PROCUREMENT PLAN (Textual Part) Project information: Economic and Environmental Rehabilitation of the Niger River Project Implementation agency: Agence du Basin du Fleuve Niger Date of the Procurement Plan: 7 Fevrier 2018 Period covered by this Procurement Plan: Avril 2018 – Septembre 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. PROCUREMENT Mali : Mali - Economic & Environmental Rehabilitation of the Niger River PLAN General Information Country: Mali 2019-03-11 Bank’s Approval Date of the Original Procurement Plan: 2023-09-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151909 GPN Date: Project Name: Mali - Economic & Environmental Rehabilitation of the Niger River Loan / Credit No: IDA / 62040, IDA / D2810, IDA / Q9690, IDA / V0530 Economic and Environmental Rehabilitation of the Niger River Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ML-PREFEN-100539-CW-RFB Enhancing Viability of Socio- / Travaux de surcreusement Economic Activities Contribu Single Stage - One E En attente d 2020-01-2 IDA / 62040 A posteriori Appel d'offres Open - National 3,200,000.00 0.00 2019-04-12 2019-04-17 2019-05-29 2019-06-28 2019-08-02 du chenal de Talagneini (4 5 ting to Climate Change Resili nvelope 'exécution 9 00 ml dans la commune de K ence olongo) ML-PREFEN-100536-CW-RFB Enhancing Viability of Socio- Single Stage - One E 2020-01-2 / Travaux de réhabilitation de IDA / 62040 Economic Activities Contribu A posteriori Appel d'offres Open - National 250,000.00 214,100.57 Achevé 2019-04-12 2019-09-09 2019-04-17 2019-09-09 2019-05-29 2019-07-23 2019-06-28 2021-04-22 2019-08-02 2021-04-26 nvelope 9 s quais de Macina ting to Climate Change Resili ence ML-PREFEN-100548-CW-RFB Enhancing Viability of Socio- Single Stage - One E En cours d'e 2020-05-2 / Travaux de dragage du tron IDA / 62040 Economic Activities Contribu A posteriori Appel d'offres Open - National 1,197,369.00 0.00 2019-06-04 2021-03-11 2019-06-09 2023-08-01 2019-07-21 2023-08-01 2019-08-20 2023-08-01 2019-09-24 nvelope xécution 1 çon Macina-Diafarabé ting to Climate Change Resili ence ML-PREFEN-187643-CW-RFB Strengthening the Strategic / Travaux de réhabilitation du Single Stage - One E 2021-06-0 IDA / 62040 Management of the Niger Ri A posteriori Appel d'offres Open - National 237,500.00 120,690.73 Signé 2020-08-11 2020-09-15 2020-08-16 2020-09-15 2020-09-27 2020-11-10 2020-10-27 2020-11-10 2020-12-10 2020-12-17 quai de Diafarabé, cercle de nvelope 8 ver Resources Tenenkou, Région de Mopti. Demande de cota ML-PREFEN-247157-CW-RFQ Enhancing Viability of Socio- tions - DTPM Petit / Construction de 2 hangars d Economic Activities Contribu Single Stage - One E En attente d 2021-11-1 IDA / 62040 A posteriori Demande de prix Limited s travaux (urgenc 9,000.00 0.00 2021-09-04 2021-09-26 e 100 m² et 1 hangar de 25m ting to Climate Change Resili nvelope 'exécution 7 e) - Avec compéti ² à Macina + plaques de visi ence tion bilité et panneaux ML-PREFEN-247158-CW-RFQ Demande de cota Enhancing Viability of Socio- / Construction de hangar, de tions - DTPM Petit Economic Activities Contribu Single Stage - One E En attente d 2021-11-1 magasin, de maisonnette, de IDA / 62040 A posteriori Demande de prix Limited s travaux (urgenc 8,106.00 0.00 2021-09-04 2021-09-26 ting to Climate Change Resili nvelope 'exécution 7 poulailler et Clôture d'un esp e) - Avec compéti ence ace + plaques de visibilité et tion panneaux à Macina ML-PREFEN-247159-CW-RFQ Demande de cota Enhancing Viability of Socio- / Construction de 1 hangars d tions - DTPM Petit Economic Activities Contribu Single Stage - One E En attente d 2021-11-1 e 100 m², 1 de 75 m² et 2 de IDA / 62040 A posteriori Demande de prix Limited s travaux (urgenc 9,000.00 0.00 2021-09-04 2021-09-26 ting to Climate Change Resili nvelope 'exécution 7 25 m² à Kokry+ plaques de e) - Avec compéti ence visibilité et panneaux tion ML-PREFEN-247160-CW-RFQ Demande de cota / Construction de 2 poulailler Enhancing Viability of Socio- tions - DTPM Petit s, Réhabilitation d'un (01) ha Economic Activities Contribu Single Stage - One E En attente d 2021-11-0 IDA / 62040 A posteriori Demande de prix Limited s travaux (urgenc 9,630.00 0.00 2021-09-10 2021-10-02 ngar, Clôtures en grillage, cu ting to Climate Change Resili nvelope 'exécution 8 e) - Avec compéti rage de drain et réalisation d ence tion ’un puit + panneaux d'identif ication à Kokry ML-PREFEN-247161-CW-RFQ / Construction de 3 hangars d Demande de cota Enhancing Viability of Socio- e 100 m² et 1 de 25 m² à Kol tions - DTPM Petit Economic Activities Contribu Single Stage - One E En attente d 2021-12-2 ongo , 2 Clotures en grillage IDA / 62040 A posteriori Demande de prix Limited s travaux (urgenc 29,000.00 0.00 2021-09-27 2021-11-05 ting to Climate Change Resili nvelope 'exécution 3 avec accessoires de 800 ml d e) - Avec compéti ence ont 400 ml chacun à Kolongo tion + plaques de visibilité et pa nneaux ML-PREFEN-247162-CW-RFQ / Clôtures en grillage avec ac Demande de cota cessoire, Réalisation de 4 ba Enhancing Viability of Socio- tions - DTPM Petit ssins, Construction de 2 mag Economic Activities Contribu Single Stage - One E En attente d 2021-12-2 IDA / 62040 A posteriori Demande de prix Limited s travaux (urgenc 15,316.00 0.00 2021-09-27 2021-10-31 asins avec des équipements ting to Climate Change Resili nvelope 'exécution 3 e) - Avec compéti solaires complets, Constructi ence tion on d'un (1) poulailler de 21 m² + plaques de visibilité et panneaux à Kolongo ML-PREFEN-247163-CW-RFQ / Construction de 2 hangars d Demande de cota Enhancing Viability of Socio- e 100 m², 1 de 75 m² et 3 de tions - DTPM Petit Economic Activities Contribu Single Stage - One E En attente d 2021-12-2 25 m² à Diafarabé+ plaque IDA / 62040 A posteriori Demande de prix Limited s travaux (urgenc 14,400.00 0.00 2021-09-28 2021-11-01 ting to Climate Change Resili nvelope 'exécution 4 de visibilité et panneau,Réha e) - Avec compéti ence bilitation d'un (1) hangar à Di tion afarabé + plaque de visibilit é et panneau ML-PREFEN-247165-CW-RFQ Demande de cota Enhancing Viability of Socio- / 4 Clôtures en grillage et Co tions - DTPM Petit Economic Activities Contribu Single Stage - One E En cours d'e 2021-11-0 nstruction d'un (1) poulailler IDA / 62040 A posteriori Demande de prix Limited s travaux (urgenc 5,486.00 0.00 2021-09-10 2021-10-02 ting to Climate Change Resili nvelope xécution 8 de 21 m² à Diafarabé + plaq e) - Avec compéti ence ues de visibilité et panneaux tion Document nation ML-PREFEN-264361-CW-RFB al de passation de Strengthening the Strategic / Travaux d’aménagement de Single Stage - One E s marchés - Proce En attente d 2022-05-2 IDA / 62040 Management of the Niger Ri A posteriori Appel d'offres Open - National 140,000.00 0.00 2021-12-10 2021-12-13 2022-01-12 2022-01-26 2022-02-26 la voie d’accès et l’éclairage nvelope ssus à une envelo 'exécution 7 ver Resources du quai de Ke-macina ppe (DTPM ne pro venant pas de la Banque) Document nation ML-PREFEN-274482-CW-RFB al de passation de / Travaux d’aménagement de Enhancing Viability of Socio- s marchés - Proce la mare et du chenal de Tala Economic Activities Contribu Single Stage - One E En cours d'e 2022-09-1 IDA / 62040 A posteriori Appel d'offres Open - National ssus à une envelo 2,000,000.00 0.00 2022-01-28 2022-03-24 2022-02-02 2022-02-05 2022-02-15 2022-03-22 gneini dans la commune de K ting to Climate Change Resili nvelope xécution 8 ppe (DTPM ne pro olongo en trois (03) lots disti ence venant pas de la ncts pour le compte du PREE Banque) FN. Demande de cota ML-CW-UGP-05-2023 / Trava tions - DTPM Petit Contingent Emergency Resp Single Stage - One E En cours d'e 2023-09-1 ux de mise en place de résea IDA / Q9690 A posteriori Demande de prix Open - National s travaux (urgenc 39,195.00 0.00 2023-07-26 2023-08-03 onse nvelope xécution 7 ux informatique complet à l'A e) - Avec compéti BFN/PREEFN tion Document nation ML-CW-MAC-DIAF-04-2023 / al de passation de Travaux de dragage des poin Enhancing Viability of Socio- s marchés - Proce ts critiques du Fleuve niger e Economic Activities Contribu Passation de marc En cours d'e 2024-02-2 IDA / Q9690 A posteriori Direct - National ssus à une envelo 2,975,884.00 0.00 2023-07-21 2023-08-01 2023-07-26 2023-08-05 2023-08-31 ntre Ké Macina et Diafarabé ting to Climate Change Resili hé de gré à gré xécution 7 ppe (DTPM ne pro dans les cercles de Macina et ence venant pas de la Téninkou pour le compte du Banque) PREEFN Page 1 ML-CW-MAC-KOK-01-2023 / Enhancing Viability of Socio- Demande de cota Travaux de réalisation d'activ Economic Activities Contribu Single Stage - One E tions (DTPM ne pr En cours d'e 2024-01-0 IDA / Q9690 A posteriori Demande de prix Open - National 110,735.00 0.00 2023-08-13 2023-08-14 2023-10-24 ités socio économiques dans ting to Climate Change Resili nvelope ovenant pas de la xécution 7 les communes de Macina et ence Banque) Kokry ML-CW-KOL-02-2023 / Trava Enhancing Viability of Socio- Demande de cota ux de réalisation d'activités s Economic Activities Contribu Single Stage - One E tions (DTPM ne pr En cours d'e 2024-01-0 IDA / Q9690 A posteriori Demande de prix Open - National 56,079.00 0.00 2023-08-13 2023-08-14 2023-10-23 ocio économiques dans la co ting to Climate Change Resili nvelope ovenant pas de la xécution 6 mmune de Kolongo ence Banque) ML-CW-DIAF-03-2023 / Trava Enhancing Viability of Socio- Demande de cota ux de réalisation d'activités s Economic Activities Contribu Single Stage - One E tions (DTPM ne pr En attente d 2024-01-1 IDA / Q9690 A posteriori Demande de prix Open - National 56,694.00 0.00 2023-08-23 2023-11-02 ocio économiques dans la co ting to Climate Change Resili nvelope ovenant pas de la 'exécution 6 mmune de Diafarabé ence Banque) Document nation ML-CW-MA-28-2023 / Travau Enhancing Viability of Socio- al de passation de x de renforcement des talus ( Economic Activities Contribu Single Stage - One E s marchés - Proce En attente d 2024-01-1 IDA / 62040 A posteriori Demande de prix Open - National 64,000.00 0.00 2023-09-17 2023-11-15 en gabionnage) du quai Ké-M ting to Climate Change Resili nvelope ssus à une envelo 'exécution 4 acina ence ppe (DTPM ne pro venant pas de la Banque) Document nation ML-CW-DIO-29-2023 / Trava Enhancing Viability of Socio- al de passation de ux de réalisation d’activités s Economic Activities Contribu Single Stage - One E s marchés - Proce En attente d 2024-02-1 IDA / 62040 A posteriori Demande de prix Open - National 70,400.00 0.00 2023-09-23 2023-12-18 ocioéconomiques dans la co ting to Climate Change Resili nvelope ssus à une envelo 'exécution 6 mmune de Dioro ence ppe (DTPM ne pro venant pas de la Banque) nation Document ML-CW-MAC-KOK-KOL-31-20 Enhancing Viability of Socio- al de passation de 23 / Travaux de réalisation d’ Economic Activities Contribu Single Stage - One E s marchés - Proce En attente d 2024-02-1 activités socioéconomiques d IDA / 62040 A posteriori Demande de prix Open - National 48,000.00 0.00 2023-09-25 2023-12-20 ting to Climate Change Resili nvelope ssus à une envelo 'exécution 8 ans les communes de Macina ence ppe (DTPM ne pro , Kokry et Kolongo venant pas de la Banque) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PREFEN-100568-GO-RFB Contingent Emergency Resp Single Stage - One E En attente d' / Acquisition de matériel et é IDA / 62040 A posteriori Appel d'offres Open - National 106,000.00 0.00 2019-07-02 2019-07-07 2019-08-18 2019-09-17 2019-10-31 2019-12-30 onse nvelope exécution quipements pour l'observatoi re ML-PREFEN-100569-GO-RFB / Acquisition de 11 vehicules Single Stage - One E (deux (02)stations wagons et IDA / 62040 Project management A posteriori Appel d'offres Open - National 594,000.00 407,995.10 Achevé 2019-03-05 2019-09-09 2019-03-10 2019-09-09 2019-04-21 2019-05-13 2019-05-21 2021-04-26 2019-07-04 2021-04-30 2019-09-02 2021-11-21 nvelope neuf (09) Pick-Up) pour le co mpte de l'ABFN et l'UGP/PRE EFN ML-PREFEN-100572-GO-RFB Enhancing Viability of Socio- / Acquisition et installation d Economic Activities Contribu Single Stage - One E IDA / 62040 A posteriori Appel d'offres Open - National 325,000.00 264,446.60 Achevé 2019-03-18 2020-09-17 2019-03-23 2020-09-17 2019-05-04 2020-11-10 2019-06-03 2021-03-18 2019-07-17 2021-04-16 2019-09-15 2021-08-27 e 27 balises de marquage et ting to Climate Change Resili nvelope entretien pour 4 ans ence ML-PREFEN-100765-GO-RFB Enhancing Viability of Socio- / Acquisition d'engin de prosp Economic Activities Contribu Single Stage - One E IDA / 62040 A posteriori Appel d'offres Open - National 800,000.00 1,162,028.80 Achevé 2019-07-16 2019-09-09 2019-07-21 2019-09-09 2019-09-01 2019-05-16 2019-10-01 2021-04-13 2019-11-14 2021-04-17 2020-07-11 2021-05-04 ection et de dépannage des ting to Climate Change Resili nvelope bateaux en cas d'échouage ence ML-PREFEN-100766-GO-RFQ Single Stage - One E En attente d' / Acquisition de fournitures d IDA / 62040 Project management A posteriori Demande de prix Limited 36,000.00 0.00 2019-03-24 2019-05-19 2019-06-18 nvelope exécution e bureau et consommables i nformatiques ML-PREFEN-100768-GO-RFQ Single Stage - One E En attente d' / Acquisition d'un groupe Ele IDA / 62040 Project management A posteriori Demande de prix Limited 40,000.00 0.00 2019-04-01 2019-05-27 2019-07-26 nvelope exécution ctrogene de 100 KWA pour l' UGP ML-PREFEN-100769-GO-RFQ Single Stage - One E En attente d' / Acquisition de quatre (04) IDA / 62040 Project management A posteriori Demande de prix Limited 5,200.00 0.00 2019-04-07 2019-06-02 2019-07-02 nvelope exécution motos pour l'ABFN et l'UGP ML-PREFEN-100772-GO-RFQ / Acquisition d'équipements, Single Stage - One E En attente d' IDA / 62040 Project management A posteriori Demande de prix Limited 44,000.00 0.00 2019-04-01 2019-05-27 2019-07-26 matériels et mobiliers de bur nvelope exécution eau pour l'ABFN et l'UGP ML-PREFEN-100571-GO-RFB Enhancing Viability of Socio- / Acquisition d'instruments d Economic Activities Contribu Single Stage - One E IDA / 62040 A posteriori Appel d'offres Open - National 700,000.00 0.00 Annulé 2019-05-01 2019-05-06 2019-06-17 2019-07-17 2019-08-30 2019-10-29 e mesure et de collecte de d ting to Climate Change Resili nvelope onnées pour l'ABFN ence ML-PREFEN-168750-GO-RFQ Single Stage - One E En cours d'ex / Acquisition , installation et IDA / D2810 Project management A posteriori Demande de prix Limited 21,500.00 0.00 2020-04-27 2020-09-15 2020-05-15 2021-02-09 nvelope écution maintenance de Kits de vidé o conférence ML-PREFEN-240859-GO-RFQ / Achat et livraison de 275 pi Enhancing Viability of Socio- erre à lécher, 60 sacs de 50 Economic Activities Contribu Single Stage - One E En attente d' Kg de son de riz , 60 sacs de IDA / D2810 A posteriori Demande de prix Limited 9,035.00 0.00 2021-10-28 2021-11-19 2021-12-04 ting to Climate Change Resili nvelope exécution 50 Kg de son de tourtaux, , 4 ence 5 sacs de 50 Kg d'aliment vol aille, 200 sacs de 20 Kg d'ali ment poisson. ML-PREFEN-240863-GO-RFQ Enhancing Viability of Socio- / Achat de petits materiels po Economic Activities Contribu Single Stage - One E En cours d'ex IDA / D2810 A posteriori Demande de prix Limited 23,008.00 0.00 2021-11-04 2022-05-17 2021-12-10 2022-01-09 ur les communes de Macina, ting to Climate Change Resili nvelope écution Kolongo, Kokry et Diafarabe. ence ML-PREFEN-240868-GO-RFQ Enhancing Viability of Socio- / Achat et livraison de 24 000 Economic Activities Contribu Single Stage - One E En cours d'ex IDA / D2810 A posteriori Demande de prix Limited 7,725.00 0.00 2021-10-18 2022-05-17 2021-11-09 2021-11-27 Alevins dont 12 000 à Kokry ting to Climate Change Resili nvelope écution et 12 000 à Macina. ence ML-PREFEN-240870-GO-RFQ Enhancing Viability of Socio- / Achat et livraison 45 bœufs Economic Activities Contribu Single Stage - One E IDA / D2810 A posteriori Demande de prix Limited 34,500.00 0.00 Annulé 2021-10-21 2021-11-24 2021-12-24 à Macina, Achat et livraison 7 ting to Climate Change Resili nvelope 0 bœufs à Kokry ence ML-PREFEN-240871-GO-RFQ Enhancing Viability of Socio- / Fourniture et pose de 2 cag Economic Activities Contribu Single Stage - One E En cours d'ex IDA / D2810 A posteriori Demande de prix Limited 14,000.00 0.00 2021-11-17 2022-05-17 2021-12-21 2022-01-20 es flottantes à Macina et Kok ting to Climate Change Resili nvelope écution ry + plaque de visibilité et pa ence nneau Page 2 ML-PREFEN-247047-GO-RFQ Enhancing Viability of Socio- Single Stage - One E En cours d'ex / Achat de produits volaille et IDA / 62040 Economic Activities Contribu A posteriori Demande de prix Limited 2,340.00 0.00 2021-10-31 2021-11-22 2021-12-10 nvelope écution poisson ting to Climate Change Resili ence ML-PREFEN-247050-GO-RFQ Enhancing Viability of Socio- Single Stage - One E / Achat et livraison de 595 sa IDA / 62040 Economic Activities Contribu A posteriori Demande de prix Limited 7,140.00 0.00 Annulé 2021-10-23 2021-11-14 2021-12-02 nvelope cs de 50 Kg de son de riz ting to Climate Change Resili ence ML-PREFEN-247052-GO-RFQ Enhancing Viability of Socio- Single Stage - One E En attente d' / Achat et livraison de 602 sa IDA / 62040 Economic Activities Contribu A posteriori Demande de prix Limited 7,224.00 0.00 2021-10-23 2021-11-14 2021-12-02 nvelope exécution cs de 50 Kg de son de mil ting to Climate Change Resili ence ML-PREFEN-247053-GO-RFQ Enhancing Viability of Socio- Single Stage - One E / Achat et livraison de 602 sa IDA / 62040 Economic Activities Contribu A posteriori Demande de prix Limited 9,632.00 0.00 Annulé 2021-10-28 2021-11-19 2021-12-07 nvelope cs de 50 Kg de son de tourta ting to Climate Change Resili ux ence ML-PREFEN-247155-GO-RFQ Enhancing Viability of Socio- Single Stage - One E / Achat et livraison de 65 bœ IDA / 62040 Economic Activities Contribu A posteriori Demande de prix Limited 19,500.00 0.00 Annulé 2021-10-21 2021-11-24 2021-12-24 nvelope ufs à kolongo ting to Climate Change Resili ence ML-PREFEN-247156-GO-RFQ Enhancing Viability of Socio- Single Stage - One E / Achat et livraison 70 bœufs IDA / 62040 Economic Activities Contribu A posteriori Demande de prix Limited 23,130.00 0.00 Annulé 2021-10-21 2021-11-24 2021-12-24 nvelope et 30 Moutons à Diafarabé ting to Climate Change Resili ence ML-ACQ-UGP-24-2023 / Acqu Enhancing Viability of Socio- Single Stage - One E En attente d' isition de matériels informati IDA / 62040 Economic Activities Contribu A posteriori Demande de prix Limited 27,200.00 0.00 2023-09-09 2023-11-04 2023-12-04 nvelope exécution ques pour l’observatoire/ABF ting to Climate Change Resili N/PREEFN ence ML-ACQ-UGP-23-2023 / Acqu isition d’équipements de vidé Single Stage - One E En attente d' o surveillance et de mobiliers IDA / 62040 Project management A posteriori Demande de prix Limited 22,400.00 0.00 2023-09-16 2023-11-11 2023-12-11 nvelope exécution de bureau pour la salle de co nférence du PREEFN ML-ACQ-UGP-25-2023 / Acqu Passation de marc En attente d' isition de licences profession IDA / 62040 Project management A posteriori Direct - National 48,000.00 0.00 2023-09-19 2023-09-29 2023-11-13 2024-05-11 hé de gré à gré exécution nelles pour l’observatoire/AB FN NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PREFEN-116705-NC-RFQ / Acquisition, installation, for Single Stage - One E En attente d' IDA / 62040 Project management A posteriori Demande de prix Limited 40,000.00 0.00 2019-06-12 2019-07-24 2019-08-23 mation et suivi du logiciel de nvelope exécution gestion pour l'ABFN et l'UGP ML-PREFEN-100574-GO-RFB / Réalisation des activités et Contingent Emergency Resp Single Stage - One E En attente d' IDA / 62040 A posteriori Demande de prix Limited 60,000.00 0.00 2019-10-21 2019-12-16 2020-02-14 production de supports/ outil onse nvelope exécution s de communication CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PREFEN-100793-CS-QCB Sélection fondée s En attente d'exéc S / Audit Techniques des trav IDA / 62040 Project management A posteriori ur la qualité et le Open - National 50,000.00 0.00 2019-07-16 2019-08-06 2019-09-19 2019-10-17 2019-11-16 2019-12-21 2020-02-03 2020-08-31 ution aux de réhabilitation des qua coût is de Macina ML-PREFEN-100773-CS-QCB S / Recrutement d'un consult Sélection fondée s ant chargé de l'étude pour la Contingent Emergency Resp En cours d'exécut IDA / 62040 A posteriori ur la qualité et le Open - National 655,800.00 0.00 2019-09-03 2019-12-12 2019-09-24 2019-11-07 2019-12-05 2020-01-04 2020-02-08 2020-03-23 2021-06-16 conception d'un modèle hydr onse ion coût ologique et d'amélioration d es fonctions hydrologiques et écologiques du DIN ML-PREFEN-100797-CS-QCB S / Audit technique des trava Sélection fondée s En attente d'exéc ux de surcreusement du che IDA / 62040 Project management A posteriori ur la qualité et le Open - National 500,000.00 0.00 2019-08-06 2019-08-27 2019-10-10 2019-11-07 2019-12-07 2020-01-11 2020-02-24 2020-09-21 ution nal de Talagnei (4500ml dan coût s la commune de Kolongo) ML-PREFEN-100776-CS-QCB S / Recrutement d'un Consult Sélection fondée s ant chargé de l'étude pour l'a Contingent Emergency Resp En cours d'exécut IDA / 62040 A posteriori ur la qualité et le Open - National 500,000.00 0.00 2019-05-02 2019-12-12 2019-05-23 2020-10-22 2019-07-06 2020-10-22 2019-08-03 2020-10-22 2019-09-02 2020-10-22 2019-10-07 2020-10-22 2019-11-20 2021-02-12 mélioration du cadre instituti onse ion coût onnel et règlementaire en rel ation avec la gestion du fleuv e Niger ML-PREFEN-100783-CS-QCB Enhancing Viability of Socio- S / Etude de bathymétrie et d Sélection fondée s Economic Activities Contribu e topographie, construction e IDA / 62040 A posteriori ur la qualité et le Open - National 500,000.00 1,852,657.03 Achevé 2019-08-19 2020-12-07 2019-09-09 2020-12-08 2019-10-23 2020-12-09 2019-11-20 2020-12-09 2019-12-20 2020-12-09 2020-01-24 2020-12-15 2020-03-08 2021-06-26 2020-12-03 2022-09-03 ting to Climate Change Resili t fourniture d'un model hydra coût ence ulique numérique dans le DI N ML-PREFEN-100784-CS-QCB S / Recrutement d'un bureau chargé du contrôle des trava Enhancing Viability of Socio- ux de réhabilitation du quai d Sélection fondée s Economic Activities Contribu e Macina (l'élaboration des t IDA / 62040 A posteriori ur les qualification Open - National 6,000.00 0.00 Annulé 2019-07-16 2019-06-20 2019-07-30 2019-09-09 2019-08-13 2019-08-27 2019-09-10 2020-04-07 ting to Climate Change Resili ermes de références, la dem s des consultants ence ande de proposition et la sél ection du bureau d'étude cha rgé du contrôle, publications du résultat, prise en chargé ML-PREFEN-100801-CS-QCB S / Audit comptable et financi Sélection fondée s En cours d'exécut er des comptes pour les exer IDA / 62040 Project management A posteriori ur les qualification Open - National 50,000.00 0.00 2019-11-12 2019-09-09 2019-11-26 2019-10-14 2019-12-10 2019-10-14 2019-12-20 2020-01-24 2020-03-24 ion cices 2019- 2020- 2021 pour s des consultants le compte du PREEFN ML-PREFEN-100855-CS-QCB Enhancing Viability of Socio- Sélection fondée s S / Recrutement d'un bureau Economic Activities Contribu En cours d'exécut IDA / 62040 A posteriori ur les qualification Open - National 3,000.00 0.00 2019-10-15 2019-06-20 2019-10-29 2019-09-09 2019-11-19 2019-12-03 2019-11-26 2019-12-24 2020-09-19 chargé du contrôle des trava ting to Climate Change Resili ion s des consultants ux de dragage du tronçon Ma ence cina-Diafarabé Page 3 ML-PREFEN-100857-CS-QCB Sélection fondée s S / Recrutement d'un consult Contingent Emergency Resp En cours d'exécut IDA / 62040 A posteriori ur les qualification Open - National 60,000.00 0.00 2019-10-02 2019-08-29 2019-10-16 2019-09-09 2019-11-06 2019-12-03 2019-11-13 2019-12-09 2020-06-06 ant pour la réalisation des co onse ion s des consultants mplements d'EIES/NIES selon le cas ML-PREFEN-100786-CS-QCB S / Recrutement d'un bureau Enhancing Viability of Socio- Sélection fondée s chargé du Contrôle et de la s Economic Activities Contribu En cours d'exécut IDA / 62040 A posteriori ur la qualité et le Open - National 300,000.00 0.00 2019-06-12 2019-09-26 2019-07-03 2019-12-02 2019-08-16 2020-03-11 2019-09-13 2020-03-11 2019-10-13 2020-03-11 2019-11-17 2019-12-31 2020-07-28 urveillance des travaux de su ting to Climate Change Resili ion coût rcreusement du Chenal de Ta ence lagneini (4 500 ml dans la co mmune de Kolongo) ML-PREFEN-129511-CS-INDV / Recrutement d’un bureau p Strengthening the Strategic Sélection fondée s our la réalisation d’études Av En cours d'exécut IDA / 62040 Management of the Niger Ri A posteriori ur les qualification Open - National 24,000.00 0.00 2019-09-25 2019-09-13 2019-10-09 2019-12-02 2019-10-28 2019-12-02 2019-11-02 2019-11-15 2019-12-10 ant-Projet Détaillé (APD) de l ion ver Resources s des consultants a réhabilitation du quai de Di afarabé dans le cercle de Tén ékou – Région de Mopti. ML-PREFEN-140058-CS-CQS Sélection fondée s / Recrutement d'un bureau c IDA / 62040 Project management A posteriori ur les qualification Open - National 100,000.00 30,615.98 Achevé 2019-10-21 2019-11-20 2019-10-28 2020-03-11 2019-11-30 2020-03-11 2019-12-03 2020-09-15 2020-01-07 2021-08-23 2020-09-03 2022-02-24 hargé du contrôle des travau s des consultants x de réhabilitation du quai de Macina ML-PREFEN-140061-CS-CQS Sélection fondée s / Recrutement d'un bureau c En cours d'exécut IDA / 62040 Project management A posteriori ur les qualification Open - National 100,000.00 0.00 2019-10-21 2019-11-20 2019-10-28 2020-10-22 2019-11-30 2020-10-22 2019-12-03 2021-01-30 2020-01-07 2020-09-03 hargé du contrôle des travau ion s des consultants x de réhabilitation du quai de Diafarabé ML-PREFEN-149920-CS-CQS Enhancing Viability of Socio- / Recrutement d'un Assistant Sélection fondée s Economic Activities Contribu En cours d'exécut Technique pour les activités IDA / 62040 A posteriori ur les qualification Open - National 126,000.00 0.00 2020-01-02 2020-09-15 2020-01-23 2020-09-15 2020-03-07 2020-09-15 2020-04-06 2020-05-11 2023-02-04 ting to Climate Change Resili ion d'opportunités socio-économi s des consultants ence ques dans la zone du projet ML-PREFEN-100777-CS-QCB S / Le recrutement d'un cons Sélection fondée s ultant chargé pour l'Assistan Contingent Emergency Resp IDA / 62040 A posteriori ur la qualité et le Open - National 131,191.40 0.00 Annulé 2019-06-18 2019-09-09 2019-07-09 2019-08-22 2019-09-19 2019-10-19 2019-11-23 2020-01-06 2021-03-31 ce technique, l'étude, la conc onse coût eption et la mise en place d'u n observatoire de données s patiales à l'ABFN ML-PREFEN-100805-CS-QCB Sélection fondée s S / Programme de formation IDA / 62040 Project management A posteriori ur la qualité et le Open - National 75,000.00 0.00 Annulé 2019-10-16 2019-11-06 2019-12-20 2020-01-17 2020-02-16 2020-03-22 2020-05-05 2021-05-05 et transfert de technologie p coût our la formalisation de l'activ ité des pinassiers ML-PREFEN-100808-CS-QCB Sélection fondée s S / Programme de formation IDA / 62040 Project management A posteriori ur la qualité et le Open - National 75,000.00 0.00 Annulé 2019-11-19 2019-12-10 2020-01-23 2020-02-20 2020-03-21 2020-04-25 2020-06-08 2021-06-08 et transfert de technologie p coût our l'amélioration de la const ruction des pinasses ML-PREFEN-100845-CS-QCB S / Programme de formation Sélection fondée s et transfert de technologie p IDA / 62040 Project management A posteriori ur la qualité et le Open - National 125,000.00 0.00 Annulé 2019-12-03 2019-12-24 2020-02-06 2020-03-05 2020-04-04 2020-05-09 2020-06-22 2021-06-22 our l'amélioration de la capa coût cité des entreprises de draga ge ML-PREFEN-100848-CS-QCB S / la conception d'un progra Sélection fondée s mme de renforcement des ca IDA / 62040 Project management A posteriori ur la qualité et le Open - National 125,000.00 0.00 Annulé 2019-12-18 2020-01-08 2020-02-21 2020-03-20 2020-04-19 2020-05-24 2020-07-07 2021-07-07 pacités et d'un programme d' coût engagement des parties pren antes à la mise en oeuvre d'a ctivités socio-économiques ML-PREFEN-100788-CS-QCB S / Recrutement d'un cabinet Sélection fondée s Contingent Emergency Resp pour l'Installation et la config IDA / 62040 A posteriori ur la qualité et le Open - National 340,000.00 0.00 Annulé 2019-06-18 2019-07-09 2019-08-22 2019-09-19 2019-10-19 2019-11-23 2020-01-06 2020-08-03 onse uration des équipements pou coût r l'observatoire, formation et transfert de technologie ML-PREFEN-100861-CS-QCB S / élaboration du manuel de Enhancing Viability of Socio- gestion des ressources alloué Sélection fondée s Economic Activities Contribu es pour les opportunités soci IDA / 62040 A posteriori ur les qualification Open - National 3,000.00 0.00 Annulé 2020-01-16 2020-01-30 2020-02-20 2020-02-27 2020-03-09 2020-09-05 ting to Climate Change Resili oéconomique et l'état des éc s des consultants ence osystèmes contribuant à la r ésilience au changement cli matique ML-PREFEN-183538-CS-CQS / Recrutement d'une ONG ch Sélection fondée s argée des activités de préve IDA / 62040 Project management A posteriori ur les qualification Open - National 300,000.00 92,599.39 Signé 2020-08-10 2020-11-10 2020-08-17 2020-11-16 2020-09-21 2021-04-26 2020-10-05 2021-05-17 2020-10-11 2021-05-20 2023-09-26 ntion, réponses aux VBG y co s des consultants mpris l'exploitation et les ab us sexuels et l'harcèlement s exuel sur trois (03) ans. ML-PREFEN-198434-CS-CQS / Recrutement d'un bureau p Enhancing Viability of Socio- our la réalisation d'études d' Sélection fondée s Economic Activities Contribu En cours d'exécut Avant Projet Détaillé (APD) d IDA / 62040 A posteriori ur les qualification Open - National 105,731.00 0.00 2020-10-14 2020-10-22 2020-11-04 2020-11-16 2020-11-14 2020-12-15 2020-12-19 2021-01-25 2021-01-09 2021-02-13 ting to Climate Change Resili ion e l'aménagement de la mare s des consultants ence et du chenal de Talagneini da ns la commune de Kolongo, c ercle de Macina-Région de Sé gou ML-PREFEN-198481-CS-CQS Enhancing Viability of Socio- / Recrutement d'un bureau p Sélection fondée s Economic Activities Contribu our le contrôle et la surveilla IDA / 62040 A posteriori ur les qualification Open - National 50,000.00 41,878.14 Signé 2020-10-14 2020-11-18 2020-11-04 2020-12-09 2020-11-18 2021-06-03 2020-12-23 2021-06-03 2021-01-20 2021-06-05 2021-08-03 ting to Climate Change Resili nce relatif à la fourniture et l' s des consultants ence installation de 27 balises de marquages ML-PREFEN-211485-CS-CQS Enhancing Viability of Socio- Sélection fondée s / RECRUTEMENT CONSUTANT Economic Activities Contribu IDA / 62040 A posteriori ur les qualification Open - National 80,000.00 26,967.15 Signé 2020-12-30 2021-01-25 2021-01-20 2021-01-24 2021-02-10 2021-04-12 2021-03-12 2021-04-12 2021-04-05 2021-04-15 2021-05-25 IDIVIDUEL POUR L’EVALUATI ting to Climate Change Resili s des consultants ON A MI-PARCOURS DU PROJ ence ET ML-PREFEN-222181-CS-CQS / Recrutement d'un consultan t (Bureau) pour la Prestation Strengthening the Strategic Sélection fondée s d’assistance technique relati IDA / 62040 Management of the Niger Ri A posteriori ur les qualification Open - National 290,000.00 256,562.44 Signé 2021-03-10 2021-04-26 2021-03-24 2021-05-17 2021-04-30 2021-05-17 2021-05-10 2021-09-28 2021-05-27 2021-10-03 2022-08-20 ve à l’étude, la conception et ver Resources s des consultants la mise en place d’un Observ atoire de données spatiales à l’ABFN Page 4 ML-PREFEN-264366-CS-CQS / Contrôle et surveillance des Strengthening the Strategic Sélection fondée s En cours d'exécut travaux d’aménagement de l IDA / 62040 Management of the Niger Ri A posteriori ur les qualification Open - National 13,600.00 0.00 2021-11-29 2022-01-13 2021-12-13 2022-01-15 2022-02-14 2022-03-10 2022-06-23 ion a voie d’accès et l’éclairage ver Resources s des consultants du quai de Ke-macina ML-PREFEN-271975-CS-QCB S / Recrutement d’un bureau pour la réalisation d’études A Enhancing Viability of Socio- Sélection fondée s vant-Projet Détaillé (APD) de Economic Activities Contribu En cours d'exécut IDA / D2810 A posteriori ur la qualité et le Open - National 320,000.00 0.00 2022-01-15 2022-03-24 2022-01-29 2022-02-19 2022-03-21 2022-03-31 2022-05-05 2022-06-09 2022-10-07 l’aménagement des berges e ting to Climate Change Resili ion coût t du quai de Mopti et la réha ence bilitation du chenal d’amené e d’eau du fleuve Niger au po rt de pêche de Konna – Régio n de Mopti. ML-PREFEN-271976-CS-CQS / RECRUTEMENT D'UN BUREA U POUR LES ETUDES DE SAU VEGARDES ENVIRONNEMENT Enhancing Viability of Socio- Sélection fondée s ALES ET SOCIALES TRAVAUX Economic Activities Contribu En cours d'exécut IDA / D2810 A posteriori ur les qualification Open - National 124,000.00 0.00 2022-01-15 2022-03-24 2022-01-29 2022-02-19 2022-03-21 2022-04-25 2022-07-24 DE REHABILITATION DU CHE ting to Climate Change Resili ion s des consultants NAL DE KONNA ET DU QUAI F ence LUVIAL ET DES BERGES DE P ROTECTION DE LA VILLE DE MOPTI ET LE CURAGE DE SED IMENTS AUX ABORDS DUDIT QUAI ML-PREFEN-285727-CS-QCB S / RECRUTEMENT D’UNE FIR Enhancing Viability of Socio- Sélection fondée s ME CHARGEE DE L’ETUDE IN Economic Activities Contribu En cours d'exécut IDA / D2810 A posteriori ur la qualité et le Open - National 60,000.00 0.00 2022-03-22 2022-03-24 2022-04-12 2022-08-31 2022-05-26 2022-06-23 2022-07-23 2022-08-27 2022-10-01 2022-11-15 STITUTIONNELLE, ORGANISA ting to Climate Change Resili ion coût TIONNELLE ET DU FINANCEM ence ENT DU SOUS-SECTEUR TRA NSPORT FLUVIAL AU MALI ML-PREFEN-308533-CS-QCB S / RECRUTEMENT D’UN AUDI Sélection fondée s TEUR EXTERNE POUR L’AUDI En attente d'exéc IDA / 62040 Project management A posteriori ur la qualité et le Open - National 40,000.00 0.00 2022-08-09 2022-08-30 2022-10-13 2022-11-10 2022-11-24 2022-12-15 2023-01-12 2023-02-11 T DES COMPTES DU PROJET ution coût Exercices 2022, 2023 et 202 4 (y compris l’audit de clôtur e). ML-PRES-06-2023 / Recrute Enhancing Viability of Socio- ment d'un consultant individ Sélection fondée s Economic Activities Contribu En attente d'exéc uel pour l'étude de formalisat IDA / Q9690 A posteriori ur les qualification Open - National 16,000.00 0.00 2023-07-21 2023-07-28 2023-08-11 2023-08-18 2023-09-01 2023-10-06 ting to Climate Change Resili ution ion des fonctions des équipa s des consultants ence ges à bord des bateaux et de s pinasses ML-REC-UGP-14-2023 / Recr utement d'un consultant indi viduel pour la production et l Sélection fondée s a diffusion de quinze (15) mi En cours d'exécut IDA / 62040 Project management A posteriori ur les qualification Open - National 24,000.00 0.00 2023-07-28 2023-08-17 2023-08-02 2023-08-12 2023-08-19 2023-09-08 2023-10-08 cro magazines de format de ion s des consultants 3 mn sur les impacts des qua is réhabilités et des micro pr ojets dans les communes d'in tervention du PREEFN ML-REC-MAC-12-2023 / REC RUTEMENT D'UN CONSULTA NT POUR LA REALISATION D’ ETUDES AVANT-PROJET DETA Strengthening the Strategic Sélection fondée s En cours d'exécut ILLE (APD) DE L’AMENAGEME IDA / 62040 Management of the Niger Ri A posteriori Open - National 168,000.00 0.00 2023-08-07 2023-08-08 2023-08-28 2023-09-06 2023-10-11 2023-09-08 2023-11-08 2023-11-28 2023-12-28 2024-02-01 2024-05-01 ur la qualité ion NT DES BERGES DANS QUAT ver Resources RE (04) LOCALITES (KE-MACI NA, KONKONKOUROU, TOUA RA ET DE KOKRY BOZO) DU C ERCLE DE MACINA – REGION DE SEGOU (LOT 3) ML-REC-KOU-10-2023 / Recr utement d'un consultant pou r la réalisqation des études d' Strengthening the Strategic avant projet détaillé (APD) d Sélection fondée s En cours d'exécut IDA / Q9690 Management of the Niger Ri A posteriori Open - National 136,000.00 0.00 2023-08-07 2023-08-08 2023-08-28 2023-09-13 2023-10-11 2023-11-08 2023-11-28 2023-12-28 2024-02-01 2024-05-01 es aménagements des berge ur la qualité ion ver Resources s dans trois localités (Kamani , Kenenkou et Niamina) du ce rcle de Koulikoro - Région de Kouilikoro (LOT ) ML-REC-SEG-11-2023 / RECR UTEMENT D'UN CONSULTANT POUR LA REALISATION D’ET UDES AVANT-PROJET DETAIL Strengthening the Strategic Sélection fondée s En cours d'exécut LE (APD) DE L’AMENAGEMEN IDA / 62040 Management of the Niger Ri A posteriori Open - National 168,000.00 0.00 2023-08-07 2023-08-08 2023-08-28 2023-09-12 2023-10-11 2023-09-13 2023-11-08 2023-12-08 2023-12-28 2024-02-01 2024-05-01 ur la qualité ion T DES BERGES DANS QUATR ver Resources E (04) LOCALITES (DIORO, SE COURA, SANSANDING ET DE SEGUELA) DU CERCLE DE SE GOU– REGION DE SEGOU (LO T2) ML-REC-SEG-MOP-13-2023 / RECRUTEMENT D'UN CONSUL TANT POUR LE CONTROLE ET SURVEILLANCE DES TRAVAU Enhancing Viability of Socio- Sélection fondée s X DES MICRO PROJETS SOCIO Economic Activities Contribu En cours d'exécut IDA / 62040 A posteriori ur les qualification Open - National 16,000.00 0.00 2023-08-07 2023-06-06 2023-08-28 2023-09-13 2023-10-11 2023-07-18 2023-10-26 2023-08-14 2023-11-24 2024-02-07 ECOMIQUES DANS LES COM ting to Climate Change Resili ion s des consultants MUNES DE KOKRY? KOLONG ence O? KE MACINA (CERCLE DE M ACINA *REGION DE SEGOU° ET DE DIAFARABE (CERCLE D E TENENKOU - REGION DE M OPTI° ML-REC-KOU-07-2023 / REC RUTEMENT D'UN POUR LA RE ALISATION DES ETUDES D’IM PACTS ENVIRONNEMENTAL E Strengthening the Strategic Sélection fondée s En cours d'exécut T SOCIAL DES TRAVAUX D’A IDA / Q9690 Management of the Niger Ri A posteriori ur les qualification Open - National 72,000.00 0.00 2023-08-08 2023-08-10 2023-08-29 2023-09-13 2023-09-07 2023-09-01 2023-09-27 2023-11-01 2024-01-30 ion MENAGEMENT DES BERGES ver Resources s des consultants DANS TROIS (03) LOCALITES (KAMANI, KENENKOU ET NIA MINA), CERCLE DE KOULIKOR O, REGION DE KOULIKORO (L OT 1) ML-REC-MAC-09-2023 / REC RUTEMENT D'UN CONSULTA NT POUR LA REALISATION DE S ETUDES D’IMPACTS ENVIR Strengthening the Strategic Sélection fondée s ONNEMENTAL ET SOCIAL DE En cours d'exécut IDA / Q9690 Management of the Niger Ri A posteriori ur les qualification Open - National 104,000.00 0.00 2023-08-08 2023-08-08 2023-08-29 2023-09-13 2023-10-02 2023-09-08 2023-10-22 2023-11-26 2024-02-24 S TRAVAUX D’AMENAGEMEN ion ver Resources s des consultants T DES BERGES DANS QUATR E (04) LOCALITES (KE-MACIN A, KONKONKOUROU, TOUAR A, KOKRY-BOZO), CERCLE DE KE-MACINA, REGION DE SEG OU (LOT 3) Page 5 ML-REC-SEG-08-2023 / RECR UTEMENT D'UN CONSULTANT POUR LA REALISATION DES E TUDES D’IMPACTS ENVIRONN Strengthening the Strategic Sélection fondée s EMENTAL ET SOCIAL DES TR En cours d'exécut IDA / Q9690 Management of the Niger Ri A posteriori ur les qualification Open - National 104,000.00 0.00 2023-08-08 2023-08-08 2023-08-29 2023-09-13 2023-10-12 2023-09-13 2023-10-22 2023-11-26 2024-02-24 AVAUX D’AMENAGEMENT DE ion ver Resources s des consultants S BERGES DANS QUATRE (04 ) LOCALITES (SEKOURA, DIOR O, SANSANDING ET SEGUELA ) DU CERCLE DE SEGOU, REG ION DE SEGOU (LOT 2) ML-REC-UGP-22-2023 / Recr Sélection fondée s utement d’un consultant pou En attente d'exéc IDA / 62040 Project management A posteriori ur les qualification Open - National 32,000.00 0.00 2023-09-25 2023-10-10 2023-11-08 2023-11-23 2023-12-28 2024-03-12 r l’évaluation environnement ution s des consultants ale et sociale finale du projet ML-REC-MAC-KOK-KOL-DIO-3 4-2023 / Contrôle et surveilla Enhancing Viability of Socio- Sélection fondée s nce des travaux de réalisatio Economic Activities Contribu En attente d'exéc IDA / 62040 A posteriori ur les qualification Open - National 16,000.00 0.00 2023-09-25 2023-10-10 2023-11-08 2023-11-15 2023-12-20 2024-03-04 n d’activités socioéconomiqu ting to Climate Change Resili ution s des consultants es dans les communes de Ma ence cina, Kokry, Kolongo et Dioro ML-REC-CON-32-MA-2023 / C Enhancing Viability of Socio- Sélection fondée s ontrôle et surveillance des tr Economic Activities Contribu En attente d'exéc IDA / 62040 A posteriori ur les qualification Open - National 8,000.00 0.00 2023-09-29 2023-10-14 2023-11-12 2023-11-19 2023-12-18 2024-02-16 avaux de renforcement des t ting to Climate Change Resili ution s des consultants alus (en gabionnage) du quai ence de Ké-Macina ML-REC-UGP-21-2023 / Recr Sélection fondée s En attente d'exéc utement d’un consultant pou IDA / 62040 Project management A posteriori Open - National 56,000.00 0.00 2023-09-28 2023-10-13 2023-11-11 2023-11-26 2023-12-11 2023-12-26 2024-01-30 2024-03-30 ur la qualité ution r l’évaluation finale du projet INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PREFEN-100546-CS-INDV En attente d'exéc / Mise en place d'un système IDA / 62040 Project management A posteriori Individuel Open 14,000.00 0.00 2019-05-08 2019-06-03 2019-06-10 2019-06-24 2019-08-23 ution d'Archivage (physique et éléc tronique) ML-PREFEN-100525-CS-INDV / Recrutement d'un Spécialist En attente d'exéc IDA / 62040 Project management A posteriori Individuel Open 3,000.00 0.00 2019-02-19 2019-03-17 2019-03-24 2019-04-07 2020-04-06 e en Développement Social p ution our le compte de l'UGP ML-PREFEN-100782-CS-QCB S / Le recrutement et la pre station d'un Assistant techniq Contingent Emergency Resp En attente d'exéc IDA / 62040 A posteriori Individuel Limited 39,000.00 0.00 2019-05-15 2019-05-20 2019-05-27 2019-06-08 2020-09-15 ue visant à renforcer les cap onse ution acités de la Direction Nationa le des Transports Terrestres, Maritimes et Fluviaux ML-PREFEN-100513-CS-INDV / Recrutement d'un Spécialist En attente d'exéc IDA / 62040 Project management A posteriori Individuel Open 3,000.00 0.00 2019-02-19 2019-03-17 2019-03-24 2019-04-07 2020-04-06 e en Communication pour le ution compte de l'UGP ML-PREFEN-128762-CS-INDV / RECRUTEMENT D’UN CONS ULTANT INDIVIDUEL POUR L’ACTUALISATION DES PLANS DE GESTION Strengthening the Strategic En cours d'exécut ENVIRONNEMENTALE ET SOC IDA / 62040 Management of the Niger Ri A posteriori Individuel Open 20,000.00 0.00 2019-09-25 2019-09-13 2019-10-28 2019-11-02 2019-11-15 2019-12-15 ion IALE DES TRAVAUX DE REHA ver Resources BILITATION DE DEUX (02) QU AIS : KE-MACINA DANS LE CE RCLE DE MACINA ET DIAFARA BÉ DANS LE CERCLE DE TENE NKOU ML-PREFEN-128765-CS-INDV / RECRUTEMENT D’UN CONS ULTANT INDIVIDUEL POUR L’ACTUALISATION DES PLANS Strengthening the Strategic D’ACTION DE REINSTALLATIO En cours d'exécut IDA / 62040 Management of the Niger Ri A posteriori Individuel Open 26,000.00 0.00 2019-09-25 2019-09-13 2019-10-28 2019-11-02 2019-11-15 2019-12-20 N (PAR) DES TRAVAUX DE RE ion ver Resources HABILITATION DE DEUX (02) QUAIS : A KE-MACINA DANS L E CERCLE DE MACINA ET A DI AFARABÉ DANS LE CERCLE D E TENENKOU ML-PREFEN-149928-CS-INDV En cours d'exécut / Recrutement d'un spécialist IDA / 62040 Project management A posteriori Individuel Open 88,000.00 0.00 2020-01-14 2019-12-24 2020-03-03 2020-03-24 2020-04-28 2023-01-22 ion e VBG pour le compte du PRE EFN ML-PREFEN-156552-CS-INDV En attente d'exéc / Recrutement d'un consultan IDA / 62040 Project management A posteriori Individuel Limited 15,200.00 0.00 2020-02-14 2020-02-19 2020-03-11 2020-04-15 2020-06-14 ution t individuel pour la mise en œuvre des PARs ML-PREFEN-100057-CS-INDV / Préparation et mise en œuv Contingent Emergency Resp IDA / 62040 A posteriori Individuel Open 25,000.00 0.00 Annulé 2019-11-22 2019-12-20 2019-12-27 2020-01-17 2020-03-17 re d'un plan de communicati onse on sur l'observatoire ML-PREFEN-100071-CS-INDV / Elaboration d'un plan de co Contingent Emergency Resp IDA / 62040 A posteriori Individuel Open 45,000.00 0.00 Annulé 2019-06-10 2019-07-08 2019-07-15 2019-08-05 2019-10-04 mmunication sur la protectio onse n du fleuve du Niger ML-PREFEN-179568-CS-INDV / Recrutement d'un consultan En cours d'exécut IDA / D2810 Project management A posteriori Individuel Limited 22,000.00 0.00 2020-07-31 2020-11-20 2020-08-07 2020-08-28 2020-10-02 2020-12-01 t individuel pour l'audit d'ach ion èvement des PARs de Macina et Diafarabé ML-PREFEN-179576-CS-INDV / Recrutement d'un consultan t individuel chargé de l'étude IDA / D2810 Project management A posteriori Individuel Limited 27,400.00 23,563.37 Achevé 2020-06-22 2020-08-06 2020-06-27 2020-10-22 2020-07-18 2021-01-25 2020-08-22 2021-04-19 2020-09-21 2021-04-19 d'élaboration de la situation de référence du PREEFN Page 6 ML-PREFEN-179574-CS-CDS / Recrutement d'un consultan Sélection de cons En cours d'exécut t pour la continuité des activi IDA / D2810 Project management A posteriori ultants par entent Direct 9,580.00 0.00 2020-07-15 2020-11-10 2020-07-25 2020-08-05 2020-08-21 ion tés de la mise en œuvre des e directe PARs de Diafarabé et Macina ML-PREFEN-198445-CS-INDV / Recrutement de deux (02) c onsultants individuels pour la Enhancing Viability of Socio- réalisation d'études d'actuali Economic Activities Contribu IDA / 62040 A posteriori Individuel Limited 60,000.00 54,753.28 Signé 2020-10-27 2020-11-02 2020-11-01 2020-11-23 2020-11-22 2021-01-25 2020-12-13 2021-06-08 2021-01-17 sation du PGES des travaux d ting to Climate Change Resili e Dragage des six (06) seuils ence critiques du Fleuve Niger sur le tronçon Ké-Macina-Diafara bé en deux (02) lots ML-PREFEN-246254-CS-CQS / RECRUTEMENT D’UN CONS Enhancing Viability of Socio- ULTANT INDIVIDUEL POUR EV Economic Activities Contribu En cours d'exécut IDA / 62040 A posteriori Individuel Limited 38,280.00 0.00 2021-08-16 2021-08-23 2021-08-30 2021-09-29 2021-11-03 2021-12-03 ALUER LE NIVEAU DE POLLUT ting to Climate Change Resili ion ION DES SEDIMENTS A DRAG ence UER DANS LE FLEUVE NIGER A KE-MACINA et A DIAFARAB É ML-PREFEN-249779-CS-INDV En cours d'exécut / Formation du personnel AB IDA / D2810 Project management A posteriori Individuel Limited 7,021.00 0.00 2021-09-06 2021-10-28 2021-09-11 2022-08-13 2021-10-02 2021-10-07 2021-10-12 ion FN/PREEFN sur la gestion axé e sur le résultat ML-PREFEN-249783-CS-INDV / ACQUISITION, INSTALLATIO N ET PARAMÉTRAGE D’UN LO En cours d'exame GICIEL DE GESTION DES STO IDA / D2810 Project management A posteriori Individuel Limited 23,482.00 0.00 2021-09-24 2021-10-28 2021-09-29 2021-10-20 2021-11-06 2021-11-11 n CKS POUR LA MISE A JOUR D U SYSTÈME D’INFORMATION AINSI QUE LA FORMATION DU PERSONNEL UTILISATEUR ML-PREFEN-251356-CS-INDV / Formation des Agents de l’A En cours d'exécut BFN dans le cadre du suivi en IDA / 62040 Project management A posteriori Individuel Limited 7,786.00 0.00 2021-09-24 2021-10-28 2021-09-29 2021-10-20 2021-11-06 2021-11-10 ion vironnemental de la qualité d e l’eau du fleuve Niger au Ma li ML-PREFEN-255617-CS-CDS / Recrutement d’un consulta Strengthening the Strategic Sélection de cons En cours d'exécut nt individuel pour l’élaboratio IDA / 62040 Management of the Niger Ri A posteriori ultants par entent Direct 32,478.00 0.00 2021-09-30 2021-10-28 2021-10-02 2021-10-05 2021-10-20 2021-11-10 ion n d’un film de capitalisation ver Resources e directe des actions de développeme nt. ML-PREFEN-273819-CS-INDV / sélection d’un consultant in Enhancing Viability of Socio- dividuel pour la réalisation d Economic Activities Contribu En cours d'exécut IDA / D2810 A posteriori Individuel Direct 50,000.00 0.00 2022-01-28 2022-03-20 2022-02-04 2022-02-18 2022-03-06 2022-04-20 e l’audit technique des trava ting to Climate Change Resili ion ux de réhabilitation des quais ence de Ké-Macina et de Diafarabé ML-PREFEN-264372-CS-INDV / Recrutement d’un consulta nt individuel pour l’élaboratio Strengthening the Strategic En cours d'exécut n du cadre de gestion enviro IDA / 62040 Management of the Niger Ri A posteriori Individuel Limited 29,000.00 0.00 2021-12-01 2022-03-21 2021-12-22 2021-11-25 2022-02-05 2021-11-30 2022-02-10 2022-03-27 ion nnementale et sociale (CGES ver Resources ) du Projet DE RESILIENCE ET DE RESTAURATION DES PAYS AGES AU MALI (PRRP- MALI). ML-PREFEN-264374-CS-INDV / Recrutement d’un consulta nt individuel pour l’élaboratio n de documents de sauvegar Strengthening the Strategic En cours d'exécut des : plan de gestion de la m IDA / 62040 Management of the Niger Ri A posteriori Individuel Limited 29,000.00 0.00 2021-12-03 2022-03-20 2021-12-17 2021-11-25 2022-01-31 2021-11-30 2022-02-16 2022-04-02 ion ain d’œuvre (PGMO) et évalu ver Resources ation des risques de sécurité (ERS) DU PROJET DE RESILIE NCE ET RESTAURATION DES PAYSAGES AU MALI (PRRP- M ALI) ML-PREFEN-264377-CS-INDV / Recrutement d’un consulta nt individuel pour l’élaboratio Strengthening the Strategic n de documents de sauvegar En cours d'exécut IDA / 62040 Management of the Niger Ri A posteriori Individuel Limited 29,000.00 0.00 2021-12-06 2022-03-20 2021-12-20 2021-11-25 2022-02-03 2021-11-30 2022-02-19 2022-04-05 des : d’un Cadre Politique d ion ver Resources e Réinstallation des Populati ons (CPRP) et d’un Plan de M obilisation des Parties Prenan tes (PMPP) du PRRP-MALI ML-PREFEN-274480-CS-INDV / L’ELABORATION DE LA STR ATEGIE DE PASSATION DES En cours d'exécut MARCHES ET DU PLAN DE PA IDA / 62040 Project management A posteriori Individuel Direct 50,000.00 0.00 2022-01-28 2022-03-20 2022-02-07 2022-02-07 2022-03-07 2022-04-06 ion SSATION DES MARCHES DU P ROJET DE RESILIENCE ET RES TAURATION DES PAYSAGES AU MALI (PRRP- MALI). ML-PREFEN-286192-CS-INDV / CONSULTANT EN CHARGE D E L’ELABORATION DU MANUE L DES PROCEDURES En cours d'exécut IDA / 62040 Project management A posteriori Individuel Limited 30,000.00 0.00 2022-03-23 2022-03-24 2022-03-28 2022-09-01 2022-04-12 2022-05-11 2022-06-25 DU PROJET DE RESTAURATIO ion N ET DE RÉSILIENCE DES PAY SAGES AU MALI (PRRP) ML-PREFEN-315433-CS-LCS / Recrutement d'un consultant pour la production d’un film s Strengthening the Strategic Sélection de cons ur les actions de sauvegarde En cours d'exécut IDA / D2810 Management of the Niger Ri A posteriori ultants par entent Direct - National 18,908.19 0.00 2022-11-01 2022-11-21 2022-11-11 2022-09-29 2022-11-29 2022-12-20 du fleuve et de protection de ion ver Resources e directe s communautés riveraines fa ce aux conséquences du cha ngement climatique et des a ctivités anthropiques sur le fl euve Niger ML-PREFEN-322059-CS-INDV / Recrutement d’un consulta nt pour l’enquête de satisfact Strengthening the Strategic En cours d'exécut ion auprès des bénéficiaires IDA / 62040 Management of the Niger Ri A posteriori Individuel Limited 34,783.00 0.00 2022-11-07 2022-11-15 2022-11-12 2022-11-15 2022-12-03 2023-01-07 2023-07-06 ion des activités du Projet de Ré ver Resources habilitation économique et e nvironnementale du fleuve Ni ger (PREEFN) Page 7 ML-REC-AT-35-2023 / Recrut ement d'un assistant techniq Enhancing Viability of Socio- ue (AT) pour la mise en oeuv Sélection de cons Economic Activities Contribu En cours d'exécut re des activités socio économ IDA / V0530 A posteriori ultants par entent Direct - National 44,800.00 0.00 2023-09-11 2023-09-14 2023-09-15 2023-09-28 2024-04-25 ting to Climate Change Resili ion iques dans quatre communes e directe ence (Ké Macina, Kokry, Kolongo e t Diafarabé) pour le compte d u PREEFN ML-REC-TAL-MAC-20-2023 / Enhancing Viability of Socio- Recrutement d'un consultant Economic Activities Contribu En attente d'exéc pour l'Audit technique des tr IDA / D2810 A posteriori Individuel Limited 44,800.00 0.00 2023-09-25 2023-09-30 2023-10-30 2023-12-04 2024-02-02 ting to Climate Change Resili ution avaux d'aménagement de la ence mare et du chenal de Talagn eni Page 8