Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by <mention name of PIU> 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under July 9, 2010 other methods July 9, 2010 PROCUREMENT Sao Tome and Principe : STP Power Sector Recovery Project PLAN General Information Country: Sao Tome and Principe 2016-07-21 Bank’s Approval Date of the Original Procurement Plan: 2023-09-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157096 GPN Date: 2016-09-29 Project Name: STP Power Sector Recovery Project Loan / Credit No: IDA / V0030, IDA / D1260, IDA / D5870 Project Fiduciary and Administrative Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 03/W/PSR/2016 / Reabilitatio Investing in enhanced reliabi n and expansion of access ro lity of electricity generation, Single Stage - One E 2018-03-0 IDA / D1260 Post Request for Bids Open - National 0.00 Canceled 2017-05-16 2017-05-21 2017-07-02 2017-08-01 2017-09-05 ads in Ponta Figo to the wate transmission and distributio nvelope 4 r channels and load chamber n 19/W/PSR/2016 / Rehabilitati Project Implementation Sup Request for Quota Single Stage - One E 2017-10-2 IDA / D1260 Post Limited 61,655.34 Signed 2017-02-28 2017-01-03 2017-04-25 2017-01-14 on of a new AFAP's office port tions nvelope 2 32/W/PSR/2018 / Obstacle cl Strengthening operational p Request for Quota Single Stage - One E 2018-11-1 IDA / D1260 Post Open - National 430,602.88 Signed 2018-03-27 2018-05-22 2018-09-08 earance in the canal access erformance and governance tions nvelope 8 to Contador of EMAE 01/W/PSR/2016 / Rehabilitati Investing in enhanced reliabi Open - Internationa Single Stage - One E 2021-01-1 on and expansion of the Cont IDA / D1260 lity of electricity generation, Prior Request for Bids 0.00 Canceled 2018-12-21 2018-12-10 2019-03-08 2019-06-12 2019-03-08 2018-12-26 2018-12-12 2019-05-17 2019-06-16 2019-07-21 l nvelope 1 ador Hydropwer Plant and ac transmission and distributio cess road n 71/W/PSR/2020 / Rehabilitati Investing in enhanced reliabi Request for Propo Open - Internationa Single Stage - One E 2021-11-2 on and expansion of the Cont IDA / D5870 lity of electricity generation, Prior 0.00 Canceled 2021-02-05 2021-02-10 2021-03-24 2021-04-23 2021-05-28 sals l nvelope 4 ador Hydropwer Plant and ac transmission and distributio cess road n 76/W/PRSE/2021 / Design, S Investing in enhanced reliabi upply and Installation of the lity of electricity generation, Open - Internationa Single Stage - One E Under Imple 2022-02-0 Electromechanical Equipmen IDA / D5870 Prior Request for Bids 0.00 2021-04-19 2022-01-20 2021-04-24 2022-01-28 2021-06-05 2022-05-27 2021-07-05 2022-10-18 2021-08-09 transmission and distributio l nvelope mentation 5 t for the Rehabilitation and E n xtension of the Contador HPP 77/W/PRSE/2021 / CIVIL WO Investing in enhanced reliabi RKS FOR THE REHABILITATIO lity of electricity generation, Request for Propo Open - Internationa Single Stage - Two E 2022-04-1 IDA / D5870 Prior 0.00 Canceled 2021-05-17 2022-02-08 2021-05-22 2022-02-14 2021-07-03 2022-07-15 2021-09-15 2023-01-13 2021-10-20 N AND EXTENSION OF THE C transmission and distributio sals l nvelope 8 ONTADOR HYDROPOWER PL n ANT (HPP) National Proc Investing in enhanced reliabi 86/W/PRSE/2021 / Reabilitaç urement Doc lity of electricity generation, Single Stage - One E 2022-07-1 ão do Armazém da EMAE par IDA / D5870 Post Request for Bids Open - National ument - 1 En 135,040.64 Signed 2021-09-27 2021-11-18 2021-10-02 2021-11-13 2022-01-28 2021-12-13 2022-04-18 2022-01-17 2022-06-06 transmission and distributio nvelope 6 a Lâmpadas LED velope proce n ss (Non Bank -SPD) National Proc 97/W/PRSE/2022 / Remoção Investing in enhanced reliabi urement Doc de derrocadas e reparação d lity of electricity generation, Request for Quota Single Stage - One E ument - 1 En 2022-11-2 IDA / D1260 Post Limited 101,160.05 Signed 2022-03-30 2022-03-16 2022-05-25 2022-05-25 e uma ponte existente na pis transmission and distributio tions nvelope velope proce 1 ta de acesso ao complexo hi n ss (Non Bank droeléctrico contador. -SPD) National Proc 102/W/PRSE/2022 / Obras de urement Doc Support to institutional refor Request for Quota Single Stage - One E 2023-01-1 reabilitação nas instalações d IDA / D1260 Post Limited ument - 1 En 82,092.23 Signed 2022-05-25 2022-06-20 2022-07-20 2022-09-14 m and sector planning tions nvelope 6 a AGER velope proce ss (Non Bank -SPD) 04/W/PSR/2016 / Rehabilitati Investing in enhanced reliabi Open - Internationa Single Stage - One E 2022-10-0 on of key components of Con IDA / D1260 lity of electricity generation, Post Request for Bids 0.00 Canceled 2021-12-15 2021-12-20 2022-01-31 2022-03-02 2022-04-06 l nvelope 3 tador transmission line and e transmission and distributio quipment n National Proc 106/W/PRSE/2022 / Construç urement Doc Project Implementation Sup Request for Quota Single Stage - One E 2023-05-0 ão/Reabilitação do edifício pa IDA / D1260 Post Limited ument - 1 En 0.00 Canceled 2022-09-14 2022-11-09 port tions nvelope 8 ra TIU do PRSE velope proce ss (Non Bank -SPD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/S/PSR/2016 / Purchase an Strengthening operational p Open - Internationa Single Stage - One E d installation of 3000 power IDA / D1260 erformance and governance Prior Request for Bids 0.00 Canceled 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 l nvelope meters for large customers of EMAE 04/S/PSR/2016 / Purchase an Strengthening operational p d installation of 2000 3-phas Open - Internationa Single Stage - One E IDA / D1260 erformance and governance Prior Request for Bids 0.00 Canceled 2018-03-18 2018-03-23 2018-05-04 2018-06-03 2018-07-08 2019-01-04 e power meters for large cust l nvelope of EMAE omers and 16000 single phas e power meters 01/G/PSR/2016 / Purchase of Investing in enhanced reliabi Request for Quota Single Stage - One E Under Imple three double cabin 4WD pick IDA / D1260 lity of electricity generation, Post Limited 0.00 2016-11-10 2017-02-02 2017-01-30 2017-07-29 tions nvelope mentation ups transmission and distributio n 23/G/PSR/2016 / Purchase of Project Implementation Sup Request for Quota Single Stage - One E Pending Impl IDA / D1260 Post Open - National 0.00 2017-02-28 2017-04-25 2017-10-22 fourniture for the new AFAP's port tions nvelope ementation office 03/S/PSR/2016 / Purchase an Strengthening operational p Open - Internationa Single Stage - One E IDA / D1260 Post Request for Bids 0.00 Canceled 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 d installation of 170 statistica erformance and governance l nvelope l meters of EMAE 70/G/PRSE/2020 / Supply of Investing in enhanced reliabi Open - Internationa Single Stage - One E Under Imple Two hundred forty six thousa IDA / D5870 lity of electricity generation, Post Request for Bids 0.00 2020-06-01 2020-07-20 2020-06-06 2020-07-20 2020-07-18 2020-09-18 2020-08-17 2020-11-13 2020-09-21 2021-03-20 l nvelope mentation nd five hundred (246,500) LE transmission and distributio D lamps n 92/G/PRSE/2021 / Supply of f Strengthening operational p Single Stage - One E Under Imple IDA / D5870 Post Request for Bids Open - National 0.00 2021-11-12 2021-10-20 2021-11-17 2021-12-29 2022-01-28 2022-03-04 2022-08-31 our lamp crushers erformance and governance nvelope mentation of EMAE 93/G/PRSE/2021 / Aquisição Strengthening operational p Request for Quota Single Stage - One E Under Imple de Materiais para a Campanh IDA / D5870 erformance and governance Post Open - National 0.00 2022-01-12 2023-03-07 2022-03-09 2022-09-05 tions nvelope mentation a de Comunicação do Consu of EMAE midor Page 1 104/G/PRSE/2022 / Aquisiçã o de equipamentos elétricos Strengthening operational p Single Stage - One E Under Imple de medição, ferramentas e d IDA / D1260 erformance and governance Post Request for Bids Open - National 0.00 2022-05-02 2023-02-01 2022-05-07 2023-02-02 2022-06-18 2023-03-24 2022-07-18 2022-08-22 2023-02-18 nvelope mentation e proteção elétrica para Gabi of EMAE nete Perda e Projecto LED 100/G/PRSE/2022 / Aquisiçã o de equipamentos informáti Support to institutional refor Request for Quota Single Stage - One E cos para AGER, Gabinete de IDA / D1260 Post Limited 0.00 Signed 2022-05-30 2022-07-28 2022-07-25 2023-04-12 2023-01-21 m and sector planning tions nvelope Perdas, equipa do Projecto L EDS e equipa da UTI e vídeo conferencia para AGER 103/G/PRSE/2022 / Aquisiçã Strengthening operational p o de duas viaturas 4X4 para t Request for Quota Single Stage - One E Under Imple IDA / D1260 erformance and governance Post Open - National 0.00 2022-06-04 2022-09-09 2022-07-30 2023-01-26 ransporte de pessoal Gabinet tions nvelope mentation of EMAE e de Perdas, Projecto LEDs 99/G/PRSE/2022 / Aquisição Investing in enhanced reliabi de peças e acessórios para g IDA / D1260 lity of electricity generation, Post Direct Selection Direct 669,115.65 Signed 2022-05-20 2022-02-25 2022-05-25 2022-08-22 2022-06-29 2022-09-18 2022-12-26 eradores ABC da EMA transmission and distributio n 101/G/PRSE/2022 / Equipam Support to institutional refor Request for Quota Single Stage - One E IDA / D1260 Post Limited 0.00 Signed 2022-05-28 2022-09-09 2022-07-23 2023-04-12 2023-01-19 entos de escritórios para AGE m and sector planning tions nvelope R 105/G/PRSE/2022 / Aquisiçã Strengthening operational p Request for Quota Single Stage - One E o de materiais de escritórios IDA / D1260 erformance and governance Post Limited 0.00 Canceled 2022-04-27 2022-06-22 2022-12-19 tions nvelope Gabinete Perda- Projecto LED of EMAE s 38/G/2018 / Purchase and in Investing in enhanced reliabi Open - Internationa Single Stage - One E stallation of turbines at the C IDA / D1260 lity of electricity generation, Prior Request for Bids 0.00 Canceled 2021-03-12 2021-03-17 2021-04-28 2021-05-28 2021-07-02 2021-12-29 l nvelope ontador Plant transmission and distributio n 65/G/PSR/2020 / Supply, Inst Investing in enhanced reliabi allation, Commissioning and lity of electricity generation, Open - Internationa Single Stage - One E Testing of Fuel Monitoring Sy IDA / D1260 Post Request for Bids 0.00 Canceled 2020-03-10 2020-03-16 2020-03-15 2020-04-26 2020-05-26 2020-06-15 2020-10-21 transmission and distributio l nvelope stem For The EMAE’s Diesel n Thermal Generation Plants 111/G/PRSE/2022 / Aquisiçã Strengthening operational p Request for Quota Single Stage - One E Under Imple o de prateleiras para os Arm IDA / D5870 erformance and governance Post Limited 0.00 2022-12-28 2023-02-17 2023-02-22 2023-08-21 tions nvelope mentation azéns de lâmpadas Led da E of EMAE MAE 122/G/PRSE/2023 / Fornecim Investing in enhanced reliabi ento de Materiais elétricos p lity of electricity generation, Single Stage - One E Pending Impl ara Reabilitar e Regularizar IDA / D5870 Post Request for Bids Open - National 0.00 2023-10-05 2023-10-10 2023-11-21 2023-12-21 2024-01-25 2024-07-23 transmission and distributio nvelope ementation as Redes Elétricas de Santa n Margarida Agostinho Neto e Boa Entrada 123/G/PRSE/2023 / Aquisiçã Investing in enhanced reliabi o de 2 Mil contadores pré-pa lity of electricity generation, Direct - Internation Pending Impl gos monofásicos "Split" seus IDA / D5870 Post Direct Selection 0.00 2023-09-22 2023-09-27 2023-11-01 2024-04-29 transmission and distributio al ementation acessórios e software de ges n tão a distancia dos consumos elétricos NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 05/S/PSR/2016 / Update of t Project Implementation Sup Under Imple IDA / D1260 Post Direct Selection Direct 0.00 2016-11-18 2016-11-23 2016-12-28 2017-06-26 he AFAP's existing managem port mentation ent software 10/S/PSR/2016 / Technical a Project Implementation Sup Request for Quota Single Stage - One E Pending Impl ssistance for designer and su IDA / D1260 Post Open - National 0.00 2017-02-28 2017-04-25 2017-10-22 port tions nvelope ementation pervision of the new AFAP's o ffice Investing in enhanced reliabi 34/S/PSR/2018 / Topographi Single Stage - One E Under Imple IDA / D1260 lity of electricity generation, Post Request for Bids Limited 0.00 2018-03-26 2018-02-21 2018-03-31 2018-01-16 2018-05-12 2018-06-11 2018-07-16 2019-01-12 c surveying study nvelope mentation transmission and distributio n 35/S/PSR/2018 / Apoio a real Investing in enhanced reliabi ização do levantamento topo IDA / D1260 lity of electricity generation, Post Direct Selection Direct 17,092.54 Signed 2018-08-27 2019-03-18 2018-09-01 2019-03-18 2018-10-06 2019-04-03 2019-04-04 gráfico transmission and distributio n 01/S/PSR/2016 / Acquisition, Strengthening operational p installation and configuration Open - Internationa Single Stage - One E IDA / D1260 erformance and governance Post Request for Bids 0.00 Canceled 2021-06-18 2021-06-23 2021-08-04 2021-09-03 2021-10-08 2022-04-06 of the management Informati l nvelope of EMAE on System in EMAE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/C/EPPF/16 / Feasibility st Investing in enhanced reliabi Quality And Cost- Open - Internationa udy for the rehabilitation of t IDA / V0030 lity of electricity generation, Prior 1,250,769.12 Signed 2016-07-21 2016-07-27 2016-07-21 2016-09-09 2016-10-26 2016-10-07 2017-02-01 2016-11-06 2017-03-06 2016-12-11 2017-07-07 2017-01-15 2017-07-16 2018-01-15 Based Selection l he Contador Hydro Power Pla transmission and distributio nt n 03/C/EPPF/16 / Technical Ass Investing in enhanced reliabi Consultant Qualifi Open - Internationa istance to elaborate the Envir IDA / V0030 lity of electricity generation, Prior 212,935.00 Signed 2016-10-07 2017-01-30 2016-10-28 2017-04-12 2016-12-11 2017-06-15 2017-01-10 2017-07-06 2017-02-14 2017-10-18 2017-08-13 cation Selection l onmental impact Study transmission and distributio n 01/C/PSR/2016 / Project audi IDA / D1260 Project Implementation Sup Post Least Cost Selecti Open - Internationa 41,160.00 Signed 2016-11-24 2016-09-28 2016-12-15 2017-01-28 2016-11-08 2017-02-25 2016-12-19 2017-03-27 2017-01-19 2017-05-01 2017-02-19 2017-06-05 2017-03-24 2017-12-02 t port on l 02/C/PSR/2016 / Developme nt of integrated Least Cost P Support to institutional refor Quality And Cost- Open - Internationa IDA / D1260 Prior 190,957.50 Completed 2017-01-27 2017-04-12 2017-02-17 2017-05-02 2017-04-02 2017-07-27 2017-04-30 2017-09-15 2017-05-30 2017-10-13 2017-07-04 2018-01-11 2017-08-08 2018-01-03 2018-08-08 2018-10-28 ower Development Plan for S m and sector planning Based Selection l ao Tome and Principe 03/C/PSR/2016 / Project plan Investing in enhanced reliabi ning and work supervision for lity of electricity generation, Consultant Qualifi IDA / D1260 Post Open - National 0.00 Canceled 2017-01-08 2017-01-29 2017-03-14 2017-04-13 2017-05-18 2017-11-14 rehabilitation work of access transmission and distributio cation Selection roads to Contador facility n Strengthening operational p Consultant Qualifi Open - Internationa 08/C/PSR/2016 / Tariff Study IDA / D1260 Prior 0.00 Canceled 2017-12-07 2017-12-28 2018-02-10 2018-03-12 2018-04-16 2018-10-13 erformance and governance cation Selection l of EMAE Page 2 09/C/PSR/2016 / Technical A Investing in enhanced reliabi Quality And Cost- Open - Internationa ssistance to prepare the net IDA / D1260 lity of electricity generation, Prior 0.00 Canceled 2018-02-01 2017-07-06 2018-02-22 2018-04-07 2018-05-05 2018-06-04 2018-07-09 2018-08-13 2019-08-13 Based Selection l work protection transmission and distributio n 04/C/PSR/2017 / Technical A ssistance to modernize and h Support to institutional refor Quality And Cost- Open - Internationa IDA / D1260 Post 283,345.90 Signed 2017-10-11 2017-07-06 2017-10-12 2017-10-30 2017-10-04 2017-11-27 2017-12-27 2018-01-26 2018-01-31 2018-02-23 2018-03-07 2018-04-14 2019-03-07 armonize legal and regulator m and sector planning Based Selection l y framework of the energy se ctor 04/C/PSR/2016 / Technical A ssistance to modernize and h Support to institutional refor Quality And Cost- Open - Internationa IDA / D1260 Prior 0.00 Canceled 2017-02-06 2017-07-06 2017-02-27 2017-08-07 2017-04-12 2017-05-10 2017-06-09 2017-07-14 2017-08-18 2018-08-18 armonize legal and regulator m and sector planning Based Selection l y framework of the energy se ctor 06/C/PSR/2016 / Consultatio Strengthening operational p Quality And Cost- n and communication Strate IDA / D1260 erformance and governance Prior Open - National 0.00 Canceled 2017-09-28 2017-10-19 2017-12-02 2017-12-30 2018-01-29 2018-03-05 2018-04-09 2019-04-09 Based Selection gy to end users of EMAE 05/C/PSR/2016 / Preparation Strengthening operational p Quality And Cost- Open - Internationa of management Improvemen IDA / D1260 erformance and governance Prior 0.00 Canceled 2017-06-15 2017-07-06 2017-08-19 2017-09-16 2017-10-16 2017-11-20 2017-12-25 2018-12-25 Based Selection l t Plan for EMAE of EMAE 33/C/PSR/2018 / Inventory of Strengthening operational p Consultant Qualifi IDA / D1260 Post Open - National 291,900.00 Signed 2018-03-01 2018-05-03 2018-03-22 2018-07-18 2018-05-05 2018-08-24 2018-06-04 2018-12-07 2018-07-09 2018-12-10 2019-01-05 EMAE's Assets erformance and governance cation Selection of EMAE 30/C/PSR/2018 / Consultatio Strengthening operational p Consultant Qualifi n and Comunication Startegy IDA / D1260 erformance and governance Post Open - National 239,213.72 Signed 2018-02-23 2017-10-27 2018-03-16 2018-04-29 2018-01-08 2018-05-29 2018-04-03 2018-07-03 2018-04-08 2018-12-30 cation Selection to end users of EMAE 41/C/PRS/2019 / Recruitmen Strengthening operational p t of a Human resource consul Consultant Qualifi Open - Internationa IDA / D1260 erformance and governance Post 162,491.19 Signed 2019-08-18 2019-07-16 2019-09-08 2019-07-31 2019-10-22 2019-10-09 2019-11-21 2019-11-27 2019-12-26 2019-12-01 2020-06-23 tant to support the selection cation Selection l of EMAE of EMAE Top Level Executive Officers 60/C/PSR/2019 / Project Audi Project Implementation Sup Least Cost Selecti Open - Internationa Under Implement IDA / D1260 Post 0.00 2019-11-25 2019-12-10 2019-12-16 2020-01-29 2020-02-26 2020-03-27 2020-05-01 2020-06-05 2020-12-02 t for the years 2019/2021 port on l ation 75/C/PRSE/2020 / Facilitatin Support to institutional refor Consultant Qualifi Open - Internationa g the Selection of an Expert f IDA / D5870 Post 0.00 Canceled 2021-03-15 2021-04-16 2021-04-05 2021-05-19 2021-06-18 2021-07-23 2022-01-19 m and sector planning cation Selection l or Pre-shipment Inspection of LED Lamps 67/C/PRSE/2020 / T.A. for E Investing in enhanced reliabi Consultant Qualifi MAE on the Preparation of A IDA / D1260 lity of electricity generation, Post Open - National 0.00 Canceled 2020-04-30 2020-05-21 2020-07-04 2020-08-03 2020-09-07 2021-03-06 cation Selection wareness Campaign for LED transmission and distributio Bulb Deployment n 98/C/PRSE/2022 / Strengthe Support to institutional refor Quality And Cost- Open - Internationa ning the institutional capaciti IDA / D1260 Post 0.00 Signed 2022-04-07 2022-04-27 2022-04-28 2022-05-04 2022-06-11 2022-08-31 2022-07-09 2022-10-14 2022-08-08 2022-10-21 2022-09-12 2022-10-28 2022-10-17 2023-01-31 2023-10-17 m and sector planning Based Selection l es of the General Regulatory Authority (AGER) 104/C/PRSE/2022 / Waste m Investing in enhanced reliabi Quality And Cost- Open - Internationa anagement plan of used lam IDA / D1260 lity of electricity generation, Post 0.00 Signed 2022-06-30 2022-06-15 2022-07-21 2022-06-27 2022-09-03 2022-09-15 2022-10-01 2022-11-11 2022-10-31 2022-11-29 2022-12-05 2023-03-06 2023-01-09 2023-02-12 2024-01-09 Based Selection l ps transmission and distributio n 110/C/PRSE/2022 / OWNER’S Investing in enhanced reliabi ENGINEER FOR THE DESIGN lity of electricity generation, Quality And Cost- Open - Internationa IDA / D1260 Post 0.00 Signed 2022-09-09 2022-09-12 2022-09-30 2022-09-12 2022-11-13 2022-10-17 2022-12-11 2022-11-25 2023-01-10 2022-12-06 2023-02-14 2023-03-06 2023-03-21 2024-03-20 AND SUPERVISION FOR THE transmission and distributio Based Selection l CONSTRUCTION OF A SOLAR n PARK IN SAO TOME 113/C/PRSE/2022 / Auditing Project Implementation Sup Least Cost Selecti Open - Internationa the projects managed by AFA IDA / D1260 Post 0.00 Signed 2022-12-29 2022-12-28 2023-01-19 2023-02-07 2023-03-04 2023-03-02 2023-04-01 2023-04-21 2023-05-01 2023-07-11 2023-06-05 2023-07-11 2023-07-10 2023-06-22 2024-01-06 port on l P for the period 2022, 2023 a nd 2024 115/C/PRSE/2023 / Environm Investing in enhanced reliabi ental and Social Impact Asse lity of electricity generation, Quality And Cost- Open - Internationa IDA / D1260 Post 0.00 Canceled 2023-03-23 2023-04-13 2023-05-27 2023-06-24 2023-07-24 2023-08-28 2023-10-02 2024-10-01 ssment (ESIA) for Solar Park transmission and distributio Based Selection l Project and Access Expansio n n in the Sao tome INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 06/C/EPPF/16 / Technical ass istance to elaborate the oper Project Implementation Sup IDA / V0030 Prior Direct Selection Direct 0.00 Canceled 2016-08-17 2016-09-06 2016-08-27 2016-09-28 2016-09-21 2017-03-20 ating, administrative and fina port ncial procedure manuals 05/C/EPPF/16 / Upgrade of th Investing in enhanced reliabi Individual Consult e study on the water potenti IDA / V0030 lity of electricity generation, Post Limited 0.00 Canceled 2016-09-26 2016-10-01 2016-10-22 2016-11-26 2017-05-25 ant Selection al of Sao Tome and Principe transmission and distributio n Investing in enhanced reliabi 25/C/PSR/2016 / Topographi Individual Consult IDA / D1260 lity of electricity generation, Post Limited 76,154.87 Signed 2017-02-28 2017-02-13 2017-03-05 2017-03-26 2017-07-10 2017-04-30 2017-07-28 2017-10-27 c surveying study ant Selection transmission and distributio n 26/C/PSR/2016 / Preparation Investing in enhanced reliabi Individual Consult of Geological surface mappin IDA / D1260 lity of electricity generation, Post Limited 32,706.01 Signed 2017-02-26 2017-02-13 2017-03-03 2017-03-24 2017-07-31 2017-04-28 2017-08-04 2017-10-25 ant Selection g transmission and distributio n 27/C/PSR/2016 / Assessment Investing in enhanced reliabi Individual Consult of the water resources availa IDA / D1260 lity of electricity generation, Post Limited 19,058.54 Signed 2017-02-27 2017-02-13 2017-03-04 2017-03-25 2017-05-26 2017-04-29 2017-05-30 2017-10-26 ant Selection ble for energy production at transmission and distributio Contador SHP n 12/C/PSR/2016 / Recruitmen Project Implementation Sup IDA / D1260 Post Direct Selection Direct 2,750.00 Signed 2016-11-30 2017-01-02 2016-12-10 2017-02-13 2017-01-07 2017-08-12 t of Financial manager port 18/C/PSR/2016 / Recruitmen Project Implementation Sup IDA / D1260 Post Direct Selection Direct 1,000.00 Signed 2016-11-30 2017-01-02 2016-12-10 2017-02-13 2017-01-07 2017-08-12 t of Administrative Assistant port 24/C/PSR/2016 / Preparation of TOR's for: Topographic sur Investing in enhanced reliabi veying, geological surface m lity of electricity generation, IDA / D1260 Post Direct Selection Direct 17,400.00 Signed 2016-12-16 2016-12-01 2016-12-26 2016-11-17 2017-03-01 2016-12-11 2017-08-28 apping and assessment of th transmission and distributio e watert resources available n for energy production at Con tador SHP 11/C/PSR/2016 / Recruitmen Project Implementation Sup IDA / D1260 Post Direct Selection Direct 0.00 Canceled 2016-11-30 2016-12-01 2016-12-10 2017-02-13 2017-08-12 t of AFAP Coordinator port Page 3 13/C/PSR/2016 / Recruitmen Project Implementation Sup IDA / D1260 Post Direct Selection Direct 3,206.50 Signed 2016-11-30 2016-12-30 2016-12-10 2017-02-13 2017-01-07 2017-08-12 t of Procurement port 16/C/PSR/2016 / Recruitmen Project Implementation Sup IDA / D1260 Post Direct Selection Direct 2,750.00 Signed 2016-11-30 2016-12-30 2016-12-10 2017-02-13 2017-01-07 2017-08-12 t of Accountant port 15/C/PSR/2016 / Recruitmen Project Implementation Sup Individual Consult t of Monitoring, environment IDA / D1260 Post Open 6,900.00 Signed 2017-02-28 2017-01-31 2017-04-18 2017-04-06 2017-05-09 2017-04-06 2017-06-13 2017-04-14 2017-12-10 port ant Selection al safeguards and indicators technician 07/C/PSR/2016 / Demand Fo Strengthening operational p Individual Consult IDA / D1260 Post Open 0.00 Canceled 2017-01-13 2017-02-01 2017-03-03 2017-03-24 2017-04-28 2017-10-25 recast Study erformance and governance ant Selection of EMAE 28/C/PSR/2017 / Recruitmen Project Implementation Sup Individual Consult IDA / D1260 Prior Direct 13,800.00 Signed 2017-03-22 2017-04-05 2017-04-01 2017-04-22 2017-07-27 2017-05-27 2018-03-14 2017-11-23 t of Procurement Assistant port ant Selection 10/C/PSR/2016 / Technical A Support to institutional refor Individual Consult ssistance to structure the PP IDA / D1260 Post Limited 0.00 Canceled 2018-01-24 2018-01-29 2018-02-19 2018-03-26 2018-09-22 m and sector planning ant Selection P strategy for AGER 09/C/PSR/2017 / Technical A Investing in enhanced reliabi Individual Consult ssistance to prepare the net IDA / D1260 lity of electricity generation, Post Open 74,000.00 Signed 2017-08-18 2017-06-15 2017-10-06 2017-12-27 2017-10-27 2018-03-02 2017-12-01 2018-03-07 2018-05-30 ant Selection work protection transmission and distributio n 14/C/PSR/2016 / Recruitmen Project Implementation Sup Individual Consult IDA / D1260 Post Open 2,320.00 Signed 2017-10-11 2015-05-04 2017-11-29 2017-12-20 2016-12-05 2018-01-24 2016-08-02 2018-07-23 t of Technical Advisor port ant Selection 14/C/PRS/2016 / Recruitmen Project Implementation Sup IDA / D1260 Post Direct Selection Direct 0.00 Canceled 2016-11-30 2015-04-05 2016-12-10 2017-02-13 2017-08-12 t of Technical Advisor port 29/C/PSR/2018 / Preparation Strengthening operational p Individual Consult of Management Improvemen IDA / D1260 erformance and governance Post Limited 34,100.00 Completed 2018-03-30 2018-03-08 2018-04-04 2018-03-14 2018-04-25 2018-05-15 2018-05-30 2018-06-12 2018-11-26 2018-12-19 ant Selection t Plan for EMAE of EMAE 31/C/PSR/2018 / Independen Support to institutional refor Individual Consult t legal opinion on the conces IDA / D1260 Post Limited 0.00 Canceled 2018-03-14 2018-03-19 2018-04-09 2018-05-14 2018-11-10 m and sector planning ant Selection sion of Catchment-basin 36/C/PSR/2018 / Supervision Investing in enhanced reliabi Individual Consult of Obstacle clearance in the IDA / D1260 lity of electricity generation, Post Limited 0.00 Canceled 2018-09-13 2018-09-18 2018-10-09 2018-11-13 2019-05-12 ant Selection canal access to Contador transmission and distributio n ST-AFAP-87635-CS-CDS / Alt Strengthening operational p ernatives for urgent solution IDA / D1260 erformance and governance Post Direct Selection Direct 76,000.00 Completed 2018-12-14 2018-12-11 2018-12-24 2019-01-16 2019-02-27 2019-02-26 2019-08-26 2019-06-19 of the power deficit in Sao To of EMAE me 39/C/PSR/16 / Technical assi stance to elaborate the oper Project Implementation Sup IDA / V0030 Post Direct Selection Direct 0.00 Canceled 2016-09-06 2016-09-05 2016-09-16 2016-11-20 2017-05-19 ating, administrative and fina port ncial procedure manuals 40/C/PSR/2019 / Consultanc Investing in enhanced reliabi y Service for Fuel Control and lity of electricity generation, Individual Consult IDA / D1260 Post Limited 32,760.00 Signed 2019-06-17 2019-06-03 2019-06-22 2019-08-12 2019-07-13 2019-10-10 2019-08-17 2019-10-15 2020-02-13 Monitoring Improvement Plan transmission and distributio ant Selection of EMAE's Diesel Thermal Ge n neration Plants 50/C/PRS/2019 / Temporary Project Implementation Sup IDA / D1260 Post Direct Selection Direct 0.00 Canceled 2019-10-04 2019-10-14 2019-12-18 2020-06-15 Procurement Assistant port 51/C/PRS/2019 / Accountant Project Implementation Sup IDA / D1260 Post Direct Selection Direct 0.00 Canceled 2019-10-08 2019-10-18 2019-12-22 2020-06-19 Assistant port 53/C/PRSE/2019 / Administra Project Implementation Sup IDA / D1260 Post Direct Selection Direct 0.00 Canceled 2019-10-08 2017-05-01 2019-10-18 2019-12-22 2020-06-19 tive Assistant of AFAP port 54/C/PRSE/2019 / Accountan IDA / D1260 Project Implementation Sup Post Direct Selection Direct 0.00 Canceled 2019-10-08 2019-10-18 2019-12-22 2020-06-19 t port 58/C/PSR/2018 / Recruitmen Project Implementation Sup Under Implement IDA / D1260 Prior Direct Selection Direct 0.00 2018-12-03 2018-12-13 2019-01-07 2020-01-07 t of a Procurement Officer port ation 56/C/PSR/2018 / Accountant IDA / D1260 Project Implementation Sup Post Direct Selection Direct 20,988.00 Signed 2018-12-03 2018-12-31 2018-12-13 2019-01-02 2019-01-07 2019-01-06 2019-02-12 port 50/C/PSRE/2019 / Temporary Project Implementation Sup Pending Impleme IDA / D1260 Post Direct Selection Direct 0.00 2018-06-03 2018-06-13 2018-07-14 2018-10-12 Procurement Assistant port ntation 59/C/PSR/2018 / Administrati Project Implementation Sup IDA / D1260 Post Direct Selection Direct 13,992.00 Signed 2018-12-03 2018-12-28 2018-12-13 2019-01-02 2019-01-07 2019-01-06 2020-01-07 ve Assistant of AFAP port 13/C/EPPF/2016 / Technical assistance to elaborate the o Project Implementation Sup Pending Impleme IDA / D1260 Post Direct Selection Direct 0.00 2016-07-05 2016-07-15 2016-08-19 2017-02-15 perating, administrative and port ntation financial procedure manuals 42/C/PRSE/2019 / T.A. FOR L Strengthening operational p Individual Consult ED BULB DEPLOYMENT PROG IDA / D1260 erformance and governance Post Open 0.00 Canceled 2019-11-07 2019-11-19 2019-12-26 2020-01-16 2020-02-20 2020-08-18 ant Selection RAMING SAO TOME AND PRIN of EMAE CIPE 61/C/PRSE/2019 / T.A. FOR L Strengthening operational p Individual Consult ED BULB DEPLOYMENT PROG IDA / D1260 erformance and governance Post Limited 63,040.00 Signed 2019-12-05 2019-12-02 2019-12-10 2019-12-19 2019-12-31 2020-01-14 2020-02-04 2020-01-17 2020-08-02 ant Selection RAMING SAO TOME AND PRIN of EMAE CIPE 63/C/PRS/2020 / Social safeg Project Implementation Sup Individual Consult IDA / D1260 Post Open 2,170.00 Signed 2020-03-02 2022-03-01 2020-04-20 2022-08-30 2020-05-11 2022-09-14 2020-06-15 2022-09-19 2020-12-12 uards port ant Selection 66/C/PRSE/2020 / Support to Strengthening operational p EMAE executives in the imple IDA / D1260 erformance and governance Post Direct Selection Direct 9,580.00 Signed 2020-03-02 2020-03-10 2020-03-12 2020-05-21 2020-05-16 2020-05-25 2020-11-12 mentation of MIP of EMAE 68/C/PRSE/2020 / T.A. on the Investing in enhanced reliabi Implementation of Network P IDA / D1260 lity of electricity generation, Post Direct Selection Direct 60,000.00 Signed 2020-03-23 2020-04-24 2020-04-02 2020-05-07 2020-06-06 2020-06-08 2020-12-03 rotection transmission and distributio n 64/C/PRS/2020 / Support to Project Implementation Sup IDA / D1260 Post Direct Selection Direct 0.00 Canceled 2020-03-23 2020-04-02 2020-06-06 2020-12-03 Safeguard department port Page 4 69/C/PSRP/2020 / Technical assistance to Updating the o Project Implementation Sup IDA / D1260 Post Direct Selection Direct 12,384.00 Signed 2020-03-20 2020-03-24 2020-03-30 2020-04-01 2020-06-03 2020-04-06 2020-11-30 perating, administrative and port financial procedure manuals with the AF 55/C/PSR/2018 / Recruitmen Project Implementation Sup IDA / D1260 Post Direct Selection Direct 114,734.40 Signed 2018-12-03 2018-12-20 2018-12-13 2019-01-02 2019-01-12 2019-01-07 2020-01-12 t of AFAP General Director port 74/C/PRSE/2021 / Consultant Investing in enhanced reliabi to develop and implement a lity of electricity generation, Individual Consult IDA / D5870 Prior Open 0.00 Canceled 2021-03-07 2021-05-20 2021-04-25 2021-05-16 2021-06-20 2021-12-17 Consumer Awareness and Co transmission and distributio ant Selection mmunication program for LE n D Program 73/C/PRSE/2021 / Expert in Monitoring and Evaluation (M Strengthening operational p Individual Consult &E) of Impacts of the LED BU IDA / D5870 erformance and governance Prior Open 0.00 Canceled 2021-04-26 2021-05-20 2021-06-14 2021-07-05 2021-08-09 2022-02-05 ant Selection LBS AND LED TUBELIGHTS D of EMAE EPLOYMENT PROGRAM IN SA O TOME AND PRINCIPE 79/C/PRSE/21 / T.A. TRANSA Support to institutional refor Individual Consult CTION ADVISOR TO ORGANIZ IDA / D5870 Post Open 0.00 Canceled 2021-04-12 2021-03-25 2021-05-31 2021-06-21 2021-07-26 2022-01-22 m and sector planning ant Selection E BIDDING PROCESS 80/C/PRSE/2021 / T.A. TRAN Support to institutional refor Individual Consult SACTION ADVISOR TO ORGA IDA / D5870 Post Limited 87,220.00 Signed 2021-04-19 2021-04-16 2021-04-24 2021-06-11 2021-05-15 2021-07-23 2021-06-19 2021-07-26 2021-12-16 m and sector planning ant Selection NIZE BIDDING PROCESS 81/C/PRSE/2021 / Assist EMA Strengthening operational p E with the Incorporation of a Individual Consult Under Implement IDA / D5870 erformance and governance Post Limited 0.00 2021-05-21 2021-06-09 2021-05-26 2021-06-16 2021-07-21 2022-01-17 n Information System for Ma ant Selection ation of EMAE nagement of Corporate Reso urces 82/C/PRSE/2021 / Facilitatin Support to institutional refor Individual Consult Under Implement g the Selection of an Expert f IDA / D5870 Post Limited 0.00 2021-06-27 2021-06-13 2021-07-02 2021-07-23 2021-08-27 2022-02-23 m and sector planning ant Selection ation or Pre-shipment Inspection of LED Lamps 84/C/PRSE/2021 / Procureme Project Implementation Sup Individual Consult IDA / D5870 Prior Limited 26,040.00 Signed 2021-08-23 2021-08-30 2021-08-28 2021-09-08 2021-09-18 2021-11-16 2021-10-23 2021-12-03 2022-04-21 nt Officer for AFAP port ant Selection 85/C/PRSE/2021 / Environme Project Implementation Sup Individual Consult Under Implement IDA / D5870 Post Open 0.00 2021-09-20 2022-02-15 2021-11-08 2023-01-03 2021-11-29 2023-01-12 2022-01-03 2022-07-02 ntal Safeguard port ant Selection ation 94/C/PRSE/2022 / RECRUITM Project Implementation Sup Individual Consult IDA / D1260 Prior Limited 136,000.00 Signed 2022-01-17 2022-01-18 2022-01-22 2022-01-18 2022-02-12 2022-04-20 2022-03-19 2022-05-06 2022-09-15 ENT OF SENIOR PROCUREME port ant Selection NT SPECIALIST 95/C/PRSE/2022 / Especialist a em Monitoramento e Avalia Strengthening operational p ção (M&E) de Impactos do Pr Individual Consult IDA / D5870 erformance and governance Post Open 0.00 Signed 2022-02-04 2022-02-18 2022-03-25 2022-08-26 2022-04-15 2022-10-19 2022-05-20 2023-04-09 2022-11-16 ograma de IMPLANTAÇÃO DE ant Selection of EMAE LÂMPADAS LED E LED TUBELI GHTS EM SÃO TOMÉ E PRINCI PE 96/C/PRSE/2022 / Consultor para desenvolver e impleme Strengthening operational p Individual Consult ntar um programa de Consci IDA / D5870 erformance and governance Post Open 0.00 Signed 2022-02-04 2022-02-17 2022-03-25 2022-08-28 2022-04-15 2022-10-19 2022-05-20 2023-04-09 2022-11-16 ant Selection entização e Comunicação do of EMAE Consumidor para o Programa LED 105/C/PRSE/2022 / Recruta Strengthening operational p Individual Consult Under Implement IDA / D1260 Post Open 0.00 2022-05-31 2022-06-13 2022-07-19 2022-09-07 2022-08-09 2022-09-28 2022-09-13 2023-03-12 mento de um Engenheiro Elé erformance and governance ant Selection ation trico of EMAE 107/C/PRSE/2022 / Recruta mento de um Consultor para Project Implementation Sup Individual Consult Under Implement IDA / D1260 Post Limited 0.00 2022-08-26 2022-08-25 2022-08-31 2022-09-08 2022-09-21 2022-11-08 2022-10-26 2023-04-24 elaborar projeto de construçã port ant Selection ation o e reabilitação do TIU e Fisc alização 108/C/PRSE/2022 / Contrata ção de consultor internacion Support to institutional refor Individual Consult al para a elaboração de instr IDA / D1260 Post Limited 0.00 Signed 2022-09-02 2022-09-01 2022-09-07 2022-09-12 2022-09-28 2022-10-25 2022-11-02 2023-04-09 2023-05-01 m and sector planning ant Selection umentos sociais para o projet o Acesso à Eletricidade Resili ente Limpa 109/C/PRSE/2022 / Contrata ção de consultor para a elab Support to institutional refor Individual Consult oração de instrumentos ambi IDA / D1260 Post Limited 0.00 Signed 2022-09-02 2022-09-01 2022-09-07 2022-09-12 2022-09-28 2022-10-24 2022-11-02 2023-04-09 2023-05-01 m and sector planning ant Selection entais para o projeto Acesso à Eletricidade Resiliente Limp a 83/C/PRSE/2021 / Internatio Project Implementation Sup Individual Consult IDA / D5870 Post Limited 0.00 Canceled 2021-07-12 2022-02-15 2021-07-17 2021-08-07 2021-09-11 2022-03-10 nal E&S Consultant port ant Selection 78/C/PRSE/2021 / T.A. to EM AE on the Incorporation of an Support to institutional refor Individual Consult IDA / D5870 Post Limited 0.00 Canceled 2021-04-30 2021-05-05 2021-05-26 2021-06-30 2021-12-27 Information System for Mana m and sector planning ant Selection gement of Corporate Resourc es 72/C/PSR/2020 / Technical A ssistance on Procurement for Project Implementation Sup Individual Consult IDA / D1260 Post Limited 0.00 Canceled 2021-01-19 2021-01-24 2021-02-14 2021-03-21 2021-09-17 the implementation of the Co port ant Selection ntador Hydropower Plant Reh abilitation Project 57/C/PSR/2018 / Accountant Project Implementation Sup IDA / D1260 Post Direct Selection Direct 0.00 Canceled 2018-12-03 2018-12-13 2019-01-07 2020-01-07 Assistant port 114/C/PRSE/2023 / CONTRAT AÇÃO DE 5 RAPARIGAS RECÉ M FORMADAS PARA REFORÇ Strengthening operational p Individual Consult Under Implement AR A EMAE NA IMPLEMENTAÇ IDA / D1260 erformance and governance Post Open - National 0.00 2023-02-10 2023-02-10 2023-03-31 2023-04-21 2023-05-26 2023-11-22 ant Selection ation ÃO DAS ACTIVIDADES DA SU of EMAE BCOMPONENTE 3.4 DO PRO JECTO DE RECUPERAÇÃO DO SECTOR ELÉTRICO (PRSE) 117/C/PRSE/2023 / CONTRAT Project Implementation Sup Individual Consult IDA / D5870 Post Direct - National 0.00 Under Review 2023-05-12 2023-05-17 2023-05-22 2023-06-12 2023-07-17 2024-01-13 AÇÃO DE UM (A) CONTABILIS port ant Selection TA PRSE 116/C/PRSE/2023 / Senior En Project Implementation Sup Individual Consult Under Implement IDA / D5870 Post Direct - National 0.00 2023-05-11 2023-05-18 2023-05-21 2023-06-11 2023-07-16 2024-01-12 vironmental and Social Coord port ant Selection ation inator Page 5