PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Sri Lanka CLIMATE RESILIENCE MULTIPHASE PROGRAMMATIC APPROACH P 160005 Project Implementation agency: Ministry of Agriculture, Rural Economic Affairs, Livestock Development, Irrigation, Fisheries and Aquatic Resources Development : [insert legal name] Date of the Procurement Plan: [insert date]April 18, 2019 Period covered by this Procurement Plan: [insert from – to period]April 2019 to October 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. : In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable”Not Applicable Procurement of Second- Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables : Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Sri Lanka : Climate Resilience Multi-Phase Programmatic Approach PLAN General Information Country: Sri Lanka 2022-07-29 Bank’s Approval Date of the Original Procurement Plan: 2023-11-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160005 GPN Date: 2019-07-28 Project Name: Climate Resilience Multi-Phase Programmatic Approach Loan / Credit No: IBRD / 89960 MINISTRY OF IRRIGATION Executing Agency(ies): WORKS Activity Reference No. Procurement Estimated Actual A Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl / Description Component Review Type Method Document Ty Amount ( mount ( rt and Recommenda Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) US$) tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne National Procur d SLMOI/CRES/DOM/W/NCB/ Component 1: Forecasting ement Docume 01 / Construction of Nation and Early Warning of High Single Stage - On 4,500,000. 2022-09-3 2022-10-0 2022-10-2 2022-11-2 2023-02-1 2024-06- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 0.00 Canceled al Meteorological Center B Impact Weather, Floods a e Envelope 00 0 5 6 5 7 14 process (Non B uilding at Department of M nd Landslides ank-SPD) eteorology National Procur SLMOI/CRES/ID/W/NCB/03 Component 1: Forecasting ement Docume / Refurbishment of the offi and Early Warning of High Single Stage - On 2022-08-3 2022-10-1 2022-09-0 2022-09-2 2022-11-2 2022-10-1 2023-01-2 2022-11-1 2023-02-0 2023-01- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 56,000.00 0.00 Signed ce space of Hydrology & D Impact Weather, Floods a e Envelope 1 2 5 6 9 7 6 4 8 13 process (Non B M Division of Irrigation De nd Landslides ank-SPD) partment National Procur SLMOI/CRES/DMC/W/NCB/ Component 1: Forecasting ement Docume Pending I Single Stage - On 2022-11-2 2022-11-2 2022-12-1 2023-01-1 2023-02-2 2023-05- 08 / Refurbishment of EOC IBRD / 89960 and Early Warning of High Post Request for Bids Open - National nt - 1 Envelope 400,000.00 0.00 mplement e Envelope 1 6 7 6 7 28 at Disaster Management C Impact Weather, Floods a process (Non B ation entre nd Landslides ank-SPD) Request for Bid SLMOI/CRES/ID/W/ICB/02 / Component 2: Flood Risk Pending I Open - Internatio Single Stage - On s - Small Works 16,750,000 2023-10-0 2023-10-1 2023-12-1 2024-03-1 2024-05-1 2026-05- Construction of Ambatale IBRD / 89960 Mitigation Investments in Prior Request for Bids 0.00 mplement nal e Envelope SPD (1 envelop .00 2 6 5 4 9 09 Salinity Barrier the lower Kelani basin ation e process) SLMOI/CRES/ID/W/NCB/04 National Procur / Development of Flood Mo Component 1: Forecasting ement Docume Pending I nitoring and Operation Ce and Early Warning of High Single Stage - On 2022-09-1 2022-09-1 2022-10-0 2022-10-2 2022-12-1 2023-06- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 520,000.00 0.00 mplement nter coupled with CCTV Flo Impact Weather, Floods a e Envelope 2 7 8 3 1 09 process (Non B ation od Level Monitoring Syste nd Landslides ank-SPD) m at Hydrology & Disaster Management Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATL/RFQ/009 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 32,691.67 0.00 mplement mants to main canal in Bo ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation wathenna scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -PUT/NCB/007 / Improvem climate resilience and mai Single Stage - On 2023-08-0 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-05- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 99,740.00 0.00 Canceled ents to Maiyawa tank & 1s ntenance of irrigation and e Envelope 2 7 8 8 2 07 process (Non B t spill in Sengaloya schem storm water infrastructure ank-SPD) e National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/RFQ/011 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,033.33 0.00 mplement ents to spill structure of Th ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation irappankadawala tank in H storm water infrastructure ank-SPD) uruluwewa Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -JAF/RFQ/003 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-10-0 2024-01- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 Canceled nt of Paravaikadal SWE Bu ntenance of irrigation and tations e Envelope 7 2 30 process (Non B nd storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID -NUE/RFQ/004 / Constructi National Procur Component 5: Improving on of canal lining from 4+ ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- 332 to 4+394, 4+426 to 4 IBRD / 89960 Post Limited nt - 1 Envelope 27,076.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 28 +438, 4+516 to 4+536 & process (Non B ation storm water infrastructure 4+550 to 4+580, Improve ank-SPD) ments to canal bund in ma in canal of Paragahaarawa scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KUR/RFQ/028 / Reconstru climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-10-0 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 28,270.00 0.00 Canceled ction of sluice at Kiniyama ntenance of irrigation and tations e Envelope 7 2 28 process (Non B tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATR/RFQ/009 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-10-0 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 22,500.00 0.00 mplement ments to drainage canals i ntenance of irrigation and tations e Envelope 7 2 29 process (Non B ation n Kadawedduwa scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/RFQ/008 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,666.67 0.00 mplement ents to Causeway in D4/5 ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation Drainage canal in Wahalka storm water infrastructure ank-SPD) da Scheme in Padaviya Di vision CRESMPA-1/RP/WORKS/ID National Procur -ANU/RFQ/018 / Constructi Component 5: Improving ement Docume Pending I on of Drainage undercrossi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ng structure including can ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation al drop structure at stn 1+ storm water infrastructure ank-SPD) 090 in feeder canal of Sole wewa in Rajanaganya Sch eme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -BAT/NCB/010 / Reconstru climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-01- IBRD / 89960 Post Open - National nt - 1 Envelope 53,333.33 0.00 Canceled ction of Vinayagar Anicut i ntenance of irrigation and tations e Envelope 5 0 08 process (Non B n Navakiri scheme, Navaki storm water infrastructure ank-SPD) ri Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -COL/RFQ/037 / Desilting a climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 25,508.34 0.00 Canceled nd removing obstacles in ntenance of irrigation and tations e Envelope 5 0 28 process (Non B Haldummulla canal from storm water infrastructure ank-SPD) 0+000km to 1+000km CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -POL/RFQ/065 / Constructi ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- on of retangular canal linin IBRD / 89960 Post Limited nt - 1 Envelope 16,800.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 28 g from stn. 0+475 to stn. process (Non B ation storm water infrastructure 0+525 in Yaya 6 D canal, ank-SPD) Tract 6 DCFO Area National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/070 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 22,960.00 0.00 mplement ents to FC - 01 canal in Go ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation visetha DCO area in HLBC storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/075 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 36,833.33 0.00 mplement on of conc. Lining from 0+ ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation 140 to 0+290 of LB 01 FC storm water infrastructure ank-SPD) / D05 / RB-01 in Girithale Main Canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/079 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 36,033.33 0.00 mplement ents to RB 07/ii of D07 / R ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation B 01 MC in Girithale Sche storm water infrastructure ank-SPD) me CRESMPA-1/RP/WORKS/ID National Procur -POL/RFQ/084 / Contructio Component 5: Improving ement Docume Pending I n of 80m long U type canal climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 39,100.00 0.00 mplement lining from stn 0+046 to st ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation n 0+126 in Batuhena (FC storm water infrastructure ank-SPD) 59Canal) Nikapitiya D can al in Elahara division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/087 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 25,366.67 0.00 mplement ents to RB/1 tail end in D0 ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation 7 canal in Girithale Schem storm water infrastructure ank-SPD) e National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/095 / Gravelling climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 18,133.33 0.00 mplement & Forming Bund Road of F ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation C09 & FC11 / LB 01 in Girit storm water infrastructure ank-SPD) hale Main Canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/098 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 28,333.33 0.00 mplement ents to RB 5 canal in Kalin ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation ga DCO area in LLMC storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur -POL/NCB/005 / Constructi Component 5: Improving ement Docume Pending I on of 147m long concrete climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 71,433.33 0.00 mplement rectangular canal lining fro ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation m stn 4+376 to stn 4+526 storm water infrastructure ank-SPD) .5 in B506/507 branch can al in Aththanakadawala un it. National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- -POL/RFQ/099 / Improvem IBRD / 89960 Post Limited nt - 1 Envelope 38,200.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 30 ents to D 10 / RB 01 process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/008 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement ents to Canal System in H ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation almilla Wewa in Hatharas storm water infrastructure ank-SPD) Kotuwa National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/024 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 26,000.00 0.00 mplement on of canal lining and box ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation culvert from 0+053 to 0+ storm water infrastructure ank-SPD) 165 in Dambewewa RB ma in canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/026 / Rehabilita climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 31,666.67 0.00 mplement tion of FC 18 canal in LBM ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation C Hambegamuwa storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/101 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 41,113.33 0.00 mplement on of 230 m long retaining ntenance of irrigation and tations e Envelope 5 0 29 process (Non B ation wall at 1+550 in RB side in storm water infrastructure ank-SPD) RB 10 off D1 east canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/NCB/103 / Constructi climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-05- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,533.33 0.00 mplement on of Gabion Walls along t ntenance of irrigation and e Envelope 1 5 6 6 0 18 process (Non B ation he Rota wewa bund in MK storm water infrastructure ank-SPD) YE in Minneriya Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -MON/NCB/027 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-10-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,000.00 0.00 lementati ents to Palugasmada Feed ntenance of irrigation and e Envelope 1 0 5 6 6 0 14 process (Non B on er canal storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/106 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 mplement ents to D - 2A canal in Sah ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation ana DCO area in HLBC1 storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID -POL/RFQ/112 / Constructi on of the 18m long rectan National Procur Component 5: Improving gular canal lining at stn. 0 ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- +000, demolished old dam IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 age existing hume pipe tro process (Non B ation storm water infrastructure ugh structure & reconstruc ank-SPD) tion of 8m long rectangula r trough structure at stn. 0 +018 & construction 36m l ong retaining wall structur eCRESMPA-1/RP/WORKS/ID at stn. National Procur -POL/RFQ/009 / Constructi Component 5: Improving ement Docume Pending I on of 50 m long concrete r climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 37,833.33 0.00 mplement ectangular canal lining fro ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation m stn 1+202 to stn 1+252 storm water infrastructure ank-SPD) in B506/507 branch canal i n Aththanakadawala unit. National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/114 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 mplement ents to D - 1 canal in Sam ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation agi DCO in LLMC storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID -POL/NCB/122 / Demalishi National Procur Component 5: Improving ng old damaged hump pip ement Docume Pending I climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- e trough at stn 0+830 & c IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 66,666.67 0.00 mplement ntenance of irrigation and e Envelope 1 5 6 6 0 14 onstruction rectangular tr process (Non B ation storm water infrastructure ough structure and rectan ank-SPD) gular canal lining stn 0+73 0 to stn 0+920 in Jambure wela DCFO area CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -POL/RFQ/128 / Constructi ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- on of canal lining from stn. IBRD / 89960 Post Limited nt - 1 Envelope 21,666.66 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 3+400 to stn. 3+510 in B5 process (Non B ation storm water infrastructure 03 Sirikanduyaya Katuwa ank-SPD) canal in Sirikanduyaya DC FO area. Page 1 National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/133 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 mplement ion of the Spill Canal (RB0 ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation 1) & Bund Road / LB-01 in storm water infrastructure ank-SPD) Girithale Main Canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/012 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement on of Feeder Canal for Bad ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation depanwila Tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/134 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement ents to Trough structure at ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation stn. 2+770 in Ihakuluwew storm water infrastructure ank-SPD) a main canal (510 LB Cana l) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/029 / Rehabilita climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement tion of FC 02 in LBMC in LB ntenance of irrigation and tations e Envelope 5 0 25 process (Non B ation tank in Mahawewa storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/135 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 36,430.00 0.00 mplement ents to FC 4 canal in Boow ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation ewa scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/015 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 mplement on of Godapoththa Bridge ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation Structure storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/032 / Rehabilita climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement tion of FC 01 RBMC in LB K ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation andiyapitiya tank storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -POL/NCB/140 / Constructi ement Docume Pending I climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- on of the 25m long damag IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 66,666.67 0.00 mplement ntenance of irrigation and e Envelope 1 5 6 6 0 14 ed cantiliver wall section a process (Non B ation storm water infrastructure t stn. 9+100 RB side of the ank-SPD) EMYE main canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -MON/NCB/037 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-10-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,000.00 0.00 lementati ensts to FC 50 canal & bun ntenance of irrigation and e Envelope 1 0 5 6 6 0 14 process (Non B on d road of RB main Canal in storm water infrastructure ank-SPD) Handapanagala CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MON/NCB/041 / Demolishi ement Docume Under Imp climate resilience and mai Single Stage - On 2023-07-3 2023-10-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- ng and Reconstruction of t IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 56,586.67 0.00 lementati ntenance of irrigation and e Envelope 1 0 5 6 6 0 14 rough and lining structure process (Non B on storm water infrastructure at 12+940 in Kumbukkana ank-SPD) main canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/142 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 28,333.33 0.00 mplement on of Canal Spill at 29+29 ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation 0 in D37/LBMC in Vihara m storm water infrastructure ank-SPD) awatha DCO in Minneriya Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/NCB/042 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 42,666.67 0.00 mplement ent of 1st Km RBMC in Ma ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation hawewa storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -POL/RFQ/143 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- ents to Elikibulawa (B 508) IBRD / 89960 Post Limited nt - 2 Envelope 20,000.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 Canal from stn. 1+500 to s process (Non B ation storm water infrastructure tn. 2+760 in Elikibulawa D ank-SPD) CFO Area National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/043 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ents of spill in Debara ara ntenance of irrigation and tations e Envelope 5 0 25 process (Non B ation Tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/148 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 2 Envelope 10,490.00 0.00 mplement ents to LB side bund at 8+ ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation 200 in D1 east canal storm water infrastructure ank-SPD) National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- -POL/RFQ/019 / Constructi IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 28 on of Godapoththa anicut process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/149 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 2 Envelope 33,333.33 0.00 mplement ents to 198 - Kongahawew ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation a (Second stage) in Konwe storm water infrastructure ank-SPD) wa DCO area National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/047 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement on of 50m lining at 1+325 ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation in RB main canal in Saddat storm water infrastructure ank-SPD) issa CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -POL/RFQ/153 / Demolishin ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- g and New Constrction of IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 160 m long retaining wall f process (Non B ation storm water infrastructure rom 0+000 km to 0+160k ank-SPD) m D17 /LBMC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/027 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 35,433.33 0.00 mplement ents to FC 13 canal in Sam ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation a DCO area in HLMC storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/NCB/031 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-09- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 75,933.33 0.00 mplement ents to RB 01 canal (from ntenance of irrigation and e Envelope 1 5 6 6 0 15 process (Non B ation 550 m to 750m) in CP Pura storm water infrastructure ank-SPD) Perakum DCO area in LLM C National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/034 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 18,186.67 0.00 mplement ents to RB6 canal in Galth ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation ambarawa DCO storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/57 / Rehabilitati climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 mplement on of LB canal section 1 in ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation Karadanda Ara Tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/58 / Rehabilitati climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 48,333.33 0.00 mplement on of LB canal section 2 in ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation Karadanda Ara Tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/59 / Extention t climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 43,333.33 0.00 mplement o LB and RB canals in Kiu ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation vle tank (500 m) storm water infrastructure ank-SPD) National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- -MON/RFQ/60 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 24 nts to Kindaliya tank canal process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/61 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 mplement nt to Nawaara Tank LB can ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation al storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -ANU/RFQ/006 / Constructi ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- on of channel spill in Mah IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 24 awilachchiya RB main can process (Non B ation storm water infrastructure al Breached section at 5+ ank-SPD) 650km in Anuradhapura National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/RFQ/012 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 29,300.00 0.00 mplement ents to U/S and D/S Troug ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation h structure in Ellapothana storm water infrastructure ank-SPD) scheme, Huruluwewa Divis ion CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -ANU/RFQ/013 / Demolishi ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- ng and Reconstruction of T IBRD / 89960 Post Limited nt - 1 Envelope 36,666.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 24 hubulla Regulator at RB M process (Non B ation storm water infrastructure ain Canal in Rajanganaya ank-SPD) Scheme CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -ANU/NCB/015 / Improvem ement Docume Pending I climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- ent to LB Main Canal of Hu IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 63,100.00 0.00 mplement ntenance of irrigation and e Envelope 1 5 6 6 0 14 ruluwewa and Ulpathgama process (Non B ation storm water infrastructure field canal (FC 04) road in ank-SPD) Huruluwewa Division CRESMPA-1/RP/WORKS/ID National Procur -ANU/RFQ/019 / Demolishi Component 5: Improving ement Docume Pending I ng & re-construction of Bal climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement ayawewa Regulator includi ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation ng casting & installation of storm water infrastructure ank-SPD) steel gates in Upper Main Canal in Padaviya scheme . National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/RFQ/023 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 46,200.00 0.00 mplement ion of FC05 Canal at LB slu ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation ice in Thuruwila in Nachch storm water infrastructure ank-SPD) aduwa scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/NCB/024 / Renovatio climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 56,666.67 0.00 mplement n to the damaged section ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation of spillway in Kallanchiya t storm water infrastructure ank-SPD) ank in Anuradhapura National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/RFQ/025 / Reconstru climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement ction of LB 01, D 09 and F ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation C 03 canals of Lower Main storm water infrastructure ank-SPD) Canal in Padaviya National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/RFQ/032 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 19,766.67 0.00 mplement ents to FC34, D 09 and RB ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation MC in Huruluwewa scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/RFQ/034 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 mplement ents to CP canal in Halpan ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation u ela anicut scheme in An storm water infrastructure ank-SPD) uradhapura National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/62 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 48,333.33 0.00 mplement nt to Nawaara Tank RB ca ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation nal storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/64 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 mplement nts to Kirioruwa Tank cana ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation l system storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -GAL/RFQ/006 / Dredging fi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 32,696.67 0.00 mplement eld canals & D-canals in H ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation oluwagoda II scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/66 / Rehabilitati climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 48,333.33 0.00 mplement on of Thenagallanda Tank ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation canal system storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -GAL/NCB/011 / Constructi climate resilience and mai Single Stage - On 2023-07-3 2023-10-0 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 51,233.33 0.00 lementati on of bank protection for e ntenance of irrigation and e Envelope 1 3 5 6 6 0 14 process (Non B on rroded section in Holuwag storm water infrastructure ank-SPD) oda I scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/NCB/035 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-05- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 67,833.33 0.00 mplement ents to branch canal (17m ntenance of irrigation and e Envelope 1 5 6 6 0 18 process (Non B ation to 300m) in Ekasth (1B Ya storm water infrastructure ank-SPD) ya) DCO area in LLMC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/038 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 26,953.33 0.00 mplement on of 145m long retaining ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation wall in LB side in RB 06 off storm water infrastructure ank-SPD) D2 main canal Page 2 CRESMPA-1/RP/WORKS/ID -POL/RFQ/039 / Constructi National Procur Component 5: Improving on of Retaining wall in D 0 ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- 2 canal (Construction of 2 IBRD / 89960 Post Limited nt - 1 Envelope 37,933.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 00 m length Retaining wall process (Non B ation storm water infrastructure both side of the main cana ank-SPD) l from No. 533 Mr. Premasi ri's paddy land to No 527 Mr. Liyanage's paddy land) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/043 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 19,383.33 0.00 mplement ents to D 01 canal in Rank ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation etha DCO area in LLMC storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/047 / Gravelling climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 19,906.67 0.00 mplement D 8 main canal road (abo ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation ut 4 km) storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur -MATR/NCB/008 / Improve Component 5: Improving ement Docume Pending I ments of Ellekanda tank m climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 56,000.00 0.00 mplement ain canal construction of c ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation anal lining from CH 4+ 14 storm water infrastructure ank-SPD) 7.5 to 4+347.5 in Kekanad ura scheme ( 200m) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATR/RFQ/011 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 39,200.00 0.00 mplement ments of main canal at Na ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation mamidola near karaputug storm water infrastructure ank-SPD) ala school in Ellewela sche me CRESMPA-1/RP/WORKS/ID National Procur -MATR/NCB/014 / Improve Component 5: Improving ement Docume Pending I ments to uyanwewa Sche climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 54,833.33 0.00 mplement me(Sub1-Improvements to ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation Uyanwewa tank bund, Sub storm water infrastructure ank-SPD) 2-Improvements to spill tai l canal & LB main canal in Uyanwewa scheme) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATR/NCB/016 / Improve climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 53,800.00 0.00 mplement ments to Haliela main can ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation al in Haliela scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATR/RFQ/019 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 21,133.33 0.00 mplement ments of palolpitiya D'can ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation al in Urapola scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATR/RFQ/020 / Construc climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 18,600.00 0.00 mplement tion of canal lining along t ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation he main spill cannel at wa storm water infrastructure ank-SPD) doruwa anicut in Ellewela scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/050 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 27,243.33 0.00 mplement ents to LB 1 canal in Deba ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation rella DCO area storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/051 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 31,206.67 0.00 mplement ents to D - 3 canal in Weer ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation akeppetipola DCO area in storm water infrastructure ank-SPD) HLBC 1A National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/056 / Filling pot climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 25,000.00 0.00 mplement holl and gravelling along L ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation B 06 canal off D04 canal storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/058 / Gravelling climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-01- IBRD / 89960 Post Limited nt - 1 Envelope 18,490.00 0.00 mplement to Canal bund road from 7 ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation +000 to 7+332 of RB1 off storm water infrastructure ank-SPD) D2 main canal National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- -POL/RFQ/059 / Improvem IBRD / 89960 Post Limited nt - 1 Envelope 34,716.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 28 ents to FC - 32 canal process (Non B ation storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -RAT/RFQ/002 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-04- ents to RB Bank of the Rak IBRD / 89960 Post Limited nt - 1 Envelope 18,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 27 wana Ganga from 0+125 t process (Non B ation storm water infrastructure o 0+170 from Wellawa Ani ank-SPD) cut structure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/060 / Filling pot climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-01- IBRD / 89960 Post Limited nt - 1 Envelope 22,400.00 0.00 mplement holls in LB03 , FC02 off LB ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation 03 , FC03 off LB03 in D04 storm water infrastructure ank-SPD) canal CRESMPA-1/RP/WORKS/ID -POL/RFQ/061 / Demolishe d existing hume pipe culve National Procur Component 5: Improving rt & construction of 11.4m ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- long box culvert at stn. 0+ IBRD / 89960 Post Limited nt - 1 Envelope 17,966.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 600, construction of 27m l process (Non B ation storm water infrastructure ong rectangular canal linin ank-SPD) g & 8m long box culvert at stn. 0+750 & construction of 6m long wall and 6m lo ng box culvert at stn. 0+8 National Procur CRESMPA-1/RP/WORKS/ID 20 in Kum Component 5: Improving ement Docume Pending I -RAT/RFQ/010 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 mplement ents to canal section from ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation 0+420 to 0+720 in D2 LB storm water infrastructure ank-SPD) MC in Kalthota scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/062 / Canal linin climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 37,776.67 0.00 mplement g at 0+036 to 0+215 in LB ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation 6 off D 2 canal storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -RAT/RFQ/012 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 17,333.33 0.00 mplement on of canal lining in Pathth ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation aduwela D Canal & FC 02 storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -RAT/RFQ/013 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 17,000.00 0.00 mplement on of Under crossing struct ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation ure at Saddathissa Main ca storm water infrastructure ank-SPD) nal to cross for Elephants National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/NCB/063 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-05- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 72,426.67 0.00 mplement ents to FC - 03 canal in Ma ntenance of irrigation and e Envelope 1 5 6 6 0 18 process (Non B ation haweli DCO area in HLBC storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -RAT/RFQ/022 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 22,000.00 0.00 mplement ents to FC02/D1/RBMC in K ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation althota scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -RAT/RFQ/032 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 28,333.33 0.00 mplement ents of downstream of spill ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation of Wewelanda Scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/008 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 30,980.00 0.00 mplement ents to main Canal from St ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation n 0+000 to 0+040 in Pann storm water infrastructure ank-SPD) algama scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/NCB/009 / Reconstru climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 61,633.33 0.00 mplement ction of DC 03 morning Gl ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation ory spill in RB main canal storm water infrastructure ank-SPD) at stn 25+200 in Damana unit National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/010 / Reconstru climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement ction of DR 13 MG structu ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation re @ 11+850 in Ekkaloya storm water infrastructure ank-SPD) MC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -AMP/NCB/011 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-09-2 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 91,566.67 0.00 lementati ents of structures in G 07 ntenance of irrigation and e Envelope 1 8 5 6 6 0 14 process (Non B on canal at Gonagolla unit storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -AMP/RFQ/013 / Reconstru ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- ction of 1.5 m span ,11.5 IBRD / 89960 Post Limited nt - 1 Envelope 32,713.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 m width culvert including process (Non B ation storm water infrastructure Retaining wall at stn 0+38 ank-SPD) 5 in PK-28 D canal in Illuku chenai unit CRESMPA-1/RP/WORKS/ID National Procur -AMP/RFQ/014 / Constructi Component 5: Improving ement Docume Pending I on of 4m span box culvert climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 mplement , drainage inlet & LB turno ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation ut structure in SK 04/1 drai storm water infrastructure ank-SPD) nage canal at the tail end of SK 11 Distributary canal CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -AMP/RFQ/016 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- ents to SKDC, SK-03 Distri IBRD / 89960 Post Limited nt - 1 Envelope 22,900.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 27 butary canal and SK-16 Di process (Non B ation storm water infrastructure stributary canal in SKBC in ank-SPD) Akkaraipattu unit. National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/017 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 49,140.00 0.00 mplement ents to KLBC in Deegawapi ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation unit storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -AMP/RFQ/018 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- ents to Seenampity Main C IBRD / 89960 Post Limited nt - 1 Envelope 44,260.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 24 hannel from stn. 0+000 to process (Non B ation storm water infrastructure stn. 0+650 Km. in Veeraya ank-SPD) di unit National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-04- -KAL/RFQ/022 / Cleaing & IBRD / 89960 Post Limited nt - 1 Envelope 18,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 27 Improvement egaloya ela process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/020 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 28,171.17 0.00 mplement on of Box culverts across S ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation almadu Periyaveli Main Chl storm water infrastructure ank-SPD) . in Paddampitty Unit National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/022 / improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 32,600.00 0.00 mplement ent of Udangaveli Anicut i ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation n Moravil unit II storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATL/RFQ/008 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 31,670.00 0.00 mplement ments to D52 RB 2 Canal i ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation n Stage III storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur -AMP/RFQ/024 / Improvem Component 5: Improving ement Docume Pending I ents to D/S of Kythiyadi re climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 22,460.00 0.00 mplement gulator cum Bridge Struct ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation ure including construction storm water infrastructure ank-SPD) of bolder Packing Rip Rap at both side In Upper weer ayadi Unit National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/025 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 18,583.33 0.00 mplement ents to Regulators and offt ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation akes in Sengappadai LB un storm water infrastructure ank-SPD) it CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -AMP/RFQ/033 / Constructi ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- on of 5 m width box culver IBRD / 89960 Post Limited nt - 1 Envelope 30,586.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 t cum regulator in Kalladi c process (Non B ation storm water infrastructure hannel stn at 0+425 at Ka ank-SPD) rangowa in Nawalaru sche me CRESMPA-1/RP/WORKS/ID National Procur -AMP/RFQ/036 / Constructi Component 5: Improving ement Docume Pending I on of two Morning Glory S climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 29,103.33 0.00 mplement pills in LB 24 canal & Impr ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation ovements to structures in storm water infrastructure ank-SPD) LB 1.1 field canal of Senag ama Dambe Ela Anicut in Gonagolla Unit Page 3 National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/037 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 18,830.00 0.00 mplement ents to Regulater structure ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation s in Pannalgama scheme storm water infrastructure ank-SPD) National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- -AMP/RFQ/072 / Improvem IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 ent for Tank Bund process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/073 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ent for Tank Bund and Spil ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation l storm water infrastructure ank-SPD) National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- -AMP/RFQ/074 / Improvem IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 27 ent of Main Cannel process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/075 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement ent of Tank Bund and Can ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation nel storm water infrastructure ank-SPD) National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- -AMP/RFQ/076 / Improvem IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 24 ent of Tank Bund process (Non B ation storm water infrastructure ank-SPD) National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- -AMP/NCB/077 / Repair of IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 66,666.67 0.00 mplement ntenance of irrigation and e Envelope 1 5 6 6 0 14 Spill process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/RFQ/078 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ent for Tank Bund, Spill, Sl ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation uice storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KUR/RFQ/008 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 19,499.33 0.00 Canceled ents to D19 canal of Doluk ntenance of irrigation and tations e Envelope 5 0 27 process (Non B anda canal in Bathalagoda storm water infrastructure ank-SPD) Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KUR/NCB/013 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 76,666.67 0.00 Canceled ents to FC1 and FC2 canal ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B s under Mukalanyaya D2 c storm water infrastructure ank-SPD) anal in Bathalagoda sche me National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/009 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 45,896.67 0.00 mplement ents to Police ela (0+900 - ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation 1+050) of HLMC,Tissa We storm water infrastructure ank-SPD) wa CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -HAM/RFQ/010 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- ents to Medagoda Ela from IBRD / 89960 Post Limited nt - 1 Envelope 35,060.82 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 24 0+085 to 0+330 in Welipa process (Non B ation storm water infrastructure tanwila RB canal of Oluwil ank-SPD) a unit in WRB scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/012 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 46,990.00 0.00 mplement on of canal lining from (0+ ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation 025 - 0+124) in main cana storm water infrastructure ank-SPD) l, Bandagiriya CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -HAM/RFQ/013 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- ents to Medagoda Ela (0+ IBRD / 89960 Post Limited nt - 1 Envelope 37,014.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 24 330 - 0+595) in Welipatan process (Non B ation storm water infrastructure wila RB canal of Oluwila U ank-SPD) nit in WRB Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/018 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 43,230.00 0.00 mplement ents to FC 15,DC 02,Track ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation 02,RBMC, Lunugamwehera storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -HAM/RFQ/020 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- ents to Overtopping sectio IBRD / 89960 Post Limited nt - 1 Envelope 25,490.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 27 n at 0+412 (150m) in Naw process (Non B ation storm water infrastructure arathnamulana Canal, Uru ank-SPD) bokka - oya scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/021 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 35,113.33 0.00 mplement ents to FC36 DC3 Bandagi ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation riya Scheme storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -KUR/RFQ/016 / Constructi ement Docume climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- on of regulator structure a IBRD / 89960 Post Limited nt - 1 Envelope 16,926.67 0.00 Canceled ntenance of irrigation and tations e Envelope 5 0 28 t 22+300 in LB Main canal process (Non B storm water infrastructure in Wariyapola (Starting poi ank-SPD) nt of Branch canal 01) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/025 / Installing f climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 16,901.03 0.00 mplement arm turn out and canal lini ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation ng at 0+010 to 0+171 in S storm water infrastructure ank-SPD) RB RB 01 canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/NCB/063 / Reconstru climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 100,000.00 0.00 mplement ction of weheragal anicut ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation across malala ara storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/069 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement on of feeder canal to Kalu ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation muththa wewa storm water infrastructure ank-SPD) National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- -HAM/RFQ/076 / Improvem IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 24 ents to Wak ari wewa process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KUR/RFQ/022 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 24,666.67 0.00 Canceled on of closed under crossin ntenance of irrigation and tations e Envelope 5 0 27 process (Non B g at 1+573 in Branch Can storm water infrastructure ank-SPD) al 2 in Wariyapola National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KUR/RFQ/027 / Improving climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 27,814.33 0.00 mplement canal from 0+850 to 1+05 ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation 5 by half-circular pipes in storm water infrastructure ank-SPD) Wellangiriya scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KUR/NCB/030 / Rehabilitat climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,000.00 0.00 Canceled ion of trough in LB canal of ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B Mahasiyabalangamuawa storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAD/RFQ/002 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ents of Aluth Ela Main Can ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation al storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAD/RFQ/045 / Concreatin climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement g 6 km of Avukana canal i ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation n Uvathanna GN division storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -GAL/NCB/017 / Constructi climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 40,000.00 0.00 mplement on of new Structures in Me ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation himulla scheme storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -GAL/RFQ/029 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- ents to Agriculture road fr IBRD / 89960 Post Limited nt - 1 Envelope 17,980.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 28 om Kammalgodayaya to A process (Non B ation storm water infrastructure thula Darshanarama road ank-SPD) (1+050 km to 1+750 km) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -GAL/RFQ/030 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 3,333.33 0.00 mplement ents to canals, flood bunds ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation , structures and pump hou storm water infrastructure ank-SPD) se in Kiribathawila scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -GAL/NCB/044 / Rehabilitat climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 51,666.67 0.00 mplement ion of gates of 2 and 3 ani ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation cut of Heenela storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KUR/NCB/066 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-0 2024-10- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 8,000.00 0.00 Canceled ents to Digandeniya tank i ntenance of irrigation and e Envelope 1 5 6 6 6 31 process (Non B n Narammala storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving -AMP/DC/002 / Estimate fo Other (with fiel Pending I climate resilience and mai 2023-08-0 2023-08-1 2023-09-1 2024-03- r Fabrication, sand blastin IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,166.67 0.00 mplement ntenance of irrigation and 7 2 6 14 g & painting 4 Nos of gate n) ation storm water infrastructure s for reulator RBMC in Akk arapattu Division CRESMPA-1/RP/WORKS/ID -BAD/DC/072 / Improment Component 5: Improving s to D1 & D2 Canal regul Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- ator gates, canal spill gate IBRD / 89960 Post Direct Selection Direct - National d for explanatio 8,766.67 0.00 mplement ntenance of irrigation and 1 5 9 07 s at 1+250 of LBMC and 2 n) ation storm water infrastructure Nos gates at D3 canal of L BMC of Sorabora wewa, M apakada Division, Bandara wela CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/113 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,123.33 0.00 mplement nts to South canal bund ro ntenance of irrigation and 1 5 9 07 n) ation ad in Swarnapaligama DC storm water infrastructure O CRESMPA-1/RP/WORKS/ID Component 5: Improving -POL/DC/002 / Installing 02 Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- Nos of lifting hoist and oth IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,666.67 0.00 mplement ntenance of irrigation and 1 5 9 07 er remedial works for Tha n) ation storm water infrastructure mbalawewa Sluice gate in Minneriya Division CRESMPA-1/RP/WORKS/ID -MON/DC/002 / Repair and installation of 10 Nos of fe Component 5: Improving eder canal gates at 01 Nos Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- of 5.4ft*3.3ft Regulator ga IBRD / 89960 Post Direct Selection Direct - National d for explanatio 19,055.89 0.00 mplement ntenance of irrigation and 1 5 9 07 te D3 and 01Nos of 5.4ft*3 n) ation storm water infrastructure .3ft Regulator gate near 0 1 Nos of 5.4ft&3.3ft Regul ator gate at D 4 in main ca nel at Muthukeliywa Sche me in Monaragala Division CRESMPA-1/RP/WORKS/ID -ANU/DC/005 / Fabrication Component 5: Improving Other (with fiel Pending I and Installation of 03 Nos climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 25,892.20 0.00 mplement of regulator gates (1025x9 ntenance of irrigation and 1 5 9 07 n) ation 00mm) of MawathaWewa storm water infrastructure Anicut in Nachchaduwa Di vision, Anuradhapura CRESMPA-1/RP/WORKS/ID -MATR/DC/001 / Fabricatio Component 5: Improving Other (with fiel Pending I n,Painting & Installation of climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,284.75 0.00 mplement 1675mmx1650mm Mild St ntenance of irrigation and 1 5 9 07 n) ation eel gates (02Nos) for Wad storm water infrastructure uwakanda anicut at Matar a Division, Galle Component 5: Improving CRESMPA-1/RP/WORKS/ID Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-09- -POL/DC/007 / Constructio IBRD / 89960 Post Direct Selection Direct - National d for explanatio 26,666.67 0.00 mplement ntenance of irrigation and 1 5 9 03 n of Thibiriela anicut n) ation storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -MON/DC/025 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 35,943.74 0.00 mplement n of 30m long trough struc ntenance of irrigation and 1 5 9 03 n) ation ture from 0+126 to 0+156 storm water infrastructure in Main canal in Kotiyagala CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/022 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,973.33 0.00 mplement n of 30m long Retaining w ntenance of irrigation and 1 5 9 07 n) ation all in RB side at 2+150 in storm water infrastructure LB 4/D 2 main canal Page 4 National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/63 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 mplement nts to Kirioruwa Tank bund ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation and sluice storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/65 / Rehabilitati climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 mplement on of Waliara tank - LB can ntenance of irrigation and tations e Envelope 5 0 24 process (Non B ation al storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID -ANU/DC/001 / Estimate fo Component 5: Improving Other (with fiel Pending I r fabrication and installatio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 32,953.47 0.00 mplement n of 16Nos of Regulator ga ntenance of irrigation and 1 5 9 07 n) ation tes of high level main cane storm water infrastructure l in Nachchaduwa Division, Anuradhapura CRESMPA-1/RP/WORKS/ID -ANU/DC/004 / Refabricati Component 5: Improving Other (with fiel Pending I on of lifting eye brackets a climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,475.83 0.00 mplement nd, replacing all lifting wir ntenance of irrigation and 1 5 9 07 n) ation e ropes and turn buckels o storm water infrastructure f radial gates at Ellapothan a Anicut in Huruluwewa Di vision, Anuradhapura CRESMPA-1/RP/WORKS/ID -MATR/DC/003 / Fabricatio Component 5: Improving Other (with fiel Pending I n,Painting & Installation of climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,391.54 0.00 mplement 1680mmx2360mm Mild St ntenance of irrigation and 1 5 9 07 n) ation eel gates (02Nos) for Mee storm water infrastructure gahagoda anicut at Matara Division, Galle CRESMPA-1/RP/WORKS/ID Component 5: Improving -MATR/DC/007 / Supply an Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- d Installation of gear moto IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,288.22 0.00 mplement ntenance of irrigation and 1 5 9 07 rs, worm & Wheel gear bo n) ation storm water infrastructure xes and Electrical wiring of gravity gates in Thudawa Pump House CRESMPA-1/RP/WORKS/ID -MATR/DC/004 / Fabricatio Component 5: Improving Other (with fiel Pending I n,Painting & Installation of climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 14,433.97 0.00 mplement 1680mmx1300mm Mild St ntenance of irrigation and 1 5 9 07 n) ation eel gates with gear box (0 storm water infrastructure 4 Nos) for Hapowita amun a anicut at Matara Division , Galle CRESMPA-1/RP/WORKS/ID -MATR/DC/002 / Fabricatio Component 5: Improving Other (with fiel Pending I n,Painting & Installation of climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,009.60 0.00 mplement 1700mmx1320mm Mild St ntenance of irrigation and 1 5 9 07 n) ation eel gates with gear box (0 storm water infrastructure 1Nos) for Indurumulla anic ut at Matara Division, Gall e CRESMPA-1/RP/WORKS/ID -HAM/DC/006 / Repair regu lar gates in GR3,GR5,GR6, Component 5: Improving Other (with fiel Pending I GR8,GR9,GR10,GR11,GR1 climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 12,239.32 0.00 mplement 3,GR14,GR18 in RBMC and ntenance of irrigation and 1 5 9 07 n) ation Fabricating, painting and i storm water infrastructure nstalling 3 Nos of 1372mm x915mm mild steel regulat or gates in Kaludora (GR 8 ) in RBMC Lunugamweher aCRESMPA-1/RP/WORKS/ID Reservoir Component 5: Improving Other (with fiel Pending I -POL/DC/004 / Constrction climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,666.67 0.00 mplement of Spillway for Dambagaha ntenance of irrigation and 1 5 9 03 n) ation ulpatha Tank storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving -AMP/DC/004 / Estimate fo Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- r the Fabrication, sand bla IBRD / 89960 Post Direct Selection Direct - National d for explanatio 29,200.00 0.00 mplement ntenance of irrigation and 1 5 9 07 sting , painting & Installati n) ation storm water infrastructure on of Lower Paddmpitiya anicut gates in Sammanth ura Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -MON/DC/021 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 48,666.67 0.00 mplement nts to FC 03 canal & bund ntenance of irrigation and 1 5 9 03 n) ation road of RB main canal in H storm water infrastructure andapanagala Wewa CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -MON/DC/003 / Impoverme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 38,365.45 0.00 mplement nts to causeway at 8+620 ntenance of irrigation and 1 5 9 03 n) ation in in bund road in Muthuka storm water infrastructure ndiya Scheme CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/081 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,133.33 0.00 mplement n of 45m long retaining wa ntenance of irrigation and 1 5 9 07 n) ation ll at 0+550 in LB 2/D 2 mai storm water infrastructure n canal CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/010 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2023-10- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 48,440.00 0.00 mplement n of retaining wall at 10+ ntenance of irrigation and 1 5 9 03 n) ation 500 in D1 east canal storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -RAT/DC/084 / Repairing of climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,666.67 0.00 mplement Damme Ela anicut main g ntenance of irrigation and 1 5 9 07 n) ation ate storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/010 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,333.33 0.00 mplement nt to Aluth Ela( 5+700-11 ntenance of irrigation and 1 5 9 06 n) ation +000) storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KUR/DC/002 / Repairs of climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,338.26 0.00 mplement Magalla RB Sluice Gate Re ntenance of irrigation and 1 5 9 07 n) ation pair in Nikawaratiya Divisi storm water infrastructure on CRESMPA-1/RP/WORKS/ID Component 5: Improving -POL/DC/144 / 77 m long c Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-03- anal lining at 2+800 and C IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,423.33 0.00 mplement ntenance of irrigation and 1 5 9 07 onstruction of 22 m long r n) ation storm water infrastructure etaining wall at 1+940 in RB side in LB 3 off D1 east canal CRESMPA-1/RP/WORKS/ID Component 5: Improving -KUR/DC/004 / Repair, Fixi Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- ng Hoisting Mechanisms of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 18,046.64 0.00 mplement ntenance of irrigation and 1 5 9 07 06 Nos of vertical gates 16 n) ation storm water infrastructure 00Wx1830H in Madulla Ani cut in Katugampola Divisio n National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -GAL/RFQ/015 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 19,616.67 0.00 mplement ents to agricultural road fr ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation om Maliyagoda to Athumal storm water infrastructure ank-SPD) e (3+340 km to 4+090 km ) CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAL/DC/048 / Rehabilitati climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,666.67 0.00 mplement on of Mihirithanna pumpho ntenance of irrigation and 1 5 9 07 n) ation use storm water infrastructure CRESMPA-1/RP/WORKS/ID -KUR/DC/006 / Fabrication, Component 5: Improving Other (with fiel Pending I sand blasting, painting an climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,000.00 0.00 mplement d installation of gates with ntenance of irrigation and 1 5 9 07 n) ation hoisting mechanisms at Ba storm water infrastructure tuwaththa Regulators,in Hi riyala Division, Kurunegala CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -RAT/DC/005 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 10,333.33 0.00 mplement n of Over crossing at 7+60 ntenance of irrigation and 1 5 9 07 n) ation 0km in RB Main canal in K storm water infrastructure althota Scheme CRESMPA-1/RP/WORKS/ID -GAL/DC/002 / Fabrication, Component 5: Improving Other (with fiel Pending I Painting & Installation of 1 climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,873.78 0.00 mplement 220mmx1695mm Mild Ste ntenance of irrigation and 1 5 9 07 n) ation el gates (01Nos) for Domb storm water infrastructure agahawatha Anicut at Am balangoda Division,Galle CRESMPA-1/RP/WORKS/ID -GAL/DC/003 / Fabrication, Component 5: Improving Other (with fiel Pending I Painting & Installation of 1 climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,094.18 0.00 mplement 340mmx2075mm Stainles ntenance of irrigation and 1 5 9 07 n) ation s Steel gates with Gear Bo storm water infrastructure x (02Nos) for Midigamu el a anicut at Ambalangoda Division, Galle CRESMPA-1/RP/WORKS/ID -HAM/DC/001 / Fabrication Component 5: Improving Other (with fiel Pending I , sandblasting,painting an climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 12,882.24 0.00 mplement d installation 04Nos of 160 ntenance of irrigation and 1 5 9 07 n) ation 0mmx1524mm mild steel storm water infrastructure gates in Kahagaha amuna Anicut, Kongalara CRESMPA-1/RP/WORKS/ID -HAM/DC/002 / Fabrication Component 5: Improving Other (with fiel Pending I , sandblasting,painting an climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 7,309.52 0.00 mplement d installation 03Nos of 147 ntenance of irrigation and 1 5 9 07 n) ation 4mmx1397mm mild steel storm water infrastructure regulator gates in Heelage deniya amuna Anicut, Kon gal ara CRESMPA-1/RP/WORKS/ID Component 5: Improving -HAM/DC/005 / Fabrication Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- , painting and installation IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,540.93 0.00 mplement ntenance of irrigation and 1 5 9 07 02Nos of gates in Liyangas n) ation storm water infrastructure tota and 01 No of gate in a barana alla in RBMC Liyan gastota CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/001 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 33,000.00 0.00 mplement nts to gates and hosting s ntenance of irrigation and 1 5 9 07 n) ation ystem of Anganmedilla ani storm water infrastructure cut in Polonnaruwa CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAL/DC/046 / Rehabilitati climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,666.67 0.00 mplement on of 3 aniut and construct ntenance of irrigation and 1 5 9 07 n) ation ion of new anicut and desil storm water infrastructure ting Wagonneyaya canala CRESMPA-1/RP/WORKS/ID National Procur -GAL/DC/001 / Fabrication, Component 5: Improving ement Docume Pending I Painting & Installation of 1 climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National nt - 1 Envelope 30,331.39 0.00 mplement 700mmx1960mm Stainles ntenance of irrigation and 1 5 9 07 process (Non B ation s Steel gates with Gear Bo storm water infrastructure ank-SPD) x (04 Nos) for Obadawatha anicut at Ambalangoda Di vision, Galle CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/012 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-04- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,000.00 0.00 mplement nts to Haliyapitiya ela (0+ ntenance of irrigation and 1 5 9 06 n) ation 000 to 4+000) in Bolgoda storm water infrastructure scheme CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/030 / Gravelling o climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,843.33 0.00 mplement f Agri road at RB17 from 4 ntenance of irrigation and 1 5 9 07 n) ation +110 to 5+410 in weerap storm water infrastructure ura DCO CRESMPA-1/RP/WORKS/ID -KAL/DC/002 / Fabrication , Component 5: Improving Other (with fiel Pending I sandblasting , painting & i climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 38,100.00 0.00 mplement nstallation of gates with lif ntenance of irrigation and 1 5 9 07 n) ation ting machanism and embe storm water infrastructure dded parts at Danwatte , C olombo Division CRESMPA-1/RP/WORKS/ID -HAM/DC/003 / Fabrication Component 5: Improving Other (with fiel Pending I , sandblasting,painting an climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,327.87 0.00 mplement d installation 02Nos of 149 ntenance of irrigation and 1 5 9 07 n) ation 9mmx1753mm mild steel storm water infrastructure regulator gates in Liyanag edeniya amuna Anicut, Kir ama ara CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -BAD/DC/075 / Fabrication climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,610.00 0.00 mplement and Installation 03Nos of R ntenance of irrigation and 1 5 9 08 n) ation egulator Gate at Dambara storm water infrastructure wa Main Canal CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -RAT/DC/085 / Repairing of climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,000.00 0.00 mplement Batugedara Main Anicut g ntenance of irrigation and 1 5 9 07 n) ation ate storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAL/DC/013 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-07- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 28,930.00 0.00 mplement nts to Hiyare reservoir in H ntenance of irrigation and 1 5 9 05 n) ation oluwagoda scheme storm water infrastructure Page 5 CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAL/DC/014 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 75,263.33 0.00 mplement n Olanda anicut at stn 0+0 ntenance of irrigation and 1 5 9 03 n) ation 25 km in Olanda channel storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving -KUR/DC/003 / Repairs, sa Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- nd blasting,Painting and in IBRD / 89960 Post Direct Selection Direct - National d for explanatio 8,518.36 0.00 mplement ntenance of irrigation and 1 5 9 07 stallation of 08 Nos of verti n) ation storm water infrastructure cal gates 1500Wx1650H in Nikapitiya Anicut in Katug ampola Division CRESMPA-1/RP/WORKS/ID -KUR/DC/005 / Supply and Component 5: Improving Other (with fiel Pending I installation of Sluice Gate ( climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,332.43 0.00 mplement CI gate 600 mm) and repla ntenance of irrigation and 1 5 9 07 n) ation cing hoisting mechanism i storm water infrastructure n Kirithalana Sluice in Katu gampola Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/019 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplement nts to flood controlling gat ntenance of irrigation and 1 5 9 06 n) ation e at Kalugoda flood bund ( storm water infrastructure 1nos) gate number 2. National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KAL/RFQ/026 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement on of Agricultural road (Fro ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation m walpita cemetry to Pabo storm water infrastructure ank-SPD) la) CRESMPA-1/RP/WORKS/ID -GAL/DC/004 / Fabrication, Component 5: Improving Other (with fiel Pending I Painting & Installation of 1 climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,577.72 0.00 mplement 650mmx1200mm Mild Ste ntenance of irrigation and 1 5 9 07 n) ation el gates with Gear Box (02 storm water infrastructure Nos) for Ala ihalayaya anic ut at Gingaga Division, Gal le CRESMPA-1/RP/WORKS/ID Component 5: Improving -MATL/DC/001 / Fabricatio Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- n & Installation 06 Nos of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,199.99 0.00 mplement ntenance of irrigation and 5 0 4 22 hoisting mechanism ,Spind n) ation storm water infrastructure le with lifting lever at Dam buluoya Anicut CRESMPA-1/RP/WORKS/ID -MATL/DC/002 / Fabricatio Component 5: Improving Other (with fiel Pending I n & Installation of 02 Nos climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,769.99 0.00 mplement of gates (900mm 1050mm ntenance of irrigation and 1 5 9 07 n) ation & 1600mmx1000mm with storm water infrastructure Hoisting Mechanism (45m mx200mm) Bowatenne Ca nel CRESMPA-1/RP/WORKS/ID -KUR/DC/007 / Supply & In Component 5: Improving Other (with fiel Pending I stallation of Cast Iron gate climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,981.75 0.00 mplement s with hoisting mechanism ntenance of irrigation and 1 5 9 07 n) ation (12 Nos,230mm) at Usgala storm water infrastructure Scheme in Galgamuwa Div ision,Kurunegala CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -BAD/DC/074 / Improment climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,533.33 0.00 mplement s to LB,RB and UT gate,Di ntenance of irrigation and 1 5 9 08 n) ation yabana oya, Bandarawela storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/073 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 10,566.67 0.00 mplement nts to FC3/RB17 canal in B ntenance of irrigation and 1 5 9 07 n) ation auddharthagama DCO are storm water infrastructure a CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -NUE/DC/003 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 37,056.67 0.00 mplement nt to main canal from 3+0 ntenance of irrigation and 1 5 9 03 n) ation 00km to 3+800km in Bola storm water infrastructure gandawala scheme. National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -NUE/DC/001 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National nt - 1 Envelope 16,786.67 0.00 mplement nts to main canal from 1+ ntenance of irrigation and 1 5 9 06 process (Non B ation 500 km to 3+000 in Ma el storm water infrastructure ank-SPD) a scheme CRESMPA-1/RP/WORKS/ID -POL/DC/003 / Fabricating Component 5: Improving Other (with fiel Pending I and Installing 03 No of 12 climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,700.00 0.00 mplement 50mmx1200mm anicut ga ntenance of irrigation and 1 5 9 07 n) ation tes with hoisting mechanis storm water infrastructure m of LLMC 0+000 Regulat or gates in Kaudulla Divisi on CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/093 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-05- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,926.67 0.00 mplement n of 152m long Retaining ntenance of irrigation and 1 5 9 06 n) ation wall at 0+550 in LB side in storm water infrastructure RB12 off D1 east canal. CRESMPA-1/RP/WORKS/ID -ANU/DC/003 / Fabrication Component 5: Improving and Installation of 09 Nos Other (with fiel Under Imp climate resilience and mai 2023-07-3 2023-06-0 2023-08-0 2023-06-0 2023-09-0 2024-03- stainless steel gates (1480 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 54,914.49 0.00 lementati ntenance of irrigation and 1 2 5 6 9 07 *1520mm) Hoisting mecha n) on storm water infrastructure nisms, guide grooves and hand rail of Mora Oya Anic ut in Padaviya Division, An uradhapura CRESMPA-1/RP/WORKS/ID -GAL/DC/005 / Fabrication, Component 5: Improving Other (with fiel Pending I Painting & Installation of 1 climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 7,544.65 0.00 mplement 700mmx1600mm Mild Ste ntenance of irrigation and 1 5 9 07 n) ation el gates with Gear Box (02 storm water infrastructure Nos) for Wathurawayaya a nicut at Gingaga Division, Galle CRESMPA-1/RP/WORKS/ID -MATR/DC/005 / Fabricatio n,Painting & Installation of Component 5: Improving 11700mmx1400mm Mild S Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- teel gates with gear box (0 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 17,354.39 0.00 mplement ntenance of irrigation and 1 5 9 07 1 Nos) for OPI/19 anicut, 1 n) ation storm water infrastructure 655mmx2240mm Mild ste el Gates with gear box (01 Nos) for OPI/26 anicut, 167 0mmx1980mm steel gates with ger box (01 Nos) OPI/ CRESMPA-1/RP/WORKS/ID 27 anicut, 1170mmx Component 5: Improving Other (with fiel Pending I -KAL/DC/008 / Fabrication climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,333.33 0.00 mplement of Damaged Gates at 0+8 ntenance of irrigation and 1 5 9 08 n) ation 00 at RB Low Level Canal storm water infrastructure CRESMPA-1/RP/WORKS/ID -AMP/DC/001 / Estimate fo Component 5: Improving Other (with fiel Pending I r repairs, sand blasting & climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,666.67 0.00 mplement painting 2 Nos of LB main ntenance of irrigation and 1 5 9 07 n) ation cannel radial gates at Sen storm water infrastructure anayaka Samudraya trifur cation in Ampara Division CRESMPA-1/RP/WORKS/ID -AMP/DC/005 / Estimate fo Component 5: Improving Other (with fiel Pending I r Fabrication, sand blastin climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 49,800.00 0.00 mplement g & painting & Installation ntenance of irrigation and 1 5 9 07 n) ation 12 Nos of regulator gates f storm water infrastructure or Panayadi,Sembukulam and Mudalaikkal in Akkara pattu Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/006 / Clearing & d climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-04- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,000.00 0.00 mplement esilting of Dummalamodar ntenance of irrigation and 1 5 9 06 n) ation a Ela - (1+600 to 5+000) storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/141 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-06- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,050.00 0.00 mplement nts to FC 01 canal in D3 So ntenance of irrigation and 1 5 9 05 n) ation uth canal in D3 unit storm water infrastructure CRESMPA-1/RP/WORKS/ID -MATR/DC/006 / Supply an Component 5: Improving Other (with fiel Pending I d Installation of gear moto climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,288.22 0.00 mplement rs, worm & Wheel gear bo ntenance of irrigation and 1 5 9 07 n) ation xes and Electrical wiring of storm water infrastructure gravity gates in Magallago da pump house, Matara Di vision, Galle CRESMPA-1/RP/WORKS/ID Component 5: Improving -AMP/DC/003 / Estimate fo Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- r the Fabrication, sand bla IBRD / 89960 Post Direct Selection Direct - National d for explanatio 33,133.33 0.00 mplement ntenance of irrigation and 1 5 9 07 sting & painting & Installat n) ation storm water infrastructure ion of Rottai pickup anicut & repair other gates in Pot uvil Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAL/DC/059 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,000.00 0.00 mplement n of Kirinuge canal and im ntenance of irrigation and 1 5 9 07 n) ation provement of canal banks storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/014 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-06- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 43,820.00 0.00 mplement nts to RB3 canal off D1 nor ntenance of irrigation and 1 5 9 05 n) ation th canal in Laxauyana DC storm water infrastructure O area CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -HAM/DC/007 / Repair regu climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,017.11 0.00 mplement lar gates in GR08 and GR ntenance of irrigation and 1 5 9 07 n) ation 09 in LBMC Lunugamwehe storm water infrastructure ra Reservoir CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -RAT/DC/086 / Repairing of climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,666.67 0.00 mplement turnout gates in Ambagah ntenance of irrigation and 1 5 9 07 n) ation awela Ela in Panamura sch storm water infrastructure eme CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -MATL/DC/003 / Fabricatio climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,156.40 0.00 mplement n, Painting & Installation of ntenance of irrigation and 5 0 4 22 n) ation 02 Nos of Gate Radagalpot storm water infrastructure ha Anicut (1330mmx750m m) CRESMPA-1/RP/WORKS/ID -MATL/DC/004 / Fabricatio Component 5: Improving Other (with fiel Pending I n & Installation of 14 Nos climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,642.11 0.00 mplement of Gates with Locking Mec ntenance of irrigation and 1 5 9 07 n) ation hanism Athirahapitiya Can storm water infrastructure nel 7 Nos of Gates (600m mx300mm) & 07 Nos of G ates (400mmx300mm) CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/020 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplement nts to flood controlling gat ntenance of irrigation and 1 5 9 06 n) ation e at Kalugoda flood bund ( storm water infrastructure 1nos) gate number 3. CRESMPA-1/RP/WORKS/ID Component 5: Improving -GAL/DC/045 / Constructio Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2023-12- n of Bogawelayaya canal, i IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,333.33 0.00 mplement ntenance of irrigation and 1 5 9 08 mprovement of canal bank n) ation storm water infrastructure s and connecting to Lenag ala main canal CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAL/DC/056 / Rehabilitati climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,000.00 0.00 mplement on of Thudugala canal (Hik ntenance of irrigation and 1 5 9 07 n) ation aduwa, Nakanda, Wellawa storm water infrastructure tta vaulgoda, nalagasdeni ya) CRESMPA-1/RP/WORKS/ID -KAL/DC/003 / Fabrication , Component 5: Improving sandblasting , painting & i Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- nstallation of mild steel ve IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,833.33 0.00 mplement ntenance of irrigation and 1 5 9 07 rtical gate with lifting mac n) ation storm water infrastructure hanism and embedded par ts at Kolamediriya anicut a t Balgoda Scheme in Kalut hara Division CRESMPA-1/RP/WORKS/ID -MATL/DC/005 / Supply & I nstallation of 50 Nos of 12 Component 5: Improving 5mm cast iron FTO Gates Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- with Hoisting Mechanism a IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,196.57 0.00 mplement ntenance of irrigation and 1 5 9 07 nd Fabrication and Installa n) ation storm water infrastructure tion 02 Nos of Gates (950x 1280 mm) with steel grove s, columns,beams and Hoi sting Mechanism (45mmx 2000mm at Dewahuwa Ma CRESMPA-1/RP/WORKS/ID in Cannel Component 5: Improving Other (with fiel Pending I -BAD/DC/073 / Improment climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,666.67 0.00 mplement s to gates at Tract 6,D2 of ntenance of irrigation and 1 5 9 08 n) ation Nagadeepa scheme Banda storm water infrastructure rawela CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/054 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-06- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 24,790.00 0.00 mplement n of 36m long Retaining w ntenance of irrigation and 1 5 9 05 n) ation all at 0+500 of RB 1 off D storm water infrastructure 2 canal in Weerapedesa D CO area Page 6 CRESMPA-1/RP/WORKS/ID -MON/DC/001 / Fabrication and Installation of 02 Nos Component 5: Improving Other (with fiel Pending I of 3.5ft *3.0ft Sluice gates, climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 23,746.50 0.00 mplement 01 Nos of 3.3ft*5.5ft Regul ntenance of irrigation and 1 5 9 07 n) ation ator gates, 01Nos of 4.8ft* storm water infrastructure 5.5ft Regulator gates and 02 Nos of 5.5ft*6.7ft Regul ator gates in Wilaoya Anic ut in Monaragala Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -POL/DC/146 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-06- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 23,686.67 0.00 mplement nts to FC 3 canal under Pul ntenance of irrigation and 1 5 9 05 n) ation asthigama DCO area storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/001 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,766.67 0.00 mplement nts to Panape ela anicut , ntenance of irrigation and 1 5 9 07 n) ation Kaluthara Division, Colomb storm water infrastructure o CRESMPA-1/RP/WORKS/ID -ANU/DC/002 / Estimate fo Component 5: Improving Other (with fiel Pending I r fabrication and installatio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 17,645.02 0.00 mplement n of 08Nos of Regulator ga ntenance of irrigation and 1 5 9 07 n) ation tes of Low level main cana storm water infrastructure l in Nachchaduwa Division, Anuradhapura CRESMPA-1/RP/WORKS/ID -AMP/DC/006 / Estimate fo Component 5: Improving Other (with fiel Pending I r the Fabrication, sand bla climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 49,500.00 0.00 mplement sting , painting & Installati ntenance of irrigation and 1 5 9 07 n) ation on of gates for Udangavell storm water infrastructure y anicut in Moravil 2 unit i n Sammanthura Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/018 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplement nts to flood controlling gat ntenance of irrigation and 1 5 9 06 n) ation e at Kalugoda flood bund ( storm water infrastructure 1nos) gate number 1. CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/009 / Improveme climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,333.33 0.00 mplement nts to Aluth Ela( 0+000-5+ ntenance of irrigation and 1 5 9 06 n) ation 700) storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KAL/RFQ/023 / Construtio climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 34,333.33 0.00 mplement n of retainning wall in Iluk ntenance of irrigation and tations e Envelope 5 0 25 process (Non B ation patha main road damage storm water infrastructure ank-SPD) part near Dewalaya CRESMPA-1/RP/WORKS/ID -KUR/DC/001 / Fabrication, Component 5: Improving Other (with fiel Pending I sand blasting, painting an climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 23,789.58 0.00 mplement d installation of 05 Nos of ntenance of irrigation and 1 5 9 07 n) ation Vertical gates 1550Wx125 storm water infrastructure 0H for Walpaluwa Wewa a nd Panda Wewa in Wariya pola Division . CRESMPA-1/RP/WORKS/ID -HAM/DC/004 / Fabrication Component 5: Improving Other (with fiel Pending I , sandblasting,painting an climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,192.51 0.00 mplement d installation 02Nos of 152 ntenance of irrigation and 1 5 9 07 n) ation 4mmx1820mm mild steel storm water infrastructure gates LBMC Ridiyagama R eservoir in Koggalu ara CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -AMP/DC/034 / Deepening climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,666.67 0.00 mplement and widening of Rambaka ntenance of irrigation and 1 5 9 07 n) ation noya spill tail canal from 6 storm water infrastructure +000 to 8+000 CRESMPA-1/RP/WORKS/ID Component 5: Improving -BAD/DC/077 / Fabricating Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- spill gates and reparing tu IBRD / 89960 Post Direct Selection Direct - National d for explanatio 7,000.00 0.00 mplement ntenance of irrigation and 1 5 9 07 rnout gates in Baduluoya n) ation storm water infrastructure anicut scheme,kandaketiy a Division,Bandarawela CRESMPA-1/RP/WORKS/ID Component 5: Improving -BAD/DC/076 / Fabricating Other (with fiel Pending I climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-01- spill gates and reparing tu IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,666.67 0.00 mplement ntenance of irrigation and 1 5 9 07 rnout gates in Bathmedilla n) ation storm water infrastructure anicut scheme,kandaketiy a Division,Bandarawela CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAD/DC/008 / Constructio climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,533.33 0.00 mplement n of 50m long canal lining ntenance of irrigation and 1 5 9 07 n) ation at 0+000 in feeder canal i storm water infrastructure n Rathnaella National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -POL/RFQ/071 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 34,833.00 0.00 mplement ion of LB11/D28/LBMC in M ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation inneriya Division storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAT/RFQ/008 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ents to Navatkadu Branch ntenance of irrigation and tations e Envelope 0 5 12 process (Non B ation Channel in Unnichchai Sch storm water infrastructure ank-SPD) eme,Rugam Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAT/RFQ/012 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 40,000.00 0.00 mplement ents to Pandarakkadu sma ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation ll bridge cum regulator in storm water infrastructure ank-SPD) Rugam Scheme,Rugam Di vision CRESMPA-1/RP/WORKS/ID National Procur -BAT/RFQ/017 / Reconstruc Component 5: Improving ement Docume Pending I tion of Causeway at Puliya climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 34,666.67 0.00 mplement di across unit 38 & 39 unit ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation 40 connecting Road at Stn storm water infrastructure ank-SPD) 0 + 865 in Navakari Sche me,Navakari Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -BAT/NCB/016 / Improvem climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 98,000.00 0.00 lementati ents to Vaikaladichenai ani ntenance of irrigation and e Envelope 5 1 0 1 1 5 29 process (Non B on cut in Unnichchai Scheme, storm water infrastructure ank-SPD) Rugam Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -BAT/NCB/009 / Improvem climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-08- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 53,666.67 0.00 lementati ents to Peelimadu Bridge c ntenance of irrigation and e Envelope 5 1 0 1 1 5 31 process (Non B on um regulator in Vahanery storm water infrastructure ank-SPD) Scheme, Rugam Division CRESMPA-1/RP/WORKS/ID National Procur -TRI/RFQ/005 / Improveme Component 5: Improving ement Docume nts to Peenganudaichan Ar climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 34,533.33 0.00 Canceled u Drainange canal from se ntenance of irrigation and tations e Envelope 0 5 09 process (Non B ew bridge to Vanniunamad storm water infrastructure ank-SPD) u Gated Regulator from St n 0+000 to Stn 1+120 in K anthale CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -BAT/NCB/014 / Improvem ement Docume Under Imp climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-08- ents to LB Main Channel b IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 55,000.00 0.00 lementati ntenance of irrigation and e Envelope 5 1 0 1 1 5 31 und access road at Stn.0 process (Non B on storm water infrastructure + 336 in Wadamunai Sche ank-SPD) me in Rugam Division, Bati caloa National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -BAT/NCB/013 / Reconstru climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-08- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 57,333.33 0.00 lementati ction of Road in LB - 44A C ntenance of irrigation and e Envelope 5 1 0 1 1 5 31 process (Non B on hannel,Navakari Scheme,N storm water infrastructure ank-SPD) avakari Division CRESMPA-1/RP/WORKS/ID Component 5: Improving -BAT/DC/001 / Supplying a Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- nd installing steel gate wit IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,333.33 0.00 mplement ntenance of irrigation and 5 0 4 22 h component to sembiyadi n) ation storm water infrastructure anicut in Vahanery schem e Rugam Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -BAT/DC/002 / Replacing of climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,333.33 0.00 mplement 06 Nos of gates in Wattaw ntenance of irrigation and 5 0 4 22 n) ation ala anicut in Navakiri Divis storm water infrastructure ion CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -BAT/DC/003 / Replacing of climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,633.33 0.00 mplement 10 Nos of gates in Navakiri ntenance of irrigation and 5 0 4 22 n) ation anicut in Navakiri Division storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAD/DC/001 / Fabrication, climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,250.39 0.00 mplement painting & Installation tra ntenance of irrigation and 5 0 4 23 n) ation shrack for Gurugaloya 130 storm water infrastructure 0mm 2400mm CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAD/DC/002 / Fabrication climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,043.26 0.00 mplement & Installation of 1 nos of 1 ntenance of irrigation and 5 0 4 23 n) ation 050x750mm Gate at Gam storm water infrastructure pola wela anicut in Kandy CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAD/DC/003 / Fabrication climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,962.03 0.00 mplement & Installation of 03 nos Hoi ntenance of irrigation and 5 0 4 23 n) ation sting Mechanisms for Ulap storm water infrastructure ane Anicut National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KAD/RFQ/004 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement ents to FC 26 at Murapola ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation ela scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/006 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 27,766.67 0.00 mplement nts to D4 canal from Stn 0 ntenance of irrigation and tations e Envelope 0 5 10 process (Non B ation +000 to Stn 1+000 in Ven storm water infrastructure ank-SPD) drasan Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KAD/RFQ/009 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 22,133.33 0.00 mplement ents to D17 canal in stage ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation ii storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -TRI/RFQ/007 / Improveme ement Docume climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- nts to Kattaparichchan Dra IBRD / 89960 Post Limited nt - 1 Envelope 42,900.00 0.00 Canceled ntenance of irrigation and tations e Envelope 0 5 09 inange Canal from stn 2+2 process (Non B storm water infrastructure 00 to Stn 3+200 in Muthur ank-SPD) Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/008 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 22,866.67 0.00 mplement nts to D7 Drainange Chan ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation nel/LBMC from Stn 0+000 storm water infrastructure ank-SPD) to Stn 4+130 in Muthur Di vision CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -GAM/NCB/001 / Constructi ement Docume Pending I climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-11- on of over-crossing across IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 57,333.33 0.00 mplement ntenance of irrigation and e Envelope 5 0 1 1 5 29 Horakndavila drainage can process (Non B ation storm water infrastructure al in Bemmulla Deranagod ank-SPD) a Irrigation scheme National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-05- -KAD/RFQ/013 / Rehabilitat IBRD / 89960 Post Limited nt - 1 Envelope 18,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 12 ion of Araththana Uda Ela process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/011 / Gravelling climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 22,000.00 0.00 mplement Mollipothana LBMC Bund R ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation oad from Stn 3+900 to Stn storm water infrastructure ank-SPD) 6+650 in Kanthale CRESMPA-1/RP/WORKS/ID -GAM/NCB/009 / Widening National Procur the left bank main canal of Component 5: Improving ement Docume Pending I Deealioya Mavita Anicut fr climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 53,000.00 0.00 mplement om 0+000 to 0+400 and l ntenance of irrigation and e Envelope 5 0 1 1 5 29 process (Non B ation aying gravel from )0+000 storm water infrastructure ank-SPD) to )+4000 and constructin g a concrete lining to prev ent erosion from 0+400 to 0+410 of the Mawita main National Procur CRESMPA-1/RP/WORKS/ID canal. Component 5: Improving ement Docume Under Imp -TRI/NCB/012 / Constructio climate resilience and mai Single Stage - On 2023-08-1 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 77,100.00 0.00 lementati n of D2 Bund Road at DC2/ ntenance of irrigation and e Envelope 5 5 0 1 1 5 29 process (Non B on BR3/RBMC from Stn 1+00 storm water infrastructure ank-SPD) 0 to Stn 3+625 in Mutur Di vision National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/013 / Constructio climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 27,666.67 0.00 mplement n of retaining walls at Stn ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation 4+800 in LBMC Mutur Divi storm water infrastructure ank-SPD) sion National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/014 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 26,000.00 0.00 mplement nts of LB2/D10 Canal from ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation stn 0+000 to stn 1+100 in storm water infrastructure ank-SPD) Morawewa Scheme Page 7 CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAM/DC/002 / Improveme climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,666.67 0.00 mplement nt to flood protection struc ntenance of irrigation and 5 0 4 23 n) ation ture Jaela Heen Ela storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving -GAM/DC/010 / Paving of g Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- ranite and boulders for the IBRD / 89960 Post Direct Selection Direct - National d for explanatio 12,500.00 0.00 mplement ntenance of irrigation and 5 0 4 22 damged sections of the rig n) ation storm water infrastructure ht bank canal of the Paluo ya Anicut in the Moranna s cheme CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAM/DC/012 / Installation climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 500.00 0.00 mplement of wooden stop logs for Mo ntenance of irrigation and 5 0 4 23 n) ation ranna Anicut storm water infrastructure CRESMPA-1/RP/WORKS/ID Component 5: Improving -GAM/DC/015 / Paving of g Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-02- ranite from 490 m to 580 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,000.00 0.00 mplement ntenance of irrigation and 5 0 4 21 m in the eroded section of n) ation storm water infrastructure left ban of Attanagalooya i n Kotawala scheme CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAM/DC/016 / Paving of g climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-05- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,000.00 0.00 mplement ranite at 0+400 on left ba ntenance of irrigation and 5 0 4 21 n) ation nk of Keenagaspillaiwa Ani storm water infrastructure cut CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAM/DC/018 / Paving of g climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplement ranite for 75 m length at 6 ntenance of irrigation and 5 0 4 21 n) ation 00 m in the downstream s storm water infrastructure ection of the Doranagoda Anicut National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KUR/RFQ/014 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 19,499.33 0.00 mplement ents of D19 canal in Doluk ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation anda canal in Bathalagoda storm water infrastructure ank-SPD) Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KUR/RFQ/017 / Contsructi climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 31,506.67 0.00 mplement on of Under crossing struct ntenance of irrigation and tations e Envelope 0 5 10 process (Non B ation ure at 16+246 Km in LBM storm water infrastructure ank-SPD) C in Deduruoya scheme. CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -KUR/RFQ/019 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-05- ents canal bund from 12+ IBRD / 89960 Post Limited nt - 1 Envelope 20,423.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 12 240 km to 12+465 km & c process (Non B ation storm water infrastructure onstruction of under crossi ank-SPD) ng structure at 12+561 in LBMC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KUR/RFQ/023 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 27,814.33 0.00 mplement on of half round pipe cana ntenance of irrigation and tations e Envelope 0 5 10 process (Non B ation l in Barawa eba from 0+8 storm water infrastructure ank-SPD) 50 to 1+055 CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KUR/DC/021 / constructio climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 19,723.33 0.00 mplement n of Kiniyama Sluice & im ntenance of irrigation and 5 0 4 22 n) ation provements of main canal storm water infrastructure in Kiniyama scheme. National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KUR/RFQ/029 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 29,146.67 0.00 mplement ents to FC18 of LBMC in M ntenance of irrigation and tations e Envelope 0 5 10 process (Non B ation agalla scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KUR/NCB/032 / Improvem climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 61,020.00 0.00 mplement ents to D2 canal & constru ntenance of irrigation and e Envelope 5 0 1 1 5 29 process (Non B ation ction of retaining wall at 1 storm water infrastructure ank-SPD) 4+600 in Dolukanda main canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KAL/RFQ/015 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 mplement ents to Kahaunage Ela MF ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation P bund (0+000 - 0+930) k storm water infrastructure ank-SPD) m and Structure CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -COL/DC/001 / Fabrication, climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 66,666.67 0.00 mplement Sandblasting, Painting & In ntenance of irrigation and 5 0 4 22 n) ation stallation of gates with lifti storm water infrastructure ng mechanism at Weniwel kola CRESMPA-1/RP/WORKS/ID -COL/DC/002 / Supply and Component 5: Improving Other (with fiel Pending I install new flood control ga climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 10,000.00 0.00 mplement te (H = 1525mm x B=137 ntenance of irrigation and 5 0 4 22 n) ation 0mm) with SS embbeded storm water infrastructure parts and hoisting (Tunnel Radius = 2') Ranwala Muth thettupola MF CRESMPA-1/RP/WORKS/ID Component 5: Improving -COL/DC/003 / Fabrication, Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- Sandblasting, Painting & In IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,666.67 0.00 mplement ntenance of irrigation and 5 0 4 22 stallation of gates with lifti n) ation storm water infrastructure ng mechanism and replac e gear box at Thalangama CRESMPA-1/RP/WORKS/ID -COL/DC/004 / Fabrication, Component 5: Improving sandblasting, painting and Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- installation of 01 no of 140 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 12,433.33 0.00 mplement ntenance of irrigation and 5 0 4 22 0 Wx2250H mild steel vert n) ation storm water infrastructure ical gate with lifting mech nism and embodeded part s and hoisting at Lanarol M awatha National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -COL/RFQ/008 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 18,750.00 0.00 mplement on of retaining wall near P ntenance of irrigation and tations e Envelope 0 5 12 process (Non B ation allekumbura Anicut storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -COL/NCB/016 / Improvem climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 62,500.00 0.00 mplement ents to Kelani River LB 24 ntenance of irrigation and e Envelope 5 0 1 1 5 29 process (Non B ation +000 to 25+320 km in Wa storm water infrastructure ank-SPD) ikkiwatte GS Division. National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -COL/NCB/017 / Constructi climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-03- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 87,500.00 0.00 mplement on of drain near Bogahawa ntenance of irrigation and e Envelope 5 0 1 1 5 04 process (Non B ation tta road and Shantha Anth storm water infrastructure ank-SPD) oni road at Weliwita National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -COL/RFQ/021 / Additional climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-01- IBRD / 89960 Post Limited nt - 1 Envelope 37,500.00 0.00 mplement estimate at Weniwelkola n ntenance of irrigation and tations e Envelope 0 5 13 process (Non B ation ew anicut storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -COL/RFQ/071 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement ents to Muneta Bokkuwa i ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation n Bodhiyawatta canal storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -COL/NCB/024 / Balancae climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 93,750.00 0.00 mplement work of Boralesgamuwa ta ntenance of irrigation and e Envelope 5 0 1 1 5 29 process (Non B ation nk U/S area Improvement storm water infrastructure ank-SPD) Project - Stage (IV) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/004 / Reconstruc climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-02- IBRD / 89960 Post Limited nt - 1 Envelope 6,666.67 0.00 mplement tion of damaged pier of tro ntenance of irrigation and tations e Envelope 0 5 12 process (Non B ation ugh structure in DI canal o storm water infrastructure ank-SPD) f Radavi Bendi ela Scheme CRESMPA-1/RP/WORKS/ID -PUT/RFQ/005 / 100m Con National Procur Component 5: Improving crete retaining wall from 4 ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- +232 to 4 + 332 and cons IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 11 truction of Drainage under process (Non B ation storm water infrastructure crossing structure at 4+45 ank-SPD) 0 in dowunstream of sypo n structure in RB main can al in Tabbowa Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/006 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement ents to BC2 from 1 + 270k ntenance of irrigation and tations e Envelope 0 5 12 process (Non B ation m to 1 + 410km in Mahau storm water infrastructure ank-SPD) swewa Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/009 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement ents to Karawita spill in ka ntenance of irrigation and tations e Envelope 0 5 12 process (Non B ation rawita Scheme storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -PUT/RFQ/010 / Canal linin ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-04- g from 2+234km to 2+374 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 12 km of main canal in paddy process (Non B ation storm water infrastructure lands for resettled people i ank-SPD) n Nelumgama 2nd village CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MAN/RFQ/009 / Flood dam ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- age reparing and improve IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 11 menst to Kooramattai feed process (Non B ation storm water infrastructure er tanks Headwork under ank-SPD) Viyadikulam Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/NCB/013 / Improvem climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-08- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 53,333.33 0.00 mplement ent to kuda wewa Kadupiti ntenance of irrigation and e Envelope 5 0 1 1 5 31 process (Non B ation ya oya canal spill storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MAN/RFQ/011 / Reconstru ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- ction of box culvert & Impr IBRD / 89960 Post Limited nt - 1 Envelope 40,000.00 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 09 ovements to Peruveli spill process (Non B ation storm water infrastructure tail canal and agricultural r ank-SPD) oad under 12th mile sluice of GT Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MAN/RFQ/014 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ents to Periyaudaippu mai ntenance of irrigation and tations e Envelope 0 5 09 process (Non B ation n canal under Periyaudaip storm water infrastructure ank-SPD) pu sluice of GT Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MAN/RFQ/015 / Reparing climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 40,000.00 0.00 mplement and improvements to Illan ntenance of irrigation and tations e Envelope 0 5 09 process (Non B ation dakulam feeder tank in Ak storm water infrastructure ank-SPD) athimurippu Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MAN/RFQ/017 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement ents to Vanchiyankulam S ntenance of irrigation and tations e Envelope 0 5 12 process (Non B ation pill tail canal under 11th m storm water infrastructure ank-SPD) ile sluice of GT Scheme CRESMPA-1/RP/WORKS/ID National Procur -MAN/RFQ/019 / Reconstru Component 5: Improving ement Docume Pending I ction of Turnout Structures climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 mplement for Achankulam and Perive ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation li feeder tanks with road c storm water infrastructure ank-SPD) rossing under 12th Mile slu ice of Giants Tank National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MAN/RFQ/021 / Reparing climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement and Improvements to Aala ntenance of irrigation and tations e Envelope 0 5 09 process (Non B ation nkulam feeder canal under storm water infrastructure ank-SPD) Akathimurippu Scheme CRESMPA-1/RP/WORKS/ID National Procur -MAN/RFQ/025 / Reconstru Component 5: Improving ement Docume Pending I ction of Trifurcation struct climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ure along Muthalaikuththu ntenance of irrigation and tations e Envelope 0 5 09 process (Non B ation - Uyilankulam drainage pa storm water infrastructure ank-SPD) th under Adaikkalamoddai Sluice of GT Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -PUT/NCB/014 / Supply, fa climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-08- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 46,666.67 0.00 Canceled bricating, fixing, liftining g ntenance of irrigation and e Envelope 5 0 1 1 5 31 process (Non B ate to the Thinipitiya anicu storm water infrastructure ank-SPD) t National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -PUT/NCB/015 / Constructi climate resilience and mai Single Stage - On 2023-08-1 2023-08-2 2023-10-0 2023-10-3 2023-12-0 2024-08- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 40,000.00 0.00 Canceled on of gabion wall bank pro ntenance of irrigation and e Envelope 5 0 1 1 5 31 process (Non B tection to Buttaulu oya storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MAN/RFQ/028 / Improvem ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- ents and formation of Ned IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 09 uvarampu feeder tank bun process (Non B ation storm water infrastructure d & spill tail canal under P ank-SPD) eriyaudauppu sluice of GT Scheme Page 8 CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -PUT/RFQ/016 / Removing ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- of damaged trough structu IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 11 re and construction of new process (Non B ation storm water infrastructure one @ 1st km in LBMC in K ank-SPD) ottukachchiya Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MAN/RFQ/032 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ents to LB Main Canal und ntenance of irrigation and tations e Envelope 0 5 09 process (Non B ation er Viyadikulam tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/017 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 mplement ents to D - 2 canal in Maha ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation Andarawawewa Scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/019 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 mplement ents of canal section in FC ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation - 2,FC - 3 (Tr - 3) canal RB storm water infrastructure ank-SPD) MC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/023 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement ents to FC - 09, D2 canal i ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation n Tr.02 in Ingnimitiya RBM storm water infrastructure ank-SPD) C CRESMPA-1/RP/WORKS/ID Component 5: Improving -MAN/DC/001 / Fabrication Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- & Installation of 04 Nos.of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,478.80 0.00 mplement ntenance of irrigation and 5 0 4 22 Canal Spill Gates of Giants n) ation storm water infrastructure Tank Scheme in Murunkan Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/026 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement ents to flood damaged in F ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation C - 16 canal in Tr.02 in Ingi storm water infrastructure ank-SPD) nimitiya RBMC CRESMPA-1/RP/WORKS/ID -MAN/DC/002 / Fabrication Component 5: Improving Other (with fiel Pending I & Installation of 10 Nos. of climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,134.56 0.00 mplement Rads & 5th Gear Box for Gi ntenance of irrigation and 5 0 4 22 n) ation ants Tank Head Sluice Gat storm water infrastructure e of Giants Tank Scheme i n Murunkan Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -MAN/DC/003 / Fabrication climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,110.12 0.00 mplement & Installation of 01 No.of S ntenance of irrigation and 5 0 4 22 n) ation S Gate for Karunagakithalv storm water infrastructure u Spill in Silavathurai Divis ion CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -PUT/DC/001 / Fabrication climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 18,667.25 0.00 mplement & Installation of deteriorat ntenance of irrigation and 5 0 4 22 n) ation ed gates and repair their n storm water infrastructure ecessary hoisting mechani sms CRESMPA-1/RP/WORKS/ID Component 5: Improving -VAV/DC/002 / Repair,Fabri Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- cation & Installation of SS IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,271.35 0.00 mplement ntenance of irrigation and 5 0 4 22 Gates & Shop planks at Pa n) ation storm water infrastructure vatkulam LB Main Canal in Vavuniya Division CRESMPA-1/RP/WORKS/ID -VAV/DC/003 / Fabrication Component 5: Improving Other (with fiel Pending I & Installation of 05 Nos.of climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,362.15 0.00 mplement Cast Iron Gates with all Co ntenance of irrigation and 5 0 4 23 n) ation mponents at FC- 19th, FC- storm water infrastructure 21st , FC - 24th & D - 05 of Muhathankulam Scheme i n Vavuniya Division CRESMPA-1/RP/WORKS/ID -VAV/DC/004 / Fabrication Component 5: Improving Other (with fiel Pending I & Installation of SS gate f climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2023-12- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,712.62 0.00 mplement or Turnout & Regulator for ntenance of irrigation and 5 0 4 23 n) ation Branch Canal of RB Main C storm water infrastructure anal of Pavatkulam Schem e in Vavuniya Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -VAV/DC/008 / Improveme climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 47,400.00 0.00 mplement nts to Purana canal in LB ntenance of irrigation and 5 0 4 18 n) ation main canal at Pavatkulam storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -VAV/RFQ/006 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 29,933.33 0.00 mplement ents to LB - 02 canal off D- ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation 15 canal off RB main canal storm water infrastructure ank-SPD) at Pavatkulam National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -VAV/RFQ/011 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 18,933.33 0.00 mplement ents to FC - 08 A canal at ntenance of irrigation and tations e Envelope 0 5 12 process (Non B ation Muhathankulam storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -VAV/RFQ/015 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 24,033.33 0.00 mplement ents to LB main canal at R ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation ajendrankulam storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -HAM/DC/014 / Improveme climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,160.00 0.00 mplement nts to Spill approach of Ud ntenance of irrigation and 5 0 4 22 n) ation ukiriwila tank,Urubokka - storm water infrastructure Oya Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/029 / Rehabilita climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 27,830.00 0.00 mplement tion of FC11,Track 01,LBM ntenance of irrigation and tations e Envelope 0 5 11 process (Non B ation C,Lunugamwehera storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving -BAT/DC/004 / Supplying a Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- nd installing steel gate wit IBRD / 89960 Post Direct Selection Direct - National d for explanatio 7,000.00 0.00 mplement ntenance of irrigation and 5 0 4 01 h component to Vellaviralo n) ation storm water infrastructure dai anicut in Rugam Sche me Rugam Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -BAT/DC/005 / Gear arrang climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,716.67 0.00 mplement ement and replacing of ga ntenance of irrigation and 5 0 4 01 n) ation tes for Thumpalai anicut in storm water infrastructure Navakiri Division CRESMPA-1/RP/WORKS/ID Component 5: Improving -BAT/DC/006 / Suppling an Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- d installing steel gate with IBRD / 89960 Post Direct Selection Direct - National d for explanatio 30,300.00 0.00 mplement ntenance of irrigation and 5 0 4 01 component to Kochcharas n) ation storm water infrastructure enai anicut in Unnichchai s cheme Rugam Division CRESMPA-1/RP/WORKS/ID Component 5: Improving -BAT/DC/007 / Suppling an Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- d installing steel gate with IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,433.33 0.00 mplement ntenance of irrigation and 5 0 4 01 component to Udayandase n) ation storm water infrastructure nai anicut in Unnichchai sc heme Rugam Division CRESMPA-1/RP/WORKS/ID Component 5: Improving -BAT/DC/011 / Constructio Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-04- n of overcrossing in RB Ma IBRD / 89960 Post Direct Selection Direct - National d for explanatio 25,133.33 0.00 mplement ntenance of irrigation and 5 0 4 01 in Channal at Stn 18+800 i n) ation storm water infrastructure n Unnichchai Scheme,Rug am Division National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-07- -BAT/RFQ/019 / Desiting of IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 21 Mahiladitheevu Kulam process (Non B ation storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -COL/DC/015 / Removing o climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,625.00 0.00 mplement f water weeds in Thalanga ntenance of irrigation and 5 0 4 28 n) ation ma tank in Kaduwela storm water infrastructure National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Single Stage - On 2023-08-2 2023-08-3 2023-10-1 2023-11-1 2023-12-1 2024-12- -GAM/NCB/053 / Reconstru IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,000.00 0.00 mplement ntenance of irrigation and e Envelope 5 0 1 0 5 09 ction of the Katiyala Anicut process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -JAF/RFQ/001 / Rehabilitati climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement on of Kappothu - Vatharav ntenance of irrigation and tations e Envelope 0 5 20 process (Non B ation aththai Flood Protection ba storm water infrastructure ank-SPD) nd National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-08- -JAF/RFQ/004 / Rehabilitati IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 20 on of Kantharodai Tank process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -JAF/NCB/007 / Rehabilitati climate resilience and mai Single Stage - On 2023-08-2 2023-08-3 2023-10-1 2023-11-1 2023-12-1 2024-12- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,000.00 0.00 mplement on of Vallai to Vatharavath ntenance of irrigation and e Envelope 5 0 1 0 5 09 process (Non B ation thai Fllod protection bund storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KILI/NCB/004 / Improving climate resilience and mai Single Stage - On 2023-08-2 2023-08-3 2023-10-1 2023-11-1 2023-12-1 2024-12- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 60,000.00 0.00 mplement and restoring the bund of ntenance of irrigation and e Envelope 5 0 1 0 5 09 process (Non B ation Kudamuruddy (Earth work, storm water infrastructure ank-SPD) Rip-rap) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MUL/RFQ/001 / Restoring climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement Flood Damage Embankme ntenance of irrigation and tations e Envelope 0 5 19 process (Non B ation nt of Vavunikkulam Canal storm water infrastructure ank-SPD) Agricultural Road, Vavunik kulam National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KILI/NCB/005 / Reconstruc climate resilience and mai Single Stage - On 2023-08-2 2023-08-3 2023-10-1 2023-11-1 2023-12-1 2024-12- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,000.00 0.00 mplement tion of Saravanas Bridge a ntenance of irrigation and e Envelope 5 0 1 0 5 09 process (Non B ation t LB Main Canal of Iranama storm water infrastructure ank-SPD) du National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KILI/RFQ/012 / Reconstruc climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement tion of LR anicut in Kilinoc ntenance of irrigation and tations e Envelope 0 5 19 process (Non B ation hchi ASC storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KILI/RFQ/014 / Constructio climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement n of Kariyampiddykulam R ntenance of irrigation and tations e Envelope 0 5 21 process (Non B ation B & LB channel in Poonaga storm water infrastructure ank-SPD) ry ASC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KILI/RFQ/015 / Constructio climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement n of Puthulyankulam Main ntenance of irrigation and tations e Envelope 0 5 22 process (Non B ation Channel I & II in kilinochchi storm water infrastructure ank-SPD) ASC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KILI/RFQ/016 / Constructio climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 mplement n Of Maniyankulam RB & L ntenance of irrigation and tations e Envelope 0 5 20 process (Non B ation B channel in Akkarayankul storm water infrastructure ank-SPD) am ASC CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MUL/RFQ/002 / Restoring ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- Flood Damage Embankme IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 19 nt of Madawalasingam Ca process (Non B ation storm water infrastructure nal Agricultural Road, Mad ank-SPD) awalasingam National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MUL/RFQ/003 / Restoring climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement Flood Damage Embankme ntenance of irrigation and tations e Envelope 0 5 19 process (Non B ation nt of Udayarkaddu Canal A storm water infrastructure ank-SPD) gricultural Road, Udayarka ddu CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MUL/RFQ/004 / Restoring ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- Flood Damage Embankme IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 19 nt of Muththayankaddu Ca process (Non B ation storm water infrastructure nal Agricultural Road, Mut ank-SPD) hthayankaddu National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MUL/RFQ/005 / Restoring climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement Flood Damage Embankme ntenance of irrigation and tations e Envelope 0 5 19 process (Non B ation nt of Kalvilan Canal Agricul storm water infrastructure ank-SPD) tural Road, Kalvilan Tank CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MUL/RFQ/006 / Restoring ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- Flood Damage Embankme IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 19 nt of Ampalaperumal Cana process (Non B ation storm water infrastructure l Agricultural Road, Ampal ank-SPD) aperumal Page 9 National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MUL/RFQ/008 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ion of Idaikaddukulam in P ntenance of irrigation and tations e Envelope 0 5 19 process (Non B ation uthukudiyiruppu ASC Divis storm water infrastructure ank-SPD) ion National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MUL/RFQ/009 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ion of Thachchadampan T ntenance of irrigation and tations e Envelope 0 5 19 process (Non B ation ank in Olumadu ASC Divisi storm water infrastructure ank-SPD) on National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MUL/RFQ/010 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 mplement ion of Chalampankulam in ntenance of irrigation and tations e Envelope 0 5 21 process (Non B ation Padiyamkulam ASC Divisio storm water infrastructure ank-SPD) n National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MUL/RFQ/012 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 mplement ion of Sinnathekilankulam ntenance of irrigation and tations e Envelope 0 5 21 process (Non B ation in Padiyamkulam ASC Divi storm water infrastructure ank-SPD) sion National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MUL/RFQ/013 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement ion of Siththandimurippuk ntenance of irrigation and tations e Envelope 0 5 21 process (Non B ation ulam under in Olumadu A storm water infrastructure ank-SPD) SC Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -MAN/DC/004 / Fabrication climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,146.36 0.00 mplement & Installation of 01 No.of S ntenance of irrigation and 5 0 4 01 n) ation S gate for Sadaiyappan Spi storm water infrastructure ll in Silavathurai Division CRESMPA-1/RP/WORKS/ID Component 5: Improving -MAN/DC/005 / Fabrication Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- & Installation of 01 No.01o IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,045.63 0.00 mplement ntenance of irrigation and 5 0 4 01 f SS gate for Periyanochchi n) ation storm water infrastructure kulam Spill in Silavathurai Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -MAN/DC/006 / Fabrication climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,919.91 0.00 mplement & Installation of 02 No.of S ntenance of irrigation and 5 0 4 01 n) ation S gate for Palaikkuli Regul storm water infrastructure ator Spill in Silavathurai D ivision CRESMPA-1/RP/WORKS/ID Component 5: Improving -MAN/DC/007 / Fabrication Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- & Installation of 02Nos of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,498.14 0.00 mplement ntenance of irrigation and 5 0 4 01 SS Gates of Sundukkuli Ma n) ation storm water infrastructure in Regulator in Giants Tan k Scheme in Murunkan Div ision CRESMPA-1/RP/WORKS/ID Component 5: Improving -MAN/DC/008 / Fabrication Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- & Installation of 01 No.of S IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,287.66 0.00 mplement ntenance of irrigation and 5 0 4 01 S Gate of Nalavankulam F n) ation storm water infrastructure eeder Canal in Giants Tank Scheme in Murunkan Divis ion CRESMPA-1/RP/WORKS/ID -TRI/DC/001 / Improvemen Component 5: Improving Other (with fiel Pending I ts to gates & hoisting syst climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 22,113.59 0.00 mplement em and fabrication and Ins ntenance of irrigation and 5 0 4 01 n) ation tallation of Trash racks an storm water infrastructure d handrail for Batahathara Regualtor in Kantale Divisi on, Trincomalee CRESMPA-1/RP/WORKS/ID -TRI/DC/002 / Fabrication Component 5: Improving & Installation of 04 Nos of Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- mild steel Anicut slide gat IBRD / 89960 Post Direct Selection Direct - National d for explanatio 28,678.23 0.00 mplement ntenance of irrigation and 5 0 4 01 es (1800x1800mm) with h n) ation storm water infrastructure oisting mechanisms and al l components and handrail for Portankadu regulator in Kantale Division, Trincoma CRESMPA-1/RP/WORKS/ID lee -TRI/DC/003 / Painting 02 Component 5: Improving Nos of Radial gate Structur Other (with fiel Pending I climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- e using Colta, installing sta IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,347.37 0.00 mplement ntenance of irrigation and 5 0 4 01 inless steel cables,fabricati n) ation storm water infrastructure on of handrail and repair g uide wheel of Kusumankad a Anicut in Kantale Divisio n, Trincomalee CRESMPA-1/RP/WORKS/ID -TRI/DC/004 / Fabrication Component 5: Improving Other (with fiel Pending I & Installation of 03 Nos of climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 14,039.92 0.00 mplement mild steel gates with Scre ntenance of irrigation and 5 0 4 01 n) ation w type hoisting mechanis storm water infrastructure ms for Wendrasan Raja A muna Regulator in Kantale Division, Trincomalee CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MAN/RFQ/049 / Bund impr ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-10- ovement, Sluice, Spill Cons IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 19 truction and canal cutting i process (Non B ation storm water infrastructure n Periyamurippkulam of M ank-SPD) urukan ASC CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MAN/RFQ/059 / Solaikkula ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-10- m tank bund improvement IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 19 , Sluice,Spill construction process (Non B ation storm water infrastructure & Canal cutting in P.P Potk ank-SPD) eny ASC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MAN/RFQ/067 / Widening climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 35,000.00 0.00 mplement the feeder canal under Ko ntenance of irrigation and tations e Envelope 0 5 19 process (Non B ation orai Irrigation Scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/023 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 17,000.00 0.00 mplement nts to Mollipothana LBMC ntenance of irrigation and tations e Envelope 0 5 22 process (Non B ation canal bund road from stn storm water infrastructure ank-SPD) 0+000 to stn 2+000 CRESMPA-1/RP/WORKS/ID -PUT/DC/002 / Fabrication Component 5: Improving Other (with fiel Pending I & Installation of deteriorat climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-02- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 23,402.62 0.00 mplement ed Verticle regulator gates ntenance of irrigation and 5 0 4 01 n) ation and repair their necessary storm water infrastructure hoisting mechanisms, in R BMC Inginimitiya Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -JAF/RFQ/002 / Rehabilitati climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 mplement on of Semani - Kopay flood ntenance of irrigation and tations e Envelope 0 5 19 process (Non B ation protection bund storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -TRI/RFQ/024 / Improveme ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-08- nts to Kattaparichchan Dra IBRD / 89960 Post Limited nt - 1 Envelope 49,666.67 0.00 mplement ntenance of irrigation and tations e Envelope 0 5 20 inange canal from stn 1+0 process (Non B ation storm water infrastructure 50 to stn 2+200 in Muthur ank-SPD) Division National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/035 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplement nts of Channel System Ne ntenance of irrigation and tations e Envelope 0 5 22 process (Non B ation ar the Olukolla Sumith Hou storm water infrastructure ank-SPD) se to 1km Drainage CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -PUT/DC/011 / Constructio climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 50,000.00 0.00 mplement n of flood bund to avoid in ntenance of irrigation and 5 0 4 28 n) ation undation of paddy lands d storm water infrastructure uring floods CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -BAT/DC/010 / Reconstruct climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-06- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 50,833.33 0.00 mplement ion of Vinayagar Anicut in, ntenance of irrigation and 5 0 4 30 n) ation Navakari Scheme, Navaka storm water infrastructure ri Division CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -COL/DC/005 / Desilting of climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplement Unnecessary obstracles in ntenance of irrigation and 5 0 4 02 n) ation Haldummulla Canal 0+000 storm water infrastructure to 1+000 CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -PUT/DC/007 / Improveme climate resilience and mai 2023-08-2 2023-08-3 2023-10-0 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 90,000.00 0.00 mplement mnts to Maiyawa tank & 1 ntenance of irrigation and 5 0 4 28 n) ation st spill in sengaloya Sche storm water infrastructure me CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -TRI/NCB/007 / Improveme ement Docume Under Imp climate resilience and mai Single Stage - On 2023-08-2 2023-08-1 2023-08-3 2023-10-1 2023-11-1 2023-12-1 2024-12- nts to Kattaparichchan Dra IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 42,900.00 0.00 lementati ntenance of irrigation and e Envelope 5 5 0 1 0 5 09 inange Canal from stn 2+2 process (Non B on storm water infrastructure 00 to Stn 3+200 in Muthur ank-SPD) Division CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -TRI/NCB/005 / Improveme ement Docume Under Imp climate resilience and mai Single Stage - On 2023-08-2 2023-08-1 2023-08-3 2023-10-1 2023-11-1 2023-12-1 2024-09- nts to Peenganudaichan Ar IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 34,533.33 0.00 lementati ntenance of irrigation and e Envelope 5 5 0 1 0 5 10 u Drainange canal from St process (Non B on storm water infrastructure n 0+000 to Stn 1+120 in K ank-SPD) antale Division. National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -TRI/NCB/021 / Rehabilitati climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- IBRD / 89960 Post Open - National nt - 1 Envelope 33,600.00 0.00 Canceled on of FC24/D4/MC from stn ntenance of irrigation and tations e Envelope 0 5 09 process (Non B 0+000 to stn 0+225 in Ma storm water infrastructure ank-SPD) hadivulwewa scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -TRI/NCB/017 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-10- IBRD / 89960 Post Open - National nt - 1 Envelope 53,333.33 0.00 Canceled nts to MKYE canal bund ro ntenance of irrigation and tations e Envelope 0 5 09 process (Non B ad from stn 5+000 to Stn storm water infrastructure ank-SPD) 10+000 in Kantale National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -BAT/NCB/021 / Improvem climate resilience and mai Single Stage - On 2023-08-3 2023-08-2 2023-09-0 2023-10-1 2023-11-1 2023-12-2 2024-09- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,000.00 0.00 lementati ent to Pilayarady Anicut/R ntenance of irrigation and e Envelope 1 1 5 7 6 1 16 process (Non B on egulator in Kalvankai River storm water infrastructure ank-SPD) ,Rugam Scheme,Rugam Di vision National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -BAT/RFQ/018 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled ents to Access road to Kan ntenance of irrigation and tations e Envelope 0 5 21 process (Non B niyammai Anicut Navakari storm water infrastructure ank-SPD) Scheme,Navakari Division CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -HAM/RFQ/031 / New const ement Docume climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- ruction of Retaining wall at IBRD / 89960 Post Limited nt - 1 Envelope 18,016.67 0.00 Canceled ntenance of irrigation and tations e Envelope 5 0 28 0+015 - 0+047,0+400 - 0 process (Non B storm water infrastructure +446,0+570 - 0+675 in R ank-SPD) BMC of Mandagala Tank CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -HAM/RFQ/034 / Improvem ement Docume climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- ents of D/S basin of regula IBRD / 89960 Post Limited nt - 1 Envelope 31,956.67 0.00 Canceled ntenance of irrigation and tations e Envelope 5 0 26 tors at 0+872 & 2+399 of process (Non B storm water infrastructure Andupelena L/B Main cana ank-SPD) l in Urubokka - oya Schem e National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/037 / Rehabilita climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 23,666.67 0.00 Canceled tion of FC 09,DC 01 in Trac ntenance of irrigation and tations e Envelope 5 0 27 process (Non B t 07 Lunugamwehera RB storm water infrastructure ank-SPD) Component 5: Improving CRESMPA-1/RP/WORKS/ID Other (with fiel climate resilience and mai 2023-07-3 2023-08-0 2023-09-1 2024-09- -HAM/DC/040 / Improveme IBRD / 89960 Post Direct Selection Direct - National d for explanatio 50,000.00 0.00 Canceled ntenance of irrigation and 1 9 3 12 nts to Pahe gate in HLMC n) storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/043 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled ents to DC13 of Weerawila ntenance of irrigation and tations e Envelope 5 0 26 process (Non B Tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/045 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,666.67 0.00 Canceled ents to trough at 0+900 (8 ntenance of irrigation and tations e Envelope 5 0 24 process (Non B 0m) in LBMC, Muruthawela storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/046 / Installing f climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 17,256.67 0.00 Canceled arm turn out & canal lining ntenance of irrigation and tations e Envelope 5 0 28 process (Non B of 4th canal from 1+050 t storm water infrastructure ank-SPD) o 1+350 in SCB LB canal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/048 / Canal linin climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 33,112.33 0.00 Canceled g from 0+600 to 1+800 in ntenance of irrigation and tations e Envelope 5 0 26 process (Non B DI canal in Pahala andara storm water infrastructure ank-SPD) wewa National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/054 / Earth fillin climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 17,203.33 0.00 Canceled g in LBMC from 0+400 to ntenance of irrigation and tations e Envelope 5 0 28 process (Non B 1+100 in LB 8 canal storm water infrastructure ank-SPD) Page 10 CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -TRI/RFQ/039 / Reconstruct ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-05- ion of Pattiyanoor tank LB IBRD / 89960 Post Limited nt - 1 Envelope 21,333.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 1 28 C.O Spill at stn 0+180 cu process (Non B ation storm water infrastructure m causeway Kinniya D.S.D ank-SPD) ivision in Trincomalee Dist rict CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -HAM/RFQ/055 / Improvem ement Docume climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- ents to existing retaining IBRD / 89960 Post Limited nt - 1 Envelope 22,786.67 0.00 Canceled ntenance of irrigation and tations e Envelope 5 0 27 wall (RB) at 0+500 (180m) process (Non B storm water infrastructure of Feeder canal from Poth ank-SPD) u wewa in Urubokka - oya scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/056 / Installing f climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 17,950.00 0.00 Canceled arm turn out & canal lining ntenance of irrigation and tations e Envelope 5 0 28 process (Non B in SCB RB 01 canal from 0 storm water infrastructure ank-SPD) +500 - 0+827 National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/059 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled ents of tank bund in pothu ntenance of irrigation and tations e Envelope 5 0 25 process (Non B wewa in Urubokka - oya sc storm water infrastructure ank-SPD) heme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/082 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled ents to Hakmana yaya ani ntenance of irrigation and tations e Envelope 5 0 24 process (Non B cut storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -AMP/DC/019 / Improveme climate resilience and mai 2023-08-0 2023-08-0 2023-09-1 2024-09- IBRD / 89960 Post Direct Selection Direct - National nt - 1 Envelope 44,988.00 0.00 Canceled nts to WG-4 D' canal inclu ntenance of irrigation and 4 9 3 12 process (Non B ding necessary structure i storm water infrastructure ank-SPD) n illukkuchenai unit CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel -GAL/DC/008 / Improveme climate resilience and mai 2023-08-0 2023-08-0 2023-09-1 2024-09- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 45,880.00 0.00 Canceled nts to main canals Idigask ntenance of irrigation and 4 9 3 12 n) etiya scheme storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/059 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-10- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement nts to Kurankupanchan ta ntenance of irrigation and tations e Envelope 5 1 25 process (Non B ation nk in Kinniya D.S.Division storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving -AMP/DC/041 / Improveme Other (with fiel climate resilience and mai 2023-07-3 2023-08-0 2023-09-0 2024-09- nts to breached section of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 44,953.33 0.00 Canceled ntenance of irrigation and 1 5 9 03 Andaloya river in Poochch n) storm water infrastructure ukudi at stn 2+520 in Wee ragoda unit CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -AMP/RFQ/039 / Improvem ement Docume climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- ents to downstream of M 1 IBRD / 89960 Post Limited nt - 1 Envelope 37,550.00 0.00 Canceled ntenance of irrigation and tations e Envelope 5 0 26 8 Regulater structure at st process (Non B storm water infrastructure n 8+800 in Mandoor Branc ank-SPD) h canal - Annamalai unit National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -AMP/NCB/007 / Reconstru climate resilience and mai Single Stage - On 2023-07-3 2023-09-2 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 100,000.00 0.00 lementati ction of RB End Spillway at ntenance of irrigation and e Envelope 1 8 5 6 6 0 19 process (Non B on Walagama Tank in Uhana storm water infrastructure ank-SPD) Unit CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel -GAM/DC/021 / Embankme climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,666.67 0.00 Canceled nt to protect Pallewela left ntenance of irrigation and 5 0 4 22 n) bank main canal to preven storm water infrastructure t from erosion CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel -GAM/DC/022 / Upgrading climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,333.33 0.00 Canceled the existing left flood bund ntenance of irrigation and 5 0 4 22 n) in Nahitiya anicut storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -GAM/RFQ/023 / Concrete l climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled ining of a 150 m long of th ntenance of irrigation and tations e Envelope 0 5 10 process (Non B e left bank main canal of T storm water infrastructure ank-SPD) ammita scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -AMP/NCB/012 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 100,000.00 0.00 mplement ents Meegahapallama Anic ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation ut in Damana unit storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID -VAV/DC/001 / Fabrication Component 5: Improving & Installation of 04 Nos.of Other (with fiel Pending I climate resilience and mai 2023-08-1 2023-08-2 2023-09-2 2024-04- Lifting Mechanism, Lifting IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,534.29 0.00 mplement ntenance of irrigation and 5 0 4 21 Rod, Passerel, Pedestal Ba n) ation storm water infrastructure se for Regulator Gates & H and- Rail of Kal - Aru Anicu t Gates in Vavuniya Divisio n National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/011 / Rehabilita climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-10-0 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 34,666.67 0.00 Canceled tion of FC 114 in branch ca ntenance of irrigation and tations e Envelope 7 2 26 process (Non B nal 9, in track III of the Mur storm water infrastructure ank-SPD) uthawela scheme CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -HAM/DC/011 / Rehabilitati climate resilience and mai 2023-08-3 2023-09-0 2023-10-1 2024-10- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 32,150.00 0.00 mplement on of FC114 in tract iii D9, ntenance of irrigation and 1 5 0 04 n) ation Muruthawela Scheme storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/015 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-10-0 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 49,996.67 0.00 Canceled ents to FC34 , DC2 track 0 ntenance of irrigation and tations e Envelope 7 2 26 process (Non B 6, RBMC , Lunugamwehera storm water infrastructure ank-SPD) scheme CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -HAM/DC/015 / Improveme climate resilience and mai 2023-08-3 2023-09-0 2023-10-1 2024-10- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 46,886.67 0.00 mplement nts to FC34,DC2,Track 06, ntenance of irrigation and 1 5 0 04 n) ation RBMC Lunugamwehera storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/028 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 35,305.00 0.00 Canceled on of canal lining of CPO 3 ntenance of irrigation and tations e Envelope 5 0 24 process (Non B 5 from 0+000 to 0+300 in storm water infrastructure ank-SPD) WRB scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/027 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 18,546.67 0.00 Canceled ents to DC 8B,Weerawila S ntenance of irrigation and tations e Envelope 5 0 28 process (Non B cheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/RFQ/006 / Rehabilita climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 27,830.00 0.00 Canceled tion of FC11,Track 01,LBM ntenance of irrigation and tations e Envelope 5 0 26 process (Non B C,Lunugamwehera storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -HAM/NCB/007 / New Cons climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 50,078.67 0.00 Canceled truction of canal lining at i ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B n P25 Ridiyagama main ca storm water infrastructure ank-SPD) nal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -BAD/RFQ/017 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled on of 15 m long R/wall at 0 ntenance of irrigation and tations e Envelope 5 0 26 process (Non B +078 and 15m long at 1+ storm water infrastructure ank-SPD) 980 in R/B side of main ca nal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -BAD/RFQ/020 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 23,000.00 0.00 Canceled ents to FC 23 in Demodara ntenance of irrigation and tations e Envelope 5 0 26 process (Non B Scheme storm water infrastructure ank-SPD) National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- -BAD/RFQ/021 / Rehabilitat IBRD / 89960 Post Limited nt - 1 Envelope 19,083.33 0.00 Canceled ntenance of irrigation and tations e Envelope 5 0 26 ion of Mahamaditta tank process (Non B storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -BAD/RFQ/006 / Cons. Of c climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled anal lining from 0+300 to ntenance of irrigation and tations e Envelope 5 0 26 process (Non B 0+400 in Main Canal storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -BAD/DC/001 / Improveme climate resilience and mai 2023-08-3 2023-09-0 2023-10-1 2024-04- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 14,666.67 0.00 mplement nts to RB canal at 6+220 i ntenance of irrigation and 1 5 0 07 n) ation n Medaela storm water infrastructure Component 5: Improving CRESMPA-1/RP/WORKS/ID Other (with fiel Pending I climate resilience and mai 2023-08-3 2023-09-0 2023-10-1 2024-03- -BAD/DC/004 / Improveme IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,000.00 0.00 mplement ntenance of irrigation and 1 5 0 08 nts to FC 1/RBMC n) ation storm water infrastructure National Procur Component 5: Improving CRESMPA-1/RP/WORKS/ID ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-04- -BAD/RFQ/010 / Improvem IBRD / 89960 Post Limited nt - 2 Envelope 26,666.67 0.00 mplement ntenance of irrigation and tations e Envelope 5 1 28 ents to FC 2/RBMC process (Non B ation storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAD/NCB/012 / Improvem climate resilience and mai Single Stage - On 2023-08-3 2023-09-0 2023-10-1 2023-11-1 2023-12-2 2024-05- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 51,333.33 0.00 mplement ents to FC 24 in Dehigama ntenance of irrigation and e Envelope 1 5 7 6 1 19 process (Non B ation Scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAT/NCB/020 / Constructi climate resilience and mai Single Stage - On 2023-08-3 2023-09-0 2023-10-1 2023-11-1 2023-12-2 2024-12- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 56,666.67 0.00 mplement on in Concrete canel lining ntenance of irrigation and e Envelope 1 5 7 6 1 15 process (Non B ation in Irassakal tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAT/NCB/022 / Improvem climate resilience and mai Single Stage - On 2023-08-3 2023-09-0 2023-10-1 2023-11-1 2023-12-2 2024-12- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 70,000.00 0.00 mplement ents to Tank Bund at Kang ntenance of irrigation and e Envelope 1 5 7 6 1 15 process (Non B ation aniyar Tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAT/RFQ/023 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplement on of Retaining wall & Imp ntenance of irrigation and tations e Envelope 5 1 27 process (Non B ation rovements to Anicut cum storm water infrastructure ank-SPD) bridge Manalpitty Anicut National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAT/RFQ/024 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 mplement ents to Downstream of Co ntenance of irrigation and tations e Envelope 5 1 27 process (Non B ation - Spill at Meiynkai Tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATR/RFQ/012 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 21,366.67 0.00 mplement ments of canal system in ntenance of irrigation and tations e Envelope 5 1 28 process (Non B ation Walgama north area in Kir storm water infrastructure ank-SPD) alakale scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATR/RFQ/015 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplement ments to sub canals of B c ntenance of irrigation and tations e Envelope 5 1 27 process (Non B ation anal in Akuressa Scheme li storm water infrastructure ank-SPD) ft irrigation system National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MATR/RFQ/051 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-04- IBRD / 89960 Post Limited nt - 1 Envelope 17,400.00 0.00 mplement ments of Sadagankanda A ntenance of irrigation and tations e Envelope 5 1 28 process (Non B ation nicut storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -MON/NCB/051 / Rehabilita climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 100,000.00 0.00 Canceled tion of 500m of LBMC in W ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B eherakema tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -MON/RFQ/67 / constructio climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled n of LB canal system in An ntenance of irrigation and tations e Envelope 5 0 24 process (Non B kada tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -MON/RFQ/68 / Improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 43,333.33 0.00 Canceled nts to Badalkumbura Madu ntenance of irrigation and tations e Envelope 5 0 24 process (Non B gasmulla Anicut storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KAD/RFQ/010 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 20,066.67 0.00 Canceled ents to D38 canal in stage ntenance of irrigation and tations e Envelope 0 5 11 process (Non B i storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KAL/RFQ/016 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled ents to gate of Halthota an ntenance of irrigation and tations e Envelope 5 0 27 process (Non B icat at panape ela storm water infrastructure ank-SPD) Page 11 National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KAL/RFQ/049 / Clearing & climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled desilting of Hikgahadeniya ntenance of irrigation and tations e Envelope 5 0 25 process (Non B Ela Bund storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -KUR/RFQ/036 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-2 2023-10-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 21,956.33 0.00 Canceled on of box culvert at 0+240 ntenance of irrigation and tations e Envelope 0 5 11 process (Non B & gravelling along the mai storm water infrastructure ank-SPD) n canal bund road CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KUR/DC/028 / Improveme climate resilience and mai 2023-08-3 2023-09-0 2023-10-1 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,246.67 0.00 mplement nts to Kahaliya Anicut and ntenance of irrigation and 1 5 0 08 n) ation bund road in Hulugalla sch storm water infrastructure eme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -ANU/RFQ/014 / Repairs of climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 27,333.33 0.00 Canceled Diulwewa Canal Spill in Na ntenance of irrigation and tations e Envelope 5 0 26 process (Non B chchaduwa Division storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -ANU/DC/014 / Repairs of climate resilience and mai 2023-08-3 2023-09-0 2023-10-1 2024-10- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 27,333.33 0.00 mplement Diulwewa Canal Spill in Na ntenance of irrigation and 1 5 0 04 n) ation chchaduwa Division storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -ANU/RFQ/038 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 19,666.67 0.00 mplement ents to D8 Road RBMC Hur ntenance of irrigation and tations e Envelope 5 0 28 process (Non B ation uluwewa scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAD/RFQ/008 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 31,333.33 0.00 mplement on of canal lining at 0+28 ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation 5 in Badulu oya main cana storm water infrastructure ank-SPD) l in Badulu oya scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAD/RFQ/009 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 27,333.33 0.00 mplement on of Canal lining at 0+32 ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation 0 of main canal storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAD/RFQ/011 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 36,000.00 0.00 mplement ents to canal lining from 0 ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation +000 to 7+500 in main ca storm water infrastructure ank-SPD) nal National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAD/NCB/003 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 87,333.33 0.00 mplement ents to Medala trough at 1 ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation +615 storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -BAD/NCB/007 / Improvem climate resilience and mai Single Stage - On 2023-07-3 2023-08-0 2023-09-1 2023-10-1 2023-11-2 2024-11- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 51,333.33 0.00 mplement ents to 1+034 canal spill i ntenance of irrigation and e Envelope 1 5 6 6 0 14 process (Non B ation n LBMC in Sorabora Schem storm water infrastructure ank-SPD) e National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/030 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 45,433.33 0.00 mplement ents to FC - 4 Gemunupur ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation a main canal of Gemunupu storm water infrastructure ank-SPD) ra Scheme in Tissa Divisio n National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -MON/RFQ/054 / Rehabilita climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled tion of FC 06 RBMC in RB o ntenance of irrigation and tations e Envelope 5 0 26 process (Non B f Kandiyapita tank storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -GAL/RFQ/097 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled ion of Niyagama Andadola ntenance of irrigation and tations e Envelope 5 0 27 process (Non B canal storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -MATR/CP/066 / Rehabilitat climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled ion yahagedramulla Anicut ntenance of irrigation and tations e Envelope 5 0 27 process (Non B , Polwattagedar Anicut and storm water infrastructure ank-SPD) paragahalaga Dam National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -MATR/CP/065 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 21,266.67 0.00 Canceled on of Anicut at Retaining w ntenance of irrigation and tations e Envelope 5 0 27 process (Non B all Galetamba storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -MATR/CP/062 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 20,666.67 0.00 Canceled on of side wall with spill at ntenance of irrigation and tations e Envelope 5 0 27 process (Non B Weressa Anicut storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -MATR/CP/051 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-03- IBRD / 89960 Post Limited nt - 1 Envelope 17,400.00 0.00 Canceled ents of Sadagankanda Ani ntenance of irrigation and tations e Envelope 5 0 28 process (Non B cut storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MON/RFQ/017 / Constructi ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-06- on of 83m long Retaining IBRD / 89960 Post Limited nt - 1 Envelope 24,400.00 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 26 wall at LB side from 0+61 process (Non B ation storm water infrastructure 5 to 0+693 in RBMC Hamb ank-SPD) egamuwa tank National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -KUR/RFQ/024 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 38,036.67 0.00 mplement on of box culvert at 0+240 ntenance of irrigation and tations e Envelope 5 0 27 process (Non B ation and graveling of main can storm water infrastructure ank-SPD) al bund road in Madulla sc heme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -MON/RFQ/028 / Demolishi climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-07- IBRD / 89960 Post Limited nt - 1 Envelope 28,973.33 0.00 mplement ng damaged trough & Can ntenance of irrigation and tations e Envelope 5 0 26 process (Non B ation al lining at 2+250 in main storm water infrastructure ank-SPD) canal in Hulandawa LB can al CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -MON/RFQ/016 / Demolishi ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-09-3 2024-04- ng and Reconstruction of 3 IBRD / 89960 Post Limited nt - 1 Envelope 17,843.33 0.00 mplement ntenance of irrigation and tations e Envelope 5 0 27 8m long trough structure a process (Non B ation storm water infrastructure t 1 + 750 in Maganda Oya ank-SPD) anicut National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -TRI/NCB/017-1 / Improve climate resilience and mai Single Stage - On 2023-08-3 2023-08-1 2023-09-0 2023-10-1 2023-11-1 2023-12-2 2024-12- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 53,333.33 0.00 lementati ments to MKYE canal bund ntenance of irrigation and e Envelope 1 5 5 7 6 1 15 process (Non B on road from stn 5+000 to St storm water infrastructure ank-SPD) n 15+000 in Kantale National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/019 / Constructio climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-10-0 2023-11- IBRD / 89960 Post Limited nt - 1 Envelope 33,500.00 0.00 mplement n of Retaining walls at stn ntenance of irrigation and tations e Envelope 7 2 01 process (Non B ation 4+920 in LBMC, Muthur Di storm water infrastructure ank-SPD) vision stage I National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -TRI/RFQ/022 / improveme climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-10-0 2023-11- IBRD / 89960 Post Limited nt - 1 Envelope 23,600.00 0.00 mplement nts to Allai kanthale raja El ntenance of irrigation and tations e Envelope 7 2 03 process (Non B ation a connecting road. storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -TRI/RFQ/030 / Constructio climate resilience and mai Request for Quo Single Stage - On 2023-08-0 2023-10-0 2023-11- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 Canceled n of retaining walls at stn ntenance of irrigation and tations e Envelope 7 2 01 process (Non B 14+409 to stn 14+494 in storm water infrastructure ank-SPD) RBMC, Muthur Division sta ge I National Procur SLMOI/CRES/ID/W/S/14 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- evelopment and Improve IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 10,470.00 0.00 mplement tations e Envelope 4 9 27 ments at Thaldena Field Of Impact Weather, Floods a process (Non B ation fice nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/15 / C Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- onstruction of PVC Coated IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 4,053.33 0.00 mplement tations e Envelope 4 9 27 Wire Mesh Fence at Rathn Impact Weather, Floods a process (Non B ation apura Field Office nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/16 / C Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- onstruction of a Gate at D IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 1,160.00 0.00 mplement tations e Envelope 4 9 27 unamale Field Office Impact Weather, Floods a process (Non B ation nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/17 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- evelopment and Improve IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 8,936.67 0.00 mplement tations e Envelope 4 9 27 ments at Kuda Oya Field O Impact Weather, Floods a process (Non B ation ffice nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/19 / C Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- onstruction of a Gate with IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 3,576.67 0.00 mplement tations e Envelope 4 9 27 Fence at the Katharagama Impact Weather, Floods a process (Non B ation Field Office nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/20 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- evelopment and Improve IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 15,163.33 0.00 mplement tations e Envelope 4 9 27 ments at Wellawaya Field Impact Weather, Floods a process (Non B ation Office nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/22 / C Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- onstruction of a Gate with IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 3,280.00 0.00 mplement tations e Envelope 4 9 27 Fence, Flood Light Post at Impact Weather, Floods a process (Non B ation Siyabalanduwa Filed Office nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/23 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- evelopment and Improve IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 9,960.00 0.00 mplement tations e Envelope 4 9 27 ments at Badalgama Field Impact Weather, Floods a process (Non B ation Office nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/24 / I Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- mprovements and supplyi IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 3,950.00 0.00 mplement tations e Envelope 4 9 27 ng water connection to the Impact Weather, Floods a process (Non B ation Giriulla Field Office nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/25 / C Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- onstruction of Field Office IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 26,130.00 0.00 mplement tations e Envelope 4 9 27 at Moraketiya Gauging Sta Impact Weather, Floods a process (Non B ation tion nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/26 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- evelopment and Improve IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 8,480.00 0.00 mplement tations e Envelope 4 9 27 ments at the Baddegama Impact Weather, Floods a process (Non B ation Field Office nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/NCB/27 Component 1: Forecasting ement Docume Pending I Single Stage - On 2023-09-2 2023-10-0 2023-11-1 2023-12-1 2024-01-1 2024-07- / Construction of Field Offi IBRD / 89960 and Early Warning of High Post Request for Bids Open - National nt - 1 Envelope 57,383.33 0.00 mplement e Envelope 9 4 5 5 9 17 ce at Holombuwa Gauging Impact Weather, Floods a process (Non B ation Station nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/28 / C Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- onstruction of Field Office IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 29,413.33 0.00 mplement tations e Envelope 4 9 27 at Norwood Gauging Statio Impact Weather, Floods a process (Non B ation n nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/29 / C Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- onstruction of Field Office IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 27,000.00 0.00 mplement tations e Envelope 4 9 27 at Glencourse Gauging Sta Impact Weather, Floods a process (Non B ation tion nd Landslides ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -GAL/NCB/008-1 / Improve climate resilience and mai Single Stage - On 2023-08-3 2023-10-0 2023-09-0 2023-10-1 2023-11-1 2023-12-2 2024-12- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 45,880.00 0.00 lementati ments to main canals Idiga ntenance of irrigation and e Envelope 1 3 5 7 6 1 15 process (Non B on sketiya scheme storm water infrastructure ank-SPD) SLMOI/CRES/ID/W/S/10 / C Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-10-1 2023-12-1 2024-06- onstruction of Field Office IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 43,276.67 0.00 mplement tations e Envelope 8 3 10 at Kalawellawa Gauging St Impact Weather, Floods a ank-SPD) ation ation in Kuda Ganga nd Landslides National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -TRI/NCB/021-1 / Rehabilit climate resilience and mai Single Stage - On 2023-08-3 2023-08-1 2023-09-0 2023-10-1 2023-11-1 2023-12-2 2024-09- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 33,600.00 0.00 lementati ation of FC24/D4/MC from ntenance of irrigation and e Envelope 1 5 5 7 6 1 16 process (Non B on stn 0+000 to stn 0+225 in storm water infrastructure ank-SPD) Mahadivulwewa scheme SLMOI/CRES/ID/W/S/11 / C Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-10-1 2023-12-1 2024-06- onstruction of Field Office IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 17,673.33 0.00 mplement tations e Envelope 8 3 10 at Peradeniya Gauging Sta Impact Weather, Floods a ank-SPD) ation tion nd Landslides SLMOI/CRES/ID/W/S/18 / C Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-10-1 2023-12-1 2024-06- onstruction of PVC Coated IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 6,573.33 0.00 mplement tations e Envelope 8 3 10 Wire Mesh Fence at Putup Impact Weather, Floods a ank-SPD) ation aula Field Office nd Landslides National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -BAT/NCB/018 / Improvem climate resilience and mai Single Stage - On 2023-08-3 2023-08-2 2023-09-0 2023-10-1 2023-11-1 2023-12-2 2024-09- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 33,333.33 0.00 lementati ents to Access road to Kan ntenance of irrigation and e Envelope 1 1 5 7 6 1 16 process (Non B on niyammai Anicut Navakari storm water infrastructure ank-SPD) Scheme,Navakari Division SLMOI/CRES/ID/W/S/12 / C Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-10-1 2023-12-1 2024-06- onstruction of Electric Fen IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 2,346.67 0.00 mplement tations e Envelope 8 3 10 ce at Galgamuwa Field Offi Impact Weather, Floods a ank-SPD) ation ce nd Landslides SLMOI/CRES/ID/W/S/13 / D Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-10-1 2023-12-1 2024-06- evelopment and Improve IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 4,403.33 0.00 mplement tations e Envelope 8 3 10 ments at Horowpathana Fi Impact Weather, Floods a ank-SPD) ation eld Office nd Landslides Page 12 SLMOI/CRES/ID/W/S/09 / C Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-10-1 2023-12-1 2024-06- onstruction of Field Office IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 21,786.67 0.00 mplement tations e Envelope 8 3 10 at Magura Gauging Station Impact Weather, Floods a ank-SPD) ation nd Landslides CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/004 / Improveme climate resilience and mai 2023-09-2 2023-09-2 2023-10-3 2024-03- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,666.67 0.00 mplement nts to Liyanagoda ela (0 ntenance of irrigation and 0 5 0 28 n) ation +000 - 0+900) storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/066 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-10-0 2023-12-0 2024-02- IBRD / 89960 Post Limited nt - 1 Envelope 22,463.33 0.00 mplement on of Retaining wall Bibila ntenance of irrigation and tations e Envelope 6 1 29 process (Non B ation goda yaya storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/032 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-10-0 2023-12-0 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 35,305.00 0.00 mplement on of canal lining of CPO 3 ntenance of irrigation and tations e Envelope 6 1 26 process (Non B ation 5 from 0+000 to 0+300 in storm water infrastructure ank-SPD) WRB scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/031-1 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-10-0 2023-12-0 2024-05- IBRD / 89960 Post Limited nt - 1 Envelope 18,546.67 0.00 mplement ments to DC 8B,Weerawila ntenance of irrigation and tations e Envelope 6 1 29 process (Non B ation Scheme storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -HAM/RFQ/034-1 / Improve climate resilience and mai Request for Quo Single Stage - On 2023-10-0 2023-12-0 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 29,683.33 0.00 mplement ments to FC - 4 Gemunupu ntenance of irrigation and tations e Envelope 6 1 26 process (Non B ation ra main canal of Gemunup storm water infrastructure ank-SPD) ura Scheme in Tissa Divisi on CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -HAM/RFQ/035 / New const ement Docume Pending I climate resilience and mai Request for Quo Single Stage - On 2023-10-0 2023-12-0 2024-04- ruction of Retaining wall at IBRD / 89960 Post Limited nt - 1 Envelope 18,016.67 0.00 mplement ntenance of irrigation and tations e Envelope 6 1 29 0+015 - 0+047,0+400 - 0 process (Non B ation storm water infrastructure +446,0+570 - 0+675 in R ank-SPD) BMC of Mandagala Tank National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -GAM/RFQ/023-1 / Concret climate resilience and mai Request for Quo Single Stage - On 2023-10-0 2023-12-0 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 34,400.00 0.00 mplement e lining of a 150 m long of ntenance of irrigation and tations e Envelope 6 1 26 process (Non B ation the left bank main canal of storm water infrastructure ank-SPD) Tammita scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume -GAM/RFQ/034 / Concrete l climate resilience and mai Request for Quo Single Stage - On 2023-08-3 2023-10-2 2024-08- IBRD / 89960 Post Limited nt - 1 Envelope 34,666.67 0.00 Canceled ining from 1+500 to 1+76 ntenance of irrigation and tations e Envelope 0 5 20 process (Non B 0 in left bank main canal o storm water infrastructure ank-SPD) f Panugala scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Under Imp -AMP/NCB/019 / Improvem climate resilience and mai Single Stage - On 2023-10-0 2023-09-2 2023-10-0 2023-10-1 2023-11-1 2023-12-1 2024-01-2 2025-01- IBRD / 89960 Post Request for Bids Open - National nt - 1 Envelope 44,988.00 0.00 lementati ents to WG-4 D' canal incl ntenance of irrigation and e Envelope 1 8 6 3 7 7 1 15 process (Non B on uding necessarry structure storm water infrastructure ank-SPD) in illukkuchenai unit CRESMPA-1/RP/WORKS/ID National Procur Component 5: Improving -AMP/RFQ/019-1 / Improve ement Docume climate resilience and mai Request for Quo Single Stage - On 2023-09-0 2023-10-3 2024-10- ments to WG-4 D' canal in IBRD / 89960 Post Limited nt - 1 Envelope 44,988.00 0.00 Canceled ntenance of irrigation and tations e Envelope 5 1 25 cluding necessarry structu process (Non B storm water infrastructure re in illukkuchenai unit (CR ank-SPD) esMPA-1/RP/WORKS/ID-AM P/RFQ/019) National Procur SLMOI/CRES/ID/W/S/21 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- evelopment and Improve IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 11,570.00 0.00 mplement tations e Envelope 4 9 27 ments at the Nakkala Field Impact Weather, Floods a process (Non B ation Office nd Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/30 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-10-0 2023-11-2 2024-05- evelopment and Improve IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 5,500.00 0.00 mplement tations e Envelope 4 9 27 ments at the Ampara Field Impact Weather, Floods a process (Non B ation Office nd Landslides ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -KAL/DC/005 / Improveme climate resilience and mai 2023-10-1 2023-10-1 2023-11-2 2024-04- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 14,000.00 0.00 mplement nts to Liyanagoda ela (0+ ntenance of irrigation and 2 7 1 19 n) ation 900 - 3+500) storm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/012 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-10-2 2023-12-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement ents to damaged brick can ntenance of irrigation and tations e Envelope 1 6 13 process (Non B ation al lining section in D2 (Tr.0 storm water infrastructure ank-SPD) 1 ) canal of Ingirimitiya LB MC National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/014 / Supply, fab climate resilience and mai Request for Quo Single Stage - On 2023-10-2 2023-12-1 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 mplement ricating, fixing, liftining gat ntenance of irrigation and tations e Envelope 1 6 11 process (Non B ation e to the Thinipitiya anicut storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/015 / Constructi climate resilience and mai Request for Quo Single Stage - On 2023-10-2 2023-12-1 2024-09- IBRD / 89960 Post Limited nt - 1 Envelope 40,000.00 0.00 mplement on of gabion wall bank pro ntenance of irrigation and tations e Envelope 1 6 11 process (Non B ation tection to Buttaulu oya storm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/018 / Improvem climate resilience and mai Request for Quo Single Stage - On 2023-10-2 2023-12-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement ents to FC - 2 in LB MC in ntenance of irrigation and tations e Envelope 1 6 13 process (Non B ation Kudaottupallama in Neela storm water infrastructure ank-SPD) bemma Scheme National Procur CRESMPA-1/RP/WORKS/ID Component 5: Improving ement Docume Pending I -PUT/RFQ/020 / Concrete c climate resilience and mai Request for Quo Single Stage - On 2023-10-2 2023-12-1 2024-06- IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplement anal lining from 0 + 000 to ntenance of irrigation and tations e Envelope 1 6 13 process (Non B ation 0+150 km in 3rd canal storm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -PUT/DC/021 / Improveme climate resilience and mai 2023-10-1 2023-10-2 2023-11-2 2024-05- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,666.67 0.00 mplement nts to SD 2 canal in D2 ca ntenance of irrigation and 6 1 5 23 n) ation nal of Radavi Bendi Ela Sc storm water infrastructure heme CRESMPA-1/RP/WORKS/ID Component 5: Improving Other (with fiel Pending I -GAM/DC/019 / Rehabilitati climate resilience and mai 2023-11-2 2023-11-2 2023-12-3 2024-01- IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,000.00 0.00 mplement on of the right bank acces ntenance of irrigation and 0 5 0 11 n) ation s road to Tammita scheme storm water infrastructure GOODS Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLMOI/CRES/ID/G/NCB/05 Component 1: Forecasting / Procurement of Compute and Early Warning of High Single Stage - On 2022-08-2 2022-10-1 2022-08-2 2022-10-1 2022-09-1 2022-11-0 2022-10-0 2023-01-0 2022-11-0 2023-03-2 2023-03-0 rs and UPS for Hydrology a IBRD / 89960 Post Request for Bids Open - National 52,000.00 0.00 Signed Impact Weather, Floods a e Envelope 6 0 8 8 8 9 3 4 9 2 9 nd Disaster Management nd Landslides Division at Irrigational Dep artment SLMOI/CRES/NBRO/G/NCB Component 1: Forecasting /02 / Procurement of IT an and Early Warning of High Single Stage - On 2022-10-2 2022-10-1 2022-10-2 2022-11-1 2023-01-1 2022-12-0 2023-07-1 2023-01-0 2023-09-1 2023-05-0 IBRD / 89960 Post Request for Bids Open - National 203,500.00 0.00 Signed d other related equipment Impact Weather, Floods a e Envelope 6 2 8 8 9 2 8 8 3 8 and High-end server for N nd Landslides BRO SLMOI/CRES/ID/G/NCB/04 Component 1: Forecasting / Procurement of hydrologi and Early Warning of High Single Stage - On Under Impl 2022-08-3 2022-10-1 2022-09-0 2022-10-1 2022-09-2 2022-11-0 2022-10-1 2022-12-2 2022-11-2 2023-03-2 cal measuring equipment IBRD / 89960 Post Request for Bids Open - National 172,000.00 0.00 Impact Weather, Floods a e Envelope ementation 1 0 2 8 3 9 4 8 0 0 and weather instruments f nd Landslides or Hydrology and Disaster Management Division SLMOI/CRES/NBRO/G/S/03 Component 1: Forecasting / Procurement of Digital Pa and Early Warning of High Request for Quo Single Stage - On 2022-10-2 2023-01-0 2023-05-0 IBRD / 89960 Post Limited 35,500.00 0.00 Canceled nals for displaying ARG Sy Impact Weather, Floods a tations e Envelope 8 9 9 stem and other sensor net nd Landslides works of NBRO SLMOI/CRES/NBRO/G/NCB Component 1: Forecasting /03 / Procurement of Digit and Early Warning of High Single Stage - On 2022-10-1 2022-10-1 2022-10-2 2022-12-0 2023-01-1 2023-01-0 2023-05-0 2023-02-0 2023-06-1 2023-06-0 2023-07-1 IBRD / 89960 Post Request for Bids Open - National 70,000.00 0.00 Completed al Panels for Displaying AR Impact Weather, Floods a e Envelope 7 2 2 3 8 2 3 6 3 6 3 G System and other Senso nd Landslides r Networks of NBRO SLMOI/CRES/NBRO/G/DS/0 Component 1: Forecasting Under Impl 2023-09-1 2023-08-0 2023-09-2 2023-09-1 2023-10-2 2024-01-2 8 / Procurement of ArcGIS IBRD / 89960 and Early Warning of High Post Direct Selection Direct - National 22,800.00 0.00 ementation 8 3 3 8 8 6 Pro for the National Buildin Impact Weather, Floods a g Research Organisation nd Landslides SLMOI/CRES/NBRO/G/S/06 Component 1: Forecasting / Procurement of office fur and Early Warning of High Request for Quo Single Stage - On 2022-10-0 2022-12-1 2023-04-1 IBRD / 89960 Post Limited 22,000.00 0.00 Canceled niture for Landslide Early Impact Weather, Floods a tations e Envelope 2 4 3 Warning Center at Nationa nd Landslides l Building Research Organi zation SLMOI/CRES/NBRO/G/NCB Component 1: Forecasting /09 / Supply, Install, Upgra Pending Im and Early Warning of High Single Stage - On 2023-10-2 2023-10-2 2023-12-0 2024-01-0 2024-02-0 2024-05-0 de and Maintenance of Aut IBRD / 89960 Post Request for Bids Open - National 988,787.00 0.00 plementati Impact Weather, Floods a e Envelope 0 5 6 5 9 9 omated Rain-Guage Syste on nd Landslides ms in 14 Landslide Prone Districts NON CONSULTING SERVICES Activity Reference No. Bid Evaluation Repo Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission / Description Component Review Type Method rt and Recommenda Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes tion for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Intere Request for Proposal Opening of Technica Evaluation of Techn / Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s st Notice s as Issued l Proposals / Minutes ical Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLMOI/CRES/ID/C/CQS/28 Component 2: Flood Risk Consultant Qual Pending Imple 2022-10-2 2022-12-0 2023-01-0 2023-02-0 2023-05-0 / Consultancy Services for IBRD / 89960 Mitigation Investments in Post ification Selecti Open - National 25,000.00 0.00 2022-09-30 mentation 1 4 3 7 8 Socio-economic Survey for the lower Kelani basin on Wee Oya Reservoir SLMOI/CRES/DMC/C/CQS/ 12 / Comprehensive Study Component 1: Forecasting Consultant Qual on Data Availability, poten and Early Warning of High Pending Imple 2022-11-0 2022-12-2 2023-01-2 2023-02-2 2023-08-2 IBRD / 89960 Post ification Selecti Open - National 44,000.00 0.00 2022-10-17 tial Application of Spatial a Impact Weather, Floods a mentation 7 1 0 4 3 on nd non spatial data for DR nd Landslides M and development of gov ernance mechanism for uti lization SLMOI/CRES/ID/C/CQS/10 Component 1: Forecasting Consultant Qual / Developing a cloud-base and Early Warning of High 2022-10-0 2022-09-2 2022-10-2 2022-11-2 2023-05-2 IBRD / 89960 Post ification Selecti Limited 28,000.00 0.00 Canceled 2022-08-31 d Web Portal for archiving Impact Weather, Floods a 5 0 0 4 3 on and displaying data gather nd Landslides ed from various systems SLMOI/CRES/ID/C/QCBS/0 Component 2: Flood Risk Quality And Cos Pending Imple 2023-02-0 2023-03-2 2023-04-1 2023-05-1 2023-06-2 2023-07-2 2024-01-2 3 / Preparation of Environ IBRD / 89960 Mitigation Investments in Post t-Based Selectio Open - National 225,000.00 0.00 2023-01-16 mentation 6 2 9 9 3 8 4 mental Impact Assessmen the lower Kelani basin n ts for Wee Oya Reservoir SLMOI/CRES/ID/C/QCBS/0 Component 2: Flood Risk Quality And Cos 5 / Consultancy Service for Open - Internatio Under Impleme 2022-10-1 2022-10-1 2022-10-2 2022-12-2 2023-05-1 2023-01-2 2023-07-1 2023-03-2 2023-09-2 2023-05-0 2023-07-0 2026-05-1 IBRD / 89960 Mitigation Investments in Prior t-Based Selectio 2,500,000.00 0.00 2022-09-12 Design Review and Constr nal ntation 2 2 0 6 5 5 9 6 6 9 7 3 the lower Kelani basin n uction Supervision of Salini ty Barrier at Ambatale SLMOI/CRES/ID/C/QCBS/0 Component 2: Flood Risk Quality And Cos Pending Imple 2023-02-0 2023-03-2 2023-04-1 2023-05-1 2023-06-2 2023-07-2 2024-04-2 2 / Preparation of Resettle IBRD / 89960 Mitigation Investments in Post t-Based Selectio Open - National 220,000.00 0.00 2023-01-16 mentation 6 2 9 9 3 8 3 ment Action Plan for Wee the lower Kelani basin n Oya Reservoir SLMOI/CRES/PCT/C/CQS/2 Consultant Qual 4 / Developing of the Web Component 4: Project Ma 2023-02-1 2022-09-2 2023-03-2 2022-10-2 2022-12-0 2023-06-0 IBRD / 89960 Post ification Selecti Limited 25,000.00 0.00 Canceled 2022-09-15 Based Management Inform nagement 3 9 7 9 3 1 on ation System (MIS) for CRe sMPA SLMOI/CRES/ID/C/CQS/06 Component 2: Flood Risk Consultant Qual Under Impleme 2022-11-0 2022-10-0 2022-11-0 2022-12-0 2023-04-0 / Biodiversity Assessment f IBRD / 89960 Mitigation Investments in Post ification Selecti Limited 30,000.00 0.00 2022-09-15 ntation 1 5 4 9 8 or Wee Oya Reservoir Area the lower Kelani basin on SLMOI/CRES/ID/C/CQS/29 Component 2: Flood Risk Consultant Qual Pending Imple 2023-01-1 2023-03-1 2023-05-1 2026-08-2 / Hiring of Consultants for IBRD / 89960 Mitigation Investments in Post ification Selecti Limited 40,000.00 0.00 2022-12-15 mentation 4 5 5 7 Dam Safety Review Panel f the lower Kelani basin on or Wee Oya Reservoir SLMOI/CRES/ID/C/QCBS/0 Component 2: Flood Risk Quality And Cos 1 / Preparation of Detail En Open - Internatio 2022-10-1 2022-10-1 2022-10-2 2023-02-1 2023-02-2 2023-04-2 2023-06-2 2023-07-2 2024-04-1 IBRD / 89960 Mitigation Investments in Prior t-Based Selectio 3,500,000.00 0.00 Canceled 2022-09-15 gineering Design and Biddi nal 1 5 0 2 6 7 5 3 8 the lower Kelani basin n ng Document for Wee Oya Reservoir SLMOI/CRES/DOM/C/QCBS Component 1: Forecasting /30 / Consultancy Services Quality And Cos and Early Warning of High Open - Internatio 2023-01-3 2023-03-1 2023-04-1 2023-05-1 2023-06-1 2023-07-2 2024-07-2 for Systems Integration for IBRD / 89960 Prior t-Based Selectio 3,000,000.00 0.00 Canceled 2023-01-10 Impact Weather, Floods a nal 1 6 3 3 7 2 1 the Modernization of the D n nd Landslides epartment of Meteorology, Sri Lanka Page 13 SLMOI/CRES/DOM/C/QCBS Component 1: Forecasting /30-2 / Consultancy Servic Quality And Cos and Early Warning of High Open - Internatio Under Impleme 2023-06-0 2023-07-0 2023-06-2 2023-08-1 2023-09-1 2023-10-1 2023-11-1 2023-12-2 2026-12-3 es for Systems Integration IBRD / 89960 Prior t-Based Selectio 3,000,000.00 0.00 2023-06-12 Impact Weather, Floods a nal ntation 7 3 3 6 3 3 7 2 1 for the Modernization of th n nd Landslides e Department of Meteorol ogy, Sri Lanka SLMOI/CRES/ID/C/QCBS/0 Component 2: Flood Risk Quality And Cos 1-3 / Preparation of Detail Open - Internatio 2023-07-1 2023-08-0 2023-12-0 2023-12-1 2024-02-1 2024-04-1 2024-05-1 2025-06-1 IBRD / 89960 Mitigation Investments in Prior t-Based Selectio 2,400,000.00 0.00 Under Review 2023-07-05 Engineering Design and Bi nal 8 4 2 6 4 3 1 1 the lower Kelani basin n dding Document for Wee Oya Reservoir SLMOI/CRES/ID/C/QCBS/0 Component 2: Flood Risk Quality And Cos 1-2 / Preparation of Detail Open - Internatio 2023-07-1 2023-11-0 2023-11-2 2024-01-2 2024-03-2 2024-04-1 2025-02-1 IBRD / 89960 Mitigation Investments in Prior t-Based Selectio 2,400,000.00 0.00 Canceled 2023-06-12 Engineering Design and Bi nal 2 9 3 2 1 8 2 the lower Kelani basin n dding Document for Wee Oya Reservoir SLMOI/CRES/DOM/C/QCBS Component 1: Forecasting /30-3 / Consultancy Servic Quality And Cos and Early Warning of High Open - Internatio Under Impleme 2023-08-0 2023-08-2 2023-08-1 2023-10-0 2023-11-0 2023-12-0 2024-01-0 2024-02-1 2026-12-3 es for Systems Integration IBRD / 89960 Prior t-Based Selectio 3,000,000.00 0.00 2023-08-04 Impact Weather, Floods a nal ntation 4 5 1 8 5 5 9 3 1 for the Modernization of th n nd Landslides e Department of Meteorol ogy, Sri Lanka SLMOI/CRES/PCT/C/QCBS/ 31 / Consultancy Service f or Design, Developing, Inst Quality And Cos Component 4: Project Ma 2023-10-2 2023-09-0 2023-10-1 2023-11-1 2023-12-1 2024-01-1 2024-02-2 2024-07-1 all & Maintain a Web-base IBRD / 89960 Post t-Based Selectio Open - National 65,000.00 0.00 Under Review 2023-08-14 nagement 3 4 8 5 5 9 3 2 d Management Informatio n n System and GIS Applicati on for Climate Resilience Multiphase Programmatic Approach (CResMPA) SLMOI/CRES/DMC/C/CQS/ Component 1: Forecasting 18 / Engineering assistanc Consultant Qual and Early Warning of High 2022-10-0 2022-11-0 2022-12-0 2023-06-0 e for the architectural and IBRD / 89960 Post ification Selecti Limited 20,000.00 0.00 Canceled 2022-09-19 Impact Weather, Floods a 3 2 7 5 interior designing of EOC c on nd Landslides onsidering the maximum u tilization of the existing re sources SLMOI/CRES/DMC/C/QCBS Component 1: Forecasting /18 / Engineering Assistan Quality And Cos and Early Warning of High Pending Imple 2023-11-0 2023-12-2 2024-01-1 2024-02-1 2024-03-2 2024-04-2 2025-04-2 ce for the Architectural an IBRD / 89960 Post t-Based Selectio Open - National 22,000.00 0.00 2023-10-16 Impact Weather, Floods a mentation 6 0 7 6 2 6 6 d Interior Designing of EO n nd Landslides C Considering the Maximu m Utilization of the Existin g Resources SLMOI/CRES/ID/C/QCBS/3 Component 1: Forecasting Quality And Cos 8 / Developing a Cloud-Bas and Early Warning of High Pending Imple 2023-12-0 2024-01-1 2024-02-1 2024-03-1 2024-04-1 2024-05-2 2025-02-1 IBRD / 89960 Post t-Based Selectio Open - National 50,000.00 0.00 2023-11-10 ed Web Portal for Archivin Impact Weather, Floods a mentation 1 4 1 2 6 1 5 n g and Displaying Data Gat nd Landslides hered from Various Syste ms INDIVIDUAL CONSULTANTS Activity Reference No. Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co / Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MAREALIFA-302011-CS Component 1: Forecasting -INDV / Cres/ID/C/IC/26 - In and Early Warning of High Individual Cons 2022-07-2 2022-08-1 2022-09-1 2023-03-1 dividual consultant for ICT IBRD / 89960 Post Limited 8,000.00 0.00 Canceled 2022-07-15 Impact Weather, Floods a ultant Selection 0 0 4 3 infrastructure developmen nd Landslides t of flood monitoring and o peration room SLMOI/CRES/ID/C/IC/26 / I Component 1: Forecasting ndividual consultant for IC and Early Warning of High Individual Cons 2022-09-1 2022-09-0 2022-11-0 2022-09-2 2023-03-0 2022-10-2 2023-04-0 2023-04-2 IBRD / 89960 Post Limited 8,000.00 0.00 Signed 2022-08-29 T infrastructure developm Impact Weather, Floods a ultant Selection 4 3 1 4 2 9 3 7 ent of flood monitoring an nd Landslides d operation room SLMOI/CRES/PCT/C/DS/23 / Consortium Architectural Component 1: Forecasting Consultancy Services of Pr and Early Warning of High Pending Imple 2022-11-2 2023-01-2 2024-08-0 IBRD / 89960 Post Direct Selection Direct - National 47,000.00 0.00 2022-11-15 oposed Disaster Risk Redu Impact Weather, Floods a mentation 5 9 1 ction Observation, Forecas nd Landslides ting and Communication H ubs for Department of Met eorology SLMOI/CRES/PCT/C/DS/25 Component 1: Forecasting Pending Imple 2022-09-2 2022-11-3 2023-08-2 / Hiring of Local Expert - IC IBRD / 89960 and Early Warning of High Post Direct Selection Direct - National 6,400.00 0.00 2022-09-16 mentation 6 0 7 T Impact Weather, Floods a nd Landslides SLMOI/CRES/ID/C/DS/27 / Consultancy Services for u Component 2: Flood Risk Under Impleme 2023-05-2 2023-02-1 2023-04-2 2026-03-1 pdating the Environmental IBRD / 89960 Mitigation Investments in Post Direct Selection Direct - National 25,000.00 0.00 2023-02-01 ntation 5 1 8 5 and Social Impact Assess the lower Kelani basin ment for Ambathale Salini ty Barrier SLMOI/CRES/DMC/C/IC/32 / Individual consultant for Component 1: Forecasting Enhancing Institutional Ca and Early Warning of High Individual Cons Pending Imple 2023-09-0 2023-09-2 2023-10-2 2024-08-2 IBRD / 89960 Post Limited 16,200.00 0.00 2023-08-28 pacity and Existing Inform Impact Weather, Floods a ultant Selection mentation 2 3 8 3 ation Systems for Disaster nd Landslides Risk Reduction and Respo nse at Disaster Manageme nt Centre SLMOI/CRES/DMC/C/IC/33 Component 1: Forecasting / Individual Consultant (Re and Early Warning of High Individual Cons Under Impleme 2023-10-0 2023-10-1 2023-10-2 2023-11-0 2024-10-3 mote Sensing and GIS) for IBRD / 89960 Post Limited 3,200.00 0.00 2023-09-22 Impact Weather, Floods a ultant Selection ntation 5 7 2 1 1 Establishing the Exposure nd Landslides and Vulnerability Databas e at Disaster Management Centre SLMOI/CRES/PCT/C/IC/34 / Individual Consultant (Res Component 4: Project Ma Individual Cons Under Impleme 2023-10-0 2023-10-1 2023-10-2 2023-11-0 2024-10-3 IBRD / 89960 Post Limited 4,400.00 0.00 2023-09-22 ettlement Mobilization) for nagement ultant Selection ntation 4 7 2 1 1 the Social and Resettleme nt Unit - CResMPA SLMOI/CRES/PCT/C/IC/35 / Individual Consultant (Soci Component 4: Project Ma Individual Cons 2023-10-2 2023-10-1 2023-10-2 2023-11-0 2024-10-3 IBRD / 89960 Post Limited 4,400.00 0.00 Under Review 2023-09-22 al Mobilization) for the Soc nagement ultant Selection 5 7 2 1 1 ial and Resettlement Unit - CResMPA SLMOI/CRES/PCT/C/IC/36 / Individual Consultant (Soci Component 4: Project Ma Individual Cons 2023-10-2 2023-10-1 2023-10-2 2023-11-0 2024-10-3 IBRD / 89960 Post Limited 4,400.00 0.00 Under Review 2023-09-22 al Safeguard) for the Socia nagement ultant Selection 5 7 2 1 1 l and Resettlement Unit - CResMPA SLMOI/CRES/PCT/C/IC/37 / Individual Consultant for Fi Component 4: Project Ma Individual Cons Pending Imple 2023-10-1 2023-10-2 2023-11-0 2024-10-3 IBRD / 89960 Post Limited 2,000.00 0.00 2023-09-22 nancial Database and MIS nagement ultant Selection mentation 7 2 1 1 Operator for Accounts Divi sion - CResMPA SLMOI/CRES/DMC/C/DS/39 Component 1: Forecasting / Individual Consultant (Re and Early Warning of High Individual Cons Pending Imple 2023-11-0 2023-11-2 2024-01-0 2024-12-3 IBRD / 89960 Post Direct - National 3,200.00 0.00 2023-10-27 mote Sensing and GIS) for Impact Weather, Floods a ultant Selection mentation 6 7 1 1 Data Base Development a nd Landslides nd Analysis Page 14