PROCUREMENT PLAN (Textual Part) Project information: Tonga TCRTP2 (P176208) Project Implementation agency: Ministry of Infrastructure Date of the Procurement Plan: June 2021 Period covered by this Procurement Plan: June 2021 to June 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Procurement Regulations of 2015 (link below) such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts;; publication of contract award information; rights for the Bank http://finance.gov.to/node/166 When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT Tonga : Tonga Climate Resilient Transport Project II PLAN General Information Country: Tonga 2021-06-08 Bank’s Approval Date of the Original Procurement Plan: 2023-11-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176208 GPN Date: 2023-04-19 Project Name: Tonga Climate Resilient Transport Project II Loan / Credit No: IDA / D9110, / Ministry of Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B MOI-WK2-02 / Rehabilitation Component 2: Climate Resili ids - Small W Single Stage - One E 2025-12-0 of Liku Road (Haveluliku - Hoi / ent and Safe Infrastructure S Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2023-05-09 2023-06-12 2023-07-13 2023-09-07 2023-11-07 nvelope 8 ) Tongatapu (3km) olutions nvelope proc ess) Request for B Component 2: Climate Resili MOI-WK2-06 / Rehabilitation Single Stage - One E ids - Small W Pending Imp 2027-02-0 / ent and Safe Infrastructure S Post Request for Bids Open - National 0.00 2024-07-03 2024-08-06 2024-09-14 2024-11-01 2024-12-23 of Road Works in 'Eua 8km nvelope orks SPD (1 e lementation 3 olutions nvelope proc ess) Request for B MOI-WK2-01 / Rehabilitation Component 2: Climate Resili ids - Small W Single Stage - One E 2025-06-0 of Liku Road (Fua'amotu - 'Ut IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-10-07 2022-11-30 2022-11-10 2022-11-30 2022-12-10 2023-01-26 2023-02-04 2023-05-04 2023-04-21 nvelope 2 ulau) Tongatapu 3 Lots olutions nvelope proc ess) Request for B MOI-WK2-03 / Rehabilitation Component 2: Climate Resili Single Stage - One E ids - Small W 2025-06-1 of Hoi-Kolonga Road 6.3km, IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National 0.00 Canceled 2023-01-27 2023-02-10 2023-03-12 2023-04-02 2023-05-16 nvelope orks SPD (1 e 6 Tongatapu olutions nvelope proc ess) MOI-WK-3-TR-C3 / Rehabilita Request for B tion and Upgrading of Priority Component 2: Climate Resili ids - Small W Roads in Tongatapu, Lot 1 T5 Single Stage - One E 2024-09-1 IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National orks SPD (1 e 0.00 Signed 2023-03-08 2023-03-09 2023-03-09 2023-03-09 2023-04-18 2023-04-18 2023-05-09 2023-07-06 2023-06-22 2023-09-28 - Loto Road (Makapaeo - Mat nvelope 4 olutions nvelope proc ahau Road 3.6km), and Lot 2 ess) T1 - Taufa'ahau Road (Hoi-Ko longa Road 6.3km Request for B Component 2: Climate Resili MOI-WK2-09 / Resurfacing of Single Stage - One E ids - Small W Pending Imp 2025-01-0 IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National 0.00 2024-01-31 2024-02-07 2024-03-20 2024-04-19 2024-06-08 Kaufana Airport, 'Eua nvelope orks SPD (1 e lementation 9 olutions nvelope proc ess) MOI-WK2-08 / Port Repair an Request for B d Improvements, Breakwater Component 2: Climate Resili ids - Small W Single Stage - One E Pending Imp 2025-06-0 rehabilitation and constructio IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National orks SPD (1 e 0.00 2024-02-06 2024-02-20 2024-03-21 2024-05-05 2024-06-24 nvelope lementation 7 n - 2 Lots olutions nvelope proc Lot 1 - 'Eua ess) Lot 2 - Ha'apai Request for B Component 2: Climate Resili MOI-WK2-07 / Rehabilitation Single Stage - One E ids - Small W Pending Imp 2026-08-2 IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National 0.00 2024-01-31 2024-02-14 2024-03-20 2024-05-15 2024-07-29 of Roads at Vava'u East nvelope orks SPD (1 e lementation 7 olutions nvelope proc ess) Request for MOI-WK2-10 / Construction o Component 2: Climate Resili Quotations - Request for Quota Single Stage - One E Pending Imp 2024-12-0 f New Passenger Terminal at IDA / D9110 ent and Safe Infrastructure S Post Open - National Small Works 0.00 2024-02-27 2024-07-08 tions nvelope lementation 5 Nafanua Port, 'Eua olutions (Emergency) SPD -Compet itive Request for MOI-WK2-11 / Road Safety Component 2: Climate Resili Quotations - Works for Tongatapu and out Request for Quota Single Stage - One E Pending Imp 2025-11-2 IDA / D9110 ent and Safe Infrastructure S Post Open - National Small Works 0.00 2024-08-12 2024-11-21 er islands tions nvelope lementation 1 olutions (Emergency) (4 Lots) SPD -Compet itive MOI-WK2-05 / Rehabilitation Request for B of Road Works in Ha'apai 7.5 Component 2: Climate Resili ids - Small W Single Stage - One E Pending Imp 2026-11-1 km of the Main Road in Pang IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National orks SPD (1 e 0.00 2024-05-21 2024-06-11 2024-07-16 2024-08-20 2024-10-10 nvelope lementation 6 ai (2 Lots) olutions nvelope proc Lot 1 - HP A34.1 ess) Lot 2 - HP A34.2 MOI-WK2-04 / Rehabilitation Request for B of Road Works in Vava'u - 8.5 Component 2: Climate Resili ids - Small W km (2 Lots) Single Stage - One E Pending Imp 2026-12-0 IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National orks SPD (1 e 0.00 2024-06-03 2024-06-17 2024-07-22 2024-09-02 2024-10-23 Lot 1 - 3.6km Tuanuku-Longo nvelope lementation 7 olutions nvelope proc mapu Road ess) Lot 2 - 4.8 km Laifone-Toula- Pangaimotu Road Request for B MOI-WK2-TR-C4 / Rehabilitat Component 2: Climate Resili ids - Small W Single Stage - One E Pending Imp 2025-11-0 ion of Vava'u South West and IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids Open - National orks SPD (1 e 0.00 2023-12-04 2023-12-18 2024-01-29 2024-03-14 2024-05-04 nvelope lementation 4 Tongatapu Roads (3 lots). olutions nvelope proc ess) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI-GO2-02 / Supply and De livery of Tractors & 4WD Vehi Component 2: Climate Resili Request for Quota Single Stage - One E cle - 2 Lots IDA / D9110 ent and Safe Infrastructure S Post Open - National 0.00 Signed 2023-02-27 2023-04-26 2023-05-15 2023-06-30 2023-08-15 tions nvelope Lot 1 - 2x Tractors olutions Lot 2 - 4WD Vehicle MOI-GO2-04 / Supply and De Component 2: Climate Resili Request for Quota Single Stage - One E livery of Aviation Safety Equi / ent and Safe Infrastructure S Post Open - National 0.00 Canceled 2023-05-30 2023-08-14 2023-11-14 tions nvelope pment & Rescue Tools olutions Component 3: Project Manag Request for Quota Single Stage - One E MOI-GO-05 / Project Vehicle IDA / D9110 Post Limited 37,324.60 Signed 2022-06-04 2022-06-24 2022-07-19 2022-08-20 2022-09-17 ement tions nvelope MOI-GO2-06 / IT Equipment ( Component 3: Project Manag Request for Quota Single Stage - One E IDA / D9110 Post Limited 14,836.75 Signed 2022-06-04 2022-06-24 2022-07-07 2022-08-15 2022-08-06 4 x Laptops plus Monitors) fo ement tions nvelope r the PMU MOI-GO2-07 / Supply of Aids Component 2: Climate Resili Request for Quota Open - Internationa Single Stage - One E IDA / D9110 Post 0.00 Signed 2023-02-23 2023-05-07 2023-04-19 2023-09-21 2023-08-17 to Navigation Lights for Ha'a ent and Safe Infrastructure S tions l nvelope pai Group olutions MOI-GO2-01 / Rescue Fire Tr Component 2: Climate Resili ucks - 2 Lots: Open - Internationa Single Stage - One E IDA / D9110 ent and Safe Infrastructure S Prior Request for Bids 0.00 Canceled 2023-09-06 2023-09-20 2023-10-24 2023-11-28 2024-01-27 2024-07-27 Lot 1 - 1x CAT 5 Fire Truck l nvelope olutions Lot 2 - 2x TACR-D Fire Trucks Page 1 MOI-GO2-01.1 / Rescue Fire Trucks - 2 Lots: Lot 1 - 1x CA Component 2: Climate Resili Request for Quota Single Stage - One E Pending Impl T 5 Fire Truck Lot 2 - 2x TAC IDA / D9110 ent and Safe Infrastructure S Prior Limited 0.00 2023-11-29 2024-03-16 2024-09-12 tions nvelope ementation R-D Fire Trucks (including Saf olutions ety Equipment & Rescue Tool s) MOI-GO2-03 / Supply and De Component 2: Climate Resili Request for Quota Open - Internationa Single Stage - One E Pending Impl livery of Maintenance Equip IDA / D9110 ent and Safe Infrastructure S Post 0.00 2023-12-15 2024-03-13 2024-06-11 tions l nvelope ementation ment & Storage Shed for Do olutions mestic Airports NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI-NCS-01 / Regional Airpo Component 1: Capacity Buil Open - Internationa Single Stage - One E Pending Impl IDA / D9110 Prior Request for Bids 0.00 2024-06-03 2024-07-06 2024-08-09 2024-10-04 2024-12-12 2029-12-13 rt Asset Maintenance Contrac ding on Transport Planning a l nvelope ementation t nd Policies CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI-CF2-01 / Coastal and Ha rbor Engineering: Investigati Component 2: Climate Resili on, Concept Design, Detailed Quality And Cost- Open - Internationa IDA / D9110 ent and Safe Infrastructure S Prior 0.00 Signed 2021-07-01 2021-10-26 2021-07-22 2021-11-03 2021-09-04 2022-04-26 2021-10-02 2022-07-12 2021-11-01 2023-01-25 2021-12-06 2023-04-06 2022-01-10 2023-06-19 2023-07-14 Engineering Design and New Based Selection l olutions Passenger Terminal - Nafanu a Port, 'EUA & Taufa'ahau Por t, HA'APAI MOI-CF2-02.1 / Design and S Component 2: Climate Resili Consultant Qualifi upervision of Resurfacing of / ent and Safe Infrastructure S Post Open - National 0.00 Signed 2021-11-30 2022-03-31 2021-12-30 2022-05-18 2022-02-14 2022-08-17 2022-03-08 2023-07-21 2022-04-08 2023-07-27 2023-09-30 cation Selection Runway at Kaufana Aiport, 'E olutions ua MOI-CF2-03 / Design and su Component 2: Climate Resili Quality And Cost- Open - Internationa Under Implement pervision for the new priority IDA / D9110 ent and Safe Infrastructure S Prior 0.00 2022-01-14 2022-09-02 2022-01-16 2022-09-19 2022-03-03 2023-05-04 2022-04-12 2023-07-06 2022-05-20 2023-11-02 2022-06-27 2022-07-20 2023-07-20 Based Selection l ation roads in Tongatapu and the olutions Outer Islands MOI-CF2-04 / Engineering De Component 2: Climate Resili Quality And Cost- Open - Internationa sign of Airport Road (Fua'am IDA / D9110 ent and Safe Infrastructure S Prior 0.00 Canceled 2022-08-17 2022-08-29 2022-12-06 2022-12-07 2023-01-12 2023-02-01 2023-03-10 2023-09-12 Based Selection l otu - Nuku'alofa) olutions MOI-CF2-06 / Road Safety Au Component 2: Climate Resili Consultant Qualifi Open - Internationa IDA / D9110 Post 0.00 Canceled 2023-04-03 2023-04-15 2023-07-29 2023-08-05 2023-09-10 2023-12-11 dit ent and Safe Infrastructure S cation Selection l olutions MOI-CF2-09 / Gender-inform Component 1: Capacity Buil Consultant Qualifi Open - Internationa IDA / D9110 Post 0.00 Canceled 2023-09-04 2023-10-04 2023-11-15 2023-11-29 2023-12-20 2024-12-21 ed commercial driver licensin ding on Transport Planning a cation Selection l g training nd Policies MOI-CF2-04.1 / Engineering Component 2: Climate Resili Quality And Cost- Open - Internationa Pending Impleme Design of Airport Road (Fua'a IDA / D9110 ent and Safe Infrastructure S Prior 0.00 2024-07-24 2024-09-07 2024-11-02 2024-12-07 2025-01-11 2025-03-08 2025-04-19 2026-04-19 Based Selection l ntation motu - Nuku'alofa) olutions MOI-CF2-08 / Feasibility Stud Component 2: Climate Resili Consultant Qualifi Pending Impleme IDA / D9110 Post Open - National 0.00 2024-01-31 2024-03-13 2024-05-22 2024-06-19 2024-07-10 2025-04-25 y Tonga Slipway ent and Safe Infrastructure S cation Selection ntation olutions MOI-CF2-07 / Public Transpo Component 1: Capacity Buil Consultant Qualifi Open - Internationa Pending Impleme IDA / D9110 Post 0.00 2024-04-01 2024-05-11 2024-07-15 2024-08-14 2024-09-04 2025-09-04 rt Study ding on Transport Planning a cation Selection l ntation nd Policies MOI-CF2-05 / Road sector cli Component 1: Capacity Buil mate vulnerability assessme Quality And Cost- Open - Internationa Pending Impleme IDA / D9110 ding on Transport Planning a Post 0.00 2024-03-29 2024-04-28 2024-06-18 2024-07-18 2024-09-01 2024-10-23 2024-11-11 2025-08-03 nt and Climate Resilient Roa Based Selection l ntation nd Policies d Strategy (CRRS) for Tongat apu and Ha'apai INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOI-IC2-01 / Social Safeguar Component 2: Climate Resili Individual Consult IDA / D9110 Post Limited 30,000.00 Completed 2021-05-28 2021-01-14 2021-05-28 2021-04-26 2021-05-28 2021-05-27 2021-07-02 2021-06-14 2021-07-17 2021-09-21 d Specialist ent and Safe Infrastructure S ant Selection olutions MOI-IC2-02 / Environmental Component 2: Climate Resili Individual Consult IDA / D9110 Post Limited 30,000.00 Completed 2021-05-28 2021-01-14 2021-05-28 2021-04-26 2021-05-28 2021-05-28 2021-06-18 2021-06-14 2021-07-03 2021-09-21 Safeguard Specialist ent and Safe Infrastructure S ant Selection olutions MOI-IC-03 / Contracts and Bi Component 3: Project Manag Individual Consult IDA / D9110 Post Open 35,817.41 Terminated 2021-07-01 2021-06-29 2021-08-19 2021-09-14 2021-09-09 2021-09-14 2021-10-14 2021-10-05 2023-10-14 d Administrator ement ant Selection MOI-CF2-02 / Resurfacing of Component 2: Climate Resili Runway at Kaufana Aiport, 'E / ent and Safe Infrastructure S Post Direct Selection Direct 0.00 Canceled 2021-07-30 2021-08-09 2021-10-29 2023-05-02 ua - Design Services olutions MOI-IC2-09 / Technical Advis Component 3: Project Manag Individual Consult IDA / D9110 Post Open 101,827.35 Signed 2021-12-01 2022-03-21 2022-02-07 2022-06-14 2022-02-08 2022-06-17 2022-03-21 2022-06-27 2023-03-21 er - Maritime Infrastructure ement ant Selection MOI-IC2-11 / Project Manage Component 3: Project Manag Individual Consult / Post Open 0.00 Signed 2022-12-01 2022-09-14 2023-02-03 2023-01-20 2023-02-04 2023-01-25 2023-03-17 2023-02-24 2025-03-16 r ement ant Selection MOI-IC2-14 / Communication Component 3: Project Manag / Post Direct Selection Direct 0.00 Canceled 2023-10-01 2023-10-11 2023-12-15 2024-12-31 , Monitoring & Evaluation Offi ement cer MOI-IC2-3-1 / Contracts and Component 3: Project Manag Individual Consult IDA / D9110 Post Open 0.00 Signed 2022-05-30 2022-06-02 2022-07-02 2022-09-15 2022-07-09 2022-09-22 2022-07-17 2022-10-23 2023-12-19 Bid Administrator ement ant Selection MOI-IC2-18 / Finance Assista Component 3: Project Manag Individual Consult IDA / D9110 Post Open 0.00 Signed 2022-06-01 2022-06-08 2022-07-09 2022-09-08 2022-07-23 2022-09-22 2022-08-06 2022-10-23 2024-01-08 nt ement ant Selection MOI-IC2-10 / Technical Advis Component 3: Project Manag Individual Consult Under Implement IDA / D9110 Post Open 0.00 2023-09-03 2023-10-25 2023-11-10 2023-11-11 2023-12-22 2024-12-21 er - Aviation ement ant Selection ation MOI-IC2-19 / Technical Advis Component 3: Project Manag Individual Consult Open - Internationa IDA / D9110 Post 0.00 Signed 2022-09-15 2022-09-22 2022-11-03 2022-11-28 2022-11-24 2022-11-30 2022-12-08 2022-12-23 2023-08-05 er - Laboratory ement ant Selection l Page 2 MOI-IC2-04 / Technical Advis Component 3: Project Manag Individual Consult Open - Internationa IDA / D9110 Prior 0.00 Signed 2023-06-01 2022-11-16 2023-07-28 2023-03-15 2023-08-11 2023-04-16 2023-08-31 2023-05-05 2025-09-01 er - Roads ement ant Selection l MOI-IC2-16 / Procurement Of Component 3: Project Manag Pending Impleme IDA / D9110 Post Direct Selection Direct - National 0.00 2024-10-01 2024-10-11 2024-12-15 2025-12-10 ficer ement ntation MOI-IC2-17 / Administrative Component 3: Project Manag Individual Consult Pending Impleme IDA / D9110 Post Open - National 0.00 2024-10-01 2024-11-29 2024-12-04 2025-01-18 2027-01-18 Assistant ement ant Selection ntation MOI-IC2-13 / Project Account Component 3: Project Manag IDA / D9110 Post Direct Selection Direct - National 0.00 Canceled 2024-10-01 2024-10-11 2024-12-15 2025-12-10 ant ement MOI-IC2-12 / Contracts Mana Component 3: Project Manag IDA / D9110 Post Direct Selection Direct - National 0.00 Canceled 2024-10-01 2024-10-11 2024-12-15 2025-12-10 ger ement MOI-IC2-15 / Environmental Component 3: Project Manag Individual Consult Pending Impleme IDA / D9110 Post Open - National 0.00 2024-10-01 2024-12-02 2024-12-07 2025-01-21 2027-01-21 & Social Safeguard Officer ement ant Selection ntation MOI-IC2-14.1 / Communicati Component 3: Project Manag Individual Consult Under Implement IDA / D9110 Post Open - National 0.00 2023-08-15 2023-08-24 2023-10-01 2023-10-15 2023-11-05 2025-10-25 on, Monitoring & Evaluation ement ant Selection ation Officer MOI-IC2-20 / Road Safety As Component 2: Climate Resili Individual Consult Open - Internationa Under Implement IDA / D9110 Post 0.00 2023-08-15 2023-08-02 2023-10-17 2023-11-07 2023-12-05 2024-08-01 sessment and Improvement ent and Safe Infrastructure S ant Selection l ation Design olutions MOI-IC2-13.1 / Project Accou Component 3: Project Manag Individual Consult Pending Impleme IDA / D9110 Post Open - National 0.00 2023-12-15 2024-02-16 2024-03-01 2024-03-22 2025-08-26 ntant ement ant Selection ntation MOI-IC2-12.1 / Contracts Ma Component 3: Project Manag Individual Consult Pending Impleme IDA / D9110 Post Open - National 0.00 2023-12-15 2024-02-14 2024-02-28 2024-03-20 2025-08-24 nager ement ant Selection ntation MOI-IC2-21 / Procurement As Component 3: Project Manag Individual Consult Pending Impleme IDA / D9110 Post Open - National 0.00 2023-11-20 2024-01-22 2024-02-05 2024-02-26 2025-08-01 sistant ement ant Selection ntation MOI-IC2-3.2 / Contract Mana Component 3: Project Manag Individual Consult Pending Impleme IDA / D9110 Post Open - National 0.00 2023-11-20 2024-01-22 2024-02-05 2024-02-26 2025-08-01 gement Assistant ement ant Selection ntation MOI-IC2-4.1 / Technical Advi Component 3: Project Manag Individual Consult Open - Internationa Pending Impleme IDA / D9110 Post 0.00 2024-02-02 2024-04-09 2024-04-30 2024-05-28 2025-02-12 ser - Roads ement ant Selection l ntation MOI-IC2-09.1 / Gender-infor Component 1: Capacity Buil Individual Consult Open - Internationa Pending Impleme IDA / D9110 Post 0.00 2023-11-20 2024-01-26 2024-02-16 2024-03-15 2024-06-13 med commercial driver licens ding on Transport Planning a ant Selection l ntation ing training nd Policies MOI-IC2-07 / Technical Cons Component 1: Capacity Buil Individual Consult Open - Internationa Pending Impleme IDA / D9110 Post 0.00 2024-04-30 2024-07-18 2024-08-08 2024-08-29 2025-08-09 ultant - Road and Traffic Acts ding on Transport Planning a ant Selection l ntation nd Policies MOI-IC2-08 / Technical Advis Component 1: Capacity Buil Individual Consult Open - Internationa Pending Impleme IDA / D9110 Post 0.00 2024-02-28 2024-04-14 2024-05-12 2024-06-16 2025-06-16 er - Maritime Policy & Legal ding on Transport Planning a ant Selection l ntation nd Policies MOI-IC2-05 / Technical Cons Component 1: Capacity Buil Individual Consult Open - Internationa Pending Impleme IDA / D9110 Post 0.00 2024-04-16 2024-07-04 2024-07-25 2024-08-15 2025-04-22 ultant - RAMS ding on Transport Planning a ant Selection l ntation nd Policies MOI-IC2-06 / Technical Cons Component 1: Capacity Buil Individual Consult Open - Internationa Pending Impleme IDA / D9110 Post 0.00 2024-02-27 2024-05-21 2024-06-18 2024-07-16 2025-07-17 ultant - CODES ding on Transport Planning a ant Selection l ntation nd Policies Page 3