Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non- consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Up to USD 100,000 (INR 6.5 m) Shopping Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b)Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises, or enterprises from any given state. (d)Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g)Two or three envelope system will not be used (except when using the e- procurement system assessed and agreed by the Bank). (h)No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget Must meet the requirements as per (FBS) Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis Must meet the requirements as per (LCS) Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Estimated not to exceed USD Qualification (CQ) 300,000, and must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for Executive, Assistant Engineers 1. 2 weeks Continuous who are responsible for Procurement – multiple trainings Contract management training – multiple 2. 2 weeks Continuous trainings Customized training on Procurement Procedures arranged for Executive, Assistant 3. 1 week Continuous Engineers who are responsible for Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India 2017-11-29 Bank’s Approval Date of the Original Procurement Plan: 2023-10-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: 2022-06-17 Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 Uttar Pradesh Ground Water Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NHP-2018-2019-UPGW-1770 Water Resources Monitoring Single Stage - Two E 2019-12-0 29-CW-NCB-SE / INSTALLATI IBRD / 87250 Post Request for Bids Open - National 960,230.77 891,947.70 Signed 2018-06-24 2018-06-26 2018-06-29 2018-08-16 2018-08-16 2018-10-29 2018-09-27 2018-12-03 2019-01-08 System nvelope 3 ON OF BLOCKWISE KEY PIEZ OMETERS NHP-2019-2020-UPGW-3132 Water Resources Monitoring Single Stage - Two E 2022-02-0 49 / Establishment of State G IBRD / 87250 Post Request for Bids Open - National 3,863,076.92 0.00 Signed 2020-02-10 2020-07-15 2020-02-15 2020-03-28 2021-08-14 2020-07-11 2021-01-14 2020-08-15 2020-03-17 System nvelope 6 round Water Informatics Cent rer NHP-2020-2021-UPGW-5561 Water Resources Operations Single Stage - Two E 2021-12-0 15 / Construction of explorat IBRD / 87250 Post Request for Bids Open - National 92,307.69 0.00 Canceled 2020-06-30 2020-07-10 2020-08-21 2020-11-03 2020-12-08 and Planning System nvelope 8 ory well for Arsenic study. NHP-2019-2020-UPGW-2194 Water Resources Monitoring Single Stage - Two E 2021-07-2 64 / REJUVENATION AND REC IBRD / 87250 Post Request for Bids Open - National 615,384.62 0.00 Canceled 2020-02-20 2020-02-20 2020-02-25 2020-04-07 2020-06-05 2020-06-20 2020-07-25 System nvelope 5 ONSTRUCTION OF EXISTING PIEZOMETERS NHP-2019-2020-UPGW-2194 Water Resources Monitoring Single Stage - Two E 2022-07-3 64_1 / REJUVENATION AND R IBRD / 87250 Post Request for Bids Open - National 615,384.62 487,432.33 Signed 2020-09-08 2020-08-05 2020-09-08 2021-01-21 2020-10-28 2020-10-28 2020-12-27 2020-12-02 2021-01-31 2021-01-17 System nvelope 1 ECONSTRUCTION OF EXISTIN G PIEZOMETERS IN-UTTAR PRADESH GW-274 840-CW-RFB / Estimation of p rimary paramenters (Aquifer parameters & factors) for rec Water Resources Operations Single Stage - Two E Other (with field f 2023-01-0 harge and draft of groundwat IBRD / 87250 Post Request for Bids Open - National 100,000.00 0.00 Signed 2022-03-11 2022-04-25 2022-03-16 2022-04-20 2022-06-22 2022-06-08 2022-07-13 2022-07-13 2022-07-29 and Planning System nvelope or explanation) 9 er in project area for Consult ancy study on micro level G W estimation ( Pilot ) in two macro basin of different hydr ogeologically scenario GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-UTTAR PRADESH GW-369 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl 38-GO-RFQ / Water Level Sou IBRD / 87250 Post Open - National 41,538.00 0.00 2017-12-04 2018-01-11 2018-01-31 System tions nvelope ementation nder, Hand held GPS, or alike devices IN-UTTAR PRADESH GW-369 53-GO-RFQ / Development/st Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 46,154.00 0.00 2017-12-06 2018-01-20 2018-02-19 rengthening of IT infrastructu System tions nvelope ementation re at field division level IN-UTTAR PRADESH GW-370 Water Resources Monitoring Request for Quota Single Stage - One E 66-GO-DIR / Procurement of IBRD / 87250 Post Open - National 30,769.00 0.00 Canceled 2017-12-11 2018-02-01 2018-03-02 System tions nvelope 4 no basic ArcGIS software IN-UTTAR PRADESH GW-370 74-GO-RFQ / Development of Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 15,385.00 0.00 Signed 2017-11-29 2018-01-24 2018-10-19 2018-05-24 mobile app for field/ Commu System tions nvelope nity based monitoring and di ssemination IN-UTTAR PRADESH GW-370 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl 81-GO-RFQ / Development of IBRD / 87250 Post Open - National 1,538.00 0.00 2017-12-20 2018-02-08 2018-03-10 System tions nvelope ementation library and E-library IN-UTTAR PRADESH GW-371 54-GO-RFQ / "To prepare res ource material ( Annual Repo rts,pamphlets,Brochure,post Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 3,846.00 0.00 2017-12-29 2018-02-19 2018-03-06 ers, audio visuals,documenta System tions nvelope ementation ries etc.,) on water conservat ion & management awarenes s creation to water users (inf ormation education & comm unication )" NHP-2018-2019-UPGW-1853 62-GO-SH-QU / Procurement Water Resources Monitoring Single Stage - One E IBRD / 87250 Post Request for Bids Open - National 107,692.31 90,618.20 Signed 2018-08-16 2018-12-14 2018-08-21 2019-11-27 2018-09-20 2019-04-05 2018-10-10 2019-05-29 2018-11-14 2019-08-04 2018-12-14 of Digital Data Logger mount System nvelope ed on vehicle (Geophysical E quipment) NHP-2018-2019-UPGW-8754 Water Resources Monitoring Request for Quota Single Stage - One E 46-CW-SH-QU / Development IBRD / 87250 Post Open - National 15,384.62 27,900.19 Signed 2018-06-20 2021-01-22 2018-09-10 2018-10-26 2019-01-08 System tions nvelope of mobile app NHP-2018-2019-UPGW-3423 Water Resources Monitoring Under Imple 27-GO-DC-DC / Software for IBRD / 87250 Post Direct Selection Direct 32,307.69 0.00 2018-08-14 2020-12-21 2018-08-14 2020-12-21 2018-10-13 2018-11-12 System mentation Data Center NHP-2018-2019-UPGW-4144 96-GO-DC-DC / Upgradation of existing Remote Sensing L Water Resources Monitoring IBRD / 87250 Post Direct Selection Direct 30,769.23 0.00 Signed 2018-07-25 2019-02-01 2018-07-25 2019-02-09 2018-10-23 2019-02-21 2018-12-22 ab alongwith procurement of System SOI Toposheets (Hard copy & digital data) and sattellite da ta, Geological Maps NHP-2018-2019-UPGW-8506 26-GO-SH-QU / Procurement of storage and backup device Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 3,046.15 0.00 Signed 2018-08-04 2018-08-06 2018-07-24 2018-09-05 s through GeM (Development System tions nvelope / strensthening of IT infrastru cture at field division level an d at SDC, RDC @ SDC) Page 1 NHP-2018-2019-UPGW-5680 07-GO-SH-QU / Procurement of Copier / photocopier throu Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 25,384.62 0.00 Signed 2018-07-13 2018-07-19 2018-07-10 2018-08-01 gh GeM (Development/ stren System tions nvelope thening of IT infrastructure at field division level and at SD C, RDC and SDC) NHP-2018-2019-UPGW-8006 07-GO-SH-QU / procurement of Networking / Internet facili Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 2,307.69 0.00 Signed 2018-07-13 2018-07-19 2018-07-19 2018-09-17 ties (Development/ strensthe System tions nvelope ning of IT infrastructure at fie ld division level and at SDC, RDC and SDC) NHP-2018-2019-UPGW-1402 08-GO-SH-QU / procurement of Plotter/Printer through Ge Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 15,798.46 0.00 Signed 2018-07-20 2018-07-23 2018-07-23 2018-09-21 M (Development/ strenstheni System tions nvelope ng of IT infrastructure at field division level and at SDC, RD C and SDC) NHP-2018-2019-UPGW-2269 15-GO-SH-QU / Procurement of Scanners through GeM (De Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 29,846.15 0.00 Signed 2018-08-20 2018-08-25 2018-07-23 2018-10-24 velopment/ strengthening of System tions nvelope IT infrastructure at field divisi on level and at SDC, RDC an d SDC) NHP-2018-2019-UPGW-9813 79-GO-SH-QU / Procurement of UPS systemr through GeM Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 1,815.38 0.00 Signed 2018-08-14 2018-09-13 2018-09-28 2018-11-12 (Development/ strensthening System tions nvelope of IT infrastructure at field di vision level and at SDC, RDC and SDC) NHP-2018-2019-UPGW-5949 66-GO-SH-QU / Procurement of workstations through GeM Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 46,150.77 0.00 Signed 2018-08-21 2018-09-10 2018-09-26 2018-11-09 (Development/ strensthening System tions nvelope of IT infrastructure at field di vision level and at SDC, RDC and SDC) NHP-2019-2020-UPGW-8605 Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 473,538.46 374,761.99 Signed 2019-06-15 2019-06-13 2019-06-20 2021-01-19 2019-08-01 2019-07-29 2019-10-14 2019-09-06 2019-12-12 2019-12-25 2020-06-09 55 / Procurement of DWLRs System nvelope NHP-2020-2021-UPGW-5192 Water Resources Monitoring Request for Quota Single Stage - One E 38 / UPGRADATION & FURNIS IBRD / 87250 Post Open - National 23,076.92 0.00 Signed 2020-06-04 2020-08-11 2021-02-07 System tions nvelope HING OF STATE DATA CENTR E AT HQ NHP-2020-2021-UPGW-4359 Water Resources Monitoring Single Stage - Two E IBRD / 87250 Post Request for Bids Open - National 384,615.38 307,054.09 Signed 2020-07-20 2020-08-16 2020-07-30 2021-01-19 2020-09-10 2020-09-25 2020-11-23 2020-10-28 2020-12-28 2021-01-03 2021-06-26 67 / PROCUREMENT OF DWL System nvelope Rs NHP-2020-2021-UPGW-4223 26 / PROCUREMENT OF COM PUTER DEVELOPMENT / STRE Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Open - National 15,384.62 0.00 2020-10-11 2020-11-26 2021-03-11 2020-12-26 NGTHENING OF IT INSTRAST System tions nvelope mentation RACTURE AT FIELD DIVISION LEVEL AND AT SDC, RDC AN D SDC IN-UTTAR PRADESH GW-239 603-GO-RFB / Supply, Installa tion, Testing and Commission ing of 300 Digital Water Leve Water Resources Monitoring Single Stage - Two E l Recorder (DWLRs) (Non-Ve IBRD / 87250 Post Request for Bids Open - National 567,858.44 0.00 Signed 2021-06-15 2021-06-23 2021-06-15 2021-07-23 2021-07-30 2021-08-30 2021-11-01 2021-10-01 2021-12-06 2026-09-30 System nvelope nted pressure type/ Acoustic type) with Telemetry, includi ng fencing and establishmen t of Data Acquisition system along with its maintenance. NHP-2019-2020-UPGW-2465 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple 93 / Develpoment of Library IBRD / 87250 Post Open - National 22,307.69 0.00 2019-08-25 2019-10-20 2020-04-17 System tions nvelope mentation & E- Library IN-UTTAR PRADESH GW-239 Water Resources Monitoring Single Stage - Two E Under Imple 626-GO-RFB / Upgradation & IBRD / 87250 Post Request for Bids Open - National 130,769.23 0.00 2021-10-01 2020-12-21 2021-10-06 2021-11-17 2021-01-01 2022-01-31 2022-03-07 2022-07-05 System nvelope mentation furnishing of State Data Cent re Centre at HO IN-UTTAR PRADESH GW-370 68-GO-RFQ / Development of Water Resources Monitoring Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 7,692.31 0.00 Signed 2021-10-01 2021-11-26 2022-05-24 2022-02-24 Ground Water Atlas of Uttar System tions nvelope Pradesh ( Urban and Rural ) IN-UTTAR PRADESH GW-259 326-GO-RFQ / Portable/Tablet Water Resources Monitoring Request for Quota Single Stage - One E op Automatic Water Quality e IBRD / 87250 Post Open - National 76,923.07 0.00 Signed 2021-10-25 2021-12-13 2021-12-22 2022-02-11 System tions nvelope quipments for water quality a nalysis and monitoring IN-UTTAR PRADESH GW-271 Water Resources Monitoring Single Stage - Two E 806-GO-RFB / Procurement of IBRD / 87250 Post Request for Bids Open - National 1,320,125.91 0.00 Signed 2022-01-04 2019-06-22 2022-01-09 2022-02-01 2019-07-29 2022-04-20 2019-09-06 2022-05-25 2022-07-10 2027-05-24 System nvelope DWLRs-IV, 600 nos. IN-UTTAR PRADESH GW-302 Institutional Capacity Enhan Single Stage - Two E 010-GO-RFB / Furnishing of S IBRD / 87250 Post Request for Bids Open - National 266,667.00 0.00 Signed 2022-06-28 2022-09-12 2022-07-03 2022-07-11 2022-10-13 2022-09-23 2022-11-23 2022-10-28 2023-01-06 2023-02-25 cement nvelope tate ground water informatic center NHP-2022-2023-UPGW-6189 51 / SUPPLY OF BOOKS UNDE Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 4,315.07 0.00 2023-09-09 2023-11-04 2024-05-02 R PIP ACTIVITY DEVELOPMEN cement tions nvelope ementation T OF LIBRARY AND E-LIBRAR Y NHP-2022-2023-UPGW-8683 11 / ACRYLIC BOARD DISPLA Institutional Capacity Enhan Request for Quota Single Stage - One E Pending Impl Y FOR BHUJAL BHAWAN UND IBRD / 87250 Post Open - National 8,082.19 0.00 2023-09-09 2023-11-04 2024-05-02 cement tions nvelope ementation ER PIP ACTIVITY FURNISHING OF STATE GROUND WATER I NFORMATIC CENTRE NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 NHP-2018-2019-UPGW-6463 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl 05-NC-SH-QU / Development IBRD / 87250 Post Open - National 7,692.31 0.00 2018-09-06 2018-11-01 2019-04-30 System tions nvelope ementation / Procurement of Spatial Data bases NHP-2018-2019-UPGW-3005 Water Resources Monitoring Request for Quota Single Stage - One E Pending Impl IBRD / 87250 Post Open - National 7,692.31 0.00 2018-10-06 2018-12-01 2019-05-30 00-NC-SH-QU / UPDATION OF System tions nvelope ementation WEBSITE NHP-2018-2019-UPGW-2696 Water Resources Monitoring Single Stage - One E Under Imple 03-NC-NCB-SE / HIRING OF V IBRD / 87250 Post Request for Bids Open - National 23,076.92 0.00 2018-07-06 2018-08-20 2018-09-19 2018-10-04 2018-11-08 2019-11-08 System nvelope mentation EHICLES FOR PROJECT NHP-2019-2020-UPGW-7977 Water Resources Monitoring Request for Quota Single Stage - One E Under Imple IBRD / 87250 Post Open - National 37,538.46 0.00 2019-06-15 2019-08-10 2020-02-06 01 / Hiring of vehicles for proj System tions nvelope mentation ect NHP-2020-2021-UPGW-8612 19 / Development of Ground Water Resources Informatio Request for Quota Single Stage - One E IBRD / 87250 Post Open - National 23,076.92 0.00 Canceled 2020-06-25 2020-09-14 2021-03-13 water Atlas of Uttar Pradesh ( n Systems tions nvelope Urban and Rural ) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2019-2020-UPGW-7456 82 / Consultancy for study of ground water quality,dynami Water Resources Monitoring Least Cost Selecti IBRD / 87250 Post Open - National 153,846.15 0.00 Canceled 2019-08-20 2019-09-10 2019-10-24 2019-11-21 2019-12-21 2020-01-25 2020-02-29 2020-08-27 cs with special reference to a System on rsenic toxicity in ground wate r regime in and around Ghag hra basin NHP-2019-2020-UPGW-1653 52 / Consultancy for evaluati Water Resources Monitoring Least Cost Selecti on of aquifer profiling throug IBRD / 87250 Post Open - National 269,230.77 0.00 Canceled 2019-09-20 2019-10-11 2019-11-24 2019-12-22 2020-01-21 2020-02-25 2020-03-31 2020-09-27 System on h resistivity imaging,testbore s &geomorphological analysi s in part of vindhyan region NHP-2019-2020-UPGW-3794 04 / Development of geomor Water Resources Monitoring Quality And Cost- phological framework with de IBRD / 87250 Post Open - National 307,692.31 0.00 Canceled 2019-07-15 2019-08-05 2019-09-18 2019-10-16 2019-11-15 2019-12-20 2020-01-24 2021-01-23 System Based Selection lineation of hydrogeological matrix in Bundelkhand regio n IN-UTTAR PRADESH GW-262 211-CS-LCS / Optimisation of ground water monitoring net Water Resources Operations Least Cost Selecti Under Implement IBRD / 87250 Post Open - National 100,000.00 0.00 2021-11-09 2021-11-24 2021-11-09 2021-12-01 2021-11-24 2021-12-29 2021-12-28 2022-01-13 2021-12-28 2022-02-03 2021-12-31 2022-03-17 2023-03-17 work in reference to different and Planning System on ation hydrogeological formation an d different level of extraction of ground water INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2019-2020-UPGW-5228 86 / Consultancy for study of ground water quality, dynami Water Resources Operations IBRD / 87250 Post Direct Selection Direct 100,000.00 0.00 Signed 2019-11-25 2019-11-04 2019-12-01 2019-11-10 2019-12-31 2020-01-26 2022-06-18 cs with special reference to a and Planning System rsenic toxicity in ground wate r regime in and around Ghag hra Basin IN-UTTAR PRADESH GW-271 753-CS-CDS / Consultancy fo r micro level GW estimation ( Water Resources Operations IBRD / 87250 Post Direct Selection Direct 92,307.69 0.00 Under Review 2022-01-04 2022-01-01 2022-01-06 2022-03-12 2023-06-05 Pilot ) in two macro basin of and Planning System different hydrogeologically sc enario alongwith validation o f various norms Page 3