PROCUREMENT PLAN (Textual Part) Project information: Mozambique - P171449 - Maputo Urban Transformation Project Project Implementation agency: Maputo Municipal Council Date of the Procurement Plan: January 2020 Period covered by this Procurement Plan: January – June 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento 5/2016 of March 8, 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable PROCUREMENT Mozambique : Maputo Urban Transformation Project PLAN General Information Country: Mozambique 2020-01-09 Bank’s Approval Date of the Original Procurement Plan: 2023-09-12 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171449 GPN Date: 2021-04-08 Project Name: Maputo Urban Transformation Project Loan / Credit No: IDA / V3130, IDA / D7490 Maputo Municipal Council Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure MZ-CMM-264889-CW-RFB / C ment Document - onstruction and Rehabilitatio Informal Settlement Upgrad Single Stage - One E 2023-02-1 IDA / D7490 Post Request for Bids Open - National 1 Envelope proce 329,000.00 0.00 Signed 2022-04-22 2022-06-16 2022-05-06 2022-06-16 2022-06-17 2022-07-25 2022-07-17 2022-10-20 2022-08-21 2022-12-08 n of Public Toilets in Markets e nvelope 7 ss (Non Bank-SPD and main Public Transport Te ) rminals MZ-CMM-186992-CW-RFB / L Request for Bids - and demarcation works, Net Open - Internationa Single Stage - One E Works (without pr 24,000,000.0 2025-01-2 IDA / V3130 Sustainable Urban Growth Prior Request for Bids 0.00 Canceled 2022-10-14 2022-10-19 2022-11-30 2022-12-30 2023-02-03 work and Urban Infrastructur l nvelope equalification) SP 0 8 e Systems and Basic Urbaniz D ation in KaTembe Request for Bids - MZ-CMM-187003-CW-RFB / Informal Settlement Upgrad Open - Internationa Single Stage - One E Works (without pr 38,000,000.0 2024-12-2 Drainage, sanitation, mobility IDA / V3130 Prior Request for Bids 0.00 Canceled 2022-09-15 2022-09-20 2022-11-01 2022-12-01 2023-01-05 e l nvelope equalification) SP 0 4 , public spaces and urban eq D uipment works Request for Bids - MZ-CMM-289566-CW-RFB / C Maputo City Center Rehabilit Open - Internationa Single Stage - One E Works (without pr 15,000,000.0 Under Imple 2024-03-2 onstruction and Rehabilitatio IDA / D7490 Prior Request for Bids 0.00 2022-11-30 2023-04-17 2022-12-05 2023-04-18 2023-01-16 2023-06-15 2023-02-15 2023-03-29 ation l nvelope equalification) SP 0 mentation 8 n of Drainage System in Dow D ntown National Procure MZ-CMM-357030-CW-RFB / C Informal Settlement Upgrad Single Stage - One E ment Document - Pending Imp 2024-06-0 onstruction of SW Recovery IDA / D7490 Post Request for Bids Open - National 194,000.00 0.00 2023-08-15 2023-08-20 2023-10-01 2023-10-31 2023-12-05 e nvelope 1 Envelope proce lementation 2 Centers ss (Non Bank-SPD ) Request for Bids - MZ-CMM-289564-CW-RFB / I Informal Settlement Upgrad Open - Internationa Single Stage - One E Works (without pr 2023-09-0 ntegrated Intervention in Info IDA / D7490 Prior Request for Bids 6,600,000.00 0.00 Canceled 2022-11-15 2022-11-20 2023-01-01 2023-01-31 2023-03-07 e l nvelope equalification) SP 3 rmal Settlements, Phase I D National Procure MZ-CMM-289565-CW-RFB / C ment Document - Informal Settlement Upgrad Open - Internationa Single Stage - One E 2023-09-1 onstruction works for compe IDA / D7490 Post Request for Bids 1 Envelope proce 826,000.00 0.00 Canceled 2022-11-22 2022-11-27 2023-01-08 2023-02-07 2023-03-14 e l nvelope 0 nsation and resettlement for ss (Non Bank-SPD phases I and II ) National Procure MZ-CMM-289568-CW-RFB / C ment Document - onstruction works of Infrastru Open - Internationa Single Stage - One E 2023-09-1 IDA / D7490 Sustainable Urban Growth Post Request for Bids 1 Envelope proce 4,500,000.00 0.00 Canceled 2022-12-01 2022-12-06 2023-01-17 2023-02-16 2023-03-23 ctures of the Execution Unity l nvelope 9 ss (Non Bank-SPD and Demarcation of the PUD ) MK MZ-CMM-377469-CW-RFB / R Request for Bids - ehabilition of Drainage Syste Informal Settlement Upgrad Single Stage - One E Small Works SPD Pending Imp 2024-12-2 IDA / D7490 Prior Request for Bids Open - National 6,500,000.00 0.00 2023-09-15 2023-09-20 2023-10-20 2023-11-19 2023-12-24 m in Informal Settlements un e nvelope (1 envelope proce lementation 3 der Component 1. ss) National Procure MZ-CMM-374294-CW-RFB / P ment Document - Single Stage - One E Pending Imp 2024-11-0 aving the access Road to the IDA / D7490 Sustainable Urban Growth Post Request for Bids Open - National 1 Envelope proce 3,400,000.00 0.00 2024-01-15 2024-01-20 2024-03-02 2024-04-01 2024-05-06 nvelope lementation 2 KaTembe Sanitary Landfill ss (Non Bank-SPD ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-168529-GO-RFQ / S Project Implementation and I Request for Quota Single Stage - One E IDA / V3130 Post Limited 10,000.00 35,290.69 Completed 2020-05-12 2020-06-10 2020-07-07 2020-10-05 2020-09-05 2021-04-25 upply of Office Furniture nstitutional Support tions nvelope MZ-CMM-186679-GO-RFB / P Project Implementation and I Single Stage - One E IDA / V3130 Post Request for Bids Open - National 150,000.00 187,062.50 Completed 2020-08-10 2020-09-02 2020-08-15 2020-09-03 2020-09-26 2020-09-22 2020-10-26 2020-10-30 2020-11-30 2020-11-23 2021-05-29 2020-12-20 ickup Double Cab Vehicles nstitutional Support nvelope MZ-CMM-167802-GO-RFP / A Project Implementation and I Request for Quota Single Stage - One E IDA / V3130 Post Limited 40,000.00 0.00 Canceled 2020-05-12 2020-06-10 2020-07-07 2021-01-03 cquisition of office equipmen nstitutional Support tions nvelope t MZ-CMM-200807-GO-RFB / 2 Informal Settlement Upgrad Single Stage - One E IDA / V3130 Post Request for Bids Open - National 200,000.00 354,971.72 Signed 2020-11-03 2021-02-10 2020-11-08 2021-02-12 2020-12-20 2021-02-25 2021-01-19 2021-04-08 2021-02-23 2021-04-29 2021-08-22 00 Hand Wash Systems e nvelope MZ-CMM-194418-GO-RFQ / I Project Implementation and I Request for Quota Single Stage - One E IDA / V3130 Post Limited 40,000.00 0.00 Canceled 2020-09-23 2020-11-09 2021-05-08 T Equipment nstitutional Support tions nvelope MZ-CMM-213554-GO-RFB / I Project Implementation and I Single Stage - One E IDA / V3130 Post Request for Bids Open - National 200,000.00 125,354.11 Signed 2021-01-22 2021-01-18 2021-01-27 2021-01-27 2021-03-10 2021-02-25 2021-03-25 2021-06-28 2021-04-22 2021-08-02 2021-10-19 T Equipment and Software's nstitutional Support nvelope MZ-CMM-215207-GO-RFQ / F Project Implementation and I Request for Quota Single Stage - One E IDA / V3130 Post Limited 50,000.00 57,378.01 Signed 2021-01-30 2021-02-02 2021-03-22 2021-05-24 2021-09-18 inancial management Softwa nstitutional Support tions nvelope re MZ-CMM-200806-GO-RFQ / P Informal Settlement Upgrad Request for Quota Single Stage - One E rotection Equipment to Preve IDA / V3130 Post Limited 230,000.00 115,076.21 Completed 2020-11-08 2021-02-10 2021-01-03 2021-04-29 2021-07-02 2021-08-14 e tions nvelope nt Covid-19 MZ-CMM-218125-GO-RFB / A Contingent Emergency Resp Single Stage - One E cquisition of Materials for Pro IDA / V3130 Post Request for Bids Open - National 220,000.00 269,208.49 Signed 2021-02-11 2021-02-10 2021-02-16 2021-02-12 2021-03-18 2021-02-25 2021-04-02 2021-04-08 2021-04-22 2021-04-25 2022-04-22 onse nvelope duction of Cloth Masks to Pre vent Cov-19 MZ-CMM-224227-GO-RFQ / V Project Implementation and I Request for Quota Single Stage - One E IDA / V3130 Post Open - National 38,000.00 0.00 Canceled 2021-03-20 2021-09-14 2021-05-15 2021-11-11 ideoconference Equipment nstitutional Support tions nvelope MZ-CMM-289558-GO-RFQ / P Project Implementation and I Request for Quota Single Stage - One E rotection Equipment and Mat IDA / D7490 Post Limited 15,000.00 0.00 Signed 2022-05-07 2023-03-15 2022-07-02 2023-05-11 2022-12-29 nstitutional Support tions nvelope erial for Project Technical Te am MZ-CMM-264275-GO-RFQ / Project Implementation and I Request for Quota Single Stage - One E IDA / D7490 Post Open - National 5,000.00 3,614.66 Completed 2022-04-04 2022-05-05 2022-05-16 2022-06-15 2022-07-15 2022-07-14 Motorized Tricycle with Cano nstitutional Support tions nvelope py Page 1 MZ-CMM-308226-GO-RFQ / A cquisition of Parts and Acces Project Implementation and I Request for Quota Single Stage - One E Pending Impl IDA / D7490 Post Open - National 69,000.00 0.00 2022-08-30 2022-10-25 2023-04-23 sories for Maintainance and nstitutional Support tions nvelope ementation Repair of Equipment for Issua nce of DUATS MZ-CMM-308234-GO-RFQ / I Project Implementation and I Request for Quota Single Stage - One E IDA / D7490 Post Limited 5,000.00 0.00 Signed 2022-09-11 2022-09-28 2022-11-06 2022-11-19 2023-05-05 T Equipment and Consumabl nstitutional Support tions nvelope es MZ-CMM-318287-GO-RFB / V Project Implementation and I Single Stage - One E IDA / D7490 Post Request for Bids Open - National 182,000.00 0.00 Signed 2022-10-07 2022-10-23 2022-10-12 2022-10-23 2022-11-23 2022-11-21 2022-12-23 2023-03-12 2023-01-27 2023-04-12 2023-07-26 ideoconference Equipment nstitutional Support nvelope MZ-CMM-350182-GO-RFB / R Project Implementation and I Single Stage - One E Under Imple oad Construction and Mainte IDA / D7490 Post Request for Bids Open - National 567,000.00 0.00 2023-03-27 2023-04-11 2023-04-01 2023-04-11 2023-05-13 2023-05-15 2023-06-12 2023-08-17 2023-07-17 2024-01-13 nstitutional Support nvelope mentation nance Vehicles MZ-CMM-350184-GO-RFB / G Project Implementation and I Single Stage - One E Under Imple enerating Sets, Air Compress IDA / D7490 Post Request for Bids Open - National 124,200.00 0.00 2023-03-27 2023-04-11 2023-04-01 2023-04-11 2023-05-13 2023-05-15 2023-06-12 2023-08-17 2023-07-17 2024-01-13 nstitutional Support nvelope mentation ors, and Water Pumps MZ-CMM-350185-GO-RFQ / C Project Implementation and I Request for Quota Single Stage - One E oncrete Mixer, Pneumatic Flo IDA / D7490 Post Limited 21,500.00 0.00 Completed 2023-04-05 2023-04-03 2023-05-31 2023-05-11 2023-11-27 2023-06-05 nstitutional Support tions nvelope or Cutting Machine, and Com pactor Plate MZ-CMM-350186-GO-RFQ / T Project Implementation and I Request for Quota Single Stage - One E IDA / D7490 Post Limited 54,000.00 0.00 Completed 2023-04-05 2023-03-29 2023-05-31 2023-06-15 2023-11-27 2023-06-27 ractor with Trailer nstitutional Support tions nvelope MZ-CMM-350189-GO-RFQ / Project Implementation and I Request for Quota Single Stage - One E Under Imple IDA / D7490 Post Limited 12,000.00 0.00 2023-04-01 2023-04-03 2023-05-27 2023-11-23 Desktop Computers nstitutional Support tions nvelope mentation MZ-CMM-357032-GO-RFQ / I Project Implementation and I Request for Quota Single Stage - One E Pending Impl T Equipment for supporting t IDA / D7490 Post Limited 60,300.00 0.00 2023-05-20 2023-07-15 2024-01-11 nstitutional Support tions nvelope ementation he Issuance of DUATS MZ-CMM-357035-GO-RFQ / Project Implementation and I Request for Quota Single Stage - One E Pending Impl IDA / D7490 Post Limited 13,000.00 0.00 2023-05-20 2023-07-15 2024-01-11 Office Furniture nstitutional Support tions nvelope ementation MZ-CMM-357146-GO-RFQ / P Informal Settlement Upgrad Request for Quota Single Stage - One E IDA / D7490 Post Open - National 100,000.00 0.00 Signed 2023-06-20 2023-05-17 2023-08-15 2023-07-27 2024-02-11 ublic lighting Material e tions nvelope MZ-CMM-357155-GO-RFQ / Project Implementation and I Request for Quota Single Stage - One E Pending Impl Office Furniture for the Great IDA / D7490 Post Limited 16,800.00 0.00 2023-05-15 2023-07-10 2024-01-06 nstitutional Support tions nvelope ementation er Taxpayers Unit MZ-CMM-357156-GO-RFQ / A Project Implementation and I Request for Quota Single Stage - One E Under Imple IDA / D7490 Post Limited 1,500.00 0.00 2023-05-15 2023-05-19 2023-07-10 2024-01-06 ir Conditioners nstitutional Support tions nvelope mentation MZ-CMM-289559-GO-RFB / E quipment and Material for Ne Contingent Emergency Resp Single Stage - One E w Community Posts for Contr IDA / D7490 Post Request for Bids Open - National 118,000.00 0.00 Canceled 2022-05-06 2022-08-15 2022-05-11 2022-08-15 2022-06-22 2022-09-09 2022-07-22 2022-08-26 2023-02-22 onse nvelope ol and Prevention of Epidemi cs and Chronic Diseases MZ-CMM-289587-GO-RFB / C Project Implementation and I Open - Internationa Single Stage - One E IDA / D7490 Post Request for Bids 363,500.00 0.00 Canceled 2022-04-26 2022-05-01 2022-06-12 2022-07-12 2022-08-16 2023-02-12 omputer and Management S nstitutional Support l nvelope oftware's MZ-CMM-374270-GO-RFQ / S Project Implementation and I Request for Quota Single Stage - One E Under Imple oundproofed diesel engine G IDA / D7490 Post Limited 10,000.00 0.00 2023-08-15 2023-09-01 2023-10-10 2024-02-07 nstitutional Support tions nvelope mentation enerating set, 15KVA, electri c start. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-187000-NC-RFB / I Informal Settlement Upgrad Open - Internationa Single Stage - One E Under Revie mplementation of the Land R IDA / V3130 Prior Request for Bids 2,500,000.00 2,696,200.00 2021-04-23 2021-08-31 2021-04-28 2021-08-31 2021-06-09 2021-10-14 2021-07-09 2022-01-21 2021-08-13 2022-04-06 2024-08-22 e l nvelope w egularization MZ-CMM-223242-NC-RFQ / S ervices for Management of C Contingent Emergency Resp Request for Quota Single Stage - One E ommunity Post within the Sc IDA / V3130 Post Limited 75,000.00 166,593.73 Signed 2021-03-17 2021-04-06 2021-05-12 2021-08-02 2022-05-12 onse tions nvelope ope of the Control and Preve ntion of Covid-19 Maputo Cit y MZ-CMM-218127-NC-RFQ / I ntegrated care services for M Contingent Emergency Resp Request for Quota Single Stage - One E aputo City residents to reduc IDA / V3130 Post Open - National 75,000.00 0.00 Canceled 2021-02-17 2021-02-12 2021-04-14 2022-04-14 onse tions nvelope e the spread of Covid-19 and vulnerability to other disease s in 20 neighborhoods MZ-CMM-223215-NC-RFB / In stallation of Recycling Equip Contingent Emergency Resp Single Stage - One E ment, Training and Conducti IDA / V3130 Post Request for Bids Open - National 308,000.00 0.00 Canceled 2021-03-12 2021-04-06 2021-03-17 2021-04-06 2021-04-16 2021-05-02 2021-06-01 2022-06-01 onse nvelope ng Awareness Campaigns in 20 Neighborhoods in the Map uto City MZ-CMM-186995-NC-RFB / I Maputo City Center Rehabilit Open - Internationa Single Stage - One E mplementation of Regulatory IDA / D7490 Post Request for Bids 500,000.00 0.00 Canceled 2022-09-22 2022-09-27 2022-11-08 2022-12-08 2023-01-12 2024-12-31 ation l nvelope and Institutional Drainage Re forms MZ-CMM-264885-NC-RFB / S ervice Provider for Productio Informal Settlement Upgrad Single Stage - One E IDA / D7490 Post Request for Bids Open - National 118,000.00 20,443.05 Signed 2021-12-03 2021-12-03 2021-12-08 2021-12-06 2022-01-19 2022-01-07 2022-02-18 2022-03-01 2022-03-25 2022-03-30 2022-09-21 n of 400,000 Cloth Masks for e nvelope Prevention against Covid-19 MZ-CMM-186987-NC-RFB / I Open - Internationa Single Stage - One E mplementation of the Social I IDA / D7490 Sustainable Urban Growth Post Request for Bids 500,000.00 0.00 Canceled 2022-04-01 2022-04-06 2022-05-18 2022-06-17 2022-07-22 2025-02-19 l nvelope nclusion Plan at KaTembe dis trict MZ-CMM-186675-NC-RFB / I Project Implementation and I Open - Internationa Single Stage - One E IDA / D7490 Post Request for Bids 100,000.00 0.00 Canceled 2022-04-01 2022-04-06 2022-05-18 2022-06-17 2022-07-22 2024-07-11 mplementation of Addressing nstitutional Support l nvelope System MZ-CMM-264319-NC-RFB / I mplementation of the Reform Open - Internationa Single Stage - One E IDA / D7490 Sustainable Urban Growth Post Request for Bids 500,000.00 0.00 Canceled 2022-08-01 2022-08-06 2022-09-17 2022-10-17 2022-11-21 2023-11-16 to the Construction Licenses l nvelope and issuance of DUATs Page 2 MZ-CMM-186674-NC-RFB / I Project Implementation and I Open - Internationa Single Stage - One E mplementation of the Remot IDA / D7490 Post Request for Bids 100,000.00 0.00 Canceled 2022-05-16 2022-05-21 2022-07-02 2022-08-01 2022-09-11 2024-12-31 nstitutional Support l nvelope e Urban Soil Monitoring Syste m MZ-CMM-186600-NC-RFB / I mplementation of the Multi-a Open - Internationa Single Stage - One E IDA / D7490 Sustainable Urban Growth Post Request for Bids 200,000.00 0.00 Canceled 2022-06-01 2022-06-06 2022-07-18 2022-08-17 2022-09-21 2024-12-31 nnual Expenditure Plan and P l nvelope rogrammatic budget MZ-CMM-186985-NC-RFB / I Open - Internationa Single Stage - One E mplementation of Land Value IDA / D7490 Sustainable Urban Growth Post Request for Bids 300,000.00 0.00 Canceled 2022-07-01 2022-07-06 2022-08-17 2022-09-16 2022-10-21 2024-12-31 l nvelope Capture Instruments in KaTe mbe MZ-CMM-186996-NC-RFB / I mplementation of the Reform Maputo City Center Rehabilit Open - Internationa Single Stage - One E Pending Impl IDA / D7490 Post Request for Bids 225,000.00 0.00 2022-05-25 2022-06-06 2022-07-18 2022-08-17 2022-09-21 2023-09-21 s of IPRA to Align with Market ation l nvelope ementation Value and Non-Productive La nd Use MZ-CMM-186990-NC-RFB / I mplementation of Reform to IDA / V3130 Sustainable Urban Growth Post Request for Bids 500,000.00 0.00 Canceled 2021-02-12 2021-02-17 2021-03-31 2021-07-18 2022-01-14 the construction licenses and the issuance of DUATs MZ-CMM-350190-NC-RFB / S ervices for Cleaning Minor Re Informal Settlement Upgrad Request for Quota Single Stage - One E IDA / D7490 Post Limited 268,000.00 0.00 Signed 2023-04-01 2023-03-22 2023-05-27 2023-05-25 2023-11-23 pairs of the Drainage System e tions nvelope Ditches in the Nlhamanculo Municipal District MZ-CMM-357131-NC-RFQ / S ervice Provider for Continued Project Implementation and I Request for Quota Single Stage - One E Under Imple IDA / D7490 Post Open - National 50,000.00 0.00 2023-05-27 2023-06-01 2023-07-22 2024-07-22 Environmental Education and nstitutional Support tions nvelope mentation Awareness Program for Com munities MZ-CMM-357182-NC-RFQ / R Request for Quota Single Stage - One E Under Imple ehabilitation of the Front Wal IDA / D7490 Sustainable Urban Growth Post Limited 100,000.00 0.00 2023-05-24 2023-05-30 2023-07-19 2024-01-15 tions nvelope mentation l and Lighting of the Hulene Dump MZ-CMM-357195-NC-RFQ / Management Services of the Request for Quota Single Stage - One E Under Imple Socioeconomic Community E IDA / D7490 Sustainable Urban Growth Post Limited 60,000.00 0.00 2023-08-30 2023-09-01 2023-10-25 2024-04-22 tions nvelope mentation ngagement Post for the Hule ne Dump Waste Pickers MZ-CMM-357215-NC-RFQ / P roduction and Dissemination Project Implementation and I Request for Quota Single Stage - One E Under Imple IDA / D7490 Post Limited 50,000.00 0.00 2023-05-10 2023-06-28 2023-07-05 2024-01-01 of Communication Materials f nstitutional Support tions nvelope mentation or the 3 Components of the P roject MZ-CMM-357375-NC-RFB / S ervice Provider for Conductin Single Stage - One E Under Imple IDA / D7490 Sustainable Urban Growth Post Request for Bids Open - National 150,000.00 0.00 2023-05-25 2023-05-22 2023-05-30 2023-05-23 2023-07-11 2023-06-27 2023-08-10 2023-09-14 2024-03-12 g a City-wide Survey of the nvelope mentation Waste Pickers and Census of Economic Activities MZ-CMM-186631-NC-RFB / D Project Implementation and I Open - Internationa Single Stage - One E evelopment of the Computeri IDA / D7490 Post Request for Bids 250,000.00 0.00 Canceled 2022-05-20 2022-05-27 2022-07-08 2022-08-07 2022-09-12 2023-09-12 nstitutional Support l nvelope sed Unique Social Registry Pl atform MZ-CMM-289550-NC-RFB / D Maputo City Center Rehabilit Open - Internationa Single Stage - Two E evelopment and Implementa IDA / D7490 Post Request for Bids 311,700.00 0.00 Canceled 2022-06-10 2022-06-15 2022-07-27 2022-10-09 2022-11-13 2023-05-12 ation l nvelope tion of Electronic Payment Sy stem MZ-CMM-299498-NC-RFB / S ocial Distancing Measures in Project Implementation and I Single Stage - One E IDA / D7490 Post Request for Bids Open - National 115,000.00 0.00 Canceled 2022-06-24 2022-06-29 2022-08-10 2022-09-09 2022-10-14 2023-04-12 Market and Public Transport nstitutional Support nvelope Terminals to prevent against Covid-19 MZ-CMM-289561-NC-RFB / S ervices for the management Contingent Emergency Resp Single Stage - One E of Community Posts within th IDA / D7490 Post Request for Bids Open - National 203,000.00 0.00 Canceled 2022-04-25 2022-08-11 2022-04-30 2022-08-11 2022-06-11 2022-09-09 2022-07-11 2022-08-15 2023-08-15 onse nvelope e Scope of the Control and Pr evention of Epidemics and C hronic Diseases MZ-CMM-289572-NC-RFB / S ervice Provider to Increase th Single Stage - One E IDA / D7490 Sustainable Urban Growth Post Request for Bids Open - National 100,000.00 0.00 Canceled 2022-07-25 2022-07-30 2022-09-10 2022-10-10 2022-11-14 2023-05-13 e Volume of Recycled and Re nvelope usable Solid Waste MZ-CMM-289571-NC-RFQ / S ervices Provider to Support t Request for Quota Single Stage - One E IDA / D7490 Sustainable Urban Growth Post Open - National 40,000.00 0.00 Canceled 2022-08-20 2022-10-15 2023-04-13 he Reintegration and Formali tions nvelope zation of the Solid Waste Pick ers MZ-CMM-289557-NC-RFQ / S ervice Provider for Productio Informal Settlement Upgrad Request for Quota Single Stage - One E IDA / D7490 Post Open - National 30,000.00 0.00 Canceled 2022-05-07 2022-07-02 2022-12-29 n of Materials to Raise Aware e tions nvelope ness of Urban Solid Waste MZ-CMM-357036-NC-RFB / S Project Implementation and I Single Stage - One E Pending Impl upport services for the Digitiz IDA / D7490 Post Request for Bids Open - National 100,000.00 0.00 2023-09-15 2023-09-20 2023-11-01 2023-12-01 2024-01-05 2024-07-03 nstitutional Support nvelope ementation ation process of 50,000 DUA TS process MZ-CMM-374282-NC-RFB / E rection of Fencing around the Single Stage - One E IDA / D7490 Sustainable Urban Growth Post Request for Bids Open - National 150,000.00 0.00 Canceled 2023-08-25 2023-08-30 2023-10-11 2023-11-10 2023-12-15 2024-06-12 landfill area and afforestation nvelope of the 200-meter reserve are a CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-168538-CS-QCBS / Consulting Services to prepa Informal Settlement Upgrad Quality And Cost- Open - Internationa IDA / V3130 Prior 1,500,000.00 638,380.88 Signed 2020-07-13 2020-04-24 2020-08-03 2020-05-18 2020-09-16 2020-11-05 2020-10-14 2021-02-08 2020-11-13 2021-06-16 2020-12-18 2021-11-10 2021-01-22 2022-01-26 2022-09-14 re studies and projects on int e Based Selection l egrated intervention of infor mal settlements MZ-CMM-169355-CS-QCBS / Consulting Services Urban m Maputo City Center Rehabilit Quality And Cost- Open - Internationa IDA / V3130 Prior 500,000.00 0.00 Canceled 2020-04-27 2020-05-18 2020-07-01 2020-07-29 2020-08-28 2020-10-02 2020-11-06 2021-11-06 obility studies and project for ation Based Selection l Baixa da Cidade Page 3 MZ-CMM-171134-CS-QCBS / Project Implementation and I Quality And Cost- Open - Internationa Development of Project Infor IDA / V3130 Post 50,000.00 0.00 Canceled 2020-05-03 2020-05-06 2020-05-24 2020-05-21 2020-07-07 2020-08-04 2020-09-03 2020-10-08 2020-11-12 2021-05-11 nstitutional Support Based Selection l mation Management System MZ-CMM-186470-CS-QCBS / Development of Technical St Maputo City Center Rehabilit Quality And Cost- Open - Internationa IDA / V3130 Prior 1,000,000.00 408,420.83 Signed 2020-08-17 2020-10-27 2020-09-07 2020-10-28 2020-10-21 2021-06-18 2020-11-18 2021-08-30 2020-12-18 2021-10-11 2021-01-22 2021-12-07 2021-02-26 2022-01-10 2022-02-26 udies and Projects for Draina ation Based Selection l ge and Sanitation for the Do wntown area MZ-CMM-186533-CS-QCBS / Consulting services for Updat Quality And Cost- Open - Internationa ing the Register, Revising the IDA / V3130 Sustainable Urban Growth Prior 500,000.00 487,375.00 Signed 2020-08-12 2021-03-11 2020-09-02 2021-03-15 2020-10-16 2021-12-17 2020-11-13 2022-02-11 2020-12-13 2022-04-21 2021-01-17 2022-06-07 2021-02-21 2022-06-20 2022-02-21 Based Selection l Urban Management Plan, Pre paration of PPs and Safeguar ds Instruments MZ-CMM-200797-CS-LCS / E Project Implementation and I Least Cost Selecti IDA / V3130 Post Open - National 300,000.00 23,378.51 Signed 2020-11-06 2020-10-24 2020-11-27 2020-10-27 2021-01-10 2021-04-14 2021-02-07 2021-05-14 2021-03-09 2021-07-21 2021-04-13 2021-10-18 2021-05-18 2021-10-25 2021-11-14 xternal Auditing nstitutional Support on MZ-CMM-216360-CS-QCBS / Elaboration of Participatory P Informal Settlement Upgrad Quality And Cost- Open - Internationa lans for Social Inclusion, Gen IDA / V3130 Prior 600,000.00 723,297.67 Signed 2021-01-29 2021-01-28 2021-02-19 2021-01-28 2021-04-04 2021-05-07 2021-05-02 2021-07-05 2021-06-01 2021-10-28 2021-07-06 2022-03-24 2021-08-10 2022-04-23 2022-08-10 e Based Selection l der Equality and for Combati ng GBV for the Neighbourhoo ds in Informal Settlements MZ-CMM-186481-CS-QCBS / Preparation of technical studi Maputo City Center Rehabilit Quality And Cost- Open - Internationa IDA / V3130 Prior 1,000,000.00 0.00 Canceled 2020-08-27 2020-09-17 2020-10-31 2020-11-28 2020-12-28 2021-02-01 2021-03-08 2022-03-08 es and projects for the impro ation Based Selection l vement of public spaces and urban facilities MZ-CMM-186540-CS-QCBS / Technical Studies and Execut Quality And Cost- Open - Internationa IDA / V3130 Sustainable Urban Growth Prior 1,000,000.00 0.00 Canceled 2021-07-07 2021-07-28 2021-09-10 2021-10-08 2021-11-07 2021-12-12 2022-01-16 2023-01-16 ive Project for Infrastructures Based Selection l Development in KaTembe MZ-CMM-168539-CS-QCBS / Consultancy Services for dra Maputo City Center Rehabilit Quality And Cost- Open - Internationa IDA / V3130 Prior 500,000.00 0.00 Canceled 2020-06-10 2020-04-24 2020-07-01 2020-08-14 2020-09-11 2020-10-11 2020-11-15 2020-12-20 2022-08-12 inage studies and projects fo ation Based Selection l r Baixa da Cidade MZ-CMM-168537-CS-QCBS / Consultancy Services to prep Quality And Cost- Open - Internationa IDA / V3130 Sustainable Urban Growth Prior 750,000.00 0.00 Canceled 2020-06-29 2020-07-20 2020-09-02 2020-09-30 2020-10-30 2020-12-04 2021-01-08 2022-01-08 are studies and projects for t Based Selection l he sustainable development of Katembe MZ-CMM-200796-CS-QCBS / Informal Settlement Upgrad Quality And Cost- Open - Internationa Environmental and Social Im IDA / V3130 Prior 500,000.00 683,853.47 Signed 2021-05-14 2021-05-14 2021-06-04 2021-05-17 2021-07-18 2021-10-06 2021-08-15 2021-12-03 2021-09-14 2022-01-17 2021-10-19 2022-03-03 2021-11-23 2022-03-27 2022-11-23 e Based Selection l pact Assessment for Compon ents 1, 2 and 3 MZ-CMM-168535-CS-QCBS / Project Implementation and I Quality And Cost- Open - Internationa Consultancy Services to deve IDA / V3130 Post 100,000.00 0.00 Canceled 2020-05-20 2020-08-12 2020-06-10 2020-07-24 2020-08-21 2020-09-20 2020-10-25 2020-11-29 2021-11-29 nstitutional Support Based Selection l lop unified social Municipal c adaster. MZ-CMM-169356-CS-QCBS / Consulting services for public Maputo City Center Rehabilit Quality And Cost- Open - Internationa IDA / V3130 Prior 500,000.00 0.00 Canceled 2020-04-27 2020-05-18 2020-07-01 2020-07-29 2020-08-28 2020-10-02 2020-11-06 2021-11-06 spaces and urban equipment ation Based Selection l studies and project for Baixa da Cidade MZ-CMM-229289-CS-QCBS / Preparation of Studies, Plans Quality And Cost- Open - Internationa and Detailed Project for the I IDA / V3130 Sustainable Urban Growth Prior 1,500,000.00 0.00 Signed 2021-04-25 2021-09-20 2021-05-16 2021-09-21 2021-06-29 2022-01-18 2021-07-27 2022-03-28 2021-08-26 2022-06-28 2021-09-30 2022-10-11 2021-11-04 2022-11-07 2022-11-04 Based Selection l mplementation of the KaTem be Landfill and Closure of the Hulene Dump MZ-CMM-264263-CS-QCBS / Institutional Diagnosis of the Project Implementation and I Quality And Cost- municipal Department of Ter IDA / D7490 Post Open - National 200,000.00 0.00 Signed 2021-12-02 2022-02-03 2021-12-23 2022-03-09 2022-01-27 2022-05-19 2022-02-24 2022-07-25 2022-03-24 2022-11-07 2022-04-28 2023-02-21 2022-06-02 2023-03-28 2022-11-29 nstitutional Support Based Selection ritorial Planning, Environmen t and Urbanization - VOTAU MZ-CMM-237534-CS-CQS / P Project Implementation and I Consultant Qualifi IDA / V3130 Post Open - National 15,000.00 0.00 Canceled 2021-06-07 2021-06-02 2021-06-21 2021-06-03 2021-07-19 2021-07-24 2021-08-14 2021-11-12 roject Team Capacity Buildin nstitutional Support cation Selection g MZ-CMM-213646-CS-QCBS / Consulting Services for Conc eption, Development and Im Project Implementation and I Quality And Cost- IDA / V3130 Post Open - National 100,000.00 0.00 Canceled 2021-01-18 2021-01-19 2021-01-25 2021-01-27 2021-03-01 2021-05-05 2021-03-29 2021-04-28 2021-06-07 2021-07-12 2022-12-04 plementation of an Integrate nstitutional Support Based Selection d Information Management S ystem for Maputo Urban Tran sformation Project MZ-CMM-227454-CS-QCBS / Project Implementation and I Quality And Cost- Development of Unique Muni IDA / V3130 Post Open - National 100,000.00 0.00 Canceled 2021-04-09 2021-04-08 2021-04-30 2021-06-13 2021-07-11 2021-08-10 2021-09-14 2021-10-19 2022-10-19 nstitutional Support Based Selection cipal Social Registry MZ-CMM-299499-CS-QCBS / Consultancy Services to Supp ort CMM in Identifying PBC3 Quality And Cost- Open - Internationa IDA / D7490 Sustainable Urban Growth Post 200,000.00 0.00 Canceled 2022-06-24 2022-12-23 2022-07-15 2023-01-29 2022-08-28 2022-09-25 2022-10-25 2022-11-29 2023-01-03 2024-01-03 Activities related to Improve Based Selection l ment of Financial Sustainabili ty of the Urban Solid Waste Management Sector MZ-CMM-286081-CS-QCBS / Quality And Cost- Open - Internationa Development of Municipal Re IDA / D7490 Sustainable Urban Growth Post 311,700.00 0.00 Canceled 2022-05-27 2022-05-11 2022-06-17 2022-07-31 2022-08-28 2022-09-27 2022-11-01 2022-12-06 2023-06-04 Based Selection l al Estate Taxation Subsystem MZ-CMM-291097-CS-CQS / S Project Implementation and I Consultant Qualifi trengthening Social Participat IDA / D7490 Post Open - National 40,000.00 0.00 Canceled 2022-05-20 2022-06-10 2022-07-24 2022-08-23 2022-09-27 2023-03-26 nstitutional Support cation Selection ion Transparency MZ-CMM-168536-CS-QCBS / Consultancy Services for add Project Implementation and I Quality And Cost- Open - Internationa IDA / D7490 Prior 500,000.00 0.00 Canceled 2022-06-10 2022-07-01 2022-08-14 2022-09-11 2022-10-11 2022-11-15 2022-12-20 2023-12-20 ressing, preparing, updating nstitutional Support Based Selection l and expanding the physical a nd fiscal registration MZ-CMM-186629-CS-CQS / C onsulting Services to support Project Implementation and I Consultant Qualifi Open - Internationa IDA / D7490 Post 50,000.00 0.00 Canceled 2022-04-20 2022-05-11 2022-06-24 2022-07-24 2022-08-28 2023-02-24 the implementation of the M nstitutional Support cation Selection l odernization of Administrativ e Processes MZ-CMM-289570-CS-QCBS / Consulting Services to Impro Quality And Cost- Open - Internationa IDA / D7490 Sustainable Urban Growth Post 200,000.00 0.00 Canceled 2022-05-23 2022-06-13 2022-07-27 2022-08-24 2022-09-23 2022-10-28 2022-12-02 2023-12-02 ve the financial sustainability Based Selection l of the Urban Solid Waste Sec tor Page 4 MZ-CMM-357038-CS-QCBS / Updating of Studies, Plans, a Informal Settlement Upgrad Quality And Cost- Open - Internationa Pending Impleme IDA / D7490 Post 480,000.00 0.00 2023-08-15 2023-09-05 2023-10-19 2023-11-16 2023-12-16 2024-01-20 2024-02-24 2025-02-23 nd Projects for Integrated Int e Based Selection l ntation erventions in Informal Settle ments - Phase 1 MZ-CMM-357114-CS-CQS / T Project Implementation and I Consultant Qualifi Under Implement echnical Training in Assets M IDA / D7490 Post Limited 11,000.00 0.00 2023-05-15 2023-05-09 2023-05-29 2023-06-15 2023-06-13 2023-07-11 2023-10-09 nstitutional Support cation Selection ation anagement and Maintenance MZ-CMM-357158-CS-QCBS / Consulting Services for Defini Project Implementation and I Quality And Cost- Pending Impleme IDA / D7490 Post Open - National 225,000.00 0.00 2023-08-15 2023-09-05 2023-10-19 2023-11-16 2023-12-16 2024-01-20 2024-02-24 2025-02-23 tion of Building Standards an nstitutional Support Based Selection ntation d Value of Square Meter of C onstruction MZ-CMM-357160-CS-QCBS / Strengthening the Institution Project Implementation and I Quality And Cost- Pending Impleme IDA / D7490 Post Open - National 120,000.00 0.00 2023-10-16 2023-11-06 2023-12-20 2024-01-17 2024-02-16 2024-03-22 2024-04-26 2025-04-26 al and Financial Capacity of nstitutional Support Based Selection ntation Drainage and Sanitation Serv ices MZ-CMM-357176-CS-QCBS / Supervision of Road Construc Quality And Cost- Open - Internationa Pending Impleme IDA / D7490 Sustainable Urban Growth Post 350,000.00 0.00 2023-10-02 2023-10-23 2023-12-06 2024-01-03 2024-02-02 2024-03-08 2024-04-12 2025-04-12 tion Works for Paving the Acc Based Selection l ntation ess Road to the KaTembe La ndfill Area MZ-CMM-299501-CS-QCBS / Consultancy Services to Supp ort CMM in Identifying Activiti Quality And Cost- Open - Internationa IDA / D7490 Sustainable Urban Growth Post 150,000.00 0.00 Canceled 2022-06-23 2023-01-16 2022-07-14 2022-08-27 2022-09-24 2022-10-24 2022-11-28 2023-01-02 2024-01-02 es regarding Inclusion of Was Based Selection l te Pickers and Recovery of R ecyclables, including Compos table Waste MZ-CMM-289569-CS-QCBS / Supervision of Construction Quality And Cost- Open - Internationa IDA / D7490 Sustainable Urban Growth Post 299,000.00 0.00 Canceled 2022-11-30 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-06-10 Works for Infrastructures of t Based Selection l he PUDMK Execution and De marcation Unity MZ-CMM-289533-CS-QCBS / Maputo City Center Rehabilit Quality And Cost- Open - Internationa Development of Digital Platfo IDA / D7490 Post 250,000.00 0.00 Canceled 2022-07-15 2022-08-05 2022-09-18 2022-10-16 2022-11-15 2022-12-20 2023-01-24 2024-01-24 ation Based Selection l rm of Unique Social Registrat ion MZ-CMM-291098-CS-CQS / D ecentralization of the BAU - S Project Implementation and I Consultant Qualifi IDA / D7490 Post Open - National 10,000.00 0.00 Canceled 2022-08-29 2022-09-19 2022-11-02 2022-12-02 2023-01-06 2023-07-05 ingle Service Desk of the Mu nstitutional Support cation Selection nicipality to the Municipal dis tricts MZ-CMM-200798-CS-QBS / P Project Implementation and I Quality Based Sel Open - Internationa IDA / V3130 Post 150,000.00 0.00 Canceled 2020-11-06 2020-11-10 2020-11-27 2020-11-16 2021-01-10 2021-11-23 2021-02-07 2022-01-07 2021-03-09 2022-03-08 2021-04-08 2021-05-13 2022-05-13 BC's Verification Agent nstitutional Support ection l MZ-CMM-186410-CS-QCBS / Informal Settlement Upgrad Quality And Cost- Open - Internationa Works Supervision in informa IDA / V3130 Prior 1,226,000.00 0.00 Canceled 2022-11-01 2022-11-22 2023-01-05 2023-02-02 2023-03-04 2023-04-08 2023-05-13 2025-12-31 e Based Selection l l settlements Phase I and II MZ-CMM-186554-CS-QCBS / Quality And Cost- Open - Internationa IDA / V3130 Sustainable Urban Growth Post 300,000.00 0.00 Canceled 2022-06-06 2022-06-27 2022-08-10 2022-09-07 2022-10-07 2022-11-11 2022-12-16 2023-12-16 Works Supervision at KaTem Based Selection l be MZ-CMM-374305-CS-LCS / E Project Implementation and I Least Cost Selecti Under Implement IDA / D7490 Post Open - National 24,000.00 0.00 2023-08-14 2023-08-17 2023-09-04 2023-08-31 2023-10-18 2023-11-15 2023-12-15 2024-01-19 2024-02-23 2026-02-12 xternal Audit for the Project nstitutional Support on ation Accounts MZ-CMM-362306-CS-QCBS / Maputo City Center Rehabilit Quality And Cost- Consulting Services for Urba IDA / D7490 Post Open - National 100,000.00 0.00 Canceled 2023-05-25 2023-05-17 2023-06-15 2023-07-29 2023-08-26 2023-09-25 2023-10-30 2023-12-04 2024-06-01 ation Based Selection n Mobility Study for Maputo C ity MZ-CMM-186501-CS-QCBS / Maputo City Center Rehabilit Quality And Cost- Open - Internationa Supervision of Drainage Wor IDA / D7490 Post 473,000.00 0.00 Canceled 2021-09-28 2021-10-19 2021-12-02 2021-12-30 2022-01-29 2022-03-05 2022-04-09 2024-12-24 ation Based Selection l ks in Downtown Area MZ-CMM-357151-CS-QCBS / Maputo City Center Rehabilit Quality And Cost- Open - Internationa Works Supervision of Drainag IDA / D7490 Post 453,000.00 0.00 Canceled 2023-06-01 2023-05-17 2023-06-22 2023-08-05 2023-09-02 2023-10-02 2023-11-06 2023-12-11 2025-06-13 ation Based Selection l e Works in Downtown MZ-CMM-357037-CS-CQS / T Project Implementation and I Consultant Qualifi echnical training in Asset Ma IDA / D7490 Post Open - National 11,000.00 0.00 Canceled 2023-05-22 2023-06-12 2023-07-26 2023-08-25 2023-09-29 2024-03-27 nstitutional Support cation Selection nagement and Maintenance MZ-CMM-264894-CS-QCBS / Preparation of Master Plan fo Project Implementation and I Quality And Cost- Open - Internationa r Markets and Fairs, including IDA / D7490 Post 325,000.00 0.00 Canceled 2022-05-30 2022-10-11 2022-06-20 2022-10-12 2022-08-03 2023-05-16 2022-08-31 2022-09-30 2022-11-04 2022-12-09 2023-06-07 nstitutional Support Based Selection l Technical Studies and Design s for priority Interventions INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-CMM-152216-CS-INDV / Informal Settlement Upgrad Individual Consult IDA / V3130 Prior Open 60,000.00 286,007.75 Signed 2020-01-10 2020-01-16 2020-02-28 2020-06-23 2020-03-20 2020-06-23 2020-04-24 2020-06-30 2021-04-24 Procurement Specialist e ant Selection MZ-CMM-167544-CS-INDV / Project Implementation and I Individual Consult Senior Finance Municipal Ma IDA / V3130 Post Open 60,000.00 152,000.00 Signed 2020-04-16 2020-04-18 2020-06-04 2020-08-20 2020-06-25 2020-10-06 2020-07-30 2020-10-11 2021-07-30 nstitutional Support ant Selection nagement Advisor MZ-CMM-171140-CS-INDV / Senior Technician in Spatial P Project Implementation and I Individual Consult IDA / V3130 Post Open 60,000.00 161,750.35 Signed 2020-05-05 2020-04-30 2020-06-23 2020-12-11 2020-07-14 2021-02-17 2020-08-18 2021-03-05 2021-02-14 lanning and Urban Soil Mana nstitutional Support ant Selection gement to integrate the PTU M Technical Team MZ-CMM-171147-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 60,000.00 67,500.00 Signed 2020-05-05 2020-04-30 2020-06-23 2020-08-28 2020-07-14 2020-09-02 2020-08-18 2020-10-06 2021-02-14 Senior Technician in Architec nstitutional Support ant Selection ture MZ-CMM-171150-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 60,000.00 78,000.00 Signed 2020-05-05 2020-04-30 2020-06-23 2020-11-03 2020-07-14 2020-11-05 2020-08-18 2020-11-21 2021-02-14 2021-11-25 Technical Team Leader nstitutional Support ant Selection MZ-CMM-171151-CS-INDV / Project Implementation and I Individual Consult Senior Drain Technician of th IDA / V3130 Post Open 60,000.00 146,450.44 Signed 2020-05-05 2020-04-30 2020-06-23 2020-09-16 2020-07-14 2020-11-05 2020-08-18 2020-11-16 2021-02-14 nstitutional Support ant Selection e technical team Page 5 MZ-CMM-171152-CS-INDV / Senior Technician in Social In Project Implementation and I Individual Consult IDA / V3130 Post Open 60,000.00 60,000.00 Signed 2020-06-02 2020-04-30 2020-07-21 2020-12-15 2020-08-11 2021-01-25 2020-09-15 2021-02-26 2021-03-14 clusion and Gender to integr nstitutional Support ant Selection ate the technical team of PT UM MZ-CMM-172416-CS-INDV / s Project Implementation and I Individual Consult enior water and sanitation te IDA / V3130 Post Open 60,000.00 128,795.78 Signed 2020-05-08 2020-05-08 2020-06-26 2020-08-25 2020-07-17 2021-05-25 2020-08-21 2021-06-06 2021-02-17 nstitutional Support ant Selection chnician of the technical tea m MZ-CMM-175939-CS-INDV / Project Implementation and I Individual Consult Senior Advisor for Gender an IDA / V3130 Post Open 60,000.00 0.00 Signed 2020-06-02 2020-09-03 2020-07-21 2021-01-20 2020-08-11 2021-01-20 2020-09-15 2021-01-10 2020-12-14 nstitutional Support ant Selection d Social Inclusion MZ-CMM-172422-CS-INDV / I ndividual Consultant for the Project Implementation and I Individual Consult definition and implementatio IDA / V3130 Post Open 60,000.00 0.00 Canceled 2020-05-10 2020-05-08 2020-06-28 2020-07-19 2020-08-23 2021-02-19 nstitutional Support ant Selection n of an integrated informatio n management system for th e project MZ-CMM-176004-CS-INDV / J Project Implementation and I Individual Consult unior Technician in Social Incl IDA / V3130 Post Open 30,000.00 126,085.52 Signed 2020-06-02 2020-06-04 2020-07-21 2020-09-02 2020-08-11 2020-09-08 2020-09-15 2020-09-27 2020-12-14 2022-10-10 nstitutional Support ant Selection usion and Gender MZ-CMM-175981-CS-INDV / J Project Implementation and I Individual Consult unior Water and Sanitation T IDA / V3130 Post Open 30,000.00 58,618.26 Signed 2020-06-02 2020-06-04 2020-07-21 2020-08-25 2020-08-11 2020-08-26 2020-09-15 2020-09-17 2020-12-14 2022-10-09 nstitutional Support ant Selection echnician of the Project's Tec hnical Team MZ-CMM-176001-CS-INDV / J Project Implementation and I Individual Consult unior Technician in Spatial Pl IDA / V3130 Post Open 30,000.00 70,322.15 Signed 2020-06-02 2020-06-04 2020-07-21 2020-11-03 2020-08-11 2020-11-06 2020-09-15 2020-11-23 2020-12-14 2022-11-28 nstitutional Support ant Selection anning and Urban Soil Manag ement MZ-CMM-175990-CS-INDV / J Project Implementation and I Individual Consult IDA / V3130 Post Open 30,000.00 70,799.99 Signed 2020-06-02 2020-06-04 2020-07-21 2020-09-03 2020-08-11 2020-09-02 2020-09-15 2020-09-22 2020-12-14 2022-10-10 unior Technician in Architect nstitutional Support ant Selection ure MZ-CMM-175998-CS-INDV / J Project Implementation and I Individual Consult IDA / V3130 Post Open 30,000.00 94,395.21 Signed 2020-06-02 2020-06-04 2020-07-21 2020-11-25 2020-08-11 2020-12-03 2020-09-15 2021-02-03 2020-12-14 2022-08-03 unior Drainage Technician nstitutional Support ant Selection MZ-CMM-186605-CS-INDV / I Project Implementation and I Individual Consult IDA / V3130 Post Open 120,000.00 190,202.90 Signed 2020-08-18 2020-09-14 2020-10-06 2021-04-28 2020-10-27 2021-06-29 2020-12-01 2021-07-07 2022-11-21 nfrastructure Senior Advisor nstitutional Support ant Selection MZ-CMM-191816-CS-INDV / Project Implementation and I Individual Consult Consulting services for prepa IDA / V3130 Post Open 10,000.00 28,081.12 Signed 2020-09-10 2020-09-09 2020-10-13 2021-02-15 2020-10-22 2021-02-15 2020-11-26 2021-03-18 2021-05-25 nstitutional Support ant Selection ration of Project Implementat ion Manual MZ-CMM-200801-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 160,000.00 96,254.58 Signed 2020-11-06 2021-03-06 2020-12-25 2021-08-02 2021-01-15 2021-08-04 2021-02-19 2021-08-23 2021-08-18 Solid Waste Management Ad nstitutional Support ant Selection visor MZ-CMM-200803-CS-INDV / Project Implementation and I Individual Consult Solid Waste Management Se IDA / V3130 Post Open 120,000.00 60,336.96 Signed 2020-11-06 2021-04-19 2020-12-25 2021-08-19 2021-01-15 2021-09-28 2021-02-19 2021-10-01 2021-08-18 nstitutional Support ant Selection nior Technician MZ-CMM-200805-CS-INDV / Project Implementation and I Individual Consult Solid Waste Management Jun IDA / V3130 Post Open 60,000.00 44,649.35 Signed 2020-11-06 2021-04-19 2020-12-25 2021-09-16 2021-01-15 2021-09-20 2021-02-19 2021-10-05 2021-08-18 nstitutional Support ant Selection ior Technician MZ-CMM-200799-CS-INDV / Project Implementation and I Individual Consult Environmental and Social Saf IDA / V3130 Post Open 30,000.00 61,959.33 Signed 2020-11-02 2020-11-10 2020-12-21 2021-04-30 2021-01-11 2021-05-11 2021-02-15 2021-06-03 2022-02-15 nstitutional Support ant Selection eguards Assistant MZ-CMM-227393-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Direct 60,000.00 79,187.75 Signed 2021-03-31 2021-04-08 2021-04-07 2021-04-21 2021-04-09 2021-04-22 2021-04-16 2021-04-28 2022-04-16 Financial Management Speci nstitutional Support ant Selection alist MZ-CMM-227397-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Direct 60,000.00 159,384.08 Signed 2021-03-31 2021-04-08 2021-04-03 2021-04-15 2021-04-05 2021-04-20 2021-04-08 2021-04-28 2022-04-08 Social Safeguards Specialist nstitutional Support ant Selection MZ-CMM-227399-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Direct 60,000.00 159,384.08 Signed 2021-03-31 2021-04-08 2021-04-05 2021-04-15 2021-04-07 2021-04-20 2021-04-12 2021-04-28 2022-04-12 Environmental Safeguards Sp nstitutional Support ant Selection ecialist MZ-CMM-174529-CS-INDV / I ndividual consultancy for the elaboration of the methodolo Individual Consult IDA / V3130 Sustainable Urban Growth Post Open 60,000.00 0.00 Canceled 2020-05-25 2020-05-21 2020-07-13 2020-08-03 2020-09-07 2021-03-06 gy for updating the physical t ant Selection ax register, the generic figur es map and the IPRA calculat ion MZ-CMM-186617-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 120,000.00 0.00 Canceled 2020-08-19 2020-10-07 2020-10-28 2020-12-02 2022-12-01 Senior Social Inclusion Adviso nstitutional Support ant Selection r MZ-CMM-167546-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 60,000.00 0.00 Canceled 2020-06-03 2020-07-22 2020-08-12 2020-09-16 2021-09-16 Senior Governance Advisor nstitutional Support ant Selection MZ-CMM-167545-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 60,000.00 0.00 Canceled 2020-04-16 2020-04-21 2020-06-04 2020-06-25 2020-07-30 2021-07-30 Senior Urban Planning Adviso nstitutional Support ant Selection r MZ-CMM-175992-CS-INDV / J Project Implementation and I Individual Consult unior Technician of Mobility a IDA / V3130 Post 30,000.00 0.00 Canceled 2020-06-02 2020-06-04 2020-07-21 2020-08-11 2020-09-15 2020-12-14 nstitutional Support ant Selection nd Roads of the project's Tec hnical Team MZ-CMM-200802-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 120,000.00 98,000.00 Signed 2021-05-14 2021-04-08 2021-07-02 2021-07-29 2021-07-23 2021-08-30 2021-08-27 2021-10-03 2022-08-27 Senior Technician for Urban nstitutional Support ant Selection Mobility MZ-CMM-200804-CS-INDV / J Project Implementation and I Individual Consult IDA / V3130 Post Open 60,000.00 30,110.12 Signed 2021-05-21 2021-04-08 2021-07-09 2021-07-30 2021-07-30 2021-08-03 2021-09-03 2021-08-08 2022-09-01 unior Technician for Urban M nstitutional Support ant Selection obility MZ-CMM-171156-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 60,000.00 0.00 Canceled 2020-05-11 2020-04-30 2020-06-29 2020-07-20 2020-08-24 2021-02-20 Urban Mobility Consultant nstitutional Support ant Selection MZ-CMM-186611-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 120,000.00 0.00 Canceled 2020-08-19 2020-10-09 2020-10-07 2020-10-28 2020-12-02 2022-11-22 Municipal Governance Senior nstitutional Support ant Selection Advisor MZ-CMM-228447-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 120,000.00 95,505.75 Signed 2021-04-12 2021-04-13 2021-05-31 2021-08-24 2021-06-21 2021-11-03 2021-07-26 2021-10-05 2023-07-26 Municipal Governance Adviso nstitutional Support ant Selection r MZ-CMM-229298-CS-INDV / Project Implementation and I Individual Consult Communication and Media Ju IDA / V3130 Post Open 30,000.00 44,171.41 Signed 2021-04-20 2021-04-15 2021-06-08 2021-08-30 2021-06-29 2021-09-03 2021-08-03 2021-09-09 2022-08-03 nstitutional Support ant Selection nior Specialist Page 6 MZ-CMM-229296-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 10,000.00 18,336.78 Signed 2021-04-20 2021-04-15 2021-06-08 2021-12-14 2021-06-29 2022-01-26 2021-08-03 2022-02-15 2022-01-30 Website Development for MU nstitutional Support ant Selection TP MZ-CMM-200800-CS-INDV / Project Implementation and I Individual Consult IDA / V3130 Post Open 36,000.00 0.00 Canceled 2020-10-30 2020-10-27 2020-12-18 2021-05-03 2021-01-08 2021-02-12 2021-08-11 Procurement Assistant nstitutional Support ant Selection MZ-CMM-248743-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Post Open 84,000.00 76,904.82 Signed 2021-08-31 2021-08-29 2021-10-19 2021-12-08 2021-11-09 2021-12-10 2021-12-14 2021-12-30 2022-12-14 2022-11-24 Team Leader for the Technic nstitutional Support ant Selection al Team MZ-CMM-248739-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Post Limited 84,000.00 60,336.96 Signed 2021-08-20 2021-08-20 2021-08-23 2021-08-23 2021-08-25 2022-02-25 2021-08-30 2022-04-06 2022-08-30 2022-09-20 Monitoring & Evaluation Spec nstitutional Support ant Selection ialist MZ-CMM-264267-CS-INDV / Consultancy services for dev Project Implementation and I Individual Consult IDA / D7490 Post Open 50,000.00 26,612.60 Signed 2021-11-30 2022-05-04 2021-12-27 2022-09-06 2022-01-10 2022-09-12 2022-02-07 2022-09-30 2022-08-06 elopment of the Unique Socia nstitutional Support ant Selection l Registry Concept MZ-CMM-264273-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Prior Open 30,000.00 35,569.41 Signed 2021-11-30 2021-11-29 2022-01-18 2022-03-31 2022-02-08 2022-04-04 2022-03-15 2022-04-15 2023-03-10 Procurement Assistant nstitutional Support ant Selection MZ-CMM-248732-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Post Open 84,000.00 0.00 Canceled 2021-08-20 2021-08-20 2021-09-15 2021-09-22 2021-10-06 2022-10-01 Procurement Specialist II nstitutional Support ant Selection MZ-CMM-277883-CS-INDV / Project Implementation and I Individual Consult Under Implement IDA / D7490 Post Limited 1,500.00 0.00 2022-02-15 2022-02-10 2022-03-01 2022-03-22 2022-04-12 2022-05-12 Team Capacity Building Facili nstitutional Support ant Selection ation tator MZ-CMM-168533-CS-QCBS / Consultancy Services for the Project Implementation and I Individual Consult elaboration of legal and tech IDA / V3130 Post Open 100,000.00 0.00 Canceled 2020-05-27 2020-10-01 2020-07-15 2020-08-05 2020-09-09 2021-03-08 nstitutional Support ant Selection nical studies for IPRA and LV C revenues maximization MZ-CMM-264318-CS-INDV / Project Implementation and I Individual Consult Development of municipal Re IDA / D7490 Post Open 180,000.00 0.00 Canceled 2021-11-30 2022-02-24 2022-01-18 2022-02-08 2022-03-15 2022-11-30 nstitutional Support ant Selection al Estate Taxation Subsystem MZ-CMM-264269-CS-INDV / Project Implementation and I Individual Consult Consultancy for Strengthenin IDA / D7490 Post Open 70,000.00 0.00 Canceled 2021-12-08 2022-03-08 2022-01-26 2022-02-16 2022-03-23 2022-09-19 nstitutional Support ant Selection g Decentralization for munici pal districts MZ-CMM-264268-CS-INDV / Project Implementation and I Individual Consult Consultancy for Strengthenin IDA / D7490 Post Open 70,000.00 0.00 Canceled 2021-12-13 2022-01-29 2022-02-11 2022-03-18 2022-09-14 nstitutional Support ant Selection g Social Participation and Tra nsparency MZ-CMM-264276-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Post Open 60,000.00 0.00 Canceled 2021-12-06 2021-11-29 2022-01-24 2022-02-14 2022-03-14 2023-03-09 Procurement Officer nstitutional Support ant Selection MZ-CMM-289562-CS-INDV / Supervision of Construction a Contingent Emergency Resp Individual Consult nd Rehabilitation of Public To IDA / D7490 Post Open 13,500.00 0.00 Canceled 2022-04-29 2022-07-13 2022-06-17 2022-07-08 2022-08-12 2023-02-08 onse ant Selection ilets in Markets and main Pub lic Transport Terminals MZ-CMM-308214-CS-INDV / Supervision of Construction a Contingent Emergency Resp Individual Consult Under Implement nd Rehabilitation of Public To IDA / D7490 Post Open - National 4,500.00 0.00 2022-08-22 2022-09-16 2022-10-10 2022-10-31 2022-12-05 2023-06-03 onse ant Selection ation ilets in Markets and main Pub lic Transport Terminals, Pack age 1 MZ-CMM-308216-CS-INDV / Supervision of Construction a Contingent Emergency Resp Individual Consult Under Implement nd Rehabilitation of Public To IDA / D7490 Post Open - National 4,500.00 0.00 2022-08-22 2022-09-16 2022-10-10 2022-10-31 2022-12-05 2023-06-03 onse ant Selection ation ilets in Markets and main Pub lic Transport Terminals - Pack age 2 MZ-CMM-308220-CS-INDV / Supervision of Construction a Contingent Emergency Resp Individual Consult Under Implement nd Rehabilitation of Public To IDA / D7490 Post Open - National 4,500.00 0.00 2022-08-22 2022-09-16 2022-10-10 2022-10-31 2022-12-05 2023-06-03 onse ant Selection ation ilets in Markets and main Pub lic Transport Terminals - Pack age 3 MZ-CMM-186609-CS-INDV / Senior Technical Advisor on L Project Implementation and I Individual Consult IDA / V3130 Post Open 120,000.00 0.00 Canceled 2020-08-18 2020-10-07 2020-10-06 2020-10-27 2020-12-01 2022-11-21 and Use Planning and Urban nstitutional Support ant Selection Land Management MZ-CMM-264271-CS-INDV / Consultancy to support the C Project Implementation and I Individual Consult IDA / D7490 Post Open 105,000.00 0.00 Canceled 2021-12-08 2021-11-24 2022-01-26 2022-02-16 2022-03-23 2022-09-19 MM in the Preparation of the nstitutional Support ant Selection Concept Note for the Green C limate Fund MZ-CMM-318277-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Post Direct - National 96,000.00 0.00 Completed 2022-09-30 2022-10-31 2022-10-10 2023-03-16 2022-10-17 2023-03-16 2022-10-31 2023-03-28 2023-10-31 2023-04-09 Project Coordinator nstitutional Support ant Selection MZ-CMM-318280-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Post Direct - National 45,000.00 0.00 Signed 2022-09-30 2022-10-20 2022-10-10 2022-05-06 2022-10-17 2022-06-01 2022-10-31 2023-02-07 2023-10-31 Project Accountant nstitutional Support ant Selection MZ-CMM-318283-CS-INDV / Project Implementation and I Individual Consult Senior Advisor on Land Use P IDA / D7490 Post Direct - National 100,000.00 0.00 Signed 2022-09-30 2022-10-20 2022-10-10 2022-09-15 2022-10-17 2022-09-15 2022-10-31 2022-07-21 2023-10-31 nstitutional Support ant Selection lanning and Urban Land Man agement MZ-CMM-319153-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Post Open - National 84,000.00 0.00 Signed 2022-10-07 2022-10-20 2022-11-09 2023-02-28 2022-11-23 2023-03-17 2022-12-21 2023-04-06 2023-12-21 Monitoring & Evaluation Spec nstitutional Support ant Selection ialist MZ-CMM-341949-CS-INDV / Consultancy Services to Supp ort CMM in Identifying PBC3 Individual Consult Open - Internationa Under Implement IDA / D7490 Sustainable Urban Growth Post 200,000.00 0.00 2023-02-15 2023-03-17 2023-03-20 2023-04-03 2023-04-24 2023-09-21 Activities related to Improve ant Selection l ation ment of Financial Sustainabili ty of the Urban Solid Waste Management Sector MZ-CMM-357142-CS-INDV / Services for Training of Oper Project Implementation and I Individual Consult Under Implement ational Brigades to Act on th IDA / D7490 Post Limited 11,000.00 0.00 2023-05-15 2023-05-09 2023-05-20 2023-06-20 2023-06-10 2023-07-15 2024-07-14 nstitutional Support ant Selection ation e Ground in the Areas of Drai nage, Roads, Solid Waste, an d Urban Sewerage MZ-CMM-357164-CS-INDV / Individual Consult Pending Impleme Works Supervision for Fence IDA / D7490 Sustainable Urban Growth Post Open - National 20,000.00 0.00 2023-09-15 2023-11-03 2023-11-24 2023-12-29 2024-06-26 ant Selection ntation Erection around KaTembe lan dfill Area Page 7 MZ-CMM-357204-CS-INDV / Consulting Services for Dece Project Implementation and I Individual Consult Under Implement IDA / D7490 Post Open - National 45,000.00 0.00 2023-09-01 2023-05-09 2023-10-20 2023-11-10 2023-12-15 2024-06-12 ntralization of Licensing of Ec nstitutional Support ant Selection ation onomic Activities to the Muni cipal Districts MZ-CMM-357221-CS-INDV / Project Implementation and I Individual Consult Pending Impleme IDA / D7490 Post Open - National 50,000.00 0.00 2023-05-02 2023-06-20 2023-07-11 2023-08-15 2024-02-11 PBCs Verification Agent nstitutional Support ant Selection ntation MZ-CMM-357227-CS-INDV / Project Implementation and I Individual Consult Under Implement IDA / D7490 Post Open - National 60,000.00 0.00 2023-05-02 2023-05-08 2023-06-20 2023-07-11 2023-08-15 2025-08-14 Procurement Assistant nstitutional Support ant Selection ation MZ-CMM-357231-CS-INDV / Project Implementation and I Individual Consult Under Implement Environmental and Social Saf IDA / D7490 Post Open - National 70,000.00 0.00 2023-05-02 2023-05-08 2023-06-20 2023-07-11 2023-08-15 2025-09-03 nstitutional Support ant Selection ation eguard Assistant MZ-CMM-289567-CS-INDV / Individual Consult Preparation of Housing Projec IDA / D7490 Sustainable Urban Growth Post Open 10,000.00 0.00 Canceled 2022-07-01 2022-08-19 2022-09-09 2022-10-14 2023-04-12 ant Selection t for KaTembe MZ-CMM-362294-CS-INDV / Project Implementation and I Individual Consult Under Implement IDA / D7490 Prior Open - National 80,000.00 0.00 2023-05-25 2023-05-26 2023-06-27 2023-07-11 2023-08-08 2025-08-07 Project Procurement Speciali nstitutional Support ant Selection ation st II MZ-CMM-374203-CS-INDV / Project Implementation and I Individual Consult Spatial Planning and Urban S IDA / D7490 Post Open - National 60,000.00 0.00 Under Review 2023-08-14 2023-08-28 2023-10-02 2023-10-23 2023-11-27 2024-11-26 nstitutional Support ant Selection oil Management Technician MZ-CMM-374206-CS-INDV / Project Implementation and I Individual Consult Social Inclusion and Gender IDA / D7490 Post Open - National 60,000.00 0.00 Under Review 2023-08-10 2023-08-31 2023-09-28 2023-10-19 2023-11-23 2024-11-22 nstitutional Support ant Selection Affairs Officer MZ-CMM-374210-CS-INDV / Project Implementation and I Individual Consult IDA / D7490 Post Open - National 60,000.00 0.00 Under Review 2023-08-10 2023-08-28 2023-09-28 2023-10-19 2023-11-23 2024-11-22 Water and Sanitation Senior nstitutional Support ant Selection Technician MZ-CMM-374265-CS-INDV / Informal Settlement Upgrad Individual Consult Environmental and Social Au IDA / D7490 Post Open - National 100,000.00 0.00 Under Review 2023-08-25 2023-09-12 2023-10-13 2023-11-03 2023-12-08 2025-12-07 e ant Selection dit for the 3 components MZ-CMM-374213-CS-INDV / J Project Implementation and I Individual Consult unior Technician for Commun IDA / D7490 Post Direct - National 18,000.00 0.00 Under Review 2023-08-28 2023-08-30 2023-09-07 2023-09-28 2023-11-02 2025-10-22 nstitutional Support ant Selection ication and Information Tech nology System MZ-CMM-380777-CS-INDV / Project Implementation and I Individual Consult Pending Impleme IDA / D7490 Post Open - National 192,000.00 0.00 2023-09-15 2023-10-18 2023-11-08 2023-12-13 2025-12-12 Project Coordinator nstitutional Support ant Selection ntation MZ-CMM-374310-CS-INDV / Project Implementation and I Individual Consult Open - Internationa Pending Impleme IDA / D7490 Post 15,000.00 0.00 2024-01-15 2024-03-04 2024-03-25 2024-04-29 2024-08-27 Mid-term Review nstitutional Support ant Selection l ntation Page 8