The World Bank Implementation Status & Results Report Local Government COVID-19 Response & Recovery Project (P174937) Local Government COVID-19 Response & Recovery Project (P174937) SOUTH ASIA | Bangladesh | Urban, Resilience and Land Global Practice | IBRD/IDA | Investment Project Financing | FY 2022 | Seq No: 4 | ARCHIVED on 21-Nov-2023 | ISR57447 | Implementing Agencies: Local Government Engineering Department, Ministry of Local Government, Rural Development and Coopera, People's Republic of Bangladesh Key Dates Key Project Dates Bank Approval Date: 24-Feb-2022 Effectiveness Date: 14-Aug-2022 Planned Mid Term Review Date: 18-Feb-2024 Actual Mid-Term Review Date: Original Closing Date: 30-Jun-2026 Revised Closing Date: 31-Dec-2025 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To strengthen urban local governments’ response to the COVID-19 pandemic and preparedness for future shocks. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: COVID-19 Response Grants:(Cost $287.74 M) Component 2: Implementation and capacity development support, digital technology, and project management:(Cost $13.59 M) Component 3: Contingency Emergency Response Component Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions Project implementation is on track. All Urban Local Government Institutions (ULGIs) have prepared their COVID-19 Response and Recovery Plans (CRRPs) and are implementing their sub-projects according to the agreed CRRPs. Guidelines for Labor Intensive Public Works and technical designs are being used by ULGIs. Capacity building activities to strengthen ULGI performance are ongoing. 11/21/2023 Page 1 of 7 The World Bank Implementation Status & Results Report Local Government COVID-19 Response & Recovery Project (P174937) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other Moderate Moderate Moderate Overall Moderate Moderate Moderate Results PDO Indicators by Objectives / Outcomes (i) Strengthened urban local governments’ response to the COVID-19 pandemic IN01329023 ►Person days of temporary work provided under public work schemes (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 365,750.00 1,500,000.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 IN01329025 Person days of temporary work provided under public work schemes - Female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 164,586.00 750,000.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 IN01329056 ►People provided with improved urban living conditions (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 924,414.00 5,000,000.00 11/21/2023 Page 2 of 7 The World Bank Implementation Status & Results Report Local Government COVID-19 Response & Recovery Project (P174937) Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 IN01329058 People provided with improved urban living conditions - Female (RMS requirement) (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 458,389.00 2,500,000.00 (ii) Strengthened urban local governments’ preparedness to future shocks IN01329024 ►Urban local governments with local climate and disaster preparedness plans developed and adopted in a participatory manner (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 240.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 This indicator will monitor the progress on the project’s investment in developing local climate and disaster preparedness plans in all ULGIs. The climate and disaster preparedness planning process will make Comments: citizens aware of local climate and disaster risks, identify actions in place in case of any climate and disaster emergency including ensuring local emergency budget, dedicated officials, roles of civil society and private organization before, during and after disasters, disaster shelters, relief and rescue operations. IN01329057 ►Municipal infrastructure construction or maintenance works that incorporate climate risks under the LGCRRP (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Comments: Measures readiness of ULGI to climate shocks Overall Comments PDO Key results as of October 15, 2023: 365,750 person days of temporary work provided under public work schemes; 924,414 people provided with improved urban living conditions 4; 1,386 Women provided with paid employment under public works schemes; and 639 ULGI officials benefitting from COVID-19 response and recovery specific trainings and technical support Intermediate Results Indicators by Components Component 1: COVID-19 Response Grants IN01329059 ►Public hand-wash and toilets, primary health care clinics rehabilitated, updated, or constructed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 5.00 100.00 11/21/2023 Page 3 of 7 The World Bank Implementation Status & Results Report Local Government COVID-19 Response & Recovery Project (P174937) Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Measures public health related interventions under the project of primary health care centers, public toilets, and hand wash rehabilitated, updated, or constructed to meet additional demand due to COVID crisis with climate proof designs. Comments: 4 public handwashing facilities in Charfasion ULGI and 1 primary public health care center in Fatichari ULGI have been completed as of Oct 15, 2023. IN01329061 ►Length of roads and drains maintained and/or rehabilitated through labor-intensive public works schemes (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 200.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Comments: Measures impact of public works schemes on municipal infrastructure IN01329063 ►ULGIs that undertake interventions on local economic development (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 30-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Comments: Measures local economic development and economic recovery impact of ULGI activities IN01329065 ►ULGIs that implement labor-intensive public works schemes (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Comments: Measures improvement in ULGI capacity to plan and deliver labor-intensive public works schemes IN01329067 ►Women provided with paid employment under public works schemes (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 1,386.00 10,000.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Comments: Measures the number of women who participate in public works schemes supported by the project IN01329068 ►ULGIs that undertake interventions on improving safety of municipal/local markets (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 11/21/2023 Page 4 of 7 The World Bank Implementation Status & Results Report Local Government COVID-19 Response & Recovery Project (P174937) Value 0.00 0.00 0.00 50.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Comments: Measures ULGI support for improving safety of municipal/local markets and local economic development IN01329069 ►Annual CRG utilization rate of participating ULGIs for financing COVID response and recovery plan priorities (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Comments: Utilization rate refers to the ratio of CRG implemented for the identified subprojects Component 2: Implementation and capacity development support, digital technology, and project manage IN01329060 ►ULGI officials benefitting from COVID-19 response and recovery specific trainings and technical support (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 639.00 1,980.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Comments: Measures outreach of project capacity development support IN01329062 ►ULGIs using MIS grant monitoring web-based portal (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 339.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Measures data- based planning and decision-making for COVID-19 response and recovery and MIS for Comments: CRG monitoring and reporting. IN01329064 ►ULGIs that have developed and adopted Own-Source Revenue Improvement Plans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Measures impact of Component 2 support for strengthening ULGI Own Source Revenue administration Comments: and collection IN01329066 ►Number of ULGIs that receive technical training to incorporate climate, disaster and disease outbreak mitigation measures in annual plans and municipal projects (Number, Custom) 11/21/2023 Page 5 of 7 The World Bank Implementation Status & Results Report Local Government COVID-19 Response & Recovery Project (P174937) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 341.00 Date 01-Sep-2022 30-Nov-2022 15-Oct-2023 30-Jun-2026 Measures impact of Component 2 support for improving the understanding of ULGI staff on climate, Comments: disaster and disease outbreak risk and mitigation measures so these can be considered into their annual planning and budgeting exercise Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P174937 IDA-70330 Effective USD 300.00 300.00 0.00 75.11 205.92 27% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P174937 IDA-70330 Effective 24-Feb-2022 07-Aug-2022 14-Aug-2022 30-Jun-2026 31-Dec-2025 Cumulative Disbursements 11/21/2023 Page 6 of 7 The World Bank Implementation Status & Results Report Local Government COVID-19 Response & Recovery Project (P174937) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 11/21/2023 Page 7 of 7