PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive 1. 3M and above All contracts Bidding (ICB) (Goods) National Competitive Bidding 2. less than 3M 2M and above (NCB) (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated : May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages LN 8421 PH Procurement Plan Updated June 2018 (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Comment Ref. No. Description g ent US$1= Source nce by Bank Opening s Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review No. Selection Method Method Threshold US$ Threshold US$ 1. Competitive Methods 0.3M & above (may be used for 1m and above (QCBS, QBS, FBS) also less than 0.3M) (Firms) 2. Competitive Method less than 0.3M None CQS (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to Firms: 1M and Individuals) justification in accordance with above; paras. 3.9 and 5.4 respectively of Individuals 0.3M and Consultant Guidelines at the above. Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref Description of Procurin Expected Bid Estimated Cost (USD Funding Selection Comm . Contract g Opening million) Source Method ents No. Package Agency Date Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 LP/GoP Selection million) US$1,042,75 Single Source Luzon A ( Php59.152 LP/GoP Selection million) LN 8421 PH Procurement Plan Updated June 2018 US$1,042,75 Single Source Luzon B ( Php48.614 LP/GoP Selection million) US$1,042,75 Single Source Visaya ( Php29.612 LP/GoP Selection million) US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines 2017-11-03 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2023-10-26 if none) Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 84210, IBRD / 88160, IBRD / 92710, TF / B5756 Department of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IFB No. 0185-N-2015 / Supp ly and Delivery of Forty (40) units Pick-up Truck, Double Component 1: Local and Na Single Stage - One IBRD / 84210 Prior Request for Bids Open - National 0.00 1,261,350.14 Signed 2015-12-29 2016-01-25 Cab, 4X4 DED (Lot 1) and Si tional Level Planning Envelope x (6) units Van, DED (Lot 2) f or Philippine Rural Develop ment Project PRDP-IS-NPCO-090-GOODS- Component 4: Project Imple Request for Quot Single Stage - One IBRD / 88160 Post Open - National 3,773.58 0.00 Canceled 2019-01-06 2019-03-03 2019-08-30 001-2019 / Cabinet/Shelves/ mentation Support ations Envelope Rack PRDP-IS-NPCO-091-GOODS- Component 4: Project Imple Request for Quot Single Stage - One 001-2019 / Baggage Protecti IBRD / 88160 Post Open - National 9,433.96 0.00 Canceled 2019-01-06 2019-03-03 2019-08-30 mentation Support ations Envelope ve Carrier for Vehicle PRDP-IS-NPCO-001-GOODS- Component 4: Project Imple Request for Quot Single Stage - One 2020 / Supply and delivery o IBRD / 88160 Post Open - National 73,000.00 55,971.69 Completed 2020-10-20 2020-12-15 2021-01-05 2021-06-13 2021-02-04 mentation Support ations Envelope f Scientific Equipment-Drone s PRDP-IS-NPCO-002-GOODS- 2020 / Supply and Delivery Component 4: Project Imple Request for Quot Single Stage - One IBRD / 88160 Post Open - National 195,000.00 3,670.68 Signed 2020-10-20 2020-12-15 2021-01-04 2021-06-13 of Laptops, Desktop comput mentation Support ations Envelope ers, and accessories for PRD P PRDP-IS-NPCO-003-GOODS- Component 4: Project Imple Request for Quot Single Stage - One 2020 / Supply and Delivery IBRD / 88160 Post Open - National 55,042.50 36,025.98 Signed 2020-10-20 2020-12-15 2022-01-02 2021-06-13 mentation Support ations Envelope of mobile phones, tablets an d accessories PRDP-IS-NPCO-004-GOODS- Component 4: Project Imple Request for Quot Single Stage - One 2020 / Supply and Delivery IBRD / 88160 Post Open - National 40,774.40 29,899.10 Signed 2020-10-20 2020-12-15 2021-01-08 2021-06-13 mentation Support ations Envelope of Cameras and acessories PRDP-IS-NPCO-005-GOODS- Component 4: Project Imple Request for Quot Single Stage - One 2020 / Supply and delivery o IBRD / 88160 Post Open - National 41,760.00 16,296.05 Signed 2020-10-20 2020-12-15 2021-01-22 2021-06-13 mentation Support ations Envelope f audio visual equipment PRDP-IS-NPCO-001-GOODS- Component 4: Project Imple Request for Quot Single Stage - One 2021 / Supply and delivery o IBRD / 88160 Post Open - National 55,330.00 0.00 Canceled 2021-01-31 2021-03-28 2021-09-24 mentation Support ations Envelope f Laptop Computers PRDP-IS-NPCO-002-GOODS- Component 4: Project Imple Request for Quot Single Stage - One 2021 / Supply and delivery o IBRD / 88160 Post Open - National 6,512.00 4,120.78 Completed 2021-01-31 2021-03-28 2021-03-26 2021-09-24 2021-03-26 mentation Support ations Envelope f Personal Digital Assistant PRDP-IS-NPCO-003-GOODS- Component 4: Project Imple Request for Quot Single Stage - One 2021 / Supply and delivery o IBRD / 88160 Post Open - National 800.00 0.00 Canceled 2021-01-31 2021-03-28 2021-09-24 mentation Support ations Envelope f document scanner PRDP-IS-NPCO-002-EU / Sup Component 4: Project Imple Request for Quot Single Stage - One Pending Impl ply and delivery of ID printer TF / B5756 Post Open - National 4,500.00 0.00 2022-01-14 2022-03-11 2022-09-07 mentation Support ations Envelope ementation and time attendance termin al PH-DA-283551-GO-RFQ / Su Component 4: Project Imple Single Stage - One Under Imple TF / B5756 Post Request for Bids Open - National 845,000.00 0.00 2022-08-15 2022-08-20 2022-10-01 2022-10-31 2022-12-05 2023-06-03 pply and delivery office equi mentation Support Envelope mentation pment PRDP-NPCO-087-GOO-002-2 Component 4: Project Imple Request for Quot Single Stage - One Pending Impl 022-EU / Supply and deliver TF / B5756 Post Open - National 29,781.00 0.00 2022-12-21 2023-02-15 2023-08-14 mentation Support ations Envelope ementation y of ICT equipment PRDP-NPCO-087-GOO-001-2 Component 4: Project Imple Single Stage - One Pending Impl 023-EU / Supply and deliver TF / B5756 Post Request for Bids Open - National 1,181,818.00 0.00 2023-02-05 2023-02-10 2023-03-24 2023-04-23 2023-05-28 2023-11-24 mentation Support Envelope ementation of service vehicles PRDP-NPCO-088-GOO-003-2 Component 4: Project Imple Request for Quot Single Stage - One Pending Impl TF / B5756 Post Open - National 17,760.00 0.00 2023-02-20 2023-04-17 2023-10-14 023-EU / Laptop Data for Pro mentation Support ations Envelope ementation cessing PRDP-NPCO-089-GOO-003-2 Component 4: Project Imple Request for Quot Single Stage - One Pending Impl 023-EU / Laptop for Image/V TF / B5756 Post Open - National 9,000.00 0.00 2023-02-20 2023-04-17 2023-10-14 mentation Support ations Envelope ementation ideo Processing PRDP-NPCO-090-GOO-003-2 Component 4: Project Imple Request for Quot Single Stage - One Pending Impl 023-EU / Desktop for Image/ TF / B5756 Post Open - National 6,000.00 0.00 2023-02-20 2023-04-17 2023-10-14 mentation Support ations Envelope ementation Video Processing & Hosting PRDP-IS-NPCO-001-2022-EU Component 4: Project Imple Request for Quot Single Stage - One Pending Impl / Supply and Delivery of lapt TF / B5756 Post Open - National 77,600.00 0.00 2022-01-14 2022-03-11 2022-09-07 mentation Support ations Envelope ementation op and desktop computers PRDP-NPCO-091-GOO-004-2 Component 4: Project Imple Request for Quot Single Stage - One Pending Impl TF / B5756 Post Open - National 4,410.50 0.00 2023-10-27 2023-11-09 2023-12-14 023-EU / Tablet 11 inches LE mentation Support ations Envelope ementation D Display PRDP-NPCO-092-GOO-004-2 Component 4: Project Imple Request for Quot Single Stage - One Pending Impl 023-EU / Laptop with Extrem TF / B5756 Post Open - National 4,410.50 0.00 2023-10-27 2023-11-09 2023-12-14 mentation Support ations Envelope ementation e Long Battery Life PRDP-NPCO-093-GOO-004-2 Component 4: Project Imple Request for Quot Single Stage - One Pending Impl TF / B5756 Post Open - National 6,615.74 0.00 2023-10-27 2023-11-13 2023-12-18 023-EU / Rotor Type Drone F mentation Support ations Envelope ementation VP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRAS No. 0076-N / Consulta ncy Services for the Conduct Component 1: Local and Na Fixed Budget Sel Open - Internation IBRD / 84210 Prior 371,145.98 371,145.91 Signed 2015-12-17 2015-12-30 of Value Chain Analysis of A tional Level Planning ection al griculture and Fisheries Com modities PRDP-NPCO-001-TA-008-20 23-AF2 / TECHNICAL ASSIST Component 4: Project Imple Consultant Qualifi Under Implement IBRD / 92710 Post Open - National 165,112.36 0.00 2023-04-14 2023-04-28 2023-05-12 2023-05-19 2023-05-24 2023-11-20 ANCE ON PRDP MAINSTREA mentation Support cation Selection ation MING (CONSULTANCY FIRM) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IS-NPCO-IB-001-000-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 9,882.35 19,451.95 Completed 2018-01-01 2017-12-14 2018-01-11 2017-12-22 2018-03-17 2018-01-09 2018-09-13 2020-01-06 018-AF / Alternate Compone mentation Support nt Head PRDP-IS-NPCO-IB-002-000-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 018-AF / Roads and Bridge S mentation Support pecialist PRDP-IS-NPCO-IB-003-001-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 018-AF / Roads Infrastructur mentation Support e Engineer PRDP-IS-NPCO-IB-003-002-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 018-AF / Roads Infrastructur mentation Support e Engineer PRDP-IS-NPCO-IB-003-003-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 018-AF / Roads Infrastructur mentation Support e Engineer PRDP-IS-NPCO-IB-003-004-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 018-AF / Roads Infrastructur mentation Support e Engineer PRDP-IS-NPCO-IB-003-005-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 018-AF / Roads Infrastructur mentation Support e Engineer PRDP-IS-NPCO-IB-003-006-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 018-AF / Roads Infrastructur mentation Support e Engineer PRDP-IS-NPCO-IB-003-007-2 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 018-AF / Roads Infrastructur mentation Support e Engineer PRDP-IS-NPCO-IB-004-001-2 Component 4: Project Imple 018-AF / Project Developme IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support nt Associate PRDP-IS-NPCO-IB-004-002-2 Component 4: Project Imple 018-AF / Project Developme IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support nt Associate PRDP-IS-NPCO-IB-004-003-2 Component 4: Project Imple 018-AF / Project Developme IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support nt Associate PRDP-IS-NPCO-OPD-001-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / Legal Officer mentation Support PRDP-IS-NPCO-OPD-002-00 Component 4: Project Imple 1-2018-AF / Project Develop IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ment Associate PRDP-IS-NPCO-OPD-002-00 Component 4: Project Imple 2-2018-AF / Project Develop IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ment Associate PRDP-IS-NPCO-DPD-001-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / Legal Officer mentation Support PRDP-IS-NPCO-DPD-002-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / Compliance Offi mentation Support cer PRDP-IS-NPCO-DPD-003-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / Executive Assist mentation Support ant PRDP-IS-NPCO-001-000-201 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 8-AF / I-Support Alternate U mentation Support nit Head PRDP-IS-NPCO-ADM-001-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 1-2018-AF / Admin Officer III mentation Support PRDP-IS-NPCO-ADM-001-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2-2018-AF / Admin Officer III mentation Support PRDP-IS-NPCO-ADM-002-00 Component 4: Project Imple 1-2018-AF / Admin Officer I / IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support Personnel Officer PRDP-IS-NPCO-ADM-002-00 Component 4: Project Imple 2-2018-AF / Admin Officer I / IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support Property and Supply Officer PRDP-IS-NPCO-ADM-003-00 Component 4: Project Imple Individual Consult 0-2018-AF / Administrative A IBRD / 84210 Post Direct 3,529.41 0.00 Canceled 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 mentation Support ant Selection ssistant / Staff PRDP-IS-NPCO-ADM-004-00 Component 4: Project Imple Individual Consult IBRD / 84210 Post Direct 3,529.41 0.00 Canceled 2018-01-01 2019-01-15 2018-01-11 2018-02-01 2018-03-08 2018-09-04 1-2018-AF / Cash Clerk mentation Support ant Selection PRDP-IS-NPCO-ADM-004-00 Component 4: Project Imple Individual Consult IBRD / 84210 Post Direct 3,529.41 0.00 Canceled 2018-01-01 2018-01-15 2018-01-11 2018-02-01 2018-03-08 2018-09-04 2-2018-AF / Cash Clerk mentation Support ant Selection PRDP-IS-NPCO-ADM-005-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 1-2018-AF / Chauffeur / Driv mentation Support er PRDP-IS-NPCO-ADM-005-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2-2018-AF / Chauffeur / Driv mentation Support er PRDP-IS-NPCO-ADM-005-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 3-2018-AF / Chauffeur / Driv mentation Support er Page 2 PRDP-IS-NPCO-ADM-005-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 4-2018-AF / Chauffeur / Driv mentation Support er PRDP-IS-NPCO-ADM-005-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 5-2018-AF / Chauffeur / Driv mentation Support er PRDP-IS-NPCO-ADM-005-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 6-2018-AF / Chauffeur / Driv mentation Support er PRDP-IS-NPCO-ADM-005-00 Component 4: Project Imple Individual Consult IBRD / 84210 Post Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 7-2018-AF / Chauffeur / Driv mentation Support ant Selection er PRDP-IS-NPCO-ADM-005-00 Component 4: Project Imple Individual Consult IBRD / 84210 Post Direct 2,823.53 0.00 Canceled 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 8-2018-AF / Chauffeur / Driv mentation Support ant Selection er PRDP-IS-NPCO-ADM-006-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 2,541.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / Messengerial St mentation Support aff PRDP-IS-NPCO-ADM-007-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 2,117.65 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / Utility Worker mentation Support PRDP-IS-NPCO-FIN-001-000- Component 4: Project Imple 2018-AF / LGU Finance / Alte IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support rnate Unit Head PRDP-IS-NPCO-FIN-002-000- Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Finance Analyst III mentation Support PRDP-IS-NPCO-FIN-003-000- Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Finance Analyst II mentation Support PRDP-IS-NPCO-FIN-004-000- Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Finance Analyst I mentation Support PRDP-IS-NPCO-FIN-005-000- Component 4: Project Imple 2018-AF / Project Developm IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ent Associate PRDP-IS-NPCO-ACC-001-001 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Financial Analyst mentation Support I PRDP-IS-NPCO-ACC-001-002 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Financial Analyst mentation Support I PRDP-IS-NPCO-ACC-001-003 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Financial Analyst mentation Support I PRDP-IS-NPCO-BUD-001-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 1-2018-AF / Budget Analyst I mentation Support PRDP-IS-NPCO-BUD-001-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2-2018-AF / Budget Analyst I mentation Support PRDP-IS-NPCO-PRO-001-000 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Alternate Unit He mentation Support ad PRDP-IS-NPCO-PRO-002-001 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Procurement Spe mentation Support cialist PRDP-IS-NPCO-PRO-002-002 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Procurement Spe mentation Support cialist PRDP-IS-NPCO-PRO-003-001 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Procurement Offi mentation Support cer PRDP-IS-NPCO-PRO-003-002 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Procurement Offi mentation Support cer PRDP-IS-NPCO-PRO-003-003 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Procurement Offi mentation Support cer PRDP-IS-NPCO-PRO-004-001 Component 4: Project Imple -2018-AF / Associate Procure IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ment Officer PRDP-IS-NPCO-PRO-004-002 Component 4: Project Imple -2018-AF / Associate Procure IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ment Officer PRDP-IS-NPCO-PRO-005-001 Component 4: Project Imple -2018-AF / Project Developm IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ent Associate PRDP-IS-NPCO-PRO-005-002 Component 4: Project Imple -2018-AF / Project Developm IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ent Associate PRDP-IS-NPCO-MAE-001-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 10,588.24 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / M&E Unit Head mentation Support PRDP-IS-NPCO-MAE-002-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / M&E Alternate U mentation Support nit Head PRDP-IS-NPCO-MAE-003-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 1-2018-AF / M&E Specialist mentation Support PRDP-IS-NPCO-MAE-003-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2-2018-AF / M&E Specialist mentation Support PRDP-IS-NPCO-MAE-004-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / M&E Officer mentation Support PRDP-IS-NPCO-MAE-005-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / MIS Officer mentation Support PRDP-IS-NPCO-MAE-006-00 Component 4: Project Imple 0-2018-AF / Project Develop IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ment Associate PRDP-IS-NPCO-SES-001-000 Component 4: Project Imple -2018-AF / Environmental Sa IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support feguards Specialist PRDP-IS-NPCO-SES-002-000 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Social Safeguard mentation Support Specialist Page 3 PRDP-IS-NPCO-SES-003-000 Component 4: Project Imple -2018-AF / Environmental Sa IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support feguards Officer PRDP-IS-NPCO-SES-004-000 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Social Safeguard mentation Support Officer PRDP-IS-NPCO-SES-005-000 Component 4: Project Imple -2018-AF / Project Developm IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ent Associate PRDP-IS-NPCO-GGU-001-00 Component 4: Project Imple 0-2018-AF / Geomapping an IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support d Governance Alternate Unit Head PRDP-IS-NPCO-GGU-002-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 0-2018-AF / GIS Data Officer mentation Support PRDP-IS-NPCO-GGU-003-00 Component 4: Project Imple 0-2018-AF / Project Develop IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ment Associate PRDP-IS-NPCO-INF-001-000- Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 6,352.94 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Web Administrato mentation Support r PRDP-IS-NPCO-INF-002-000- Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Graphics / Layout mentation Support Artist PRDP-IS-NPCO-INF-003-001- Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Photographer / Vi mentation Support deographer PRDP-IS-NPCO-INF-003-002- Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Photographer / Vi mentation Support deographer PRDP-IS-NPCO-INF-004-000- Component 4: Project Imple 2018-AF / Project Developm IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ent Associate PRDP-IS-NPCO-ECO-001-00 Component 4: Project Imple 0-2018-AF / Economics Alter IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support nate Unit Head PRDP-IS-NPCO-ECO-002-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 1-2018-AF / Associate Econo mentation Support mist PRDP-IS-NPCO-ECO-002-00 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2-2018-AF / Associate Econo mentation Support mist PRDP-IS-NPCO-ECO-003-00 Component 4: Project Imple 0-2018-AF / Project Develop IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ment Associate PRDP-IS-NPCO-GEF-001-000 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 10,588.24 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / GEF NRM Unit He mentation Support ad PRDP-IS-NPCO-GEF-002-000 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / GEF NRM Officer mentation Support PRDP-IS-NPCO-GEF-003-001 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Regional GEF NR mentation Support M Officer PRDP-IS-NPCO-GEF-003-002 Component 4: Project Imple IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 -2018-AF / Regional GEF NR mentation Support M Officer PRDP-IS-NPCO-GEF-004-000 Component 4: Project Imple -2018-AF / Project Developm IBRD / 84210 Post Direct Selection Direct 4,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 mentation Support ent Associate PRDP-IS-NPCO-001-IB-001-2 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 20,377.36 20,832.93 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 019-AF / Alternate Compone mentation Support ant Selection nt Head PRDP-IS-NPCO-002-IB-002-2 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 14,943.40 15,290.16 Completed 2019-04-01 2018-11-12 2019-05-20 2019-01-03 2019-06-10 2019-01-03 2019-07-15 2019-01-18 2020-01-11 2020-01-15 019-AF / Rural Infrastructure mentation Support ant Selection Specialist PRDP-IS-NPCO-003-IB-003-2 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,900.15 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 019-AF / Roads Infrastructur mentation Support ant Selection e Engineer PRDP-IS-NPCO-004-IB-004-2 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,900.15 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 019-AF / Roads Infrastructur mentation Support ant Selection e Engineer PRDP-IS-NPCO-005-IB-005-2 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,888.62 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-23 2019-09-04 2020-01-20 019-AF / Roads Infrastructur mentation Support ant Selection e Engineer PRDP-IS-NPCO-006-IB-006-2 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,900.15 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 019-AF / Roads Infrastructur mentation Support ant Selection e Engineer PRDP-IS-NPCO-007-IB-007-2 Component 4: Project Imple Individual Consult 019-AF / Project Developme IBRD / 88160 Post Direct 9,509.43 9,730.10 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 mentation Support ant Selection nt Associate PRDP-IS-NPCO-008-ISP-001- Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 20,377.36 20,922.13 Completed 2019-01-01 2018-11-20 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 2019-AF / I-Support Alternat mentation Support ant Selection e Unit Head PRDP-IS-NPCO-012-OPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 16,301.89 16,761.07 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 1-2019-AF / Legal Officer mentation Support ant Selection PRDP-IS-NPCO-013-OPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 9,509.43 9,777.29 Completed 2019-04-01 2018-11-12 2019-05-20 2019-01-03 2019-06-10 2019-01-03 2019-07-15 2019-01-18 2020-01-11 2020-01-15 2-2019-AF / Administrative mentation Support ant Selection Officer II PRDP-IS-NPCO-014-OPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 7,471.70 5,664.83 Completed 2019-04-01 2019-01-13 2019-05-20 2019-03-21 2019-06-10 2019-04-01 2019-07-15 2019-04-10 2020-01-11 2020-01-12 3-2019-AF / Administrative mentation Support ant Selection Officer I PRDP-IS-NPCO-015-DPD-00 Component 4: Project Imple Individual Consult 1-2019-AF / Senior Project D IBRD / 88160 Post Open 12,226.42 12,673.58 Completed 2019-04-01 2019-01-18 2019-05-20 2019-03-14 2019-06-10 2019-03-14 2019-07-15 2019-04-10 2020-01-11 2020-01-12 mentation Support ant Selection evelopment Specialist PRDP-IS-NPCO-016-DPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 7,924.53 4,107.18 Completed 2019-04-01 2019-06-05 2019-05-20 2019-07-26 2019-06-10 2019-07-15 2019-08-10 2020-01-11 2020-01-12 2-2019-AF / Administrative mentation Support ant Selection Officer II PRDP-IS-NPCO-017-DPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 7,924.53 7,392.92 Completed 2019-04-01 2019-01-18 2019-05-20 2019-03-21 2019-06-10 2019-03-29 2019-07-15 2019-04-10 2020-01-11 2020-01-12 3-2019-AF / Administrative mentation Support ant Selection Officer II PRDP-IS-NPCO-019-DPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 14,943.40 12,673.58 Completed 2019-04-01 2019-01-18 2019-05-20 2019-03-21 2019-06-10 2019-03-29 2019-07-15 2019-04-10 2020-01-11 2020-01-12 5-2019-AF / Senior Economis mentation Support ant Selection t Page 4 PRDP-IS-NPCO-020-DPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,907.67 Completed 2019-01-01 2018-11-19 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 6-2019-AF / Economist mentation Support ant Selection PRDP-IS-NPCO-021-DPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 9,509.43 10,561.31 Completed 2019-04-01 2019-01-18 2019-05-20 2019-03-21 2019-06-10 2019-03-21 2019-07-15 2019-04-10 2020-01-11 2020-01-12 7-2019-AF / Economist mentation Support ant Selection PRDP-IS-NPCO-022-ADM-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 10,867.92 9,777.29 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 1-2019-AF / Supply & Proper mentation Support ant Selection ty Officer PRDP-IS-NPCO-023-ADM-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 10,867.92 11,165.17 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 2-2019-AF / Administrative mentation Support ant Selection Officer III PRDP-IS-NPCO-024-ADM-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 9,509.43 11,165.17 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 3-2019-AF / Administrative mentation Support ant Selection Officer III PRDP-IS-NPCO-025-ADM-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 6,792.45 9,769.53 Completed 2019-04-01 2018-11-12 2019-05-20 2019-01-03 2019-06-10 2019-01-03 2019-07-15 2019-01-18 2020-01-11 2020-01-15 4-2019-AF / Administrative mentation Support ant Selection Officer II PRDP-IS-NPCO-039-GGU-00 Component 4: Project Imple Individual Consult 1-2019-AF / Geomapping & IBRD / 88160 Post Direct 19,018.87 20,861.51 Completed 2019-01-01 2018-11-11 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 mentation Support ant Selection Governance Alternate Unit H ead PRDP-IS-NPCO-040-GGU-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,900.15 Completed 2019-01-01 2018-11-11 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 2-2019-AF / GIS Officer mentation Support ant Selection PRDP-IS-NPCO-041-FIN-001- Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 19,018.87 19,470.74 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-18 2019-09-04 2020-01-15 2019-AF / Alternate Unit Hea mentation Support ant Selection d PRDP-IS-NPCO-042-FIN-002- Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,907.67 Completed 2019-04-01 2018-11-12 2019-04-11 2019-01-03 2019-05-02 2019-01-03 2019-06-06 2019-01-18 2019-12-03 2020-01-08 2019-AF / Financial Analyst I mentation Support ant Selection I PRDP-IS-NPCO-044-FIN-004- Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 12,452.83 7,081.04 Completed 2019-04-01 2018-11-12 2019-05-20 2019-06-18 2019-06-10 2019-06-24 2019-07-15 2019-07-05 2020-01-11 2020-01-05 2019-AF / Financial Analyst I mentation Support ant Selection I PRDP-IS-NPCO-045-ACT-001 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 12,226.42 12,510.13 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 -2019-AF / Financial Analyst mentation Support ant Selection I PRDP-IS-NPCO-046-ACT-002 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Direct 12,226.42 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 -2019-AF / Financial Analyst mentation Support ant Selection ntation I PRDP-IS-NPCO-047-ACT-003 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 12,226.42 12,510.13 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 -2019-AF / Financial Analyst mentation Support ant Selection I PRDP-IS-NPCO-048-BUD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 12,226.42 12,510.13 Completed 2019-01-01 2018-11-07 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 1-2019-AF / Budget Analyst mentation Support ant Selection PRDP-IS-NPCO-049-BUD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 12,226.42 12,510.13 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 2-2019-AF / Budget Analyst mentation Support ant Selection PRDP-IS-NPCO-050-BUD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 9,169.81 8,494.24 Completed 2019-04-01 2019-01-18 2019-05-20 2019-05-16 2019-06-10 2019-05-20 2019-07-15 2019-05-24 2020-01-11 2020-01-05 3-2019-AF / Budget Analyst mentation Support ant Selection PRDP-IS-NPCO-051-PRO-001 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 19,018.87 19,470.74 Completed 2019-01-01 2018-11-09 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 -2019-AF / Alternate Unit He mentation Support ant Selection ad PRDP-IS-NPCO-052-PRO-002 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 14,943.40 15,298.44 Completed 2019-01-01 2018-11-09 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 -2019-AF / Procurement Spe mentation Support ant Selection cialist PRDP-IS-NPCO-053-PRO-003 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,907.67 Completed 2019-01-01 2018-11-09 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 -2019-AF / Procurement Offi mentation Support ant Selection cer PRDP-IS-NPCO-054-PRO-004 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 13,584.91 13,907.67 Completed 2019-01-01 2018-11-09 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 -2019-AF / Procurement Offi mentation Support ant Selection cer PRDP-IS-NPCO-055-PRO-00- Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 9,169.81 9,516.35 Completed 2019-04-01 2019-01-19 2019-05-20 2019-03-21 2019-06-10 2019-03-21 2019-07-15 2019-04-02 2020-01-11 2020-01-05 2019-AF / Associate Procure mentation Support ant Selection ment Officer PRDP-IS-NPCO-056-MNE-00 Component 4: Project Imple Individual Consult 1-2019-AF / Monitoring & Ev IBRD / 88160 Post Direct 20,377.36 20,861.51 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 mentation Support ant Selection aluation Unit Head PRDP-IS-NPCO-057-MNE-00 Component 4: Project Imple Individual Consult 2-2019-AF / Monitoring & Ev IBRD / 88160 Post Direct 19,018.87 0.00 Canceled 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 mentation Support ant Selection aluation Alternate Head PRDP-IS-NPCO-059-MNE-00 Component 4: Project Imple Individual Consult 4-2019-AF / Monitoring & Ev IBRD / 88160 Post Direct 14,943.40 15,298.44 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 mentation Support ant Selection aluation Specialist PRDP-IS-NPCO-060-MNE-00 Component 4: Project Imple Individual Consult 5-2019-AF / Monitoring & Ev IBRD / 88160 Post Open 12,226.42 11,639.63 Completed 2019-04-01 2019-01-15 2019-05-20 2019-03-04 2019-06-10 2019-03-11 2019-07-15 2019-03-21 2020-01-11 2020-01-08 mentation Support ant Selection aluation Officer PRDP-IS-NPCO-061-SES-001 Component 4: Project Imple Individual Consult -2019-AF / Social & Environ IBRD / 88160 Post Direct 14,943.40 15,298.44 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 mentation Support ant Selection ment Safeguards Specialist PRDP-IS-NPCO-062-SES-002 Component 4: Project Imple Individual Consult -2019-AF / Social & Environ IBRD / 88160 Post Direct 13,584.91 13,907.67 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 mentation Support ant Selection ment Safeguards Officer PRDP-IS-NPCO-063-SES-003 Component 4: Project Imple Individual Consult -2019-AF / Social & Environ IBRD / 88160 Post Direct 13,584.91 13,907.67 Completed 2019-01-01 2018-11-12 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-11 2019-09-04 2020-01-08 mentation Support ant Selection ment Safeguards Officer PRDP-IS-NPCO-064-SES-004 Component 4: Project Imple Individual Consult -2019-AF / Associate Social IBRD / 88160 Post Open 12,226.42 8,494.24 Completed 2019-04-01 2019-03-24 2019-05-20 2019-05-16 2019-06-10 2019-05-16 2019-07-15 2019-05-24 2020-01-11 2020-01-05 mentation Support ant Selection & Environment Safeguards Officer PRDP-IS-NPCO-066-ICE-002- Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 12,226.42 10,617.80 Completed 2019-04-01 2019-01-18 2019-05-20 2019-03-04 2019-06-10 2019-03-04 2019-07-15 2019-03-13 2020-01-11 2019-06-04 2019-AF / Writer mentation Support ant Selection PRDP-IS-NPCO-067-ICE-003- Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 7,523.51 Completed 2019-04-01 2019-03-15 2019-05-20 2019-05-14 2019-06-10 2019-05-14 2019-07-15 2019-05-19 2020-01-11 2020-01-05 2019-AF / Media Production mentation Support ant Selection Officer PRDP-IS-NPCO-068-R00-001 Component 4: Project Imple Individual Consult -2019-AF / Rural Infrastructu IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 mentation Support ant Selection re Specialist PRDP-IS-NPCO-069-R00-002 Component 4: Project Imple Individual Consult -2019-AF / Rural Infrastructu IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 mentation Support ant Selection re Specialist PRDP-IS-NPCO-070-R00-003 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer Page 5 PRDP-IS-NPCO-071-R00-004 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-072-R00-005 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-073-R00-006 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-074-R00-007 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-075-R00-008 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-076-R00-009 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-077-R00-010 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-078-R00-011 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-079-R00-012 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-080-R00-013 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 8,150.94 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 -2019-AF / Rural Infrastructu mentation Support ant Selection re Engineer PRDP-IS-NPCO-081-R00-001 Component 4: Project Imple Individual Consult -2019-AF / Web-based Finan IBRD / 88160 Post Open 15,094.34 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 mentation Support ant Selection cial Management System PRDP-IS-NPCO-082-OPD-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 3,735.85 3,872.48 Completed 2019-01-01 2018-11-28 2019-01-11 2018-12-28 2019-02-01 2018-12-28 2019-03-08 2019-01-08 2019-09-04 2019-04-04 4-2019-AF / Compliance Offi mentation Support ant Selection cer PRDP-IS-NPCO-083-OPD-00 Component 4: Project Imple Individual Consult 5-2019-AF / Project Develop IBRD / 88160 Post Direct 2,377.36 0.00 Canceled 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-06-06 mentation Support ant Selection ment Associate PRDP-IS-NPCO-084-OPD-00 Component 4: Project Imple Individual Consult 6-2019-AF / Project Develop IBRD / 88160 Post Direct 2,377.36 2,467.20 Completed 2019-01-01 2018-11-28 2019-01-11 2018-12-28 2019-02-01 2019-01-03 2019-03-08 2019-01-08 2019-09-04 2019-04-04 mentation Support ant Selection ment Associate PRDP-IS-NPCO-085-PRO-006 Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 3,396.23 3,185.34 Completed 2019-01-01 2018-12-18 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-08 2019-03-17 2019-04-04 -2019-AF / Procurement Offi mentation Support ant Selection cer PRDP-IS-NPCO-086-PRO-007 Component 4: Project Imple Individual Consult -2019-AF / Associate Procure IBRD / 88160 Post Direct 3,056.60 3,185.34 Completed 2019-01-01 2018-12-18 2019-01-11 2019-01-03 2019-02-01 2019-01-03 2019-03-08 2019-01-08 2019-09-04 2019-04-04 mentation Support ant Selection ment Officer PRDP-IS-NPCO-087-ICE-004- Component 4: Project Imple Individual Consult IBRD / 88160 Post Direct 2,716.98 2,819.66 Completed 2019-01-01 2018-11-28 2019-01-11 2018-12-28 2019-02-01 2019-03-08 2019-01-08 2019-03-17 2019-04-04 2019-AF / Graphic and Lay o mentation Support ant Selection ut Artist PRDP-IS-NPCO-088-FIN-005- Component 4: Project Imple Individual Consult 2019-AF / Project Developm IBRD / 88160 Post Direct 2,377.36 2,467.20 Completed 2019-01-01 2018-12-28 2019-01-11 2018-12-28 2019-02-01 2018-12-28 2019-03-08 2019-01-08 2019-09-04 2019-04-04 mentation Support ant Selection ent Associate PRDP-IS-NPCO-001-IB-001-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 21,176.47 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 020-AF / Alternate Compone mentation Support ant Selection ation nt Head PRDP-IS-NPCO-002-IB-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 15,529.41 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 020-AF / Rural Infrastructure mentation Support ant Selection ation Specialist PRDP-IS-NPCO-003-IB-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 14,117.64 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 020-AF / Roads Infrastructur mentation Support ant Selection ation e Engineer PRDP-IS-NPCO-004-IB-004-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 020-AF / Roads Infrastructur mentation Support ant Selection ation e Engineer PRDP-IS-NPCO-005-IB-005-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 020-AF / Roads Infrastructur mentation Support ant Selection ntation e Engineer PRDP-IS-NPCO-006-IB-006-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 84210 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 020-AF / Roads Infrastructur mentation Support ant Selection ation e Engineer PRDP-IS-NPCO-007-IB-007-2 Component 4: Project Imple Individual Consult Under Implement 020-AF / Project Developme IBRD / 88160 Post Direct 9,882.35 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 mentation Support ant Selection ation nt Associate PRDP-IS-NPCO-008-ISP-001- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 21,176.47 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2020-AF / I-Support Alternat mentation Support ant Selection ation e Unit Head PRDP-IS-NPCO-012-OPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 16,941.18 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 1-2020-AF / Legal Officer mentation Support ant Selection ation PRDP-IS-NPCO-013-OPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 9,882.35 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2-2020-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-014-OPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 7,764.71 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 3-2020-AF / Administrative mentation Support ant Selection ation Officer I PRDP-IS-NPCO-015-DPD-00 Component 4: Project Imple Individual Consult Under Implement 1-2020-AF / Senior Project D IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 mentation Support ant Selection ation evelopment Specialist PRDP-IS-NPCO-016-DPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 8,235.29 0.00 2020-01-02 2020-04-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2-2020-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-017-DPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 8,235.29 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 3-2020-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-020-DPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 6-2020-AF / Economist mentation Support ant Selection ation PRDP-IS-NPCO-021-DPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 9,882.35 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 7-2020-AF / Economist mentation Support ant Selection ation PRDP-IS-NPCO-022-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 11,294.12 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 1-2020-AF / Supply & Proper mentation Support ant Selection ation ty Officer PRDP-IS-NPCO-023-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 11,294.12 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2-2020-AF / Administrative mentation Support ant Selection ation Officer III Page 6 PRDP-IS-NPCO-024-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 9,882.35 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 3-2020-AF / Administrative mentation Support ant Selection ation Officer III PRDP-IS-NPCO-025-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 7,058.82 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 4-2020-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-039-GGU-00 Component 4: Project Imple Individual Consult Under Implement 1-2020-AF / Geomapping & IBRD / 88160 Post Direct 19,764.71 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 mentation Support ant Selection ation Governance Alternate Unit H ead PRDP-IS-NPCO-040-GGU-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 2-2020-AF / GIS Officer mentation Support ant Selection ation PRDP-IS-NPCO-041-FIN-001- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 19,764.71 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2020-AF / Alternate Unit Hea mentation Support ant Selection ation d PRDP-IS-NPCO-042-FIN-002- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2020-AF / Financial Analyst I mentation Support ant Selection ation I PRDP-IS-NPCO-043-FIN-003- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 12,941.18 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 2020-AF / Financial Analyst I mentation Support ant Selection ation I PRDP-IS-NPCO-044-FIN-004- Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 12,941.18 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 2020-AF / Financial Analyst I mentation Support ant Selection ntation I PRDP-IS-NPCO-045-ACT-001 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 12,705.88 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 -2020-AF / Financial Analyst mentation Support ant Selection ntation I PRDP-IS-NPCO-046-ACT-002 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 -2020-AF / Financial Analyst mentation Support ant Selection ation I PRDP-IS-NPCO-047-ACT-003 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 -2020-AF / Financial Analyst mentation Support ant Selection ation I PRDP-IS-NPCO-048-BUD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 1-2020-AF / Budget Analyst mentation Support ant Selection ation PRDP-IS-NPCO-049-BUD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2-2020-AF / Budget Analyst mentation Support ant Selection ation PRDP-IS-NPCO-050-BUD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 9,529.41 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 3-2020-AF / Budget Analyst mentation Support ant Selection ation PRDP-IS-NPCO-051-PRO-001 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 19,764.71 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 -2020-AF / Alternate Unit He mentation Support ant Selection ation ad PRDP-IS-NPCO-052-PRO-002 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 15,529.41 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 -2020-AF / Procurement Spe mentation Support ant Selection ation cialist PRDP-IS-NPCO-053-PRO-003 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 -2020-AF / Procurement Offi mentation Support ant Selection ation cer PRDP-IS-NPCO-054-PRO-004 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 -2020-AF / Procurement Offi mentation Support ant Selection ation cer PRDP-IS-NPCO-055-PRO-00- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 9,529.41 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2020-AF / Associate Procure mentation Support ant Selection ation ment Officer PRDP-IS-NPCO-056-MNE-00 Component 4: Project Imple Individual Consult Under Implement 1-2020-AF / Monitoring & Ev IBRD / 88160 Post Direct 21,176.47 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 mentation Support ant Selection ation aluation Unit Head PRDP-IS-NPCO-057-MNE-00 Component 4: Project Imple Individual Consult Pending Impleme 2-2020-AF / Monitoring & Ev IBRD / 88160 Post Open 19,764.71 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 mentation Support ant Selection ntation aluation Alternate Head PRDP-IS-NPCO-058-MNE-00 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 3,882.35 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 3-2020-AF / MIS Specialist mentation Support ant Selection ntation PRDP-IS-NPCO-059-MNE-00 Component 4: Project Imple Individual Consult Under Implement 4-2020-AF / Monitoring & Ev IBRD / 88160 Post Open 15,529.41 0.00 2020-01-02 2020-01-02 2020-02-20 2020-03-12 2020-04-16 2020-10-13 mentation Support ant Selection ation aluation Specialist PRDP-IS-NPCO-060-MNE-00 Component 4: Project Imple Individual Consult Under Implement 5-2020-AF / Monitoring & Ev IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 mentation Support ant Selection ation aluation Officer PRDP-IS-NPCO-061-SES-001 Component 4: Project Imple Individual Consult Under Implement -2020-AF / Social & Environ IBRD / 88160 Post Direct 15,529.41 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 mentation Support ant Selection ation ment Safeguards Specialist PRDP-IS-NPCO-062-SES-002 Component 4: Project Imple Individual Consult Under Implement -2020-AF / Social & Environ IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 mentation Support ant Selection ation ment Safeguards Officer PRDP-IS-NPCO-063-SES-003 Component 4: Project Imple Individual Consult Under Implement -2020-AF / Social & Environ IBRD / 88160 Post Direct 14,117.65 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 mentation Support ant Selection ation ment Safeguards Officer PRDP-IS-NPCO-064-SES-004 Component 4: Project Imple Individual Consult Under Implement -2020-AF / Associate Social IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 mentation Support ant Selection ation & Environment Safeguards Officer PRDP-IS-NPCO-065-ICE-001- Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 15,529.41 0.00 2020-03-02 2020-04-20 2020-05-11 2020-06-15 2020-12-12 2020-AF / Information Speci mentation Support ant Selection ntation alist PRDP-IS-NPCO-066-ICE-002- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 12,705.88 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 2020-AF / Writer mentation Support ant Selection ation PRDP-IS-NPCO-067-ICE-003- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 8,470.59 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-12-31 2020-AF / Media Production mentation Support ant Selection ation Officer PRDP-IS-NPCO-001-IB-001-2 Component 4: Project Imple Individual Consult Under Implement 021-AF / Alternate IBUILD Co IBRD / 88160 Post Direct 9,375.00 0.00 2021-01-03 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 mentation Support ant Selection ation mponent Head PRDP-IS-NPCO-002-IB-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,875.00 0.00 2021-01-03 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 021-AF / Rural Infrastructure mentation Support ant Selection ation Specialist PRDP-IS-NPCO-003-IB-003-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Direct 6,875.00 0.00 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 021-AF / Roads Infrastructur mentation Support ant Selection ntation e Engineer PRDP-IS-NPCO-004-IB-004-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,875.00 0.00 2021-01-03 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 021-AF / Roads Infrastructur mentation Support ant Selection ation e Engineer Page 7 PRDP-IS-NPCO-005-IB-005-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,875.00 0.00 2021-01-03 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 021-AF / Roads Infrastructur mentation Support ant Selection ation e Engineer PRDP-IS-NPCO-006-IB-006-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,875.00 0.00 2021-01-03 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 021-AF / Roads Infrastructur mentation Support ant Selection ation e Engineer PRDP-IS-NPCO-007-IB-007-2 Component 4: Project Imple Individual Consult Under Implement 021-AF / Project Developme IBRD / 88160 Post 4,375.00 0.00 2021-01-03 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 mentation Support ant Selection ation nt Associate PRDP-IS-NPCO-008-ISP-001- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 9,375.00 0.00 2021-01-03 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 2021-AF / I-Support Alternat mentation Support ant Selection ation e Unit Head PRDP-IS-NPCO-009-OPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Open 7,500.00 0.00 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 1-2021-AF / Legal Officer mentation Support ant Selection ation PRDP-IS-NPCO-010-OPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Open 4,375.00 0.00 2021-01-03 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 2-2021-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-011-OPD-00 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Direct 3,750.00 0.00 2020-12-21 2020-12-27 2020-12-28 2021-02-01 2021-06-30 3-2021-AF / Administrative mentation Support ant Selection ntation Officer I PRDP-IS-NPCO-012-DPD-00 Component 4: Project Imple Individual Consult Under Implement 4-2021-AF / Senior Project D IBRD / 88160 Post Direct 7,500.00 0.00 2021-01-03 2021-01-03 2021-01-13 2021-02-03 2021-03-10 2021-09-06 mentation Support ant Selection ation evelopment Specialist PRDP-IS-NPCO-013-DPD-00 Component 4: Project Imple Individual Consult Pending Impleme 5-2021-AF / Senior Institutio IBRD / 88160 Post Open 4,500.00 0.00 2021-01-04 2021-02-22 2021-03-15 2021-04-19 2021-06-30 mentation Support ant Selection ntation nal Development Specialist PRDP-IS-NPCO-014-DPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 4,375.00 0.00 2021-01-05 2021-01-05 2021-01-15 2021-02-05 2021-03-12 2021-09-08 6-2021-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-016-DPD-00 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 3,750.00 0.00 2021-01-07 2021-02-25 2021-03-18 2021-04-22 2021-10-19 8-2021-AF / Compliance Offi mentation Support ant Selection ntation cer PRDP-IS-NPCO-017-DPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 7,500.00 0.00 2021-01-08 2020-01-08 2021-01-18 2021-02-08 2021-03-15 2021-09-11 9-2021-AF / Senior Economis mentation Support ant Selection ation t PRDP-IS-NPCO-018-DPD-01 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,250.00 0.00 2021-01-09 2021-01-11 2021-01-19 2021-02-09 2021-03-16 2021-09-12 0-2021-AF / Economist mentation Support ant Selection ation PRDP-IS-NPCO-019-DPD-01 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,250.00 0.00 2021-01-10 2021-01-11 2021-01-20 2021-02-10 2021-03-17 2021-09-13 1-2021-AF / Economist mentation Support ant Selection ation PRDP-IS-NPCO-020-ADM-00 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 5,250.00 0.00 2021-01-11 2021-03-01 2021-03-22 2021-04-26 2021-10-23 1-2021-AF / Alternate Admin mentation Support ant Selection ntation Unit Head PRDP-IS-NPCO-025-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Open 5,250.00 0.00 2021-01-16 2021-01-15 2021-03-06 2021-03-27 2021-05-01 2021-10-28 6-2021-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-026-GGU-00 Component 4: Project Imple Individual Consult Under Implement 1-2021-AF / Geomapping & IBRD / 88160 Post Direct 8,750.00 0.00 2021-01-17 2021-01-15 2021-01-27 2021-02-17 2021-03-24 2021-09-20 mentation Support ant Selection ation Governance Alternate Unit H ead PRDP-IS-NPCO-027-GGU-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 8,250.00 0.00 2021-01-18 2021-01-18 2021-01-28 2021-02-18 2021-03-25 2021-09-21 2-2021-AF / GIS Officer mentation Support ant Selection ation PRDP-IS-NPCO-028-GGU-00 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 6,250.00 0.00 2021-01-19 2021-03-09 2021-03-30 2021-05-04 2021-10-31 3-2021-AF / GIS Specialist mentation Support ant Selection ntation PRDP-IS-NPCO-029-GGU-00 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 6,250.00 0.00 2021-01-20 2021-03-10 2021-03-31 2021-05-05 2021-11-01 4-2021-AF / GIS Officer mentation Support ant Selection ntation PRDP-IS-NPCO-030-FIN-001- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 10,500.00 0.00 2021-01-21 2021-01-21 2021-01-31 2021-02-21 2021-03-28 2021-09-24 2021-AF / Alternate Finance mentation Support ant Selection ation Unit Head PRDP-IS-NPCO-019-DPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 15,529.41 0.00 2020-01-02 2020-01-02 2020-01-12 2020-02-02 2020-03-08 2020-09-04 5-20120-AF / Senior Econom mentation Support ant Selection ation ist PRDP-IS-NPCO-033-FIN-004- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Open 7,500.00 0.00 2021-01-03 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 2021-AF / Financial Analyst I mentation Support ant Selection ation I PRDP-IS-NPCO-034-FIN-005- Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 7,500.00 0.00 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 2021-AF / Financial Analyst I mentation Support ant Selection ntation I PRDP-IS-NPCO-044-PRO-006 Component 4: Project Imple Individual Consult Under Implement -2021-AF / Associate Procure IBRD / 88160 Post Open 6,750.00 0.00 2021-01-03 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 mentation Support ant Selection ation ment Officer PRDP-IS-NPCO-046-MNE-00 Component 4: Project Imple Individual Consult Under Implement 2-2021-AF / Monitoring & Ev IBRD / 88160 Post Open 6,875.00 0.00 2021-01-03 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 mentation Support ant Selection ation aluation Alternate Head PRDP-IS-NPCO-047-MNE-00 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 4,125.00 0.00 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 3-2021-AF / MIS Specialist mentation Support ant Selection ntation PRDP-IS-NPCO-049-MNE-00 Component 4: Project Imple Individual Consult Pending Impleme 5-2021-AF / Monitoring & Ev IBRD / 88160 Post Open 7,500.00 0.00 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 mentation Support ant Selection ntation aluation Officer PRDP-IS-NPCO-054-ICE-001- Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open 6,875.00 0.00 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 2021-AF / Information Speci mentation Support ant Selection ntation alist PRDP-IS-NPCO-055-ICE-002- Component 4: Project Imple Individual Consult Pending Impleme 2021-AF / Knowledge Manag IBRD / 88160 Post Open 4,125.00 0.00 2021-01-03 2021-02-21 2021-03-14 2021-04-18 2021-10-15 mentation Support ant Selection ntation ement Specialist PRDP-IS-NPCO-043-FIN-003- Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 12,452.83 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 2019-AF / Financial Analyst I mentation Support ant Selection I PRDP-IS-NPCO-058-MNE-00 Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 3,735.85 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 3-2019-AF / MIS Specialist mentation Support ant Selection PRDP-IS-NPCO-065-ICE-001- Component 4: Project Imple Individual Consult IBRD / 88160 Post Open 14,943.40 0.00 Canceled 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 2019-AF / Information Speci mentation Support ant Selection alist PRDP-IS-NPCO-015-DPD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 4,375.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 7-2021-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-021-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 5,250.00 0.00 2020-12-18 2020-11-19 2020-12-28 2021-01-18 2021-02-22 2021-08-21 2-2021-AF / Supply & Proper mentation Support ant Selection ation ty Officer PRDP-IS-NPCO-022-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,000.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 3-2021-AF / Administrative mentation Support ant Selection ation Officer III Page 8 PRDP-IS-NPCO-023-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,000.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 4-2021-AF / Administrative mentation Support ant Selection ation Officer III PRDP-IS-NPCO-024-ADM-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 5,250.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 5-2021-AF / Administrative mentation Support ant Selection ation Officer II PRDP-IS-NPCO-031-FIN-002- Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Direct 8,250.00 0.00 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 2021-AF / Financial Analyst I mentation Support ant Selection ntation II PRDP-IS-NPCO-032-FIN-003- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 7,500.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 2021-AF / Financial Analyst I mentation Support ant Selection ation I PRDP-IS-NPCO-035-ACT-001 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Direct 6,750.00 0.00 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 -2021-AF / Financial Analyst mentation Support ant Selection ntation II PRDP-IS-NPCO-036-ACT-002 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Direct 6,750.00 0.00 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 -2021-AF / Financial Analyst mentation Support ant Selection ntation II PRDP-IS-NPCO-037-BUD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,750.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 1-2021-AF / Budget Analyst mentation Support ant Selection ation PRDP-IS-NPCO-038-BUD-00 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,750.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 2-2021-AF / Budget Analyst mentation Support ant Selection ation PRDP-IS-NPCO-039-PRO-001 Component 4: Project Imple Individual Consult Under Implement -2021-AF / Alternate Procure IBRD / 88160 Post Direct 8,750.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 mentation Support ant Selection ation ment Unit Head PRDP-IS-NPCO-040-PRO-002 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,875.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 -2021-AF / Procurement Spe mentation Support ant Selection ation cialist PRDP-IS-NPCO-041-PRO-003 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 7,500.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 -2021-AF / Procurement Offi mentation Support ant Selection ation cer PRDP-IS-NPCO-042-PRO-004 Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 7,500.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 -2021-AF / Procurement Offi mentation Support ant Selection ation cer PRDP-IS-NPCO-043-PRO-005 Component 4: Project Imple Individual Consult Under Implement -2021-AF / Associate Procure IBRD / 88160 Post Direct 6,750.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 mentation Support ant Selection ation ment Officer PRDP-IS-NPCO-048-MNE-00 Component 4: Project Imple Individual Consult Under Implement 4-2021-AF / Monitoring & Ev IBRD / 88160 Post Direct 7,500.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 mentation Support ant Selection ation aluation Specialist PRDP-IS-NPCO-050-SES-001 Component 4: Project Imple Individual Consult Under Implement -2021-AF / Social & Environ IBRD / 88160 Post Direct 8,250.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 mentation Support ant Selection ation ment Safeguards Specialist PRDP-IS-NPCO-051-SES-002 Component 4: Project Imple Individual Consult Under Implement -2021-AF / Social & Environ IBRD / 88160 Post Direct 7,500.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 mentation Support ant Selection ation ment Safeguards Officer PRDP-IS-NPCO-052-SES-003 Component 4: Project Imple Individual Consult Under Implement -2021-AF / Social & Environ IBRD / 88160 Post Direct 6,250.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 mentation Support ant Selection ation ment Safeguards Officer PRDP-IS-NPCO-053-SES-004 Component 4: Project Imple Individual Consult Under Implement -2021-AF / Associate Social IBRD / 88160 Post Direct 5,625.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 mentation Support ant Selection ation & Environment Safeguards Officer PRDP-IS-NPCO-056-ICE-003- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,750.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 2021-AF / Writer mentation Support ant Selection ation PRDP-IS-NPCO-057-ICE-004- Component 4: Project Imple Individual Consult Under Implement IBRD / 88160 Post Direct 6,000.00 0.00 2020-12-18 2020-12-18 2020-12-28 2021-01-18 2021-02-22 2021-08-21 2021-AF / Media Production mentation Support ant Selection ation Officer PRDP-NPCO-001-IP-001-202 Component 1: Local and Na Individual Consult Under Implement IBRD / 92710 Post Direct 15,840.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-29 2022-03-08 2022-09-04 2-AF2 / Planning Specialist tional Level Planning ant Selection ation PRDP-NPCO-002-IP-002-202 Component 1: Local and Na Individual Consult IBRD / 92710 Post Direct 14,400.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-01-03 2022-09-04 2-AF2 / Planning Officer tional Level Planning ant Selection PRDP-NPCO-003-IP-003-202 Component 1: Local and Na Individual Consult IBRD / 92710 Post Direct 14,400.00 1,052.45 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-28 2022-02-01 2022-01-02 2022-03-08 2022-01-12 2022-09-04 2022-07-11 2-AF2 / Planning Officer tional Level Planning ant Selection PRDP-NPCO-004-IP-004-202 Component 1: Local and Na Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-29 2022-03-08 2022-09-04 2-AF2 / Planning Officer tional Level Planning ant Selection ation PRDP-NPCO-005-IP-005-202 Component 1: Local and Na Individual Consult Under Implement IBRD / 92710 Post Open 14,400.00 0.00 2022-02-01 2021-11-22 2022-03-22 2022-04-12 2022-05-17 2022-11-13 2-AF2 / Planning Officer tional Level Planning ant Selection ation PRDP-NPCO-006-IP-006-202 Component 2: Infrastructur Individual Consult Under Implement IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2022-03-08 2022-09-04 2-AF2 / Project Development e Development ant Selection ation Associate PRDP-NPCO-007-IB-001-202 Component 2: Infrastructur Individual Consult Under Implement 2-AF2 / IBUILD Alternate Co IBRD / 92710 Post Direct 21,600.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-17 2022-02-01 2022-03-08 2022-09-04 e Development ant Selection ation mponent Head PRDP-NPCO-008-IB-002-202 Component 2: Infrastructur Individual Consult Under Implement IBRD / 92710 Post Direct 15,840.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2022-12-16 2022-03-08 2022-09-04 2-AF2 / Rural Infrastructure e Development ant Selection ation Specialist PRDP-NPCO-009-IB-003-202 Component 2: Infrastructur Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 2-AF2 / Roads Infrastructure e Development ant Selection ation Engineer PRDP-NPCO-010-IB-004-202 Component 2: Infrastructur Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 2-AF2 / Roads Infrastructure e Development ant Selection ation Engineer PRDP-NPCO-011-IB-005-202 Component 2: Infrastructur Individual Consult IBRD / 92710 Post Direct 14,400.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-01-03 2022-09-04 2-AF2 / Roads Infrastructure e Development ant Selection Engineer PRDP-NPCO-012-IB-006-202 Component 2: Infrastructur Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-09-04 2-AF2 / Roads Infrastructure e Development ant Selection ation Engineer PRDP-NPCO-013-IB-007-202 Component 2: Infrastructur Individual Consult Under Implement IBRD / 92710 Post Open 14,400.00 0.00 2022-02-01 2021-11-22 2022-03-22 2022-04-12 2022-05-17 2022-11-13 2-AF2 / Roads Infrastructure e Development ant Selection ation Engineer PRDP-NPCO-014-IB-008-202 Component 2: Infrastructur Individual Consult Under Implement IBRD / 92710 Post Open 14,400.00 0.00 2022-02-01 2021-11-22 2022-03-22 2022-04-12 2022-05-17 2022-11-13 2-AF2 / Roads Infrastructure e Development ant Selection ation Engineer PRDP-NPCO-015-IB-009-202 Component 2: Infrastructur Individual Consult Under Implement IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-29 2022-03-08 2022-09-04 2-AF2 / Project Development e Development ant Selection ation Associate PRDP-NPCO-016-IR-001-202 Component 3. Enterprise D Individual Consult Under Implement 2-AF2 / Enterprise Developm IBRD / 92710 Post Direct 15,840.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-29 2022-02-01 2021-12-31 2022-03-08 2022-09-04 evelopment ant Selection ation ent & Marketing Specialist ( EDMS) Page 9 PRDP-NPCO-017-IR-002-202 Component 3. Enterprise D Individual Consult 2-AF2 / Enterprise Developm IBRD / 92710 Post Direct 15,840.00 13,851.64 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-29 2022-02-01 2021-12-28 2022-03-08 2022-01-15 2022-09-04 evelopment ant Selection ent & Marketing Specialist ( EDMS) PRDP-NPCO-018-IR-003-202 Component 3. Enterprise D Individual Consult IBRD / 92710 Post Direct 15,840.00 1,154.30 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-29 2022-02-01 2021-12-31 2022-03-08 2022-01-15 2022-09-04 2022-07-12 2-AF2 / Business Developme evelopment ant Selection nt Specialist PRDP-NPCO-019-IR-004-202 Component 3. Enterprise D Individual Consult IBRD / 92710 Post Direct 15,840.00 1,154.30 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-29 2022-02-01 2021-12-31 2022-03-08 2022-01-15 2022-09-04 2022-07-09 2-AF2 / Business Developme evelopment ant Selection nt Specialist PRDP-NPCO-020-IR-005-202 Component 3. Enterprise D Individual Consult 2-AF2 / Project Development IBRD / 92710 Post Direct 10,080.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-01-03 2022-09-04 evelopment ant Selection Associate (PDA) PRDP-NPCO-021-IS-001-202 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 21,600.00 1,561.70 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-01-15 2022-09-04 2022-07-12 2-AF2 / I-Support Alternate mentation Support ant Selection Unit Head PRDP-NPCO-022-IS-002-202 Component 4: Project Imple Individual Consult 2-AF2 / Senior Institutional D IBRD / 92710 Post Direct 17,280.00 1,256.15 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-07 2022-02-01 2021-12-31 2022-03-08 2022-01-15 2022-09-04 2022-07-12 mentation Support ant Selection evelopment Specialist PRDP-NPCO-023-OPD-001-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 10,080.00 746.90 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-01-15 2022-09-04 2022-07-09 022-AF2 / Administrative Off mentation Support ant Selection icer II PRDP-NPCO-024-OPD-001-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 8,640.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-29 2022-03-08 2022-09-04 022-AF2 / Administrative Off mentation Support ant Selection ation icer I PRDP-NPCO-025-DPD-001-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Senior Project Dev IBRD / 92710 Post Direct 17,280.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 mentation Support ant Selection ation elopment Specialist PRDP-NPCO-026-DPD-001-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 15,840.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2022-03-08 2022-09-04 022-AF2 / Compliance Office mentation Support ant Selection ation r PRDP-NPCO-027-DPD-001-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 17,280.00 1,256.15 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-31 2022-02-01 2021-12-31 2022-03-08 2022-01-15 2022-09-04 2022-07-12 022-AF2 / Senior Economist mentation Support ant Selection PRDP-NPCO-028-DPD-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 14,400.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-01-03 2022-09-04 022-AF2 / Economist mentation Support ant Selection PRDP-NPCO-029-DPD-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / Economist mentation Support ant Selection ation PRDP-NPCO-030-DPD-004-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / Administrative Off mentation Support ant Selection ation icer II PRDP-NPCO-031-DPD-005-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / Administrative Off mentation Support ant Selection ation icer II PRDP-NPCO-032-GGU-001-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Geomapping & Go IBRD / 92710 Post Direct 20,000.16 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-29 2022-03-08 2022-09-04 mentation Support ant Selection ation vernance Alternate Unit Hea d PRDP-NPCO-033-GGU-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 15,840.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / GIS Specialist mentation Support ant Selection ation PRDP-NPCO-034-GGU-003-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 15,840.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-01-07 2022-09-04 022-AF2 / GIS Specialist mentation Support ant Selection PRDP-NPCO-035-GGU-004-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 14,400.00 0.00 2022-02-01 2021-11-22 2022-03-22 2022-04-12 2022-05-17 2022-11-13 022-AF2 / GIS Officer mentation Support ant Selection ation PRDP-NPCO-036-PRO-001-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Alternate Procure IBRD / 92710 Post Direct 20,160.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-29 2022-03-08 2022-09-04 mentation Support ant Selection ation ment Unit Head PRDP-NPCO-037-PRO-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 15,840.00 1,154.30 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-29 2022-02-01 2021-12-31 2022-03-08 2022-01-15 2022-09-04 022-AF2 / Procurement Spec mentation Support ant Selection ialist PRDP-NPCO-038-PRO-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / Procurement Offic mentation Support ant Selection ation er PRDP-NPCO-039-PRO-004-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-09-04 022-AF2 / Procurement Offic mentation Support ant Selection ation er PRDP-NPCO-040-PRO-005-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 12,960.00 950.60 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-01-15 2022-09-04 2022-07-09 022-AF2 / Associate Procure mentation Support ant Selection ment Officer PRDP-NPCO-041-PRO-006-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 12,960.00 0.00 2022-02-01 2021-11-22 2022-03-22 2021-12-16 2022-04-12 2022-05-17 2022-11-13 022-AF2 / Associate Procure mentation Support ant Selection ation ment Officer PRDP-NPCO-042-MNE-001-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Monitoring & Eval IBRD / 92710 Post Direct 20,160.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-09-04 mentation Support ant Selection ation uation Alternate Head PRDP-NPCO-043-MNE-002-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Monitoring & Eval IBRD / 92710 Post Direct 15,840.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 mentation Support ant Selection ation uation Specialist PRDP-NPCO-044-MNE-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 15,840.00 0.00 2022-02-01 2021-11-22 2022-03-22 2022-04-12 2022-05-17 2022-11-13 022-AF2 / MIS Specialist mentation Support ant Selection ation PRDP-NPCO-045-MNE-004-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Knowledge Manag IBRD / 92710 Post Open 15,840.00 0.00 2022-01-01 2021-11-22 2022-02-19 2022-03-12 2022-04-16 2022-10-13 mentation Support ant Selection ation ement Specialist PRDP-NPCO-046-MNE-005-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Monitoring & Eval IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 mentation Support ant Selection ation uation Officer PRDP-NPCO-047-SES-001-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Social & Environm IBRD / 92710 Post Direct 15,840.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2022-03-08 2022-09-04 mentation Support ant Selection ation ent Safeguards Specialist PRDP-NPCO-048-SES-002-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Social & Environm IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 mentation Support ant Selection ation ent Safeguards Officer PRDP-NPCO-049-SES-003-2 Component 4: Project Imple Individual Consult 022-AF2 / Social & Environm IBRD / 92710 Post Direct 14,400.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-01-03 2022-09-04 mentation Support ant Selection ent Safeguards Officer PRDP-NPCO-050-SES-004-2 Component 4: Project Imple Individual Consult Under Implement 022-AF2 / Associate Social & IBRD / 92710 Post Open 12,960.00 0.00 2022-02-01 2021-11-22 2022-03-22 2022-04-12 2022-05-17 2022-11-13 mentation Support ant Selection ation Environment Safeguards Off icer Page 10 PRDP-NPCO-051-ACE-001-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 15,800.04 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-15 2022-03-08 2022-01-03 2022-09-04 022-AF2 / Information Speci mentation Support ant Selection alist PRDP-NPCO-052-ACE-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / Writer mentation Support ant Selection ation PRDP-NPCO-053-ACE-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / Media Production mentation Support ant Selection ation Officer PRDP-NPCO-054-FIN-001-20 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 20,160.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-09-04 22-AF2 / Alternate Finance U mentation Support ant Selection ation nit Head PRDP-NPCO-055-FIN-002-20 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 15,840.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2022-03-08 2022-09-04 22-AF2 / Financial Analyst III mentation Support ant Selection ation PRDP-NPCO-056-FIN-003-20 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 22-AF2 / Financial Analyst II mentation Support ant Selection ation PRDP-NPCO-057-FIN-004-20 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 14,400.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2022-03-08 2022-09-04 22-AF2 / Financial Analyst II mentation Support ant Selection ation PRDP-NPCO-058-FIN-005-20 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 14,400.00 0.00 2022-02-01 2021-11-22 2022-03-22 2022-04-12 2022-05-17 2022-11-13 22-AF2 / Financial Analyst II mentation Support ant Selection ation PRDP-NPCO-059-ACT-001-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 12,960.00 0.00 Completed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-01-06 2022-09-04 022-AF2 / Financial Analyst I mentation Support ant Selection PRDP-NPCO-060-ACT-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 12,960.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-17 2022-03-08 2022-01-07 2022-09-04 022-AF2 / Financial Analyst I mentation Support ant Selection PRDP-NPCO-061-ACT-003-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 12,960.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-01-03 2022-09-04 022-AF2 / Financial Analyst I mentation Support ant Selection PRDP-NPCO-062-BUD-001-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct 12,960.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-01-03 2022-09-04 022-AF2 / Budget Analyst mentation Support ant Selection PRDP-NPCO-063-BUD-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 12,960.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-09-04 022-AF2 / Budget Analyst mentation Support ant Selection ation PRDP-NPCO-064-BUD-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 12,960.00 0.00 2022-02-01 2021-11-22 2022-03-22 2022-04-12 2022-05-17 2022-11-13 022-AF2 / Budget Analyst mentation Support ant Selection ation PRDP-NPCO-065-ADM-001-2 Component 4: Project Imple Individual Consult 022-AF2 / Alternate Adminis IBRD / 92710 Post Direct 20,160.00 0.00 Signed 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2023-01-03 2022-09-04 mentation Support ant Selection trative Unit Head PRDP-NPCO-066-ADM-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2022-12-31 2022-03-08 2022-09-04 022-AF2 / Administrative Off mentation Support ant Selection ation icer III PRDP-NPCO-067-ADM-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 11,520.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / Administrative Off mentation Support ant Selection ation icer III PRDP-NPCO-068-ADM-004-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-31 2022-03-08 2022-09-04 022-AF2 / Supply & Property mentation Support ant Selection ation Officer PRDP-NPCO-069-ADM-005-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct 10,080.00 0.00 2022-01-01 2021-11-22 2022-01-11 2021-12-16 2022-02-01 2021-12-16 2022-03-08 2022-09-04 022-AF2 / Administrative Off mentation Support ant Selection ation icer II PRDP-NPCO-070-IR-005-202 Component 2: Infrastructur Individual Consult Under Implement 2-EU / Enterprise Developm TF / B5756 Post Open 15,840.00 0.00 2022-01-03 2021-11-22 2022-02-21 2022-03-14 2022-04-18 2022-10-15 e Development ant Selection ation ent & Marketing Specialist ( EDMS PRDP-NPCO-071-IR-006-202 Component 3. Enterprise D Individual Consult Under Implement TF / B5756 Post Open 15,840.00 0.00 2022-01-03 2021-11-22 2022-02-21 2022-03-14 2022-04-18 2022-10-15 2-EU / Business Developmen evelopment ant Selection ation t Specialist PH-DA-277210-CS-INDV / IR Component 3. Enterprise D Individual Consult Pending Impleme IBRD / 92710 Post Open 21,600.00 0.00 2022-02-15 2022-04-05 2022-04-26 2022-05-31 2022-11-27 EAP Alternate Component H evelopment ant Selection ntation ead PH-DA-277212-CS-INDV / Le Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 16,000.00 0.00 2022-02-15 2022-01-14 2022-04-05 2022-04-26 2022-05-31 2022-11-27 gal Officer mentation Support ant Selection ation PH-DA-277213-CS-INDV / A Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 12,000.00 0.00 2022-02-15 2022-01-14 2022-04-05 2022-04-26 2022-05-31 2022-11-27 dministrative Officer III mentation Support ant Selection ation PH-DA-277214-CS-INDV / Ec Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 14,880.00 0.00 2022-02-15 2022-01-14 2022-04-05 2022-04-26 2022-05-31 2022-11-27 onomist mentation Support ant Selection ation PH-DA-277215-CS-INDV / Pr Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 7,920.00 0.00 2022-02-15 2022-02-11 2022-04-05 2022-04-26 2022-05-31 2022-11-27 ogrammer -output based mentation Support ant Selection ation PH-DA-277217-CS-INDV / As Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 13,440.00 0.00 2022-02-15 2022-01-14 2022-04-05 2022-04-26 2022-05-31 2022-11-27 sociate M&E Officer mentation Support ant Selection ation PH-DA-277218-CS-INDV / In Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 14,880.00 0.00 2022-02-15 2022-01-14 2022-04-05 2022-04-26 2022-05-31 2022-11-27 formation Officer mentation Support ant Selection ation PH-DA-277220-CS-INDV / As Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open 9,120.00 0.00 2022-02-15 2022-01-14 2022-04-05 2022-04-26 2022-05-31 2022-11-27 sociate Supply & Property Of mentation Support ant Selection ation ficer PH-DA-283546-CS-INDV / Pr Component 4: Project Imple Individual Consult Pending Impleme TF / B5756 Post Open 14,800.00 0.00 2022-03-11 2022-04-29 2022-05-20 2022-06-24 2022-12-21 ocurement Officer mentation Support ant Selection ntation PH-DA-283549-CS-INDV / GI Component 4: Project Imple Individual Consult Pending Impleme TF / B5756 Post Open 16,800.00 0.00 2022-03-15 2022-05-03 2022-05-24 2022-06-28 2022-12-25 S Data Specialist mentation Support ant Selection ntation PH-DA-283550-CS-INDV / GI Component 4: Project Imple Individual Consult Pending Impleme TF / B5756 Post Open 16,800.00 0.00 2022-03-15 2022-05-03 2022-05-24 2022-06-28 2022-12-25 S Data Specialist mentation Support ant Selection ntation PH-DA-277216-CS-INDV / Pr Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Open - National 14,960.00 0.00 2022-08-31 2022-10-19 2022-11-09 2022-12-14 2023-06-12 ogrammer1 mentation Support ant Selection ntation PH-DA-310289-CS-INDV / Pr Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 7,920.00 0.00 2022-09-15 2022-01-02 2022-11-03 2022-11-24 2022-12-29 2023-06-27 ogrammer mentation Support ant Selection ation PH-DA-283548-CS-INDV / Fi Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open - National 16,800.00 0.00 2022-03-15 2022-05-03 2022-05-24 2022-06-28 2022-12-25 nancial Analyst II mentation Support ant Selection ntation PH-DA-318209-CS-INDV / In Component 4: Project Imple Individual Consult Pending Impleme TF / B5756 Post Open - National 3,720.00 0.00 2022-09-30 2022-11-18 2022-12-09 2023-01-13 2023-07-12 formation Officer (EU) mentation Support ant Selection ntation PH-DA-322226-CS-INDV / Hi ring of Additional Staff for W Component 4: Project Imple Individual Consult Pending Impleme rapping Up Activities of GEF TF / B5756 Post Open - National 16,640.00 0.00 2022-10-31 2022-11-16 2022-11-18 2022-11-30 2022-12-31 mentation Support ant Selection ntation NRM- Writer, Finance Analys t II, NRM Officer and Project Development Associate Page 11 PRDP-NPCO-001-IP-001-202 Component 1: Local and Na Individual Consult IBRD / 92710 Post Direct - National 16,018.00 0.00 Signed 2023-01-02 2022-12-18 2023-01-10 2022-12-22 2023-01-11 2022-12-25 2023-01-17 2023-01-06 2023-12-31 3-AF2 / Planning Specialist tional Level Planning ant Selection PRDP-NPCO-002-IP-002-202 Component 1: Local and Na Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-25 2023-01-02 2022-12-30 2023-12-31 3-AF2 / Planning Officer tional Level Planning ant Selection PRDP-NPCO-003-IP-003-202 Component 1: Local and Na Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-29 2023-01-17 2022-12-29 2023-12-31 3-AF2 / Planning Officer tional Level Planning ant Selection PRDP-NPCO-004-IP-004-202 Component 1: Local and Na Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2022-12-18 2022-12-22 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-30 2023-12-31 3-AF2 / Planning Officer tional Level Planning ant Selection PRDP-NPCO-005-IP-005-202 Component 1: Local and Na Individual Consult Pending Impleme IBRD / 92710 Post Open - National 14,618.00 0.00 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 3-AF2 / Planning Officer tional Level Planning ant Selection ntation PRDP-NPCO-006-IP-006-202 Component 1: Local and Na Individual Consult IBRD / 92710 Post Direct - National 10,364.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-25 2023-01-02 2022-12-31 2023-12-31 3-AF2 / Project Development tional Level Planning ant Selection Associate PRDP-NPCO-007-IB-001-202 Component 2: Infrastructur Individual Consult IBRD / 92710 Post Direct - National 21,673.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-28 2023-12-31 3-AF2 / Alternate Componen e Development ant Selection t Head PRDP-NPCO-009-IB-002-202 Component 2: Infrastructur Individual Consult 3-AF2 / Rural Infrastructure IBRD / 92710 Post Direct - National 16,018.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 e Development ant Selection Specialist( Roads & Bridges, Water, Irrigations) PRDP-NPCO-010-IB-003-202 Component 2: Infrastructur Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2022-12-18 2022-12-22 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-29 2023-12-31 3-AF2 / Rural Infrastructure e Development ant Selection Engineer PRDP-NPCO-011-IB-004-202 Component 2: Infrastructur Individual Consult Pending Impleme IBRD / 92710 Post Direct - National 14,618.00 0.00 2022-12-18 2022-12-26 2022-12-27 2023-01-02 2023-12-31 3-AF2 / Rural Infrastructure e Development ant Selection ntation Engineer PRDP-NPCO-012-IB-005-202 Component 2: Infrastructur Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-25 2023-01-02 2022-12-29 2023-12-31 3-AF2 / Rural Infrastructure e Development ant Selection Engineer PRDP-NPCO-013-IB-006-202 Component 2: Infrastructur Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-29 2023-12-31 3-AF2 / Rural Infrastructure e Development ant Selection Engineer PRDP-NPCO-014-IB-007-202 Component 2: Infrastructur Individual Consult 3-AF2 / Project Development IBRD / 92710 Post Direct - National 10,364.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-28 2023-12-31 e Development ant Selection Associate (PDA) PRDP-NPCO-016-IR-001-202 Component 3. Enterprise D Individual Consult Pending Impleme IBRD / 92710 Post Open - National 21,673.00 0.00 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 3-AF2 / IREAP Alternate Com evelopment ant Selection ntation ponent Head PRDP-NPCO-017-IR-002-202 Component 3. Enterprise D Individual Consult 3-AF2 / Enterprise Developm IBRD / 92710 Post Direct - National 15,555.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 evelopment ant Selection ent & Marketing Specialist ( EDMS) PRDP-NPCO-018-IR-003-202 Component 3. Enterprise D Individual Consult Pending Impleme 3-AF2 / Enterprise Developm IBRD / 92710 Post Direct - National 15,555.00 0.00 2023-01-02 2023-01-10 2023-01-11 2023-01-17 2023-12-31 evelopment ant Selection ntation ent & Marketing Specialist ( EDMS) PRDP-NPCO-019-IR-004-202 Component 3. Enterprise D Individual Consult IBRD / 92710 Post Direct - National 15,555.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-25 2023-01-02 2022-12-29 2023-12-31 3-AF2 / Business Developme evelopment ant Selection nt Specialist PRDP-NPCO-020-IR-005-202 Component 3. Enterprise D Individual Consult IBRD / 92710 Post Direct - National 15,555.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-29 2023-01-17 2023-01-01 2023-12-31 3-AF2 / Business Developme evelopment ant Selection nt Specialist PRDP-NPCO-021-IR-006-202 Component 3. Enterprise D Individual Consult 3-AF2 / Project Development IBRD / 92710 Post Direct - National 10,364.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-30 2023-12-31 evelopment ant Selection Associate (PDA) PRDP-NPCO-022-IS-001-202 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 21,673.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-29 2023-12-31 3-AF2 / Alternate Componen mentation Support ant Selection t Head PRDP-NPCO-023-OPD-001-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Open - National 17,436.00 0.00 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 023-AF2 / Legal Officer mentation Support ant Selection ntation PRDP-NPCO-024-OPD-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 11,782.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-28 2023-01-19 2022-12-29 2023-12-31 023-AF2 / Administrative Off mentation Support ant Selection icer III PRDP-NPCO-025-OPD-003-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 10,364.00 0.00 Signed 2022-12-18 2022-12-22 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-30 2023-12-31 023-AF2 / Administrative Off mentation Support ant Selection icer II PRDP-NPCO-026-OPD-004-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 8,945.00 0.00 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 023-AF2 / Administrative Off mentation Support ant Selection ation icer I PRDP-NPCO-027-DPD-001-2 Component 4: Project Imple Individual Consult 023-AF2 / Senior Institutiona IBRD / 92710 Post Direct - National 17,436.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-28 2023-01-17 2022-12-29 2023-12-31 mentation Support ant Selection l Development Specialist PRDP-NPCO-028-DPD-002-2 Component 4: Project Imple Individual Consult 023-AF2 / Senior Project Dev IBRD / 92710 Post Direct - National 17,436.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-28 2022-12-25 2023-01-02 2022-12-31 2023-12-31 mentation Support ant Selection elopment Specialist PRDP-NPCO-029-DPD-003-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 16,018.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-30 2023-12-31 023-AF2 / Compliance Office mentation Support ant Selection r PRDP-NPCO-030-DPD-004-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 10,364.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-28 2023-01-02 2022-12-29 2023-12-31 023-AF2 / Administrative Off mentation Support ant Selection icer II PRDP-NPCO-031-DPD-005-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 10,364.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-28 2023-01-02 2022-12-30 2023-12-31 023-AF2 / Administrative Off mentation Support ant Selection icer II PRDP-NPCO-032-GGU-001-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 20,273.00 0.00 2022-12-18 2022-12-16 2022-12-26 2022-12-22 2022-12-27 2022-12-25 2023-01-02 2023-12-31 023-AF2 / Alternate Unit Hea mentation Support ant Selection ation d PRDP-NPCO-033-GGU-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 16,018.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-12 2022-12-22 2023-01-13 2022-12-28 2023-01-19 2023-01-01 2023-12-31 023-AF2 / GIS Specialist mentation Support ant Selection PRDP-NPCO-034-GGU-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 16,018.00 0.00 2022-12-18 2022-12-16 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2023-12-31 023-AF2 / GIS Specialist mentation Support ant Selection ation PRDP-NPCO-035-GGU-004-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 023-AF2 / GIS Officer mentation Support ant Selection PRDP-NPCO-036-FIN-001-20 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 20,273.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-28 2023-01-17 2022-12-29 2023-12-31 23-AF2 / Alternate Unit Head mentation Support ant Selection PRDP-NPCO-037-FIN-002-20 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 16,018.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 23-AF2 / Financial Analyst III mentation Support ant Selection PRDP-NPCO-038-FIN-003-20 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Direct - National 14,618.00 0.00 2023-01-02 2023-01-10 2023-01-11 2023-01-17 2023-12-31 23-AF2 / Financial Analyst II mentation Support ant Selection ntation Page 12 PRDP-NPCO-039-FIN-004-20 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 14,618.00 0.00 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2023-12-31 23-AF2 / Financial Analyst II mentation Support ant Selection ation PRDP-NPCO-040-FIN-005-20 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 14,618.00 0.00 2023-01-02 2023-01-02 2023-02-20 2023-02-25 2023-04-01 2023-12-31 23-AF2 / Financial Analyst II mentation Support ant Selection ation PRDP-NPCO-041-PRO-001-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 20,273.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-31 2022-12-26 2023-02-18 2023-01-01 2023-12-31 023-AF2 / Alternate Unit Hea mentation Support ant Selection d PRDP-NPCO-042-PRO-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 16,018.00 0.00 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2023-01-02 2023-12-31 023-AF2 / Procurement Spec mentation Support ant Selection ation ialist PRDP-NPCO-043-PRO-003-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-28 2023-01-17 2023-01-01 2023-12-31 023-AF2 / Procurement Offic mentation Support ant Selection er PRDP-NPCO-044-PRO-004-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2022-12-18 2022-12-22 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-29 2023-12-31 023-AF2 / Procurement Offic mentation Support ant Selection er PRDP-NPCO-045-PRO-005-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 13,200.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-25 2023-01-02 2022-12-31 2023-12-31 023-AF2 / Associate Procure mentation Support ant Selection ment Officer PRDP-NPCO-046-PRO-006-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Limited 13,200.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-23 2022-12-16 2022-12-26 2022-12-29 2023-01-02 2022-12-30 2023-12-31 023-AF2 / Associate Procure mentation Support ant Selection ment Officer PRDP-NPCO-047-MNE-001-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 20,273.00 0.00 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-28 2023-01-02 2023-12-02 023-AF2 / Alternate M&E Uni mentation Support ant Selection ation t Head PRDP-NPCO-048-MNE-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 16,018.00 0.00 2023-01-02 2022-12-22 2023-02-20 2023-03-13 2023-04-17 2023-12-31 023-AF2 / M&E Specialist mentation Support ant Selection ation PRDP-NPCO-049-MNE-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 16,018.00 0.00 2022-12-18 2022-12-22 2022-12-26 2022-12-22 2022-12-27 2022-12-28 2023-01-02 2023-12-31 023-AF2 / MIS Specialist mentation Support ant Selection ation PRDP-NPCO-050-MNE-004-2 Component 4: Project Imple Individual Consult Under Implement 023-AF2 / Knowledge Manag IBRD / 92710 Post Direct - National 16,018.00 0.00 2023-01-02 2023-01-10 2023-01-11 2023-02-15 2023-12-31 mentation Support ant Selection ation ement Specialist PRDP-NPCO-051-MNE-005-2 Component 4: Project Imple Individual Consult Under Implement 023-AF2 / Knowledge Manag IBRD / 92710 Post Open - National 14,618.00 0.00 2022-12-18 2022-12-18 2023-02-05 2023-02-26 2023-04-02 2023-12-31 mentation Support ant Selection ation ement Officer PRDP-NPCO-052-MNE-006-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 023-AF2 / M&E Officer mentation Support ant Selection PRDP-NPCO-053-MNE-007-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 13,200.00 0.00 2023-01-02 2022-12-22 2023-02-20 2023-03-13 2023-04-17 2023-12-31 023-AF2 / Associate M & E mentation Support ant Selection ation Officer PRDP-NPCO-054-SES-001-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Open - National 16,018.00 0.00 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 023-AF2 / SES Specialist mentation Support ant Selection ntation PRDP-NPCO-055-SES-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-12 2022-12-22 2023-02-02 2022-12-28 2023-03-09 2023-01-01 2023-09-05 023-AF2 / SES Officer mentation Support ant Selection PRDP-NPCO-056-SES-003-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-25 2023-01-02 2022-12-31 2023-12-31 023-AF2 / SES Officer mentation Support ant Selection PRDP-NPCO-057-SES-004-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 13,200.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-31 2022-12-26 2023-02-06 2023-01-01 2023-12-31 023-AF2 / Associate SES Offi mentation Support ant Selection cer PRDP-NPCO-058-ECO-001-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Direct - National 20,273.00 0.00 2023-01-02 2023-01-10 2023-01-11 2023-01-17 2023-12-31 023-AF2 / Alternate Unit Hea mentation Support ant Selection ntation d PRDP-NPCO-059-ECO-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 17,436.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-30 2023-12-31 023-AF2 / Senior Economist mentation Support ant Selection PRDP-NPCO-060-ECO-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 14,618.00 0.00 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2023-01-17 2023-12-31 023-AF2 / Economist mentation Support ant Selection ation PRDP-NPCO-061-ECO-004-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 023-AF2 / Economist mentation Support ant Selection PRDP-NPCO-062-ECO-005-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 14,618.00 0.00 2023-01-02 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 023-AF2 / Economist mentation Support ant Selection ation PRDP-NPCO-063-ACE-001-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 16,018.00 0.00 2023-01-02 2023-06-08 2023-01-10 2023-01-11 2023-01-17 2023-12-31 023-AF2 / Information Speci mentation Support ant Selection ation alist PRDP-NPCO-064-ACE-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 14,618.00 0.00 2022-12-18 2022-12-22 2022-12-26 2022-12-28 2023-01-02 2023-12-31 023-AF2 / Information Office mentation Support ant Selection ation r PRDP-NPCO-065-ACE-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 14,618.00 0.00 2023-01-02 2022-12-22 2023-02-17 2023-03-10 2023-04-14 2023-12-31 023-AF2 / Information Office mentation Support ant Selection ation r PRDP-NPCO-066-ACE-004-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Direct - National 13,200.00 0.00 2022-12-18 2022-12-26 2022-12-27 2023-01-02 2023-12-16 023-AF2 / Writer mentation Support ant Selection ntation PRDP-NPCO-067-ACT-001-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Direct - National 13,200.00 0.00 2023-01-02 2023-01-10 2023-01-11 2023-01-17 2023-12-31 023-AF2 / Financial Analyst I mentation Support ant Selection ntation PRDP-NPCO-068-ACT-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 13,200.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-29 2023-12-31 023-AF2 / Financial Analyst I mentation Support ant Selection PRDP-NPCO-069-ACT-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 13,200.00 0.00 2022-12-18 2022-12-16 2022-12-26 2022-12-27 2023-01-02 2023-12-31 023-AF2 / Financial Analyst I mentation Support ant Selection ation PRDP-NPCO-070-BUD-001-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 13,200.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 023-AF2 / Budget Analyst mentation Support ant Selection PRDP-NPCO-071-BUD-002-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 13,200.00 0.00 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2023-12-31 023-AF2 / Budget Analyst mentation Support ant Selection ation PRDP-NPCO-072-BUD-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 13,200.00 0.00 2023-01-02 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 023-AF2 / Budget Analyst mentation Support ant Selection ation PRDP-NPCO-073-ADM-001-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 20,273.00 0.00 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-28 2023-01-02 2023-12-31 023-AF2 / Alternate Unit Hea mentation Support ant Selection ation d PRDP-NPCO-074-ADM-002-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 11,782.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-28 2023-01-17 2023-01-01 2023-12-31 023-AF2 / Administrative Off mentation Support ant Selection icer III PRDP-NPCO-075-ADM-003-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 11,782.00 0.00 2022-12-18 2022-12-18 2022-12-28 2022-12-22 2023-01-02 2022-12-22 2023-01-24 2023-12-31 023-AF2 / Administrative Off mentation Support ant Selection ation icer III Page 13 PRDP-NPCO-076-ADM-004-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 10,364.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 023-AF2 / Administrative Off mentation Support ant Selection icer II PRDP-NPCO-077-ADM-005-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Direct - National 10,364.00 0.00 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-12-31 023-AF2 / Supply & Property mentation Support ant Selection ation Officer PRDP-NPCO-078-ADM-006-2 Component 4: Project Imple Individual Consult 023-AF2 / Associate Supply IBRD / 92710 Post Direct - National 10,364.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-22 2023-01-11 2022-12-26 2023-01-17 2023-01-01 2023-12-31 mentation Support ant Selection & Property Officer PRDP-NPCO-079-IR-007-202 Component 3. Enterprise D Individual Consult Pending Impleme 3-EU / Enterprise Developm TF / B5756 Post Open - National 15,545.00 0.00 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 evelopment ant Selection ntation ent & Marketing Specialist ( EDMS) PRDP-NPCO-080-IR-008-202 Component 3. Enterprise D Individual Consult TF / B5756 Post Direct - National 15,545.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-25 2023-01-02 2022-12-31 2023-12-31 3-EU / Business Developmen evelopment ant Selection t Specialist PRDP-NPCO-082-GGU-005-2 Component 4: Project Imple Individual Consult Under Implement TF / B5756 Post Open - National 16,491.00 0.00 2023-01-15 2023-03-05 2023-03-26 2023-04-30 2023-12-31 023-EU / GIS Data Specialist mentation Support ant Selection ation PRDP-NPCO-083-GGU-004-2 Component 4: Project Imple Individual Consult Pending Impleme 023-EU / GIS Data Specialist IBRD / 92710 Post Open - National 16,491.00 0.00 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 mentation Support ant Selection ntation (Programmer or MIS) PRDP-NPCO-084-PRO-007-2 Component 4: Project Imple Individual Consult TF / B5756 Post Direct - National 14,618.00 0.00 Signed 2022-12-18 2022-12-18 2022-12-26 2022-12-22 2022-12-27 2022-12-29 2023-01-02 2022-12-31 2023-12-31 023-EU / Procurement Office mentation Support ant Selection r PRDP-NPCO-085-FIN-006-20 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Open - National 14,618.00 0.00 2023-01-02 2023-02-20 2023-03-13 2023-04-17 2023-12-31 23-EU / Financial Analyst II mentation Support ant Selection ntation PRDP-NPCO-086-ACE-005-2 Component 4: Project Imple Individual Consult IBRD / 92710 Post Direct - National 14,618.00 0.00 Signed 2023-01-02 2023-01-02 2023-01-10 2022-12-28 2023-01-11 2022-12-29 2023-01-17 2023-01-01 2023-12-31 023-EU / Information Officer mentation Support ant Selection PRDP-NPCO-020-IB-012-202 Component 2: Infrastructur Individual Consult Under Implement 3-AF2 / Rural Infrastructure IBRD / 92710 Post Open - National 16,080.00 0.00 2023-02-15 2023-03-23 2023-04-13 2023-05-18 2023-12-31 e Development ant Selection ation Engineer (Civil Works) PRDP-NPCO-004-ACE-004-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 13,392.00 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-12-31 023-AF2 / Media Production mentation Support ant Selection ation Officer PRDP-NPCO-056-SES-003-2 Component 4: Project Imple Individual Consult Under Implement TF / B5756 Post Open - National 16,070.40 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-12-31 023-EU / SES Officer mentation Support ant Selection ation PRDP-NPCO-057-SES-004-2 Component 4: Project Imple Individual Consult Pending Impleme TF / B5756 Post Open - National 16,070.40 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-12-31 023-EU / SES Officer mentation Support ant Selection ntation PRDP-NPCO-090-PRO-011-2 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 1,468.80 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-12-31 023-AF2 / Procurement Spec mentation Support ant Selection ation ialist PRDP-NPCO-010-IP-010-202 Component 1: Local and Na Individual Consult Pending Impleme IBRD / 92710 Post Open - National 12,052.80 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-12-31 3-AF2 / Planning Officer tional Level Planning ant Selection ntation PRDP-NPCO-007-IP-007-202 Component 1: Local and Na Individual Consult Pending Impleme IBRD / 92710 Post Open - National 12,052.80 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-12-31 3-AF2 / Planning Officer tional Level Planning ant Selection ntation PRDP-NPCO-008-IP-008-202 Component 1: Local and Na Individual Consult Pending Impleme IBRD / 92710 Post Open - National 12,052.80 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-12-31 3-AF2 / Planning Officer tional Level Planning ant Selection ntation PRDP-NPCO-009-IP-009-202 Component 1: Local and Na Individual Consult Pending Impleme IBRD / 92710 Post Open - National 8,553.60 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-12-31 3-AF2 / Project Dev't. Associ tional Level Planning ant Selection ntation ate PRDP-NPCO-06-GGU-GO-01 Component 4: Project Imple Individual Consult Under Implement IBRD / 92710 Post Open - National 9,692.06 0.00 2023-04-14 2023-05-06 2023-05-11 2023-05-21 2023-12-31 3-2023-AF2 / GIS OFFICER mentation Support ant Selection ation PRDP-NPCO-06-ECONALTER Component 4: Project Imple Individual Consult Under Implement NATE-012-2023-AF2 / ALTER IBRD / 92710 Post Open - National 13,449.13 0.00 2023-04-14 2023-05-06 2023-05-11 2023-05-25 2023-12-31 mentation Support ant Selection ation NATE ECONOMICS UNIT HEA D PRDP-NPCO-064-GGU-005-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Open - National 7,304.72 0.00 2023-06-07 2023-06-24 2023-06-27 2023-07-04 2023-12-31 023-AF2 / GIS OFFICER mentation Support ant Selection ntation PRDP-NPCO-058-MNE-006-2 Component 4: Project Imple Individual Consult Pending Impleme 023-AF2 / KNOWLEDGE MAN IBRD / 92710 Post Open - National 9,739.63 0.00 2023-06-07 2023-06-23 2023-06-28 2023-07-04 2023-12-31 mentation Support ant Selection ntation AGEMENT OFFICER PRDP-NPCO-066-ACE-002-2 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 92710 Post Open - National 8,011.63 0.00 2023-07-01 2023-07-12 2023-07-13 2023-07-17 2024-01-13 023-AF2 / INFORMATION SPE mentation Support ant Selection ntation CIALIST PRDP-NPCO-005-FIN-005-20 Component 4: Project Imple Individual Consult Pending Impleme IBRD / 88160 Post Open - National 6,597.81 0.00 2023-06-20 2023-07-01 2023-07-02 2023-07-04 2023-12-31 23-AF2 / Finance Analyst I mentation Support ant Selection ntation PRDP-NPCO-044-MNE-003-2 Component 4: Project Imple Individual Consult Pending Impleme 023-AF2 / Monitoring and Ev IBRD / 92710 Post Open - National 7,304.72 0.00 2023-06-22 2023-07-03 2023-07-05 2023-07-09 2023-12-31 mentation Support ant Selection ntation aluation Officer (M&E) PRDP-NPCO-045-MNE-004-2 Component 4: Project Imple Individual Consult Pending Impleme 023-AF2 / Monitoring and Ev IBRD / 92710 Post Open - National 7,304.72 0.00 2023-06-22 2023-07-03 2023-07-05 2023-07-09 2023-12-03 mentation Support ant Selection ntation aluation Officer (M&E) PRDP-NPCO-046-MNE-005-2 Component 4: Project Imple Individual Consult Pending Impleme 023-AF2 / Monitoring and Ev IBRD / 92710 Post Open - National 8,011.63 0.00 2023-07-01 2023-07-12 2023-07-14 2023-07-18 2023-12-31 mentation Support ant Selection ntation aluation Specialist (M&E) Page 14