Procurement Plan I. General 1. Project Information Country: Tanzania Project Name: Resilient Natural Resources Management for Growth Project Project ID: P150523 2. Project Implementation Agency: Ministry of Natural Resources and Tourism (MNRT) Tanzania National Parks (TANAPA) Tanzania Wildlife Management Authority (TAWA) National Irrigation Commission (NIrC) Rufiji Basin Water Board (RBWB) 3. Date of the Procurement Plan: June 2017 4. Period Covered by this Procurement Plan: First 18 Months Procurement Plan II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ Prior Review millions) Category (US$ Open Open Request for millions) International National Quotation (RfQ) Works ≥5 ≥ 15.0 < 15 < 0.2 Goods, IT, and non- ≥1.5 ≥5 <5 < 0.1 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ (US$ million) millions) Consulting Engineering and Services Construction Supervision Consultants ≥ 0.5 <0.3 < 0.3 (Firms) Individual ≥ 0.2 NA. NA. 1 Consultants [Overall Project Procurement Risk is HIGH] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 2 III. Packages for Goods, Works and Non-Consulting Services Sr./ No Contract Description Estimate Review Market Selection Evaluation Procurement Prequa Domesti Expected Expected d Cost by Bank Approach Method Options Process: lificatio c date of date of (US$) (Prior/Pos (Open- (RFP, RFB, (BAFO, (Single/Multipl n Preferen bid/ Contract t) National/ RFQ, DS Rated e Stages; (Yes/ ce proposal Signature International etc.) Criteria One/Two No) (Yes/No) opening Limited etc.) etc.) Envelopes etc) Goods Works Non-Consulting Services 3 I. Packages for Consulting Services Sr. No Contract Description Estimated Review Market Selection Shortlisti Expected date of Expected date Cost (US$) by Bank Approach Method ng bid/ proposal of Contract (Prior/Pos (Open- (QCBS, FBBS, (Yes/ No) opening Signature t) National/ LCBS, QBS, International CQS, DS etc.) Limited etc.) 4 PROCUREMENT Tanzania : Tanzania: Resilient Natural Resource Management for Tourism and Growth PLAN General Information Country: Tanzania 2018-04-09 Bank’s Approval Date of the Original Procurement Plan: 2022-09-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150523 GPN Date: 2018-08-17 Project Name: Tanzania: Resilient Natural Resource Management for Tourism and Growth Loan / Credit No: IDA / 61430 Tanzania National Parks Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TANAPA-135732-CW-RFB / Construction of Roads,Trails 1. Strengthen management Single Stage - One E 2021-03-2 and associated drainage stru IDA / 61430 and improve infrastructure i Post Request for Bids Open - National 0.00 Canceled 2020-06-10 2020-06-15 2020-07-27 2020-08-26 2020-09-30 nvelope 9 ctures in Ruaha, Mikumi and n priority Protected Areas Udzungwa National Parks TZ-TANAPA-135738-CW-RFB / Construction of building for ranger posts, tourist arrival a 1. Strengthen management menities, entry/exit gates, vi Single Stage - One E 2021-04-0 IDA / 61430 and improve infrastructure i Post Request for Bids Open - National 0.00 Canceled 2020-06-18 2020-06-23 2020-08-04 2020-09-03 2020-10-08 sitor information centers, you nvelope 6 n priority Protected Areas th hostels, rest houses, and b andas and workshop and eco logical monitoring in Ruaha, Mikumi and Udzungwa Natio nal Parks. TZ-TANAPA-135741-CW-RFB 1. Strengthen management / Upgrading of existing airstri Single Stage - One E 2021-06-0 IDA / 61430 and improve infrastructure i Post Request for Bids Open - National 0.00 Canceled 2020-08-20 2020-08-25 2020-10-06 2020-11-05 2020-12-10 ps in Ruaha, Mikumi and Nye nvelope 8 n priority Protected Areas rere National Parks TZ-TANAPA-303894-CW-RFB / Construction and Upgrading of Airstrips in Mikumi, Nyerer e, and Ruaha National Parks. Request for B 1. Strengthen management ids - Small W Lot 1: Construction and Upgr IDA / 61430 Open - Internationa Single Stage - One E Under Imple 2023-05-2 and improve infrastructure i Prior Request for Bids orks SPD (1 e 0.00 2022-08-02 2022-07-28 2022-08-07 2022-08-01 2022-09-18 2022-10-18 2022-11-22 ading of Kikoboga Airstrip in l nvelope mentation 1 n priority Protected Areas nvelope proc Mikumi National Park. ess) & Lot 2: Construction and Upgr ading of Mtemere and Kibam bawe Airstrips in Nyerere Nat i TZ-TANAPA-303898-CW-RFB / Construction and Upgrading of Airstrips in Mikumi, Nyerer Request for B e, and Ruaha National Parks. 1. Strengthen management ids - Works ( Open - Internationa Single Stage - One E Under Imple 2023-05-2 IDA / 61430 and improve infrastructure i Prior Request for Bids without preq 0.00 2022-08-02 2022-07-28 2022-08-07 2022-08-01 2022-09-18 2022-10-18 2022-11-22 Package B: Construction and l nvelope mentation 1 n priority Protected Areas ualification) Upgrading of three (3) Airstri SPD ps (Ulanga, Kiganga & Jongo mero) in Ruaha National Park . Request for B TZ-TANAPA-315619-CW-RFB 1. Strengthen management ids - Small W / Construction of Radio Com Single Stage - One E Pending Imp 2023-07-2 IDA / 61430 and improve infrastructure i Post Request for Bids Open - National orks SPD (1 e 0.00 2022-09-30 2022-10-14 2022-11-25 2022-12-25 2023-01-29 munications Towers at Ruaha nvelope lementation 8 n priority Protected Areas nvelope proc , Mikumi and Udzungwa Nati ess) onal Parks. TZ-TANAPA-316214-CW-RFB / Procurement of Contractor f or Construction of Building(s) Request for B Infrastructure for Staff and T 1. Strengthen management ids - Small W ourist Amenities for Ruaha, M Open - Internationa Single Stage - One E Pending Imp 2024-04-2 IDA / 61430 and improve infrastructure i Prior Request for Bids orks SPD (1 e 0.00 2022-10-03 2022-10-10 2022-11-21 2022-12-21 2023-01-25 ikumi, Udzungwa Mountains l nvelope lementation 5 n priority Protected Areas nvelope proc and Nyerere National Parks. ess) LOT 1:MIKUMI NP LOT 2:NYERERE NP LOT 3:RUAHA NP LOT 4: UDZUNGWA NP GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 2. Strengthen alternative liv TZ-TANAPA-57583-GO-RFQ / elihoods for targeted comm Request for Quota Single Stage - One E Supply of IT and Office equip IDA / 61430 Post Limited 37,600.70 Completed 2018-09-11 2018-10-10 2018-11-06 2019-01-07 2019-05-05 2020-01-08 unities in proximity to the pr tions nvelope ment iority Protected Areas TZ-TANAPA-40964-GO-RFQ / Procurement of Office suppli 4. Project management, insti es (toners, paper, pens, stapl tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Canceled 2018-09-11 2018-11-06 2019-05-05 ers and other consumables)O ty assurance and control, an tions nvelope ffice supplies (toners, paper, d monitoring and evaluation pens, staplers and other cons umables) TZ-TANAPA-40813-GO-RFB / 1. Strengthen management Single Stage - One E Supply of patrol equipment f IDA / 61430 and improve infrastructure i Post Request for Bids Open - National 527,576.78 Completed 2018-09-13 2018-11-27 2018-09-18 2018-12-03 2018-10-30 2018-12-28 2018-11-29 2019-08-15 2019-01-03 2019-04-23 2019-07-02 2019-12-13 nvelope or RUNAPA,MINAPA & UMNP n priority Protected Areas 2. Strengthen alternative liv TZ-TANAPA-57441-GO-RFQ / elihoods for targeted comm Request for Quota Single Stage - One E IDA / 61430 Post Limited 19,329.82 Completed 2018-09-11 2018-09-14 2018-11-06 2018-12-31 2019-05-05 2019-01-02 Supply of furniture unities in proximity to the pr tions nvelope iority Protected Areas 1. Strengthen management TZ-TANAPA-59924-GO-RFB / Open - Internationa Single Stage - One E IDA / 61430 and improve infrastructure i Prior Request for Bids 0.00 Canceled 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 Supply of Heavy equipment l nvelope n priority Protected Areas 1. Strengthen management TZ-TANAPA-59915-GO-DIR / IDA / 61430 and improve infrastructure i Prior Direct Selection Direct 0.00 Canceled 2018-05-16 2018-05-21 2018-06-25 2018-12-22 Supply of Motor Vehicles n priority Protected Areas Page 1 1. Strengthen management TZ-TANAPA-89480-GO-DIR / IDA / 61430 and improve infrastructure i Prior Direct Selection Direct 5,135,218.01 Signed 2018-12-10 2019-05-06 2018-12-15 2019-06-25 2019-01-19 2020-09-21 2019-07-18 Supply of Heavy equipment n priority Protected Areas TZ-TANAPA-111426-GO-UN / 1. Strengthen management UN Agencies (Dire Procurement of Motor Vehicl IDA / 61430 and improve infrastructure i Prior Direct 1,305,438.00 Completed 2019-04-23 2019-05-02 2019-04-28 2019-09-02 2019-06-02 2020-02-28 2019-11-29 2021-04-22 ct) es n priority Protected Areas TZ-TANAPA-57606-GO-RFB / 1. Strengthen management Single Stage - One E Supply of equipment for co IDA / 61430 and improve infrastructure i Post Request for Bids Open - National 0.00 Canceled 2018-05-01 2018-05-06 2018-06-17 2018-07-17 2018-08-21 2019-02-17 nvelope mmunication system for TAN n priority Protected Areas APA TZ-TANAPA-135704-GO-DIR / 1. Strengthen management Upgrading of Radio Commun IDA / 61430 and improve infrastructure i Post Direct Selection Direct 0.00 Canceled 2020-01-13 2020-01-30 2020-01-18 2020-02-22 2020-08-20 ication systems in Ruaha, Mi n priority Protected Areas kumi and Udzungwa National Parks TZ-TANAPA-170905-GO-RFB 1. Strengthen management / Procurement of Patrol Eque Single Stage - One E IDA / 61430 and improve infrastructure i Post Request for Bids Open - National 0.00 Canceled 2020-05-15 2021-03-11 2020-05-20 2021-03-11 2020-07-01 2021-04-08 2020-07-31 2021-04-23 2020-09-04 2021-03-03 pment and Rangers Uniforms nvelope n priority Protected Areas for Nyerere National Park TZ-TANAPA-170901-GO-DIR / 1. Strengthen management Procurement of Heavy Plant f IDA / 61430 and improve infrastructure i Prior Direct Selection Direct 0.00 Canceled 2020-05-15 2020-05-11 2020-05-20 2020-06-24 2020-12-21 or Nyerere National Park n priority Protected Areas TZ-TANAPA-172208-GO-UN / 1. Strengthen management UN Agencies (Dire Procurement of Motor Vehicl IDA / 61430 and improve infrastructure i Prior Direct 0.00 Canceled 2020-06-03 2020-05-11 2020-06-08 2020-07-13 2021-01-09 ct) es for Nyerere National Park n priority Protected Areas TZ-TANAPA-172209-GO-RFQ 2. Strengthen alternative liv / Procurement of Office and I elihoods for targeted comm Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Canceled 2020-06-27 2020-08-31 2020-08-22 2021-02-18 T Equipment for Nyerere Nati unities in proximity to the pr tions nvelope onal Park iority Protected Areas TZ-TANAPA-221842-GO-RFQ 4. Project management, insti / Procurement of IT and Offic tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 45,062.83 Completed 2021-03-17 2021-04-20 2021-05-12 2021-06-02 2021-11-08 2021-06-23 e equipment for Nyerere Nati ty assurance and control, an tions nvelope onal Park d monitoring and evaluation TZ-TANAPA-233158-GO-RFB 1. Strengthen management / Procurement of Rangers Uni Single Stage - One E IDA / 61430 and improve infrastructure i Post Request for Bids Open - National 300,346.39 Signed 2021-05-11 2021-05-19 2021-05-16 2021-05-19 2021-06-27 2021-06-15 2021-07-27 2021-06-21 2021-08-31 2021-09-21 2022-02-27 form and Patrol equipment fo nvelope n priority Protected Areas r Nyerere National Park TZ-TANAPA-239088-GO-DIR / PROCUREMENT OF TRACTOR 1. Strengthen management S AND ACCESSORIES FOR RU IDA / 61430 and improve infrastructure i Post Direct Selection Direct 462,690.36 Signed 2021-06-14 2021-06-14 2021-06-18 2021-09-17 2021-07-23 2022-01-31 2022-01-19 AHA, NYERERE, MIKUMI AND n priority Protected Areas UDZUNGWA NATIONAL PARK S 4. Project management, insti TZ-TANAPA-241613-GO-RFQ tutional strengthening, quali Request for Quota Single Stage - One E / PROCUREMENT OF LAPTOPS IDA / 61430 Post Limited 16,223.13 Completed 2021-07-20 2021-12-10 2021-09-14 2022-03-02 2022-03-13 2022-04-04 ty assurance and control, an tions nvelope FOR TANAPA PIU d monitoring and evaluation TZ-TANAPA-241704-GO-DIR / 1. Strengthen management PROCUREMENT OF TRUCKS F IDA / 61430 and improve infrastructure i Prior Direct Selection Direct 6,425,270.00 Signed 2021-07-15 2021-07-25 2021-07-20 2021-10-26 2021-08-24 2022-01-31 2022-02-20 OR NYERERE,RUAHA, UDZUN n priority Protected Areas GWA AND MIKUMI NATIONAL PARK TZ-TANAPA-273231-GO-RFQ 2. Strengthen alternative liv / PROCUREMENT OF IT EQUE elihoods for targeted comm Request for Quota Single Stage - One E Pending Impl IDA / 61430 Post Limited 0.00 2022-02-07 2022-04-04 2022-10-01 PMENT FOR COMPONENT 2 C unities in proximity to the pr tions nvelope ementation OORDINATION OFFICE iority Protected Areas TZ-TANAPA-273233-GO-RFQ 2. Strengthen alternative liv / PROCUREMENT OF FURNITU elihoods for targeted comm Request for Quota Single Stage - One E Pending Impl IDA / 61430 Post Limited 0.00 2022-02-07 2022-04-04 2022-10-01 RE FOR COMPONENT 2 COOR unities in proximity to the pr tions nvelope ementation DINATION OFFICE iority Protected Areas TZ-TANAPA-273497-GO-DIR / 2. Strengthen alternative liv PROCUREMENT OF 188 META elihoods for targeted comm IDA / 61430 Post Direct Selection Direct 32,316.45 Completed 2022-02-28 2022-03-23 2022-03-05 2022-04-14 2022-04-09 2022-06-02 2022-10-06 2022-07-04 L BOXESFOR COCOBA GROU unities in proximity to the pr PS iority Protected Areas TZ-TANAPA-303899-GO-RFB 1. Strengthen management Single Stage - One E Under Imple / PROCUREMENT OF TWO AIR IDA / 61430 and improve infrastructure i Post Request for Bids Open - National 0.00 2022-08-02 2022-09-24 2022-08-07 2022-09-24 2022-09-18 2022-10-18 2022-11-22 2023-05-21 nvelope mentation BOAT FOR RUAHA NATIONAL n priority Protected Areas PARK TZ-TANAPA-303915-GO-DIR / 1. Strengthen management PROCUREMENT OF SIX LIGHT Direct - Internation Pending Impl IDA / 61430 and improve infrastructure i Post Direct Selection 0.00 2022-08-31 2022-09-05 2022-10-10 2023-04-08 VEHICLES FOR SAFEGUARD A al ementation n priority Protected Areas ND COMP 2 ACTIVITIES NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TANAPA-264073-NC-RFQ 4. Project management, insti / REINFORCEMENT & PAINTIN tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Canceled 2021-11-28 2022-01-23 2022-07-22 G OF 32 PA's REGROW VEHIC ty assurance and control, an tions nvelope LES d monitoring and evaluation TZ-TANAPA-303935-NC-RFB 4. Project management, insti / REINFORCEMENT AND PAIN tutional strengthening, quali Single Stage - One E Pending Impl IDA / 61430 Post Request for Bids Open - National 0.00 2022-08-02 2022-08-07 2022-09-18 2022-10-18 2022-11-22 2023-05-21 TING OF REGROW VEHICLES ty assurance and control, an nvelope ementation & TRUCKS d monitoring and evaluation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 TZ-TANAPA-40673-CS-QCBS / Design, Preparation of Biddi 1. Strengthen management Quality And Cost- Open - Internationa ng Documents and Construct IDA / 61430 and improve infrastructure i Prior 1,020,700.00 Signed 2018-05-01 2018-06-14 2018-05-22 2018-12-06 2018-07-05 2019-08-01 2018-08-02 2019-09-30 2018-09-01 2020-04-14 2018-10-06 2020-08-04 2018-11-10 2020-10-16 2019-11-10 Based Selection l ion Supervision roads, bridge n priority Protected Areas s and trails in Ruaha, Mikumi, Udzungwa and Selous TZ-TANAPA-41049-CS-QCBS / Consultancy Services For Th 3. Strengthen landscape ma e Environmental And nagement and infrastructure Quality And Cost- Open - Internationa Social Impact Assessment St IDA / 61430 investments in and upstrea Post 0.00 Canceled 2018-05-01 2018-05-22 2018-07-05 2018-08-02 2018-09-01 2018-10-06 2018-11-10 2019-11-10 Based Selection l udy Of Regrow-Financed Infr m of the Ruaha National Par astructure k For Ruaha, Mikumi, Udzungw a National Parks TZ-TANAPA-59929-CS-QCBS / Design, Preparation of Biddi 1. Strengthen management ng Documents and Construct Quality And Cost- Open - Internationa IDA / 61430 and improve infrastructure i Prior 1,041,262.95 Signed 2018-09-13 2018-11-29 2018-10-04 2018-12-06 2018-11-17 2019-10-15 2018-12-15 2020-02-25 2019-01-14 2020-04-29 2019-02-18 2020-08-04 2019-03-25 2020-10-16 2020-03-24 ion Supervision of the Buildin Based Selection l n priority Protected Areas gs and facilities in Ruaha, Mi kumi & Udzungwa National P ark TZ-TANAPA-89472-CS-QCBS / Consultancy Services For Th 1. Strengthen management e Environmental And Social I Quality And Cost- Open - Internationa IDA / 61430 and improve infrastructure i Prior 609,620.45 Signed 2018-12-05 2018-12-05 2018-12-26 2018-12-06 2019-02-08 2019-10-16 2019-03-08 2019-12-13 2019-04-07 2020-04-27 2019-05-12 2020-08-26 2019-06-16 2020-11-30 2020-06-15 mpact Assessment Study Of Based Selection l n priority Protected Areas Regrow-Financed Infrastructu re For Ruaha, Mikumi, Udzun gwa National Parks TZ-TANAPA-113093-CS-QCB S / Consultancy services for f easibility study, detailed engi 1. Strengthen management Quality And Cost- Open - Internationa neering design and preparati IDA / 61430 and improve infrastructure i Post 892,929.77 Signed 2019-05-06 2019-05-05 2019-05-27 2019-05-05 2019-07-10 2019-10-22 2019-08-07 2019-12-10 2019-09-06 2020-04-17 2019-10-11 2020-11-30 2019-11-15 2020-12-11 2020-11-14 Based Selection l on of tender documents for r n priority Protected Areas ehabilitation of airstrips to gr avel standard for Ruaha and Mikumi National Parks TZ-TANAPA-170903-CS-QCB S / Conduct Enviromental an 1. Strengthen management Quality And Cost- Open - Internationa d social impact assessment ( IDA / 61430 and improve infrastructure i Post 112,779.95 Signed 2020-05-15 2020-05-19 2020-06-05 2020-06-19 2020-07-19 2021-02-02 2020-08-16 2021-03-01 2020-09-15 2021-03-19 2020-10-20 2021-04-28 2020-11-24 2021-08-26 2021-11-24 Based Selection l ESIA) study of REGROW finan n priority Protected Areas ced infrastructure for Nyerer e National Park TZ-TANAPA-188910-CS-QCB S / Consultancy services for 2. Strengthen alternative liv providing technical support t elihoods for targeted comm Quality And Cost- Open - Internationa he implementation of the RE IDA / 61430 Post 0.00 Canceled 2020-08-18 2020-08-24 2020-09-08 2020-10-22 2020-11-19 2020-12-19 2021-01-23 2021-02-27 2022-02-27 unities in proximity to the pr Based Selection l GROW Project- Strengthen al iority Protected Areas ternative livelihoods for targe ted communities in proximity to PA's TZ-TANAPA-193863-CS-CQS / Consultancy services for co 1. Strengthen management ncept design and financial vi Consultant Qualifi IDA / 61430 and improve infrastructure i Post Open - National 64,487.00 Completed 2020-09-21 2020-09-14 2020-10-12 2021-01-25 2020-11-25 2021-03-29 2020-12-25 2021-06-02 2021-01-29 2021-06-16 2021-07-28 2022-04-12 ability (business plan for the cation Selection n priority Protected Areas southern circuit tourism desti nation market center at Iring a TZ-TANAPA-209992-CS-QCB S / PROVSION OF CONSULTA NCY SERVICES FOR SUPERVI 1. Strengthen management SION OF CONSTRUCTION OF Quality And Cost- Open - Internationa IDA / 61430 and improve infrastructure i Post 0.00 Canceled 2020-12-22 2020-12-20 2021-01-12 2021-02-25 2021-03-25 2021-04-24 2021-05-29 2021-07-03 2022-07-03 BUILDING INFRASTRUCTURE Based Selection l n priority Protected Areas FOR STAFF AND TOURIST AM ENITIES FOR RUAHA, UDZUN GWA,MIKUMI AND NYERERE NATIONAL PARKS TZ-TANAPA-209989-CS-QCB S / PROVISION OF CONSULTA NCY SERVICES FOR SUPERVI 1. Strengthen management SION FOR REHABILITATION O Quality And Cost- Open - Internationa IDA / 61430 and improve infrastructure i Post 0.00 Canceled 2020-12-22 2021-01-26 2021-01-12 2021-02-25 2021-03-25 2021-04-24 2021-05-29 2021-07-03 2022-07-03 F ROADS (2051KM) AND TRAI Based Selection l n priority Protected Areas LS (132.5KM) TO GRAVEL ST ANDARD FOR RUAHA,MIKUMI ,NYERERE AND UDZUNGWA NATIONAL PARKS TZ-TANAPA-211046-CS-CQS / PROVISION OF CONSULTAN 1. Strengthen management CY SERVICES FOR SUPERVISI Consultant Qualifi IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2020-12-22 2021-01-26 2021-01-12 2021-02-25 2021-03-27 2021-05-01 2021-10-28 ON OF REHABILITATION OF AI cation Selection n priority Protected Areas RSTRIPS TO GRAVEL STANDA RD FOR RUAHA, MIKUMI AND NYERERE NATIONAL PARKS TZ-TANAPA-253929-CS-QCB S / PROVSION OF CONSULTA NCY SERVICES FOR SUPERVI 1. Strengthen management SION OF CONSTRUCTION OF Quality And Cost- Open - Internationa Under Implement IDA / 61430 and improve infrastructure i Prior 0.00 2021-09-20 2021-10-26 2021-10-11 2021-10-27 2021-11-24 2022-07-26 2021-12-22 2022-09-14 2022-01-21 2022-02-25 2022-04-01 2023-04-01 BUILDING INFRASTRUCTURE Based Selection l ation n priority Protected Areas FOR STAFF AND TOURIST AM ENITIES FOR RUAHA, UDZUN GWA,MIKUMI AND NYERERE NATIONAL PARKS TZ-TANAPA-253933-CS-QCB S / PROVISION OF CONSULTA NCY SERVICES FOR SUPERVI 1. Strengthen management SION FOR REHABILITATION O Quality And Cost- Open - Internationa Under Implement IDA / 61430 and improve infrastructure i Prior 0.00 2021-09-20 2021-10-26 2021-10-11 2021-10-27 2021-11-24 2021-12-22 2022-01-21 2022-02-25 2022-04-01 2023-04-01 F ROADS (2051KM) AND TRAI Based Selection l ation n priority Protected Areas LS (132.5KM) TO GRAVEL ST ANDARD FOR RUAHA,MIKUMI ,NYERERE AND UDZUNGWA NATIONAL PARKS TZ-TANAPA-253934-CS-QCB S / PROVISION OF CONSULTA 1. Strengthen management NCY SERVICES FOR SUPERVI Quality And Cost- Open - Internationa Under Implement IDA / 61430 and improve infrastructure i Prior 0.00 2021-09-20 2021-10-26 2021-10-11 2021-10-27 2021-11-24 2022-05-30 2021-12-22 2022-07-21 2022-01-21 2022-02-25 2022-04-01 2023-04-01 SION OF REHABILITATION OF Based Selection l ation n priority Protected Areas AIRSTRIPS TO GRAVEL STAN DARD FOR RUAHA, MIKUMI A ND NYERERE NATIONAL PARK S INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-TANAPA-135710-CS-INDV 2. Strengthen alternative liv / Provision of consultancy ser elihoods for targeted comm Individual Consult IDA / 61430 Prior Open 0.00 Canceled 2020-05-15 2020-07-03 2020-07-24 2020-08-28 2021-02-24 vices for engagement of cap unities in proximity to the pr ant Selection acity building partner iority Protected Areas Page 3 TZ-TANAPA-242285-CS-CDS / PROVISION OF CONSULTAN CY SERVICES FOR FEASIBILIT 1. Strengthen management Y STUDY,DETAILED ENGINEE IDA / 61430 and improve infrastructure i Post Direct Selection Direct 870,368.00 Signed 2021-06-30 2021-06-30 2021-07-10 2021-07-22 2021-09-13 2021-09-08 2022-03-12 RING DESIGN AND PREPARAT n priority Protected Areas ION OF TENDER DOCUMENT FOR REHABILITATION OF ROA DS (792 KM) FOR NYERERE N ATIONAL PARK TO GRAVEL S TANDARD TZ-TANAPA-315626-CS-CDS / CONSULTANCY SERVICES F 2. Strengthen alternative liv OR TECHNICAL ASSISTANCE elihoods for targeted comm Direct - Internation Under Implement FROM WATERLUTION FOR CA IDA / 61430 Post Direct Selection 0.00 2022-09-30 2022-09-14 2022-10-10 2022-12-14 2023-06-12 unities in proximity to the pr al ation PACITY BUILDING IN WATER I iority Protected Areas NNOVATIVE SOLUTIONS IN C OMMUNITIES AROUND RUAH A NATIONAL PARK Page 4