Procurement Plan of GEF7 China Sustainable City Impact Program: Green and Carbon Neutral Cities Project information: Country: The People’s Republic of China Borrower: The People’s Republic of China Project Name: GEF7 China Sustainable City Impact Program: Green and Carbon Neutral Cities Loan/Credit No: TF0B8386 Project ID: P173316 Project Implementation Agency (PIA): Chongqing: CPMO is set in Chongqing Development and Reform Commission, and CPMO will take overall responsibility for coordination and management during the preparation and implementation of the project. Chongqing Development and Reform Commission,Chongqing Bureau of Environment and Ecology,Yuzhong District Development and Reform Commission, Bishan District Development and Reform Commission, the 4 departments will be the project implementation agency, are responsible for the implementation of the specific procurement activities of the project. Chengdu: The Chengdu PMO is set in the Chengdu Development and Reform Commission, and is responsible for overall project planning, organization and implementation, coordinated management, and work docking with the World Bank. As the project implementation agency, the Chengdu Government Investment Project Evaluation Center is responsible for the implementation of the specific procurement activities of the project. Ningbo: Ningbo PMO is set in Ningbo Housing and Urban-rural Development Bureau, which will be responsible for carrying out the process and the contract administration of all the contracts of Ningbo part. Component PIUs/Beneficiaries Chongqing Development and Reform Commission, Chongqing Bureau of Environment and Ecology, 1. Strengthen high- Yuzhong District Development and Reform quality development Chongqin Commission, framework with the g Bishan District Development and Reform focus on promoting ecological and Commission. biodiversity Chengdu Development and Reform Commission Chengdu conservation, and carbon neutrality Ningbo Ningbo Municipal Statistics Bureau Component PIUs/Beneficiaries Chongqing Development and Reform Commission, Chongqing Bureau of Environment and Ecology, Chongqin Yuzhong District Development and Reform g Commission, Bishan District Development and Reform 2.Support integrated Commission. solutions to Chengdu Chengdu Development and Reform Commission biodiversity and climate change - Government of Ninghai County; planning for and Ningbo Municipal Bureau of Ecology and investing in “nature” Environment; and carbon Ningbo Municipal Development &Reform neutrality Commission; Ningbo Ningbo Housing and Urban-rural Development Bureau; Ningbo Financial Bureau; Government of Haishu District Chongqing Development and Reform Commission, Chongqing Bureau of Environment and Ecology, Chongqin Yuzhong District Development and Reform g Commission, 3.Knowledge Bishan District Development and Reform sharing, capacity Commission. building and project management Chengdu Chengdu Development and Reform Commission Ningbo Housing and Urban-rural Development Ningbo Bureau Date of the Procurement Plan: November 18, 2022 Period covered by this Procurement Plan: 2022-2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a. All procurement notices shall be published in a national newspaper of wide circulation, or on a widely-used website / electronic portal with free access. b. A minimum of 30 days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c. Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d. Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e. Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. A winning Bidder, shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f. The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g. No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h. The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j. The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. k. The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. l. The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. A. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. B. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable: C. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable. G. Other Relevant Procurement Information: Goods, Works and Non-Consulting Services: Prior Review Threshold: Procurement Decisions are subject to Prior Review by the Bank as stated in Annex II to the Procurement Regulations (July 2016, revised November 2017 and August 2018). Procuremen Contract t Value Procurement Method Bank Prior Review Category (US$) Goods, IT ≥ 10 International Open Systems & million Competitive Procurement Non- (International + Open) Consulting Services ≥ 500k to National Open Competitive All contracts ≥ USD 4 Procurement million. < 10 million (National + Open) < 500 K Shopping (RFQ) None Others DS (Direct Selection) All contracts ≥ USD 4 million. Works, ≥ 40 International Open Supply & million Competitive Procurement Installation (International + Open) ≥ 500k to National Open Competitive All contracts ≥ USD 15 Procurement million. < 40 million (National + Open) < 500 K Shopping (RFQ) None N/A DS (Direct Selection) All contracts ≥ USD 15million. Notes: DS: Direct Selection NA: Not Applicable Selection of Consultants: Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II to the Procurement Regulations (July 2016, revised November 2017 and August 2018): Procurem Contract Value Selection ent Bank Prior Review (US$) Method Category ≥ 300,000 QCBS, QBS, Firms: All contracts >=USD 2 million; QCBS, QBS, < 300,000 FBS, LCS, Firms: All DS contracts >= Consultant CQS USD 1 million; s Others DS Individual Consultant: All contracts >=400 K; Others IC DS for individual consultant: All contracts>=USD 400 K Notes: QCBS: Quality- and Cost-Based Selection DS: Direct Selection QBS: Quality-Based Selection IC: Individual Consultant selection procedure FBS: Fixed Budget Selection NA: Not Applicable LCS: Least Cost Selection CQS: Consultants’ Qualifications-based Selection Consultancy Assignments with Selection Methods and Time Schedule: Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date CHONGQING Development of green and low carbon indicator system of Development of green and low carbon CQ- Chongqing and indicator system of Chongqing and Open+ CS- construction plan of construction plan of Chongqing for green 29 Nationa Post 2023.6 12 2023.9 01 Chongqing for green and smart platform based on carbon l+CQS and smart cloud peaking and carbon neutrality platform based on carbon peaking and carbon neutrality Pilot Evaluation of Green and Low CQ- Carbon Indicator Pilot Evaluation of Green and Low Carbon Open+ CS- System of Indicator System of Chongqing in "One 60 Nationa Post 2025.4 12 2025.7 02 Chongqing in "One Area and Two Clusters" l+QCBS Area and Two Clusters" Research on the CQ- Implementation Open+ Research on the Implementation Plan of CS- Plan of Carbon 141 Nationa Prior 2026.4 12 2026.7 Carbon Neutrality in Chongqing 03 Neutrality in l+QCBS Chongqing CQ- Natural capital Manual of natural capital accounting for Open+ CS- accounting and Bishan; empirical study of the natural 60 Nationa Post 2023.05 48 2023.6 04 biodiversity capital accounting for Bishan; baseline l+QCBS 8 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date protection for survey of Bishan biodiversity index; Bishan District development of Bishan urban biodiversity index; integration of Bishan urban biodiversity in territorial space planning; urban biodiversity protection strategy for Bishan; and public awareness and outreach of urban biodiversity protection CQ- Open+ Bishan nature-based NBS for water for Bishan; and wind corridor CS- 70 Nationa Post 2023.05 48 2023.5 solutions (NBS) pilot control plan for Bishan 05 l+QCBS Formulation of green project handbook for Chongqing green finance services; CQ- Open+ approaches absorbing social capital to CS- Green finance 50 Nationa Post 2023.5 18 2023.6 participate in investing in green projects; 06 l+QCBS financing models development and implementation for demonstration projects Put forward the specific scheme of low- carbon design and transformation of old community buildings with mountain characteristics; put forward specific plans Pilot of near-zero for building low-carbon public service CQ- Open+ carbon transition of facilities and infrastructure; put forward CS- 80 Nationa Post 2023.5 24 2023.7 old communities - specific schemes to create a beautiful and 07 l+QCBS Yuzhong District livable community environment; put forward specific measures for the classification and recovery of domestic garbage; explore the low-carbon operation and management mode and long-term 9 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date mechanism; explore and formulate supporting incentive measures for low- carbon construction investment and behavior guidance; guide the participation and consultation of the private sector Level monitoring indicator system of green and low-carbon synergetic development; capability assessment system of green and Assessment system low-carbon synergetic development; and implementation CQ- optimization of CCEC green and low- Open+ mechanism of CCEC 2023.6 CS- carbon synergetic development; 60 Nationa Post 2023.3 60 green and low- 08 construction of economic system of CCEC l+QCBS carbon synergetic green and low-carbon synergetic development development; integration of factor market for CCEC; and mechanism for value realization of ecological products in CCEC General framework design of net zero/ near-zero industrial park; development of net zero energy system construction CQ- Trans-regional net Open+ scheme for trans-regional net zero CS- zero industrial park 60 Nationa Post 2023.9 60 2023.12 industrial park; design of interconnection 09 construction action l+QCBS of every system in CCEC; design of professional and normalized trans-regional renewable energy recovery system CQ- Trans-regional net Technical supporting platform and Open+ CS- zero urban-rural certification system for green city; net zero Nationa Post 60 2023.9 60 2023.12 10 construction action building standard and certification system; l+QCBS design of general framework of net zero 10 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date and near-zero rural areas; and net zero/near-zero carbon industrial planning for rural revitalization Handbook for mountains, river, forest, farmland, lake, grassland ecological Trans-regional CQ- restoration; handbook for trans-regional Open+ ecological CS- watershed pollution synergetic control 40 Nationa Post 2023.3 60 2023.6 environment 11 engineering; standard and guide for l+QCBS protection action contingency plan startup for heavy trans- regional pollution weather Policy toolkits for synergetic green Pilot action on development for central Sichuan and green, low-carbon Chongqing area; design of transformation CQ- and high-quality Open+ development mechanism for South CS- development in 180 Nationa Prior 2023.9 60 2023.12 Sichuan and West Chongqing area; design 12 adjacent areas of l+QCBS of ecological protection and development Sichuan and mechanism for East Chongqing and North Chongqing Sichuan area CQ- Open+ Project CS- 1 policy and planning expert 8 Nationa Post 2022.12 60 2023.2 management 15-1 l+ICS CQ- Open+ Project CS- 1 procurement expert 6 Nationa Post 2022.12 60 2023.2 management 15-2 l+ICS 11 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date CQ- Open+ Project CS- 1 financial expert 3 Nationa Post 2022.12 60 2023.2 management 15-3 l+ICS CQ- 1 environmental and social expert Open+ Project CS- 3 Nationa Post 2022.12 60 2023.2 management 15-4 l+ICS CHENGDU 1. Develop green and low-carbon indicators that have the characteristics of a park city and the requirements of new human-centered urbanization, and clarify the source, connotation, Research and standards and boundaries of indicators, piloting for as well as work requirements strengthening high- 2. Formation of indicator guidelines and quality development monitoring and evaluation framework Open CD- frameworks with a for Chengdu's green and low-carbon +Intern development 140 Post 2022.4 48 2022.6 CS1 focus on promoting ational ecological, 3. Mid-term monitoring and evaluation of + QCBS biodiversity Chengdu’s green and low-carbon conservation and development level during the “14th carbon neutrality Five-Year Plan” period using indicator guidelines and evaluation frameworks 4. Suggestions on the preparation and index setting of the "15th Five-Year Plan" 5. Under the requirements of new urbanization, establish a green and low- 12 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date carbon indicator system for metropolitan areas with cross-regional characteristics 6. Construct a guide for green and low- carbon development indicators in the Chengdu metropolitan area 7. Use the indicator system and indicator guide to conduct mid-term monitoring and evaluation of the implementation of the Chengdu Metropolitan Area Development Plan and the green and low-carbon development of the Chengdu Metropolitan Area 8. Put forward opinions and suggestions on the green and low-carbon development of Chengdu metropolitan area. 9. Relying on the Chengdu City Smart Management Platform (City Brain) to build a "dual carbon" sharing platform 10.According to the main carbon emission sources in Chengdu, classify and integrate urban management and monitoring data 11.Develop green and low-carbon development indicators comparison, trend analysis, abnormal monitoring and early warning and other functions 12.Standardize the data sharing process and mechanism for green and low- 13 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date carbon development, and promote the interconnection and data sharing of information systems of municipal departments and institutions. 13.Based on the development status and trend of Chengdu industrial parks (functional zones), carrying out the construction of green and low-carbon development index of parks (functional zones). 14.Based on index construction, selecting typical parks (functional zone) for evaluation, and regularly publish evaluation results. 15.According to the evaluation report, carrying out the selection and promotion of excellent green and low- carbon development cases of industrial parks (functional zones), and forming a number of typical cases. 16.Carry out research on green, low- carbon and circular development of industrial parks (functional zoness) in metropolitan areas 17.Carry out the research and design of the circular transformation of industrial parks (one industrial park in Deyang, Meishan and Ziyang will be selected as a pilot) 14 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date 1. Focusing on Chengdu wetlands, actively carrying out biodiversity surveys and formulating Chengdu wetland biodiversity assessment reports. Chengdu Wetland 2. In response to the problems assessed Biodiversity Survey, in the report, highlight the unique Ecological natural features of Chengdu and the Restoration, ecological barrier characteristics of the Biodiversity upper reaches of the Yangtze River, Management and formulate ecological restoration Open System Research, guidelines based on natural solutions CD- +Intern andTuojiang (NBS). 130 Post 2023.7 48 2023.9 CS2 ational Comprehensive 3. Formulate specific restoration plans for + QCBS Management the Minshan L population and Strategic Daxiangling B population in the Framework and Chengdu metropolitan area of the Giant Method Panda National Park, and make Optimization and professional plans for restoration Improvement Plan methods, restoration areas, and restoration timing. 4. Carry out wetland biodiversity monitoring, and establish a wetland biodiversity management system 15 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date 1. Assess the quality of the giant panda habitat in the Chengdu area of the Giant Panda National Park, formulate a systematic ecological restoration plan, and make professional plans for restoration sites, restoration areas, CD- Ecological restoration methods, restoration timing, Open CS3 restoration plan for etc. +Intern 160 Post 2023.10 24 2023.12 Chengdu Giant 2. Formulate specific restoration plans for ational Panda Habitat the Minshan L population and + QCBS Daxiangling B population in the Chengdu metropolitan area of the Giant Panda National Park, and make professional plans for restoration methods, restoration areas, and restoration timing. Wetland Biodiversity Select wetlands to install monitoring CD- facilities. Monitoring 30 RFQ Post 2024.3 6 2024.5 GD1 Equipment 1. In view of the characteristics of Chengdu's large population growth, rapid economic development, low per Research and capita carbon emission level, and Open CD- Piloting for Carbon relatively clean energy structure, +Intern 60 Post 2023.3 36 2023.5 CS4 Neutrality Roadmap dealing with the contradiction between ational and Green Finance development and carbon reduction + QCBS based on overall planning, solving the problem of continuous carbon reduction at lower carbon emission levels, 16 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date developing a roadmap to peak carbon neutrality. 2. Analyze different types of green projects, revenue sources and business models in the private sector, and sort out the main products and paths of green finance. 3. According to the characteristics of different projects, select and match appropriate financing models, and carry out green financing model pilot projects in the fields of giant panda national park ecological restoration, green and low-carbon transformation of functional zones, and urban renewal and transformation. 1. Analyze different types of green projects, revenue sources and business models in the private sector, and sort out the main products and paths of Guidelines and green finance. Piloting for Green 2. According to the characteristics of Open CD- and Low-Carbon different projects, select and match +Intern 100 Post 2023.10 24 2023.12 CS5 Transformation of appropriate financing models, and carry ational Communities in out green financing model pilot projects + QCBS Chengdu in the fields of giant panda national park ecological restoration, green and low-carbon transformation of functional zones, and urban renewal and transformation. 17 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date Project Management Open CD- Support for project management and and Procurement 10 +Natio Post 2022.12 48 2023.1 IC1 procurement during implementation phase Management Experts nal+ IC Technical Experts Open CD- Technical Support for Carbon Neutralization (Carbon +Natio Post IC2 and Green Development during 5 2022.12 48 2023.1 Neutralization and nal+ IC implementation phase Green Development) Technical Specialist Open CD- Technical Support for Biodiversity and (Biodiversity and 5 +Natio Post 2022.12 48 2023.1 IC3 Wetlands during implementation phase Wetlands) nal+ IC NINGBO 1. To establish green and high-quality development indicators  Theoretical research and policy interpretation  Conduct international case studies and analyze the current situation Open Study on Indicator  Establish indicator system and +Intern NB- system of Green evaluation model ational CS- High-quality 2. To proposing a monitoring and 40 Post 2023.06 46 2023.08 + 1.1 Development in evaluation framework for the green and QCBS/Q Ningbo City low carbon development in Ningbo BS 3. Use the framework to conduct mid-term monitoring and evaluation on the implementation of the 14th five-year plan. 4. To make suggestions on the preparation of the 15th Five-Year Plan 18 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date and its indicators setting. 1. To survey the natural assets and analyzing ecosystem services of the natural assets in Ninghai Open Pilot Project of Blue 2. To conduct natural capital accounting +Intern NB- and Green Natural for the County ational CS- 90 Post 2023.08 44 2023.10 Assets Accounting 3. To explore the realization of ecological + 2.1 in Ninghai County product value and the transformation QCBS/Q path from GEP to GDP BS 4. To formulate strategic plans for Ninghai ecological space Study on the 1. To conduct baseline surveys and Open NB- Strategy of assessments of the biodiversity in +Intern CS- Biodiversity Ningbo 100 ational Post 2023.07 45 2023.09 2.2 Conservation in 2. To develop a strategy plan of + Ningbo City biodiversity conservation QCBS/Q 19 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date 3. To develop a monitoring framework for BS biodiversity and a biodiversity index. 4. Display the results of biodiversity baseline investigation and dynamic monitoring on the “Beautiful Ningbo” map 1. To undertake studies and modeling Study on the Road Open NB- work to formulate a roadmap for visions Map to Carbon +Intern CS- toward carbon neutrality and timeframe Neutrality in Ningbo 50 ational+ Post 2023.07 30 2023.09 2.3 2. To conduct consultations with various City QCBS/Q agencies as well as public on the BS roadmap 1. To prepare a implementation plan for the platform  Background surveys and policy interpretation  Overall design of the platform  Task breakdown  Investment estimation for the Ningbo Construction Open NB- platform development Industry Double- +Intern CS- 2. To develop the platform, sub-modules Carbon Smart 80 ational+ Post 2023.07 45 2023.09 2.4 and tools. Service Platform QCBS/Q  Special planning sub-module (new) BS  Energy saving evaluation sub-module (upgrade existing system)  Construction Drawing Review Sub- module (Upgrade existing system)  Green Building Identification Sub- Module (Upgrade existing system)  Green Building Materials 20 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date Management Sub-module (New)  As-built energy efficiency evaluation sub-module (upgrade existing system)  Energy consumption online monitoring sub-module (upgrade existing system)  Existing Building Renovation Sub- module (New Construction)  Green Finance Sub-module (New)  Social Supervision Sub-module (New)  Supporting function sub-module (new) 3. To compile supporting policies for double-carbon digitalization and intelligent development of the construction industry  To analyze the status of double- carbon digitalization and intelligent development of the construction industry  To propose solutions to the difficulties of double-carbon digitalization and intelligent development in the construction industry  To formulate supporting policies to promote double-carbon digitalization and intelligent development of the construction industry 21 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date Conceptual Design 1. To formulate NBS strategy for Ninghai Open NB- water system Project with Nature- +Intern CS- 2. To provide NBS design options for the 40 Post 2023.12 24 2024.02 Based Solutions in ational 2.5 selected site in Ninghai based on a set Ninghai County + QCBS of criteria in annex 1. To Help three local city commercial banks with corporate headquarters in Ningbo (Bank of Ningbo, Ningbo Commerce Bank, Donghai Bank) to establish and improve green financial business, establish due diligence, rating, data collection and analysis mechanisms, effectively improve energy efficiency, decarbonize and Study on Green sequester carbon and the ability to Open NB- Financial Products identify projects such as renewable +Intern CS- and Innovation of energy utilization. 60 ational+ Post 2023.07 24 2023.9 2.6 Green Financial 2. Investigate projects in the fields of QCBS/Q Model carbon reduction and biodiversity in BS Ningbo, and form a list of investment and financing projects to adapt to climate change and promote biodiversity 3. Form independent financial product and financial model evaluation reports for typical demonstration projects, and form investment and financing empirical cases 4. Develop green financial products and 22 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date green financial model manuals 1. Design of the low-carbon/net-zero carbon renewal scheme in the pilot area  Investigation on the development status and economic indicators of the pilot area Study and pilot on  Carry out feasibility analysis of key Urban Renewal scene placement in combination with Open NB- Technology based future communities; +Intern CS- 60 Post 2024.01 24 2024.3 on the concept of  Overall design of low-carbon/net-zero ational+ 2.7 low carbon/net zero carbon emission transformation CQS carbon emissions scheme;  Deepening design of special scheme 2. To explore low-carbon/net-zero carbon urban renewal technologies 3. To build a low-carbon/net-zero carbon community evaluation indicator system 23 Procurement Plan Estimat Expect Expecte Contra ed Cost Review ed Procure d ct contract (USD: by Bank Contra Contract Name Description ment Proposal Period number 10 (Prior / ct Method Submiss (Month thousan Post) Signing ion Date ) d) Date Expert of Open+ NB- Environment 5 Nationa Post 2023.02 51 2023.03 IC1 Safeguard l+ICS Open+ NB- Expert of Social 5 Nationa Post 2023.02 51 2023.03 IC2 Safeguard l+ICS Technical Expert of Open+ NB- Low Cabon and 3 Nationa Post / 52 2023.02 IC3 Green Development l+ICS Expert of Project Open+ NB- Management/ 14 Nationa Post / 51 2023.03 IC4 Contract l+ICS Management Open+ NB- Project Translator 1 Nationa Post / 51 2023.03 IC5 l+ICS 24 PROCUREMENT China : GEF7: Green and Carbon Neutral Cities PLAN General Information Country: China 2023-04-03 Bank’s Approval Date of the Original Procurement Plan: 2023-09-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173316 GPN Date: 2022-11-14 Project Name: GEF7: Green and Carbon Neutral Cities Loan / Credit No: TF / B8386 GEF7 Ningbo Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 2. Support integrated solutio NB-CS-2.4 / Ningbo Construc ns to biodiversity and climat Quality And Cost- Open - Internationa Under Implement tion Double-carbon Smart Se TF / B8386 Post 800,000.00 0.00 2023-08-25 2023-08-07 2023-09-15 2023-10-31 2023-12-15 2024-01-12 2024-02-15 2024-03-21 2027-06-15 e change - planning for and i Based Selection l ation rvice Platform nvesting in “nature” and car bon neu trality 2. Support integrated solutio NB-CS-2.2 / Strategy and Act ns to biodiversity and climat Quality And Cost- Open - Internationa Under Implement ion Planning for Biodiversity TF / B8386 Prior 1,000,000.00 0.00 2023-08-25 2023-09-13 2023-09-30 2023-11-13 2023-12-30 2024-01-29 2024-03-04 2024-04-08 2027-06-15 e change - planning for and i Based Selection l ation Conservation in Ningbo City nvesting in “nature” and car bon neu trality 1. Strengthen the high-qualit NB-CS-1.1 / Study on Indicat y development framework w or system of Green High-qual Quality And Cost- Open - Internationa Pending Impleme TF / B8386 ith the focus on promoting e Post 400,000.00 0.00 2023-11-01 2023-11-22 2024-01-05 2024-02-02 2024-03-03 2024-04-07 2024-05-12 2027-06-15 ity Development in Ningbo Ci Based Selection l ntation cological and biodiversity co ty nservation, and carbon neut rality NB-CS-2.1 / Pilot Project of Bl 2. Support integrated solutio ue and Green Natural Assets ns to biodiversity and climat Quality And Cost- Open - Internationa Pending Impleme TF / B8386 Post 900,000.00 0.00 2024-01-10 2024-02-15 2024-03-30 2024-05-16 2024-06-15 2024-07-20 2024-08-24 2027-06-15 Accounting in Jiangbei Distri e change - planning for and i Based Selection l ntation ct nvesting in “nature” and car bon neu trality 2. Support integrated solutio NB-CS-2.3 / Study on the Ro ns to biodiversity and climat Quality And Cost- Open - Internationa Pending Impleme ad Map to Carbon Neutrality i TF / B8386 Post 500,000.00 0.00 2023-11-20 2023-12-26 2024-02-08 2024-03-26 2024-04-25 2024-05-30 2024-07-04 2027-06-15 e change - planning for and i Based Selection l ntation n Ningbo City nvesting in “nature” and car bon neu trality 2. Support integrated solutio NB-CS-2.5 / Conceptual Desi ns to biodiversity and climat Quality And Cost- Open - Internationa Pending Impleme gn Project with Nature-Based TF / B8386 Post 400,000.00 0.00 2023-12-25 2024-01-30 2024-03-14 2024-04-30 2024-05-30 2024-07-04 2024-08-08 2026-08-08 e change - planning for and i Based Selection l ntation Solutions in Jiangbei District nvesting in “nature” and car bon neu trality NB-CS-2.6 / Study on Green 2. Support integrated solutio Financial Products and Innov ns to biodiversity and climat Quality And Cost- Open - Internationa Pending Impleme TF / B8386 Post 600,000.00 0.00 2024-03-20 2024-04-25 2024-06-08 2024-07-25 2024-08-24 2024-09-28 2024-11-02 2027-04-21 ation of Green Financial Mod e change - planning for and i Based Selection l ntation el nvesting in “nature” and car bon neu trality NB-CS-2.7 / Study and pilot 2. Support integrated solutio on Urban Renewal Technolog ns to biodiversity and climat Quality And Cost- Open - Internationa Pending Impleme TF / B8386 Post 600,000.00 0.00 2024-05-10 2024-06-15 2024-07-29 2024-09-14 2024-10-14 2024-11-18 2024-12-23 2026-12-23 y based on the concept of lo e change - planning for and i Based Selection l ntation w carbon/net zero carbon em nvesting in “nature” and car issions bon neu trality INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 3. Support knowledge sharin Individual Consult NB-IC5 / Project Translator TF / B8386 g, capacity building, and pro Post Open - National 10,000.00 0.00 Signed 2023-04-06 2023-04-04 2023-04-24 2023-07-09 2023-04-27 2023-07-17 2023-05-01 2023-07-24 2027-06-30 ant Selection ject management 3. Support knowledge sharin NB-IC2 / Expert of Social Saf Individual Consult TF / B8386 g, capacity building, and pro Post Open - National 25,000.00 0.00 Signed 2023-04-06 2023-04-04 2023-04-24 2023-06-13 2023-04-27 2023-07-17 2023-05-01 2023-07-24 2027-06-30 eguard ant Selection ject management 3. Support knowledge sharin NB-IC1 / Expert of Environm Individual Consult TF / B8386 g, capacity building, and pro Prior Open - National 25,000.00 0.00 Signed 2023-04-06 2023-04-05 2023-04-24 2023-06-08 2023-04-27 2023-07-17 2023-05-01 2023-07-24 2027-06-30 ent Safeguard ant Selection ject management 3. Support knowledge sharin NB-IC4 / Expert of Project Ma Individual Consult TF / B8386 g, capacity building, and pro Post Open - National 60,000.00 0.00 Signed 2023-04-21 2023-05-17 2023-06-06 2023-06-30 2023-06-09 2023-07-17 2023-06-16 2023-07-24 2025-06-15 nagement ant Selection ject management NB-IC3 / Technical Expert of 3. Support knowledge sharin Individual Consult Under Implement Low Cabon and Green Develo TF / B8386 g, capacity building, and pro Post Open - National 30,000.00 0.00 2023-06-04 2023-07-18 2023-06-25 2023-06-30 2023-07-02 2025-06-30 ant Selection ation pment ject management Page 1