PROCUREMENT PLAN (Textual Part) Project Country: Republic of Tajikistan information Full Project Name: TAJIKISTAN RESILIENT IRRIGATION (project preparation) Total Finance ($): USD 0,517 million Project Number: P175356 Project Implementation agency Agency on Land Reclamation and Irrigation Date of the Procurement Plan November 17, 2021 (initial) Period covered by this Procurement Project preparation duration (till Plan: June 30, 2022) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017, August 2018, and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Tendering with Unlimited Participation” method set forth in the Law of the Republic of Tajikistan “Оn Public Procurement of Goods, Works and Services”, # 168 dated March 3, 2006 (as amended by Law #815, the “Law of the Republic of Tajikistan on “Introduction of Amendments and Additions to the Law of the Republic of Tajikistan on ‘Public Procurement of Goods, Works and Services’” dated April 16, 2012), provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • The request for bids/request for proposals document, including contract forms, acceptable to the Bank shall be used. • Borrower shall put in place an effective complaints review mechanism with procurement related complaints, and shall disclose the details in all the bidding documents. All complaints shall be recorded by the Borrower in the appropriate tracking and monitoring system, as agreed between the Bank and the Borrower. • No preference shall be applied under competitive bidding following national market approach. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as as tendering with limited participation, request for quotations, direct contracting, may be used on the above stated conditions. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): “Not Applicable” PROCUREMENT Tajikistan : Tajikistan Strengthening Water and Irrigation Management Project PLAN General Information Country: Tajikistan 2021-11-19 Bank’s Approval Date of the Original Procurement Plan: 2022-12-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175356 GPN Date: 2022-08-22 Project Name: Tajikistan Strengthening Water and Irrigation Management Project Loan / Credit No: / , IDA / E0790 Project Management Unit for the “Fergana Valley Water Resources Management Project” Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SWIM-CW-RFQ-01 / Reconstr Request for Quota uction of administrative build Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Imp 2023-09-2 IDA / E0790 Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-02-04 2023-04-01 ings of the Vakhsh , Shuroba titutional Strengthening tions nvelope lementation 8 PD) d scheme organizations and SDLRI in BHC National Procure SWIM-CW-NCB-03 / Canal O Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2024-06-2 IDA / E0790 Post Request for Bids Open - National 850,000.00 0.00 2023-09-04 2023-09-09 2023-10-21 2023-11-20 2023-12-25 MC ents nvelope 1 Envelope proce lementation 2 ss (Non Bank-SPD ) National Procure SWIM-CW-NCB-04 / Central c Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2024-07-0 IDA / E0790 Post Request for Bids Open - National 265,000.00 0.00 2023-09-20 2023-09-25 2023-11-06 2023-12-06 2024-01-10 anal system ents nvelope 1 Envelope proce lementation 8 ss (Non Bank-SPD ) National Procure SWIM-CW-NCB-07 / Jilikul Kof Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2025-02-2 IDA / E0790 Post Request for Bids Open - National 1,340,000.00 0.00 2024-05-06 2024-05-11 2024-06-22 2024-07-22 2024-08-26 ir canal ents nvelope 1 Envelope proce lementation 2 ss (Non Bank-SPD ) Request for Quota SWIM-CW-RFQ-02 / PMU offic Request for Quota Single Stage - One E Pending Imp 2024-08-1 IDA / E0790 Project Management Post Open - National tions (Non Bank-S 65,000.00 0.00 2023-12-20 2024-02-14 e renovation tions nvelope lementation 2 PD) National Procure SWIM-CW-NCB-02 / Rehabilit ment Document - ation of head water intake fa Irrigation Scheme Improvem Single Stage - One E Pending Imp 2025-03-0 IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 800,000.00 0.00 2024-05-20 2024-05-25 2024-07-06 2024-08-05 2024-09-09 cilities at PK33 in the system ents nvelope lementation 8 ss (Non Bank-SPD of Vakhsh, Shurabad main ca ) nals National Procure SWIM-CW-NCB-05 / Rehabilit ment Document - ation of the subsystem of the Irrigation Scheme Improvem Single Stage - One E Pending Imp 2025-02-1 IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 2,175,000.00 0.00 2024-04-29 2024-05-04 2024-06-15 2024-07-15 2024-08-19 Northern branch in the syste ents nvelope lementation 5 ss (Non Bank-SPD m of the Vakhsh main canal ) National Procure SWIM-CW-NCB-06 / Rehabilit ment Document - ation of the subsystem Canal Irrigation Scheme Improvem Single Stage - One E Pending Imp 2025-02-1 IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 1,825,000.00 0.00 2024-04-30 2024-05-05 2024-06-16 2024-07-16 2024-08-20 L-2 Head in the system of the ents nvelope lementation 6 ss (Non Bank-SPD Vakhsh main canal ) Request for Bids - SWIM-CW-ICB-01 / Rehabilita Irrigation Scheme Improvem Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2025-02-1 tion VMK system subsystem IDA / E0790 Post Request for Bids 5,675,000.00 0.00 2024-05-01 2024-05-06 2024-06-17 2024-07-17 2024-08-21 ents l nvelope (1 envelope proce lementation 7 Kumsangir canal ss) National Procure SWIM-CW-NCB-08 / Rehabilit Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2025-01-2 ation of Shurobad main canal IDA / E0790 Post Request for Bids Open - National 1,215,000.00 0.00 2024-04-10 2024-04-15 2024-05-27 2024-06-26 2024-07-31 ents nvelope 1 Envelope proce lementation 7 system ss (Non Bank-SPD ) SWIM-CW-NCB-010 / Emerge National Procure ncy recovery work on rehabili ment Document - Irrigation Scheme Improvem Single Stage - One E Pending Imp 2023-09-3 tation of the floating platform IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 450,000.00 0.00 2022-12-12 2022-12-17 2023-01-28 2023-02-27 2023-04-03 ents nvelope lementation 0 and gates and the Dangara ss (Non Bank-SPD main canal of irrigation tunne ) l of Dangara district National Procure SWIM-CW-NCB-011 / Critical ment Document - Irrigation Scheme Improvem Single Stage - One E Pending Imp 2024-09-1 reconstruction of the Beshke IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 500,000.00 0.00 2023-12-01 2023-12-06 2024-01-17 2024-02-16 2024-03-22 ents nvelope lementation 8 nt hydroelectric complex ss (Non Bank-SPD ) Request for Quota SWIM-CW-RFQ-03 / Renovati Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Imp 2023-10-0 IDA / E0790 Post Open - National tions (Non Bank-S 20,000.00 0.00 2023-02-12 2023-04-09 on the IMIS department in A titutional Strengthening tions nvelope lementation 6 PD) MI SWIM-CW-NCB-014 / SCADA National Procure system design, supply, install ment Document - Irrigation Scheme Improvem Single Stage - One E Pending Imp 2024-04-2 ation and commissioning of IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 200,000.00 0.00 2023-07-03 2023-07-08 2023-08-19 2023-09-18 2023-10-23 ents nvelope lementation 0 main water intakes, control g ss (Non Bank-SPD ates and pumping stations ) National Procure SWIM-CW-NCB-09 / Rehabilit Irrigation Scheme Improvem Single Stage - One E ment Document - Pending Imp 2024-03-3 ation of the Dangara Main Ca IDA / E0790 Post Request for Bids Open - National 252,000.00 0.00 2023-06-12 2023-06-17 2023-07-29 2023-08-28 2023-10-02 ents nvelope 1 Envelope proce lementation 0 nal (DMK) ss (Non Bank-SPD ) National Procure SWIM-CW-NCB-01 / Reconstr ment Document - uction of mechanical repair/p Irrigation Scheme Improvem Single Stage - One E Pending Imp 2025-11-0 IDA / E0790 Post Request for Bids Open - National 1 Envelope proce 700,000.00 0.00 2025-01-13 2025-01-18 2025-03-01 2025-03-31 2025-05-05 ump shop with installation of ents nvelope lementation 1 ss (Non Bank-SPD equipment in Lower Vakhsh ) and Upper Kafernigan GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SWIM-G-NCB-03 / Equipment Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 150,000.00 0.00 2024-01-08 2024-01-13 2024-02-24 2024-03-25 2024-04-29 2024-10-26 for the ALRI design group titutional Strengthening nvelope ementation SWIM-G-NCB-01 / Procureme nt of office furniture and equi Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 150,000.00 0.00 2023-07-10 2023-07-15 2023-08-26 2023-09-25 2023-10-30 2024-04-27 pment for organizations of th titutional Strengthening nvelope ementation e Vakhsh, Shurobad and BHC schemes. SWIM-G-NCB-05 / Procureme nt of heavy equipment for W Water Sector Reform and Ins Single Stage - One E Pending Impl UAs in the Lower Vakhsh and IDA / E0790 Post Request for Bids Open - National 920,000.00 0.00 2025-01-06 2025-01-11 2025-02-22 2025-03-24 2025-04-28 2025-10-25 titutional Strengthening nvelope ementation Upper Vakhsh basins (based on a thorough needs assess ment) Page 1 SWIM-G-NCB-06 / Procureme nt and equipping of instrume nts for measuring/water level Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 210,000.00 0.00 2024-04-22 2024-04-27 2024-06-08 2024-07-08 2024-08-12 2025-02-08 (electronic sensors/radar for titutional Strengthening nvelope ementation transmitting water level moni toring data to ISMI, WIS and WUAs) SWIM-G-NCB-07 / Procureme nt of simple drip and sprinkle r irrigation systems, introduc Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 160,000.00 0.00 2024-08-05 2024-08-10 2024-09-21 2024-10-21 2024-11-25 2025-05-24 tion of laser leveling and oth titutional Strengthening nvelope ementation er irrigation management me thods for WUA demonstration plots SWIM-G-NCB-08 / Procureme nt of heavy equipment for th Water Sector Reform and Ins Single Stage - One E Pending Impl IDA / E0790 Post Request for Bids Open - National 540,000.00 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 2024-03-02 e scheme organizations Vakh titutional Strengthening nvelope ementation sh and Shurobad SWIM-RFQ-G-01 / Procureme nt of equipment and furnitur Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Impl e for the WUA support depart IDA / E0790 Post Open - National 10,000.00 0.00 2023-02-06 2023-04-03 2023-09-30 titutional Strengthening tions nvelope ementation ment in AMI (including for th e Сomplaint Investigation Me chanism department) SWIM-RFQ-G-03 / Procureme nt of vehicles for organizatio Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Impl IDA / E0790 Post Open - National 60,000.00 0.00 2024-02-10 2024-04-06 2024-10-03 ns of the level of the Vakhsh titutional Strengthening tions nvelope ementation and Shurabad schemes SWIM-RFQ-G-04 / Procureme nt of office equipment, furnit Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Impl ure for 11 WUAs and tablets f IDA / E0790 Post Open - National 60,000.00 0.00 2024-02-24 2024-04-20 2024-10-17 titutional Strengthening tions nvelope ementation or 66 WUAs (+partial equipm ent for 20 WUAs based on ne eds assessment) SWIM-RFQ-G-05 / Procureme Water Sector Reform and Ins Request for Quota Single Stage - One E Pending Impl nt of furniture and equipmen IDA / E0790 Post Open - National 14,000.00 0.00 2023-04-01 2023-05-27 2023-11-23 titutional Strengthening tions nvelope ementation t for the IMSI department in AMI SWIM-G-NCB-02 / Hardware Water Sector Reform and Ins Single Stage - One E Pending Impl and software for IMIS, integra IDA / E0790 Post Request for Bids Open - National 200,000.00 0.00 2023-07-17 2023-07-22 2023-09-02 2023-10-02 2023-11-06 2024-05-04 titutional Strengthening nvelope ementation ted billing system, call center SWIM-G-NCB-04 / Procureme Single Stage - One E Pending Impl nt of vehicles for PMU and PC IDA / E0790 Project Management Post Request for Bids Open - National 130,000.00 0.00 2022-12-01 2022-12-06 2023-01-17 2023-02-16 2023-03-23 2023-09-19 nvelope ementation U in Bokhtar, WUA support gr oup in AMI SWIM-RFQ-G-06 / Procureme nt of office furniture and equi Request for Quota Single Stage - One E Pending Impl pment for PMU, PCU in Bokht IDA / E0790 Project Management Post Open - National 85,000.00 0.00 2022-12-24 2023-02-18 2023-08-17 tions nvelope ementation ar, PMU representatives in G UMI Zarafshan, Upper Vakhs h and BGK NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SWIM-CS-QCBS-01 / Preparat ion of feasibility study, detail ed engineering designs, envir onmental and social impact a Irrigation Scheme Improvem Quality And Cost- Under Implement / Post Open - National 500,000.00 0.00 2022-04-15 2022-07-07 2022-05-06 2022-09-01 2022-06-19 2022-10-11 2022-07-17 2022-08-16 2022-09-20 2022-10-25 2023-10-25 ssessments, and bidding doc ents Based Selection ation uments for performance impr ovement in the Vakhsh Main Canal (VMC) and Shurobod M ain Canal (ShMC) irrigation sc hemes SWIM-CS-QCBS-02 / Feasibili ty study and design estimate Irrigation Scheme Improvem Quality And Cost- Open - Internationa for the rehabilitation of the D IDA / E0790 Post 500,000.00 0.00 Under Review 2022-10-14 2022-11-11 2022-11-04 2022-12-18 2023-01-15 2023-02-14 2023-03-21 2023-04-25 2024-04-24 ents Based Selection l angara tunnel and the Beshk ent hydroelectric complex SWIM-CS-QCBS-07 / Develop ment of a River Basin Manag Water Sector Reform and Ins Quality And Cost- Open - Internationa Pending Impleme IDA / E0790 Post 600,000.00 0.00 2023-04-10 2023-05-01 2023-06-14 2023-07-12 2023-08-11 2023-09-15 2023-10-20 2024-10-19 ement Plan and support for c titutional Strengthening Based Selection l ntation apacity development of Vakh sh RBO SWIM-CS-QCBS-03 / Develop ment of an Irrigation Sector Water Sector Reform and Ins Quality And Cost- Open - Internationa Pending Impleme Development Strategy (inclu IDA / E0790 Post 1,100,000.00 0.00 2023-07-28 2023-08-18 2023-10-01 2023-10-29 2023-11-28 2024-01-02 2024-02-06 2025-02-05 titutional Strengthening Based Selection l ntation ding an audit of the energy s ector and revision of tariffs a nd subsidies) SWIM-CS-QCBS-04 / Support for the WUA department at A Water Sector Reform and Ins Quality And Cost- Open - Internationa Pending Impleme LRI to promote and administ IDA / E0790 Post 500,000.00 0.00 2023-01-25 2023-02-15 2023-03-31 2023-04-28 2023-05-28 2023-07-02 2023-08-06 2024-08-05 titutional Strengthening Based Selection l ntation er the incentive program for targeted WUAs and create a national WUA database SWIM-CS-QCBS-06 / Consulti ng services for institutional, f inancial management and co Water Sector Reform and Ins Quality And Cost- Open - Internationa Pending Impleme IDA / E0790 Post 850,000.00 0.00 2023-01-24 2023-02-14 2023-03-30 2023-04-27 2023-05-27 2023-07-01 2023-08-05 2024-08-04 mmercial capacity building, titutional Strengthening Based Selection l ntation GIS-based inventory and ass et management developmen t for single scheme-base SWIM-CS-QCBS-05 / Constru Irrigation Scheme Improvem Quality And Cost- Open - Internationa Pending Impleme ction supervision for Vakhsh IDA / E0790 Post 1,196,000.00 0.00 2023-05-05 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 ents Based Selection l ntation Main Canal and Shurobod irri gation systems Page 2 SWIM-CS-CQS-012 / Baseline Consultant Qualifi Pending Impleme IDA / E0790 Project Management Post Open - National 30,000.00 0.00 2027-06-01 2027-06-22 2027-08-05 2027-09-04 2027-10-09 2028-04-06 survey cation Selection ntation SWIM-CS-CQS-08 / Survey C Consultant Qualifi Pending Impleme onsulting Services for the Ba IDA / E0790 Project Management Post Open - National 30,000.00 0.00 2023-01-05 2023-01-26 2023-03-11 2023-04-10 2023-05-15 2023-11-11 cation Selection ntation seline Study SWIM-CS-CQS-010 / Preparat ion of design and estimate d ocumentation and architectu ral supervision for the rehabil Water Sector Reform and Ins Consultant Qualifi Pending Impleme IDA / E0790 Post Open - National 110,000.00 0.00 2023-01-04 2023-01-25 2023-03-10 2023-04-09 2023-05-14 2023-11-10 itation of a floating platform, titutional Strengthening cation Selection ntation a chamber gate for DIT and DMK and inspection after co mpletion of emergency work s in the Dangara irrigation tu nnel SWIM-CS-CQS-01 / Feasibilit y study and DEDs for prioritiz Irrigation Scheme Improvem Consultant Qualifi Pending Impleme IDA / E0790 Post Open - National 90,000.00 0.00 2023-01-20 2023-02-10 2023-03-26 2023-04-25 2023-05-30 2023-11-26 ed small and medium invest ents cation Selection ntation ments in Zarafshon and Upp er Vakhsh basins SWIM-CS-CQS-02 / Advisory services for consultation with the population in Rasht, Tajik Irrigation Scheme Improvem Consultant Qualifi Pending Impleme IDA / E0790 Post Open - National 15,000.00 0.00 2023-01-03 2023-01-24 2023-03-09 2023-04-08 2023-05-13 2023-11-09 abad and Lakhsh districts on ents cation Selection ntation eligibility criteria for the sele ction of small-scale irrigation schemes SWIM-CS-CQS-011 / Consulti Water Sector Reform and Ins Consultant Qualifi Open - Internationa Pending Impleme IDA / E0790 Post 100,000.00 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-14 2023-05-19 2023-11-15 ng services for updating the I titutional Strengthening cation Selection l ntation MIS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TRIP-CS-DC-03 / M&E Consul / Project Management Post Direct Selection Direct 8,500.00 6,208.50 Signed 2021-11-16 2021-12-06 2021-11-26 2021-10-18 2022-01-30 2021-11-01 2022-07-29 tant TRIP-CS-DC-04 / Social Devel / Project Management Post Direct Selection Direct 5,000.00 5,843.29 Signed 2021-11-16 2021-12-06 2021-11-26 2021-10-18 2022-01-30 2021-11-01 2022-07-29 opment Consultant TRIP-CS-DC-05 / Environmen / Project Management Post Direct Selection Direct 3,750.00 1,826.03 Signed 2021-11-16 2021-12-06 2021-11-26 2021-10-18 2022-01-30 2021-11-01 2022-07-29 tal Consultant TRIP-CS-IC-01 / Agro econom Individual Consult / Project Management Post Limited 4,875.00 3,956.40 Signed 2021-11-15 2021-12-06 2021-11-20 2021-11-01 2021-12-11 2021-12-01 2022-01-15 2021-12-09 2022-07-14 ist ant Selection TRIP-CS-IC-02 / Electrical En Individual Consult / Project Management Post Limited 4,500.00 4,382.47 Signed 2021-11-15 2021-12-06 2021-11-20 2021-11-01 2021-12-11 2021-11-22 2022-01-15 2021-12-20 2022-07-14 gineer ant Selection TRIP-CS-IC-03 / Rural Area D Individual Consult / Project Management Post Limited 3,125.00 3,652.06 Signed 2021-11-15 2021-12-06 2021-11-20 2021-11-01 2021-12-11 2021-11-22 2022-01-15 2021-12-14 2022-07-14 evelopment Consultant ant Selection TRIP-CS-IC-04 / WUA Support Individual Consult / Project Management Post Limited 4,063.00 3,043.38 Signed 2021-11-15 2021-12-06 2021-11-20 2021-11-01 2021-12-11 2021-12-07 2022-01-15 2021-12-09 2022-07-14 Consultant ant Selection TRIP-CS-IC-05 / Consultant E Individual Consult Under Implement / Project Management Post Open 3,438.00 0.00 2021-11-15 2021-12-06 2022-01-03 2022-01-24 2022-02-28 2022-08-27 ngineer-Designer ant Selection ation TRIP-CS-IC-06 / Consultant E Individual Consult / Project Management Post Open 3,438.00 0.00 Under Review 2021-11-15 2021-12-06 2022-01-03 2022-01-24 2022-02-28 2022-08-27 ngineer-Estimator ant Selection TRIP-CS-IC-07 / Consultant E Individual Consult / Project Management Post Open 3,438.00 0.00 Under Review 2021-11-15 2021-12-06 2022-01-03 2022-01-24 2022-02-28 2022-08-27 ngineer-Topographer ant Selection TRIP-CS-DC-02 / Procuremen / Project Management Post Direct Selection Direct 6,000.00 5,843.29 Signed 2021-11-23 2021-12-09 2021-12-03 2021-10-18 2022-02-06 2021-12-01 2022-08-05 t Consultant TRIP-CS-DC-01 / Project Prep / Project Management Post Direct Selection Direct 7,000.00 5,112.88 Signed 2021-11-23 2021-12-09 2021-12-03 2021-10-18 2022-01-30 2021-11-01 2022-07-29 aration Manager TRIP-CS-IC-08 / Consultant In Individual Consult / Project Management Post Limited 6,125.00 0.00 Canceled 2021-11-15 2021-12-06 2021-11-20 2021-12-11 2022-01-15 2022-07-14 terpreter/Translator ant Selection SWIM-CS-INT-001 / Internati Irrigation Scheme Improvem Individual Consult Open - Internationa onal Consultant to support irr IDA / E0790 Post 70,000.00 0.00 Under Review 2022-11-14 2022-12-01 2023-01-02 2023-01-23 2023-02-27 2023-08-26 ents ant Selection l igation systems design SWIM-CS-IC-01 / Technical A dvisor for IWRM, technical ex Water Sector Reform and Ins Individual Consult Open - Internationa Pending Impleme IDA / E0790 Post 120,000.00 0.00 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2023-11-27 pert on the development of t titutional Strengthening ant Selection l ntation he basin plan and IWRM SWIM-CS-IC-03 / Internationa Water Sector Reform and Ins Individual Consult Open - Internationa Pending Impleme IDA / E0790 Post 60,000.00 0.00 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2023-11-12 l remote sensing consultant titutional Strengthening ant Selection l ntation SWIM-IC-L-02 / Local GIS Con Water Sector Reform and Ins Individual Consult Pending Impleme IDA / E0790 Post Open - National 54,000.00 0.00 2023-01-12 2023-03-02 2023-03-23 2023-04-27 2023-10-24 sultant for IMIS titutional Strengthening ant Selection ntation SWIM-IC-L-03 / IMIS local dat Water Sector Reform and Ins Individual Consult Pending Impleme IDA / E0790 Post Open - National 54,000.00 0.00 2023-01-17 2023-03-07 2023-03-28 2023-05-02 2023-10-29 abase consultant titutional Strengthening ant Selection ntation SWIM-IC-L-04 / Local Irrigatio Water Sector Reform and Ins Individual Consult Pending Impleme IDA / E0790 Post Open - National 36,000.00 0.00 2023-01-18 2023-03-08 2023-03-29 2023-05-03 2023-10-30 n Engineer/IMIS Consultant titutional Strengthening ant Selection ntation SWIM-CS-IC-012 / Impact ev Individual Consult Open - Internationa Pending Impleme IDA / E0790 Project Management Post 20,000.00 0.00 2023-02-01 2023-03-22 2023-04-12 2023-05-17 2023-11-13 aluation survey ant Selection l ntation SWIM-CS-INT-002 / Internati onal Engineer for feasibility s Irrigation Scheme Improvem Individual Consult Open - Internationa tudies and DEDs for target irr IDA / E0790 Post 30,000.00 0.00 Under Review 2022-12-05 2022-12-08 2023-01-23 2023-02-13 2023-03-20 2023-09-16 ents ant Selection l igation schemes in Lower Va khsh Basin - VMC and ShMC Page 3 SWIM-CS-IC-06 / Advisor to A LRI (international) on asset m Water Sector Reform and Ins Individual Consult Open - Internationa Pending Impleme IDA / E0790 Post 84,000.00 0.00 2023-02-20 2023-04-10 2023-05-01 2023-06-05 2023-12-02 anagement, performance mo titutional Strengthening ant Selection l ntation nitoring and capital strategy SWIM-CS-IC-09 / IMIS local d Water Sector Reform and Ins Individual Consult Pending Impleme IDA / E0790 Post Open - National 54,000.00 0.00 2023-03-27 2023-05-15 2023-06-05 2023-07-10 2026-07-14 atabase consultant titutional Strengthening ant Selection ntation SWIM-IC-L-01 / Local coordin ator of the Interagency Worki Water Sector Reform and Ins Individual Consult Pending Impleme ng Group (IWG) on the devel IDA / E0790 Post Open - National 36,000.00 0.00 2023-01-12 2023-03-02 2023-03-23 2023-04-27 2025-04-16 titutional Strengthening ant Selection ntation opment of an irrigation strate gy and overall coordinator of sub-component 1.2 SWIM-CS-IC-011 / ALRI Advis Water Sector Reform and Ins Individual Consult Open - Internationa Pending Impleme or for Irrigation Strategy Dev IDA / E0790 Post 150,000.00 0.00 2025-02-10 2025-03-31 2025-04-21 2025-05-26 2025-11-22 titutional Strengthening ant Selection l ntation elopment and IMIS Page 4