Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: February 24, 2017 2. Date of General Procurement Notice: To Be Published 3. Period covered by this procurement plan: August 2017 to February 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (>=US million) Works (including turnkey, supply and 5 installation of plant and equipment, and Public Private Partnership (PPP) Goods, information technology and 1.5 non-consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual Issued by the Ministry of Water, Irrigation and Electricity, August 2017. 5. Any Other Special Procurement Arrangements: Not Applicable. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 July 9, 2010 Ref. Descripti Estimated Packag Domestic Review Com No. on Cost es Preference by Bank men US$ (yes/no) (Prior / ts million Post) 1 Summary 32 2 To be Prior of the ICB Determine (Works) d 2 Summary 10.2 6 To be Prior of the ICB Determine (Goods) d 3 Summary 19.4 5 No Post of the NCB (Works) 4 Summary 0.28 1 No Post of the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Type of Procurement Prior Review Threshold (>=US million) Consultants: firms 0.5 Consultants: Individuals 0.2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimat Package Review Comment No. Assignment ed s by Bank s Cost (Prior / US$ Post) million 1 Summary of 3.5 3 Prior number of July 9, 2010 contracts that will be let under QCBS 2 Summary of 11.8 14 Post number of contracts that will be let under QCBS 3 Summary of 10.1 31 Post CQS/IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Ethiopia Urban Water Supply and Sanitation Project PLAN General Information Country: Ethiopia 2018-01-15 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2023-03-16 if none) Project ID: P156433 GPN Date: 2018-02-02 Project Name: Second Ethiopia Urban Water Supply and Sanitation Project Loan / Credit No: IDA / 60070, IDA / 60080 Ministry of Water Irrigation and Electricity, WSS Program Management Unit Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount ( t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) US$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-MOWIE-77733-CW-DIR / Component 2: Sanitation an Pending Im 2018-11-2 2018-12-0 2019-01-0 2019-05- Pipe laying for Dire Dewa to IDA / 60070 d water supply services imp Post Direct Selection Direct 458,379.00 0.00 plementati 8 3 7 07 wn water supply project by rovement in secondary citie on Dire Dewa town s ET-MOWIE-143512-CW-RFB Component 2: Sanitation an Pending Im / Construction of public and d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- IDA / 60070 Post Request for Bids Open - National 0.00 plementati communal toilet for Asosa to rovement in secondary citie Envelope 0 0 5 5 4 8 26 on wn by Asosa Water Supply a s nd Sewerage Authority ET-MOWIE-143682-CW-RFB Component 2: Sanitation an Pending Im / Construction of public an d water supply services imp Single Stage - One 1,626,000.0 2019-11-2 2019-12-0 2020-01-0 2020-01-3 2020-03-0 2021-05- IDA / 60070 Post Request for Bids Open - National 0.00 plementati d communal latrines for Ba rovement in secondary citie Envelope 0 7 2 1 1 6 30 on hirdar town by Bahirdar to s wn Water Supply Project ET-MOWIE-143697-CW-RFB Component 2: Sanitation an / Construction of public an Pending Im d water supply services imp Single Stage - One 1,002,000.0 2019-11-2 2019-12-0 2020-01-0 2020-02-0 2020-03-0 2021-05- d communal latrines for Ad IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 8 3 2 1 7 31 ama Town By Adama Town on s Waste Water Management P roject ET-MOWIE-143699-CW-RFB Component 2: Sanitation an / Construction of public an Pending Im d water supply services imp Single Stage - One 1,192,000.0 2019-11-2 2019-12-0 2020-01-0 2020-02-0 2020-03-0 2021-05- d communal latrines for Dir IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 8 3 2 1 7 31 edewa Town by Diredewa T on s own Water Supply and Sewe rage Enterprise ET-MOWIE-143704-CW-RFB Component 2: Sanitation an / Construction of public an Pending Im d water supply services imp Single Stage - One 1,436,000.0 2019-11-2 2019-12-0 2020-01-0 2020-02-0 2020-03-0 2021-05- d communal latrines for Ha IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 8 3 2 1 7 31 wasa Town by Hawasa Tow on s n Water supply and sewerag e service ET-MOWIE-143535-CW-RFB Component 2: Sanitation an Pending Im / Construction of public and d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- IDA / 60070 Post Request for Bids Open - National 0.00 plementati communal toilet for Dessie t rovement in secondary citie Envelope 0 0 5 5 4 8 26 on own by Water Supply and Se s werage Authority ET-MOWIE-143530-CW-RFB Component 2: Sanitation an / Construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- communal toilet for Deghab IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 4 8 26 ur town by Deghabur Water on s Supply and Sewerage Enterp rise ET-MOWIE-143532-CW-RFB Component 2: Sanitation an Pending Im / Construction of public and d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-12-0 2020-01-0 2020-02-0 2020-03-0 2020-09- IDA / 60070 Post Request for Bids Open - National 0.00 plementati communal toilet for Sodo to rovement in secondary citie Envelope 0 8 3 2 1 7 03 on wn by Sodo Water Supply a s nd Sewerage Authority ET-MOWIE-142793-CW-RFB Component 2: Sanitation an / Construction of FSM (fecal d water supply services imp Open - Internation Single Stage - One 8,610,620.7 2019-12-2 2019-12-3 2020-02-1 2020-03-1 2020-04-1 2021-11- sludge management) for Ba IDA / 60070 Post Request for Bids 0.00 Canceled rovement in secondary citie al Envelope 8 5 0 0 1 5 06 hirdar and Hawasa Towns by s water development commiss ion ET-MOWIE-143521-CW-RFB Component 2: Sanitation an / Construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- communal toilet for Semera IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 4 8 26 towns by Semera Water Sup on s ply and Sewerage Authority ET-MOWIE-143537-CW-RFB Component 2: Sanitation an / Construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-12-0 2020-01-0 2020-02-0 2020-03-0 2020-09- communal toilet for Debrebir IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 8 3 2 1 7 03 han town by Debrebirhan W on s ater Supply and Sewerage A uthority ET-MOWIE-143510-CW-RFB Component 2: Sanitation an / Construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- communal toilet for Asella T IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 4 8 26 own by Asella Water Supply on s and Sewerage Enterprise ET-MOWIE-143522-CW-RFB Component 2: Sanitation an / Construction of public and d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2020-02-1 2019-11-2 2019-12-2 2020-04-2 2020-01-2 2020-05-1 2020-02-2 2020-06-3 2020-08- IDA / 60070 Post Request for Bids Open - National 490,071.10 Signed communal toilet for Adigrat rovement in secondary citie Envelope 0 0 3 5 5 8 4 2 8 0 26 towns by Adigrat Water Sup s ply and Sewerage service ET-MOWIE-143528-CW-RFB Component 2: Sanitation an Pending Im / Construction of public and d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- IDA / 60070 Post Request for Bids Open - National 0.00 plementati communal toilet for Jigjiga to rovement in secondary citie Envelope 0 0 5 5 4 8 26 on wn by Jigjiga Water Supply s and Sewerage Enterprise ET-MOWIE-143501-CW-RFB Component 2: Sanitation an / construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-12-0 2020-01-1 2020-02-1 2020-03-1 2020-09- communal toilet for Bishoftu IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 8 3 4 3 9 15 town by Bishoftu Water S on s upply and Sewerage Authori ty ET-MOWIE-143272-CW-RFB Component 2: Sanitation an / construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- communal toilet for Nekem IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 4 8 26 te Town By Nekemte Water on s supply and Sewerage Enterp rise . ET-MOWIE-143519-CW-RFB Component 2: Sanitation an / Construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-12-0 2020-01-0 2020-02-0 2020-03-0 2020-09- communal toilet for Gambell IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 8 3 2 1 7 03 a towns by Gambella Water on s Supply and Sewerage Author ity ET-MOWIE-143478-CW-RFB Component 2: Sanitation an Pending Im / Construction of public and d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- IDA / 60070 Post Request for Bids Open - National 0.00 plementati communal toilet for Jima tow rovement in secondary citie Envelope 0 0 5 5 4 8 26 on n by Jima Water Supply and s Sewerage Authority ET-MOWIE-143524-CW-RFB Component 2: Sanitation an / Construction of public and d water supply services imp Single Stage - One 2,000,000.0 Under Impl 2019-11-2 2020-05-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- IDA / 60070 Post Request for Bids Open - National 0.00 communal toilet for Harar t rovement in secondary citie Envelope 0 ementation 0 0 5 5 4 8 26 own by Harar Water Supply s and Sewerage Authority ET-MOWIE-143531-CW-RFB Component 2: Sanitation an / Construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- communal toilet for Arbamin IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 4 8 26 ch town by Arbaminch Wat on s er Supply and Sewerage Aut hority ET-MOWIE-143536-CW-RFB Component 2: Sanitation an Pending Im / Construction of public and d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- IDA / 60070 Post Request for Bids Open - National 0.00 plementati communal toilet for Gonder rovement in secondary citie Envelope 0 0 5 5 4 8 26 on town by Gonder Water Suppl s y and Sewerage Authority ET-MOWIE-143503-CW-RFB Component 2: Sanitation an / Construction of public and Pending Im d water supply services imp Single Stage - One 2,000,000.0 2019-11-2 2019-11-2 2019-12-2 2020-01-2 2020-02-2 2020-08- communal toilet for Shasha IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 4 8 26 mene town by Shashamene on s Water Supply and Sewerage Enterprise ET-MOWIE-139087-CW-RFB / Design, Construction and O peration of Five Cities Faecal Component 2: Sanitation an Sludge Treatment Plant (FST d water supply services imp Open - Internation Single Stage - One 21,643,000. 2020-03-1 2020-04-1 2020-06-0 2020-07-0 2020-08-2 2020-10- IDA / 60070 Prior Request for Bids 0.00 Canceled P) under two lots ( Lot I Ada rovement in secondary citie al Envelope 00 3 7 1 2 4 17 ma, Dire Dewa and Mekelle s and Lot II Bahir Dar and Haw asa). Implementing Agency: Water Development Commis sion. ET-MOWIE-172250-CW-RFQ Component 2: Sanitation an / construction of civil work, s Pending Im d water supply services imp Request for Quot Single Stage - One 2020-05-2 2020-07-2 2020-10- upply and installation of pipe IDA / 60070 Post Limited 73,970.00 0.00 plementati rovement in secondary citie ations Envelope 5 0 18 s and fittings for Shashamen on s e town WSSE low income are by Shashamene town WSSE ET-MOWIE-172255-CW-RFQ Component 2: Sanitation an / Civil work and supply and i Pending Im d water supply services imp Request for Quot Single Stage - One 2020-05-2 2020-07-2 2020-10- nstallation of electromagneti IDA / 60070 Post Limited 90,640.00 0.00 plementati rovement in secondary citie ations Envelope 5 0 18 cal equipment for Nekemte t on s own low income are by Neke mte town WSSE ET-MOWIE-172258-CW-RFQ Component 2: Sanitation an Pending Im / Expansion of Water Supply d water supply services imp Request for Quot Single Stage - One 2020-05-2 2020-07-2 2020-10- IDA / 60070 Post Limited 75,260.00 0.00 plementati system for Adigrat town low rovement in secondary citie ations Envelope 5 0 18 on income area by Adigrat town s WSSE ET-MOWIE-172259-CW-RFQ Component 2: Sanitation an / Earth Work, supply and inst d water supply services imp Request for Quot Single Stage - One 2020-05-2 2020-04-1 2020-07-2 2020-04-3 2020-10- IDA / 60080 Post Limited 75,800.00 29,363.01 Completed allation of pipes and fitting f rovement in secondary citie ations Envelope 5 8 0 0 18 or Jigjiga town low income ar s e by Jigijiga town WSSE ET-MOWIE-172260-CW-RFQ Component 2: Sanitation an / Earth work and supply and d water supply services imp Request for Quot Single Stage - One 2020-05-2 2020-04-0 2020-07-2 2020-04-2 2020-09- installation of pipes and fitti IDA / 60070 Post Limited 75,800.00 16,028.61 Signed rovement in secondary citie ations Envelope 5 9 0 7 18 ng for Degahabur town low i s ncome area water supply pr oject by Deghabur town WS SE ET-MOWIE-208763-CW-RFB / Procurement of constructio Component 2: Sanitation an n and rehabilitation 20 publi Pending Im d water supply services imp Single Stage - One 2020-12-2 2020-12-3 2021-01-2 2021-02-1 2021-03-2 2021-09- c and communal latrines (10 IDA / 60070 Post Request for Bids Open - National 488,000.00 0.00 plementati rovement in secondary citie Envelope 5 0 9 3 0 16 new construction and 10 exi on s sting latrines rehabilitation) f or Bahir Dar Town by Bahir Dar Town WSSA ET-MOWIE-208771-CW-RFB Component 2: Sanitation an / Construction of 22 public a Pending Im d water supply services imp Single Stage - One 2020-12-1 2020-12-2 2021-01-1 2021-02-0 2021-03-0 2021-08- nd communal latrines for Dir IDA / 60070 Post Request for Bids Open - National 816,000.00 0.00 plementati rovement in secondary citie Envelope 5 0 9 3 3 30 e Dewa town Under two lots on s (lot I 11 public and lot II 11 c ommunal) by Dire Dewa WS SE ET-MOWIE-208775-CW-RFB Component 2: Sanitation an / Construction of civil works f d water supply services imp Single Stage - One 2020-12-2 2021-06-1 2020-12-2 2021-01-2 2021-04-0 2021-02-1 2021-06-1 2021-03-1 2021-08-0 2021-09- or completing the sludge dry IDA / 60070 Post Request for Bids Open - National 369,000.00 182,459.98 Signed rovement in secondary citie Envelope 2 6 7 6 4 0 4 7 9 13 ing bed for fecal sludge man s agement for Arbaminch tow n by Arbaminch town WSS ET-MOWIE-227378-CW-RFB Component 2: Sanitation an / Construction of ten(10) pu Pending Im d water supply services imp Single Stage - One 2021-04-3 2021-05-1 2021-06-0 2021-06-2 2021-07-2 2022-01- blic and communal toilet for IDA / 60070 Post Request for Bids Open - National 509,670.00 0.00 plementati rovement in secondary citie Envelope 0 0 9 9 0 16 shashamane town by shash on s amane Water Supply and S ewerage Authority ET-MOWIE-143701-CW-RFB / Construction of 32 public Component 2: Sanitation an and communal latrines und Pending Im d water supply services imp Single Stage - One 1,600,000.0 2021-04-2 2021-04-2 2021-05-2 2021-06-2 2021-07-2 2022-07- er two lots ( Lot I #14 and L IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 4 9 29 ot II 18) for Mekelle Town b on s y Mekelle Town Water Suppl y and Sewerage Enterprise b y Mekelle town WSSE. Page 1 ET-MOWIE-250447-CW-RFB / Civil Work Construction wit Component 2: Sanitation an Request for Bids Pending Im h supply and laying pipes an d water supply services imp Single Stage - One - Small Works SP 1,900,000.0 2021-09-1 2021-09-1 2021-10-1 2021-10-3 2021-12-0 2022-10- IDA / 60070 Post Request for Bids Open - National 0.00 plementati d fittings and supply and ins rovement in secondary citie Envelope D (1 envelope pr 0 0 5 5 0 4 30 on tallation of EME for Deghabu s ocess) r town emergency response by Somali Region Water Bur eau ET-MOWIE-250451-CW-RFB / Civil Work Construction wit Component 2: Sanitation an Request for Bids Pending Im h supply and laying pipes an d water supply services imp Single Stage - One - Small Works SP 2,120,000.0 2021-09-1 2021-09-2 2021-10-2 2021-11-0 2021-12-0 2022-11- IDA / 60070 Post Request for Bids Open - National 0.00 plementati d fittings and supply and ins rovement in secondary citie Envelope D (1 envelope pr 0 5 0 0 4 9 04 on tallation of EME for Logia to s ocess) wn emergency response by afar Region Water Bureau ET-MOWIE-250453-CW-RFB / Civil Work Construction wit Component 2: Sanitation an Request for Bids Pending Im h supply and laying pipes an d water supply services imp Single Stage - One - Small Works SP 2,220,000.0 2021-09-1 2021-09-2 2021-10-2 2021-11-1 2021-12-2 2022-06- IDA / 60070 Post Request for Bids Open - National 0.00 plementati d fittings and supply and ins rovement in secondary citie Envelope D (1 envelope pr 0 5 0 0 9 4 22 on tallation of EME for Jigjiga to s ocess) wn emergency response by Somali Region Water Bureau ET-MOWIE-254110-CW-RFB / Rebidding of lot-2 1km acc National Procure Component 2: Sanitation an ess road and bridge structur ment Document Pending Im d water supply services imp Single Stage - One 2021-10-1 2021-11-1 2021-12-1 2022-01-1 2022-02-1 2022-06- e for construction of civil IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 350,000.00 0.00 plementati rovement in secondary citie Envelope 4 3 3 2 6 16 works for completing the slu cess (Non Bank-S on s dge drying bed for fecal slud PD) ge management for Arbamin ch town by Arbaminch town WSS National Procure ET-MOWIE-263469-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of 10 Commu d water supply services imp Single Stage - One 1,318,000.0 2021-12-1 2021-12-2 2022-01-1 2022-02-1 2022-03-2 2022-09- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati nal toilets and 10 public toile rovement in secondary citie Envelope 0 5 0 9 8 5 21 cess (Non Bank-S on ts- in Hawassa town by Haw s PD) assa town water utility National Procure ET-MOWIE-263472-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of 1 Public an d water supply services imp Single Stage - One 2021-12-1 2021-12-2 2022-01-1 2022-02-0 2022-03-1 2022-09- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 400,000.00 0.00 plementati d 5 Communal toilets-in Ada rovement in secondary citie Envelope 5 0 9 9 6 12 cess (Non Bank-S on ma town by Adama Water Ut s PD) ility National Procure ET-MOWIE-263475-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of 25 Commu d water supply services imp Single Stage - One 2021-12-1 2021-12-2 2022-01-1 2022-02-0 2022-03-1 2022-09- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 244,000.00 0.00 plementati nal Toilets in Dire Dawa tow rovement in secondary citie Envelope 5 0 9 9 6 12 cess (Non Bank-S on n by Dire Dawa town Water s PD) Utility National Procure ET-MOWIE-263476-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of 4 public an d water supply services imp Single Stage - One 2021-12-1 2021-12-2 2022-01-1 2022-02-0 2022-03-1 2022-08- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 277,000.00 0.00 plementati d 1 communal toilets-in Jigjig rovement in secondary citie Envelope 5 0 9 9 6 13 cess (Non Bank-S on a town by Jigjiga town Water s PD) Utility National Procure ET-MOWIE-263477-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of 7 public an d water supply services imp Single Stage - One 2021-12-1 2021-12-2 2022-01-1 2022-02-0 2022-03-1 2022-09- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 670,000.00 0.00 plementati d 8 communal toilets in Gon rovement in secondary citie Envelope 5 0 9 9 6 12 cess (Non Bank-S on der town by Gonder town wa s PD) ter utility ET-MOWIE-264799-CW-RFQ / Procurement of Water supp Component 2: Sanitation an Request for Quot Pending Im ly provision supplies (pipes, f d water supply services imp Request for Quot Single Stage - One 2021-12-2 2022-02-1 2022-06- IDA / 60070 Post Limited ations (Non Bank 54,300.00 0.00 plementati ittings and water meters) to rovement in secondary citie ations Envelope 0 4 14 -SPD) on unserved and low-income ar s eas of Jimma town by jimma town water utility ET-MOWIE-286606-CW-RFQ / Civil works construction w Component 2: Sanitation an ith five 10m3 capacity und Request for Quot Pending Im d water supply services imp Request for Quot Single Stage - One 2022-04-0 2022-05-3 2022-08- erground wet well water ta IDA / 60070 Post Limited ations (Non Bank 56,000.00 0.00 plementati rovement in secondary citie ations Envelope 4 0 28 nker and supply and installat -SPD) on s ion of five units of small boo ster pumps by Semera Logia town Water Utility ET-MOWIE-287404-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / construction of public and c d water supply services imp Single Stage - One - Small Works SP 2022-04-1 2022-04-1 2022-05-2 2022-06-2 2022-07-3 2023-01- IDA / 60070 Post Request for Bids Open - National 785,000.00 0.00 plementati ommunal toilet for Bishoftu t rovement in secondary citie Envelope D (1 envelope pr 0 5 7 6 1 27 on own by Bishoftu Water Suppl s ocess) y and Sewerage Authority ET-MOWIE-298420-CW-RFB / Construction of six public t Component 2: Sanitation an Request for Bids oilets, one communal toilet, Pending Im d water supply services imp Single Stage - One - Small Works SP 2022-06-1 2022-06-1 2022-07-1 2022-08-0 2022-09-0 2023-03- and finishing the remaining t IDA / 60070 Post Request for Bids Open - National 505,000.00 0.00 plementati rovement in secondary citie Envelope D (1 envelope pr 2 7 7 7 4 03 hree communal toilets in thr on s ocess) ee lots for Nekemte Town by Nekemte Town Water Suppl y and Sewerage Service Ent erprise ET-MOWIE-313926-CW-RFB / Construction of new #28 p National Procure ublic and #16 communal toil Component 2: Sanitation an ment Document Pending Im ets, rehabilitation of #2 publ d water supply services imp Single Stage - One 1,500,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-04- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati ic and #8 communal toilets, rovement in secondary citie Envelope 0 0 5 5 5 0 09 cess (Non Bank-S on rehabilitation of #6 septic ta s PD) nks and construction of #6 s eptic tanks for condominium areas with different lots for S odo town ET-MOWIE-313927-CW-RFB / Construction of new #10 p National Procure ublic and #10 communal toil Component 2: Sanitation an ment Document Pending Im ets and upgrading and const d water supply services imp Single Stage - One 1,504,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-07- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati ruction of #11 septic tank fo rovement in secondary citie Envelope 0 0 5 5 5 0 18 cess (Non Bank-S on r condominium and rehabilit s PD) ation of # 6 public and #4 c ommunal toilets with differe nt lots for Gonder town ET-MOWIE-313928-CW-RFB National Procure Component 2: Sanitation an / Construction of new #25 p ment Document Pending Im d water supply services imp Single Stage - One 2,700,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-06- ublic and #25 communal toil IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 5 0 18 ets and rehabilitation of #6 cess (Non Bank-S on s public toilets with different l PD) ots for Hawassa town ET-MOWIE-313929-CW-RFB National Procure / Construction of new #8 pu Component 2: Sanitation an ment Document Pending Im blic and #50 communal toile d water supply services imp Single Stage - One 1,300,000.0 2022-09-1 2022-09-2 2022-10-2 2022-11-1 2022-12-1 2023-07- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati t and rehabilitation of #5 pu rovement in secondary citie Envelope 0 5 0 0 0 5 13 cess (Non Bank-S on blic and #3 communal toilet s PD) s with different lots Dire De wa town ET-MOWIE-313930-CW-RFB National Procure / Construction of new #14 p Component 2: Sanitation an ment Document Pending Im ublic #15 communal, and # d water supply services imp Single Stage - One 2,700,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-08- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati 2 institutional toilets and reh rovement in secondary citie Envelope 0 0 5 5 5 0 17 cess (Non Bank-S on abilitation of #12 public and s PD) #15 communal toilets with d ifferent lots for Bishoftu tow n ET-MOWIE-313931-CW-RFB / Construction of new #20 p National Procure Component 2: Sanitation an ublic, #30 communal toilets ment Document Pending Im d water supply services imp Single Stage - One 2,630,000.0 2022-09-1 2022-09-2 2022-10-2 2022-11-1 2022-12-1 2023-08- and #20 septic tanks for con IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati rovement in secondary citie Envelope 0 5 0 0 0 5 12 dominium and rehabilitation cess (Non Bank-S on s of #3 public and #10 comm PD) unal toilets with different lot s for Bahir Dar town National Procure ET-MOWIE-313933-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of new 7 publi d water supply services imp Single Stage - One 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-06- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 903,000.00 0.00 plementati c, 9 communal and 1 institut rovement in secondary citie Envelope 0 5 5 5 0 18 cess (Non Bank-S on ional toilet with different lots s PD) for Semera Logia town ET-MOWIE-313934-CW-RFB / Construction of new #13 P National Procure Component 2: Sanitation an ublic, #20 Communal, and # ment Document Pending Im d water supply services imp Single Stage - One 3,400,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-08- 1 institutional toilet, #1 sept IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 5 0 17 ic tank at Goro Condominiu cess (Non Bank-S on s m and rehabilitation of # 6 p PD) ublic toilets with different lot s for Adama town ET-MOWIE-313935-CW-RFB National Procure / Construction of new #3 pu Component 2: Sanitation an ment Document Pending Im blic and #35 communal and d water supply services imp Single Stage - One 1,230,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-06- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati #1 institutional toilets and r rovement in secondary citie Envelope 0 0 5 5 5 0 18 cess (Non Bank-S on ehabilitation of #3 public an s PD) d #30 communal toilets with different lots for Harar town ET-MOWIE-313936-CW-RFB National Procure / Rehabilitation of #11 cond Component 2: Sanitation an ment Document Pending Im ominium sites septic tanks t d water supply services imp Single Stage - One 2022-10-2 2022-10-2 2022-11-2 2022-11-2 2022-12-3 2023-04- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 538,000.00 0.00 plementati hrough provision of soak pits rovement in secondary citie Envelope 0 5 4 6 1 30 cess (Non Bank-S on , replacement of pipes, reno s PD) vation of manholes and septi c tanks for Harar town ET-MOWIE-313937-CW-RFB / Construction of new #17 p ublic, #22 communal and # National Procure Component 2: Sanitation an 1 institutional toilet and #7 ment Document Pending Im d water supply services imp Single Stage - One 1,700,000.0 2022-09-1 2022-09-2 2022-10-2 2022-11-1 2022-12-1 2023-08- new septic tanks with sock a IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati rovement in secondary citie Envelope 0 5 0 0 0 5 12 way at #7 condominium site cess (Non Bank-S on s s and rehabilitation of #10 s PD) eptic tanks at condominium sites, #4 public and #6 com munal toilets with different l ots ET-MOWIE-313938-CW-RFB National Procure / Construction of new #16 p Component 2: Sanitation an ment Document Pending Im ublic and #31 communal toil d water supply services imp Single Stage - One 3,240,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-06- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati ets and rehabilitation of #15 rovement in secondary citie Envelope 0 0 5 5 5 0 18 cess (Non Bank-S on public and #12 communal to s PD) ilets with different lots for Sh ashamene town National Procure ET-MOWIE-313939-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of new #5 pu d water supply services imp Single Stage - One 1,034,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-06- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati blic and #15 communal toile rovement in secondary citie Envelope 0 0 5 5 5 0 18 cess (Non Bank-S on ts with different lots for Debr s PD) eberhan town ET-MOWIE-313940-CW-RFB National Procure / Construct of new #11 publi Component 2: Sanitation an ment Document Pending Im c, #21 communal and #1 in d water supply services imp Single Stage - One 1,500,000.0 2022-09-2 2022-09-2 2022-10-2 2022-10-2 2022-12-0 2023-06- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati stitutional toilets and rehabil rovement in secondary citie Envelope 0 0 5 5 7 1 29 cess (Non Bank-S on itation of #3 public and #12 s PD) communal toilets with differ ent lots for Jimma town ET-MOWIE-313941-CW-RFB National Procure Component 2: Sanitation an / Construction of new #10 p ment Document Pending Im d water supply services imp Single Stage - One 1,408,000.0 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-07- ublic and #20 communal toil IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati rovement in secondary citie Envelope 0 0 5 5 5 0 18 ets and rehabilitation of #3 cess (Non Bank-S on s communal toilets with differ PD) ent lots for Dessie town National Procure ET-MOWIE-313942-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of new #4 pu d water supply services imp Single Stage - One 2022-09-2 2022-09-2 2022-10-2 2022-11-1 2022-12-2 2023-05- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 570,000.00 0.00 plementati blic, #6 communal and #1 I rovement in secondary citie Envelope 0 5 5 5 0 19 cess (Non Bank-S on nstitutional toilet with differe s PD) nt lots for Nekemte town National Procure ET-MOWIE-313943-CW-RFB Component 2: Sanitation an ment Document Pending Im / Construction of new #4 pu d water supply services imp Single Stage - One 2022-09-2 2022-09-2 2022-10-2 2022-11-0 2022-12-0 2023-05- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 340,000.00 0.00 plementati blic, #1 communal toilet and rovement in secondary citie Envelope 0 5 5 8 6 05 cess (Non Bank-S on #1 institutional toilet for Jigji s PD) ga town National Procure ET-MOWIE-313944-CW-RFB Component 2: Sanitation an ment Document Pending Im Single Stage - One 2022-09-1 2022-09-2 2022-10-2 2022-11-1 2022-12-1 2022-12- / Construction of new #5 Co IDA / 60070 d water supply services imp Post Request for Bids Open - National - 1 Envelope pro 266,000.00 0.00 plementati Envelope 5 0 0 0 5 30 mmunal toilets for Degabour rovement in secondary citie cess (Non Bank-S on town s PD) ET-MOWIE-313946-CW-RFB National Procure Component 2: Sanitation an / Construction of new #5 pu ment Document Pending Im d water supply services imp Single Stage - One 2022-09-1 2022-09-2 2022-10-2 2022-11-1 2022-12-1 2023-06- blic and #15 communal and IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 980,000.00 0.00 plementati rovement in secondary citie Envelope 5 0 0 0 5 13 #1 institutional toilet with di cess (Non Bank-S on s fferent lots for Assela town PD) ET-MOWIE-316114-CW-RFQ / civil work for pressure main Component 2: Sanitation an pipeline laying and Installati Request for Quot Pending Im d water supply services imp Request for Quot Single Stage - One 2022-10-2 2022-12-2 2023-02- on of pumps with all accesso IDA / 60070 Post Limited ations (Non Bank 93,000.00 0.00 plementati rovement in secondary citie ations Envelope 5 0 18 ries for the two bore holes fo -SPD) on s r the improvement of the exi sting water supply system of Debre Berhan town Page 2 National Procure ET-MOWIE-316116-CW-RFQ Component 2: Sanitation an ment Document Pending Im / Rehabilitation of 10 existin d water supply services imp Request for Quot Single Stage - One 2022-10-3 2022-12-2 2023-03- IDA / 60070 Post Limited - 1 Envelope pro 96,000.00 0.00 plementati g deep wells to improve the rovement in secondary citie ations Envelope 0 5 25 cess (Non Bank-S on existing water supply syste s PD) m of Dire Dewa town ET-MOWIE-314177-CW-RFB National Procure Component 2: Sanitation an / Civil works, supply & laying ment Document Pending Im d water supply services imp Single Stage - One 3,240,000.0 2022-10-1 2022-10-2 2022-11-2 2022-12-0 2023-01-1 2024-01- of Pipes and fittings & electr IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 0.00 plementati rovement in secondary citie Envelope 0 8 3 2 7 1 11 omechanical equipment sup cess (Non Bank-S on s ply and installation for Shas PD) hamene town ET-MOWIE-325383-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 2,400,000.0 2022-12-1 2022-12-2 2023-01-1 2023-02-1 2023-03-2 2024-03- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 5 0 9 8 5 24 on plant (FSTP) for Gambela to s ocess) wn ET-MOWIE-325386-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 3,550,000.0 2022-12-1 2022-12-2 2023-01-3 2023-03-0 2023-04-0 2024-04- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 5 0 1 2 6 05 on plant (FSTP) for Asosa town s ocess) ET-MOWIE-325388-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 2,705,000.0 2022-12-1 2022-12-2 2023-01-3 2023-03-0 2023-04-0 2024-04- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 5 0 1 2 6 05 on plant (FSTP) for Semera Logi s ocess) a town ET-MOWIE-325390-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 6,551,000.0 2022-12-2 2022-12-2 2023-01-2 2023-02-2 2023-03-3 2024-03- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 0 5 4 3 0 29 on plant (FSTP) for Sodo town s ocess) ET-MOWIE-325392-CW-RFB / Procurement of Constructio Component 2: Sanitation an Request for Bids Pending Im n of new fecal sludge treatm d water supply services imp Single Stage - One - Small Works SP 4,732,000.0 2022-12-2 2022-12-2 2023-02-0 2023-03-0 2023-04-1 2024-04- IDA / 60070 Post Request for Bids Open - National 0.00 plementati ent plant (FSTP) Rehabilitati rovement in secondary citie Envelope D (1 envelope pr 0 0 5 5 7 1 10 on on; Upgrade and Expansion s ocess) of Existing Drying Bed for Ar ba Minch town. ET-MOWIE-325393-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 2,691,000.0 2023-01-2 2023-01-2 2023-03-0 2023-04-0 2023-05-1 2024-05- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 0 5 8 7 2 11 on plant for Bishoftu town s ocess) ET-MOWIE-325396-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 4,803,000.0 2023-01-2 2023-01-3 2023-03-0 2023-03-3 2023-05-0 2024-05- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 5 0 1 1 5 04 on plant for Shashemene town s ocess) ET-MOWIE-325398-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 2,604,000.0 2023-01-2 2023-01-3 2023-03-1 2023-04-1 2023-05-1 2024-05- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 5 0 3 2 7 16 on plant for Assela town s ocess) ET-MOWIE-325400-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 4,966,000.0 2023-01-0 2023-01-1 2023-02-2 2023-03-2 2023-04-2 2024-04- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 5 0 1 3 7 26 on plant for Jimma town s ocess) ET-MOWIE-325407-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 3,672,000.0 2023-01-0 2023-01-1 2023-02-2 2023-03-2 2023-04-2 2024-04- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 5 0 1 3 7 26 on plant for Nekemte town s ocess) ET-MOWIE-325410-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 6,600,000.0 2023-01-1 2023-01-1 2023-02-2 2023-03-2 2023-05-0 2024-05- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 0 5 6 8 2 01 on plant (FSTP) for Dessie town s ocess) ET-MOWIE-325412-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 3,100,000.0 2023-01-1 2023-01-1 2023-02-2 2023-03-2 2023-05-0 2024-05- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 0 5 6 8 2 01 on plant (FSTP) for Debre Berha s ocess) n town ET-MOWIE-325414-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 2,500,000.0 2023-03-3 2023-04-0 2023-05-1 2023-06-1 2023-07-2 2024-07- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment rovement in secondary citie Envelope D (1 envelope pr 0 1 5 7 6 1 20 on plant (FSTP) for Jigjiga town s ocess) Request for Bids ET-MOWIE-325415-CW-RFB Component 2: Sanitation an Pending Im Single Stage - One - Small Works SP 1,700,000.0 2023-03-3 2023-04-0 2023-05-0 2023-06-0 2023-07-0 2024-07- / Construction of fecal sludg IDA / 60070 d water supply services imp Post Request for Bids Open - National 0.00 plementati Envelope D (1 envelope pr 0 1 5 5 4 9 08 e treatment plant (FSTP) for rovement in secondary citie on ocess) Degehabour town s ET-MOWIE-325416-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Single Stage - One - Small Works SP 3,000,000.0 2022-12-3 2023-01-0 2023-02-0 2023-03-0 2023-04-0 2024-04- IDA / 60070 Post Request for Bids Open - National 0.00 plementati n of fecal sludge treatment P rovement in secondary citie Envelope D (1 envelope pr 0 0 4 3 5 9 08 on lant (FSTP) for Harar City s ocess) ET-MOWIE-325418-CW-RFB Component 2: Sanitation an Request for Bids / Construction of wastewater Pending Im d water supply services imp Single Stage - One - Small Works SP 2,800,000.0 2023-01-3 2023-02-0 2023-03-0 2023-04-0 2023-05-1 2024-11- treatment plant (WWTP), tru IDA / 60070 Post Request for Bids Open - National 0.00 plementati rovement in secondary citie Envelope D (1 envelope pr 0 1 5 7 6 1 01 nk and collector line /Sewer on s ocess) network with appurtenances , with different lots for Harar City National Procure ET-MOWIE-325424-CW-RFQ Component 2: Sanitation an ment Document Pending Im Request for Quot Single Stage - One 2023-01-0 2023-03-0 2023-08- / Construction of small size t IDA / 60070 d water supply services imp Post Limited - 1 Envelope pro 29,000.00 0.00 plementati ations Envelope 4 1 28 est bench house for Arbamin rovement in secondary citie cess (Non Bank-S on ch Utility s PD) ET-MOWIE-325429-CW-RFQ Component 2: Sanitation an Request for Quot Pending Im Request for Quot Single Stage - One 2023-01-0 2023-03-0 2023-08- / Construction of small size t IDA / 60070 d water supply services imp Post Limited ations (Non Bank 29,000.00 0.00 plementati ations Envelope 4 1 28 est bench house by Jimma U rovement in secondary citie -SPD) on tility s National Procure ET-MOWIE-325431-CW-RFQ Component 2: Sanitation an ment Document Pending Im / Procurement of Constructio d water supply services imp Request for Quot Single Stage - One 2023-01-0 2023-03-0 2023-08- IDA / 60070 Post Limited - 1 Envelope pro 29,000.00 0.00 plementati n of small size test bench ho rovement in secondary citie ations Envelope 4 1 28 cess (Non Bank-S on use by Dessie Utility s PD) National Procure ET-MOWIE-325428-CW-RFQ Component 2: Sanitation an ment Document Pending Im Request for Quot Single Stage - One 2023-01-0 2023-03-0 2023-08- / Construction of small size t IDA / 60070 d water supply services imp Post Limited - 1 Envelope pro 29,000.00 0.00 plementati ations Envelope 4 1 28 est bench house by W/Sodo rovement in secondary citie cess (Non Bank-S on Utility s PD) ET-MOWIE-313925-CW-RFB National Procure / Construction of new # 4 pu Component 2: Sanitation an ment Document Pending Im blic, #1 communal and #1 i d water supply services imp Single Stage - One 2022-12-2 2022-12-2 2023-01-2 2023-02-1 2023-03-2 2023-09- IDA / 60070 Post Request for Bids Open - National - 1 Envelope pro 467,300.00 0.00 plementati nstitutional and completion rovement in secondary citie Envelope 0 5 4 4 1 17 cess (Non Bank-S on of the remaining works for # s PD) 8 public toilet under differen t lot for Asosa town ET-MOWIE-325409-CW-RFB Component 2: Sanitation an Request for Bids Pending Im / Procurement of Constructio d water supply services imp Open - Internation Single Stage - One - Small Works SP 9,500,000.0 2023-01-1 2023-01-1 2023-02-2 2023-03-2 2023-05-0 2024-05- IDA / 60070 Post Request for Bids 0.00 plementati n of fecal sludge treatment rovement in secondary citie al Envelope D (1 envelope pr 0 0 5 6 8 2 01 on plant (FSTP) for Gonder town s ocess) ET-MOWIE-172944-CW-RFP / Design, Construction and O peration of Five Cities Faecal Component 2: Sanitation an Sludge Treatment Plant (FST d water supply services imp Request for Prop Open - Internation Single Stage - Two 21,643,000. 2020-06-0 2020-08-2 2020-08-2 2021-04-0 2020-08-2 2021-08-1 2020-06-1 2020-09-0 2020-10-3 2021-12-2 2021-01-1 2021-02-1 2022-08- IDA / 60070 Prior 0.00 Canceled P) under two lots ( Lot I Ada rovement in secondary citie osals al Envelope 00 5 1 1 7 1 6 0 8 0 3 2 6 10 ma, Dire Dewa and Mekelle s and Lot II Bahir Dar and Haw asa). Implementing Agency: Water Development Commis sion. ET-MOWIE-334601-CW-RFB / Construction of #7 new se Component 2: Sanitation an Request for Bids Pending Im ptic tanks with sock away at d water supply services imp Single Stage - One - Small Works SP 2023-01-2 2023-02-2 2023-03-0 2023-03-2 2023-05-0 2023-10- IDA / 60070 Post Request for Bids Open - National 280,240.00 0.00 plementati #7 condominium sites and r rovement in secondary citie Envelope D (1 envelope pr 6 5 7 7 1 28 on ehabilitation of #10 septic t s ocess) anks at condominium sites w ith two lots. by A/ Minich utili ty GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43004-GO-DIR / Component 2: Sanitation an Supply of pipes and fittings f d water supply services imp Under Imple 2018-01-1 2018-01-1 2018-02-2 2018-05-2 IDA / 60070 Prior Direct Selection Direct 1,897,466.00 0.00 or the remaining work of Dir rovement in secondary citie mentation 2 7 4 5 e Dewa City Water Supply a s nd Sanitation Project ET-MOWIE-43329-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-1 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 7 6 gthening py machines and lap top co mputers) for Gambella City Water Supply and Sewerage Service ET-MOWIE-43286-GO-RFQ / procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One 2018-03-2 2019-09-1 2018-05-0 2020-03-2 2018-06-0 2020-04-1 IDA / 60070 gement & institutional stren Post Limited 10,000.00 5,098.59 Completed mputers, scanners, photo co ations Envelope 2 0 3 1 2 0 gthening py machines and lap top co mputers)for Deghabur Town Water Supply and Sewerage Service ET-MOWIE-43289-GO-RFQ / procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Under Imple 2018-03-2 2020-09-1 2018-05-0 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope mentation 2 7 3 2 gthening py machines and lap top co mputers) for Arbaminch Tow n Water Supply and Sewerag e Service ET-MOWIE-43291-GO-RFQ / procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-0 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 2 3 2 gthening py machines and lap top co mputers) for Harar Town Wa ter Supply and Sewerage Se rvice ET-MOWIE-43294-GO-RFQ / procurement of office equip Component 3: Project mana ment(printers, desk top com Request for Quot Single Stage - One 2018-03-2 2019-11-2 2018-05-1 2020-06-2 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 6,182.79 Signed puters, scanners, photo copy ations Envelope 9 5 0 3 9 gthening machines and lap top compu ters) for Bishoftu Town Wate r Supply and Sewerage Servi ce ET-MOWIE-43297-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-1 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 7 6 gthening py machines and lap top co mputers) for Shashemane Ci ty Water Supply and Sewera ge Service ET-MOWIE-43299-GO-RFQ / procurement of office equip Component 3: Project mana ment(printers, desk top com Request for Quot Single Stage - One 2018-03-2 2017-09-1 2018-05-1 2020-04-0 2018-06-1 2020-04-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 11,105.57 Completed puters, scanners, photo copy ations Envelope 9 1 7 2 6 2 gthening machines and lap top compu ters) for Jigjiga City Water Su pply and Sewerage Service ET-MOWIE-43300-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 0 9 gthening py machines and lap top co mputers) for Hawassa City Water Supply and Sewerage Service ET-MOWIE-43035-GO-RFQ / Procurement of IT equipmen Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2018-04-1 2018-06-0 2018-07-0 t (printers, desk top comput IDA / 60070 gement & institutional stren Post Limited 50,000.00 0.00 ations Envelope lementation 4 9 9 ers, scanners, photo copy m gthening achines and lap top compute rs) for Ministry PIU Page 3 ET-MOWIE-43317-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-1 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 7 6 gthening py machines and lap top co mputers) for Assosa City Wa ter Supply and Sewerage Se rvice ET-MOWIE-43319-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 0 9 gthening py machines and lap top co mputers) for Asella City Wat er Supply and Sewerage Ser vice ET-MOWIE-43322-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 0 9 gthening py machines and lap top co mputers) for Sodo City Wate r Supply and Sewerage Servi ce ET-MOWIE-43324-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One 2018-03-2 2018-12-2 2018-05-1 2019-02-0 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 3,436.18 Signed mputers, scanners, photo co ations Envelope 9 7 0 7 9 gthening py machines and lap top co mputers) for Debre Berhan C ity Water Supply and Sewera ge Service ET-MOWIE-43326-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 0 9 gthening py machines and lap top co mputers) for Dessie City Wat er Supply and Sewerage Ser vice ET-MOWIE-43328-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 0 9 gthening py machines and lap top co mputers) for Gonder City Wa ter Supply and Sewerage Se rvice ET-MOWIE-43331-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One 2018-03-2 2018-09-0 2018-05-1 2018-09-2 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 3,362.55 Signed mputers, scanners, photo co ations Envelope 9 6 0 9 9 gthening py machines and lap top co mputers) for Nekmte City W ater Supply and Sewerage S ervice ET-MOWIE-43333-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One 2018-03-2 2018-09-1 2018-05-1 2018-11-0 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 545.62 Signed mputers, scanners, photo co ations Envelope 9 9 0 3 9 gthening py machines and lap top co mputers) for Jimma City Wa ter Supply and Sewerage Se rvice ET-MOWIE-43303-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One 2018-03-2 2019-09-2 2018-05-1 2019-10-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 8,151.84 Signed mputers, scanners, photo co ations Envelope 9 6 0 9 9 gthening py machines and lap top co mputers) for Adama City W ater Supply and Sewerage S ervice ET-MOWIE-43304-GO-RFQ / Procurement of office equip Component 3: Project mana ment (printers, desk top co Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 mputers, scanners, photo co ations Envelope lementation 9 0 9 gthening py machines and lap top co mputers) for Mekelle City W ater Supply and Sewerage S ervice ET-MOWIE-43307-GO-RFQ / Procurement of office equip Component 3: Project mana ment(printers, desk top com Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 puters, scanners, photo copy ations Envelope lementation 9 0 9 gthening machines and lap top compu ters) for Bahir Dar City Wat er Supply and Sewerage Ser vice ET-MOWIE-43310-GO-RFQ / Procurement of office equip Component 3: Project mana ment for Dire Dawa City Wat Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 er Supply and Sewerage Ser ations Envelope lementation 9 0 9 gthening vice(Printers, desk top comp uters, scanners, photo copy machines and lap top compu ters) ET-MOWIE-43311-GO-RFQ / Procurement of office equip Component 3: Project mana ment for Semera City Water Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 Supply and Sewerage Servic ations Envelope lementation 9 0 9 gthening e(Printers, desk top compute rs, scanners, photo copy ma chines and lap top computer s) ET-MOWIE-43313-GO-RFQ / Procurement of office equip Component 3: Project mana ment for Adegrat City Water Request for Quot Single Stage - One Pending Imp 2018-03-2 2018-05-1 2018-06-0 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 Supply and Sewerage Servic ations Envelope lementation 9 0 9 gthening e (printers, desk top comput ers, scanners, photo copy m achines and lap top compute rs) ET-MOWIE-50407-GO-DIR / Component 2: Sanitation an Procurement of Bulk Flow m d water supply services imp 2018-02-2 2018-04-0 2018-03-0 2018-04-0 2018-07-0 IDA / 60070 Prior Direct Selection Direct 433,013.00 0.00 Canceled eter for Mekelle Town Water rovement in secondary citie 8 5 5 6 5 Supply and Sewerage Servic s e by Mekelle town WSSS ET-MOWIE-55837-GO-RFB / Component 2: Sanitation an Single Stage - One Pending Imp 2018-06-2 2018-06-2 2018-07-2 2018-08-2 2018-09-2 2018-12-2 Procurement of Automatic W IDA / 60070 d water supply services imp Post Request for Bids Open - National 250,000.00 0.00 Envelope lementation 0 5 5 4 8 7 ater Meter Test Bench rovement in secondary citie s ET-MOWIE-75633-GO-RFQ / Procurement of office equip ment (printers, desk top co mputers, scanners photocop Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2018-09-1 2018-11-1 2018-12-1 y machines and laptop comp IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 ations Envelope lementation 5 0 0 uters for Amhara Region Wa gthening ter,Irrigation and Energy De velopment Bureau by Amhar a Region Water,Irrigation an d Energy Development Bure au ET-MOWIE-75634-GO-RFQ / Procurement of office equip ment (printers, desk top co Component 3: Project mana mputers, scanners photocop Request for Quot Single Stage - One Pending Imp 2018-09-1 2018-11-1 2018-12-1 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 y machines and laptop comp ations Envelope lementation 5 0 0 gthening uters for Oromia Region Wat er,Mineral and Energy Bure au by Oromia Region Water, Mineral and Energy Bureau. ET-MOWIE-75635-GO-RFQ / Procurement of office equip ment (printers, desk top co mputers, scanners photocop Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2018-09-1 2018-11-1 2018-12-1 y machines and laptop comp IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 ations Envelope lementation 5 0 0 uters for SNNPR Region Wat gthening er,Irrigation and Energy Dev elopment Bureau by SNNPR Region Water,Irrigation and Energy Development Bureau ET-MOWIE-75636-GO-RFQ / Procurement of office equip ment (printers, desk top co Component 3: Project mana mputers, scanners photocop Request for Quot Single Stage - One Pending Imp 2018-09-1 2018-11-1 2018-12-1 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 y machines and laptop comp ations Envelope lementation 5 0 0 gthening uters for Afar Region Water Resource Development Bure au by Afar Region Water Res ource Development Bureau ET-MOWIE-75637-GO-RFQ / Procurement of office equip ment (printers, desk top co Component 3: Project mana mputers, scanners photocop Request for Quot Single Stage - One Pending Imp 2018-09-1 2018-11-1 2018-12-1 IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 y machines and laptop comp ations Envelope lementation 5 0 0 gthening uters for Somali Region Wat er Resource Development B ureau by Somali Region Wat er Resource Development B ureau ET-MOWIE-75641-GO-RFQ / Procurement of office equip ment (printers, desk top co mputers, scanners photocop Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2018-09-1 2018-11-1 2018-12-1 y machines and laptop comp IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 ations Envelope lementation 5 0 0 uters for Gambella Region gthening Water,Irrigation and Energy Development Bureau by Ga mbella Region Water,Irrigati on and Energy Development Bureau ET-MOWIE-75643-GO-RFQ / Procurement of office equip ment (printers, desk top co mputers, scanners photocop Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2018-09-1 2018-11-1 2018-12-1 y machines and laptop comp IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 ations Envelope lementation 5 0 0 uters for Benshangul Gumuz gthening Region Water,Irrigation and Energy Development Bureau by Benshangul Region Wate r,Irrigation and Energy Devel opment Bureau ET-MOWIE-75646-GO-RFQ / Procurement of Office Equip ment (printers, desktop com Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2018-09-1 2018-11-1 2018-12-1 puters, scanners, photocopy IDA / 60070 gement & institutional stren Post Limited 10,000.00 0.00 ations Envelope lementation 5 0 0 machines and laptop compu gthening ters) for Tigray Region Wate r Bureau by Tigray Region W ater Bureau ET-MOWIE-84615-GO-RFB / Procurement of 44 Double C Component 3: Project mana Open - Internation Single Stage - One 2018-11-1 2019-02-0 2018-11-2 2019-02-2 2019-01-0 2019-04-1 2019-01-3 2019-07-1 2019-03-0 2019-09-0 2019-09-0 2020-06-2 up vehicles for 22 Secondary IDA / 60080 gement & institutional stren Prior Request for Bids 1,800,000.00 1,412,937.01 Completed al Envelope 5 2 0 7 1 5 1 0 7 5 3 9 Cities, Regional Water Burea gthening us PMU, and Federal PMU ET-MOWIE-98176-GO-RFB / Supply and Installation Equi Component 2: Sanitation an pment for Water Quality La d water supply services imp Open - Internation Single Stage - One Pending Imp 2019-03-1 2019-03-1 2019-04-3 2019-05-3 2019-07-0 2019-11-0 IDA / 60070 Post Request for Bids 1,000,000.00 0.00 boratory and Training Center rovement in secondary citie al Envelope lementation 4 9 0 0 4 1 for Mekelle Town Water Sup s ply Project by Mekelle Town Water Supply Office ET-MOWIE-143211-GO-RFB / Procurement of 25 (twenty Component 2: Sanitation an five ) 10m3 and 8m3 size v d water supply services imp Open - Internation Single Stage - One Under Imple 2019-11-2 2020-08-1 2019-11-3 2020-09-0 2020-01-1 2020-11-2 2020-02-1 2021-04-2 2020-03-1 2020-09-1 acuum track for 5 towns( Ad IDA / 60070 Prior Request for Bids 5,500,000.00 0.00 rovement in secondary citie al Envelope mentation 9 9 0 1 4 2 3 3 9 5 ama,Mekele,Diredewa, Bahir s dar ,and Hawasa) of UWSSP -2 By Water Development Commission . ET-MOWIE-156913-GO-RFB / procurement of 44 (forty-fou Component 2: Sanitation an r) Motorcycles for 22 Towns d water supply services imp Single Stage - One 2020-02-1 2020-07-0 2020-03-1 2020-04-1 2020-07-2 2020-05-1 2020-12-2 2020-06-1 2020-12-1 IDA / 60070 Post Request for Bids Open - National 180,000.00 0.00 Canceled of Urban Water Supply and S rovement in secondary citie Envelope 2 7 3 2 1 2 3 6 3 anitation project II (UWSSP-2 s ) by Water Development Co mmission ET-MOWIE-166460-GO-DIR / Procurement of IT Equipmen t (E-video (ten in number) Component 3: Project mana Modem with subscription 4G Pending Imp 2020-03-3 2020-04-0 2020-05-0 2020-06-1 IDA / 60070 gement & institutional stren Post Direct Selection Direct 3,600.00 0.00 B and Fixed Wireless Broadb lementation 0 4 9 8 gthening and (WIFI) (3) three apparat uses for water Development Commission offices and Sta ffs will be implemented by W DC ET-MOWIE-166453-GO-RFQ / Procurement of Core i7 7 ( Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2020-04-0 2020-05-3 2020-07-2 seven) Laptops for Water D IDA / 60070 gement & institutional stren Post Limited 10,937.50 0.00 ations Envelope lementation 4 0 9 evelopment commission Sta gthening ffs which will be implemente d by WDC. Page 4 ET-MOWIE-168265-GO-RFB / procurement of pipes and fit Component 2: Sanitation an tings, water meters and leak d water supply services imp Open - Internation Single Stage - One 2020-04-3 2020-01-2 2020-05-0 2020-06-0 2021-02-0 2020-07-0 2021-04-2 2020-08-0 2021-06-2 2020-12-0 IDA / 60070 Post Request for Bids 907,000.00 507,531.01 Signed detection equipment for Gon rovement in secondary citie al Envelope 0 9 5 4 3 4 9 8 4 6 der town Water Supply and s Sewerage service enterprise by Gonder town WSSE ET-MOWIE-172211-GO-RFQ Component 2: Sanitation an / Procurement of Pipes and fi d water supply services imp Request for Quot Single Stage - One 2020-05-2 2020-07-0 2020-07-1 2020-07-2 2020-08-1 IDA / 60070 Post Limited 75,800.00 60,209.31 Signed ttings and water meters for rovement in secondary citie ations Envelope 0 6 5 2 4 Arbaminch Town WSSE by Ar s baminch town WSSE ET-MOWIE-172215-GO-RFQ Component 2: Sanitation an / Procurement of Pipes and fi d water supply services imp Request for Quot Single Stage - One 2020-05-2 2020-06-2 2020-07-1 2020-07-0 2020-08-1 IDA / 60070 Post Limited 75,700.00 61,772.81 Signed ttings and water meters for rovement in secondary citie ations Envelope 0 9 5 3 4 Wolaita Sodo Town WSSE by s Wolaita town WSSE ET-MOWIE-172221-GO-RFQ Component 2: Sanitation an / Procurement of Pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-1 2020-08-1 IDA / 60070 Post Limited 75,800.00 0.00 ttings Hawasa Town WSSE b rovement in secondary citie ations Envelope lementation 0 5 4 y Hawasa town WSSE for low s income area ET-MOWIE-172233-GO-RFQ Component 2: Sanitation an / Procurement of HDPE Pipes d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-1 2020-08-1 and fittings and water meter IDA / 60070 Post Limited 75,800.00 0.00 rovement in secondary citie ations Envelope lementation 0 5 4 s for Debre Brerhan Town W s SSE by DebreBerhan town W SSE for low income area ET-MOWIE-172236-GO-RFQ Component 2: Sanitation an / Procurement of Pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-1 2020-08-1 IDA / 60070 Post Limited 75,700.00 0.00 ttings for Dessie Town WSSE rovement in secondary citie ations Envelope lementation 0 5 4 by Dessie town WSSE for low s income area ET-MOWIE-172241-GO-RFQ Component 2: Sanitation an / Procurement of Pipes and fi d water supply services imp Request for Quot Single Stage - One 2020-05-2 2020-01-2 2020-07-1 2020-03-1 2020-08-1 IDA / 60070 Post Limited 75,800.00 39,738.87 Signed ttings for Gonder Town WSS rovement in secondary citie ations Envelope 3 9 8 7 7 E by Gonder town WSSE for l s ow income area ET-MOWIE-172244-GO-RFQ Component 2: Sanitation an / Procurement of Pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-1 2020-08-1 IDA / 60070 Post Limited 75,800.00 0.00 ttings for Bahir Dar Town lo rovement in secondary citie ations Envelope lementation 0 5 4 w income area WSSE by Bah s ir Dar town WSSE ET-MOWIE-172245-GO-RFQ Component 2: Sanitation an / Procurement of HDPE Pipe d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-2 2020-08-1 s and fittings and water met IDA / 60070 Post Limited 75,690.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 9 ers for Bishftu Town WSSE b s y Bishftu town WSSE for low income area ET-MOWIE-172248-GO-RFQ Component 2: Sanitation an / Procurement of HDPE Pipes d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-2 2020-08-1 and fittings and Water meter IDA / 60070 Post Limited 74,980.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 9 s for Jimma Town WSSE by Ji s mma town WSSE for low inc ome area ET-MOWIE-172256-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-2 2020-09-1 ttings, leak detection and w IDA / 60070 Post Limited 75,800.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 8 ater quality test equipment f s or Assela town low income a rea by Assela town WSSE ET-MOWIE-172257-GO-RFQ Component 2: Sanitation an / Supply and installation of p d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-1 2020-10-1 ipes and fittings for Mekelle IDA / 60070 Post Limited 75,800.00 0.00 rovement in secondary citie ations Envelope lementation 0 5 3 town low income area water s supply project by Mekelle to wn WSSP ET-MOWIE-172262-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-2 2020-09-1 ttings for Gambella town tow IDA / 60070 Post Limited 75,800.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 8 n low income area water sup s ply project by Gambella tow n WSSP ET-MOWIE-172263-GO-RFQ Component 2: Sanitation an / Procurement of pipe fitting d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-2 2020-08-1 IDA / 60070 Post Limited 5,000.00 0.00 s for Asosa town low income rovement in secondary citie ations Envelope lementation 5 0 9 area water supply project by s Asosa WSSE ET-MOWIE-172265-GO-RFQ Component 2: Sanitation an / procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-2 2020-07-2 2020-09-1 IDA / 60070 Post Limited 69,500.00 0.00 ttings for Harar town low inc rovement in secondary citie ations Envelope lementation 5 0 8 ome area water supply proje s ct by Harar town WSSE ET-MOWIE-172275-GO-RFQ Component 2: Sanitation an / supply of pipes and fittings d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-3 2020-07-2 2020-09-2 for Semera Logia town low i IDA / 60070 Post Limited 72,500.00 0.00 rovement in secondary citie ations Envelope lementation 1 6 4 ncome area water supply pr s oject by Semera Logia WSSE ET-MOWIE-172933-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-3 2020-07-2 2020-09-2 ttings for Dire Dewa town lo IDA / 60070 Post Limited 75,800.00 0.00 rovement in secondary citie ations Envelope lementation 0 5 3 w income area water supply s project by Dire Dewa Town WSSE ET-MOWIE-168264-GO-RFB / Procurement of Water meter Component 2: Sanitation an s, Bulk flow meters, pipes an d water supply services imp Open - Internation Single Stage - One 2020-05-2 2021-03-1 2020-06-0 2020-07-0 2021-05-1 2020-08-0 2021-05-2 2020-09-0 2021-09-0 2021-01-0 IDA / 60070 Post Request for Bids 1,565,000.00 1,156,445.83 Signed d fittings and leak detection rovement in secondary citie al Envelope 8 6 2 2 4 1 6 5 8 3 Equipments for Jima Town W s ater Supply and Sewerage E nterprise by Jima town WSSE ET-MOWIE-174562-GO-RFQ / Procurement of Aluminium Component 2: Sanitation an sulfate for covid-19 interven d water supply services imp Request for Quot Single Stage - One 2020-05-3 2020-07-0 2020-07-1 IDA / 60070 Post Limited 46,154.00 0.00 Canceled tion in Gmbella towns healt rovement in secondary citie ations Envelope 1 5 9 h stations, hospitals, isolatio s n centers and areas with acu te waster supply shortage b y WDC ET-MOWIE-174573-GO-RFQ Component 2: Sanitation an / Procurement of filter media d water supply services imp Request for Quot Single Stage - One 2020-05-3 2020-07-0 2020-07-1 IDA / 60070 Post Limited 46,154.00 0.00 Canceled Sand for Gambella town Wat rovement in secondary citie ations Envelope 1 5 9 er Treatment plant by Gamb s ella Town Water Utility ET-MOWIE-175708-GO-RFQ Component 2: Sanitation an / Procurement of Pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-06-1 2020-07-1 2020-08-1 ttings for Adama town low in IDA / 60070 Post Limited 76,900.00 0.00 rovement in secondary citie ations Envelope lementation 0 5 4 come area water supply proj s ect by Adama town Water Ut ility ET-MOWIE-43018-GO-RFB / Procurement of 44 vehicles( double Cabins) for secondar Component 3: Project mana 2018-06-2 2018-06-2 2018-07-3 2018-11-2 y city utilities, Regional Wat IDA / 60070 gement & institutional stren Prior Direct Selection Direct 1,800,000.00 0.00 Canceled 0 5 0 7 er Bureaus and 2 Vehicles( gthening double Cabins) for Ministry P IU by the Ministry of Water Ir rigation and Electricity throu gh UNOPS ET-MOWIE-181638-GO-RFB / Procurement of Pipes and Fit Component 2: Sanitation an tings for covid-19 interventio d water supply services imp Open - Internation Single Stage - One Under Imple 2020-07-0 2020-09-0 2020-07-1 2020-09-0 2020-08-0 2020-08-1 2020-09-0 2020-12-0 IDA / 60070 Post Request for Bids 573,766.00 0.00 n in 13 towns health statio rovement in secondary citie al Envelope mentation 6 4 1 8 1 5 5 4 ns, hospitals, isolation cente s rs and areas with acute wast er supply shortage by WDC ET-MOWIE-174564-GO-RFQ / Procurement of Water treat Component 2: Sanitation an ment Chemicals and Reagen d water supply services imp Request for Quot Single Stage - One 2020-07-1 2020-08-1 2020-08-2 IDA / 60070 Post Limited 110,769.00 0.00 Canceled ts for covid-19 intervention rovement in secondary citie ations Envelope 1 5 9 in Bonga town to areas with s acute waster supply shortag e by WDC ET-MOWIE-181653-GO-RFQ Component 2: Sanitation an / Procurement of pipe fitting d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-07-1 2020-08-2 2020-09-1 IDA / 60070 Post Limited 2,700.00 0.00 s for Harar town water suppl rovement in secondary citie ations Envelope lementation 1 9 2 y project by Harar town s ET-MOWIE-181625-GO-RFB / Procurement of Electromec hanical Equipment (59 subm Component 2: Sanitation an ersible water pumps (lot I) ,1 d water supply services imp Open - Internation Single Stage - One Under Imple 2020-07-0 2020-09-0 2020-07-1 2020-09-0 2020-08-0 2020-10-2 2020-08-1 2020-09-0 2020-12-0 IDA / 60070 Post Request for Bids 4,139,530.00 0.00 1 surface pumps (lot II) ,2 S rovement in secondary citie al Envelope mentation 8 4 3 8 3 1 7 7 6 urge Vessels (Lot III) and 29 s Generators (lot IV) for 25 to wns covid-19 intervention in acute water supply shortag e areas by WDC. ET-MOWIE-183159-GO-DIR / Component 2: Sanitation an Procurement of filter media d water supply services imp Pending Imp 2020-07-1 2020-07-2 2020-08-1 2020-09-0 IDA / 60070 Post Direct Selection Direct 46,154.00 0.00 Sand for Gambella town Wat rovement in secondary citie lementation 5 0 0 9 er Treatment plant by Gamb s ella Town Water Utility ET-MOWIE-185679-GO-RFQ / Procurement of Office Equi pment (#12 laptop compute Component 3: Project mana Request for Quot Single Stage - One 2020-08-1 2021-05-2 2020-10-0 2021-06-2 2020-10-2 rs, #1 Led Projector, #2 Hea IDA / 60070 gement & institutional stren Post Limited 50,000.00 835.30 Signed ations Envelope 0 3 5 8 0 vy duty color printers, #1 sc gthening anner and #1 heavy duty ph oto copy machine) for WDC PIU by WDC ET-MOWIE-208762-GO-RFB / Component 2: Sanitation an Procurement of pipes and fit d water supply services imp Single Stage - One Pending Imp 2020-12-2 2020-12-2 2021-01-2 2021-02-0 2021-03-0 2021-05-0 ting for expansion of water s IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 rovement in secondary citie Envelope lementation 1 6 5 9 2 1 upply system to low income s area of Mekelle town by Mek elle town WSS ET-MOWIE-208765-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-01-0 2021-03-0 2021-03-3 tting for expansion of water IDA / 60070 Post Limited 65,000.00 0.00 rovement in secondary citie ations Envelope lementation 4 1 1 supply system for unserved l s ow income area by Bahir Dar WSS ET-MOWIE-208767-GO-RFB / Component 2: Sanitation an Procurement of pipes and fit d water supply services imp Single Stage - One Pending Imp 2020-12-2 2020-12-2 2021-01-2 2021-02-0 2021-03-0 2021-04-0 tings for expansion of water IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 rovement in secondary citie Envelope lementation 1 6 5 9 2 1 supply system for unserved l s ow income are for Adama to wn by Adama town WSSE ET-MOWIE-208769-GO-RFB / Component 2: Sanitation an Procurement of pipes and fit d water supply services imp Single Stage - One Pending Imp 2020-12-2 2020-12-2 2021-01-2 2021-02-1 2021-03-0 2021-05-0 tings for expansion of water IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 rovement in secondary citie Envelope lementation 2 7 6 0 3 2 supply system for unserved l s ow income area of Hawasa t own by Hawasa town WSSE ET-MOWIE-208770-GO-RFB / Procurement of pipes and fit Component 2: Sanitation an tings for expansion of water d water supply services imp Single Stage - One Pending Imp 2020-12-2 2020-12-2 2021-01-2 2021-02-1 2021-03-0 2021-05-0 IDA / 60070 Post Request for Bids Open - National 132,000.00 0.00 supply system for unserved l rovement in secondary citie Envelope lementation 2 7 6 0 3 2 ow income area of Dire Dew s a town by Dire Dewa town W SSE ET-MOWIE-208774-GO-RFQ Component 2: Sanitation an / procurement of pumps and d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-01-1 2021-02-2 2021-03-2 generators for Debre Birhan IDA / 60070 Post Limited 79,000.00 0.00 rovement in secondary citie ations Envelope lementation 0 1 3 town Water Supply Project b s y Debre Birhan town Dar To wn WSSE ET-MOWIE-220715-GO-RFB / Procurement of operational s ervice improvement equipm Component 2: Sanitation an ent's under two lots ( lot I W d water supply services imp Open - Internation Single Stage - One 2021-03-1 2021-06-3 2021-03-1 2021-09-1 2021-04-2 2021-10-1 2021-05-2 2022-01-1 2021-06-3 2022-04-2 2021-11-2 IDA / 60070 Prior Request for Bids 8,900,000.00 8,419,701.42 Signed ater Meters, lot II leak detect rovement in secondary citie al Envelope 0 0 5 0 6 2 6 7 0 9 7 ion equipment, welding mac s hines, Bulk flow meters, and test bench) for improvement of 22 town Water supply proj ects by WDC Page 5 ET-MOWIE-220716-GO-RFB / Component 2: Sanitation an procurement of pipes and fit d water supply services imp Open - Internation Single Stage - One 2021-03-1 2021-06-0 2021-03-1 2021-07-1 2021-04-2 2021-08-2 2021-05-2 2022-03-1 2021-06-3 2022-04-2 2021-11-2 tings for 22 towns water sup IDA / 60070 Prior Request for Bids 2,800,000.00 2,860,870.64 Signed rovement in secondary citie al Envelope 0 4 5 5 6 4 6 1 0 9 7 ply projects operational effic s iency improvement by WDC ET-MOWIE-221971-GO-DIR / Procurement of Water treat Component 2: Sanitation an ment Chemicals and Reagen d water supply services imp Pending Imp 2021-03-0 2021-03-0 2021-04-1 2021-06-0 IDA / 60070 Post Direct Selection Direct 110,769.00 0.00 ts for covid-19 intervention rovement in secondary citie lementation 1 6 0 9 in Bonga town to areas with s acute waster supply shortag e by WDC ET-MOWIE-221972-GO-DIR / Procurement of Aluminium s Component 2: Sanitation an ulfate for covid-19 interventi d water supply services imp Pending Imp 2021-03-0 2021-03-0 2021-04-1 2021-06-0 IDA / 60070 Post Direct Selection Direct 46,154.00 0.00 on in Gmbella towns health s rovement in secondary citie lementation 1 6 0 9 tations, hospitals, isolation c s enters and areas with acute waster supply shortage by WDC ET-MOWIE-221973-GO-UN / Procurement of Electromec Component 2: Sanitation an hanical Equipment (59 subm d water supply services imp UN Agencies (Dir 2021-03-0 2021-04-1 2021-03-0 2021-04-1 2021-04-1 2021-07-1 2021-07-1 ersible water pumps (lot I) a IDA / 60070 Post Direct 1,500,000.00 795,559.00 Signed rovement in secondary citie ect) 2 7 7 7 1 3 0 nd 11 surface pumps (lot II) s ) for 25 towns covid-19 inte rvention in acute water sup ply shortage ET-MOWIE-228528-GO-RFB- RE-BID / Procurement of 44 Component 3: Project mana Single Stage - One 2021-04-3 2021-12-2 2021-05-0 2022-03-0 2021-06-0 2022-01-2 2021-06-1 2022-03-0 2021-07-2 2022-04-1 2021-11-2 Motorcycles for 22 Towns of IDA / 60070 gement & institutional stren Post Request for Bids Open - National 150,000.00 172,624.17 Signed Envelope 0 4 5 8 4 5 9 8 4 2 1 Urban Water Supply and San gthening itation Project II (UWSSP-2) b y WDC (Re-bid) ET-MOWIE-232948-GO-DIR / Procurement of Electromech anical Equipment lot I (# 4 w Component 2: Sanitation an ater pump motors, #6 surfac d water supply services imp Pending Imp 2021-05-2 2021-05-3 2021-07-0 2021-10-0 e pumps, #7 submersible pu IDA / 60070 Post Direct Selection Direct 1,179,000.00 0.00 rovement in secondary citie lementation 5 0 4 2 mps), lot II (# 12 Generators s ) lot III control panel parts f or Mekelle and Adegarat tow ns water utilities emergency situation by WDC from UNOP S. ET-MOWIE-232953-GO-RFQ Component 2: Sanitation an / Procurement of water quali d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-06-1 2021-08-1 2021-08-2 ty chemicals and instrument IDA / 60070 Post Limited 70,000.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 5 s for Mekelle town Water su s pply service emergency situ ation by WDC ET-MOWIE-232956-GO-RFQ Component 2: Sanitation an / Procurement of riser pipes d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-05-1 2021-07-1 2021-08-1 IDA / 60070 Post Limited 78,050.00 0.00 for Mekelle town water suppl rovement in secondary citie ations Envelope lementation 7 2 1 y service emergency situatio s n by WDC ET-MOWIE-232961-GO-RFQ Component 2: Sanitation an / Procurement of Office Furni d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2021-09-1 ture (#72 chairs and #25 ta IDA / 60070 Post Limited 28,000.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 8 bles) for Adegarat town wate s r utility by Tigray Region Wa ter Bureau ET-MOWIE-232977-GO-RFQ Component 2: Sanitation an / Procurement of #2 Genera d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2021-08-0 IDA / 60070 Post Limited 1,000.00 0.00 tor batters for Mekelle town rovement in secondary citie ations Envelope lementation 6 1 5 water utility by Mekelle town s utility ET-MOWIE-232959-GO-RFQ / procurement of Office equi Component 2: Sanitation an pment lot I (#48 desk top co d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-06-2 2021-08-1 2021-09-1 mputers and #13 laptop co IDA / 60070 Post Limited 143,000.00 0.00 rovement in secondary citie ations Envelope lementation 0 5 4 mputers) and lot II (#1 fax s machine, #2 Scanners and # 2 printers) for Adegarat to wn utility by WDC. ET-MOWIE-263548-GO-RFQ / Procurement of Water sup Component 2: Sanitation an ply provision supplies (pipes, d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 32,000.00 0.00 fittings and water meters) t rovement in secondary citie ations Envelope lementation 0 4 5 o unserved and low-income s areas of Asosa town by Asos a town water utility ET-MOWIE-263550-GO-RFQ / Procurement of Water sup Component 2: Sanitation an ply provision supplies (pipes, d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 54,300.00 0.00 fittings and water meters) t rovement in secondary citie ations Envelope lementation 0 4 5 o unserved and low-income s areas of Nekemte town by N ekemte town water utility ET-MOWIE-263551-GO-RFQ / Procurement of Water sup Component 2: Sanitation an ply provision supplies (pipes, d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-2 IDA / 60070 Post Limited 50,000.00 0.00 fittings and water meters) t rovement in secondary citie ations Envelope lementation 5 9 0 o unserved and low-income s areas of shashemene town b y Shashemene town water u tility ET-MOWIE-263556-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Under Imple 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 54,300.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope mentation 0 4 5 ) to unserved and low-incom s e areas of Gonder town by G onder town water utility ET-MOWIE-263559-GO-RFB / procurement of Water suppl Component 2: Sanitation an y provision supplies (pipes a d water supply services imp Single Stage - One Pending Imp 2021-12-3 2022-01-0 2022-02-1 2022-03-1 2022-04-2 2022-07-2 IDA / 60070 Post Request for Bids Open - National 109,000.00 0.00 nd fittings and water meters rovement in secondary citie Envelope lementation 0 4 5 7 1 0 ) to unserved and low-incom s e areas of Bahir Dar town by Bahir Dar town water utility ET-MOWIE-263561-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-01-0 2022-03-0 2022-04-3 IDA / 60070 Post Limited 54,300.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope lementation 4 1 0 ) to unserved and low-incom s e areas of Dessie town by D essie town water utility ET-MOWIE-263562-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-01-0 2022-03-0 2022-04-3 IDA / 60070 Post Limited 54,300.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope lementation 4 1 0 ) to unserved and low-incom s e areas of D/Brhan town by D/Brhan town water utility ET-MOWIE-263563-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 54,300.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope lementation 0 4 5 ) to unserved and low-incom s e areas of Harar town by Har ar town water utility ET-MOWIE-263564-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 54,300.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope lementation 0 4 5 ) to unserved and low-incom s e areas of Dire Dawa town b y Dire Dawa town water utili ty ET-MOWIE-263566-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 54,300.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope lementation 0 4 5 ) to unserved and low-incom s e areas of Asella town by As ella town water utility ET-MOWIE-263567-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 50,000.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope lementation 0 4 5 ) to unserved and low-incom s e areas of Bishoftu town by Bishoftu town water utility ET-MOWIE-263570-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 54,300.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope lementation 0 4 5 ) to unserved and low-incom s e areas of A/Minch town by A/Minch town water utility ET-MOWIE-263571-GO-RFQ / procurement of Water supp Component 2: Sanitation an ly provision supplies (pipes a d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-04-1 IDA / 60070 Post Limited 50,000.00 0.00 nd fittings and water meters rovement in secondary citie ations Envelope lementation 0 4 5 ) to unserved and low-incom s e areas of Sodo town by Sod o town water utility ET-MOWIE-263583-GO-RFQ / Procurement of Office furni ture and office equipment's Component 3: Project mana Under two lots ( lot I, tables, Request for Quot Single Stage - One Pending Imp 2022-01-0 2022-03-0 2022-03-3 IDA / 60070 gement & institutional stren Post Limited 9,500.00 0.00 shelfs and chairs and lot II d ations Envelope lementation 4 1 1 gthening esk top computers, laptop c omputers and printers) for Harar town water utility PMU by Harar town Water Utility ET-MOWIE-263586-GO-RFQ / Procurement of office equip Component 2: Sanitation an ment's (#1desk top comput d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-03-1 IDA / 60070 Post Limited 1,400.00 0.00 ers, #1 laptop computers an rovement in secondary citie ations Envelope lementation 0 4 6 d #1 printers) for B/Gumuz s Region PMU by B/Gumuz Wa ter Bureau ET-MOWIE-263589-GO-RFQ / Procurement of Office furni ture and office equipment's Component 2: Sanitation an Under two lots ( lot I, tables, d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-03-3 IDA / 60070 Post Limited 13,000.00 0.00 shelfs and chairs and lot II d rovement in secondary citie ations Envelope lementation 0 4 1 esk top computers, laptop c s omputers and printers) for S idama Region Water Bureau PMU by the regional water b ureau ET-MOWIE-263679-GO-RFQ / Procurement of office equip ment and office furniture un Component 2: Sanitation an der two lots (lot I office furni d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-2 2022-02-1 2022-03-3 IDA / 60070 Post Limited 13,000.00 0.00 ture; tables, chairs and shelf rovement in secondary citie ations Envelope lementation 0 4 1 and lot II office equipment (p s rinter, desk top and lap top c omputer) for Afar Region Wa ter Bureau PMU by Afar Regi on Water Bureau ET-MOWIE-266217-GO-RFQ / Procurement of 14 sets of s Component 2: Sanitation an ubmersible water pumps for d water supply services imp Request for Quot Single Stage - One 2021-12-1 2021-12-1 2022-02-0 2022-03-1 2022-05-1 emergency response in war IDA / 60070 Post Limited 770,000.00 468,106.11 Signed rovement in secondary citie ations Envelope 5 6 9 5 0 affected project towns (#3 G s onder, #3 Bahir Dar, #2 Deb re-Birhan and #6 Semera-Lo gia) water supply projects by MoWE. ET-MOWIE-266222-GO-RFQ / procurement of 7 surface Component 2: Sanitation an water pumps for emergency d water supply services imp Request for Quot Single Stage - One 2021-12-1 2021-12-1 2022-02-0 2022-03-0 2022-05-1 IDA / 60070 Post Limited 230,000.00 198,145.81 Signed response in war affected pro rovement in secondary citie ations Envelope 5 6 9 8 0 ject towns (# 4 Gonder and s #3 Bahir Dar) water supply project by MoWE ET-MOWIE-266224-GO-RFQ / Procurement of 12 sets of g Component 2: Sanitation an enerators for emergency res d water supply services imp Request for Quot Single Stage - One 2021-12-1 2021-12-1 2022-02-0 2022-03-0 2022-05-1 ponse in war affected projec IDA / 60070 Post Limited 540,000.00 341,988.92 Signed rovement in secondary citie ations Envelope 5 6 9 8 0 t towns (#3 Gonder, #2 Bahi s r Dar, #2 D/Berahn and #5 Semera-Logia) water supply projects by MoWE Page 6 ET-MOWIE-266233-GO-RFQ / Procurement of supply and installation of #8 steel water Component 2: Sanitation an tanks for emergency respon d water supply services imp Request for Quot Single Stage - One Pending Imp 2021-12-1 2022-02-0 2022-06-0 IDA / 60070 Post Limited 125,000.00 0.00 se in war affected project to rovement in secondary citie ations Envelope lementation 5 9 9 wns (#4 Semera-Logia, #2 s Gonder, #1 Bahir-Dar and # 1 Debre-Berhan) water suppl y projects by MoWE ET-MOWIE-273916-GO-RFQ Component 2: Sanitation an / Procurement of #2 surface d water supply services imp Request for Quot Single Stage - One Under Imple 2022-02-0 2022-04-0 2022-05-1 IDA / 60070 Post Limited 35,000.00 0.00 pumps for Dessie Town Wat rovement in secondary citie ations Envelope mentation 5 2 7 er Supply Utility emergency s response by MoWE ET-MOWIE-273917-GO-RFQ Component 2: Sanitation an / Procurement of #2 Diesel d water supply services imp Request for Quot Single Stage - One Under Imple 2022-02-1 2022-03-1 2022-04-0 2022-05-2 IDA / 60070 Post Limited 86,000.00 0.00 Generators for Dessie Town rovement in secondary citie ations Envelope mentation 2 1 9 4 Water Supply Utility emerge s ncy response by MoWE ET-MOWIE-273918-GO-RFQ / procurement of Office Equi Component 2: Sanitation an pment (#42 Desk top compu d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-02-1 2022-04-0 2022-06-0 ters, #2 Lap top computers, IDA / 60070 Post Limited 73,000.00 0.00 rovement in secondary citie ations Envelope lementation 2 9 8 #26 printers, #1 Scanner an s d # 1 photo copy machine fo r Dessie town Water Utility e mergency response by MoW E ET-MOWIE-286449-GO-RFQ Component 2: Sanitation an / Supply and Installation of fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-04-0 2022-05-2 2022-08-2 ve units of 10m3 capacity w IDA / 60070 Post Limited 5,000.00 0.00 rovement in secondary citie ations Envelope lementation 6 6 4 ater tankers and five units of s small booster pumps by Gon der city Water Utility ET-MOWIE-286447-GO-RFQ Component 2: Sanitation an / Supply and Installation of fi d water supply services imp Request for Quot Pending Imp 2022-04-0 2022-06-1 2022-09-1 ve units of 10m3 capacity w IDA / 60070 Post 14,000.00 0.00 rovement in secondary citie ations lementation 6 3 1 ater tankers and five units of s small booster pumps by jigji ga town water utility ET-MOWIE-286452-GO-RFQ Component 2: Sanitation an / Supply and Installation of fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-04-0 2022-05-2 2022-08-2 ve units of 10m3 capacity w IDA / 60070 Post Limited 14,000.00 0.00 rovement in secondary citie ations Envelope lementation 6 6 4 ater tankers and five units of s small booster pumps by D/H abour town Water Utility ET-MOWIE-286446-GO-RFQ Component 2: Sanitation an / Supply and Installation of fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-04-0 2022-05-2 2022-08-2 ve units of 10m3 capacity w IDA / 60070 Post Limited 14,000.00 0.00 rovement in secondary citie ations Envelope lementation 6 6 4 ater tankers and five units of s small booster pumps by Har ari city Water utility ET-MOWIE-291166-GO-RFQ / Supply and installation of 1 Component 2: Sanitation an 2 units of 10m3 capacity wat d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-05-0 2022-06-2 2022-09-1 er tankers and 12 units of s IDA / 60070 Post Limited 37,215.00 0.00 rovement in secondary citie ations Envelope lementation 1 0 8 mall booster pumps for publi s c toilets and 12 units of 3m3 Roto water tanker for comm unal toilets by Bahirdar city water utility ET-MOWIE-291192-GO-RFQ Component 2: Sanitation an / Supply and installation of 5 d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-05-0 2022-06-2 2022-09-1 units of 10m3 capacity wate IDA / 60070 Post Limited 14,358.00 0.00 rovement in secondary citie ations Envelope lementation 1 0 8 r tankers and 5 units of smal s l booster pumps for public to ilets by Assela city water util ity ET-MOWIE-291160-GO-RFQ / Supply and Installation of 1 Component 2: Sanitation an 1 units of 10m3 capacity wat d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-08-2 2022-10-1 2023-01-1 IDA / 60070 Post Limited 28,715.00 0.00 er tanker and 11 units of sm rovement in secondary citie ations Envelope lementation 4 3 1 all booster pumps for public s toilets by Shashemane city water utility ET-MOWIE-314136-GO-RFQ Component 2: Sanitation an / Supply and installation of 8 d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-1 units of 10m3 capacity wate IDA / 60070 Post Limited 10,900.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 8 r tankers and 8 units of smal s l booster pump for 8 public t oilets for Gonder town ET-MOWIE-314140-GO-RFQ / Supply and installation of 1 Component 2: Sanitation an 1 units of 10m3 capacity wat d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-1 er tankers and 11 units of s IDA / 60070 Post Limited 21,150.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 8 mall booster pump for 11 pu s blic toilets and 35 units of 2 m3 capacity water tanker for 35 Communal toilets for Dire Dewa town ET-MOWIE-314147-GO-RFQ Component 2: Sanitation an / Supply and installation of 8 d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-09-2 2022-11-2 2023-01-1 units of 10m3 capacity wate IDA / 60070 Post Limited 8,800.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 9 r tankers and 8 units of smal s l booster pump for 8 public t oilets for Asosa town ET-MOWIE-314150-GO-RFQ Component 2: Sanitation an / Supply and installation of 7 d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-09-2 2022-11-0 2023-01-0 units of 10m3 capacity wate IDA / 60070 Post Limited 7,600.00 0.00 rovement in secondary citie ations Envelope lementation 5 6 5 r tankers and 7 units of smal s l booster pump for 7 public t oilets for Bishftu town ET-MOWIE-314154-GO-RFQ Component 2: Sanitation an / Supply and installation of 5 d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-11-2 2023-01-2 units of 10m3 capacity wate IDA / 60070 Post Limited 5,500.00 0.00 rovement in secondary citie ations Envelope lementation 5 2 1 r tankers and 5 units of smal s l booster pump for 5 public t oilets for Dessie town ET-MOWIE-314166-GO-RFQ Component 2: Sanitation an / Supply and installation of 5 d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-1 2023-02-1 units of 10m3 capacity wate IDA / 60070 Post Limited 29,000.00 0.00 rovement in secondary citie ations Envelope lementation 5 3 1 r tankers and 5 units of boos s ter pumps for 5 public toilets for Assela town ET-MOWIE-314171-GO-RFQ Component 2: Sanitation an / Supply and installation of 5 d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-3 2022-12-2 2023-02-2 units of 10m3 capacity wate IDA / 60070 Post Limited 29,000.00 0.00 rovement in secondary citie ations Envelope lementation 0 5 3 r tankers and 5 units of boos s ter pumps for 5 public toilets for Assela town ET-MOWIE-314173-GO-RFB / Component 2: Sanitation an Single Stage - One Pending Imp 2022-12-3 2023-01-0 2023-02-0 2023-02-2 2023-03-3 2023-07-2 Procurement of IT equipmen IDA / 60070 d water supply services imp Post Request for Bids Open - National 720,000.00 0.00 Envelope lementation 0 4 3 4 1 9 t for implementation MIS in rovement in secondary citie 22 towns s ET-MOWIE-316023-GO-RFB / Procurement of Electromech Component 2: Sanitation an anical equipment (6 pumps) d water supply services imp Single Stage - One Pending Imp 2022-10-2 2022-10-2 2022-11-2 2022-12-2 2023-01-2 2023-04-2 IDA / 60070 Post Request for Bids Open - National 346,000.00 0.00 for the improvement of exist rovement in secondary citie Envelope lementation 0 5 4 4 8 8 ing water system for the dro s ught affected 3 towns throu gh emergency response ET-MOWIE-316090-GO-RFB / Procurement of Electromech Component 2: Sanitation an anical equipment (4 pumps d water supply services imp Single Stage - One Pending Imp 2022-10-1 2022-10-1 2022-11-1 2022-11-2 2023-01-0 2023-04-0 and 4 generators) for the im IDA / 60070 Post Request for Bids Open - National 193,000.00 0.00 rovement in secondary citie Envelope lementation 0 5 4 9 3 3 provement of existing water s system for the drought affec ted 2 towns (Godey and Kab ridahar) through emergency response ET-MOWIE-316097-GO-RFB / Procurement of Electromech anical equipment (#34 Sub Component 2: Sanitation an mersible pumps, #4 Surface d water supply services imp Open - Internation Single Stage - One Pending Imp 2022-10-2 2022-10-2 2022-12-0 2023-01-0 2023-02-0 2023-07-0 IDA / 60070 Prior Request for Bids 2,600,000.00 0.00 pumps and #38 Generators) rovement in secondary citie al Envelope lementation 0 5 6 5 9 9 for the improvement of exist s ing water system for the dro ught affected 23 towns thro ugh emergency response w ith different lots ET-MOWIE-316106-GO-RFB / Procurement of Electromech anical equipment (#34 Sub Component 2: Sanitation an mersible pumps, #4 Surface d water supply services imp Open - Internation Single Stage - One Under Imple 2022-11-1 2022-11-1 2022-11-1 2022-11-2 2022-12-2 2023-01-2 2023-03-0 2023-07-3 IDA / 60070 Prior Request for Bids 2,600,000.00 0.00 pumps and #38 Generators) rovement in secondary citie al Envelope mentation 0 2 5 3 7 6 2 0 for the improvement of exist s ing water system for the dro ught affected 23 towns thro ugh emergency response w ith different lots ET-MOWIE-316107-GO-RFB / Procurement of Electromech Component 2: Sanitation an anical equipment (Raw wate d water supply services imp Single Stage - One 2022-10-2 2022-09-0 2022-10-2 2022-11-2 2022-12-2 2023-01-2 2023-04-2 IDA / 60070 Post Request for Bids Open - National 270,000.00 0.00 Canceled r and treatment plant 2 sub rovement in secondary citie Envelope 0 4 5 4 4 8 8 mersible pump for the impro s vement of existing water su pply system ET-MOWIE-316112-GO-RFB / Procurement of HDPE PN 16 Component 2: Sanitation an OD 250mm L = 3000m and d water supply services imp Single Stage - One Pending Imp 2022-10-2 2022-10-2 2022-11-2 2022-12-2 2023-01-2 2023-05-2 IDA / 60070 Post Request for Bids Open - National 277,000.00 0.00 HDPE fittings for the improv rovement in secondary citie Envelope lementation 0 5 4 4 8 8 ement of existing water sup s ply system of Debrebirhan t own ET-MOWIE-316113-GO-RFQ / Procurement of heavy-duty Component 2: Sanitation an riser pipes and fittings GS di d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-0 ameter 100mm for the newl IDA / 60070 Post Limited 24,000.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 3 y drilled two bore holes and s other accessories for the im provement of the existing w ater supply system Debre Be rhan town ET-MOWIE-316117-GO-RFB / Procurement of Electromech Component 2: Sanitation an anical equipment (5 Submer d water supply services imp Single Stage - One Pending Imp 2022-10-2 2022-10-2 2022-11-2 2022-12-0 2023-01-1 2023-04-1 IDA / 60070 Post Request for Bids Open - National 240,000.00 0.00 sible Water Pumps with acce rovement in secondary citie Envelope lementation 0 5 4 9 3 3 ssories) for the improvement s of existing water supply syst em for Dire Dewa town ET-MOWIE-316118-GO-RFB / Procurement of Stainless ste Component 2: Sanitation an el 6'' riser pipes with Access d water supply services imp Single Stage - One Pending Imp 2022-10-2 2022-10-2 2022-11-2 2022-12-0 2023-01-1 2023-05-1 IDA / 60070 Post Request for Bids Open - National 350,000.00 0.00 ories (350 pcs each 6mt len rovement in secondary citie Envelope lementation 0 5 4 9 3 3 gth) for the improvement of s the existing water supply sy stem of Dire Dewa town ET-MOWIE-316119-GO-RFB / Procurement of Electromech Component 2: Sanitation an anical equipment (3 Submer d water supply services imp Single Stage - One Pending Imp 2022-10-1 2022-10-1 2022-11-1 2022-11-2 2023-01-0 2023-04-0 IDA / 60070 Post Request for Bids Open - National 385,000.00 0.00 sible Pump and 3 Surface Pu rovement in secondary citie Envelope lementation 0 5 4 9 3 3 mp) for the improvement of s the existing water supply sy stem of Harar town ET-MOWIE-316121-GO-RFB / Procurement of PIPES and FI TTINGS and HYDRAULIC ACC Component 2: Sanitation an ESSORIES Riser stainless ste d water supply services imp Single Stage - One Pending Imp 2022-10-2 2022-10-2 2022-11-2 2022-12-0 2023-01-1 2023-03-1 el pipe for 4 BH’s in Hasselis IDA / 60070 Post Request for Bids Open - National 145,000.00 0.00 rovement in secondary citie Envelope lementation 0 5 4 9 3 4 so and Hulahulul Boreholes ( s replacement of damaged ris er pipe) for the improvemen t of the existing water suppl y system of Harar town ET-MOWIE-316122-GO-RFB / Procurement of Pipes and fit Component 2: Sanitation an tings for about 950-meter ris d water supply services imp Single Stage - One Pending Imp 2022-10-2 2022-10-2 2022-11-2 2022-12-0 2023-01-1 2023-03-1 er main with full accessary a IDA / 60070 Post Request for Bids Open - National 154,000.00 0.00 rovement in secondary citie Envelope lementation 0 5 4 9 3 4 nd 450-meter riser main insi s de the well with full accessar y to increase Water Supply e fficiency of Dessie Town ET-MOWIE-316123-GO-RFB / procurement of supply and I Component 2: Sanitation an nstallation of #2 Surface Pu d water supply services imp Single Stage - One Pending Imp 2022-10-2 2022-10-2 2022-11-2 2022-12-0 2023-01-1 2023-04-1 IDA / 60070 Post Request for Bids Open - National 231,000.00 0.00 mps & #1 Submersible Pum rovement in secondary citie Envelope lementation 0 5 4 9 3 3 p with full accessary to impr s ove the existing water suppl y system of Dessie Town Page 7 ET-MOWIE-316124-GO-RFB / Component 2: Sanitation an Procurement of 2 surface pu d water supply services imp Single Stage - One Pending Imp 2022-09-3 2022-10-0 2022-11-0 2022-11-1 2022-12-2 2023-03-2 mp with accessories to impr IDA / 60070 Post Request for Bids Open - National 231,000.00 0.00 rovement in secondary citie Envelope lementation 0 5 4 9 4 4 ove the existing water suppl s y system of Arbaminch town ET-MOWIE-316125-GO-RFQ Component 2: Sanitation an / procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-0 2022-11-3 2023-01-1 IDA / 60070 Post Limited 77,000.00 0.00 ttings for unserved low-inco rovement in secondary citie ations Envelope lementation 5 0 4 me areas water provision of s Harar town ET-MOWIE-316126-GO-RFQ Component 2: Sanitation an / procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-11-2 2023-01-1 2023-03-1 IDA / 60070 Post Limited 28,000.00 0.00 ttings for unserved low-inco rovement in secondary citie ations Envelope lementation 0 5 6 me areas of Asosa to town s ET-MOWIE-316127-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-0 IDA / 60070 Post Limited 77,000.00 0.00 tting for Water Supply provis rovement in secondary citie ations Envelope lementation 5 0 3 ion for unserved low-income s areas Dire Dewa town ET-MOWIE-316128-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-0 IDA / 60070 Post Limited 58,000.00 0.00 tting for Water Supply provis rovement in secondary citie ations Envelope lementation 5 0 3 ion for unserved low-income s areas Bahir Dar town ET-MOWIE-316130-GO-RFQ Component 2: Sanitation an / procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-06-1 ttings for provision of water IDA / 60070 Post Limited 48,000.00 0.00 rovement in secondary citie ations Envelope lementation 5 0 8 supply to unserved low-inco s me area of Semea Logia tow n ET-MOWIE-316131-GO-RFQ Component 2: Sanitation an / procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-0 IDA / 60070 Post Limited 60,000.00 0.00 ttings for Water Supply provi rovement in secondary citie ations Envelope lementation 5 0 3 sion for unserved low-incom s e areas of Adama town ET-MOWIE-316154-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-11-2 2023-01-1 2023-03-0 IDA / 60070 Post Limited 68,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 0 5 1 supply to low-income area of s Gonder town ET-MOWIE-316155-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-11-2 2023-01-1 2023-03-0 IDA / 60070 Post Limited 68,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 0 5 1 supply to low-income area of s Bishoftu town ET-MOWIE-316156-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-11-2 2023-01-1 2023-03-1 IDA / 60070 Post Limited 96,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 0 5 6 supply to low-income area of s Wolayita Sodo town ET-MOWIE-316157-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-0 IDA / 60070 Post Limited 48,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 5 0 3 supply to low-income area of s Gambella town ET-MOWIE-316158-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-11-2 2023-01-1 2023-03-1 IDA / 60070 Post Limited 96,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 0 5 6 supply to low-income area of s Hawasa town ET-MOWIE-316159-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-1 IDA / 60070 Post Limited 69,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 5 0 8 supply to low-income area of s Arba Minch town ET-MOWIE-316160-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-1 IDA / 60070 Post Limited 96,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 5 0 8 supply to low-income area of s Shashamene town ET-MOWIE-316161-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-1 IDA / 60070 Post Limited 67,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 5 0 8 supply to low-income area of s Debre Berhan town ET-MOWIE-316163-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Single Stage - One Pending Imp 2022-11-1 2022-11-2 2022-12-2 2023-01-0 2023-02-0 2023-06-0 IDA / 60070 Post Request for Bids Open - National 104,000.00 0.00 ttings for provision of water rovement in secondary citie Envelope lementation 5 0 0 4 8 8 supply to low-income area of s Jimma town ET-MOWIE-316164-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-1 IDA / 60070 Post Limited 58,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 5 0 8 supply to low-income area of s Dessie town ET-MOWIE-316165-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-1 IDA / 60070 Post Limited 58,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 5 0 8 supply to low-income area of s Nekemte town ET-MOWIE-316166-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-0 IDA / 60070 Post Limited 39,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 5 0 3 supply to low-income area of s Jigjiga town ET-MOWIE-316167-GO-RFQ Component 2: Sanitation an / Procurement of pipes and fi d water supply services imp Request for Quot Single Stage - One Pending Imp 2022-10-2 2022-12-2 2023-02-0 IDA / 60070 Post Limited 48,000.00 0.00 ttings for provision of water rovement in secondary citie ations Envelope lementation 5 0 3 supply to low-income area of s Assela town ET-MOWIE-325423-GO-RFB / Component 2: Sanitation an Single Stage - One Pending Imp 2022-11-3 2022-12-0 2023-01-0 2023-02-0 2023-03-1 2023-09-0 Procurement of Water Meter IDA / 60070 d water supply services imp Post Request for Bids Open - National 601,000.00 0.00 Envelope lementation 0 5 4 3 0 6 12500 for Diredawa Utility rovement in secondary citie s ET-MOWIE-332114-GO-RFQ Component 3: Project mana / Procurement of office equip Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-03-0 2023-04-3 IDA / 60070 gement & institutional stren Post Limited 37,500.00 0.00 ment (13 laptop,1 desktop c ations Envelope lementation 3 1 0 gthening omputer, 2LCD Projectors an d 1 scanner ) for MOWE ET-MOWIE-332138-GO-RFQ Component 3: Project mana / Procurement of office equip Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 8,654.00 0.00 ment (4 Laptops and 1 print ations Envelope lementation 1 6 7 gthening er) by Amhara region WB ET-MOWIE-332141-GO-RFQ Component 3: Project mana / procurement of office eq Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 8,654.00 0.00 uipment (2 Laptops, 2 print ations Envelope lementation 1 6 7 gthening ers, 1copier and 1 scanner) by SNNP Region WB ET-MOWIE-332145-GO-RFQ Component 3: Project mana / procurement of office eq Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 11,538.00 0.00 uipment (4 Laptops,1printer ations Envelope lementation 1 7 8 gthening ,1 copier, and 1 scanner) by Somali Region WB ET-MOWIE-332200-GO-RFQ Component 3: Project mana / procurement of office equi Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 11,538.00 0.00 pment (4 laptops, 1 printer, ations Envelope lementation 1 7 8 gthening 1 copier and 1 scanner) by H arrar utility ET-MOWIE-332202-GO-RFQ Component 3: Project mana / procurement of office equi Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 2,885.00 0.00 pment (1 laptop and 1 printe ations Envelope lementation 1 7 8 gthening r) by Diredawa utility ET-MOWIE-332203-GO-RFQ Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 / procurement of office equi IDA / 60070 gement & institutional stren Post Limited 2,885.00 0.00 ations Envelope lementation 1 7 8 pment(1 laptop and 1 printe gthening r) by Assosa utility ET-MOWIE-332205-GO-RFQ Component 3: Project mana / procurement of office equi Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 2,885.00 0.00 pment (1 laptop and 1 print ations Envelope lementation 1 7 8 gthening er) by Gambella utility ET-MOWIE-332207-GO-RFQ Component 3: Project mana / procurement of office equi Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 2,885.00 0.00 pment (1 laptop and 1 printe ations Envelope lementation 1 7 8 gthening r) by S/Logia utility ET-MOWIE-332209-GO-RFQ Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 / procurement of office furn IDA / 60070 gement & institutional stren Post Limited 17,500.00 0.00 ations Envelope lementation 1 6 7 iture (15 Tables and 15 chair gthening s) by MOWE ET-MOWIE-332239-GO-RFQ Component 3: Project mana / procurement of office furnit Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 4,038.00 0.00 ure (6 tables and 6 chairs) b ations Envelope lementation 1 6 7 gthening y Oromia region WB ET-MOWIE-332300-GO-RFQ Component 3: Project mana / procurement of office furnit Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 4,038.00 0.00 ure (6 tables and 6 chairs ) ations Envelope lementation 1 6 7 gthening by Amhara region WB ET-MOWIE-332303-GO-RFQ Component 3: Project mana / procurement of office furni Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 4,038.00 0.00 ture (7 tables and 7 chairs) ations Envelope lementation 1 6 7 gthening by SNNP Region WB ET-MOWIE-332307-GO-RFQ Component 3: Project mana / procurement of office furnit Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 5,385.00 0.00 ure ( 8 tables and 8 chairs ) ations Envelope lementation 1 6 7 gthening by the Somali region WB. ET-MOWIE-332403-GO-RFQ Component 3: Project mana / procurement of office furni Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 1,346.00 0.00 ture ( 2 tables and 2 chairs ations Envelope lementation 1 6 7 gthening ) by the Hawassa utility ET-MOWIE-332410-GO-RFQ Component 3: Project mana / procurement of office furni Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 5,385.00 0.00 ture ( 8 tables and 8 chairs ations Envelope lementation 1 6 7 gthening ) by the Harar utility ET-MOWIE-332413-GO-RFQ Component 3: Project mana / procurement of office furni Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 1,346.00 0.00 ture ( 2 tables and 2 chairs) ations Envelope lementation 1 6 7 gthening by the Diredewa utility ET-MOWIE-332414-GO-RFQ Component 3: Project mana / procurement of office furni Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 1,346.00 0.00 ture ( 2 tables and 2 chairs ations Envelope lementation 1 6 7 gthening ) by the Assosa utility ET-MOWIE-332416-GO-RFQ Component 3: Project mana / procurement of office fur Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 1,346.00 0.00 niture f( 2 tables and 2 chair ations Envelope lementation 1 6 7 gthening s) by the Gambella utility ET-MOWIE-332419-GO-RFQ Component 3: Project mana / procurement of office fur Request for Quot Single Stage - One Pending Imp 2023-01-0 2023-02-2 2023-04-2 IDA / 60070 gement & institutional stren Post Limited 1,346.00 0.00 niture ( 2 tables and 2 chairs ations Envelope lementation 1 6 7 gthening ) by the S/Logia utility ET-MOWIE-334478-GO-RFQ Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2023-01-1 2023-03-1 2023-05-1 / procurement of 18 tables IDA / 60070 gement & institutional stren Post Limited 12,114.00 0.00 ations Envelope lementation 7 4 3 and 18 chairs by Oromia reg gthening ion WB ET-MOWIE-334480-GO-RFQ Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2023-01-1 2023-03-1 2023-05-1 / procurement of 14 Tables IDA / 60070 gement & institutional stren Post Limited 9,422.00 0.00 ations Envelope lementation 7 4 3 and 14 Chairs by Amhara re gthening gion WB Page 8 ET-MOWIE-334481-GO-RFQ Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2023-01-1 2023-03-1 2023-05-1 / procurement of 11 Chairs IDA / 60070 gement & institutional stren Post Limited 4,038.00 0.00 ations Envelope lementation 7 4 3 and 11 Tables by SNNP Regi gthening on WB. ET-MOWIE-334483-GO-RFQ Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2023-01-1 2023-03-1 2023-05-1 / procurement of 2 tables an IDA / 60070 gement & institutional stren Post Limited 1,346.00 0.00 ations Envelope lementation 7 4 3 d 2 chairs by Hawassa Utilit gthening y ET-MOWIE-334484-GO-RFQ Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2023-01-1 2023-03-1 2023-05-1 / procurement of 10 Laptop IDA / 60070 gement & institutional stren Post Limited 25,964.00 0.00 ations Envelope lementation 7 4 3 s and 7 printers by Oromia gthening Region WB ET-MOWIE-334485-GO-RFQ Component 3: Project mana Request for Quot Single Stage - One Pending Imp 2023-01-1 2023-03-1 2023-05-1 / procurement of 8 Laptops IDA / 60070 gement & institutional stren Post Limited 20,194.00 0.00 ations Envelope lementation 7 4 3 and 5 printers by Amhara re gthening gion WB ET-MOWIE-334487-GO-RFQ Component 3: Project mana / procurement of 4 Laptops Request for Quot Single Stage - One Pending Imp 2023-01-1 2023-03-1 2023-05-1 IDA / 60070 gement & institutional stren Post Limited 14,424.00 0.00 ,4 printers, 1copier and 1s ations Envelope lementation 7 4 3 gthening canner by the SNNP Region WB ET-MOWIE-339464-GO-RFB / Procurement of Electromech Component 2: Sanitation an anical equipment (Raw wate d water supply services imp Single Stage - One Pending Imp 2023-01-3 2023-02-0 2023-03-0 2023-04-0 2023-05-1 2023-08-0 r and treatment IDA / 60070 Post Request for Bids Open - National 270,000.00 0.00 rovement in secondary citie Envelope lementation 1 5 7 6 1 9 plant 2 submersible pump fo s r the improvement of existin g water supply system NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-174570-NC-RFQ / Component 2: Sanitation an Procurement of maintenanc d water supply services imp Request for Quot Single Stage - One Pending Imp 2020-05-3 2020-07-0 2020-07-1 IDA / 60070 Post Limited 30,769.00 0.00 e service of Generators and rovement in secondary citie ations Envelope lementation 1 5 9 transformer for shire town b s y shire town Water Utility CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technica Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued l Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43244-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-07-1 2018-05-1 2018-07-0 2018-03-0 2018-07-2 2018-12-3 2018-09-2 2018-01-1 2018-11-0 2019-04-2 2018-12-2 2019-07-0 2019-09-1 IDA / 60070 Post Open - National 250,000.00 214,456.00 Signed 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 7 1 1 3 9 1 7 5 8 7 0 4 6 Design of Waste Water Mana s gement System for Harari to wn by Harari Town water su pply and sewerage service ET-MOWIE-50559-CS-QCBS / Consultancy Service for Esta Component 2: Sanitation an blishment of Urban Water Su d water supply services imp Quality And Cost- Under Implemen 2018-07-2 2018-09-0 2018-09-3 2018-10-3 2018-12-0 2019-01-0 2020-01-0 IDA / 60070 Post Open - National 200,000.00 0.00 2018-06-20 pply and Waste Water Mana rovement in secondary citie Based Selection tation 0 2 0 0 4 8 8 gement Service Regulation i s n Ethiopia by Ministry of Wat er Irrigation and Electricity ET-MOWIE-43193-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- Open - Internation 2018-08-1 2018-07-1 2018-10-0 2018-08-2 2019-06-2 2018-09-2 2019-09-0 2018-10-2 2020-02-1 2018-11-2 2020-09-0 2018-12-3 2020-10-0 2019-09-2 IDA / 60070 Prior 600,000.00 995,043.88 Signed 2018-06-20 Feasibility Study and Detail rovement in secondary citie Based Selection al 0 1 3 4 7 1 2 1 2 5 3 0 1 6 Design of Waste Water Mana s gement System for Jimma a nd Nekemte Towns by Oromi a Water Mineral and Energy Bureau ET-MOWIE-43212-CS-QCBS / Consultancy Service for Dev Component 2: Sanitation an elopment of an Integrated Ci d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 ty Wide Sanitation plan and IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Feasibility Study and Detail s Design for Asella Town WSS S by Asella Town water supp ly and sewerage service ET-MOWIE-43209-CS-QCBS / Consultancy Service for Dev Component 2: Sanitation an elopment of an Integrated Ci d water supply services imp Quality And Cost- Under Implemen 2018-04-1 2018-05-3 2018-06-2 2018-08-2 2018-10-0 2018-11-1 2019-08-1 ty Wide Sanitation plan and IDA / 60070 Post Open - National 500,000.00 0.00 2018-03-20 rovement in secondary citie Based Selection tation 0 1 8 7 8 9 6 Feasibility Study and Detail s Design for Sodo and Arbami nch Towns by SNNPR Water Bureau ET-MOWIE-43208-CS-QCBS / Consultancy Service for Dev Component 2: Sanitation an elopment of an Integrated Ci d water supply services imp Quality And Cost- 2018-04-1 2018-05-3 2018-06-2 2018-08-2 2018-10-0 2018-11-1 2019-08-0 ty Wide Sanitation plan and IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-03-20 rovement in secondary citie Based Selection 0 1 8 7 1 2 9 Feasibility Study and Detail s Design for Sodo Town WSSS by Sodo Town water supply and sewerage service ET-MOWIE-43214-CS-QCBS / Consultancy service for Dev Component 2: Sanitation an elopment of an integrated Ci d water supply services imp Quality And Cost- 2018-08-0 2018-05-1 2018-07-0 2018-08-0 2018-07-2 2019-03-0 2018-09-2 2019-06-0 2018-11-0 2019-09-1 2018-12-2 2019-09-2 2019-09-1 ty Wide Sanitation plan and IDA / 60070 Post Open - National 250,000.00 217,285.63 Signed 2018-04-20 rovement in secondary citie Based Selection 1 1 1 1 9 9 7 3 8 8 0 7 6 Feasibility Study and Detail s Design of Waste Water Mana gement System for Adegrat town by Tigray Region Water Bureau ET-MOWIE-43206-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Dessie to wn by Dessie Town water su pply and sewerage service ET-MOWIE-43200-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Gambell a town by Gambella Town w ater supply and sewerage se rvice ET-MOWIE-43198-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-06-2 2018-07-2 2018-09-2 2018-11-0 2018-12-1 2019-09-0 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 4 2 0 1 3 9 Design of Waste Water Mana s gement System for Nekemet town by Nekemet Town wat er supply and sewerage serv ice ET-MOWIE-43237-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Jigjiga to wn by Jigijiga Town water su pply and sewerage service ET-MOWIE-43239-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Shashem ene town by Shashemene To wn water supply and sewera ge service ET-MOWIE-43216-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Semera t own by Semera Town water supply and sewerage service ET-MOWIE-43241-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Bishoftu town by Bishoftu Town wate r supply and sewerage servi ce ET-MOWIE-43059-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Deghabu r town by Deghabur Town w ater supply and sewerage se rvice ET-MOWIE-43248-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Arbamin ch town by Arbaminch Town water supply and sewerage service ET-MOWIE-43203-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 Feasibility Study and Detail rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Design of Waste Water Mana s gement System for Gonder t own by Gonder Town water supply and sewerage service ET-MOWIE-65731-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- Open - Internation 2018-08-0 2018-07-1 2018-09-0 2018-08-2 2019-01-1 2018-09-2 2019-03-0 2018-10-2 2019-08-3 2018-11-2 2019-12-0 2018-12-3 2019-12-1 2019-09-2 IDA / 60080 Prior 900,000.00 1,246,690.99 Signed 2018-06-20 Feasibility Study and Detail rovement in secondary citie Based Selection al 6 1 4 4 4 1 5 1 0 5 8 0 8 6 Design of Waste Water Mana s gement System for Gambell a, Semera and Asosa Towns by Ministry of Water Irrigatio n and Electricity ET-MOWIE-65735-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- Open - Internation Under Implemen 2018-08-1 2018-07-1 2018-10-0 2018-09-0 2019-08-1 2018-09-2 2019-11-1 2018-10-2 2020-02-2 2018-12-0 2020-09-2 2019-01-0 2019-10-0 Feasibility Study and Detail IDA / 60080 Prior 900,000.00 0.00 2018-06-28 rovement in secondary citie Based Selection al tation 0 9 5 1 4 9 2 9 6 3 2 7 4 Design of Waste Water Mana s gement System for Asella, S hashemene and Bishoftu to wns by Oromia Water, Mine ral and Energy Bureau ET-MOWIE-65737-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- Open - Internation 2018-08-1 2018-07-1 2018-10-1 2018-09-0 2019-06-2 2018-09-2 2019-09-1 2018-10-2 2019-12-0 2018-12-0 2020-06-0 2019-01-0 2020-08-2 2019-10-0 IDA / 60080 Prior 900,000.00 1,163,667.22 Signed 2018-06-28 Feasibility Study and Detail rovement in secondary citie Based Selection al 0 9 4 1 7 9 7 9 8 3 2 7 1 4 Design of Waste Water Mana s gement System for Gonder, Dessie and Debreberhan tow ns by Amehara Water Burea u Page 9 ET-MOWIE-65751-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- Open - Internation Under Implemen 2018-08-1 2018-07-1 2018-10-1 2018-08-2 2020-02-1 2018-09-2 2020-05-2 2018-10-2 2020-12-1 2018-11-2 2021-02-2 2018-12-3 2019-09-2 IDA / 60080 Prior 600,000.00 0.00 2018-06-20 Feasibility Study and Detail rovement in secondary citie Based Selection al tation 0 1 7 4 6 1 1 1 6 5 2 0 6 Design of Waste Water Mana s gement System for Sodo an d Arbaminch Towns by SNNP R Water Bureau ET-MOWIE-65753-CS-QCBS / Consultancy service for Dev elopment of an integrated Ci Component 2: Sanitation an ty Wide Sanitation plan and d water supply services imp Quality And Cost- Open - Internation 2018-08-0 2018-07-1 2018-10-0 2018-08-3 2019-07-1 2018-09-2 2019-09-0 2018-10-2 2019-10-3 2018-12-0 2020-05-3 2019-01-0 2020-06-3 2019-10-0 IDA / 60080 Prior 600,000.00 1,279,278.48 Signed 2018-06-26 Feasibility Study and Detail rovement in secondary citie Based Selection al 6 7 5 0 6 7 5 7 1 1 0 5 0 2 Design of Waste Water Mana s gement System for Jijiga and Deghabur Towns by Somali Region Water Resource Dev elopment Bureau ET-MOWIE-43213-CS-QCBS / Consultancy Service for Dev Component 2: Sanitation an elopment of an Integrated Ci d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-09-2 2018-11-0 2018-12-2 2019-09-1 ty Wide Sanitation plan and IDA / 60070 Post Open - National 250,000.00 0.00 Canceled 2018-04-20 rovement in secondary citie Based Selection 1 1 9 7 8 0 6 Feasibility Study and Detail s Design for Aossosa Town WS SS by Assosa Town water su pply and sewerage service ET-MOWIE-55840-CS-QCBS / Component 2: Sanitation an Procurement of re-innovatio d water supply services imp Quality And Cost- Pending Impleme 2018-07-1 2018-08-2 2018-09-2 2018-10-2 2018-11-2 2018-12-3 2019-12-3 n of Enterprise level Informa IDA / 60070 Post Open - National 250,000.00 0.00 2018-06-20 rovement in secondary citie Based Selection ntation 1 4 1 1 5 0 0 tion Management System by s Mekele Town Water Supply a nd Sewerage Service ET-MOWIE-43218-CS-QCBS / Consultancy service for Dev Component 2: Sanitation an elopment of an integrated T d water supply services imp Quality And Cost- 2018-04-1 2018-05-3 2018-06-2 2018-08-2 2018-10-0 2018-11-1 2019-08-1 IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 own Sanitation plan for Dire rovement in secondary citie Based Selection 0 1 8 7 8 9 6 Dewa town by Dire Dawa To s wn water supply and sewera ge service ET-MOWIE-43231-CS-QCBS / Consultancy service for Dev Component 2: Sanitation an elopment of an integrated T d water supply services imp Quality And Cost- 2018-04-1 2018-05-3 2018-06-2 2018-08-2 2018-10-0 2018-11-1 2019-08-0 IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 own Sanitation plan for Ada rovement in secondary citie Based Selection 0 1 8 7 1 2 9 ma town by Adama Town wa s ter supply and sewerage ser vice ET-MOWIE-43234-CS-QCBS / Consultancy service for Dev Component 2: Sanitation an elopment of an integrated T d water supply services imp Quality And Cost- 2018-04-1 2018-05-3 2018-06-2 2018-08-2 2018-10-0 2018-11-1 2019-08-0 IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 own Sanitation plan for Haw rovement in secondary citie Based Selection 0 1 8 7 1 2 9 assa town by Hawassa Town s water supply and sewerage service ET-MOWIE-43227-CS-QCBS / Consultancy service for Dev Component 2: Sanitation an elopment of an integrated T d water supply services imp Quality And Cost- 2018-04-1 2018-05-3 2018-06-2 2018-08-2 2018-10-0 2018-11-1 2019-08-1 IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-03-20 own Sanitation plan for Mek rovement in secondary citie Based Selection 0 1 8 7 8 9 6 elle town by Mekelle Town w s ater supply and sewerage se rvice ET-MOWIE-43222-CS-QCBS / Consultancy service for Dev Component 2: Sanitation an elopment of an integrated Ci d water supply services imp Quality And Cost- 2018-05-1 2018-07-0 2018-07-2 2018-08-2 2018-10-0 2018-11-2 2019-08-1 IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2018-04-20 ty Wide Sanitation plan for rovement in secondary citie Based Selection 1 1 9 8 9 0 7 Bahir Dar town by Bahir Dar s Town water supply and sewe rage service ET-MOWIE-77764-CS-QCBS / consultancy service for prep Component 2: Sanitation an aration of business plan for Ji d water supply services imp Quality And Cost- 2018-10-1 2018-12-0 2018-12-2 2019-01-2 2019-03-0 2019-04-0 2019-08-0 IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 ma, Nekemte and Bishoftu T rovement in secondary citie Based Selection 8 1 9 8 4 8 6 owns Water Supply project b s y Oromia Water, Mineral and Energy Bureau ET-MOWIE-75929-CS-QCBS / Selection and employment o Component 2: Sanitation an f consultant for situational a d water supply services imp Quality And Cost- 2018-10-1 2018-12-0 2018-12-2 2019-01-2 2019-03-0 2019-04-0 2019-08-0 ssessment and developmen IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 rovement in secondary citie Based Selection 8 1 9 8 4 8 6 t of NRW reduction and man s agement interventions for Ji gjiga and Deghabur towns b y Somali Region Water Bure au ET-MOWIE-75924-CS-QCBS / Selection and employment o Component 2: Sanitation an f consultant for situational a d water supply services imp Quality And Cost- 2018-10-1 2018-12-0 2018-12-2 2019-01-2 2019-03-0 2019-04-0 2019-10-0 ssessment and developmen IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 rovement in secondary citie Based Selection 8 1 9 8 4 8 5 t of NRW reduction and man s agement interventions for B ahirdar, D/berhan and Dessi e towns by Amhara Water B ureau ET-MOWIE-77752-CS-QCBS / Consultancy service for prep Component 2: Sanitation an aration of business plan for d water supply services imp Quality And Cost- 2018-10-1 2018-12-0 2018-12-2 2019-01-2 2019-03-0 2019-04-0 2019-08-0 IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 Mekele and Adegrat towns rovement in secondary citie Based Selection 8 1 9 8 4 8 6 Water supply and Sewerage s authorities by Tigray Region Water Bureau ET-MOWIE-75935-CS-QCBS / Selection and employment o Component 2: Sanitation an f consultant for situational a d water supply services imp Quality And Cost- 2018-10-2 2018-12-0 2019-01-0 2019-02-0 2019-03-0 2019-04-1 2019-07-1 ssessment and developmen IDA / 60070 Post Open - National 50,000.00 0.00 Canceled 2018-10-02 rovement in secondary citie Based Selection 3 6 3 2 9 3 2 t of NRW reduction and man s agement interventions for H arari town by Harari water s upply and sewerage service ET-MOWIE-77885-CS-QCBS / Component 2: Sanitation an Consultancy Service for prep d water supply services imp Quality And Cost- 2018-10-2 2018-12-0 2019-01-0 2019-02-0 2019-03-1 2019-04-1 2019-08-1 aration of Business plan for IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-10-05 rovement in secondary citie Based Selection 6 9 6 5 2 6 4 Adama, Asella and Shasham s ene towns by Oromia Water Mineral and Energy Bureau ET-MOWIE-75932-CS-QCBS / Selection and employment o f consultant for Consultancy Component 2: Sanitation an service for preparation of bu d water supply services imp Quality And Cost- Pending Impleme 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-09-2 IDA / 60070 Post Open - National 130,000.00 0.00 2018-11-15 siness plan and NRW Reduc rovement in secondary citie Based Selection ntation 6 9 6 8 2 7 4 tion strategic plan and imple s mentation mechanisms for S oda, Hawasa and Arbamich towns by SNNP reginal wate r bureaus ET-MOWIE-75927-CS-QCBS / Selection and employment o Component 2: Sanitation an f consultant for situational a d water supply services imp Quality And Cost- 2018-10-1 2018-12-0 2018-12-2 2019-01-2 2019-03-0 2019-04-0 2019-10-0 ssessment and developmen IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-09-27 rovement in secondary citie Based Selection 8 1 9 8 4 8 5 t of NRW reduction and man s agement interventions for G ambella, Semera and Asosa towns by MoWIE ET-MOWIE-84640-CS-QCBS / Component 2: Sanitation an Consultancy Service for Prep d water supply services imp Quality And Cost- Open - Internation 2018-12-0 2018-12-2 2019-02-1 2019-02-0 2019-11-2 2019-03-0 2020-04-0 2019-04-0 2020-06-0 2019-05-0 2021-06-0 2019-06-1 2021-07-0 2020-06-1 IDA / 60080 Prior 540,000.00 899,550.78 Signed 2018-11-30 aration of Urban Water Supp rovement in secondary citie Based Selection al 5 1 4 3 7 3 3 2 9 7 1 1 8 0 ly Study and Design Criteria s ET-MOWIE-77886-CS-QCBS / Component 2: Sanitation an Consultancy Service for prep d water supply services imp Quality And Cost- Under Implemen 2019-09-0 2018-12-1 2019-01-2 2019-02-2 2019-03-2 2019-04-2 2019-06-0 2019-09-2 IDA / 60070 Post Open - National 50,000.00 0.00 2018-11-20 aration of Business plan for rovement in secondary citie Based Selection tation 4 1 4 1 3 7 1 9 Dire Dewa town by Diredew s a town water utility ET-MOWIE-75898-CS-QCBS / Selection and Employment o f Consultant for Developmen t of Billing and Accounting S Component 3: Project mana Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-11-2 ystem, Customer Care, FM i IDA / 60070 gement & institutional stren Post Open - National 51,000.00 0.00 Canceled 2018-11-15 Based Selection 6 9 6 8 2 7 3 mprovement, network mana gthening gement and and capacity Bu ilding for Deghabur and Jigji ga towns by Somali Region Water Resource Developme nt Bureau ET-MOWIE-75900-CS-QCBS / Selection and Employment o f Consultant for Developmen Component 3: Project mana t of Billing and Accounting S Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-11-2 IDA / 60070 gement & institutional stren Post Open - National 51,000.00 0.00 Canceled 2018-11-15 ystem, Customer Care, FM i Based Selection 6 9 6 8 2 7 3 gthening mprovement, network mana gement and and capacity Bu ilding for Adegrat and Mekell e towns by Tigray Region W ater Bureau ET-MOWIE-75896-CS-QCBS / Selection and Employment o f Consultant for Developmen t of Billing and Accounting S Component 3: Project mana Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-11-2 ystem, Customer Care, FM i IDA / 60070 gement & institutional stren Post Open - National 76,000.00 0.00 Canceled 2018-11-15 Based Selection 6 9 6 8 2 7 3 mprovement, network mana gthening gement and and capacity Bu ilding for Bahirdar, Gonder, Debrebrihan and Dessie tow ns by Amahara Water Burea u ET-MOWIE-75897-CS-QCBS / Selection and Employment o f Consultant for Developmen Component 3: Project mana t of Billing and Accounting S Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-11-2 IDA / 60070 gement & institutional stren Post Open - National 76,000.00 0.00 Canceled 2018-11-15 ystem, Customer Care, FM i Based Selection 6 9 6 8 2 7 3 gthening mprovement, network mana gement and and capacity Bu ilding for Gambella, Semera, and Asosa towns by MoWIE ET-MOWIE-75892-CS-QCBS / Selection and Employment o f Consultant for Developmen Component 3: Project mana t of Billing and Accounting S Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-11-2 IDA / 60070 gement & institutional stren Post Open - National 76,000.00 0.00 Canceled 2018-11-15 ystem, Customer Care, FM i Based Selection 6 9 6 8 2 7 3 gthening mprovement, network mana gement and and capacity Bu ilding for Nekemte and Jimm a towns by by Oromia WMEB ET-MOWIE-75903-CS-QCBS / Selection and Employment o f Consultant for Developmen Component 3: Project mana t of Billing and Accounting S Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-11-2 IDA / 60070 gement & institutional stren Post Open - National 76,000.00 0.00 Canceled 2018-11-14 ystem, Customer Care, FM i Based Selection 5 8 5 7 1 6 2 gthening mprovement, network mana gement and and capacity Bu ilding for Hawassa, Sodo, an d Arbaminch towns by SNRP R Water Bureau ET-MOWIE-75888-CS-INDV / Selection and Employment o f Consultant for Developmen Component 3: Project mana t of Billing and Accounting S Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-11-2 IDA / 60070 gement & institutional stren Post Open - National 76,000.00 0.00 Canceled 2018-11-15 ystem, Customer Care, FM i Based Selection 6 9 6 8 2 7 3 gthening mprovement, network mana gement and Capacity Buildi ng for Adama, Assela, Bishof tu and Shashamene towns b y Oromia WMEB ET-MOWIE-75899-CS-QCBS / Selection and Employment o f Consultant for Developmen Component 3: Project mana Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-08-2 t of Billing and Accounting S IDA / 60070 gement & institutional stren Post Open - National 75,000.00 0.00 Canceled 2018-11-15 Based Selection 6 9 6 8 2 7 5 ystem, Customer Care, FM i gthening mprovement, network mana gement and and capacity Bu ilding for Harar town by by H arar WMEB ET-MOWIE-75905-CS-QCBS / Selection and Employment o f Consultant for Developmen Component 3: Project mana t of Billing and Accounting S Quality And Cost- 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-08-2 IDA / 60070 gement & institutional stren Post Open - National 100,000.00 0.00 Canceled 2018-11-15 ystem, Customer Care, FM i Based Selection 6 9 6 8 2 7 5 gthening mprovement, network mana gement and and capacity Bu ilding for Diredewa town WS SS by diredewa town WSSS Page 10 ET-MOWIE-107046-CS-QCBS / Consultancy Service for De Component 2: Sanitation an sign and Implementation of d water supply services imp Quality And Cost- Open - Internation Under Implemen 2019-09-1 2019-09-1 2019-11-0 2019-10-2 2020-05-0 2019-12-0 2020-06-2 2020-01-0 2021-11-1 2020-02-0 2022-03-2 2020-03-1 2021-09-0 an Integrated Management I IDA / 60070 Prior 4,067,243.00 0.00 2019-08-20 rovement in secondary citie Based Selection al tation 6 0 7 4 7 5 6 4 8 8 3 4 5 nformation System for Urba s n Water Utilities in Ethiopia, by Water Development Com mission ET-MOWIE-139130-CS-QCBS / consultancy service on the Component 2: Sanitation an construction supervision of F d water supply services imp Quality And Cost- Open - Internation Under Implemen 2020-06-1 2019-12-1 2020-07-1 2020-01-2 2021-04-2 2020-02-2 2021-06-0 2020-03-2 2021-12-1 2020-04-2 2020-06-0 2022-01-2 SM (fecal sludge manageme IDA / 60070 Prior 1,400,000.00 0.00 2019-11-21 rovement in secondary citie Based Selection al tation 2 2 4 5 7 4 4 5 4 9 3 4 nt ) for Adama, Bahirdar, Ha s wasa, DireDewa, and Mekele Towns by Water Developme nt Comision. ET-MOWIE-143194-CS-QCBS / Selection and Employment of Independent procuremen Component 2: Sanitation an t Audit service for multi y d water supply services imp Quality And Cost- 2020-01-0 2020-01-0 2020-01-2 2020-03-0 2020-05-1 2020-04-0 2020-07-1 2020-05-0 2020-11-0 2020-06-1 2021-04-2 2020-07-1 2021-06-0 2022-02-0 IDA / 60070 Prior Open - National 300,000.00 243,328.50 Signed 2019-12-25 ears procurement Audit (2 rovement in secondary citie Based Selection 1 8 7 8 2 7 4 7 9 1 1 6 4 6 009-2013 EFY) for 23 towns s o f Urban Water and Sanit ation Project II (UWSSP-2) by Water Development Com mission ET-MOWIE-152576-CS-QCBS / Consultancy service for pre paration of business plan an Component 2: Sanitation an d NRW Reduction strategic p d water supply services imp Quality And Cost- Open - Internation Under Implemen 2020-03-1 2020-02-1 2020-06-0 2020-03-2 2022-11-2 2020-04-2 2020-05-2 2020-06-2 2020-08-0 2022-01-2 IDA / 60070 Prior 3,105,582.00 0.00 2020-01-23 lan and implement for Adam rovement in secondary citie Based Selection al tation 3 3 8 8 4 5 5 9 3 5 a, Asela, Shashamene, Neke s mete, Jima and Bishoftu tow ns Water supply and Sewera ge authorities by Oromia Re gion Water Bureau ET-MOWIE-152577-CS-QCBS / Consultancy service for pre paration of business plan an Component 2: Sanitation an d NRW Reduction strategic p d water supply services imp Quality And Cost- Open - Internation Under Implemen 2020-03-1 2020-02-1 2020-05-2 2020-03-2 2022-03-1 2020-04-2 2022-05-2 2020-05-2 2022-10-1 2020-06-2 2023-01-1 2020-08-0 2021-11-2 IDA / 60070 Prior 2,552,791.00 0.00 2020-01-23 lan and implement for Bhir D rovement in secondary citie Based Selection al tation 3 3 8 8 0 5 3 5 1 9 6 3 6 ar, Gonder, Dessie and Debr s e-birhan towns Water suppl y and Sewerage authorities by Amhara Region Water Bu reau ET-MOWIE-152580-CS-QCBS / Consultancy service for pre paration of business plan an Component 2: Sanitation an d NRW Reduction strategic p d water supply services imp Quality And Cost- Open - Internation Under Implemen 2021-02-2 2020-02-1 2021-04-0 2020-03-2 2022-09-0 2020-04-2 2022-12-0 2020-05-2 2020-06-2 2020-08-0 2021-09-2 IDA / 60070 Prior 2,258,370.00 0.00 2020-01-23 lan and implement for Gamb rovement in secondary citie Based Selection al tation 6 3 7 8 5 5 7 5 9 3 7 ella, Semera and Asosa tow s ns Water supply and Sewera ge authorities by Water Dev elopment Commission ET-MOWIE-77756-CS-QCBS / Consultancy service for prep Component 2: Sanitation an aration of business plan and d water supply services imp Quality And Cost- 2019-09-0 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-09-2 NRW Reduction strategic pla IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-11-15 rovement in secondary citie Based Selection 4 6 9 6 8 2 7 4 n and implementation for JIji s ga and Deghabur towns Wat er supply and Sewerage aut horities by Somali Region W ater Bureau ET-MOWIE-77754-CS-QCBS / Consultancy service for prep aration of business plan and Component 2: Sanitation an NRW Reduction strategic pla d water supply services imp Quality And Cost- 2019-09-0 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-09-2 IDA / 60070 Post Open - National 130,000.00 0.00 Canceled 2018-11-14 n and implement for A/Minc rovement in secondary citie Based Selection 4 5 8 5 7 1 6 3 h, Sodo and Hawassa towns s Water supply and Sewerage authorities by SNNPR Region Water Bureau ET-MOWIE-75930-CS-QCBS / Selection and employment o f consultant for Consultancy Component 2: Sanitation an service for preparation of bu d water supply services imp Quality And Cost- 2019-09-0 2018-12-2 2019-02-0 2019-03-0 2019-04-0 2019-05-0 2019-06-1 2019-10-0 IDA / 60070 Post Open - National 110,000.00 0.00 Canceled 2018-11-30 siness plan and NRW Reduc rovement in secondary citie Based Selection 4 1 3 3 2 7 1 9 tion strategic plan and imple s mentation mechanisms Mek ele and Adigrat towns by Ti gray regional water bureau ET-MOWIE-77755-CS-QCBS / Consultancy service service for preparation of business p Component 2: Sanitation an lan and NRW Reduction stra d water supply services imp Quality And Cost- 2019-09-0 2018-12-2 2019-02-0 2019-03-0 2019-04-0 2019-05-0 2019-06-1 2019-10-0 IDA / 60070 Post Open - National 130,000.00 0.00 Canceled 2018-11-29 tegic plan and implementati rovement in secondary citie Based Selection 4 0 2 2 1 6 0 8 on m for Gambella, Semera s and Asosa towns Water supp ly and Sewerage authorities by Ministry of Water Irrigatio n and Electricity ET-MOWIE-107044-CS-QCBS / Selection and employment of consultant for Consultanc Component 2: Sanitation an y service for preparation of d water supply services imp Quality And Cost- 2019-09-0 2019-05-0 2019-06-1 2019-07-1 2019-08-1 2019-09-1 2019-10-2 2020-04-1 business plan and NRW Red IDA / 60070 Post Open - National 200,000.00 0.00 Canceled 2019-04-10 rovement in secondary citie Based Selection 4 1 4 2 1 5 0 7 uction strategic plan and im s plementation mechanisms f or Adama, Asella, Shashame ne, Nekemte, Jimma and Bis hoftu towns by Oromia WME B ET-MOWIE-75921-CS-QCBS / Selection and employment o f consultant for Consultancy Component 2: Sanitation an service for preparation of bu d water supply services imp Quality And Cost- 2018-12-1 2019-01-2 2019-02-2 2019-03-2 2019-04-2 2019-06-0 2019-11-3 IDA / 60070 Post Open - National 150,000.00 0.00 Canceled 2018-11-22 siness plan and NRW Reduc rovement in secondary citie Based Selection 3 6 3 5 9 3 0 tion strategic plan and imple s mentation mechanisms for f or Adama, Asella, Shashame ne and Bishoftu towns by Or omia WMEB ET-MOWIE-77757-CS-QCBS / Consultancy service for prep aration of business plan and Component 2: Sanitation an NRW Reduction strategic pla d water supply services imp Quality And Cost- 2019-09-0 2018-12-2 2019-02-0 2019-03-0 2019-04-0 2019-05-0 2019-06-1 2019-10-0 IDA / 60070 Post Open - National 60,000.00 0.00 Canceled 2018-11-30 n and implementation mech rovement in secondary citie Based Selection 4 1 3 3 2 7 1 9 anisms for Harar town Water s supply and Sewerage author ities by Harar town Water su pply and Sewerage authoriti es ET-MOWIE-75919-CS-QCBS / Selection and employment o f consultant for Consultancy Component 3: Project mana service for preparation of bu Quality And Cost- 2018-12-2 2019-02-0 2019-03-0 2019-04-0 2019-05-0 2019-06-1 2019-12-0 IDA / 60070 gement & institutional stren Post Open - National 110,000.00 0.00 Canceled 2018-11-30 siness plan and NRW Reduc Based Selection 1 3 3 2 7 1 8 gthening tion strategic plan and imple mentation mechanisms for J imma and Nekemte towns b y Oromia WMEB ET-MOWIE-77761-CS-QCBS / Consultancy service for prep Component 2: Sanitation an aration of business plan and d water supply services imp Quality And Cost- 2019-09-0 2018-12-0 2019-01-1 2019-02-1 2019-03-1 2019-04-2 2019-05-2 2019-09-2 NRW Reduction strafor Gond IDA / 60070 Post Open - National 150,000.00 0.00 Canceled 2018-11-15 rovement in secondary citie Based Selection 4 6 9 6 8 2 7 4 er, Dessie, Debreberhan an s d Bahirdar towns Water sup ply and Sewerage authoritie s by Amhara Region Water Bureau ET-MOWIE-152586-CS-QCBS / Consultancy service for pre Component 2: Sanitation an paration of business plan an d water supply services imp Quality And Cost- Open - Internation Under Implemen 2020-07-1 2020-03-1 2020-04-2 2020-05-2 2020-06-2 2020-07-2 2020-08-3 2021-08-3 d NRW Reduction strategic p IDA / 60070 Post 1,505,580.00 0.00 2020-02-19 rovement in secondary citie Based Selection al tation 3 1 4 2 1 6 0 0 lan and implement for Jigjiga s and Degnabur towns Water supply and Sewerage author ities by somali Region Water Bureau ET-MOWIE-152559-CS-QCBS / Consultancy service for pre paration of business plan an Component 2: Sanitation an d NRW Reduction strategic p d water supply services imp Quality And Cost- Open - Internation Under Implemen 2020-03-1 2020-03-1 2020-04-2 2020-05-2 2020-06-2 2020-07-2 2020-08-3 2021-10-2 IDA / 60070 Post 1,700,000.00 0.00 2020-02-20 lan and implement for A/Min rovement in secondary citie Based Selection al tation 6 2 5 3 2 7 1 5 ch, Sodo and Hawassa towns s Water supply and Sewerage authorities by SNNPR Region Water Bureau ET-MOWIE-152583-CS-QCBS / Consultancy service for pre Component 2: Sanitation an paration of business plan an d water supply services imp Quality And Cost- Open - Internation Under Implemen 2020-07-1 2020-03-1 2020-04-2 2020-05-2 2020-06-2 2020-07-2 2020-08-3 2021-08-3 d NRW Reduction strategic p IDA / 60070 Post 1,500,000.00 0.00 2020-02-20 rovement in secondary citie Based Selection al tation 3 2 5 3 2 7 1 1 lan and implement for Adegr s at and Mekelle towns Water supply and Sewerage author ities by Tigray Region Water Bureau ET-MOWIE-152591-CS-QCBS / Consultancy service for pre Component 2: Sanitation an paration of business plan an d water supply services imp Quality And Cost- Open - Internation Under Implemen 2020-04-1 2020-03-1 2020-04-2 2020-05-2 2020-06-2 2020-07-2 2020-08-3 2021-08-3 d NRW Reduction strategic p IDA / 60070 Post 1,500,000.00 0.00 2020-02-20 rovement in secondary citie Based Selection al tation 5 2 5 3 2 7 1 1 lan and implement for Harar s town Water supply and Sew erage authority by Harar R egion Water Bureau ET-MOWIE-146021-CS-QBS / Component 2: Sanitation an Selection and Employment o d water supply services imp Consultant Qualif 2020-02-0 2020-03-1 2020-04-1 2020-05-2 2020-11-1 f Environmental & Social Im IDA / 60070 Post Open - National 29,100.00 0.00 Canceled 2020-01-14 rovement in secondary citie ication Selection 4 9 8 3 9 pact Assessment for Arba M s inch & Wolaita Sodoby water Development commission ET-MOWIE-146020-CS-QBS / Selection and Employment o Component 2: Sanitation an f Environmental & Social Im d water supply services imp Consultant Qualif Under Implemen 2020-04-0 2020-03-1 2020-05-0 2020-06-0 2020-07-0 2020-12-0 IDA / 60070 Post Open - National 60,000.00 0.00 2020-02-28 pact Assessment for Gondar, rovement in secondary citie ication Selection tation 3 3 2 1 6 3 Dessie, Debre Berhan, Jigjig s a and Degehabur by water Development commission. ET-MOWIE-146016-CS-QBS / Selection and Employment o Component 2: Sanitation an f Environmental & Social Im d water supply services imp Consultant Qualif Under Implemen 2020-04-0 2020-03-1 2020-05-0 2020-06-0 2020-07-0 2020-12-0 pact Assessment for Jimma, IDA / 60070 Post Open - National 91,300.00 0.00 2020-02-28 rovement in secondary citie ication Selection tation 3 3 2 1 6 3 Nekemte, Bishoftu, Shashe s mene, Assela, W/Sodo and Arba Minch by water Develo pment commission ET-MOWIE-146024-CS-QBS / Selection and Employment o Component 2: Sanitation an f Environmental & Social Im d water supply services imp Consultant Qualif Under Implemen 2020-04-0 2020-03-1 2020-05-0 2021-02-2 2020-06-0 2020-07-0 2020-12-0 IDA / 60070 Post Open - National 52,200.00 0.00 2020-02-28 pact Assessment for Harar, rovement in secondary citie ication Selection tation 3 3 2 1 1 6 3 Adigrat, Gambella, Semera-L s ogia and, Assosa by water Development commission ET-MOWIE-205117-CS-QCBS Component 2: Sanitation an / Consultancy Service for Pre d water supply services imp Quality And Cost- Open - Internation Under Implemen 2022-03-2 2020-12-1 2023-01-2 2021-01-2 2021-02-2 2021-03-2 2021-05-0 2021-06-0 2022-11-2 paring Technical Design Man IDA / 60080 Prior 1,700,000.00 0.00 2020-11-25 rovement in secondary citie Based Selection al tation 2 6 9 9 6 8 2 6 8 ual, Operation, Maintenance s and Management for Urban Sanitation by WDC ET-MOWIE-243682-CS-QCBS Component 2: Sanitation an / procurement of consultanc d water supply services imp Quality And Cost- Open - Internation Pending Impleme 2021-11-1 2022-01-2 2022-02-2 2022-03-2 2022-04-2 2022-06-0 2023-06-0 IDA / 60080 Prior 2,000,000.00 0.00 2021-10-20 y service in preparation of d rovement in secondary citie Based Selection al ntation 0 4 1 3 7 1 1 etail design document for taf s o town by WDC ET-MOWIE-263459-CS-QCBS / Supervision consultant for f Component 2: Sanitation an ecal sludge management sy d water supply services imp Quality And Cost- Under Implemen 2022-03-1 2021-12-1 2022-01-1 2022-02-1 2022-03-0 2022-04-1 2022-05-1 2023-05-1 IDA / 60070 Post Open - National 350,000.00 0.00 2021-11-30 stem construction for Assosa rovement in secondary citie Based Selection tation 4 4 8 5 8 2 7 7 , Semera Logiya and Gambel s la by Ministry of Water and E nergy ET-MOWIE-263461-CS-QCBS Component 2: Sanitation an / Supervision consultant for f d water supply services imp Quality And Cost- Under Implemen 2021-12-2 2022-01-2 2022-02-2 2022-03-1 2022-04-1 2022-05-2 2023-05-2 ecal sludge management sy IDA / 60070 Post Open - National 300,000.00 0.00 2021-11-30 rovement in secondary citie Based Selection tation 1 5 2 5 9 4 4 stem construction for Jimma s and Nekemte-Oromia- By Or omia Water Bureau ET-MOWIE-263462-CS-QCBS / Supervision consultant for f Component 2: Sanitation an ecal sludge management sy d water supply services imp Quality And Cost- Under Implemen 2021-12-1 2022-01-1 2022-02-1 2022-03-0 2022-04-1 2022-05-1 2023-05-1 IDA / 60070 Post Open - National 450,000.00 0.00 2021-11-30 stem construction for Assella rovement in secondary citie Based Selection tation 4 8 5 8 2 7 7 , Shashemene & Bishoftu -Or s omia by Oromia Water Bure au Page 11 ET-MOWIE-263463-CS-QCBS / Supervision consultant for f Component 2: Sanitation an ecal sludge management sy d water supply services imp Quality And Cost- Under Implemen 2022-12-2 2021-12-1 2022-01-1 2022-02-1 2022-03-0 2022-04-1 2022-05-1 2023-05-1 IDA / 60070 Post Open - National 250,000.00 0.00 2021-11-30 stem construction for Jigjiga rovement in secondary citie Based Selection tation 2 4 8 5 8 2 7 7 and Degehanour-Somali by s Somali Region Water Bureau ET-MOWIE-263465-CS-QCBS / Supervision consultant for f Component 2: Sanitation an ecal sludge management sy d water supply services imp Quality And Cost- Under Implemen 2022-07-1 2021-12-1 2022-01-1 2022-02-1 2022-03-0 2022-04-1 2022-05-1 2023-05-1 IDA / 60070 Post Open - National 450,000.00 0.00 2021-11-30 stem construction for Gonde rovement in secondary citie Based Selection tation 2 4 8 5 8 2 7 7 r, Dessie & Debre Berhan-A s mhara by Amhara Region W ater Bureau ET-MOWIE-263468-CS-QCBS Component 2: Sanitation an / Supervision consultant for f d water supply services imp Quality And Cost- Under Implemen 2022-07-1 2021-12-1 2022-01-1 2022-02-1 2022-03-0 2022-04-1 2022-05-1 2023-05-1 ecal sludge management sy IDA / 60070 Post Open - National 300,000.00 0.00 2021-11-30 rovement in secondary citie Based Selection tation 2 4 8 5 8 2 7 7 stem construction for W/Sod s o and Arbaminch-Minch SNN P by SNNPR Water Bureau ET-MOWIE-263275-CS-QCBS Component 2: Sanitation an / Supervision consultant for f d water supply services imp Quality And Cost- Under Implemen 2022-03-1 2021-12-1 2022-01-1 2022-02-0 2022-02-2 2022-03-3 2022-05-0 2023-05-0 ecal sludge management sy IDA / 60070 Post Open - National 200,000.00 0.00 2021-11-30 rovement in secondary citie Based Selection tation 1 4 2 9 4 1 5 5 stem construction of Harar t s own by Harar town water util ity ET-MOWIE-278521-CS-CQS / Component 2: Sanitation an Consultancy Service for upd d water supply services imp Consultant Qualif Pending Impleme 2022-03-2 2022-04-1 2022-05-1 2022-06-2 2022-10-2 IDA / 60070 Post Open - National 40,000.00 0.00 2022-02-28 ating of Business plan for Dir rovement in secondary citie ication Selection ntation 1 9 9 3 1 e Dewa Town Water Utility b s y Dire Dewa Town WSSE INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-55842-CS-INDV / Component 3: Project mana Selection and Employment o Individual Consul Pending Impleme 2018-07-2 2018-08-1 2018-09-1 2024-08-1 IDA / 60070 gement & institutional stren Post Open 54,000.00 0.00 2018-06-18 f Procurement Specialist for tant Selection ntation 2 2 6 5 gthening Mekelle Town Water Utility b y Mekelle Town Utility ET-MOWIE-63893-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2020-06-1 2018-07-1 2018-07-2 2018-07-2 2019-07-2 2018-08-3 2018-07-2 2019-08-2 f Financial specialist for Ada IDA / 60080 gement & institutional stren Post Open 5,185.00 3,908.81 Signed 2018-06-14 tant Selection 6 3 6 7 7 1 7 6 ma Town Waste Water Man gthening agement project by Adama Town Utility office. ET-MOWIE-70084-CS-INDV / Component 3: Project mana Selection and employment o Individual Consul 2018-12-0 2018-09-0 2019-03-0 2018-09-1 2019-03-1 2018-10-1 2019-03-1 2019-10-1 IDA / 60070 gement & institutional stren Post Open 7,500.00 6,474.26 Signed 2018-08-07 f Technical specialist for Am tant Selection 2 5 7 5 0 3 0 3 gthening hara regional bureau by Am hara regional bureau ET-MOWIE-70090-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-0 2018-09-1 2018-10-1 2019-10-1 f Technical specialist for Oro IDA / 60070 gement & institutional stren Post Open 7,500.00 0.00 2018-08-07 tant Selection ntation 5 5 3 3 mia Region Water Mineral an gthening d Energy Bureau by Oromia OWMEB ET-MOWIE-70097-CS-INDV / Component 3: Project mana selection and employment o Individual Consul 2018-12-0 2018-09-0 2019-02-2 2018-09-1 2019-03-1 2018-10-1 2019-03-1 2019-10-1 IDA / 60070 gement & institutional stren Post Open 7,500.00 6,470.41 Signed 2018-08-07 f Technical specialist for Am tant Selection 3 5 0 2 0 0 0 0 gthening hara regional bureau by Am hara regional bureau ET-MOWIE-70098-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-0 2018-09-2 2018-10-2 2019-10-2 f Technical specialist for Oro IDA / 60070 gement & institutional stren Post Open 7,500.00 0.00 2018-08-07 tant Selection ntation 5 6 4 4 mia Region Water Mineral an gthening d Energy Bureau by Oromia OWMEB ET-MOWIE-70101-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2019-02-1 2018-09-0 2020-04-1 2018-09-2 2019-04-1 2018-10-2 2019-04-1 2019-10-2 f Technical specialist for SNN IDA / 60070 gement & institutional stren Post Open 7,500.00 5,366.75 Signed 2018-08-07 tant Selection 8 5 1 6 5 4 5 4 PR Region Water Resource D gthening evelopment Bureau by SNNP R Water Resource Bureau ET-MOWIE-70102-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-0 2018-09-1 2018-10-2 2019-10-2 f Technical specialist for SNN IDA / 60070 gement & institutional stren Post Open 7,500.00 0.00 2018-08-07 tant Selection ntation 5 9 4 4 PR Region Water Mineral an gthening d Energy Bureau by SNNPR Water Resource Bureau ET-MOWIE-70104-CS-INDV / Selection and Employment o f Technical specialist for Ethi Component 3: Project mana Individual Consul Pending Impleme 2018-09-0 2018-09-2 2018-10-3 2019-10-3 opian Somali Region Water IDA / 60070 gement & institutional stren Post Open 7,500.00 0.00 2018-08-07 tant Selection ntation 5 6 1 1 Resource Development Bure gthening au by Ethiopian Somali Regi on Water Resource Develop ment Bureau ET-MOWIE-70107-CS-INDV / Selection and Employment o Component 3: Project mana f Technical specialist for Ben Individual Consul Pending Impleme 2018-09-0 2018-09-2 2018-10-3 2019-10-3 IDA / 60070 gement & institutional stren Post Open 7,500.00 0.00 2018-08-07 ishangulegumuz Region Wat tant Selection ntation 5 6 1 1 gthening er Mineral and Energy Burea u by Benshangulgumuz Regi on Water Bureau ET-MOWIE-70109-CS-INDV / Selection and Employment o Component 3: Project mana f Project Coordinator for Ada Individual Consul 2018-12-0 2018-09-0 2018-12-2 2018-09-2 2018-08-2 2018-11-0 2018-08-2 2019-11-0 IDA / 60070 gement & institutional stren Post Open 8,800.00 5,556.55 Signed 2018-08-08 ma Town Waste Water Mana tant Selection 7 6 8 7 8 1 8 1 gthening gement Project by Adama To wn Water Supply and Sewer age Authority ET-MOWIE-70111-CS-INDV / Selection and employment o Component 3: Project mana f financial specialist for Meke Individual Consul Pending Impleme 2018-09-0 2018-09-1 2018-10-1 2019-10-1 IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-08-08 le Town Water supply and se tant Selection ntation 6 3 8 8 gthening werage service by mekele to wn water supply and sewera ge Authority ET-MOWIE-70119-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-11-0 2018-09-1 2019-03-1 2018-09-2 2019-03-1 2018-11-0 2019-03-1 2019-11-0 f Project coordinator for Haw IDA / 60070 gement & institutional stren Post Open 8,800.00 5,364.91 Signed 2018-08-15 tant Selection 6 3 8 7 9 1 9 1 asa Town by Hawasa Town gthening Water Supply and Sewerage Service ET-MOWIE-70125-CS-INDV / Selection and employment o Component 3: Project mana f financial specialist for Haw Individual Consul Pending Impleme 2018-09-1 2018-09-2 2018-11-0 2019-11-0 IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-08-15 asa Town Water supply and tant Selection ntation 3 7 1 1 gthening sewerage service by Hawasa town water supply and sewe rage Authority ET-MOWIE-70129-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-07-1 2018-09-0 2018-10-0 2018-09-1 2018-10-1 2018-10-2 2018-10-1 2019-10-2 f Project Coordinator for Asel IDA / 60070 gement & institutional stren Post Open 8,800.00 6,509.16 Signed 2018-08-06 tant Selection 5 4 2 8 2 3 2 3 a town by Asela town Water gthening Supply and Sewerage Author ity ET-MOWIE-70150-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2019-12-0 2018-09-1 2019-12-2 2018-09-2 2020-06-0 2018-11-0 2020-06-0 2019-11-0 f Project Coordinator for Sha IDA / 60070 gement & institutional stren Post Open 8,800.00 6,514.68 Signed 2018-08-15 tant Selection 1 3 0 7 8 1 8 1 shamene town by Shashame gthening ne town Water Supply and S ewerage Authority ET-MOWIE-70157-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-06-1 2018-09-0 2018-08-0 2018-09-2 2018-08-0 2018-10-2 2018-08-0 2019-10-2 f Project Coordinator for Nek IDA / 60070 gement & institutional stren Post Open 8,800.00 7,801.64 Signed 2018-08-10 tant Selection 7 8 3 2 3 7 3 7 emte town by Nekemte town gthening Water Supply and Sewerage Authority ET-MOWIE-70166-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-07-0 2018-09-1 2018-09-0 2018-09-2 2018-09-1 2018-11-0 2018-09-1 2019-11-0 f Project Coordinator for Arb IDA / 60070 gement & institutional stren Post Open 8,800.00 5,530.78 Signed 2018-08-15 tant Selection 1 3 2 7 1 1 1 1 aminch town by Arbaminch t gthening own Water Supply and Sewe rage Authority ET-MOWIE-70176-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-1 2018-09-2 2018-10-3 2019-10-3 f Project Coordinator for Ga IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-08-13 tant Selection ntation 1 5 0 0 mbella town by Gambella to gthening wn Water Supply and Sewer age Autrity ET-MOWIE-70184-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-1 2018-09-2 2018-10-3 2019-10-3 f Project Coordinator for Aso IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-08-14 tant Selection ntation 2 6 1 1 sa town by Asosa town Wate gthening r Supply and Sewerage Auth ority ET-MOWIE-70191-CS-INDV / Selection and employment o Component 3: Project mana Individual Consul Under Implemen 2018-12-0 2018-09-0 2019-12-0 2018-09-1 2020-01-1 2018-10-2 2019-10-2 f project coordinator for Adig IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-08-07 tant Selection tation 6 5 2 9 2 4 4 rat town by Adigrat town wa gthening ter supply and sewerage ser vice ET-MOWIE-70193-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-1 2018-09-2 2018-10-3 2019-10-3 f Procurement Specialist for IDA / 60070 gement & institutional stren Post Open 7,921.00 0.00 2018-08-13 tant Selection ntation 1 5 0 0 Asosa town by Asosa town gthening Water Supply and Sewerage Authority ET-MOWIE-70194-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-1 2018-09-2 2018-10-3 2019-10-3 f financial spcialist for Asosa IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-08-13 tant Selection ntation 1 5 0 0 town by Asosa town Water S gthening upply and Sewerage Authori ty ET-MOWIE-70198-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-1 2018-09-2 2018-11-0 2019-11-0 f Procurement Specialist for IDA / 60070 gement & institutional stren Post Open 7,921.00 0.00 2018-08-15 tant Selection ntation 3 7 1 1 Adigrat town by Adigerat to gthening wn Water Supply and Sewer age Authority ET-MOWIE-70199-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Under Implemen 2018-09-1 2018-09-2 2018-11-0 2019-11-0 f Financial Specialist for Adig IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-08-15 tant Selection tation 3 7 1 1 rat town by Adigerat town W gthening ater Supply and Sewerage A uthority ET-MOWIE-70202-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-09-1 2018-09-2 2018-10-1 2019-10-1 f financial Specialist for Jijiga IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-08-15 tant Selection ntation 3 0 8 8 town by Jijiga town Water Su gthening pply and Sewerage Authority ET-MOWIE-75716-CS-INDV / Selection and Employmnt of Component 3: Project mana Individual Consul 2019-01-1 2018-11-0 2019-02-1 2018-11-2 2019-02-1 2018-12-2 2019-02-1 2019-12-2 Financial Specialist for Bahir IDA / 60070 gement & institutional stren Post Open 6,600.00 4,713.49 Signed 2018-09-14 tant Selection 0 2 2 3 2 8 6 8 dar town Water Supply and gthening Sewerage Authority by Bahir dar Town ET-MOWIE-75723-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-05-0 2018-11-0 2018-05-0 2018-11-2 2018-05-0 2018-12-2 2019-05-0 2019-12-2 f Financial Specialist for Gon IDA / 60070 gement & institutional stren Post Open 6,600.00 4,884.75 Signed 2018-09-13 tant Selection 1 1 1 2 1 7 1 7 der town Water Supply and gthening Sewerage Authority by Gond er Town ET-MOWIE-75730-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-09-1 2018-11-0 2019-04-2 2018-11-2 2019-04-2 2018-12-2 2019-04-2 2019-12-2 f Financial Specialist for Des IDA / 60070 gement & institutional stren Post Open 6,600.00 4,716.23 Signed 2018-09-14 tant Selection 0 2 5 3 6 8 6 8 sie town Water Supply and S gthening ewerage Authority by Dessie Town Page 12 ET-MOWIE-75736-CS-INDV / Selection and Employmenta Component 3: Project mana Individual Consul 2018-09-1 2018-11-0 2019-12-1 2018-11-2 2019-12-1 2018-12-2 2019-12-1 2019-12-2 sw2q of Financial Specialist f IDA / 60070 gement & institutional stren Post Open 6,600.00 4,575.98 Signed 2018-09-14 tant Selection 2 2 8 3 8 8 8 8 or Bishoftu town Water Supp gthening ly and Sewerage Authority b y Bishoftu Town ET-MOWIE-75738-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-11-0 2018-11-2 2018-12-2 2019-12-2 f Financial Specialist for Ga IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-09-14 tant Selection ntation 2 3 8 8 mbella town Water Supply a gthening nd Sewerage Authority by G ambella Town ET-MOWIE-75746-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-11-0 2018-11-2 2018-12-2 2019-12-2 f Financial Specialist for Jima IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-09-14 tant Selection ntation 2 3 8 8 town Water Supply and Sew gthening erage Authority by Jima Tow n ET-MOWIE-75749-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-11-0 2018-11-2 2018-12-2 2019-12-2 f Financial Specialist for Sem IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-09-14 tant Selection ntation 2 3 8 8 era town Water Supply and gthening Sewerage Authority by Sem era Town ET-MOWIE-75750-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-11-0 2018-11-2 2018-12-2 2019-12-2 f Financial Specialist for Deg IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-09-14 tant Selection ntation 2 3 8 8 habur town Water Supply an gthening d Sewerage Authority by De ghabur Town ET-MOWIE-75753-CS-INDV / Selection and Employmnt of Component 3: Project mana Individual Consul Pending Impleme 2018-11-0 2018-11-2 2018-12-2 2019-12-2 Financial Specialist for Harar IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-09-14 tant Selection ntation 2 3 8 8 town Water Supply and Sew gthening erage Authority by Harar To wn ET-MOWIE-75755-CS-INDV / Selection and Employmnt of Component 3: Project mana Individual Consul Pending Impleme 2018-11-0 2018-11-2 2018-12-2 2019-12-2 Financial Specialist for Dired IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-09-14 tant Selection ntation 2 3 8 8 ewa town Water Supply and gthening Sewerage Authority by Dired ewa Town ET-MOWIE-75757-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-07-0 2018-11-0 2019-01-1 2018-11-2 2019-02-1 2018-12-2 2019-02-1 2019-12-2 f Financial Specialist for Sod IDA / 60070 gement & institutional stren Post Open 6,600.00 4,716.23 Signed 2018-09-14 tant Selection 3 2 7 3 5 8 5 8 o town Water Supply and Se gthening werage Authority by Sodo To wn ET-MOWIE-75758-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-06-0 2018-11-0 2018-08-0 2018-11-2 2018-10-2 2018-12-2 2018-11-2 2019-12-2 f Financial Specialist for Deb IDA / 60070 gement & institutional stren Post Open 6,600.00 4,735.33 Signed 2018-09-14 tant Selection 1 2 1 3 9 8 9 8 reberhan town Water Supply gthening and Sewerage Authority by Debreberhan Town ET-MOWIE-75810-CS-INDV / Component 3: Project mana Selection and Employment o Individual Consul 2018-06-0 2018-10-3 2019-02-1 2018-11-2 2019-02-1 2018-12-2 2019-02-1 2019-12-2 IDA / 60070 gement & institutional stren Post Open 8,800.00 5,536.05 Signed 2018-09-12 f Project Coordinator for Bahi tant Selection 1 1 8 1 6 6 6 6 gthening rdar Town Water Supply Proj ect by Bahirdar Town ET-MOWIE-75811-CS-INDV / Component 3: Project mana Selection and Employment o Individual Consul 2018-05-0 2018-10-3 2018-10-3 2018-11-2 2018-11-0 2018-12-2 2018-11-0 2019-12-2 IDA / 60070 gement & institutional stren Post Open 8,800.00 5,698.88 Signed 2018-09-12 f Project Coordinator for Gon tant Selection 1 1 0 1 1 6 1 6 gthening der Town Water Supply Proje ct by Gonder Town ET-MOWIE-75866-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-12-0 2018-12-2 2019-01-2 2020-01-2 f Project Coordinator for Des IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-10-15 tant Selection ntation 3 4 8 8 sie Town Water Supply and gthening Sewerage Enterprise by Des sie Town ET-MOWIE-75871-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-06-2 2018-12-0 2018-10-0 2018-12-2 2019-11-2 2019-01-2 2018-11-2 2019-07-2 f Project Coordinator for Deb IDA / 60070 gement & institutional stren Post Open 8,800.00 5,550.54 Signed 2018-10-15 tant Selection 8 3 8 4 5 8 5 7 rebirhan Town Water Supply gthening and Sewerage Enterprise by Debrabrihan Town ET-MOWIE-75872-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2019-12-1 2018-12-0 2019-12-1 2018-12-2 2019-12-1 2019-01-2 2019-12-1 2020-01-2 f Project Coordinator for Bish IDA / 60070 gement & institutional stren Post Open 8,800.00 6,537.11 Signed 2018-10-15 tant Selection 9 3 0 4 8 8 8 8 oftu Town Water Supply and gthening Sewerage Enterprise by Bish oftu Town ET-MOWIE-75873-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-12-0 2018-12-2 2019-01-2 2020-01-2 f Project Coordinator for Jim IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-10-15 tant Selection ntation 3 4 8 8 ma Town Water Supply and gthening Sewerage Enterprise by Jim ma Town ET-MOWIE-75874-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-12-0 2018-12-2 2019-01-2 2020-01-2 f Project Coordinator for Se IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-10-15 tant Selection ntation 3 4 8 8 mera Town Water Supply an gthening d Sewerage Enterprise by Se mera Town ET-MOWIE-75875-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-12-0 2018-12-2 2019-01-2 2020-01-2 f Project Coordinator for Har IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-10-15 tant Selection ntation 3 4 8 8 ar Town Water Supply and S gthening ewerage Enterprise by Harar Town ET-MOWIE-75876-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-12-0 2018-12-2 2019-01-2 2020-01-2 f Project Coordinator for Dire IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-10-15 tant Selection ntation 3 4 8 8 dewa Town Water Supply an gthening d Sewerage Enterprise by Di redewa Town ET-MOWIE-75877-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-12-0 2018-12-2 2019-01-2 2020-01-2 f Project Coordinator for Mek IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-10-15 tant Selection ntation 3 4 8 8 elle Town Water Supply and gthening Sewerage Enterprise by Mek elle Town ET-MOWIE-75880-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-12-0 2018-12-2 2019-01-2 2020-01-2 f Project Coordinator for Jigji IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-10-15 tant Selection ntation 3 4 8 8 ga Town Water Supply and S gthening ewerage Enterprise by Jigijig a Town ET-MOWIE-75881-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-12-0 2018-12-2 2019-01-2 2020-01-2 f Project Coordinator for Deg IDA / 60070 gement & institutional stren Post Open 8,800.00 0.00 2018-10-15 tant Selection ntation 3 4 8 8 haburTown Water Supply an gthening d Sewerage Enterprise by D eghaburTown ET-MOWIE-75882-CS-INDV / Component 3: Project mana Selection and Employment o Individual Consul Under Implemen 2018-07-0 2018-12-0 2018-12-2 2019-01-2 2020-01-2 IDA / 60070 gement & institutional stren Post Open 7,500.00 0.00 2018-10-15 f Technical Specialist for MO tant Selection tation 1 3 4 8 8 gthening WIE Program management u nit by MoWIE ET-MOWIE-75883-CS-INDV / Component 3: Project mana Selection and Employment o Individual Consul Under Implemen 2018-12-0 2018-12-2 2019-01-2 2020-01-2 IDA / 60070 gement & institutional stren Prior Open 7,500.00 0.00 2018-10-15 f Procurement Specialist for tant Selection tation 3 4 8 8 gthening MoWIE PMU by MoWIE ET-MOWIE-77731-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-06-1 2018-11-1 2018-09-3 2018-12-0 2020-01-2 2019-01-0 2020-01-2 2020-01-0 f Project Coordinator for Sod IDA / 60070 gement & institutional stren Post Open 8,800.00 5,204.12 Signed 2018-09-26 tant Selection 1 4 0 5 0 9 0 9 oTown Water Supply and Se gthening werage Enterprise by Sodo T own ET-MOWIE-77735-CS-INDV / Component 3: Project mana Selection and employment o Individual Consul 2018-07-0 2018-11-1 2018-07-2 2018-12-0 2018-09-1 2019-01-0 2018-09-1 2020-01-0 IDA / 60070 gement & institutional stren Post Open 6,600.00 4,880.10 Signed 2018-09-26 f financial specialist for Arba tant Selection 2 4 5 5 1 9 1 9 gthening minch town WSSE for Arbam inch Town ET-MOWIE-77736-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2018-08-1 2018-11-1 2018-07-0 2018-12-0 2018-08-0 2019-01-0 2018-08-0 2020-01-0 f Financial specialist for Nek IDA / 60070 gement & institutional stren Post Open 6,600.00 2,676.54 Signed 2018-09-26 tant Selection 6 4 3 5 1 9 1 9 emte Town Water Supply an gthening d Sewerage Enterprise by N ekemte Town ET-MOWIE-77737-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul Pending Impleme 2018-11-1 2018-12-0 2019-01-0 2020-01-0 f Financial specialist for Asel IDA / 60070 gement & institutional stren Post Open 6,600.00 0.00 2018-09-26 tant Selection ntation 4 5 9 4 la Town Water Supply and S gthening ewerage Enterprise by Asell a Town ET-MOWIE-77738-CS-INDV / Selection and Employment o Component 3: Project mana Individual Consul 2019-05-1 2018-11-1 2018-09-0 2018-12-0 2018-07-1 2019-01-0 2018-09-1 2020-01-0 f Financial specialist for Sha IDA / 60070 gement & institutional stren Post Open 6,600.00 3,922.27 Signed 2018-09-26 tant Selection 1 4 9 5 1 9 7 9 shamene Town Water Suppl gthening y and Sewerage Enterprise b y Shashamene Town ET-MOWIE-77734-CS-CDS / Component 2: Sanitation an Selection and employment o d water supply services imp Under Implemen 2018-09-1 2018-12-1 2019-02-1 2019-08-1 f consultant for construction IDA / 60070 Post Direct Selection Direct 110,011.00 0.00 2018-11-30 rovement in secondary citie tation 2 0 3 2 supervision and contract ad s ministration for Dire Dewa T own WSSE by Dire Dewa To wn ET-MOWIE-107048-CS-INDV / Selection and Employment Component 3: Project mana Individual Consul Under Implemen 2019-05-0 2019-05-0 2020-02-2 2019-05-2 2020-05-0 2019-06-3 2023-06-2 of Individual Procurement Co IDA / 60070 gement & institutional stren Prior Open 100,000.00 0.00 2019-04-01 tant Selection tation 9 5 7 6 6 0 9 nsultant/Specialist by Water gthening Development Commission ET-MOWIE-107059-CS-INDV / Selection and Employment Component 3: Project mana Individual Consul Pending Impleme 2019-05-0 2019-05-1 2019-06-2 2023-04-2 of Individual Technical Cons IDA / 60070 gement & institutional stren Post Open 100,000.00 0.00 2019-04-01 tant Selection ntation 4 8 2 7 ultant/ Specialist by Water D gthening evelopment Commission ET-MOWIE-107052-CS-INDV / Selection and Employment Component 3: Project mana of Contract Management Sp Individual Consul 2019-04-3 2019-05-0 2019-08-3 2019-05-2 2019-11-0 2019-06-2 2019-11-1 2023-07-0 IDA / 60070 gement & institutional stren Post Open 100,000.00 22,948.29 Signed 2019-04-01 ecialist for Water Developme tant Selection 0 4 0 5 5 9 3 8 gthening nt commission Urban WSSP I I by Water Development Co mmission ET-MOWIE-107049-CS-INDV / Selection and Employment Component 3: Project mana Individual Consul 2019-04-3 2019-05-0 2019-10-1 2019-05-2 2019-11-0 2019-06-2 2019-11-1 2023-07-0 of Individual Financial Mana IDA / 60070 gement & institutional stren Post Open 100,000.00 24,407.63 Terminated 2019-04-01 tant Selection 0 4 1 5 5 9 4 8 gement Consultant/ Speciali gthening st for Urban WSSP II by Wate r Development Commission ET-MOWIE-110854-CS-INDV Component 3: Project mana Individual Consul Under Implemen 2019-06-0 2019-06-0 2019-06-3 2022-12-2 / Selection and Employment IDA / 60070 gement & institutional stren Post Open 50,000.00 0.00 2019-04-30 tant Selection tation 2 9 0 8 of Social Safeguard Senior gthening ET-MOWIE-107057-CS-INDV / Selection and Employment Component 2: Sanitation an of Environmental and Social d water supply services imp Individual Consul Pending Impleme 2019-07-2 2019-08-1 2019-09-0 2019-11-0 Safeguard Specialist for revi IDA / 60070 Post Open 52,000.00 0.00 2019-06-20 rovement in secondary citie tant Selection ntation 4 4 7 6 ew of 3 towns ( Adama, Dire s Dewa, Mekele) feasibility stu dy and detail design by Wat er Development Commission ET-MOWIE-118398-CS-INDV / Selection and Employment Component 2: Sanitation an of Environmental and Social d water supply services imp Individual Consul Pending Impleme 2019-08-0 2019-08-2 2019-10-0 2019-12-0 Safeguard Specialist for revi IDA / 60070 Post Open 35,000.00 0.00 2019-06-20 rovement in secondary citie tant Selection ntation 8 9 3 2 ew of 2 towns ( Hawasa and s Bahirdar) feasibility study an d detail design by Water De velopment Commission ET-MOWIE-143029-CS-INDV Component 3: Project mana / Selection and employment Individual Consul 2019-12-2 2020-01-0 2020-04-0 2020-01-2 2020-06-2 2020-02-2 2020-06-2 2020-05-2 IDA / 60070 gement & institutional stren Post Open 25,000.00 21,813.30 Signed 2019-11-15 of Sociologist for WDC by W tant Selection 0 3 3 4 3 8 3 8 gthening ater Development Commissi on Page 13 ET-MOWIE-143055-CS-INDV Component 2: Sanitation an / Selection and Employment d water supply services imp Individual Consul 2018-07-2 2020-01-1 2019-02-2 2020-02-0 2019-02-2 2020-03-1 2019-01-2 2021-03-1 IDA / 60070 Post Open 30,000.00 5,536.05 Signed 2019-11-28 of sanitation and Hygiene sp rovement in secondary citie tant Selection 5 6 8 6 2 2 8 2 ecialist by water Developme s nt Commission. ET-MOWIE-143022-CS-INDV / Selection and Employment Component 3: Project mana Individual Consul Under Implemen 2020-01-0 2020-01-2 2020-02-2 2020-06-2 of Water Supply and Sanitati IDA / 60070 gement & institutional stren Prior Open 30,000.00 0.00 2019-11-15 tant Selection tation 3 4 8 7 on Regulatory Specialist for gthening WDC by World Bank country office ET-MOWIE-143032-CS-INDV Component 3: Project mana / Selection and employment Individual Consul 2019-04-3 2020-01-0 2020-04-0 2020-01-2 2020-06-2 2020-02-2 2020-06-2 2020-07-2 IDA / 60070 gement & institutional stren Post Open 35,000.00 20,755.86 Signed 2019-11-15 of Environmental specialist f tant Selection 0 3 3 4 3 8 3 7 gthening or Water Development Com mission by WDC ET-MOWIE-143016-CS-INDV Component 3: Project mana / Selection and employment Individual Consul 2019-12-1 2020-01-1 2020-04-0 2020-02-0 2020-06-2 2020-03-1 2020-06-2 2020-08-0 IDA / 60070 gement & institutional stren Post Open 40,000.00 21,341.44 Signed 2019-11-28 of legal specialist for WDC b tant Selection 9 6 3 6 3 2 3 9 gthening y Water Development Comm ission ET-MOWIE-143025-CS-INDV Component 3: Project mana / Selection and Employment Individual Consul 2019-12-1 2020-01-0 2020-04-0 2020-01-2 2020-06-2 2020-02-2 2020-06-2 2020-07-2 IDA / 60070 gement & institutional stren Post Open 35,000.00 31,319.66 Signed 2019-11-15 of Technical Specialist for W tant Selection 8 3 3 4 3 8 3 7 gthening DC by Water Development C ommission ET-MOWIE-143026-CS-INDV Component 3: Project mana / Selection and Employment Individual Consul 2019-12-2 2020-01-0 2020-04-0 2020-01-2 2020-06-2 2020-02-2 2020-06-2 2020-07-2 IDA / 60070 gement & institutional stren Post Open 30,000.00 28,520.21 Signed 2019-11-15 of Economist for WDC by Wa tant Selection 0 3 3 4 3 8 3 7 gthening ter Development Commissio n ET-MOWIE-143012-CS-INDV / Selection and Employment Component 3: Project mana Individual Consul 2019-12-2 2020-01-1 2020-04-0 2020-01-3 2020-06-2 2020-03-0 2020-06-2 2020-09-0 of Governance/Public Policy IDA / 60070 gement & institutional stren Post Open 50,000.00 48,149.24 Signed 2019-11-22 tant Selection 0 0 3 1 3 6 3 2 Specialist for WDC by Water gthening Development Commission ET-MOWIE-145062-CS-QBS / Component 2: Sanitation an Selection and Employment o d water supply services imp Individual Consul Pending Impleme 2020-01-1 2020-02-0 2020-03-1 2021-03-1 IDA / 60070 Post Open 30,000.00 0.00 2019-11-28 f business management spe rovement in secondary citie tant Selection ntation 6 6 2 2 cialist by the Water Develop s ment Commission ET-MOWIE-75885-CS-INDV / Component 3: Project mana Selection and Employment o Individual Consul Under Implemen 2019-01-0 2019-01-2 2019-02-2 2020-02-2 IDA / 60070 gement & institutional stren Prior Open 7,500.00 0.00 2018-11-15 f Procurement Specialist for tant Selection tation 3 4 8 8 gthening MoWIE PMU by MoWIE ET-MOWIE-181047-CS-INDV / Selection and Employment Component 3: Project mana Individual Consul Under Implemen 2020-10-2 2020-08-2 2020-09-1 2020-10-2 2021-10-2 of one Additional Individual IDA / 60070 gement & institutional stren Prior Open 30,000.00 0.00 2020-07-08 tant Selection tation 8 6 6 1 1 Procurement Consultant for gthening Water Development Commis sion implemented by WDC ET-MOWIE-189851-CS-INDV / Selection and Employment Component 3: Project mana of Individual Consultant who Individual Consul Pending Impleme 2020-11-0 2020-11-2 2020-12-2 2021-12-2 IDA / 60070 gement & institutional stren Post Open 75,000.00 0.00 2020-09-15 provide support in selection tant Selection ntation 3 4 9 9 gthening of contractor and contract a dministration of 5 towns FST P DBO contract. ET-MOWIE-227402-CS-INDV Component 2: Sanitation an / Individual consultants for R d water supply services imp Individual Consul Under Implemen 2021-04-2 2021-06-1 2021-07-0 2021-08-0 2021-11-0 IDA / 60070 Post Open 14,034.00 0.00 2021-04-15 esettlement Action Plan (RA rovement in secondary citie tant Selection tation 2 3 4 8 6 P) Preparation for Hawassa s ET-MOWIE-282389-CS-INDV / Selection and Employment of Environmental engineer i Component 3: Project mana Individual Consul Under Implemen 2022-03-0 2022-03-2 2022-04-1 2022-05-1 2022-11-1 ndividual Consultant who pr IDA / 60070 gement & institutional stren Post Direct 9,000.00 0.00 2022-03-10 tant Selection tation 3 0 0 5 1 ovides technical support to t gthening he ongoing CWIS and DBO project delivery methods for the Ministry of Water and E nergy ET-MOWIE-282387-CS-CDS / Selection and Employment o f one Environmental engine Component 3: Project mana er /Hydrologist individual C Individual Consul Under Implemen 2022-03-1 2022-03-2 2022-04-1 2022-05-1 2022-11-1 IDA / 60070 gement & institutional stren Post Direct 9,000.00 0.00 2022-03-14 onsultant who provides tech tant Selection tation 5 4 4 9 5 gthening nical support to the ongoing CWIS and DBO project deli very methods for the Ministr y of Water and Energy ET-MOWIE-282262-CS-CDS / Selection and Employment o f one water supply and sanit Component 3: Project mana ary engineer individual Con Individual Consul Under Implemen 2022-03-1 2022-03-2 2022-04-1 2022-05-1 2022-11-1 IDA / 60070 gement & institutional stren Post Direct 9,000.00 0.00 2022-03-14 sultant who provides technic tant Selection tation 5 4 4 9 5 gthening al support to the ongoing C WIS and DBO project deliv ery methods for the Ministry of Water and Energy. ET-MOWIE-322413-CS-INDV / Selection and Employment Component 3: Project mana Individual Consul Under Implemen 2022-11-1 2022-11-2 2022-11-2 2022-12-1 2023-12-1 of M&E individual consultant IDA / 60070 gement & institutional stren Post Open - National 15,000.00 0.00 2022-10-25 tant Selection tation 5 7 8 3 3 for Second Urban Water Sup gthening ply and Sanitation Project ET-MOWIE-332119-CS-INDV Component 3: Project mana Individual Consul Under Implemen 2023-01-0 2023-02-0 2023-02-2 2023-03-2 2024-03-2 / Selection and employment IDA / 60070 gement & institutional stren Post Open - National 21,000.00 0.00 2022-12-30 tant Selection tation 3 8 2 9 8 of Procurement Specialist (IC gthening ) for MoWE ET-MOWIE-332134-CS-INDV Component 3: Project mana / Selection and employment Individual Consul Under Implemen 2023-02-0 2023-02-1 2023-03-1 2024-03-1 IDA / 60080 gement & institutional stren Post Open - National 15,000.00 0.00 2022-12-30 of Wastewater Management tant Selection tation 1 5 5 4 gthening Technical Specialist for MoW E ET-MOWIE-338955-CS-INDV / Selection of Individual Cons Component 3: Project mana Individual Consul Under Implemen 2023-01-3 2023-03-1 2023-03-2 2023-04-2 2024-04-2 ultant of Financial Managem IDA / 60070 gement & institutional stren Post Open - National 50,000.00 0.00 2023-01-31 tant Selection tation 0 8 8 6 5 ent for MoWE in place of Pre gthening vious Terminated Contract by MoWE ET-MOWIE-347468-CS-INDV / Selection and Employment Component 3: Project mana Individual Consul Pending Impleme 2023-03-1 2023-04-0 2023-05-0 2023-07-3 of three Individual Procure IDA / 60070 gement & institutional stren Post Limited 100,000.00 0.00 2023-03-14 tant Selection ntation 9 3 1 0 ment Consultant for upload gthening ing of procurement activitie s on the STEPs for the MOW E. Page 14