Viet Nam: Investing and Innovating for Grassroots Service Delivery Reform PROJECT Procurement Plan (as of February 20, 2019) 1. Project information: Country: Viet Nam Borrower/Recipient: Socialist Republic of Viet Nam Project Name: Investing and Innovating for Grassroots Service Delivery Reform Project Project ID No: P161283 Project Implementing Agency: MoH and participating provinces 2. Bank’s approval date of the Procurement Plan • Original Plan: at project negotiation. • First Revision: … 3. Date of General Procurement Notice: …. 4. Period covered by this procurement plan: the first 18 months implementation I. Works and Goods and Non-Consultant Services: 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Applicable Category thresholds Applicable (in US$ Remarks thresholds Remarks equivalent (in US$) ) Works RFB through ≥ 20 million – Above US$ 10 Open million International market approach RFB through ≥ 200,000 – Above US$ 10 Open National < 20 million million market approach Request for < 200,000 – None Quotation Direct None No threshold; Same as for Selection meet competitive requirements selection 1 of regulations 7.13-7.15 Goods and Non-Consulting Services RFB through ≥ 3 million – Above US$ 2 Open million International market approach RFB through ≥ 100,000 - Above US$ 2 Open National < 3 million million market approach Request for < 100,000 None Quotation Direct None No threshold; Same as for Selection meet competitive requirements selection of regulations 7.13-7.15 2. Prequalification. Not expected for the works/goods packages. 3. Any Other Special Procurement Arrangements: National procurement procedures as specified under paragraph 5.4 of the Procurement Regulations and the conditions specified in Annex 1 to this Procurement Plan 4. Leased assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. 5. Procurement of second hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable. 6. Hands-on Expanded Implementation Support (HEIS) as specified under paragraph 3.10 and 3.11 of the Procurement Regulations: Not applicable. 7. Procurement packages for Goods (prior and post reviews) with method and Time Schedule Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Bac Can - construction of CHSs in Lowest Ngoc Phai, W_1_BC 440 RFB Post Q3 2020 National Evaluate Quang Bach d Cost commune (Cho Don District) 2 Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Bac Can - Renovation of Lowest W_2_BC 5 CHSs in 286 RFB Post Q2 2020 National Evaluate Ngan Son d Cost District Bac Can - Lowest Renovation of W_3_BC 158 RFQ Post Q3 2020 National Evaluate 3 CHSs in Na d Cost Ri District Ha Giang - construction of CHSs in Lowest W_1_H Ngam La, 704 RFB Post Q3 2020 National Evaluate G Sung Thai d Cost (Yen Minh District) Ha Giang - - Lowest W_2_H Renovation of 440 RFB Post Q2 2020 National Evaluate G 5 CHSs in Meo d Cost Vac District Ha Giang - - Renovation of Lowest W_3_H 3 CHSs in 528 RFB Post Q3 2020 National Evaluate G Quan Ba d Cost District Son La - construction Lowest W_1_SL of 4 CHSs in 880 RFB Post Q2 2020 National Evaluate Thuan Chau d Cost District Son La - construction Lowest W_2_SL of 4 CHSs in 880 RFB Post Q3 2020 National Evaluate Luc Yen d Cost District Yen Bai- construction of CHSs in Lowest Lang Nhi, Ta W_1_YB 540 RFB Post Q3 2020 National Evaluate Xi Lang d Cost communes (Tram Tau District) Yen Bai - Lowest Renovation of W_2_YB 265 RFB Post Q2 2020 National Evaluate 4 CHSs in Yen d Cost Binh District Yen Bai - Lowest Renovation of W_3_YB 735 RFB Post Q3 2020 National Evaluate 4 CHSs in Luc d Cost Yen District 3 Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Hoa Binh - construction of CHS in Tan Lowest W_1_HB Son 364 RFB Post Q3 2020 National Evaluate Commune in d Cost Mai Chau District Hoa Binh - Lowest Renovation of W_2_HB 440 RFB Post Q2 2020 National Evaluate 3 CHSs in Mai d Cost Chau District Hoa Binh - Lowest Renovation of W_3_HB 295 RFB Post Q3 2020 National Evaluate 3 CHSs in Da d Cost Bac District Quang Binh - construction of 2 CHSs in Lowest W_1_Q Tan Trach, 140 RFQ Post Q3 2020 National Evaluate B Thuong Trach d Cost communes in Bo Trach District Quang Binh - Renovation of Lowest W_2_Q 4 CHSs in 194 RFQ Post Q2 2020 National Evaluate B Quang Ninh d Cost District Quang Binh - Renovation of Lowest W_3_Q 3 CHSs in 195 RFQ Post Q3 2020 National Evaluate B Quang Trach d Cost District Quang Tri - construction of 2 CHSs in Lowest Cam Tuyen, W_1_QT 300 RFB Post Q3 2020 National Evaluate Cam Chinh d Cost communes in Cam Lo District Quang Tri - Renovation of Lowest W_3_QT 3 CHSs in 466 RFB Post Q2 2020 National Evaluate Vinh Linh d Cost District Quang Ngai - construction Lowest W_1_Q of 3 CHSs in 660 RFB Post Q2 2020 National Evaluate B Binh Son d Cost District 4 Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Quang Ngai - Renovation of Lowest W_1_Q 3 CHSs in 352 RFB Post Q2 2020 National Evaluate N Quang Ninh d Cost District Quang Ngai - Lowest W_2_Q Renovation of 264 RFB Post Q3 2020 National Evaluate N 3 CHSs in Tra d Cost Bong District Ninh Thuan - construction of CHS in Lowest W_1_NT Phuong Hai 119 RFQ Post Q3 2020 National Evaluate communes in d Cost Ninh Hai District Ninh Thuan - Renovation of Lowest W_2_NT 4 CHSs in 185 RFQ Post Q2 2020 National Evaluate Thuan Nam d Cost District Bac Lieu - construction of CHS in Lowest Long Dien W_1_BL 264 RFB Post Q3 2020 National Evaluate Dong A d Cost commune in Dong Hai District Bac Lieu - Lowest Renovation of W_2_BL 132 RFQ Post Q2 2021 National Evaluate 2 CHSs in Hoa d Cost Binh District Tra Vinh - construction of 2 CHSs in Lowest W_1_TV Ham Giang, 380 RFB Post Q2 2020 National Evaluate Kim Son d Cost communes in Tra Cu District Tra Vinh - Lowest Renovation of W_2_TV 332 RFB Post Q2 2020 National Evaluate 4 CHSs in Cau d Cost Ngang District Hau Giang - construction Lowest W_1_H of CHS in Mai 704 RFB Post Q3 2020 National Evaluate G Dam town in d Cost Chau Thanh District 5 Works Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Works by provinces A Component 1 - Construction/Renovations of CHS/DHC Hau Giang - Renovation of Lowest W_2_H 4 CHSs in 372 RFB Post Q2 2020 National Evaluate G Long My d Cost District Long An - construction Lowest W_1_LA of 3 CHSs in 572 RFB Post Q2 2020 National Evaluate Tan Hung d Cost District Long An - Lowest Renovation of W_2_LA 334 RFB Post Q2 2020 National Evaluate 4 CHSs in Moc d Cost Hoa District Long An - Lowest Renovation of W_3_LA 202 RFB Post Q3 2020 National Evaluate 3 CHSs in Ben d Cost Luc District Total Works 12,758 Goods Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Goods by provinces B Component 2 GeneXpert equipment Ha Giang - G_1_HG GeneXpert 34.29 DS Post Q3 2020 DS NA equipment Ye Bai - 34.29 G_1_YB GeneXpert DS Post Q3 2020 DS NA equipment Hoa Binh - 68.57 G_1_HB GeneXpert DS Post Q3 2020 DS NA equipment Quang Binh - 102.86 G_1_QB GeneXpert DS Post Q3 2020 DS NA equipment Quang Tri - 102.86 G_1_QT GeneXpert DS Post Q3 2020 DS NA equipment Quang Ngai - 205.71 G_1_QN GeneXpert DS Post Q3 2020 DS NA equipment 6 Goods Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Goods by provinces B Component 2 Ninh Thuan - 137.14 G_1_NT GeneXpert DS Post Q3 2020 DS NA equipment Bac Lieu - 102.86 G_1_BL GeneXpert DS Post Q3 2020 DS NA equipment Tra Vinh - 137.14 G_1_TV GeneXpert DS Post Q3 2020 DS NA equipment Hau Giang - G_1_Hu 68.57 GeneXpert DS Post Q3 2020 DS NA G equipment Long An - 205.71 G_1_LA GeneXpert DS Post Q3 2020 DS NA equipment Total GE 1,200 Vaccine Cold Chain equipment Bac Can - 77.89 G_2_BC Vaccine Cold DS Post Q3 2020 DS NA Chain Ha Giang - 168.38 G_2_HG Vaccine Cold DS Post Q3 2020 DS NA Chain Son La - 148.91 G_2_SL Vaccine Cold DS Post Q3 2020 DS NA Chain Yen Bai - 103.09 G_2_YB Vaccine Cold DS Post Q3 2020 DS NA Chain Hoa Binh - 126.00 G_2_HB Vaccine Cold DS Post Q3 2020 DS NA Chain Quang Binh - 68.73 G_2_QB Vaccine Cold DS Post Q3 2020 DS NA Chain Quang Tri - 59.56 G_2_QT Vaccine Cold DS Post Q3 2020 DS NA Chain Quang Ngai - 95.07 G_2_QN Vaccine Cold DS Post Q3 2020 DS NA Chain Ninh Thuan - 27.49 G_2_NT Vaccine Cold DS Post Q3 2020 DS NA Chain Bac Lieu - 27.49 G_2_BL Vaccine Cold DS Post Q3 2020 DS NA Chain Tra Vinh - 45.82 G_2_TV Vaccine Cold DS Post Q3 2020 DS NA Chain 7 Goods Estimat Expecte Contract Revie Market Evaluati Ref. ed Cost Procureme d bid (Description w by approa on No. (US$10 nt Method opening ) Bank ch Method 00) time Goods by provinces B Component 2 Hau Giang - G_2_Hu 13.75 Vaccine Cold DS Post Q3 2020 DS NA G Chain Long An - 37.80 G_2_LA Vaccine Cold DS Post Q3 2020 DS NA Chain Total VCC 1,000 DS Post Q3 2020 DS NA Total Works and 14,958 Goods 8 II. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II of the Procurement Regulations: Procurement Method Prior Review Thresholds Thresholds Applicable Category Applicable thresholds thresholds (in US$ Remarks Remarks (in US$, equivalent millions) ) QCBS, QBS, ≥ 300,000 Shortlist of only ≥ 1.0 million FBS, LCS National (Using the Consultants most (Firms) for appropriate contract agreed market in the PP approach) CQS (Open or < 300,000 QCBS, QBS, FBS, None limited LCS) can be competition applied for through contracts with national or value under international $300,000 market approach, specified in the PP and agreed with the Bank. Direct None No threshold; Same as for Selection of meet competitive firms requirements of selection regulations 7.13- 7.15 Individual N/A Essential ≥ 300,000 depending individual and for the Consultants on nature of assignments will positions as services be defined in the specified in Procurement the PP agreed Plan agreed with with the Bank the Bank and in line with regulations 7.34- 7.39 using the most appropriate market approach 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 500,000 equivalent per contract, may comprise entirely of national consultants in 9 accordance with the provisions of paragraph 7.1, Section VII of the Procurement Regulations. 3. Consultancy Assignments with Selection Methods and Time Schedule Consulting Services Expecte Estimate Selecti d Revie Market Ref. Description of d Cost on Proposa Remar w by approa No. Assignment (US$ Metho l k Bank ch 1000) d Submiss ion Time B. Component 2 Post Training need assessment, development 12 and revisions of C_2b_ Nationa months professional 24 IC Post Q1 2020 1 l in 3 and years management training material C_2b_ IEC and Health Nationa 200 CQS Post Q1 2020 1 promotion l Development of the Balanced 6 C_2c_ Score cards - Nationa months 12 IC Post Q1 2020 1 health l in 1 system/public year health expert Development of 6 C_2c_ the Balanced Nationa months 12 IC Post Q1 2020 2 Score cards - l in 1 clinical expert year C. Component 3 Development of decree on functions and responsibilities of District 5 man- C_3a_ Health Center Nationa months 25 CQS/IC Post Q2 2020 1 (that cover l in a Regional clinic year and CHS) for primary health care at grassroot level Evidence for tracer conditions in the project to 5 man- C_3a_ provide inputs Nationa months 25 CQS/IC Post Q2 2020 2 for l in a development of year guidelines for Primary Healthcare at 10 commune level (to replace Decision 2919/QD-BYT International Experience on e-learning for continuous training, to 3 man- C_3a_ provide inputs Nationa months 15 CQS/IC Post Q3 2020 3 for the l in 6 development of months new decree replacing decree 22/2013/TT-BYT Development and supervision of the implementation 36 of electronic man- C_3b_ health record Nationa 500 QCBS Post Q3 2020 month 1 module at l in 5 commune level years (trans district- commune), balanced score card software Design and pilot C_3b_ implementation Nationa 25 CQS/IC Post Q2 2021 2 of community l health screening Design and C_3b_ implementation Nationa 6 25 CQS/IC Post Q4 2020 3 of tools for l months clinical decision C_3b_ Nationa 6 Quality service 25 CQS/IC Post Q2 2021 4 l months C_3d_ Auditing Nationa 50 CQS Post Q2 2021 1 Service l C_3d_ Nationa Coordinator 36 IC Post Q1 2020 2 l C_3d_ Nationa Planning Expert 27 IC Post Q1 2021 3 l C_3d_ Disbursement Nationa 27 IC Post Q1 2022 4 Expert l C_3d_ Nationa FM expert 27 IC Post Q1 2023 5 l C_3d_ Procurement Nationa 27 IC Post Q1 2024 6 Expert l Total consulting services 1,082 Total Works, Goods and Consulting 16,040 Services 11 12 Annex 1 - Additional National Procurement Provisions. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 1. Open Competitive Procurement: When the Recipient uses its own national open competitive procurement arrangements as set forth in (a) Article 20 on Open Bidding of the Recipient’s Law on Procurement No. 43/2013/QH13 dated November 26, 2013 and related provisions necessary to effect the same; and (b) the Recipient’s Decree No. 63/2014/ND-CP dated June 26, 2014 Guiding Implementation of the Law on the Procurement (collectively, “National Procurement Laws”), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (i) No domestic preference over foreign bidders shall be granted to national bidders in bid evaluation, nor shall foreign bidders be asked or required to form joint ventures with or be subcontractors to national bidders in order to submit a bid. (ii) The model bidding documents (harmonized model bidding documents) agreed with the Association shall be used. (iii) No bid shall be eliminated from detailed evaluation on the basis of minor, non-substantive deviations. The evaluation of bidder’s qualifications shall be conducted separately subsequent to the technical and commercial evaluation of the bid. (iv) A bidder shall neither be required nor permitted, as a condition for award, to undertake obligations not specified in the bidding documents or otherwise to modify the bid as originally submitted. (v) No bid shall be rejected on the basis of a comparison with the employer’s estimate and budget ceiling. (vi) The Recipient shall implement an effective mechanism allowing bidders to complaint and have their complaints handled in a timely manner. The complaints mechanism shall allow the submission of anonymous complaints. 13 PROCUREMENT Viet Nam : Investing and Innovating for Grassroots Health Service Delivery PLAN General Information Country: Viet Nam 2021-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-11-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161283 GPN Date: 2020-09-14 Project Name: Investing and Innovating for Grassroots Health Service Delivery Loan / Credit No: IDA / 64390 Quang Ngai Provincial Project Management Unit for GSD Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned QN-C1-XL1 / Construction: R epairing medical station in B National Procure a Xa commune, Ba To district ment Document - Component 1: Upgrading of Single Stage - One E Under Imple 2022-02-2 ; New construction of Long Hi IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 325,514.00 0.00 2021-06-01 2021-06-18 2021-06-18 2021-07-19 2021-07-19 2021-08-18 2021-08-31 2021-09-01 CHS Infrastructure nvelope mentation 8 ep commune medical station ss (Non Bank-SPD , Repair of Long Son commun ) e health station, Minh Long d istrict National Procure QN-C1-XL2 / Repairing com ment Document - mune health stations: Binh H Component 1: Upgrading of Single Stage - One E Under Imple 2022-02-2 IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 626,460.00 0.00 2021-06-01 2021-06-18 2021-06-18 2021-07-19 2021-07-19 2021-08-18 2021-09-01 oa, Binh Nguyen, Binh An, Bi CHS Infrastructure nvelope mentation 8 ss (Non Bank-SPD nh Chau, Binh Son district ) QN-C1-XL3 / Repairing the m National Procure edical station of Tra Phu com ment Document - Component 1: Upgrading of Single Stage - One E Under Imple 2022-02-2 mune, Tra Lam, and building IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 377,747.00 0.00 2021-06-01 2021-06-18 2021-06-18 2021-07-19 2021-07-19 2021-08-18 2021-08-31 2021-09-01 CHS Infrastructure nvelope mentation 8 a new medical station in Tra ss (Non Bank-SPD Giang commune, Tra Bong di ) strict QN-C1-XL4 / Repairing medi cal stations of Tinh Ha, Tinh National Procure Hiep, Tinh Minh communes, ment Document - Son Tinh district; Repairing t Component 1: Upgrading of Single Stage - One E Under Imple 2022-02-2 IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 674,776.00 0.00 2021-06-01 2021-06-18 2021-06-18 2021-07-19 2021-07-19 2021-08-18 2021-09-01 he medical stations of Tinh C CHS Infrastructure nvelope mentation 8 ss (Non Bank-SPD hau commune, Tinh Hoa, Qu ) ang Ngai city; to build a new medical station in Nghia Tha ng commune, Tu Nghia distri ct QN-C1-XL5 / Thi công xây dự National Procure ng: cải tạo sửa chữa 07 Trạm ment Document - Y tế xã Sơn Liên, Sơn Lập, S Component 1: Upgrading of Single Stage - One E Under Imple 2023-02-2 IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 841,872.00 0.00 2022-06-20 2022-08-02 2022-06-25 2022-07-26 2022-09-05 2022-08-09 2022-09-30 2022-08-24 ơn Long, Sơn Màu, Sơn Mùa, CHS Infrastructure nvelope mentation 0 ss (Non Bank-SPD Sơn Tân, Sơn Tinh huyện Sơn ) Tây; Xây mới 01 Trạm Y tế xã Tịnh Bình huyện Sơn Tịnh QN-CL-XL6 / Thi công xây dự National Procure ng: cải tạo sửa chữa 03 Trạm ment Document - Y tế xã Ba Động, Ba Vinh huy Component 1: Upgrading of Single Stage - One E Under Imple 2023-02-2 IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 434,088.00 0.00 2022-06-20 2022-08-03 2022-06-25 2022-07-26 2022-09-05 2022-08-09 2022-09-19 2022-08-24 ện Ba Tơ và Trạm Y tế xã Tịn CHS Infrastructure nvelope mentation 0 ss (Non Bank-SPD h Đông huyện Sơn Tịnh; Xây ) dựng mới 01 Trạm Y tế xã Ba Nam huyện Ba Tơ QN-CL-XL7 / Thi công xây dự ng: cải tạo sửa chữa 02 Trạm National Procure Y tế xã Tịnh Khê Tp Quảng N ment Document - Component 1: Upgrading of Single Stage - One E Under Imple 2023-02-2 gãi, Trạm Y tế xã Bình Chánh IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 813,268.00 0.00 2022-06-20 2022-08-03 2022-06-25 2022-07-26 2022-09-05 2022-08-09 2022-09-30 2022-08-24 CHS Infrastructure nvelope mentation 0 huyện Bình Sơn; Xây dựng m ss (Non Bank-SPD ới 03 Trạm Y tế xã Trà Bình, ) xã Trà Thủy, Thị trấn Trà Xuâ n huyện Trà Bồng QN-CL-XL8 / Thi cong xay du National Procure ng: cai tao sua chua 05 Tram ment Document - Component 1: Upgrading of Single Stage - One E Pending Imp 2024-02-1 y te xa Binh Duong, Binh Min IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 604,624.00 0.00 2023-06-20 2023-06-25 2023-07-25 2023-08-09 2023-08-19 CHS Infrastructure nvelope lementation 5 h, Binh My, Binh Thuan, Binh ss (Non Bank-SPD Thanh huyen Binh Son ) QN-CL-XL9 / Thi cong xay du ng: cai tao sua chua 02 Tram National Procure y te xa Nghia Hiep, Nghia My ment Document - Component 1: Upgrading of Single Stage - One E Pending Imp 2024-02-1 huyen Tu Nghia va 02 Tram y IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 758,881.00 0.00 2023-06-20 2023-06-25 2023-07-25 2023-08-09 2023-08-19 CHS Infrastructure nvelope lementation 5 te xa Duc Chanh, Duc Lan hu ss (Non Bank-SPD yen Mo Duc; Xay dung moi 0 ) 1 Tram Y te xa Pho Chau thi xa Duc Pho QN-CL-XL10 / Thi cong xay d National Procure ung: cai tao sua chua 02 Tra ment Document - m y te xa Huong Tra, Tra Pho Component 1: Upgrading of Single Stage - One E Pending Imp 2024-02-1 IDA / 64390 Post Request for Bids Open - National 1 Envelope proce 755,617.00 0.00 2023-06-20 2023-06-25 2023-07-25 2023-08-09 2023-08-19 ng huyen Tra Bong; Xay dun CHS Infrastructure nvelope lementation 5 ss (Non Bank-SPD g moi 01 Tram Y te xa Tra Bu ) i huyen Tra Bong và 01 Tram Y te xa Nghia Dien huyen Tu Nghia GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Improving the QN-TB-MS2 / Supply of medi Single Stage - One E Pending Impl IDA / 64390 Readiness of CHS to Manage Post Request for Bids Open - National 457,007.00 0.00 2022-12-20 2022-12-25 2023-02-03 2023-03-05 2023-03-19 2023-06-17 cal equipment (phase 1) nvelope ementation Tracer Conditions Component 2: Improving the QN-TB-MS3 / Supply of medi Single Stage - One E Pending Impl IDA / 64390 Readiness of CHS to Manage Post Request for Bids Open - National 716,254.00 0.00 2023-10-10 2023-10-15 2023-11-15 2023-11-30 2023-12-14 2024-04-12 cal equipment (phase 2) nvelope ementation Tracer Conditions Component 2: Improving the QN-TB-MS1 / Supply of office Single Stage - One E IDA / 64390 Readiness of CHS to Manage Post Request for Bids Open - National 462,328.00 0.00 Canceled 2022-10-27 2022-11-01 2022-12-01 2022-12-08 2022-12-15 2023-02-13 equipment nvelope Tracer Conditions QN-TB-MS1.1 / Purchasing of Component 2: Improving the Single Stage - One E Pending Impl fice equipment - Computer a IDA / 64390 Readiness of CHS to Manage Post Request for Bids Open - National 116,758.00 0.00 2023-12-25 2023-12-30 2024-01-30 2024-02-29 2024-04-04 2024-07-03 nvelope ementation nd printer group Tracer Conditions Page 1 QN-TB-MS1.2 / Procurement of office equipment - Equipm Component 2: Improving the Single Stage - One E Pending Impl ent group in the field of Elect IDA / 64390 Readiness of CHS to Manage Post Request for Bids Open - National 188,117.00 0.00 2023-12-25 2023-12-30 2024-01-30 2024-02-29 2024-04-04 2024-07-03 nvelope ementation rical and Electronics: TVs, sp Tracer Conditions eakers, Air conditioners and Dehumidifiers QN-TB-MS1.3 / Purchasing of fice equipment - Equipment group in the field of office su Component 2: Improving the pplies: Media document cabi Single Stage - One E Pending Impl IDA / 64390 Readiness of CHS to Manage Post Request for Bids Open - National 190,564.00 0.00 2023-12-25 2023-12-30 2024-01-30 2024-02-29 2024-04-04 2024-07-03 nets, File racks, Meeting roo nvelope ementation Tracer Conditions m tables and chairs, Domesti c waste bins, Medical waste bins , Hazardous waste bin, S tainless steel swivel stool, Me dical waitin NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2