PROCUREMENT PLAN (Textual Part) Project information: Cote d’Ivoire Electricity Transmission and Access Project(P157055) Project Implementation agency: CI-ENERGIES Date of the Procurement Plan: September 7, 2017 Period covered by this Procurement Plan: September 2017- December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing is not applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is not applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Cote d'Ivoire : Cote d'Ivoire - Electricity Transmission and Access Project PLAN General Information Country: Cote d'Ivoire 2017-09-25 Bank’s Approval Date of the Original Procurement Plan: 2022-10-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157055 GPN Date: 2017-08-23 Project Name: Cote d'Ivoire - Electricity Transmission and Access Project Loan / Credit No: IDA / 59990 CI-ENERGIES Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CI-CI-ENERGIES-27208-CW-R FB / Construction du poste so urce 225/90/33/15 kV de Gag noa Rehabilitation, Reinforceme lot 1: Travaux de création du nt, and Extension of Distribu Open - Internationa Single Stage - One E 13,900,000.0 15,774,796. 2019-06-2 IDA / 59990 A priori Appel d'offres Signé 2017-09-05 2017-09-19 2017-10-06 2017-10-31 2018-01-04 2017-11-30 2018-01-19 2018-01-04 2018-02-26 poste source tion Systems in Abidjan and l nvelope 0 66 8 lot 2: Travaux de création de 10 Regional Capital cities l'entrée en coupure des ligne 225 et 90 kV lot 3 : Télétransmission du po ste source CI-CI-ENERGIES-27217-CW-R FB / Construction des postes sources 225/90kV de Yopoug on 1, Treichville et Bia Sud Rehabilitation, Reinforceme lot 1: Poste 225kV incluant 1 nt, and Extension of Distribu Open - Internationa Single Stage - One E 43,000,000.0 38,432,380. 2019-08-0 IDA / 59990 A priori Appel d'offres Signé 2017-09-12 2017-11-08 2017-09-21 2018-02-11 2017-11-02 2018-04-17 2017-12-03 2019-01-24 2018-01-08 2019-01-21 transfo 225/90kV 100MVA tion Systems in Abidjan and l nvelope 0 22 5 lot 2: Poste 225kV incluant 2 10 Regional Capital cities transfo 225/90kV 100MVA lot 3: Poste 225kV incluant 2 travées transfo 225/90kV 10 0MVA CI-CI-ENERGIES-30306-CW-R FB / Extension et renforceme Reinforcement of Transmissi Open - Internationa Single Stage - One E 41,900,000.0 27,326,220. 2019-10-1 IDA / 59990 A priori Appel d'offres Signé 2018-01-16 2018-02-20 2018-02-13 2018-02-21 2018-03-27 2018-04-18 2018-04-26 2019-01-24 2018-05-22 2019-01-23 nt des réseaux de distributio on Systems l nvelope 0 21 6 n dans 10 chefs lieux de régi ons- 3 lots CI-CI-ENERGIES-30308-CW-R FB / Passage en souterrain d e réseaux HTA aériens d'Abid Reinforcement of Transmissi Open - Internationa Single Stage - One E 40,000,000.0 En cours d'e 2020-03-2 IDA / 59990 A priori Appel d'offres 0.00 2018-03-13 2018-12-19 2018-04-10 2019-01-10 2018-05-22 2018-06-21 2018-07-17 jan et remplacement des câb on Systems l nvelope 0 xamen 5 les HTA de type CPI en câble HTA de type CIS dans les DR AS et DRYOP - 3 lots CI-CI-ENERGIES-30313-CW-R Rural Electrification and Sup Open - Internationa Single Stage - One E 15,700,000.0 2019-11-2 FB / Travaux d'électrification IDA / 59990 port to Electricity for All Prog A priori Appel d'offres 0.00 Annulé 2018-03-13 2018-04-10 2018-05-22 2018-06-21 2018-07-17 l nvelope 0 8 de localités dans la région du ram Gbôklè - 5 lots CI-CI-ENERGIES-30315-CW-R Rural Electrification and Sup FB / Travaux d'électrification Open - Internationa Single Stage - One E 19,100,000.0 2019-11-2 IDA / 59990 port to Electricity for All Prog A priori Appel d'offres 0.00 Annulé 2018-03-13 2018-04-10 2018-05-22 2018-06-21 2018-07-17 de localités dans la région du l nvelope 0 6 ram Haut Sassandra - 5 lots CI-CI-ENERGIES-30316-CW-R Rural Electrification and Sup Open - Internationa Single Stage - One E 15,000,000.0 2019-11-2 FB / Travaux d'électrification IDA / 59990 port to Electricity for All Prog A priori Appel d'offres 0.00 Annulé 2018-03-13 2018-04-10 2018-05-22 2018-06-21 2018-07-17 l nvelope 0 6 de localités dans la région de ram la Nawa - 5 lots CI-CI-ENERGIES-30317-CW-R Rural Electrification and Sup FB / Travaux d'électrification Open - Internationa Single Stage - One E 18,600,000.0 2019-11-2 IDA / 59990 port to Electricity for All Prog A priori Appel d'offres 0.00 Annulé 2018-03-13 2018-04-10 2018-05-22 2018-06-21 2018-07-17 de localités dans la région de l nvelope 0 6 ram San Pédro - 5 lots CI-CI-ENERGIES-30548-CW-R FB / Fourniture et Installation de transformateurs à Kossou, Rehabilitation, Reinforceme Ferké, Man, Abobo, Taabo et nt, and Extension of Distribu Open - Internationa Single Stage - One E 55,500,000.0 45,271,581. 2019-11-2 IDA / 59990 A priori Appel d'offres Signé 2018-01-16 2018-03-09 2018-02-12 2018-03-20 2018-03-26 2018-05-29 2018-04-25 2018-07-23 2018-05-22 2018-09-27 Renforcement et Sécurisatio tion Systems in Abidjan and l nvelope 0 91 6 n des postes de Agboville, At 10 Regional Capital cities takro, Ayamé, Bongo, Bouak é 1, Abengourou, Dabou, Dal oa, Danané et Dimbokro Gag noa - 4 lots CI-CI-ENERGIES-95225-CW-R Rural Electrification and Sup FB / Travaux d'électrification Open - Internationa Single Stage - One E 15,700,000.0 2020-11-1 IDA / 59990 port to Electricity for All Prog A priori Appel d'offres 0.00 Annulé 2019-04-24 2019-05-21 2019-07-10 2019-07-26 2019-08-23 rurale des localités dans la ré l nvelope 0 5 ram gion du Gboklê - 5 Lots CI-CI-ENERGIES-95232-CW-R Rural Electrification and Sup FB / Travaux d'électrification Open - Internationa Single Stage - One E 18,600,000.0 2020-10-1 IDA / 59990 port to Electricity for All Prog A priori Appel d'offres 0.00 Annulé 2019-03-26 2019-04-23 2019-06-12 2019-06-28 2019-07-26 des localités dans la région d l nvelope 0 8 ram e San Pédro- 5 lots CI-CI-ENERGIES-95234-CW-R Rural Electrification and Sup FB / Travaux d'électrification Open - Internationa Single Stage - One E 19,100,000.0 13,630,277. 2020-10-1 IDA / 59990 port to Electricity for All Prog A priori Appel d'offres Signé 2019-03-26 2019-03-31 2019-04-23 2019-04-04 2019-06-12 2019-05-21 2019-06-28 2019-11-12 2019-07-26 2020-01-09 des localités dans la région d l nvelope 0 91 8 ram u Haut- Sassandra- 5 lots CI-CI-ENERGIES-95236-CW-R Rural Electrification and Sup FB / Travaux d'électrification Open - Internationa Single Stage - One E 15,000,000.0 11,691,486. 2020-08-1 IDA / 59990 port to Electricity for All Prog A priori Appel d'offres Signé 2019-01-23 2019-01-29 2019-02-19 2019-02-04 2019-04-10 2019-03-26 2019-04-26 2019-06-06 2019-05-24 2019-08-27 des localités dans la région d l nvelope 0 30 6 ram e la Nawa- 5 lots CI-CI-ENERGIES-168080-CW- RFQ / Electrification des local ités de Bolorouko, Diomandé Rural Electrification and Sup carrefour, Leledou, Louloudo Single Stage - One E 2021-09-0 IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 3,900,000.00 0.00 Annulé 2020-04-15 2020-04-17 2020-06-10 u, Zuzuoko, Zakareko et Yak nvelope 3 ram assé, Dassioko et Kpata Abid ou, Gbabililié/Kroukrou(Yober i), Grogbaledou, Mahamankr o, Wawakro, Wawapéko,Zakp beri et Zériberi CI-CI-ENERGIES-168081-CW- RFQ / Electrification des local Rural Electrification and Sup Single Stage - One E 2021-07-0 ités de Gnago I et Gnago II, T IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 3,600,000.00 0.00 Annulé 2020-04-15 2020-04-17 2020-06-10 nvelope 5 ripoko, Gnégrouboué, Gobrok ram o, Bolo V1, Bolo V2, Bolo V3, Boutoubré I et Zégréboué Page 1 CI-CI-ENERGIES-168083-CW- RFQ / Construction des lignes Rural Electrification and Sup MT/BT Gaoulou-Grihiri et Bey Single Stage - One E 2021-09-0 IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 4,100,000.00 0.00 Annulé 2020-04-15 2020-06-10 o-PK 31 et électrification des nvelope 3 ram localités de Grihiri, Godekro, Tiazalé, Vodieko, Lohiri (Godi è) et Madinatché CI-CI-ENERGIES-168085-CW- Rural Electrification and Sup RFQ / Electrification des local Single Stage - One E 2021-06-0 IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 2,100,000.00 0.00 Annulé 2020-04-15 2020-04-17 2020-06-10 ités de Balokouya, Gréguibré nvelope 5 ram I, Lobakuya, Medon et Zaebr é CI-CI-ENERGIES-168086-CW- Rural Electrification and Sup RFQ / Electrification des local Single Stage - One E 2021-09-0 IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 2,000,000.00 0.00 Annulé 2020-04-15 2020-04-17 2020-06-10 ités de Labakuya, Lossan Kou nvelope 3 ram amekro, Pauly brousse, Saho ua et Sialloukro CI-CI-ENERGIES-168087-CW- RFQ / Electrification des local Rural Electrification and Sup ité de Djimimbo, Gliké-Est, Ir Single Stage - One E 2021-06-2 IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 3,700,000.00 0.00 Annulé 2020-05-06 2020-07-01 atéké, Trahé, Mani Béréby, I nvelope 6 ram boké, Grélé, Néro-Brousse, o uro, Pataké, Grélelon et Roc douGbalél/Roc Oulidié/ SUF CI-CI-ENERGIES-168088-CW- RFQ / Electrification des local Rural Electrification and Sup Single Stage - One E 2021-06-2 ités de Baba, Dimoulé, Tabok IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 4,700,000.00 0.00 Annulé 2020-05-06 2020-07-01 nvelope 6 é, Waté, Dagadji, Djapadji, G ram agny, Gnepasso, Dahoro, Gli gbeuadji et Goh CI-CI-ENERGIES-168089-CW- RFQ / Electrification des local Rural Electrification and Sup ités de Blahou, Kpoté, petit P Single Stage - One E 2021-09-2 IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 3,700,000.00 0.00 Annulé 2020-05-06 2020-07-01 edro, Kounouko, Ligne Gabia nvelope 4 ram dji-san Pédro, Monogaga, Blo ho, Gnity cailloux, Gnaké, To uih et Touré Dougou/SUF CI-CI-ENERGIES-168090-CW- RFQ / Electrification des local ités de Soumahorodougou, C Rural Electrification and Sup Single Stage - One E 2021-06-2 antondougou, Pont Bascule, IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 4,300,000.00 0.00 Annulé 2020-05-06 2020-07-01 nvelope 6 Béoué, Karie, Nekawuinho (N ram eka village), Petit Grabo, Pou tou, Youkou, Néro village, pet it Guiglo, Podoué et Soto CI-CI-ENERGIES-168091-CW- RFQ / Electrification des local Rural Electrification and Sup ités de Blidouba, Dapo Iboké, Single Stage - One E 2021-06-2 IDA / 59990 port to Electricity for All Prog A posteriori Demande de prix Limited 2,200,000.00 0.00 Annulé 2020-05-06 2020-07-01 Dégné, Déhé, Georges-Town, nvelope 6 ram Gnénaholoké, Néro V1 et Ner o V2, Niplou et tépo Iboké/ S UF CI-CI-ENERGIES-178152-CW- RFB / Electrification des locali tés de Bolorouko, Diomandé Rural Electrification and Sup carrefour, Leledou, Louloudo Single Stage - One E 2,910,065.8 2021-10-2 IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 3,900,000.00 Signé 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-07-17 2020-08-13 2020-08-27 2020-08-27 2020-11-03 u, Zuzuoko, Zakareko et Yak nvelope 6 1 ram assé, Dassioko et Kpata Abid ou, Gbabililié/Kroukrou(Yober i), Grogbaledou, Mahamankr o, Wawakro, Wawapéko,Zakp beri et Zériberi CI-CI-ENERGIES-178153-CW- RFB / Electrification des locali Rural Electrification and Sup Single Stage - One E 2,743,732.9 2021-08-2 tés de Gnago I et Gnago II, Tr IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 3,600,000.00 Signé 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-07-17 2020-08-13 2020-08-27 2020-08-27 2020-11-03 nvelope 1 2 ipoko, Gnégrouboué, Gobrok ram o, Bolo V1, Bolo V2, Bolo V3, Boutoubré I et Zégréboué CI-CI-ENERGIES-178156-CW- RFB / Construction des lignes Rural Electrification and Sup MT/BT Gaoulou-Grihiri et Bey Single Stage - One E 2,915,531.2 2021-10-2 IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 4,100,000.00 Signé 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-07-17 2020-08-13 2020-08-27 2020-08-27 2020-11-03 o-PK 31 et électrification des nvelope 9 1 ram localités de Grihiri, Godekro, Tiazalé, Vodieko, Lohiri (Godi è) et Madinatché CI-CI-ENERGIES-178157-CW- Rural Electrification and Sup RFB / Electrification des locali Single Stage - One E 1,466,529.3 2021-08-2 IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 2,100,000.00 Résilié 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-07-17 2020-08-13 2020-08-27 2020-08-27 2020-11-03 tés de Balokouya, Gréguibré nvelope 4 2 ram I, Lobakuya, Medon et Zaebr é CI-CI-ENERGIES-178159-CW- Rural Electrification and Sup RFB / Electrification des locali Single Stage - One E 1,532,244.1 2021-08-2 IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 2,000,000.00 Résilié 2020-06-16 2020-06-16 2020-06-23 2020-06-24 2020-07-23 2020-08-27 2020-08-13 2020-08-27 2020-08-27 2020-11-03 tés de Labakuya, Lossan Kou nvelope 6 2 ram amekro, Pauly brousse, Saho ua et Sialloukro CI-CI-ENERGIES-178161-CW- RFB / Electrification des locali Rural Electrification and Sup té de Djimimbo, Gliké-Est, Ira Single Stage - One E 257,870,66 2021-10-2 IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 3,700,000.00 Résilié 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-03 2020-09-03 2021-03-04 téké, Trahé, Mani Béréby, Ib nvelope 3.61 8 ram oké, Grélé, Néro-Brousse, our o, Pataké, Grélelon et Roc do uGbalél/Roc Oulidié/ SUF CI-CI-ENERGIES-178164-CW- RFB / Electrification des locali Rural Electrification and Sup Single Stage - One E 2,930,439.7 2021-08-2 tés de Baba, Dimoulé, Tabok IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 4,700,000.00 Signé 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-03 2020-09-03 2021-03-16 nvelope 0 9 é, Waté, Dagadji, Djapadji, G ram agny, Gnepasso, Dahoro, Gli gbeuadji et Goh CI-CI-ENERGIES-178165-CW- RFB / Electrification des locali Rural Electrification and Sup tés de Blahou, Kpoté, petit P Single Stage - One E 2,417,694.6 2021-10-2 IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 3,700,000.00 Signé 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-03 2020-09-03 2021-03-09 edro, Kounouko, Ligne Gabia nvelope 9 8 ram dji-san Pédro, Monogaga, Blo ho, Gnity cailloux, Gnaké, To uih et Touré Dougou/SUF CI-CI-ENERGIES-178166-CW- RFB / Electrification des locali tés de Soumahorodougou, Ca Rural Electrification and Sup Single Stage - One E 1,626,547.9 2021-08-2 ntondougou, Pont Bascule, B IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 4,300,000.00 Signé 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-14 2020-09-03 2021-03-16 nvelope 5 9 éoué, Karie, Nekawuinho (Ne ram ka village), Petit Grabo, Pout ou, Youkou, Néro village, peti t Guiglo, Podoué et Soto Page 2 CI-CI-ENERGIES-178168-CW- RFB / Electrification des locali Rural Electrification and Sup tés de Blidouba, Dapo Iboké, Single Stage - One E 1,251,188.0 2021-08-2 IDA / 59990 port to Electricity for All Prog A posteriori Appel d'offres Open - National 2,200,000.00 Signé 2020-06-23 2020-06-30 2020-06-30 2020-07-09 2020-07-30 2020-08-18 2020-08-20 2020-12-14 2020-09-03 2021-02-26 Dégné, Déhé, Georges-Town, nvelope 0 9 ram Gnénaholoké, Néro V1 et Ner o V2, Niplou et tépo Iboké/ S UF CI-CI-ENERGIES-189370-CW- DIR / Passage en 225 kV du p Rural Electrification and Sup Passation de marc 1,720,403.5 2021-07-2 oste de Bia Sud: Collecte et t IDA / 59990 port to Electricity for All Prog A priori Direct 1,700,000.00 Signé 2020-08-24 2020-09-09 2020-08-31 2020-09-25 2020-09-26 2020-10-21 hé de gré à gré 5 3 ransfert des terres et eaux p ram olluées aux micropolluants CI-CI-ENERGIES-245517-CW- DIR / Travaux d'électrification rurale des localité de Niani, D National Procure abeda, Gapé, Tano Kouadiokr Rural Electrification and Sup ment Document - Passation de marc 2,906,925.5 2022-06-2 o, Cocoplage, Tate ville, Libre IDA / 59990 port to Electricity for All Prog A posteriori Direct 1 Envelope proce 2,704,126.00 Signé 2021-07-28 2021-05-06 2021-08-02 2021-05-06 2021-08-24 2021-08-05 hé de gré à gré 5 0 ville, Bahbli, Nado, Bassawoa ram ss (Non Bank-SPD , Missehi2, Niani Carrefour, A ) kakro, Sanogola, Djoroplo, Mi ssehi, Assagouyo, Okrouyo, Dakpadou et Sago/ Gboklê GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CI-ENERGIES-30322-GO-R Strengthening Institutional C Single Stage - One E FQ / Acquisition et entretien IDA / 59990 apacity of the Electricity Sec A posteriori Demande de prix Limited 862,000.00 724,363.68 Achevé 2017-09-27 2017-09-25 2017-11-03 2017-10-30 2017-12-20 2017-12-23 nvelope de véhicules tor and Project Management CI-CI-ENERGIES-30325-GO-R Strengthening Institutional C FQ / Acquisition de Camion L Single Stage - One E IDA / 59990 apacity of the Electricity Sec A posteriori Demande de prix Limited 400,000.00 0.00 Annulé 2018-01-10 2018-02-22 2018-04-10 abo y compris formation et pi nvelope tor and Project Management èces de réchanges CI-CI-ENERGIES-95231-GO-R FB / Passage en souterrain d Reinforcement of Transmissi Open - Internationa Single Stage - One E e réseaux HTA aériens et re IDA / 59990 A priori Appel d'offres 40,000,000.00 44,302,794.00 Signé 2019-01-17 2019-01-17 2019-02-26 2019-02-26 2019-03-14 2019-03-19 2019-04-18 2019-04-19 2020-12-08 on Systems l nvelope mplacement des câbles HTA de type CPI en CIS dans la vil le d'Abidjan - 3 lots CI-CI-ENERGIES-95240-GO-R Strengthening Institutional C FQ / Acquisition du camion la Single Stage - One E IDA / 59990 apacity of the Electricity Sec A posteriori Demande de prix Limited 400,000.00 0.00 Annulé 2019-01-29 2019-02-11 2019-03-13 2019-07-11 bo y compris formation et piè nvelope tor and Project Management ce de réchange CI-CI-ENERGIES-95242-GO-R Strengthening Institutional C Single Stage - One E FQ / Acquisition d'instrument IDA / 59990 apacity of the Electricity Sec A posteriori Demande de prix Limited 300.00 0.00 Annulé 2019-01-28 2019-03-07 2019-04-22 nvelope s de mesures et de controle- tor and Project Management 2 Lots CI-CI-ENERGIES-95244-GO-R Strengthening Institutional C FQ / Acquisition de materiel i Single Stage - One E IDA / 59990 apacity of the Electricity Sec A posteriori Demande de prix Limited 8,500.00 0.00 Annulé 2019-01-22 2019-02-14 2019-03-01 nformatique, de bureau et co nvelope tor and Project Management nsommables informatiques CI-CI-ENERGIES-146023-GO- Strengthening Institutional C Passation de marc DIR / FOURNITURES DE DEUX IDA / 59990 apacity of the Electricity Sec A posteriori Direct 601,000.00 585,667.64 Signé 2019-11-25 2019-06-24 2019-11-30 2019-06-24 2020-01-04 2019-12-04 2020-08-31 2020-08-13 hé de gré à gré CAMIONS LABORATOIRE tor and Project Management Rehabilitation, Reinforceme CI-CI-ENERGIES-239558-GO- nt, and Extension of Distribu Open - Internationa Single Stage - One E RFB / Acquisition de trente-tr IDA / 59990 A priori Appel d'offres 26,135,000.00 29,271,012.28 Signé 2021-06-17 2021-07-12 2021-06-27 2021-07-29 2021-08-10 2021-09-29 2021-08-31 2022-02-01 2021-10-05 2022-04-14 2022-08-01 tion Systems in Abidjan and l nvelope ois (33) transformateurs 10 Regional Capital cities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CI-ENERGIES-22356-CS-Q CBS / Ingénieurs-Conseils po ur le contrôle et la surveillan Strengthening Institutional C Sélection fondée s Open - Internationa ce des travaux de transport, IDA / 59990 apacity of the Electricity Sec A priori ur la qualité et le 8,300,000.00 0.00 Annulé 2017-09-05 2017-09-12 2017-09-28 2017-10-09 2018-02-11 2017-11-21 2018-02-27 2017-12-12 2018-03-19 2017-12-21 2018-01-25 2019-08-31 l distribution et électrification tor and Project Management coût rurale - Lot 1: Transport- Dist ribution et Lot 2: Électrificati on rurale CI-CI-ENERGIES-222501-CS- QCBS / Ingenieurs-Conseils p our le contrôle et la surveilla Strengthening Institutional C Sélection fondée s Open - Internationa En cours d'exame nce des travaux de transport IDA / 59990 apacity of the Electricity Sec A priori ur la qualité et le 4,700,000.00 0.00 2021-03-03 2021-03-08 2021-03-17 2021-03-09 2021-04-30 2021-05-28 2021-06-27 2021-08-01 2021-09-05 2023-02-27 l n , distribution et électrification tor and Project Management coût rurale: Contrôle et surveillan ce des travaux de Transport et de Distribution CI-CI-ENERGIES-220229-CS- QCBS / Ingenieurs-Conseils p our le contrôle et la surveilla Strengthening Institutional C Sélection fondée s Open - Internationa nce des travaux de transport IDA / 59990 apacity of the Electricity Sec A priori ur la qualité et le 4,700,000.00 0.00 Annulé 2021-02-17 2021-02-24 2021-03-03 2021-04-16 2021-05-14 2021-06-13 2021-07-18 2021-08-22 2023-04-14 l , distribution et électrification tor and Project Management coût rurale: Contrôle et surveillan ce des travaux de Transport et de Distribution CI-CI-ENERGIES-220225-CS- QCBS / Ingenieurs-Conseils p our le contrôle et la surveilla Strengthening Institutional C Sélection fondée s Open - Internationa nce des travaux de transport IDA / 59990 apacity of the Electricity Sec A priori ur la qualité et le 3,600,000.00 0.00 Annulé 2021-02-17 2021-02-24 2021-03-03 2021-04-16 2021-05-14 2021-06-13 2021-07-18 2021-08-22 2022-08-22 l , distribution et électrification tor and Project Management coût rurale- Contrôle te surveillan ce des travaux d'Electrificati on Rurale Page 3 CI-CI-ENERGIES-226512-CS- QCBS / Ingenieurs-Conseils p our le contrôle et la surveilla Strengthening Institutional C Sélection fondée s Open - Internationa nce des travaux de transport IDA / 59990 apacity of the Electricity Sec A priori ur la qualité et le 4,700,000.00 11,268,903.84 Signé 2017-09-05 2021-03-31 2017-09-26 2017-11-09 2017-12-07 2018-03-27 2018-01-06 2021-03-31 2018-02-10 2021-03-31 2018-03-17 2018-08-23 2019-03-17 l , distribution et électrification tor and Project Management coût rurale- Contrôle et surveillan ce des travaux de Transport et de Distribution CI-CI-ENERGIES-226514-CS- QCBS / Ingenieurs-Conseils p our le contrôle et la surveilla Strengthening Institutional C Sélection fondée s Open - Internationa nce des travaux de transport IDA / 59990 apacity of the Electricity Sec A posteriori ur la qualité et le 3,600,000.00 3,003,233.06 Signé 2017-09-05 2017-08-21 2017-09-26 2017-11-09 2018-01-23 2017-12-07 2018-02-27 2018-01-06 2018-03-12 2018-02-10 2018-06-18 2018-03-17 2018-07-31 2019-03-17 l , distribution et électrification tor and Project Management coût rurale- Contrôle te surveillan ce des travaux d'Electrificati on Rurale CI-CI-ENERGIES-222502-CS- QCBS / Ingenieurs-Conseils p our le contrôle et la surveilla Strengthening Institutional C Sélection fondée s Open - Internationa nce des travaux de transport IDA / 59990 apacity of the Electricity Sec A posteriori ur la qualité et le 3,600,000.00 0.00 Annulé 2021-03-03 2021-03-08 2021-03-17 2021-04-30 2021-05-28 2021-06-27 2021-08-01 2021-09-05 2023-04-28 l , distribution et électrification tor and Project Management coût rurale: Contrôle te surveillan ce des travaux d'Electrificati on Rurale INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-CI-ENERGIES-95249-CS-C Strengthening Institutional C Sélection de cons DS / Audit comptable et finan IDA / 59990 apacity of the Electricity Sec A priori ultants par entent Direct 93,000.00 99,106.06 Signé 2019-01-23 2019-01-28 2018-10-08 2019-02-11 2019-05-13 2019-03-01 cier du projet tor and Project Management e directe CI-CI-ENERGIES-95251-CS-IN Strengthening Institutional C DV / Consultant individuel co IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Limited 10,500.00 10,144.86 Signé 2019-01-21 2019-02-05 2019-01-26 2019-02-08 2019-02-06 2019-04-03 2019-02-15 2019-04-03 2019-02-15 urt-terme en appui au spécial tor and Project Management iste genre et développement social. CI-CI-ENERGIES-146017-CS-I Strengthening Institutional C NDV / Recrutement d'un Con IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Limited 75,000.00 112,900.00 Achevé 2019-11-20 2019-11-28 2019-11-25 2019-11-29 2019-12-16 2020-01-09 2020-01-20 2020-01-30 2021-01-19 2020-09-30 sultant International en Appu tor and Project Management i à la Mise en Œuvre des Sau vegardes CI-CI-ENERGIES-157500-CS-I Strengthening Institutional C NDV / Recrutement d'un assi IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Limited 50,000.00 1,520.45 Signé 2020-02-06 2020-01-28 2020-02-20 2020-03-19 2020-02-27 2020-04-29 2020-03-08 2020-05-14 2020-07-06 stant en passation de march tor and Project Management és CI-CI-ENERGIES-174199-CS- CDS / Recrutement d'une fir me (Hydrogen) en vue de la r Strengthening Institutional C Sélection de cons éalisation du CIES du Projet d IDA / 59990 apacity of the Electricity Sec A posteriori ultants par entent Direct 55,000.00 48,057.22 Achevé 2020-05-22 2020-06-16 2020-06-01 2020-06-16 2020-06-15 2020-07-06 2020-07-15 2020-12-06 e fourniture, d’installation, d tor and Project Management e directe e systèmes de stockage d'én ergie par batteries 300 MWh & des équipements de synch ronisation CI-CI-ENERGIES-207215-CS-I NDV / Consultant Internation al en appui technique à la mi Strengthening Institutional C se en œuvre des sauvegarde IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Direct 108,950.00 108,950.00 Signé 2020-11-30 2020-11-17 2020-12-04 2020-11-17 2020-12-09 2020-11-30 2020-12-19 2020-12-17 2021-12-14 s environnementales et socia tor and Project Management les, santé et sécurité au trav ail, gestion des plaintes et as pects genre et vulnérabilité d ans le cadre du projet CI-CI-ENERGIES-207228-CS-I NDV / Recrutement d'un(e) c Strengthening Institutional C En attente d'exéc onsultant(e) pour l'élaboratio IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Direct 52,000.00 0.00 2020-12-02 2020-12-14 2020-12-28 2021-01-11 2021-02-10 ution n du CIES du projet de constr tor and Project Management uction et de restructuration d u réseau HTA de Gagnoa CI-CI-ENERGIES-207241-CS-I Strengthening Institutional C NDV / Recrutement d'un(e) s IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Limited 86,200.00 3,605.88 Signé 2020-11-30 2020-06-12 2020-12-05 2020-06-18 2020-12-26 2020-11-18 2021-01-30 2020-11-26 2022-12-31 pécialiste en Développement tor and Project Management Social et Genre CI-CI-ENERGIES-207252-CS-I Strengthening Institutional C NDV / Recrutement d'un(e) s IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Limited 86,200.00 3,577.22 Signé 2020-11-30 2020-07-03 2020-12-05 2020-06-18 2020-12-26 2020-12-08 2021-01-30 2020-12-08 2022-12-31 pécialiste en sauvegarde env tor and Project Management ironnemental CI-CI-ENERGIES-215321-CS- CDS / Contrat avec EDF CI po Sélection de cons ur le contrôle, la supervision Reinforcement of Transmissi IDA / 59990 A priori ultants par entent Direct 3,300,000.00 0.00 Annulé 2021-01-25 2021-01-29 2021-03-01 2022-06-24 , la surveillance et le suivi e on Systems e directe nvironnemental et social des ouvrages de Transport et Dis tribution du PTDAE CI-CI-ENERGIES-207236-CS-I NDV / Recrutement d'un(e) c Strengthening Institutional C onsultant(e) pour l'actualisati IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Direct 34,500.00 0.00 Annulé 2020-12-03 2020-12-15 2021-01-05 2021-01-19 2021-02-18 on du PAR de la DRAS dans l tor and Project Management e cadre du passage en soute rrain de câbles CI-CI-ENERGIES-207232-CS-I NDV / Recrutement d'un(e) c Strengthening Institutional C onsultant(e) pour l'élaboratio IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Direct 43,000.00 0.00 Annulé 2020-12-03 2020-12-15 2021-01-05 2021-01-19 2021-02-18 n du PAR du projet de constr tor and Project Management uction et de restructuration d u réseau HTA de Gagnoa CI-CI-ENERGIES-207238-CS-I NDV / Recrutement d'un(e) c Strengthening Institutional C onsultant(e) pour l'actualisati IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Direct 43,000.00 0.00 Annulé 2020-12-03 2020-12-15 2021-01-05 2021-01-19 2021-02-18 on du CIES de la DRAS dans l tor and Project Management e cadre du passage en soute rrain de câbles CI-CI-ENERGIES-157499-CS-I NDV / RECRUTEMENT D’UN(E ) CONSULTANT(E) INDIVIDUE L(LE) CHARGE(E) DE L’ELABO Strengthening Institutional C RATION DU PLAN D’ACTION D IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Limited 44,000.00 0.00 Annulé 2020-02-06 2020-01-02 2020-02-11 2020-03-03 2020-04-07 2021-04-07 E REINSTALLATION (PAR) PER tor and Project Management SONNES AFFECTEES PAR LES TRAVAUX DE CONNEXION DU NOUVEAU POSTE DE GAGNO A AU CHEF-LIEU DE REGION DU GOH Page 4 CI-CI-ENERGIES-268120-CS- Strengthening Institutional C Sélection de cons CDS / Audit environnemental IDA / 59990 apacity of the Electricity Sec A posteriori ultants par entent Direct 124,000.00 120,225.97 Signé 2022-01-20 2021-12-10 2022-02-03 2021-12-23 2022-02-17 2022-02-08 2022-04-18 et social PTDAE tor and Project Management e directe CI-CI-ENERGIES-276101-CS- Strengthening Institutional C Sélection de cons CDS / Audit comptable et fina IDA / 59990 apacity of the Electricity Sec A posteriori ultants par entent Direct 53,800.00 51,373.56 Signé 2022-02-01 2022-01-12 2022-02-11 2022-02-01 2022-02-25 2022-02-23 2022-03-21 ncier du PTDAE exercices 20 tor and Project Management e directe 21-2022 CI-CI-ENERGIES-289267-CS-I NDV / Recrutement d’un Con sultant individuel internation al en appui technique dans la Strengthening Institutional C En cours d'exécut mise en œuvre des mesures IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Direct 166,350.00 0.00 2022-04-11 2022-02-16 2022-04-15 2022-04-20 2022-04-30 2022-11-16 ion de Sauvegardes Environnem tor and Project Management entales et Sociales, Santé et Sécurité au Travail, Gestion d es Plaintes et Aspects Gente et Vulnérabilité dans le c CI-CI-ENERGIES-289243-CS- CDS / Recrutement d'un cabi Strengthening Institutional C Sélection de cons net pour l'actualisation du CI IDA / 59990 apacity of the Electricity Sec A posteriori ultants par entent Direct 127,000.00 0.00 Annulé 2022-04-11 2022-02-18 2022-04-20 2022-05-09 2022-06-13 ES du passage en souterrain tor and Project Management e directe du réseau HTA aérien et rem placement des câbles HTA C PI par des CIS à la DR Abidja n Sud CI-CI-ENERGIES-289258-CS- CDS / Recrutement d'un cabi net pour l'actualisation du PA Strengthening Institutional C Sélection de cons R des personnes affectées po IDA / 59990 apacity of the Electricity Sec A posteriori ultants par entent Direct 109,000.00 96,935.53 Signé 2022-04-11 2022-02-18 2022-04-20 2022-02-18 2022-05-09 2022-07-05 2022-06-13 ur le passage en souterrain d tor and Project Management e directe u réseau HTA aérien et de re mplacement des câbles HTA CPI par CIS dans la DR abidja n SUD CI-CI-ENERGIES-319419-CS-I Strengthening Institutional C NDV / Recrutement d'un spéc En attente d'exéc IDA / 59990 apacity of the Electricity Sec A posteriori Individuel Open - National 40,000.00 0.00 2022-10-07 2022-11-05 2022-11-10 2022-12-06 2023-12-01 ialiste en passation de march ution tor and Project Management é en remplacement du titulai re démissionnaire Page 5