PROCUREMENT PLAN (Textual Part) Project information: Ukraine, Ukraine Improving Higher Education for Results Project (UIHERP), P171050 Project Implementation agency: Ministry of Education and Science of Ukraine Date of the Procurement Plan: October 2021 Period covered by this Procurement Plan: October 2021 – December 2026 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Law of Ukraine "On Public Procurement" introduced by Law of Ukraine № 114-IX dated 19 September 2019, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations - Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations - Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. - Not applicable PROCUREMENT Ukraine : Ukraine Improving Higher Education for Results Project PLAN General Information Country: Ukraine 2021-10-27 Bank’s Approval Date of the Original Procurement Plan: 2024-09-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171050 GPN Date: 2021-10-25 Project Name: Ukraine Improving Higher Education for Results Project Loan / Credit No: IBRD / 92380 Ministry of Education and Science of Ukraine Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOES-C1-EXAMS-01 LOT 1. NMT / Upgrade (additional de Sector-Wide Improvements t velopment) of the software f Request for Quota Single Stage - One E IBRD / 92380 o Governance, Financing, Qu Post Open - National 410,000.00 0.00 Completed 2023-02-27 2023-03-23 2023-05-13 2023-12-31 2024-03-27 or conducting the National M tions nvelope ality and Transparency ultisubject Test (NMT), Unifie d Professional Entrance Test (UPET), Unified entrance exa m (UEE) MOES-C1-EXAMS-01 LOT 2. Sector-Wide Improvements t USQE / Upgrade of the softw Request for Quota Single Stage - One E IBRD / 92380 o Governance, Financing, Qu Post Open - National 120,000.00 0.00 Completed 2023-02-27 2023-03-23 2023-05-13 2023-12-31 2024-04-04 are for conducting the Unifie tions nvelope ality and Transparency d State Qualification Exam (U SQE) MOES-C1-EDEBO-02 / Moder Sector-Wide Improvements t Request for Quota Single Stage - One E nization of the EDEBO hardw IBRD / 92380 o Governance, Financing, Qu Post Open - National 250,000.00 0.00 Completed 2023-10-17 2023-10-12 2023-11-17 2023-11-16 2024-01-30 2024-03-27 tions nvelope are ality and Transparency MOES-C1-EXAMS-05 EQUIP / Computers, network equipm Sector-Wide Improvements t Request for Quota Single Stage - One E ent and backup power syste IBRD / 92380 o Governance, Financing, Qu Post Open - National 40,000.00 0.00 Signed 2024-03-15 2024-03-22 2024-04-10 2024-05-23 2024-06-28 tions nvelope m for Ukrainian Center for Ed ality and Transparency ucational Quality Assessment (UCEQA) MOES-C4 ICT / Computers a Project Management, Monito Request for Quota Single Stage - One E IBRD / 92380 Post Open - National 25,000.00 0.00 Canceled 2024-03-20 2024-04-23 2024-05-31 nd office equipment for PIU ring & Evaluation tions nvelope MOES-C4 FUR / Office furnitu Project Management, Monito Request for Quota Single Stage - One E IBRD / 92380 Post Open - National 3,500.00 0.00 Signed 2024-03-20 2024-04-23 2024-05-14 2024-05-31 re ring & Evaluation tions nvelope MOES-C4 ICT-R / Computers Project Management, Monito Request for Quota Single Stage - One E Under Imple IBRD / 92380 Post Open - National 25,000.00 0.00 2024-04-23 2024-05-01 2024-05-21 2024-06-30 and office equipment for PIU ring & Evaluation tions nvelope mentation MOES-C1-EXAMS-05-3-R / Pr Sector-Wide Improvements t otection gateway for Ukrainia Request for Quota Single Stage - One E Under Imple IBRD / 92380 o Governance, Financing, Qu Post Open - National 9,000.00 0.00 2024-07-16 2024-07-19 2024-08-21 2024-10-20 n Center for Educational Qual tions nvelope mentation ality and Transparency ity Assessment (UCEQA) UIHERP-C2-MERGERS-08 / Pr Alliances and Partnerships fo Request for Quota Single Stage - One E IBRD / 92380 Post Open - National 7,310.00 0.00 Canceled 2024-07-31 2024-09-14 2024-10-31 ocurement of rotary evaporat r Improved Efficiency and Q tions nvelope ors uality MOES-UIHERP-C2-MERGERS- Alliances and Partnerships fo Request for Quota Single Stage - One E Under Imple 01 / Procurement of analytica IBRD / 92380 r Improved Efficiency and Q Post Open - National 381,550.00 0.00 2024-08-25 2024-08-21 2024-10-20 2025-05-18 tions nvelope mentation l laboratory and other equip uality ment. Part 1. MOES-UIHERP-C2-MERGERS- Alliances and Partnerships fo Request for Quota Single Stage - One E Under Imple 02 / Procurement of spectro IBRD / 92380 r Improved Efficiency and Q Post Open - National 107,320.00 0.00 2024-08-25 2024-08-21 2024-10-20 2025-01-18 tions nvelope mentation metry equipment. Part 1. uality MOES-UIHERP-C2-MERGERS- Alliances and Partnerships fo Request for Quota Single Stage - One E Under Imple 03 / Procurement of chromat IBRD / 92380 r Improved Efficiency and Q Post Open - National 407,390.00 0.00 2024-08-25 2024-08-21 2024-10-20 2025-01-18 tions nvelope mentation ography equipment. Part 1. uality MOES-UIHERP-C2-MERGERS- Alliances and Partnerships fo Request for Quota Single Stage - One E Under Imple 04 / Procurement of educatio IBRD / 92380 r Improved Efficiency and Q Post Open - National 541,700.00 0.00 2024-08-25 2024-08-21 2024-10-20 2025-04-18 tions nvelope mentation nal laboratories uality MOES-UIHERP-C2-MERGERS- Alliances and Partnerships fo Request for Quota Single Stage - One E Under Imple 05 / Procurement of a power IBRD / 92380 r Improved Efficiency and Q Post Open - National 21,280.00 0.00 2024-08-25 2024-08-21 2024-10-20 2025-02-17 tions nvelope mentation quality analyzer uality MOES-UIHERP-C2-MERGERS- 06 / Procurement of a potenti Alliances and Partnerships fo Request for Quota Single Stage - One E Under Imple ostat / galvanostat equipped IBRD / 92380 r Improved Efficiency and Q Post Open - National 25,360.00 0.00 2024-08-25 2024-08-21 2024-10-20 2025-02-17 tions nvelope mentation with an impedance measure uality ment module and analytical cell MOES-UIHERP-C2-MERGERS- Alliances and Partnerships fo 07 / Procurement of an electr Request for Quota Single Stage - One E Under Imple IBRD / 92380 r Improved Efficiency and Q Post Open - National 519,460.00 0.00 2024-08-25 2024-08-21 2024-10-20 2025-02-17 on scanning microscope with tions nvelope mentation uality an energy dispersive spectro meter MOES-UIHERP-C2-MERGERS- Alliances and Partnerships fo Request for Quota Single Stage - One E Under Imple 08 / Procurement of a high-te IBRD / 92380 r Improved Efficiency and Q Post Open - National 55,470.00 0.00 2024-08-25 2024-08-21 2024-10-20 2024-12-19 tions nvelope mentation mperature chamber furnace uality NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MOES-C1-EDEBO-01 / Moder Sector-Wide Improvements t nization of the unified state e IBRD / 92380 o Governance, Financing, Qu Post Direct Selection Direct - National 463,709.30 0.00 Completed 2023-03-07 2023-02-23 2023-03-09 2023-03-24 2023-03-21 2023-05-11 2024-03-20 2023-10-08 lectronic database on educati ality and Transparency on (EDEBO) software MOES-C1-EXAMS-02 DBQ / C Sector-Wide Improvements t reation of banks of tasks (con Request for Quota Single Stage - One E IBRD / 92380 o Governance, Financing, Qu Post Open - National 185,774.62 0.00 Completed 2023-03-21 2023-04-09 2023-05-12 2024-01-31 2024-03-30 tent) for the Unified Professio tions nvelope ality and Transparency nal Entrance Test MOES-C4-10-1 EXPERTISE / I ndependent assessment of e Project Management, Monito IBRD / 92380 Post Direct Selection Direct - National 6,000.00 0.00 Completed 2023-10-04 2023-10-12 2023-10-16 2024-01-12 2023-10-23 2024-01-15 2024-02-14 2024-03-08 xclusive property rights to an ring & Evaluation object of intellectual property MOES-C4-10-2 EXPERTISE / I ndependent assessment of e Project Management, Monito IBRD / 92380 Post Direct Selection Direct - National 12,000.00 0.00 Completed 2023-11-16 2023-11-15 2023-11-22 2023-11-20 2023-12-10 2024-02-01 2024-02-28 2024-04-25 xclusive property rights to an ring & Evaluation object of intellectual property MOES-C1-EXAMS-03 DBQMS / Development of software of Sector-Wide Improvements t Request for Quota Single Stage - One E the "Bank of test tasks" Mod IBRD / 92380 o Governance, Financing, Qu Post Open - National 145,000.00 0.00 Canceled 2024-01-08 2024-01-10 2024-03-06 2024-08-31 tions nvelope ule for the software of the Un ality and Transparency ified State Qualification Exam (USQE) in 2024 MOES-C1-EXAMS-04 NMT/2 / Modernization (additional de velopment) of software base d on the Open edX platform Sector-Wide Improvements t Request for Quota Single Stage - One E of the National Multisubject T IBRD / 92380 o Governance, Financing, Qu Post Open - National 550,000.00 0.00 Signed 2024-03-08 2024-03-11 2024-03-31 2024-04-12 2025-01-31 tions nvelope est (NMT), Unified Profession ality and Transparency al Entrance Test (UPET), Unifi ed entrance exam (UEE) and Unified State Qualification Ex am (USQE) in 2024 MOES-C1-EXAMS-04 USQE/2 / Modernization (additional d Sector-Wide Improvements t Request for Quota Single Stage - One E evelopment) of the software IBRD / 92380 o Governance, Financing, Qu Post Open - National 330,000.00 0.00 Signed 2024-03-08 2024-03-11 2024-03-31 2024-04-12 2025-03-31 tions nvelope of the Unified State Qualificat ality and Transparency ion Exam (USQE) in 2024 MOES-C1-EXAMS-03 DBQMS- R / Development of software Sector-Wide Improvements t Request for Quota Single Stage - One E of the "Bank of test tasks" M IBRD / 92380 o Governance, Financing, Qu Post Open - National 145,000.00 0.00 Signed 2024-03-15 2024-03-22 2024-04-10 2024-04-25 2024-09-30 tions nvelope odule for the software of the ality and Transparency Unified State Qualification Ex am (USQE) in 2024 MOES-C1-EDEBO-01/2 / Mod Sector-Wide Improvements t ernization of the unified state Request for Quota Single Stage - One E IBRD / 92380 o Governance, Financing, Qu Post Open - National 1,400,000.00 0.00 Signed 2024-04-09 2024-04-10 2024-04-24 2024-05-07 2025-05-31 electronic database on educa tions nvelope ality and Transparency tion (EDEBO) software in 202 4 MOES-C1-SCI-01 / System of reporting on completed rese Sector-Wide Improvements t arch and/or developments fin Request for Quota Single Stage - One E Under Imple IBRD / 92380 o Governance, Financing, Qu Post Open - National 80,000.00 0.00 2024-04-25 2024-05-02 2024-05-22 2025-05-31 anced from the state budget tions nvelope mentation ality and Transparency of Ukraine under the budget programs of the Ministry of E ducation and Science of Ukra ine CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOES-C3 TRAINING / Develo Capacity Building and Educa Quality And Cost- Open - Internationa pment and implementation o IBRD / 92380 tion Environment Enhancem Prior 950,000.00 0.00 Under Review 2023-12-25 2024-02-20 2024-01-15 2024-02-27 2024-02-13 2024-06-03 2024-03-12 2024-07-08 2024-03-27 2024-04-13 2024-04-30 2026-10-29 Based Selection l f a training program for acad ent emic managers INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOES-IC-01 / Position of Proj Project Management, Monito Individual Consult ect Manager – Lead of group IBRD / 92380 Prior Open 213,500.00 205,800.00 Terminated 2021-10-28 2021-10-27 2021-11-17 2022-01-21 2021-11-24 2022-02-11 2021-12-01 2022-02-24 2026-12-31 ring & Evaluation ant Selection of consultants MOES-IC-03 / Procurement S Project Management, Monito Individual Consult IBRD / 92380 Post Open 62,500.00 62,496.00 Terminated 2021-11-15 2021-11-18 2021-12-01 2022-01-24 2021-12-02 2022-01-24 2021-12-03 2022-02-12 2023-12-31 pecialist ring & Evaluation ant Selection MOES-IC-02 / Financial Mana Project Management, Monito Individual Consult IBRD / 92380 Post Open 62,500.00 62,496.00 Terminated 2021-11-10 2021-11-19 2021-11-29 2022-01-24 2021-11-30 2022-01-24 2021-12-01 2022-02-23 2023-12-31 2022-12-14 gement Specialist ring & Evaluation ant Selection MOES-IC-05 / Social and Envi Project Management, Monito Individual Consult IBRD / 92380 Post Open 60,000.00 0.00 Canceled 2022-01-14 2022-01-18 2022-02-08 2022-02-09 2022-02-15 2024-02-15 ronmental Compliance Speci ring & Evaluation ant Selection alist MOES-IC-04 / Communicatio Project Management, Monito Individual Consult IBRD / 92380 Post Open 60,000.00 0.00 Canceled 2022-01-14 2022-01-18 2022-02-08 2022-02-09 2022-02-15 2024-02-15 n Specialist ring & Evaluation ant Selection MOES-IC-06 / IT architect an Individual Consult d Information-Communicatio IBRD / 92380 Post Open 174,000.00 0.00 Canceled 2022-01-24 2022-02-02 2022-02-18 2022-02-19 2022-02-25 2026-12-31 ant Selection n Technologies Development Manager MOES-IC-07 / Legal Specialis Project Management, Monito Individual Consult IBRD / 92380 Post Open 150,800.00 0.00 Canceled 2022-01-25 2022-02-01 2022-02-19 2022-02-20 2022-02-26 2026-12-31 t ring & Evaluation ant Selection MOES-IC-04-2 / Communicati Project Management, Monito Individual Consult IBRD / 92380 Post Open 60,000.00 0.00 Canceled 2022-01-26 2022-01-27 2022-02-20 2022-02-21 2022-02-27 2024-02-27 ons and Outreach Specialist ring & Evaluation ant Selection MOES-IC-08 / Project Assista Project Management, Monito Individual Consult IBRD / 92380 Post Open 48,000.00 0.00 Canceled 2022-02-17 2022-02-23 2022-04-07 2022-04-28 2022-06-02 2024-06-01 nt ring & Evaluation ant Selection MOES-IC-01-PM / Project Ma Project Management, Monito Individual Consult IBRD / 92380 Prior Open 213,500.00 0.00 Under Review 2022-07-08 2022-07-19 2022-07-25 2022-10-12 2022-08-01 2022-10-21 2022-08-08 2022-10-25 2026-12-31 nager – Lead of group of con ring & Evaluation ant Selection sultants Page 2 MOES-IC-03 PS / Procuremen Project Management, Monito Individual Consult IBRD / 92380 Post Open 62,500.00 0.00 Signed 2022-07-08 2022-07-18 2022-07-25 2022-11-14 2022-08-01 2022-11-16 2022-08-08 2023-01-24 2024-08-07 t Specialist ring & Evaluation ant Selection MOES-IC-04-COS / Communi Project Management, Monito Individual Consult Open - Internationa IBRD / 92380 Post 60,000.00 0.00 Completed 2022-08-10 2022-08-22 2022-09-08 2022-11-14 2022-09-13 2022-12-09 2022-09-18 2022-12-21 2024-09-17 2023-05-28 cations and Outreach Special ring & Evaluation ant Selection l ist MOES-IC-05-SECS / Social an Project Management, Monito Individual Consult Open - Internationa d Environmental Compliance IBRD / 92380 Post 60,000.00 0.00 Completed 2022-08-10 2022-08-22 2022-09-08 2022-11-14 2022-09-13 2022-12-09 2022-09-18 2022-12-21 2024-09-17 2024-03-31 ring & Evaluation ant Selection l Specialist MOES-IC-10-ITM1 / IT Produc Project Management, Monito Individual Consult IBRD / 92380 Post Open - National 65,000.00 0.00 Signed 2022-11-22 2022-12-07 2022-12-13 2023-02-07 2022-12-18 2023-02-22 2023-01-01 2023-04-04 2024-12-31 t manager ring & Evaluation ant Selection MOES-IC-10-ITM2 / IT Produc Project Management, Monito Individual Consult IBRD / 92380 Post Open - National 65,000.00 0.00 Signed 2022-11-22 2022-12-07 2022-12-13 2023-02-07 2022-12-18 2023-02-22 2023-01-01 2023-04-04 2024-12-31 t manager ring & Evaluation ant Selection MOES-IC-07-LS / Legal Speci Project Management, Monito Individual Consult IBRD / 92380 Post Open - National 65,000.00 0.00 Signed 2022-12-16 2022-12-27 2023-01-08 2023-02-07 2023-01-13 2023-02-22 2023-01-19 2023-04-04 2025-01-18 alist ring & Evaluation ant Selection MOES-IC-08-PA / Project assi Project Management, Monito Individual Consult IBRD / 92380 Post Open - National 48,000.00 0.00 Signed 2022-12-16 2022-12-27 2023-01-09 2023-02-07 2023-01-14 2023-02-22 2023-01-19 2023-04-04 2025-01-18 stant ring & Evaluation ant Selection Sector-Wide Improvements t UIHERP-IC-12-ES / Education Individual Consult IBRD / 92380 o Governance, Financing, Qu Post Direct - National 49,920.00 0.00 Signed 2023-03-07 2023-02-24 2023-03-14 2023-04-14 2023-03-17 2023-05-04 2023-03-20 2023-05-11 2025-03-19 specialist ant Selection ality and Transparency MOES-IC-04-COS-2 / Speciali Project Management, Monito Individual Consult st in communication issues a IBRD / 92380 Post Open - National 37,500.00 0.00 Completed 2023-10-04 2023-10-12 2023-11-02 2023-11-06 2023-11-03 2023-11-20 2023-11-08 2023-12-05 2025-02-06 2024-02-29 ring & Evaluation ant Selection nd information coverage MOES-C3-05-SUP-IC-02 / Onli Capacity Building and Educa Individual Consult IBRD / 92380 Post Direct - National 31,200.00 0.00 Signed 2023-10-04 2023-10-12 2023-10-10 2023-10-16 2023-10-11 2023-11-22 2023-11-16 2023-11-24 2024-12-31 ne Education Specialist tion Environment Enhancem ant Selection ent MOES-IC-02-FMS / Financial Project Management, Monito Individual Consult IBRD / 92380 Post Open - National 62,500.00 0.00 Canceled 2022-12-23 2023-03-22 2023-01-28 2023-02-04 2023-02-14 2025-02-13 management specialist ring & Evaluation ant Selection MOES-C3-05-SUP-IC-01 / Spe Capacity Building and Educa Individual Consult cialist in Legislative Develop IBRD / 92380 tion Environment Enhancem Post Open - National 5,000.00 0.00 Completed 2023-10-04 2023-10-13 2023-11-02 2023-12-04 2023-11-03 2023-12-12 2023-11-08 2023-12-21 2023-12-29 2024-03-14 ant Selection ment for Higher Education Re ent form MOES-IC-02-FMS-R / Financia Project Management, Monito Individual Consult IBRD / 92380 Post Open - National 62,500.00 0.00 Signed 2023-10-20 2023-10-13 2023-11-12 2023-11-06 2023-11-19 2023-11-20 2023-11-25 2023-11-24 2025-11-24 l Management Specialist. Re- ring & Evaluation ant Selection selection. MOES-IC-15-IMP / Implement ation Manager for the Educat Project Management, Monito Individual Consult IBRD / 92380 Post Open - National 65,000.00 0.00 Signed 2023-11-09 2023-11-15 2023-12-03 2023-12-22 2023-12-10 2024-02-05 2023-12-20 2024-03-13 2025-12-31 ion Environment and Infrastr ring & Evaluation ant Selection ucture Enhancement MOES-C3-05-SUP-IC-03 / Dat Capacity Building and Educa Individual Consult IBRD / 92380 Post Open - National 24,000.00 0.00 Canceled 2023-12-25 2024-01-10 2024-01-26 2024-04-08 2024-02-02 2024-02-08 2026-02-07 a Analyst tion Environment Enhancem ant Selection ent MOES-IC-14-TRAINING / Coor Project Management, Monito Individual Consult Open - Internationa Under Implement dinator of the Academic Man IBRD / 92380 Post 65,000.00 0.00 2024-03-19 2024-04-02 2024-04-15 2024-04-20 2024-04-30 2025-12-31 ring & Evaluation ant Selection l ation agers Training MOES-IC-05 SECS-2 / Special Project Management, Monito Individual Consult Open - Internationa IBRD / 92380 Post 60,000.00 0.00 Canceled 2024-04-05 2024-04-15 2024-05-05 2024-05-19 2024-05-27 2026-05-26 ist in environmental and soci ring & Evaluation ant Selection l al issues MOES-C3-05-SUP-IC-04 / Spe cialist for Development of Inn Capacity Building and Educa Individual Consult Under Implement ovation Ecosystem and Inter IBRD / 92380 tion Environment Enhancem Post Open - National 40,000.00 0.00 2024-04-23 2024-04-23 2024-05-22 2024-05-17 2024-06-01 2024-05-27 2024-06-07 2026-01-01 ant Selection ation national Science, Technology ent and Innovation (STI) Coopera tion MOES-C3-05-SUP-IC-05 / Spe Capacity Building and Educa Individual Consult Under Implement cialist for Development and IBRD / 92380 tion Environment Enhancem Post Open - National 40,000.00 0.00 2024-04-23 2024-04-23 2024-05-22 2024-05-17 2024-06-01 2024-05-30 2024-06-07 2026-01-01 ant Selection ation Management of Research Infr ent astructure MOES-C1-COM-01 / Developi Sector-Wide Improvements t Individual Consult Under Implement ng Communication Strategy IBRD / 92380 o Governance, Financing, Qu Post Open - National 70,000.00 0.00 2024-04-29 2024-04-29 2024-05-25 2024-05-17 2024-05-30 2024-05-23 2024-06-05 2024-08-31 ant Selection ation on Transforming the Higher E ality and Transparency ducation MOES-C3-05-SUP-IC-06 / Spe Capacity Building and Educa Individual Consult Under Implement cialist for HEIs’ Network Opti IBRD / 92380 tion Environment Enhancem Post Open - National 47,500.00 0.00 2024-05-22 2024-05-23 2024-06-15 2024-06-22 2024-07-01 2026-01-01 ant Selection ation mization and Institutional Ref ent orm Support MOES-IC-04-COS-3 / Speciali Project Management, Monito Individual Consult Under Implement st in communication issues a IBRD / 92380 Post Open - National 47,500.00 0.00 2024-05-22 2024-06-05 2024-06-17 2024-06-27 2024-07-06 2025-12-31 ring & Evaluation ant Selection ation nd information coverage MOES-IC-16-SSE / Social and Project Management, Monito Under Implement IBRD / 92380 Post Direct Selection Direct - National 36,000.00 0.00 2024-07-14 2024-07-31 2024-07-22 2024-08-10 2026-07-31 Stakeholder Engagement Sp ring & Evaluation ation ecialist MOES-IC-08-PA-2 / Project As Project Management, Monito Individual Consult Under Implement IBRD / 92380 Post Open - National 30,000.00 0.00 2024-07-14 2024-07-08 2024-08-14 2024-08-17 2024-08-29 2025-12-31 sistant ring & Evaluation ant Selection ation MOES-C3-05-SUP-IC-03-R / D Capacity Building and Educa Individual Consult Under Implement IBRD / 92380 Post Open - National 42,500.00 0.00 2024-07-15 2024-07-25 2024-08-15 2024-08-18 2024-08-30 2025-12-31 ata Analyst tion Environment Enhancem ant Selection ation ent MOES-IC-17-OHS / Environm Project Management, Monito Individual Consult Under Implement ental and Occupational Healt IBRD / 92380 Post Open - National 70,000.00 0.00 2024-08-21 2024-08-22 2024-09-14 2024-09-17 2024-10-04 2026-12-31 ring & Evaluation ant Selection ation h and Safety Specialist MOES-IC-13-MON / Monitorin Project Management, Monito Under Implement IBRD / 92380 Post Direct Selection Direct - National 70,000.00 0.00 2024-09-11 2024-09-12 2024-09-16 2024-10-01 2026-12-31 g and evaluation specialist ring & Evaluation ation MOES-C3-05-SUP-IC-07 / Spe Capacity Building and Educa Individual Consult Pending Impleme cialist in Supporting Student IBRD / 92380 tion Environment Enhancem Post Open - National 30,000.00 0.00 2024-09-18 2024-10-14 2024-10-21 2024-10-31 2025-12-31 ant Selection ntation Self-Governance ent MOES-C3-05-SUP-IC-08 / Inte Capacity Building and Educa Individual Consult Pending Impleme IBRD / 92380 Post Open - National 37,500.00 0.00 2024-09-18 2024-10-14 2024-10-21 2024-10-31 2025-12-31 rnational Cooperation Special tion Environment Enhancem ant Selection ntation ist ent MOES-C1-COM-02 / Specialis Sector-Wide Improvements t Individual Consult Pending Impleme t in communication and outre IBRD / 92380 o Governance, Financing, Qu Post Open - National 25,500.00 0.00 2024-09-18 2024-10-14 2024-10-21 2024-10-31 2025-12-31 ant Selection ntation ach for science in HEIs ality and Transparency Page 3