HYDROPOWER DEVELOPMENT ON THE SANAGA RIVER TECHNICAL ASSISTANCE PROJECT (P157733) – NEGOTIATED PROCUREMENT PLAN Type of procurement Procurement Comments Prior Review Thresholds (US$ millions) Goods, information technology 1.5 Prior review thresholds of the type of and non-consulting services procurement are identical to those of Consultants: firms 0.5 Single Source Selection and Direct Contract. Direct contracting and Single Consultants: individuals 0.2 Source justification are cleared by the Bank as a part of the procurement plan and justified Estimat Review ed Cost by World Selection Comments/ Ref. No. Description of Assignment (US$ Bank Method Completion date millions (Prior/Pos ) t) A. MINEE-implemented activities Recruitment the Project Several Fiduciary Management team contracts to be (Coordinator, Financial 1,200,0 MI.1 IC Prior renewed every management specialist, 00 two years accountant, procurement July 2023 specialist) Several Recruitment of a Panel of contracts to be 1,500,0 MI.2 Experts (multiple individual IC Prior renewed every 00 contracts) two years June 2022 Recruitment of a qualified firm to provide support to the GoC in 1,000,0 MI.3 QCBS Prior June 2022 its contractual obligations 00 related to the Nachtigal project Recruitment of a firm for the development of the Hydrology 250,00 MI.4 QCBS Post June 2018 and Climate Change Study on 0 the Sanaga River basin Recruitment of a firm for the development of the Hydrology 1,000,0 MI.5 QCBS Prior June 2019 risk mitigation strategy and 00 mitigation mechanisms Recruitment of a firm for the 300,00 MI.6 development of a Dam safety QCBS Post December 2018 0 framework Recruitment of a firm for the Analysis of Options for 150,00 MI.7 sustainable operation and QCBS Post March 2018 0 maintenance of Publicly- financed Hydroelectric Assets Recruitment of a firm to provide 1,000,0 MI.8 QCBS Prior December 2019 support to the GoC in the 00 Implementation of the Concession type options selected under MI.7 Recruitment of a firm to identify Human Resources needs in the hydroelectricity sector in the 250,00 MI.9 QCBS Prior December 2018 medium and long term and 0 develop a related capacity building strategy Procurement handled outside MI.10 Recruitment of a project auditor 50,000 LCS Prior of the Project (MINEPAT) July 2023 B. EDC-implemented activities Reinforcement of the fiduciary capacities of UGP-2 (social 420,00 EDC.1 IC Prior July 2023 development specialist, 0 environment specialist) Financed under Lom Pangar Recruitment of an individual Hydropower EDC.2 consultant to write the Project 50,000 IC Post Project or Implementation Manual (PIM) SONATREL June 2017 Recruitment of a firm for the 1,000,0 EDC.3 Sanaga River Basin Hydropower QCBS Prior December 2018 00 Potential Optimization Study Recruitment of a firm for engineering studies and the 3,000,0 EDC.4 feasibility study of a selected QCBS Prior December 2020 00 New Hydroelectric scheme (including geological baseline) Recruitment of a consultant in charge of conducting a Social 100,00 EDC.5 IC Post December 2018 Assessment alongside the 0 Sanaga River Recruitment of a firm for the Strategic Environmental and 100,00 EDC.6 Social Assessment (SESA) for the IC Post June 2019 0 development of hydroelectricity in the Sanaga basin Recruitment of a firm for the, the Environmental and a Social 200,00 EDC.7 Impact Assessment (ESIA) of the QCBS Post June 2020 0 selected hydropower plant site (including transmission lines) Recruitment of a Transaction Advisor firm to develop and pre- negotiate contractual 1,500,0 EDC.8 QCBS Prior December 2021 documents and draft the bidding 00 documents for the selection of the private developer Recruitment of a firm for the 2,000,0 EDC.9 Dam Safety Assessment of QCBS Prior December 2019 00 Mapé, Bamendjin et Mbakaou Recruitment of a fir as Assistant 750,00 EDC.10 Project Manager (APM) for the QCBS Prior December 2019 0 Operationalization of the STP Recruitment of a firm to Ensure the Reliability of the Water 150,00 EDC.11 QCBS Post December 2018 Information System of the 0 Sanaga Recruitment of a firm to develop an operational tool for 100,00 EDC.12 QCBS Post December 2018 planning and managing water 0 allocation Recruitment of an individual consultant to develop a methodology to evaluate and EDC.13 80,000 IC Post December 2017 measure specific capacity enhancement achieved by the Project Recruitment of interns to learn 300,00 6 to 12 interns EDC.14 on-the-job about hydropower IC Post 0 December 2020 related professions PROCUREMENT Cameroon : Hydropower Development on the Sanaga River Technical Assistance Project PLAN General Information Country: Cameroon 2018-09-26 Bank’s Approval Date of the Original Procurement Plan: 2023-10-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157733 GPN Date: Project Name: Hydropower Development on the Sanaga River Technical Assistance Project Loan / Credit No: IDA / 60440 Electricity Development Corporation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-EDC-178380-GO-RFB / F Establishment of an integrat ourniture et installation des é ed reservoir management pl Open - Internationa Single Stage - One E quipements des stations mét IDA / 60440 an for optimal hydropower g Post Request for Bids 992,000.00 1,030,718.51 Signed 2020-06-08 2018-11-01 2020-06-13 2020-06-10 2020-07-25 2019-04-23 2020-08-24 2019-06-11 2020-09-28 2020-03-19 2021-05-27 l nvelope éorologiques et hydrologique eneration on the Sanaga riv s dans le bassin versant de la er Sanaga CM-EDC-178385-GO-RFQ / F Establishment of an integrat ourniture et installation du m ed reservoir management pl Request for Quota Single Stage - One E IDA / 60440 Post Open - National 36,000.00 37,025.52 Terminated 2020-06-13 2020-06-11 2020-08-08 2019-06-29 2021-02-04 atériel et équipements infor an for optimal hydropower g tions nvelope matiques pour l'unité de gest eneration on the Sanaga riv ion de l'eau à EDC er CM-EDC-178396-GO-RFQ / A Supervision of the Nachtigal Request for Quota Single Stage - One E cquisition du logociel TOMPR IDA / 60440 Post Limited 17,000.00 13,436.95 Signed 2020-06-13 2020-05-08 2020-07-23 2020-05-31 2020-08-22 Hydroelectric Project tions nvelope O 2 pour le projet PATDHS/E DC CM-EDC-198808-GO-RFQ / A cquisition du matériel inform Project Management Suppor Request for Quota Single Stage - One E IDA / 60440 Post Limited 15,000.00 15,371.18 Signed 2020-12-12 2021-01-18 2021-02-06 2021-02-15 2021-04-07 atique pour le personnel du p t and Capacity Building tions nvelope rojet PATDHS à EDC CM-EDC-204924-GO-RFQ / A cquisition des équipements e Project Management Suppor Request for Quota Single Stage - One E IDA / 60440 Post Limited 15,000.00 0.00 Completed 2021-10-18 2022-07-06 2021-12-13 2022-08-04 2022-02-11 2022-08-14 t matériel informatique pour l t and Capacity Building tions nvelope e sysytème d'information sur l'eau (SIE) à EDC CM-EDC-198807-GO-RFQ / A cquisition du petit matériel et Project Management Suppor Request for Quota Single Stage - One E IDA / 60440 Post Limited 15,000.00 0.00 Canceled 2021-12-04 2022-01-03 ustensils pour la salle de réu t and Capacity Building tions nvelope nion du projet PATDHS à EDC CM-EDC-287710-GO-RFQ / A cquisition du petit matériel et Project Management Suppor Request for Quota Single Stage - One E IDA / 60440 Post Limited 15,000.00 12,913.62 Completed 2022-04-02 2021-12-13 2022-04-11 2021-11-26 2022-04-21 2022-02-26 ustensils pour la salle de réu t and Capacity Building tions nvelope nion du projet PATDHS à EDC CM-EDC-190074-GO-RFB / F ourniture et installation des é Identification of hydropower Open - Internationa Single Stage - One E Under Imple quipements du système d'inf IDA / 60440 project sites on the Sanaga Post Request for Bids 500,000.00 0.00 2023-03-31 2023-04-04 2023-04-30 2023-06-23 2023-06-29 2023-08-24 2023-07-29 2023-10-13 2023-09-27 2024-03-25 l nvelope mentation ormation géographique à Ele River Basin cticity Development Corporat ion (EDC) CM-EDC-341981-GO-RFQ / A Project Management Suppor Request for Quota Single Stage - One E cquisition du mobilier de bur IDA / 60440 Post Limited 15,000.00 0.00 Completed 2023-04-22 2022-12-20 2023-04-30 2023-01-04 2023-05-14 2023-05-25 t and Capacity Building tions nvelope eau pour le personnel de l'U GP PATDHS EDC CM-EDC-351294-GO-RFQ / A Project Management Suppor Request for Quota Single Stage - One E cquisition du matériel inform IDA / 60440 Post Limited 20,000.00 0.00 Signed 2023-10-13 2023-05-09 2023-10-22 2023-05-09 2023-11-05 t and Capacity Building tions nvelope atique pour le personnel de l' UGP EDC CM-EDC-351308-GO-RFQ / A Project Management Suppor Request for Quota Single Stage - One E Under Imple cquisition des ustensiles pour IDA / 60440 Post Limited 20,000.00 0.00 2023-10-13 2023-10-05 2023-10-22 2023-12-21 t and Capacity Building tions nvelope mentation la salle de réunion de l'UGP E DC CM-EDC-365964-GO-RFQ / A Project Management Suppor Request for Quota Single Stage - One E IDA / 60440 Post Limited 20,000.00 0.00 Signed 2023-10-07 2023-10-02 2023-10-28 2023-10-10 2023-11-18 cquisition des encres pour le t and Capacity Building tions nvelope PATDHS CM-EDC-383330-GO-RFQ / A cquisition des fournitures no Project Management Suppor Request for Quota Single Stage - One E Under Imple IDA / 60440 Post Limited 10,000.00 0.00 2023-10-22 2023-10-05 2023-11-22 2023-12-06 n stockables pour réunions à t and Capacity Building tions nvelope mentation l'UGP PATDHS EDC Establishment of an integrat CM-EDC-389867-GO-RFQ / A ed reservoir management pl Request for Quota Single Stage - One E Pending Impl cquisition du matériel inform IDA / 60440 Post Limited 20,000.00 0.00 2023-12-05 2023-12-22 2024-01-05 an for optimal hydropower g tions nvelope ementation atique pour le SIE eneration on the Sanaga riv er NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CM-EDC-80813-CS-QCBS / Et Establishment of an integrat ude d'optimisation de la mise ed reservoir management pl Quality And Cost- Open - Internationa en valeur du potentiel hydro IDA / 60440 an for optimal hydropower g Prior 1,500,000.00 1,630,256.01 Signed 2018-10-04 2018-10-21 2018-12-04 2020-03-03 2019-01-03 2020-06-18 2019-01-18 2020-10-08 2019-03-01 2021-01-26 2019-04-05 2021-02-21 2020-04-04 Based Selection l électrique du bassin versant eneration on the Sanaga riv de la Sanaga au Cameroun er CM-EDC-135649-CS-QCBS / Establishment of an integrat Evaluation environnementale ed reservoir management pl Quality And Cost- Open - Internationa et sociale stratégique pour le IDA / 60440 an for optimal hydropower g Post 600,000.00 826,597.78 Under Review 2020-02-27 2020-03-02 2020-03-07 2020-06-10 2020-05-08 2020-09-18 2020-09-17 2020-10-18 2020-12-10 2020-12-13 2021-02-08 2021-02-21 2021-05-06 2022-07-31 2022-09-11 Based Selection l développement de l’hydroéle eneration on the Sanaga riv ctricité sur le fleuve Sanaga er au Cameroun CM-EDC-186480-CS-QCBS / Etude diagnostic et d'évaluat Hydrological Risk Mitigation Quality And Cost- Open - Internationa ion de la sécurité des barrag IDA / 60440 Prior 1,500,000.00 0.00 Signed 2020-08-03 2021-09-06 2020-09-17 2021-10-27 2020-11-16 2021-12-21 2020-12-31 2022-02-16 2021-01-30 2022-07-20 2021-03-22 2022-11-15 2021-05-21 2022-12-14 2022-05-21 and Dam Safety Based Selection l es réservoirs Mapé, Bamendji n et Mbakaou sur la Sanaga CM-EDC-186510-CS-QCBS / Audit comptable et financier Project Management Suppor Quality And Cost- du projet d'assistance techni IDA / 60440 Post Open - National 100,000.00 29,730.82 Signed 2020-08-10 2020-08-17 2020-08-31 2020-11-02 2020-10-30 2021-01-15 2020-11-29 2021-03-10 2020-12-29 2021-04-22 2021-01-22 2021-05-14 2021-03-14 2021-07-21 2021-05-13 2022-10-27 t and Capacity Building Based Selection que pour le développement d e l'hydroélectricité sur la San aga exercice 2020 et 2021 CM-EDC-348452-CS-QCBS / Establishment of an integrat Recrutement d'un Consultant ed reservoir management pl Quality And Cost- Open - Internationa Under Implement IDA / 60440 Post 725,000.00 0.00 2023-03-31 2023-04-04 2023-04-21 2023-04-06 2023-06-04 2023-07-10 2023-07-02 2023-10-05 2023-08-01 2023-09-05 2023-10-10 2024-04-07 pour l'élaboration du Busines an for optimal hydropower g Based Selection l ation s Plan de EDC eneration on the Sanaga riv er CM-EDC-351319-CS-QCBS / Establishment of an integrat Recrutement d'un consultant ed reservoir management pl Quality And Cost- Open - Internationa Pending Impleme chargé de la fiabilisation des IDA / 60440 an for optimal hydropower g Post 330,000.00 0.00 2023-11-29 2023-12-20 2024-02-02 2024-03-01 2024-03-31 2024-05-05 2024-06-09 2024-12-06 Based Selection l ntation données physiques du systè eneration on the Sanaga riv me d'information sur l'eau da er ns le bassin de la Sanaga CM-EDC-351329-CS-QCBS / Etude d'APD pour la réhabilit Hydrological Risk Mitigation Quality And Cost- Open - Internationa Pending Impleme IDA / 60440 Post 840,000.00 0.00 2023-11-29 2023-12-20 2024-02-18 2024-04-03 2024-05-03 2024-06-11 2024-07-04 2024-12-31 ation des barrages réservoirs and Dam Safety Based Selection l ntation de Lom Pangar, Bamendjin, Mapé et Mbakaou CM-EDC-365962-CS-QCBS / Recrutement d'un consultant en charge de l'étude d'impac Identification of hydropower Quality And Cost- Open - Internationa Pending Impleme ts biodiversité cumulatifs sur IDA / 60440 project sites on the Sanaga Post 729,470.00 0.00 2023-11-14 2023-12-05 2024-01-19 2024-02-03 2024-02-18 2024-04-18 2024-05-10 2025-01-05 Based Selection l ntation la cascade Kikot - Grand Ewe River Basin ng - Song Mbengue - song Do ng - Edéa amont sur la Sanag a INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-EDC-79556-CS-INDV / re crutement d'un hydromécani cien pour constituer le Panel Supervision of the Nachtigal Individual Consult d'Experts Indépendants en S IDA / 60440 Post Limited 190,000.00 155,111.78 Signed 2018-09-25 2018-08-07 2018-09-30 2018-08-12 2018-10-21 2018-08-20 2018-11-25 2018-10-13 2020-11-24 Hydroelectric Project ant Selection écurité des Barrages du proje t d'Assistance Technique pou r le développement de l'Hydr oélectricité sur le fleuve San aga CM-EDC-79559-CS-INDV / re crutement d'un géologue-gé otechnicien pour constituer l e Panel d'Experts Indépenda Supervision of the Nachtigal Individual Consult IDA / 60440 Post Limited 190,000.00 137,192.34 Signed 2018-09-25 2018-09-25 2018-09-30 2018-08-30 2018-10-21 2018-09-26 2018-11-25 2018-10-27 2020-11-24 nts en Sécurité des Barrages Hydroelectric Project ant Selection du projet d'Assistance Techni que pour le développement d e l'Hydroélectricité sur le fleu ve Sanaga CM-EDC-79560-CS-INDV / re crutement d'un Expert Barra giste, Chef du Panel pour con stituer le Panel d'Experts Ind Supervision of the Nachtigal Individual Consult IDA / 60440 Post Limited 198,000.00 191,557.27 Signed 2018-09-25 2018-09-25 2018-09-30 2018-10-21 2018-09-26 2018-11-25 2018-10-13 2020-11-24 épendants en Sécurité des B Hydroelectric Project ant Selection arrages du projet d'Assistanc e Technique pour le dévelop pement de l'Hydroélectricité sur le fleuve Sanaga CM-EDC-80816-CS-INDV / Re crutement d'un consultant in dividuel en vue de la prépara tion des sections administrati Project Management Suppor Individual Consult ve, comptable, financière et IDA / 60440 Post Open 50,000.00 23,046.16 Signed 2018-10-04 2018-11-01 2018-11-22 2018-10-24 2018-12-13 2019-04-12 2019-01-17 2019-05-08 2019-07-16 t and Capacity Building ant Selection opérationnelle du Manuel d'e xécution du Projet d'Assistan ce Technique pour le Dévelo ppement de l'Hydroélectricit é sur la Sanaga (PATDHS) CM-EDC-79548-CS-INDV / re crutement d'un hydrologue p our constituer le Panel d'Exp Supervision of the Nachtigal Individual Consult erts Indépendants en Sécurit IDA / 60440 Post Limited 190,000.00 0.00 Canceled 2018-09-25 2018-09-25 2018-09-30 2019-09-25 2018-10-21 2018-11-25 2020-11-24 Hydroelectric Project ant Selection é des Barrages du projet d'As sistance Technique pour le d éveloppement de l'Hydroélec tricité sur le fleuve Sanaga. CM-EDC-79554-CS-INDV / re crutement d'un expert d'un e xpert en planification et dime nsionnement des systèmes é Supervision of the Nachtigal Individual Consult IDA / 60440 Post Limited 190,000.00 0.00 Canceled 2018-09-25 2018-09-25 2018-09-30 2018-10-30 2018-10-21 2018-11-25 2020-11-24 lectriques pour constituer le Hydroelectric Project ant Selection Panel en Sécurité des Barrag es du projet d'Assistance Tec hnique pour le développeme nt de l'Hydroélectricité sur la Sanaga CM-EDC-198798-CS-INDV / S ELECTION D'UN STAGIAIRE P ROFESSIONNEL Ingénieur bar rage dans la spécialité du GE Project Management Suppor Individual Consult NIE CIVIL AU SEIN DE EDC DA IDA / 60440 Post Open 15,000.00 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2021-06-05 t and Capacity Building ant Selection NS LE CADRE DU PROJET D’A SSISTANCE TECHNIQUE POU R LE DÉVELOPPEMENT DE L’ HYDROÉLECTRICITÉ SUR LE F LEUVE SANAGA (PATDHS) Page 2 CM-EDC-201677-CS-INDV / R ECRUTEMENT D'UN STAGIAIR E PROFESSIONNEL Ingénieur géologue / géotechnicien AU Project Management Suppor Individual Consult SEIN DE EDC DANS LE CADR IDA / 60440 Post Open 15,000.00 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-25 t and Capacity Building ant Selection E DU PROJET D’ASSISTANCE TECHNIQUE POUR LE DÉVEL OPPEMENT DE L’HYDROÉLEC TRICITÉ SUR LE FLEUVE SAN AGA (PATDHS) CM-EDC-201684-CS-INDV / R ECRUTEMENT D'UN STAGIAIR E PROFESSIONNELIngénieur hydraulique AU SEIN DE EDC Project Management Suppor Individual Consult IDA / 60440 Post Open 15,000.00 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-25 DANS LE CADRE DU PROJET t and Capacity Building ant Selection D’ASSISTANCE TECHNIQUE P OUR LE DÉVELOPPEMENT DE L’HYDROÉLECTRICITÉ SUR LE FLEUVE SANAGA (PATDHS) CM-EDC-201686-CS-INDV / R ECRUTEMENT D'UN STAGIAIR E PROFESSIONNELIngénieur Hydro-Électro-Mécanique (HE Project Management Suppor Individual Consult M) AU SEIN DE EDC DANS LE IDA / 60440 Post Open 15,000.00 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-25 t and Capacity Building ant Selection CADRE DU PROJET D’ASSISTA NCE TECHNIQUE POUR LE DÉ VELOPPEMENT DE L’HYDROÉ LECTRICITÉ SUR LE FLEUVE S ANAGA (PATDHS) CM-EDC-204919-CS-INDV / S ELECTION D'UN STAGIAIRE P ROFESSIONNEL Ingénieur éle ctricien HT AU SEIN DE EDC Project Management Suppor Individual Consult IDA / 60440 Post Open 15,000.00 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2022-04-16 2021-03-26 2021-04-30 2022-04-25 DANS LE CADRE DU PROJET t and Capacity Building ant Selection D’ASSISTANCE TECHNIQUE P OUR LE DÉVELOPPEMENT DE L’HYDROÉLECTRICITÉ SUR LE FLEUVE SANAGA (PATDHS) CM-EDC-204920-CS-INDV / S ELECTION D'UN STAGIAIRE P ROFESSIONNEL Ingénieur Hy drologue AU SEIN DE EDC DA Project Management Suppor Individual Consult IDA / 60440 Post Open 15,000.00 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-25 NS LE CADRE DU PROJET D’A t and Capacity Building ant Selection SSISTANCE TECHNIQUE POU R LE DÉVELOPPEMENT DE L’ HYDROÉLECTRICITÉ SUR LE F LEUVE SANAGA (PATDHS) CM-EDC-204921-CS-INDV / S ELECTION D'UN STAGIAIRE P ROFESSIONNEL Ingénieur En vironnementaliste AU SEIN D Project Management Suppor Individual Consult IDA / 60440 Post Open 15,000.00 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-25 E EDC DANS LE CADRE DU P t and Capacity Building ant Selection ROJET D’ASSISTANCE TECHNI QUE POUR LE DÉVELOPPEME NT DE L’HYDROÉLECTRICITÉ SUR LE FLEUVE SANAGA (PAT DHS) CM-EDC-204922-CS-INDV / S ELECTION D'UN STAGIAIRE P ROFESSIONNEL Ingénieur Car tographe / SIG AU SEIN DE E Project Management Suppor Individual Consult IDA / 60440 Post Open 15,000.00 0.00 Canceled 2021-01-15 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-25 DC DANS LE CADRE DU PROJ t and Capacity Building ant Selection ET D’ASSISTANCE TECHNIQU E POUR LE DÉVELOPPEMENT DE L’HYDROÉLECTRICITÉ SU R LE FLEUVE SANAGA (PATD HS) CM-EDC-383334-CS-INDV / R ecrutement d’un consultant i ndividuel chargé de l’étude s ur l’élaboration d’un Cadre d Identification of hydropower Individual Consult Open - Internationa Under Implement e Planification en faveur des IDA / 60440 project sites on the Sanaga Post 100,000.00 0.00 2023-10-30 2023-10-03 2023-12-18 2024-01-08 2024-02-12 2024-06-11 ant Selection l ation Peuples Autochtones suscept River Basin ibles d’être impactés par le d éveloppement de l’hydroélec tricité sur le bassin de la vers ant de la Sanaga CM-EDC-389847-CS-INDV / R ecrutement d'un Expert Séni or en sécurité des barrages p Hydrological Risk Mitigation Individual Consult Open - Internationa Pending Impleme IDA / 60440 Post 100,000.00 0.00 2023-10-30 2023-11-19 2023-11-29 2023-12-09 2024-08-17 our la mise en place du cadre and Dam Safety ant Selection l ntation réglementaire de la sécurité des barrages au Cameroun CM-EDC-389856-CS-INDV / R ecrutement d'un Expert en s Hydrological Risk Mitigation Individual Consult Open - Internationa Pending Impleme écurité des barrages pour la IDA / 60440 Post 100,000.00 0.00 2023-10-30 2023-11-19 2023-11-29 2023-12-09 2024-08-17 and Dam Safety ant Selection l ntation mise en place du cadre régle mentaire de la sécurité des b arrages au Cameroun CM-EDC-389864-CS-INDV / R ecrutement d'un Expert Jurist Hydrological Risk Mitigation Individual Consult Open - Internationa Pending Impleme e pour la mise en place du ca IDA / 60440 Post 100,000.00 0.00 2023-10-30 2023-11-19 2023-11-29 2023-12-09 2024-08-17 and Dam Safety ant Selection l ntation dre réglementaire de la sécu rité des barrages au Camero un Page 3