PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western and Central Africa 2019-02-12 Bank’s Approval Date of the Original Procurement Plan: 2023-09-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / D2890, TF / A7132, TF / B4205 Project Fiduciary and Administrative Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 20/STP/COMP2/W/WACA/201 Component 2: Strengthening Request for Quota Single Stage - One E 2019-11-0 IDA / D2890 Post Limited 25,000.00 21,815.20 Signed 2019-03-16 2019-05-14 2019-05-11 2019-07-28 9 / Réparation et entretien d the Policy and Institutional F tions nvelope 7 es phares. ramework 01/STP/COMP3/W/WACA/201 9 / Construction des routes d' Component 3: Strengthening Single Stage - One E 2020-10-3 accès,d'égouts et d'autres inf IDA / D2890 National Physical and Social Post Request for Bids Open - National 450,000.00 0.00 Canceled 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 nvelope 1 rastructures dans les zones d Investments 'expansion sécurisées. 02/STP/COMP3/W/WACA720 Component 3: Strengthening Single Stage - One E 2021-01-1 19 / Infrastructures sociales IDA / D2890 National Physical and Social Post Request for Bids Open - National 240,000.00 0.00 Canceled 2020-04-01 2020-04-06 2020-05-18 2020-06-17 2020-07-22 nvelope 8 pour Malanza, Santa catarina Investments et Praia Burra. 03/STP/COMP3/W/WACA/201 Component 3: Strengthening 9 / Construtions de maisons Request for Quota Single Stage - One E 2021-01-2 IDA / D2890 National Physical and Social Post Limited 190,000.00 0.00 Canceled 2020-06-06 2020-08-01 pour les plus vulnérables au tions nvelope 8 Investments Malanza, Santa Catarina et P raia Burra. 26/STP/COMP3/W/WACA/201 Component 3: Strengthening 9 / Reabilitação dos dispositi 2020-07-1 IDA / D2890 National Physical and Social Post Direct Selection Direct 30,110.00 33,182.29 Signed 2019-12-09 2019-12-13 2019-12-14 2019-12-12 2020-01-18 2019-12-30 vos de protecção do Rio de R 6 Investments ibeira Afonso contra inundaç ões 32/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Obras de murro de proteç Single Stage - One E 2021-01-0 IDA / D2890 National Physical and Social Post Request for Bids Open - National 400,000.00 506,252.93 Signed 2020-03-17 2020-03-31 2020-03-22 2020-04-06 2020-05-03 2020-06-25 2020-06-02 2020-06-26 2020-07-07 2020-08-19 ão e ordenamento urbanístic nvelope 3 Investments o de Santa Catarina 33/STP/COMP3/W/WACA/202 Component 3: Strengthening Single Stage - One E 1,073,025.3 2021-01-0 0 / Obras de ordenamento ur IDA / D2890 National Physical and Social Post Request for Bids Open - National 350,000.00 Signed 2020-03-17 2020-03-31 2020-03-22 2020-04-06 2020-05-03 2020-08-14 2020-06-02 2020-10-01 2020-07-07 2020-10-09 nvelope 6 3 banístico de Malanza e Praia Investments Burra 37/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Obras de construção de in Single Stage - One E 2021-05-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National 190,000.00 0.00 Canceled 2020-08-03 2020-08-08 2020-09-19 2020-10-19 2020-11-23 fraestruturas sociais em Mala nvelope 2 Investments nza, Praia Burra e Santa Cata rina 46/STP/COMP3/W/WACA/202 0 / Appui à la construction de Component 3: Strengthening s maisons (Coût de l'appui, d Open - Internationa Single Stage - One E 2021-05-2 IDA / D2890 National Physical and Social Post Request for Bids 375,000.00 0.00 Canceled 2020-08-10 2020-08-15 2020-09-26 2020-10-26 2020-11-30 u materiel et de l'accompagn l nvelope 9 Investments ement technique) à Malanza, à Praia Burra et à Santa Cata rina. 47/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Preparation zone expansi Request for Quota Single Stage - One E 2021-09-2 IDA / D2890 National Physical and Social Post Limited 200,000.00 0.00 Canceled 2021-02-03 2021-03-31 on: urbanisation et infraestru tions nvelope 7 Investments tures sociales à Praia Abade. 53/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Constructions de maisons Open - Internationa Single Stage - One E 2021-07-1 IDA / D2890 National Physical and Social Post Request for Bids 500,000.00 0.00 Canceled 2020-09-22 2020-10-16 2020-09-27 2020-10-21 2020-11-08 2020-12-08 2021-01-12 et infraestructures sociales e l nvelope 1 Investments n Santa Catarina, Malanza et Praia Burra 65/STP/COMP3/W/WACA/202 Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2022-02-2 1 / Construction de infrastruc IDA / D2890 National Physical and Social Post Limited tions (Non Bank-S 160,000.00 264,961.83 Signed 2021-07-07 2021-07-05 2021-09-01 2021-08-27 tions nvelope 8 tures sociales à Santa Catari Investments PD) na et à Malanza. 56/STP/COMP3/W/WACA/202 1 / Drainage des eaux pluvial Request for Bids - es et mur de protection contr Component 3: Strengthening Single Stage - One E Small Works SPD 2,688,495.9 2022-06-1 e l'inondation marine à IÔ Gr IDA / D2890 National Physical and Social Post Request for Bids Open - National 1,680,000.00 Signed 2021-08-25 2021-09-30 2021-08-30 2021-10-05 2021-10-11 2021-11-30 2021-11-10 2022-05-24 2021-12-15 2022-05-24 nvelope (1 envelope proce 9 3 ande, Micoló et Praia Abade Investments ss) et Préparation de zone d'exp ansion sécurité à IÔ Grande, Micoló et Praia Abade 60/STP/COMP3/W/WACA/202 Request for Bids - Component 3: Strengthening 1 / Construção de casas soci Single Stage - One E Small Works SPD 2022-06-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National 1,050,000.00 960,282.18 Signed 2021-09-06 2021-12-09 2021-09-11 2022-01-12 2021-10-23 2022-03-03 2021-11-22 2022-03-30 2021-12-27 2022-05-01 ais em Santa Catarina, Micol nvelope (1 envelope proce 5 Investments ó, Malanza, Iô Grande, Praia ss) Burra e Praia Abade 71/STP/COMP3/W/WACA/202 2 / Berma rochosa e rampa e Request for Bids - Component 3: Strengthening m Pantufo; Berma rochosa e Single Stage - One E Small Works SPD 2,013,000.0 2023-02-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National 1,720,000.00 Signed 2022-05-12 2022-06-14 2022-05-17 2022-06-14 2022-06-28 2022-08-01 2022-07-28 2022-09-12 2022-09-01 2022-10-03 parte da rede de drenagem e nvelope (1 envelope proce 0 8 Investments m Praia Melão; Parte do queb ss) ra-mar e aterro em praias Lo chinga, Gamboa e Cruz Request for Quota 82/STP/COMP3/W/WACA/202 Component 3: Strengthening Request for Quota Single Stage - One E tions - Small Work 2023-09-1 2 / Construção da ponte que l TF / A7132 National Physical and Social Post Open - National 200,000.00 0.00 Signed 2023-01-22 2023-06-09 2023-03-19 2023-08-01 tions nvelope s (Emergency) SP 5 iga Morro Peixe à Praia Gueg Investments D -Competitive ue 91/STP/W/WACA/2022 / Cons Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2023-04-2 trução de infraestrutura soci IDA / D2890 National Physical and Social Post Open - National tions (Non Bank-S 120,000.00 0.00 Canceled 2022-09-05 2022-10-31 tions nvelope 9 al(Polidesportivo) em Praia B Investments PD) urra. 93/STP/COMP3/W/WACA/202 Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2023-09-0 3 / Construção de infraestrut IDA / D2890 National Physical and Social Post Limited tions (Non Bank-S 170,000.00 0.00 Signed 2023-01-16 2023-02-06 2023-03-13 2023-04-20 tions nvelope 9 ura social em Micoló (escola) Investments PD) 73/STP/COMP3/W/WACA/202 Request for Bids - Component 3: Strengthening 2 / Construção de infraestrut Single Stage - One E Small Works SPD 2023-04-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National 540,000.00 0.00 Canceled 2022-07-04 2022-07-09 2022-08-20 2022-09-19 2022-10-24 uras sociais em Praia Burra, nvelope (1 envelope proce 2 Investments Micoló, Iô Grande e Praia Aba ss) de Page 1 94/STP/COMP3/W/WACA/202 National Procure 3 / Drenagem de águas pluvi Component 3: Strengthening ment Document - Under Imple 2024-03-0 ais e muro de proteção contr IDA / D2890 National Physical and Social Post Direct Selection Direct - National 1 Envelope proce 349,881.48 0.00 2023-08-01 2023-08-01 2023-08-06 2023-08-02 2023-09-10 mentation 8 a inundações marítimas e pr Investments ss (Non Bank-SPD eparação da zona de expans ) ão segura em Iô Grande 78/STP/COMP3/W/WACA/202 Request for Bids - Component 3: Strengthening 2 / Construção de 13 casas s Single Stage - One E Small Works SPD 2024-02-2 IDA / D2890 National Physical and Social Post Request for Bids Open - National 276,000.00 0.00 Canceled 2023-05-08 2023-05-05 2023-05-13 2023-05-08 2023-06-24 2023-06-06 2023-07-24 2023-08-28 ociais em Praia Abade na Re nvelope (1 envelope proce 4 Investments gião Autónoma do Príncipe ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/STP/COMP2/G/WACA/201 Component 2: Strengthening Open - Internationa Single Stage - One E 9 / Kit d'equipements de séc IDA / D2890 the Policy and Institutional F Post Request for Bids 200,000.00 267,258.69 Signed 2019-06-24 2019-09-17 2019-06-29 2019-09-20 2019-08-10 2019-10-21 2019-09-09 2019-10-21 2019-10-14 2020-10-25 2020-04-11 l nvelope urite en mer pour les pêcheu ramework rs. 03/STP/COMP2/G/WACA/201 9 / Acquisition de matériel inf Component 2: Strengthening Request for Quota Single Stage - One E ormatique et de logiciels dan TF / A7132 the Policy and Institutional F Post Open - National 10,000.00 57,751.70 Completed 2019-03-30 2019-05-25 2019-07-21 2019-11-21 2019-09-28 tions nvelope s le domaine de la surveillan ramework ce pour l'observatoire de l'en vironnement 04/STP/COMP4/G/WACA/201 9 / Acquisition de biens et de Component 4: National Coor Request for Quota Single Stage - One E IDA / D2890 Post Open - National 22,000.00 0.00 Canceled 2019-04-06 2019-06-01 2019-11-28 matériaux aux propriétaires dination tions nvelope pour la cession de terres. 21/STP/COMP4/G/WACA/201 Component 4: National Coor 9 / Acquisition de biens aux p IDA / D2890 Post Direct Selection Direct 4,700.00 4,700.00 Completed 2019-05-23 2019-05-27 2019-05-28 2019-06-05 2019-07-02 2019-06-16 2019-12-29 2019-06-17 dination roprietaires pour la cession d es terres. 27/STP/COMP4/G/WACA/201 9 / Aquisição de bens para os Component 4: National Coor Request for Quota Single Stage - One E IDA / D2890 Post Limited 7,000.00 6,969.30 Signed 2019-11-20 2019-12-23 2020-01-15 2020-02-22 2020-07-13 2020-03-01 proprietários pela concepção dination tions nvelope de terras em Praia Abade 29/STP/COMP4/G/WACA/201 Component 4: National Coor Under Imple 9 / Aquisição e instalação de IDA / D2890 Post Direct Selection Direct 5,000.00 0.00 2019-12-09 2019-12-16 2019-12-14 2019-12-23 2020-01-18 2020-07-16 dination mentation sistema de contabilidade e g estão financeira 38/STP/COMP4/G/WACA/202 Component 4: National Coor Request for Quota Single Stage - One E IDA / D2890 Post Limited 15,000.00 14,343.87 Signed 2020-03-28 2020-04-06 2020-05-23 2020-06-10 2020-11-19 0 / Equipamentos para a UGP dination tions nvelope 39/STP/COMP4/G/WACA/202 Component 4: National Coor 0 / Aquisição de software de IDA / D2890 Post Direct Selection Direct 11,000.00 8,880.00 Signed 2020-04-08 2020-04-10 2020-04-13 2020-04-15 2020-05-18 2020-05-02 2020-11-14 dination monitoria e avaliação RUCHE 52/STP/COMP3/G/WACA/202 Component 3: Strengthening 0 / Aquisição de uma moto c IDA / D2890 National Physical and Social Post Direct Selection Direct 4,000.00 3,018.79 Completed 2020-06-15 2020-06-22 2020-06-20 2020-07-07 2020-07-25 2020-07-05 2021-01-21 2020-07-06 arrinha Investments 54/STP/COMP4/G/WACA/202 Component 4: National Coor Request for Quota Single Stage - One E IDA / D2890 Post Limited 50,000.00 40,400.50 Signed 2022-01-18 2022-01-27 2022-03-15 2022-04-10 2022-09-11 2 / Aquisição de uma Pick up dination tions nvelope 63/STP/COMP4/G/WACA/202 2 / Aquisição de equipament Component 4: National Coor Request for Quota Single Stage - One E TF / A7132 Post Limited 7,000.00 10,111.78 Signed 2022-04-10 2022-03-29 2022-06-05 2022-07-02 2022-12-02 o suplementar para drone: b dination tions nvelope ateria e telefone portátil 85/STP/COMP3/G/WACA/202 Component 3: Strengthening Request for Quota Single Stage - One E 2 / Aquisição de três portátei TF / A7132 National Physical and Social Post Open - National 10,000.00 0.00 Signed 2022-07-03 2022-08-28 2022-12-14 2023-02-24 tions nvelope s e uma fotocopiadora para U Investments GP 86/STP/COMP3/G/WACA/202 Component 3: Strengthening 2 / Apetrechamento das esco Request for Quota Single Stage - One E IDA / D2890 National Physical and Social Post Limited 16,000.00 18,112.88 Signed 2022-07-03 2022-06-30 2022-08-28 2022-07-28 2023-02-24 las de Santa Catarina e Mala tions nvelope Investments nza com mobiliário 88/STP/COMP2/G/WACA/202 Component 2: Strengthening Single Stage - One E 2 / Aquisição de materiais de TF / A7132 the Policy and Institutional F Post Request for Bids Open - National 100,000.00 0.00 Canceled 2022-07-07 2022-07-12 2022-08-23 2022-09-22 2022-10-27 2023-04-25 nvelope segurança marítima ramework 76/STP/COMP2/G/WACA/202 Component 2: Strengthening Request for Quota Single Stage - One E 2 / Compra e instalação de p TF / B4205 the Policy and Institutional F Post Limited 30,000.00 0.00 Signed 2022-09-03 2022-10-20 2022-10-29 2023-01-31 2023-04-27 tions nvelope ainel solar para INM ramework 75/STP/ COMP2/G/WACA/202 2 / Aquisição e instalação de estação meteorológica auto mática e 2 marégrafos; aquis Component 2: Strengthening Open - Internationa Single Stage - One E ição de kits de manutenção d TF / B4205 the Policy and Institutional F Post Request for Bids 160,000.00 0.00 Signed 2022-09-29 2022-09-29 2022-10-04 2022-09-29 2022-11-15 2022-11-11 2022-12-15 2023-01-16 2023-01-19 2023-02-14 2023-07-18 l nvelope e estações e formação; aquis ramework ição de 17 termómetros de b alde marítimos; e reparação de 7 estações meteorológica s automáticas e 1 marégrafo 92/STP/COMP4/G/WACA/202 Component 2: Strengthening Request for Quota Single Stage - One E TF / A7132 Post Open - National 10,000.00 0.00 Canceled 2023-05-15 2023-05-12 2023-07-10 2024-01-06 3 / Aquisição de acessórios p the Policy and Institutional F tions nvelope ara drone. ramework 97/STP/COMP4/G/WACA/202 Component 4: National Coor Request for Quota Single Stage - One E Pending Impl 3 / Aquisição de novo drone TF / A7132 Post Limited 10,000.00 0.00 2023-09-20 2023-11-15 2024-05-13 dination tions nvelope ementation e peças sobressalentes. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/STP/COMP2/S/WACA/201 Component 2: Strengthening Request for Quota Single Stage - One E 9 / Aquisition peinture pour IDA / D2890 the Policy and Institutional F Post Open - National 9,000.00 0.00 Canceled 2019-05-20 2019-07-15 2020-01-11 tions nvelope Marquage des pirogues. ramework Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/STP/COMP3/C/WACA/201 Component 3: Strengthening 9 / Dessins techniques pour l Consultant Qualifi IDA / D2890 National Physical and Social Post Open - National 30,000.00 65,815.47 Signed 2019-02-08 2019-04-24 2019-03-01 2019-06-12 2019-04-14 2019-10-10 2019-05-14 2019-10-17 2019-06-18 2019-10-22 2019-12-15 a planification spatiale de zo cation Selection Investments nes d'expansion sûres 34/STP/COMP3/C/WACA/202 0 / Fiscalização das obras de Component 3: Strengthening Consultant Qualifi ordenamento urbanístico em IDA / D2890 National Physical and Social Post Open - National 20,000.00 133,492.96 Signed 2020-03-17 2020-03-31 2020-04-07 2020-04-27 2020-05-21 2020-07-08 2020-06-20 2020-09-28 2020-07-25 2020-08-26 2021-01-21 cation Selection S.Tomé e Príncipe (Santa Cat Investments arina, Malanza e Praia Burra) 45/STP/COMP3/C/WACA/202 Component 3: Strengthening 0 / Supervision des travaux c Consultant Qualifi IDA / D2890 National Physical and Social Post Open - National 20,000.00 0.00 Canceled 2020-05-11 2020-04-08 2020-06-01 2020-07-15 2020-08-14 2020-09-18 2021-03-17 onstruction des oeuvres soci cation Selection Investments aux à S.Tomé et à RAP. 44/STP/COMP3/C/WACA/202 Component 3: Strengthening 0 / Design d'oeuvres pour les Consultant Qualifi IDA / D2890 National Physical and Social Post Open - National 140,000.00 196,330.00 Signed 2020-04-23 2020-04-25 2020-05-14 2020-07-12 2020-06-27 2020-09-22 2020-07-27 2020-12-18 2020-08-31 2020-12-22 2021-02-27 travaux des communités (Pa cation Selection Investments ntufo,Praia Melão, Praia Gam boa-Lochinga-Cruz) 48/STP/COMP3/C/WACA/202 Component 3: Strengthening 0 / Etude d'impact environne Consultant Qualifi Open - Internationa IDA / D2890 National Physical and Social Post 40,000.00 88,393.37 Signed 2020-05-15 2020-12-16 2020-06-05 2021-01-07 2020-07-19 2021-04-06 2020-08-18 2021-05-05 2020-09-22 2021-04-22 2021-03-21 mentale et sociale au Pantuf cation Selection l Investments o, Praia Melão et Praia Gamb oa-Lochinga-Cruz 57/STP/COMP3/C/WACA/202 1 / Supervision des travaux d Component 3: Strengthening 'aménagement des zones d'e Consultant Qualifi IDA / D2890 National Physical and Social Post Limited 50,000.00 0.00 Canceled 2021-08-27 2021-09-10 2021-10-10 2021-11-14 2022-05-13 xpansion à Iô Grande et Mico cation Selection Investments ló et des travaux de drainage et mur de protection à Iô Gra nde et Micoló 58/STP/COMP3/C/WACA/202 1 / Supervisão de trabalhos d e ordenamento das zonas de Component 3: Strengthening expansão em Iô Grande, Mic Consultant Qualifi IDA / D2890 National Physical and Social Post Limited 100,000.00 100,000.00 Signed 2021-09-08 2021-09-14 2021-09-22 2021-12-27 2021-10-22 2022-06-08 2021-11-26 2022-06-10 2022-05-25 oló e em Praia Abade e de tr cation Selection Investments abalhos de drenagem, proteç ão costeira e muro de proteç ão em Iô Grande, Micoló e e m Praia Abade 59/STP/COMP3/C/WACA/202 1 / Supervision des travaux c Component 3: Strengthening Consultant Qualifi onstruction des maisons soci IDA / D2890 National Physical and Social Post Limited 100,000.00 60,000.00 Signed 2021-09-15 2022-03-21 2021-09-29 2022-04-08 2021-10-29 2022-06-09 2021-12-03 2022-06-21 2022-06-01 cation Selection aux à Santa Catarina, Micoló, Investments Iô Grande Malanza, à Praia Burra et Praia Abade 79/STP/COMP2/C/WACA/202 Component 2: Strengthening 2 / Assistência técnica intern Consultant Qualifi Open - Internationa TF / B4205 the Policy and Institutional F Post 120,000.00 0.00 Canceled 2022-03-17 2022-03-17 2022-04-07 2022-03-17 2022-05-21 2022-07-18 2022-06-20 2022-07-25 2023-01-21 acional para elaboração do pl cation Selection l ramework ano de ordenamento costeiro e marítimo 83/STP/COMP3/C/WACA/202 Component 3: Strengthening 2 / Fiscalização da obras de c Consultant Qualifi TF / A7132 National Physical and Social Post Open - National 30,000.00 0.00 Signed 2022-05-06 2022-05-05 2022-05-27 2022-05-06 2022-07-10 2022-09-12 2022-08-09 2022-09-05 2022-09-13 2023-04-05 2023-03-12 onstrução da ponte que liga cation Selection Investments Morro Peixe à Praia guegue 72/STP/COMP3/C/WACA/202 2 / Supervision des travaux d Component 3: Strengthening Consultant Qualifi 'adaptation dans des commu TF / B4205 National Physical and Social Post Open - National 100,000.00 0.00 Signed 2022-05-20 2022-07-18 2022-06-10 2022-07-24 2022-08-25 2022-08-23 2022-09-16 2022-09-27 2022-09-27 2023-03-26 cation Selection nautés de Praia Melão, Pantu Investments fo, Lochinga, Gamboa e Cruz 74/STP/COMP3/C/WACA/202 Component 3: Strengthening Consultant Qualifi Under Implement 2 / Fiscalização da infraestrut IDA / D2890 National Physical and Social Post Open - National 15,000.00 0.00 2023-01-10 2023-03-06 2023-01-31 2023-03-16 2023-08-07 2023-04-15 2023-04-07 2023-05-20 2023-11-16 cation Selection ation ura social em Micoló. Investments 96/STP/COMP3/C/WACA/202 3 / Hiring a legal office to dev Component 3: Strengthening Consultant Qualifi Open - Internationa Under Implement elop the voluntary transfer a IDA / D2890 National Physical and Social Post 30,000.00 0.00 2023-08-04 2023-08-28 2023-08-25 2023-08-28 2023-10-08 2023-11-07 2023-12-12 2024-06-09 cation Selection l ation greements for families who o Investments wn houses in risk areas. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/STP/COMP2/C/WACA/201 Component 2: Strengthening 9 / Diagnostic de la situation Individual Consult TF / A7132 the Policy and Institutional F Post Open 10,000.00 48,973.00 Completed 2019-02-08 2019-04-18 2019-03-29 2019-09-05 2019-04-19 2019-09-05 2019-05-24 2019-09-02 2019-11-20 2020-01-05 de la météorologie maritime ant Selection ramework pour la création d'un centre de prévision maritime 04/STP/COMP2/C/WACA/201 Component 2: Strengthening 9 / Assistance technique à l'I Individual Consult TF / A7132 the Policy and Institutional F Post Open 4,000.00 0.00 Canceled 2019-05-27 2019-05-12 2019-07-15 2019-08-05 2019-09-09 2020-03-07 NM pour la préparation et la t ant Selection ramework ransmission d'informations m étéorologiques sur TVS 05/STP/COMP2/C/WACA/201 Component 2: Strengthening 9 / Conseil en techniques de Individual Consult TF / A7132 the Policy and Institutional F Post Limited 20,000.00 20,000.00 Completed 2019-05-24 2019-08-21 2019-05-29 2019-10-03 2019-06-19 2019-10-17 2019-07-24 2019-10-23 2020-01-20 2019-11-21 suivi et de traitement de don ant Selection ramework nées pour les indicateurs de projet 07/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual Consult 9 / Appui à la loi de gestion d TF / A7132 the Policy and Institutional F Prior Open 15,000.00 0.00 Canceled 2019-04-24 2019-06-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 ant Selection es risques et catastrophes ramework 09/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual Consult TF / A7132 Prior Open 15,000.00 0.00 Canceled 2019-04-25 2019-06-13 2019-07-04 2019-08-08 2020-02-04 9 / Appui au cadre juridique p the Policy and Institutional F ant Selection our le littoral ramework 10/STP/COMP4/C/WACA/STA Component 4: National Coor Individual Consult FF/2019 / Spécialiste en suivi TF / A7132 Post Open 18,000.00 18,000.00 Signed 2019-01-31 2019-02-13 2019-03-21 2019-04-16 2019-04-11 2019-04-17 2019-05-16 2019-04-11 2019-11-12 dination ant Selection et évaluation Page 3 11/STP/COMP4/C/WACA/STA Component 4: National Coor Individual Consult FF/2019 / Spécialiste en com IDA / D2890 Post Limited 2,400.00 10,411.00 Signed 2019-01-31 2019-02-21 2019-02-05 2019-05-27 2019-02-26 2019-06-14 2019-04-02 2019-06-17 2019-09-29 dination ant Selection munication à temps partiel 12/STP/COMP4/C/WACA/STA Component 4: National Coor Individual Consult IDA / D2890 Post Open 21,600.00 21,600.00 Signed 2019-01-31 2019-02-13 2019-03-21 2019-04-16 2019-04-11 2019-04-17 2019-05-16 2019-04-10 2019-11-12 FF/2019 / Hiring a civil engin dination ant Selection eer 06/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual Consult 9 / Amélioration de la diffusio TF / A7132 the Policy and Institutional F Post Open 10,000.00 11,327.50 Signed 2019-03-20 2019-04-18 2019-05-08 2019-07-10 2019-05-29 2019-07-22 2019-07-03 2019-07-02 2019-12-30 ant Selection n de messages. ramework 03/STP/COMP2/C/WACA/201 9 / Réalisation du diagnostic Component 2: Strengthening Individual Consult de la situation du studio de t TF / A7132 the Policy and Institutional F Post Open 10,000.00 0.00 Canceled 2019-04-01 2019-09-26 2019-05-20 2019-06-10 2019-07-15 2020-01-11 ant Selection élévision pour la diffusion d'i ramework nformations météorologiques 22/C/AFAP/STAFF/2019 / Spé Component 4: National Coor cialiste en sauvegardes envir IDA / D2890 Post Direct Selection Direct 32,181.60 32,181.60 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-08 2020-04-20 dination onnemental et sociales 23/C/AFAP/STAFF/2019 / Assi Component 4: National Coor IDA / D2890 Post Direct Selection Direct 32,181.60 32,181.60 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-07 2020-04-20 stente de operações dination 24/C/AFAP/STAFF/2019 / Spé Component 4: National Coor IDA / D2890 Prior Direct Selection Direct 33,000.00 33,000.00 Signed 2019-08-09 2019-09-19 2019-08-19 2019-09-25 2019-10-23 2019-01-07 2020-04-20 cialiste en passation de marc dination hés 25/C/AFAP/STAFF/2019 / Ges Component 4: National Coor IDA / D2890 Post Direct Selection Direct 33,000.00 33,000.00 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-07 2020-04-20 tor financeiro adjunto dination 08/STP/COMP3/C/WACA/201 Component 3: Strengthening Individual Consult 9 / Soutien à la mise en œuvr TF / A7132 National Physical and Social Post Open 10,000.00 0.00 Canceled 2020-02-10 2020-03-30 2020-04-20 2020-05-25 2020-11-21 ant Selection e de solutions végétatives Investments 28/STP/COMP4/C/WACA/201 Component 4: National Coor Under Implement 9 / Auditoria as contas do an IDA / D2890 Post Direct Selection Direct 17,440.00 0.00 2019-12-20 2019-12-19 2019-12-30 2019-12-23 2020-03-04 2020-08-31 dination ation o de 2018 do Projecto WACA . 30/STP/COMP3/C/WACA/201 Component 3: Strengthening Individual Consult 9 / Levantamento topográfico IDA / D2890 National Physical and Social Post Limited 2,600.00 2,600.00 Signed 2019-12-30 2020-01-13 2020-01-04 2020-03-06 2020-01-25 2020-03-11 2020-02-29 2020-03-15 2020-08-27 ant Selection da zona de expansão segura Investments de Micoló 36/STP/COMP3/C/WACA/202 Component 3: Strengthening Individual Consult 0 / Desenhos técnicos das ca IDA / D2890 National Physical and Social Post Limited 10,000.00 13,200.00 Signed 2020-03-20 2020-04-06 2020-03-25 2020-05-04 2020-04-15 2020-06-26 2020-05-20 2020-07-03 2020-11-16 ant Selection sas e infraestruturas sociais Investments 35/STP/COMP3/C/WACA/202 Component 3: Strengthening 0 / Estudos técnicos de orden IDA / D2890 National Physical and Social Post Direct Selection Direct 140,000.00 137,960.00 Signed 2020-03-20 2020-04-06 2020-03-30 2020-04-13 2020-06-03 2020-04-27 2020-11-30 amento urbanístico em Iô Gr Investments ande, Micoló e Praia Abade 31/STP/COMP4/C/WACA/202 Component 4: National Coor IDA / D2890 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-03-23 2019-12-30 2020-04-02 2020-01-02 2020-06-06 2020-01-08 2020-12-03 0 / Assistente de Direcção dination 40/STP/COMP2/C/WACA/202 Component 2: Strengthening 0 / Diagnostic des réglement Individual Consult IDA / D2890 the Policy and Institutional F Post Open 30,000.00 88,108.10 Signed 2020-04-16 2020-04-17 2020-06-04 2021-05-05 2020-06-25 2021-06-22 2020-07-30 2021-07-01 2021-01-26 ations et des cadres politique ant Selection ramework s côtières, et les textes d'app lication. 41/STP/COMP2/C/WACA/202 Component 2: Strengthening 0 / Appui aux réformes législ Individual Consult IDA / D2890 the Policy and Institutional F Prior Open 10,000.00 8,740.00 Signed 2020-04-20 2020-07-07 2020-06-08 2021-01-27 2020-06-29 2021-02-11 2020-08-03 2021-02-15 2021-01-30 atives visant à promouvoir la ant Selection ramework sécurité maritime (actualisati on du decret) 43/STP/COMP2/C/WACA/202 0 / Appui à la préparation des Component 2: Strengthening bulletins météorologiques et Individual Consult IDA / D2890 the Policy and Institutional F Post Open 30,000.00 0.00 Canceled 2020-09-08 2020-10-27 2020-11-17 2020-12-22 2021-06-20 formation des cadres techniq ant Selection ramework ues de INM dans la préparati on de prévisions météorologi ques. 42/STP/COMP2/C/WACA/202 0 / Assistance technique pour Component 2: Strengthening Individual Consult un système de partage d'info IDA / D2890 the Policy and Institutional F Post Open 30,000.00 0.00 Canceled 2020-09-01 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection rmations climatolgiques (à co ramework mbiner avec le studio COROB OR) 49/STP/COMP2/C/WACA/202 0 / Recrutement du juriste na Component 2: Strengthening Individual Consult tional pour l’analyse du cadr TF / A7132 the Policy and Institutional F Post Limited 15,000.00 9,500.00 Signed 2021-05-14 2021-05-14 2021-05-19 2021-06-28 2021-06-09 2021-07-06 2021-07-14 2021-07-09 2022-01-10 ant Selection e legal et institutionnel pour l ramework a gestion des zones côtières 50/STP/COMP2/C/WACA/202 Component 2: Strengthening Individual Consult 0 / Elaboração da Lei de gest TF / A7132 the Policy and Institutional F Post Open 60,000.00 55,700.00 Signed 2021-05-17 2021-05-17 2021-07-05 2021-07-26 2021-07-26 2021-08-16 2021-08-30 2021-08-14 2022-02-26 ant Selection ão de riscos e catástrofes ramework 64/STP/COMP2/C/WACA/202 Component 2: Strengthening 1 / Recrutement du juriste na Individual Consult TF / A7132 the Policy and Institutional F Post Limited 15,000.00 7,500.00 Signed 2021-05-26 2021-05-27 2021-05-31 2021-06-11 2021-06-21 2021-08-16 2021-07-26 2021-08-18 2022-01-22 tional pour l’appui a l' elabor ant Selection ramework ation de loi de gestion des ris ques et catastrophes 67/STP/COMP4/C/WACA/202 Component 4: National Coor Individual Consult IDA / D2890 Post Limited 20,000.00 29,750.00 Signed 2021-07-14 2021-07-15 2021-07-19 2021-10-14 2021-08-09 2021-11-03 2021-09-13 2021-11-18 2022-03-12 1 / Revisão a meio percurso dination ant Selection do projecto 66/STP/COMP3/C/WACA/202 Component 3: Strengthening 1 / Supervision des constructi Individual Consult IDA / D2890 National Physical and Social Post Limited 15,000.00 17,050.00 Signed 2021-08-09 2021-07-15 2021-08-14 2021-08-09 2021-09-04 2021-09-13 2021-10-09 2021-08-28 2022-04-07 on des infrastructures sociau ant Selection Investments x à Santa Catarina et Malanz a 68/STP/COMP4/C/WACA/202 Component 4: National Coor Individual Consult IDA / D2890 Post Limited 10,000.00 0.00 Canceled 2021-07-21 2021-07-26 2021-08-16 2021-09-20 2022-03-19 1 / Revisão a meio percurso dination ant Selection 69/STP/COMP2/C/WACA/202 Component 2: Strengthening 1 / Elaboração dos regulame Individual Consult IDA / D2890 the Policy and Institutional F Post Open 30,000.00 15,960.00 Signed 2021-08-30 2021-10-06 2021-10-18 2022-03-16 2021-11-08 2022-05-11 2021-12-13 2022-05-16 2022-06-11 ntos da lei de exploração e e ant Selection ramework xtração de inertes Page 4 55/STP/COMP2/C/WACA/202 1 / Recrutamento de um cons Component 2: Strengthening Individual Consult ultor para ministrar Formaçã TF / B4205 the Policy and Institutional F Post Open 20,000.00 11,835.60 Signed 2021-09-06 2021-09-14 2021-10-25 2021-12-28 2021-11-15 2021-12-29 2021-12-20 2022-01-01 2022-06-18 ant Selection o para Observatório ambient ramework al sobre plataforma DR clima 70/STP/COMP4/C/WACA/STA Component 4: National Coor Individual Consult FF/2021 / Contratação de en IDA / D2890 Post Open 21,600.00 18,000.00 Signed 2021-12-13 2021-12-13 2022-01-31 2022-01-31 2022-02-21 2022-02-21 2022-03-28 2022-02-24 2022-09-24 dination ant Selection genheiro civil 62/STP/COMP4/C/STAFF/WAC Component 4: National Coor Individual Consult IDA / D2890 Post Limited 6,000.00 6,000.00 Signed 2022-01-13 2022-01-18 2022-01-18 2022-01-20 2022-02-08 2022-03-07 2022-03-15 2022-03-10 2022-09-11 A/2022 / Condutor/Animador dination ant Selection para UGT 61/STP/COMP2/C/WACA/202 Component 2: Strengthening 1 / Recrutement d'un expert i Individual Consult TF / A7132 the Policy and Institutional F Post Open 120,000.00 0.00 Canceled 2021-05-19 2022-01-18 2021-07-07 2021-07-28 2021-09-01 2022-02-28 nternational pour l'élaboratio ant Selection ramework n du plan spatial maritime. 84/STP/C/WACA/2022 / Avali Component 3: Strengthening ação ambiental e social simpl Individual Consult TF / A7132 National Physical and Social Post Limited 5,000.00 5,000.00 Signed 2022-05-26 2022-05-24 2022-05-31 2022-06-09 2022-06-21 2022-06-28 2022-07-26 2022-07-01 2023-01-22 ificada para as obras da Pont ant Selection Investments e pedonal de Morro Peixe à P raia Guegue 87/STP/COMP2/C/WACA/202 Component 2: Strengthening Individual Consult 2 / Contratação de um inform TF / A7132 the Policy and Institutional F Post Limited 2,800.00 0.00 Signed 2022-06-30 2022-07-15 2022-07-05 2022-07-25 2022-07-26 2022-12-14 2022-08-30 2022-12-23 2023-02-26 ant Selection ático a part time ramework 80/STP/COMP4/C/STAFF/WAC Component 4: National Coor IDA / D2890 Post Direct Selection Direct 59,185.50 59,185.50 Signed 2022-07-04 2022-07-18 2022-07-14 2022-08-03 2022-09-17 2022-09-04 2023-03-16 A/2022 / Coordenador técnic dination o da UGP 90/STP/COMP4/C/STAFF/AFA Component 4: National Coor IDA / D2890 Prior Direct Selection Direct 38,295.36 0.00 Signed 2022-07-01 2022-07-19 2022-07-11 2022-02-18 2022-09-14 2022-02-25 2023-03-13 P/2022 / Afap's Procurement dination expert 89/STP/COMP4/C/STAFF/AFA Component 4: National Coor IDA / D2890 Post Direct Selection Direct 38,295.36 38,295.36 Signed 2022-07-01 2022-07-15 2022-07-11 2022-01-05 2022-09-14 2022-01-04 2023-03-13 P/2022 / Gestor financeiro ad dination junto da AFAP 81/STP/COMP4/C/STAFF/WAC A/2022 / Especialista em Salv Component 4: National Coor IDA / D2890 Post Direct Selection Direct 32,283.00 0.00 Signed 2022-07-04 2022-07-15 2022-07-14 2022-08-03 2022-09-17 2022-08-30 2023-03-16 aguarda Social e Desenvolvi dination mento Institucional do WACA 77/STP/COMP2/C/WACA/202 Component 2: Strengthening Individual Consult TF / B4205 Post Open - National 35,000.00 0.00 Signed 2022-10-07 2022-10-31 2022-11-25 2023-04-17 2022-12-16 2023-04-17 2023-01-20 2023-04-23 2023-07-19 2 / Development of the INM the Policy and Institutional F ant Selection Web site ramework 95/STP/COMP4/C/WACA/202 Component 4: National Coor Direct - Internation Under Implement 3 / Auditoria financeira de 20 IDA / D2890 Post Direct Selection 9,634.00 0.00 2023-07-17 2023-08-02 2023-07-27 2023-08-11 2023-09-30 2024-03-28 dination al ation 22, 2023 e 2024 Page 5