Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 10, 2017 (Original procurement plan). 2. Date of General Procurement Notice: NA 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. Goods Above US$ 4 million All 2. Works Above US$ 15 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. NA. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: The Project Implementation Manual (PIM) makes reference to all applicable procurement guidelines and manuals including the Commune/Sangkat Fund PIM for small-scale infrastructure activities carried out by the sub-national levels (Commune/Sangkat), has been developed for this project. 4. Any Other Special Procurement Arrangements: 5 packages (goods) would be financed under retroactive financing 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comments No. on ed stic by Bank Cost Prefe (Prior / US$ rence Post) million (yes/ no) Communi 5.48 60 No Post procured by ty Communes/ June 12, 2017 infrastruc Sangkats tures individually for the whole life of the project Procure 0.92 8 No Post will be ment of procured vehicles, centrally at office the beginning of equipme project nt, office implementa furniture, tion motorcyc (shopping les, etc. method) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Selection of Consulting firms Above US$ 2 million All 2. Selection of Individual Above US$ All Consultant 400,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 11 individual consultants would be financed through retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 6 7 Ref. Description Estimate Pac Review Comments No. d kag by Bank Cost es (Prior / US$ Post) million Producer Group 0.34 1 Post QCBS method Mobilization for June 12, 2017 Siem Reap (NGO package) Self-help Group 0.27 1 Post QCBS method Mobilization for SRP (NGO) Human Resources 0.92 2 Post QBS method Development Services Provider (HRDSP) for Siem Reap (NGO/Firm) Consulting firms for 0.175 1 Post CQS method baseline survey, impact survey, and final impact survey, and External financial auditing Individual 2.93 126 Post Selection of consultants for individual supporting the consultant. national level and sub-national level project entities (finance, procurement, infrastructure, community development, micro-finance experts, livelihood specialists, etc.) June 12, 2017 PROCUREMENT Cambodia : KH - Livelihood Enhancement and Association of the Poor Project (LEAP) PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2017-06-12 Revised Plan Date(s): (comma delineated, leave blank if2023-09-26 none) Project ID: P153591 GPN Date: Project Name: KH - Livelihood Enhancement and Association of the Poor Project (LEAP) Loan / Credit No: IDA / 59600 Ministry of Interior Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approac Procurement Pr Prequalification High SEA/SH Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Contract Comple Description Component Review Type Method Document Typ Amount (U mount (U t and Recommendati Signed Contract No. h ocess (Y/N) Risk tatus n Documents uation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes tion e S$) S$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KH-MOI-99874-CW-RFQ / Offi Component 3: Project Manag Request for Quota Single Stage - One E Pending Im 2019-05-1 IDA / 59600 Post Open - National 30,000.00 0.00 2019-03-06 2019-04-17 ce Renovation at PCO-MOI ement tions nvelope plementatio 7 n KH-MOI-99875-CW-CDD / Th e rehabilitation laterite road ( Component 1: Improving Liv Pending Im Length 2400m, Width 4.00m, Community Drive 2019-09-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National 28,341.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 0.15m thick) and Single Pipe n Development 9 ulnerable Households n Culvert Ø 1.0m (2 units) for A nlong Samnar, Chi Kraeng. KH-MOI-99886-CW-CDD / Th e rehabilitation laterite road ( Component 1: Improving Liv Pending Im Length 1500m, Width 4.00m, Community Drive 2019-08-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National 29,208.00 0.00 plementatio 2019-03-01 2019-03-08 2019-04-30 2019-05-07 2019-05-21 0.15m Thick) and Constructio n Development 9 ulnerable Households n n of Box Culver heigth 2m wit h Stop Log (1 unit) for Doun K aev, Puok. KH-MOI-99878-CW-CDD / Th Component 1: Improving Liv Pending Im e rehabilitation laterite road ( Community Drive 2019-07-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National 25,921.00 0.00 plementatio 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 Length 2419m, Width 3.50m, n Development 1 ulnerable Households n 0.15m thick) for Chi Kraeng, Chi Kraeng. KH-MOI-99880-CW-CDD / Th e rehabilitation laterite road ( Length 2090m, Width 4.00m, Component 1: Improving Liv Pending Im 0.15m thick) and Constructio Community Drive 2019-07-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,721.00 0.00 plementatio 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 n of Single Pipe Culvert Ø 0.6 n Development 1 ulnerable Households n m (1 unit), Single Pipe Culver t Ø 0.8m (1 unit) and Single P ipe Culvert Ø 1.0m (1unit) fo r Dan Run, Soutr Nikom. KH-MOI-99881-CW-CDD / Th e rehabilitation laterite road ( Length 1550m, Width 4.00m, Component 1: Improving Liv Pending Im Community Drive 2019-09-1 0.15m thick), Single Pipe Cul IDA / 59600 elihoods for Rural Poor and V Post Open - National 29,965.00 0.00 plementatio 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 n Development 9 vert Ø 1.0m (1unit) and Cons ulnerable Households n truction of Double Pipe Culve rt Ø 0.8m (5units), for Ballan gk, Prasat Bakong. KH-MOI-99887-CW-CDD / Co nstruction of Box Culvert heig th 2m with stop Log (1unit), Component 1: Improving Liv Pending Im Community Drive 2019-09-0 Box Culvert heigth 1.5m with IDA / 59600 elihoods for Rural Poor and V Post Open - National 29,896.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 stop Log (1unit) Pipe Culver ulnerable Households n Ø 0.8m with Stop Log (1unit) and Single Pipe Culvert Ø 0.8 m (4 unit) for Sasar Sdam, P uok. KH-MOI-99888-CW-CDD / Co nstruction of Reinforced Conc Component 1: Improving Liv Pending Im Community Drive 2019-09-0 rete Road (Lengh 260m, widt IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,417.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 h 5.00m, 0.15m thick) for Ka ulnerable Households n mpong Thkov, Kralanh. Total: 0.260 km KH-MOI-99890-CW-CDD / Th e rehabilitation ponds size (6 Component 1: Improving Liv Pending Im Community Drive 2019-07-1 0mx30mx5m), (30mx25mx5 IDA / 59600 elihoods for Rural Poor and V Post Open - National 29,949.00 0.00 plementatio 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 n Development 1 m), (40mx20mx5m), (50mx5 ulnerable Households n 0mx5m) for Slaeng Spean, Sr ei Snam. Total:4 Places KH-MOI-99891-CW-CDD / Th e rehabilitation laterite road ( Component 1: Improving Liv Pending Im Community Drive 2019-09-0 1.450km) and Single Pipe Cul IDA / 59600 elihoods for Rural Poor and V Post Open - National 32,660.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 vert Ø 1.0m (3 units) for Svay ulnerable Households n Chek, Angkor Thum. KH-MOI-99892-CW-CDD / Th e rehabilitation laterite road ( Component 1: Improving Liv Pending Im Length 2520m, Width 4.00m, Community Drive 2019-09-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National 34,064.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 0.15 Thick) and Construction n Development 9 ulnerable Households n of Single Pipe Culvert Ø 1.0m (2 unit) for Leang Dai, Angkor Thum. KH-MOI-99893-CW-CDD / Th e rehabilitation laterite road ( Length 1080m, Width 4.00m, Component 1: Improving Liv Pending Im Community Drive 2019-08-0 0.15m thick) and Constructio IDA / 59600 elihoods for Rural Poor and V Post Open - National 27,869.20 0.00 plementatio 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-05-07 n Development 5 n of Single Pipe Culvert Ø 0.8 ulnerable Households n m (1 unit) and Triple Pipe Cul vert, Ø 1.0m (3 unit) for Ta S iem, Svay Leu. KH-MOI-99894-CW-CDD / Co nstruction of Reinforced Conc Component 1: Improving Liv Pending Im Community Drive 2019-09-0 rete Road (Length 445m, Wi IDA / 59600 elihoods for Rural Poor and V Post Open - National 48,510.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 dth 3.50m, 0.15m thick) for ulnerable Households n khnang Phnum, Svay Leu. KH-MOI-99889-CW-CDD / Th e rehabilitation laterite road ( Component 1: Improving Liv Pending Im Community Drive 2019-09-0 Length 2600m, Width 5.00m, IDA / 59600 elihoods for Rural Poor and V Post Open - National 29,932.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 0.15m thick) for Klang Hay, S ulnerable Households n rei Snam. Total: 2.600 km KH-MOI-110153-CW-CDD / C onstruction:1- Reinforcement concrete road:(L353m, W 4m Component 1: Improving Liv Pending Im Community Drive 2019-09-0 , T0.15m) and drainage syste IDA / 59600 elihoods for Rural Poor and V Post Open - National 89,712.00 0.00 plementatio 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 n Development 9 m (L353m, 0.6m ) and 2-Rein ulnerable Households n forcement concrete road (L35 7m, W 4m, T 0.15m) in Sangk at Dangkao, Khan Dangkao KH-MOI-110154-CW-CDD / C onstruction of Reinforcement concrete road and Drainage Component 1: Improving Liv Pending Im System: 1- Road (100m) , 2- Community Drive 2019-09-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 98,080.00 0.00 plementatio 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 Road (171m ), 3-Road (52m), n Development 4 ulnerable Households n 4- Road(88m) ,5- Road (90m) , 6- Road (93m) and 7-Road ( L128m) in Sangkat Prey Veae ng, Khan Dangkao KH-MOI-110159-CW-CDD / C onstruction of reinforcement concrete road:(466m, width 5 Component 1: Improving Liv Pending Im Community Drive 2019-09-2 m, thickness 0.15m ), 2-Road IDA / 59600 elihoods for Rural Poor and V Post Open - National 105,204.00 0.00 plementatio 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 n Development 4 :(312m, width 4m, thickness ulnerable Households n 0.15m ) and drainage system :(312m,cross section 0.6m) in Sangkat Kork Roka, Khan Pre ak Pnov KH-MOI-110165-CW-CDD / C onstruction of reinforcement concrete road and and draina Component 1: Improving Liv Pending Im ge system in Prey Spueu & Pr Community Drive 2019-10-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National 84,579.00 0.00 plementatio 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 ey Sandaek, Sangkat Chaom n Development 9 ulnerable Households n Chau 2, Khan Por Sen Chey ( 663m) and drainage system ( 523m) in Sangkat Chaom Ch au 2, Khan Por Sen Chey KH-MOI-110174-CW-CDD / C onstruction of reinforcement concrete: 1- Road(124m), 2- Component 1: Improving Liv Pending Im Community Drive 2019-10-0 Road (137m). 3- Road (117m IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,250.00 0.00 plementatio 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 n Development 9 ). 4-Installation of Sola street ulnerable Households n lighting and poles (117m), an d (139m ) in Sangkat Chbar A mpov Ti Pir, Khan Chbar Amp ov KH-MOI-110155-CW-CDD / C onstruction of reinforcement concrete: 1- Road (99m) ,1- R oad(101m), 2-Road(60m), 3- Component 1: Improving Liv Pending Im Community Drive 2019-12-2 Drainage system:(9m), 4-Inst IDA / 59600 elihoods for Rural Poor and V Post Open - National 28,703.49 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 allation of Sola street lighting ulnerable Households n and poles (120m),(439m),(43 9m) and (98m) in Sangkat Ch rang Chamreas Ti Muoy,Khan Russey Keo Page 1 KH-MOI-110151-CW-CDD / C onstruction: 1-Reinforcement concrete road (340m) and dr ainage system:(448m), 2-Roa Component 1: Improving Liv Pending Im Community Drive 2019-12-2 d (L130m) and drainage syst IDA / 59600 elihoods for Rural Poor and V Post Open - National 171,670.08 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 em (130m), 3-Road (120m) a ulnerable Households n nd drainage system:(250m), 4- Road (238m) and drainage system (238m) in Sangkat Tr apeang Krasang, Khan Por Se n Chey KH-MOI-110147-CW-CDD / C onstruction:1-Reinforcement concrete road, Drainage (L17 1m),Installation of Sola street Component 1: Improving Liv Pending Im Community Drive 2019-12-2 lighting and poles(171m), 2-R IDA / 59600 elihoods for Rural Poor and V Post Open - National 43,476.23 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 einforcement concrete road( ulnerable Households n 147m),drainage(48m), Install ation of Sola street lighting a nd poles (147m) in Sangkat K hmuonh, Khan Saen Sokh KH-MOI-110144-CW-CDD / C onstruction: 1-Reinforcement concrete road:(L262m, w 2.6 m, T 0.12m) ,Drainage syste Component 1: Improving Liv Pending Im Community Drive 2019-12-2 m:(262m,0.6m), 2- Installatio IDA / 59600 elihoods for Rural Poor and V Post Open - National 71,818.97 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 n:(18 Sola street lighting and ulnerable Households n poles for 262m) and 3-Concr ete bridge: (L206m, width1.5 0m, T0.07m) in Sangkat Srah Chak, Khan Daun Penh KH-MOI-110162-CW-CDD / C onstruction of reinforcement concrete:1- road:(L102m, wid Component 1: Improving Liv Pending Im th 2.5m, thickness 0.12m) an Community Drive 2019-12-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 37,878.83 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 d drainage system:(114m).2- n Development 5 ulnerable Households n road:(169m, width 3.5m, thic kness 0.15m) and drainage s ystem:(169m) in Sangkat Bo eng Kak 1, Khan Tuol Kork KH-MOI-110173-CW-CDD / C onstruction of reinforcement concrete: 1- Road(110m, widt Component 1: Improving Liv Pending Im Community Drive 2019-12-2 h 4m, thickness 0.15m), 2- R IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,281.06 0.00 plementatio 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 n Development 5 oad(100m),2-Installation of S ulnerable Households n ola street lighting and poles ( 250m) in Khtor,Sangkat Prea k Leap, Khan Chroy Changvar KH-MOI-110168-CW-CDD / C onstruction of reinforcement concrete:1- road(158m) and drainage (138m), 2-Road and Component 1: Improving Liv Pending Im Community Drive 2019-10-0 drainage system (77m),3- roa IDA / 59600 elihoods for Rural Poor and V Post Open - National 73,334.73 0.00 plementatio 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 n Development 9 d(261m) and drainage (207m ulnerable Households n ),4-Installation of Sola street l ighting and poles(158m), (77 m)and (261m) in Sangkat Ch ak Angrae Leu, Khan Mean C hey KH-MOI-140916-CW-CDD / R Component 1: Improving Liv Pending Im epair Dike 78 for Sangkat Kra Community Drive 2020-02-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,005.00 0.00 plementatio 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 bei Riel, Siem Reap Municipal n Development 7 ulnerable Households n ity ( Size 2.95Km length, 4.00 m width, 2.00m height) KH-MOI-140917-CW-CDD / C onstruction of Reinforced Con Component 1: Improving Liv Pending Im Community Drive 2020-02-2 crete Road for Kampong Khle IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,248.00 0.00 plementatio 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 n Development 7 ang Commune, Sotr Nikom Di ulnerable Households n strict ( Size 0.25Km length, 5. 00m width, 0.15m thick) KH-MOI-140918-CW-CDD / U pgrade Earth Road to Laterite Pavement for Sangkat Chong Component 1: Improving Liv Pending Im Khneas, Siem Reap Municipal Community Drive 2020-02-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 27,191.00 0.00 plementatio 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 ity ( Size 0.80Km length, 4.00 n Development 7 ulnerable Households n m width, 0.15m thick), includi ng 1 unit of culvert constructi on, 0.60m Diameter, 16.00m length. KH-MOI-146743-CW-CDD / Di gging Community Pond one p lace (size 100mx75mx6.00m) including fence construction Component 1: Improving Liv Pending Im Community Drive 2020-04-1 and Earth Dam with laterite p IDA / 59600 elihoods for Rural Poor and V Post Open - National 45,730.00 0.00 plementatio 2019-12-06 2019-12-13 2019-12-27 2020-01-03 2020-01-17 n Development 6 avement 4.00 meter width, 2 ulnerable Households n .00 meter heigh surrounding the pond and 2 reinforced co ncrete stairs, access laterite r oad 170m length, 4.00m wid KH-MOI-146745-CW-CDD / U nlined Earth Canal Rehabilitat ion with 1500m Length, 2m b ed, 1.60m Depth including th Component 1: Improving Liv Pending Im Community Drive 2020-04-1 e Construction of Cented Cau IDA / 59600 elihoods for Rural Poor and V Post Open - National 41,288.00 0.00 plementatio 2019-12-06 2019-12-13 2019-12-27 2020-01-03 2020-01-17 n Development 6 seway with pipe 0.80m diam ulnerable Households n eter, 8m length, 4m width 5 places and Construction of Tr apezoidal Section Lined Conc rete canal with 16m length, 2 KH-MOI-162028-CW-CDD / E arth Road Repair and Laterite Pavement 2 lines for Sangkat Svay Dangkum, Siem Reap M Component 1: Improving Liv Pending Im Community Drive 2020-07-2 unicipality (For line 1: 0.87 K IDA / 59600 elihoods for Rural Poor and V Post Open - National 22,511.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 m length, 4.00 m width, 0.15 ulnerable Households n m thick including 1 unit of sin gle culvert construction, 1.00 m Diameter, 7.00m length ( F or line 2: 0.60 Km le KH-MOI-162399-CW-CDD / R einforced Concrete Road for Component 1: Improving Liv Pending Im Community Drive 2020-07-2 Kampong Thkov Commune, K IDA / 59600 elihoods for Rural Poor and V Post Open - National 29,950.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 ralanh District ( 0.26 Km leng ulnerable Households n th,4.50m Width, 0.15 thick). KH-MOI-162400-CW-CDD / E arth Road Repair and Laterite Pavement for Svay Leu Com Component 1: Improving Liv Pending Im Community Drive 2020-07-2 mune, Svay Leu District ( 3.7 IDA / 59600 elihoods for Rural Poor and V Post Open - National 55,881.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 0 Km length, 4.00 m width, 0. ulnerable Households n 15m thick), including 2 units of double culvert constructio n, 1.00 m Diameter, 6.00 m l ength. KH-MOI-162401-CW-CDD / E arth Road Repair and Laterite Pavement for Ta Siem Comm Component 1: Improving Liv Pending Im Community Drive 2020-07-2 une, Svay Leu District ( 2.335 IDA / 59600 elihoods for Rural Poor and V Post Open - National 35,980.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 Km length, 4.50 m width, 0.1 ulnerable Households n 5m thick), including 1 unit of single culvert construction, 1. 00m Diameter, 6.00 m length . KH-MOI-162402-CW-CDD / E arth Road Repair and Laterite Pavement for Boeng Mealea Component 1: Improving Liv Pending Im Commune, Svay Leu District ( Community Drive 2020-07-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 44,027.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 2.80 Km length, 5.00 m width n Development 0 ulnerable Households n , 0.15m thick), including 2 un its of single culvert constructi on, 0.60m&0.80 Diameter, 6. 00 m length. KH-MOI-162403-CW-CDD / E arth Road Repair and Laterite Pavement 3 lines for Peak Sn aeng Commune, Angkor Tho Component 1: Improving Liv Pending Im Community Drive 2020-07-2 m District ( For Line1: 1.95 K IDA / 59600 elihoods for Rural Poor and V Post Open - National 54,983.00 0.00 plementatio 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 n Development 0 m length, 4.00 m width, 0.15 ulnerable Households n m thick including 2 units of si ngle culvert construction, 1.0 0 m Diameter, 5.00 m length & 1 unit of single culver KH-MOI-162406-CW-CDD / E arth Road Repair and Laterite Pavement 5 lines for Kampon Component 1: Improving Liv Pending Im Community Drive 2020-07-3 g Kdei Commune, Chi kraeng IDA / 59600 elihoods for Rural Poor and V Post Open - National 59,812.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 District, ( Total length 3190m ulnerable Households n , 4.00m width, 0.15 thick incl uding 1 unit of Double box cu lvert 2.00m heigh, 6.00m len gth) KH-MOI-162407-CW-CDD / E arth Road Repair and Literate Pavement 3 lines for Chi krae ng Commune, Chi kraeng Dis Component 1: Improving Liv Pending Im Community Drive 2020-07-3 trict, ( Total length 1680m, 4. IDA / 59600 elihoods for Rural Poor and V Post Open - National 39,802.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 00m, 0.15 thick width includi ulnerable Households n ng 2 units of single pipe culv ert 0.60m diameter, 6.00m le ngth and 3 units of single pip e culvert 1.00m diam KH-MOI-162408-CW-CDD / R einforced Concrete Bridge Co Component 1: Improving Liv Pending Im Community Drive 2020-07-3 nstruction for Tram Sasar Co IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,100.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 mmune, Srei Snam District ( ulnerable Households n 4.00m Heigh, 11.00m length, 4.00m width). Page 2 KH-MOI-162409-CW-CDD / E arth Road Repair and Laterite Pavement for Mean Chey Co Component 1: Improving Liv Pending Im Community Drive 2020-07-3 mmune, Brasat Bakong Distri IDA / 59600 elihoods for Rural Poor and V Post Open - National 31,649.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 ct ( Length 1800m, 4.00m wi ulnerable Households n dth, 0.15 thick and 1 unit of s ingle box culvert with water g ate, 2.50m heigh, 5.90m leng th ) KH-MOI-162410-CW-CDD / E arth Road Repair and Laterite Pavement for Roluos Commu ne, Brasat Bakong District, ( Component 1: Improving Liv Pending Im Community Drive 2020-07-3 Length 4625m, 4.00m width, IDA / 59600 elihoods for Rural Poor and V Post Open - National 49,078.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 0.15 thick including 1 units of ulnerable Households n single pipe culvert 0.60m dia meter, 6.00m length and 2 u nits of single pipe culvert 0.8 0m diameter, 6.00m len KH-MOI-162412-CW-CDD / E arth Road Repair and Laterite Pavement 2 lines for Kantrea Component 1: Improving Liv Pending Im Community Drive 2020-07-3 ng Commune, Brasat Bakong IDA / 59600 elihoods for Rural Poor and V Post Open - National 19,225.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 District, ( Total length 1500m ulnerable Households n , 4.00m width, 0.15 thick incl uding 1 unit of single pipe cu lvert 0.80m diameter, 5.00m length) KH-MOI-162414-CW-CDD / E arth Road Repair and Laterite Pavement for Ballangk Comm Component 1: Improving Liv Pending Im Community Drive 2020-07-3 une, Brasat Bakong District, ( IDA / 59600 elihoods for Rural Poor and V Post Open - National 20,670.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 Length 985m, 4.00m width, 0 ulnerable Households n .15 thick including 3 units of single pipe culvert 0.60m dia meter, 5.00m length) KH-MOI-162415-CW-CDD / E arth Road Repair and Laterite Component 1: Improving Liv Pending Im Community Drive 2020-07-3 Pavement for Dan Run Comm IDA / 59600 elihoods for Rural Poor and V Post Open - National 26,913.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 une, Sotr Nikom District, ( Le ulnerable Households n ngth 2600m, 4.00m width, 0. 15m thick ) KH-MOI-162416-CW-CDD / L aterite Road Construction for Prey Chruk Commune, Pouk Component 1: Improving Liv Pending Im District ( 3614 m length, 4.00 Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National 62,129.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 m width, 0.15 thick including n Development 0 ulnerable Households n 5 units of single pipe culvert, 0.60m Diameter, length 6.00 m and 1 unit of single pipe cu lvert 0.80m diameter, length 6.00m ) KH-MOI-162417-CW-CDD / L aterite Road Construction for Doun Kaev Commune, Pouk Component 1: Improving Liv Pending Im District ( 2500 m length, 4.00 Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National 49,293.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 m width, 0.15 thick including n Development 0 ulnerable Households n 1 unit of single pipe culvert,0 .80m Diameter length 6.00m and 1 unit of single pipe culv ert 1.00m diameter, length 6. 00m ) KH-MOI-162418-CW-CDD / Di gging Community Pond 2 pla ces for Kdei Run Commune, P Component 1: Improving Liv Pending Im Community Drive 2020-07-3 ouk District including fence c IDA / 59600 elihoods for Rural Poor and V Post Open - National 34,396.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 n Development 0 onstruction surrounding the p ulnerable Households n ond and 2 doors ( Size: 60mx33mx5m and 60 mx24mx5m) KH-MOI-162419-CW-CDD / R einforced Concrete Road Con struction for Khnat Commune Component 1: Improving Liv Pending Im , Pouk District ( 400m length, Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National 57,625.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 5.00m width, 0.15m thick incl n Development 0 ulnerable Households n uding 1 unit of single pipe cul vert 0.60 diameter, 6.00m le ngth and 1 unit of single pipe culvert 0.80 diameter, 6.00m length KH-MOI-162420-CW-CDD / L aterite Road Construction for Component 1: Improving Liv Pending Im Sasar Sdam Commune, Pouk Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National 39,060.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 District ( 1500m length, 5.00 n Development 0 ulnerable Households n m width, 0.15 thick including 2 units of single pipe culvert, 0.80m Diameter length 6.00 m) KH-MOI-162421-CW-CDD / L aterite Road Construction for Component 1: Improving Liv Pending Im Lvea Commune, Pouk District Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National 38,419.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 ( 2200m length, 4.00m width, n Development 0 ulnerable Households n 0.15 thick including 3 units of single pipe culvert,0.60m Dia meter length 6.00m) KH-MOI-162422-CW-CDD / U nlined Earth Canal Rehabilitat Component 1: Improving Liv Pending Im ion for Spean Tnoat Commun Community Drive 2020-07-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National 33,487.00 0.00 plementatio 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 e, Chi Kraeng District ( 2100 n Development 0 ulnerable Households n m length, 1.20m bed, 1.20 D epth including of 6 units of si ngle pipe culvert with water gate) KH-MOI-162423-CW-CDD / R einforced Concrete Bridge up grade in Phum 2, Sangkat Sra h Chak, Khan Daun Pend ( To Component 2: Improving Liv Pending Im Community Drive 2020-08-0 tal length 73m, 1.20m width, IDA / 59600 elihoods for Urban Poor and Post Open - National 65,309.00 0.00 plementatio 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 n Development 9 1.50 heigh, 0.07m thickness), Vulnerable Households n Reinforced Concrete Road in Phum 20, Sangkat Srah Chak, Khan Daun Penh ( Total lengt h 60m, 2.40m widt, 0.15m thi KH-MOI-162424-CW-CDD / R einforced Concrete Road in P hum 3, Sangkat Boeung Kak 1, Khan Toul Kork( Total lengt Component 2: Improving Liv Pending Im Community Drive 2020-08-0 h 46m, 2m width, 0.15m thic IDA / 59600 elihoods for Urban Poor and Post Open - National 9,333.00 0.00 plementatio 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 n Development 9 kness) and Drainage system Vulnerable Households n (Total length 34m, 0.6m dia meter). Reinforced concrete r oad in Phum 4, Sangkat Boeu ng Kak 1, Khan Toul kork(Tot al le KH-MOI-162425-CW-CDD / R einforced Concrete Road in T alei Village, Sangkat Dangka o, Khan Dangkao( Total lengt Component 2: Improving Liv Pending Im Community Drive 2020-08-1 h 149m, 3.5m width, 0.15m t IDA / 59600 elihoods for Urban Poor and Post Open - National 50,729.00 0.00 plementatio 2020-04-06 2020-04-13 2020-04-27 2020-05-04 2020-05-18 n Development 6 hickness) and Drainage syste Vulnerable Households n m (Total length 67m, 0.6m di ameter). Reinforced concrete road in Khva Village, Sangkat Dangkao, Khan Dangkao(Tot al KH-MOI-162426-CW-CDD / R einforced Concrete Road in T Component 2: Improving Liv Pending Im Community Drive 2020-08-1 oap Boss Village, Sangkat Pre IDA / 59600 elihoods for Urban Poor and Post Open - National 40,542.00 0.00 plementatio 2020-04-06 2020-04-13 2020-04-27 2020-05-04 2020-05-18 n Development 6 y Veang, Khan Dangkao( Tota Vulnerable Households n l length 310m, 4m width, 0.1 5m thickness) KH-MOI-162428-CW-CDD / R einforced Concrete Road in Pr eak Leap Village, Sangkat Pre Component 2: Improving Liv Pending Im Community Drive 2020-08-0 ak Leap, Khan Chroy Changv IDA / 59600 elihoods for Urban Poor and Post Open - National 55,323.00 0.00 plementatio 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 n Development 9 ar( Total length 287m, 3.5m Vulnerable Households n width, 0.15m thickness) and drainage system (Total lengt h 287m, 0.6m diameter) KH-MOI-162429-CW-CDD / R einforced Concrete Road in S en Sok Ty Mouy Village, Sang Component 2: Improving Liv Pending Im Community Drive 2020-08-1 kat Khmounh, Khan Sen Sok( IDA / 59600 elihoods for Urban Poor and Post Open - National 111,552.00 0.00 plementatio 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 n Development 3 Total length 547m, 4m width, Vulnerable Households n 0.15m thickness) and drainag e system (Total length 550m, 0.6m diameter) KH-MOI-162430-CW-CDD / R einforced Concrete Road in S amaki 5 Village, Sangkat Tra peang Krasang, Khan Pou Se Component 2: Improving Liv Pending Im Community Drive 2020-08-1 n Chey( Total length 196m, 6 IDA / 59600 elihoods for Urban Poor and Post Open - National 64,039.00 0.00 plementatio 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 n Development 3 m width, 0.15m thickness) R Vulnerable Households n einforced Concrete Road in S amaki 6 Village, Sangkat Tra peang Krasang, Khan Pou Se n Chey( Total length 121m, 4 m & 5m KH-MOI-162432-CW-CDD / R einforced Concrete Road in C hrey Koang Village, Sangkat Choam Chau 2, Khan Pou Sen Component 2: Improving Liv Pending Im Community Drive 2020-08-1 Chey( Total length 287m, 5m IDA / 59600 elihoods for Urban Poor and Post Open - National 177,610.00 0.00 plementatio 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 n Development 3 width, 0.15m thickness) and Vulnerable Households n Drainage System(Total Lengt h 287, 0.6m diameter) , Reinf orced Concrete Road in Prey Lvea Village, Sangkat Choam Ch Page 3 KH-MOI-162433-CW-CDD / R einforced Concrete Road in A ndong 1 & Andong 2 Villages, Component 2: Improving Liv Pending Im Community Drive 2020-08-1 Sangkat Kork Roka, Khan Pee IDA / 59600 elihoods for Urban Poor and Post Open - National 42,245.00 0.00 plementatio 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 n Development 3 ak Phnov( Total length 211m, Vulnerable Households n 4m width, 0.15m thickness) and Drainage System(Total L ength 211m, 0.6m diameter) KH-MOI-162435-CW-CDD / R einforced Concrete Road in D Component 2: Improving Liv Pending Im aeum Sleng Village, Sangkat Community Drive 2020-08-2 IDA / 59600 elihoods for Urban Poor and Post Open - National 28,928.00 0.00 plementatio 2020-04-10 2020-04-17 2020-05-01 2020-05-08 2020-05-22 Chbar Ampov 2, Khan Chbar n Development 0 Vulnerable Households n Ampov ( Total length 234m, 3.4m width, 0.15m thickness) KH-MOI-169345-CW-CDD / S olar LED Power Street lightin g in Phum 2, Sangkat Srah C hak, Khan Daun Pend ( Total Component 2: Improving Liv Pending Im Community Drive 2020-09-1 sets 22 sets), Solar LED Powe IDA / 59600 elihoods for Urban Poor and Post Open - National 13,469.00 0.00 plementatio 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 n Development 4 r Street lighting in Phum 22, Vulnerable Households n Sangkat Srah Chak, Khan Da un Pend ( Total sets 11 sets), Solar LED Power Street lighti ng in Phum 24, Sangkat KH-MOI-169346-CW-CDD / S Component 2: Improving Liv Pending Im olar LED Power street lighting Community Drive 2020-09-1 IDA / 59600 elihoods for Urban Poor and Post Open - National 3,613.00 0.00 plementatio 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 in Phum 8, Sangkat Boeung K n Development 4 Vulnerable Households n ak 1, Khan Toul Kork( Total s ets 11 sets) KH-MOI-169347-CW-CDD / S olar LED Power street lighting in Khva Village, Sangkat Dan Component 2: Improving Liv Pending Im Community Drive 2020-09-1 gkao, Khan Dangkao( Total s IDA / 59600 elihoods for Urban Poor and Post Open - National 15,774.00 0.00 plementatio 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 n Development 4 ets 26 sets), Solar LED Power Vulnerable Households n street lighting in Mol Village, Sangkat Dangkao, Khan Dan gkao(Total sets 23 sets) KH-MOI-169348-CW-CDD / S olar LED Power street lighting Component 2: Improving Liv Pending Im Community Drive 2020-09-1 in Phum 3, Sangkat Chrang C IDA / 59600 elihoods for Urban Poor and Post Open - National 5,495.00 0.00 plementatio 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 n Development 4 hamreas Ty Mouy, Khan Russ Vulnerable Households n ei Kao( Total sets 17 sets) KH-MOI-169349-CW-CDD / S Component 2: Improving Liv Pending Im olar LED Power street lighting Community Drive 2020-09-1 IDA / 59600 elihoods for Urban Poor and Post Open - National 9,674.00 0.00 plementatio 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 in Khtor Village, Sangkat Prea n Development 5 Vulnerable Households n k Leap, Khan Chroy Chang Va r( Total sets 30 sets) KH-MOI-169350-CW-CDD / S olar LED Power street lighting Component 2: Improving Liv Pending Im Community Drive 2020-09-1 in Svay Ckek Thmei Village, IDA / 59600 elihoods for Urban Poor and Post Open - National 15,064.00 0.00 plementatio 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 n Development 5 Dandong 1&2 Villages, Sangk Vulnerable Households n at Kork Roka, Khan Preak Phn ov( Total sets 47 sets) KH-MOI-169351-CW-CDD / S olar LED Power street lighting Component 2: Improving Liv Pending Im in Daeum Sleng, Daeum Slen Community Drive 2020-09-1 IDA / 59600 elihoods for Urban Poor and Post Open - National 21,978.00 0.00 plementatio 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 g I, Daeum Chan I Villages, S n Development 5 Vulnerable Households n angkat Chbar Ampov 2, Khan Chbar Ampov( Total sets 69 s ets) KH-MOI-191867-CW-CDD / R einforced Concrete Road Con Component 1: Improving Liv Pending Im struction for Khnang Phnum Community Drive 2020-12-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 20,181.00 0.00 plementatio 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 Commune,Svay Leu District, n Development 6 ulnerable Households n Siem Reap Province ( Length: 0.18 Km, Width 5.00 m, 0.15 m thick) KH-MOI-191856-CW-CDD / E arth Road Repair and Laterite Pavement for Anlong Samnar Component 1: Improving Liv Pending Im Community Drive 2021-08-2 , Siem Reap Province ( Lengt IDA / 59600 elihoods for Rural Poor and V Post Open - National 27,338.00 0.00 plementatio 2021-04-15 2021-04-22 2021-05-06 2021-05-13 2021-05-27 n Development 5 h 1.80 Km, Width 4.00 m, 0.1 ulnerable Households n 5m thick including 2 units of single culvert construction, Ø 0.80m, length 6.00m) KH-MOI-191857-CW-CDD / E arth Road Repair and Laterite Pavement two lines for Sangk at Krabei Riel, Siem Reap Mu Component 1: Improving Liv Pending Im Community Drive 2021-07-2 nicipality, Siem Reap Provinc IDA / 59600 elihoods for Rural Poor and V Post Open - National 45,396.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 e ( For line1: Length: 1.868 K ulnerable Households n m, Width 5.00m, 0.15 thick in cluding 2 units of single culve rts, Ø 0.80m, length 7.00m a nd Ø1.00m, length 7.0 KH-MOI-191859-CW-CDD / E arth Road Repair and Laterite Pavement for Sangkat Tuek V il ,Siem Reap Municipality, Si Component 1: Improving Liv Pending Im Community Drive 2021-07-2 em Reap Province ( Length: 2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 64,903.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 .325 Km , Width: 5.00 m, 0.1 ulnerable Households n 5m thick), including 5 units of single culvert construction, 1 Unit Ø1.00 m, length 6.00 m, 4 units Ø1.00 m, l KH-MOI-191860-CW-CDD / R einforced Concrete Road Con Component 1: Improving Liv Pending Im struction for Kampong Khlean Community Drive 2021-06-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 33,774.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 g Commune, Sotr Nikom Distr n Development 5 ulnerable Households n ict, Siem Reap Province ( Len gth 0.25 Km, Width 5.00 m, 0 .15m thick) KH-MOI-162413-CW-CDD / E arth Road Repair and Laterite Pavement for Bakong Comm Component 1: Improving Liv Pending Im Community Drive 2021-07-2 une, Brasat Bakong District, ( IDA / 59600 elihoods for Rural Poor and V Post Open - National 42,032.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 Length 1.60 Km, 4.00m width ulnerable Households n , 0.15 thick including 3 units of double pipe culvert 1.00m diameter, 5.00m length) KH-MOI-191861-CW-CDD / R einforced Concrete Road Con Component 1: Improving Liv Pending Im struction for Kampong Phluk Community Drive 2021-06-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 39,635.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 Commune, Brasat Bakong Dis n Development 5 ulnerable Households n trict, Siem Reap Province ( Le ngth 0.23 Km, Width 6.00 m, 0.15m thick) KH-MOI-191862-CW-CDD / E arth Road Repair and Laterite Pavement 2 lines for Trapean Component 1: Improving Liv Pending Im g Thum Commune ,Brasat Ba Community Drive 2021-07-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 36,380.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 kong District, Siem Reap Prov n Development 5 ulnerable Households n ince ( For line1: Length 0.50 Km, Width 4.00m, 0.15 thick , For line 2: Length 3.05 Km, W idth 4.00m, 0.15 thick) KH-MOI-191863-CW-CDD / L aterite Road Construction 2 li nes for Reul Commune ,Pouk Component 1: Improving Liv Pending Im Community Drive 2021-07-2 District, Siem Reap Province IDA / 59600 elihoods for Rural Poor and V Post Open - National 31,787.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 (For line Length 2.09 Km, Wid ulnerable Households n th 4.00m, 0.15 thick , For line 2: Length 0.75 Km, Width 4.0 0m, 0.15 thick) KH-MOI-191865-CW-CDD / D rilled wells Construction with Component 1: Improving Liv Pending Im Community Drive 2021-06-2 Afridev Pump for Yeang Com IDA / 59600 elihoods for Rural Poor and V Post Open - National 11,429.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 mune ,Pouk District, Siem Re ulnerable Households n ap Province for 5 places KH-MOI-191864-CW-CDD / L aterite Road Construction 2 li nes for Trei Nhoar Commune ,Pouk District, Siem Reap Pro Component 1: Improving Liv Pending Im Community Drive 2021-07-2 vince ( For line 1: Length 1.2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 35,805.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 n Development 5 0 Km, Width 4.00m, 0.15 thic ulnerable Households n k , For line 2: Length 1.45 Km , Width 4.00m, 0.15 thick incl uding 1 unit of double culvert Ø0.60m, length 6.0 KH-MOI-191866-CW-CDD / D rilled wells with solar Pump a Component 1: Improving Liv Pending Im nd Water Distributed Connect Community Drive 2021-07-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National 47,530.00 0.00 plementatio 2021-03-15 2021-03-22 2021-04-05 2021-04-12 2021-04-26 ion 4 places for Chrouy Nean n Development 5 ulnerable Households n g NguonCommune ,Srei Sna m District, Siem Reap Provinc e KH-MOI-162411-CW-CDD / C onstruction of Community Sh elter for Ampil Commune, Bra sat Bakong District ( Size: 8m Component 1: Improving Liv Pending Im Community Drive 2021-09-2 x12m, with steel frame, reinf IDA / 59600 elihoods for Rural Poor and V Post Open - National 15,377.00 0.00 plementatio 2021-05-14 2021-05-21 2021-06-04 2021-06-11 2021-06-25 n Development 3 orced concrete slab 0.10m th ulnerable Households n ick and zinc roof ) including o ne latrine construction with 4 separated rooms and installa tion of one unit of wa Page 4 KH-MOI-251230-CW-RFQ / La terite Road Construction for Mukh Paen Commune, Pouk Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-1 District, Siem Reap Province ( IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 26,739.00 0.00 plementatio 2021-09-11 2021-10-16 tions nvelope 4 2 lines, for line1: Length= 1.2 ulnerable Households SPD) n 0 Km, Width= 5.00m, Thick= 0.15m , For line 2: Length= 0 .85 Km, Width= 4.00m, Thick =0.15m) KH-MOI-251231-CW-RFQ / La terite Road Construction for S amraong Yea Commune, Pou Component 1: Improving Liv Request for Quot Pending Im k District, Siem Reap Provinc Request for Quota Single Stage - One E 2022-01-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 36,214.00 0.00 plementatio 2021-09-11 2021-10-16 e (04 Lines, Total Length= 3. tions nvelope 4 ulnerable Households SPD) n 16 Km, Width= 4.00m, Thick =0.15m including 1 unit of do uble culvert construction, Ø0. 60 m, length 6.00m) KH-MOI-253012-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Kandeak Comm Component 1: Improving Liv Request for Quot Pending Im une, Brasat Bakong District, Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 32,966.00 0.00 plementatio 2021-09-22 2021-10-27 Siem Reap Province ( 5 lines, tions nvelope 5 ulnerable Households SPD) n Total Length=2.77 Km, Width = 4.00 m, Thick=0.15m incl uding 1 unit of single culvert construction, Ø1.00m, length 6.00m KH-MOI-253013-CW-RFQ / La terite Road Construction for K aev Poar Commune, Pouk Dis trict, Siem Reap Province ( 2 l Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 ines, For line1: Length= 0.53 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 30,147.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 Km, Width= 4.00m, Thick=0. ulnerable Households SPD) n 15 m , For line 2: Length 1.15 Km, Width: 4.00m, 0.15 thick including 4 units of single cul vert construction, KH-MOI-253014-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Svay Chek Com Component 1: Improving Liv Request for Quot Pending Im mune, Angkor Thum District, Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 33,360.00 0.00 plementatio 2021-09-22 2021-10-27 Siem Reap Province (Length tions nvelope 5 ulnerable Households SPD) n = 2.10 Km, Width= 5.00 m, T hick=0.15m including 1 unit of single culvert construction, Ø1.00m, length= 7.00m) KH-MOI-253015-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Leang Dai Com mune, Angkor Thum District, Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 Siem Reap Province ( For lin IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 37,682.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 e one, Length= 0.922 Km, Wi ulnerable Households SPD) n dth= 4.00 m, Thick=0.15m in cluding 3 units of single culve rt construction, Ø0.80m, leng th= 6.00m, 1 units of sing KH-MOI-253016-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Sangkat Svay Dangkum , Siem Reap Munici Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 pality, Siem Reap Province (T IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 61,110.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 otal Length= 1.799 Km, Widt ulnerable Households SPD) n h= 5.00 m, Thick=0.15m incl uding 1 unit of single culvert construction, Ø1.00m, length = 7.00m and 1 unit of double c KH-MOI-253017-CW-RFQ / Ea rth Road Repair and Laterite Component 1: Improving Liv Request for Quot Pending Im Pavement for Sangkat Krabei Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 9,885.00 0.00 plementatio 2021-09-22 2021-10-27 Riel , Siem Reap Municipality, tions nvelope 5 ulnerable Households SPD) n Siem Reap Province ( Total L ength= 0.315 Km, Width= 5. 00 m, Thick=0.15m ) KH-MOI-253018-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Sangkat Tuek V Component 1: Improving Liv Request for Quot Pending Im il , Siem Reap Municipality, Si Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,757.00 0.00 plementatio 2021-09-22 2021-10-27 em Reap Province ( Total Len tions nvelope 5 ulnerable Households SPD) n gth= 0.54 Km, Width= 5.00 m, Thick=0.15m including 1 unit of single culvert construc tion, Ø1.00m, length= 7.00m ) KH-MOI-253019-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Bakong Comm une , Brasat Bakong District, Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 Siem Reap Province ( Total L IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 24,131.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 ength= 1.015 Km, Width= 4. ulnerable Households SPD) n 00 m, Thick=0.15m includin g 6 unist of single culvert con struction, Ø0.60m, Length= 5 .00m, 1 unist of single culver KH-MOI-253020-CW-RFQ / Ea rth Road Repair and Laterite Component 1: Improving Liv Request for Quot Pending Im Pavement for Kantreang Com Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 37,561.00 0.00 plementatio 2021-09-22 2021-10-27 mune , Brasat Bakong Distric tions nvelope 5 ulnerable Households SPD) n t, Siem Reap Province ( Total Length= 3.695 Km, Width= 4 .00 m, Thick=0.15m) KH-MOI-253021-CW-RFQ / Re inforced Concrete Road Const Component 1: Improving Liv Request for Quot Pending Im ruction for Kandeak Commun Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 32,469.00 0.00 plementatio 2021-09-22 2021-10-27 e, Brasat Bakong District, Sie tions nvelope 5 ulnerable Households SPD) n m Reap Province ( Total Leng th= 0.265 Km, Width= 4.00 m, Thick=0.15m) KH-MOI-253022-CW-RFQ / Ea rth Road Repair and Laterite Component 1: Improving Liv Request for Quot Pending Im Pavement for Roluos Commu Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 37,913.00 0.00 plementatio 2021-09-22 2021-10-27 ne, Brasat Bakong District, Si tions nvelope 5 ulnerable Households SPD) n em Reap Province ( Total Len gth= 3.892 Km, Width= 4.00 m, Thick=0.15m) KH-MOI-253023-CW-RFQ / Dr illed Wells with Pump 8 place Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 s for Sasar Sdam Commune, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 16,174.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 Pouk District, Siem Reap Prov ulnerable Households SPD) n ince (Depth=5m, Ø150mm) KH-MOI-253024-CW-RFQ / Dr illed Wells with Pump 3 place Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 s for Doun Kaev Commune, P IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 6,065.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 ouk District, Siem Reap Provi ulnerable Households SPD) n nce (Depth=5m, Ø150mm) KH-MOI-253025-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Khnat Commu Component 1: Improving Liv Request for Quot Pending Im ne, Pouk District, Siem Reap Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 27,381.00 0.00 plementatio 2021-09-22 2021-10-27 Province ( Total Length= 1.6 tions nvelope 5 ulnerable Households SPD) n 17 Km, Width= 4.00 m, Thick =0.15m including 1 single cul vert construction, Ø0.60m, le ngth= 6.00m ) KH-MOI-253026-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Lvea Commun Component 1: Improving Liv Request for Quot Pending Im e, Pouk District, Siem Reap Pr Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 46,633.00 0.00 plementatio 2021-09-22 2021-10-27 ovince ( Total Length= 2.225 tions nvelope 5 ulnerable Households SPD) n Km, Width= 4.00 m, Thick=0. 15m including 3 places of do uble culvert construction, Ø1. 00m, length= 6.00m ) KH-MOI-253027-CW-RFQ / Dr illed Wells with Pump 21 plac Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 es for Mukh Paen Commune, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 42,456.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 Pouk District, Siem Reap Prov ulnerable Households SPD) n ince, (Depth=5m, Ø150mm) KH-MOI-253028-CW-RFQ / Dr illed Wells with Pump 11 plac Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 es for Prey Chruk Commune, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 22,239.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 Pouk District, Siem Reap Prov ulnerable Households SPD) n ince, (Depth=5m, Ø150mm) KH-MOI-253029-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Reul Commune Component 1: Improving Liv Request for Quot Pending Im , Pouk District, Siem Reap Pro Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 47,248.00 0.00 plementatio 2021-09-22 2021-10-27 vince ( Total Length= 1.60 K tions nvelope 5 ulnerable Households SPD) n m, Width= 4.00 m, Thick=0.1 5m including 4 places of singl e culvert construction, Ø0.80 m, length= 6.00m ) KH-MOI-253030-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Samraong Yea Component 1: Improving Liv Request for Quot Pending Im Commune, Pouk District, Sie Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 45,144.00 0.00 plementatio 2021-09-22 2021-10-27 m Reap Province ( Total Leng tions nvelope 5 ulnerable Households SPD) n th= 2.10 Km, Width= 4.00 m, Thick=0.15m including 4 plac es of single culvert constructi on, Ø0.60m, length= 6.00m ) Page 5 KH-MOI-253031-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Chob Ta Trav C ommune, Angkor Thum Distri Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 ct, Siem Reap Province ( Tota IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 41,040.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 l Length= 1.772 Km, Width= ulnerable Households SPD) n 4.00 m, Thick=0.15m includi ng 2 places of single culvert c onstruction, Ø1.00m, length= 6.00m and 1double culvert KH-MOI-253032-CW-RFQ / W Component 1: Improving Liv Request for Quot Pending Im ater gate Construction 2 plac Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 45,000.00 0.00 plementatio 2021-09-22 2021-10-27 es for Chob Ta Trav Commun tions nvelope 5 ulnerable Households SPD) n e, Angkor Thum District, Sie m Reap Provincial KH-MOI-253033-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Leang Dai Com Component 1: Improving Liv Request for Quot Pending Im mune, Angkor Thum District, Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 22,163.00 0.00 plementatio 2021-09-22 2021-10-27 Siem Reap Province ( Total L tions nvelope 5 ulnerable Households SPD) n ength= 0.974Km, Width= 4.0 0 m, Thick=0.15m including 3 places of single culvert con struction, Ø1.00m, length= 5. 00m) KH-MOI-253034-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Peak Snaeng C ommune, Angkor Thum Distri Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 ct, Siem Reap Province ( Tota IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 35,005.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 l Length= 0.98 Km, Width= 4 ulnerable Households SPD) n .00 m, Thick=0.15m includin g 1 place of single culvert co nstruction, Ø1.00m, length= 6.00m, 1triple culvert KH-MOI-253035-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Svay Chek Com Component 1: Improving Liv Request for Quot Pending Im mune, Angkor Thum District, Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 24,196.00 0.00 plementatio 2021-09-22 2021-10-27 Siem Reap Province ( Total L tions nvelope 5 ulnerable Households SPD) n ength= 0.943 Km, Width= 4. 00 m, Thick=0.15m including 1 place of single culvert cons truction, Ø1.00m, length= 7. 00m) KH-MOI-253036-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Boeng Mealea Component 1: Improving Liv Request for Quot Pending Im Commune, Svay Leu District, Request for Quota Single Stage - One E 2022-01-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 23,729.00 0.00 plementatio 2021-09-22 2021-10-27 Siem Reap Province ( Total L tions nvelope 5 ulnerable Households SPD) n ength= 1.15 Km, Width= 4.0 0 m, Thick=0.15m including 2 places of single culvert con struction, Ø1.00m, length= 6. 00m) KH-MOI-253037-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Svay Leu Com mune, Svay Leu District, Sie Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 m Reap Province ( Total Leng IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 38,068.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 th= 1.05 Km, Width= 5.00 m, ulnerable Households SPD) n Thick=0.15m including 1 plac e of single culvert constructio n, Ø1.00m, length= 7.00m, 2 places of double culvert con KH-MOI-253038-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Ta Siem Comm une, Svay Leu District, Siem Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-2 Reap Province ( Total Length IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 22,587.00 0.00 plementatio 2021-09-22 2021-10-27 tions nvelope 5 = 0.771 Km, Width= 5.00 m, ulnerable Households SPD) n Thick=0.15m including 1 sing le culvert , Ø0.80m, length= 6.00m, 1 single and double c ulvert,Ø1.00m KH-MOI-253039-CW-RFQ / Re inforced Concrete Road upgr ade in Trapeang Krasang, Kh an Pou Sen Chey ( Total lengt Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-1 h 275m, 4m width, 0.15m thi IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 86,535.67 0.00 plementatio 2021-09-16 2021-10-21 tions nvelope 9 ckness) and Reinforced Concr Vulnerable Households SPD) n ete Road in Sangkat Trapean g Krasang, Khan Pou Sen Che y ( Total length 178m, 4m wi dth, 1.50) with Drainage Syst em KH-MOI-253040-CW-RFQ / Re inforced Concrete Road in Ph um Andong 1 & Phum Andon Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-1 g 2, Sangkat Kork Roka, Khan IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 78,963.02 0.00 plementatio 2021-09-16 2021-10-21 tions nvelope 9 Preak Phnov ( Total length 56 Vulnerable Households SPD) n 1m, 4m width, 0.15m thickne ss) and Drainage system (Tot al length 244m, 0.6m diamet er). KH-MOI-253041-CW-RFQ / Re inforced Concrete Road in Sa ngkat Choam Chau 2, Khan P ou Sen Chey (Total length 60 Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-1 m, 4.50m width, 0.15m thick IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 59,825.69 0.00 plementatio 2021-09-16 2021-10-21 tions nvelope 9 ness, 89m, 4m width, 0.15m Vulnerable Households SPD) n thickness, 223m, 3m length, 0.15m thickness) and Draina ge System ( Total length 377 m, 0.6m diameter) KH-MOI-253042-CW-RFQ / Re inforced Concrete Road in Sa ngkat Prey Vaeng, Khan Dan gkao ( Total length 104m, 5m Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-01-1 width, 0.15m thickness, 82m, IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 56,055.11 0.00 plementatio 2021-09-16 2021-10-21 tions nvelope 9 4m width, 0.15m thickness, 1 Vulnerable Households SPD) n 28m, 3m length, 0.15m thick ness) and Drainage System ( Total length 190m, 0.6m dia meter, 135m, 0.4m diameter) . KH-MOI-259610-CW-RFQ / Re inforced Concrete Road Const Component 1: Improving Liv Request for Quot Pending Im ruction for Pou Treay Commu Request for Quota Single Stage - One E 2022-03-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 42,895.00 0.00 plementatio 2021-11-07 2021-12-12 ne ,Pouk District, Siem Reap tions nvelope 2 ulnerable Households SPD) n Province ( Total Length=0.23 Km, Width= 5.00 m, Thick=0. 15m) KH-MOI-259611-CW-RFQ / Co nstruction of ring concrete w ater storage system with mes h fence surrounding, steel fra Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-03-1 me building with plastics zinc IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 27,159.00 0.00 plementatio 2021-11-07 2021-12-12 tions nvelope 2 roof , water pipe distributed c ulnerable Households SPD) n onnection, and installation of automatic solar pump 340W, for Khnang Phnum Commune , Svay Leu District KH-MOI-259612-CW-RFQ / Co nstruction of livestock buildin Component 1: Improving Liv Request for Quot Pending Im g and Chicken Incubator 2 pl Request for Quota Single Stage - One E 2022-04-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 16,422.00 0.00 plementatio 2021-12-06 2022-01-10 aces for Anlong Samnar Com tions nvelope 0 ulnerable Households SPD) n mune ,Chi Kraeng District, Si em Reap Province, (Size: 4m x8m, 4mx8m) KH-MOI-259613-CW-RFQ / Co nstruction of livestock buildin Component 1: Improving Liv Request for Quot Pending Im g and Chicken Incubator 3 pl Request for Quota Single Stage - One E 2022-04-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 24,633.00 0.00 plementatio 2021-12-06 2022-01-10 aces for Kampong Kdei Com tions nvelope 0 ulnerable Households SPD) n mune ,Chi Kraeng District, Si em Reap Province, (Size: 5m x8m) KH-MOI-259614-CW-RFQ / Co nstruction of livestock buildin Component 1: Improving Liv Request for Quot Pending Im g and Chicken Incubator 1 pl Request for Quota Single Stage - One E 2022-04-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 8,211.00 0.00 plementatio 2021-12-06 2022-01-10 ace for Chrouy Neang Nguon tions nvelope 0 ulnerable Households SPD) n Commune ,Srei Snam District , Siem Reap Province, (Size: 5mx8m) KH-MOI-267134-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Sambuor Com Component 1: Improving Liv Request for Quot Pending Im mune, Kralanh District, Siem Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,000.00 0.00 plementatio 2022-01-05 2022-02-09 Reap Province (Length= 1.05 tions nvelope 0 ulnerable Households SPD) n Km, Width= 4.00 m, Thick=0. 15m including 1 unit of single culvert construction, Ø0.80m, length 7.00m) KH-MOI-267135-CW-RFQ / U nlined Earth Canal Rehabilitat ion for Khlang Hay Commune , Srei Snam District,Siem Rea Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-1 p Province ( Length=3.35 Km IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 63,783.00 0.00 plementatio 2022-01-05 2022-02-09 tions nvelope 0 , Depth= 1.50 m including 2 ulnerable Households SPD) n units of single culvert with ga te, Ø1.00m,length 6.00m,1 u nit of single culvert with gate , Ø0.60m, length= 6.0m Page 6 KH-MOI-267137-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Slaeng Spean C Component 1: Improving Liv Request for Quot Pending Im ommune, Srei Snam District, Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 61,875.00 0.00 plementatio 2022-01-05 2022-02-09 Siem Reap Province ( Length tions nvelope 0 ulnerable Households SPD) n = 3.35 Km, Width= 4.00 m, T hick=0.15m including 1 unit of double culvert constructio n, Ø1.00m, length 6.00m.. KH-MOI-267138-CW-RFQ / Re Component 1: Improving Liv Request for Quot Pending Im habilitation of Community Po Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 28,518.00 0.00 plementatio 2022-01-05 2022-02-09 nd 2 places for Chi Kraeng Co tions nvelope 0 ulnerable Households SPD) n mmune, Chi Kraeng District, Siem Reap Province KH-MOI-267140-CW-RFQ / Re habilitation of Community Po Component 1: Improving Liv Request for Quot Pending Im nd and Construction of water Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 16,184.00 0.00 plementatio 2022-01-05 2022-02-09 tank's support 2 places for Ko tions nvelope 0 ulnerable Households SPD) n uk Thlork Kraom Commune, Chi Kraeng District, Siem Rea p Province. KH-MOI-267141-CW-RFQ / Dr illed Wells Construction with Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-1 Pump 1 place for Spean Tnoa IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 7,998.00 0.00 plementatio 2022-01-05 2022-02-09 tions nvelope 0 t Commune, Chi Kraeng Distri ulnerable Households SPD) n ct, Siem Reap Province. KH-MOI-267142-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Dan Run Comm une , Sotr Nikom District, Sie Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-1 m Reap Province ( Total Leng IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,199.00 0.00 plementatio 2022-01-05 2022-02-09 tions nvelope 0 th= 1.60 Km, Width= 5.00 m, ulnerable Households SPD) n Thick=0.15m including 1 uni t of double culvert constructi on with water gate, Ø1.00m, Length= 5.00m ) KH-MOI-267143-CW-RFQ / Re habilitation of Community Po Component 1: Improving Liv Request for Quot Pending Im nds two place for Kampong Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 25,234.00 0.00 plementatio 2022-01-05 2022-02-09 Khleang Commune , Sotr Nik tions nvelope 0 ulnerable Households SPD) n om District, Siem Reap Provin ce (Size:35mx35mx5m & 40 mx40mx5m ) KH-MOI-267144-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Ballangk Comm Component 1: Improving Liv Request for Quot Pending Im une , Brasat Bakong District, Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 32,490.00 0.00 plementatio 2022-01-05 2022-02-09 Siem Reap Province ( Total L tions nvelope 0 ulnerable Households SPD) n ength= 1.240 Km, Width= 4. 00 m, Thick=0.15m includin g 3 unist of single culvert con struction, Ø1.00m, Length= 6 .00m, . KH-MOI-267145-CW-RFQ / U nlined Earth Canal Rehabilitat ion for Mean Chey Commune Component 1: Improving Liv Request for Quot Pending Im , Brasat Bakong District, Sie Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 29,031.00 0.00 plementatio 2022-01-05 2022-02-09 m Reap Province ( Total Leng tions nvelope 0 ulnerable Households SPD) n th= 1.25 Km, Width= 1.50 m, Depth=2.00m including one place of box culvert with wat er gate 3mx2.50mx5m) KH-MOI-267146-CW-RFQ / Di gging Community Pond 2 pla Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-1 ces for Kaev Poar Commune, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 52,270.00 0.00 plementatio 2022-01-05 2022-02-09 tions nvelope 0 Pouk District, Siem Reap Prov ulnerable Households SPD) n ince, (Size: 60mx50mx5m) KH-MOI-267147-CW-RFQ / Di ke Rehabilitation for Trapean g Thum Commune, Brasat Ba Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-1 kong District, Siem Reap Prov IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 38,935.00 0.00 plementatio 2022-01-05 2022-02-09 tions nvelope 0 ince ( Total Length= 0.80 Km ulnerable Households SPD) n , Depth=1.50m including six place of single culvert with w ater gate, Ø1.00m, Length= 6.00m) KH-MOI-267149-CW-RFQ / Re inforced Concrete Road Const Component 1: Improving Liv Request for Quot Pending Im ruction for Pou Treay Commu Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 39,500.00 0.00 plementatio 2022-01-05 2022-02-09 ne ,Pouk District, Siem Reap tions nvelope 0 ulnerable Households SPD) n Province ( Total Length=0.23 Km, Width= 5.00 m, Thick=0. 15m) KH-MOI-267151-CW-RFQ / Di gging Community Pond for Tr Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-1 ei Nhoar Commune, Pouk Dis IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 47,500.00 0.00 plementatio 2022-01-05 2022-02-09 tions nvelope 0 trict, Siem Reap Province, 4 p ulnerable Households SPD) n laces (Size: 50mx30mx5m) KH-MOI-267152-CW-RFQ / Di gging Community Pond for Ye Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-1 ang Commune, Pouk District, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 34,016.00 0.00 plementatio 2022-01-05 2022-02-09 tions nvelope 0 Siem Reap Province, 1 places ulnerable Households SPD) n (Size:100mx50mx5m) KH-MOI-267153-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Sambuor Com Component 1: Improving Liv Request for Quot Pending Im mune, Kralanh District, Siem Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 21,086.00 0.00 plementatio 2022-01-05 2022-02-09 Reap Province ( Total Length tions nvelope 0 ulnerable Households SPD) n = 0.95Km, Width= 4.00 m, T hick=0.15m including 1 place of single culvert construction, Ø1.00m, length= 7.00m ) KH-MOI-267154-CW-RFQ / Ea rth Road Repair and Laterite Pavement for Tram Sasar Co Component 1: Improving Liv Request for Quot Pending Im mmune, Srei Snam District, S Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 58,347.00 0.00 plementatio 2022-01-05 2022-02-09 iem Reap Province ( Total Le tions nvelope 0 ulnerable Households SPD) n ngth= 2.00Km, Width= 4.00 m, Thick=0.15m including 1 place of single culvert constr uction, Ø0.80m, length= 7.00 m, . KH-MOI-267156-CW-RFQ / Ea rth Road Repair and Laterite Component 1: Improving Liv Request for Quot Pending Im Pavement for Kouk Thlork Kra Request for Quota Single Stage - One E 2022-05-1 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 50,569.00 0.00 plementatio 2022-01-05 2022-02-09 om Commune, Kouk Chi Krae tions nvelope 0 ulnerable Households SPD) n ng District, Siem Reap Provin ce ( Total Length= 2.385 Km, Width= 4.00 m, Thick=0.15m .. KH-MOI-267157-CW-RFQ / Co nstruction of safe place for co mmunity evacuation for Sang Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-1 kat Chong Khneas, Siem Rea IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 57,605.00 0.00 plementatio 2022-01-05 2022-02-09 tions nvelope 0 p Municilpality, Siem Reap Pr ulnerable Households SPD) n ovince (Length=0.52Km, Wid th=20m) including1 unit of la trine construction with 4 roo ms. KH-MOI-267160-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-0 in Phum Trapeang Anhchanh IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 2,523.40 0.00 plementatio 2022-01-05 2022-03-02 tions nvelope 1 6, Sangkat Trapeang krasang Vulnerable Households SPD) n , Khan Pou Sen Chey (Total S et 12 sets) KH-MOI-267165-CW-RFQ / So Component 2: Improving Liv Request for Quot Pending Im lar LED Power Street lighting Request for Quota Single Stage - One E 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,610.90 0.00 plementatio 2022-01-05 2022-03-02 in Phum Saen Sok 1, Sangkat tions nvelope 1 Vulnerable Households SPD) n Khmounh, Khan Saen Sok (To tal Set 37 sets) KH-MOI-267219-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-0 in Phum Andong1, Phum And IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,817.00 0.00 plementatio 2022-01-05 2022-03-02 tions nvelope 1 ong 2, Sangkat Kork Roka, Kh Vulnerable Households SPD) n an Prek Phnov (Total set 38 s ets) KH-MOI-267220-CW-RFQ / So Component 2: Improving Liv Request for Quot Pending Im lar LED Power Street lighting Request for Quota Single Stage - One E 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 2,317.70 0.00 plementatio 2022-01-05 2022-03-02 in Phum Talei, Sangkat Dang tions nvelope 1 Vulnerable Households SPD) n kao, Khan Dangkao (Total set 11 sets) KH-MOI-267223-CW-RFQ / So Component 2: Improving Liv Request for Quot Pending Im lar LED Power Street lighting Request for Quota Single Stage - One E 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 5,403.20 0.00 plementatio 2022-01-05 2022-03-02 in Phum 3 & 4 , Sangkat Boe tions nvelope 1 Vulnerable Households SPD) n ung Kak 1, Khan Toul Kork (T otal set 26 sets) KH-MOI-267224-CW-RFQ / So Component 2: Improving Liv Request for Quot Pending Im lar LED Power Street lighting Request for Quota Single Stage - One E 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 6,637.40 0.00 plementatio 2022-01-05 2022-03-02 in Phum 2, Sangkat Chrang C tions nvelope 1 Vulnerable Households SPD) n hamreas 1, Khan Russei Kao (Total set 32 sets) KH-MOI-267260-CW-RFQ / So Component 2: Improving Liv Request for Quot Pending Im lar LED Power Street lighting Request for Quota Single Stage - One E 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 3,757.60 0.00 plementatio 2022-01-05 2022-03-02 in Phum Prek Leap, Sankat Pr tions nvelope 1 Vulnerable Households SPD) n ek Leap, Khan Chroy Changv ar (Total set 18 Sets) Page 7 KH-MOI-267261-CW-RFQ / So Component 2: Improving Liv Request for Quot Pending Im lar LED Power Street lighting Request for Quota Single Stage - One E 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 10,340.00 0.00 plementatio 2022-01-05 2022-03-02 in Phum 15 & 16, Sangkat Sr tions nvelope 1 Vulnerable Households SPD) n ah Chak, Khan Daun Penh (To tal set 50 sets) KH-MOI-267262-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-05-0 in Phum Prek Tanou, Sangkat IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 6,431.70 0.00 plementatio 2022-01-05 2022-03-02 tions nvelope 1 Chak Angrae Leu, Khan Mean Vulnerable Households SPD) n Chey (Total set 31 sets) KH-MOI-267263-CW-RFQ / Re inforced concrete road in Phu Component 2: Improving Liv Request for Quot Pending Im m Saen Sok 1, Sangkat Khmo Request for Quota Single Stage - One E 2022-05-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 18,925.00 0.00 plementatio 2022-01-05 2022-03-02 unh, Khan Saen Sok (Total le tions nvelope 1 Vulnerable Households SPD) n ngth 148m, 4m width, 0,15m thickness) Pipe culvert (Total length 6m, Ǿ80 Diameter) KH-MOI-297191-CW-RFQ / Re inforced concrete Road in Ph um Trapeang Anhchanh 3 & Phum Trapeang Anhchanh 5, Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-10-2 Sangkat Trapeang Krasang, K IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 47,187.35 0.00 plementatio 2022-06-20 2022-07-25 tions nvelope 3 han Pou Sen Chey (Total len Vulnerable Households SPD) n gth 104m, 4m width, 165m, 4 m width, 0,15 thickness) Pipe Drainage ( Total length 269m , Ǿ60 Diameter) KH-MOI-297193-CW-RFQ / Re inforced concrete Road in Ph Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-10-2 um Khmer Leu Thmei, Sangk IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 40,573.39 0.00 plementatio 2022-06-20 2022-07-25 tions nvelope 3 at Kork Roka, Khan Prek Phno Vulnerable Households SPD) n v (Total length 383m, 4m wid th, 0,15m thickness) KH-MOI-297195-CW-RFQ / Re inforced concrete Road in Ph um Prey Veng Lek, Sangkat P rey Veng, Khan Dangkao (Tot Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-10-2 al length 86m, 4m width, 39 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 17,766.00 0.00 plementatio 2022-06-20 2022-07-25 tions nvelope 3 m, 3m width, 74m, 2,5m widt Vulnerable Households SPD) n h, 0,15m thickness) and Rein forced concrete Road in Phu m Komreang Sangkat Prey V eng ( Total length 94m) KH-MOI-297196-CW-RFQ / Re inforced concrete Road in Ph Component 2: Improving Liv Request for Quot Pending Im um Anlong Kngan & Phum Tr Request for Quota Single Stage - One E 2022-10-2 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 30,062.60 0.00 plementatio 2022-06-20 2022-07-25 apeang Rang, Sangkat Khmo tions nvelope 3 Vulnerable Households SPD) n unh, Khan Saen Sok(Total len gth 120m, 3m width, 18.5m, 2.6m width, 171m, 4m width) KH-MOI-297198-CW-RFQ / Re inforced concrete Road in Ph um Thmar Kol 1, Sangkat Ch oam Chau 2, Khan Pou Sen c Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-10-2 hey (Total length 306m, 3m IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 55,356.59 0.00 plementatio 2022-06-20 2022-07-25 tions nvelope 3 width, 0,15m thickness) Reinf Vulnerable Households SPD) n orced concrete Road in Phum Prey Lvea, Sangkat Choam C hau 2, Khan Pou Senchey (To tal length 128m, 4m width, 0, 15m ) KH-MOI-297199-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-11-0 in Phum Serei Deidos & Phum IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 21,366.76 0.00 plementatio 2022-07-05 2022-08-09 tions nvelope 7 Toul Sambo, Sangkat Prey Ve Vulnerable Households SPD) n ng , Khan Dangkao (Total set 111 Sets) KH-MOI-297200-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im in Phum Khmer Leu Thmei, P Request for Quota Single Stage - One E 2022-11-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 20,227.63 0.00 plementatio 2022-07-05 2022-08-09 hum Chres Thmei & Phum An tions nvelope 7 Vulnerable Households SPD) n dong 3, Sangkat Kork Roka , Khan Prek Phnov (Total set 1 11 Sets) KH-MOI-297201-CW-RFQ / Re inforced concrete Road in Ph Component 2: Improving Liv Request for Quot Pending Im um Sampore Thmei & Phum Request for Quota Single Stage - One E 2022-11-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 13,270.01 0.00 plementatio 2022-07-05 2022-08-09 Chres Thmei, Sangkat Kork R tions nvelope 7 Vulnerable Households SPD) n oka, Khan Prek Phnov (Total l ength 70m, 4m width, 67m, 3 m width, 0,15m thickness) KH-MOI-297202-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-11-0 in Phum Sen Sok 5 & Phum A IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,446.96 0.00 plementatio 2022-07-05 2022-08-09 tions nvelope 7 nlong Kra Ngan, Sangkat Kh Vulnerable Households SPD) n mounh , Khan Sen Sok (Total set 35 Sets) KH-MOI-308334-CW-RFQ / Ea rth road repair and laterite p avement at Kok Tlok Krom Co mmune,Chikreang District, Si Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-0 em Reap Province(1 line leng IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 14,832.01 0.00 plementatio 2022-09-04 2022-10-09 tions nvelope 7 th 0.600Km, width 4.00m, lat ulnerable Households SPD) n erite thickness 0.15m includi ng 1 single pipe culvert Ø0.8 0m length 6m and 1 double p ipe culvert Ø1.00m, leng 7m KH-MOI-308335-CW-RFQ / Ea rth road repair and laterite p avement at Spean Tnot Com mune, Chikreang District,Sie Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-0 m Reap Province (6 line lengt IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 50,504.18 0.00 plementatio 2022-09-06 2022-10-11 tions nvelope 9 h 2.400Km,width 4.00m & 6 ulnerable Households SPD) n m,laterite thickness 0.15m in cluding 1single pipe culvert Ø 1.00m length 6m and 1doubl e pipe culvert Ø0.80m, lengt h7m KH-MOI-308336-CW-RFQ / Re inforced concrete road constr uction at Sangkat Svay Dang Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-0 kum, Siem Reap Municilpality IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 30,901.96 0.00 plementatio 2022-09-06 2022-10-11 tions nvelope 9 , Siem Reap Province (1line l ulnerable Households SPD) n ength 0.157Km, width 5m, thi ckness 0.15m and lean concr ete thickness 0.05m). KH-MOI-308340-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Sangkat Krabei R Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 34,276.00 0.00 plementatio 2022-09-06 2022-10-11 iel, Siem Reap Municilpality, tions nvelope 9 ulnerable Households SPD) n Siem Reap Province ( 1 line l ength 1.153Km, width 4.00m, laterite thickness 0.15m). KH-MOI-308344-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Sangkat Tuek Vil, Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 32,644.33 0.00 plementatio 2022-09-06 2022-10-11 Siem Reap Municilpality, Sie tions nvelope 9 ulnerable Households SPD) n m Reap Province ( 3 line leng th 1.190Km, width 4.00m, lat erite thickness 0.15m). KH-MOI-308346-CW-RFQ / Re inforced concrete road constr uction at Ampil Commune, Br Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-0 asat Bakong District, Siem Re IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 28,513.00 0.00 plementatio 2022-09-06 2022-10-11 tions nvelope 9 ap Province(1line length 0.20 ulnerable Households SPD) n 0Km, width 5m, thickness 0.1 5m and lean concrete thickn ess 0.05m). KH-MOI-308347-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Ballangk Commu Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 13,912.00 0.00 plementatio 2022-09-06 2022-10-11 ne, Brasat Bakong District, Si tions nvelope 9 ulnerable Households SPD) n em Reap Province ( 1 line len gth 1.380Km, width 4.50m, la terite thickness 0.15m). KH-MOI-308348-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Kampong Phlouk Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 11,630.00 0.00 plementatio 2022-09-06 2022-10-11 Commune, Brasat Bakong Dis tions nvelope 9 ulnerable Households SPD) n trict, Siem Reap Province ( 1 l ine length 0.610Km, width 7. 00m, laterite thickness 0.15 m). KH-MOI-308349-CW-RFQ / Ea rth road repair and laterite p avement at Kantreang Comm Component 1: Improving Liv Request for Quot une, Brasat Bakong District, Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 28,305.00 0.00 Canceled 2022-09-06 2022-10-11 Siem Reap Province ( 1 line l tions nvelope 9 ulnerable Households SPD) ength 2.340Km, width 4.00m, laterite thickness 0.15m inclu ding 2 single pipe culvert wit h water gate Ø0.80m length 6m). KH-MOI-308350-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Mean Chey Com Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 22,180.00 0.00 plementatio 2022-09-06 2022-10-11 mune, Brasat Bakong District tions nvelope 9 ulnerable Households SPD) n , Siem Reap Province ( 3 line length 2.180Km, width 4.00m , laterite thickness 0.15m). Page 8 KH-MOI-308351-CW-RFQ / Ea rth road repair and laterite p avement at Trapeang Thum Component 1: Improving Liv Request for Quot Pending Im Commune, Brasat Bakong Dis Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 14,804.00 0.00 plementatio 2022-09-06 2022-10-11 trict, Siem Reap Province ( 1 l tions nvelope 9 ulnerable Households SPD) n ine length 1.650Km, width 5. 00m, laterite thickness 0.15 m including 1 double pipe cul vert Ø1.00m, length 7m). KH-MOI-308352-CW-RFQ / Re inforced concrete road constr uction at Mukh Paen Commu Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-0 ne, Pouk District, Siem Reap IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,945.92 0.00 plementatio 2022-09-06 2022-10-11 tions nvelope 9 Province(1line length 0.100K ulnerable Households SPD) n m, width 4.00m, thickness 0. 15m and lean concrete thick ness 0.05m) KH-MOI-308353-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Samrong Yea Co Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,013.94 0.00 plementatio 2022-09-06 2022-10-11 mmune, Pouk District, Siem R tions nvelope 9 ulnerable Households SPD) n eap Province ( 2 line length 0 .710Km, width 4.00m, laterit e thickness 0.15m) KH-MOI-308354-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Roeul Commune, Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,857.46 0.00 plementatio 2022-09-06 2022-10-11 Pouk District, Siem Reap Prov tions nvelope 9 ulnerable Households SPD) n ince ( 1 line length 0.850Km, width 4.00m, laterite thickne ss 0.15m) KH-MOI-308355-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Trei Nhor Commu Request for Quota Single Stage - One E 2023-01-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 13,194.23 0.00 plementatio 2022-09-06 2022-10-11 ne, Pouk District, Siem Reap tions nvelope 9 ulnerable Households SPD) n Province ( 1 line length 0.650 Km, width 4.00m, laterite thic kness 0.15m) KH-MOI-308356-CW-RFQ / Ea rth road repair and laterite p avement at Yeang Commune, Pouk District, Siem Reap Prov Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-0 ince (1 line length 0.616Km, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 38,310.02 0.00 plementatio 2022-09-06 2022-10-11 tions nvelope 9 width 4.00m, laterite thickne ulnerable Households SPD) n ss 0.15m including 2 single pi pe culvert Ø1.00m length 6m and 1 single pipe culvert Ø1. 00m, length 10m). KH-MOI-308358-CW-RFQ / Ea rth road repair and laterite p avement at Chroy Neang Ngo un Commune, Srei Snom Dist Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-0 rict, Siem Reap (1 line length IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 26,958.64 0.00 plementatio 2022-09-06 2022-10-11 tions nvelope 9 0.900Km, width 5.00m,laterit ulnerable Households SPD) n e thickness 0.15m including 1 small spillway length 50m, width 3.00m and 1 triple pipe culvert Ø1.00,length 20m) KH-MOI-308359-CW-RFQ / Ea rth road repair and laterite p avement at Leang Dai Comm une, Angkor Thom District, Si Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-0 em Reap (1 line length 0.600 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 21,613.52 0.00 plementatio 2022-09-06 2022-10-11 tions nvelope 9 Km, width 4.00m, laterite thic ulnerable Households SPD) n kness 0.15m including 1 singl e pipe culvert Ø1.00m length 8m and 3 double pipe culvert Ø1.00m, length 6m) KH-MOI-308361-CW-RFQ / Re inforced concrete Road in Ph um Prey Veng Lek, Sangkat P Component 2: Improving Liv Request for Quot Pending Im rey Veng, Khan Dangkao (Tot Request for Quota Single Stage - One E 2023-01-1 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 27,518.93 0.00 plementatio 2022-09-13 2022-10-18 al length 86m width, 0,15m t tions nvelope 6 Vulnerable Households SPD) n hickness) and Reinforced con crete Road in Phum Komrean g Sangkat Prey Veng ( Total l ength 94m, width, 0.15m thic kness) KH-MOI-308362-CW-RFQ / Re inforced concrete Road in Ph Component 2: Improving Liv Request for Quot Pending Im um Toul Sambo, Sangkat Pre Request for Quota Single Stage - One E 2023-01-1 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 15,831.22 0.00 plementatio 2022-09-13 2022-10-18 y Veng, Khan Dangkao (Total tions nvelope 6 Vulnerable Households SPD) n length 82m, 5m width, 0,15m thickness) Pipe Drainage (Tot al length 82m, Ǿ60 Diameter ) KH-MOI-308363-CW-RFQ / Re inforced concrete Road in Ph Component 2: Improving Liv Request for Quot Pending Im um Svay Chek Thmei, Sangka Request for Quota Single Stage - One E 2023-01-1 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 68,451.63 0.00 plementatio 2022-09-13 2022-10-18 t Kork Roka (Total length 420 tions nvelope 6 Vulnerable Households SPD) n m, 5m width, 0.15m thicknes s, Pipe (drainageTotal length 420m, Ǿ60 Diameter) KH-MOI-308365-CW-RFQ / Re inforced concrete Road in Ph um Prek Takong, Sangkat Ch Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-1 ak Angrae Leu, Khan Mean C IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 33,748.78 0.00 plementatio 2022-09-13 2022-10-18 tions nvelope 6 hey ( Total length 331m, 1,9 Vulnerable Households SPD) n m width, 0,15m thickness) Pi pe drainage (Total length 331 m,Ǿ60 Diameter) KH-MOI-308367-CW-RFQ / Re inforced concrete Road in Ph um Samaki 1 & Phum Samaki Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-03-1 2, Sangkat Trapeang Krasang IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 49,180.01 0.00 plementatio 2022-11-14 2022-12-19 tions nvelope 9 , Khan Pou Sen Chey (Total le Vulnerable Households SPD) n ngth 303m, 5m width, 0,15m thickness) Pipe drainage (Tot al length 202m, Ǿ60 Diamet er) KH-MOI-308369-CW-RFQ / Re inforced concrete Road in Ph um Thmar Kol 2, Sangkat Ch Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-03-1 oam Chau 2, Khan Pou Sen C IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 58,664.38 0.00 plementatio 2022-11-14 2022-12-19 tions nvelope 9 hey (Total length 223m, 5m Vulnerable Households SPD) n width, 230m, 4m width, 0,15 m thickness) Pipe Drainage ( Total length 95m, Ǿ60 Diam eter) KH-MOI-308373-CW-RFQ / Re inforced concrete Road in Ph um Prey Lvea, Sangkat Choa Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-03-1 m Chau 2, Khan Pou Senchey IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 21,069.09 0.00 plementatio 2022-11-14 2022-12-19 tions nvelope 9 (Total length 128m, 4m width Vulnerable Households SPD) n , 0,15m thickness) Pipe drain age (Total length 128m, Ǿ60 Diameter) KH-MOI-308377-CW-RFQ / Re inforced concrete Road in Ph Component 2: Improving Liv Request for Quot Pending Im um 8, Sangkat Boeung Kak 1, Request for Quota Single Stage - One E 2022-11-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 6,267.27 0.00 plementatio 2022-09-06 2022-10-04 Khan Toul Kork (Total length tions nvelope 3 Vulnerable Households SPD) n 60m, 2m width, 0,15m thickn ess) and Pipe drainage (Total length 60m, Ǿ50 Diameter) KH-MOI-308399-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-01-1 in Phum Sampore Thmei & Ph IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 9,548.35 0.00 plementatio 2022-11-14 2022-12-19 tions nvelope 8 um Andong 4, Sangkat Korkr Vulnerable Households SPD) n oka, Khan Praek Phnov (Total set 48 Sets) KH-MOI-308400-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im in Phum Khmer Leu Thmei, P Request for Quota Single Stage - One E 2022-11-1 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 20,227.63 0.00 plementatio 2022-09-06 2022-10-11 hum Chres Thmei & Phum An tions nvelope 0 Vulnerable Households SPD) n dong 3, Sangkat Kork Roka , Khan Prek Phnov (Total set 1 15 Sets) KH-MOI-308404-CW-RFQ / Re inforced concrete Road in Ph Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-12-0 um Trapeng Reang Chas, San IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 23,178.21 0.00 plementatio 2022-09-06 2022-10-04 tions nvelope 3 gkat Khmounh, Khan Sen Sok Vulnerable Households SPD) n (Total length 201m, 4m width , 0,15m thickness) KH-MOI-308407-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-12-0 in Phum Samaki 3 & Phum Sa IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 10,995.89 0.00 plementatio 2022-09-06 2022-10-04 tions nvelope 3 maki 4, Sangkat Trapeang Kr Vulnerable Households SPD) n asang, Khan Pou Senchey (To tal set 57 Sets) KH-MOI-308408-CW-RFQ / Re inforced concrete Road in Ph um Samaki1, Sangkat Trapen Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-12-0 g Krasang, Khan Pou Sen Che IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 18,293.00 0.00 plementatio 2022-09-06 2022-10-04 tions nvelope 3 y (Total length 101m, 5m wid Vulnerable Households SPD) n th, 0,15m thickness) and Pipe drainage (Total length 101m, Ǿ60 Diameter) KH-MOI-308411-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im in Phum Trapeang Chak, Phu Request for Quota Single Stage - One E 2022-12-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,422.16 0.00 plementatio 2022-09-06 2022-10-04 m Prey Veng Lech and Phum tions nvelope 3 Vulnerable Households SPD) n Kamreang , Sangkat Prey Ve ng , Khan Dangkao (Total set 38 Sets) Page 9 KH-MOI-308412-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2022-12-0 in Phum Serei Deidos & Phum IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 21,366.76 0.00 plementatio 2022-09-06 2022-10-04 tions nvelope 3 Toul Sambo, Sangkat Prey Ve Vulnerable Households SPD) n ng , Khan Dangkao (Total set 111 Sets) KH-MOI-308413-CW-RFQ / So Component 2: Improving Liv Request for Quot Pending Im lar LED Power Street lighting Request for Quota Single Stage - One E 2023-03-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 3,982.03 0.00 plementatio 2022-12-06 2023-01-03 in Phum Mol, Sangkat Dangk tions nvelope 4 Vulnerable Households SPD) n ao , Khan Dangkao (Total set 21 Sets) KH-MOI-308416-CW-RFQ / Re inforced concrete Road in Ph um Daeum Slaeng 1, Sangkat Component 2: Improving Liv Request for Quot Pending Im Chbar Ampov 2, Khan Chbar Request for Quota Single Stage - One E 2023-03-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 19,091.50 0.00 plementatio 2022-12-06 2023-01-03 Ampov (Total length 218m, 2 tions nvelope 4 Vulnerable Households SPD) n ,8m everage width, 0,15m thi ckness) and Solar LED Power Street lighting in Phum Daeu m Chan total set ( 15 Sets) KH-MOI-308420-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-03-0 in Phum Prek Takong 3 , San IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 5,684.32 0.00 plementatio 2022-12-06 2023-01-03 tions nvelope 4 gkat Chak Angrae Leu, Khan Vulnerable Households SPD) n Meanchey (Total set 30 Sets) KH-MOI-308422-CW-RFQ / So Component 2: Improving Liv Request for Quot Pending Im lar LED Power Street lighting Request for Quota Single Stage - One E 2023-03-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 11,697.35 0.00 plementatio 2022-12-06 2023-01-03 in Phum 3 & Phum 12, Sangk tions nvelope 4 Vulnerable Households SPD) n at Srah Chak, Khan Daun Pen h (Total set 70 Sets) KH-MOI-308423-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-03-0 in Phum Sen Sok 5 & Phum A IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 7,446.96 0.00 plementatio 2022-12-06 2023-01-03 tions nvelope 4 nlong Kra Ngan, Sangkat Kh Vulnerable Households SPD) n mounh , Khan Sen Sok (Total set 35 Sets) KH-MOI-308424-CW-RFQ / So lar LED Power Street lighting Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-03-0 in Phum Andong 5 & Phum A IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 11,697.35 0.00 plementatio 2022-12-06 2023-01-03 tions nvelope 4 ndong 6, Sangkat Kork Roka, Vulnerable Households SPD) n Khan Prek Phnov (Total set 8 5Sets) KH-MOI-308425-CW-RFQ / Re inforced concrete Road in Ph Component 2: Improving Liv Request for Quot Pending Im um Sampore Thmei & Phum Request for Quota Single Stage - One E 2023-03-0 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 13,270.01 0.00 plementatio 2022-12-06 2023-01-03 Chres Thmei, Sangkat Kork R tions nvelope 4 Vulnerable Households SPD) n oka, Khan Prek Phnov (Total l ength 70m, 4m width, 67m, 3 m width, 0,15m thickness) KH-MOI-335443-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Anlong Samnor C Request for Quota Single Stage - One E 2023-05-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 14,567.66 0.00 plementatio 2023-01-25 2023-03-01 ommune, Chikreang District, tions nvelope 0 ulnerable Households SPD) n Siem Reap Province ( 1 line l ength 1Km, width 4.00m, late rite thickness 0.15m) KH-MOI-340923-CW-RFQ / Ea rth road repair and laterite p Component 1: Improving Liv Request for Quot Pending Im avement at Anlong Samnor C Request for Quota Single Stage - One E 2023-06-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 14,567.66 0.00 plementatio 2023-02-17 2023-03-24 ommune, Chikreang District, tions nvelope 2 ulnerable Households SPD) n Siem Reap (2 lines length 1. 000Km, width 4.00m, laterite thickness 0.15m), KH-MOI-340924-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im nstruction of animal feed mill Request for Quota Single Stage - One E 2023-06-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,000.00 0.00 plementatio 2023-02-25 2023-04-01 at Svay Chek Commune, Ang tions nvelope 0 ulnerable Households SPD) n kor Thom District Siem Reap (1 places) KH-MOI-340925-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im nstruction of animal feed mill Request for Quota Single Stage - One E 2023-06-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,000.00 0.00 plementatio 2023-02-25 2023-04-01 at Chob Ta Trav Commune, A tions nvelope 0 ulnerable Households SPD) n ngkor Thom District Siem Re ap (1 places) KH-MOI-343643-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im nstruction of community agri Request for Quota Single Stage - One E 2023-06-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,000.00 0.00 plementatio 2023-02-25 2023-04-01 culture center at Sambour Co tions nvelope 0 ulnerable Households SPD) n mmune, Kralanh District, Sie m Reap (1 place) KH-MOI-343645-CW-RFQ / Co nstruction of community agri Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-3 culture center at Peak Sneing IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,000.00 0.00 plementatio 2023-02-25 2023-04-01 tions nvelope 0 Commune, Angkor Thom Dist ulnerable Households SPD) n rict, Siem Reap (1 place) KH-MOI-343652-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im nstruction of community agri Request for Quota Single Stage - One E 2023-06-3 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,000.00 0.00 plementatio 2023-02-25 2023-04-01 culture center at Svay Leu Co tions nvelope 0 ulnerable Households SPD) n mmune, Svay Leu District, Si em Reap (1 place) KH-MOI-343656-CW-RFQ / Re inforced concrete road in Ph Component 2: Improving Liv Request for Quot Pending Im um Trapeang Anhchanh 6, Sa Request for Quota Single Stage - One E 2023-06-3 IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 22,000.00 0.00 plementatio 2023-02-25 2023-04-01 ngkat Trapeang Krasang, Kha tions nvelope 0 Vulnerable Households SPD) n n Pou Saen Chey (Total lengt h 220m, 4m width, 0.15m thi ckness) KH-MOI-343661-CW-RFQ / Re inforced concrete road in Ph um Trapeang Anhchanh 3, Sa ngkat Trapeang Krasang, Kha Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-3 n Pou Saen Chey (Total lengt IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 18,950.00 0.00 plementatio 2023-02-25 2023-04-01 tions nvelope 0 h 55m, 4m width, 0.15m thic Vulnerable Households SPD) n kness) and Pipe drainage in P hum Trapeang Anhchanh 5, S angkat Trapeang Krasang, Kh an Pou Saen Chey (Total leng th 269 KH-MOI-343666-CW-RFQ / So lar LED Street Lighting in Phu Component 2: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-3 m Samaki 5 & Samaki 6, San IDA / 59600 elihoods for Urban Poor and Post Open - National ations (Non Bank- 15,400.00 0.00 plementatio 2023-02-25 2023-04-01 tions nvelope 0 gkat Trapeang Krasang, Khan Vulnerable Households SPD) n Pou Saen Chey ( Ttal set 77 S ets) KH-MOI-352202-CW-RFQ / Co ncrete road at Chroy Neang Component 1: Improving Liv Request for Quot Pending Im Ngoun Commune, Srei Snom Request for Quota Single Stage - One E 2023-08-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 51,452.00 0.00 plementatio 2023-04-05 2023-05-10 District, Siem Reap ( 1 line le tions nvelope 8 ulnerable Households SPD) n ngth 1.750Km, width 4.00m, concrete thickness 0.15m) KH-MOI-352204-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im nstruction of animal feed mill Request for Quota Single Stage - One E 2023-08-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 30,920.00 0.00 plementatio 2023-04-05 2023-05-10 at Dan Run Commune, Sotr N tions nvelope 8 ulnerable Households SPD) n ikum District Siem Reap (2 pl aces) KH-MOI-352205-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im nstruction of animal feed mill Request for Quota Single Stage - One E 2023-08-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 30,285.00 0.00 plementatio 2023-04-04 2023-05-09 at Kandeak Commune, Prasat tions nvelope 7 ulnerable Households SPD) n Bakong District Siem Reap (2 places) KH-MOI-352208-CW-RFQ / So Component 1: Improving Liv Request for Quot Pending Im lar street lights at Bakong Co Request for Quota Single Stage - One E 2023-08-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 36,192.00 0.00 plementatio 2023-04-05 2023-05-10 mmune, Prasat Bakong Distri tions nvelope 8 ulnerable Households SPD) n ct Siem Reap ( 208 poles) KH-MOI-352211-CW-RFQ / So Component 1: Improving Liv Request for Quot Pending Im lar street lights at Khnorng P Request for Quota Single Stage - One E 2023-08-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 13,640.55 0.00 plementatio 2023-04-04 2023-05-09 hmon Commune, Svay Leu Di tions nvelope 7 ulnerable Households SPD) n strict Siem Reap ( 77 poles) KH-MOI-352214-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im mmunity water supply syste Request for Quota Single Stage - One E 2023-08-0 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 34,268.58 0.00 plementatio 2023-04-05 2023-05-10 m at Beung Mealea Commun tions nvelope 8 ulnerable Households SPD) n e, Svay Leu District Siem Rea p (1place) KH-MOI-352218-CW-RFQ / Co nstruction of animal feed mill Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-2 at Anlong Samnar Commune IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,750.00 0.00 plementatio 2023-04-05 2023-04-23 tions nvelope 2 , Chikreang District, Siem Re ulnerable Households SPD) n ap (1places), Location: Lberk Village. KH-MOI-352222-CW-RFQ / Co nstruction of animal feed mill Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-2 at Anlong Samnar Commune IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,750.00 0.00 plementatio 2023-04-05 2023-04-23 tions nvelope 2 , Chikreang District, Siem Re ulnerable Households SPD) n ap (1places), Location: Anlon g Samnar Villages. KH-MOI-352225-CW-RFQ / Co nstruction of animal feed mill Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-2 at Kampong Kdei Commune, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,750.00 0.00 plementatio 2023-04-05 2023-04-23 tions nvelope 2 Chikreang District, Siem Rea ulnerable Households SPD) n p (1places), Location: Ponleu Preah Phos Village Page 10 KH-MOI-352226-CW-RFQ / Co nstruction of animal feed mill Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-2 at Kampong Kdei Commune, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,750.00 0.00 plementatio 2023-04-05 2023-04-23 tions nvelope 2 Chikreang District, Siem Rea ulnerable Households SPD) n p (1places), Location: Roka Vi llage. KH-MOI-352227-CW-RFQ / Co nstruction of animal feed mill Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-2 at Kampong Kdei Commune, IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,750.00 0.00 plementatio 2023-04-05 2023-04-23 tions nvelope 2 Chikreang District, Siem Rea ulnerable Households SPD) n p (1places), Location: Chamb ak Thom Village KH-MOI-352228-CW-RFQ / Co nstruction of animal feed mill Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-2 at Chrouy Neang Nguon Com IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 15,750.00 0.00 plementatio 2023-04-05 2023-04-23 tions nvelope 2 mune Srey Snom District, Sie ulnerable Households SPD) n m Reap (1place), Location: Tr om Tbong Village. KH-MOI-352229-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im nstruction of community agri Request for Quota Single Stage - One E 2023-06-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,000.00 0.00 plementatio 2023-04-05 2023-04-23 culture center at Klang Hai C tions nvelope 2 ulnerable Households SPD) n ommune, Srei Snom District, Siem Reap (1 place) KH-MOI-352230-CW-RFQ / Co nstruction of community agri Component 1: Improving Liv Request for Quot Pending Im Request for Quota Single Stage - One E 2023-06-2 culture center at Kampongkd IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,000.00 0.00 plementatio 2023-04-05 2023-04-23 tions nvelope 2 rey Commune, Chi Kreang Di ulnerable Households SPD) n strict, Siem Reap (1 place) KH-MOI-352233-CW-RFQ / Co Component 1: Improving Liv Request for Quot Pending Im nstruction of community agri Request for Quota Single Stage - One E 2023-06-2 IDA / 59600 elihoods for Rural Poor and V Post Open - National ations (Non Bank- 20,000.00 0.00 plementatio 2023-04-05 2023-04-23 culture center at Sasar Sdom tions nvelope 2 ulnerable Households SPD) n Commune, Pourk District, Sie m Reap (1 place) GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approac Procurement Pr Prequalification Estimated Am Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. h ocess (Y/N) ount (US$) t (US$) atus n Documents uation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-14029-GO-RFQ / Offi Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl ce Furniture for National Leve IDA / 59600 Post Open - National 27,380.00 0.00 2017-07-14 2017-09-03 2017-10-18 ement tions nvelope ementation l and Sub National Level KH-MOI-14017-GO-RFQ / Soft Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 59600 Post Open - National 10,000.00 0.00 2017-07-31 2017-09-20 2017-11-19 wares ( Accounting) for PCO- ement tions nvelope ementation MOI 1 unit KH-MOI-26199-GO-RFB / Mot Component 1: Improving Liv orcycles plus helmets for Nati Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Request for Bids Open - National 226,100.00 0.00 2017-10-02 2017-10-16 2017-11-15 2017-12-06 2018-01-03 2018-03-04 onal level and Sub-National ( nvelope ementation ulnerable Households Total 133 Units) KH-MOI-26827-GO-RFB / Lot 1: Develop Management Infor mation System (MIS) System Component 3: Project Manag Single Stage - One E Pending Impl Lot2: Server, Networ IDA / 59600 Post Request for Bids Open - National 140,000.00 0.00 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 ement nvelope ementation k, Tablet, website, etc.) Lot 3 :MIS webside maintenance fo r PCO-MOI KH-MOI-33988-GO-RFQ / 4 L Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 59600 Post Open - National 9,200.00 0.00 2017-11-05 2017-12-05 2017-12-20 aptop Computers for Manage ement tions nvelope ementation ment KH-MOI-34259-GO-RFB / Offi Component 3: Project Manag Single Stage - One E Under Imple ce Equipment for National an IDA / 59600 Post Request for Bids Open - National 132,200.00 0.00 2017-11-08 2019-01-10 2017-11-13 2017-12-15 2019-02-15 2018-01-14 2018-02-18 2018-04-19 ement nvelope mentation d Sub National Leve KH-MOI-36613-GO-UN / Lot1: Vehicles (Station Wagon) 3 u nits for -PCO-MOI and 1 units Component 1: Improving Liv UN Agencies (Dire Pending Impl for MEF, IDA / 59600 elihoods for Rural Poor and V Post Direct 330,000.00 0.00 2017-11-17 2017-11-22 2017-12-25 2018-02-23 ct) ementation Lot2:Vehicles (Pick up Cars) f ulnerable Households or 1units for GDA-MAFF, 3 uni ts for Siem Reap and 2 units for PPM. The total Vehicles: 10 Units KH-MOI-34266-GO-UN / Vehi Component 1: Improving Liv cles (Station Wagon) 3 units f UN Agencies (Dire IDA / 59600 elihoods for Rural Poor and V Post Direct 132,000.00 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-02-23 or -PCO-MOI and 1 units for ct) ulnerable Households MEF, Total Vehicles: 4 Units KH-MOI-11051-GO-RFB / Veh Component 1: Improving Liv icles (Pick up Cars) for 1units Single Stage - One E IDA / 59600 elihoods for Rural Poor and V Post Request for Bids Open - National 198,000.00 0.00 Canceled 2017-10-02 2017-10-16 2017-11-15 2017-12-15 2018-01-07 2018-05-07 for GDA-MAFF, 3 units for Sie nvelope ulnerable Households m Reap and 2 units for PPM. Total Vehicles: 6 Units KH-MOI-99858-GO-RFQ / Tot Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 59600 Post Open - National 4,900.00 0.00 2019-03-06 2019-04-03 2019-04-17 al 7 Air Conditioners for PCO ement tions nvelope ementation and MAFF KH-MOI-99860-GO-RFQ / Offi Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 59600 Post Open - National 20,000.00 0.00 2019-03-06 2019-04-03 2019-05-03 ce Furniture for MOI-PCO ement tions nvelope ementation KH-MOI-99861-GO-RFQ / Prin Component 1: Improving Liv ting Material and Thumbprint Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 22,644.00 0.00 2019-03-06 2019-04-03 2019-05-03 pad for SHG/producer group/ tions nvelope ementation ulnerable Households commune federation for 201 9 KH-MOI-99863-GO-RFQ / Mat Component 1: Improving Liv erial for SHG/producer group/ Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 31,250.00 0.00 2019-03-06 2019-04-24 2019-05-24 commune federation (Boxes f tions nvelope ementation ulnerable Households or keeping documents and ca sh) KH-MOI-99865-GO-RFQ / Equ Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl ipment for Commune/Sangka IDA / 59600 elihoods for Rural Poor and V Post Open - National 10,000.00 0.00 2019-03-06 2019-04-03 2019-04-18 tions nvelope ementation t Investment Projects (SRP an ulnerable Households d PPCH) KH-MOI-99868-GO-RFQ / 72 Component 1: Improving Liv Tablets for MIS (3 MoI, 3 GDA Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 24,840.00 0.00 2019-04-06 2019-05-04 2019-06-03 , 3 PPCH, 3 Pro. S_Reap, 47 c tions nvelope ementation ulnerable Households ommune, 13 Sangkat) KH-MOI-99869-GO-RFQ / Prin Component 1: Improving Liv ting Materials (Logos, Printed Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 20,250.00 0.00 2019-05-06 2019-06-03 2019-06-24 Folder, Factsheets, Newslette tions nvelope ementation ulnerable Households rs, Brochures, Posters and St anding Poster) KH-MOI-99871-GO-RFQ / Prin Component 1: Improving Liv Request for Quota Single Stage - One E Under Imple ting Materials for SHG/produc IDA / 59600 elihoods for Rural Poor and V Post Open - National 20,145.00 0.00 2019-12-06 2020-01-04 2020-02-03 tions nvelope mentation er group/commune federatio ulnerable Households n for 2020 KH-MOI-26829-GO-RFB / Mat erial for SHG/Poducer group/c Component 1: Improving Liv ommune federation(books ke Single Stage - One E IDA / 59600 elihoods for Rural Poor and V Post Request for Bids Open - National 126,250.70 0.00 Canceled 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 eping, cash book, pay and lo nvelope ulnerable Households an record book, SHG box for keeping docs. And Thumprint pad) for SRP KH-MOI-121052-GO-RFQ / Pr Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl ocurement of supply Server IDA / 59600 Post Open - National 20,000.00 0.00 2019-07-10 2019-08-04 2019-09-03 ement tions nvelope ementation and network for LEAP Project KH-MOI-136652-GO-RFQ / Of Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl fice Furniture for Skill Develo IDA / 59600 elihoods for Rural Poor and V Post Open - National 4,400.00 0.00 2019-10-16 2019-11-11 2019-11-25 tions nvelope ementation pment Activities ulnerable Households KH-MOI-136666-GO-RFQ / M Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl otorcycles for Skill Developm IDA / 59600 elihoods for Rural Poor and V Post Open - National 17,500.00 0.00 2019-10-16 2019-11-11 2019-11-25 tions nvelope ementation ent Activities (10 Units) ulnerable Households KH-MOI-168855-GO-RFQ / Ve Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl hicles (VAN) 1 units for -PCO- IDA / 59600 elihoods for Rural Poor and V Post Open 30,000.00 0.00 2020-04-29 2020-06-05 2020-07-05 tions nvelope ementation MOI ( Import tax will be exem ulnerable Households pted) KH-MOI-168856-GO-RFQ / Of Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl fice Furniture for Sub Nationa IDA / 59600 elihoods for Rural Poor and V Post Open - National 16,915.00 0.00 2020-05-02 2020-05-28 2020-06-27 tions nvelope ementation l Level (PCO, SRP ) ulnerable Households KH-MOI-168859-GO-RFQ / St udy Equipment (Hummer Tes Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl t, DCP Test, Autormatic Level IDA / 59600 elihoods for Rural Poor and V Post Open - National 11,000.00 0.00 2020-05-06 2020-05-29 2020-06-13 tions nvelope ementation , GPS…2sets) for Commnune/ ulnerable Households Sangkat Investment Projects (SRP) KH-MOI-168860-GO-RFQ / Pri nting Communication Materia Component 1: Improving Liv Request for Quota Single Stage - One E Under Imple ls (LEAP Newsletters semi-an IDA / 59600 elihoods for Rural Poor and V Post Open - National 12,000.00 0.00 2020-06-20 2020-07-18 2020-08-08 tions nvelope mentation nual (2time/years) in Khmer ulnerable Households and English 2time/year) Page 11 KH-MOI-168861-GO-RFQ / Pri Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl nting Communication Materia IDA / 59600 elihoods for Rural Poor and V Post Open - National 4,000.00 0.00 2020-09-06 2020-10-04 2020-10-25 tions nvelope ementation ls ( Success Story 4 time/year ulnerable Households ) KH-MOI-168862-GO-RFQ / Vi Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl deo Production of project ach IDA / 59600 elihoods for Rural Poor and V Post Open - National 7,000.00 0.00 2020-09-06 2020-09-29 2020-10-29 tions nvelope ementation ievement (15 Minute) ulnerable Households KH-MOI-226724-GO-RFB / Ve Component 1: Improving Liv hicles (VAN) 1 units for -PCO- Single Stage - One E Under Imple IDA / 59600 elihoods for Rural Poor and V Post Request for Bids Open - National 130,000.00 0.00 2021-04-18 2021-04-23 2021-04-23 2021-04-27 2021-05-23 2021-06-22 2021-07-27 2021-08-02 MOI, Vehicles (Pick up Cars) nvelope mentation ulnerable Households 2 units for Siem Reap KH-MOI-226726-GO-UN / SU Component 2: Improving Liv UN Agencies (Dire Pending Impl V Vehicles 1 units for PPCH( I IDA / 59600 elihoods for Urban Poor and Post Direct 40,000.00 0.00 2021-04-18 2021-04-21 2021-06-02 2021-08-31 ct) ementation mport tax will be exempted) Vulnerable Households KH-MOI-226728-GO-RFQ / M Component 1: Improving Liv Request for Quota Single Stage - One E Under Imple otorcycles( 12 Units for SRP a IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,000.00 0.00 2021-04-19 2021-04-27 2021-05-29 2021-06-28 tions nvelope mentation nd 3 Units for MAFFs) ulnerable Households KH-MOI-226744-GO-RFQ / Of fice Equipment: (4 Laptops fo r PCO, 2 Laptops for PPCH ,5 Component 3: Project Manag Request for Quota Single Stage - One E Under Imple IDA / 59600 Post Open - National 33,032.00 0.00 2021-04-26 2021-05-21 2021-06-23 2021-07-23 Laptops for MAFF , 4 Note Bo ement tions nvelope mentation ok for SC, 2 Desktops for PPC H, 1 Printer for MAFF, and 15 Tablets for New CF-SRP) KH-MOI-226750-GO-RFQ / Pr ocurement of 1 unit Stability Camera Stand ,1 unit Zoom-L Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl IDA / 59600 Post Open - National 7,400.00 0.00 2021-05-02 2021-06-15 2021-07-15 en Camera ,1 Unit Drone Ca ement tions nvelope ementation mera for SRP and 1Unit Zoom -Len Camera,1set Equipment of video conference for PPCH KH-MOI-226753-GO-RFQ / Ins Component 3: Project Manag Request for Quota Single Stage - One E Pending Impl tallation Microphone System IDA / 59600 Post Open - National 20,000.00 0.00 2021-06-02 2021-07-16 2021-08-15 ement tions nvelope ementation for PCO-LEAP meeting room KH-MOI-226767-GO-RFQ / M aterials for SHG/producer gro up (14000 Cash book for SHG Component 1: Improving Liv Request for Quota Single Stage - One E Under Imple s member, 1200 SHGs Saving IDA / 59600 elihoods for Rural Poor and V Post Open - National 30,400.00 0.00 2021-04-26 2021-04-27 2021-06-23 2021-07-23 tions nvelope mentation , Loan & Repayment Books,1 ulnerable Households 200 SHG minute books, 4000 SHG minute books and 1200 Thumbprint pad for SHG 202 1 KH-MOI-226770-GO-RFQ / Pu Component 1: Improving Liv rchase 25 Booth for PGs to pr Request for Quota Single Stage - One E Under Imple IDA / 59600 elihoods for Rural Poor and V Post Open - National 6,875.00 0.00 2021-05-04 2021-06-10 2021-07-10 omote agriculture products f tions nvelope mentation ulnerable Households or weekend Market for SMT-S RP KH-MOI-226776-GO-RFQ / Pri nting Communication Materia Component 1: Improving Liv Request for Quota Single Stage - One E Under Imple ls (LEAP Newsletters semi-an IDA / 59600 elihoods for Rural Poor and V Post Open - National 8,500.00 0.00 2021-05-08 2021-11-10 2021-06-05 2021-12-02 tions nvelope mentation nual (2time/years) in Khmer ulnerable Households and English 2time/year) 2021 KH-MOI-226782-GO-RFQ / Pri Component 1: Improving Liv nting 140 Produce PCV Banne Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 9,400.00 0.00 2021-04-19 2021-05-25 2021-06-15 r and 11200 leaflets on Skills tions nvelope ementation ulnerable Households Development information for SRP and PPCH KH-MOI-226783-GO-RFQ / Pri nting Tools to Provide technic al training for CAHEWs in Q1 Component 1: Improving Liv and Q2 on (Chicken Eggs Inc Request for Quota Single Stage - One E Under Imple IDA / 59600 elihoods for Rural Poor and V Post Open - National 52,500.00 0.00 2021-05-04 2021-11-01 2021-06-30 2021-12-27 ubator Making), (how to use tions nvelope mentation ulnerable Households vaccination kits), 50 Sets ( ch icken raising ) (Pig Raising) a nd 50 Sets PCV Banner Traini ng Tools (Fish (rice and vege table production) KH-MOI-226784-GO-RFQ / De Component 1: Improving Liv sign and print out banner to Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 3,000.00 0.00 2021-05-04 2021-06-09 2021-06-30 mainstream information on g tions nvelope ementation ulnerable Households ender to target beneficiaries KH-MOI-283063-GO-RFQ / Pri Component 1: Improving Liv nting Newsletters semi-annu Request for Quota Single Stage - One E Under Imple IDA / 59600 elihoods for Rural Poor and V Post Open - National 12,750.00 0.00 2022-05-06 2022-11-22 2022-06-03 2022-06-24 al (2 time/year) and Success tions nvelope mentation ulnerable Households Story leaflet (SRP and PPCH) KH-MOI-283065-GO-RFQ / Pri Component 1: Improving Liv nting Material for SHG (SHGs Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 5,500.00 0.00 2022-04-20 2022-05-18 2022-06-08 cash, bank book, SHGs savin tions nvelope ementation ulnerable Households g, loan & repayment book) to tal 2000books KH-MOI-283066-GO-RFQ / De Component 1: Improving Liv sign and print out Poster to m Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 3,000.00 0.00 2022-04-20 2022-05-18 2022-06-08 ainstream information on gen tions nvelope ementation ulnerable Households der to target beneficiaries (S HGs1,000) KH-MOI-340907-GO-RFQ / Pri Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl nting Newsletters (SRP and P IDA / 59600 elihoods for Rural Poor and V Post Open - National 4,500.00 0.00 2023-05-06 2023-06-03 2023-06-24 tions nvelope ementation PCH) ulnerable Households KH-MOI-340911-GO-RFQ / 8 Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl Computers desktops and 8 pr IDA / 59600 elihoods for Rural Poor and V Post Open - National 4,683.00 0.00 2023-03-28 2023-05-04 2023-06-03 tions nvelope ementation inters for Acs ulnerable Households KH-MOI-364895-GO-RFQ / Pr Component 1: Improving Liv Request for Quota Single Stage - One E Under Imple oduce short video stories (20 IDA / 59600 elihoods for Rural Poor and V Post Open - National 8,000.00 0.00 2023-06-30 2023-08-25 2023-10-24 tions nvelope mentation minutes) on project achieve ulnerable Households ments (PCO) KH-MOI-378255-GO-RFQ / 16 Component 1: Improving Liv Request for Quota Single Stage - One E Pending Impl mobile tablets to replace the IDA / 59600 elihoods for Rural Poor and V Post Open - National 6,720.00 0.00 2023-09-22 2023-10-15 2023-11-05 tions nvelope ementation old ones that are broken ulnerable Households NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approac Procurement Pr Prequalification Estimated Am Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. h ocess (Y/N) ount (US$) t (US$) atus n Documents uation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-99864-NC-RFQ / Dev Component 3: Project Manag Request for Quota Single Stage - One E Under Imple IDA / 59600 Post Open - National 5,600.00 0.00 2019-03-06 2019-04-03 2019-05-03 elop Website for LEAP Projec ement tions nvelope mentation Component 1: Improving Liv KH-MOI-99870-NC-RFQ / Fou Request for Quota Single Stage - One E Pending Impl IDA / 59600 elihoods for Rural Poor and V Post Open - National 20,000.00 0.00 2019-07-06 2019-08-17 2019-10-16 r (4) Video Spots tions nvelope ementation ulnerable Households KH-MOI-226780-NC-RFQ / Vi Component 3: Project Manag Request for Quota Single Stage - One E Under Imple deo Production of project ach IDA / 59600 Post Open - National 7,000.00 0.00 2021-07-06 2021-09-20 2021-08-17 2021-10-16 ement tions nvelope mentation ievement 2021 KH-MOI-283064-NC-RFQ / Pr Component 3: Project Manag Request for Quota Single Stage - One E Under Imple oduce short video stories (15 IDA / 59600 Post Open - National 7,000.00 0.00 2022-06-06 2022-10-27 2022-07-18 2022-09-16 ement tions nvelope mentation minutes) on project achieve ments (PCO) CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interes Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Request for Proposal Report and Draft Neg Signed Contract Contract Completion No. h unt (US$) t (US$) t Notice s as Issued Proposals / Minutes cal Proposal s otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-82848-CS-CQS / Dev elopment of Community Instit Component 1: Improving Liv Consultant Qualifi Under Implement utions of the Poor for 4 Distri IDA / 59600 elihoods for Rural Poor and V Post Open - National 280,000.00 0.00 2018-10-22 2019-01-18 2018-11-12 2019-01-11 2019-02-10 2019-03-17 2022-11-30 cation Selection ation cts​​  (Angkor Thum, Kralanh, P ulnerable Households ouk and Srei Snam District) KH-MOI-82083-CS-CQS / Dev elopment of Community Instit Component 1: Improving Liv Consultant Qualifi Under Implement utions of the Poor for 5 Distri IDA / 59600 elihoods for Rural Poor and V Post Open - National 290,000.00 0.00 2018-10-22 2018-12-21 2018-11-12 2019-01-11 2019-03-22 2019-02-10 2019-06-14 2019-03-17 2022-12-05 cation Selection ation cts ( Chi Kraeng, Prasat Bako ulnerable Households ng, Siem Reap, Soutr Nikom and Svay Leu District) KH-MOI-70310-CS-QCBS / Hu Component 1: Improving Liv Quality And Cost- Open - Internationa man Resource Development IDA / 59600 elihoods for Rural Poor and V Prior 784,000.00 0.00 Canceled 2018-12-14 2019-01-13 2019-01-16 2019-02-26 2019-05-10 2019-04-12 2019-05-12 2019-06-16 2019-07-21 2023-06-30 Based Selection l Service Provider (HRDSP) for ulnerable Households SRP and PPCH KH-MOI-39858-CS-QCBS / Hu Component 2: Improving Liv man Resources Development Quality And Cost- Open - Internationa IDA / 59600 elihoods for Urban Poor and Post 367,932.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Services Provider(HRDSP) for Based Selection l Vulnerable Households PPM (NGO/Firm) Page 12 KH-MOI-39860-CS-CQS / Bas Component 3: Project Manag Consultant Qualifi eline Survey (1st year)(Local IDA / 59600 Post Open - National 30,000.00 0.00 Canceled 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 ement cation Selection Firm) at PCO-MOI KH-MOI-39857-CS-QCBS / Hu Component 1: Improving Liv man Resources Development Quality And Cost- Open - Internationa IDA / 59600 elihoods for Rural Poor and V Post 545,936.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Services Provider(HRDSP) for Based Selection l ulnerable Households SRP (NGO/Firm) KH-MOI-187154-CS-CQS / Tr Component 1: Improving Liv acer Study Consultant for 24 Consultant Qualifi Under Implement IDA / 59600 elihoods for Rural Poor and V Post Open - National 45,000.00 0.00 2020-08-10 2020-08-07 2020-08-31 2020-08-23 2020-10-14 2020-11-13 2020-12-18 2022-12-08 months (one firm consultant cation Selection ation ulnerable Households will be hired for both SRP and PPCH) KH-MOI-39863-CS-CQS / Imp act Survey (3nd year of the p Component 3: Project Manag Consultant Qualifi IDA / 59600 Post Open - National 30,000.00 0.00 Canceled 2020-01-02 2020-01-23 2020-03-07 2020-04-06 2020-05-11 2020-11-07 roject/Mid-term review) (Loca ement cation Selection l Firm) at PCO-MOI KH-MOI-39867-CS-CQS / Fina l Impact Survey ( (5th year of Component 3: Project Manag Consultant Qualifi IDA / 59600 Post Open - National 40,000.00 0.00 Canceled 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 Project evaluation and compl ement cation Selection etion report) (Local Firm) at P CO-MOI INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion No. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-13893-CS-INDV / Pro Component 1: Improving Liv Individual Consult Under Implement vincial Operation and M&E Sp IDA / 59600 elihoods for Rural Poor and V Post Open 120,000.00 0.00 2017-06-26 2017-12-07 2017-08-23 2018-04-30 2017-09-06 2018-04-30 2017-10-11 2022-10-10 ant Selection ation ecialist for SRP (60 Months) ulnerable Households KH-MOI-13901-CS-INDV / Pro Component 3: Project Manag Individual Consult Pending Impleme IDA / 59600 Post Open 18,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2020-10-24 ject Assistant for PCO-MOI (6 ement ant Selection ntation 0 Months) KH-MOI-13903-CS-INDV / Nat Component 2: Improving Liv Individual Consult Pending Impleme ional Operation and M&E Spe IDA / 59600 elihoods for Urban Poor and Post Open 150,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2022-10-10 ant Selection ntation cialist for PPM (60 Months) Vulnerable Households KH-MOI-13905-CS-INDV / Pro Component 1: Improving Liv Individual Consult Pending Impleme vincial Finance Management IDA / 59600 elihoods for Rural Poor and V Post Open 72,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2020-10-10 ant Selection ntation Specialist for SRP (36 Months ulnerable Households ) KH-MOI-13907-CS-INDV / Pro Component 1: Improving Liv Individual Consult Pending Impleme ject Assistant for SRP (60 Mo IDA / 59600 elihoods for Rural Poor and V Post Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 ant Selection ntation nths) ulnerable Households KH-MOI-13910-CS-INDV / Pro Component 2: Improving Liv Individual Consult Pending Impleme ject Assistant for PPM (60 Mo IDA / 59600 elihoods for Urban Poor and Post Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 ant Selection ntation nths) Vulnerable Households KH-MOI-13913-CS-INDV / 01 Component 2: Improving Liv Individual Consult Pending Impleme PPM Infrastructure Specialist IDA / 59600 elihoods for Urban Poor and Post Open 72,000.00 0.00 2017-07-17 2017-09-13 2017-09-27 2017-11-01 2020-10-31 ant Selection ntation at PPM (36 Months) Vulnerable Households KH-MOI-11055-CS-INDV / Nat Component 3: Project Manag Individual Consult Pending Impleme ional Project Management an IDA / 59600 Post Open 180,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2022-11-30 ement ant Selection ntation d M&E consultant at PCO-MOI KH-MOI-11263-CS-INDV / Nat Component 1: Improving Liv Individual Consult Pending Impleme ional Finance Management S IDA / 59600 elihoods for Rural Poor and V Post Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 ant Selection ntation pecialist for MOI/PPM(36 Mon ulnerable Households ths) KH-MOI-13886-CS-INDV / Nat Component 2: Improving Liv Individual Consult Pending Impleme ional procurement Specialist IDA / 59600 elihoods for Urban Poor and Post Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 ant Selection ntation based at PCO Vulnerable Households KH-MOI-30826-CS-INDV / Pro Component 1: Improving Liv Individual Consult Pending Impleme vincial Infrastructure Speciali IDA / 59600 elihoods for Rural Poor and V Post Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 ant Selection ntation st (P M & E Engineer) at SRP ( ulnerable Households 36 Months) KH-MOI-30834-CS-INDV / Pro Component 1: Improving Liv vincial Infrastructure Speciali Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and V Post Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 st (Building Construction Engi ant Selection ntation ulnerable Households neer) at SRP (36 Months) KH-MOI-30840-CS-INDV / Pro Component 1: Improving Liv vincial Infrastructure Speciali Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and V Post Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 st (Rural Road Construction E ant Selection ntation ulnerable Households ngineer) at SRP (36 Months) KH-MOI-39794-CS-INDV / Int Component 3: Project Manag Individual Consult Pending Impleme ernational Micro-Finance Exp IDA / 59600 Post Open 60,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-07-16 ement ant Selection ntation ert at PCO-MOI(60 days) KH-MOI-39797-CS-INDV / Nat Component 3: Project Manag Individual Consult Pending Impleme ional Communication Speciali IDA / 59600 Post Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 ement ant Selection ntation st at PCO-MOI (36 Months) KH-MOI-39798-CS-INDV / Nat Component 3: Project Manag Individual Consult Pending Impleme ional MIS Specialist at PCO-M IDA / 59600 Post Open 60,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 ement ant Selection ntation OI (24 Months) KH-MOI-39800-CS-INDV / Nat Component 1: Improving Liv Individual Consult Pending Impleme ional Agriculture Likelihood S IDA / 59600 elihoods for Rural Poor and V Post Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 ant Selection ntation pecialist for GDA-MAFF (36 M ulnerable Households onths) KH-MOI-39817-CS-INDV / Nat Component 1: Improving Liv Individual Consult Pending Impleme ional HR Development Specia IDA / 59600 elihoods for Rural Poor and V Post Open 48,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 ant Selection ntation list for SRP (24 Months) ulnerable Households KH-MOI-39821-CS-INDV / Nat Component 2: Improving Liv Individual Consult Pending Impleme ional HR Development Specia IDA / 59600 elihoods for Urban Poor and Post Open 48,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2020-05-06 ant Selection ntation list for PPM ( 24 Months) Vulnerable Households KH-MOI-39888-CS-INDV / 7 D Component 1: Improving Liv Individual Consult Pending Impleme istrict Facilitators (7 DF x 55 IDA / 59600 elihoods for Rural Poor and V Post Open 336,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 ant Selection ntation Months) at Siem Reap ulnerable Households KH-MOI-40438-CS-INDV / Pro Component 1: Improving Liv Individual Consult Pending Impleme vincial Micro-Finance Speciali IDA / 59600 elihoods for Rural Poor and V Post Open 72,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 ant Selection ntation st for SRP ( 36 Months) ulnerable Households KH-MOI-40440-CS-INDV / Sen Component 1: Improving Liv Individual Consult Pending Impleme ior Livelihood/business devel IDA / 59600 elihoods for Rural Poor and V Post Open 90,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 ant Selection ntation opment Specialist for SRP (36 ulnerable Households Months) KH-MOI-40447-CS-INDV / 47 Component 1: Improving Liv Individual Consult Pending Impleme Commune Facilitators (47CFs IDA / 59600 elihoods for Rural Poor and V Prior Open 564,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 ant Selection ntation x55 Months) for SRP ulnerable Households KH-MOI-40449-CS-INDV / 47 Component 1: Improving Liv Commune Animal Health & E Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and V Post Open 338,400.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 xtension Workers (47 CAHEW ant Selection ntation ulnerable Households x 55 Months) for SRP KH-MOI-40453-CS-INDV / 4 L Component 2: Improving Liv Individual Consult Pending Impleme ocal Coordinator for urban po IDA / 59600 elihoods for Urban Poor and Post Open 96,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 ant Selection ntation or(4CLUPs x 55 Months) for P Vulnerable Households PM KH-MOI-99872-CS-INDV / Pro Component 3: Project Manag Individual Consult Pending Impleme IDA / 59600 Post Open 15,000.00 0.00 2019-03-01 2019-04-21 2019-05-05 2019-06-09 2022-06-08 ject Assistant for MAFF ement ant Selection ntation KH-MOI-99873-CS-INDV / Tra Component 1: Improving Liv Individual Consult cer Study Consultant (60 Wor IDA / 59600 elihoods for Rural Poor and V Post Open 18,000.00 0.00 Canceled 2019-06-03 2019-07-22 2019-07-29 2019-08-12 2019-10-11 ant Selection king Days) ulnerable Households KH-MOI-136635-CS-INDV / In Component 1: Improving Liv ternational Skill Development Individual Consult Under Implement IDA / 59600 elihoods for Rural Poor and V Post Open 112,800.00 0.00 2019-10-04 2019-10-18 2019-11-10 2019-11-15 2019-11-28 2020-03-27 Advisor (120 days x 1 pax) fo ant Selection ation ulnerable Households r (20day-2019, 80 days-2020 and 20 days-2021) KH-MOI-136641-CS-INDV / N Component 2: Improving Liv Individual Consult Pending Impleme ational Skills Development Sp IDA / 59600 elihoods for Urban Poor and Post Open 85,000.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 ant Selection ntation ecialist (34 monthsx1pax) for Vulnerable Households PCO-LEAP KH-MOI-136643-CS-INDV / H Component 2: Improving Liv Individual Consult Pending Impleme uman Resource Development IDA / 59600 elihoods for Urban Poor and Post Open 190,400.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 ant Selection ntation Facilitators for SRP (34month Vulnerable Households x 7 paxes) KH-MOI-136648-CS-INDV / H Component 1: Improving Liv Individual Consult Pending Impleme uman Resource Development IDA / 59600 elihoods for Rural Poor and V Post Open 81,600.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 ant Selection ntation Facilitators for PPCH (34mont ulnerable Households h x 3 paxes) Page 13 KH-MOI-168864-CS-INDV / N Component 1: Improving Liv ational Consultant for Market Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and V Post Open 56,000.00 0.00 2020-05-24 2020-07-12 2020-08-02 2020-09-06 2022-09-06 Linkage Study (Intermittent) f ant Selection ntation ulnerable Households or 3 year (2020-2022) KH-MOI-168866-CS-INDV / N Component 1: Improving Liv ational Consultant for Sturdy Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and V Post Open 31,200.00 0.00 2020-05-01 2020-06-19 2020-07-10 2020-08-14 2022-08-14 research promote Linkage wit ant Selection ntation ulnerable Households h formal Financial sector for 3 year (2020-20220) KH-MOI-220888-CS-INDV / Pr Component 1: Improving Liv Individual Consult Under Implement ocure to replacement of Ms. IDA / 59600 elihoods for Rural Poor and V Post Open 33,360.00 0.00 2021-03-01 2021-02-23 2021-04-03 2021-04-08 2021-04-22 2022-04-22 ant Selection ation Teng Ratana Resigned on 22 ulnerable Households July 2020 KH-MOI-226812-CS-INDV / O ne National Independent audi Component 3: Project Manag Individual Consult Under Implement IDA / 59600 Post Open 6,000.00 0.00 2021-05-03 2022-11-23 2021-06-21 2021-07-12 2021-08-16 2021-10-15 tor for Infrastructure with (2 ement ant Selection ation month 2021) Based in PCO KH-MOI-226814-CS-INDV / O Component 1: Improving Liv Individual Consult Under Implement ne National Agriculture Likeli IDA / 59600 elihoods for Rural Poor and V Post Open 30,000.00 0.00 2021-04-08 2021-04-23 2021-05-27 2021-06-17 2021-07-22 2022-07-22 ant Selection ation hood Specialist for GDA-MAFF ulnerable Households (12 Months) KH-MOI-226815-CS-INDV / Pr ovincial Infrastructure Special Component 1: Improving Liv ist (Rural Road Construction Individual Consult Under Implement IDA / 59600 elihoods for Rural Poor and V Post Open 24,000.00 0.00 2021-04-08 2021-04-23 2021-05-27 2021-06-17 2021-07-22 2022-07-22 Engineer) at SRP (12 Months) ant Selection ation ulnerable Households to replacement Mr Set Chamr oeun Resigned on 31 Jan 21 KH-MOI-226816-CS-INDV / O Component 3: Project Manag Individual Consult ne Junior Finance/Admin Offic IDA / 59600 Post Open 9,600.00 0.00 Canceled 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 ement ant Selection er Based in PCO (12 Months) KH-MOI-226817-CS-INDV / O Component 2: Improving Liv Individual Consult ne Junior Finance/Admin Offic IDA / 59600 elihoods for Urban Poor and Post Open 9,600.00 0.00 Canceled 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 ant Selection er Based in SMT-PPCH (12 Mo Vulnerable Households nths) KH-MOI-226818-CS-INDV / O Component 1: Improving Liv Individual Consult ne Junior Finance/Admin Offic IDA / 59600 elihoods for Rural Poor and V Post Open 9,600.00 0.00 Canceled 2021-05-03 2021-05-21 2021-06-23 2021-07-07 2021-08-11 2022-08-11 ant Selection er Based in SMT- SRP (12 Mo ulnerable Households nths) KH-MOI-226819-CS-INDV / O Component 1: Improving Liv ne Promote finance linkage f Individual Consult Pending Impleme IDA / 59600 elihoods for Rural Poor and V Post Open 9,600.00 0.00 2021-05-03 2021-06-09 2021-06-23 2021-07-26 2022-07-26 acilitators Base in SMT-SRP ( ant Selection ntation ulnerable Households 1pax x12 Months) KH-MOI-259609-CS-INDV / G Component 3: Project Manag Individual Consult Under Implement IDA / 59600 Post Open 6,000.00 0.00 2021-11-02 2022-02-03 2021-12-21 2022-01-11 2022-02-15 2022-03-17 ender specialist (20 working ement ant Selection ation days) KH-MOI-226811-CS-INDV / O ne National procurement Sp Component 2: Improving Liv Individual Consult ecialist based at PCO (12 mo IDA / 59600 elihoods for Urban Poor and Post Open 30,000.00 0.00 Canceled 2021-04-08 2021-04-23 2021-06-05 2021-06-19 2021-07-24 2022-07-24 ant Selection nths) to replacement Mr. Cha Vulnerable Households y Ponlork Resigned on 01 Oct 2019 KH-MOI-364896-CS-INDV / C onsultancy contract (Lead Int Component 3: Project Manag Individual Consult Open - Internationa Under Implement ernational Evaluation Individu IDA / 59600 Post 45,000.00 0.00 2023-06-19 2023-08-07 2023-08-28 2023-09-12 2023-10-27 ement ant Selection l ation al Consultant) (45 days over 3 months (Aug-Oct 2023) KH-MOI-367354-CS-INDV / C onsultancy contract (National Component 3: Project Manag Individual Consult Under Implement IDA / 59600 Post Open - National 13,500.00 0.00 2023-06-19 2023-08-07 2023-08-28 2023-09-12 2023-10-27 Evaluation Individual Consult ement ant Selection ation ant) (45 days over 3 months from Aug-Oct 2023) Page 14