0.00 2021-08-23 2021-09-02 2021-11-06 2022-05-05 mise en œuvre de l'enquête ution e directe par téléphone auprès des mé nages issus de de l'ECVM à K inshasa pour mesurer l'impac t du Covid-19 ZR-FSRDC-246412-CS-INDV / Recrutement de Cinq (5) Cha rgés en Transferts Monétaire s (CTM) subdivisé en 5 lots: Lo 1: CTM du Kasai Central; IDA / 66650 4. Project Management A posteriori Individuel Open 250,000.00 0.00 Annulé 2021-09-01 2021-08-07 2021-10-20 2021-11-10 2021-12-15 2022-06-13 Lot 2: CTM du Nord Ubangi; Lot 3: CTM du Nord Kivu; Lot 4: CTM du Sud Kivu; Lot 5: CTM de l'Ituri ZR-FSRDC-247147-CS-INDV / Recrutement de cinq (5) Cha rgés de Suivi du Numero Vert (CSNV) subdivisé en 5 lots: En cours d'exécut Lot 1: CSNV du Kasai Central IDA / 66650 4. Project Management A posteriori Individuel Limited 90,000.00 0.00 2021-09-06 2021-09-28 2021-09-27 2021-10-18 2021-11-22 2022-05-21 ion Lot 2: CSNV du Nord Ubangi Lot 3: CSNV du Nord Kivu Lot 4: CSNV du Sud Kivu Lot 5: CSNV de l'Ituri ZR-FSRDC-247148-CS-INDV / Recrutement de cinq (5) Assi stants Administratif et Financ ier (AAF) subdivisé en 5 lots: En attente d'exéc Lot 1: AAF du Kasai Central IDA / 66650 4. Project Management A posteriori Individuel Limited 90,000.00 0.00 2021-09-06 2021-09-11 2021-10-02 2021-11-06 2022-05-05 ution Lot 2: AAF du Nord Ubangi Lot 3: AAF du Nord Kivu Lot 4: AAF du Sud Kivu Lot 5: AAF de l'Ituri ZR-FSRDC-249785-CS-INDV / Recrutement de Cinq (5) Cha rgés en Transferts Monétaire s (CTM) pour les provinces su En cours d'exécut ivantes: IDA / 66650 4. Project Management A posteriori Individuel Limited 250,000.00 0.00 2021-09-30 2021-08-24 2021-10-12 2021-11-02 2021-12-07 2022-06-05 ion 1. La province du Kasai Centr al; 2. La province du Nord Uban gi; 3. La province du Sud Kivu. 4. La province du Nord Kivu ZR-FSRDC-244175-CS-INDV 5. La province d'Ituri / Recrutement d’un Chargé en IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Travaux à Haute Intensité de Main d'Œuvre du STEP 2 pou r le Sud Kivu ZR-FSRDC-244206-CS-INDV / Recrutement d’un Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 Suivi et Evaluation du STEP 2 pour l’Ituri ZR-FSRDC-244145-CS-INDV / Recrutement d’un Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 Annulé 2021-08-16 2021-10-04 2021-10-25 2021-11-29 2022-05-28 s Sauvegardes Environneme ntales et Sociales du STEP 2 pour le Nord Kivu ZR-FSRDC-253315-CS-INDV / Renouvellement du contrat d En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Direct 74,400.00 0.00 2021-09-20 2021-09-22 2021-09-23 2021-09-25 2021-09-26 u Chargé des Opération du S ution TEP II_ François KABEMBA ZR-FSRDC-253615-CS-INDV / Contractualisation par entent En cours d'exécut e directe avec Mr Alain KABO IDA / 66650 4. Project Management A posteriori Individuel Direct 40,000.00 0.00 2021-10-29 2021-09-22 2021-11-08 2021-11-29 2022-01-03 2022-07-02 ion NGO KUMWIMBA, Chargé de l a comptabilité au Sud-Kivu Page 9 ZR-FSRDC-253638-CS-INDV / Contractualisation par entent En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Direct 48,000.00 0.00 2021-10-15 2021-09-24 2021-10-17 2021-10-18 2021-10-20 2022-10-15 e directe avec Mr Pascal KIN ion GITSI KYAVULIKIRWA, CTIC a u Sud-Kivu ZR-FSRDC-253614-CS-INDV / Contractualisation par entent En cours d'exécut e directe avec Mr Polidor KAB IDA / 66650 5. CERC A posteriori Individuel Direct 52,000.00 0.00 2021-10-29 2021-09-28 2021-10-31 2021-11-01 2021-11-03 2022-10-29 ion ANGWE, Expert en Transfert Monétaire pour le CERC KIN ZR-FSRDC-252496-CS-CDS / Contractualisation par entent En cours d'exécut e directe avec Mr Christian R IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 2021-09-30 2021-09-24 2021-10-02 2021-10-03 2021-10-05 2022-09-30 ion aphaël NDAYE KABATANCHI, Chargé de Passation des Mar chés au Sud-Kivu ZR-FSRDC-252489-CS-CDS / Contractualisation par entent En cours d'exécut e directe avec Mr Augustin F IDA / 66650 4. Project Management A posteriori Individuel Direct 36,900.00 0.00 2021-09-30 2021-09-24 2021-10-02 2021-10-03 2021-10-05 2022-09-30 ion UABUNA DOMPETELO, Charg é de THIMO au Sud-Kivu ZR-FSRDC-257652-CS-INDV / (12): Recrutement d'un Char En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2021-11-15 2021-11-12 2022-01-03 2022-01-24 2022-02-28 2022-08-27 gé de Comptabilité du Projet ion STEP 2 pour l'antenne du Sud Kivu ZR-FSRDC-257656-CS-INDV / (13): Contractualisation par e ntente directe avec la Consul En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 2021-11-15 2021-11-11 2021-11-25 2021-11-24 2021-12-16 2021-11-25 2022-01-20 2022-07-19 tante Julie Patricia GILABI NGI ion NDA comme Chargée de Suiv i et Evaluation du Projet STEP 2 pour l'antenne d'Ituri ZR-FSRDC-257660-CS-INDV / (16): Recrutement de cinq (5 En attente d'exéc IDA / 66650 5. CERC A posteriori Individuel Limited 60,000.00 0.00 2021-11-15 2021-11-20 2021-12-11 2022-01-15 2022-07-14 ) Assistants en Sauvegardes ution pour le CERC de Kinshasa ZR-FSRDC-257658-CS-INDV / (15): Contractualisation par e ntente directe avec le Consul En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Direct 48,000.00 0.00 2021-11-15 2021-11-23 2021-11-25 2021-11-26 2021-12-16 2022-01-20 2022-07-19 tant Gilles BIRINDWA NTUGU ion LO comme spécialiste en Sau vegardes Sociales du Projet S TEP 2 ZR-FSRDC-262066-CS-INDV / (11): Recrutement d'un Char En attente d'exéc gé de Passation des Marchés IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2021-12-30 2022-02-17 2022-03-10 2022-04-14 2022-10-11 ution du Projet STEP 2/Equipe régi onale de l'Antenne d'Ituri ZR-FSRDC-262067-CS-INDV / (12): Recrutement d'un Assis En attente d'exéc tant en Gestion des Bases de IDA / 66650 4. Project Management A posteriori Individuel Limited 24,000.00 0.00 2021-12-30 2022-01-04 2022-01-25 2022-03-01 2022-08-28 ution s Données du Projet STEP 2/E quipe régionale de l'Antenne d'Ituri ZR-FSRDC-262069-CS-INDV / (13): Recrutement d'un Char En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2021-12-30 2022-02-17 2022-03-10 2022-04-14 2022-10-11 gé de la Comptabilité du Proj ution et STEP 2/Equipe régionale d e l'Antenne de l'Ituri ZR-FSRDC-262076-CS-INDV / (15): Recrutement d'un Char En cours d'exécut gé de Développement Comm IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2021-12-30 2022-02-13 2022-02-17 2022-03-10 2022-04-14 2022-10-11 ion unautaire du Projet STEP 2/E quipe régionale de l'Antenne du Nord-Kivu ZR-FSRDC-262072-CS-INDV / (14) : Contractualisation avec le consultant Derrick MANE G En cours d'exécut ABE BAHAYA comme Chargé IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 2021-11-30 2021-11-23 2021-12-10 2021-12-31 2022-02-04 2022-08-03 ion de Développement Commun autaire et Gestion des Conflit s du STEP II pour l'équipe rég ionale de l’antenne du Sud Ki vu ZR-FSRDC-264848-CS-INDV / En attente d'exéc (1): Chargé des Techniques d IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 2021-12-24 2022-02-11 2022-03-04 2022-04-08 2022-10-05 ution e l’Information (IT) du STEP 2 ZR-FSRDC-265048-CS-INDV / En attente d'exéc (1): Chargé de Développeme IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 2022-01-12 2022-03-02 2022-03-23 2022-04-27 2022-10-24 ution nt Communautaire pour le N ord-Kivu ZR-FSRDC-265061-CS-INDV / En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 2022-01-12 2022-03-02 2022-03-23 2022-04-27 2022-10-24 (6): Chargé de Comptabilité ution de l'Ituri ZR-FSRDC-265064-CS-INDV / En cours d'exécut (7): Chargé de Développeme IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 2022-01-12 2022-02-13 2022-03-02 2022-03-23 2022-04-27 2022-10-24 ion nt Communautaire de l'Ituri ZR-FSRDC-265074-CS-INDV / En attente d'exéc (11): Chargé de Passation de IDA / 66650 4. Project Management A posteriori Individuel Open 36,600.00 0.00 2022-01-12 2022-03-02 2022-03-23 2022-04-27 2022-10-24 ution s Marchés de l'Ituri ZR-FSRDC-256710-CS-INDV / (10): Recrutement de 200 Co 2. Livelihoods and Employm nsultants Individuels chef d'é IDA / 66650 A posteriori Individuel Open 240,000.00 0.00 Annulé 2021-11-15 2022-01-03 2022-01-24 2022-02-28 2022-08-27 ent Generation quipe pour la mise en œuvre des THIMO dans le Sud Kivu ( Bukavu) ZR-FSRDC-258478-CS-INDV / (14): Recrutement du ASNV p IDA / 66650 4. Project Management A posteriori Individuel Open 18,000.00 0.00 Annulé 2021-11-30 2022-01-18 2022-02-08 2022-03-15 2022-09-11 our l'antenne du Sud-Kivu ZR-FSRDC-266522-CS-INDV / (4): Contractualisation par en tente directe avec Mme Jocel En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 2022-01-12 2022-01-22 2022-02-12 2022-03-19 2022-09-15 yne KUMWUIMBA comme Ch ution argée de Travaux à Haute Int ensité de Main d'Œuvre à l'a ntenne du Sud-Kvu Page 10 ZR-FSRDC-266524-CS-INDV / (4): Contractualisation par en tente directe avec Mr Jean Pa En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Direct 39,600.00 0.00 2022-01-12 2022-01-22 2022-02-12 2022-03-19 2022-09-15 ul NKONDOLO comme Charg ution é des Travaux à Haute Intens ité de Main d'Œuvre à l'anten ne de l'Ituri ZR-FSRDC-274022-CS-CDS / Recrutement de Price Water Sélection de cons House Coopers _ RDC pour l' En cours d'exécut IDA / 66650 4. Project Management A posteriori ultants par entent Direct 25,000.00 0.00 2022-02-28 2022-01-25 2022-03-10 2022-02-01 2022-05-14 2022-11-10 audit externe des comptes d ion e directe u STEP Exercice_ 18 septemb re 2020 au 31 décembre 202 1 ZR-FSRDC-274127-CS-INDV / Recrutement d'un spécialiste En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 54,000.00 0.00 2022-04-29 2022-01-25 2022-06-17 2022-07-08 2022-08-12 2023-02-08 en passation des marchés au ion sein de la CG de STEPII ZR-FSRDC-274128-CS-INDV / Recrutement d'un Spécialiste En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 54,000.00 0.00 2022-04-29 2022-01-25 2022-06-17 2022-07-08 2022-08-12 2023-02-08 Suivi et Evaluation au sein de ion la CG du STEPII ZR-FSRDC-275576-CS-INDV / Recrutement d'un Assistant e En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 24,600.00 0.00 2022-05-31 2022-07-19 2022-08-09 2022-09-13 2023-03-12 n Passation des Marchés au s ution ein de la CG de STEPII ZR-FSRDC-285254-CS-INDV / En cours d'exécut (SU- C4) Chargé de Passation IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-03-25 2022-06-26 2022-07-01 2022-07-06 2023-07-01 ion des Marchés de l'antenne du Sud Ubangi ZR-FSRDC-285258-CS-INDV / En cours d'exécut (SU-C4) Chargé de Comptabil IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-03-25 2022-06-26 2022-07-01 2022-07-06 2023-07-01 ion ité de l'antenne du Sud Uban gi ZR-FSRDC-285262-CS-INDV / (SU- C4) Chargé de Développ En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-03-25 2022-06-26 2022-07-01 2022-07-06 2023-07-01 ement Communautaire de l'A ion ntenne Sud Ubangi ZR-FSRDC-285264-CS-INDV / (SU- C4) Chargé des Travaux En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-03-25 2022-06-26 2022-07-01 2022-07-06 2023-07-01 d'Infrastructure Communauta ion ire de l'Antenne du Sud Uban gi ZR-FSRDC-285265-CS-INDV / En cours d'exécut (SU- C4) Chargé de Suivi et E IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-03-25 2022-06-26 2022-07-01 2022-07-06 2023-07-01 ion valuation de l'antenne du Su d Ubangi ZR-FSRDC-285266-CS-INDV / (SU- C4) Chargé des Sauvega En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-03-25 2022-06-26 2022-07-01 2022-07-06 2023-07-01 rdes Environnementales et S ion ociales de l'antenne Sud Uba ngi ZR-FSRDC-285268-CS-INDV / (SU- C4) Chargé en Travaux En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-06-26 2022-07-01 2022-07-06 2023-07-01 à Haute Intensité de Main d' ution Œuvre de l'Antenne du Sud U bangi ZR-FSRDC-285270-CS-INDV / En cours d'exécut (SU- C4) Chargé MEDAC de l' IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-03-25 2022-06-26 2022-07-01 2022-07-06 2023-07-01 ion Antenne du Sud Ubangi ZR-FSRDC-285271-CS-INDV / En cours d'exécut (SU- C4) Chargé de Transfert IDA / 66650 4. Project Management A posteriori Individuel Open 39,600.00 0.00 2022-05-31 2022-03-25 2022-06-26 2022-07-01 2022-07-06 2023-07-01 ion Monétaire de l'Antenne du Su d Ubangi ZR-FSRDC-289300-CS-INDV / Recrutement par Entente Dir En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Direct 36,600.00 0.00 2022-03-30 2022-04-05 2022-04-01 2022-04-02 2022-04-04 2023-03-30 ecte ( Yves MISSIATU) Charg ion é de passation des marchés de la province Ituri ZR-FSRDC-301453-CS-INDV / Recrutement d'un Consultant En cours d'exécut IDA / 66650 4. Project Management A posteriori Individuel Open 50,000.00 0.00 2022-07-20 2022-07-21 2022-08-09 2022-08-11 2022-08-13 2022-09-12 pour la Root Cause Analysis ( ion analyse des causes profonde s) ZR-FSRDC-310117-CS-INDV / Recrutement per Entente Dir ecte avec MABUBI MVULA M En attente d'exéc IDA / 66650 4. Project Management A posteriori Individuel Direct - National 39,600.00 0.00 2022-08-31 2022-09-02 2022-09-03 2022-09-05 2023-08-31 UINI BILLY en qualité de Char ution gé des travaux à haute Inten sité de Main d’œuvre à l’ante nne du Nord Ubangi ZR-FSRDC-310957-CS-INDV / Consultant Individuel ayant u ne expertise en passation de En attente d'exéc s marches pour la conduite IDA / 66650 4. Project Management A posteriori Individuel Open - National 30,000.00 0.00 2022-10-31 2022-11-20 2022-11-22 2022-11-25 2022-12-25 ution d’une formation des marches des acteurs issus des antenn es provinciales (KC- NU-SK-N K-IT- SU) ZR-FSRDC-317801-CS-INDV / Recrutement (01) Chargé de En attente d'exéc la coordination de la gestion IDA / D8440 5. CERC A posteriori Individuel Limited 33,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ution des plaintes des centres d'ap pels pour le CERC KIN ZR-FSRDC-317799-CS-INDV / Recrutement d’un (01) Assist En attente d'exéc IDA / D8440 5. CERC A posteriori Individuel Limited 22,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ant Gestion de base de donn ution ées pour le CERC KIN ZR-FSRDC-317797-CS-INDV / En attente d'exéc Recrutement d’un (01) Chauf IDA / D8440 5. CERC A posteriori Individuel Limited 11,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ution feur pour le CERC KIN ZR-FSRDC-317803-CS-INDV / En attente d'exéc Recrutement de quatre (04) IDA / D8440 5. CERC A posteriori Individuel Limited 80,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ution Assistants MGP pour le CERC KIN Page 11 ZR-FSRDC-317796-CS-INDV / En cours d'exécut Recrutement de huit (08) Ass IDA / D8440 5. CERC A posteriori Individuel Limited 160,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ion istants de sauvegarde pour l e CERC KIN ZR-FSRDC-317795-CS-INDV / Recrutement d’un (01) Assist En cours d'exécut IDA / D8440 5. CERC A posteriori Individuel Limited 33,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ant Chargé des Opérations e ion n charge de CERC KIN ZR-FSRDC-317800-CS-INDV / Recrutement de deux (02) As En attente d'exéc sistants de gestion des plaint IDA / D8440 5. CERC A posteriori Individuel Limited 40,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ution es auprès des centres d’appe ls des prestataires pour le CE RC KIN ZR-FSRDC-317802-CS-INDV / En cours d'exécut Recrutement d’un (01) Charg IDA / D8440 5. CERC A posteriori Individuel Limited 33,000.00 0.00 2022-10-24 2022-10-29 2022-11-19 2022-12-24 2023-06-22 ion é de communication pour le CERC KIN ZR-FSRDC-322616-CS-CDS / Recrutement du Consultant Sélection de cons Direct - Internation En attente d'exéc GIVE DIRECTLY pour l'implém IDA / D8440 5. CERC A priori ultants par entent 1,186,000.00 0.00 2022-10-24 2022-11-03 2023-01-07 2023-07-06 al ution entation, le paiement digital e directe et l'accompagnement du Proj et STEP-KIN2 Page 12