PROCUREMENT PLAN (Textual Part) Project information: Burkina Faso-WAPP North Core Regional Interconnector Project-P162933 Project Implementation agency: SONABEL Date of the Procurement Plan: December 31st, 2018 Period covered by this Procurement Plan: from January 2019 – to June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Décret N°2017-00049/PRES/PM/MINEFID du 01/02/2017 portant procédures de passation, d’exécution et de règlement des marchés publics et des délégations de service publics au Burkina Faso, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. The National Bidding Document clause allowed to reject all bid when arithmetic error is 15% on + or – of original bid is not applied to the project. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable. PROCUREMENT Western and Central Africa : North Core/Dorsale Nord Regional Power Interconnector Project PLAN General Information Country: Western and Central Africa Bank’s Approval Date of the Original Procurement Plan: 2019-06-20 Revised Plan Date(s): (comma delineated, leave blank if 2023-11-14 none) Project ID: P162933 GPN Date: 2019-04-09 Project Name: North Core/Dorsale Nord Regional Power Interconnector Project Loan / Credit No: IDA / D3910, IDA / 63420, IDA / 63390, IDA / 63400, IDA / D3920, IDA / D3940, IDA / D3930, IDA / 63410 Project Management Unit for North Core / Dorsale Nord Regional Power Interconnector Project Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WAPP-NC-REF-1A-TL-002 / 6 Power Interconnection betw 97 Km of 330 kV Transmissio Open - Internationa Single Stage - One E 155,830,65 En cours d'e 2023-02-2 IDA / 63390 een Niger, Nigeria, Benin an A priori Appel d'offres 2019-07-10 2019-08-27 2019-10-14 2020-06-17 2019-11-04 2020-10-25 2019-07-29 2019-09-04 2020-01-27 2021-02-18 2020-03-23 2021-03-29 2020-06-03 2021-12-04 n Lines in Niger (316 Km),Bur l nvelope 3.85 xamen 0 d Burkina Faso kina Faso (381 Km) and Beni n (12 Km) WAPP-NC-REF-1B-SS-003 / S Power Interconnection betw Open - Internationa Single Stage - One E 71,736,673. 2023-02-2 ubstations and dispatching c IDA / 63400 een Niger, Nigeria, Benin an A priori Appel d'offres Signé 2019-07-10 2019-08-29 2019-10-14 2020-07-24 2019-11-04 2021-02-07 2019-07-29 2019-09-04 2020-01-27 2021-06-29 2020-03-23 2021-10-05 2020-06-03 2022-03-11 l nvelope 03 0 enters in Niger and Benin d Burkina Faso WAPP-NC-REF-1A-TL-001 / L Power Interconnection betw ot 1-A-TL: 330 kV Transmissi Open - Internationa Single Stage - One E 14,594,488. 2023-02-2 IDA / 63420 een Niger, Nigeria, Benin an A priori Appel d'offres Signé 2019-07-10 2019-08-27 2019-10-14 2020-06-10 2019-11-04 2020-10-23 2019-07-29 2019-09-04 2020-01-27 2021-01-29 2020-03-23 2021-03-24 2020-06-03 2022-04-16 on Lines NIGERIA: Birnin-Nige l nvelope 03 0 d Burkina Faso ria/Niger Border (62 km) NG-PMU-WAPP-NC-146209-C W-DIR / Finalisation et Achèv Power Interconnection betw ement du Contrat N°035/CEB Passation de marc 3,145,998.1 2020-08-2 IDA / 63400 een Niger, Nigeria, Benin an A posteriori Direct Signé 2020-02-18 2020-06-18 2020-03-03 2020-08-09 2020-04-24 2021-06-19 /DG/DED/DAP/SAT/2013 relati hé de gré à gré 8 2 d Burkina Faso f aux travaux de construction au Bénin d'une ligne 33O kV de la CEB NG-PMU-WAPP-NC-146232-C W-DIR / Finalisation des trava Power Interconnection betw Passation de marc 1,155,393.3 2020-09-2 ux de l’extension du poste de IDA / 63400 een Niger, Nigeria, Benin an A posteriori Direct Signé 2020-02-18 2020-06-18 2020-02-23 2020-09-22 2020-03-29 2021-09-05 hé de gré à gré 4 5 Sakété au Bénin : Travaux co d Burkina Faso mplémentaires, Essais, régla ges et mise en service NG-PMU-WAPP-NC-154016-C W-RFB / Conception, fournitu Power Interconnection betw re, montage et mise en servi Single Stage - One E 2021-07-0 IDA / 63400 een Niger, Nigeria, Benin an A posteriori Appel d'offres Open - National 777,427.17 Signé 2020-03-02 2020-09-11 2020-03-07 2020-10-12 2020-05-06 2021-01-25 2020-06-05 2021-05-06 2020-07-10 2022-02-19 ces des systèmes de télécom nvelope 5 d Burkina Faso munications pour le Projet d’i nterconnexion 330 kV / Ghan a – Togo - Bénin WAPP-NC-REF-1A-TL-002-B / Demande d'o Construction des Lignes élect Power Interconnection betw ffres - DTPM Open - Internationa Single Stage - One E 30,511,576. 2023-09-2 riques de transport 330 kV e IDA / 63400 een Niger, Nigeria, Benin an A posteriori Appel d'offres Travaux (apr Signé 2021-12-14 2021-12-14 2021-12-14 2021-12-19 2021-03-29 2021-12-29 2021-11-23 l nvelope 01 0 ntre la frontière Niger / Bénin d Burkina Faso ès préqualific - Malanville (Bénin) (environ ation) 12 km) Lot 1C-TL GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WAPP-NC-REF-3B-003 / Othe Institutional Framework and Single Stage - One E r Software licences & IT Servi IDA / D3910 A posteriori Appel d'offres Open - National 0.00 Annulé 2020-01-06 2020-01-11 2020-02-22 2020-03-08 2020-04-12 2020-07-11 Project Oversight nvelope ces outsourcing WAPP-NC-REF-3B-004 / Supp ly of VOIP Communication, Vi Institutional Framework and Single Stage - One E IDA / D3910 A posteriori Appel d'offres Open - National 0.00 Annulé 2019-12-08 2019-12-13 2020-01-24 2020-02-08 2020-03-14 2020-06-12 deoconference, Projectors, m Project Oversight nvelope edia & Interpretation équipm ents WAPP-NC-REF-3B-001 / Supp Institutional Framework and Single Stage - One E ly of vehicles for Abuja HQ Fir IDA / D3910 A posteriori Appel d'offres Open - National 0.00 Annulé 2019-07-15 2019-07-20 2019-08-31 2019-09-15 2019-10-20 2020-01-18 Project Oversight nvelope st batch (07 SUV + 01 Doubl e Cabin Pickup) NG-PMU-WAPP-NC-175735-G Institutional Framework and Open - Internationa Single Stage - One E O-RFB / Supply of Vehicles to IDA / D3910 A posteriori Appel d'offres 597,820.00 Signé 2020-06-08 2020-06-22 2020-06-13 2020-06-23 2020-07-25 2020-08-14 2020-08-24 2020-09-30 2020-09-28 2020-12-03 2021-03-27 Project Oversight l nvelope the PMU HQ NG-PMU-WAPP-NC-222546-G O-RFQ / Fourniture et installa tion du matériel pour réseaut Institutional Framework and Single Stage - One E IDA / D3910 A posteriori Demande de prix Limited 56,832.70 Signé 2021-03-20 2021-07-27 2021-05-15 2022-02-04 2021-06-14 age informatique et électriqu Project Oversight nvelope e dans les locaux de l'Unité C entrale de Gestion du Projet ( extension) NG-PMU-WAPP-NC-222549-G Institutional Framework and Single Stage - One E O-RFQ / Acquisition de 5 Ordi IDA / D3910 A posteriori Demande de prix Limited 11,649.55 Signé 2021-03-20 2021-04-16 2021-05-15 2021-10-28 2021-06-14 Project Oversight nvelope nateurs portables pour le nou veau staff NG-PMU-WAPP-NC-265780-G O-RFQ / Acquisition de véhicu Institutional Framework and Single Stage - One E les pour l'antenne du projet à IDA / 63400 A posteriori Demande de prix Limited 0.00 Résilié 2022-02-19 2022-07-25 2022-04-23 2022-10-10 2022-06-07 Project Oversight nvelope Malanville et pour l'Agence B éninoise de l'Environnement (ABE) NG-PMU-WAPP-NC-266698-G O-RFQ / Acquisition de mobili Institutional Framework and Single Stage - One E IDA / D3910 A posteriori Demande de prix Limited 0.00 Signé 2022-01-29 2022-08-10 2022-03-26 2022-11-19 2022-05-10 ers additionnel de bureau po Project Oversight nvelope ur le siège du Projet NG-PMU-WAPP-NC-266702-G Institutional Framework and Single Stage - One E En attente d' O-RFQ / Impression et acquisi IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-01-22 2022-03-19 2022-05-18 Project Oversight nvelope exécution tion de supports de communi cation Page 1 NG-PMU-WAPP-NC-266705-G O-RFB / Acquisition de drone Institutional Framework and Single Stage - One E En attente d' s, cameras, ordinateurs et le IDA / D3910 A posteriori Appel d'offres Open - National 0.00 2022-01-24 2022-01-29 2022-02-28 2022-03-10 2022-04-23 2022-06-22 Project Oversight nvelope exécution urs accessoires et logiciels, G PS, Table traçante et Project eur NG-PMU-WAPP-NC-266706-G O-RFQ / Équipements de séc Institutional Framework and Single Stage - One E En attente d' IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-03-19 2022-05-14 2022-07-13 urité informatique et kit d'out Project Oversight nvelope exécution ils de maintenance NG-PMU-WAPP-NC-266711-G Institutional Framework and Single Stage - One E En attente d' O-RFQ / Installation d'une de IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-02-06 2022-04-17 2023-04-17 Project Oversight nvelope exécution uxième connexion Internet d e secours NG-PMU-WAPP-NC-268215-G Institutional Framework and Single Stage - One E En attente d' O-RFQ / Fourniture de mobili IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-03-19 2022-05-14 2022-06-28 Project Oversight nvelope exécution ers de bureau à Birnin Kebbi NG-PMU-WAPP-NC-268224-G O-RFQ / Fourniture de Mobilie Institutional Framework and Single Stage - One E En attente d' IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-03-13 2022-05-08 2022-06-22 rs de bureau pour l'antenne Project Oversight nvelope exécution de l'UGP de Malanville (Bénin ) NG-PMU-WAPP-NC-268334-G Institutional Framework and Single Stage - One E En attente d' O-RFQ / Câblage des locaux IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-03-13 2022-05-08 2022-06-22 Project Oversight nvelope exécution de l'antenne de l'UGP de Mal anville (Bénin) NG-PMU-WAPP-NC-268339-G O-RFQ / Câblage des locaux Institutional Framework and En attente d' IDA / D3910 A posteriori Demande de prix 0.00 2022-03-19 2022-05-14 2022-06-28 de l'antenne du Projet à Birn Project Oversight exécution in Kebbi (Nigéria) NG-PMU-WAPP-NC-268347-G Institutional Framework and Single Stage - One E En attente d' O-RFQ / Parking et installatio IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-04-30 2022-06-25 2022-08-09 Project Oversight nvelope exécution n de conteneurs aménagés e n magasin NG-PMU-WAPP-NC-268360-G O-RFQ / Fourniture de deux v Institutional Framework and Single Stage - One E IDA / 63410 A posteriori Demande de prix Limited 65,555.42 Signé 2022-01-23 2022-01-25 2022-03-20 2022-04-30 2022-05-04 éhicules au profit du Bureau Project Oversight nvelope National d'Evaluation Environ nementale (BNEE) NG-PMU-WAPP-NC-268366-G O-RFQ / Fourniture de deux v Institutional Framework and Single Stage - One E éhicules au profit du BUNEE ( IDA / 63390 A posteriori Demande de prix Limited 57,639.33 Signé 2022-01-23 2022-01-26 2022-03-20 2022-04-30 2022-05-04 Project Oversight nvelope Bureau National des Evaluati ons Environnementales. NG-PMU-WAPP-NC-353729-G O-DIR / FOURNITURE DE 57 LI Institutional Framework and Passation de marc En attente d' CENCES DU LOGICIEL ARCGI IDA / D3910 A posteriori Direct - National 0.00 2023-03-30 2023-04-04 2023-04-07 2023-04-13 Project Oversight hé de gré à gré exécution S POUR L’OPERATIONALISATI ON DU SIG DU PROJET WAPP DORSALE NORD NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-PMU-WAPP-NC-268326-N C-RFQ / Fourniture de la conn Institutional Framework and Single Stage - One E En attente d' IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-04-11 2022-05-17 2023-05-17 ectivité internet à l'antenne Project Oversight nvelope exécution de l'UGP de Birnin Kebbi (Nig éria) NG-PMU-WAPP-NC-268330-N Institutional Framework and Single Stage - One E En attente d' C-RFQ / Fourniture de la conn IDA / D3910 A posteriori Demande de prix Limited 0.00 2022-04-11 2022-05-17 2023-05-17 Project Oversight nvelope exécution ectivité internet à l'antenne de Malanville CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WAPP-NC-REF-3B-006 / EX-N Institutional Framework and Sélection au moin Open - Internationa IDA / D3910 A posteriori 72,939.00 Signé 2019-06-14 2019-08-20 2019-07-05 2019-10-04 2019-09-16 2020-03-03 2019-10-16 2020-04-07 2019-11-06 2020-04-29 2019-11-28 2020-05-07 2019-12-24 2020-06-12 2022-06-30 C2 External auditor Project Oversight dre coût l WAPP-NC-REF-C3B2-001 / O E-NC1 Recruitment Owner's Sélection fondée s Institutional Framework and Open - Internationa Engineer for the WAPP North IDA / D3910 A priori ur la qualité et le 9,767,997.77 Signé 2019-05-19 2019-07-14 2019-05-21 2019-05-25 2019-07-15 2019-05-27 2018-10-01 2019-05-29 2019-07-15 2019-06-02 2019-07-23 2019-06-05 2019-05-08 2024-01-05 Project Oversight l Core Project (Project Manage coût ment, Supervision of Works, Support ESMP). WAPP-NC-REF-4A2-001 / Lin e route , Environmental and Strengthening Institutional C Sélection fondée s Open - Internationa Social Impact Assessment (E IDA / 63420 apacity for Regional Electrici A priori ur la qualité et le 4,639,172.91 Signé 2019-06-10 2019-07-19 2019-07-08 2019-08-04 2019-11-01 2020-01-13 2019-12-31 2020-06-08 2020-02-20 2020-07-13 2020-05-17 2021-01-27 2020-06-22 2021-04-08 2021-09-25 l SIA) Study for the 330 kV Do ty Trade coût uble Circuit Median Interconn ector Project WAPP-NC-REF-A42-003 / Fea sibility study and preparation Strengthening Institutional C Sélection fondée s Open - Internationa of bidding documents of the IDA / 63420 apacity for Regional Electrici A priori ur la qualité et le 1,682,060.57 Signé 2019-06-10 2019-07-19 2019-07-08 2019-08-04 2019-11-01 2020-01-23 2019-12-31 2020-06-08 2020-02-20 2020-07-15 2020-05-17 2020-12-17 2020-06-22 2021-03-13 2021-11-24 l 330 kV Double Circuit Median ty Trade coût Interconnector Project. WAPP-NC-4A2-004 / Update Strengthening Institutional C Sélection fondée s of the inventory of affected p IDA / D3910 apacity for Regional Electrici A posteriori ur les qualification Open - National 0.00 Annulé 2019-06-14 2020-01-07 2019-07-12 2019-09-09 2019-10-24 2019-11-21 2020-03-20 roperty and the list of affecte ty Trade s des consultants d persons in Nigeria WAPP-NC-4A2-005 / Update Strengthening Institutional C Sélection fondée s of the inventory of affected p IDA / D3910 apacity for Regional Electrici A posteriori ur les qualification Open - National 0.00 Annulé 2019-06-14 2020-01-07 2019-07-12 2019-09-09 2019-10-24 2019-11-21 2020-03-20 roperty and the list of affecte ty Trade s des consultants d persons in Benin WAPP-NC-4A2-006 / Update Strengthening Institutional C Sélection fondée s of the inventory of affected p IDA / D3910 apacity for Regional Electrici A posteriori ur les qualification Open - National 0.00 Annulé 2019-06-14 2020-01-07 2019-07-12 2019-09-09 2019-10-24 2019-11-21 2020-03-20 roperty and the list of affecte ty Trade s des consultants d persons in Niger Page 2 WAPP-NC-4A2-007 / Update Strengthening Institutional C Sélection fondée s of the inventory of affected p IDA / D3910 apacity for Regional Electrici A posteriori ur les qualification Open - National 0.00 Annulé 2019-06-14 2020-02-28 2019-07-12 2019-09-09 2019-10-24 2019-11-21 2020-03-20 roperty and the list of affecte ty Trade s des consultants d persons in Burkina Faso NG-PMU-WAPP-NC-176166-C Sélection fondée s S-CQS / Update of the invent Institutional Framework and IDA / D3920 A posteriori ur les qualification Open - National 161,618.49 Signé 2020-06-23 2020-05-07 2020-07-14 2020-08-27 2020-09-11 2020-09-26 2021-06-01 2020-10-31 2021-06-07 2021-04-29 ory of affected property and t Project Oversight s des consultants he list of affected persons in Burkina Faso NG-PMU-WAPP-NC-176167-C Sélection fondée s S-CQS / Update of the invent Institutional Framework and IDA / D3940 A posteriori ur les qualification Open - National 232,773.50 Signé 2020-06-23 2020-05-07 2020-07-14 2020-08-27 2020-09-11 2020-09-26 2020-11-02 2020-10-31 2020-11-16 2021-01-23 ory of affected property and t Project Oversight s des consultants he list of affected persons in Niger NG-PMU-WAPP-NC-176168-C Sélection fondée s S-CQS / Update of the invent Institutional Framework and IDA / D3930 A posteriori ur les qualification Open - National 53,172.29 Signé 2020-06-23 2020-05-07 2020-07-14 2020-08-27 2020-09-11 2020-09-26 2021-02-01 2020-10-31 2021-03-09 2020-12-12 ory of affected property and t Project Oversight s des consultants he list of affected persons in Benin NG-PMU-WAPP-NC-219755-C S-LCS / Mise en place d'Un Sy Institutional Framework and Sélection au moin Open - Internationa IDA / D3910 A posteriori 86,612.00 Signé 2021-02-17 2021-01-15 2021-03-10 2021-03-17 2021-04-23 2021-10-22 2021-05-21 2021-12-07 2021-06-20 2022-06-15 2021-07-25 2022-06-23 2021-08-29 2022-07-22 2021-12-07 stème d'Informations Géogra Project Oversight dre coût l phiques pour le Projet Dorsal e Nord NG-PMU-WAPP-NC-222534-C Sélection fondée s S-CQS / Mise en place d'une Institutional Framework and IDA / 63390 A posteriori ur les qualification Open - National 114,277.16 Signé 2021-03-15 2021-02-15 2021-04-05 2021-05-26 2021-05-19 2022-01-13 2021-06-18 2022-05-25 2021-07-23 2022-06-23 2021-10-26 Base de Données Environne Project Oversight s des consultants mentales au Burkina Faso NG-PMU-WAPP-NC-222540-C Sélection fondée s S-CQS / Mise en place d'une Institutional Framework and IDA / 63410 A posteriori ur les qualification Open - National 98,525.14 Signé 2021-03-15 2021-02-15 2021-04-05 2021-05-26 2021-05-19 2022-01-13 2021-06-18 2022-04-21 2021-07-23 2022-05-16 2022-01-19 Base de Données Environne Project Oversight s des consultants mentales au Niger NG-PMU-WAPP-NC-265031-C Sélection fondée s S-CQS / Recrutement ONG po Institutional Framework and IDA / 63410 A posteriori ur les qualification Open - National 0.00 Signé 2021-11-30 2021-09-15 2021-12-14 2022-01-27 2022-06-28 2022-02-26 2022-09-02 2022-03-26 2022-11-19 2024-03-25 ur la supervision du processu Project Oversight s des consultants s de réinstallation des PAPs a u Niger NG-PMU-WAPP-NC-265765-C S-CQS / RECRUTEMENT D'ON G POUR LA SUPERVISION DU Sélection fondée s Institutional Framework and PROCESSUS DE REINSTALLAT IDA / 63390 A posteriori ur les qualification Open - National 0.00 Signé 2021-11-30 2021-09-15 2021-12-21 2022-02-03 2022-06-28 2022-03-05 2022-09-02 2022-04-02 2022-11-20 2024-04-01 Project Oversight ION DES PERSONNES AFFECT s des consultants EES PAR LE PROJET WAPP DO RSALE NORD AU BURKINA FASO NG-PMU-WAPP-NC-265767-C S-CQS / Recrutement d’une O Sélection fondée s rganisation Non Gouverneme Institutional Framework and IDA / 63400 A posteriori ur les qualification Open - National 0.00 Signé 2021-11-30 2021-09-15 2021-12-21 2022-02-03 2022-06-28 2022-03-05 2022-09-08 2022-04-02 2022-11-18 2024-04-01 ntale (ONG) pour la supervisi Project Oversight s des consultants on du processus de réinstalla tion des personnes affectées par le projet au Bénin. NG-PMU-WAPP-NC-222544-C Sélection fondée s S-CQS / Mise en place d'une Institutional Framework and IDA / 63410 A posteriori ur les qualification Open - National 0.00 Annulé 2021-03-15 2021-02-15 2021-04-05 2021-05-26 2021-05-19 2021-06-18 2021-07-23 2021-10-01 Base de Données Environne Project Oversight s des consultants mentales au Bénin NG-PMU-WAPP-NC-222541-C Sélection fondée s S-CQS / Mise en place d'une Institutional Framework and IDA / 63420 A posteriori ur les qualification Open - National 0.00 Annulé 2021-03-15 2021-02-15 2021-04-05 2021-05-26 2021-05-19 2021-06-18 2021-07-23 2021-10-11 Base de Données Environem Project Oversight s des consultants entales au Nigéria WAPP-NC-REF-4A2-002 / EX- NC1 Consultant Services for t Strengthening Institutional C Sélection fondée s he preparation and Negotiati Open - Internationa IDA / D3910 apacity for Regional Electrici A posteriori ur les qualification 0.00 Annulé 2019-06-14 2019-07-12 2019-09-22 2019-11-06 2019-12-04 2020-06-01 on of PPAs (Power Purchase l ty Trade s des consultants Agreements) and TSAs (Tran smission Service Agreements ) NG-PMU-WAPP-NC-265017-C Sélection fondée s Institutional Framework and Open - Internationa S-CQS / Conception de site in IDA / D3910 A posteriori ur les qualification 0.00 Annulé 2022-02-08 2022-02-23 2022-04-15 2022-04-29 2022-05-23 2022-07-22 Project Oversight l ternet du Projet s des consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WAPP-NC-3B-007 / SC-HQA I Institutional Framework and IDA / D3910 A priori Individuel Open 363,088.98 Signé 2019-07-15 2020-03-10 2019-10-16 2021-01-21 2019-11-13 2021-02-02 2020-01-31 2021-03-09 2023-02-27 nternal Auditor PMU HQ Project Oversight WAPP-NC-REF-3B-008 / SC-H Institutional Framework and IDA / D3910 A priori Individuel Open 322,389.10 Signé 2019-10-15 2020-03-10 2020-01-07 2021-01-22 2020-01-14 2021-02-02 2020-02-27 2021-03-09 2023-02-26 QA Communication Officer P Project Oversight MU HQ WAPP-NC-REF-3B-010 / SC-H Institutional Framework and IDA / D3910 A priori Individuel Open 322,389.10 Signé 2019-07-15 2020-03-03 2019-10-16 2021-01-22 2019-11-13 2021-02-02 2020-01-31 2021-03-09 2023-02-27 QA IT Officer PMU HQ Project Oversight WAPP-NC-REF-3B-011 / SC-H Institutional Framework and IDA / D3910 A priori Individuel Open 342,739.04 Signé 2019-07-15 2020-03-10 2019-10-16 2021-01-22 2019-11-13 2021-02-01 2020-01-31 2021-03-09 2023-02-27 QA Lines Engineer PMU HQ Project Oversight WAPP-NC-REF-3B-012 / SC-H Institutional Framework and IDA / D3910 A priori Individuel Open 342,739.04 Signé 2019-07-15 2020-03-10 2019-10-16 2021-01-22 2019-11-13 2021-02-04 2020-01-31 2021-03-09 2023-02-27 QA Substations Engineer PM Project Oversight U HQ WAPP-NC-REF-3B-013 / SC-H Institutional Framework and IDA / D3910 A priori Individuel Open 342,739.04 Signé 2019-07-15 2020-03-10 2019-10-16 2021-01-22 2019-11-13 2021-02-02 2020-01-31 2021-03-09 2023-02-27 QA SCADA Engineer PMU HQ Project Oversight WAPP-NC-REF-3B-014 / SC-H Institutional Framework and IDA / D3910 A priori Individuel Open 342,739.04 Signé 2019-10-15 2020-03-10 2020-01-07 2021-01-22 2020-01-14 2021-02-02 2020-02-27 2021-03-09 2023-02-26 QA Civil Engineer PMU HQ Project Oversight WAPP-NC-REF-3B-015 / SC-H Institutional Framework and IDA / D3910 A posteriori Individuel Open 123,924.00 Signé 2019-07-15 2020-01-28 2019-10-16 2022-03-18 2019-10-23 2022-09-02 2019-12-28 2022-10-04 2023-02-27 QA Superintendant PMU HQ Project Oversight WAPP-NC-REF-3B-016 / SC-H Institutional Framework and QA Finance & Account Assist IDA / D3910 A posteriori Individuel Open 217,360.00 Signé 2019-10-15 2020-01-26 2020-01-07 2022-03-18 2020-01-14 2022-08-08 2020-02-27 2022-08-19 2023-02-26 Project Oversight ant PMU HQ Page 3 WAPP-NC-REF-3B-017 / SC-H QA Executive Billingual Assist Institutional Framework and ant / PA - Director PMU HQ IDA / D3910 A priori Individuel Open 261,339.28 Signé 2019-07-15 2020-03-02 2019-10-16 2021-01-22 2019-11-13 2021-02-04 2020-01-31 2021-03-09 2023-02-27 Project Oversight Total Contract: 330 761$ / W B(IDA):132 536$ / AfDB (FAD ): 198 225$ WAPP-NC-REF-3B-018 / SC-H Institutional Framework and IDA / D3910 A posteriori Individuel Open 179,939.52 Signé 2019-07-15 2020-01-29 2019-10-16 2021-01-22 2019-10-23 2021-01-28 2019-12-28 2021-03-09 2023-02-27 QA Billingual Assistant #1 PM Project Oversight U HQ WAPP-NC-3B-018 / SC-HQA B Institutional Framework and IDA / D3910 A posteriori Individuel Open 179,939.52 Signé 2019-07-15 2020-01-26 2019-10-16 2021-01-22 2019-10-23 2021-01-28 2020-05-29 2021-03-09 2023-02-17 illingual Assistant #2 PMU H Project Oversight Q WAPP-NC-REF-3B-27 / SC-HQ Institutional Framework and A Administrative, Protocol & IDA / D3910 A priori Individuel Open 363,088.98 Signé 2019-07-15 2020-03-02 2019-10-16 2021-01-22 2019-11-13 2021-02-02 2020-01-31 2021-03-04 2023-02-27 Project Oversight Logistics Officer WAPP-NC-REF-3B-019 / SC-H Institutional Framework and IDA / D3910 A priori Individuel Direct 1,159,928.00 Signé 2019-07-10 2019-09-14 2019-07-12 2019-10-04 2019-07-26 2019-10-17 2019-08-04 2019-10-02 2023-08-03 QA Director PMU HQ Project Oversight NG-PMU-WAPP-NC-141072-C Sélection de cons Institutional Framework and S-CDS / Audit de sécurité et d IDA / D3910 A posteriori ultants par entent Direct 65,381.45 Signé 2019-11-08 2020-01-09 2019-11-18 2019-11-18 2020-01-22 2020-02-12 2020-07-20 Project Oversight e sureté des sites du Projet D e directe orsale Nord NG-PMU-WAPP-NC-146202-C S-CDS / Supervision et Contr Power Interconnection betw Sélection de cons ôle de la finalisation des trav IDA / 63400 een Niger, Nigeria, Benin an A posteriori ultants par entent Direct 583,171.14 Signé 2020-02-18 2020-06-18 2020-03-08 2020-07-24 2020-05-12 2021-02-07 2021-09-04 aux du Projet 330 kV Ghana- d Burkina Faso e directe Togo-Bénin de la CEB (Lignes , postes et Télécom) NG-PMU-WAPP-NC-153263-C Sélection de cons Institutional Framework and S-CDS / Senior Environmental IDA / D3910 A priori ultants par entent Direct 371,679.00 Signé 2020-02-18 2020-04-16 2020-03-08 2020-06-05 2020-04-30 2020-10-04 2023-04-30 Project Oversight Specialist e directe NG-PMU-WAPP-NC-153272-C Sélection de cons Institutional Framework and S-INDV / Senior Social Safegu IDA / D3910 A priori ultants par entent Direct 371,445.00 Signé 2020-02-18 2020-04-16 2020-03-08 2020-06-05 2020-04-30 2020-10-05 2023-04-30 Project Oversight ard Specialist e directe Sélection de cons NG-PMU-WAPP-NC-153283-C Institutional Framework and IDA / D3910 A priori ultants par entent Direct 366,679.00 Signé 2020-02-18 2020-03-21 2020-03-08 2020-06-05 2020-04-30 2020-10-05 2023-04-30 S-CDS / Senior Accountant Project Oversight e directe NG-PMU-WAPP-NC-153291-C Sélection de cons Institutional Framework and S-INDV / Junior Procurement IDA / D3910 A priori ultants par entent Direct 335,011.00 Signé 2020-02-18 2020-03-21 2020-03-08 2020-06-05 2020-04-30 2020-10-13 2023-04-30 Project Oversight Specialist e directe NG-PMU-WAPP-NC-153293-C Sélection de cons Institutional Framework and S-INDV / Senior Procurement IDA / D3910 A priori ultants par entent Direct 407,764.00 Signé 2020-02-18 2020-03-21 2020-03-08 2020-06-05 2020-04-30 2020-10-13 2023-04-30 Project Oversight Specialist e directe NG-PMU-WAPP-NC-153295-C Sélection de cons Institutional Framework and S-INDV / Senior Financial Spe IDA / D3910 A priori ultants par entent Direct 405,494.00 Signé 2020-02-18 2020-03-21 2020-03-08 2020-06-05 2020-04-30 2020-10-13 2023-04-30 Project Oversight cialist e directe NG-PMU-WAPP-NC-153296-C Sélection de cons Institutional Framework and S-INDV / Senior Technical Co IDA / D3910 A priori ultants par entent Direct 440,940.00 Signé 2020-02-18 2020-03-21 2020-02-28 2020-06-05 2020-04-30 2020-10-13 2023-04-30 Project Oversight ordinator e directe NG-PMU-WAPP-NC-153298-C Sélection de cons Institutional Framework and S-INDV / Senior Monitoring & IDA / D3910 A priori ultants par entent Direct 362,731.00 Signé 2020-02-18 2020-04-16 2020-03-08 2020-06-05 2020-04-30 2020-10-13 2023-05-30 Project Oversight Evaluation Specialist e directe NG-PMU-WAPP-NC-155336-C S-INDV / Assistant en Environ Institutional Framework and IDA / 63420 A posteriori Individuel Open 125,399.64 Signé 2020-04-06 2020-07-07 2020-06-03 2021-07-17 2020-06-24 2021-07-17 2020-07-13 2021-08-01 2023-07-28 nement et Sauvegarde Social Project Oversight e pour l'unité locale de Birnin Kebbi NG-PMU-WAPP-NC-219719-C Institutional Framework and S-INDV / Specialiste Pricipal e IDA / D3910 A priori Individuel Limited 424,138.80 Signé 2021-02-26 2021-03-06 2021-03-03 2020-11-30 2021-03-24 2021-03-15 2021-04-28 2021-03-04 2024-05-10 Project Oversight n Sauvegarde Social NG-PMU-WAPP-NC-219741-C S-CDS / Selection d'une Agen Sélection de cons Institutional Framework and ce de recrutement du person IDA / D3910 A posteriori ultants par entent Direct 57,701.00 Signé 2021-02-19 2021-01-15 2021-03-01 2021-01-15 2021-03-21 2021-03-06 2021-05-20 Project Oversight nel chargé des Sauvegardes e directe Environnementales et Social es NG-PMU-WAPP-NC-268372-C S-CDS / Convention avec le B Sélection de cons ureau National d'Evaluation E Institutional Framework and En attente d'exéc IDA / 63410 A posteriori ultants par entent Direct 0.00 2022-01-10 2022-01-20 2022-03-06 2024-03-05 nvironnementale (BNEE) pou Project Oversight ution e directe r la Surveillance et le Suivi d e la mise en oeuvre du PAR e t du PGES NG-PMU-WAPP-NC-268384-C S-CDS / Convention avec le B Sélection de cons ureau National des Evaluatio Institutional Framework and En attente d'exéc IDA / 63390 A posteriori ultants par entent Direct 0.00 2022-03-01 2022-03-11 2022-04-25 2024-04-24 ns Environnementales (BUNE Project Oversight ution e directe E) pour le Suivi de la mise en oeuvre du PAR et du PGES au Burkina Faso NG-PMU-WAPP-NC-268394-C S-CDS / Convention avec l'Ag Sélection de cons ence Béninoise pour l'Enviro Institutional Framework and En attente d'exéc IDA / 63400 A posteriori ultants par entent Direct 0.00 2022-03-01 2022-03-11 2022-04-25 2024-04-24 nnement (ABE) pour la survei Project Oversight ution e directe llance et le suivi de la mise e n œuvre du PAR et du PGES NG-PMU-WAPP-NC-278784-C S-CDS / Recrutement du Cabi Sélection de cons Institutional Framework and net pour le recrutement du P IDA / D3910 A posteriori ultants par entent Direct 79,653.00 Signé 2022-03-28 2022-03-22 2022-04-16 2022-04-07 2022-05-01 2022-05-01 2022-06-30 Project Oversight ersonnel des antennes locale e directe s du Projet (Nigeria, Niger, B énin et Burkina Faso) NG-PMU-WAPP-NC-265021-C S-INDV / Recrutement d'un c Institutional Framework and IDA / D3910 A posteriori Individuel Open 0.00 Annulé 2022-04-18 2022-03-30 2022-06-22 2022-07-13 2022-08-17 2022-09-16 onsultant Individuel chargé d Project Oversight e l'évaluation à mi-parcours du Projet NG-PMU-WAPP-NC-155331-C S-INDV / Ingénieur Gestionna Institutional Framework and IDA / 63420 A posteriori Individuel Limited 0.00 Annulé 2020-04-06 2020-04-20 2020-05-20 2020-06-08 2024-01-19 ire de Contrats pour l'unité d Project Oversight e Birnin Kebbi au Nigéria Page 4 NG-PMU-WAPP-NC-155339-C Institutional Framework and S-INDV / Supreviseur Ligne p IDA / 63420 A posteriori Individuel Limited 0.00 Annulé 2020-04-06 2020-04-20 2020-05-20 2020-06-08 2023-01-24 Project Oversight our l'unité locale de Birnin Ke bbi au Nigéria NG-PMU-WAPP-NC-155343-C S-INDV / Ingénieur Gestionair Institutional Framework and IDA / D3930 A posteriori Individuel Limited 0.00 Annulé 2020-04-06 2020-04-20 2020-04-23 2020-05-12 2023-12-23 e de contrats pour l'unité de Project Oversight Malanville au Bénin NG-PMU-WAPP-NC-155347-C Institutional Framework and S-INDV / Superviseur Lignes IDA / D3930 A posteriori Individuel Limited 0.00 Annulé 2020-04-06 2020-04-07 2020-05-07 2020-05-26 2023-01-11 Project Oversight et Postes pour l'unité de Mala nville au Bénin NG-PMU-WAPP-NC-378678-C Sélection de cons S-CDS / Reprise de la réalisat Institutional Framework and Direct - Internation En attente d'exéc IDA / D3910 A posteriori ultants par entent 0.00 2023-08-24 2023-08-26 2023-08-31 2023-09-30 ion de l’audit des Comptes (e Project Oversight al ution e directe xercices 2022) du Projet NG-PMU-WAPP-NC-392730-C S-CDS / Characterization of p hysical, biological and social Strengthening Institutional C Sélection de cons Direct - Internation En attente d'exéc components TO FINALYSE th IDA / 63420 apacity for Regional Electrici A posteriori ultants par entent 0.00 2023-11-27 2023-12-07 2023-12-26 2024-04-24 al ution e median core's Line Route a ty Trade e directe nd Environmental and Social Impact Assessment (ESIA) St udy NG-PMU-WAPP-NC-392732-C S-CDS / Demarcation activitie Strengthening Institutional C Sélection de cons s in Côte d'Ivoire TO FINALYS Direct - Internation En attente d'exéc IDA / 63420 apacity for Regional Electrici A posteriori ultants par entent 0.00 2023-11-27 2023-12-07 2023-12-26 2024-04-24 E the median core's Line Rou al ution ty Trade e directe te and Environmental and So cial Impact Assessment (ESIA ) Study. Page 5