PROCUREMENT PLAN (Textual Part) Project information: Côte d’Ivoire Sustainable and Inclusive Secondary Cities Project (P177062) Project Implementation agency: Urban Sanitation and Resilience Project Date of the Procurement Plan: 11/14/2023 Period covered by this Procurement Plan: from 11/14/2023 to 30/03/2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in not applicable such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. not applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables not applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. not applicable Other Relevant Procurement Information. The project will be implemented regarding the loan agreement and the World Bank Procurement Regulations for IPF Borrowers (July 2016) (“Procurement Regulations”) PROCUREMENT Cote d'Ivoire : Sustainable and Inclusive Secondary Cities Project PLAN General Information Country: Cote d'Ivoire 2023-11-14 Bank’s Approval Date of the Original Procurement Plan: 2023-11-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177062 GPN Date: Project Name: Sustainable and Inclusive Secondary Cities Project Loan / Credit No: IDA / 72870 URBAN SANITATION AND RESILIENCE PROJECT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-390798-GO-RFB / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements médicaux des ét IDA / 72870 A posteriori Appel d'offres Open - National 800,000.00 0.00 2023-12-29 2024-01-03 2024-02-14 2024-03-15 2024-04-19 2024-10-16 rban infrastructure in Select nvelope exécution ablissements sanitaires des v ed Secondary Cities illes de Man et Odienné CI-PARU-390800-GO-RFQ / F ourniture et installation des é Component 1: Developing G quipements des établisseme reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited 280,000.00 0.00 2023-12-24 2024-02-18 2024-08-16 nts scolaires (tables bancs, b rban infrastructure in Select nvelope exécution ureaux, chaises, documentati ed Secondary Cities ons scolaires) des villes de Man et Odienné CI-PARU-390854-GO-RFB / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements médicaux des ét IDA / 72870 A posteriori Appel d'offres Open - National 1,200,000.00 0.00 2023-12-29 2024-01-03 2024-02-14 2024-03-15 2024-04-19 2024-10-16 rban infrastructure in Select nvelope exécution ablissements sanitaires des v ed Secondary Cities illes de Korhogo, Boundiali et Trengrela CI-PARU-390856-GO-RFQ / F ourniture et installation des é Component 1: Developing G quipements des établisseme reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited 420,000.00 0.00 2023-12-20 2024-02-14 2024-08-12 nts scolaires (tables bancs, b rban infrastructure in Select nvelope exécution ureaux, chaises, documentati ed Secondary Cities ons scolaires) des villes de Korhogo, Boundiali, Tengrela CI-PARU-390927-GO-RFB / F Component 1: Developing G ourniture et installation des é reen and Climate Resilient U Single Stage - One E En attente d' quipements médicaux des ét IDA / 72870 A posteriori Appel d'offres Open - National 1,200,000.00 0.00 2023-12-20 2023-12-25 2024-02-05 2024-03-06 2024-04-10 2024-10-07 rban infrastructure in Select nvelope exécution ablissements sanitaires dans ed Secondary Cities les villes de la Ferké, Ouango lo et Bouna CI-PARU-390931-GO-RFQ / F ourniture et installation des é Component 1: Developing G quipements des établisseme reen and Climate Resilient U Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited 420,000.00 0.00 2023-12-26 2024-02-20 2024-08-18 nts scolaires (tables bancs, b rban infrastructure in Select nvelope exécution ureaux, chaises, documentati ed Secondary Cities ons scolaires) des villes de F erké, Ouangolo et Bouna CI-PARU-391036-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' cquisition de mobiliers de bur IDA / 72870 A posteriori Demande de prix Limited 120,000.00 0.00 2023-12-24 2024-02-18 2024-08-16 ement and Coordination nvelope exécution eaux pour l'UDEP CI-PARU-391042-GO-RFQ / A Component 3: Project Manag Single Stage - One E En attente d' IDA / 72870 A posteriori Demande de prix Limited 400,000.00 0.00 2024-01-01 2024-02-26 2024-08-24 cquisition de véhicules pour l ement and Coordination nvelope exécution 'UDEP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-PARU-390794-CS-CQS / R ecrutement de Consultants fi Component 1: Developing G Sélection fondée s rmes pour la réalisation d'étu reen and Climate Resilient U En attente d'exéc IDA / 72870 A posteriori ur les qualification Open - National 240,000.00 0.00 2023-12-15 2024-01-05 2024-02-18 2024-03-19 2024-04-23 2024-10-20 des techniques détaillées des rban infrastructure in Select ution s des consultants travaux à impact rapide « Q ed Secondary Cities UICK WINS » dans les villes d e Man et Odienné CI-PARU-390795-CS-CQS / R ecrutement de consultants/fi Component 1: Developing G rmes pour la réalisation d’étu Sélection fondée s reen and Climate Resilient U En attente d'exéc des techniques détaillées des IDA / 72870 A posteriori ur les qualification Open - National 360,000.00 0.00 2023-12-15 2024-01-05 2024-02-18 2024-03-19 2024-04-23 2024-10-20 rban infrastructure in Select ution travaux a impact rapide « QU s des consultants ed Secondary Cities ICK WINS » dans les villes de Boundiali, Korhogo, et Tengr ela CI-PARU-390796-CS-CQS / R ecrutement de Consultants fi Component 1: Developing G rmes pour la réalisation d'étu Sélection fondée s reen and Climate Resilient U En attente d'exéc des techniques détaillées des IDA / 72870 A posteriori ur les qualification Open - National 360,000.00 0.00 2023-12-15 2024-01-05 2024-02-18 2024-03-19 2024-04-23 2024-10-20 rban infrastructure in Select ution travaux à impact rapide « QU s des consultants ed Secondary Cities ICK WINS » dans les villes de Bouna, Ferkessédougou et O uangolodougou Page 1 CI-PARU-390935-CS-QCBS / Réalisation des études techni Component 1: Developing G ques (APS/APD/DAO), de prio Sélection fondée s reen and Climate Resilient U Open - Internationa En attente d'exéc risation et de mobilité des tra IDA / 72870 A posteriori ur la qualité et le 1,000,000.00 0.00 2023-12-21 2024-01-11 2024-02-24 2024-03-23 2024-04-22 2024-05-27 2024-07-01 2025-07-01 rban infrastructure in Select l ution vaux d'infrastructures de voir coût ed Secondary Cities ies urbaines et de drainage d es eaux pluviales des villes d e Man et Odienné CI-PARU-390978-CS-QCBS / Réalisation des études techni Component 1: Developing G ques (APS/APD/DAO),de prior Sélection fondée s reen and Climate Resilient U Open - Internationa En attente d'exéc isation et de mobilité des tra IDA / 72870 A posteriori ur la qualité et le 1,500,000.00 0.00 2023-12-20 2024-01-10 2024-02-23 2024-03-22 2024-04-21 2024-05-26 2024-06-30 2025-06-30 rban infrastructure in Select l ution vaux d'infrastructures de voir coût ed Secondary Cities ies urbaines et de drainage d es eaux pluviales des villes de korhogo, Boundiali et Ten grela CI-PARU-391015-CS-QCBS / Component 1: Developing G Sélection fondée s Préparation de plans directeu reen and Climate Resilient U Open - Internationa En attente d'exéc IDA / 72870 A posteriori ur la qualité et le 1,600,000.00 0.00 2024-01-25 2024-02-15 2024-03-30 2024-04-27 2024-05-27 2024-07-01 2024-08-05 2025-08-05 rs d’assainissement et de dra rban infrastructure in Select l ution coût inage de Bouna, Ouangolodo ed Secondary Cities ugou et Tengrela CI-PARU-391024-CS-QCBS / Réalisation des études techni ques (APS/APD/DAO), de prio Component 1: Developing G Sélection fondée s risation et de mobilité des tr reen and Climate Resilient U Open - Internationa En attente d'exéc IDA / 72870 A posteriori ur la qualité et le 1,580,000.00 0.00 2023-12-29 2024-01-19 2024-03-03 2024-03-31 2024-04-30 2024-06-04 2024-07-09 2025-07-09 avaux d'infrastructures de vo rban infrastructure in Select l ution coût iries urbaines et de drainage ed Secondary Cities des eaux pluviales des villes de Ferkessédougou, Ouangol odougou et Bouna INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2