PROCUREMENT PLAN (Textual Part) Project information: [country]Sri Lanka Primary Healthcare System Strengthening Project[Project name] [P- number] (PSSP) P163721 Project Implementation agency: [insert legal name]Ministry of Health, Nutrition and Indigenous Medicine Date of the Procurement Plan: [insert date]01 May 2018 Period covered by this Procurement Plan: 1[insert from – to period]May 2018 to 30 November 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Sri Lanka : Sri Lanka: Primary Health Care System Strengthening Project PLAN General Information Country: Sri Lanka 2018-12-21 Bank’s Approval Date of the Original Procurement Plan: 2023-11-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163721 GPN Date: 2020-07-28 Project Name: Sri Lanka: Primary Health Care System Strengthening Project Loan / Credit No: IBRD / 88780 Ministry of Health, Nutrition and Indigenous Medicine Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LK-MHNIM-100651-CW-RFQ / partitioning, modification for Project Implementation Sup Request for Quota Single Stage - One E 2019-05-1 IBRD / 88780 Post Limited 22,580.00 16,088.12 Completed 2019-02-20 2019-02-27 2019-04-03 2019-04-28 a dining room and a toilet for port and Innovation Grants tions nvelope 8 new office space of PSSP LK-MHNIM-219048-CW-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 2021-11-2 Improvements for patients a IBRD / 88780 Post Limited 15,800.00 10,993.17 Completed 2021-03-30 2021-07-01 2021-05-25 2021-08-17 port and Innovation Grants tions nvelope 1 nd staff access at new PMCU pallewela LK-MHNIM-252240-CW-RFB / Request for Bids - Construction and Installation Project Implementation Sup Single Stage - One E Small Works SPD 2022-07-2 IBRD / 88780 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2021-10-01 2021-11-30 2021-10-06 2021-12-01 2021-11-17 2021-12-17 2022-01-21 of 26 Nos of Air Conditioned port and Innovation Grants nvelope (1 envelope proce 0 Cargo Drug Stores with Solar ss) Power GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MHNIM-93182-GO-RFQ / P rocurement of 05 Nos Laptop Project Implementation Sup Request for Quota Single Stage - One E s, 04 Nos Desk Tops, 01 No H IBRD / 88780 Post Limited 12,903.00 12,002.80 Completed 2019-01-02 2018-11-30 2019-02-20 2019-01-26 2019-03-06 2019-08-15 port and Innovation Grants tions nvelope eavy Duty Multi-function Co pier and 01 No Laser-jet Colo ur Printer LK-MHNIM-106319-GO-RFQ / Print and Supply 1300 Nos M Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 5,714.00 3,006.21 Completed 2019-04-05 2019-04-10 2019-05-31 2019-05-04 2019-06-30 2019-06-11 anuals of Operational Guide port and Innovation Grants tions nvelope Line and Essential Service Pa ckage with Docket LK-MHNIM-128666-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 5,714.00 55.82 Completed 2019-09-01 2019-09-17 2019-10-27 2019-11-09 2020-04-24 2019-11-11 Office Furniture and Equipme port and Innovation Grants tions nvelope nt LK-MHNIM-128685-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Supply Installation and com IBRD / 88780 Post Limited 3,428.00 856.04 Completed 2019-09-04 2019-09-17 2019-10-30 2019-12-29 2020-04-27 2020-01-21 port and Innovation Grants tions nvelope missioning of A/C Plant and P ABX System LK-MHNIM-128983-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 2,857.00 1,390.92 Completed 2019-09-09 2019-10-31 2019-11-04 2019-12-28 2020-05-02 2020-03-17 02 Nos Laptops port and Innovation Grants tions nvelope LK-MHNIM-143692-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 1,666.70 1,639.30 Completed 2019-11-09 2019-10-30 2020-01-04 2019-12-27 2020-07-02 2020-01-16 300 Nos Pen Drives port and Innovation Grants tions nvelope LK-MHNIM-143702-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 555.55 0.00 Canceled 2019-11-11 2020-01-06 2020-07-04 Accounting Software Packag port and Innovation Grants tions nvelope e LK-MHNIM-106305-GO-RFQ / Equipment and Technologies Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 28,571.00 0.00 Canceled 2019-05-05 2019-06-30 2019-08-29 for Mobile Registration and S port and Innovation Grants tions nvelope creening of Population for ad vocacy of PSSP LK-MHNIM-106316-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Design, Make and supply of 6 IBRD / 88780 Post Limited 5,714.00 0.00 Canceled 2019-04-05 2019-05-31 2019-06-30 port and Innovation Grants tions nvelope 3 Nos Display Boards for Hos pitals LK-MHNIM-125522-GO-RFB / Supply Installation Commissi Project Implementation Sup Single Stage - One E IBRD / 88780 Post Request for Bids Limited 56,200.00 0.00 Canceled 2019-08-31 2019-09-05 2019-10-17 2019-11-16 2019-12-21 2020-06-18 oning and maintenance of Di port and Innovation Grants nvelope gital Signage System for 60 Hospitals LK-MHNIM-106268-GO-RFB / Design, Supply Installation, C Project Implementation Sup Single Stage - Two E ommissioning and maintain o IBRD / 88780 Post Request for Bids Open - National 114,286.00 0.00 Canceled 2019-05-07 2019-05-12 2019-06-23 2019-09-05 2019-10-10 2020-04-07 port and Innovation Grants nvelope f Video Conference System f or 10 Institutions in Sri Lanka LK-MHNIM-106285-GO-RFP / Project Implementation Sup Single Stage - Two E Design, Built, Implement and IBRD / 88780 Post Request for Bids Limited 114,285.00 0.00 Canceled 2020-01-22 2020-01-27 2020-03-09 2020-05-22 2020-06-26 2020-12-23 port and Innovation Grants nvelope Maintain Mobile Exhibition Un it for PSSP LK-MHNIM-153616-GO-RFB / Supply, Installation, Commiss Project Implementation Sup Single Stage - One E IBRD / 88780 Post Request for Bids Open - National 550,000.00 382,847.71 Signed 2020-03-25 2020-12-01 2020-03-30 2020-12-14 2020-05-11 2021-01-05 2020-06-10 2021-01-18 2020-07-15 2021-05-19 2021-01-11 ioning and maintenance of D port and Innovation Grants nvelope igital Signage System for 600 Hospitals LK-MHNIM-218211-GO-RFQ / Procurement of IT equipment for mobile communication ga lary and for initiation of Digit Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 27,778.00 15,439.46 Signed 2021-03-30 2021-06-22 2021-05-25 2021-08-06 2021-11-21 al Health Information system port and Innovation Grants tions nvelope in PMCII located in hard to re ach/disadvantaged areas pre ferably 10 POS kits with a bar code sticker printer & small l azer printer LK-MHNIM-219039-GO-RFQ / Supply and Installation of of Project Implementation Sup Request for Quota Single Stage - One E 3 Nos AC (24000 BTU) machi IBRD / 88780 Post Limited 7,900.00 956.37 Signed 2021-05-15 2021-10-09 2021-07-10 2021-10-30 2022-01-06 port and Innovation Grants tions nvelope nes to the new clinic building of t he PMCU- Pallewela Page 1 LK-MHNIM-219041-GO-RFQ / Essential bio-medical equipm ent for the ETU, OPD and Clin Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 27,778.00 16,963.63 Completed 2021-05-15 2021-06-22 2021-07-10 2021-08-06 2022-01-06 2021-12-12 ics including Autoclave, Dent port and Innovation Grants tions nvelope al Chair units, Examination B eds, Multipara monitor, ETU beds, Sport lamps, suckers et c LK-MHNIM-218212-GO-RFQ / 04 Nos Point of care Equipme Project Implementation Sup Request for Quota Single Stage - One E nt (1 for mobile communicati IBRD / 88780 Post Limited 49,500.00 25,160.48 Completed 2021-05-15 2021-07-30 2021-07-10 2021-10-19 2022-01-06 2021-12-15 port and Innovation Grants tions nvelope on galary and other 03 for se lected PMCIi in hard to reach areas. LK-MHNIM-219046-GO-RFQ / Essential furniture items for t Project Implementation Sup Request for Quota Single Stage - One E he new building of PMCU at P IBRD / 88780 Post Limited 15,800.00 12,982.44 Completed 2021-05-15 2021-08-09 2021-07-10 2021-09-28 2022-01-06 2021-12-05 port and Innovation Grants tions nvelope allewela – ( Furniture for ETU, clinics and OPD- Chairs, cupb oards, racks, tables etc.) LK-MHNIM-247224-GO-RFQ / Implementation of the PHC S Request for Quota Single Stage - One E 100,000 Nos of Gel Tube -3 IBRD / 88780 ystem Reorganization and St Post Limited 7,500.00 8,640.28 Signed 2021-08-30 2021-09-22 2021-10-25 2021-12-16 2022-04-23 tions nvelope ml (SL-GEL Clot Activator wit rengthening Strategies h Gel) LK-MHNIM-247728-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 01 No Refrigerator and 01 No IBRD / 88780 Post Limited 1,500.00 449.49 Completed 2021-08-30 2021-10-05 2021-10-25 2021-11-09 2022-04-23 2021-11-12 port and Innovation Grants tions nvelope . Electric Kettle for Pallewela PMCU. LK-MHNIM-252250-GO-RFB / Design supply and delivery o Project Implementation Sup Single Stage - One E f 1,000,000 Nos of Small Plas IBRD / 88780 Post Request for Bids Open - National 150,000.00 0.00 Canceled 2021-10-01 2021-11-08 2021-10-06 2021-11-24 2021-11-17 2021-12-17 2022-01-21 2022-07-20 port and Innovation Grants nvelope tic Containers for Medicinal t ablets with specially design li d LK-MHNIM-263323-GO-RFQ / Still Camera and Accessories, Graphic & Photo Editing Mac Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 45,000.00 0.00 Canceled 2021-12-07 2022-02-01 2022-07-31 hine with Accessories, Video port and Innovation Grants tions nvelope Camera and Accessories and Video Editing Machine with a ccessories LK-MHNIM-356112-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Pending Impl 40,000,000 Nos of Chlorphen IBRD / 88780 Post Limited 34,000.00 0.00 2023-05-02 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope ementation amine Tab. 4mg(Chlorphenir amines) LK-MHNIM-356122-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Under Imple 10,000,000 Nos of Amitriptyli IBRD / 88780 Post Limited 20,000.00 0.00 2023-05-02 2023-08-04 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope mentation ne Tab. 25mg LK-MHNIM-356126-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Pending Impl 20,950,000 Nos of Hydrochlo IBRD / 88780 Post Limited 30,000.00 0.00 2023-05-02 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope ementation rothiazide Tab.25mg LK-MHNIM-356137-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Under Imple 6,000,000 Nos of Thyroxine IBRD / 88780 Post Limited 33,400.00 0.00 2023-05-02 2023-08-04 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope mentation Tab. 100mcg LK-MHNIM-356177-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Under Imple IBRD / 88780 Post Limited 13,500.00 0.00 2023-05-02 2023-06-26 2023-06-27 2023-12-24 2,000 Packs of Zinc oxide- eu port and Innovation Grants tions nvelope mentation genol LK-MHNIM-356193-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 750 Packs of Composite fillin IBRD / 88780 Post Limited 41,500.00 0.00 Completed 2023-05-02 2023-06-26 2023-06-27 2023-08-15 2023-12-24 port and Innovation Grants tions nvelope g material with four syringes LK-MHNIM-356174-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 1000 Packs of Glass Ionomer IBRD / 88780 Post Limited 23,200.00 0.00 Signed 2023-06-14 2023-06-26 2023-08-09 2023-09-01 2024-02-05 port and Innovation Grants tions nvelope dental filling material for pos terior teeth LK-MHNIM-356117-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 4,000,000 Nos of Sodium Val IBRD / 88780 Post Limited 32,000.00 0.00 Canceled 2023-05-02 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope proate Tab. 100mg LK-MHNIM-356168-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 500 Packs of Glass Ionomer d IBRD / 88780 Post Limited 11,600.00 0.00 Canceled 2023-06-14 2023-06-26 2023-08-09 2024-02-05 port and Innovation Grants tions nvelope ental filling material for anter ior teeth LK-MHNIM-356130-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 82,500 Nos of Salbutamol Re IBRD / 88780 Post Limited 15,300.00 0.00 Canceled 2023-05-02 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope spiratory Sol.0.5%,15mL Vial LK-MHNIM-356107-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 25,000,000 Nos of Nifedipine IBRD / 88780 Post Limited 41,000.00 0.00 Canceled 2023-05-02 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope ER Tab.20mg LK-MHNIM-356128-GO-RFQ / 3,500,000 Nos of Beclometha Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 30,000.00 0.00 Canceled 2023-05-02 2023-06-27 2023-12-24 sone DP Caps port and Innovation Grants tions nvelope 200mcg LK-MHNIM-356104-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 3,500,000 Nos of Fluoxetine IBRD / 88780 Post Limited 18,000.00 0.00 Canceled 2023-05-03 2023-06-28 2023-12-25 port and Innovation Grants tions nvelope HCI Cap.20mg LK-MHNIM-356114-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 4,000,000 Nos of Olanzapine IBRD / 88780 Post Limited 11,000.00 0.00 Canceled 2023-05-02 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope Tab.10mg LK-MHNIM-356123-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 17,000.00 0.00 Canceled 2023-05-02 2023-06-27 2023-12-24 7,500,000 Nos of Atenolol Ta port and Innovation Grants tions nvelope b. 50 mg LK-MHNIM-356110-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 21,000,000 Nos of Salbutam IBRD / 88780 Post Limited 26,000.00 0.00 Canceled 2023-05-02 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope ol Tab 2mg LK-MHNIM-356108-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E 3,000,000 Nos of Propranolol IBRD / 88780 Post Limited 5,100.00 0.00 Canceled 2023-05-02 2023-06-27 2023-12-24 port and Innovation Grants tions nvelope Tab. 40 mg NON CONSULTING SERVICES Page 2 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MHNIM-93929-NC-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Hire of Vehicles for Project Di IBRD / 88780 Post Limited 27,067.00 1,947.76 Signed 2019-01-13 2019-01-08 2019-03-10 2019-03-01 2020-03-04 port and Innovation Grants tions nvelope rector and Office staff transp ort LK-MHNIM-120909-NC-RFQ / Service of Instructional Desig n, Development and deploym Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 28,571.00 11,528.36 Completed 2019-07-01 2019-07-22 2019-08-14 2019-09-29 2019-09-18 2020-05-12 ent of E-learning Material for port and Innovation Grants tions nvelope Health Capacity Building for Primary Healthcare Strength ening LK-MHNIM-106298-NC-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Production of Short Promotio IBRD / 88780 Post Limited 5,714.00 0.00 Canceled 2019-04-10 2019-06-05 2019-08-04 port and Innovation Grants tions nvelope nal Video for PSSP LK-MHNIM-231252-NC-RFQ / Develop, Designing, Producti on, Storage, Transportation Project Implementation Sup Request for Quota Single Stage - One E & Maintenance of Portable St IBRD / 88780 Post Limited 49,500.00 0.00 Canceled 2021-05-15 2021-07-10 2022-01-06 port and Innovation Grants tions nvelope alls including canopy & partit ioning panel, Portable chairs & Tables, LED/Digital screen, Generator and Sound system LK-MHNIM-218210-NC-RFQ / Development of 5 short Vide o Clips for the promotion of P Project Implementation Sup Request for Quota Single Stage - One E IBRD / 88780 Post Limited 31,580.00 16,257.89 Signed 2021-05-15 2021-11-08 2021-07-10 2022-05-01 2022-01-06 rimary Healthcare reorganisa port and Innovation Grants tions nvelope tion activities through the mo bile communication gallery. LK-MHNIM-259170-NC-RFQ / Selection of two service provi Project Implementation Sup Request for Quota Single Stage - One E ders for training of selected h IBRD / 88780 Post Limited 37,500.00 0.00 Canceled 2021-11-15 2022-01-10 2022-07-09 port and Innovation Grants tions nvelope ealth staff on creative comm unication in Sinhala & Tamil medium. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MHNIM-86114-CS-QCBS / Project Implementation Sup Quality And Cost- Selection of a Consultant for IBRD / 88780 Post Open - National 350,000.00 488,679.99 Signed 2018-12-25 2018-12-19 2019-01-15 2019-02-12 2019-03-14 2019-03-14 2019-03-12 2019-03-28 2019-03-14 2019-04-14 2019-04-30 2019-05-05 2019-06-18 2023-12-30 port and Innovation Grants Based Selection Third Party Verification of DLI Achievements LK-MHNIM-93923-CS-QCBS / Project Implementation Sup Quality And Cost- Consultancy for Developing IBRD / 88780 Post Open - National 12,903.00 17,299.33 Completed 2019-01-07 2018-10-16 2019-01-09 2019-01-13 2018-11-01 2019-01-15 2018-12-05 2019-01-17 2018-12-13 2019-01-21 2018-12-19 2019-02-13 2019-02-20 2019-06-30 2020-01-19 port and Innovation Grants Based Selection Web site and Project Monitori ng Tool for PSSP LK-MHNIM-128700-CS-CQS / Consultancy for the evaluatio n of The National Policy and Project Implementation Sup Consultant Qualifi IBRD / 88780 Post Open - National 20,000.00 0.00 Canceled 2019-09-05 2019-10-16 2019-09-26 2019-11-09 2019-12-09 2020-01-13 2020-07-11 Strategic Framework for Prev port and Innovation Grants cation Selection ention and Control of Chronic Non Communicable Diseases - 2009 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MHNIM-81510-CS-INDV / Developing Guide Lines for O Project Implementation Sup Individual Consult pe-rationalizing the Concept IBRD / 88780 Post Open 6,452.00 5,613.25 Completed 2018-10-11 2018-08-08 2018-11-15 2018-09-03 2018-11-25 2018-10-12 2018-12-02 2018-11-01 2019-01-16 2019-03-13 port and Innovation Grants ant Selection of Reorganization and Streng thening of Primary Healthcar e Delivery System LK-MHNIM-81547-CS-INDV / Project Implementation Sup Individual Consult Consultancy for Developmen IBRD / 88780 Post Open 6,452.00 4,181.87 Completed 2018-10-15 2018-12-03 2018-12-24 2019-01-02 2018-12-31 2019-01-08 2019-01-21 2018-11-01 2019-04-21 2019-06-13 port and Innovation Grants ant Selection t of Standard Protocol LK-MHNIM-81552-CS-INDV / Project Implementation Sup Individual Consult Consultancy for Establish Citi IBRD / 88780 Post Open 6,452.00 4,687.06 Completed 2018-10-16 2018-10-18 2018-11-20 2018-11-09 2018-11-27 2018-11-19 2018-12-18 2018-12-29 2019-02-12 2019-06-11 port and Innovation Grants ant Selection zen Engagement Mechanism Guidelines LK-MHNIM-81533-CS-INDV / Consultant for Gap Analysis a Project Implementation Sup Individual Consult IBRD / 88780 Post Open 6,452.00 5,630.63 Completed 2018-10-11 2018-10-01 2018-11-13 2018-10-23 2018-11-20 2018-11-01 2018-12-04 2018-11-26 2019-02-26 2020-03-15 nd Planning for Implementati port and Innovation Grants ant Selection on at the Provincial Level LK-MHNIM-117401-CS-INDV / Project Implementation Sup Individual Consult Consultancy for Developing C IBRD / 88780 Post Open 2,857.00 4,694.18 Completed 2019-06-14 2019-07-09 2019-08-02 2019-08-27 2019-08-23 2019-09-19 2019-09-27 2019-10-09 2020-03-25 2020-12-31 port and Innovation Grants ant Selection omprehensive plan for Capac ity Building LK-MHNIM-140116-CS-INDV / Consultancy for revise Guidel Project Implementation Sup Individual Consult IBRD / 88780 Post Direct 4,167.00 4,225.58 Completed 2019-10-30 2019-12-10 2019-11-09 2020-01-06 2019-11-30 2020-02-25 2020-01-04 2020-03-10 2020-07-02 2022-01-04 ines for Procurement of Phar port and Innovation Grants ant Selection maceuticals and Medical Dev ices LK-MHNIM-106282-CS-INDV / Consultancy for the Preparati Project Implementation Sup Individual Consult IBRD / 88780 Post Open 5,714.00 0.00 Canceled 2019-03-31 2019-05-19 2019-06-09 2019-07-14 2019-08-28 on of Strategic Plan for the to port and Innovation Grants ant Selection tal Project period LK-MHNIM-106302-CS-INDV / Consultancy for Developmen Project Implementation Sup Individual Consult t of Legal Frame work and Re IBRD / 88780 Post Open 5,714.00 0.00 Canceled 2019-04-08 2019-05-27 2019-06-17 2019-07-22 2019-09-05 port and Innovation Grants ant Selection sponsive Healthcare Delivery Mechanism at Primary Care L evel LK-MHNIM-81535-CS-INDV / Project Implementation Sup Individual Consult Consultancy for Developing a IBRD / 88780 Post Open 6,452.00 0.00 Canceled 2018-10-11 2018-11-22 2018-12-06 2019-01-03 2019-01-24 port and Innovation Grants ant Selection plan for Media Publicity Cam paign Page 3 LK-MHNIM-183941-CS-CDS / Consultancy for Capacity Buil ding on Emerging, Re-emergi Contingent Emergency Resp IBRD / 88780 Post Direct Selection Direct 156,756.00 0.00 Canceled 2020-07-22 2020-08-01 2020-10-05 2023-07-20 ng Diseases & Non-Communi onse Component cable Diseases (NCDs) for he ath, non-health and related workforce LK-MHNIM-258424-CS-INDV / Consultancy Service to study Project Implementation Sup Individual Consult provider knowledge, practice IBRD / 88780 Post Open 10,000.00 0.00 Canceled 2021-11-30 2022-01-10 2022-01-18 2022-02-08 2022-03-15 2022-09-11 port and Innovation Grants ant Selection s and adaptation of screenin g and referral protocols for N CD at PMCI in S.L LK-MHNIM-153633-CS-INDV / Project Implementation Sup Individual Consult IT Consultancy service for Ex IBRD / 88780 Post Open 5,555.00 0.00 Canceled 2020-01-29 2020-03-18 2020-04-08 2020-05-13 2020-11-09 port and Innovation Grants ant Selection pansion of the HIMS Module I mplementation LK-MHNIM-283062-CS-INDV / Consultancy service for Grap Project Implementation Sup Individual Consult IBRD / 88780 Post Open 3,130.00 0.00 Canceled 2022-03-23 2022-06-02 2022-05-11 2022-06-01 2022-07-06 2023-01-02 hic designing support for Digi port and Innovation Grants ant Selection tal Signage System for one-y ear period LK-MHNIM-283059-CS-INDV / Consultancy service for the Project Implementation Sup Individual Consult Maintenance of HIMS, daily a IBRD / 88780 Post Open 5,220.00 0.00 Canceled 2022-03-17 2022-06-02 2022-05-05 2022-05-26 2022-06-30 2022-12-27 port and Innovation Grants ant Selection dministrative functions and a ttending to trouble shooting f or one-year period LK-MHNIM-218206-CS-INDV / consultancy service for facili tation of activities of the offic Project Implementation Sup Individual Consult IBRD / 88780 Post Open 3,695.00 0.00 Canceled 2021-03-18 2021-01-25 2021-05-06 2021-05-27 2021-07-01 2021-12-28 e of the Director Genaral of H port and Innovation Grants ant Selection ealth Services in relation to P SSP and ERHSP projects to co rdinate with other satakehold ers. LK-MHNIM-218205-CS-INDV / consultancy service to study Project Implementation Sup Individual Consult the quality of cervical cancer IBRD / 88780 Post Open 10,526.00 0.00 Canceled 2021-03-15 2021-05-03 2021-05-24 2021-06-28 2021-12-25 port and Innovation Grants ant Selection screening and referral practic es in Sri Lankan Public Health System LK-MHNIM-182625-CS-CDS / Modification and Improveme Project Implementation Sup nts of the for website and M& IBRD / 88780 Post Direct Selection Direct 9,500.00 0.00 Canceled 2020-07-07 2020-07-12 2020-09-15 2021-03-14 port and Innovation Grants E tool of the Primary Health Care Systems Strengthening Project Page 4