PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Crisis Recovery Project c. Project Number: P173315 d. Total Finance: USD 137.5 Million 2. Project Implementation Agency: Ministry of Finance, FGS 3. Date of Project Plan: July 2020 4. Period Covered by this Procurement: July-2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Category Open Open Request for International National Quotation (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants n.a. n.a. 2 Consulting Services Re Contract Estimated Review Market Selecti Shortli Expected Expected f Description Cost (US$) by Bank Approach on sting Date of Date of No (Prior/Po (Open- Metho (Yes/N Bid Contract . st) National/ d o) Proposal Signatur Limited (QCBS Opening e etc.) , LCBCS , QBS, DS Social Development 70,200.00 July 16, C1 Prior Limited INDV N/A July 11, 2020 Specialist 2020 Agreement for Delivery of Outputs: Provision of Desert Locust Control, Emergency Support to 10,000,000. Direct Un July 16, C2 affected 00 Prior N/A July 9, 2020 Contracting Agency 2020 communities, and Re- establish the Desert Locust Surveillance and Control System. 10,070,20 Total 0.00 3 4 PROCUREMENT Somalia : Somalia Crisis Recovery Project PLAN General Information Country: Somalia 2020-07-09 Bank’s Approval Date of the Original Procurement Plan: 2023-11-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173315 GPN Date: Project Name: Somalia Crisis Recovery Project Loan / Credit No: IDA / D6300, IDA / D8730 Federal Government of Somalia Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-188762-CW-RFB / R ehabilitation and Reconstruct Component 2: Medium-Ter Open - Internationa Single Stage - One E Pending Imp 2021-12-1 IDA / D6300 Prior Request for Bids 0.00 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 ion in Open River Breakages m Flood Recovery l nvelope lementation 7 along Jubba and Shabelle bas in SO-MOF-188768-CW-RFB / R Component 2: Medium-Ter Open - Internationa Single Stage - One E Pending Imp 2021-12-1 ehabilitation of flood relief ca IDA / D6300 Prior Request for Bids 0.00 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 m Flood Recovery l nvelope lementation 7 nals of shabelle and Jubba Ri vers SO-MOF-228020-CW-RFQ / R ehabilitation of River Embank Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 ments (7 Sites) in Beledweyn IDA / D6300 Prior Limited 198,109.19 Signed 2021-04-14 2021-05-10 2021-06-09 2021-05-24 m Flood Recovery tions nvelope 6 District – Somalia (Lot-1) SO-MOF-228024-CW-RFQ / R EHABILITATION OF BELEDWE Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 YNE/BUNDOWEY N/KAWANKA IDA / D6300 Prior Limited 164,868.31 Signed 2021-04-14 2021-04-26 2021-06-09 2021-05-03 m Flood Recovery tions nvelope 6 /BUULADA RIVER EMBANKME NT IN BELEDWEYN DISTRICT – SOMALIA (Lot-2) SO-MOF-228026-CW-RFQ / R EHABILITATION OF BELEDWE Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 YNE/XAWO IDA / D6300 Prior Limited 90,134.76 Signed 2021-04-14 2021-04-29 2021-06-09 2021-05-09 m Flood Recovery tions nvelope 6 TAKO/HORSEED RIVER EMBA NKMENT IN BELEDWEYN DIST RICT – SOMALIA (Lot-3) SO-MOF-229815-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION BELEDWEYN/ BULO Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 -KAHIN B-1 (RIGHT) AND BAL IDA / D6300 Prior Limited 159,147.00 Signed 2021-05-05 2021-05-17 2021-06-30 2021-05-24 m Flood Recovery tions nvelope (Emergency) 7 ADWEYN/BULO-KAHIN A-1 (RI SPD -Compet GHT) RIVER EMBANKMENT IN itive BELEDWEYN DISTRICT – SOM ALIA (C4) SO-MOF-229841-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION OF CEELKA TOWFIQ Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 (BEERTA HUSEEN DHEERE) A IDA / D6300 Prior Limited 62,680.00 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-24 m Flood Recovery tions nvelope (Emergency) 5 ND HELO KILIYO TO HOODLE SPD -Compet Y RIVER EMBANKMENT IN BE itive LEDWEYN DISTRICT – SOMALI A (C5) SO-MOF-229843-CW-RFQ / B atch-2 (Beledwyne): REHABIL Request for ITATION OF BELEDWEYN/DHA Quotations - RKEYNTA 1, BELEDWEYN/DH Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 181,262.94 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-24 ARKEYNTA 2, BELEDWEYN/S m Flood Recovery tions nvelope (Emergency) 5 HINIILE 1, AND BALADWEYN/ SPD -Compet SHINIILE 2 RIVER EMBANKME itive NT IN BELEDWEYN DISTRICT – SOMALIA (C7) SO-MOF-229844-CW-RFQ / B atch-2 (Beledwyn): REHABILI Request for TATION OF BELEDWEYNE/ DO Quotations - OLOGAAL (BEERTA CIILOW) Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 239,419.76 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-24 (LEFT), BELEDWEYNE/XUBEE m Flood Recovery tions nvelope (Emergency) 5 Y 2, BELEDWEYNE/ XUBEEY 3 SPD -Compet AND BEBELEDWEYNE/XUBEE itive Y 4 RIVER EMBANKMENT IN B ELEDWEYN DISTRICT – SOMA LIA (C8) SO-MOF-229845-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BELEDWEYNE/XU Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 155,960.80 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 BEEY 6 AND BELEDWEYNE / m Flood Recovery tions nvelope (Emergency) 5 XUBEEY 8 RIVER EMBANKME SPD -Compet NT IN BELEDWEYN DISTRICT itive – SOMALIA (C9) SO-MOF-229846-CW-RFQ / B atch-2 (Beledwyn): REHABILI TATION OF DAMALAW/XURIY Request for E1, / SIIGAALOW/ KALIAGA Y Quotations - UUSUF A, BELEDWEYNE/ SIIG Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 172,386.28 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 AALOW / KALIAGA YUUSUF B, m Flood Recovery tions nvelope (Emergency) 5 BELEDWEYN/BEERATA MOHA SPD -Compet MED SALAAD 1, AND BELED itive WEYN/BEERATA MOHAMED S ALAAD 2 RIVER EMBANKMEN T IN BELEDWEYN DISTRICT –( C10) SO-MOF-229847-CW-RFQ / B atch-2 (Beledwyn): REHABILI TATION OF BELEDWEYNE/CE Request for ELKA TAWFIIQ/ BEERTA HUSE Quotations - EN DHEERE1, BELEDWEYNE/ Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 153,159.44 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 LAANTA HILAAC/KALIGA ABDI m Flood Recovery tions nvelope (Emergency) 5 GARAAD, BELEDWEYNE/ BER SPD -Compet DAHA/RADERKA/HILO BARDO itive 1AND BELEDWEYNE/ BERDA HA/RADERKA/HILO BARDO 2 RIVER EMBANKMENT ( C11) SO-MOF-229848-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BLEDWEYNE/HAA Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 WOTAKOBALADWEYN-4 (LEF IDA / D6300 Prior Limited 152,241.50 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 m Flood Recovery tions nvelope (Emergency) 5 T) AND BELEDWEYNE/BILIS D SPD -Compet IID 2 RIVER EMBANKMENT IN itive BELEDWEYN DISTRICT – SOM ALIA (C12) Page 1 SO-MOF-229849-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BELEDWEYN/ QO Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 OQANE, BELELDWAYN/XAWO IDA / D6300 Prior Limited 161,580.00 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-14 m Flood Recovery tions nvelope (Emergency) 5 TAKO, /BELEDWEYN/BILISDII SPD -Compet D 1 RIVER EMBANKMENT IN B itive ELEDWEYN DISTRICT – SOMA LIA (C13) Request for SO-MOF-229852-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 170,543.80 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-22 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Magadley 2) - C2 SPD -Compet itive Request for SO-MOF-229853-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 150,315.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-22 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/gafaay 1) - C3 SPD -Compet itive Request for SO-MOF-229857-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E 2022-01-2 IDA / D6300 Prior Limited Small Works 96,958.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-22 n of River Embankments (Jow m Flood Recovery tions nvelope 7 (Emergency) har/Sabuun) - C7 SPD -Compet itive Request for SO-MOF-229860-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 140,354.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-22 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Buulo haji) - C10 SPD -Compet itive SO-MOF-229842-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION OF BALADWEYN/BU Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 ULO KAHIN 2, BALADWEYN /B IDA / D6300 Prior Limited 198,329.46 Signed 2021-05-15 2021-06-07 2021-07-10 2021-06-21 m Flood Recovery tions nvelope (Emergency) 6 UULO KAHIN 3 AND BALADW SPD -Compet EYN/BUULO KAHIN 4RIVER E itive MBANKMENT IN BELEDWEYN DISTRICT – SOMALIA (C6) Request for SO-MOF-229854-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 162,610.60 Signed 2021-05-16 2021-06-14 2021-07-11 2021-06-21 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/gafaay 2) - C4 SPD -Compet itive Request for SO-MOF-229856-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 172,125.85 Signed 2021-05-15 2021-06-14 2021-07-10 2021-06-23 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 6 har/Geedo Barkan 2 & Buulo SPD -Compet Ahmed) C6 itive Request for SO-MOF-229855-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 185,812.00 Signed 2021-05-16 2021-06-14 2021-07-11 2021-06-23 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Geedo Barkan 1) - C5 SPD -Compet itive Request for B SO-MOF-235315-CW-RFB / S ids - Small W Component 5: Contingent Single Stage - One E 2022-05-1 upply and Installation of Sola IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-07-31 2021-08-05 2021-09-16 2021-10-16 2021-11-20 Emergency Response nvelope 9 r panels to hospitals (Martini nvelope proc & Banadir) ess) Request for SO-MOF-229850-CW-RFQ / B Quotations - atch-2 (Beledwyn): REHABILI Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 TATION OF BELEDWEYN/HOO IDA / D6300 Prior Limited 0.00 Canceled 2021-05-03 2021-06-28 m Flood Recovery tions nvelope (Emergency) 5 DLEY RIVER EMBANKMENT IN SPD -Compet BELEDWEYN DISTRICT – SOM itive ALIA (C4) Request for SO-MOF-238412-CW-RFQ / B Quotations - ardhere: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-02-2 IDA / D6300 Prior Limited 0.00 2021-07-05 2021-10-19 2021-08-30 er Embankments Shimbiro ea m Flood Recovery tions nvelope (Emergency) mentation 6 st, Baardhere District – Soma SPD -Compet lia (C1) itive Request for SO-MOF-238415-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 156,525.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-12 ver Embankments Bandar 2, m Flood Recovery tions nvelope (Emergency) 6 Baardhere District – Somalia SPD -Compet (C2) itive Request for SO-MOF-238416-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 151,605.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-12 ver Embankments Bandar 3, m Flood Recovery tions nvelope (Emergency) 6 Baardhere District – Somalia SPD -Compet (C3) itive Request for SO-MOF-238417-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-02-2 ver Embankments Hilo banee IDA / D6300 Prior Limited 0.00 2021-07-05 2021-10-19 2021-08-30 m Flood Recovery tions nvelope (Emergency) mentation 6 d 1 and Hilo baneed 2, Baard SPD -Compet here District – Somalia (C4) itive Request for SO-MOF-238418-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 152,534.20 Signed 2021-07-05 2021-10-19 2021-08-30 2022-03-12 ver Embankments Hilo banee m Flood Recovery tions nvelope (Emergency) 6 d 3, Baardhere District – Som SPD -Compet alia (C5) itive Request for SO-MOF-238419-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 177,395.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-12 ver Embankments Hilo banee m Flood Recovery tions nvelope (Emergency) 6 d 6, Baardhere District – Som SPD -Compet alia (C6) itive Request for SO-MOF-238421-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 ver Embankments Bandar 1, IDA / D6300 Prior Limited 136,540.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-12 m Flood Recovery tions nvelope (Emergency) 6 Bulo cesan 1 and Bulo-cesan SPD -Compet 2, Baardhere District – Somal itive ia (C7) Request for SO-MOF-235264-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Daaf bari 1 in m Flood Recovery tions nvelope (Emergency) 6 Agooye District – Somalia (C1 SPD -Compet 1) itive Request for SO-MOF-235233-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 Embankments (3 Sites) in Af m Flood Recovery tions nvelope (Emergency) 8 goye district – Somalia (C1) SPD -Compet itive Request for SO-MOF-235235-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 Embankments Beerta Kuwayt m Flood Recovery tions nvelope (Emergency) 8 1 in Afgoye District – Somalia SPD -Compet (C2) itive Page 2 Request for SO-MOF-235267-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 Embankments Ceelka cartan/ IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 m Flood Recovery tions nvelope (Emergency) 6 farta baabaa hasan1 in Afgoo SPD -Compet ye District – Somalia (C13) itive Request for SO-MOF-235272-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Raqayle 1 in A m Flood Recovery tions nvelope (Emergency) 6 fgooye District – Somalia (C1 SPD -Compet 5) itive Request for SO-MOF-235278-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Damalay1 in A m Flood Recovery tions nvelope (Emergency) 6 fgooye District – Somalia (C1 SPD -Compet 7) itive Request for SO-MOF-235281-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Dhagax tuurk m Flood Recovery tions nvelope (Emergency) 6 a 1 in Afgooye District – Som SPD -Compet alia (C19) itive Request for SO-MOF-235283-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Baalguri in Af m Flood Recovery tions nvelope (Emergency) 6 gooye District – Somalia (C21 SPD -Compet ) itive Request for SO-MOF-235284-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Beerta imaara m Flood Recovery tions nvelope (Emergency) 6 adka 1 in Afgooye District – S SPD -Compet omalia (C22) itive Request for SO-MOF-235288-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankment (1 Site) in Afgo m Flood Recovery tions nvelope (Emergency) 6 ye District – Somalia (C24) SPD -Compet itive SO-MOF-238422-CW-RFQ / D ollow: Procurement of: Qansa Request for xlay,Qansaxlay/Beerta Aadan Quotations - Modoobe 1, Qansaxlay/Beert Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 a Aadan Modoobe 2, Dollow/ m Flood Recovery tions nvelope (Emergency) 9 Qansaxlay/Beerta osman Abd SPD -Compet ikadir1, Dollow/ Qansaxlay/B itive eerta osman Abdikadir2. In J ubba-land Somalia (C1) Request for SO-MOF-238426-CW-RFQ / D Quotations - ollow: Procurement of Lot2 i Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 n Dollow/ Cambaha/ Dhuma IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 dhumay1/ Dhumadhumay2 D SPD -Compet huudhhumy 3 of Jubaland - S itive omalia (C2) SO-MOF-238428-CW-RFQ / D Request for ollow: Procurement of: [Five Quotations - villages Dollow/Una/Beerta Z Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 akaria Abdirashid1, Dollow/U m Flood Recovery tions nvelope (Emergency) 9 na/Beerta Zakaria Abdirashid SPD -Compet 2 district Jubaland state of So itive malia. (C3) Request for SO-MOF-238430-CW-RFQ / D Quotations - ollow: Procurement of: Five v Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 illages in Dollow/Una/Hilo, Un IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 a/Beerta Abdi dool and Una/B SPD -Compet eerta Abdikawi mohamed (C itive 4) Request for SO-MOF-238431-CW-RFQ / D Quotations - ollow: Procurement of: Dollo Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 w/Suul Guduud/Abdiyo Abdi m Flood Recovery tions nvelope (Emergency) 9 Baale, Suul Guduud/mohame SPD -Compet d Abdullahi (C5) itive Request for SO-MOF-238432-CW-RFQ / D Quotations - ollow: Procurement of: [Suulg Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 udud/Ali sharif , Quracleey/K IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 eli Dahir, Suulgudud/Adam Ib SPD -Compet rahim] in Dollow Juba land So itive malia. (C6) SO-MOF-257503-CW-RFB / Jo Request for B whar Batch 2 Works: Rehabili ids - Small W tation of River Embankment Component 2: Medium-Ter Single Stage - One E 2022-08-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-10-30 2021-11-04 2021-12-16 2022-01-15 2022-02-19 at Magadley 1, Muriyaale, Gu m Flood Recovery nvelope 8 nvelope proc maray and Mareeray 1 (3 LO ess) TS) in Jowhar, Hirshabelle Sta te. Request for SO-MOF-255371-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope (Emergency) 3 yt 2 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C6) itive Request for SO-MOF-255309-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 Embankments at Aytiro 1 an IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 d Dhagaxtuurka 2 sites in Af SPD -Compet goye District, Lower Shabelle itive Region - (C1) Request for SO-MOF-255347-CW-RFQ / A Quotations - fgooye: Rehabilitation of Rive Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 r Embankment at Baalguri 2 IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 site in Afgoye District, Lower SPD -Compet Shabelle Region - (C2) itive Request for SO-MOF-255357-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 Embankment and Canal Intak IDA / D6300 Post Limited 0.00 Canceled 2021-10-19 2021-12-14 m Flood Recovery tions nvelope (Emergency) 2 e at Beerta Imaaraadka 1 in SPD -Compet Afgoye District, Lower Shabel itive le Region - (C3) SO-MOF-255367-CW-RFQ / A Request for fgoye: Rehabilitation of River Quotations - Embankment & Canal Intake Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 Chamber at Beerta Imaaraad m Flood Recovery tions nvelope (Emergency) 4 ka 2 site in Afgoye District, L SPD -Compet ower Shabelle Region - (C4) itive Page 3 Request for SO-MOF-255369-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope (Emergency) 3 yt 1 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C5) itive Request for SO-MOF-255372-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope (Emergency) 3 yt 3 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C7) itive Request for SO-MOF-255373-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope (Emergency) 3 yt 4 in Afgoye District, Lower SPD -Compet Shabelle Region - (C8) itive Request for SO-MOF-255374-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope (Emergency) 3 yt 5 in Afgoye District, Lower SPD -Compet Shabelle Region - (C9) itive Request for SO-MOF-255375-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope (Emergency) 3 yt 6 in Afgoye District, Lower SPD -Compet Shabelle Region - (C10) itive Request for B SO-MOF-262209-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-10-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-12-15 2022-05-26 2021-12-20 2022-06-05 2022-01-31 2022-07-31 2022-03-02 2022-04-06 ments at Dhagaxtuurka 2 an m Flood Recovery nvelope 3 nvelope proc d Aytiro 1 (2 Sites) in Afgoye ess) District, SWS State Request for SO-MOF-262214-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 Embankment at Baalguri 2 si m Flood Recovery tions nvelope (Emergency) 3 te in Afgoye District, Lower S SPD -Compet habelle Region (C2) itive Request for SO-MOF-262215-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Imaa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope (Emergency) 3 raakda 1 in Afgoye District, L SPD -Compet ower Shabelle Region (C3) itive Request for SO-MOF-262216-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Imaa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2022-05-21 m Flood Recovery tions nvelope (Emergency) 3 raadka 2 in Afgoye District, L SPD -Compet ower Shabelle Region (C4) itive Request for SO-MOF-257752-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-11-04 2021-12-30 Embankment at Qansaxlay Si m Flood Recovery tions nvelope (Emergency) 8 te In Dollow District, Gedo Re SPD -Compet gion (Lot 1) itive Request for B SO-MOF-262226-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-10-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-12-15 2022-05-26 2021-12-20 2022-06-05 2022-01-31 2022-03-02 2022-04-06 ment (five sites) in Dollow Di m Flood Recovery nvelope 3 nvelope proc strict, Gedo Region - (2 Lots) ess) SO-MOF-257753-CW-RFQ / D Request for ollow: Rehabilitation of River Quotations - Embankment at Qansaxlay ( Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-08-1 IDA / D6300 Prior Limited 0.00 2021-12-20 2022-03-07 2022-02-14 Beerta Aden madobe1,2 and m Flood Recovery tions nvelope (Emergency) mentation 3 Beerta osman Abdikadir1,2) i SPD -Compet n Dollow District, Gedo Regio itive n (C2) SO-MOF-257760-CW-RFQ / D Request for ollow: Rehabiliation of River Quotations - Embankment at Buulo Qaloo Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2023-05-14 c (Mohamed Qase 1,2,3 and m Flood Recovery tions nvelope (Emergency) 3 Dollow/Iskudaraha Ahmed Ali SPD -Compet Qeyr) in Dollow District, Ged itive o Region (C9) Request for SO-MOF-257758-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Sulguduud ( IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2023-05-14 m Flood Recovery tions nvelope (Emergency) 3 Ali Sharif, Adan Ibrahim, Abdi SPD -Compet rashid, and Hassan) in Dollo itive w District, Gedo Region - (C7 ) Request for SO-MOF-257759-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-11-04 2021-12-30 Embankment at Sulguduud N m Flood Recovery tions nvelope (Emergency) 8 asteh in Dollow District, Gedo SPD -Compet Region (Lot 8) itive Request for B SO-MOF-257755-CW-RFB / R ids - Small W ehbilitation of River embank Component 2: Medium-Ter Single Stage - One E 2022-09-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-30 2022-05-26 2021-12-05 2022-06-05 2022-01-16 2022-02-15 2022-03-22 ment (5 sites) in Dollow distri m Flood Recovery nvelope 8 nvelope proc ct, Jubaland (2 Lots) ess) Request for B SO-MOF-257754-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-09-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-30 2022-06-06 2021-12-05 2022-06-10 2022-01-16 2022-02-15 2022-03-22 ments (4 sites) in Dollow Dist m Flood Recovery nvelope 8 nvelope proc rict, Jubaland State (2 Lots) ess) Request for SO-MOF-256788-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-08-1 IDA / D6300 Prior Limited 0.00 2021-12-20 2022-03-24 2022-02-14 mbankment at Boyle farm 1 i m Flood Recovery tions nvelope (Emergency) mentation 3 n Luuq District, Gedo Region SPD -Compet - (C1) itive Request for SO-MOF-256790-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-10-30 2021-12-25 mbankment at Bacaad Weyn m Flood Recovery tions nvelope (Emergency) 3 1&2 in Luuq District, Gedo Re SPD -Compet gion - (C2) itive Request for SO-MOF-256791-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2023-03-23 mbankment at Bacaadlay Far m Flood Recovery tions nvelope (Emergency) 3 m 3 in Luuq District, Gedo Re SPD -Compet gion - (C3) itive Page 4 Request for SO-MOF-256792-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Canceled 2021-12-20 2022-02-14 mbankment at Bacaadlay Far m Flood Recovery tions nvelope (Emergency) 3 m 4 in Luuq District, Gedo Re SPD -Compet gion - (C4) itive SO-MOF-255593-CW-RFQ / K Request for ismayo: Rehabilitation of Riv Quotations - er Embankments at Goobwey Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 n (Farta school ka, Fargeelee IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 y, Farta Garoonka and Masha SPD -Compet qo 1 & 2) and Qamqam (Maq itive ara'as 1, 2 & 3) in Kismayo T own, Jubba-land state - (C1) Request for SO-MOF-262246-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2022-05-21 er Embankment In Kismayo T m Flood Recovery tions nvelope (Emergency) 3 own, Jubaland State (C1) SPD -Compet itive Request for SO-MOF-255595-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 er Embankment at Yoontoow IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 (Mayakondo & Shubiiro sites) SPD -Compet in Kismayo town, Jubba-land itive state (C2) Request for SO-MOF-262247-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2022-05-21 er Embankment in Kismayo T m Flood Recovery tions nvelope (Emergency) 3 own, Jubaland State (C2) SPD -Compet itive Request for SO-MOF-238433-CW-RFQ / D Quotations - ollaw: Procurement of: [Five Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 villages in dollaw Suulgudud/ IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 Ali sharif, Quracleey/Keli Dahi SPD -Compet r district Jubaland state of So itive malia. (C7) SO-MOF-235230-CW-RFQ / B Request for atch-3 (Beledwyn): Rehabilita Quotations - tion of Masonry Retaining Wa Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 ll (in Hilo Bardo, Horseed, Bal IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 m Flood Recovery tions nvelope (Emergency) 8 adweyn 1, Ibrahim Farm & D SPD -Compet onsubagle 5 Villages)for Floo itive d Protection in Beledweyn Di strict – Somalia (C15) Request for SO-MOF-235875-CW-RFQ / R Quotations - ehabilitation of Beledweyn/H Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-1 IDA / D6300 Post Limited 0.00 Canceled 2021-07-20 2021-09-14 oodley River Embankment in m Flood Recovery tions nvelope (Emergency) 3 Beledweyn District – Somalia SPD -Compet (C14). itive SO-MOF-266544-CW-RFB / R Request for B ehabilitation of River Embank ids - Small W Component 2: Medium-Ter Single Stage - One E 2023-01-1 ment at Magadley 1, Muriyaa IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-08-06 2022-06-16 2022-07-21 m Flood Recovery nvelope 7 le, nvelope proc Gumaray and Mareeray 1 (3 ess) LOTS) in Jowhar, Hirshabelle State Request for B SO-MOF-262257-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-01-1 ehabilitation of Far Libaax Ro IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-07-07 2022-06-16 2022-07-21 m Flood Recovery l nvelope 7 ad (phase-I) in Beledwayne, nvelope proc Hirshabelle State ess) SO-MOF-262258-CW-RFB / L Request for B ot 1: Rehabilitation of Habala ids - Small W Component 2: Medium-Ter Single Stage - One E 2023-01-1 Adey MCH in Bardhere Distric IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-06-16 2022-07-21 m Flood Recovery nvelope 7 t nvelope proc Lot 2: Rehabilitation of Horse ess) ed Health Facility in Berdere District SO-MOF-262259-CW-RFB / L Request for B ot 1: Rehabilitation of Sigaalo ids - Small W w MCH in Beldewyne District Component 2: Medium-Ter Single Stage - One E 2023-01-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-07-05 2022-06-16 2022-07-21 Lot 2: Rehabilitation of Haaw m Flood Recovery nvelope 7 nvelope proc o Taako Health Facility in Bal ess) edweyn District Request for B SO-MOF-276917-CW-RFB / R ids - Small W ehabilitation of 5 sites ( Kalu Component 2: Medium-Ter Single Stage - One E Under Imple 2022-12-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-02-20 2022-03-14 2022-02-25 2022-03-16 2022-04-08 2022-03-26 2022-05-08 2022-04-26 2022-06-12 undi 1 &2, Garaash and Moky m Flood Recovery nvelope mentation 9 nvelope proc o 1& 3) in Jowhar District ess) Request for SO-MOF-277130-CW-RFQ / C Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-11-2 onstruction of two rooms to h IDA / D6300 Prior Limited 0.00 2022-04-05 2022-05-31 Emergency Response tions nvelope Non Bank-SP lementation 7 ouse Oxygen plants in Baido D) a and Kismayo Request for SO-MOF-295717-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-08 2022-09-02 Emergency Response tions nvelope Non Bank-SP lementation 1 rehouse for the State of Jubal D) and Request for SO-MOF-295721-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-08 2022-09-02 Emergency Response tions nvelope Non Bank-SP lementation 1 rehouse for the State of Sout D) hwest Request for SO-MOF-295723-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 Emergency Response tions nvelope Non Bank-SP lementation 2 rehouse for the State of Gal D) mudug Request for SO-MOF-295724-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 Emergency Response tions nvelope Non Bank-SP lementation 2 rehouse for the State of Hirsh D) abelle Request for SO-MOF-295727-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 ehabilitation of Medical Natio IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 Emergency Response tions nvelope Non Bank-SP lementation 9 nal warehouse in Mogadishu D) SO-MOF-295726-CW-RFQ / R Request for ehabilitation of Medical ware Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 house for Banadir regional ad Emergency Response tions nvelope Non Bank-SP lementation 9 ministration (BRA) D) Request for SO-MOF-295719-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 ehabilitation of Medical ware IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 Emergency Response tions nvelope Non Bank-SP lementation 9 house in Puntland State D) Request for B SO-MOF-307801-CW-RFB / R ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-06-1 ehabilitation of river embank IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-08-31 2022-08-25 2022-09-05 2022-09-02 2022-10-17 2022-09-29 2022-11-16 2022-12-15 2022-12-21 m Flood Recovery nvelope mentation 9 ment (3 sites) in Luuq district nvelope proc , Jubaland State ess) Page 5 Request for B SO-MOF-307802-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-06-1 ehabilitation of Belethawa's IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-08-31 2022-09-13 2022-09-05 2022-09-14 2022-10-17 2022-10-17 2022-11-16 2023-02-14 2022-12-21 m Flood Recovery l nvelope mentation 9 Dolow (2.9Km) and Elwaq (1. nvelope proc 9Km) Roads ess) Request for B SO-MOF-307803-CW-RFB / R ids - Small W ehabilitation of Hudur Main R Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-06-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 Canceled 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 oad (2.5 kilometers) and Blim m Flood Recovery l nvelope 9 nvelope proc aqasi Road (3.9 kilometers) i ess) n Hudur Request for B SO-MOF-316762-CW-RFB / R ids - Small W ehabilitation of Hudur Main R Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-07-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-09-30 2022-10-04 2022-10-05 2022-11-16 2022-11-16 2022-12-17 2022-12-16 2023-03-07 2023-01-20 oad (2.5Km) and Blimaqasi R m Flood Recovery l nvelope mentation 9 nvelope proc oad (3.9Km) in Hudur district ess) , South West State Request for B SO-MOF-316766-CW-RFB / R ids - Small W ehabilitation of Dhulu Ale (3. Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-07-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-09-30 2022-11-08 2022-10-05 2022-11-15 2022-11-16 2022-12-20 2022-12-16 2023-05-23 2023-01-20 5Km), Dolow (1.25Km) and B m Flood Recovery l nvelope mentation 9 nvelope proc oiya Road (4.0Km) in Luuq, Ju ess) baland State SO-MOF-316767-CW-RFB / R Request for B e-construction of Kulmis Mat ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-08-0 ernal and Child Health (MCH) IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-10-15 2022-11-08 2022-10-20 2022-11-15 2022-12-01 2022-12-19 2022-12-31 2023-01-31 2023-02-04 m Flood Recovery l nvelope mentation 3 Facility in Jowhar District -Hir nvelope proc shabelle State, Somalia. ess) SO-MOF-316794-CW-RFB / R Request for B e-construction of Shidley Mat Component 3: Longer-Ter ids - Small W Open - Internationa Single Stage - One E Under Imple 2023-08-0 ernal and Child Health (MCH) IDA / D6300 m Disaster Risk Preparednes Prior Request for Bids orks SPD (1 e 0.00 2022-10-15 2022-11-08 2022-10-20 2022-11-15 2022-12-01 2022-12-15 2022-12-31 2023-03-14 2023-02-04 l nvelope mentation 3 Facility in Hudur District - So s nvelope proc uth West State, Somalia. ess) Request for B SO-MOF-319819-CW-RFB / R ids - Small W ehabilitation of Far Libaax Ro Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2023-01-17 2022-12-17 2022-11-26 2023-01-16 2023-01-31 2023-02-20 ad (2 km) in Beledweyne, Hir m Flood Recovery nvelope mentation 9 nvelope proc shabelle State of Somalia ess) SO-MOF-319822-CW-RFB / R Request for B e-Construction of Habala Ade ids - Small W y Maternal and Child Health ( Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-27 2023-02-15 2023-03-06 2023-03-22 MCH) Facility and Re-Constru m Flood Recovery nvelope mentation 8 nvelope proc ction Horseed Healthcare Fac ess) ility, Bardere District, Jubbala nd State, Somalia SO-MOF-319827-CW-RFB / R Request for B e-construction of Sigaalow M ids - Small W aternal and Child Health (MC Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2022-12-21 2022-12-17 2022-11-27 2023-01-16 2023-03-06 2023-02-20 H) Facility and Haawa Taako m Flood Recovery nvelope mentation 9 nvelope proc Healthcare (HF) Facility in Be ess) ledweyne District, Hirshabell e State SO-MOF-319829-CW-RFB / R Request for B ehabilitation of river embank ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 ments at Dhagaxtuurka 2 (21 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2022-12-14 2022-12-17 2022-11-24 2023-01-16 2023-02-07 2023-02-20 m Flood Recovery nvelope mentation 9 0m) and Aytiro 1 (200m) Site nvelope proc s in Afgoye District, Southwe ess) st State of Somalia. SO-MOF-319831-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-16 2022-12-05 2022-12-14 2023-01-16 2022-11-23 2023-02-15 2023-03-06 2023-03-22 - Lot-1: Dollow/Una (Qansa m Flood Recovery nvelope mentation 8 nvelope proc xlay (276m). ess) - Lot-2: Dollow/Una/ (Beert a Zakaria Abdirashid1 & 2 (2 05.5m) SO-MOF-319832-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-23 2023-02-15 2023-03-06 2023-03-22 - LOT 1: Dollow/Sulguduud m Flood Recovery nvelope mentation 8 nvelope proc (Mudeey Ali 1,2&3 (349m) an ess) d; - LOT 2: Dollow Sulguduud/ Nasteh (196m) SO-MOF-319835-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following two sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 - Lot-1: Dollow/Una (Beerta IDA / D6300 m Flood Recovery Prior Request for Bids Limited nvelope orks SPD (1 e 0.00 mentation 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-23 2023-02-15 2023-01-31 2023-03-22 8 Abdikawi Mohamed, Beerta A nvelope proc bdi dool, and Hillo (360.2m) ess) and; - Lot-2: Doolaw/Sulguduud (Husein Ibrahim 1&2 (466m) SO-MOF-319837-CW-RFB / R ehabilitation of river embank ment sites in Jowhar District, Hirshabelle State of Somalia, Request for B consisting of the following 3 l ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 ots IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-24 2023-02-15 2023-03-06 2023-03-22 m Flood Recovery nvelope mentation 8 nvelope proc Lot 1 - Jowhar/Magadley 1 (3 ess) 30m) Lot 2 - Jowhar/Muryaale & Gu mareey (460m) Lot 3- Jowhar/Mareerey 1 & Mareerey 2 (450m) Request for B SO-MOF-262240-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-11-1 IDA / D6300 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-01-31 2022-02-05 2022-03-19 2022-04-18 2022-05-23 ment Bacaadlay Farm 1, 2 & m Flood Recovery nvelope 9 nvelope proc 4 in Luuq District, Gedo Regi ess) on. Request for B SO-MOF-328327-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-09-1 e-habilitation of Imbresso Ro IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-01 2022-12-14 2022-12-06 2023-01-11 2023-01-17 2023-02-07 2023-02-16 2023-05-31 2023-03-23 m Flood Recovery l nvelope mentation 9 ad (8.4Km) in Barawe, South nvelope proc West State ess) SO-MOF-328329-CW-RFB / R Request for B e-construction of Malkariyey ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-2 Maternal and Child Health (M IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-12-05 2022-12-14 2022-12-10 2023-01-11 2023-01-21 2023-02-06 2023-02-20 2023-04-26 2023-03-27 m Flood Recovery nvelope mentation 3 CH) Facility Belet Hawo Distri nvelope proc ct Jubbaland State, Somalia ess) Page 6 Request for B SO-MOF-328797-CW-RFB / R ids - Small W e-construction of Bulobarde Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-10-0 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-20 2023-01-11 2022-12-25 2023-01-17 2023-02-05 2023-02-22 2023-03-07 2023-04-20 2023-04-11 Cholera Unit Healthcare Facil m Flood Recovery l nvelope mentation 8 nvelope proc ity in Bulobarde District Hirsh ess) abelle State, Somalia Request for B SO-MOF-333065-CW-RFB / R ids - Small W e-construction of Barawe TB Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-10-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-31 2023-01-11 2023-01-05 2023-01-17 2023-02-16 2023-02-16 2023-03-18 2023-04-20 2023-04-22 Unit Healthcare Facility, in Ba m Flood Recovery l nvelope mentation 9 nvelope proc rawe District, South West Sta ess) te, Somalia. Request for B SO-MOF-331714-CW-RFB / R ids - Small W e-construction of Barawe TB Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-10-1 IDA / D6300 Post Request for Bids orks SPD (1 e 0.00 Canceled 2022-12-31 2023-01-05 2023-02-16 2023-03-18 2023-04-22 Unit Healthcare Facility, Bara m Flood Recovery l nvelope 9 nvelope proc we District, South West State ess) , Somalia. Request for SO-MOF-352047-CW-RFQ / R Quotations - ehabilitation of river embank Component 2: Medium-Ter Request for Quota Single Stage - One E Under Imple 2023-12-2 IDA / D8730 Prior Limited Small Works 0.00 2023-05-05 2023-05-03 2023-06-30 ment site (Moyko 3) in Jowha m Flood Recovery tions nvelope mentation 7 (Emergency) r District. SPD -Compet itive Request for B SO-MOF-358679-CW-RFB / R ids - Small W ehabilitation of Two Canals ( Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2024-03-1 IDA / D8730 Prior Request for Bids orks SPD (1 e 0.00 2023-05-31 2023-06-28 2023-06-05 2023-08-07 2023-07-17 2023-09-06 2023-08-16 2023-10-23 2023-09-20 Xanshoore and Aslubta) in Jo m Flood Recovery l nvelope mentation 8 nvelope proc whar District, Hirshabelle Sta ess) te of Somalia Request for B SO-MOF-369640-CW-RFB / R ids - Small W ehabilitation of 15 irrigation c Component 2: Medium-Ter Single Stage - One E Under Imple 2024-04-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-06-30 2023-08-06 2023-07-05 2023-08-10 2023-08-16 2023-09-10 2023-09-15 2023-10-19 2023-10-20 anals in Afgoye, Baidoa and m Flood Recovery nvelope mentation 7 nvelope proc Marka Districts of Southwest ess) State. Request for B SO-MOF-369642-CW-RFB / R ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2024-04-1 ehabilitation of Bulo Bartire Ir IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-06-30 2023-08-14 2023-07-05 2023-08-21 2023-08-16 2023-09-18 2023-09-15 2023-10-20 m Flood Recovery nvelope mentation 7 rigation Canal in Kismayo, Ju nvelope proc baland State ess) Request for B SO-MOF-373253-CW-RFB / R Component 3: Longer-Ter ids - Small W Single Stage - One E Pending Imp 2024-05-1 ehabilitation of Galmudug St IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National orks SPD (1 e 0.00 2023-07-31 2023-08-05 2023-09-16 2023-10-16 2023-11-20 nvelope lementation 8 ate Desert Locust Control Uni s nvelope proc t (SDLU) Premise. ess) Request for B SO-MOF-373554-CW-RFB / R ids - Small W ehabilitation of river embank Component 2: Medium-Ter Single Stage - One E Under Imple 2024-05-1 IDA / D6300 Post Request for Bids Open - National orks SPD (1 e 0.00 2023-07-31 2023-09-25 2023-08-05 2023-09-26 2023-09-16 2023-10-16 2023-11-20 ments (3 sites) in Kismayo di m Flood Recovery nvelope mentation 8 nvelope proc strict, Jubaland State Somalia ess) Request for SO-MOF-373548-CW-RFQ / R Quotations - ehabilitation of river embank Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2024-03-2 IDA / D6300 Post Limited 0.00 Canceled 2023-08-05 2023-09-30 ments (3 sites) in Afgoye dist m Flood Recovery tions nvelope (Emergency) 8 rict, South West State Somali SPD -Compet a itive SO-MOF-377894-CW-RFB / R Request for B ehabilitation of River Embank ids - Works ( Component 2: Medium-Ter Single Stage - One E Under Imple 2024-06-0 ment Works in Afgoye Distric IDA / D6300 Post Request for Bids Open - National without preq 0.00 2023-08-19 2023-09-25 2023-08-24 2023-09-26 2023-10-05 2023-11-04 2023-12-09 m Flood Recovery nvelope mentation 6 t (Aytiro 2, Kuwayt 8, Dhagax ualification) tur ka 1 and Balbaley Sites) SPD Request for B SO-MOF-378040-CW-RFB / R Component 3: Longer-Ter ids - Works ( Single Stage - One E Pending Imp 2024-06-0 ehabilitation and remodeling IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National without preq 0.00 2023-08-28 2023-09-02 2023-10-02 2023-11-01 2023-12-06 nvelope lementation 3 work of 7 regional hospitals s ualification) SPD Request for B SO-MOF-393121-CW-RFB / R Component 3: Longer-Ter ids - Small W Single Stage - One E Pending Imp 2024-09-1 ehabilitation of De Martini, B IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National orks SPD (1 e 0.00 2023-11-30 2023-12-05 2024-01-16 2024-02-15 2024-03-21 nvelope lementation 7 anadir & Folanini Hospitals, B s nvelope proc RA (3 lots) ess) Request for B SO-MOF-393132-CW-RFB / R Component 3: Longer-Ter ids - Small W Single Stage - One E Pending Imp 2024-09-1 ehabiliation of Adado Genera IDA / D8730 m Disaster Risk Preparednes Post Request for Bids Open - National orks SPD (1 e 0.00 2023-11-30 2023-12-05 2024-01-16 2024-02-15 2024-03-21 nvelope lementation 7 l Hospital, Galmudug State s nvelope proc ess) Request for SO-MOF-393134-CW-RFQ / R Component 3: Longer-Ter Request for Quota Single Stage - One E Quotations ( Pending Imp 2024-07-2 ehabilitation of Kismayo Regi IDA / D6300 m Disaster Risk Preparednes Post Limited 0.00 2023-12-05 2024-01-30 tions nvelope Non Bank-SP lementation 8 onal Hospital, Jubaland State s D) Request for B SO-MOF-393135-CW-RFB / R Component 3: Longer-Ter ids - Small W Single Stage - One E Pending Imp 2024-09-1 ehabiliation of Bay Regional IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National orks SPD (1 e 0.00 2023-11-30 2023-12-05 2024-01-16 2024-02-15 2024-03-21 nvelope lementation 7 Hospital, Southwest State s nvelope proc ess) Request for B SO-MOF-393140-CW-RFB / R Component 3: Longer-Ter ids - Small W Single Stage - One E Pending Imp 2024-09-1 ehabilitation of Jowhar Regio IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National orks SPD (1 e 0.00 2023-11-30 2023-12-05 2024-01-16 2024-02-15 2024-03-21 nvelope lementation 7 nal Hospital, Hirshabelle Stat s nvelope proc e ess) Request for SO-MOF-393144-CW-RFQ / R Component 3: Longer-Ter Quotations - Request for Quota Single Stage - One E Pending Imp 2024-07-2 ehabilitation of Garowe Gene IDA / D6300 m Disaster Risk Preparednes Post Limited Small Works 0.00 2023-12-05 2024-01-30 tions nvelope lementation 8 ral Hospital, Puntland Statne s (Emergency) SPD -Compet itive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-214333-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E IDA / D6300 Prior Limited 84,861.70 Signed 2021-04-05 2021-07-14 2021-05-31 2021-08-07 2021-11-27 ocurement of 2 Vehicle for PI ement tions nvelope U SO-MOF-214334-GO-RFQ / Fi Component 4: Project Manag Request for Quota Single Stage - One E Under Imple IDA / D6300 Prior Limited 0.00 2021-04-05 2021-04-26 2021-05-31 2021-11-27 ttings and furniture for PIU Of ement tions nvelope mentation fice SO-MOF-230645-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ocurement of IT equipment f IDA / D6300 Prior Limited 0.00 2021-05-06 2021-07-12 2021-07-01 2021-12-28 ement tions nvelope mentation or PIU Office SO-MOF-235305-GO-RFB / Pr ocurement of Locally made cl Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 oth face masks for the gener Emergency Response nvelope ementation al public (schools, mosques, etc) SO-MOF-235307-GO-RFB / Pr Component 5: Contingent Single Stage - One E Pending Impl ocure Hygiene supplies (Clor IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 Emergency Response nvelope ementation ox, soaps, disinfectants, han d sanitizers etc) Page 7 SO-MOF-235309-GO-DIR / Pr ocurement, commissioning a Component 5: Contingent nd installation of two oxygen IDA / D6300 Prior Direct Selection Direct 0.00 Canceled 2021-06-30 2021-07-05 2021-08-09 2022-02-05 Emergency Response plants for Southwest and Jub aland States of Somalia SO-MOF-235310-GO-RFB / Pr ocurement of Continuous su Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 pply of oxygen to hospitals to Emergency Response nvelope ementation be used for Covid-19 patients SO-MOF-233802-GO-RFQ / B atch-2 (Beledwyn): REHABILI Component 2: Medium-Ter Request for Quota Single Stage - One E TATION OF BELEDWEYN/HOO IDA / D6300 Prior Limited 0.00 Canceled 2021-05-16 2021-07-11 2022-01-07 m Flood Recovery tions nvelope DLEY RIVER EMBANKMENT IN BELEDWEYN DISTRICT – SOM ALIA (C14) SO-MOF-238495-GO-RFQ / Pr ocurement, commissioning a Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2021-07-15 2021-07-20 2021-08-31 2021-09-30 2021-11-04 2022-05-03 nd installation of One oxygen Emergency Response l nvelope ementation plant for Banadir SO-MOF-242309-GO-RFB / Pr ocurement, commissioning a Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-05-08 nd installation of 2 oxygen pl Emergency Response l nvelope ementation ants for Southwest and Jubal and States of Somalia SO-MOF-247166-GO-RFB / S upply, delivery, installation, c ommissioning and maintenan Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-08-15 2021-08-20 2021-10-01 2021-10-31 2021-12-05 2022-06-03 ce of solar systems to Martini Emergency Response nvelope ementation Hospital, Banadir Hospital, N ational Laboratory and Minist ry of Health SO-MOF-273751-GO-RFQ / P Component 4: Project Manag Request for Quota Single Stage - One E Under Imple urchase of IT equipment for S IDA / D6300 Prior Limited 0.00 2022-04-05 2022-03-03 2022-05-31 2022-11-27 ement tions nvelope mentation tate project teams (3 Lots) SO-MOF-273756-GO-RFQ / P Component 4: Project Manag Request for Quota Single Stage - One E Under Imple urchase of office furniture for IDA / D6300 Prior Limited 0.00 2022-04-05 2022-03-03 2022-05-31 2022-11-27 ement tions nvelope mentation State project teams (3 Lots) SO-MOF-235291-GO-RFQ / Pr ocurement of Medical grade Component 5: Contingent Request for Quota Single Stage - One E IDA / D6300 Post Limited 0.00 Canceled 2021-07-20 2021-09-14 2022-03-13 masks for health care worker Emergency Response tions nvelope s at hospitals and health facil ities SO-MOF-235311-GO-RFB / Pr ocurement of Essential Covid Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 -19 medicines and kits, labor Emergency Response l nvelope ementation atory reagents and other ess entials countrywide SO-MOF-295728-GO-RFQ / Pr Component 5: Contingent Request for Quota Single Stage - One E Pending Impl ocurement of a vehicle for th IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 2023-03-02 Emergency Response tions nvelope ementation e FMOH to transport Medical Supplies. SO-MOF-304013-GO-RFB / Pr ocurement and installation of Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl additional solar panels (comp IDA / D8730 Prior Request for Bids 0.00 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2023-06-19 Emergency Response l nvelope ementation lete with spare parts) at the COVID-19 Health Facilities in Mogadishu and FMS SO-MOF-304000-GO-RFB / Pr Component 5: Contingent Open - Internationa Single Stage - One E Under Imple ocurement of Lab & medical IDA / D8730 Prior Request for Bids 0.00 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2023-06-19 Emergency Response l nvelope mentation equipment for Federal & FMS Health Ministries SO-MOF-328332-GO-DIR / Pr Component 3: Longer-Ter ocurement of Hydrological an Direct - Internation Under Imple IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection 0.00 2022-12-10 2022-12-29 2022-12-15 2023-04-14 2023-01-19 2023-07-18 d hydraulic modeling and Flo al mentation s od Early Warning System soft ware package SO-MOF-346330-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ocurement of office furniture IDA / D6300 Prior Limited 0.00 2023-04-05 2023-05-15 2023-05-31 2023-11-27 ement tions nvelope mentation for Hirshabelle and Jubaland SPT offices SO-MOF-357130-GO-RFB / Pr Component 6: Anticipatory a Open - Internationa Single Stage - One E Under Imple ocurement of Refrigerated tr IDA / D6300 nd Recovery Support for Add Prior Request for Bids 0.00 2023-06-30 2023-05-15 2023-07-05 2023-05-23 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope mentation ucks for fishing associations ressing Food Insecurity SO-MOF-357133-GO-RFB / Pr Component 6: Anticipatory a Open - Internationa Single Stage - One E Under Imple ocurement of Mobile refriger IDA / D6300 nd Recovery Support for Add Prior Request for Bids 0.00 2023-06-30 2023-05-17 2023-07-05 2023-05-19 2023-08-16 2023-06-22 2023-09-15 2023-08-21 2023-10-20 2024-04-17 l nvelope mentation ated fish kiosks ressing Food Insecurity SO-MOF-359405-GO-RFQ / Pr Component 3: Longer-Ter Request for Quota Single Stage - One E Under Imple ocurement of Office Furniture IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-05 2023-09-08 2023-07-31 2024-01-27 tions nvelope mentation and Equipment for NEOC s SO-MOF-359413-GO-RFB / Pr Component 3: Longer-Ter Single Stage - One E IDA / D8730 Post Request for Bids Open - National 0.00 Canceled 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 2024-03-18 ocurement of Vehicles for NE m Disaster Risk Preparednes nvelope OC s SO-MOF-369645-GO-RFQ / Pr ocurement of Operational Ve Component 3: Longer-Ter Request for Quota Single Stage - One E Under Imple hicles for National Emergenc IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope mentation y Operation Center (Two Toy s ota Hilux 2.4L 4WD Double Cap) SO-MOF-373550-GO-RFB / S Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple upply of Health Medical Equi IDA / D6300 Post Request for Bids 0.00 2023-07-31 2023-08-19 2023-08-05 2023-09-16 2023-10-16 2023-11-20 2024-05-18 m Flood Recovery l nvelope mentation p to the destinations (9 HF) SO-MOF-373552-GO-RFQ / O Component 2: Medium-Ter Request for Quota Single Stage - One E Pending Impl ffice Furniture procurement IDA / D6300 Post Limited 0.00 2023-08-05 2023-09-30 2023-10-09 m Flood Recovery tions nvelope ementation & supply to the 9 HFs SO-MOF-377882-GO-RFQ / Pr Component 3: Longer-Ter ocure office furniture and IC Request for Quota Single Stage - One E Pending Impl IDA / D6300 m Disaster Risk Preparednes Post Limited 0.00 2023-08-24 2023-10-19 2024-04-16 T equipment (Servers , comp tions nvelope ementation s uters, printers, tablets for FG S &FMS EDMU offices) Page 8 SO-MOF-377883-GO-RFQ / Pr ocure equipment for vet sup Component 3: Longer-Ter plies, diagnostic kits, reagent Request for Quota Single Stage - One E Under Imple IDA / D6300 m Disaster Risk Preparednes Post Limited 0.00 2023-08-24 2023-10-19 2024-04-16 s, field rapid test kits and Sa tions nvelope mentation s mple shipment to Mogadishu CVL laboratory (shipment an d cold chain costs) SO-MOF-378082-GO-RFB / Pr Component 3: Longer-Ter Single Stage - One E Under Imple ocurement and installation of IDA / D6300 m Disaster Risk Preparednes Post Request for Bids Open - National 0.00 2023-08-26 2023-10-07 2023-08-31 2023-10-14 2023-10-12 2023-11-11 2023-12-16 2024-06-13 nvelope mentation one CT Scan s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-174236-NC-UN / Agr eement for Delivery of Outpu ts: Provision of Desert Locust Component 1: Immediate UN Agencies (Dire Control, Emergency Support IDA / D6300 Basic Services and Livelihoo Prior Direct 41,156,567.00 Signed 2020-07-09 2020-07-10 2020-07-14 2020-07-10 2020-08-18 2020-08-10 2021-02-14 ct) to affected communities, and d Support Re-establish the Desert Locu st Surveillance and Control S ystem. SO-MOF-190204-NC-DIR / No n-consulting Service contract with the INGO- Building Resil Component 1: Immediate ience Communities in Somali IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 14,142,000.00 Signed 2020-12-31 2020-10-28 2021-01-05 2021-02-24 2021-02-09 2022-01-28 2021-08-08 a (BRC for the implementatio d Support n of Immediate basic service s and livelihood support for e arly recovery SO-MOF-217511-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire OUTPUTS WITH UNICEF: SOM IDA / D6300 Prior Direct 0.00 Canceled 2021-03-15 2021-03-20 2021-04-24 2021-10-21 Emergency Response ct) ALIA COVID-19 OUTBREAK RE SPONSE UNDER SOMALIA CRI SIS RESPONSE SO-MOF-223676-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire IDA / D6300 Prior Direct 871,500.00 Signed 2021-04-30 2021-04-07 2021-05-05 2021-04-12 2021-06-09 2021-08-14 2021-12-06 OUTPUTS WITH IOM- SOMALI Emergency Response ct) A COVID-19 RESPONSE UNDE R SCRP SO-MOF-223678-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire IDA / D6300 Prior Direct 8,175,120.00 Signed 2021-04-30 2021-04-07 2021-05-05 2021-04-12 2021-06-09 2021-05-08 2021-12-06 OUTPUTS WITH WHO - SOMA Emergency Response ct) LIA COVID-19 RESPONSE UN DER SCRP PROJECT SO-MOF-223679-NC-DIR / Ag reement with SomRep consor Component 1: Immediate tia for the provision of Early IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 10,681,000.00 Signed 2021-04-30 2021-04-12 2021-05-05 2021-04-29 2021-06-09 2022-07-12 2021-12-06 Recovery Support to The Floo d Support d Affected Communities in Hi rshabelle, Jubaland And Sout hwest SO-MOF-223686-NC-DIR / Ag reement with NEXUS Consort Component 1: Immediate ia for the provision of early r IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 0.00 Canceled 2021-05-31 2021-08-05 2021-06-05 2021-07-10 2022-01-06 ecovery Support to The Flood d Support Affected Communities in Hirs habelle, Jubaland And South west States of Somalia SO-MOF-226047-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire OUTPUTS WITH UNICEF: SOM IDA / D6300 Prior Direct 4,416,509.11 Signed 2021-03-31 2021-03-23 2021-04-05 2021-04-01 2021-05-10 2021-04-26 2021-11-06 Emergency Response ct) ALIA COVID-19 OUTBREAK RE SPONSE UNDER SOMALIA CRI SIS RESPONSE SO-MOF-328356-NC-DIR / Str Component 3: Longer-Ter engthening medical emergen Direct - Internation Under Imple IDA / D8730 m Disaster Risk Preparednes Prior Direct Selection 0.00 2022-12-01 2023-01-02 2022-12-06 2023-02-27 2023-01-10 2023-07-09 cy services including intensiv al mentation s e care units for Federal & Sta te referral hospitals SO-MOF-333084-NC-DIR / Ca Component 3: Longer-Ter Direct - Internation Under Imple pacity Building of Somalia Se IDA / D8730 m Disaster Risk Preparednes Prior Direct Selection 0.00 2023-02-28 2023-04-14 2023-03-05 2023-05-17 2023-04-09 2023-10-06 al mentation ed Systems Recovery Initiati s ve (SSRI) SO-MOF-373546-NC-DIR / Str Component 3: Longer-Ter Direct - Internation Under Imple engthening and Linking Fede IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection 0.00 2023-07-31 2023-10-10 2023-08-05 2023-09-09 2025-03-02 al mentation ral & State Early Warning Sys s tems SO-MOF-383788-NC-DIR / De Component 3: Longer-Ter livery, installation, commissi Pending Impl IDA / D6300 m Disaster Risk Preparednes Post Direct Selection Direct - National 0.00 2023-09-30 2023-10-05 2023-11-09 2024-05-07 oning and maintenance of on ementation s e year for PSA oxygen plant t o Southwest state. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-183832-CS-CDS / Te chnical assistance agency for Component 4: Project Manag UN Agencies (Dire IDA / D6300 Prior Direct 4,437,254.00 Signed 2020-08-28 2020-09-28 2022-08-28 the provision of Project Mana ement ct) gement Support SO-MOF-187653-CS-QCBS / Component 4: Project Manag Least Cost Selecti Open - Internationa SCRP Project Audit and Indep IDA / D6300 Prior 406,932.40 Signed 2020-10-31 2020-11-05 2020-11-21 2020-11-19 2021-01-04 2021-02-24 2021-02-01 2021-04-03 2021-03-03 2021-06-28 2021-04-07 2021-09-30 2021-05-12 2021-12-03 2021-11-08 ement on l endent Verification Agent IVA SO-MOF-188776-CS-UN / De Component 2: Medium-Ter UN Agencies (Dire velopment of Designs & Supe IDA / D6300 Prior Direct 0.00 Canceled 2020-11-09 2021-05-08 m Flood Recovery ct) rvision of Construction Works SO-MOF-318290-CS-QCBS / Component 3: Longer-Ter Consultancy service to stren Quality And Cost- Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2022-11-30 2022-11-28 2022-12-21 2022-12-14 2023-02-03 2023-05-04 2023-03-03 2023-06-28 2023-04-02 2023-05-07 2023-06-11 2024-06-10 gthen Hydromet service diss Based Selection ation s emination and community en gagement Page 9 SO-MOF-328349-CS-FBS / Co Component 3: Longer-Ter Fixed Budget Sele Under Implement nsultancy Service for Strengt IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2022-12-10 2022-12-14 2022-12-31 2023-03-09 2023-02-13 2023-07-19 2023-03-13 2023-08-20 2023-04-12 2023-05-17 2023-06-21 2024-06-20 ction ation hening Hydro-Met and Hazar s d Monitoring SO-MOF-328353-CS-FBS / Co Component 3: Longer-Ter nsultancy Service to Strength Fixed Budget Sele Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2022-12-10 2022-12-14 2022-12-31 2023-01-11 2023-02-13 2023-07-19 2023-03-13 2023-04-12 2023-05-17 2023-06-21 2024-06-20 en Hydromet Service Dissemi ction ation s nation and Community Enga gement SO-MOF-333116-CS-CQS / C onsultancy Services for the d Component 3: Longer-Ter evelopment of a Basin Diagn Quality And Cost- Open - Internationa Under Implement IDA / D8730 m Disaster Risk Preparednes Prior 0.00 2023-03-31 2023-03-13 2023-04-21 2023-04-14 2023-06-04 2023-07-19 2023-07-02 2023-08-20 2023-08-01 2023-09-05 2023-10-10 2024-10-09 ostic and a Strategic Action P Based Selection l ation s lan for the Juba Basin, Somali a, and preparation of prioritiz ed action projects SO-MOF-346332-CS-LCS / Pr Component 3: Longer-Ter ovision of Consulting Service Consultant Qualifi IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 Canceled 2023-03-31 2023-03-15 2023-04-14 2023-05-14 2023-06-18 2023-12-15 s for Mogadishu's Water Secu cation Selection s rity Diagnostic Study SO-MOF-347690-CS-QCBS / Component 6: Anticipatory a Consulting Service - Capacity Quality And Cost- Open - Internationa Under Implement IDA / D8730 nd Recovery Support for Add Prior 0.00 2023-03-31 2023-05-19 2023-04-21 2023-05-31 2023-06-04 2023-10-30 2023-07-02 2023-08-01 2023-09-05 2023-10-10 2024-10-09 Assessment of Federal and S Based Selection l ation ressing Food Insecurity tate level Ministries of Agricu lture and Irrigation SO-MOF-348357-CS-CQS / P Component 3: Longer-Ter ublic Private Engagement (PP Consultant Qualifi Pending Impleme IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-03-31 2023-04-14 2023-05-14 2023-06-18 2023-12-15 E) to strengthen Hydro-mete cation Selection ntation s orological services SO-MOF-352038-CS-CQS / C Component 3: Longer-Ter onsulting Services - Assessm Consultant Qualifi Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-04-30 2023-05-14 2023-06-13 2023-07-18 2024-01-14 ent & Delivery of Design & C cation Selection ation s ost Estimation for Eight Regi onal Hospitals SO-MOF-358654-CS-CQS / T Component 3: Longer-Ter echnical assistance to suppor Consultant Qualifi Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-16 2023-06-14 2023-07-14 2023-08-18 2024-02-14 t Mogadishu's Water Security cation Selection ation s Diagnostic Study SO-MOF-358661-CS-QCBS / Component 3: Longer-Ter Provision of Consulting Servic Quality And Cost- Pending Impleme IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-01 2023-12-01 2024-01-05 2024-02-09 2025-02-08 es for Mogadishu's Water Sec Based Selection ntation s urity Diagnostic Study SO-MOF-375021-CS-QCBS / Component 3: Longer-Ter Quality And Cost- Under Implement Strengthening the Coordinati IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-08-05 2023-08-07 2023-08-26 2023-08-29 2023-10-09 2023-10-26 2023-11-06 2023-12-06 2024-01-10 2024-02-14 2025-02-13 Based Selection ation on of National Resilience Buil s ding SO-MOF-393131-CS-CQS / As Component 4: Project Manag Consultant Qualifi Pending Impleme sessment of beneficiary satis IDA / D6300 Post Limited 0.00 2023-11-30 2023-12-14 2024-01-13 2024-02-17 2024-08-15 ement cation Selection ntation faction for SCRP Project. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-183841-CS-INDV / H Component 5: Contingent Individual Consult ealth/COVID19 Response Faci IDA / D6300 Prior Limited 120,000.00 Signed 2020-08-20 2020-08-19 2020-08-27 2020-12-12 2020-09-01 2021-01-07 2020-09-04 2021-02-03 2021-06-01 Emergency Response ant Selection litation Consultant SO-MOF-186983-CS-CDS / Fo Component 3: Longer-Ter recasting, Aid Tracking Syste IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 769,060.00 Signed 2020-08-31 2020-11-16 2020-09-10 2020-12-19 2020-11-14 2021-04-09 2021-05-13 m & Needs Assessment to Int s egrate COVID-19 Country Wi de efforts SO-MOF-184256-CS-INDV / R Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 227,880.00 Signed 2020-08-17 2020-09-03 2020-08-22 2020-10-07 2020-09-12 2020-10-09 2020-10-17 2020-10-24 2021-04-15 ecovery Planning Specialist ement ant Selection SO-MOF-183833-CS-QCBS / Component 4: Project Manag Security Risk Management C IDA / D6300 Prior Direct Selection Direct 1,581,419.71 Signed 2020-10-31 2020-09-04 2020-11-10 2020-09-23 2021-01-14 2021-01-25 2021-07-13 ement onsulting Services SO-MOF-183838-CS-INDV / Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 140,400.00 Completed 2020-08-15 2020-09-03 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-10-07 2021-04-18 2022-01-02 Monitoring & Evaluation Spec ement ant Selection ialist SO-MOF-183836-CS-INDV / F Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 213,780.00 Signed 2020-08-15 2020-09-04 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-10-10 2021-04-18 inancial Management Special ement ant Selection ist SO-MOF-183837-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 213,780.00 Signed 2020-08-15 2020-09-03 2020-08-20 2020-09-09 2020-09-10 2020-09-17 2020-10-15 2020-10-10 2021-04-13 roject Engineer ement ant Selection SO-MOF-183834-CS-CDS / Pr Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 334,440.00 Signed 2020-08-15 2020-09-03 2020-08-25 2020-09-01 2020-09-15 2020-09-17 2020-10-20 2020-10-10 2021-04-18 oject Coordinator ement ant Selection SO-MOF-183835-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 222,420.00 Signed 2020-08-15 2020-09-04 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-10-10 2021-04-18 rocurement Specialist ement ant Selection SO-MOF-183839-CS-INDV / E Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 70,200.00 Signed 2020-08-15 2020-09-03 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-10-08 2021-04-18 nvironmental Safeguard Spe ement ant Selection cialist SO-MOF-183157-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-07-09 2020-07-09 2020-07-14 2020-08-04 2020-09-08 2021-03-07 ocial Development Specialist ement ant Selection SO-MOF-187526-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-08-15 2020-08-20 2020-09-10 2020-10-15 2021-04-13 ocial Development Specialist ement ant Selection SO-MOF-190535-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 140,400.00 Signed 2020-10-31 2020-10-05 2020-11-05 2020-12-09 2020-11-26 2020-12-15 2020-12-31 2020-12-28 2021-06-29 takeholder Engagement Spec ement ant Selection ialist SO-MOF-190539-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 65,035.00 Terminated 2020-10-31 2020-10-05 2020-11-05 2021-02-25 2020-11-26 2021-03-01 2020-12-31 2021-03-10 2021-06-29 roject Administrative Officer ement ant Selection SO-MOF-190541-CS-INDV / T Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 105,600.00 Signed 2020-12-31 2020-11-05 2021-01-05 2020-11-16 2021-01-26 2020-11-20 2021-03-02 2020-12-15 2021-08-29 oll-free Hotline Operator (GR ement ant Selection M) Page 10 SO-MOF-190545-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 52,800.00 Completed 2020-11-30 2020-10-05 2020-12-05 2021-03-22 2020-12-26 2021-04-21 2021-01-30 2021-05-25 2021-07-29 2022-05-25 roject Security Officer ement ant Selection SO-MOF-190709-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 229,320.00 Signed 2020-08-31 2020-10-05 2020-09-05 2020-08-18 2020-09-26 2020-10-08 2020-10-31 2020-09-11 2021-04-29 ocial Development Specialist ement ant Selection SO-MOF-196562-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 0.00 Signed 2020-11-15 2020-11-16 2021-01-03 2022-03-03 2021-01-24 2022-03-14 2021-02-28 2023-03-30 2021-08-27 ement ant Selection er, Hirshabelle State Project Team SO-MOF-196565-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 82,200.00 Signed 2020-12-15 2020-11-16 2021-02-02 2021-05-17 2021-02-23 2021-06-07 2021-03-30 2021-06-21 2021-09-26 ement ant Selection er, Southwest State Project T eam SO-MOF-196570-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 82,200.00 Signed 2020-11-15 2020-11-16 2021-01-03 2021-05-17 2021-01-24 2021-06-06 2021-02-28 2021-06-21 2021-08-27 roject Engineer, Southwest St ement ant Selection ate SO-MOF-196571-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 40,320.00 Signed 2020-12-15 2020-11-16 2021-02-02 2022-01-09 2021-02-23 2022-01-19 2021-03-30 2022-02-22 2021-09-26 roject Engineer, Hirshabelle S ement ant Selection tate SO-MOF-196572-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 102,120.00 Signed 2020-11-15 2020-11-16 2021-01-03 2021-05-19 2021-01-24 2021-06-06 2021-02-28 2021-06-17 2021-08-27 roject Coordinator, Southwes ement ant Selection t SPT SO-MOF-196574-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 49,920.00 Signed 2020-12-15 2020-11-16 2021-02-02 2022-01-09 2021-02-23 2022-01-19 2021-03-30 2022-02-22 2021-09-26 roject Coordinator, Hirshabell ement ant Selection e SPT SO-MOF-197348-CS-INDV / G Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 105,600.00 Signed 2020-10-31 2020-11-16 2020-11-05 2021-02-07 2020-11-26 2021-02-12 2020-12-31 2021-02-21 2021-06-29 BV Officer ement ant Selection SO-MOF-196560-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 0.00 Canceled 2020-12-31 2020-11-25 2021-02-18 2021-03-11 2021-04-15 2021-10-12 ement ant Selection er, Jubalad SPT SO-MOF-196555-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2020-12-31 2020-11-25 2021-02-18 2022-03-17 2021-03-11 2022-03-23 2021-04-15 2023-04-18 2021-10-12 roject Coordinator, Jubaland ement ant Selection State SPT SO-MOF-196556-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2020-12-31 2020-11-25 2021-02-18 2022-03-17 2021-03-11 2022-03-23 2021-04-15 2023-04-28 2021-10-12 roject Engineer, Jubaland SPT ement ant Selection SO-MOF-196568-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 82,200.00 Signed 2020-12-15 2020-11-25 2021-02-02 2021-05-17 2021-02-23 2021-06-06 2021-03-30 2021-06-21 2021-09-26 ement ant Selection er, Southwest SPT SO-MOF-196567-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 40,320.00 Signed 2020-12-31 2020-11-30 2021-02-18 2022-01-09 2021-03-11 2022-01-19 2021-04-15 2022-02-10 2021-10-12 ement ant Selection er, Hirshabelle SPT SO-MOF-196558-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 0.00 Canceled 2020-12-31 2020-11-30 2021-02-18 2021-03-11 2021-04-15 2021-10-12 ement ant Selection er, Jubaland SPT SO-MOF-210970-CS-INDV / Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 140,400.00 Signed 2021-01-31 2021-02-10 2021-02-05 2021-03-04 2021-02-26 2021-03-17 2021-04-02 2021-04-01 2021-09-29 MOH Senior Coordinator for S m Disaster Risk Preparednes ant Selection CRP Project s SO-MOF-214330-CS-INDV / F Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 118,560.00 Signed 2021-02-28 2021-02-09 2021-03-05 2021-05-10 2021-03-26 2021-06-06 2021-04-30 2021-04-03 2021-10-27 inancial Specialist, MOH m Disaster Risk Preparednes ant Selection s SO-MOF-214331-CS-INDV / Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 77,400.00 Signed 2021-03-01 2021-03-15 2021-03-06 2021-03-04 2021-03-27 2021-03-18 2021-05-01 2021-03-27 2021-10-28 MOH Communication Officer m Disaster Risk Preparednes ant Selection s SO-MOF-210968-CS-INDV / Component 5: Contingent Individual Consult MOH COVID-19 RESPONSE & IDA / D6300 Prior Limited 139,617.75 Signed 2021-03-31 2021-03-15 2021-04-05 2021-03-04 2021-04-26 2021-03-18 2021-05-31 2021-03-24 2021-11-27 Emergency Response ant Selection RECOVERY COORDINATOR SO-MOF-217509-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 164,040.00 Signed 2021-04-30 2021-04-16 2021-05-10 2021-05-17 2021-05-31 2021-06-07 2021-07-05 2021-06-21 2022-01-01 CRP Operations Manager ement ant Selection SO-MOF-190538-CS-INDV / C Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-10-31 2020-10-05 2020-11-05 2020-11-26 2020-12-31 2021-06-29 ommunication Specialist ement ant Selection SO-MOF-229866-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open 0.00 2021-04-30 2021-05-21 2021-06-18 2021-07-09 2021-08-13 2022-02-09 IU Communications Specialist ement ant Selection ation SO-MOF-239607-CS-CDS / A GREEMENT FOR DELIVERY OF Component 4: Project Manag IDA / D6300 Prior Direct Selection Direct 0.00 Canceled 2021-07-01 2021-07-11 2021-09-14 2022-03-13 OUTPUTS WITH UNOPS: TECH ement NICAL STUDIES & DESIGN SO-MOF-188776-CS-UN-2 / P Component 2: Medium-Ter Under Implement rovision of Design and Super IDA / D6300 Prior Direct Selection Direct 0.00 2021-08-15 2021-08-25 2021-10-29 2022-04-27 m Flood Recovery ation vision of Flood and Irrigation System with FAO SO-MOF-256503-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open 0.00 2021-10-20 2021-10-22 2021-12-08 2022-03-24 2021-12-29 2022-03-29 2022-02-02 2022-08-01 nvironmental Safeguard Spe ement ant Selection ation cialist SO-MOF-260028-CS-CDS / Pr ovision of Technical Studies a Component 4: Project Manag Under Implement IDA / D6300 Prior Direct Selection Direct 0.00 2021-11-05 2022-01-20 2021-11-15 2022-01-19 2022-07-18 nd Design Services as part of ement ation the Somalia Crisis Recovery Project SO-MOF-273757-CS-INDV / Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2022-02-28 2022-02-07 2022-04-18 2022-06-07 2022-05-09 2022-06-13 2022-06-13 2023-06-21 2022-12-10 Monitoring and Evaluation Sp ement ant Selection ecialist SO-MOF-277118-CS-CDS / Te Component 3: Longer-Ter chnical Advisor for National E Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 0.00 2022-03-31 2022-03-30 2022-04-10 2022-04-13 2022-06-14 2022-12-11 mergency Operation Centre ( ation s NEOC), Office of the Prime Mi nster SO-MOF-277127-CS-CDS / C Component 3: Longer-Ter ommunication Consultant, N IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 0.00 Signed 2022-03-31 2022-03-30 2022-04-10 2022-04-13 2022-06-14 2022-05-02 2022-12-11 ational Emergency Operation s Centre (NEOC) - Office of the Prime Minster SO-MOF-276900-CS-CDS / C Component 5: Contingent Under Implement ERC Coordinator for Banadir IDA / D6300 Prior Direct Selection Direct 0.00 2022-03-31 2022-04-05 2022-04-10 2022-04-13 2022-06-14 2022-12-11 Emergency Response ation Regional Administration (BRA ) Page 11 SO-MOF-276905-CS-CDS / C Component 5: Contingent Under Implement ERC Finance Specialist for Ba IDA / D6300 Prior Direct Selection Direct 0.00 2022-03-31 2022-04-05 2022-04-10 2022-04-13 2022-06-14 2022-12-11 Emergency Response ation ndir Regional Administration SO-MOF-307794-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2022-08-31 2022-08-25 2022-09-05 2022-12-06 2022-09-26 2023-02-22 2022-10-31 2023-04-29 roject Security Officer ement ant Selection ation SO-MOF-307795-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-08-25 2022-10-19 2023-02-25 2022-11-09 2023-05-11 2022-12-14 2023-06-12 roject Admin Officer ement ant Selection ation SO-MOF-307796-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement nvironmental and Social Safe IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-09-19 2022-10-19 2023-04-27 2022-11-09 2023-05-11 2022-12-14 2023-06-12 ement ant Selection ation guard Officer, Jubaland SPT SO-MOF-307798-CS-INDV / Component 4: Project Manag Individual Consult Under Implement Monitoring and evaluation off IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-09-26 2022-10-19 2023-02-15 2022-11-09 2023-05-11 2022-12-14 2023-06-12 ement ant Selection ation icer, Jubaland SPT SO-MOF-316799-CS-CDS / C Component 4: Project Manag ontract Management and Pro IDA / D6300 Prior Direct Selection Direct - National 0.00 Signed 2022-11-30 2022-10-12 2022-12-10 2022-10-22 2023-02-13 2022-11-09 2023-08-12 ement curement Specialist, PIU SO-MOF-322581-CS-INDV / D Component 3: Longer-Ter rought Management Advisor Individual Consult Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2022-10-31 2022-11-08 2022-11-05 2023-01-25 2022-11-26 2023-03-13 2022-12-31 2023-06-29 for the office of Somalia spec ant Selection ation s ial envoy for drought respons e SO-MOF-322582-CS-INDV / R esource Mobilization and Don Component 3: Longer-Ter Individual Consult Under Implement or Relations Advisor for the o IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2022-10-31 2022-11-08 2022-11-05 2023-01-25 2022-11-26 2023-03-07 2022-12-31 2023-06-29 ant Selection ation ffice of Somalia’s special env s oy for drought response SO-MOF-328720-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-10 2022-12-14 2022-12-15 2023-03-01 2023-01-05 2023-06-14 2023-02-09 2023-08-08 rocurement officer, PIU ement ant Selection ation SO-MOF-328721-CS-INDV / F Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-10 2022-12-14 2022-12-15 2023-03-01 2023-01-05 2023-06-12 2023-02-09 2023-08-08 inance Officer, PIU ement ant Selection ation SO-MOF-333068-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-31 2023-01-17 2023-01-05 2023-01-26 2023-03-02 2023-08-29 IU Communication Officer ement ant Selection ation SO-MOF-333073-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D8730 Prior Open - National 0.00 2022-12-31 2023-08-21 2023-02-18 2023-03-11 2023-04-15 2023-10-12 nesthetics/Intensivist Consult m Disaster Risk Preparednes ant Selection ation ant s SO-MOF-333077-CS-INDV / B Component 3: Longer-Ter Individual Consult Under Implement lood Bank Technologist for R IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection ation egional Referral Hospitals s SO-MOF-333079-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement IDA / D8730 Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 mergency Medicine Consulta m Disaster Risk Preparednes ant Selection ation nt s SO-MOF-333082-CS-INDV / Component 3: Longer-Ter Individual Consult Under Implement Medical Laboratory Consulta IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection ation nt for Regional Referral Hospi s tals SO-MOF-331702-CS-INDV / C Component 4: Project Manag Individual Consult IDA / D8730 Post Limited 0.00 Canceled 2022-12-29 2023-01-03 2023-01-24 2023-02-28 2023-08-27 ommunication Officer, PIU ement ant Selection SO-MOF-333083-CS-INDV / I Component 3: Longer-Ter Individual Consult ntegration and Organizationa IDA / D8730 m Disaster Risk Preparednes Post Open - National 0.00 Canceled 2022-12-31 2023-02-13 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection l Development Consultant for s NEOC/SODMA SO-MOF-344251-CS-INDV / F Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Direct - National 0.00 2023-02-25 2023-03-10 2023-03-07 2023-03-14 2023-03-28 2023-03-20 2023-05-02 2023-10-29 inancial Management Special ement ant Selection ation ist SO-MOF-344255-CS-INDV / I Component 3: Longer-Ter Individual Consult Under Implement ntegration and Organizationa IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-02-28 2023-04-10 2023-03-05 2023-10-23 2023-03-26 2023-04-30 2023-10-27 ant Selection ation l Consultant for NEOC/SODM s A SO-MOF-350971-CS-CDS / C ONSULTING SERVICES TO SU Component 4: Project Manag Direct - Internation Under Implement IDA / D6300 Prior Direct Selection 0.00 2023-04-30 2023-06-08 2023-05-10 2023-06-17 2023-07-14 2024-01-10 PPORT THE SCRP PROJECT WI ement al ation TH SECURITY RISK MANAGEM ENT SO-MOF-357102-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-11 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Banadir Hospital, Benadi s r Region SO-MOF-357104-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-11 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Martini Hospital, Benadir s Region SO-MOF-357112-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-17 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Hirshabelle State of Som s alia SO-MOF-357113-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt – Jubbaland State of Somal s ia SO-MOF-357115-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-17 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Government of Somalila s nd SO-MOF-357116-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt – Galmudug State of Soma s lia SO-MOF-357117-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt - Southwest State of Soma s lia SO-MOF-357119-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-07-31 2023-05-17 2023-08-05 2023-08-26 2023-09-30 2024-03-28 ant Selection ation nt – Puntland State of Somali s a Page 12 SO-MOF-328359-CS-INDV / S Component 3: Longer-Ter Individual Consult enior Health Emergency Prep IDA / D8730 m Disaster Risk Preparednes Post Direct - National 0.00 Canceled 2022-12-10 2023-01-17 2022-12-20 2023-01-10 2023-02-14 2023-08-13 ant Selection aredness & Response Adviso s r SO-MOF-357121-CS-INDV / S Component 3: Longer-Ter Individual Consult Under Implement enior Health emergency prep IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2023-06-30 2023-05-15 2023-08-18 2023-10-15 2023-09-08 2023-10-13 2024-04-10 ant Selection ation aredness and Response Advi s sor SO-MOF-357128-CS-INDV / S Component 3: Longer-Ter enior Medical Technical Advis Individual Consult Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2023-05-31 2023-05-15 2023-07-19 2023-07-19 2023-08-09 2023-09-13 2023-09-13 2024-03-11 or for the Ministry of Health ant Selection ation s & Human Services SO-MOF-362318-CS-INDV / V Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2023-06-30 2023-08-10 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ector Control Advisor m Disaster Risk Preparednes ant Selection ation s SO-MOF-362320-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2023-06-30 2023-08-06 2023-07-05 2023-07-26 2023-08-30 2024-02-26 nimal Health Advisor m Disaster Risk Preparednes ant Selection ation s SO-MOF-362323-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, Vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-08-06 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation ol for Southwest State s SO-MOF-362418-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-08-06 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation ol in Jubaland State s SO-MOF-362421-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-07-31 2023-08-06 2023-08-05 2023-08-26 2023-09-30 2024-03-28 ant Selection ation ol in Hirshabelle State s SO-MOF-362428-CS-INDV / C Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2023-06-20 2023-07-11 2023-08-08 2023-10-30 2023-08-29 2023-10-03 2024-03-31 apacity building specialist, N m Disaster Risk Preparednes ant Selection ation EOC s SO-MOF-362432-CS-INDV / I Component 3: Longer-Ter Individual Consult Under Implement nformation management spe IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2023-06-20 2023-07-11 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection ation cialist, NEOC s SO-MOF-362434-CS-INDV / N Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2023-06-20 2023-08-21 2023-08-08 2023-08-29 2023-10-03 2024-03-31 EOC Coordinator m Disaster Risk Preparednes ant Selection ation s SO-MOF-362438-CS-INDV / N Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-21 2023-08-08 2023-08-29 2023-10-03 2024-03-31 EOC Deputy Coordinator m Disaster Risk Preparednes ant Selection s SO-MOF-362440-CS-INDV / D Component 3: Longer-Ter Individual Consult Under Implement isaster Risk Management (DR IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2023-06-20 2023-08-21 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection ation M) specialist s SO-MOF-366795-CS-INDV / O Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2023-06-20 2023-08-21 2023-08-08 2023-08-29 2023-10-03 2024-03-31 perations Manager, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-366797-CS-INDV / P Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-21 2023-08-08 2023-08-29 2023-10-03 2024-03-31 olicy & Planning Advisor, NE m Disaster Risk Preparednes ant Selection OC s SO-MOF-366804-CS-INDV / P Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2023-06-20 2023-08-21 2023-08-08 2023-08-29 2023-10-03 2024-03-31 rocurement & Logistics Office m Disaster Risk Preparednes ant Selection ation r, NEOC s SO-MOF-366805-CS-INDV / Li Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2023-06-21 2023-08-21 2023-08-09 2023-08-30 2023-10-04 2024-04-01 aison Officer, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-366806-CS-INDV / P Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2023-06-20 2023-08-21 2023-08-08 2023-08-29 2023-10-03 2024-03-31 lanning Officer, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-366808-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement nvironmental & Safeguard Sp IDA / D8730 Prior Open - National 0.00 2023-06-20 2023-07-14 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ement ant Selection ation ecialist, PIU SO-MOF-374996-CS-INDV / S Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 0.00 2023-08-05 2023-08-21 2023-09-23 2023-10-14 2023-11-18 2024-05-16 afety and Security Manager, m Disaster Risk Preparednes ant Selection ation NEOC s SO-MOF-375000-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 0.00 2023-08-05 2023-08-21 2023-09-23 2023-10-14 2023-11-18 2024-05-16 dmin and Finance officer m Disaster Risk Preparednes ant Selection ation s SO-MOF-375003-CS-INDV / R Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 0.00 2023-08-05 2023-10-28 2023-09-23 2023-10-14 2023-11-18 2024-05-16 isk Management Officer, NEO m Disaster Risk Preparednes ant Selection ation C s SO-MOF-375007-CS-INDV / I Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 0.00 2023-08-05 2023-08-21 2023-09-23 2023-10-14 2023-11-18 2024-11-17 CT Systems Specialist, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-375012-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement inancial & risk management IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-08-05 2023-09-23 2023-10-14 2023-11-18 2024-11-17 ant Selection ation specialist, NEOC s SO-MOF-375014-CS-INDV / I Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Post Open - National 0.00 2023-08-05 2023-08-21 2023-09-23 2023-10-14 2023-11-18 2024-11-17 CT Officer, NEOC m Disaster Risk Preparednes ant Selection ation s SO-MOF-377884-CS-INDV / D Component 3: Longer-Ter Individual Consult Pending Impleme atabase /System Developer C IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-09-28 2024-01-26 ant Selection ntation onsultant, NEOC s SO-MOF-375016-CS-INDV / O Component 3: Longer-Ter Individual Consult Pending Impleme rganizational Development S IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-08-19 2023-10-07 2023-10-28 2023-12-02 2024-05-30 ant Selection ntation pecialist (international), NEO s C SO-MOF-375018-CS-INDV / D Component 3: Longer-Ter Individual Consult Pending Impleme IDA / D6300 Post Open - National 0.00 2023-08-19 2023-10-07 2023-10-28 2023-12-02 2024-05-30 RM specialist (international), m Disaster Risk Preparednes ant Selection ntation NEOC s SO-MOF-378294-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2023-08-26 2023-10-05 2023-10-14 2023-11-04 2023-12-09 2024-06-06 rocurement Specialist, PIU ement ant Selection ation SO-MOF-382916-CS-INDV / L Component 3: Longer-Ter Individual Consult Pending Impleme aboratory Consultant - De Ma IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-09-25 2023-11-13 2023-12-04 2024-01-08 2024-07-06 ant Selection ntation rtini Hospital s Page 13 SO-MOF-382918-CS-INDV / L Component 3: Longer-Ter Individual Consult Pending Impleme aboratory Consultant - Banad IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-09-25 2023-11-13 2023-12-04 2024-01-08 2024-07-06 ant Selection ntation ir Hospital s SO-MOF-382920-CS-INDV / L Component 3: Longer-Ter Individual Consult Pending Impleme IDA / D6300 Post Open - National 0.00 2023-09-25 2023-11-13 2023-12-04 2024-01-08 2024-07-06 aboratory Consultant - Jowha m Disaster Risk Preparednes ant Selection ntation r Hospital s SO-MOF-383300-CS-INDV / L Component 3: Longer-Ter Individual Consult Pending Impleme aboratory Consultant - Adado IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ntation general hospital s SO-MOF-383302-CS-INDV / L Component 3: Longer-Ter Individual Consult Pending Impleme aboratory Consultant - Bay R IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ntation egional Hospital s SO-MOF-383303-CS-INDV / L Component 3: Longer-Ter Individual Consult Pending Impleme aboratory Consultant - Kisma IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ntation yo Regional Hospital s SO-MOF-383306-CS-INDV / L Component 3: Longer-Ter Individual Consult Pending Impleme aboratory Consultant - Garow IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ntation e General Hospital s SO-MOF-383310-CS-INDV / R Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist -De Martini m Disaster Risk Preparednes ant Selection s SO-MOF-383728-CS-INDV / R Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Banadir Referral m Disaster Risk Preparednes ant Selection Hospital s SO-MOF-383732-CS-INDV / R Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Bay Regional Hos m Disaster Risk Preparednes ant Selection pital s SO-MOF-383735-CS-INDV / R Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Adado General H m Disaster Risk Preparednes ant Selection ospital s SO-MOF-383737-CS-INDV / R Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Garowe General m Disaster Risk Preparednes ant Selection Hospital s SO-MOF-383738-CS-INDV / R Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Kismayo Regional m Disaster Risk Preparednes ant Selection Hospital s SO-MOF-383752-CS-INDV / R Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-04 2023-11-18 2023-12-09 2024-01-13 2024-07-11 adiologist - Jowhar Hospital m Disaster Risk Preparednes ant Selection s SO-MOF-383753-CS-INDV / A Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 nesthesiologist - De Martini m Disaster Risk Preparednes ant Selection s SO-MOF-383755-CS-INDV / A Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 nesthesiologist - Banadir hos m Disaster Risk Preparednes ant Selection pital s SO-MOF-383756-CS-INDV / A Component 3: Longer-Ter Individual Consult nesthesiologist - Garowe gen IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 Under Review 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection eral hospital s SO-MOF-383761-CS-INDV / A Component 3: Longer-Ter Individual Consult nesthesiologist - Adado gene IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 Under Review 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ral hospital s SO-MOF-383765-CS-INDV / A Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 nesthesiologist - Bay regional m Disaster Risk Preparednes ant Selection hospital s SO-MOF-383767-CS-INDV / A Component 3: Longer-Ter Individual Consult nesthesiologist - Kismayo reg IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 Under Review 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ional hospital s SO-MOF-383768-CS-INDV / A Component 3: Longer-Ter Individual Consult IDA / D6300 Post Open - National 0.00 Under Review 2023-09-30 2023-11-06 2023-11-18 2023-12-09 2024-01-13 2024-07-11 nesthesiologist - Jowhar hosp m Disaster Risk Preparednes ant Selection ital s SO-MOF-383769-CS-INDV / H Component 3: Longer-Ter Individual Consult Pending Impleme IDA / D6300 Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - De Martini m Disaster Risk Preparednes ant Selection ntation s SO-MOF-383771-CS-INDV / H Component 3: Longer-Ter Individual Consult Pending Impleme IDA / D6300 Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - Banadir hospita m Disaster Risk Preparednes ant Selection ntation l s SO-MOF-383772-CS-INDV / H Component 3: Longer-Ter Individual Consult Pending Impleme IDA / D6300 Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - Garowe genera m Disaster Risk Preparednes ant Selection ntation l hospital s SO-MOF-383773-CS-INDV / H Component 3: Longer-Ter Individual Consult Pending Impleme IDA / D6300 Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - Adado general m Disaster Risk Preparednes ant Selection ntation hospital s SO-MOF-383774-CS-INDV / H Component 3: Longer-Ter Individual Consult Pending Impleme IDA / D6300 Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ematologist - Bay regional ho m Disaster Risk Preparednes ant Selection ntation spital s SO-MOF-383775-CS-INDV / H Component 3: Longer-Ter Individual Consult Pending Impleme ematologist - Kismayo region IDA / D6300 m Disaster Risk Preparednes Post Open - National 0.00 2023-09-30 2023-11-18 2023-12-09 2024-01-13 2024-07-11 ant Selection ntation al hospital s SO-MOF-383777-CS-INDV / H Component 3: Longer-Ter Individual Consult Pending Impleme IDA / D6300 Post Open - National 0.00 2023-09-29 2023-11-17 2023-12-08 2024-01-12 2024-07-10 ematologist - Jowhar hospita m Disaster Risk Preparednes ant Selection ntation l s SO-MOF-393088-CS-CDS / Pr Component 4: Project Manag Direct - Internation Pending Impleme IDA / D6300 Prior Direct Selection 0.00 2023-11-16 2023-11-26 2024-01-30 2025-05-14 oject Coordinator, PIU ement al ntation Page 14