Procurement Plan National Roads and Airport Infrastructure Project (P122007) I. General 1. Bank’s approval Date of the procurement Plan Original: September 6, 2017 in Excel format 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: The procurement period of project covered from year 2015 to 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods and Non- Above US$ 500,000 All Consultant Services) 2. NCB (Goods) Above US$ 50,000 None 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 250,000 None 2. Prequalification. Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P122007 04/10/2012 issued by AASANA III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Bolivia : National Roads and Airport Infrastructure Project PLAN General Information Country: Bolivia 2017-04-19 Bank’s Approval Date of the Original Procurement Plan: 2023-09-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122007 GPN Date: Project Name: National Roads and Airport Infrastructure Project Loan / Credit No: IDA / 49230 Bolivian Road Administrator Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned No: LPI/015/2013 Segunda C onvocatoria / MEJORAMIENTO Y CONSTRUCCION DEL TRAM O CARRETERO SAN BUENAVE Improving the San Buenave Solicitud de oferta Open - Internationa Single Stage - One E 115,986,578. 135,997,02 NTURA - IXIAMAS Lote 1: Tra IDA / 49230 ntura - Ixiamas National Roa Previa Firmado 2014-10-01 2014-12-11 s l nvelope 00 5.93 mo I San Buenaventura - Tu d mupasa incluye variante y Ac cesos a Tumupasa (Avenida y Conexi n Variante - Avenid a) Lote 2: Tramo II Tumupasa - Ixiamas BO-ABC-70411-CW-RFQ / CO NSERVACION VIAL TRAMO LP Improving the San Buenave Solicitud de cotiza Single Stage - One E 2019-05-2 02R CR. RT A RURRENABAQU IDA / 49230 ntura - Ixiamas National Roa Posterior Limited 249,426.54 217,962.18 Firmado 2018-07-24 2018-09-04 2018-08-25 2018-10-15 ciones nvelope 2 E-TUMUPASA-IXIAMAS, TRAM d O 1: SAN BUENAVENTURA-TU MUPASA BO-ABC-70415-CW-RFQ / CO NSERVACION VIAL TRAMO LP Improving the San Buenave Solicitud de cotiza Single Stage - One E 2019-05-2 02R CR. RT A RURRENABAQU IDA / 49230 ntura - Ixiamas National Roa Posterior Limited 242,889.22 209,983.84 Firmado 2018-07-24 2018-09-04 2018-08-25 2018-10-15 ciones nvelope 2 E-TUMUPASA-IXIAMAS, TRAM d O 2: TUMUPASA-IXIAMAS BO-ABC-91659-CW-RFB / Mej oramiento y Construcción del Tramo Carretero San Buenav entura-Ixiamas. LOTE 1: Tra Improving the San Buenave Solicitud de oferta Open - Internationa Single Stage - One E 118,508,769. 2021-12-1 mo I San Buenaventura-Tum IDA / 49230 ntura - Ixiamas National Roa Previa 0.00 Cancelado 2018-12-21 2018-12-26 2019-02-09 2019-03-01 2019-04-01 s l nvelope 75 6 upasa incluye Variante y Acc d esos a Tumupasa (Avenida y Conexión Variante-Avenida)L OTE 2:TramoII Tumupasa-Ixia mas.(con condición suspensi va) BO-ABC-201996-CW-RFB / C Improving the San Buenave Solicitud de oferta Open - Internationa Single Stage - One E 10,305,992.0 9,523,391.7 2022-06-3 ONSTRUCCION DE PUENTES IDA / 49230 ntura - Ixiamas National Roa Previa Firmado 2020-11-20 2021-01-04 2020-11-27 2021-02-12 2021-01-08 2021-03-19 2021-02-01 2021-05-20 2021-03-20 2021-07-07 s l nvelope 0 6 0 SAN BUENAVENTURA - TUMU d PASA LOTE 1A BO-ABC-201998-CW-RFB / C Improving the San Buenave Solicitud de oferta Open - Internationa Single Stage - One E 8,637,136.9 2022-06-3 ONSTRUCCION DE PUENTES IDA / 49230 ntura - Ixiamas National Roa Previa 9,463,906.00 Firmado 2020-11-20 2021-01-04 2020-11-27 2021-02-12 2021-01-08 2021-03-19 2021-02-01 2021-05-20 2021-03-20 2021-07-07 s l nvelope 9 0 SAN BUENAVENTURA - TUMU d PASA LOTE 1B BO-ABC-202002-CW-RFB / C Improving the San Buenave Solicitud de oferta Open - Internationa Single Stage - One E 8,735,701.3 Bajo Revisio 2022-06-3 ONSTRUCCION DE PUENTES IDA / 49230 ntura - Ixiamas National Roa Previa 8,803,807.00 2020-11-20 2020-12-24 2020-11-27 2021-02-12 2021-01-08 2021-03-19 2021-02-01 2021-05-31 2021-03-20 2021-07-08 s l nvelope 3 n 0 TUMUPASA - IXIAMAS LOTE 2 d A BO-ABC-202004-CW-RFB / C Improving the San Buenave Solicitud de oferta Open - Internationa Single Stage - One E 6,743,129.1 2022-06-3 ONSTRUCCION DE PUENTES IDA / 49230 ntura - Ixiamas National Roa Previa 9,147,370.00 Firmado 2020-11-20 2021-01-04 2020-11-27 2021-02-12 2021-01-08 2021-03-19 2021-02-01 2021-05-31 2021-03-20 2021-07-06 s l nvelope 9 0 TUMUPASA - IXIAMAS LOTE 2 d B GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-ABC-205616-NC-RFB / IM Improving the San Buenave PRESIÓN, RE DIAGRAMACIÓN Solicitud de cotiza Single Stage - One E IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 10,000.00 0.00 Cancelado 2020-12-12 2021-02-06 2021-04-07 , PUBLICACIÓN Y DIFUSIÓN D ciones nvelope d EL LIBRO DE LA CULTURA TA CANA BO-ABC-210850-NC-RFQ / IM Improving the San Buenave PRESIÓN, REDIAGRAMACIÓN, Solicitud de cotiza Single Stage - One E IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 10,000.00 0.00 Cancelado 2020-12-26 2021-02-07 2021-03-09 PUBLICACIÓN Y DIFUSIÓN DE ciones nvelope d L LIBRO DE LA CULTURA TAC ANA BO-ABC-218977-NC-RFQ / IM Improving the San Buenave PRESIÓN, REDIAGRAMACIÓN, Solicitud de cotiza Single Stage - One E IDA / 49230 ntura - Ixiamas National Roa Posterior Limited 10,000.00 9,914.55 Firmado 2021-02-15 2021-04-28 2021-03-28 2021-05-26 2021-04-17 PUBLICACIÓN Y DIFUSIÓN DE ciones nvelope d L LIBRO DE LA CULTURA TAC ANA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-ABC-63413-CS-LCS / AUD ITORIA FINANCIERA EXTERNA DE CREDITOS FINANCIADOS Improving the San Buenave POR EL BANCO MUNDIAL- GE Selección basada IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 6,936.59 8,581.62 Finalizado 2018-05-18 2018-01-17 2018-06-02 2018-06-17 2018-07-15 2018-07-17 2018-07-20 2018-07-17 2018-07-28 2018-07-19 2018-08-12 2018-08-27 2018-09-06 2018-09-06 STION 2017 CREDITO 4923-B en el menor costo d O PROYECTO MEJORAMIENTO Y CONSTRUCCION DE LA CAR RETERA SAN BUENA VENTU RA - IXIAMAS Page 1 BO-ABC-87963-CS-LCS / AUD ITORIA FINANCIERA EXTERNA DE CRÉDITOS FINANCIADOS Improving the San Buenave POR EL BANCO MUNDIAL - G Selección basada IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 11,700.00 12,251.65 Finalizado 2018-12-06 2019-02-06 2018-12-11 2018-12-24 2019-01-28 2019-01-21 2019-03-22 2019-01-31 2019-03-27 2019-02-21 2019-04-05 2019-03-14 2019-06-15 2019-04-18 2019-06-15 ESTIÓN 2018, CRÉDITO 4923 en el menor costo d -BO PROYECTO MEJORAMIEN TO Y CONSTRUCCIÓN DE LA CARRETERA SAN BUENA VE NTURA - IXIAMAS BO-ABC-91672-CS-LCS / SER VICIO DE CONSULTORIA PAR A LA ACTUALIZACIÓN DEL PL AN DE REASENTAMIENTO E I Improving the San Buenave Selección basada NDEMNIZACIÓN DE POBLACI IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 100,000.00 0.14 Firmado 2019-01-14 2019-03-22 2019-01-28 2019-09-04 2019-02-12 2019-07-25 2019-03-12 2019-12-09 2019-03-27 2019-11-29 2019-04-15 2019-12-11 2019-05-16 2020-03-02 2019-10-13 en el menor costo ONES AFECTADAS (PRIPA) Y d CONCLUSIÓN DE LA LIBERACI ÓN DEL DERECHO DE VÍA DE L PROYECTO SAN BUENAVEN TURA - IXIAMAS BO-ABC-93262-CS-QCBS / Su pervisión Técnica y Socioam biental de las Obras de Mejor Improving the San Buenave Selección basada Open - Internationa amiento y Construcción del T IDA / 49230 ntura - Ixiamas National Roa Previa 5,439,221.00 0.00 En ejecución 2019-01-10 2019-04-11 2019-01-24 2019-02-15 2019-03-15 2019-03-30 2019-04-24 2019-05-23 2022-02-06 en calidad y costo l ramo Carretero San Buenave d ntura - Ixiamas LOTE 1 y LO TE 2 (con condición suspensi va) BO-ABC-188361-CS-LCS / AU DITORIA FINANCIERA EXTERN Improving the San Buenave A DEL CRÉDITO 4923-BO PRO Selección basada IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 7,185.00 8,395.21 Firmado 2020-08-14 2020-08-16 2020-08-14 2020-08-17 2020-08-18 2020-09-14 2020-09-16 2020-09-21 2020-09-17 2020-09-25 2020-09-22 2020-10-06 2020-10-05 2020-11-15 YECTO MEJORAMIENTO Y CO en el menor costo d NSTRUCCIÓN DE LA CARRET ERA SAN BUENA VENTURA - I XIAMAS GESTIÓN 2019 BO-ABC-202008-CS-QCBS / S Improving the San Buenave UPERVISION DE OBRAS DE C Selección basada Open - Internationa IDA / 49230 ntura - Ixiamas National Roa Previa 1,886,054.00 2,084,448.72 Firmado 2020-11-11 2020-12-10 2020-11-25 2020-12-11 2020-12-11 2021-02-04 2021-01-08 2021-03-09 2021-01-20 2021-04-08 2021-02-09 2021-07-28 2021-03-10 2021-08-30 2022-07-31 ONSTRUCCION DE PUENTES en calidad y costo l d SAN BUENAVENTURA . IXIAM AS BO-ABC-206147-CS-LCS / AU DITORIA FINANCIERA EXTERN A DEL CREDITO 4923-BO PRO Improving the San Buenave Selección basada YECTO MEJORAMIENTO Y CO IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 3,645.00 0.00 Cancelado 2020-12-01 2020-12-17 2020-12-01 2020-12-04 2021-01-01 2021-01-08 2021-01-12 2021-01-23 2021-02-27 en el menor costo NSTRUCCION DE LA CARRET d ERA SAN BUENAVENTURA – IXIAMAS GESTION 2020 BO-ABC-276618-CS-LCS / AU DITORIA FINANCIERA Y DE CI ERRE EXTERNA DEL CRÉDITO Improving the San Buenave Selección basada 4923-BO PROYECTO MEJORA IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 10,932.95 10,484.78 Finalizado 2022-02-07 2022-03-16 2022-02-07 2022-02-14 2021-02-18 2022-03-14 2022-04-25 2022-03-21 2022-04-27 2022-04-04 2022-05-05 2022-04-25 2022-06-02 2022-06-04 2022-07-02 en el menor costo MIENTO Y CONSTRUCCIÓN D d E LA CARRETERA SAN BUEN AVENTURA – IXIAMAS - GESTI ÓN 2021 BO-ABC-339605-CS-CDS / A UDITORIA FINANCIERA EXTER Improving the San Buenave NA DEL CREDITO 4923-BO PR Selección basada IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 9,129.00 0.00 Cancelado 2023-02-09 2023-02-06 2023-02-09 2023-02-16 2023-03-16 2023-03-23 2023-04-06 2023-04-27 2023-06-16 OYECTO MEJORAMIENTO Y C en el menor costo d ONSTRUCCION DE LA CARRE TERA SAN BUENAVENTURA - IXIAMAS -GESTION 2022 BO-ABC-348131-CS-LCS / AU DITORIA FINANCIERA EXTERN Improving the San Buenave A DEL CREDITO 4923-BO PRO Selección basada IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 11,772.00 0.00 Cancelado 2023-03-08 2023-03-13 2023-03-08 2023-03-08 2023-03-24 2023-04-07 2023-04-21 2023-04-11 2023-04-24 2023-04-21 2023-04-28 2023-05-16 2023-06-20 YECTO MEJORAMIENTO Y CO en el menor costo d NSTRUCCION DE LA CARRET ERA SAN BUENAVENTURA - I XIAMAS - GESTION 2022 BO-ABC-348131-CS-LCS.- / A UDITORIA FINANCIERA EXTER Improving the San Buenave NA DEL CREDITO 4923-BO PR Selección basada Ejecución pendien IDA / 49230 ntura - Ixiamas National Roa Posterior Open - National 11,772.00 0.00 2023-03-08 2023-03-24 2023-03-24 2023-04-21 2023-04-24 2023-05-01 2023-05-24 2023-06-28 OYECTO MEJORAMIENTO Y C en el menor costo te d ONSTRUCCION DE LA CARRE TERA SAN BUENAVENTURA - IXIAMAS -GESTION 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual No CI 1 / Consultor a para la Improving the San Buenave IDA / 49230 Previa Individual Open 10,000.00 9,531.11 Firmado 2014-09-04 2014-09-23 elaboraci n de Pueblos Indige ntura - Ixiamas National Roa nas (PPI) d BO-ABC-133503-CS-INDV / C Improving the San Buenave ONSULTOR/A ADMINISTRADO IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 3,246.00 1,792.18 Firmado 2019-09-23 2017-06-08 2019-10-20 2019-10-10 2019-10-30 2019-10-18 2019-11-24 2019-11-13 2020-02-22 R DEL PPI ESSE EJJA d BO-ABC-133508-CS-INDV / C ONSULTOR/A DE LÍNEA TECNI Improving the San Buenave CO/A FORESTAL DE EQUIPO T IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 3,246.00 1,792.18 Firmado 2019-09-23 2019-10-09 2019-10-23 2019-10-10 2019-11-13 2019-10-18 2019-12-12 2019-11-11 2020-03-11 ÉCNICO DE PLANES DE PUEB d LOS INDÍGENAS (ET-PPI) BO-ABC-133511-CS-INDV / C Improving the San Buenave ONSULTOR/A ADMINISTRADO Ejecución pendien IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 3,246.00 0.00 2019-09-23 2019-10-23 2019-11-02 2019-11-27 2020-02-25 R DE EQUIPO TÉCNICO DEL P te d LANES DE PUEBLOS INDÍGEN AS (ET-PPI) BO-ABC-133513-CS-INDV / C Improving the San Buenave ONSULTOR/A ABOGADO/A DE IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 3,246.00 1,792.18 Firmado 2019-09-23 2019-10-09 2019-10-23 2019-10-10 2019-11-02 2019-11-07 2019-11-27 2019-11-11 2020-02-25 EQUIPO TÉCNICO DE PLANES d DEL PUEBLOS INDIGENAS (ET - PPI) BO-ABC-156949-CS-CDS / A UDITORIA FINANCIERA EXTER Improving the San Buenave NA DEL CREDITO 4923-BO PR Selección directa IDA / 49230 ntura - Ixiamas National Roa Posterior Direct 4,200.00 0.00 Cancelado 2020-02-10 2020-03-17 2020-03-01 2020-03-26 2020-05-05 OYECTO MEJORAMIENTO Y C de consultores d ONSTRUCCIÓN DE LA CARRE TERA SAN BUENA VENTURA – IXIAMAS GESTIÓN 2019 BO-ABC-205613-CS-INDV / FI Improving the San Buenave SCALIZACION DE OBRA, JEFE IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 38,636.00 14,187.81 Firmado 2020-12-04 2021-03-24 2021-01-22 2021-06-01 2021-02-12 2021-06-14 2021-03-05 2021-06-27 2022-07-28 DE FISCALIZACION d Page 2 BO-ABC-205614-CS-INDV / FI Improving the San Buenave SCALIZACION DE OBRA, FISC IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 35,070.00 13,096.83 Firmado 2020-12-04 2021-03-24 2021-01-22 2021-06-01 2021-02-12 2021-06-14 2021-03-19 2021-06-27 2022-08-11 AL DE OBRA d BO-ABC-205615-CS-INDV / FI Improving the San Buenave SCALIZACION DE OBRA, FISC IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 35,070.00 9,109.63 Firmado 2020-12-04 2021-03-24 2021-01-22 2021-07-21 2021-02-12 2021-07-29 2021-03-05 2021-08-16 2022-07-28 AL AMBIENTAL d BO-ABC-210865-CS-INDV / I NGENIERO DE SEGUIMIENTO Improving the San Buenave TÉCNICO DE OBRAS - CONST IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 40,180.00 10,745.84 Firmado 2021-01-08 2021-03-24 2021-02-26 2021-06-18 2021-03-19 2021-06-28 2021-04-23 2021-08-15 2022-08-23 RUCCIÓN DE LOS PUENTES D d E LA CARRETERA SAN BUENA VENTURA - IXIAMAS BO-ABC-222216-CS-INDV / C Improving the San Buenave ONSULTOR EN LÍNEA ESPECI IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 30,170.00 7,366.21 Firmado 2021-03-04 2021-03-24 2021-04-22 2021-07-26 2021-05-13 2021-08-02 2021-06-17 2021-08-21 2021-12-14 ALISTA SOCIAL DEL EQUIPO d DE FISCALIZACIÓN BO-ABC-224553-CS-CDS / A UDITORIA FINANCIERA EXTER NA DEL CREDITO 4923-BO PR Improving the Rurrenabaque Selección directa IDA / 49230 Posterior Direct 3,645.00 7,224.47 Finalizado 2021-03-15 2021-03-16 2021-03-19 2021-03-30 2021-05-23 2021-05-16 2021-06-17 2021-08-03 OYECTO MEJORAMIENTO Y C Airport de consultores ONSTRUCCION DE LA CARRE TERA SAN BUENAVENTURA - IXIAMAS GESTION 2020 BO-ABC-272895-CS-INDV / C Improving the San Buenave ONSULTOR DE LINEA FISCAL IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 15,832.00 0.00 En ejecución 2022-01-14 2022-07-26 2022-03-04 2022-03-25 2022-04-29 2022-10-26 AMBIENTAL d BO-ABC-272898-CS-INDV / C Improving the San Buenave ONSULTOR DE LÍNEA INGENI IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 18,542.27 0.00 En ejecución 2022-01-14 2022-09-05 2022-03-04 2022-03-25 2022-04-29 2022-10-26 ERO DE SEGUIMIENTO TECNI d CO DE OBRA BO-ABC-272901-CS-INDV / C Improving the San Buenave ONSULTOR DE LÍNEA ESPECI IDA / 49230 ntura - Ixiamas National Roa Posterior Individual Open 13,260.64 0.00 En ejecución 2022-01-14 2022-08-01 2022-03-04 2022-03-25 2022-04-29 2022-10-26 ALISTA SOCIAL DE FISCALIZA d CIÓN BO-ABC-371466-CS-CDS / A UDITORIA FINANCIERA EXTER NA DE CIERRE DEL CONVENI Improving the San Buenave Selección directa O DE CRÉDITO 4923-BO PRO IDA / 49230 ntura - Ixiamas National Roa Posterior Direct - National 16,640.00 0.00 En ejecución 2023-07-11 2023-07-14 2023-07-21 2023-07-31 2023-09-04 de consultores YECTO MEJORAMIENTO Y CO d NSTRUCCION DE LA CARRET ERA SAN BUENAVENTURA – I XIAMAS, GESTIÓN 2023 Page 3