Procurement Plan (Text Part) Bangladesh Weather and Climate Services Regional Project (BWCSRP) Agency: Bangladesh Meteorological Department (BMD) Bangladesh Water Development Board Department of Agricultural Extension I. General 1. Date of General Procurement Notice: July 10, 2017 2. Period covered by this procurement plan: The procurement period of project covered from July 2016 to December 2022. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank: Procurement Prior Review Thresholds (US$ millions) (Procurement Activity) Type of Substantial High risk Moderate risk Low risk Procurement risk Works (including turnkey, supply & installation of plant 5 10 15 20 and equipment, and PPP) Goods, information technology and 1.5 2 4 6 non-consulting services Notes: 1. Use of Standard Procurement Documents: For all procurements under the project, the Bank’s Standard Procurement Documents (or other documents agreed with the Bank) shall be used; 2. Request for Bids (Open-National), if allowed in the Procurement Plan, will be carried out under the Bank’s Procurement Guidelines following procedures for Open Tendering Method (OTM) of the People’s Republic of Bangladesh (Public Procurement Act, 2006 and The Public Procurement Rules, 2008) using standard/model bidding documents satisfactory to the Bank. For the purpose of Request for Bids (Open- National) the following shall apply: a. Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; b. Bids should be submitted and opened in public in one location immediately after the deadline for submission; c. Lottery in award of contracts shall not be allowed; d. Bidders’ qualification/experience requirement shall be mandatory; e. Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost and contract award shall be based on the lowest evaluated bid price of compliant bid from eligible and qualified bidder; and f. Single-stage two-envelope procurement system shall not be allowed. 2. Prequalification. Not Applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: A Project Operational Manual will be prepared. 5. Any Other Special Procurement Arrangements: Not Applicable. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank: Procurement Prior Review Thresholds (US$ millions) (Procurement Activity) Type of Substantial High risk Moderate risk Low risk Procurement risk Consultants: firms 0.5 1 2 4 Consultants: 0.2 0.3 0.4 0.5 Individual 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. PROCUREMENT Bangladesh : Bangladesh Weather and Climate Services Regional Project PLAN General Information Country: Bangladesh 2017-08-22 Bank’s Approval Date of the Original Procurement Plan: 2023-10-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150220 GPN Date: 2017-07-10 Project Name: Bangladesh Weather and Climate Services Regional Project Loan / Credit No: IDA / 58370 Bangladesh Water Development Board Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BWDB-W2 / Supply and insta Component B- Strengthenin llation of New Ground water g Hydrological Information S Single Stage - One E 2020-04-1 nests in coastal region and h IDA / 58370 Post Request for Bids Open - National 830,000.00 693,701.41 Completed 2018-12-27 2019-01-07 2019-01-01 2019-02-12 2019-02-10 2019-03-14 2019-03-07 2019-04-18 2019-03-17 ervices and Early Warning S nvelope 7 otspot areas including Dhaka ystems Work (Digging of New Groun d Water Borehole) Component B- Strengthenin BWDB-W4 / Refurbishing Div Single Stage - One E 2022-04-1 IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 1,081,149.80 836,378.05 Completed 2019-02-03 2019-10-21 2019-02-08 2019-03-08 2019-11-28 2019-03-22 2019-12-15 2019-04-19 2020-01-08 ision level hydrology offices nvelope 9 ervices and Early Warning S ystems Component B- Strengthenin BWDB-W5 / Establishment of Single Stage - One E 2019-06-3 IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 327,016.03 256,482.38 Completed 2019-01-06 2019-03-05 2019-01-12 2019-02-09 2019-04-04 2019-02-23 2019-04-18 2019-03-23 2019-05-03 BM Pillar for SW nvelope 0 ervices and Early Warning S ystems Component B- Strengthenin BWDB-W-1 / Refurbishing H Single Stage - One E 2021-04-1 IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 716,675.15 660,266.73 Completed 2020-01-30 2020-03-23 2020-02-05 2020-03-04 2020-04-27 2020-03-18 2020-06-11 2020-04-15 2020-06-23 Q of hydrology office nvelope 5 ervices and Early Warning S ystems BWDB-W3 / Establishment of Component B- Strengthenin Single Stage - One E 2021-04-1 Hydrology-lab (Construction IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 381,582.30 332,398.94 Completed 2019-12-29 2019-12-12 2020-01-03 2020-02-14 2020-01-14 2020-03-15 2020-02-02 2020-04-19 2020-02-14 nvelope 9 & Furbishing) ervices and Early Warning S ystems BWDB-W1 / Procurement of Component B- Strengthenin Single Stage - One E 2019-02-2 Refurshibing HQ and Division IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 1,671,025.00 0.00 Canceled 2017-11-23 2017-11-28 2017-12-26 2018-01-16 2018-02-27 nvelope 7 level hydrology offices Work ervices and Early Warning S ystems National Procure BWDB-W6A / Establishment Component B- Strengthenin ment Document - Single Stage - One E Pending Imp 2022-12-1 of B. M. Values (SoB) on B. M. IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 1 Envelope proce 450,882.00 0.00 2022-04-03 2022-04-09 2022-05-07 2022-05-21 2022-06-18 nvelope lementation 5 Pillar in 730 Locations ervices and Early Warning S ss (Non Bank-SPD ystems ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BWDB-G7 / Procurement of L Component B- Strengthenin Single Stage - One E ab and field equipment and a IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 240,002.50 230,257.56 Completed 2018-10-04 2018-08-05 2018-10-06 2018-11-03 2018-08-26 2018-11-17 2018-09-25 2018-12-22 2018-10-28 2019-02-05 2019-01-22 nvelope ccessories ervices and Early Warning S ystems Component B- Strengthenin BWDB-G12 / Procurement of Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 89,939.00 56,121.22 Completed 2017-09-28 2018-05-03 2017-10-03 2017-10-14 2018-05-20 2017-11-11 2018-05-23 2017-12-09 2018-06-11 2018-01-23 2018-08-04 Double cabin pick-up nvelope ervices and Early Warning S ystems Component B- Strengthenin BWDB-G13 / Procurement of Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 102,060.00 79,758.44 Completed 2017-09-28 2018-04-16 2017-10-03 2017-10-31 2018-05-13 2017-11-14 2018-05-21 2017-12-26 2018-06-03 2018-02-09 2018-06-04 Motorcycles nvelope ervices and Early Warning S ystems Component B- Strengthenin BWDB-G18 / Procurement of Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 72,717.00 41,439.69 Completed 2017-12-17 2018-04-08 2017-12-21 2018-01-11 2018-04-09 2018-01-18 2018-04-15 2018-02-01 2018-05-15 2018-02-16 2018-06-12 Office Equipment nvelope ervices and Early Warning S ystems Component B- Strengthenin BWDB-G19 / Purchase of Offi Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 46,744.00 24,706.99 Signed 2018-01-25 2018-02-06 2018-01-30 2018-02-20 2018-02-28 2018-02-27 2018-03-08 2018-03-13 2018-04-05 2018-03-28 2018-07-06 ce Furniture and Fixtures nvelope ervices and Early Warning S ystems BWDB-G5 / Procurement of Systems for Morphological su Component B- Strengthenin rvey- (1) 15 Handheld TDS 2 g Hydrological Information S Open - Internationa Single Stage - One E ) RTK GPS 3) 6 DGPS beacon IDA / 58370 Post Request for Bids 1,800,000.00 0.00 Canceled 2018-10-04 2018-12-31 2018-10-09 2019-01-01 2018-11-20 2019-01-30 2018-12-20 2019-03-12 2019-01-24 2019-05-24 ervices and Early Warning S l nvelope receiver 4) 8 Total stations 5 ystems ) 4 First order digital leveling machine 6) 2 Sub-bottom pr ofiler. BWDB-G1 / Procurement of Component B- Strengthenin Upgrade ground water statio g Hydrological Information S Open - Internationa Single Stage - One E IDA / 58370 Prior Request for Bids 5,145,777.00 4,585,080.82 Signed 2019-03-17 2019-06-16 2019-03-22 2019-08-08 2019-05-03 2019-09-04 2019-06-02 2020-01-14 2019-09-05 2020-02-23 2020-09-04 ns and nests from manual to ervices and Early Warning S l nvelope automatic and new stations ystems BWDB-G3 / Procurement of Component B- Strengthenin Single Stage - One E Catamarans and Survey Boat IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 652,747.39 605,953.02 Completed 2018-11-11 2019-04-01 2018-11-16 2018-12-14 2018-11-29 2018-12-29 2018-12-10 2019-02-02 2019-01-16 2019-04-03 2022-03-04 nvelope s (01 no. Catamaran, 01 no. ervices and Early Warning S Survey Boat) ystems BWDB-G10 / ICT System incl Component B- Strengthenin Single Stage - One E uding VC Systems in 13 locat IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 330,704.00 352,816.98 Signed 2018-11-11 2018-10-28 2018-11-16 2018-12-14 2018-11-20 2018-12-28 2019-02-08 2019-01-16 2019-04-09 2019-07-07 nvelope ions ervices and Early Warning S ystems Component B- Strengthenin BWDB-G11 / Purchase of Cro Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 254,388.20 189,083.52 Completed 2018-12-02 2019-02-06 2018-12-06 2019-01-03 2019-02-28 2019-01-13 2019-03-09 2019-02-03 2019-04-06 2019-04-25 2019-06-24 ss country vehicle nvelope ervices and Early Warning S ystems BWDB-G14 / Procurement of Component B- Strengthenin Single Stage - One E GIS software with 10 years li IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 60,000.00 115,439.22 Completed 2019-01-27 2018-12-23 2019-02-01 2019-02-22 2019-01-13 2019-03-04 2019-01-20 2019-04-08 2019-02-22 2019-05-23 2019-04-19 nvelope censing ervices and Early Warning S ystems Component B- Strengthenin BWDB-G20 / Purchase of IPS Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 25,438.82 7,019.57 Completed 2019-07-07 2019-10-31 2019-07-12 2019-08-09 2019-11-20 2019-08-16 2019-11-27 2019-09-13 2019-12-21 2019-12-08 2020-02-17 & Electrical equipment nvelope ervices and Early Warning S ystems Component B- Strengthenin BWDB-G10B / Purchase of C Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 362,630.37 334,381.18 Completed 2019-01-16 2019-02-03 2019-01-21 2019-03-04 2019-04-04 2019-04-03 2019-03-09 2019-05-08 2019-03-30 2019-11-04 2019-06-16 omputers and Accessories nvelope ervices and Early Warning S ystems Page 1 BWDB-G4 / Purchase of Syst Component B- Strengthenin ems for Hydro-logical Survey g Hydrological Information S Single Stage - One E ( 10 ADCP, 20 Sondes (water IDA / 58370 Post Request for Bids Open - National 795,815.31 744,309.56 Completed 2017-09-28 2017-10-03 2017-10-31 2018-06-07 2017-11-14 2018-06-12 2017-12-19 2018-06-30 2018-02-17 2018-09-30 ervices and Early Warning S nvelope quality), 8 Echosonder, 01 Si ystems de Scanner, 2 Survey grade Echosonder) BWDB-G2 / Procurement of Component B- Strengthenin Automatic Water Level Statio g Hydrological Information S Open - Internationa Single Stage - One E ns and Upgrade existing 3 cli IDA / 58370 Prior Request for Bids 8,905,634.00 6,175,616.11 Signed 2020-01-15 2020-09-16 2020-01-20 2020-12-08 2020-03-02 2020-12-30 2020-04-01 2021-06-02 2020-07-05 2021-08-01 2021-04-01 ervices and Early Warning S l nvelope mate stations and 257 rain g ystems uages to automatic and real t ime. BWDB-G9 / procurement of Component B- Strengthenin nowcasting workstations for g Hydrological Information S Open - Internationa Single Stage - One E IDA / 58370 Post Request for Bids 501,499.62 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 short lead time events and d ervices and Early Warning S l nvelope evelopment of flash flood for ystems ecasts Component B- Strengthenin BWDB-15A / Purchase of GIS Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 498,324.85 388,941.26 Completed 2019-12-10 2019-12-09 2019-12-15 2019-12-31 2019-12-26 2020-01-30 2020-01-07 2020-03-05 2020-01-28 2020-09-01 /Satellite Image nvelope ervices and Early Warning S ystems BWDB-G22 / Purchase of Ele Component B- Strengthenin Single Stage - One E ctrical Materials & IPS (Phase IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 39,430.00 0.00 Canceled 2020-02-16 2020-02-20 2020-03-05 2020-03-12 2020-04-02 2020-06-30 nvelope -02) ervices and Early Warning S ystems BWDB-G16 / Purchase of dat Component B- Strengthenin a and information sharing sof g Hydrological Information S Open - Internationa Single Stage - One E IDA / 58370 Post Request for Bids 180,002.00 0.00 Canceled 2018-10-09 2018-10-14 2018-11-11 2018-11-25 2018-12-16 2019-12-30 tware to share info between ervices and Early Warning S l nvelope BWDB and stakeholders-supp ystems ly and installation BWDB-G21 / Purchase of Ele Component B- Strengthenin Single Stage - One E ctrical Materials & IPS (Phase IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 38,794.00 0.00 Canceled 2018-01-25 2018-01-30 2018-02-13 2018-02-20 2018-03-13 2018-06-28 nvelope -01) ervices and Early Warning S ystems BWDB-G23 / Purchase of Ele Component B- Strengthenin Single Stage - One E ctrical Materials & IPS (Phase IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 26,075.00 0.00 Canceled 2021-05-16 2021-05-20 2021-06-03 2021-06-10 2021-07-01 2021-09-29 nvelope -03) ervices and Early Warning S ystems BWDB-G5-2 / Procurement o f Systems for Morphological Component B- Strengthenin Survey- (i) 15 TDS ii) 12 RTK g Hydrological Information S Single Stage - One E IDA / 58370 Post Request for Bids Open - National 1,800,000.00 1,130,556.00 Completed 2019-12-07 2019-01-01 2019-12-12 2020-01-23 2019-01-30 2020-02-22 2019-03-11 2020-03-28 2019-03-31 2020-09-24 2020-01-08 GPS iii) 6 DGPS Beacon recei ervices and Early Warning S nvelope ver iv) 8 Total Station v) First ystems Order Digital Leveling Machin e & vi) Sub-bottom Profiler Component B- Strengthenin BWDB-G-20 / Purchase of Off Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 22,197.00 0.00 Canceled 2019-07-14 2019-07-19 2019-08-02 2019-08-09 2019-08-30 2019-10-29 ice Equipment (Package-02) nvelope ervices and Early Warning S ystems BWDB-G6 / Coastal Flood Mo Component B- Strengthenin nitoring Stations- 1) 40 Wate g Hydrological Information S Open - Internationa Single Stage - One E IDA / 58370 Post Request for Bids 826,761.64 0.00 Canceled 2020-03-15 2020-11-10 2020-03-20 2020-11-11 2020-05-01 2020-05-31 2020-07-05 2021-05-01 r Level Stations 2) Repeater ervices and Early Warning S l nvelope Network 3) Software and Har ystems dware Component B- Strengthenin BWDB-G18A / Purchase of Of Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 20,530.00 19,066.40 Completed 2021-07-01 2020-09-13 2021-07-05 2021-07-26 2020-09-30 2021-08-02 2020-09-29 2021-08-16 2021-01-07 2021-09-15 2021-07-09 fice Equipment nvelope ervices and Early Warning S ystems Component B- Strengthenin BWDB-G-18 / Purchase of Off Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 44,518.00 0.00 Canceled 2018-01-25 2019-12-01 2018-01-30 2018-02-13 2018-04-09 2018-02-20 2018-03-13 2018-06-28 ice Equipment (Phase-01) nvelope ervices and Early Warning S ystems Component B- Strengthenin BWDB-18A / Purchase of Offi Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 22,196.64 0.00 Canceled 2020-02-02 2020-02-07 2020-03-20 2020-04-19 2020-05-24 2020-11-20 ce Equipment nvelope ervices and Early Warning S ystems BWDB-G 23 / Purchase of 06 Component B- Strengthenin Single Stage - One E Drilling Machine ( Rig Machin IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 176,470.00 299,921.18 Completed 2021-01-03 2022-02-13 2021-01-08 2021-02-19 2022-03-24 2021-03-21 2022-05-11 2021-04-25 2022-06-19 2021-10-22 nvelope e) for GW well Construction ervices and Early Warning S ystems BWDB-G 21 / Purchase of VC Component B- Strengthenin Single Stage - One E System (in 25 location) inclu IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 410,000.00 0.00 Canceled 2021-04-04 2021-12-22 2021-04-09 2021-05-21 2022-01-27 2021-06-20 2022-03-23 2021-07-25 2021-10-23 nvelope ding ICT ervices and Early Warning S ystems BWDB-G25 / Purchase of 03 Component B- Strengthenin Open - Internationa Single Stage - One E nos. Survey Boat & 03 nos. IDA / 58370 g Hydrological Information S Prior Request for Bids 2,235,295.00 1,562,043.30 Signed 2021-03-28 2021-09-01 2021-04-02 2021-12-15 2021-05-14 2022-01-10 2021-06-13 2022-04-12 2021-07-18 2022-05-22 2022-07-13 l nvelope Catamaran ervices and Early Warning S ystems Component B- Strengthenin BWDB-G19A / Purchase of Of Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 20,000.00 19,409.25 Completed 2021-10-03 2021-09-12 2021-10-08 2021-11-19 2021-10-04 2021-12-19 2021-10-25 2022-01-23 2021-11-11 2022-03-24 2022-01-13 fice Furniture and Fixtures nvelope ervices and Early Warning S ystems BWDB-G 22 / Purchase of 04 Component B- Strengthenin nos. Multi-Beam Echo sounde g Hydrological Information S Single Stage - One E IDA / 58370 Post Request for Bids Open - National 1,880,000.00 1,783,076.76 Completed 2021-04-04 2021-08-08 2021-04-09 2021-05-21 2021-09-19 2021-06-20 2021-11-14 2021-07-25 2021-12-26 2021-10-23 r with survey grade laptop ( ervices and Early Warning S nvelope Software and Accessories) ystems BWDB-G28 / Purchase of ICT Component B- Strengthenin Single Stage - One E Equipment for Data Centre & IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 590,000.00 0.00 Canceled 2021-07-01 2022-06-09 2021-07-06 2021-07-08 2022-07-28 2021-07-09 2022-06-01 2021-08-13 2021-11-11 nvelope Hydrological Network Upgrad ervices and Early Warning S ation ystems BWDB-G 6 / Coastal Flood M Component B- Strengthenin onitoring Stations, Software g Hydrological Information S Open - Internationa Single Stage - One E and Hardware ( Costal Inund IDA / 58370 Post Request for Bids 760,000.00 587,062.20 Signed 2021-03-14 2020-11-05 2021-03-19 2021-04-30 2021-01-20 2021-05-30 2021-04-29 2021-07-04 2021-08-21 2022-03-01 ervices and Early Warning S l nvelope ation & Storm Monitoring Sys ystems tem and Comprehensive Ann ual Maintenance BWDB-G29 / Purchase of FF Component B- Strengthenin Single Stage - One E WC Forecasting Software incl IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 470,588.00 0.00 Canceled 2021-01-03 2021-01-08 2021-02-19 2021-03-21 2021-04-25 2021-10-22 nvelope uding training ervices and Early Warning S ystems Component B- Strengthenin BWDB-G8 / Procurement of Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 60,000.00 0.00 Canceled 2022-02-01 2022-02-06 2022-03-08 2022-03-18 2022-04-22 2022-05-22 Calibration goods nvelope ervices and Early Warning S ystems BWDB-G15B / Development Component B- Strengthenin Single Stage - One E Under Imple of DEM using Arial Photograp IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 400,000.00 0.00 2022-12-15 2023-02-14 2022-12-20 2023-01-17 2023-03-21 2023-02-16 2023-04-06 2023-03-23 2023-07-21 nvelope mentation hic Data ervices and Early Warning S ystems BWDB-G28-2 / Purchase of I Component B- Strengthenin Single Stage - One E Pending Impl CT Equipment for Data Centr IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 590,000.00 0.00 2022-10-02 2022-10-07 2022-10-09 2022-10-10 2022-11-14 2023-07-12 nvelope ementation e & Hydrological Network Up ervices and Early Warning S gradation ystems Page 2 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BWDB-NS7 / Hiring of Vehicl Component B- Strengthenin Single Stage - One E es for project office and field IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 457,898.75 590,729.87 Signed 2017-09-21 2018-11-08 2017-09-26 2017-10-24 2018-12-19 2017-11-03 2019-01-19 2017-12-08 2019-01-21 2021-07-03 nvelope works( 6 double cabin pickup ervices and Early Warning S ) ystems BWDB-NS6 / Hiring of Survey Component B- Strengthenin Single Stage - One E , Study & Investigation servic IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 169,994.90 70,075.50 Completed 2017-09-12 2018-04-24 2017-09-17 2017-10-15 2018-06-19 2017-10-29 2018-07-17 2017-12-03 2018-09-07 2018-12-03 nvelope es ervices and Early Warning S ystems BWDB-NS10 / Hiring of Vehic Component B- Strengthenin Single Stage - One E les (02 nos Microbus)(Phase- IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 45,790.00 43,552.46 Completed 2018-01-11 2018-01-04 2018-01-14 2018-01-28 2018-02-13 2018-02-04 2018-03-14 2018-02-25 2018-04-08 2019-08-31 2019-08-26 nvelope 01) ervices and Early Warning S ystems BWDB-NS4 / Hiring of Sampli Component B- Strengthenin ng and Analysis of Groundwa g Hydrological Information S Single Stage - One E IDA / 58370 Post Request for Bids Open - National 500,178.07 341,891.43 Signed 2019-02-06 2019-12-12 2019-02-11 2019-03-25 2020-01-06 2019-04-24 2020-01-19 2019-05-29 2020-01-30 2020-05-20 ter Samples for Water Qualit ervices and Early Warning S nvelope y (20 physio-chemical param ystems eters) Services BWDB-NS5 / Survey, Study, Component B- Strengthenin Single Stage - One E & Investigation (Survey of B IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 305,265.84 218,401.72 Completed 2018-12-06 2020-03-08 2018-12-11 2019-01-22 2020-05-04 2019-02-21 2020-05-31 2019-03-28 2020-06-12 2019-09-24 2022-01-05 nvelope M for SW level Stations) ervices and Early Warning S ystems BWDB-NS8 / Survey, Study Component B- Strengthenin Single Stage - One E & Investigation (Survey of B IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 254,388.20 119,530.04 Completed 2018-12-02 2019-07-02 2018-12-07 2018-12-21 2019-07-22 2018-12-28 2019-08-06 2019-01-18 2019-08-31 2021-02-26 2020-05-03 nvelope M for GW level Stations) ervices and Early Warning S ystems Component B- Strengthenin BWDB-NS9 / Hiring of Vehicl Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 137,369.63 164,445.12 Signed 2019-07-02 2019-06-03 2019-07-07 2019-07-21 2019-06-27 2019-07-28 2019-07-21 2019-08-18 2019-08-07 2021-08-26 es (02 nos. Micro-bus)) nvelope ervices and Early Warning S ystems BWDB-NS11 / Design of Hyd Component B- Strengthenin Single Stage - One E rology-lab and Research Cent IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 48,270.16 41,815.87 Completed 2018-12-24 2019-01-27 2018-12-30 2019-01-13 2019-02-13 2019-01-20 2019-02-27 2019-02-10 2019-03-17 2021-12-20 2021-03-07 nvelope er ervices and Early Warning S ystems Component B- Strengthenin BWDB-NS13 / Service of C & Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 19,079.10 14,309.36 Signed 2019-01-31 2019-04-30 2019-02-05 2019-03-19 2019-05-15 2019-04-18 2019-06-19 2019-05-23 2019-06-01 2021-06-30 F Agent for ICB nvelope ervices and Early Warning S ystems BWDB-NS-6 / Survey, Study Component B- Strengthenin Single Stage - One E & Investigation (site survey f IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 76,317.00 70,166.29 Completed 2018-02-06 2018-06-03 2018-02-11 2018-03-04 2018-06-18 2018-03-11 2018-07-17 2018-04-01 2018-09-02 2018-06-28 2019-03-20 nvelope or selection of Hydrometric s ervices and Early Warning S tations) ystems BWDB-NS14 / Logistic Suppo rt on Training On General Hy Component B- Strengthenin drology, River Morphology & g Hydrological Information S Ground Water Hydrology & S IDA / 58370 Post Direct Selection Direct 100,000.00 71,721.68 Completed 2019-02-18 2018-10-14 2019-02-23 2019-02-25 2019-03-30 2019-08-09 2019-09-26 ervices and Early Warning S tudy tour/Exposure Visit for S ystems enior Level Officials on Hydro logical Equipment Experienc e in European Countries/Orga nizations Component B- Strengthenin BWDB-NS12 / Outsourcing of Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 161,918.09 0.00 Canceled 2018-11-29 2018-12-04 2019-01-15 2019-02-14 2019-03-21 2021-06-30 Manpower for PIU Office nvelope ervices and Early Warning S ystems BWDB-NS2 / Hiring Facilitati Component B- Strengthenin on of Regional: data sharing, g Hydrological Information S Single Stage - One E collaboration on identifying tr IDA / 58370 Post Request for Bids Open - National 1,150,000.00 0.00 Canceled 2019-01-17 2019-01-22 2019-03-05 2019-04-04 2019-05-09 2020-05-08 ervices and Early Warning S nvelope ansboundary risk,cooperatio ystems n on mitigating transboundar y risk works BWDB- NS1 / Hiring Media a Component B- Strengthenin Single Stage - One E Under Imple nd Communication outreach IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 40,000.00 0.00 2021-07-04 2022-12-13 2021-07-09 2021-08-06 2021-08-16 2021-09-20 2022-09-15 nvelope mentation Work (media access purchas ervices and Early Warning S e) ystems BWDB-NS15 / Crest level, Ba nkline, Spot level, Bathymetr Component B- Strengthenin y & river cross section, struc g Hydrological Information S Single Stage - One E IDA / 58370 Post Request for Bids Open - National 447,060.00 0.00 Canceled 2021-04-08 2022-06-26 2021-04-13 2021-05-04 2022-07-20 2021-06-03 2022-07-25 2021-07-08 2021-11-05 ture inventory, etc. survey ervices and Early Warning S nvelope and Secondary Data Collectio ystems n for Consultancy Services of BWDB-C2 BWDB-NS3 / Hiring Commun Component B- Strengthenin ity based EWS in 2 flood pron g Hydrological Information S Single Stage - One E e districts (Nethrkona and Su IDA / 58370 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2021-05-02 2021-05-07 2021-06-18 2021-07-18 2021-08-22 2022-08-22 ervices and Early Warning S nvelope namganj) in collaboration wit ystems h DDM, including community participation Work BWDB-NS15-2 / Crest level, Component B- Strengthenin Bank Line, Spot Level, Bathy g Hydrological Information S Single Stage - One E metry, River Cross-sections, IDA / 58370 Post Request for Bids Open - National 447,060.00 0.00 Signed 2022-10-02 2022-06-30 2022-10-07 2022-10-28 2022-08-11 2022-11-27 2022-08-30 2023-01-01 2023-04-05 2023-05-01 ervices and Early Warning S nvelope Structure inventory, etc. surv ystems ey and secondary services of BWDB-C2 BWDB-NS7A / Hiring of Vehic Component B- Strengthenin Single Stage - One E le- 08 nos. Double Cabin Pick IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 294,118.00 0.00 Canceled 2021-03-21 2021-03-26 2021-05-07 2021-06-06 2021-07-11 2022-01-07 nvelope -up/Jeep ervices and Early Warning S ystems Component B- Strengthenin BWDB-NS9A / Hiring of Vehic Single Stage - One E IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 82,353.00 0.00 Canceled 2021-03-01 2021-03-06 2021-04-17 2021-05-17 2021-06-21 2022-06-30 le-02 nos. Microbus nvelope ervices and Early Warning S ystems BWDB NS-3 / Community ba Component B- Strengthenin Single Stage - One E sed EWS in 02 flood prone di IDA / 58370 g Hydrological Information S Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-11-29 2022-12-02 2022-12-23 2022-12-30 2023-02-03 2023-12-30 nvelope stricts ( Netrokona and Suna ervices and Early Warning S mgonj)- Piloting ystems CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BWDB-C1 / Hiring Water Res Component B- Strengthenin Quality And Cost- Open - Internationa ources System Integrator (W IDA / 58370 g Hydrological Information S Prior 1,351,961.44 1,522,122.86 Under Review 2017-09-14 2018-01-10 2017-10-12 2018-04-19 2017-11-25 2018-09-13 2017-12-23 2018-01-22 2018-11-13 2018-02-26 2019-01-28 2018-04-02 2019-04-12 2021-06-30 Based Selection l RSI) Consultancy services ervices and Early Warning S ystems Page 3 Component B- Strengthenin BWDB C-21 / Performance A Fixed Budget Sele IDA / 58370 g Hydrological Information S Post Open - National 69,255.00 63,735.84 Signed 2018-12-02 2019-03-20 2018-12-23 2019-02-05 2019-07-24 2019-03-05 2019-08-22 2019-04-04 2019-08-22 2019-05-09 2019-11-20 2019-06-13 2020-01-01 2021-06-30 uditing of 3 PIUs by PCU ction ervices and Early Warning S ystems BWDB-C8 / Hiring project Te Component B- Strengthenin Quality And Cost- chnical Consultant (PTC) in PI IDA / 58370 g Hydrological Information S Post Open - National 146,947.00 0.00 Canceled 2017-09-28 2018-01-25 2017-10-19 2017-12-02 2017-12-30 2018-01-29 2018-03-05 2018-04-09 2020-10-07 Based Selection U services ervices and Early Warning S ystems BWDB-C 13 / Technical Cons ultancy on M&E: (i) Develop M&E framework and survey i Component B- Strengthenin nstrument; (ii) Conduct basel g Hydrological Information S Fixed Budget Sele ine survey and two monitorin IDA / 58370 Post Open - National 127,779.00 118,241.93 Signed 2019-12-04 2019-05-13 2019-12-25 2020-02-07 2019-11-06 2020-03-06 2019-12-05 2020-04-05 2020-01-07 2020-05-10 2020-02-11 2020-06-14 2020-03-31 2021-06-14 ervices and Early Warning S ction g surveys; (iii) Build capacity ystems and support PCU and BWDB PIU in developing & impleme nting M&E tools; and mid&en d-term evaluation. BWDB C-17 / Hiring of Consu Component B- Strengthenin Consultant Qualifi ltancy for Development of M IDA / 58370 g Hydrological Information S Post Open - National 57,021.00 0.00 Canceled 2019-07-15 2019-08-05 2019-09-18 2019-10-18 2019-11-22 2020-06-30 cation Selection obile Apps Services ervices and Early Warning S ystems Component B- Strengthenin BWDB C-20 / Hiring of Upgra Consultant Qualifi IDA / 58370 g Hydrological Information S Post Open - National 63,889.00 0.00 Canceled 2019-07-14 2019-08-04 2019-09-17 2019-10-17 2019-11-21 2020-06-30 ding Web-portal Services cation Selection ervices and Early Warning S ystems BWDB-C 22 / Development o f Mobile Apps Service, Upgra Component B- Strengthenin ding Web-portal Services and g Hydrological Information S Consultant Qualifi Develop, Supply & Installatio IDA / 58370 Post Open - National 205,882.00 0.00 Signed 2020-10-01 2022-03-12 2020-10-22 2020-12-05 2022-11-24 2021-01-04 2023-03-16 2021-02-08 2023-03-29 2021-08-07 ervices and Early Warning S cation Selection n Data and Information shari ystems ng Software to share informa tion between BWDB and Stak eholders. BWDB-C22 / Data and Infor mation sharing software to s Component B- Strengthenin hare information between B g Hydrological Information S Quality And Cost- IDA / 58370 Post Open - National 222,665.00 0.00 Canceled 2020-01-01 2022-03-12 2020-01-22 2020-03-06 2020-04-03 2020-05-03 2020-06-07 2020-07-22 2021-04-18 WDB and stakeholders includ ervices and Early Warning S Based Selection ing development of mobile a ystems pps and upgrading webportal - Supply and Instllation Component B- Strengthenin BWDB C-18 / Consultancy on Consultant Qualifi Pending Impleme IDA / 58370 g Hydrological Information S Post Open - National 50,000.00 0.00 2021-08-01 2021-08-22 2021-10-05 2021-11-04 2021-12-09 2022-09-05 Data Sharing Policy cation Selection ntation ervices and Early Warning S ystems BWDB-C16 / Hiring of consul Component B- Strengthenin Consultant Qualifi tancy for Development of Ins IDA / 58370 g Hydrological Information S Post Open - National 51,106.58 0.00 Canceled 2020-10-14 2020-11-04 2020-12-18 2021-01-17 2021-02-21 2021-08-20 cation Selection titutional Analysis of Dept. of ervices and Early Warning S Hydrology ystems BWDB-C14 / Hiring Technical studies on mitigatiing transb oundary disaster risks, regio Component B- Strengthenin nal collaboration, Risk analys g Hydrological Information S Quality And Cost- IDA / 58370 Post Open - National 435,844.00 0.00 Canceled 2019-10-13 2020-01-12 2020-02-25 2020-03-24 2020-04-23 2020-05-28 2020-07-02 2022-07-02 is and Mitigation - Hazard, vu ervices and Early Warning S Based Selection lnerability, risk assessment, ystems development of feasibility st udies for mitigation measure s of flood and disaster BWDB C-19 / Hiring of Desig Component B- Strengthenin Consultant Qualifi Open - Internationa n, Implementation and Traini IDA / 58370 g Hydrological Information S Post 82,142.00 0.00 Canceled 2019-07-14 2019-08-04 2019-09-17 2019-10-17 2019-11-21 2020-06-30 cation Selection l ng on CAP Services ervices and Early Warning S ystems BWDB-C15 / Development o f hydrological service produc ts- sediment prediction & riv Component B- Strengthenin er bank erosion, hyd. drough g Hydrological Information S Quality And Cost- Open - Internationa IDA / 58370 Post 530,000.00 0.00 Canceled 2021-03-15 2021-04-05 2021-05-12 2021-07-11 2021-08-10 2021-09-14 2021-10-19 2022-10-19 t prediction, basin wise flood ervices and Early Warning S Based Selection l forecast, salinity intrusion for ystems ecast, ground water & surfac e water outlook and forecast, etc. and upgrade existing we bsite BWDB-C2 / Expand flood for Component B- Strengthenin ecasting model (whole count g Hydrological Information S Consultant Qualifi Open - Internationa ry), Improve inundation mod IDA / 58370 Post 552,940.00 0.00 Canceled 2021-03-15 2021-04-05 2021-05-12 2021-07-11 2021-08-15 2022-02-11 ervices and Early Warning S cation Selection l el in coastal and hotspot are ystems as (depth and area of inunda tion BWDB-C 15 / Development o f hydrological service produc ts- sediment prediction & riv Component B- Strengthenin er bank erosion, hyd. drough g Hydrological Information S Fixed Budget Sele Open - Internationa IDA / 58370 Post 530,000.00 0.00 Signed 2021-05-09 2021-06-29 2021-05-30 2021-07-13 2021-07-13 2021-11-09 2021-08-10 2021-12-22 2021-09-09 2022-03-15 2021-10-14 2022-04-21 2021-11-18 2022-05-31 2022-08-15 t prediction, basin wise flood ervices and Early Warning S ction l forecast, salinity intrusion for ystems ecast, ground water & surfac e water outlook and forecast, etc. and upgrade existing we bsite BWDB- C24 / Feasibility and Component B- Strengthenin Consultant Qualifi Under Implement details technical design for s IDA / 58370 g Hydrological Information S Post Open - National 300,000.00 0.00 2023-04-16 2023-08-12 2023-04-30 2023-05-28 2023-06-11 2023-06-23 2023-12-20 cation Selection ation econd phase of BWCSRP ervices and Early Warning S ystems BWDB-C24 / Pre-feasibility a Component B- Strengthenin Quality And Cost- Open - Internationa nd details technical design fo IDA / 58370 g Hydrological Information S Prior 1,270,000.00 0.00 Canceled 2021-05-02 2021-05-23 2021-06-07 2021-07-19 2021-08-18 2021-09-22 2021-10-27 2022-04-25 Based Selection l r second phase of BWCSRP ervices and Early Warning S ystems INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BWBD-C3 / Hiring project Co Component B- Strengthenin Individual Consult ordination Consultant PCU se IDA / 58370 g Hydrological Information S Post Open 138,476.00 89,914.18 Completed 2017-09-12 2017-10-31 2017-11-21 2018-01-02 2018-08-31 2020-01-01 2020-12-14 ant Selection rvices ervices and Early Warning S ystems BWDB-C4 / Hiring Senior Soc Component B- Strengthenin Individual Consult ial safeguards and communit IDA / 58370 g Hydrological Information S Post Open 47,914.00 51,991.32 Signed 2019-09-08 2018-03-04 2019-10-27 2019-03-18 2019-11-17 2019-03-21 2019-12-22 2019-04-08 2020-12-21 ant Selection cations specialist for PCU (Na ervices and Early Warning S tional) serivces ystems BWDB-C5 / Hiring Senior Env Component B- Strengthenin Individual Consult ironmental safeguards specia IDA / 58370 g Hydrological Information S Post Open 47,914.00 29,522.27 Completed 2019-09-08 2019-10-27 2019-11-17 2019-12-22 2018-10-11 2020-12-21 2019-04-22 ant Selection list for PCU (National) service ervices and Early Warning S s ystems Page 4 BWDB-C9 / Hiring Senior M& Component B- Strengthenin Individual Consult E specialist for PIU (National) IDA / 58370 g Hydrological Information S Post Open 121,381.00 103,975.23 Signed 2017-09-28 2018-01-25 2017-11-16 2019-03-18 2017-12-07 2019-03-21 2018-01-11 2019-04-04 2020-01-11 ant Selection services ervices and Early Warning S ystems BWDB-C10 / Hiring ground Component B- Strengthenin Individual Consult Water Specialist(National) se IDA / 58370 g Hydrological Information S Post Open 69,918.00 59,474.92 Completed 2017-09-28 2018-01-25 2017-11-16 2018-09-13 2017-12-07 2018-09-18 2018-01-11 2018-11-15 2020-01-11 2019-09-09 ant Selection rvices ervices and Early Warning S ystems Component B- Strengthenin BWDB-C11 / Hiring Administr Individual Consult IDA / 58370 g Hydrological Information S Post Open 44,880.25 50,769.04 Signed 2017-09-12 2017-12-07 2017-10-31 2018-04-08 2017-11-21 2018-04-09 2017-12-26 2018-06-07 2021-06-30 ative Associate services ant Selection ervices and Early Warning S ystems Component B- Strengthenin BWDB-C12 / Hiring Logistic Individual Consult IDA / 58370 g Hydrological Information S Post Open 44,880.25 35,004.72 Terminated 2017-09-12 2017-11-16 2017-10-31 2018-04-03 2017-11-21 2018-04-09 2017-12-26 2018-06-08 2021-06-29 Associate Services ant Selection ervices and Early Warning S ystems BWDB-C6 / Hiring of Senior P Component B- Strengthenin Individual Consult rocurement specialist for PIU IDA / 58370 g Hydrological Information S Post Open 209,296.62 230,084.56 Signed 2017-12-17 2017-11-16 2018-02-04 2018-04-26 2018-02-25 2018-04-09 2018-04-01 2018-05-25 2021-06-30 ant Selection ( National ). ervices and Early Warning S ystems BWDB-C7 / Hiring of Senior F Component B- Strengthenin Individual Consult inancial Management speciali IDA / 58370 g Hydrological Information S Post Open 209,296.62 179,173.80 Signed 2017-12-17 2017-11-16 2018-02-04 2018-04-16 2018-02-25 2018-04-16 2018-04-01 2018-06-09 2021-06-30 ant Selection st for PIU ( national ) ervices and Early Warning S ystems BWDB-C17 / Hiring of consul Component B- Strengthenin Individual Consult tancy for Development of M IDA / 58370 g Hydrological Information S Post Open 82,142.00 0.00 Canceled 2018-07-15 2018-09-02 2018-09-23 2018-10-28 2019-10-28 ant Selection obile apps services ervices and Early Warning S ystems Component B- Strengthenin BWDB-C20 / Hiring of Upgra Individual Consult IDA / 58370 g Hydrological Information S Post Open 63,889.00 0.00 Canceled 2019-01-24 2019-03-14 2019-04-04 2019-05-12 2020-01-07 ding webportal services ant Selection ervices and Early Warning S ystems BWDB-C18 / Hiring Consulta Component B- Strengthenin Individual Consult ncy on Data Sharing Policy S IDA / 58370 g Hydrological Information S Post Open 51,106.60 0.00 Canceled 2019-01-10 2019-02-28 2019-03-21 2019-04-25 2020-04-24 ant Selection ervices ervices and Early Warning S ystems BWDB-C13 / Hiring Technical Component B- Strengthenin consultancy on M&E:Develop g Hydrological Information S Individual Consult IDA / 58370 Post Open 127,779.00 0.00 Canceled 2017-09-28 2017-11-16 2017-12-07 2018-01-11 2021-01-10 M&E framework and survey i ervices and Early Warning S ant Selection nstruments,Conduct Baseline ystems survey etc. BWDB- C8 / Hiring Project Te Component B- Strengthenin Individual Consult chnical Consultant (PTC) in PI IDA / 58370 g Hydrological Information S Post Limited 146,947.00 117,248.16 Signed 2019-12-04 2018-03-11 2019-12-09 2019-03-11 2019-12-30 2019-03-21 2020-02-03 2019-04-06 2022-01-23 ant Selection U services ervices and Early Warning S ystems Component B- Strengthenin BWDB-C10A / Senior Ground Individual Consult IDA / 58370 g Hydrological Information S Post Limited 50,000.00 44,345.91 Completed 2019-12-04 2019-09-08 2019-12-09 2019-09-24 2019-12-30 2019-12-04 2020-02-03 2020-01-02 2022-02-12 2020-11-24 Water Specialist ant Selection ervices and Early Warning S ystems BWDB-C21 / Hiring performa Component B- Strengthenin Individual Consult nce auditing of 3 Project Impl IDA / 58370 g Hydrological Information S Post Open 69,257.00 0.00 Canceled 2020-09-01 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection ementation Units by PCU ser ervices and Early Warning S vices. ystems BWDB-C19 / Hiring of design Component B- Strengthenin Individual Consult , implementation and trainin IDA / 58370 g Hydrological Information S Post Open 82,142.00 0.00 Canceled 2018-09-20 2018-11-08 2018-11-29 2019-01-06 2019-11-02 ant Selection g on CAP services ervices and Early Warning S ystems Component B- Strengthenin BWDB-C3A / Project Coordin Individual Consult IDA / 58370 g Hydrological Information S Post Open 75,000.00 0.00 Signed 2020-08-21 2020-07-05 2020-10-28 2020-10-05 2020-11-18 2020-10-08 2020-12-30 2020-11-04 2022-12-29 ation Consultant ant Selection ervices and Early Warning S ystems Component B- Strengthenin BWDB-C10B / Ground Water Individual Consult IDA / 58370 g Hydrological Information S Post Limited 18,790.00 0.00 Signed 2021-05-02 2021-03-01 2021-05-07 2021-03-08 2021-05-28 2021-05-02 2021-07-02 2021-05-25 2022-12-31 Specialist ant Selection ervices and Early Warning S ystems Component B- Strengthenin BWDB-C12A / Logistic Associ Individual Consult Pending Impleme IDA / 58370 g Hydrological Information S Post Limited 30,000.00 0.00 2021-05-09 2021-05-14 2021-06-04 2021-07-09 2022-12-31 ate ant Selection ntation ervices and Early Warning S ystems BWDB-C 2 / Development of hydrological service products - sediment prediction & river Component B- Strengthenin bank erosion, hyd. drought p g Hydrological Information S IDA / 58370 Post Direct Selection Direct 552,940.00 545,459.67 Signed 2021-05-16 2021-05-16 2021-05-26 2021-09-09 2021-07-30 2021-12-13 2022-01-26 rediction, basin wise flood for ervices and Early Warning S ecast, salinity intrusion forec ystems ast, ground water & surface water outlook and forecast, e tc. and upgrade existing web site Component B- Strengthenin BWDB-C25 / Senior Hydrolog Individual Consult IDA / 58370 g Hydrological Information S Post Open 56,470.00 28,183.06 Signed 2022-03-15 2022-04-16 2022-04-17 2022-08-16 2022-05-08 2022-08-17 2022-06-12 2022-09-03 2023-12-04 ist for PIU ant Selection ervices and Early Warning S ystems Component B- Strengthenin BWDB-C26A / Junior Hydrolo Individual Consult IDA / 58370 g Hydrological Information S Post Open 21,176.00 10,651.51 Signed 2022-03-15 2022-04-16 2022-04-18 2022-08-16 2022-05-09 2022-08-17 2022-06-13 2022-09-03 2023-12-05 gist for PIU ant Selection ervices and Early Warning S ystems BWDB C-5A / Senior Environ Component B- Strengthenin Individual Consult mental Safeguards Specialist IDA / 58370 g Hydrological Information S Post Direct - National 33,235.00 0.00 Signed 2022-10-16 2020-01-15 2022-10-26 2020-02-27 2022-11-16 2020-03-25 2022-12-21 2023-04-20 2023-12-31 ant Selection for PCU ervices and Early Warning S ystems Component B- Strengthenin BWDB-C26B / Junior Hydrolo Individual Consult IDA / 58370 g Hydrological Information S Post Open 21,176.00 0.00 Canceled 2022-03-15 2022-04-16 2022-04-18 2022-05-09 2022-06-13 2023-12-05 gist for PIU ant Selection ervices and Early Warning S ystems BWDB-C27 / Community bas Component B- Strengthenin Under Implement ed EWS in 2 flood prone distri IDA / 58370 g Hydrological Information S Post Direct Selection Direct - National 309,550.00 0.00 2023-04-30 2023-08-19 2023-05-10 2023-06-21 2024-06-15 ation cts (Nethrkona and Sunamga ervices and Early Warning S nj)-Piloting ystems BWDB-C5B / Senior Environ Component B- Strengthenin Individual Consult Pending Impleme mental Safeguards Specialist IDA / 58370 g Hydrological Information S Post Direct - National 8,750.00 0.00 2023-10-15 2023-10-17 2023-10-22 2023-11-01 2024-02-29 ant Selection ntation for PCU ervices and Early Warning S ystems BWDB-C4A / Senior Social Sa Component B- Strengthenin Individual Consult Pending Impleme feguards and Communication IDA / 58370 g Hydrological Information S Post Direct - National 8,200.00 0.00 2023-10-15 2023-10-17 2023-10-24 2023-11-01 2024-02-29 ant Selection ntation Specialist ervices and Early Warning S ystems Page 5