Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: October 2016]: Revision 1 of Updated Procurement Plan, January 2017] 2. Date of General Procurement Notice: 15 July 2017 3. Period covered by this procurement plan: The procurement period of project covered from year January 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 780,000 All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 476,000 First contract 5. Consultation of the suppliers Above US$ 20,000 First contract (Works) 6. (Non-Consultant Services) Above US$ 10,000 First contract 6. Individual consultants Above US$ 19,200 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project under preparation. 5. Any Other Special Procurement Arrangements: 5 ICB works packages will be financed under Project preparation advance. PADAP August 22, 2017 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimat Packages Dome Review Comme No. ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary of the ICB 0.00 0 No Prior (Works) Summary of the ICB 0.50 1 No Prior (Goods) Summary of the NCB 3.656 5 No Prior (Works) Summary of the NCB 0.78 1 No Prior (Goods) Summary of the ICB 0.00 0 No Prior (Non-Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) All 2. Single Source (Firms) All 3. Individual All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 PADAP August 22, 2017 Ref. Description of Assignment Estimated Package Review Comment No. Cost s by Bank s US$ (Prior / million Post) Summary of number of 0.00 0 Prior contracts that will be let under QCBS Summary of number of 0.00 0 Prior contracts that will be let under other methods PADAP August 22, 2017 PROCUREMENT Madagascar : Sustainable Landscape Management Project PLAN General Information Country: Madagascar 2017-11-23 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank 2023-11-25 if none) Project ID: P154698 GPN Date: Project Name: Sustainable Landscape Management Project Loan / Credit No: IDA / V0430, IDA / 59790, COFN / C1540 PADAP PROJECT UNIT MANAGEMENT Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount (U t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) S$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned T 05-18/CN / Travaux de ré novation des locaux de l'UG Component 3: Project Mana Single Stage - One 2018-11-1 2018-10-1 2018-11-1 2018-12-1 2018-11-1 2018-12-2 2018-12-2 2019-02-0 2019-02-1 2019-07- P (Unité de Gestion du Proje IDA / 59790 gement Coordination and M A posteriori Appel d'offres Open - National 50,000.00 69,010.77 Signé Envelope 3 3 8 8 4 8 0 1 6 01 t) du PADAP à la direction d &E u Génie rural - MINAE à Nani sana Antananarivo. T 01-19/SAV / Travaux de r éhabilitation de deux (02) b âtiments de la DRAEP : Component 3: Project Mana Single Stage - One 2019-03-1 2019-04-1 2019-03-2 2019-04-2 2019-05-1 2019-05-0 2019-06-1 2019-06-0 2019-07-1 2019-08- Lot 01 : sis à Sambava, Co COFN / C1540 gement Coordination and M A posteriori Appel d'offres Open - National 65,000.00 55,651.97 Achevé Envelope 5 1 6 5 3 5 7 9 3 18 mmune Sambava, District S &E ambava Lot 02 : à Sahamazava Anda pa, Commune Andapa, Distri ct Andapa T 03-19/SOF / Travaux de ré habilitations des bureaux de Component 3: Project Mana Single Stage - One 2019-05-2 2019-08-1 2019-05-2 2019-06-2 2019-09-1 2019-07-0 2019-10-2 2019-08-1 2019-11-3 2020-01- la DRAEP Sofia : COFN / C1540 gement Coordination and M A posteriori Appel d'offres Open - National 100,000.00 80,022.23 Signé Envelope 4 4 9 8 6 8 5 2 0 09 Lot 01 : Antsohihy &E Lot 02 : Bealanana T 01-19/ANJ / Travaux de ré Component 2: Investments habilitation des ouvrages su Single Stage - One 2019-02-2 2019-02-1 2019-02-2 2019-03-2 2019-03-1 2019-04-0 2019-04-0 2019-05-0 2019-05-0 2019-08- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 427,520.00 239,627.26 Achevé r canaux d'irrigation dans le Envelope 1 4 1 3 8 7 3 2 2 30 selected landscapes périmètre de Sahavaviana-I azafo. T 02-19/ANJ / Travaux de ré Component 2: Investments habilitation des barrages de Single Stage - One 2019-02-2 2019-02-1 2019-02-2 2019-03-2 2019-03-1 2019-04-0 2019-04-0 2019-05-0 2019-05-0 2019-08- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 427,520.00 328,571.95 Signé dérivation dans le périmètre Envelope 1 4 1 3 8 7 3 2 2 30 selected landscapes de Sahanofia-Iazafo. T 02-19/SOF / Travaux d'am énagement du périmètre de Bealanana I Component 2: Investments Single Stage - One 2019-03-1 2019-03-0 2019-03-2 2019-04-2 2019-04-0 2019-05-0 2019-04-2 2019-06-0 2019-06-0 2019-11- Lot 01 : La partie amont du COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 756,250.00 500,253.01 Achevé Envelope 1 5 1 0 4 5 4 5 6 02 PM 580 sur le canal principal selected landscapes de la rive droite. Lot 02 : La partie aval du PM 580 sur le canal principal de la rive droite. T 01-19/SOF / Construction des ouvrages hydraulique et piste d'entretien dans le PI Mangindrano: Lot 1:BARRAGE ANTAFIANA Component 2: Investments MALONA Single Stage - One 2,188,071.8 1,554,350. 2019-03-1 2019-03-0 2019-03-2 2019-04-2 2019-04-0 2019-05-0 2019-04-2 2019-06-0 2019-06-0 2019-11- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National Signé Lot 2:CANAL CPRD DU PM 2 Envelope 7 58 1 5 1 0 4 5 4 5 4 02 selected landscapes 153 - BOUT DU RESEAU Lot 3:CANAL CPRG 1er TRON ÇON DE 2921 ML Lot 4:CANAL CPRG 2ème TR ONÇON DE 3261 ML Lot 5:PISTE-PONT T 03-20/SOF / Travaux d'am Component 2: Investments énagement du périmètre d' Single Stage - One 2020-04-3 2020-05-1 2020-05-1 2020-06-0 2020-07-0 2020-06-2 2020-08-1 2020-08-0 2020-09-2 2021-01- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 375,000.00 234,454.72 Signé Anjohibe-Ambatosia dans le Envelope 0 5 0 9 6 9 7 4 4 01 selected landscapes Paysage de Bealanana. T 02-20/ANJ / Travaux de ré Component 2: Investments habilitation des infrastructur Single Stage - One 2020-02-2 2020-02-0 2020-03-1 2020-04-1 2020-03-1 2020-05-0 2020-03-2 2020-06-0 2020-05-0 2021-02- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 340,000.00 193,722.01 Achevé es hydroagricoles dans le pé Envelope 8 1 4 3 0 3 4 3 3 08 selected landscapes rimètre d'Iazafo- Mahatsara - Andapatsara T 05-19/ANJ / Travaux de ré Component 2: Investments habilitation des infrastructur Single Stage - One 2019-09-3 2019-10-1 2019-10-1 2019-11-1 2019-11-1 2019-12-0 2020-01-0 2020-06- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 340,000.00 0.00 Annulé es hydroagricoles dans le pé Envelope 0 0 5 4 9 4 4 02 selected landscapes rimètre d'Iazafo- Mahatsara - Andapatsara T 04-19/SOF / Travaux de ré habilitation route non revêtu e (RIP 117M) reliant Bealana na à Ambatoriha District Be Component 2: Investments Single Stage - One 4,600,000.0 4,790,803. 2020-05-2 2020-06-2 2020-06-0 2020-07-0 2020-08-0 2020-07-2 2020-09-0 2020-09-0 2020-10-0 2021-03- alanana, Région Sofia repart COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National Signé Envelope 0 16 9 0 8 8 4 8 4 1 3 30 is en trois (03): selected landscapes Lot1:du PK 0+000-PK 18+00 0. Lot2:du PK 18+000-PK 22+0 00. Lot3:du PK 22+000-PK 30+8 T 05-19/SAV 25 / Travaux d'am (barrière Ambatoriha). élioration du réseau hydroa Component 2: Investments Single Stage - One 2020-03-2 2020-05-2 2020-04-0 2020-05-0 2020-07-0 2020-05-2 2020-08-0 2020-06-2 2020-08-2 2020-12- gricole du périmètre Ambala IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 324,800.00 359,580.46 Achevé Envelope 0 3 2 2 7 2 6 6 6 23 fary de 252 ha, Commune R selected landscapes urale Ambodidivaina, Distric t Andapa, Région SAVA T 03-19/SAV / Travaux de re construction du réseau hydr Component 2: Investments oagricole de la grappe des p Single Stage - One 2020-03-1 2020-05-2 2020-03-2 2020-04-2 2020-07-0 2020-05-1 2020-08-0 2020-06-2 2020-08-2 2020-12- IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 313,500.00 248,719.71 Achevé érimètres Andalamena et A Envelope 6 3 8 7 7 7 7 1 9 18 selected landscapes mboadiala de 191 ha , Com mune Rurale Andasibe Koba hina, District Andapa, Régio n SAVA. T 06-19/SAV / Travaux de ré novation du réseau hydroag Component 2: Investments Single Stage - One 2020-03-2 2020-05-2 2020-04-0 2020-05-0 2020-07-0 2020-05-2 2020-08-0 2020-06-2 2020-08-2 2020-12- ricole du périmètre Tanand IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 598,500.00 494,317.43 Achevé Envelope 0 3 2 2 7 2 6 6 6 23 ava sur 400 ha, Commune selected landscapes Rurale Tanandava, District A ndapa, Région SAVA. T 04-19/SAV / Travaux de re mise en état du réseau hydr oagricole de la grappe de Pé Component 2: Investments Single Stage - One 2020-03-1 2020-05-2 2020-03-2 2020-04-2 2020-07-0 2020-05-1 2020-08-0 2020-06-2 2020-12- rimètre Antanimbaribe, Amb COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 412,500.00 0.00 Annulé Envelope 6 3 8 7 7 7 7 1 18 atoharanana et Andasimena selected landscapes lamba de 244 ha, CR Ambal amanasy II, District Andapa, Région SAVA. T 02-19/SAV / Travaux de re nforcement du réseau hydro Component 2: Investments agricole du Périmètre Ambo Single Stage - One 2020-03-2 2020-05-2 2020-04-0 2020-05-0 2020-07-0 2020-05-2 2020-08-1 2020-06-2 2020-09-0 2020-12- IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 465,000.00 351,675.26 Résilié divitagnona de 370ha, Com Envelope 0 3 1 1 7 1 0 5 1 22 selected landscapes mune Rurale Ambalamanas y II, District Andapa, Région SAVA. T 01-20/BOE / Travaux de r Component 2: Investments éhabilitation des réseaux de Single Stage - One 2020-09-0 2020-08-2 2020-09-1 2020-10-1 2020-09-2 2020-11-0 2021-08-1 2020-12-0 2021-09-1 2021-04- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 800,000.00 0.00 Signé drainage des secteurs 04, 0 Envelope 8 8 8 8 9 3 6 2 1 01 selected landscapes 5 et 06 répartis en trois (3) lots. T 01-19/BOE / Travaux de c Component 2: Investments Single Stage - One -724,049.4 2020-07-1 2020-07-0 2020-07-3 2020-08-2 2020-08-1 2020-09-1 2020-09-1 2020-10-2 2020-10-0 2022-03- urage du drain de ceinture e COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 431,250.00 Achevé Envelope 4 6 8 0 9 0 8 5 3 2 07 t du drain naturel Manompo selected landscapes T 02-19/BOE / Travaux de r egabaritage des cours d’eau exutoire du drainage des PI Marovoay, répartis en 2 lots Component 2: Investments : Single Stage - One 2020-07-2 2020-07-1 2020-08-0 2020-09-1 2020-08-1 2020-10-1 2020-09-2 2020-11-2 2020-10-1 2022-04- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 458,000.00 299,370.00 Signé Lot 01: dans le secteur 5 du Envelope 8 7 7 6 8 1 9 1 7 20 selected landscapes PM 2903 (Ambohijaoka) au P M 4114 (Andranodaka). Lot 02: dans le secteur 4 du PM 4114 (Andranodaka) au PM 5865 (Ambolomoty). T 02-20/SAV / Travaux de re mise en état du réseau hydr oagricole de la grappe de Pé Component 2: Investments Single Stage - One 2020-10-1 2020-09-2 2020-10-1 2020-11-1 2020-10-2 2020-12-0 2020-12-0 2021-01-1 2020-12-2 2021-05- rimètre Antanimbaribe, Amb COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 412,500.00 166,314.53 Achevé Envelope 3 4 8 7 6 7 3 1 7 11 atoharanana et Andasimena selected landscapes lamba de 244 ha, CR Ambal amanasy II, District Andapa, Région SAVA (RELANCE). T 4-19/ANJ / Travaux de réh abilitation des canaux d'irrig ation et ouvrages de franchi Component 2: Investments ssement dans le district de Single Stage - One 2,720,000.0 1,255,680. 2019-12-2 2019-12-2 2019-12-3 2020-01-3 2020-01-2 2020-02-1 2020-02-2 2020-03-2 2020-04-0 2020-08- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National Signé Soanierana Ivongo : Lot 01 : Envelope 0 22 1 1 1 0 1 9 6 1 3 18 selected landscapes périmètre de Marovinanto L ot 02 : périmètre de Sahafar y Lot 03 : périmètre de Vohij iny Lot 04 : périmètre d'Amp asimbola T 04-19/ANJ / Travaux de ré habilitation des canaux d'irri gation et des ouvrages de fr Component 2: Investments anchissement dans le distric Single Stage - One 2,720,000.0 2019-07-1 2019-12-2 2019-07-2 2019-08-2 2020-01-2 2019-09-0 2019-10-0 2020-03- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Annulé t de Soanierana Ivongo : Envelope 0 1 1 1 0 1 9 4 02 selected landscapes Lot 01 : périmètre de Marovi nanto Lot 02 : périmètre de Sahafa ry Lot 03 : périmètre de Vohijin yT 03-19/ANJ / Travaux de re mise Lot 04en état des ouvrages : périmètre d'Ampasi e mbola et curage des drains xistant dans le PI d'Iazaf: Lot 1:zone Mahanoro-Mahat Component 2: Investments Single Stage - One 2,550,000.0 2019-04-2 2019-05-0 2019-05-1 2019-06-1 2019-06-1 2019-06-3 2019-07-3 2019-12- sara COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Annulé Envelope 0 6 6 1 0 1 0 1 28 Lot 2:zone Ambalabe II-Antsi selected landscapes ratenina Lot 3:zone B1-B6 Lot 4:zone Maromitety Lot 5:zone Sahafana-Ambat omirahalahy Lot 6:Mahatsara-Andapat T 05-20/SAV / Travaux de re piquage mécanisé dans les communes rurales d'Andasi Component 2: Investments Passation de mar 2020-10-2 2020-09-2 2020-11-0 2020-10-0 2020-12-2 2020-12-2 2021-01- be Kobahina, Ankiakabe Nor COFN / C1540 and capacity building in the A posteriori Direct 450,000.00 446,347.92 Achevé ché de gré à gré 3 8 7 9 2 7 21 d, Bealampona et Ambodidi selected landscapes vaina, district d'Andapa dan s le cadre de la relance de la production post-Covid. T 09-20/SOF / Reprise des tr avaux de réhabilitation du r éseau hydroagricole du péri Component 2: Investments mètre Andranomafana Mang Passation de mar 2020-10-2 2020-10-2 2020-11-0 2020-10-2 2020-12-0 2020-12-1 2021-04- COFN / C1540 and capacity building in the A posteriori Direct 295,000.00 269,166.98 Signé indrano du paysage de Beal ché de gré à gré 7 6 6 6 6 2 05 selected landscapes anana, CR Mangindrano ; ré gion SOFIA lot 01 : travaux s ur le barrage d'Antafianamal ona CPRD, partiteur, bâche et chute Page 1 T 08-20/SOF / Reprise des tr avaux de réhabilitation des i nfrastructures hydroagricole Component 2: Investments s du périmètre Bealanana 1 Passation de mar 2020-10-2 2020-10-0 2020-11-0 2020-10-0 2020-12-0 2020-10-2 2021-04- COFN / C1540 and capacity building in the A posteriori Direct 180,000.00 172,694.40 Signé du paysage de Bealanana, C ché de gré à gré 7 2 6 2 6 1 05 selected landscapes R Bealanana district Bealana na région SOFIA- lot 01 bis : la partie amont du pm 580 s ur le canal principal de la riv e droite T 01-21/ANJ / Travaux de pr otection des berges des rivi ères dans les Paysages d'Iaz afo et de Soanierana Ivongo : Component 2: Investments Single Stage - One 2021-09-1 2021-09-2 2021-10-2 2021-11-0 2021-11-2 2022-03- -Lot 01: Berges de la rivière COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 824,600.00 0.00 Annulé Envelope 0 0 0 4 4 24 Iazafo selected landscapes -Lot 02: Berges de la rivière Sahavaviana -Lot 03: Berges de rivière Sa hafototra Lot 04: Berges de la rivière Sahave T 04-20/BOE / Travaux de tr ouaison et plantation de ban Component 2: Investments des anti-érosives : Single Stage - One 2020-10-3 2020-11-0 2020-12-0 2020-12-2 2021-01-2 2021-05- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé Lot 1: CR Ambolomoty Envelope 0 9 9 9 7 27 selected landscapes Lot 2: CR Tsararano lot 3: CR Anosinalainolona T 07-20/SOF / Travaux de pr otection biologique des Bass ins Versants: Lot 1:Ambatosia Lot 2:Antsamaka, Beandrare Component 2: Investments Single Stage - One 2,766,000.0 2021-01-2 2021-02-0 2021-03-0 2021-03-2 2021-05-0 2022-08- zona COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Annulé Envelope 0 8 7 9 9 3 26 Lot 3:Ambodiampana, Beala selected landscapes nana Lot 4:Ambatoriha, Ambarara tabe, Mangindrano Lot 5: , Marotolana, Analila, Anjozoromadosy, Ankazotok ana,Ambovonomby T 05-20/BOE / Travaux de Component 2: Investments mise en place de dispositifs Single Stage - One 2021-02-0 2021-02-1 2021-03-1 2021-04-0 2021-05-0 2021-11- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 468,000.00 0.00 Annulé antiérosifs sur courbes de ni Envelope 2 2 4 3 8 04 selected landscapes veau dans le paysage de Ma rovoay. T 06-20/BOE / Travaux de p rotection des bassins versan ts par la plantation d'acacia et eucalyptus répatis en 4 lo Component 2: Investments ts de 300 ha Single Stage - One 2021-02-0 2021-02-1 2021-03-2 2021-04-2 2021-05-2 2022-09- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 480,000.00 0.00 Annulé Lot 1: Commune d' Anosinal Envelope 9 9 1 0 5 17 selected landscapes ainolona Lot 2: Commune de Tsarara no Ouest Lot 3: Commune de Tsarara no Est lot 4: Commune d'Ambolom Document nation T 01-21/SAV / Reprise des tr oty al de passation d avaux de renforcement du r Component 2: Investments es marchés - Pro éseau hydroagricole du péri Passation de mar 2021-05-1 2021-06-3 2021-05-2 2022-04-2 2021-07-0 2022-07-2 2021-10- COFN / C1540 and capacity building in the A posteriori Direct cessus à une env 215,824.00 308,588.34 Signé mètre Ambodivitagnona, Co ché de gré à gré 7 0 7 2 4 9 02 selected landscapes eloppe (DTPM ne mmune Rurale Ambalamana provenant pas d sy II, District Andapa, Régio e la Banque) n SAVA. T 05-20/SOF / Travaux de L Component 2: Investments Single Stage - One 2,367,000.0 2021-06-1 2021-06-2 2021-07-2 2021-08-1 2021-09-2 2022-09- utte Antiérosive et de restau COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Annulé Envelope 0 8 8 8 7 1 21 ration des sols dans le pays selected landscapes age de Bealanana. T 06-20/SOF / Travaux d'am Component 2: Investments énagement de champs d'agr Single Stage - One 2021-02-0 2021-02-0 2021-03-0 2021-03-2 2021-05-0 2022-05- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 522,710.00 0.00 Annulé oforesterie et plantation d'ar Envelope 1 6 8 8 2 02 selected landscapes bres fruitiers dans le paysag e de Bealanana. T 02-20/SOF / Travaux d'am Component 2: Investments Single Stage - One 2021-06-2 2021-07-0 2021-07-3 2021-08-2 2021-09-2 2022-02- énagement du périmètre de COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 160,000.00 0.00 Annulé Envelope 1 1 1 0 4 21 Doany dans le paysage de B selected landscapes ealanana. T 07-19/SAV / Traitement et stabilisation des quatres (04 Component 2: Investments ) lavaka dans les anciennes Single Stage - One 2021-05-3 2021-06-1 2021-07-1 2021-08-0 2021-09-0 2022-03- IDA / 59790 and capacity building in the A posteriori Appel d'offres Open - National 61,820.00 0.00 Annulé zones d'exploitation minière Envelope 1 5 5 4 8 07 selected landscapes s à Andasinimaro, Commune Rurale Bealampona, District Andapa, Région SAVA T 3-19/ANJ. / Travaux de re mise en état ouvrages et cu Demande d'offre rage des drains dans le PI d'I Component 2: Investments s - DTPM Petits tr azaf: Lot 1:zone Mahanoro- Single Stage - One 2,550,000.0 1,642,079. 2019-05-0 2019-05-1 2019-05-1 2019-06-2 2019-06-1 2019-07-2 2019-08-1 2019-08-2 2019-09-0 2020-02- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National avaux - (Process Achevé Mahatsara Lot 2:zone Ambal Envelope 0 05 6 1 1 2 1 2 4 6 9 22 selected landscapes us à 1 enveloppe abe II-Antsiratenina Lot 3:zo ) ne B1-B6 Lot 4:zone Maromi tety Lot 5:zone Sahafana-A mbatomirahalahy Lot 6:Mah atsara-Andapatsara T 03-20/SAV / Travaux d'am Component 2: Investments Single Stage - One 2021-06-2 2021-07-0 2021-08-0 2021-08-2 2021-09-2 2022-07- énagement des zones à fort COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 140,000.00 0.00 Annulé Envelope 8 3 2 2 6 23 e érosion au niveau du pays selected landscapes age d'Andapa. T 04-20/SAV / Travaux pour la protection et restauration Component 2: Investments Single Stage - One 1,257,400.0 2021-06-3 2021-07-1 2021-08-0 2021-08-2 2021-10-0 2022-07- des flancs de colline (bassin COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Annulé Envelope 0 0 0 9 9 3 30 s versants) du Paysage d'An selected landscapes dapa, District d'Andapa, Rég ion SAVA. T 01-21/BOE / Travaux de c Document nation onstruction dans les CR d'A al de passation d mbolomoty, de Tsararano et Component 2: Investments es marchés - Pro Single Stage - One 2021-10-1 2021-10-2 2021-11-2 2021-12-0 2022-01-1 2022-05- d'Anosinalainolona COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National cessus à une env 80,000.00 0.00 Annulé Envelope 3 3 2 7 1 11 lot 1: 06 ateliers d'élevage p selected landscapes eloppe (DTPM ne ilote provenant pas d Lot 2: 06 unités de compost e la Banque) age Lot 3: 3 couloirs de vaccina T 01-20/SOF tion / Travaux d'am des bovidés Demande d'offre Component 2: Investments énagement du périmètre irri Single Stage - One s - DTPM Travau 1,940,330.0 2022-05-2 2022-05-2 2022-05-3 2022-06-0 2022-06-2 2022-07-0 2022-07-1 2022-08-1 2022-08-1 2022-11-0 2023-07- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 0.00 Signé gué de Beandrarezona dans Envelope x - Droit civil fran 0 0 8 0 1 9 1 9 1 9 3 30 selected landscapes le Paysage de Bealanana ré çais (français) partis en trois (03) lots. Document nation T 02-20/BOE / Travaux de st al de passation d Component 2: Investments abilisation des zones d'érosi Single Stage - One es marchés - Pro 2021-10-2 2021-11-0 2021-12-0 2021-12-2 2022-01-1 2022-05- COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 50,000.00 0.00 Annulé on CPRD et CSPC Ambolomo Envelope cessus à une env 7 6 6 6 9 19 selected landscapes ty composé d'un seul lot. eloppe (DTPM ne provenant pas d e la Banque) T 01-21/SOF / La constructi on de 12 unités de compost age dans le paysage de Beal anana repartis en trois lots : Demande de cot Component 2: Investments Lot 01 : 4 unités dans le sou Single Stage - One ations (DTPM ne 2022-01-3 2022-04-2 2022-07- COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 45,000.00 0.00 Annulé s-paysage d’Ambatotsia, Envelope provenant pas d 1 3 22 selected landscapes Lot 02 : 4 unités dans le sou e la Banque) s-paysage de Bealanana, Lot 03 : 4 unités dans le sou s-paysage d’Ambatoriha. GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project Mana Passation de mar F 18-17/CN / Acquisition des 2017-11-2 2017-11-2 2017-12-2 2018-03-2 2018-02-1 2018-06-2 IDA / V0430 gement Coordination and M A posteriori chés auprès des Direct 500,000.00 341,428.00 Signé 10 Voitures et des 20 Motos 7 3 7 2 2 0 &E agences de l'ON U F 01-17/CN / Fournitures de s matériels informatiques: - Lot 01:08 ordinateurs de b ureau (desktop) avec 01 ond Component 3: Project Mana uleur de chaque et 10 ordin Demande de pro Single Stage - One 2017-11-3 2017-09-0 2017-12-0 2017-09-1 2017-12-2 2017-10-1 2017-12-2 2017-10-1 2017-12-2 2018-01-1 IDA / V0430 gement Coordination and M A posteriori Limited 70,000.00 0.00 Annulé ateurs portable (Laptop). positions Envelope 0 5 5 9 1 9 3 0 7 6 &E - Lot 02: fournitures des acc essoires informatiques 09 i mprimantes, 09 scanners, - lot 03: 06 phootcopieu MG-UGP PADAP-38789-GO- Component 3: Project Mana RFP / L'acquisition des fourni Demande de pro Single Stage - One 2017-11-3 2017-12-0 2017-12-2 2017-12-2 2018-01-0 2018-01-2 IDA / V0430 gement Coordination and M A posteriori Limited 20,000.00 0.00 Annulé tures de bureau, consomma positions Envelope 0 5 1 6 3 3 &E bles informatiques et produi ts d'entretien du PADAP. F 04-18/CN / Fournitures de s matériels informatiques po Component 3: Project Mana Single Stage - One 2018-03-2 2018-02-0 2018-05-2 2018-03-3 2018-06-1 2018-04-1 ur Quatre cellules régionales IDA / V0430 gement Coordination and M A posteriori Demande de prix Limited 12,000.00 10,848.04 Achevé Envelope 6 5 0 1 9 4 d'exécution : 08 ordinateurs &E de bureau (desktop) avec 0 1 onduleur de chaque. F 5-18/CN / Acquisition des matériels informatiques pou Component 3: Project Mana Single Stage - One 2018-03-2 2018-01-2 2018-05-2 2018-03-2 2018-06-1 2018-04-1 r Quatre cellules régionales IDA / V0430 gement Coordination and M A posteriori Demande de prix Limited 80,000.00 74,307.22 Achevé Envelope 4 4 0 3 9 2 d'exécution : 40 ordinateurs &E portables (laptop) avec une disque dure externe de chaq ue. MG-UGP PADAP-55622-GO- Component 3: Project Mana DIR / Migration en version w Passation de mar 2018-03-2 2018-03-2 2018-04-0 2018-03-0 2018-05-0 2018-04-0 2018-06-2 IDA / V0430 gement Coordination and M A posteriori Direct 30,000.00 28,504.82 Signé eb et Formation de logiciel T ché de gré à gré 3 7 2 6 6 7 5 &E OM²PRO licence PN-BVPI pou r PADAP. F 15-18/CN / L'acquisition d Component 3: Project Mana Single Stage - One 2018-07-2 2018-07-2 2018-09-0 2018-08-2 2018-10-0 2018-09-0 es Consommables informati IDA / 59790 gement Coordination and M A posteriori Demande de prix Limited 9,400.00 3,282.13 Achevé Envelope 5 0 5 9 5 5 ques pour l'Unité de Gestion &E de Projet PADAP F 06-18/CN / Acquisition de : Component 3: Project Mana lot 01 03 photocopieuses po Single Stage - One 2018-07-2 2018-08-0 2018-09-0 2018-09-2 2018-10-0 2018-09-2 IDA / 59790 gement Coordination and M A posteriori Demande de prix Limited 48,000.00 29,323.39 Achevé ur l'unité de gestion projet P Envelope 5 8 5 2 5 9 &E ADAP. lot 02 08 photocopieuses m onochromes pour les quatre cellules d'exécution régional MG-UGP es PADAP-38789-GO- du PADAP. Component 3: Project Mana RFQ / L'acquisition des fourn Single Stage - One 2017-12-0 2017-07-0 2018-02-0 2017-07-1 2018-03-0 2017-08-3 IDA / V0430 gement Coordination and M A posteriori Demande de prix Limited 20,000.00 7,545.86 Achevé itures de bureau, consomma Envelope 5 5 4 9 6 0 &E bles informatiques et produi ts d'entretien du PADAP. F 01B-17/CN / Fournitures d es matériels informatiques:- Lot 01:08 ordinateurs de bur Component 3: Project Mana eau (desktop) avec 01 ondul Single Stage - One 2017-09-1 2017-09-0 2017-11-2 2017-11-0 2017-12-1 2017-11-1 IDA / V0430 gement Coordination and M A posteriori Demande de prix Limited 70,000.00 46,297.28 Achevé eur de chaque et 10 ordinat Envelope 9 6 7 1 7 3 &E eurs portable (Laptop).- Lot 02: fournitures des accessoi res informatiques 09 imprim antes, 09 scanners,- lot 03: 06 phootcopie F 12-18/CN / Acquisition de : - Lot 01 : Fournitures de b Component 3: Project Mana Single Stage - One 2018-11-1 2019-01-1 2019-01-1 2019-02-1 2019-01-1 ureau pour l'Unité de Gestio IDA / 59790 gement Coordination and M A posteriori Demande de prix Open - National 12,500.00 9,848.58 Achevé Envelope 8 3 4 2 6 n de Projet PADAP. &E - Lot 02 : Produits d'entreti en pour l'Unité de Gestion d e Projet PADAP. Page 2 MG-UGP PADAP-87379-GO- DIR / Acquisition du logiciel Component 1: Information a Passation de mar 2018-11-1 2018-12-2 2018-11-2 2018-12-3 2019-01-3 2019-01-2 2019-02-1 ArcGIS auprès de la société IDA / 59790 A posteriori Direct 35,000.00 22,299.71 Achevé nd planning ché de gré à gré 6 4 6 0 0 9 3 MAKY Engineering et formati on sur son utilisation (Stock age et gestion des données) . F 01-18/BOE / Dotation de t Component 2: Investments Single Stage - One 2018-11-3 2019-01-3 2019-04-0 2019-03-0 arares pour le Centre Multipl IDA / 59790 and capacity building in the A posteriori Demande de prix Open - National 12,000.00 6,360.81 Résilié Envelope 0 1 2 2 icateur de Semence de Tsar selected landscapes arano (Marovoay) F 01-18/SAV / Dotations de 02 moto pompes suivi d'une Component 2: Investments Single Stage - One 2018-11-3 2019-01-3 2019-03-1 2019-03-0 2019-04-0 formation sur l'utilisation et l IDA / 59790 and capacity building in the A posteriori Demande de prix Open - National 8,000.00 4,034.55 Achevé Envelope 0 1 3 2 7 'entretien aux deux Fédérati selected landscapes ons : MEVA Ambodidivaina e t SOA Ankiakabe Nord F 9-18/CN / Acquisition des mobiliers de bureau pour les quatre Cellule d'Exécution R Component 3: Project Mana Single Stage - One 2018-11-2 2019-01-1 2019-04-2 2019-02-1 2019-05-2 égionale du PADAP repartis IDA / 59790 gement Coordination and M A posteriori Demande de prix Open - National 40,000.00 64,583.70 Achevé Envelope 8 4 7 3 5 en 04 lots : Lot 01 région SO &E FIA, lot 02 région Boeny, lot 03 région SAVA et lot 04 rég ion Analanjirofo. F 02-19/BOE / Acquisition d Component 2: Investments Single Stage - One 2019-05-2 2019-04-0 2019-07-0 2019-05-0 2019-07-2 2019-07-3 es semences pour la diffusio COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 4,400.00 4,361.57 Achevé Envelope 7 4 8 8 8 1 n des paquets technique rizi selected landscapes cole. MG-UGP PADAP-113663-GO Component 3: Project Mana Single Stage - One 2019-06-0 2019-08-1 2019-09-1 2019-11-0 2019-11-2 -RFQ / Acquisition de 09 can COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 31,000.00 21,856.23 Achevé Envelope 4 0 1 8 0 opy pour les matériels roula &E nt du projet F 1-18/ANJ / Acquisition : lot Component 3: Project Mana 01 des fournitures de burea Single Stage - One 2018-12-0 2019-01-3 2019-03-0 IDA / 59790 gement Coordination and M A posteriori Demande de prix Open - National 4,500.00 0.00 Annulé u et lot 02 des consommabl Envelope 5 0 1 &E es informatiques pour le CE R Analanjirofo. F 05-19/SAV / Acquisition d'i Component 2: Investments Single Stage - One 2019-06-1 2019-08-1 2019-07-2 2019-08-2 2019-07-2 ntrants au profit des paysan COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 7,000.00 5,300.62 Achevé Envelope 0 6 0 6 7 s formateurs (PF). selected landscapes F 06-19/SAV / Acquisition d Component 2: Investments e matériels pour le sarclage Single Stage - One 2019-06-1 2019-08-1 2019-07-1 2019-11-2 2019-10-3 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 10,620.00 7,662.18 Achevé et la récolte au profit des pa Envelope 0 6 8 9 0 selected landscapes ysans formateurs (PF). MG-UGP PADAP-87384-GO- RFQ / Acquisition des matéri els informatiques (02 Deskto Component 1: Information a Single Stage - One 2018-11-2 2019-01-2 2019-02-1 IDA / 59790 A posteriori Demande de prix Open - National 35,000.00 0.00 Annulé p) et accessoires (02 imprim nd planning Envelope 1 0 9 antes) pour le logiciel ArcGI S ( Stockage et gestion des données) plus 10 GPS. MG-UGP PADAP-113652-GO -RFQ / Acquisition des matér iels et accessoires informati ques : Lot 1:11 Desktop Component 1: Information a Single Stage - One 2019-06-3 2019-08-2 2020-01-1 2019-09-2 2020-02-2 Lot 2:11 onduleurs online COFN / C1540 A posteriori Demande de prix Open - National 33,000.00 134,817.17 Achevé nd planning Envelope 0 9 2 8 2 Lot 3:09 Laptop avec 01 dis que dur externe de chaque Lot 4: imprimante : 01 A1, 0 6 A3 et 01 jet d'encre A4 Lot 5: 09 vidéoprojecteurs a vec écran MG-UGP PADAP-116266-GO -RFQ / Acquisition des : Component 3: Project Mana Lot 01 : 10 GPS (Global Posit Single Stage - One 2019-07-0 2019-09-0 2019-10-2 2019-10-0 2019-11-2 COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 12,000.00 46,888.43 Achevé ioning System). Envelope 3 1 1 1 6 &E Lot 02 : 10 appareils photos numériques. MG-UGP PADAP-120173-GO Component 3: Project Mana Single Stage - One 2019-07-1 2019-09-2 2020-01-0 2019-11-2 2020-02-1 -RFQ / Materiel et mobiler de COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 75,000.00 36,864.87 Achevé Envelope 1 3 3 2 0 bureau de l'UGP. &E MG-UGP PADAP-120176-GO Component 3: Project Mana Single Stage - One 2019-08-0 2019-10-1 2020-01-1 2019-11-1 -RFQ / Équipement de prote COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 3,000.00 5,206.72 Signé Envelope 4 7 2 6 ction individuel (EPI) du Proj &E et. F 01-19/BOE / Acquisition d Component 2: Investments e matériels pour les AUEs/Fé Single Stage - One 2019-06-0 2019-08-2 2019-10-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 82,000.00 0.00 Annulé dérations (Mini pelle, mini c Envelope 6 0 9 selected landscapes ompacteur motorisé et moto pompe) F 01-19/SOF / Achats des in Component 2: Investments Single Stage - One 2019-06-2 2019-09-0 2020-01-0 2019-10-0 2020-01-1 trants agricole pour paysans COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 11,800.00 1,487.51 Achevé Envelope 2 1 5 1 2 leaders/adoptants selected landscapes F 02-20 /SAV / Acquisition d' intrants (semences et engrai Component 2: Investments s) au profit des 111 anciens Single Stage - One 2020-05-1 2020-07-0 2020-07-0 2020-07-2 2020-07-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 8,110.00 6,732.54 Achevé paysans formateurs et de 50 Envelope 1 9 6 3 6 selected landscapes nouveaux paysans formateu rs dans le paysage d'Andapa , Région SAVA F 01-19/SAV / Acquisition d Component 3: Project Mana Single Stage - One 2019-08-1 2019-10-2 2019-11-2 e deux groupes électrogène COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 5,000.00 0.00 Annulé Envelope 9 9 8 s de la CER SAVA. &E F 02-19/SOF / Dotation en Component 2: Investments Single Stage - One 2019-04-0 2019-06-1 2019-07-1 matériels et équipements de COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 15,310.00 0.00 Annulé Envelope 3 3 3 surveillance des COBA selected landscapes F 02-19/ANJ / Acquisition de Component 2: Investments matériesl agricoles pour le r Single Stage - One 2019-10-0 2019-12-1 2020-01-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 15,710.00 0.00 Annulé eboisement dans les paysag Envelope 5 5 4 selected landscapes es de Soanierana Ivongo et I azafo. F 06-19/ANJ / Acquisition de Component 2: Investments s jeunes plants pour les acti Single Stage - One 2019-09-1 2019-11-2 2020-01-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 23,270.00 0.00 Annulé vités de reboisement dans l Envelope 4 4 8 selected landscapes es paysages d'Iazafo et de S oanierana Ivongo. F 02-18/BOE / Acquisition d Component 3: Project Mana e divers articles pour le fonc Single Stage - One 2018-11-3 2019-01-3 2019-03-0 IDA / 59790 gement Coordination and M A posteriori Demande de prix Limited 1,700.00 0.00 Annulé tionnement du bureau du Pr Envelope 0 0 1 &E ojet (Marovoay et Mahajang a) F 03-20/BOE / Acquisition d Component 2: Investments Single Stage - One 2020-06-0 2020-08-3 2021-07-2 2020-11-2 2021-07-2 e tarare pour le centre multi COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 21,875.00 20,276.70 Achevé Envelope 4 0 1 8 1 plicateur de semence à Tsar selected landscapes arano (RELANCE) F 04-20/SAV / Acquisition d Component 2: Investments es balances automatiques fo Single Stage - One 2020-04-2 2020-06-2 2020-07-1 2020-07-2 2020-09-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 1,250.00 794.36 Achevé rce de 20kg pour les semen Envelope 0 3 3 3 1 selected landscapes ciers dans le paysage d'And apa, Région SAVA. F 03-20/SAV / Acquisition d Component 2: Investments e 31 panneaux d'indication Single Stage - One 2020-03-1 2020-05-2 2020-06-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 1,300.00 0.00 Annulé pour les sites de reboisemnt Envelope 2 5 4 selected landscapes dans le paysage d'Andapa, Région SAVA. F 05-20/CN / Acquisition d' Component 3: Project Mana Passation de mar 2020-02-2 2020-03-0 2020-04-2 2020-10-2 un véhicule 4x4 pick-up du P IDA / V0430 gement Coordination and M A posteriori chés auprès des Direct 83,500.00 0.00 Annulé 8 9 3 0 ADAP &E agences de l'ON U F 01-20/CN / Acquisition de 4 véhicules (Motos) pour les Component 2: Investments Single Stage - One 2020-03-0 2020-05-1 2020-07-1 agents communaux chargés COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 16,000.00 0.00 Annulé Envelope 4 7 6 de l'appui aux Communauté selected landscapes s Locales à l'approche LIFE MG-UGP PADAP-76372-GO- RFQ / Acquisition d’images s atellitaires à haute résolutio Component 1: Information a Open - Internation Single Stage - One 2020-04-0 2020-06-1 2020-08-1 COFN / C1540 A posteriori Demande de prix 50,000.00 0.00 Annulé n avec modèle numérique d nd planning al Envelope 8 8 7 e terrain pour le paysage de Bealanana, d’une superficie de 2776 km2 environ. F 04-20/ANJ / Achat d'intran ts agricoles: Lot 01: Engrais minéraux Lot 02: Engrais organiques Lot 03: Semences: riz améli Component 2: Investments Single Stage - One 2021-06-2 2021-09-0 2020-12-2 2021-10-0 orés, de base, maïs et haric COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 89,280.00 26,212.33 Signé Envelope 5 7 6 7 ot selected landscapes Lot 04: Semences: tephrosia et stylosanthes Lot 05: Eclats de souches de Bachiaria et Pennisetum Lot 06: Semence riz F 06-20/BOE / Acquisition d e manguiers Component 2: Investments Single Stage - One 2020-10-0 2020-12-1 2020-12-1 2021-02-1 Lot 01 : Site d'Ambolomoty COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 97,500.00 9,896.21 Achevé Envelope 5 6 7 4 Lot 02 : Site de Tsararano selected landscapes Lot 03: Site d'Anosinalainolo na F 07-20/BOE / Acquisition d' Component 2: Investments Single Stage - One 2020-09-2 2020-12-0 2020-11-1 2021-03-3 2021-03-2 acacia pour la protection du COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,000.00 96,805.52 Achevé Envelope 6 1 7 1 2 sol selected landscapes F 08-20/BOE / Acquisition d' Component 2: Investments Single Stage - One 2020-09-2 2020-12-0 2020-11-2 2021-03-3 2021-04-0 eucalyptus pour le reboisem COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,500.00 101,868.48 Achevé Envelope 6 1 8 1 1 ent à vocation bois d'œuvre selected landscapes F 09-20/BOE / Acquisition d Component 2: Investments Single Stage - One 2020-10-0 2020-12-1 2020-11-1 2021-04-0 e plantule pour le regarniss COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 12,500.00 14,002.23 Signé Envelope 5 0 7 9 age des terrains de reboise selected landscapes ment 2019 - 2020 F 06-19/BOE / Acquisition d' Component 2: Investments engrais Single Stage - One 2020-09-2 2020-11-2 2020-12-1 2021-11-2 2021-04-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 97,000.00 29,536.56 Achevé Lot 1: Engrais organique Envelope 2 8 7 8 8 selected landscapes Lot 2: NPK et Urée F 10-20/BOE / Acquisition d e bouture et de haie vive Component 2: Investments Single Stage - One 2020-10-0 2020-12-1 2020-12-2 2021-03-1 Lot 1: Stylosanthès COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,000.00 30,351.26 Signé Envelope 5 0 3 0 lot 2: Brachiaria selected landscapes Lot 3: Vétiver F 11-20/BOE / Acquisition d Component 2: Investments e matériel végétal et de cult Single Stage - One 2020-09-2 2020-12-0 2020-12-1 2021-01-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 96,000.00 2,228.17 Achevé ure vivrière Envelope 7 2 6 1 selected landscapes Lot 1: arachide, riz pluvial, Maïs Lot 2: Bouture de manioc F 12-20/BOE / Acquisition d es citronniers Component 2: Investments Single Stage - One 2020-10-0 2020-12-1 2020-12-2 2021-02-0 Lot 01 : Site d'Ambolomoty COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 95,000.00 19,160.49 Achevé Envelope 5 0 3 8 Lot 02 : Site de Tsararano selected landscapes Lot 03: Site d'Anosinalainolo na Page 3 F 13-20/BOE / Achat d'oran Component 2: Investments giers : Single Stage - One 2020-10-0 2020-12-1 2020-12-2 2021-02-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,400.00 15,892.82 Achevé Lot 01 : Site d'Ambolomoty Envelope 5 0 8 8 selected landscapes Lot 02 : Site de Tsararano Lot 03: Site d'Anosinalainolo na F 03-19/ANJ / Achat d'intran ts agricoles pour:les payasn s formateurs, semenciers, a Component 2: Investments doptants et banques de sem Single Stage - One 2020-09-0 2020-11-1 2020-12-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 89,500.00 0.00 Annulé ences: Lot 01: Engrais minér Envelope 1 1 6 selected landscapes al et organique Lot 02: Sem ences rizicoles Lot 03: Matér iels végétaux pour l'agroéco logie et production fourragèr e F 03-20/ANJ / Acquisition de Component 2: Investments jeunes plants de culture de r 2020-08-2 2020-11-1 2020-09-0 2021-01-0 COFN / C1540 and capacity building in the A posteriori Demande de prix 22,150.00 10,262.33 Achevé ente pour l'agroforesterie à I 8 0 8 9 selected landscapes azafo et Soanierana Ivongo F 04-19/SOF / Achat des éq Component 2: Investments Single Stage - One 2019-06-2 2019-09-0 2019-10-0 uipement agricole pour pays COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 36,600.00 0.00 Annulé Envelope 3 2 2 ans leaders/adoptants. selected landscapes Component 2: Investments F 07-19/BOE / Acquisition d Single Stage - One 2019-09-2 2019-11-3 2019-12-3 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 33,000.00 0.00 Annulé es jeunes plants. Envelope 4 0 0 selected landscapes F 09-20/CN / Acquisition de Component 3: Project Mana Single Stage - One 2020-12-1 2020-12-1 2021-01-2 2021-03-1 2021-02-2 2021-03-2 fournitures de bureau pour l' COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 4,000.00 3,828.99 Achevé Envelope 0 7 4 6 3 6 Unité de Gestion de Projet P &E ADAP F 01-20/BOE / Acquisition d Component 2: Investments Single Stage - One 2021-02-2 2021-05-2 2021-11-2 e semence pour la diffusion COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 2,200.00 0.00 Annulé Envelope 0 5 1 des paquets techniques agri selected landscapes coles F 3-20/BOE / Acquisition de Component 2: Investments Single Stage - One 2020-06-0 2020-09-0 2020-07-1 2020-11-3 tarare pour le centre multipl COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 21,900.00 19,670.17 Signé Envelope 6 1 2 0 icateur de semence à Tsarar selected landscapes ano. F 04-20/CN / Acquisition de Component 3: Project Mana Single Stage - One 2020-11-1 2020-12-1 2021-01-1 2021-03-2 2021-02-1 COFN / C1540 A posteriori Demande de prix Open - National 2,250.00 7,641.34 Signé 7 coffres forts du PADAP. gement Coordination and M Envelope 5 7 4 1 3 &E F 07-20/CN / Acquisition de Component 3: Project Mana Single Stage - One 2020-11-0 2020-12-1 2021-01-1 2021-03-2 2021-03-1 2021-04-0 matériels informatiques du P COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 3,000.00 2,796.37 Achevé Envelope 7 7 6 2 7 5 ADAP: 9 stabilisateurs &E F 08-20/CN / Acquisition des Component 3: Project Mana Single Stage - One 2020-11-0 2020-12-1 2021-01-0 2021-03-2 2021-02-0 2021-03-2 09 vidéoprojecteurs avec éc COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 25,000.00 17,232.84 Achevé Envelope 7 7 6 4 5 5 ran du PADAP. &E F 04-19/SAV / Acquisition d Component 3: Project Mana Single Stage - One 2020-11-2 2021-01-1 2020-12-2 2021-02-0 2021-02-1 es consommables informati COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 21,880.00 21,420.49 Achevé Envelope 8 0 6 9 5 ques pour la CER SAVA &E F 02-19/SAV / Acquisition d Component 3: Project Mana Single Stage - One 2020-11-3 2021-01-1 2020-12-2 2021-02-1 2021-02-1 es fournitures de bureau po COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 21,880.00 13,631.51 Achevé Envelope 0 2 7 1 6 ur la CER SAVA. &E F 05-20/SAV / Acquisition d'i ntrants agricoles repartis en quatre lots: Lot1 : Semences de base Component 2: Investments Single Stage - One 2020-12-0 2021-02-0 2021-01-1 2021-03-1 2021-02-1 Lot2 : semences certifiées d COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 34,000.00 19,235.18 Achevé Envelope 5 8 1 0 6 e riz irrigué selected landscapes Lot 3 : Engrais organique Lot 4 : Urée Lot 5 : Graines pour 56 sites de pépinières permanente. F 01-20/SAV / Acquisition d es panneaux d'indication de s sites dans le paysage d'An Component 2: Investments Single Stage - One 2020-11-2 2021-02-1 2020-12-2 2021-03-1 2021-06-2 dapa, Région SAVA : COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 8,600.00 7,829.69 Achevé Envelope 8 1 6 3 7 Lot 01: sites de reboisement selected landscapes Lot 02 : sites de parcelle de démonstration F 14-20/CN / Achat de Prod Component 3: Project Mana Single Stage - One 2020-12-1 2020-12-1 2021-01-2 2021-02-2 uits d'entretien pour l'Unité COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 3,000.00 0.00 Annulé Envelope 0 7 4 3 de Gestion de Projet PADAP &E F 15-20/CN / Achat de cons Component 3: Project Mana Single Stage - One 2020-12-1 2020-12-1 2021-01-2 2021-03-2 2021-02-2 2021-04-0 ommable informatiques pou COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 20,500.00 18,530.15 Achevé Envelope 0 7 4 6 3 5 r l'Unité de Gestion de Projet &E PADAP F 06-20/CN / Acquisition des Component 3: Project Mana Single Stage - One 2020-11-1 2021-01-1 2021-02-1 matériels de lavage à haute COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 1,500.00 0.00 Annulé Envelope 5 4 3 pression du PADAP. &E F 07-20/SAV / Acquisition p our les vétérinaires mandat aires en vue d’améliorer la s anté des animaux d’élevage Component 2: Investments Single Stage - One 2020-12-1 2021-02-2 2021-03-2 au niveau du paysage d’And COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 5,000.00 0.00 Annulé Envelope 2 5 7 apa : selected landscapes Lot 1 : 02 (deux) réfrigérate urs solaires Lot 2 : 02 (deux) kits de vac cination F 02-20/SOF / Acquisitions d e semences certifiées de riz Component 2: Investments Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-04-2 2021-02-0 irrigué pour le Paysage de B COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 75,000.00 40,209.69 Signé Envelope 1 8 5 2 9 ealanana : selected landscapes LOT 01: riz certifiées X-265 Lot 02 : riz certifiées MK-34 F 04-20/SOF / Acquisition d Component 2: Investments e fumier de parc pour la mis Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-05-0 2020-12-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 100,000.00 67,305.70 Achevé e en œuvre de la riziculture Envelope 1 5 3 4 3 selected landscapes et de l'agroforesterie dans le paysage de Bealanana. F 05-20/SOF / Acquisition d' agrumes : Lot 1: 20 000 greffes de ma ndarinier ou de greffes d'ora Component 2: Investments Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-08-0 2021-05-0 nger COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 80,000.00 45,208.10 Achevé Envelope 1 8 4 5 1 Lot 2: 10 000 de citronnier selected landscapes Lot 3: 10 000 greffes de Pa mplemoussiers Lot 4: 30 000 porte-greffes d e la famille de mandarinier F 07-20/SOF / Acquisition d es jeunes plants de caféier e Component 2: Investments Single Stage - One 2021-01-1 2021-03-0 2020-12-2 2021-08-0 n 2 lots pour le paysage de COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 91,450.00 31,516.80 Achevé Envelope 1 8 6 5 Bealanana: selected landscapes Lot 01: 5 000 de caféier Ro busta Lot 02: 75 000 de caféier Ar F 08-20/SOF / Acquisition d' abica Component 2: Investments Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-04-1 2020-12-2 Engrais organique de type G COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 54,400.00 38,341.43 Achevé Envelope 1 5 4 9 2 uano pour le Paysage de Be selected landscapes alanana F 09-20/SOF / Acquisition d Component 2: Investments es jeunes plants pour stabili Single Stage - One 2021-01-2 2021-03-1 2020-12-0 2021-06-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,500.00 57,812.66 Achevé sation de terrains dégradés Envelope 1 7 9 5 selected landscapes (Ambararatabe Nord - Amba toriha Est) F 10-20/SOF / Fourniture de Component 2: Investments s jeunes plants pour protecti Single Stage - One 2021-01-2 2021-03-2 2020-12-2 2021-06-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,000.00 57,812.66 Achevé on des pistes ruraux (Antsa Envelope 1 8 1 6 selected landscapes maka -Beandrarezona) F 11-20/SOF / Achat des jeu Component 2: Investments Single Stage - One 2021-01-1 2021-03-2 2021-06-2 nes plants pour production d COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,500.00 0.00 Annulé Envelope 6 3 1 e bois énergie (Ambatosia) selected landscapes F 12-20/SOF / Achat des jeu Component 2: Investments Single Stage - One 2021-01-1 2021-03-1 2020-12-2 2021-06-1 2021-05-1 nes plants pour production d COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,400.00 67,907.88 Achevé Envelope 1 8 6 6 9 e bois d'œuvre (Ambatosia) selected landscapes F 13-20/SOF / Fourniture de Component 2: Investments s jeunes plants pour protecti Single Stage - One 2021-01-1 2021-03-1 2020-12-2 2021-06-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,000.00 57,239.35 Résilié on des périmètres irrigués à Envelope 1 8 2 6 selected landscapes réhabiliter par le Projet F 14-20/SOF / Acquisition d Component 2: Investments e jeunes plants pour protecti Single Stage - One 2021-01-1 2021-03-1 2020-12-2 2021-06-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 80,000.00 43,641.23 Résilié on des Lacs et Etangs (Beal Envelope 1 8 7 6 selected landscapes anana - Beandrarezona) F 15-20/SOF / Fourniture de Component 2: Investments s plants pour restauration d Single Stage - One 2021-01-1 2021-03-1 2020-12-2 2021-09-1 2022-02-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,000.00 92,215.65 Achevé es forêts dégradées (Analila Envelope 1 8 1 4 5 selected landscapes - Anjozoromadosy- Marotola na - Ankazotokana) F 16-20/SOF / Acquisition d Component 2: Investments es jeunes plants pour restau Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-06-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,000.00 57,926.23 Achevé ration/conservation des sols Envelope 1 8 0 6 selected landscapes (Bealanana - Ambodiampan a) F 17-20/SOF / Fourniture de Component 2: Investments s jeunes plants pour la prote Single Stage - One 2021-01-1 2021-03-2 2020-12-1 2021-06-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,800.00 87,330.08 Achevé ction autour des zones géré Envelope 6 6 6 4 selected landscapes es par les COBA (Mangindra no - Ambovonomby) F 18-20/SOF / Acquisition d' arbres autochtones à fruits c Component 2: Investments Single Stage - One 2021-01-1 2021-03-0 2020-12-1 2021-08-0 2021-04-2 omestibles : COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 69,000.00 125,053.64 Achevé Envelope 1 8 6 5 9 Lot 1: 30 000 Jacquier produ selected landscapes it Lot 2: 30 000 jeunes plants d'Eugenia F 19-20/SOF / Acquisition d es jeunes plaqueminiers, de bibaciers et de litchi: Lot 1: 30 000 variété amélio Component 2: Investments Single Stage - One 2021-01-1 2021-03-0 2020-12-2 2021-08-0 rée de plaqueminier (Kaki) COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 86,000.00 66,761.00 Achevé Envelope 1 8 1 5 Lot 2: 25 000 variété amélio selected landscapes rée de bibacier Lot 3: 20 000 jeunes plants de litchi F 20-20/SOF / Acquisition d e manguiers 2 lots pour le p aysage de Bealanana: Component 2: Investments Single Stage - One 2021-01-1 2021-03-0 2020-12-2 2021-08-0 Lot 01: 20 000 Manguier por COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 69,000.00 22,894.92 Signé Envelope 1 8 6 5 te-greffe selected landscapes Lot 02: 40 000 variétés amél iorées de manguiers F 21-20/SOF / Acquisition d e papayer en 2 lots : Component 2: Investments Lot 1: 40 000 de papayer (S Single Stage - One 2021-01-1 2021-03-0 2020-12-2 2021-08-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 92,000.00 39,921.28 Achevé olo Sunset, Solo Waimanalo, Envelope 1 8 5 5 selected landscapes Sunrise...) Lot2: 40 000 d'avocatier de race MEXICAIN. Page 4 F 22-20/SOF / Acquisition d Component 2: Investments Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-04-2 e dolomie agricole de redres COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 64,000.00 43,150.08 Achevé Envelope 6 3 4 7 sement du sol pour le Paysa selected landscapes ge de Bealanana F 23-20/SOF / Acquisition d'i Component 2: Investments Single Stage - One 2021-01-1 2021-03-1 2020-12-1 2021-04-2 ntrants agricoles de synthès COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 89,000.00 56,716.05 Achevé Envelope 6 3 5 7 e (NPK et Urée) pour le Pays selected landscapes age de Bealanana F 25-20/SOF / Acquisition d Component 2: Investments e Semences de Brachiaria o Single Stage - One 2021-01-1 2021-03-2 2020-12-2 2021-04-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 95,000.00 106,338.91 Résilié u de Stylosanthès dans le pa Envelope 6 1 6 0 selected landscapes ysage de Bealanana. F 08-20/SAV / Acquisition d Component 3: Project Mana es produits d'entretien pour Single Stage - One 2021-02-0 2021-04-0 2021-05-0 COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 3,130.00 0.00 Annulé la Cellule d'Exécution Régio Envelope 3 9 9 &E nale SAVA (RELANCE). F 03-19/SAV / Acquisition d Component 3: Project Mana Single Stage - One 2020-11-3 2021-01-1 2021-02-1 COFN / C1540 A posteriori Demande de prix Open - National 3,130.00 0.00 Annulé es produits d'entretien pour gement Coordination and M Envelope 0 2 1 la CER SAVA &E F 02-20/ BOE / Acquisition Component 3: Project Mana Single Stage - One 2021-01-0 2021-04-0 2021-05-0 de consommables informati COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 2,000.00 0.00 Annulé Envelope 2 8 8 ques pour 2 années &E F 04-21/BOE / Acquisition d’ intrants pour les riziculteu Component 2: Investments rs dans les CR d'Ambolomot Single Stage - One 2021-03-0 2021-05-2 2021-04-1 2021-06-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,500.00 98,512.49 Achevé y, de Tsararano et d'Anosina Envelope 5 3 2 2 selected landscapes lainolona Lot 1 engrais de type organi que Lot 2 NPK et d' Urée F 02-21/BOE / Acquisition d e semence certifiée de riz irr Component 2: Investments Single Stage - One 2021-03-0 2021-05-1 2021-03-2 2021-06-1 2021-04-2 igué X 360 et X 398 pour les COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,500.00 7,704.83 Achevé Envelope 2 5 7 4 0 riziculteurs dans les CR d'A selected landscapes mbolomoty, de Tsararano et d'Anosinalainolona F 03-19/BOE / Acquisition d Component 3: Project Mana Single Stage - One 2021-03-2 2021-06-0 2021-04-2 2021-07-0 2021-06-2 COFN / C1540 A posteriori Demande de prix Open - National 3,400.00 3,612.33 Achevé es fournitures de bureau gement Coordination and M Envelope 2 2 3 2 0 &E F 06-20/SAV / Acquisition d' Component 2: Investments Single Stage - One 2021-03-0 2021-04-2 2021-04-0 2021-05-2 2021-04-3 équipements pour les 4 COB COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 6,810.00 2,660.40 Achevé Envelope 3 6 4 6 0 AS dans le paysage d'Andap selected landscapes a, Région SAVA; F 09-20/SAV / Acquisition d es matériels pour la mise en Component 2: Investments oeuvre des activités liées à l Single Stage - One 2021-02-0 2021-04-1 2021-04-0 2021-05-1 2021-06-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 22,000.00 19,805.99 Achevé a production des jeunes pla Envelope 3 9 4 9 7 selected landscapes nts de 56 sites pépinières po lyvalents dans les 14 Comm unes du Paysage d'Andapa F 02-21/ANJ / Achat d'engrai s minéraux pour les Paysans Component 2: Investments Single Stage - One 2021-03-2 2021-05-1 2021-05-2 Formateurs (PF) et les Paysa COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 9,500.00 0.00 Annulé Envelope 6 6 2 ns Semenciers (PS) dans les selected landscapes paysages d'Iazafo et de Soa nierana Ivongo F 27-20/SOF / Achat des pet its matériels d'entretien (bro Component 2: Investments Single Stage - One 2021-10-0 2021-12-1 2022-02-0 uettes, gants, gilets, etc.) po COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 16,000.00 0.00 Annulé Envelope 5 8 1 ur la pérennité de la route RI selected landscapes P 117 M Bealanana - Ambat oriha Est F 2-21/ANJ / Achat d'engrais minéraux pour les Paysans F Component 2: Investments Single Stage - One 2021-05-2 2021-02-1 2021-07-1 2021-03-2 2021-08-0 ormateurs (PF) et les Paysan COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 9,500.00 10,185.75 Achevé Envelope 7 0 6 6 5 s Semenciers (PS) dans les p selected landscapes aysages d'Iazafo et de Soani erana Ivongo. F 13-20/CN / Acquisition de Component 2: Investments Single Stage - One 2021-07-1 2021-09-1 2021-08-1 2021-10-1 2021-08-2 12 GPS pour les Services tec COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 7,000.00 10,351.39 Achevé Envelope 0 8 6 8 7 hniques déconcentrées. selected landscapes F 11-20/CN / Acquisition de 43 motos pour les régions d' intervention du Projet (dont Component 2: Investments Single Stage - One 2021-06-3 2021-06-1 2021-07-1 2021-06-1 2021-08-0 2021-06-2 2021-08-2 2021-08-1 2021-10-0 2022-04-0 : 7 motos pour les fédératio COFN / C1540 and capacity building in the A posteriori Appel d'offres Limited 253,520.00 0.00 Annulé Envelope 0 1 0 1 9 9 9 7 3 1 ns des AUEs, 24 motos pour selected landscapes les Services techniques déc oncentrées et 12 motos pou r les nouveaux agent du Proj et. F 01-21/SAV / Acquisition d Component 2: Investments es intrants pour la mécanisa Passation de mar 2021-04-2 2021-04-2 2021-05-0 2021-04-2 2021-06-1 2021-04-2 2022-04-1 COFN / C1540 and capacity building in the A posteriori Direct 59,760.00 61,074.43 Achevé tion des travaux de repiqua ché de gré à gré 9 6 4 6 8 1 4 selected landscapes ge dans le paysage d'Andap a. F 02-21/SAV / Acquisition d Component 2: Investments e Graines pour les 56 sites p Single Stage - One 2021-05-0 2021-05-3 2021-06-0 2021-06-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 20,400.00 3,833.58 Résilié épinières polyvalents dans l Envelope 2 0 5 4 selected landscapes es 14 Communes du Paysag e d'Andapa (RELANCE) F 01-19/ANJ / Fourniture de Component 2: Investments Single Stage - One 2021-05-1 2021-07-2 2021-10-1 bureau pour la CER Analanjir COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 40,000.00 0.00 Annulé Envelope 5 3 1 ofo. selected landscapes F 04-19/ANJ / Acquisition de Component 3: Project Mana Single Stage - One 2021-05-2 2021-07-3 2021-08-2 s consommables informatiq COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 27,000.00 0.00 Annulé Envelope 5 0 9 ues pour la CER Analanjirofo &E . F 05-19/ANJ / Acquisition de Component 3: Project Mana Single Stage - One 2021-04-3 2021-07-0 2021-08-0 s produits d'entretien pour l COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 43,530.00 0.00 Annulé Envelope 0 8 7 a CER Analanjirofo &E F 03-21/SAV / Acquisition d'i ntrants agricoles au profit d es Paysans Formateurs du p aysage d'Andapa, répartis e Component 2: Investments Single Stage - One 2021-07-1 2021-09-2 2021-07-2 2021-10-1 2021-09-1 n trois lots : COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 8,000.00 244,181.21 Achevé Envelope 9 7 1 2 4 - Lot 1 : Semences certifiées selected landscapes de riz irrigué - Lot 2 : Engrais organique d e type Guano - Lot 3 : Urée" F 12-20/CN / Acquisition de : Lot 1: 31 ordinateurs portabl e. Component 2: Investments Single Stage - One 2021-07-0 2021-09-1 2021-08-1 2021-10-1 2021-08-2 Lot 2: 11 ordinateurs de bur COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,500.00 96,956.92 Achevé Envelope 4 2 6 2 7 eau avec 1 onduleur de cha selected landscapes que (05 pour les fédérations des AUEs et 06 pour le Proje t). Lot 3: 08 imprimantes laser (04 pour les fédérations des F 02-20/ANJ AUEs le Projet) de / Acquisition et 04 pour matériels agricoles: - Lot 01: 277 sarcleuses - Lot 02: 900 Sarcleuses, 18 Component 2: Investments 0 charrues et 450 fourches Single Stage - One 2021-09-0 2021-11-1 2020-12-0 2021-12-3 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 66,000.00 3,737.93 Signé - Lot 03: 63 vanneuses et 63 Envelope 5 5 8 0 selected landscapes batteuses - Lot 04: 90 Pulvérisateurs, 1 35 arrosoirs et 9 rouleau de 100 m de gaine en polyprop ylène F 05-21/BOE / Acquisition d e semence de riz irrigué X Component 2: Investments Single Stage - One 2021-02-2 2021-02-1 2021-04-2 2021-05-2 360 et X 398 pour les rizicult COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 98,500.00 0.00 Annulé Envelope 8 2 8 8 eurs dans les CR d'Ambolom selected landscapes oty, de Tsararano et d'Anosi nalainolona F 04-19/BOE / Achat pneus Component 3: Project Mana Single Stage - One 2021-04-1 2021-07-1 2021-08-1 COFN / C1540 A posteriori Demande de prix Open - National 4,000.00 0.00 Annulé pou 2 années pour la CER B gement Coordination and M Envelope 9 3 2 oeny &E F 10-20/SAV / Acquisition d es 56 lots des EPI (Bottes, C ombinaisons, Gants, Imperm Component 2: Investments Single Stage - One 2021-07-1 2021-09-2 2021-09-0 2021-10-2 2021-10-0 éables, Gilets, casquettes) p COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 7,000.00 5,623.74 Achevé Envelope 8 1 4 1 2 our les Pépiniéristes travaill selected landscapes ant dans les sites pépinières polyvalents dans les 14 Com munes du Paysage d'Andap a F 05-21/SAV / Acquisition d'i ntrants (semences pour les Component 2: Investments cultures intercalaires et eng Single Stage - One 2021-09-0 2021-10-2 2021-11-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 14,000.00 0.00 Annulé rais organique) au profit des Envelope 6 3 2 selected landscapes 50 paysans adoptant l'agrof oresterie dans le paysage d' Andapa, F 24-20/SOF / Acquisition d Component 2: Investments e matériels végétaux pour p Single Stage - One 2021-01-1 2021-03-2 2021-05-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,000.00 0.00 Annulé lante de couverture dans le Envelope 6 3 7 selected landscapes Paysage de Bealanana F 03-20/SOF / Acquisition ar bres fruitiers: Lot1: 5 000 pommier porte- greffe Lot2: 20 000 variété amélior Component 2: Investments Single Stage - One 2021-01-1 2021-03-0 2021-07-3 ée de pommier COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 86,000.00 0.00 Annulé Envelope 1 3 1 Lot3: 5 000 pêcher porte-gr selected landscapes effe Lot4: 20 000 variété amélior ée de pêcher Lot5: 5 000 poirier porte-gre ffe Lot6: 20 000 variété amélior de poirier / Acquisition d' F 01-21/ANJ ée Alambics et accessoires d'al Component 2: Investments ambics pour les paysans pra Single Stage - One 2021-08-2 2021-11-0 2022-05-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 46,060.00 0.00 Annulé tiquants la distillation d'esse Envelope 2 5 4 selected landscapes nce de girofle dans les pays ages d'Iazafo et de Soaniera na Ivongo. F 05-19/BOE / Acquisition d es matériels agricole (Sarcle Component 2: Investments Single Stage - One 2020-09-2 2020-11-2 2020-12-2 use, charrue à soc, herse à COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 43,800.00 0.00 Annulé Envelope 3 9 9 dents, pulvérisateur, batteu selected landscapes se à pédale, bâche) pour un e année. F 02-21/CN / Acquisition de 19 motos routier du Projet ( Component 2: Investments Single Stage - One 2021-09-2 2021-12-2 2021-12-1 2022-03-1 dont : 7 motos pour les fédé COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 58,000.00 0.00 Annulé Envelope 7 4 0 0 rations des AUEs et 12 moto selected landscapes s pour les nouveaux agent d u Projet). F 03-21/CN / Acquisition de Component 2: Investments 24 motos cross pour les Ser Single Stage - One 2021-09-3 2021-12-2 2021-10-1 2021-12-2 2021-11-0 2022-01-2 2021-11-2 2022-02-1 2022-01-0 2022-04-0 COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé vices techniques déconcentr Envelope 0 3 0 4 9 5 9 8 3 3 selected landscapes ées dans la zone d'interventi on du Projet. F 03-21/ANJ / Acquisition de Component 3: Project Mana Passation de mar 2021-09-1 2021-09-2 2021-11-0 2022-05-0 véhicule 4x4 pick-up pour F COFN / C1540 gement Coordination and M A posteriori Direct 50,000.00 0.00 Annulé ché de gré à gré 5 5 9 8 DAR Analanjirofo &E Page 5 F 03-21/BOE / Acquisition d' Component 2: Investments alevins pour les pisciculteur Single Stage - One 2021-03-1 2021-05-1 2021-06-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 97,000.00 0.00 Annulé s dans les CR de Marosakoa Envelope 2 1 5 selected landscapes , d'Ambolomoty et de Tsarar ano F 04-21BOE / Acquisition de divers matériels pour les pis Component 2: Investments Single Stage - One 2021-03-0 2021-05-1 2021-07-0 ciculteurs dans les CR de M COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 98,000.00 0.00 Annulé Envelope 7 7 1 arosakoa, d'Ambolomoty et selected landscapes de Tsararano ( filets, bacs,glacières, fumo irs) F 02-20/CN / Conception et Component 2: Investments fourniture de supports de co Single Stage - One 2021-10-0 2021-12-1 2022-01-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 9,500.00 0.00 Annulé mmunication pour le PADAP Envelope 5 8 7 selected landscapes (Flyers, banderôles, T-shirt, Polo, …) F 07-21/SAV / Acquisition d es matériels et outillages au profit du Lycée Technique et Component 2: Investments Single Stage - One 2021-08-2 2021-10-1 2021-11-1 Professionnel d'Andapa pour COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 11,500.00 0.00 Annulé Envelope 1 1 0 : selected landscapes Lot 1: L' Atelier d'entretien e t de réparation des matériel s agricoles Lot 2: Les travaux pratiques F 04-21/CN / Acquisition de Component 3: Project Mana Single Stage - One 2021-12-1 2021-12-2 2021-12-2 2021-12-2 2022-01-2 2022-01-2 2022-02-1 2022-02-1 2022-03-1 2022-03-1 2022-08-0 COFN / C1540 A posteriori Appel d'offres Open - National 496,000.00 513,604.00 Achevé 8 voitures type 4x4 . gement Coordination and M Envelope 3 3 3 4 2 5 1 8 2 4 9 &E F 10-20/CN / Acquisition de réfrigérateurs solaires (RS) e t kits de vaccination (KV) po Component 2: Investments ur les Paysages d’Andapa, d Single Stage - One 2022-02-1 2022-04-1 2022-06-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 50,000.00 0.00 Annulé e Bealalana et de Marovoay Envelope 0 0 9 selected landscapes : Lot 1 : 7 réfrigérateurs solair es (RS) Lot 2 : 7 kits de vaccination (KV). F 05-22/CN / Achat d'équipe Component 3: Project Mana Single Stage - One En attente d 2022-10-0 2022-12-0 2023-01-0 COFN / C1540 A posteriori Demande de prix Open - National 9,000.00 0.00 ment de protection individu gement Coordination and M Envelope 'exécution 3 5 4 elle &E F 08-22/CN / Acquisition des Component 2: Investments kits solaire pour les 40 Com Single Stage - One En attente d 2022-09-0 2022-11-3 2023-02-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 52,000.00 0.00 munes Rurales dans les pay Envelope 'exécution 8 0 3 selected landscapes sages d'intervention du Proj et. F 03-22/CN / Achats des ma tériels informatiques du Proj Component 2: Investments et : Single Stage - One 2022-10-2 2022-12-2 2022-11-0 2022-12-2 2022-12-0 2023-01-2 2022-12-2 2023-03-2 2023-01-2 2023-04-2 2023-03-2 COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 200,000.00 0.00 Achevé Lot 01 : 40 ordinateurs de b Envelope 8 3 2 3 2 4 2 1 6 8 7 selected landscapes ureau (DESKTOP) Lot 02 : 40 onduleurs Lot 03 : 20 ordinateurs porta bles F 01-22CN / Acquisition de Component 2: Investments motos du Projet : Single Stage - One En cours d'e 2022-10-1 2022-11-0 2022-10-1 2022-11-1 2022-11-1 2022-12-0 2022-12-1 2023-03-0 2022-12-2 2023-02-2 COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 240,000.00 0.00 Lot 01 : 33 motos cross Envelope xécution 4 5 9 4 8 6 0 3 7 5 selected landscapes Lot 02 : 04 motos routiers F 04-22/CN / Développemen Component 3: Project Mana Single Stage - One 2022-09-0 2022-12-0 2023-04-0 t d'un logiciel de suivi-évalu COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 31,000.00 0.00 Annulé Envelope 8 8 7 ation du Projet. &E F 01-21/CN / Achat de Prod Component 3: Project Mana Single Stage - One 2021-10-1 2021-10-1 2021-11-2 2021-12-2 uits d'entretien pour l'Unité COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 3,500.00 0.00 Annulé Envelope 0 9 4 4 de Gestion de Projet PADAP &E F 01-23/CN / Acquisition de Component 3: Project Mana Single Stage - One En attente d 2023-11-2 2023-11-2 2023-12-2 2024-01-1 2024-02-0 2024-03-0 COFN / C1540 A posteriori Appel d'offres Open - National 150,000.00 0.00 smart board gement Coordination and M Envelope 'exécution 0 5 5 5 4 5 &E F 6-22/CN / Acquisition de d Component 1: Information a Single Stage - One En attente d 2023-11-3 2023-12-0 2024-01-0 2024-01-1 2024-02-0 2024-03-1 rones : COFN / C1540 A posteriori Appel d'offres Open - National 172,000.00 0.00 nd planning Envelope 'exécution 0 2 1 6 2 8 Lot 01 : Drones semeurs Lot 02 : Drones agricoles F 06-22/CN / Acquisition des Component 1: Information a Single Stage - One 2022-09-0 2022-11-3 2023-02-0 COFN / C1540 A posteriori Demande de prix Open - National 45,000.00 0.00 Annulé drones pour le Projet nd planning Envelope 8 0 3 F 05-23/CN / Acquisition des matériels informatiques pou Component 2: Investments r remonter et le traitement Single Stage - One En attente d 2023-12-0 2024-02-0 2024-04-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 65,000.00 0.00 des données : Envelope 'exécution 5 3 3 selected landscapes Lot 01 : 01 Serveur avec on duleur Lot 02 : 10 Ordinateurs port ables F 07-23/CN Lot / Acquisition d'i 03 : 03 Imprimantes ntrants : Lot 01 : Engrais NPK 11 22 1 Component 2: Investments Single Stage - One En attente d 2023-11-3 2023-12-0 2024-01-0 2024-01-2 2024-02-1 2024-04-1 6 COFN / C1540 and capacity building in the A priori Appel d'offres Open - National 2,351,000.00 0.00 Envelope 'exécution 0 5 4 4 8 8 Lot 02 : Engrais organique e selected landscapes nrichis de phosphate Lot 03 : Urée Lot 04 : Diverse semence F 09-23/CN / Achat de maté riels agricoles : Lot 01 : Tracteurs à puissan Component 2: Investments ce élevée avec accessoires Single Stage - One En attente d 2023-12-0 2023-12-1 2024-01-0 2024-01-2 2024-02-2 2024-04-2 COFN / C1540 and capacity building in the A posteriori Appel d'offres Open - National 1,910,000.00 0.00 Lot 02 : Motoculteurs avec a Envelope 'exécution 5 0 9 9 2 2 selected landscapes ccessoires Lot 03 : matériels motorisés Lot 04 : petit matériels agric oles F 10-23/CN / Acquisition de semences améliorés : Lot 1: semence de arachide Component 2: Investments Single Stage - One En attente d 2023-12-1 2024-02-1 2024-04-1 Lot 2: semence de haricot COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 99,500.00 0.00 Envelope 'exécution 0 2 2 Lot 3: semence de oignon ro selected landscapes uge Lot 4: semence de ail Lo 5 : semences riz NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UGP PADAP-70332-NC- RFQ / Service de transit pour Component 3: Project Mana dédouanement de matériels Single Stage - One 2018-07-2 2018-09-0 2018-08-0 2018-10-0 IDA / 59790 gement Coordination and M A posteriori Demande de prix Open - National 57,000.00 34,129.26 Signé roulants (10 voitures et 20 Envelope 4 4 5 4 &E motos), et service de mise e n circulation des véhicules e t moto du PADAP. C 03-20/CN / Service de tra Component 3: Project Mana Single Stage - One 2020-03-0 2020-04-1 2020-05-1 nsit et douane pour le dédo COFN / C1540 gement Coordination and M A posteriori Demande de prix Open - National 5,500.00 0.00 Annulé Envelope 8 7 7 uanement des matériels roul &E ants du PADAP PSNC 01-21/SOFIA / Mise en œuvre des activités de reboi sement à vocation bois d'œ uvre et d'agroforesterie : Component 2: Investments Single Stage - One 2021-04-0 2021-02-1 2021-05-1 2021-03-1 2022-02-0 Lot 1 : dans le Fokontany d' COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 99,800.00 90,458.98 Signé Envelope 5 9 0 9 4 Ampandrana de la CR Amba selected landscapes tosia Lot 2 : dans les Fokontany : Ambalabe, Ambohimitsinjo e t Beanatsindra de la CR Amb atosia PSNC 01-21/BOE / Réalisati on des activités de reboisem ent dans le Paysage de Mar Component 2: Investments Passation de mar 2021-02-2 2021-02-2 2021-03-0 2021-03-0 2021-04-2 2021-03-1 2022-07-1 2021-06-2 ovoay COFN / C1540 and capacity building in the A posteriori Direct 800,000.00 438,445.98 Achevé ché de gré à gré 6 6 8 2 2 5 6 4 Lot 01: Essence à vocation é selected landscapes nergetique Lot 02: Essence à vocation b ois d'oeuvre PSNC 03-21/SOFIA / Conduit e de reboisement à vocation bois énergie et 115 Ha de pl Component 2: Investments Single Stage - One 2021-04-0 2021-02-1 2021-05-1 2021-03-1 2022-02-0 antation d'arbres fruitiers Lo COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 99,500.00 158,708.79 Signé Envelope 5 9 0 9 4 t 1: dans 04 Fokontany de la selected landscapes CR Ambodiampana Lot 2 : dans 06 Fokontany d e la CR Antsamaka PSNC 04-21/SOFIA / Mise en œuvre de reboisement et d' embocagement pour protect Component 2: Investments Single Stage - One 2021-04-0 2021-02-1 2021-05-1 2021-03-1 2022-02-0 ion et restauration des sols. COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 99,700.00 158,708.79 Signé Envelope 5 9 0 9 4 Lot 1 : dans 04 Fokontany d selected landscapes e la CR Ambodiampana Lot 2 : dans 06 Fokontany d e la CR Bealanana PSNC 07-21/SOFIA / Protecti on PI via reboisement et pla ntation d'arbres fruitiers dan s la Commune Rurale de Be Component 2: Investments Single Stage - One 2021-04-0 2021-02-1 2021-05-1 2021-03-1 2022-02-0 andrarezona COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 99,600.00 143,231.68 Signé Envelope 5 9 0 9 4 Lot 1 : dans le Fokontany de selected landscapes Beandrarezona, Lot 2 : dans les 03 Fokontan y : Andraratrarina, Ambodis atrana, Amberivery PSNC 03-21/BOE / Agence d e paiement des travaux de r Component 2: Investments Single Stage - One 2021-03-2 2021-05-1 2021-08-1 eboisement , de l'agroforest COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 40,000.00 0.00 Annulé Envelope 0 8 6 erie et l'amélioration des pât selected landscapes urages dans la Région Boen y PSNC 08-21/SOFIA / Agence Component 2: Investments de paiement des travaux de Single Stage - One 2021-04-1 2021-06-0 2021-09-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 50,000.00 0.00 Annulé reboisement ,de l'agroforest Envelope 0 8 6 selected landscapes erie pour la Région Sofia PSNC 06-21/ANJ / Agence d e paiement: -Lot 1 : Reboisement à Anal abe -Lot 2: Reboisement Iazafo n Component 2: Investments ord et sud Single Stage - One 2021-08-0 2021-07-1 2021-10-0 2021-09-0 2022-04-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 52,796.00 46,078.02 Signé -Lot 3: Reboisement à Soani Envelope 9 4 8 4 6 selected landscapes erana ouest -Lot 4: Reboisement pour les COBA -Lot 5: Installation d’un peup lement forestier et agrofores terie -Paysage Soanierana Iv ongo PSNC 05-21/SOFIA / Rebois ement pour protection auto ur des zones gérées par les Component 2: Investments Single Stage - One 2021-04-0 2021-05-1 2022-02-0 COBA COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 99,150.00 0.00 Annulé Envelope 5 0 4 Lot 1 : dans 08 Fokontany d selected landscapes e la CR Mangindrano Lot 2 : dans 05 Fokontany d e la CR Ambovonomby PSNC 06-21/SOFIA / Réalisa tion de reboisement pour st abilisation des terrains dégr Component 2: Investments Single Stage - One 2021-04-0 2021-05-1 2022-02-0 adés COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 99,750.00 0.00 Annulé Envelope 5 0 4 Lot 1 : dans 07 Fokontany d selected landscapes e la CR Ambatoriha Est Lot 2 : dans 03 Fokontany d e la CR Ambararatabe Nord Page 6 PSNC 02-21/SOFIA / Plantati on d'arbres à vocations mult iples pour la protection des versants dénudés: Component 2: Investments Single Stage - One 2021-04-0 2021-05-1 2022-02-0 Lot 1 : dans 05 Fokontany d COFN / C1540 and capacity building in the A posteriori Demande de prix Limited 99,150.00 0.00 Annulé Envelope 5 0 4 e la CR Analila selected landscapes Lot 2 : dans 05 Fokontany d e la CR Anjozoromadosy ; 1 Fokontany de la CR Ankazot okana ; dans 05 Fokontany de la CR Marotolana PSNC 05-21/ANJ / Recrutem ent d'agence d'encadrement d'un peuplement forestier et Component 2: Investments Single Stage - One 2021-09-0 2021-11-0 2022-12-1 agroforestier dans les Com COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 57,000.00 0.00 Annulé Envelope 3 2 7 munes de Manompana, Anta selected landscapes nifotsy, Soanierana Ivongo, Fotsialanana et Ambinanisak ana- Paysage de Soanierana Ivongo PSNC 02-21/ANJ / Encadrem ent des travaux de reboisem ent sur une surface de 257h Component 2: Investments a dans le PAYSAGE D'IAZAF Single Stage - One 2021-02-2 2021-04-2 2022-09-1 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 34,154.00 0.00 Annulé O ZONE NORD ET SUD, Com Envelope 0 6 8 selected landscapes munes Maromitety, Ampasi mazava, Antanamarina, Vav atenina, Mahanoro et Ambat oharanana- Région Analanjir ofo PSNC 03-21/ANJ / Gestion d es personnels HIMO et suivi- encadrement des travaux d Component 2: Investments e reboisement sur une surfa Single Stage - One 2021-03-0 2021-05-0 2022-06-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 64,106.00 0.00 Annulé ce de 482ha au niveau de 0 Envelope 8 7 1 selected landscapes 7 Fokontany dans le PAYSAG E DE SOANIERANA IVONGO, ZONE OUEST, Communes A mbahoabe et Antenina- Régi on Analanjirofo PSNC 01-21/ANJ / Encadrem ent technique et socio-organ isationnel des travaux de re Component 2: Investments Single Stage - One 2021-03-0 2021-05-0 2022-06-2 boisement sur une surface d COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 54,422.00 0.00 Annulé Envelope 8 7 1 e 409ha au niveau de 03 Fo selected landscapes kontany dans le PAYSAGE D' IAZAFO, ZONE ANALABE, Co mmune Maromitety- Région Analanjirofo PSNC 04-21/ANJ / Recrutem ent d’une Agence d’Exécutio Component 2: Investments n pour l’accomplissement d Single Stage - One 2021-03-0 2021-05-0 2022-06-2 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 50,623.00 0.00 Annulé u reboisement à grande éch Envelope 8 7 1 selected landscapes elle au niveau des zones de transfert de gestion des CO BA de la Commune Ambaho abe PSNC 04-21/SAV / Agence de paiement: Component 2: Investments Lot 1: Reboisement dans la Single Stage - One 2021-12-0 2022-02-0 2022-10-0 COFN / C1540 and capacity building in the A posteriori Demande de prix Open - National 20,000.00 0.00 Annulé zone sud du Paysage d'Anda Envelope 5 4 2 selected landscapes pa Lot 2: Reboisement dans la zone nord du Paysage d'And apa PSNC 01-22/CN / Édition de s plans d’aménagement et d Component 1: Information a Single Stage - One 2022-02-1 2022-03-2 2022-05-0 2022-05-0 2022-05-3 COFN / C1540 A posteriori Demande de prix Open - National 98,000.00 26,652.22 Achevé e gestion durable des paysa nd planning Envelope 0 8 1 7 1 ges (PAGDP) pour les cinq P aysages du PADAP. PSNC 02-22/CN / Service po ur encadrement des activité s : de stabilisation de flancs Component 2: Investments de collines (terracing), la res Passation de mar 2023-01-0 2022-12-2 2023-01-1 2023-01-2 2023-03-0 2023-04-2 2023-03-1 COFN / C1540 and capacity building in the A posteriori Direct - National 1,323,000.00 0.00 Signé tauration des forêts et les tr ché de gré à gré 6 7 1 5 3 8 7 selected landscapes avaux d’assainissement ma nuel des canaux secondaire s en HIMO dans les paysage s d’intervention du PADAP. CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C 6-18/CN / Etude d'aména gement (APS-APD-EIES-PAR- Component 2: Investments Sélection fondée 2018-04-1 2018-02-0 2018-02-2 2018-05-1 2018-03-3 2018-06-1 2018-04-1 2018-07-0 2018-05-0 2018-07-2 2018-05-2 2018-09-1 2018-10-2 DAO-MGE) et surveillance d IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 62,500.00 51,882.50 Signé 2018-01-22 9 6 8 1 0 2 4 2 4 4 8 3 5 es travaux dans le périmètr selected landscapes e coût e d'Andranomafana Mangind rano, région Sofia. C 4-18/CN / Etude de rehabi litation des infrasrtuctures Component 2: Investments Sélection fondée hydroagricoles (APS-APD-EIE 2018-03-2 2018-02-0 2018-02-2 2018-05-1 2018-03-3 2018-06-1 2018-04-1 2018-07-0 2018-05-0 2018-07-2 2018-05-2 2018-09-1 2018-11-2 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 500,000.00 287,114.06 Signé 2018-01-22 S-PAR-DAO-MGE) et surveilla 7 6 8 0 0 2 4 2 4 7 8 8 4 selected landscapes e coût nce des travaux dans le péri mètre de Iazafo, Région Ana lanjirofo C 5-18/CN / Etude de recon struction du barrage et réfec Component 2: Investments Sélection fondée tion des réseaux hydroagric 2018-04-1 2018-02-0 2018-02-2 2018-05-1 2018-03-3 2018-06-1 2018-04-1 2018-07-1 2018-05-0 2018-07-2 2018-05-2 2018-09-1 2018-10-2 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 87,500.00 23,197.46 Signé 2018-01-22 oles (APD-EIES-PAR-DAO-MG 9 6 8 0 0 2 4 3 4 4 8 5 5 selected landscapes e coût E) et surveillance des travau x dans le périmètre d'Anjohi be Ambatosia, Région Sofia. C 7-18/CN / Etude de réhabi litation de périmètre irrigué Component 2: Investments Sélection fondée 2018-04-1 2018-02-0 2018-02-2 2018-05-1 2018-03-3 2018-06-1 2018-04-1 2018-07-1 2018-05-0 2018-07-2 2018-05-2 2018-09-2 2018-11-2 (APD-EIES-PAR-DAO-MGE) et IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 125,000.00 29,974.84 Signé 2018-01-22 9 6 8 0 0 2 4 3 4 4 8 5 4 surveillance des travaux dan selected landscapes e coût s le périmètre de Bealanana I, région Sofia. C 8-18/CN / Etude d'aména gement (APS-APD-EIES-PAR- Component 2: Investments Sélection fondée 2018-02-0 2018-02-2 2018-03-3 2018-04-1 2018-05-0 2018-05-2 2018-11-2 DAO-MGE) pour la stabilisati IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 54,000.00 0.00 Annulé 2018-01-22 6 8 0 4 4 8 4 on des terrasse à Bealanana selected landscapes e coût et surveillance des travaux. C 03-18/CN / Un cabinet d'a Component 3: Project Mana Sélection au moi 2018-01-2 2018-01-3 2018-02-1 2018-04-1 2018-03-1 2018-05-1 2018-03-2 2018-05-1 2018-04-0 2018-05-2 2018-04-2 2018-06-1 2018-07-2 IDA / 59790 A posteriori Open - National 30,000.00 8,305.01 Signé 2018-01-15 udit financier du PADAP. gement Coordination and M ndre coût 3 1 7 7 9 7 9 8 9 5 9 2 8 &E C 04-17/CN / Études prépar atoires du Projet Agriculture Durable par une Approche P Sélection fondée Component 1: Information a 2017-06-2 2018-02-1 2018-03-3 2017-09-2 2018-04-2 2017-10-3 2018-05-0 2017-11-0 2018-05-2 2018-02-0 2018-06-1 2018-02-2 2018-09-1 aysage (PADAP) Périmètre d IDA / V0430 A posteriori sur la qualité et l Open - National 200,000.00 224,827.15 Signé 2018-01-24 nd planning 8 4 0 8 7 0 7 8 1 2 4 4 2 'Iazafo dans le district de Va e coût vatenina et dans le district d e Soanierana Ivongo, région ANALANJIROFO. C 02-17/CN / Études prépar atoires du Projet Agriculture Sélection fondée Component 1: Information a 2017-06-2 2018-02-1 2018-03-3 2017-09-2 2018-04-2 2017-10-3 2018-05-0 2017-11-0 2018-05-2 2017-12-0 2018-06-1 2018-02-2 2018-09-1 Durable par une Approche P IDA / V0430 A posteriori sur la qualité et l Open - National 150,000.00 156,130.05 Signé 2018-01-24 nd planning 8 4 0 8 7 0 7 8 1 7 4 8 2 aysage (PADAP) dans le dist e coût rict de Marovoay, région BO ENY C 01-17/CN / Études prépar Sélection fondée atoires du Projet Agriculture Component 1: Information a 2017-06-2 2018-02-1 2018-03-3 2017-09-2 2018-04-2 2017-10-3 2018-05-0 2017-11-0 2018-05-2 2018-02-0 2018-06-1 2018-03-1 2018-09-1 IDA / V0430 A posteriori sur la qualité et l Open - National 150,000.00 234,393.50 Signé 2018-01-24 Durable par une Approche P nd planning 8 4 0 8 7 0 7 8 1 6 4 6 2 e coût aysage (PADAP) dans le dist rict d'Andapa, région SAVA C 01-18/CN / Développeme Component 1: Information a Sélection fondée Open - Internation 2018-05-0 2018-05-1 2018-05-1 2018-07-1 2018-08-1 2018-08-2 2018-09-0 2018-09-3 2018-12-2 nt d'un guide pour l'élaborat IDA / 59790 A posteriori 100,000.00 0.00 Annulé 2018-04-30 nd planning sur la qualité al 3 0 5 3 2 2 6 0 9 ion des PAGDP (Firme intern ational) C 18-18/CN / Service de con Component 2: Investments Sélection fondée sultant pour l'encadrement, 2018-09-1 2018-05-3 2018-06-1 2019-12-0 2018-07-1 2020-01-0 2018-07-2 2020-01-2 2018-09-0 2020-02-0 2018-09-2 2020-04-1 2019-04-2 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 50,000.00 22,725.03 Résilié 2018-05-09 formation et suivi des agent 8 0 9 2 9 3 9 0 2 4 6 3 4 selected landscapes e coût s communaux pour l'approc he LIFE C 24-18/CN / Etude de trait ement des points critiques d Component 2: Investments Sélection fondée 2018-11-0 2018-06-0 2018-06-2 2018-12-2 2018-07-2 2019-01-2 2018-08-1 2019-02-1 2018-09-2 2019-02-2 2018-10-2 2019-03-1 2019-08-2 e la RN31 route non revêtue IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 400,000.00 124,815.95 Signé 2018-05-14 6 4 8 7 8 8 7 5 1 5 6 3 2 reliant Bealanana-Ambatorih selected landscapes e coût a d'une longueur de 32 km - Contrôle et surveillance C 12-18/CN / Etude et contr Component 3: Project Mana Sélection fondée ôle-surveillance sur Les trav 2018-09-2 2018-06-0 2018-06-2 2018-10-3 2018-07-2 2018-12-0 2018-08-0 2019-02-1 2018-09-1 2019-02-1 2018-10-1 2019-03-0 2019-02-1 IDA / 59790 gement Coordination and M A posteriori sur la qualité et l Open - National 21,000.00 24,935.50 Signé 2018-05-14 aux d'extension et de Réhab 4 4 8 0 8 3 7 2 1 5 6 7 3 &E e coût ilitation locaux Sofia C 15-18/CN / Etude et contr Component 3: Project Mana Sélection fondée ôle-surveillance sur Les trav 2018-05-1 2018-06-0 2018-06-2 2018-06-1 2018-07-2 2018-07-1 2018-08-0 2018-08-3 2018-09-1 2018-10-0 2018-10-1 2018-11-2 2019-02-1 IDA / 59790 gement Coordination and M A posteriori sur la qualité et l Open - National 10,500.00 3,669.43 Signé 2018-05-14 aux d'extension et de Réhab 4 4 8 5 8 6 7 1 1 4 6 6 3 &E e coût ilitation locaux Sava C 37-18/CN / Inventaire : s urfaces pâturables, espèces fourragères naturelles, point s d'abreuvement, infrastruct Sélection fondée Component 1: Information a En cours d'exécu 2018-09-0 2018-08-0 2018-08-1 2018-11-2 2018-09-1 2018-09-2 2018-10-3 2018-12-0 2019-04-0 ures d'élevage existantes d IDA / 59790 A posteriori sur la qualité et l Open - National 125,000.00 0.00 2018-07-12 nd planning tion 5 2 6 6 5 5 0 4 3 ans la zone. e coût Lot 01 : de Bealanana. Lot 02 : d'Andapa. Lot 03 : de Marovoay Lot 04 : d'Iazafo C 01BIS-18/CN / Développe Sélection fondée Component 1: Information a Open - Internation 2018-05-2 2018-07-0 2018-08-0 2018-08-3 2018-11-2 ment d'un guide pour l'élabo IDA / 59790 A posteriori sur les qualificati 100,000.00 0.00 Annulé 2018-05-03 nd planning al 4 7 6 0 8 ration des PAGDP (Firme int ons des consulta ernational) nts C 41-18/CN / Inventaire des Sélection fondée périmètres hydroagricoles r Component 1: Information a 2018-09-0 2018-10-1 2018-11-1 2018-11-2 2018-12-1 2019-01-0 2018-12-2 2019-02-0 2019-01-2 2019-03-1 2019-02-2 2020-04-1 2019-06-2 2020-10-1 IDA / 59790 A posteriori sur la qualité et l Open - National 230,000.00 155,001.04 Signé 2018-08-30 epartis en quatre (04) lots p nd planning 4 4 7 1 7 4 7 1 0 4 4 9 4 9 e coût our les régions : Sava, Boen y, Sofia et Analanjirofo. C 01-18/BOE / Recrutement d'une ONG chargée du renfo rcement de capacités et de l Component 2: Investments Sélection fondée 2018-11-1 2018-12-1 2019-01-2 2018-12-0 2019-02-2 2019-03-0 2019-04-0 2019-05-1 2019-08-1 'appui des paysans pilotes s IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 23,500.00 0.00 Annulé 2018-11-20 4 1 4 3 3 5 9 4 2 ur les paquets techniques d selected landscapes e coût e la production fourragère, a groécologie, agroforesterie et arboriculture C 02-18/BOE / Recrutement d'une ONG ou Association c Component 2: Investments Sélection fondée 2018-12-0 2018-12-1 2019-01-2 2019-02-0 2019-02-2 2019-03-0 2019-03-0 2019-03-2 2019-04-0 2019-04-1 2019-05-1 2019-05-1 2019-08-1 2019-10-2 hargée du diagnostic et redy IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 5,200.00 5,702.82 Achevé 2018-11-20 5 1 4 6 3 7 5 0 9 2 4 8 2 6 namisation des 03 Coopérati selected landscapes e coût ves de producteurs de seme nces à Tsararano C 05-18/BOE / Etude spécifi Component 2: Investments Sélection fondée que de protection des lavak 2019-07-0 2018-12-0 2018-12-2 2020-01-2 2019-01-2 2020-02-1 2019-02-1 2020-05-0 2019-03-0 2020-05-1 2019-03-2 2020-08-0 2019-04-2 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 47,000.00 77,973.66 Signé 2018-11-20 a au niveau des SBV Ambari 8 5 7 8 6 2 0 4 2 9 6 4 5 selected landscapes e coût ndahy, Androtra, Belafrika C 1-18/SAV / Amélioration d Component 2: Investments Sélection fondée e la disponibilité de semenc 2019-01-0 2018-12-2 2019-02-0 2019-03-2 2019-03-0 2019-04-2 2019-03-1 2019-05-3 2019-04-1 2019-06-1 2019-05-2 2019-07-0 2019-07-0 2019-11-1 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 7,910.00 15,635.97 Achevé 2018-11-30 es améliorées et certifiées d 7 1 3 6 5 5 5 0 9 4 4 4 8 2 selected landscapes e coût ans le paysage d'Andapa Page 7 C 5-18/ANJ / Etude de rehab ilitation des infrasrtuctures hydroagricoles (APS-APD-EIE Component 2: Investments Sélection fondée 2019-01-1 2018-12-1 2019-01-0 2019-01-2 2019-02-0 2019-02-2 2019-02-2 2019-03-0 2019-03-1 2019-03-1 2019-04-0 2019-04-1 2020-08-1 S-PAR-DAO-MGE) et surveilla IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 79,200.00 46,026.84 Signé 2018-11-30 0 5 6 4 5 5 0 1 2 3 5 1 7 nce des travaux des périmèt selected landscapes e coût res Marovinanto et Sahafary dans le paysage Soanierana Ivongo. C 02-18/SAV / Amélioration Component 2: Investments Sélection fondée de la disponibilité de semen 2018-12-1 2019-01-2 2019-02-2 2019-03-1 2019-04-1 2019-05-1 2019-07-0 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 7,910.00 0.00 Annulé 2018-11-20 ces améliorées et certifiées 1 4 3 0 4 9 3 selected landscapes e coût dans le paysage d'Andapa C 01-19/SAV / Études de ré habilitation du barrage soupl e avec avant canal rive droit Component 2: Investments Sélection fondée e et réfection des réseaux h 2018-12-1 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-04-1 2019-05-1 2019-05-2 2020-12-1 2022-12-0 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 45,500.00 67,478.28 Achevé 2019-01-30 ydroagricoles, digue de prot 1 4 2 1 1 4 5 9 7 7 7 6 2 3 selected landscapes e coût ection et pistes (APS-APD-E IES-PAR-DAO-MGE) et contrô le - surveillance du périmètr e Ambalafary sur 203 ha et Analambe Est C 02-19/SAV / Études de ré habilitation du barrage en d ur avec avant canal rive droi Component 2: Investments Sélection fondée te et renovation des réseaux 2019-01-1 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-05-0 2019-05-1 2019-05-2 2020-12-1 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 72,220.00 37,620.86 Achevé 2019-01-30 hydroagricoles et pistes (AP 8 4 2 1 1 4 5 9 7 2 7 1 2 selected landscapes e coût S-APD-EIES-PAR-DAO-MGE) et contrôle - surveillance du périmètre Ambodivitagnona sur 310ha, CR Ambalamana sy II, district d'Andap C 04-19/SAV / Études de ré habilitation d'un barrage av ec avant canal rive gauche et de réfection des réseaux Component 2: Investments Sélection fondée 2019-01-2 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-05-0 2019-05-1 2019-05-2 2020-12-1 hydroagricoles et les ouvrag IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 63,500.00 64,941.59 Achevé 2019-01-30 5 4 2 1 1 4 5 9 7 3 7 1 2 es connexes du grappe (APS selected landscapes e coût -APD-EIES-PAR-DAO-MGE) et contrôle - surveillance du Pé rimètre Antanimbaribe et pé rimètre d'Ambatoharanan C 05-19/SAV / Études de ré habilitation du barrage en d ur avec avant canal rive droi Component 2: Investments Sélection fondée te et réfection des réseaux h 2019-01-2 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-05-0 2019-05-1 2019-05-2 2020-12-1 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 94,470.00 45,623.17 Achevé 2019-01-30 ydroagricoles (APS-APD-EIE 5 4 2 1 1 4 5 9 7 3 7 1 2 selected landscapes e coût S-PAR-DAO-MGE) et contrôle - surveillance du périmètre Tanandava sur 399ha CR Ta nandava, district d'Andapa C 08-19/SAV / Etude techni que et maitrise d'œuvre de t raitements et stabilisation d Component 2: Investments Sélection fondée 2019-11-0 2019-03-1 2019-04-0 2019-12-1 2019-05-0 2020-01-1 2019-05-2 2020-03-0 2019-06-1 2020-05-0 2019-07-0 2020-06-2 2020-02-0 2021-06-2 es « lavaka » dans les ancie IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 16,510.00 23,156.10 Achevé 2019-02-11 4 3 6 2 6 3 6 5 9 7 9 3 4 7 nnes zones d'exploitation mi selected landscapes e coût nières à Ankarierabe, Comm une Rurale Bealampona, Dis trict d'Andapa C 06-19/SAV / Création et m Component 2: Investments Sélection fondée ise en place des huit (08) no 2019-09-1 2019-03-1 2019-04-0 2019-05-2 2019-05-0 2019-06-2 2019-05-2 2019-07-1 2019-06-2 2019-09-1 2019-07-1 2019-10-1 2020-07-0 2021-07-0 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 40,500.00 13,786.27 Achevé 2019-02-12 uveaux AUE sur les périmètr 3 4 7 9 7 8 7 7 0 6 0 1 4 2 selected landscapes e coût es nouvellement à réhabilite r C 03-19/ANJ / Etude de reha bilitation des infrasrtuctures hydroagricoles (APS-APD-EIE Component 2: Investments Sélection fondée 2019-02-0 2019-03-2 2019-04-1 2019-02-1 2019-05-1 2019-03-1 2019-05-2 2019-03-2 2019-06-1 2019-03-2 2019-07-1 2019-05-0 2021-02-2 2022-05-0 S-PAR-DAO-MGE) et Contrôl IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 207,200.00 54,623.16 Signé 2019-02-20 8 2 3 4 3 8 8 2 7 8 1 2 0 1 e-surveillance des travaux d selected landscapes e coût ans les périmètres de Vohiji ny et Ampasimbola-District de Soanierana Ivongo C 04-19/ANJ / Recrutement de firme pour la capitalisatio n des acquis sur les paquets Component 2: Investments Sélection fondée 2019-02-0 2019-03-2 2019-04-1 2019-06-0 2019-05-1 2019-07-0 2019-05-2 2019-08-1 2019-06-1 2019-08-2 2019-07-1 2019-09-3 2022-10-2 techniques agroécologique, IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 55,500.00 65,328.45 Signé 2019-02-20 8 2 3 6 3 8 8 3 7 3 1 0 3 agroforesterie, arbiriculture selected landscapes e coût et culture fourragère dans le s paysages d'Iazafo et Soani erana Ivongo C 01-19/BOE / Recrutement Component 2: Investments Sélection fondée d'une ONG chargée des étu 2019-02-1 2019-03-2 2019-04-1 2019-04-2 2019-05-1 2019-05-2 2019-06-0 2019-06-1 2019-07-0 2019-06-1 2019-07-2 2019-07-1 2019-10-1 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 16,090.00 0.00 Signé 2019-02-24 des de diagnostic des AUE 8 6 9 6 9 8 3 2 2 8 7 2 0 selected landscapes e coût dans les secteurs 04, 05 et 06 C 02-19/BOE / Recrutement d'une ONG chargée de l'étu Component 2: Investments Sélection fondée de de stabilisation des zone 2019-02-1 2019-03-2 2019-04-1 2019-04-1 2019-05-1 2019-05-1 2019-06-0 2019-05-2 2019-06-2 2019-06-0 2019-07-1 2019-06-2 2019-10-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 10,000.00 7,934.21 Signé 2019-02-24 s d'érosion et protection des 8 6 7 5 7 4 1 9 1 6 5 8 3 selected landscapes e coût réseaux hydroagricoles le lo ng du CPRD et CSPC Ambolo moty (ONG) C 03-19/BOE / Etudes, contr Component 2: Investments Sélection fondée ôle et surveillance des trava 2018-12-1 2019-03-2 2019-04-1 2019-02-1 2019-05-1 2019-03-1 2019-06-0 2019-04-1 2019-06-2 2019-04-2 2019-07-1 2019-05-1 2021-01-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 26,000.00 20,616.05 Signé 2019-02-24 ux de curage du drain de cei 8 6 7 9 7 9 1 2 1 4 5 3 5 selected landscapes e coût nture et reprofilage du drain naturel Manompo C 04-19/BOE / Etudes des tr Component 2: Investments Sélection fondée 2019-03-0 2019-03-2 2019-04-1 2019-02-2 2019-05-1 2019-04-0 2019-06-0 2019-04-0 2019-06-2 2019-04-3 2019-07-1 2019-06-1 2021-01-2 avaux de reprofilage des rés COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 52,500.00 69,283.53 Signé 2019-02-24 3 6 7 8 7 1 1 9 1 0 5 3 5 eaux de drainage des secte selected landscapes e coût urs 04, 05 et 06 C 16-18/CN / Analyse des pr Sélection fondée oblématiques d'entretien de Component 1: Information a sur les qualificati 2018-10-0 2018-08-0 2018-09-1 2018-11-3 2018-10-2 2018-11-1 2019-02-2 IDA / 59790 A posteriori Open - National 30,000.00 0.00 Annulé 2018-06-28 s ouvrages hydroagricoles, p nd planning ons des consulta 8 7 0 0 0 3 1 roposition d'instruments et s nts tratégies C 01-19/CN / Élaboration du Plans d'Aménagement et de Gestion Durable des Paysag es (PAGDP) du PADAP pour l Sélection fondée e: Component 1: Information a Open - Internation 2019-05-0 2019-05-1 2019-06-0 2019-05-2 2019-07-1 2019-07-0 2019-08-0 2019-07-1 2019-08-3 2019-08-1 2019-10-0 2019-09-3 2020-02-2 COFN / C1540 A posteriori sur la qualité et l 967,463.00 1,014,833.73 Achevé 2019-03-29 Lot 01 : Paysage d'Andapa nd planning al 1 3 2 5 7 8 1 9 1 6 1 0 8 e coût Lot 02 : Paysage de Bealala na Lot 03 : Paysage de Marovo ay Lot 04 : Paysage d'Iazafo Lot 05 : Paysage de Soanier Ivongo / Développeme C 29-18/CN ana Sélection fondée nt d'une méthodologie d'inv Component 1: Information a 2018-09-2 2018-10-1 2018-11-1 2018-12-1 2018-12-2 2019-01-2 2019-02-2 2019-06-2 IDA / 59790 A posteriori sur la qualité et l Open - National 25,000.00 0.00 Annulé 2018-08-30 entaire des ressources en e nd planning 6 4 7 7 7 0 4 4 e coût au et estimation des besoins C 04 BIS-18/BOE / Etudes et contrôle-surveillance des tra Component 2: Investments Sélection fondée vaux de regabaritage des co 2019-03-0 2018-12-2 2019-02-0 2018-12-0 2019-03-0 2019-01-0 2019-04-0 2019-02-2 2019-05-0 2019-02-2 2019-06-1 2019-04-0 2020-06-1 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 145,000.00 90,071.60 Signé 2018-11-21 urs d'eau exutoire du draina 3 1 3 7 5 7 4 0 9 5 3 6 2 selected landscapes e coût ge de périmètre irrigué des secteurs 4, 5 et 6 de la plain e de Marovoay. C 04-18/BOE / Etudes de Ré Component 2: Investments Sélection fondée habilitation des cours d'eau 2018-11-2 2018-12-1 2019-01-0 2019-02-0 2019-02-1 2019-03-2 2019-04-2 2019-12-1 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 62,500.00 0.00 Annulé 2018-11-20 exutoire du drainage (Rivièr 1 1 4 3 3 0 4 0 selected landscapes e coût e Marovoay Aval, Rivière Kar ambo Aval) MG-UGP PADAP-117841-CS- Component 3: Project Mana Sélection fondée QCBS / Agence de communi 2019-04-1 2019-07-0 2019-08-2 2019-05-2 2019-09-2 2019-10-0 2019-10-1 2019-11-0 2019-11-0 2019-12-0 2019-11-2 2020-01-1 2020-01-2 COFN / C1540 gement Coordination and M A posteriori sur la qualité et l Open - National 28,500.00 20,587.41 Signé 2019-06-17 cation pour la création, anim 0 8 1 3 0 2 0 6 3 3 7 3 6 &E e coût ation et l'hébergement du si te web du PADAP. MG-UGP PADAP-118799-CS- Component 3: Project Mana LCS / Recrutement d'un cabi Sélection au moi 2019-06-2 2019-06-2 2019-06-2 2019-08-2 2019-07-2 2019-09-3 2019-08-0 2019-10-0 2019-08-2 2019-10-2 2019-10-0 2020-01-0 2020-01-0 COFN / C1540 gement Coordination and M A posteriori Open - National 75,000.00 17,544.75 Signé 2019-06-20 net pour l'audit externe des ndre coût 7 0 2 9 2 0 6 4 1 1 4 9 2 &E trois (03) exercices du PADA P : 2019, 2020 et 2021. C 01 BIS-18/BOE / Recrute ment d'une ONG chargée du renforcement de capacités e Component 2: Investments Sélection fondée 2018-10-0 2018-12-0 2019-01-1 2018-12-0 2019-02-1 2019-01-0 2019-03-1 2019-01-2 2019-04-2 2019-01-3 2019-05-2 2019-02-2 2020-05-2 t de l'appui des paysans pilo COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 70,500.00 49,883.77 Signé 2018-11-14 8 5 8 3 5 3 7 4 1 1 6 0 5 tes sur les paquets techniqu selected landscapes e coût es de la production fourragè re, agroécologie, agroforest erie et arboriculture C 03-19/SAV / Etudes APS-A PD-EIES-PAR-MGE-DAO-assis tance passation de marché et contrôle-surveillance des Component 2: Investments Sélection fondée 2019-01-2 2019-02-1 2019-03-0 2019-01-3 2019-04-0 2019-03-0 2019-04-1 2019-03-0 2019-04-2 2019-04-1 2019-05-1 2019-05-3 2020-12-1 travaux reconstruction des d IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 47,000.00 46,114.62 Achevé 2019-01-30 5 4 2 1 1 4 5 9 7 9 7 0 2 eux barrages avec avant-ca selected landscapes e coût naux rive gauche & droite et des réseaux hydroagricoles d'Antsahameloka pour les PI Ambodiala et Andalamena. C 16 BIS-18/CN / Analyse de s problématiques d’entretie Component 2: Investments Sélection fondée 2018-11-0 2018-12-2 2019-01-2 2019-02-1 2019-03-2 2019-04-3 2019-08-0 n des ouvrages hydroagricol COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 30,000.00 0.00 Annulé 2018-10-08 7 1 0 9 6 0 8 es à Madagascar, propositio selected landscapes e coût n d’instrument et stratégies C 07-19/SAV / Mise en place des douze (12) pépinières c Component 2: Investments Sélection fondée 2019-04-1 2019-03-2 2019-04-1 2019-05-1 2019-06-0 2019-06-2 2019-07-1 2020-03-1 ommunautaires au niveau d IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 37,490.00 0.00 Annulé 2019-02-20 2 2 5 5 4 8 8 4 es villages et des COBAS aut selected landscapes e coût our des aires protegées de l a cuvette d'Andapa C 07-20/SOF / Contrôle et S Component 2: Investments Sélection fondée urveillance des Travaux de r 2020-04-0 2020-03-0 2020-04-0 2020-04-3 2020-05-0 2020-06-0 2020-06-0 2020-07-2 2020-06-2 2020-08-0 2020-07-2 2020-09-2 2020-08-0 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 24,000.00 13,580.72 Signé 2020-02-28 éhabilitation du Périmètre d' 2 9 2 0 2 2 1 1 6 1 1 3 5 selected landscapes e coût Anjohibe Ambatosia dans le Paysage de Bealanana C 02-20/SAV / Etude de fais abilité, mise en place et opé Component 2: Investments Sélection fondée 2020-05-2 2020-03-1 2020-04-2 2020-09-1 2020-05-2 2020-10-1 2020-06-1 2020-11-2 2020-07-1 2020-12-1 2020-08-2 2021-01-0 2020-10-2 2021-08-3 rationnalisation des comités COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 10,500.00 10,290.96 Achevé 2020-02-28 9 3 6 5 6 9 5 3 9 1 3 9 2 1 de gestion des matériels agr selected landscapes e coût icoles dans le paysage d'An dapa, Région SAVA. C 04-19/SOF / Études, contr Component 2: Investments Sélection fondée ôle et surveillance de travau 2019-10-0 2020-03-0 2020-04-0 2019-10-0 2020-05-0 2019-11-0 2020-05-2 2020-01-2 2020-06-2 2020-02-2 2020-07-2 2020-03-3 2020-12-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 41,000.00 18,719.00 Achevé 2020-02-20 x d'aménagement du périm 4 1 5 4 5 6 5 3 4 8 4 1 1 selected landscapes e coût ètre de Doany,Paysage de B ealanana T 1-18/SOF / Travaux de sta Sélection fondée bilisation biologique des lav Component 1: Information a 2018-12-1 2019-01-0 2019-02-0 2019-02-2 2019-03-1 2019-04-0 2019-05-0 IDA / 59790 A posteriori sur la qualité et l Open - National 9,800.00 0.00 Annulé 2018-11-30 aka avec mise en place de f nd planning 5 6 5 0 2 5 5 e coût ascines dans le sous paysag e d'Ambatoriha MG-UGP PADAP-118793-CS- QCBS / Inventaire forestier e t écologique : - Lot 01: dans le paysage d' Andapa Sélection fondée Component 1: Information a 2019-07-1 2019-08-1 2019-09-1 2019-09-2 2019-10-1 2019-11-2 2020-03-1 - Lot 02 : dans le paysage d COFN / C1540 A posteriori sur la qualité et l Open - National 365,000.00 0.00 Annulé 2019-06-12 nd planning 2 1 0 5 5 0 9 e Bealalana e coût - Lot 03 : dans le paysage d e Marovoay - Lot 04 : dans le paysage S onierana Ivongo et Iazafo Page 8 MG-UGP PADAP-117852-CS- QCBS / Un cabinet spécialisé Component 3: Project Mana Sélection fondée 2019-06-2 2019-07-1 2019-08-1 2019-09-0 2019-09-3 2019-10-2 2019-12-2 en communication en vue d COFN / C1540 gement Coordination and M A posteriori sur la qualité et l Open - National 22,900.00 0.00 Annulé 2019-06-03 4 8 7 6 0 4 3 e la réalisation du film docu &E e coût mentaire sur le PADAP et le PAGDP. C 09-18/ANJ / Recrutement d'agence d'encadrement po ur la communauté locale fai Component 2: Investments Sélection fondée 2019-11-1 2019-12-0 2020-01-0 2020-01-2 2020-04-0 2020-05-0 2022-05-0 sant la création pépinière et COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 85,000.00 0.00 Annulé 2019-10-16 5 7 6 1 1 8 8 la Plantation d'espèces pére selected landscapes e coût nnes par les agro forêts et le s espèces forestières à Iazaf o et Soanierana Ivongo. C 06-19/ANJ / Mise en place/ Component 2: Investments Sélection fondée Actualisation de base des do 2019-05-3 2019-06-2 2019-07-2 2019-08-0 2019-08-2 2019-09-1 2019-12-2 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 37,500.00 0.00 Annulé 2019-04-30 nnées sur les référentiels te 0 1 1 5 5 8 7 selected landscapes e coût chnico financiers des filières porteuses régionales C 02-19/ANJ / Formation de Component 2: Investments Sélection fondée tous les membres des AUEs 2019-09-0 2019-06-3 2019-07-2 2019-08-2 2019-09-0 2019-10-0 2019-10-3 2020-01-2 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 56,100.00 0.00 Annulé 2019-05-31 sur la gestion des réseaux tr 2 0 4 3 7 6 1 9 selected landscapes e coût ansférables (Entretien/Maint enance) C 03-20/BOE / Diagnostic d es banques de semences co Component 2: Investments Sélection fondée mmunautaires à Madagasca 2020-02-1 2020-06-1 2020-08-0 2020-05-1 2020-08-3 2020-06-1 2020-09-2 2020-06-3 2020-10-2 2020-08-1 2020-11-2 2020-09-2 2021-08-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 20,000.00 11,848.65 Signé 2020-05-26 r et redynamisation de la ba 0 0 1 5 1 5 0 0 0 8 3 3 3 selected landscapes e coût nque de semence communa utaire à Tsararano, district d e Marovoay, Région Boeny C 03-19/SOF / Etudes et con Component 2: Investments Sélection fondée trôle et surveillance de trav 2021-03-2 2021-04-1 2021-05-1 2021-06-0 2021-06-2 2021-07-1 2022-11-1 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 27,810.00 0.00 Annulé 2021-02-25 aux de construction du centr 7 8 8 2 2 6 8 selected landscapes e coût e de multiplication de seme nces à Betainkankana C 08-20/SOF / étude de fais abilité de la réouverture du Component 2: Investments Sélection fondée 2020-03-2 2020-05-0 2020-06-0 2020-06-2 2020-07-1 2020-08-0 2020-11-0 centre de sélection variétale COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 52,000.00 0.00 Annulé 2020-02-28 9 8 7 2 2 6 4 et de multiplication de seme selected landscapes e coût nces Betaikankana dans le P aysage de Bealanana C 30-20/SOF / Recrutement d'un Bureau d'études pour l Component 2: Investments Sélection fondée 2020-11-2 2020-10-2 2020-12-0 2020-11-3 2021-01-0 2021-01-2 2021-01-3 2021-02-2 2021-03-0 2021-03-2 2021-04-1 2021-04-2 2022-04-1 a réalisation d'études, contr COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 66,500.00 121,048.69 Signé 2020-09-30 5 1 4 0 1 0 1 6 7 2 1 6 1 ôle et surveillance des trava selected landscapes e coût ux des travaux d'aménage ment PI Beandrarezona (567 ha) C 05/19/SOF / Etudes et con Component 2: Investments Sélection fondée 2019-07-0 2019-06-2 2019-07-2 2019-10-2 2019-08-2 2020-01-2 2019-09-0 2020-02-2 2019-09-2 2019-10-1 2019-12-1 trôle et surveillance de trav COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 58,590.00 0.00 Annulé 2019-05-30 8 9 1 1 0 2 4 1 4 8 7 aux de stabilisation de lavak selected landscapes e coût a à Bealanana C 01-20/SAV / Elaboration c ontrat plan pluriannuel et Ac Component 2: Investments Sélection fondée 2020-08-3 2020-09-1 2020-10-1 2020-10-2 2020-11-2 2020-12-3 2022-06-2 compagnement (Encadreme COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 29,690.00 0.00 Annulé 2020-08-31 1 0 1 1 5 0 3 nt et Suivi) des AUEs sur la selected landscapes e coût mise en œuvre des Contrat Plan C 02-20/ANJ / Etudes et Con trôle-Surveillance des travau x de réhabilitation des périm Component 2: Investments Sélection fondée ètres dans le district de Soa En cours d'exécu 2020-11-2 2020-10-3 2020-12-0 2020-12-0 2021-01-0 2021-01-1 2021-01-2 2021-02-1 2021-02-2 2021-04-0 2022-04-0 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 91,000.00 0.00 2020-09-30 nierana Ivongo tion 5 0 3 7 2 2 2 5 6 2 2 selected landscapes e coût - Lot 01: PI d'Antanetilava et Vohilava - Lot 02: PI de Diavolamaso, Ambodiboanara et Sahondra na C 06-20/SOF / Etude, Contrô le et surveillance des travau Component 2: Investments Sélection fondée 2020-09-3 2020-11-0 2020-12-0 2020-12-2 2021-01-1 2021-02-2 2021-06-2 x de réhabilitation (APD-EIES COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 187,500.00 0.00 Annulé 2020-08-31 0 4 4 4 8 3 3 -PAR-DAO-MGE) du Périmètr selected landscapes e coût e de Beandrarezona dans le paysage de Bealanana C 04-20/BOE / Recrutement Component 2: Investments Sélection fondée d'une firme pour l'appui, enc 2020-10-0 2020-11-0 2020-12-0 2020-12-2 2021-01-3 2021-02-2 2022-02-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 125,000.00 0.00 Annulé 2020-09-18 adrement et réalisation des 3 8 9 9 1 5 5 selected landscapes e coût actions de reboisement C 04-20/SAV / Etude, contrô le et surveillance des travau x de réhabilitation : Lot 1 : Périmètre irrigué Ank Component 2: Investments Sélection fondée aibe 2020-11-2 2020-12-2 2021-02-0 2020-12-2 2021-03-0 2021-01-2 2021-03-2 2021-02-2 2021-04-2 2021-04-0 2021-06-0 2021-05-1 2022-06-0 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 481,350.00 297,378.67 Signé 2020-11-30 Lot 2 : Périmètre Andasibe 5 1 3 1 5 0 5 6 9 1 3 4 3 selected landscapes e coût Mahaverika , Ambodipont, A ntsahanibalana Lot 3 : Périmètre Ambodirafi a I, Ambodirafia II, Antsahab e, Ambavala, Andasibe koba hina C 1-20/CN / Service de cons Sélection fondée Component 3: Project Mana ultant pour l'évaluation à mi sur les qualificati 2020-10-1 2020-12-1 2021-01-2 2020-10-2 2021-02-2 2020-11-3 2021-04-0 2021-02-0 2021-09-2 COFN / C1540 gement Coordination and M A posteriori Open - National 18,750.00 54,171.09 Signé 2020-11-23 -parcours du Projet Agricultu ons des consulta 6 4 7 6 6 0 2 7 9 &E re Durable par une Approch nts e Paysage C 14-20/SOF / Études, contr ôle et surveillance des trava ux de réhabilitation: Lot 01: Périmètre Irrigué Sa hatsara Ambalamanga Component 2: Investments Sélection fondée 2020-12-1 2021-01-1 2021-02-1 2020-12-2 2021-03-1 2021-01-2 2021-03-1 2021-02-1 2021-04-0 2021-03-2 2021-04-2 2021-04-2 2022-04-2 Lot 02: Périmètre Irrigué Sa COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 375,000.00 54,443.56 Signé 2020-12-28 8 7 3 1 5 0 5 2 1 2 1 3 1 hatsara Ouest selected landscapes e coût Lot 03 : Périmètre Irrigué A mbovonomby Lot 04: Périmètre Irrigué Ma nakana-Antelopolo. C 09-20/SAV / Etudes, contr ôle- surveillance des travaux de réhabilitation des pistes: Lot 1: axe Matsobe Andrano Component 2: Investments Sélection fondée 2020-12-2 2021-01-1 2021-02-0 2020-12-3 2021-03-1 2021-02-0 2021-03-3 2021-02-2 2021-05-0 2021-04-0 2021-06-0 2021-05-1 2021-09-2 2022-05-1 mena Ambalamanasy II de 2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 161,130.00 210,652.81 Signé 2020-12-21 3 1 9 1 1 2 1 6 5 2 9 5 7 0 5 km et réhabilitation de 8 selected landscapes e coût Ponts Lot 2: axe Belaoko, Anjavibe , Ambodirafia, Antanimbarib e Ambalamanasy, Ambavala , Ambodivohitra C 09-20/BOE / ETUDES APS- APD-EIES-PAR- MGE- DAO-A SSISTANCE A LA PASSATION Component 2: Investments Sélection fondée DE MARCHE ET CONTROLE-S 2021-02-0 2020-12-2 2021-02-1 2020-12-2 2021-03-1 2021-01-2 2021-04-1 2021-01-1 2021-05-1 2021-02-2 2021-06-1 2021-04-0 2022-03-0 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 150,000.00 186,693.24 Signé 2020-12-08 URVEILLANCE DES TRAVAUX 4 9 1 3 1 2 0 2 5 4 9 6 1 selected landscapes e coût DE REVETEMENT EN BETON ARME DES CANAUX PRINCIP AUX (CPRD ET CPRG) DES P ERIMETRES IRRIGUES SECTE URS 04, 05 ET 06 C 01-20/CN / Service de con Component 3: Project Mana Sélection fondée sultant pour l'évaluation à m 2020-10-1 2020-03-2 2020-04-2 2020-05-2 2020-06-0 2020-06-2 2020-07-1 2020-10-1 COFN / C1540 gement Coordination and M A posteriori sur la qualité et l Open - National 18,750.00 0.00 Annulé 2020-02-28 i-parcours du Projet Agricult 6 9 0 0 4 4 8 6 &E e coût ure Durable par une Approc he Paysage C 15-20/SOF / Recrutement d'un bureau d'études pour l a réalisation d'études, contr Component 2: Investments Sélection fondée ôle et surveillance des trava 2020-11-2 2021-01-2 2021-02-2 2020-12-2 2021-03-2 2021-01-2 2021-04-2 2021-02-1 2021-05-1 2021-04-1 2021-05-3 2021-05-1 2022-05-3 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 270,000.00 87,027.34 Signé 2021-01-06 ux d’extension du réseau d’i 7 6 2 1 4 0 3 9 0 4 0 7 0 selected landscapes e coût rrigation du périmètre d'Am balavelona Antsamaka Com mune Rurale Antsamaka, du paysage de Belanana C 18-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'études, contr ôle et surveillance des trava Component 2: Investments Sélection fondée 2020-12-1 2021-01-2 2021-02-2 2020-12-2 2021-03-2 2021-01-2 2021-04-2 2021-02-1 2021-05-1 2021-03-2 2021-05-3 2021-04-2 2022-05-3 ux d'aménagement : COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 622,000.00 112,115.98 Signé 2021-01-06 8 6 2 1 4 0 3 2 0 2 0 3 0 LOT 01: Périmètre irrigué A selected landscapes e coût mbararatabe Nord Ambahiv ahy Mahatsinjo - LOT 02 Péri mètre Irrigué Nord Ouest A mbahivahy Ambararatabe N ord C 01-21/CN / Prestation de la communication (relecture Sélection fondée Component 3: Project Mana , de synthèse, de reprograp sur les qualificati 2021-01-2 2021-02-1 2021-03-2 2021-04-0 2021-04-1 2021-05-2 2021-05-1 2021-06-1 2021-07-0 COFN / C1540 gement Coordination and M A posteriori Open - National 90,000.00 115,715.44 Achevé 2021-01-29 hie et de plaidoyer instituion ons des consulta 2 9 5 1 4 1 3 2 2 &E nel) autour des Plans d'Amé nts nagement et de Gestion Dur able des Paysages (PAGDP). C 01-19/SOF / ONG ou Asso Component 2: Investments Sélection fondée 2020-05-3 2020-06-2 2020-07-2 2020-08-1 2020-09-2 2020-10-2 2021-01-2 ciation pour le renouvelleme COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 32,120.00 0.00 Annulé 2020-04-30 0 9 9 8 1 0 8 nt des contrats de transfert selected landscapes e coût gestion. C 11-20/BOE / Recrutement d'une firme pour l'étude de f Component 2: Investments Sélection fondée aisabilité de la mise en plac 2021-01-0 2021-03-1 2021-04-2 2021-02-1 2021-05-2 2021-03-1 2021-06-2 2021-06-0 2021-07-2 2021-07-0 2021-08-2 2021-07-2 2021-12-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 9,400.00 9,165.71 Signé 2021-02-17 e et formalisation de comité 8 0 3 8 1 9 0 8 5 8 9 4 7 selected landscapes e coût de gestion de matériels agri coles dans le paysage de Ma rovoay C 05-19/BOE / Recrutement d'une firme chargée de la re Component 2: Investments Sélection fondée 2021-03-2 2021-03-2 2021-04-2 2020-12-1 2021-05-2 2021-01-1 2021-06-1 2021-04-1 2021-07-1 2021-04-2 2021-08-1 2021-05-1 2022-06-1 dynamisation et à l'élaborati COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 95,000.00 135,810.28 Signé 2021-03-05 6 1 5 1 5 2 4 4 4 8 2 4 1 on des contrats-plans pluri-a selected landscapes e coût nnuels des AUE dans les sec teurs 4-5-6 de Marovoay C 06-20/BOE / Etudes, contr ôle et surveillance des trava ux de réhabilitation des pist es reliant le Chef-lieu de la c Component 2: Investments Sélection fondée ommune Ambolomoty à la R 2021-03-2 2021-03-3 2021-05-1 2020-12-2 2021-06-1 2021-01-2 2021-07-1 2021-03-1 2021-08-1 2021-03-2 2021-09-1 2021-05-0 2022-04-0 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 106,000.00 165,601.53 Signé 2021-03-10 N4 5 1 4 8 1 6 1 2 5 6 9 3 2 selected landscapes e coût Lot 1 Piste Ambolomoty – M arosakoa répartis en 2 lots Lot 2 Piste Ampizaramaso – Maintimaso – Tsiandrarafa – Chantier Sinoa" C 05-20/ANJ / Recrutement d'un Bureau d'Etude pour ét Component 2: Investments Sélection fondée udes, contrôle et surveillanc 2022-07-2 2021-07-1 2021-08-2 2021-09-2 2021-10-1 2021-11-1 2021-12-0 2022-12-0 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 15,200.00 0.00 Annulé 2021-06-25 e des travaux de constructio 8 6 9 8 8 1 6 6 selected landscapes e coût n de bâtiment à usage de ba nque de semence à Iazafo e t Soanierana Ivongo. C 01-21/SAV / Recrutement d'une firme spécialisée pour la création, formalisation, co Sélection fondée Component 2: Investments nduite des formations, suivi sur les qualificati 2021-06-3 2021-05-2 2021-06-2 2021-08-1 2021-07-1 2021-10-2 2021-07-1 2021-11-2 2022-07-1 COFN / C1540 and capacity building in the A posteriori Open - National 55,260.00 98,488.84 Achevé 2021-05-21 et encadrement , accompag ons des consulta 0 1 7 9 1 0 6 8 6 selected landscapes nement à l'élaboration des c nts ontrats plans pluriannuels d es AUEs et le recensement p arcellaire des périmètres irri gués à Andapa. C 02-19/SOF / Élaboration d Component 2: Investments Sélection fondée 2020-10-3 2020-11-2 2020-12-2 2021-01-0 2021-02-0 2021-03-0 2021-06-1 'un cadre incitatif (Contrat Pl COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 56,250.00 0.00 Annulé 2020-09-30 0 3 3 7 5 2 0 an Pluriannuel) par AUE selected landscapes e coût Page 9 C 17-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'études, contr Component 2: Investments Sélection fondée ôle et surveillance de la mis 2021-01-2 2021-02-2 2021-03-2 2021-04-2 2021-05-1 2021-06-0 2022-06-0 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 195,000.00 0.00 Annulé 2021-01-06 e en œuvre : LOT 01: Travau 6 2 2 1 6 5 5 selected landscapes e coût x Piste Ambatosia-Anjohibe LOT 02: travaux de réhabilit ation d'un ouvrage de franc hissement "pont Andranotak atra" C 03-20/SOF / Recrutement d'une ONG ou association e n vue de l’Élaboration des sc hémas d'aménagement com Component 2: Investments Sélection fondée 2021-03-2 2021-05-0 2021-06-0 2021-07-0 2021-08-0 2021-09-1 2022-05-1 munaux (SAC) dans la distri COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 252,000.00 0.00 Annulé 2021-03-01 2 5 2 2 6 0 8 ct de Bealalana repartis en selected landscapes e coût 03 lots: Lot 01: 06 communes Lot 02 : 05 communes Lot 03: 03 communes C 19-20/SOF / Recrutement ONG en vue de l'élaboration des contrats plans pluriannu els des AUE pour les périmèt Component 2: Investments Sélection fondée 2021-06-1 2021-08-1 2021-09-1 2021-06-1 2021-10-1 2021-07-1 2021-11-0 2021-10-0 2021-12-0 2021-10-1 2022-01-0 2021-11-0 2022-11-0 res de : Mangindrano, Beala COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 240,000.00 41,315.90 Signé 2021-07-30 7 5 9 9 9 9 8 6 8 1 6 3 2 nana I, Beandrarezona, Anjo selected landscapes e coût hibe, Ambalavelona, Anjana borona, Sahatsara Anjanabo rona, Ambahivahy, Nord-Ou est Ambahivahy, Ambovono mby C 21-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'études, contr Component 2: Investments Sélection fondée 2020-12-1 2021-01-1 2021-02-1 2021-03-1 2021-04-1 2021-05-0 2021-05-2 2022-05-2 ôle et surveillance de la mis IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 220,000.00 0.00 Annulé 2021-01-06 8 6 2 2 1 8 5 5 e en œuvre des travaux pou selected landscapes e coût r amélioration de la voie d'a ccès ralliant Ambatoriha Est- Ambararatabe Nord C 05-20/SAV / Recrutement d'une firme pour la diffusion Component 2: Investments Sélection fondée d'itinéraire technique agricol 2021-05-1 2021-06-2 2021-07-2 2021-08-1 2021-08-2 2021-09-1 2022-07-3 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 542,000.00 0.00 Annulé 2021-04-30 e et la promotion de l'éleva 8 2 2 1 8 7 0 selected landscapes e coût ge intensif du paysage d'An dapa, district d'Andapa, Rég ion SAVA C 07-20/ANJ / Etudes et Con trôle-Surveillance des travau x de réhabilitation des périm Component 2: Investments Sélection fondée En cours d'exécu 2020-12-1 2021-09-1 2021-10-2 2020-12-3 2021-11-2 2021-02-0 2021-12-1 2021-03-2 2022-01-1 2021-04-1 2022-02-2 2023-02-2 ètres dans le District de Soa COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 153,000.00 0.00 2021-08-20 tion 0 0 4 1 3 3 3 2 7 2 1 1 nierana Ivongo:Lot 01:PI Tsa selected landscapes e coût ratanàna,Namantoana et Sa hasoa;Lot 02:PI Ambatonand roka,Vaniaraka et Antanetila va C 19-20/ANJ / Etudes,Contrô le et surveillance des travau x de réhabilitation des piste Component 2: Investments Sélection fondée s à Iazafo et Soanierana Ivo 2021-05-1 2021-09-2 2021-10-1 2021-01-1 2021-11-1 2021-02-1 2021-11-2 2021-03-2 2021-12-1 2021-04-0 2022-01-1 2021-05-1 2023-01-1 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 283,500.00 126,545.83 Signé 2021-08-25 ngo:Lot 01:Antanifotsy à Ma 2 4 9 9 8 8 8 2 8 6 2 8 2 selected landscapes e coût rovinanto;Lot 02:Maromitety à Mahanoro,Maromitety à V avazahana,Marofototra à Ma hanoro et Ambodinonoka à Mahatera. C 04-20/ANJ / Recrutement de firme pour l'instauration Component 2: Investments Sélection fondée et la formalisation de neuf ( 2020-11-0 2021-09-2 2021-11-0 2020-12-0 2021-12-0 2021-01-1 2021-12-2 2021-02-2 2022-01-2 2021-03-1 2022-03-0 2021-04-0 2022-05-3 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 12,000.00 10,179.28 Signé 2021-08-30 09) comités de gestion des 4 9 2 4 2 4 2 4 6 8 2 8 1 selected landscapes e coût matériels agricole dans le p aysage d'Iazafo et Soaniera na Ivongo C 16-20/ANJ / Etudes et Con trôle-Surveillance des travau x de réhabilitation des barra Component 2: Investments Sélection fondée 2020-12-1 2021-09-2 2021-11-0 2020-12-2 2021-12-0 2021-01-2 2021-12-3 2021-02-2 2022-02-0 2021-03-2 2022-03-1 2021-04-2 2023-03-1 ges et des ouvrages connex COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 64,000.00 64,322.18 Signé 2021-08-30 0 0 3 8 1 7 1 4 4 4 1 7 1 es dans la zone Ambatohar selected landscapes e coût anana du paysage d'Iazafo; CR Ambatoharanana-District de Fénérive Est C 03-20/ANJ / Etudes et Con trôle-Surveillance des travau x de réhabilitation des résea Component 2: Investments Sélection fondée ux d'irrigation et de drainag 2021-05-1 2021-09-0 2021-10-2 2020-12-3 2021-11-1 2021-02-0 2021-12-1 2021-03-0 2022-01-2 2021-04-1 2022-02-2 2021-05-0 2023-02-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 94,000.00 111,294.13 Signé 2021-08-17 e des périmètres Ampoezan 9 7 1 1 8 3 8 2 2 2 6 1 6 selected landscapes e coût a, Anamborano, Fandrianom by et Antsirabeniseva; CR S oanierana Ivongo et Fotsiala nana-District de Soanierana Ivongo C 18-20/ANJ / Etudes (APS, APD, DAO, EIE), Contrôle et surveillance des travaux de protection des berges des ri Component 2: Investments Sélection fondée 2021-06-0 2021-07-2 2021-08-1 2021-09-1 2021-10-2 2021-11-2 2022-11-2 vières dans le paysage de S COFN / C1540 and capacity building in the A posteriori sur la qualité et l 65,040.00 0.00 Annulé 2021-05-17 7 1 8 7 2 6 6 oanierana Ivongo : selected landscapes e coût - Sahave dans la Commune Soanierana Ivongo - Sahafotra dans la Commu ne Antanifotsy C 06-19/BOE / Recrutement d'une ONG ou Association p Component 2: Investments Sélection fondée our l'opérationnalisation du En cours d'exécu 2021-08-0 2020-06-0 2020-07-0 2022-04-2 2020-08-0 2022-05-2 2020-08-2 2020-09-2 2020-10-1 2021-05-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 55,000.00 0.00 2020-05-12 DINA Régionale et la mise e tion 2 1 6 2 5 4 5 4 9 7 selected landscapes e coût n œuvre des plans d'action contre les feux de brousses, dans le paysage de Marovoa y C 018-20/ANJ / Etudes (APS, APD, DAO, EIE), Contrôle et surveillance des travaux de Component 2: Investments Sélection fondée protection des berges des ri 2021-05-3 2021-09-0 2021-10-1 2020-12-2 2021-11-1 2021-01-2 2021-12-0 2021-03-1 2021-12-1 2021-04-1 2022-01-2 2021-05-1 2022-07-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 66,000.00 33,945.00 Signé 2021-08-24 vières dans le paysage de S 1 8 2 9 1 8 1 9 6 2 0 1 9 selected landscapes e coût oanierana Ivongo : - Sahave dans la Commune Soanieran a Ivongo - Sahafotra dans la Commune Antanifotsy C 05-21/CN / Étude Genre d Sélection fondée ans le développement de la Component 1: Information a sur les qualificati 2021-07-2 2021-08-2 2021-10-1 2021-10-0 2022-02-1 2021-11-0 2022-06-1 2021-12-0 2022-07-2 2021-12-1 filière rizicole à Madagascar COFN / C1540 A posteriori Open - National 50,000.00 47,143.38 Signé 2021-07-30 nd planning ons des consulta 6 0 5 3 8 2 0 7 6 6 (Régions : Melaky, Sofia, Ala nts otra Mangoro, Analamanga, Atsinanana). C 01-20/BOE / Recrutement Component 2: Investments Sélection fondée d'ONG/Association pour l'ins 2021-04-0 2021-05-0 2021-06-0 2021-06-2 2021-07-2 2021-08-3 2021-11-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 2,000.00 0.00 Annulé 2021-03-12 tauration et la formalisation 1 8 7 7 9 0 9 selected landscapes e coût de comités de gestion de m atériels agricoles C 16-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'études, contr ôle et surveillance des trava Component 2: Investments Sélection fondée 2020-12-1 2021-01-2 2021-02-2 2021-03-2 2021-04-2 2021-05-1 2021-06-0 2022-06-0 ux: IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 234,000.00 0.00 Annulé 2021-01-06 8 6 2 2 1 8 7 7 LOT 1: piste depuis croisem selected landscapes e coût ent de la route "Bealanana-a ntsamaka"-Beandrarezona ; LOT2: piste "Bealanana-ant samaka"de 15 km de longue ur C 20-20/SOF / Recrutement d'un Bureau d'études pour l a réalisation d'étude, contrôl Component 2: Investments Sélection fondée 2021-03-0 2021-04-0 2021-05-0 2021-06-0 2021-06-1 2021-07-0 2022-07-0 e et surveillance de la mise COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 27,000.00 0.00 Annulé 2021-02-15 7 3 3 2 9 9 9 en œuvre des travaux pour l selected landscapes e coût e regabaritage des drains de la plaine d'Ankitrobaka, Ant animanga et Antsirakasada. C 09-20/SOF / Recrutement d'une ONG ou Association p our l'Instauration et Formalis ation des Comités de Gestio Component 2: Investments Sélection fondée 2021-03-3 2021-05-1 2021-06-0 2021-06-2 2021-07-1 2021-08-1 2021-12-1 n des matériels agricoles : COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 9,500.00 0.00 Annulé 2021-03-01 1 0 9 4 9 3 1 Lot 01 : dans le périmètre d selected landscapes e coût e Mangindrano Lot 02 : dans le périmètre d e Bealanana C 07-21/SAV / Recrutement d'un Bureau d'études pour l' Sélection fondée Component 2: Investments EIES, contrôle et surveillanc sur les qualificati 2021-09-0 2021-10-0 2021-10-1 2021-10-3 2022-04-2 COFN / C1540 and capacity building in the A posteriori Open - National 32,000.00 0.00 Annulé 2021-08-05 e des travaux de constructio ons des consulta 4 4 9 1 9 selected landscapes n de tueries dans les Comm nts unes Rurales d'Ambalamana sy II et d'Ambodiangezoka C 01-20/ANJ / Elaboration ( Component 2: Investments Sélection fondée PCD/SAC) au niveau des co 2021-07-1 2021-08-1 2021-09-1 2021-10-0 2021-11-0 2021-12-0 2022-03-0 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 33,140.00 0.00 Annulé 2021-06-10 mmunes dans les paysages 0 9 8 8 7 6 6 selected landscapes e coût d'intervention du PADAP CE R Analanjirofo C 01-19/ANJ / Élaboration d' Component 2: Investments Sélection fondée un cadre incitatif (contrat pl 2020-09-0 2020-09-1 2020-10-1 2020-11-1 2020-11-2 2020-12-2 2021-01-1 2021-04-1 IDA / 59790 and capacity building in the A posteriori sur la qualité et l Open - National 82,820.00 0.00 Annulé 2020-08-19 an pluriannuel) par AUE Iaza 2 8 2 1 6 5 9 9 selected landscapes e coût fo et Soanierana Ivongo. C 05-20/SOF / Etudes, mise en place et accompagneme Component 2: Investments Sélection fondée nt d’une Structure de gestio 2021-02-1 2021-03-1 2021-04-3 2021-05-3 2021-06-2 2021-07-1 2021-08-1 2021-12-1 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 245,000.00 0.00 Annulé 2021-03-01 n adaptée pour l’axe routier 1 6 0 0 9 9 3 1 selected landscapes e coût Bealanana – Ambatoriha (RI P 117) dans le district de Be alanana, région Sofia C 04-20/CN / Service de Co nsultant pour la caractérisati Component 2: Investments Sélection fondée En attente d'exé 2022-03-2 2022-04-2 2022-05-2 2022-06-1 2022-07-2 2022-08-2 2022-11-2 on des ressources en eau et COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 351,300.00 0.00 2022-02-22 cution 4 7 7 6 1 5 3 estimation des besoins dans selected landscapes e coût les 5 paysages d'interventio n du PADAP (5 lots) C 24-20/CN / Recrutement Sélection fondée Component 2: Investments d'un Bureau d'étude pour la sur les qualificati 2021-11-0 2021-12-1 2021-12-2 2022-01-1 2022-04-1 COFN / C1540 and capacity building in the A posteriori Open - National 32,000.00 0.00 Annulé 2021-10-15 réalisation de la Mémoire te ons des consulta 5 5 5 4 4 selected landscapes chnique de construction de t nts uerie. C 17-20/ANJ / Etudes , Contr ôle et surveillance des trava ux de protection des berges Component 2: Investments Sélection fondée par méthode biologique et 2021-07-0 2021-08-1 2021-09-1 2021-10-1 2021-11-1 2021-12-2 2022-12-2 COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 38,500.00 0.00 Annulé 2021-06-10 mécanique des rivières dans 1 4 1 1 5 0 0 selected landscapes e coût le paysage d'Iazafo : - Sahavaviana dans la Co mmune Maromitety - Iazafo C 07-22/CN / Recrutement Component 3: Project Mana d'un cabinet pour l'audit ext Sélection au moi En cours d'exécu 2022-12-0 2022-10-1 2022-11-1 2023-01-0 2022-12-1 2023-02-0 2023-01-0 2023-03-2 2023-02-0 2023-03-0 2023-08-0 COFN / C1540 gement Coordination and M A posteriori Open - National 70,000.00 0.00 2022-10-18 erne des deux (02) dernière ndre coût tion 1 9 2 9 0 9 9 1 9 1 8 &E exercices du PADAP : 2022, 2023 et clôture du Projet. C 02-20/CN / Service de con sultant pour le développeme Component 3: Project Mana Sélection fondée 2020-08-2 2020-08-2 2020-10-0 2020-11-0 2020-11-2 2020-12-1 2021-01-0 2022-01-0 nt d'un logiciel pour le suivi- COFN / C1540 gement Coordination and M A posteriori sur la qualité et l Open - National 25,000.00 0.00 Annulé 2020-07-30 8 0 3 2 2 6 9 4 évaluation du Projet Agricult &E e coût ure Durable par une Approc he Paysage C 08-22/CN / Élaboration et Sélection fondée mise en œuvre du Fond Régi Component 1: Information a sur les qualificati En cours d'exécu 2023-03-2 2023-01-1 2023-02-2 2023-06-0 2023-03-2 2023-04-2 2023-07-2 onal d'entretien du réseaux COFN / C1540 A posteriori Open - National 101,000.00 0.00 2022-12-29 nd planning ons des consulta tion 4 9 2 9 4 8 7 hydoagricole (FRERHA) dans nts les zones d'intervention du P ADAP. Page 10 C 24-20/SOF / Recrutement ONG pour la Mise en place, Formation, Encadrement, et Mise en place d'une cadre in citative pour l'Association de Component 2: Investments Sélection fondée 2021-02-2 2021-03-1 2021-04-2 2021-06-1 2021-05-2 2021-06-1 2021-07-1 2021-08-0 2022-06-0 s usagers des pistes: COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 76,000.00 0.00 Annulé 2021-03-01 6 7 1 9 1 0 0 8 4 Lot 1: Bealanana-Antsamaka selected landscapes e coût Lot 2: croisement Antsamak a-Beandrarezona Lot 3: RIP 117m Bealanana - Ambatoriha C 04-21/SOF / Recrutement d’un bureau d’études pour l’ établissement d’un mémoire Sélection fondée Component 2: Investments technique, contrôle et survei sur les qualificati 2021-08-0 2021-08-1 2021-09-2 2021-10-2 2021-11-2 2022-05-2 COFN / C1540 and capacity building in the A posteriori Open - National 30,000.00 0.00 Annulé 2021-07-29 llance des travaux d’extensi ons des consulta 4 9 2 2 6 5 selected landscapes on du réseau d’irrigation du nts périmètre irrigue Bealanana I pour desservir le secteur A naborano du paysage de Be alanana C 21-20/BOE / Firme pour le s études, contrôle et surveill Component 2: Investments Sélection fondée 2022-02-1 2022-03-3 2022-04-2 2022-05-2 2022-07-0 2022-08-0 2023-08-0 ance des travaux de stabilis COFN / C1540 and capacity building in the A posteriori sur la qualité et l Open - National 100,000.00 0.00 Annulé 2022-01-25 5 1 8 8 2 6 6 ation des bassins versants d selected landscapes e coût es canneaux de périmètre d e Marovoay secteur 4, 5 et 6 . C 03-23/CN / Une firme en c harge de l’audit de mise en Sélection fondée œuvre des plans de gestion Component 3: Project Mana sur les qualificati En cours d'exécu 2023-08-1 2023-07-2 2023-11-0 2023-09-0 2023-10-0 2023-11-1 2024-04-2 environnementale et sociale COFN / C1540 gement Coordination and M A posteriori Open - National 68,000.00 0.00 2023-06-30 ons des consulta tion 7 1 6 9 9 3 1 (PGES), et des mesures envi &E nts ronnementales et sociales ( E&S) au niveau des sous pro jets financés par PADAP. C 09-23/CN / Recrutement Component 3: Project Mana Sélection au moi En cours d'exécu 2023-11-2 2023-10-0 2023-11-0 2023-11-2 2023-12-0 2023-12-2 2024-01-1 2024-02-0 2024-04-0 d'un cabinet d'audit externe COFN / C1540 gement Coordination and M A posteriori Open - National 80,000.00 0.00 2023-09-28 ndre coût tion 2 8 7 4 7 2 3 4 4 pour l'exercice 2023 et clôtu &E res du PADAP. C 12-23/CN / Recrutement d'une Firme pour la formatio Sélection fondée Component 2: Investments n, encadrement et à l’accom sur les qualificati En attente d'exé 2023-11-2 2023-12-2 2024-01-2 2024-02-0 2024-04-0 COFN / C1540 and capacity building in the A posteriori Open - National 206,000.00 0.00 2023-11-23 pagnement des CMS, des B ons des consulta cution 8 3 2 6 6 selected landscapes anque Semences Communa nts utaire, des GPS et des CGMA dans les paysages du Projet. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-UGP PADAP-38775-CS-I Component 3: Project Mana NDV / Responsable de Passa 2017-08-1 2017-12-3 2018-02-0 2018-01-0 2018-03-0 2018-02-0 2018-04-0 2019-02-0 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 11,178.36 Signé 2017-11-30 tion des marchés pour l'unit 7 0 6 9 8 2 4 2 &E é de Coordination Régionale d'Andapa. MG-UGP PADAP-38776-CS-I Component 3: Project Mana NDV / Responsable de Passa 2017-08-1 2018-01-1 2018-01-2 2018-01-2 2018-02-2 2018-02-1 2019-02-2 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 13,209.42 Signé 2017-11-30 tion des Marchés (RPM) pour 7 9 9 3 2 2 2 &E l'Unité de Coordination Régi onale de Sofia. C 61-17/CN / Responsable A Component 3: Project Mana dministratif et Finacier (RAF) 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-0 2018-02-0 2018-03-1 2019-02-0 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 14,267.74 Signé 2017-11-30 pour l'Unité de Coordination 5 0 2 9 9 2 1 2 &E Régionale d'Analanjirofo. C 62-17/CN / Responsable d Component 3: Project Mana e Passation des Marchés (RP 2017-08-1 2018-01-1 2018-04-2 2018-01-2 2018-04-2 2018-02-1 2018-05-1 2019-02-1 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 12,272.69 Signé 2017-11-27 M) pour l'Unité de Coordinati 7 6 4 6 7 9 1 9 &E on Régionale d'Analanjirofo. MG-UGP PADAP-38779-CS-I Component 3: Project Mana NDV / Responsable Administ 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-1 2018-02-0 2018-03-1 2019-02-0 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 14,308.06 Signé 2017-11-30 ratif et Finacier (RAF) pour l' 5 0 2 9 6 2 1 2 &E Unité de Coordination Régio nale de Sava. MG-UGP PADAP-38780-CS-I Component 3: Project Mana NDV / Responsable Administ 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-0 2018-02-0 2018-03-1 2019-02-0 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 11,889.78 Signé 2017-11-30 ratif et Finacier (RAF) pour l' 5 0 2 9 9 2 1 2 &E Unité de Coordination Régio nale de Sofia. C 63-14/CN / Comptable po Component 3: Project Mana 2017-09-0 2017-12-3 2018-02-0 2018-01-0 2018-02-0 2018-02-0 2018-03-1 2019-02-0 ur l'Unité de Coordination R IDA / 59790 gement Coordination and M A posteriori Individuel Open 12,000.00 8,181.79 Signé 2017-11-30 5 0 8 9 9 2 1 2 égionale d'Analanjirofo. &E C 57-17/CN / Responsable e Component 3: Project Mana 2017-12-2 2017-12-3 2018-01-1 2018-01-0 2018-02-0 2018-01-3 2019-02-0 IDA / 59790 A posteriori Individuel Open 48,000.00 12,980.94 Achevé 2017-12-01 au/irrigation national du Proj gement Coordination and M 2 1 0 3 3 0 3 et. &E C 49-17/CN / Comptable nat Component 3: Project Mana 2017-09-1 2017-12-3 2017-11-0 2018-01-0 2018-02-0 2018-02-0 2018-03-1 2019-02-0 IDA / 59790 A posteriori Individuel Open 24,000.00 11,923.38 Achevé 2017-11-30 ional du PADAP. gement Coordination and M 4 0 2 9 1 2 0 2 &E MG-UGP PADAP-38784-CS-I Component 3: Project Mana 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-2 2018-02-0 2018-03-1 2019-02-0 NDV / Comptable pour l'Unit IDA / 59790 gement Coordination and M A posteriori Individuel Open 12,000.00 8,176.03 Signé 2017-11-30 5 0 2 9 8 2 2 2 é de Coordination Régionale &E de Sofia. MG-UGP PADAP-38778-CS-I Component 3: Project Mana NDV / Responsable Administ 2017-09-0 2017-12-3 2017-11-0 2018-01-0 2018-02-0 2018-02-0 2018-03-1 2019-02-0 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 13,588.32 Signé 2017-11-30 ratif et Finacier (RAF) pour l' 5 0 2 9 9 2 1 2 &E Unité de Coordination Régio nale de Boeny. MG-UGP PADAP-38781-CS-I Component 3: Project Mana 2017-09-0 2017-12-3 2018-02-0 2018-01-0 2018-02-0 2018-02-0 2018-03-1 2019-02-0 NDV / Comptable pour l'Unit IDA / 59790 gement Coordination and M A posteriori Individuel Open 12,000.00 8,181.79 Signé 2017-11-30 5 0 8 9 9 2 1 2 é de Coordination Régionale &E de Boeny. MG-UGP PADAP-38783-CS-I Component 3: Project Mana 2017-09-0 2017-12-3 2018-03-0 2018-01-0 2018-03-0 2018-02-0 2018-03-1 2019-02-0 NDV / Comptable pour l'Unit IDA / 59790 gement Coordination and M A posteriori Individuel Open 12,000.00 8,176.03 Signé 2017-11-30 5 0 1 9 5 2 7 2 é de Coordination Régionale &E de Sava. MG-UGP PADAP-38445-CS-I Component 3: Project Mana NDV / Responsable de Passa 2017-08-1 2017-12-2 2018-01-0 2018-01-2 2018-01-3 2018-02-2 2019-01-3 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 13,166.16 Signé 2017-11-27 tion des Marchés (RPM) pour 7 7 6 3 0 7 0 &E l'Unité de Coordination Régi onale de Boeny. C 65-17/CN / 04 Responsabl es en Agriculture pour les 0 4 Unités de Gestion régional Component 3: Project Mana 2018-01-2 2018-02-1 2018-04-1 2018-03-1 2018-04-2 2018-04-1 2018-05-1 2019-04-1 2018-05-1 e du PADAP : Iazafo-Soanier IDA / 59790 gement Coordination and M A posteriori Individuel Open 192,000.00 23,032.99 Signé 2018-01-08 5 7 7 0 4 4 1 4 1 ana Ivongo (Région Analanji &E rofo), Marovoay (Région Boe ny), Bealalana (Région SOFI A) et Andapa (Région SAVA) C 69-17/CN / 04 Responsabl es Socio-orga et développe ment local pour les 04 Unité Component 3: Project Mana s de Gestion régionale du PA 2017-12-2 2018-02-1 2018-04-1 2018-03-0 2018-04-2 2018-04-1 2018-05-0 2019-04-1 IDA / 59790 gement Coordination and M A posteriori Individuel Open 192,000.00 40,130.70 Signé 2018-01-08 DAP : Iazafo-Soanierana Ivo 8 6 7 9 5 3 5 3 &E ngo (Région Analanjirofo), M arovoay (Région Boeny), Be alalana (Région SOFIA) et An dapa (Région SAVA). C 67-17/CN / 04 Responsabl es en environnement et For esterie pour les 04 Unités de Component 3: Project Mana Gestion régionale du PADAP 2018-02-0 2018-02-1 2018-04-1 2018-03-1 2018-05-0 2018-04-1 2018-05-2 2019-04-1 IDA / 59790 gement Coordination and M A posteriori Individuel Open 192,000.00 43,958.48 Signé 2018-01-08 : Iazafo-Soanierana Ivongo ( 7 7 9 0 2 4 3 4 &E Région Analanjirofo), Marov oay (Région Boeny), Bealala na (Région SOFIA) et Andap a (Région SAVA). C 55-17/CN / Responsable S Component 3: Project Mana 2018-02-2 2018-02-1 2018-03-3 2018-03-1 2018-04-2 2018-04-1 2018-05-1 2019-04-1 2020-05-0 auvegarde Environnemental IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 15,286.86 Achevé 2018-01-08 3 7 0 0 7 4 1 4 1 e et Sociale au niveau natio &E nal (UGP) MG-UGP PADAP-44922-CS-I NDV / 04 Responsables Eau et Irrigation pour les 04 Unit Component 3: Project Mana és de Gestion régionale du P 2018-02-0 2018-03-1 2018-04-1 2018-04-0 2018-04-2 2018-05-0 2018-05-1 2019-05-0 IDA / 59790 gement Coordination and M A posteriori Individuel Open 192,000.00 43,958.48 Signé 2018-01-22 ADAP : Iazafo-Soanierana Iv 8 2 7 2 7 7 1 7 &E ongo (Région Analanjirofo), Marovoay (Région Boeny), B ealalana (Région SOFIA) et A ndapa (Région SAVA). C 60-17/CN / 04 Assistants t echniques des Opérations p our chaque Unité de Gestion Component 3: Project Mana 2017-10-2 2017-12-3 2018-01-2 2018-01-1 2018-02-2 2018-02-0 2018-05-1 2019-02-0 Régionale du PADAP : Iazafo IDA / 59790 gement Coordination and M A posteriori Individuel Open 384,000.00 58,083.89 Signé 2017-12-01 3 1 2 0 3 3 7 3 -Soanierana Ivongo (Région &E Analanjirofo), Marovoay (Ré gion Boeny), Bealalana (Rég ion SOFIA) et Andapa (Régio n SAVA). MG-UGP PADAP-44950-CS-I Component 3: Project Mana 2018-03-2 2018-02-2 2018-05-1 2018-03-1 2018-06-2 2018-03-2 2018-07-1 2019-03-2 IDA / 59790 A posteriori Individuel Open 48,000.00 17,197.72 Achevé 2018-01-22 NDV / Auditeur interne gement Coordination and M 1 6 8 3 7 8 4 8 &E MG-UGP PADAP-59456-CS-C DS / Recrutement d'un cons Component 2: Investments Sélection de cons ultant international en vue d 2018-04-3 2018-05-0 2018-04-3 2018-06-2 2018-05-2 2018-07-2 2018-08-2 IDA / V0430 and capacity building in the A posteriori ultants par enten Direct 30,250.00 40,425.00 Achevé 2018-04-16 e la finalisation du plan d'act 0 6 0 9 2 9 4 selected landscapes te directe ions sur la gestion des bois précieux (Diospyros spp, Dal bergia spp) MG-UGP PADAP-59459-CS-I NDV / Recrutement d'un con Component 2: Investments sultant national francophone 2018-05-1 2018-05-1 2018-04-1 2018-05-2 2018-05-2 2018-06-1 2018-05-2 2018-07-1 2018-08-2 IDA / V0430 and capacity building in the A posteriori Individuel Limited 10,000.00 2,437.96 Achevé 2018-04-16 pour l'assistance au consult 4 6 9 6 1 5 8 5 4 selected landscapes ant international en vue de l a finalisation du plan d'actio ns sur la gestion des bois pr écieux. C 11-18/CN / Etude sur la R Component 3: Project Mana 2018-06-0 2018-06-0 2018-06-2 2018-06-1 2018-08-0 2018-07-0 2018-09-0 IDA / 59790 A posteriori Individuel Open 2,500.00 2,172.74 Signé 2018-05-09 énovation locaux de l'UGP à gement Coordination and M 6 7 8 4 2 9 1 Nanisana. &E MG-UGP PADAP-64943-CS-I NDV / Prestations d'un cons ultant individuel pour le post Component 3: Project Mana 2018-07-0 2018-07-1 2018-10-0 2018-07-2 2018-10-1 2018-08-1 2018-10-1 2019-08-1 e de IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 12,229.49 Signé 2018-06-01 9 6 8 3 1 2 7 2 Responsable en Suivi-évalua &E tion pour l'Unité de Coordina tion Régionale de PADAP-Ré gion ANALANJIROFO MG-UGP PADAP-65206-CS-C DS / Prestations pour 03 ans Component 3: Project Mana Sélection de cons 2018-04-1 2018-06-1 2018-07-1 2018-05-0 2021-07-1 d'un consultant individuel p IDA / 59790 gement Coordination and M A posteriori ultants par enten Direct 65,000.00 76,705.15 Signé 2018-06-04 9 4 8 8 7 our le poste de RESPONSAB &E te directe LE ADMINISTRATIF ET FINAN CIER du projet PADAP. MG-UGP PADAP-66144-CS-I NDV / Prestations d'un cons Component 3: Project Mana 2018-02-2 2018-07-2 2018-03-2 2018-08-1 2018-03-2 2018-09-0 2018-03-3 2019-09-0 2020-03-2 ultant individuel pour le post IDA / 59790 gement Coordination and M A posteriori Individuel Open 10,000.00 7,459.85 Achevé 2018-06-11 0 0 1 0 2 3 1 3 4 e d'Assistant Informatique p &E our l'Unité de Gestion du PA DAP Page 11 MG-UGP PADAP-75687-CS-C DS / Prestations pour 03 ans Component 3: Project Mana Sélection de cons 2017-01-1 2018-09-0 2018-10-1 2018-08-0 2021-10-0 d'un consultant individuel p IDA / 59790 gement Coordination and M A posteriori ultants par enten Direct 65,000.00 50,287.43 Signé 2018-08-27 6 6 0 7 9 our le poste de RESPONSAB &E te directe LE PASSATION DES MARCHE S du projet PADAP C 42-18/CN / La mise en pla ce d'un système d'informati Component 1: Information a 2018-08-3 2018-11-0 2019-01-1 2018-11-1 2019-02-0 2018-12-2 2019-02-2 2019-04-2 IDA / 59790 A posteriori Individuel Open 10,000.00 7,436.62 Achevé 2018-08-30 on géographique des périmè nd planning 0 8 5 8 5 3 0 2 tres hydroagricoles (SIGPHY) C 17-18/CN / Adaptation de la méthodologie et le protoc Component 1: Information a 2018-09-2 2018-12-0 2018-12-1 2019-01-0 2019-01-1 2019-01-3 2019-04-0 IDA / 59790 A posteriori Individuel Open 25,000.00 15,699.95 Signé 2018-11-09 ole du MEEF des inventaires nd planning 4 8 8 3 8 0 3 forestiers et écologiques. MG-UGP PADAP-86980-CS-C DS / Prestations d'un an d'u Component 3: Project Mana Sélection de cons 2018-10-0 2018-11-2 2018-12-2 2018-11-0 2019-12-2 n consultant individuel pour IDA / 59790 gement Coordination and M A posteriori ultants par enten Direct 20,250.00 18,284.62 Signé 2018-11-13 2 3 7 2 7 le poste d'Assistant Techniq &E te directe ue des Opérations du projet PADAP C 54-17/CN / Responsable e Component 3: Project Mana 2018-02-1 2018-03-0 2018-04-1 2019-04-1 IDA / 59790 A posteriori Individuel Open 48,000.00 0.00 Annulé 2018-01-08 n Agriculture au niveau nati gement Coordination and M 6 9 3 3 onal (UGP) &E C 10-19/ANJ / Recrutement Component 2: Investments 2019-05-1 2019-05-2 2019-06-1 2019-09-2 d'agent de suivi et d'accom COFN / C1540 and capacity building in the A posteriori Individuel Open 6,560.00 0.00 Annulé 2019-03-12 8 8 7 5 pagnement des COBA. selected landscapes MG-UGP PADAP-86978-CS-C DS / Protocole d'accord PAP RIZ pour les Chaînes de vale Component 2: Investments Sélection de cons 2018-10-1 2018-11-3 2019-01-1 2019-02-1 ur riz irrigué (Introduction d IDA / 59790 and capacity building in the A posteriori ultants par enten Direct 31,400.00 0.00 Annulé 2018-11-13 6 0 3 2 es nouvelles technologie à tr selected landscapes te directe avers de formation, Facilitati on d'accés à des intrants et des materiels Agricoles) MG-UGP PADAP-87818-CS-C DS / Protocole d'accord avec Component 2: Investments Sélection de cons la DREEF analanjirofo pour l 2018-12-0 2019-01-1 2019-05-1 IDA / 59790 and capacity building in the A posteriori ultants par enten Direct 35,000.00 0.00 Annulé 2018-11-22 a redynamisation et renforc 9 2 2 selected landscapes te directe ement de capacité des COB A existants dans le paysage de Soanierana Ivongo MG-UGP PADAP-87819-CS-C DS / Protocole d'accord avec Component 2: Investments Sélection de cons la DREEF Sofia pour la redyn 2018-12-0 2019-01-1 2019-05-1 IDA / 59790 and capacity building in the A posteriori ultants par enten Direct 25,000.00 0.00 Annulé 2018-11-22 amisation et renforcement d 9 2 2 selected landscapes te directe e capacité des COBA existan ts dans le paysage de Soani erana Ivongo C 02-18/CN / Protocole avec Component 2: Investments Sélection de cons DPV sur l'atelier de formatio 2018-05-2 2018-07-0 2019-04-0 IDA / 59790 and capacity building in the A posteriori ultants par enten Direct 40,000.00 0.00 Annulé 2018-05-09 n et production des fiches te 6 9 5 selected landscapes te directe chniques de gestion des pes tes et pesticides MG-UGP PADAP-127049-CS- CDS / Contrôle et surveillanc e des travaux sur PI d’Iazafo : Component 2: Investments Sélection de cons LOT 3: réseaux d’irrigation e 2019-08-0 2019-08-2 2019-08-2 2019-09-2 2019-10-0 2020-02-1 COFN / C1540 and capacity building in the A posteriori ultants par enten Direct 72,900.00 68,676.43 Signé 2019-08-16 t drainage zone d’Antsiraten 9 3 8 1 7 8 selected landscapes te directe ina-Nosibe LOT 4: réseaux d’irrigation e t drainage zone d’Ambatomi paka-Maromitety LOT 6: réseaux d’irrigation z one de Mahatsara MG-UGP PADAP-127177-CS- CDS / Contrôle&surveillance des travaux sur PI Andrano mafana Mangindrano-paysa ge Bealanana : Component 2: Investments Sélection de cons 2019-08-0 2019-08-2 2019-08-2 2019-09-2 2019-09-0 2020-02-1 -lot n°2: canal CPRD du pm COFN / C1540 and capacity building in the A posteriori ultants par enten Direct 47,900.00 42,922.67 Signé 2019-08-16 9 3 3 1 6 8 2153 jusqu’au bout du résea selected landscapes te directe u -lot n°3: canal CPRG 1er tro nçon de 2921 m -lot n°4: canal CPRG 2ème tr onçon de 3261 m -lot n°5: piste et pont C 22-18/CN / Protocole avec réseau des observatoires rur Sélection de cons Component 1: Information a 2018-05-1 2018-07-2 2019-02-1 eaux sur l'observatoire des IDA / 59790 A posteriori ultants par enten Direct 20,000.00 0.00 Annulé 2018-04-30 nd planning 7 1 6 données socio-économiques te directe pour le paysage de Bealana na. C 07-19/ANJ / Appui aux dial Component 2: Investments ogues public-privé régionau 2019-05-1 2019-05-2 2019-06-1 2019-09-1 IDA / 59790 and capacity building in the A posteriori Individuel Open 4,000.00 0.00 Annulé 2019-03-12 x pour la promotion de 3P d 1 1 0 8 selected landscapes ans l'agriculture et l'élevage C 02-20/BOE / Recrutement de 3 Consultants Individuels pour la validation expérimen tale des paquets techniques Component 2: Investments 2020-05-0 2020-07-1 2020-08-0 2020-07-2 2020-08-0 2020-08-2 2020-10-2 2022-08-2 agroécologie, agroforesterie COFN / C1540 and capacity building in the A posteriori Individuel Open 5,800.00 4,204.56 Signé 2020-05-22 8 6 1 7 3 6 8 6 , arboriculture et cultures fo selected landscapes urragères Lot 1: Commune d'Ambolom oty Lot 2: Commune Tsararano Lot 3: Commune Anosinalain C 03-18/BOE / Recrutement olona d'un consultant individuel ch Component 2: Investments 2020-03-0 2020-03-1 2020-03-1 2020-12-2 argé du diagnostic du foncti IDA / 59790 and capacity building in the A posteriori Individuel Open 5,000.00 0.00 Annulé 2020-01-21 8 0 5 2 onnement et opérationnalis selected landscapes ation de la Banque de seme nces au CMS Tsararano. C 06-20/CN / Responsables Component 3: Project Mana en environnement et Forest 2020-01-2 2020-07-0 2020-05-1 2020-07-2 2020-05-1 2020-08-3 2020-07-1 2022-07-3 COFN / C1540 gement Coordination and M A posteriori Individuel Open 35,000.00 9,410.11 Signé 2020-05-18 erie pour Unité de Gestion r 0 6 3 7 5 1 4 0 &E égionale du PADAP Andapa ( Région SAVA). C 07-20/CN / Responsable A Component 3: Project Mana Sélection de cons dministratif et Finacier (RAF) 2020-02-0 2020-05-2 2020-02-2 2020-08-0 2020-03-1 2022-08-0 IDA / 59790 gement Coordination and M A posteriori ultants par enten Direct 170,000.00 121,661.24 Signé 2020-05-18 pour les 04 CERs (Sava, Boe 3 8 6 1 6 1 &E te directe ny, Analanjirofo et Sofia) C 08-20/CN / Responsable P Component 3: Project Mana Sélection de cons assation des marchés pour l 2020-02-0 2020-05-2 2020-02-2 2020-08-0 2020-05-2 2022-08-0 COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 170,000.00 98,127.18 Signé 2020-05-18 es 04 CERs (Sava, Sofia, Boe 3 8 0 1 7 1 &E te directe ny et Analanjirofo). C 09-20/CN / Comptable po Component 3: Project Mana Sélection de cons 2020-02-1 2020-05-2 2020-02-2 2020-08-0 2020-03-2 2022-08-0 ur les 04 CERs (Sava, Sofia, COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 85,000.00 73,670.47 Signé 2020-05-18 7 8 5 1 0 1 Boeny et Analanjirofo). &E te directe C 10-20/CN / Responsable E Component 3: Project Mana Sélection de cons 2020-04-1 2020-05-2 2020-04-2 2020-08-0 2020-05-1 2022-08-0 au et Irrigation pour les 04 C COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 120,000.00 88,330.28 Signé 2020-05-18 0 8 0 1 4 1 ERs (Sava, Sofia, Boeny et A &E te directe nalanjirofo). C 11-20/CN / Responsables Socio-orga et développemen t local pour les 04 CERs du P Component 3: Project Mana Sélection de cons 2020-04-1 2020-05-2 2020-04-2 2020-08-0 2020-05-1 2022-08-0 ADAP : Iazafo-Soanierana Iv COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 115,000.00 83,913.76 Signé 2020-05-18 0 8 7 1 4 1 ongo (Région Analanjirofo), &E te directe Marovoay (Région Boeny), B ealalana (Région SOFIA) et A ndapa (Région SAVA). C 12-20/CN / 04 Assistants t echniques des Opérations p our chaque CER du PADAP : Component 3: Project Mana Sélection de cons 2020-01-2 2020-05-2 2021-02-1 2020-08-0 2021-03-1 2022-08-0 Iazafo-Soanierana Ivongo (R COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 200,000.00 120,566.77 Signé 2020-05-18 4 8 9 1 5 1 égion Analanjirofo), Marovoa &E te directe y (Région Boeny), Bealalana (Région SOFIA) et Andapa (R égion SAVA). C 13-20/CN / 03 Responsabl es en environnement et For Component 3: Project Mana Sélection de cons esterie pour les 03 CER du P 2020-04-1 2020-05-2 2020-04-2 2020-08-0 2020-05-2 2022-08-0 COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 90,000.00 65,920.56 Signé 2020-05-18 ADAP : Iazafo-Soanierana Iv 6 8 7 1 5 1 &E te directe ongo (Région Analanjirofo), Marovoay (Région Boeny) et Bealalana (Région SOFIA). C 14-20/CN / 03 Responsabl es en Agriculture pour les 0 Component 3: Project Mana Sélection de cons 3 CER du PADAP : Iazafo-Soa 2020-03-2 2020-05-2 2020-04-2 2020-08-0 2020-05-1 2022-08-0 COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 90,000.00 66,498.81 Signé 2020-05-18 nierana Ivongo (Région Anal 6 8 7 1 0 1 &E te directe anjirofo), Marovoay (Région Boeny) et Andapa (Région S AVA) C 15-20/CN / Responsable e Component 3: Project Mana Sélection de cons 2020-05-1 2020-05-2 2020-05-2 2020-08-0 2020-10-2 2022-08-0 n Suivi-évaluation pour la Ré COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 40,000.00 19,598.78 Signé 2020-05-18 9 8 9 1 2 1 gion ANALANJIROFO du PAD &E te directe AP. Component 3: Project Mana Sélection de cons C 18-20/CN / Comptable nat 2020-02-1 2020-05-2 2020-02-2 2020-08-0 2020-03-1 2022-08-0 COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 40,000.00 28,308.96 Signé 2020-05-18 ional du PADAP. 7 8 6 1 3 1 &E te directe C 16-20/CN / Responsable S Component 3: Project Mana Sélection de cons 2020-05-1 2020-05-2 2020-04-2 2020-08-0 2020-05-1 2022-08-0 auvegarde Environnemental COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 40,000.00 32,056.56 Signé 2020-05-18 8 8 8 1 1 1 e et Sociale au niveau natio &E te directe nal (UGP). C 17-20/CN / Assistant Tech Component 3: Project Mana Sélection de cons 2020-05-1 2020-05-2 2020-10-0 2020-08-0 2020-11-0 2022-08-0 nique des Opérations du pro COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 48,000.00 29,064.61 Signé 2020-05-18 8 8 9 1 2 1 jet PADAP au niveau de l'UG &E te directe P. C 21-20/CN / Assistant Infor Component 3: Project Mana Sélection de cons 2020-03-2 2020-05-2 2020-03-2 2020-08-0 2020-04-1 2022-08-0 matique pour l'Unité de Gest COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 21,000.00 16,253.16 Signé 2020-05-18 3 8 3 1 4 1 ion du PADAP. &E te directe Component 3: Project Mana Sélection de cons C 20-20/CN / Auditeur inter 2020-05-1 2020-05-2 2020-06-2 2020-08-0 2020-07-1 2022-08-0 COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 48,000.00 33,884.58 Signé 2020-05-18 ne du Projet. 8 8 2 1 4 1 &E te directe C 19-20/CN / Responsable e Component 3: Project Mana Sélection de cons 2020-01-1 2020-05-2 2020-01-1 2020-08-0 2020-02-0 2022-08-0 au et irrigation national du P COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 37,000.00 29,710.39 Signé 2020-05-18 3 8 3 1 3 1 rojet. &E te directe C 11-20/SOF / Recrutement d’un Consultant Spécialiste en Travaux Publics chargé d Component 2: Investments 2020-12-3 2020-07-2 2021-05-1 2020-08-0 2021-05-1 2020-08-1 2021-06-1 2021-06-1 e l’appui à la Cellule d’exécu IDA / 59790 and capacity building in the A posteriori Individuel Open 9,500.00 9,911.20 Signé 2020-06-17 0 9 1 5 4 9 9 5 tion Régionale Sofia sur l’ex selected landscapes écution des travaux de réha bilitation de la RIP 117 relian t Bealanana à Ambatoriha C 26-18/ CN / Diagnostic ag Component 2: Investments Sélection de cons roécologique et Formation 2018-10-2 2018-05-2 2018-11-2 2018-07-2 2018-12-1 IDA / 59790 and capacity building in the A posteriori ultants par enten Direct 45,000.00 0.00 Annulé 2018-05-09 des Organisations paysanne 6 6 2 0 7 selected landscapes te directe s et des paysans sur les prat iques agroécologiques Page 12 C 03-20/SAV / Recrutement de 02 techniciens agricoles pour encadrer les 300 pays ans adoptants en riziculture Component 2: Investments 2020-08-2 2020-09-2 2020-11-2 2020-10-1 2020-12-0 2020-11-1 2021-01-0 2021-05-1 2021-08-0 ameliorée dans le paysage d COFN / C1540 and capacity building in the A posteriori Individuel Open 5,630.00 7,865.70 Achevé 2020-08-05 0 3 4 4 3 8 2 7 6 'Andapa: selected landscapes Lot 1: Un technicien s'occup ant des périmètres de l'axe nord Lot 2: Un technicien s'occup ant des périmètres de l'axe C 06-20/ANJ / Consultant in ouest Component 2: Investments 2020-06-1 2020-06-2 2020-07-2 2020-10-2 dividuel pour formation des COFN / C1540 and capacity building in the A posteriori Individuel Open 5,140.00 0.00 Annulé 2020-04-17 3 1 2 0 dirigeants du Tranoben'ny T selected landscapes antsaha C 09-19/ANJ / Recrutement d'un consultant individuel p our/ Component 2: Investments Lot 1: la formation en GIRE 2020-06-0 2020-06-1 2020-07-2 2020-12-1 COFN / C1540 and capacity building in the A posteriori Individuel Open 4,500.00 0.00 Annulé 2020-04-13 des personnels de DREEH/D 9 9 0 7 selected landscapes RAEP/DREDD Lot 2: Diffuser et expliquer l es rôles, responsabilités de l ’Autorité Nationale de l’Eau et de l’Assainissement C 23-20/CN / Responsables Component 3: Project Mana Sélection de cons en Agriculture pour la cellule 2020-06-3 2020-07-1 2020-06-2 2020-08-0 2020-07-1 2022-08-0 COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 23,000.00 20,447.60 Signé 2020-06-30 d'exécution régionale du PA 0 0 9 9 5 9 &E te directe DAP Région SOFIA (Basé à B ealalana). C 27-20/CN / Recrutement d’un Responsable Agricultur Component 3: Project Mana 2020-09-2 2020-10-2 2020-10-2 2020-11-0 2020-10-2 2020-11-1 2020-11-2 2022-08-1 e au niveau de l’Unité de Ge IDA / 59790 gement Coordination and M A posteriori Individuel Open 20,000.00 11,440.66 Signé 2020-09-28 8 8 9 4 9 8 8 0 stion du Projet Agriculture D &E urable par une Approche Pa ysage C 26-20/CN / Assistant tech Component 2: Investments Sélection de cons 2020-09-1 2020-09-1 2020-09-1 2020-10-1 2020-09-2 2021-01-1 nique pour la gestion des co COFN / C1540 and capacity building in the A posteriori ultants par enten Direct 90,000.00 11,872.80 Signé 2020-09-03 6 3 7 3 2 1 ntrats. selected landscapes te directe C 12-20/SOF / Recrutement Component 2: Investments d'un Consultant Individuel s 2020-12-3 2020-11-2 2021-05-1 2020-12-0 2021-05-1 2021-01-0 2021-06-1 2022-03-0 COFN / C1540 and capacity building in the A posteriori Individuel Open 13,500.00 9,911.20 Signé 2020-10-15 pécialiste en irrigation pour 0 8 1 8 4 6 3 2 selected landscapes appuyer la Cellule d’exécuti on Régionale Sofia C 29-20/CN / Recrutement Component 3: Project Mana 2020-11-2 2021-01-1 2021-05-1 2021-01-2 2021-05-1 2021-02-2 2021-06-0 2022-08-0 COFN / C1540 A posteriori Individuel Open 8,500.00 5,769.58 Signé 2020-11-30 d'un Assistant Administratif gement Coordination and M 6 9 1 9 2 6 4 4 et Financier. &E C 30-20/CN / Recrutement Component 3: Project Mana de 04 Secrétaires en passati 2020-11-2 2021-01-1 2021-01-2 2021-01-2 2021-01-2 2021-02-2 2021-05-2 2022-08-0 COFN / C1540 gement Coordination and M A posteriori Individuel Open 34,000.00 9,736.23 Signé 2020-11-30 on des marchés en tant que 5 9 5 9 7 6 4 4 &E personnel d'appui pour les C ER du PADAP. C 31-20/CN / Spécialiste en Component 3: Project Mana 2020-12-0 2021-01-1 2021-01-2 2021-01-2 2021-03-2 2021-02-2 2021-04-1 2022-08-0 Passation des marchés au ni COFN / C1540 gement Coordination and M A posteriori Individuel Open 16,000.00 10,812.70 Signé 2020-11-30 1 9 2 9 5 6 9 4 veau de l'UGP. &E C 28-20/CN / 02 Responsabl Component 3: Project Mana es en Suivi-évaluation dont 2020-12-1 2021-02-0 2021-02-1 2021-02-1 2021-04-0 2021-03-0 2021-05-3 2022-07-3 COFN / C1540 gement Coordination and M A posteriori Individuel Open 36,000.00 13,996.22 Signé 2020-12-18 01 pour la Région SOFIA et 0 0 6 8 6 7 5 0 0 &E 1 pour la région de SAVA du PADAP. C 28-20/BOE / Recrutement de 3 Consultants individuels pour l'encadrement techniq Component 2: Investments 2021-03-0 2021-04-0 2021-04-1 2021-04-2 2021-04-1 2021-05-3 2021-05-0 2021-12-2 ue et suivi de l'adoption du COFN / C1540 and capacity building in the A posteriori Individuel Open 12,600.00 7,616.83 Signé 2021-02-25 1 5 6 6 6 1 2 7 paquet technique par les rizi selected landscapes culteurs. Lot 1 d'Ambolomot y, lot 2 Tsararano Lot 3 Anos inalinolona C 14-20/ANJ / Recrutement de 8 Techniciens en environ nement: Lot 1:1/3 CR Vavatenina zo ne Sud Component 2: Investments Lot 2:1/1 CR Vavatenina zon 2020-12-1 2020-12-2 2021-02-0 2023-02-0 COFN / C1540 and capacity building in the A posteriori Individuel Open 71,300.00 0.00 Annulé 2020-10-30 e Nord-2CR Fen Est 3 8 1 1 selected landscapes Lot 3:2/3CR Soanierana Ivon go zone Sud Lot 4:1/CR Antanifotsy-Mano mpana Lot 5: 1/CR Ambahoabe-Am bodiampana Lot 6:1/CR Antenina C 35-20/SOF / Recrutement de trois (03) consultants indi viduels au titre de technicie Component 2: Investments ns accompagnateurs pour l' 2020-10-1 2021-02-1 2021-01-2 2021-02-2 2021-02-0 2021-03-0 2021-02-1 2021-10-0 COFN / C1540 and capacity building in the A posteriori Individuel Open 33,500.00 5,787.94 Achevé 2021-01-06 encadrement et l'appui cons 5 0 6 0 8 9 4 5 selected landscapes eils de proximité aux paysan s formateurs et paysans ado ptant la riziculture amélioré e dans le paysage de Bealan ana C 05-20/CN / Responsables Component 3: Project Mana en Agriculture pour la cellule 2020-04-2 2020-06-1 2020-07-0 2020-08-1 2022-08-1 IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 0.00 Annulé 2020-04-30 d'exécution régionale du PA 3 8 9 3 3 &E DAP Région SOFIA (Basé à Bealalana). C 05-21/ANJ / Recrutement d’un(e)consultant(e) spéciali Component 2: Investments 2021-02-1 2021-04-0 2021-05-1 2021-04-0 2021-05-1 2021-04-2 2021-06-1 2022-04-2 ste en travaux publics charg COFN / C1540 and capacity building in the A posteriori Individuel Open 11,884.00 387.26 Résilié 2021-02-25 6 6 1 7 4 7 2 7 e de l’appui a la cellule d’ex selected landscapes écution régionale Analanjirof o C 20-20/ANJ / Assistance te Component 2: Investments Sélection de cons chnique de FDA pour la mise 2021-02-1 2021-03-1 2021-03-2 2021-04-2 2021-06-1 2022-07-2 COFN / C1540 and capacity building in the A posteriori ultants par enten Direct 531,956.00 67,639.56 Achevé 2021-02-26 en oeuvre d'AGR priorisées 2 8 3 7 2 1 selected landscapes te directe dans les paysages d'Iazafo e t de Soanierana Ivongo C 7-20/BOE / Recrutement de 3 consultants individuels pour l'encadrement techniq Component 2: Investments ue des agriculteurs sur tane En cours d'exécu 2021-07-2 2021-04-2 2021-05-1 2021-06-1 2021-12-1 COFN / C1540 and capacity building in the A posteriori Individuel Open 10,000.00 0.00 2021-03-10 ty dans le paysage de Marov tion 8 4 5 9 6 selected landscapes oay Lot 1: Ambolomoty Lot 2: Tsararano Lot 3: Anosinalainolona C 07-20/BOE / Recrutement de 3 consultants individuels Component 2: Investments pour l'encadrement techniq 2020-12-2 2021-01-1 2021-02-2 2021-09-2 COFN / C1540 and capacity building in the A posteriori Individuel Open 10,000.00 0.00 Annulé 2020-10-30 ue des agriculteurs sur tane 9 9 3 1 selected landscapes ty dans le paysage de Marov oay Lot 1: Ambolomoty Lot 2: Tsararano Lot 3: Anosinal ainolona. C 08-20/ANJ / Recrutement d'un consultant individuel p Component 2: Investments 2021-03-2 2021-04-0 2021-04-2 2021-05-0 our la formation du personn COFN / C1540 and capacity building in the A posteriori Individuel Open 2,250.00 0.00 Annulé 2021-02-10 5 4 4 9 el des Ministères au niveau selected landscapes Régional à la construction et mise en œuvre du SIS (Form ation) C 13-20/ANJ / Recrutement des techniciens accompagn ateurs dans les paysages d'I Component 2: Investments azafo et de Soanierana Ivon En cours d'exécu 2021-03-0 2021-04-2 2021-04-0 2021-05-0 2021-04-1 2021-05-3 2021-11-2 COFN / C1540 and capacity building in the A posteriori Individuel Open 115,900.00 0.00 2021-03-03 go: tion 2 1 6 1 2 0 6 selected landscapes Lot 01: 05 techniciens en ag riculture Lot 02: 08 techniciens en en vironnement C 10-20/SOF / Recrutement de Consultants individuels p Component 2: Investments 2020-12-2 2021-01-1 2021-02-2 2021-05-2 our l'encadrement et l'appui COFN / C1540 and capacity building in the A posteriori Individuel Open 6,000.00 0.00 Annulé 2020-09-30 9 9 3 4 conseils de proximité aux Pa selected landscapes ysans Formateurs et aux Pa ysans adoptants C 05-19/ANJ / Consultant in Component 2: Investments dividuel pour appuyer la red 2021-03-1 2021-03-2 2021-04-1 2021-08-1 COFN / C1540 and capacity building in the A posteriori Individuel Open 5,630.00 0.00 Annulé 2021-01-13 ynamisation duTranoben'ny 4 5 5 3 selected landscapes Tantsaha à Fenérive Est. C 22-20 / CN / Responsable Environnement et Foresterie Component 3: Project Mana 2020-05-0 2020-07-2 2020-05-1 2020-08-1 2020-09-2 2022-08-1 au niveau de la Cellule d’Ex IDA / 59790 gement Coordination and M A posteriori Individuel Open 48,000.00 0.00 Annulé 2020-06-10 5 9 3 9 3 4 écution Régionale du projet &E : Poste basé à Andapa (Régi on SAVA) C 23-20/BOE / Recrutement d'un consultant individuel p our les Etudes - contrôle et Component 2: Investments 2021-03-2 2021-04-2 2021-04-1 2021-05-2 2021-04-2 2021-06-2 2021-07-0 2021-12-2 surveillance des travaux de COFN / C1540 and capacity building in the A posteriori Individuel Open 9,500.00 9,690.00 Signé 2021-03-16 5 9 6 0 2 4 1 1 réhabilitation des trois maga selected landscapes sins de stockage à la disposi tion des trois coopératives s emencières de Tsararano C 03-21/CN / Analyse du ma Sélection de cons Component 1: Information a 2021-05-0 2021-06-1 2021-05-0 2021-09-0 2021-10-0 2022-03-0 rché et de la politique rizicol COFN / C1540 A posteriori ultants par enten Direct 125,000.00 104,172.41 Signé 2021-05-21 nd planning 3 0 4 4 1 3 e à Madagascar. te directe C 04-21/CN / Responsable A Component 3: Project Mana griculture pour la Cellule d’E 2021-05-0 2021-06-0 2021-06-1 2021-06-1 2021-06-2 2021-07-0 2021-07-2 2022-07-0 COFN / C1540 gement Coordination and M A posteriori Individuel Open 16,000.00 9,693.95 Signé 2021-05-03 xécution Régionale du PADA 3 2 7 2 1 6 3 6 &E P BOENY (Basé à Marovoay). C 02-21/CN / Responsable E Component 3: Project Mana nvironnement et Foresterie 2021-03-1 2021-04-1 2021-05-1 2021-04-2 2021-05-2 2021-05-2 2021-06-1 2022-08-1 COFN / C1540 gement Coordination and M A posteriori Individuel Open 16,000.00 10,362.62 Signé 2021-03-19 pour la Cellule d’Exécution R 9 8 9 8 1 2 9 5 &E égionale du PADAP SOFIA (B asé à Bealanana). C 02-21/SAV / Mémoire tech nique et contrôle-surveillanc e’ des travaux restant pour l Component 2: Investments Sélection de cons a réhabilitation du barrage e 2021-05-3 2021-06-1 2021-07-1 2021-08-0 2021-08-0 2022-01-3 COFN / C1540 and capacity building in the A posteriori ultants par enten Direct 18,600.00 18,045.72 Signé 2021-05-21 n dur avec avant-canal rive 1 0 3 4 3 1 selected landscapes te directe droite et la rénovation des r éseaux hydroagricoles du pé rimètre Ambodivitagnona su r 370 ha, CR Ambalamanasy II, District Andapa. C 03-21/SAV / Recrutement Component 2: Investments de 03 techniciens agricoles 2021-05-1 2021-06-2 2021-07-1 2021-07-0 2021-07-1 2021-07-1 2021-08-0 2022-07-1 2023-03-1 COFN / C1540 and capacity building in the A posteriori Individuel Open 18,500.00 7,890.30 Achevé 2021-05-10 pour encadrer les Paysans F 2 9 3 6 9 9 4 9 7 selected landscapes ormateurs dans le paysage d'Andapa, Région SAVA. C 02-20/SOF / Recrutement de deux (02) agents commu Component 2: Investments 2021-03-2 2021-04-1 2021-05-1 2023-02-2 naux sur l'approche LIFE : 0 COFN / C1540 and capacity building in the A posteriori Individuel Open 8,750.00 0.00 Annulé 2021-01-29 0 0 5 4 1 Commune Rurale AMBODI selected landscapes AMPANA- 01 Commune Rura le AMBATOSIA C 12-20/ANJ / Contrôle et su rveillance des travaux de ré Component 2: Investments Sélection de cons habilitation des réseaux hyd 2021-03-3 2021-09-0 2020-10-1 2021-10-1 2020-12-1 2022-02-0 COFN / C1540 and capacity building in the A posteriori ultants par enten Direct 24,500.00 20,661.41 Signé 2021-08-19 roagricoles de la zone Mahat 0 8 2 2 6 9 selected landscapes te directe sara Sud- Andapatsra, dans l a plaine d'Iazafo (Lot 06); Di strict de Vavatenina. Page 13 C 04-21/ANJ / Recrutement d'un Consultants individuel s Component 2: Investments pécialiste en Socio organisat 2021-06-2 2021-07-0 2021-07-2 2022-01-1 COFN / C1540 and capacity building in the A posteriori Individuel Open 23,030.00 0.00 Annulé 2021-04-30 ion pour appui au développe 3 3 3 9 selected landscapes ment de chaîne de valeur gi rofle dans le paysage de So anierana Ivongo C 03-21/ANJ / Recrutement de Consultant individuel spé Component 2: Investments cialiste en Distillation pour a 2021-05-1 2021-06-0 2021-07-0 2022-05-0 COFN / C1540 and capacity building in the A posteriori Individuel Open 46,060.00 0.00 Annulé 2021-03-18 ppui au développement de c 1 1 6 2 selected landscapes haîne de valeur girofle dans les paysages d’Iazafo et de Soanierana Ivongo C 02-21/ANJ / Recrutement de Consultant individuel spé Component 2: Investments cialiste en Chaudronnerie po 2021-05-1 2021-06-0 2021-07-0 2022-05-0 COFN / C1540 and capacity building in the A posteriori Individuel Open 46,060.00 0.00 Annulé 2021-03-18 ur appui au développement 1 1 6 2 selected landscapes de chaîne de valeur girofle d ans les paysages d’Iazafo et de Soanierana Ivongo C 13-20/BOE / Recrutement de 03 consultants individuel s pour l'encadrement techni Component 2: Investments 2021-03-2 2021-04-1 2021-05-2 2021-07-2 que et suivi de l'adoption du COFN / C1540 and capacity building in the A posteriori Individuel Open 12,600.00 0.00 Annulé 2021-02-02 8 8 3 2 paquet technique par les rizi selected landscapes culteurs dans les CR d'Ambo lomoty, de Tsararano et d'A nosinalainolona C 05-20/BOE / Recrutement de deux (02) agents commu naux pour l'approche LIFE d Component 2: Investments ans le district de Marovoay, 2021-07-2 2021-08-1 2021-09-0 2023-09-1 COFN / C1540 and capacity building in the A posteriori Individuel Open 8,100.00 0.00 Annulé 2021-06-09 Région Boeny. 8 2 8 8 selected landscapes Lot 1: Commune rurale de T sararano Lot 2: Commune rurale d' An osinalainolona C 07-21/CN / Recrutement Component 3: Project Mana 2021-08-0 2021-09-2 2022-01-0 2021-10-1 2022-07-0 2021-11-1 2022-09-2 2022-11-1 d’un consultant pour la com COFN / C1540 gement Coordination and M A posteriori Individuel Open 12,000.00 0.00 Signé 2021-08-02 4 0 5 1 5 5 6 5 munication du PADAP. &E C 09-21/CN / Spécialiste en Component 3: Project Mana 2021-10-0 2021-12-0 2021-12-0 2021-12-2 2022-01-1 2022-02-0 2022-01-3 2022-08-0 Passation des marchés pour COFN / C1540 gement Coordination and M A posteriori Individuel Open 20,000.00 5,956.39 Signé 2021-10-20 1 8 1 9 8 2 1 1 la Cellule d'Exécution Régio &E nale Sofia. C 08-21/CN / Responsable A Component 3: Project Mana griculture pour la Cellule d’E 2021-10-2 2021-12-1 2021-12-0 2022-01-0 2022-01-1 2022-02-0 2022-01-3 2022-09-0 COFN / C1540 gement Coordination and M A posteriori Individuel Open 16,000.00 4,662.83 Signé 2021-10-20 xécution Régionale du PADA 7 3 1 3 0 7 0 2 &E P SOFIA (Basé à Bealanana) C 10-20/ANJ / Recrutement consultant individuel pour la Component 2: Investments 2021-09-0 2021-09-1 2021-10-0 2021-10-2 formation en GIRE des perso COFN / C1540 and capacity building in the A posteriori Individuel Open 2,925.00 0.00 Annulé 2021-07-20 6 6 6 1 nnels des 03 Directions Régi selected landscapes onales de tutelles et ceux d e la CER C 10-21/CN / Consultant sp Component 3: Project Mana Sélection de cons 2021-10-1 2021-11-0 2021-11-0 2021-12-2 2021-11-2 2022-09-0 écialiste en travaux publics COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 16,000.00 6,614.38 Signé 2021-10-20 5 9 3 3 0 2 à la cellule d’exécution régio &E te directe nale Analanjirofo C 11-21/CN / Responsable E Component 3: Project Mana Sélection de cons 2021-10-1 2021-11-1 2021-11-0 2021-12-2 2021-11-2 2022-09-0 nvironnement et Foresterie COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct 16,000.00 8,267.97 Signé 2021-10-20 5 4 3 8 0 2 au niveau de l'UGP. &E te directe C 13-20/SOF / Recrutement d'un Consultant Individuel s Component 2: Investments 2020-12-3 2021-01-3 2021-02-1 2021-03-0 2022-06-0 pécialiste en infrastructure r COFN / C1540 and capacity building in the A posteriori Individuel Open 13,500.00 0.00 Annulé 2020-12-18 0 1 0 2 5 outière pour appuyer la Cell selected landscapes ule d’exécution Régionale S ofia C 12-20/BOE / Recrutement d'un consultant individuel p our l'étude - contrôle et surv Component 2: Investments 2021-07-2 2021-12-0 2021-12-2 2022-01-2 2022-06-2 eillance des travaux de cons COFN / C1540 and capacity building in the A posteriori Individuel Open 2,400.00 0.00 Annulé 2021-10-13 8 1 2 6 5 truction de 3 couloirs de va selected landscapes ccination des bovidés dans l es CR d'Ambolomoty, de Tsa rarano et d'Anosinalainolona C 13-21/CN / Quatre (04) as sistants régionaux en sauve Component 3: Project Mana 2021-10-0 2021-12-1 2022-01-0 2022-01-0 2022-01-0 2022-02-1 2022-02-1 2022-08-1 garde environnementale et COFN / C1540 gement Coordination and M A posteriori Individuel Open 40,000.00 8,755.14 Signé 2021-10-29 1 8 5 8 6 2 2 1 sociale (ARSES) au niveau d &E es paysages d’intervention du PADAP C 26-20/BOE / Recrutement de consultant individuel pou Component 2: Investments 2021-10-2 2021-11-0 2021-11-2 2022-06-2 r l'encadrement technique d COFN / C1540 and capacity building in the A posteriori Individuel Open 3,600.00 0.00 Annulé 2021-09-20 4 3 3 1 es 40 pisciculteurs dans les selected landscapes CR de Marosakoa, d'Ambolo moty et de Tsararano C 22-20/BOE / Recrutement d'un Consultant individuel p our le contrôle et surveillanc Component 2: Investments 2021-12-0 2021-12-2 2022-01-2 2022-07-2 e des Travaux de stabilisatio COFN / C1540 and capacity building in the A posteriori Individuel Open 5,000.00 0.00 Annulé 2021-10-13 1 2 6 5 n des zones d'érosion et pro selected landscapes tection des réseaux hydroag ricole le long du CPRD et CS PC Ambolomoty C 10-20/BOE / Recrutement d'un consultant individuel p our identification, formation Component 2: Investments 2021-11-2 2021-12-1 2022-01-1 2022-09-1 des Paysans formateurs et COFN / C1540 and capacity building in the A posteriori Individuel Open 5,400.00 0.00 Annulé 2021-10-01 4 5 9 6 encadrement de 06 ateliers selected landscapes d'élevage bovin pilotes dans les CR d'Ambolomoty, de Ts ararano et d'Anosinalainolon a C 19-20/BOE / Recrutement de deux (2) techniciens fore Component 2: Investments stiers 2020-11-1 2020-12-0 2021-01-0 2021-07-0 COFN / C1540 and capacity building in the A posteriori Individuel Open 21,000.00 0.00 Annulé 2020-09-25 Lot 1: Zone Marosakoa-Amb 3 4 8 7 selected landscapes olomoty Lot 2: Zone Tsararano-Anosi nalainolona C 14-21/CN / Recrutement d'un consultant individuel p Component 1: Information a 2021-12-2 2022-01-1 2022-03-3 2022-01-2 2022-04-0 2022-02-1 2022-04-1 2022-04-1 our l'actualisation de la strat COFN / C1540 A posteriori Individuel Open 10,000.00 0.00 Signé 2021-11-30 nd planning 1 4 1 4 1 3 8 4 égie national de développe ment rizicole à Madagascar. C 06-21/CN / Recrutement Component 3: Project Mana 2021-12-0 2021-12-1 2022-01-0 2022-11-2 d’un Assistant en Informatiq COFN / C1540 gement Coordination and M A posteriori Individuel Open 8,500.00 0.00 Annulé 2021-11-04 4 4 7 7 ue du PADAP, poste basé à : &E Antananarivo C 01-22/CN / 02 Assistants Component 3: Project Mana en Génie Civil pour les Cellul 2022-03-1 2022-04-0 2022-09-2 2022-04-1 2022-05-1 2022-10-0 COFN / C1540 gement Coordination and M A posteriori Individuel Open 20,000.00 0.00 Annulé 2022-01-31 es d’Exécution Régionales d 4 6 0 6 0 7 &E u Projet PADAP Sofia et Ana nalanjirofo. C 03-22/CN / Spécialiste en Component 3: Project Mana Passation des Marchés char 2022-05-1 2022-06-2 2022-07-0 2022-07-2 2023-07-2 COFN / C1540 gement Coordination and M A posteriori Individuel Open 16,000.00 0.00 Annulé 2022-05-10 gé de l’appui technique de l’ 2 9 9 9 9 &E Unité de Gestion de Projet s ur les activités FSRP. C 04-22/CN / Spécialiste en Component 3: Project Mana Passation des Marchés char 2022-10-1 2022-08-2 2022-09-0 2022-09-2 2023-07-2 COFN / C1540 gement Coordination and M A posteriori Individuel Open 16,000.00 0.00 Annulé 2022-07-15 gé de l’appui technique de l’ 0 9 9 7 4 &E Unité de Gestion de Projet. C 05-22/CN / Responsable e Component 3: Project Mana 2022-09-2 2022-09-2 2022-12-0 2022-10-0 2022-12-0 2022-10-2 2023-02-0 2023-07-3 COFN / C1540 A posteriori Individuel Open - National 11,000.00 0.00 Signé 2022-08-08 au et irrigation national du P gement Coordination and M 9 2 7 2 9 2 4 1 rojet. &E C 06-22/CN / Spécialiste en Component 3: Project Mana 2022-10-1 2022-09-2 2022-10-0 2022-10-2 2023-07-3 Passation des marchés pour COFN / C1540 gement Coordination and M A posteriori Individuel Open - National 22,000.00 0.00 Annulé 2022-08-08 0 2 2 2 1 les 02 CERs (Sofia et Analanj &E irofo). C 02-22/CN / Recrutement Component 2: Investments 2022-11-1 2022-12-1 2023-03-1 2022-12-2 2023-03-3 2023-01-1 2023-04-1 2023-04-1 2023-07-0 d'un consultant individuel p COFN / C1540 and capacity building in the A posteriori Individuel Open - National 5,000.00 0.00 Achevé 2022-10-27 0 7 5 8 1 7 8 7 1 our la formation en SIG du P selected landscapes rojet. C 02-23/CN / Recrutement Component 3: Project Mana Sélection de cons 2023-05-3 2023-05-2 2023-05-1 2023-06-2 2023-06-0 2023-07-2 d'un cabinet pour l'audit ext COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct - National 30,000.00 0.00 Signé 2023-05-22 1 7 9 0 8 0 erne de l’exercice 2022 du P &E te directe ADAP. C 04-23/CN / Service de con Component 3: Project Mana Sélection de cons sultant pour l'évaluation fina En cours d'exécu 2023-11-1 2023-09-2 2023-11-0 2024-02-2 COFN / C1540 gement Coordination and M A posteriori ultants par enten Direct - National 180,000.00 0.00 2023-09-12 le du Projet Agriculture Dura tion 3 2 1 9 &E te directe ble par une Approche Paysa ge C 05-23/CN / Responsable A Component 3: Project Mana En cours d'exécu 2023-09-3 2023-10-2 2023-11-0 2023-11-2 2024-04-3 IDA / 59790 A posteriori Individuel Open - National 9,000.00 0.00 2023-09-15 dministratif et financier CER gement Coordination and M tion 0 8 7 4 0 Analanjorofo &E C 06-23/CN / Spécialiste en Component 3: Project Mana En cours d'exécu 2023-11-2 2023-10-2 2023-11-0 2023-11-2 2024-04-3 Passation des marchés pour COFN / C1540 gement Coordination and M A posteriori Individuel Open - National 18,000.00 0.00 2023-09-15 tion 2 8 7 4 0 les 02 CERs (Sofia et Sava). &E C 07-23/CN / Assistant en P Component 3: Project Mana assation des Marchés charg En attente d'exé 2023-10-2 2023-11-0 2023-11-2 2024-04-3 COFN / C1540 gement Coordination and M A posteriori Individuel Open - National 6,000.00 0.00 2023-09-15 é de l’appui technique de l’ cution 8 7 4 0 &E Unité de Gestion de Projet. C 08-23/CN / Un Consultant Component 2: Investments senior chargé de planificatio En cours d'exécu 2023-10-0 2023-11-0 2023-11-1 2023-11-3 2024-04-2 COFN / C1540 and capacity building in the A posteriori Individuel Open - National 10,000.00 0.00 2023-09-21 n et de suivi d’infrastructure tion 3 3 3 0 6 selected landscapes s routières du PADAP. C 01-23/CN / Études des inf Component 2: Investments Sélection de cons Direct - Internatio 2023-05-0 2023-06-0 2023-07-2 rastructures du système d’ir COFN / C1540 and capacity building in the A posteriori ultants par enten 210,000.00 0.00 Annulé 2023-04-29 nal 9 5 5 rigation solaire pour PADAP. selected landscapes te directe C 10-23/CN / Un (01) assist Component 3: Project Mana ant régional en sauvegarde En attente d'exé 2024-01-0 2024-01-0 2024-02-0 2024-05-0 COFN / C1540 gement Coordination and M A posteriori Individuel Open - National 6,000.00 0.00 2023-11-23 environnementale et sociale cution 2 7 1 1 &E (ARSES) au niveau de la CER SAVA C 11-23/CN / Consultant ind ividuel pour renforcement d Component 2: Investments En attente d'exé 2024-02-0 2024-02-1 2024-03-0 2024-04-0 es capacités des diverses St COFN / C1540 and capacity building in the A posteriori Individuel Open - National 13,300.00 0.00 2023-12-15 cution 4 5 6 5 aff et Ministères en suivi-éva selected landscapes luation et gestion de base d e données. C 13-23/CN / Responsable P Component 3: Project Mana En attente d'exé 2024-01-0 2024-01-2 2024-02-0 2024-04-2 COFN / C1540 A posteriori Individuel Open - National 10,000.00 0.00 2023-11-30 assation des marchés de l'U gement Coordination and M cution 9 4 8 8 GP. &E Page 14